JP5572539B2 - Temporary piping installation method - Google Patents

Temporary piping installation method Download PDF

Info

Publication number
JP5572539B2
JP5572539B2 JP2010289529A JP2010289529A JP5572539B2 JP 5572539 B2 JP5572539 B2 JP 5572539B2 JP 2010289529 A JP2010289529 A JP 2010289529A JP 2010289529 A JP2010289529 A JP 2010289529A JP 5572539 B2 JP5572539 B2 JP 5572539B2
Authority
JP
Japan
Prior art keywords
temporary
temporary piping
sand
earth
piping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2010289529A
Other languages
Japanese (ja)
Other versions
JP2012136862A (en
Inventor
寛 長谷川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Meiwa Kogyo Co Ltd
Original Assignee
Meiwa Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Meiwa Kogyo Co Ltd filed Critical Meiwa Kogyo Co Ltd
Priority to JP2010289529A priority Critical patent/JP5572539B2/en
Publication of JP2012136862A publication Critical patent/JP2012136862A/en
Application granted granted Critical
Publication of JP5572539B2 publication Critical patent/JP5572539B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Road Paving Structures (AREA)

Description

本発明は、本管の修理や交換工事に先立ち、本管の迂回管となる仮設配管の設置工法に関するものである。   The present invention relates to an installation method of a temporary pipe that becomes a bypass pipe of a main pipe before repair or replacement work of the main pipe.

ガス管や水道管工事に際して、ガスや水道等の供給が途絶えないように、当該本管の迂回管(仮設配管)を設置する必要がある。そこで仮設配管を埋設し、本管工事終了後に埋設した仮設配管を掘り起こす仮設配管設置工事が行われている。   In the construction of gas pipes and water pipes, it is necessary to install detour pipes (temporary pipes) for the main pipes so that the supply of gas and water is not interrupted. Therefore, temporary piping installation work is performed in which temporary piping is buried and the temporary piping buried after the main construction is dug.

前記の仮設配管の掘り起こしは、仮設配管埋設深さの近くまでは、機械掘削(ユンボ:登録商標名やパワーショベル)で行い、その後は仮設配管の周囲部分を手掘りで行っているものである。 The above-mentioned temporary pipe digging is performed by mechanical excavation ( Yumbo: registered trade name or power shovel ) up to the vicinity of the temporary pipe burying depth, and thereafter, the peripheral part of the temporary pipe is manually dug. .

また本管工事においては、工事が数日間にわたる場合には、一日の工事終了後に仮埋め戻しを行い、工事再開時に仮埋め戻し個所を再度掘り起こして工事を続行するが、仮埋め戻し後の掘り起こし作業を簡素化するために、重い土砂の変わりに、合成樹脂製中空球体を多数ネットに入れ、当該ネット体を掘削溝の底方に充填し、掘削溝の上方部分は、一定の仕切り材(透水シート)を介して路盤材を充填して仮埋設する手段が知られている(特許文献1:特開平7−317008号公報)。   In addition, in the case of main construction, if the construction takes several days, temporary backfilling will be carried out after the completion of the day's construction, and the temporary backfilling site will be dug up again when the construction is resumed. In order to simplify the excavation work, instead of heavy earth and sand, a lot of synthetic resin hollow spheres are put in a net, the net body is filled at the bottom of the excavation groove, and the upper part of the excavation groove is a fixed partition material Means for filling a roadbed material via a (water-permeable sheet) and temporarily burying it is known (Patent Document 1: Japanese Patent Laid-Open No. 7-317008).

また特許文献2(特開平8−193304号公報)には、前記の中空球体充填ネット体に替えて、5〜20kgの独立発泡樹脂ブロック体を採用し、前記のブロック体の上方に砂袋を中層仮埋体として採用し、更に上層仮埋体として土砂を採用する工法が開示されている。   Further, in Patent Document 2 (Japanese Patent Laid-Open No. 8-193304), instead of the hollow sphere-filled net body, 5-20 kg of an independent foamed resin block body is adopted, and a sand bag is placed above the block body. A construction method has been disclosed that employs a middle layer temporary buried body and further employs earth and sand as an upper layer temporary buried body.

特開平7−317008号公報。JP-A-7-317008. 特開平8−193304号公報。JP-A-8-193304.

仮設配管の掘り起こしに際しては、前記したとおり機械掘りと手掘りの組み合わせで行っており、手掘り作業が煩瑣な作業であることは本管工事と同様である。しかし前記の特許文献1,2に開示されている仮埋体の採用が、仮設配管の埋設工事に適しているとは認められない。   As described above, the temporary piping is dug up by a combination of machine digging and manual digging, and the manual digging work is a cumbersome work, similar to the main pipe construction. However, it is not recognized that the use of the temporary buried body disclosed in Patent Documents 1 and 2 is suitable for the construction of temporary piping.

本管工事は毎日のように掘り返しが必要であり、樹脂製の仮埋体の変形などは毎日の掘り返し時に確認でき、破損変形を確認すると直ぐに取り換えることが可能であるが、仮設配管の埋設は、本管工事における仮埋め戻しのように直ぐに掘り返すのではなく、ある程度の長期間(数か月)埋設状態が維持されるので、その間に埋設個所上の車両走行などの荷重が絶えず加わることになり、樹脂製の仮埋体が変形した場合に、当該個所が陥没して車両走行に危険性が生じてしまう。   Main pipe construction requires daily digging, and the deformation of the resin temporary embedding can be confirmed at the time of daily digging, and it can be replaced as soon as damage deformation is confirmed. Rather than digging up immediately like temporary backfilling in main construction, the state of burial for a long period (several months) is maintained, so that loads such as vehicle travel on the burial site are constantly added during that period. Thus, when the resin-made temporary embedded body is deformed, the portion is depressed, and there is a danger in vehicle travel.

また本管は、長期間の安全性確保のために相応の深さに埋設する必要があり、埋め戻し再掘削がある程度の深さを必要とするので、種々の仮埋体を組み合わせるコスト高となる煩雑な作業であっても、総合的にみると種々の仮埋体の使用が効果的であるといえるが、本管より浅く埋設することが可能である仮設配管の設置工事においては、樹脂製仮埋体の採用は過剰品質といえ、コスト的に問題となる。   In addition, the main pipe must be buried at a suitable depth to ensure long-term safety, and backfilling and re-digging requires a certain depth. Although it can be said that the use of various temporary buried bodies is effective when viewed comprehensively, in the construction work of temporary piping that can be buried shallower than the main pipe, Adoption of a temporary manufacturing body is an excessive quality, which is a problem in terms of cost.

そこで本発明は、仮埋体を使用することなく仮設配管の掘り起こしを容易にする新規な仮設配管の設置工法を提案したものである。   Therefore, the present invention proposes a novel temporary piping installation method that facilitates excavation of temporary piping without using a temporary buried body.

本発明に係る仮設配管の設置工法は、仮設配管設置用の掘削溝を掘穿して、掘削溝の底面上に仮設配管を配置した後、掘削溝内に土砂を埋め戻してなる仮設配管の設置工法において、適宜幅の長尺帯状のシート本体の端部に引上用の係止部を突設したシート体を、前記の土砂埋め戻しに際して、仮設配管に添い、且つ当該シート本体の捲り上げ、或いは持ち上げで仮設配管の表面が露出するように仮設配管に被せてなることを特徴とするものである。   The temporary pipe installation method according to the present invention is a temporary pipe formed by digging a digging groove for setting a temporary pipe, placing the temporary pipe on the bottom surface of the digging groove, and backfilling the earth and sand in the digging groove. In the installation method, a sheet body in which an engaging portion for pulling is projected from the end of a long belt-like sheet body having an appropriate width is attached to the temporary piping when the earth and sand are backfilled, and the sheet body is turned. The temporary piping is covered so that the surface of the temporary piping is exposed by raising or lifting.

而して前記の仮設配管の設置工法において、仮設配管撤去に際しての掘り起こしは、適宜深さ(後述するシート本体の捲り上げ或いは持ち上げが可能な深さ)までは従前と同様の機械掘りで行い、前記機械掘りの後に、シート本体の引上用の係止部を、ユンボ(登録商標名)等の掘削機械、ダンプ等の走行機械、クレーン等の吊り上げ機械に連結して、シート本体の捲り上げ、或いは持ち上げを行うと、仮設配管の表面が露出することになり、そのままで或いは多少の手掘りを行って仮設配管を撤去するものである。 Thus, in the above-described temporary pipe installation method, the excavation when removing the temporary pipe is performed by the same machine digging as before until the appropriate depth (the depth at which the sheet body can be raised or lifted later), After the machine digging, the locking part for pulling up the seat body is connected to an excavating machine such as Yumbo (registered trademark) , a traveling machine such as a dump truck, a lifting machine such as a crane, and the like. Alternatively, when the surface is lifted, the surface of the temporary piping is exposed, and the temporary piping is removed as it is or by performing some manual digging.

また本発明(請求項2)に係る仮設配管の設置工法は、前記の設置工法において、土砂の埋め戻しに際して、係止部の位置が、少なくとも埋め戻した土砂の機械掘削可能な深さ以上の高さとしてなるもので、埋め戻し土砂の機械掘削で係止部が確実に露出するので、当該露出した係止部を所定の機械に連結し、仮設配管を覆う埋め戻し土砂のシート本体による除去が、効率的に行われるものである。   The temporary piping installation method according to the present invention (Claim 2) is the above-described installation method, wherein when the earth and sand are backfilled, the position of the locking portion is at least greater than the depth at which the backfilled earth and sand can be mechanically excavated. Since the engaging part is exposed reliably by mechanical excavation of backfill earth and sand, removal of the backfill earth and sand covering the temporary piping by connecting the exposed engaging part to a predetermined machine However, this is done efficiently.

更に本発明(請求項4)に係る仮設配管の設置工法は、シート本体の一部又は全部が、ネットその他の透水構造としてなるもので、雨が埋め戻した掘削溝に浸透してもシート体で滞留することがない。   Furthermore, the temporary pipe installation method according to the present invention (Claim 4) is such that part or all of the sheet main body has a net or other water-permeable structure, and even if the rain penetrates into the excavation groove backfilled, the sheet body Will not stay.

本発明の構成は上記のとおりで、特別な樹脂製の仮埋体を採用することなく、従前と同様に掘削溝の掘削土や、埋め戻し用砂を使用して埋め戻しを行うものであるが、仮設配管撤去時の仮設配管掘り起こしに際して、その大部分は機械力による掘削ですみ、仮設配管の撤去に際しても仮設配管使用期間中に車両走行などで固められた埋め戻し土砂のうち、仮設配管の周囲部分(特に上面を覆っている部分)は、シート本体の捲り上げで除去され、仮に残存していたとしても、仮設配管の近傍の周囲の土砂は、前記のシート体の捲り上げによって解されることになり、そのままの状態又は簡単な手掘りで容易に仮設配管を撤去できるもので、仮設配管撤去に際しての掘り起こし土砂量が少なくて済み、簡易な仮設配管設置工法で、仮設配管撤去作業の作業能率を格段に向上させるものである。   The configuration of the present invention is as described above, and without using a special resin temporary embedding body, the excavation soil of the excavation groove and the backfilling sand are used in the same manner as before. However, when digging up the temporary piping when the temporary piping is removed, most of it is excavated by mechanical force. The surrounding part (particularly the part covering the upper surface) is removed by raising the sheet main body, and even if it remains, the surrounding earth and sand in the vicinity of the temporary piping is removed by raising the sheet body. The temporary pipe can be easily removed as it is or by simple manual digging, and the amount of excavated earth and sand when removing the temporary pipe is small, and the temporary pipe can be removed with a simple temporary pipe installation method. The work efficiency of the work is intended to significantly improve.

本発明の第一実施形態工法に使用するシート体の説明図。Explanatory drawing of the sheet | seat body used for 1st embodiment construction method of this invention. 同工法の仮設配管設置工程の説明図。Explanatory drawing of the temporary piping installation process of the construction method. 同掘り起こし作業の説明図(機械堀りの斜視図)。Explanatory drawing of the excavation work (perspective view of mechanical excavation). 同図(機械掘りの側面図)。The same figure (side view of machine digging). 同図(シート本体捲り上げ時の斜視図)。The same figure (perspective view when the seat body is lifted). 同図(シート本体捲り上げ時の側面図)。The same figure (side view when the seat body is lifted). 同図(仮設配管の解体撤去)。The figure (dismantling and removal of temporary piping). 同仮設配管とシート体配置の別例図。The other example figure of the temporary piping and sheet | seat body arrangement | positioning. 本発明の第二実施形態工法に使用するシート本体の説明図。Explanatory drawing of the sheet | seat main body used for the 2nd embodiment construction method of this invention. 同掘り起こし時の説明図(機械掘り終了時の斜視図)。Explanatory drawing at the time of digging up (perspective view at the end of machine digging). 同図(シート本体捲り上げ時の斜視図)。The same figure (perspective view when the seat body is lifted).

次に本発明の実施形態工法について説明する。本発明工法は所定のシート体1を使用するものである。またシート体1の形状・構造に合わせてシート体1の捲り上げに必要な連結具2を使用する。   Next, an embodiment method according to the present invention will be described. The method of the present invention uses a predetermined sheet body 1. Further, a connecting tool 2 necessary for raising the sheet body 1 is used in accordance with the shape and structure of the sheet body 1.

シート体1は、シート本体11が土砂を乗せたまま上方に吊上げた際に破損しないような充分に耐久力を有する材質で形成したもので、幅は少なくとも仮設配管の管径と同じかそれ以上で、長さは後述する作業に対応できる適宜なものとし、少なくとも一端側に引上用の係止部12を設けたものである。   The sheet body 1 is formed of a material having a sufficient durability so that the sheet body 11 is not damaged when the sheet body 11 is lifted upward with earth and sand placed thereon, and the width is at least equal to or larger than the pipe diameter of the temporary piping. Thus, the length is appropriate for the work described later, and a pulling-up locking portion 12 is provided on at least one end side.

係止部12は、土砂を乗せたままシート本体11を捲り上げたり、或いは吊り上げたりすることができるように設けたもので、例えば図示しているようにシート本体11に付設した腕帯部13の先端を輪状に形成して設けたもので、当該輪状の係止部12に連結具(棒状体)2を装着し、前記連結具2を引上げ用の機械(掘削機械3のアーム先端:作用部31や、その他走行機械等)に接続したり、或いは更に連結具2の他にチェーン等の介在具21等を介して接続するものである。勿論連結具2を使用せずにチェーン等の介在具21のみを使用しても良いし、また引き上げ用機械も特に限定されるものではなく、使用する機械に対応して係止部12の構造・形状を定めればよいものである。 The locking portion 12 is provided so that the seat body 11 can be lifted or lifted with earth and sand on it. For example, as shown in the figure, an arm band portion 13 attached to the seat body 11 is provided. The connecting tool (rod-like body) 2 is attached to the ring-shaped engaging portion 12 and the connecting tool 2 is pulled up (the tip of the arm of the excavating machine 3 : action). Part 31 and other traveling machines), or further connected via an intervening tool 21 such as a chain in addition to the connecting tool 2. Of course, only the intervening tool 21 such as a chain may be used without using the connecting tool 2, and the lifting machine is not particularly limited, and the structure of the locking portion 12 corresponding to the machine to be used.・ The shape should be determined.

また係止部12は、特にシート本体11を吊り上げて使用する場合には、四隅部に設けておき、機械による吊り上げを可能とし、また捲り上げて使用するものであれば、連続的に捲り上げることができるように、シート体1の側縁に適宜間隔で設けておくものである。   In addition, when the seat body 11 is lifted and used, the locking portion 12 is provided at the four corners so that it can be lifted by a machine. For this reason, the sheet body 1 is provided with appropriate intervals on the side edges.

次に本発明工法(仮設配管の設置工法)を、前記のシート体1を使用しての施工手順について説明する。仮設配管4を埋設するために仮設配管設置用の掘削溝5を、ユンボ(登録商標名)等の油圧ショベルを備えた所定の掘削機械3で掘穿する。掘削溝5は、仮設配管4同士の連結に必要な個所を除き、仮設配管4を設置すべき深さと一致する深さとする。 Next, the construction method using the sheet body 1 according to the present invention construction method (temporary piping installation construction method) will be described. In order to embed the temporary piping 4, the excavation groove 5 for installing the temporary piping is excavated by a predetermined excavating machine 3 equipped with a hydraulic excavator such as Yumbo (registered trademark) . The excavation groove 5 has a depth that matches the depth at which the temporary piping 4 should be installed, except for the portions necessary for the connection of the temporary piping 4.

仮設配管4は、前記掘削溝5の底面51に直接載置し、次にこの仮設配管4にシート本体11を、仮設配管4に密着させて被せ、係止部12を例えば鉤状杆6の様な器具を使用して立ち上げ状態として(図2ロ)、土砂7で掘削溝5の埋め戻しを行う。尚シート本体11の掘削溝5内への配置は、前記の手順に限定されるものではなく、例えば仮設配管4の側方空間に土砂7を投入して一部埋め戻しを行った後に、仮設配管4の上方に被せるようにしても良い。   The temporary pipe 4 is placed directly on the bottom surface 51 of the excavation groove 5, and the sheet main body 11 is then put in close contact with the temporary pipe 4 to cover the temporary pipe 4. As a starting state using such a tool (FIG. 2B), the excavation groove 5 is backfilled with earth and sand 7. The arrangement of the sheet main body 11 in the excavation groove 5 is not limited to the above-described procedure. For example, after the earth and sand 7 is put into the side space of the temporary piping 4 and partially backfilled, the temporary installation is performed. You may make it cover the piping 4 upper part.

土砂7の埋め戻し工事は、通常掘削溝5の上方部分を残して行い、適宜填圧して表面に砕石71並びに仮舗装72を施したり、或いは被覆マットを敷設して仮設配管4の設置工事を終了する(図2ハ)。   The refilling of the earth and sand 7 is usually performed while leaving the upper part of the excavation groove 5 and is appropriately filled with crushed stone 71 and temporary pavement 72 on the surface, or a covering mat is laid and the temporary piping 4 is installed. The process ends (FIG. 2C).

そして前記の仮設配管4は、本管工事が終了した後には、掘り起こして撤去する必要がある。本発明は、この撤去作業の効率化を目的としたものである。   And the said temporary piping 4 needs to be dug up and removed after the main pipe construction is completed. The present invention aims to improve the efficiency of this removal work.

仮設配管撤去作業は、始めに掘削機械3で仮舗装72を剥がし(被覆マット使用時は不要)、砕石71を除去し、更に必要に応じて係止部12の先端(係止部分)が露出するまで、土砂7を掘削する。勿論仮設配管4の埋設位置が浅い場合には、土砂7の掘削を行わず、単に砕石71の除去を行うのみで、係止部12が露出するようにシート体1の埋設を行うようにしておいても良い。   In the temporary pipe removal work, the temporary pavement 72 is first peeled off by the excavating machine 3 (not required when using the covering mat), the crushed stone 71 is removed, and the tip of the locking portion 12 (locking portion) is exposed as necessary. Until then, excavate the sediment 7. Of course, when the embedding position of the temporary pipe 4 is shallow, the excavation of the earth and sand 7 is not performed, and the crushed stone 71 is simply removed, and the sheet body 1 is embedded so that the locking portion 12 is exposed. You can leave it.

また機械掘りで係止部12が露出しない場合には、手掘りで係止部12を露出させ、後述するシート本体11の捲り上げ、吊り上げを行うものである。   Further, when the locking portion 12 is not exposed by machine digging, the locking portion 12 is exposed by manual digging, and a sheet body 11 described later is lifted and lifted.

次にシート体1の係止部12(腕帯部13の先端)を露出させた後、左右の係止部12に連結具2を挿通して装着し、掘削機械3の作用部(アーム先端のショベル部分)31に、フックチェーン等の介在具21で連結し、掘削機械3でシート本体11を、シート本体11の埋設方向へ折り返すように捲り上げると、シート本体11の上に乗った土砂7は、仮設配管4の周囲(特に上方被覆個所)から取り除かれ、仮設配管4の表面(上面部分)が露出する(図5)。露出の程度が少ない場合には、手掘りで必要分を露出させる。そして前記状態で仮設配管4を掘削溝5内から撤去するものである(図7)。   Next, after the locking portion 12 of the sheet body 1 (the tip of the armband portion 13) is exposed, the connector 2 is inserted and attached to the left and right locking portions 12, and the working portion of the excavating machine 3 (the tip of the arm) The excavator 3 is connected to the excavator portion 31 with an intervening tool 21 such as a hook chain, and the excavating machine 3 lifts the seat body 11 so as to be folded back in the direction in which the seat body 11 is embedded. 7 is removed from the periphery of the temporary piping 4 (particularly the upper covering portion), and the surface (upper surface portion) of the temporary piping 4 is exposed (FIG. 5). If the degree of exposure is low, the necessary amount is exposed by hand digging. And the temporary piping 4 is removed from the inside of the excavation groove 5 in the said state (FIG. 7).

尚前記の仮設配管4の取り出し作業において、必要に応じて手掘りを行っても良く、その場合でも、車両走行等で踏み固められた土砂7は、シート本体11の捲り上げによって仮設配管4の近傍の土砂7は解されるので、容易に手掘り作業も実施出来るものである。   In the operation of taking out the temporary piping 4, manual digging may be performed as necessary. Even in this case, the earth and sand 7 that has been squeezed by running of the vehicle or the like is lifted up by lifting the seat body 11. Since the nearby earth and sand 7 is unraveled, it is possible to easily carry out manual digging work.

また前記のシート本体11の捲り上げに代えて、シート体1全体を土砂7と共に吊り上げるようにしても良く、その際には係止部12の構造・形状も吊り上げ作業に適するものとする。   Further, instead of lifting the sheet main body 11, the entire sheet body 1 may be lifted together with the earth and sand 7. In this case, the structure and shape of the locking portion 12 are also suitable for the lifting work.

以上のように本発明(第一実施形態)の仮設配管の設置工法を採用すると、仮設配管撤去作業において、掘削溝5内の土砂7の殆ど全てを掘削することなく、必要最小限の土砂7のみを基本的に機械掘削で掘削溝5から除去することで、仮設配管4の取り出しが可能となるものである。   As described above, when the temporary piping installation method of the present invention (first embodiment) is adopted, the minimum necessary sediment 7 is not excavated in the temporary piping removal operation without excavating almost all of the sediment 7 in the excavation groove 5. The temporary piping 4 can be taken out by removing only from the excavation groove 5 by mechanical excavation.

このようにシート体1の捲り上げで、仮設配管4を直接、或いは簡易な手掘り作業を付加することでその取り出しを可能とするものであるから、当該仮設配管の埋設深さ、仮設配管4の管径等によって、シート本体11の幅や、撤去作業時の機械掘削深さ(係止部12を設けている帯腕部13の長さ、立ち上げ高さ)が定められる。またシート本体11の吊り上げによって土砂7の除去を行う場合には、シート本体11は、吊り上げ可能な大きさにするものである。   As described above, the temporary pipe 4 can be taken out directly or by adding a simple manual digging operation when the sheet body 1 is rolled up. The width of the sheet body 11 and the machine excavation depth (the length of the belt arm portion 13 provided with the locking portion 12 and the rising height) are determined by the tube diameter and the like. When the earth and sand 7 is removed by lifting the sheet main body 11, the sheet main body 11 is sized to be lifted.

また本発明における仮設配管4の配置は、図示したように掘削溝5の底面中央に限ることが無く、掘削溝5の底面51の偏った位置の場合もあり、その際には図8に例示するように、偏った位置の仮設配管4の上面に密着させて配置するものである。   Further, the arrangement of the temporary piping 4 in the present invention is not limited to the center of the bottom surface of the excavation groove 5 as shown in the figure, and there may be a case where the bottom surface 51 of the excavation groove 5 is biased. In this way, it is arranged in close contact with the upper surface of the temporary pipe 4 at a biased position.

また本発明は図9乃至11に示すように、腕帯部13を備えないシート体1aを使用するようにしても良い(第二実施形態工法)。   In addition, as shown in FIGS. 9 to 11, the present invention may use a sheet body 1a that does not include the armband portion 13 (second embodiment method).

即ち長尺のシート体1aは、シート本体11aが土砂を乗せたまま上方に吊り上げた際に破損しないような充分に耐久力を有する材質で形成され、シート本体11aの隅部に透孔で形成した引き上げ用の係止部12aを設けたものである。   That is, the long sheet body 1a is formed of a material having a sufficient durability so that the sheet body 11a is not damaged when the sheet body 11a is lifted upward with the earth and sand placed thereon, and is formed with a through hole in a corner portion of the sheet body 11a. The raised locking portion 12a is provided.

而して前記のシート体1aも、前記の第一実形態工法と同様に、掘削溝5の底面51に仮設配管4を設置し、次にこの仮設配管4にシート体1aを、仮設配管4に密着させて被せ、土砂7の埋め戻しを行うものである。特に前記の埋め戻しに際しては、図10に示すように、シート体1aの隅部の透孔部分(係止部)12aが跳ね上がっている状態とするのが好ましい。そして従前通り仮復旧を行って仮設配管4の設置工事を終了する。   Thus, in the same manner as in the first embodiment, the sheet body 1a is also provided with the temporary piping 4 on the bottom surface 51 of the excavation groove 5, and then the temporary piping 4 with the sheet body 1a and the temporary piping 4. The earth and sand 7 are back-filled by being in close contact with each other. In particular, at the time of the backfilling, as shown in FIG. 10, it is preferable that the through-hole portions (locking portions) 12a at the corners of the sheet body 1a are jumped up. And temporary restoration is performed as before and the installation work of the temporary piping 4 is completed.

本管工事が終了した後の仮設配管撤去作業は、第一実施形態工法と同様に、掘削機械3で仮舗装72を剥がし、砕石71を除去し、更に係止部(透孔)12aが露出するまで、或いは適宜深さまで土砂7を掘削し、必要に応じて手掘りによって係止部(透孔)12aを露出させる。   As with the first embodiment method, the temporary piping removal work after the main pipe work is completed is performed by peeling the temporary pavement 72 with the excavating machine 3, removing the crushed stone 71, and further exposing the locking part (through hole) 12a. The earth and sand 7 is excavated to the depth or appropriately, and the locking portion (through hole) 12a is exposed by manual digging as necessary.

露出した係止部(透孔)12aに、適宜な連結具(フックチェーン等)2aを引っ掛けて、掘削機械3やその他の機械(走行機械等)で、シート本体11aを折り返すように捲り上げ、仮設配管4の周囲(特に上方被覆個所)の土砂7を除去し、仮設配管4の表面(上面部分)を露出させる(図11)。   Hook an appropriate coupling tool (hook chain or the like) 2a to the exposed locking portion (through hole) 12a, and lift up the seat body 11a with the excavating machine 3 or other machine (traveling machine or the like). The earth and sand 7 around the temporary piping 4 (particularly the upper covering portion) is removed, and the surface (upper surface portion) of the temporary piping 4 is exposed (FIG. 11).

従って前記第一実施形態工法と同様に、仮設配管撤去作業に際して、掘削溝5内の土砂7の殆ど全てを掘削することなく、必要最小限の土砂7のみを基本的に機械掘削で掘削溝5から除去することで、仮設配管4の取り出しが可能となるものである。   Accordingly, as in the first embodiment method, when removing the temporary pipe, the excavation groove 5 is basically mechanically excavated with only the necessary minimum earth and sand 7 without excavating almost all of the earth and sand 7 in the excavation groove 5. It is possible to take out the temporary piping 4 by removing it.

勿論本発明は、前記の第一実施形態及び第二実施形態に限定されるものではなく、仮設配管4の埋め戻しに際して、仮設配管4にシート体を被せ、仮設配管撤去時の埋め戻し土砂の除去を、前記のシート体の捲り上げ又は吊り上げで実施することができれば良いもので、シート体は、前記を実現するものであれば、例えば、シート本体の材質として透水性のものを利用したりその形状・構造は任意である。   Of course, the present invention is not limited to the first embodiment and the second embodiment described above, and when the temporary piping 4 is backfilled, the temporary piping 4 is covered with a sheet body, and the backfill earth and sand when the temporary piping is removed. As long as the removal can be carried out by lifting or lifting the sheet body, and the sheet body can realize the above, for example, a material having water permeability can be used as the material of the sheet body. The shape and structure are arbitrary.

1,1a シート体
11,11a シート本体
12 係止部
12a 係止部(透孔)
13 腕帯部
2 連結具
2a 連結具(フックチェーン)
21 介在具(フックチェーン)
3 掘削機械
31 作用部
4 仮設配管
5 掘削溝
51 底面
6 鉤状杆
7 土砂
71 砕石
72 仮舗装
1, 1a Sheet body 11, 11a Sheet body 12 Locking portion 12a Locking portion (through hole)
13 Armband 2 Connector 2a Connector (hook chain)
21 Interposer (hook chain)
DESCRIPTION OF SYMBOLS 3 Excavation machine 31 Action part 4 Temporary piping 5 Excavation groove 51 Bottom face 6 Corrugated ridge 7 Earth and sand 71 Crushed stone 72 Temporary pavement

Claims (4)

仮設配管設置用の掘削溝を掘穿して、掘削溝の底面上に仮設配管を配置した後、掘削溝内に土砂を埋め戻してなる仮設配管設置工法において、適宜幅の長尺帯状のシート本体の端部に引上用の係止部を設けたシート体を、前記の土砂埋め戻しに際して、仮設配管に添い、且つ当該シート本体の捲り上げ、或いは持ち上げで仮設配管の表面が露出するように仮設配管に被せてなることを特徴とする仮設配管の設置工法。   In the temporary piping installation method in which the excavation groove for temporary piping installation is dug, temporary piping is arranged on the bottom surface of the excavation groove, and earth and sand are backfilled in the excavation groove, a long belt-like sheet having an appropriate width At the end of the main body, a sheet body provided with a pulling-up locking portion is attached to the temporary piping when the earth and sand are backfilled, and the surface of the temporary piping is exposed by raising or lifting the sheet main body. Temporary piping installation method, characterized by covering the temporary piping. 土砂の埋め戻しに際して、係止部の位置が、少なくとも埋め戻した土砂の機械掘削可能な深さ以上の高さとしてなる請求項1記載の仮設配管の設置工法。   The temporary pipe installation method according to claim 1, wherein when the earth and sand are backfilled, the position of the locking portion is at least a height that is at least a depth capable of machine excavation of the backfilled earth and sand. 係止部を、シート本体に付設した腕帯部の先端部分に設けてなる請求項1又は2記載の仮設配管の設置工法。   The temporary piping installation method according to claim 1 or 2, wherein the locking portion is provided at a distal end portion of an arm band portion attached to the seat body. シート本体の一部又は全部が、ネットその他の透水構造としてなる請求項1乃至3の何れか一項に記載の仮設配管の設置工法。 The temporary piping installation method according to any one of claims 1 to 3 , wherein a part or all of the sheet main body has a net or other water-permeable structure.
JP2010289529A 2010-12-27 2010-12-27 Temporary piping installation method Active JP5572539B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010289529A JP5572539B2 (en) 2010-12-27 2010-12-27 Temporary piping installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010289529A JP5572539B2 (en) 2010-12-27 2010-12-27 Temporary piping installation method

Publications (2)

Publication Number Publication Date
JP2012136862A JP2012136862A (en) 2012-07-19
JP5572539B2 true JP5572539B2 (en) 2014-08-13

Family

ID=46674482

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010289529A Active JP5572539B2 (en) 2010-12-27 2010-12-27 Temporary piping installation method

Country Status (1)

Country Link
JP (1) JP5572539B2 (en)

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3952529A (en) * 1974-04-12 1976-04-27 Lefever Kenneth W Earthquake fault zone pipeline construction method and arrangement
JP2920177B2 (en) * 1991-06-13 1999-07-19 大阪瓦斯株式会社 Temporary backfill method and temporary backfill materials
US5385430A (en) * 1993-04-23 1995-01-31 Connors; Geoff W. Pipeline ballasting device
JPH07317008A (en) * 1994-05-27 1995-12-05 Osaka Gas Co Ltd Temporary back-filling method
JPH08193304A (en) * 1995-01-13 1996-07-30 Nippon Steel Corp Temporary burying method for hole excavated for laying burying pipe
JP2007255165A (en) * 2006-03-27 2007-10-04 Capty Co Ltd Temporary restoring method of vertical shaft
JP4822426B2 (en) * 2006-04-03 2011-11-24 鹿島建設株式会社 Construction method of buried pipe under the road
JP5324413B2 (en) * 2009-07-31 2013-10-23 明和工業株式会社 Temporary piping installation method

Also Published As

Publication number Publication date
JP2012136862A (en) 2012-07-19

Similar Documents

Publication Publication Date Title
JP2007277891A (en) Shaft skeleton, shaft, segment and construction method of shaft
JP5572539B2 (en) Temporary piping installation method
JP6068774B1 (en) Earth retaining prior construction method using adjustable erection
JP4111445B2 (en) Basic settlement settlement method using sandbag
JP3219554U (en) Pile driving device
JP5324413B2 (en) Temporary piping installation method
JP4863312B2 (en) Excavation method
JP5142269B2 (en) Casing installation device and buried object laying method
JP2776695B2 (en) Prevention of settlement of buried pipeline by civil engineering sheet
JP3776987B2 (en) Vertical shaft construction method using a manhole wall combined tubular body
JP5432814B2 (en) Construction method of concrete body for septic tank protection
JP6814581B2 (en) Pipe burying method
KR100581403B1 (en) Method for constructing for a soft-ground breakwater
JP2009013608A (en) Wall structure and construction method for it
JP4614217B2 (en) Tubing burial method
JP4693606B2 (en) Vertical shaft construction method
JP3611937B2 (en) Temporary buried structure of borehole
JP5241804B2 (en) Vertical shaft construction method
JP2006016892A (en) Method for preventing lift of lining body
JP2008008127A (en) Construction method for correcting differential settlement of building by utilizing buoyancy
JP2013238303A (en) Burial indication material for temporary pipe and method of burying temporary pipe
JP4651328B2 (en) Tubing burial method
JP3720989B2 (en) Sewer pipe burial method
JP2003055950A (en) Compaction device of earth under pipe
JP2023158429A (en) Buried structure of buried pipe and method for burying buried pipe

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20131030

A977 Report on retrieval

Effective date: 20140423

Free format text: JAPANESE INTERMEDIATE CODE: A971007

A131 Notification of reasons for refusal

Effective date: 20140513

Free format text: JAPANESE INTERMEDIATE CODE: A131

A521 Written amendment

Effective date: 20140523

Free format text: JAPANESE INTERMEDIATE CODE: A523

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20140624

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20140630

R150 Certificate of patent (=grant) or registration of utility model

Country of ref document: JP

Ref document number: 5572539

Free format text: JAPANESE INTERMEDIATE CODE: R150