JP5324413B2 - Temporary piping installation method - Google Patents
Temporary piping installation method Download PDFInfo
- Publication number
- JP5324413B2 JP5324413B2 JP2009290497A JP2009290497A JP5324413B2 JP 5324413 B2 JP5324413 B2 JP 5324413B2 JP 2009290497 A JP2009290497 A JP 2009290497A JP 2009290497 A JP2009290497 A JP 2009290497A JP 5324413 B2 JP5324413 B2 JP 5324413B2
- Authority
- JP
- Japan
- Prior art keywords
- temporary
- excavation groove
- sheet body
- groove
- installation method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Road Paving Structures (AREA)
Description
本発明は、本管の修理や交換工事に先立ち、本管の迂回管となる仮設配管の設置工法に関するものである。 The present invention relates to an installation method of a temporary pipe that becomes a bypass pipe of a main pipe before repair or replacement work of the main pipe.
ガス管や水道管工事に際して、ガスや水道等の供給が途絶えないように、当該本管の迂回管(仮設配管)を設置する必要がある。そこで仮設配管を埋設し、本管工事終了後に埋設した仮設配管を掘り起こす仮設配管設置工事が行われている。 In the construction of gas pipes and water pipes, it is necessary to install detour pipes (temporary pipes) for the main pipes so that the supply of gas and water is not interrupted. Therefore, temporary piping installation work is performed in which temporary piping is buried and the temporary piping buried after the main construction is dug.
前記の仮設配管の掘り起こしは、仮設配管埋設深さの近くまでは、機械掘削(ユンボ・パワーショベル)で行い、その後は仮設配管の周囲部分を手掘りで行っているものである。 The digging of the temporary pipe is performed by mechanical excavation (yumbo power shovel) up to the vicinity of the temporary pipe burying depth, and thereafter, the peripheral portion of the temporary pipe is manually dug.
また本管工事においては、工事が数日間にわたる場合には、一日の工事終了後に仮埋めを行い、工事再開時に仮埋め戻し個所を再度掘り起こして工事を続行するが、仮埋め戻し後の掘り起こし作業を簡素化するために、重い土砂の変わりに、合成樹脂製中空球体を多数ネットに入れ、当該ネット体を掘削溝の底方に充填し、掘削溝の上方部分は、一定の仕切り材(透水シート)を介して路盤材を充填して仮埋設する手段が知られている(特許文献1:特開平7−317008号公報)。 In addition, in the case of main construction, if the construction takes several days, temporary filling is performed after the completion of the day's construction, and the temporary backfilling site is dug up again when the construction is resumed. In order to simplify the work, instead of heavy earth and sand, a large number of synthetic resin hollow spheres are put into a net, the net body is filled at the bottom of the excavation groove, and the upper part of the excavation groove is a fixed partition material ( Means for filling a roadbed material via a water-permeable sheet and temporarily burying it is known (Patent Document 1: JP-A-7-317008).
また特許文献2(特開平8−193304号公報)前記の中空体充填ネット体に替えて、5〜20kgの独立発泡樹脂ブロック体を採用し、前記のブロック体の上方に砂袋を中層仮埋体として採用し、更に上層仮埋体として土砂を採用する工法が開示されている。 Patent Document 2 (Japanese Patent Laid-Open No. 8-193304) In place of the hollow body-filled net body, a 5 to 20 kg closed foam resin block body is adopted, and a sand bag is temporarily buried above the block body. The construction method which employ | adopts as a body and also employs earth and sand as an upper layer temporary embedding body is disclosed.
仮設配管の掘り起こしに際しては、前記したとおり機械掘りと手掘りの組み合わせで行っており、手掘り作業が煩瑣な作業であることは本管工事と同様である。しかし前記の特許文献1,2に開示されている仮埋体の採用が、仮設配管の埋設工事に適しているとは認められない。
As described above, the temporary piping is dug up by a combination of machine digging and manual digging, and the manual digging work is a cumbersome work, similar to the main pipe construction. However, it is not recognized that the use of the temporary buried body disclosed in
本管工事は毎日のように掘り返しが必要であり、樹脂製の仮埋体の変形などは毎日の掘り返し時に確認でき、破損変形を確認すると直ぐに取り換えることが可能であるが、仮設配管の埋設は、本管工事における仮埋め戻しのように直ぐに掘り返すのではなく、ある程度の長期間(数か月)埋設状態が維持されるので、その間に埋設個所上の車両走行などの荷重が絶えず加わることになり、樹脂製の仮埋体が変形した場合に、当該個所が陥没して車両走行に危険性が生じてしまう。 Main pipe construction requires daily digging, and the deformation of the resin temporary embedding can be confirmed at the time of daily digging, and it can be replaced as soon as damage deformation is confirmed. Rather than digging up immediately like temporary backfilling in main construction, the state of burial for a long period (several months) is maintained, so that loads such as vehicle travel on the burial site are constantly added during that period. Thus, when the resin-made temporary embedded body is deformed, the portion is depressed, and there is a danger in vehicle travel.
また本管は、長期間の安全性確保のために相応の深さに埋設する必要があり、埋め戻し再掘削がある程度の深さを必要とするので、種々の仮埋体を組み合わせるコスト高となる煩雑な作業であっても、総合的にみると種々の仮埋体の使用が効果的であるといえるが、本管より浅く埋設することが可能である仮設配管の設置工事においては、樹脂製仮埋体の採用は過剰品質といえ、コスト的に問題となる。 In addition, the main pipe must be buried at a suitable depth to ensure long-term safety, and backfilling and re-digging requires a certain depth. Although it can be said that the use of various temporary buried bodies is effective when viewed comprehensively, in the construction work of temporary piping that can be buried shallower than the main pipe, Adoption of a temporary manufacturing body is an excessive quality, which is a problem in terms of cost.
そこで本発明は、仮埋体を使用することなく仮設配管の掘り起こしを容易にする新規な仮設配管の設置工法を提案したものである。 Therefore, the present invention proposes a novel temporary piping installation method that facilitates excavation of temporary piping without using a temporary buried body.
本発明(請求項1)に係る第一の仮設配管の設置工法は、仮設配管設置用の掘削溝を掘穿した後、掘削溝の底面上に仮設配管を載置し、適宜大きさで且つ少なくとも四隅側縁に吊上げ連結部を設けたシート体を、前記仮設配管に密着させて被せると共に、掘削溝の溝側面の下方部分を覆うように溝内に敷いて、掘削溝内に土砂を埋め戻してなることを特徴とするものである。 In the first temporary pipe installation method according to the present invention (Claim 1), after excavating the excavation groove for installing the temporary pipe, the temporary pipe is placed on the bottom surface of the excavation groove, and is appropriately sized and Cover the temporary piping with a sheet body with lifting connection parts at least at the four corner side edges, and lay it in the groove so as to cover the lower part of the groove side surface of the excavation groove, and fill the excavation groove with earth and sand It is characterized by being returned.
而して前記の仮設配管の設置工法において、仮設配管撤去に際しての掘り起こしは、仮設配管の埋設深さの近くまでは従前と同様の機械掘りで行い、前記機械掘りの後にシート体の吊上げ連結部を、ユンボやクレーン付き油圧ショベル等の掘削機械の作用部(アーム先端)やクレーン等で、チェーンを介在させたり或いはその他適宜な吊上げ具を介して持ち上げると、残余の埋め戻し土を一挙に掘削溝から取り出す吊上げ掘削となり、手掘りすることなく仮設配管を撤去することができる。 Thus, in the above-described temporary pipe installation method, the excavation when removing the temporary pipe is performed by the same mechanical digging up to the vicinity of the buried depth of the temporary pipe, and after the mechanical digging, the lifting connection portion of the sheet body Digging the remaining backfill soil at once by lifting the chain with a working part (arm tip) of a drilling machine such as a yumbo or a hydraulic excavator with a crane or a crane, etc. It becomes the lifting excavation taken out from the groove, and the temporary piping can be removed without digging by hand.
また本発明(請求項2)に係る仮設配管の設置工法は、前記の設置工法において、シート体が、溝側面における仮設配管の上縁より高い位置まで達する大きさとしてなるもので、仮設配管の埋設深さ近くまでの機械掘りで、シート体の吊上げ連結部が確実に露出することになるので、吊上げ掘削が容易に行える。 The temporary piping installation method according to the present invention (Claim 2) is the above-described installation method, in which the sheet body has a size that reaches a position higher than the upper edge of the temporary piping on the groove side surface. Since the lifting connection portion of the sheet body is reliably exposed by machine digging to a depth near the embedding depth, lifting excavation can be easily performed.
また本発明(請求項3)に係る仮設配管の設置工法は、シート体における吊上げ連結部が、シート長と対応する平行に配置した杆体を備えた吊上げ器具と対応する構造としてなるもので、持ち上げ掘削に際して前後の吊上げ連結部の間の撓みを少なくすることができ、持ち上げ掘削を効率的に実施することができる。 The temporary piping installation method according to the present invention (Claim 3) is a structure in which the lifting connection portion in the sheet body corresponds to a lifting device having a casing arranged in parallel corresponding to the seat length. When excavating, the bending between the front and rear lifting connection portions can be reduced, and lifting excavation can be performed efficiently.
本発明(請求項4)に係る第二の仮設配管の設置工法は、仮設配管設置用の掘削溝を掘穿した後、掘削溝の底面上に仮設配管を載置し、掘削溝の幅に対応する所定幅で、先端部分のみ或いは先端部分及び適宜間隔で側縁に引張連結部を設けた適宜長さのシート体を、シート体の先端の引張連結部が、少なくとも機械掘削可能な埋め戻し土砂の高さ以上に位置するように、前記仮設配管に密着させて被せると共に、掘削溝の底面全体を覆うように溝内に敷いて、掘削溝内に土砂を埋め戻してなることを特徴とするものである。 In the second temporary pipe installation method according to the present invention (Claim 4), after excavating the excavation groove for installing the temporary pipe, the temporary pipe is placed on the bottom surface of the excavation groove to obtain the width of the excavation groove. A sheet body of an appropriate length with a corresponding predetermined width, with only a front end portion or a front end portion and an appropriate distance provided on a side edge at a side edge, and a back end capable of at least mechanical excavation at the front end of the sheet body. It is characterized in that it is placed in close contact with the temporary piping so as to be located above the height of the earth and sand, and is laid in the groove so as to cover the entire bottom surface of the excavation groove, and the earth and sand are backfilled in the excavation groove. To do.
而して前記の仮設配管の設置工法は、前述(請求項1の発明)の設置工法と同様に、仮設配管撤去に際しての掘り起こしは、仮設配管の埋設深さの近くまでは従前と同様の機械掘りで行い、前記機械掘りの後にシート体の先端の引張連結部を、ユンボやダンプのように走行機械や吊り上げ機械の適宜個所に連結して引っ張り或いは吊り上げると、残余の埋め戻し土がシート体の捲り上げと一緒に引き上げられて掘削溝の側方に零れ出ることになり、手掘りすることなく仮設配管を撤去することができる。またシート体の捲り上げ長さが長くなると、シート体の途中に設けた引張連結部を使用すると、残余の埋め戻し土の排出を連続的に行うことができる。 Thus, the temporary pipe installation method is the same as the conventional machine until the burial depth of the temporary pipe is removed, as in the case of the above-described installation method (the invention of claim 1). After digging, after the machine digging, if the tensile connection part at the tip of the sheet body is connected to an appropriate part of a traveling machine or a lifting machine such as a yumbo or a dumping machine and pulled or lifted, the remaining backfilling soil will be It will be lifted together with the uplifting and will spill out to the side of the excavation groove, and the temporary piping can be removed without digging by hand. Further, if the sheet body is raised, the remaining backfill soil can be discharged continuously by using a tensile connecting portion provided in the middle of the sheet body.
また本発明(請求項5)に係る仮設配管の設置工法は、特に前記のシート体における引張連結部を、シート幅と対応する杆体を備えた吊り上げ器具又は引張器具と対応する構造としてなるもので、例えば側縁に通し輪等を形成し、前記通し輪(引張連結部)に杆体を挿通し、前記杆体を適宜な装置(ユンボ等の走行機体や吊り上げ機械)で、引っ張り或いは吊り上げることでシート体の捲り上がり、シート体が左右に偏ることなく効果的に行うことができるものである。 Moreover, the temporary pipe installation method according to the present invention (Claim 5) has a structure in which the tensile connecting portion in the sheet body corresponds to a lifting instrument or a tension instrument provided with a casing corresponding to the sheet width. For example, a sheet is formed by forming a through ring or the like on a side edge, inserting a housing into the through ring (tensile connection portion), and pulling or lifting the housing with an appropriate device (running machine body or lifting machine such as a yumbo). It is possible to carry out effectively without the body rising and the sheet body being biased left and right.
更に本発明に係る仮設配管の設置工法は、シート体の一部又は全部が、ネットその他の透水構造としてなるもので、雨が埋め戻した掘削溝に浸透してもシート体で滞留することがない。 Furthermore, in the temporary pipe installation method according to the present invention, part or all of the sheet body has a net or other water-permeable structure, and even if the rain penetrates into the excavated groove, it can remain in the sheet body. Absent.
本発明の構成は上記のとおりで、特別な樹脂製の仮埋体を採用することなく、従前と同様に掘削溝の掘削土や、埋め戻し用砂を使用して埋め戻しを行うものであるが、仮設配管撤去時の仮設配管掘り起こしに際して、機械力による掘削ですむもので、作業能率が格段に向上するものである。 The configuration of the present invention is as described above, and without using a special resin temporary embedding body, the excavation soil of the excavation groove and the backfilling sand are used in the same manner as before. However, when the temporary pipe is dug up when the temporary pipe is removed, it is only necessary to excavate by mechanical force, and the work efficiency is remarkably improved.
次に本発明の第一実施形態(第一工法)について説明する。図1乃至4に示した第一工法である仮設配管の設置工法には、シート体1及び吊上げ具2を使用するものである。
Next, a first embodiment (first construction method) of the present invention will be described. In the temporary piping installation method, which is the first method shown in FIGS. 1 to 4, the
シート体1は、シート本体11が土砂の吊上げに充分に耐久力を有する材質及び大きさ(後述する幅を備える)に形成されると共に、必要に応じて全体を網目の細かいネット(土砂が零れない程度の細かさ)、或いは一部をネット状、又は微細透孔を穿設して一部又は全部に透水性を有するようにしたもので、四隅(シート本体は長方形状とする)の側縁に、シート本体11と同様の材質でリング状耳部を縫合して吊上げ連結部12を形成したものである。
The
勿論前記吊上げ連結部12は、リング状耳部を別体で形成してシート本体11に装着するようにしても良いし、後述する吊上げ具2の連結部の構造に対応するものであれば良い。また四隅部分以外にも、その中間にも設けるようにしても良い。
Of course, the
吊上げ具2は、前記シート本体11の長さに対応した長さを備えて平行に配置した2本の杆体21と、前記杆体21の前後端に鉤状に形成する等の前記吊上げ連結部12との連結が可能な形状の連結部22と、杆体21をユンボ等の掘削機械Eで持ち上げることが可能となるようなチェーンなどで形成した吊上げ部23とを備えたものである。
The
前記の器具を使用しての本発明工法は、仮設配管Aを埋設するために仮設配管設置用の掘削溝Bを、ユンボ等の油圧ショベルを備えた所定の掘削機械Eで掘穿する。掘削溝Bは、仮設配管A同士の連結に必要な個所を除き、仮設配管Aを設置すべき深さと一致する深さとする。 In the construction method of the present invention using the above-described instrument, the excavation groove B for temporary pipe installation is excavated by a predetermined excavation machine E equipped with a hydraulic excavator such as a jumbo in order to embed the temporary pipe A. The excavation groove B has a depth that matches the depth at which the temporary piping A should be installed, except for the portions necessary for the connection between the temporary piping A.
仮設配管Aは、前記掘削溝Bの底面b1に直接載置し、次にこの仮設配管Aにシート本体11を、仮設配管Aに密着させて被せると共に、掘削溝Bの底面b1及び側面b2の下方部分を覆うように敷設する。この場合にシート本体11を掘削溝Bの側面b2における仮設配管Aの上縁より高い位置まで達するようにする。しかる後掘削溝B内に土砂Cを埋め戻して、適宜填圧して表面に舗装を施したり、或いは被覆マットDを敷設して仮設配管Aの設置工事を終了する(図2)。 The temporary piping A is placed directly on the bottom surface b1 of the excavation groove B, and then the sheet main body 11 is put on the temporary piping A in close contact with the temporary piping A, and the bottom surface b1 and the side surface b2 of the excavation groove B are covered. Lay down to cover the lower part. In this case, the seat body 11 is made to reach a position higher than the upper edge of the temporary pipe A on the side surface b2 of the excavation groove B. Thereafter, the earth and sand C are backfilled in the excavation groove B and the surface is paved by appropriately filling, or the covering mat D is laid and the installation work of the temporary piping A is completed (FIG. 2).
そして仮設配管Aは、本管工事が終了した後には、掘り起こして撤去する必要がある。この撤去作業は、掘削機械Eで仮設配管Aの埋設深さ近くまで機械掘りを行う(図3)。 The temporary pipe A needs to be dug up and removed after the main pipe work is completed. In this removal operation, the excavating machine E performs machine excavation to a depth near the burial depth of the temporary piping A (FIG. 3).
次にシート体1の吊上げ連結部12を露出させ、吊り上げ連結部12を吊上げ具2の連結部22に掛け止めなどの手段で連結し、吊上げ具2の吊上げ部23を掘削機械Eの作用部(アーム先端のショベル部分)に連結し、掘削機械Eでシート体1を持ち上げると、残余の埋め戻し土砂Cを一挙に掘削溝Bから取り出すことになり、仮設配管Aが露出する(図4)。
Next, the
そこで仮設配管Aを撤去し、掘削溝Bを埋め戻し、路面舗装等を行って仮設配管Aの撤去作業が終了するもので、何ら手掘り作業を行うことなく効率的に仮設配管Aの撤去が可能となるものである。 Therefore, the temporary piping A is removed, the excavation groove B is refilled, the road surface is paved, and the temporary piping A is removed. The temporary piping A can be efficiently removed without any manual digging work. It is possible.
次に本発明工法の第二実施形態(第二工法)について説明する。第二工法は、図5乃至8に示したとおりで、シート体3及び杆体4を使用するものである。
Next, a second embodiment (second method) of the method according to the present invention will be described. The second construction method is as shown in FIGS. 5 to 8 and uses the
シート体3は、シート体1と同様に、充分な強度及び耐久力を備えると共に、必要に応じて全体を網目の細かいネット状、或いは一部をネット状、又は微細透孔を穿設して一部又は全部に透水性を有するようにしたもので、シート本体31は、仮設配管Aを埋設する掘削溝Bの底面b1と同一幅か、或いはそれより少し幅広の長尺帯であり、具体的には、掘削溝Bに仮設配管Aを設置した上に被せた場合に、両端が掘削溝Bの側面と一致するか或いは側面より少し内側に位置する幅としたもので、更に適宜個所に引張連結部32,32aを設けているものである。
Similar to the
引張連結部32は、シート本体31の先端部分の左右端に、引張連結部(中間連結部)32aは、適宜間隔をおいて、シート本体31の側縁に添って設けたもので、所定長さで且つ適宜な強度を備えた杆体4が、幅方向に貫通して装着される通し輪形状に形成したものである。
The tensile connecting
前記の器具を使用しての本発明の第二工法は、第一工法と同様に、仮設配管Aを埋設するための掘削溝Bを掘穿する。掘削溝Bは、仮設配管A同士の連結に必要な個所を除き、仮設配管Aを設置すべき深さと一致する深さとする。そして仮設配管Aを、前記掘削溝Bの底面b1に直接載置し、次にこの仮設配管Aにシート本体31を、仮設配管Aに密着させて被せると共に、掘削溝Bの底面b1を覆うように敷設する(図7イ)。
The second construction method of the present invention using the above-mentioned tool digs the excavation groove B for embedding the temporary piping A, similarly to the first construction method. The excavation groove B has a depth that matches the depth at which the temporary piping A should be installed, except for the portions necessary for the connection between the temporary piping A. Then, the temporary piping A is directly placed on the bottom surface b1 of the excavation groove B, and then the temporary piping A is covered with the
この場合にシート本体31の先端部分の引張連結部32は、後述する機械掘削可能ライン(図6のラインa)以上に突出するように敷設し、しかる後掘削溝B内に土砂Cを埋め戻して、適宜填圧して表面に舗装を施したり、或いは被覆マットDを敷設して仮設配管Aの設置工事を終了する(図6)。
In this case, the
そして仮設配管Aは、本管工事が終了した後には、掘り起こして撤去する必要がある。この撤去作業は、掘削機械Eで仮設配管Aの埋設深さ近く(機械掘削可能ラインa)まで機械掘りを行う(図8イ)。 The temporary pipe A needs to be dug up and removed after the main pipe work is completed. In this removal operation, the excavating machine E performs the machine excavation up to the burial depth of the temporary pipe A (machine excavation line a) (FIG. 8A).
次にシート本体31の先端部分の左右の引張連結部32に杆体4を通し、前記掘削機械Eやその他の走行機械で、前記杆体4を掘削溝Bに添ってシート体の後方へ引っ張り上げると、残余の埋め戻し土Cがシート体3の捲り上げと一緒に引き上げられて掘削溝Bの側方に零れ出ることになり、更にシート体3の捲り上げ作業が進行して中間連結部32aが露出すると、当該中間連結部32aに杆体4を挿通して更に後方に引っ張り上げると、順次埋め戻し土Cが掘削溝Bの側方に零れ出ることになり、仮設配管Aが順次露出する。
Next, when the housing 4 is passed through the left and right tensile connecting
そこで仮設配管Aを撤去し、掘削溝Bを埋め戻し、路面舗装等を行って仮設配管Aの撤去作業が終了するもので、何ら手掘り作業を行うことなく効率的に仮設配管Aの撤去が可能となるものである。 Therefore, the temporary piping A is removed, the excavation groove B is refilled, the road surface is paved, and the temporary piping A is removed. The temporary piping A can be efficiently removed without any manual digging work. It is possible.
1 シート体
11 シート本体
12 吊上げ連結部
2 吊上げ具
21 杆体
22 連結部
23 吊上げ部
3 シート体
31 シート本体
32 引張連結部
32a 引張連結部(中間連結部)
4 杆体
A 仮設配管
B 掘削溝
b1 底面
b2 側面
C 土砂
D 被覆マット
E 掘削機械
DESCRIPTION OF
4 Housing A Temporary piping B Excavation groove b1 Bottom b2 Side C Earth and sand D Cover mat E Excavation machine
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2009290497A JP5324413B2 (en) | 2009-07-31 | 2009-12-22 | Temporary piping installation method |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2009178613 | 2009-07-31 | ||
JP2009178613 | 2009-07-31 | ||
JP2009290497A JP5324413B2 (en) | 2009-07-31 | 2009-12-22 | Temporary piping installation method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2011047259A JP2011047259A (en) | 2011-03-10 |
JP5324413B2 true JP5324413B2 (en) | 2013-10-23 |
Family
ID=43833843
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2009290497A Active JP5324413B2 (en) | 2009-07-31 | 2009-12-22 | Temporary piping installation method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP5324413B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5572539B2 (en) * | 2010-12-27 | 2014-08-13 | 明和工業株式会社 | Temporary piping installation method |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07317008A (en) * | 1994-05-27 | 1995-12-05 | Osaka Gas Co Ltd | Temporary back-filling method |
JPH08193304A (en) * | 1995-01-13 | 1996-07-30 | Nippon Steel Corp | Temporary burying method for hole excavated for laying burying pipe |
-
2009
- 2009-12-22 JP JP2009290497A patent/JP5324413B2/en active Active
Also Published As
Publication number | Publication date |
---|---|
JP2011047259A (en) | 2011-03-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105970900A (en) | Offshore wind turbine gravity type foundation installation seabed treatment process | |
CN110219359A (en) | A kind of Submersed type inspection well and its construction method | |
JP5324413B2 (en) | Temporary piping installation method | |
CN107724499A (en) | The construction method and pedestal of sewage conduct | |
JP4675130B2 (en) | Drain structure of embankment bank and its construction method | |
CN108894206B (en) | Sandbar sewage pipe and well anti-floating system and construction method | |
KR101023983B1 (en) | Method for executing punching type ditch | |
JP4863312B2 (en) | Excavation method | |
JP5572539B2 (en) | Temporary piping installation method | |
JP3756077B2 (en) | Burial method and structure of underground objects | |
KR20180028256A (en) | Method for preventing erosion and slope collapse | |
CN207376679U (en) | A kind of channel excavation auxiliary device | |
JP3611937B2 (en) | Temporary buried structure of borehole | |
JP4175755B2 (en) | Structure to prevent levitation of buried pipelines | |
JP5142269B2 (en) | Casing installation device and buried object laying method | |
JP5115456B2 (en) | Laying and burying pipelines on steep slopes | |
JP4614217B2 (en) | Tubing burial method | |
JP4498047B2 (en) | Reinforcement method for ground and / or underground objects | |
KR100581403B1 (en) | Method for constructing for a soft-ground breakwater | |
JP5121293B2 (en) | Shallow burial method of underground structure by geotextile | |
JP3720989B2 (en) | Sewer pipe burial method | |
JP2006299780A (en) | Temporary protector for end of buried pipe | |
JP2009257012A (en) | Paving mixture delivery system and buried object laying method | |
JPH07293748A (en) | Laying construction method for pipe body | |
KR101023507B1 (en) | Punching type ditch |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20120711 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20130626 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20130709 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20130718 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 5324413 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |