JP5254686B2 - Rebar assembly jig - Google Patents

Rebar assembly jig Download PDF

Info

Publication number
JP5254686B2
JP5254686B2 JP2008178636A JP2008178636A JP5254686B2 JP 5254686 B2 JP5254686 B2 JP 5254686B2 JP 2008178636 A JP2008178636 A JP 2008178636A JP 2008178636 A JP2008178636 A JP 2008178636A JP 5254686 B2 JP5254686 B2 JP 5254686B2
Authority
JP
Japan
Prior art keywords
reinforcing bar
feed screw
link
loose
rebar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2008178636A
Other languages
Japanese (ja)
Other versions
JP2010018974A (en
Inventor
透 笹川
大輔 土田
Original Assignee
東鉄工業株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 東鉄工業株式会社 filed Critical 東鉄工業株式会社
Priority to JP2008178636A priority Critical patent/JP5254686B2/en
Publication of JP2010018974A publication Critical patent/JP2010018974A/en
Application granted granted Critical
Publication of JP5254686B2 publication Critical patent/JP5254686B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Movable Scaffolding (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Description

本発明は、高構造物の補強工法における鉄筋組立方法に用いるに好適な鉄筋組立用冶具に関する。   The present invention relates to a reinforcing bar assembling tool suitable for use in a reinforcing bar assembling method in a reinforcing method for a high structure.

既存のコンクリート橋脚を耐震補強するため、例えば特許文献1により、既存橋脚の対向面に少なくとも一対の縦溝を形成し、縦溝間に形成された貫通孔内に挿通した中間帯鉄筋の両端を、縦溝内に固定された支保鋼材に固定し、既存橋脚の表面に複数の補強軸方向鉄筋を配筋し、複数の補強帯鉄筋を支保鋼材に貫通させて補強軸方向鉄筋のうえから既存橋脚の外周に巻き、これら補強鉄筋や支保鋼材をモルタル被覆層で被覆してなる補強構造が知られている。   In order to seismically reinforce existing concrete piers, for example, according to Patent Document 1, at least a pair of longitudinal grooves are formed on opposite surfaces of the existing piers, and both ends of intermediate strip reinforcing bars inserted into through holes formed between the longitudinal grooves are , Fixed to the supporting steel material fixed in the longitudinal groove, multiple reinforcing bar reinforcing bars are arranged on the surface of the existing pier, and several reinforcing bar reinforcing bars are penetrated through the supporting steel material and existing from above the reinforcing axial steel bars A reinforcement structure is known that is wound around the outer periphery of a bridge pier and covered with a mortar coating layer of these reinforcing steel bars and supporting steel materials.

ところで、高さが25mを超える構造物(以下、高構造物)の施工箇所としては、山間部、海岸部の山あいや谷あいに多く、施工条件が厳しい状況となっている。高構造物を耐震補強する場合、これまでは枠組み足場を橋脚に沿って設置し、RC巻き立て工法等で施工していた。また、鉄筋の組立作業には大型クレーンにより、鋼材を吊上げる必要があり、広い作業ヤードの確保も必要であった。   By the way, as a construction location of a structure having a height of more than 25 m (hereinafter referred to as a high structure), there are many places in mountainous areas, mountains and valleys in coastal areas, and the construction conditions are severe. In the past, in order to seismically strengthen high structures, framework scaffolds were installed along the piers and were constructed using the RC winding method. In addition, it was necessary to lift the steel material with a large crane for assembling the reinforcing bars, and it was necessary to secure a large work yard.

また、通常は大型クレーンを使用して鉄筋・型枠組立作業を行うが、山間部や海岸部の山あいや谷あいは、クレーンなどの大型重機械が入らないケースが多いため、クレーンを使わないで効率的に施工する方法が求められている。
また、これまでは鉄筋・型枠組立、コンクリート打設を、例えば5m程度を1サイクルとして施工してきたが、1サイクル毎に枠組み足場を組立て施工することにより、工程が多く必要となっていた。
In addition, rebar and formwork assembly work is usually performed using a large crane, but there are many cases where large heavy machinery such as cranes do not enter in mountains and coastal areas, so do not use cranes. There is a need for an efficient construction method.
In the past, rebar / formwork assembly and concrete placement have been carried out with, for example, about 5 m as one cycle. However, many steps are required by assembling and constructing a frame scaffold every cycle.

すなわち、高構造物の耐震補強を行う場合、足場はコンクリート打設高さに合わせて枠組み足場を設置するため、多くの日数を要している。   In other words, when a seismic reinforcement of a high structure is performed, it takes a lot of days because the scaffold is installed in accordance with the concrete placement height.

ここで、特許文献2により、複数本の支柱に沿って昇降する1基の作業台よりなり、作業台の床板には折り曲げ自在な可撓性の連結部を設けた、昇降足場が知られている。   Here, according to Patent Document 2, an elevating scaffold is known, which is composed of one work table that moves up and down along a plurality of support columns, and is provided with a flexible connecting portion that can be bent on the floor plate of the work table. Yes.

また、特許文献3により、装置本体を、橋脚の支承部を囲むようにしてそれぞれ沓座上に載置され、隣接するものどうしが互いに連結固定される4つのセグメントで構成し、各セグメントの突出部の先端部には、ねじ機構を設け、このねじ機構で上部構造体を押すことにより、装置本体を沓座に押圧固定して、各セグメントには、支持バーを設け、各支持バーには、電動ウインチを着脱可能に支持させた橋脚用吊り装置が知られている。
特開平11−36230号公報 特開平7−197641号公報 特開平9−302949号公報
Further, according to Patent Document 3, the apparatus main body is composed of four segments that are respectively placed on a scorpion so as to surround the support portion of the pier, and adjacent ones are connected and fixed to each other. A screw mechanism is provided at the tip, and the upper structure is pushed by this screw mechanism to press and fix the device body to the saddle. Each segment is provided with a support bar, and each support bar is electrically operated. 2. Description of the Related Art A suspension device for a bridge pier in which a winch is detachably supported is known.
JP 11-36230 A JP-A-7-197641 JP-A-9-302949

しかし、高構造物に対し枠組み足場ではジベル筋、軸方向鉄筋、帯鉄筋の施工は連続作業ができないため、工期を多く必要としていた。また、高構造物施工箇所は作業ヤードの確保が困難なことから、大型クレーンを必要としない工法の開発が求められていた。   However, construction work of gibber, axial rebar and strip rebar cannot be performed continuously on a framework scaffold for high structures, requiring a lot of work period. In addition, since it is difficult to secure a work yard at high-structure construction sites, development of a construction method that does not require a large crane has been sought.

つまり、山あいや谷あい等の現場においては、鉄筋組立等の作業にはクレーンが使用できないことがあることから、ホイストにより鉄筋を吊上げて組立てる必要がある。しかし、ホイストにより吊り込むためには、既存の吊り上げ方法では効率が悪いため、例えば特許文献2の昇降足場と例えば特許文献3のような電動ウインチ等と連携を図る方法で効率化する必要がある。   In other words, in a site such as a mountain or a valley, a crane may not be used for operations such as rebar assembly. Therefore, it is necessary to assemble the rebar by lifting it with a hoist. However, in order to suspend with a hoist, since the efficiency of the existing lifting method is low, it is necessary to improve the efficiency by a method that cooperates with, for example, the lifting scaffold of Patent Document 2 and the electric winch or the like of Patent Document 3, for example. .

本発明の課題は、高構造物の補強工法における鉄筋組立に用いるのに好適し、軸方向鉄筋、帯鉄筋を設計鉄筋間隔に精度良くセットして、鉄筋組立が連続的にでき、大幅な工期短縮に寄与できる治具を提供することである。   The object of the present invention is suitable for rebar assembly in the reinforcement method of high structures, and can set the axial rebars and strip rebars accurately in the design rebar spacing, and can continuously assemble the rebars. It is to provide a jig that can contribute to shortening.

以上の課題を解決するため、請求項1に記載の発明は、送りねじと、この送りねじの一端部に固定するストッパーと、前記送りねじ上にねじ係合する係合部材と、前記ストッパーと係合部材との間において前記送りねじ上に遊合する複数個の遊合部材と、前記係合部材と遊合部材にそれぞれ設けられ、鉄筋を1本ずつ保持する鉄筋保持部と、前記係合部材に対して前記遊合部材を順に連結するリンク機構と、を備え、前記遊合部材に対し前記リンク機構のリンクの一端部を連結して、前記送りねじと平行に配置され、前記リンクの中間部に遊合する案内軸を備える鉄筋組立用冶具を特徴とする。   In order to solve the above problems, the invention described in claim 1 is directed to a feed screw, a stopper fixed to one end of the feed screw, an engagement member engaged with the screw on the feed screw, and the stopper. A plurality of idler members that loosely engage with the engaging member on the feed screw, a reinforcing bar holding portion that is provided on each of the engaging member and the idler member, and holds the reinforcing bars one by one; A link mechanism for sequentially connecting the loose members to the mating member, one end of the link of the link mechanism being coupled to the loose member, and arranged in parallel with the feed screw, the link A reinforcing bar assembling tool including a guide shaft loosely engaged with an intermediate portion of the steel plate is characterized.

また、請求項2に記載の発明は、送りねじと、この送りねじの一端部に固定するストッパーと、前記送りねじ上にねじ係合する係合部材と、前記ストッパーと係合部材との間において前記送りねじ上に遊合する複数個の遊合部材と、前記係合部材と遊合部材にそれぞれ設けられ、鉄筋を1本ずつ保持する鉄筋保持部と、前記係合部材に対して前記遊合部材を順に連結するリンク機構と、を備え、前記遊合部材に対し前記リンク機構のリンクの中間部を結合してなる鉄筋組立用冶具を特徴とする。   According to a second aspect of the present invention, there is provided a feed screw, a stopper fixed to one end portion of the feed screw, an engaging member engaged with the screw on the feed screw, and between the stopper and the engaging member. A plurality of idler members loosely mated on the feed screw, an engagement member and an idler member, respectively, and a reinforcing bar holding portion for holding one reinforcing bar at a time; And a link mechanism for sequentially connecting the loose members, and a rebar assembly jig formed by joining intermediate portions of the links of the link mechanism to the loose members.

請求項3に記載の発明は、請求項2に記載の鉄筋組立用冶具であって、前記遊合部材に対し前記リンクが交差して結合されていることを特徴とする。   A third aspect of the present invention is the reinforcing bar assembling jig according to the second aspect, wherein the link is crossed and coupled to the loose member.

また、請求項4に記載の発明は、送りねじと、この送りねじの一端部に固定するストッパーと、前記送りねじ上にねじ係合する係合部材と、前記ストッパーと係合部材との間において前記送りねじ上に遊合する遊合部材と、前記係合部材に対して前記遊合部材を連結し、かつ、前記遊合部材と反対側に延長して設けられるリンク機構と、前記係合部材と遊合部材と、前記リンク機構の前記遊合部材と反対側に延長して設けられる複数個のリンクにそれぞれ設けられ、鉄筋を1本ずつ保持する鉄筋保持部と、前記送りねじと平行に配置され、前記リンク機構のリンクの中間部に遊合する案内軸と、を備え、前記遊合部材に対し前記リンク機構のリンクの一端部を連結して、前記リンク機構の前記遊合部材と反対側に延長して設けられる複数個のリンクの一端部に前記鉄筋保持部を備える鉄筋組立用冶具を特徴とする。   According to a fourth aspect of the present invention, there is provided a feed screw, a stopper fixed to one end portion of the feed screw, an engagement member engaged with the screw on the feed screw, and between the stopper and the engagement member. And a link mechanism that is connected to the engagement member and extends to the opposite side of the engagement member, and the engagement mechanism. A rebar holding part that is provided on each of a plurality of links provided to extend on the opposite side of the link member to the loose member, the rebar holding part that holds rebars one by one, and the feed screw; A guide shaft that is arranged in parallel and loosely engages an intermediate portion of the link of the link mechanism, and connects the one end of the link of the link mechanism to the loose member, and the looseness of the link mechanism A plurality of parts provided to extend on the opposite side of the member Wherein the jig reinforcing bar assembly comprising said reinforcing bar holding portion at one end of the link.

請求項5に記載の発明は、請求項4に記載の鉄筋組立用冶具であって、前記案内軸は、前記送りねじの2倍以上長尺であることを特徴とする。   A fifth aspect of the present invention is the reinforcing bar assembling jig according to the fourth aspect, wherein the guide shaft is at least twice as long as the feed screw.

請求項6に記載の発明は、請求項1または4に記載の鉄筋組立用冶具であって、前記リンクの中間部に、前記案内軸上に遊合する第2の遊合部材を備えることを特徴とする。   The invention according to claim 6 is the reinforcing bar assembling tool according to claim 1 or 4, wherein a second loosening member that loosely engages with the guide shaft is provided at an intermediate portion of the link. Features.

請求項7に記載の発明は、請求項1または4に記載の鉄筋組立用冶具であって、前記案内軸の先端部に、前記リンクの移動を規制する第2のストッパーが設けられていることを特徴とする。   The invention according to claim 7 is the reinforcing bar assembling tool according to claim 1 or 4, wherein a second stopper for restricting movement of the link is provided at a tip portion of the guide shaft. It is characterized by.

本発明によれば、高構造物の補強工法における鉄筋組立において、軸方向鉄筋、帯鉄筋を冶具により設計鉄筋間隔に精度良くセットして、鉄筋組立が連続的にできるため、工期を大幅に短縮できる。   According to the present invention, in rebar assembly in the reinforcement method for high structures, axial rebars and strip rebars can be set with high accuracy in the design rebar spacing using jigs, and rebar assembly can be performed continuously, greatly shortening the work period. it can.

以下、図を参照して本発明を実施するための最良の形態を詳細に説明する。
図1は本発明を適用する高構造物の耐震補強工法の一例の構成として橋脚の耐震補強におけるジベル筋施工を示したもので、1はコンクリート橋脚(高構造物)、2はマスト(支柱)、3はワークプラットホーム(昇降足場)、4は天井レール、5はホイスト、11はジベル筋である。
Hereinafter, the best mode for carrying out the present invention will be described in detail with reference to the drawings.
FIG. 1 shows the construction of a gibber bar in the seismic reinforcement of a bridge pier as an example of the structure of a seismic reinforcement method for a high structure to which the present invention is applied. 1 is a concrete pier (high structure), 2 is a mast (post). 3 is a work platform (elevating scaffold), 4 is a ceiling rail, 5 is a hoist, and 11 is a dowel.

図示のように、高構造物であるコンクリート橋脚(以下、単に橋脚と呼ぶ)1の前後左右の四面を囲むように、前後各々二本ずつのマスト2に沿って昇降動作する昇降足場であるワークプラットホーム3が備えられている。このワークプラットホーム3には昇降動作の駆動源である電動モータが搭載されている。また、橋脚1の上部には、その前後面に平行する天井レール4に沿って移動する複数ずつのホイスト5が備えられている。   As shown in the figure, a work that is an elevating scaffold that moves up and down along two masts 2 on the front and rear sides so as to surround the four front and rear four sides of a concrete pier (hereinafter simply referred to as a pier) 1 that is a high structure. A platform 3 is provided. The work platform 3 is equipped with an electric motor which is a drive source for the lifting operation. In addition, a plurality of hoists 5 each moving along a ceiling rail 4 parallel to the front and rear surfaces of the pier 1 are provided on the upper portion of the pier 1.

なお、マスト2は前後各一本ずつでも良い。また、ワークプラットホーム3は、図示例では、前後のマスト2に沿って昇降するワークプラットホーム3が対をなす構成となっているが、全一体の構成のものでも良い。そして、天井レール4は、橋脚1とマスト2との間に配置されている。この天井レール4は、橋脚1またはマスト2に固定される。さらに、その天井レール4の両端間にも天井レール4が架設されている。   The mast 2 may be one each before and after. Further, in the illustrated example, the work platform 3 is configured such that the work platform 3 that moves up and down along the front and rear masts 2 forms a pair. The ceiling rail 4 is disposed between the pier 1 and the mast 2. The ceiling rail 4 is fixed to the pier 1 or the mast 2. Further, the ceiling rail 4 is also constructed between both ends of the ceiling rail 4.

以上のワークプラットホーム3には、耐震補強資材が天井レール4に備えられたホイスト5を利用して積み込まれ、ここでは、ジベル筋11が積み込まれて、マスト2に沿ったワークプラットホーム3の上昇・停止の都度、図示のように、橋脚1の外面にジベル筋11が組み付けられる。   The work platform 3 is loaded with the seismic reinforcement material using the hoist 5 provided on the ceiling rail 4. Here, the gibber muscle 11 is loaded and the work platform 3 is raised along the mast 2. Each time the vehicle is stopped, as shown in the figure, the gibber muscles 11 are assembled to the outer surface of the pier 1.

図2は次の軸方向鉄筋・帯鉄筋施工を示したもので、12は軸方向鉄筋、13・14は帯鉄筋である。   FIG. 2 shows the construction of the next axial rebar / strand reinforcement, 12 is an axial rebar, and 13 and 14 are rebars.

すなわち、ワークプラットホーム3には、天井レール4のホイスト5を利用して橋脚1の周囲を囲む軸方向鉄筋12と直線状の帯鉄筋13及び平面視コ字状の帯鉄筋14が積み込まれて、ワークプラットホーム3の上昇・停止の都度、図示のように、橋脚1の周囲に軸方向鉄筋12が組み付けられて、その軸方向鉄筋12に対し直線状の帯鉄筋13及び平面視コ字状の帯鉄筋14が組み付けられる。   That is, the work platform 3 is loaded with the axial rebar 12 surrounding the pier 1 around the hoist 5 of the ceiling rail 4, the straight rebar 13, and the U-shaped rebar 14 in plan view. Each time the work platform 3 is raised or stopped, an axial rebar 12 is assembled around the pier 1 as shown in the figure, and a linear rebar 13 and a U-shaped band in a plan view with respect to the axial rebar 12. The reinforcing bar 14 is assembled.

図3は次の型枠・コンクリート打設を示したもので、15は型枠、16は打設コンクリートである。   FIG. 3 shows the next formwork / concrete placement, in which 15 is the formwork and 16 is the cast concrete.

すなわち、ワークプラットホーム3には、天井レール4のホイスト5を利用して型枠15が積み込まれて、ワークプラットホーム3の上昇・停止の都度、橋脚1の周囲に組み付けた鉄筋を囲む型枠15が組み付けられて、さらに、図示のように、ワークプラットホーム3の上昇・停止後、型枠15内にコンクリートが打設される。図示例では、例えば、1段目から3段目までの型枠脱型が済んで、打設コンクリート16が現れ、4段目の型枠15・コンクリート打設工程となっている。   That is, the work platform 3 is loaded with a form 15 using the hoist 5 of the ceiling rail 4, and each time the work platform 3 is raised or stopped, the form 15 surrounding the reinforcing bars assembled around the pier 1 is provided. Further, as shown in the figure, after the work platform 3 is raised and stopped, concrete is placed in the mold 15. In the illustrated example, for example, the mold removal from the first stage to the third stage is completed, and the cast concrete 16 appears, which is the fourth-stage mold 15 / concrete placing process.

図4は次の型枠脱型を示したものである。
図示のように、例えば、5段目及び最終6段目の型枠15・コンクリート打設後、型枠脱型される。
FIG. 4 shows the next mold release.
As shown in the figure, for example, the mold 15 is removed from the mold after the casting of the fifth stage and the final sixth stage of the mold 15 and concrete.

次に、図5は図2の軸方向鉄筋・帯鉄筋施工における軸方向鉄筋組立方法を示したもので、20は鉄筋組立用冶具である。
図示のように、軸方向鉄筋12は、天井レール4の一対のホイスト5から繰り出されるケーブル6により吊り下げた鉄筋組立用冶具20を上下一対用いて、横方向に間隔を開けて垂直に保持された状態で組み付けられる。
Next, FIG. 5 shows an axial rebar assembling method in the axial rebar / band rebar construction shown in FIG. 2, and 20 is a rebar assembling jig.
As shown in the figure, the axial rebar 12 is held vertically with a space in the horizontal direction using a pair of upper and lower rebar assembly jigs 20 suspended by cables 6 fed from a pair of hoists 5 of the ceiling rail 4. It is assembled in the state.

鉄筋組立用冶具20は、図6に拡大して示したように、複数本の鉄筋を1本ずつ保持する複数個の鉄筋保持部21と、これら複数個の鉄筋保持部21の間隔を調整する間隔調整部30と、を備えている。鉄筋保持部21は、例えば一部を切り欠いたパイプ状の保持金具22に鉄筋(図示では軸方向鉄筋12)を通してボルト23の締め付けにより固定する方式のものである。   As shown in an enlarged view in FIG. 6, the reinforcing bar assembly jig 20 adjusts the intervals between the plurality of reinforcing bar holding parts 21 that hold a plurality of reinforcing bars one by one, and the plurality of reinforcing bar holding parts 21. An interval adjusting unit 30. The reinforcing bar holding portion 21 is of a type that is fixed to a pipe-shaped holding fitting 22 with a part cut away by tightening a bolt 23 through a reinforcing bar (axial reinforcing bar 12 in the drawing).

間隔調整部30は、軸線が水平方向の送りねじ31と、この送りねじ31上にねじ係合するナットによる係合部材32と、送りねじ31に対し遊合する複数個の鞘材による遊合部材33(図10参照)と、これら複数個の遊合部材33を送りねじ31の回転時に係合部材32に連動させるリンク34・35とから構成されている。図示例において、隣り合う係合部材32及び遊合部材33間に2枚1組のリンク34とリンク35が回動自在に連結されて、送りねじ31の一端部に対し回転自在に組み付けた固定プレート36と、その隣り合う遊合部材33間に2枚1組のリンク34が回動自在に架設されている。   The interval adjusting unit 30 includes a feed screw 31 whose axis is in the horizontal direction, an engagement member 32 using a nut that is screw-engaged with the feed screw 31, and a plurality of sheath members that are engaged with the feed screw 31. A member 33 (see FIG. 10) and links 34 and 35 for interlocking the plurality of loose members 33 with the engaging member 32 when the feed screw 31 is rotated. In the illustrated example, a set of two links 34 and a link 35 are rotatably connected between adjacent engaging members 32 and idler members 33, and fixed to one end portion of the feed screw 31 so as to be rotatable. A set of two links 34 is rotatably mounted between the plate 36 and the adjacent idler member 33.

ここで、係合部材32及び遊合部材33の位置に対応して、リンク34・35の回動連結部の一側面に鉄筋保持部21の保持金具22が取り付けられている。
以上により間隔調整部30は、固定プレート36と反対側端部の係合部材32が送りねじ31との相対回転に連動して移動することで、その間のリンク34・35の伸縮動作を伴って遊合部材33の間隔が等間隔を保ちながら変更される。
Here, corresponding to the positions of the engaging member 32 and the loose member 33, the holding metal fitting 22 of the reinforcing bar holding portion 21 is attached to one side surface of the rotation connecting portion of the links 34 and 35.
As described above, the distance adjusting unit 30 moves with the engagement member 32 at the end opposite to the fixing plate 36 in conjunction with the relative rotation with the feed screw 31, thereby causing the links 34 and 35 to expand and contract therebetween. The interval between the loose members 33 is changed while maintaining an equal interval.

図7(a)は以上の鉄筋組立用冶具20による鉄筋保持を示したもので、図示例では、前述した固定プレート36に代えて、リンク35及び固定部材37を設けている。この固定部材37は送りねじ31の一端部に対し回転自在に組み付けたもので、この固定部材37に鉄筋保持部21の保持金具22が設けられている。そして、図示例では、その固定部材37の鉄筋保持部21を除いて、他の鉄筋保持部21に軸方向鉄筋12が保持されている。   FIG. 7A shows the reinforcing bar holding by the reinforcing bar assembly jig 20 described above. In the illustrated example, a link 35 and a fixing member 37 are provided in place of the fixing plate 36 described above. The fixing member 37 is rotatably assembled to one end portion of the feed screw 31, and the holding member 22 of the reinforcing bar holding portion 21 is provided on the fixing member 37. In the illustrated example, the axial reinforcing bars 12 are held by other reinforcing bar holding parts 21 except for the reinforcing bar holding part 21 of the fixing member 37.

図7(b)は間隔調整部30の収縮調整を示したもので、図7(c)はその収縮状態での先行既設鉄筋12Aへの固定と鉄筋間隔調整を矢印で示したものであり、図示のように、固定部材37の鉄筋保持部21を端部の先行既設鉄筋12Aに固定する。
このように、間隔調整部30を収縮調整してコンパクトにしながら、固定部材37の鉄筋保持部21を先行既設鉄筋12Aに固定することで、鉄筋組立用冶具20がブラブラせず安全を確保できる。
その後、矢印で示すように、間隔調整部30を伸張調整する。
FIG. 7B shows the contraction adjustment of the interval adjusting unit 30, and FIG. 7C shows the fixing to the pre-existing rebar 12 </ b> A in the contracted state and the reinforcement interval adjustment with arrows, As illustrated, the reinforcing bar holding part 21 of the fixing member 37 is fixed to the preceding existing reinforcing bar 12A at the end.
In this way, by fixing the reinforcing bar holding part 21 of the fixing member 37 to the preceding existing reinforcing bar 12A while shrinking and adjusting the interval adjusting part 30 to be compact, the rebar assembling jig 20 can be secured without being dangled.
Thereafter, as shown by the arrows, the distance adjusting unit 30 is stretched and adjusted.

図7(d)は下方の先行既設鉄筋12Bへの軸方向鉄筋12の圧接を示したもので、仮想線で簡略化して示した上下一対の鉄筋組立用冶具20で保持された軸方向鉄筋12を、下方の先行既設鉄筋12Bに緊結・圧接する。   FIG. 7D shows the pressure welding of the axial rebar 12 to the lower preceding existing rebar 12B, and the axial rebar 12 held by a pair of upper and lower rebar assembling jigs 20 simplified by phantom lines. Are fastened and pressed against the preceding existing reinforcing bar 12B.

以上の軸方向鉄筋12の組立フローは以下のとおりである。
1.鉄筋組立用冶具20に軸方向鉄筋12を取り付ける。
2.鉄筋組立用冶具20の間隔調整部30を収縮調整する。
3.鉄筋組立用冶具20を図示しない小型クレーンによりワークプラットホーム3内に吊り込む。
4.ワークプラットホーム3を作業箇所まで上昇させる。
5.ホイスト5により鉄筋組立用冶具20を吊り上げる。
6.鉄筋組立用冶具20を端部の先行既設鉄筋12Aに固定する。
7.鉄筋組立用冶具20の間隔調整部30を伸張調整する。
8.鉄筋組立用冶具20の軸方向鉄筋12を下方の先行既設鉄筋12Bに緊結・圧接する。
The assembly flow of the above axial rebar 12 is as follows.
1. The axial rebar 12 is attached to the rebar assembly jig 20.
2. Shrinkage adjustment of the space | interval adjustment part 30 of the rebar assembly jig 20 is carried out.
3. The reinforcing bar assembly jig 20 is suspended in the work platform 3 by a small crane (not shown).
4). The work platform 3 is raised to the work location.
5. The rebar assembly jig 20 is lifted by the hoist 5.
6). The reinforcing bar assembly jig 20 is fixed to the preceding existing reinforcing bar 12A at the end.
7. The distance adjusting unit 30 of the reinforcing bar assembling jig 20 is stretched and adjusted.
8). The axial rebar 12 of the reinforcing bar assembling tool 20 is tightly bonded and pressed to the lower preceding existing reinforcing bar 12B.

次に、図8は図2の軸方向鉄筋・帯鉄筋施工における帯鉄筋組立方法を示したもので、図示のように、帯鉄筋13・14は、天井レール4の一対のホイスト5から繰り出されるケーブル6により吊り下げた鉄筋組立用冶具20を左右一対または前後一対用いて、縦方向に間隔を開けて水平に保持された状態で組み付けられる。   Next, FIG. 8 shows a method for assembling the band rebar in the axial rebar / band rebar construction shown in FIG. 2. As shown in the figure, the band rebars 13 and 14 are fed out from a pair of hoists 5 of the ceiling rail 4. The rebar assembling jig 20 suspended by the cable 6 is assembled using a pair of left and right or a pair of front and rear in a state of being held horizontally with a space in the vertical direction.

ここで、図9(a)は帯鉄筋13・14の配置を示したもので、橋脚1の周囲に軸方向鉄筋12を囲むようにして、図示のように、平行する直線状の帯鉄筋13及び対向する平面視コ字状の帯鉄筋14が組み付けられる。   Here, FIG. 9A shows the arrangement of the rebars 13 and 14. The axial rebar 12 is surrounded around the pier 1 so that the parallel straight rebars 13 are opposed to each other as shown in the figure. A band rebar 14 having a U-shape in plan view is assembled.

図9(b)は平面視コ字状の帯鉄筋14の鉄筋組立用冶具20による保持箇所を示したもので、平面視コ字状の帯鉄筋14は、図示のように、中央部を鉄筋保持部21で保持して、両側部を対応するポイントPで、天井レール4の一対のホイスト5から繰り出されるケーブル6により保持される。
こうして、平面視コ字状の帯鉄筋14の両側部はホイスト5により所定高さで吊り上げて組み付けられる。
FIG. 9B shows a holding position of the U-shaped band rebar 14 in plan view by the reinforcing bar assembly jig 20, and the U-shaped band rebar 14 in plan view has a reinforcing bar at the center as shown in the figure. It is held by the holding part 21, and both sides are held at the corresponding points P by the cable 6 fed out from the pair of hoists 5 of the ceiling rail 4.
In this way, both sides of the U-shaped band reinforcing bar 14 in plan view are lifted and assembled by the hoist 5 at a predetermined height.

図9(c)は直線状の帯鉄筋13の鉄筋組立用冶具20による保持箇所を示したもので、直線状の帯鉄筋13は、図示のように、両端部側を鉄筋保持部21で保持される。   FIG. 9 (c) shows a holding position of the linear band reinforcing bar 13 by the reinforcing bar assembly jig 20, and the linear band reinforcing bar 13 is held by the reinforcing bar holding part 21 at both ends as shown in the figure. Is done.

図10は図8(b)の鉄筋組立用冶具20を拡大したもので、基本的には、前述した鉄筋組立用冶具20の送りねじ31を垂直方向に向けるとともに、係合部材32に鉄筋保持部21の保持金具22を設けたものである。   FIG. 10 is an enlarged view of the reinforcing bar assembly jig 20 shown in FIG. 8B. Basically, the feed screw 31 of the reinforcing bar assembly jig 20 is directed in the vertical direction, and the engaging member 32 holds the reinforcing bar. The holding metal fitting 22 of the part 21 is provided.

図11は図10の鉄筋保持部21の保持方式と異なる保持方式を示したもので、図11(a)は回転式の鉄筋保持部24であり、図示のように、例えば切欠部を有するリング状の保持金具25・26を組み合わせて帯鉄筋13・14を着脱する回転式のものである。
また、図11(b)はワンタッチ式の鉄筋保持部27であり、図示のように、例えばフック状の保持金具28にストッパピン29を組み合わせて帯鉄筋13・14を着脱するワンタッチ式のものである。
FIG. 11 shows a holding method different from the holding method of the reinforcing bar holding part 21 of FIG. 10, and FIG. 11 (a) shows a rotary reinforcing bar holding part 24. As shown in the figure, for example, a ring having a notch part. It is a rotary type that attaches and detaches the strip reinforcing bars 13 and 14 by combining the holding brackets 25 and 26 in the shape of a ring.
FIG. 11B shows a one-touch type reinforcing bar holding portion 27. As shown in the figure, for example, the hook-type holding bracket 28 is combined with a stopper pin 29 to attach and detach the band reinforcing bars 13 and 14. is there.

図12はワークプラットホーム3上の鉄筋取込みガイド40を示したもので、図示のように、ワークプラットホーム3の床面上には、左右一対の傾斜ガイド板41及びその上方に連続する曲線ガイド板42による鉄筋取込みガイド40が設置されている。
図示のように、帯鉄筋13を保持した一対の鉄筋組立用冶具20は、図示しない小型クレーンによりワークプラットホーム3上の所定の床面上の橋脚1側に、図示したように、固定プレート36を下にしてセットされる。このとき、鉄筋組立用冶具20に保持された帯鉄筋13は、一対の鉄筋取込みガイド40の傾斜ガイド板41の近傍位置にある。
FIG. 12 shows a reinforcing bar take-in guide 40 on the work platform 3. As shown in the figure, on the floor surface of the work platform 3, a pair of left and right inclined guide plates 41 and a curved guide plate 42 continuous above the left and right inclined guide plates 41. A reinforcing bar take-in guide 40 is installed.
As shown in the figure, a pair of rebar assembling jigs 20 holding the rebar 13 is provided with a fixing plate 36 as shown in the figure on the side of the pier 1 on a predetermined floor surface on the work platform 3 by a small crane (not shown). Set down. At this time, the band reinforcing bar 13 held by the reinforcing bar assembling jig 20 is in the vicinity of the inclined guide plate 41 of the pair of reinforcing bar take-in guides 40.

そして、一対の鉄筋組立用冶具20に、天井レール4の一対のホイスト5から繰り出されるケーブル6を連結した後、ホイスト5により鉄筋組立用冶具20を吊り上げると、鉄筋組立用冶具20に保持された帯鉄筋13は、一対の鉄筋取込みガイド40の傾斜ガイド板41にガイドされながら上昇し、その上部の曲線ガイド板42により橋脚1側に吊り込まれて上昇する。   Then, after connecting the cable 6 fed from the pair of hoists 5 of the ceiling rail 4 to the pair of rebar assembly jigs 20 and then lifting the rebar assembly jig 20 by the hoists 5, the rebar assembly jig 20 holds the rebar assembly jig 20. The band reinforcing bar 13 is raised while being guided by the inclined guide plate 41 of the pair of reinforcing bar take-in guides 40 and is lifted by being hung to the pier 1 side by the curved guide plate 42 on the upper part thereof.

図13は鉄筋組立用冶具20による先行既設鉄筋13A・14Aへの固定を示したもので、最下段の鉄筋保持部21を除いて、他の鉄筋保持部21に帯鉄筋13(または帯鉄筋14)が保持されている。その後、図示のように、最下段の鉄筋保持部21を下方の先行既設鉄筋13A(または先行既設鉄筋14A)に固定する。   FIG. 13 shows the fixing to the pre-existing reinforcing bars 13A and 14A by the reinforcing bar assembly jig 20. Except for the lowermost reinforcing bar holding part 21, the reinforcing bar holding part 13 (or the band reinforcing bar 14) is connected to the other reinforcing bar holding parts 21. ) Is held. Thereafter, as shown in the drawing, the lowermost reinforcing bar holding portion 21 is fixed to the lower preceding existing reinforcing bar 13A (or the preceding existing reinforcing bar 14A).

以上の帯鉄筋13・14の組立フローは、前述した軸方向鉄筋12の組立フローと同様である。   The assembly flow of the band rebars 13 and 14 is the same as the assembly flow of the axial rebar 12 described above.

以上の施工方法によれば、橋脚1に対しワークプラットホーム3により耐震補強を行う場合、ジベル筋11、軸方向鉄筋12、帯鉄筋13・14の施工が連続的にできるため、工期を大幅に短縮できる。   According to the construction method described above, when the seismic reinforcement is performed on the pier 1 by the work platform 3, the construction of the gibber reinforcement 11, the axial reinforcement 12, and the strip reinforcements 13 and 14 can be continuously performed, so the construction period is greatly shortened. it can.

なお、以上においては、橋脚の耐震補強としたが、耐震補強の対象は他に塔などの高構造物であっても良い。
また、昇降足場の構成等も任意であり、その他、具体的な細部構造等についても適宜に変更可能であることは勿論である。
In the above description, the bridge pier is seismic strengthened, but the target of seismic strengthening may be a high structure such as a tower.
Further, the structure of the lifting scaffold is arbitrary, and it is needless to say that other specific detailed structures can be appropriately changed.

(実施形態1)
図14から図16は本発明を適用した鉄筋組立用冶具20の実施形態1の構成として軸方向鉄筋12の吊り込み時及び鉄筋設置時(最大間隔調整時)を示したもので、前述した実施形態と同様、6はケーブル、20は鉄筋組立用冶具、21は鉄筋保持部、31は送りねじ、32は係合部材、33は遊合部材、34・35はリンクであって、39はストッパー、51は案内軸、52は第2の遊合部材、53は第2のストッパーである。
(Embodiment 1)
14 to 16 show the configuration of the first embodiment of the reinforcing bar assembly jig 20 to which the present invention is applied, when the axial reinforcing bar 12 is suspended and when the reinforcing bar is installed (when the maximum interval is adjusted). As in the embodiment, 6 is a cable, 20 is a reinforcing bar assembly jig, 21 is a reinforcing bar holding part, 31 is a feed screw, 32 is an engaging member, 33 is a loose member, 34 and 35 are links, and 39 is a stopper. , 51 is a guide shaft, 52 is a second idler member, and 53 is a second stopper.

すなわち、実施形態1の鉄筋組立用冶具20は、図示のように、送りねじ31の一端部にナットによるストッパー39を固定して、このストッパー39と係合部材32との間において送りねじ31上に遊合する複数個(図示例では5個)の遊合部材33を設けている。そして、遊合部材33に対しリンク34・35の一端部を連結して、送りねじ31と平行に配置した案内軸51をリンク34・35の中間部に遊合する。
具体的には、対をなすリンク34・35の一端部の間に、送りねじ31上の係合部材32及び遊合部材33をそれぞれ回動自在に組み付けて、同じく対をなすリンク34・35の中間部の間に、案内軸51上に遊合する鞘材による第2の遊合部材52をそれぞれ回動自在に組み付けている。また、案内軸51の両端部にナットによる第2のストッパー53をそれぞれ固定する。
That is, in the reinforcing bar assembly jig 20 of the first embodiment, as shown in the drawing, a stopper 39 by a nut is fixed to one end portion of the feed screw 31, and the feed screw 31 is placed between the stopper 39 and the engaging member 32. A plurality of (five in the illustrated example) idler members 33 are provided. Then, one end portions of the links 34 and 35 are connected to the loose member 33, and the guide shaft 51 arranged in parallel with the feed screw 31 is loosely engaged with the intermediate portion of the links 34 and 35.
Specifically, the engaging member 32 and the loose member 33 on the feed screw 31 are rotatably assembled between one end portions of the paired links 34 and 35, respectively, and the paired links 34 and 35 are also formed. The second idler member 52 made of a sheath material that engages on the guide shaft 51 is rotatably assembled between the intermediate portions of the intermediate shafts. Moreover, the 2nd stopper 53 by a nut is fixed to the both ends of the guide shaft 51, respectively.

以上において、図示左端部のストッパー39側の鉄筋保持部21を先行既設鉄筋12Aに固定した後、前述した実施形態と同様に、他の鉄筋保持部21に保持された軸方向鉄筋12の間隔を伸張調整する。その調整は、ナットによる係合部材32を図示しないラチェットで回転操作することにより行う。なお、軸方向鉄筋12の間隔調整を作業床で行ってから、前述した天井レール4の一対のホイスト5から繰り出されるケーブル6により吊り上げても良い。   In the above, after fixing the reinforcing bar holding part 21 on the stopper 39 side at the left end of the figure to the preceding existing reinforcing bar 12A, the interval between the axial reinforcing bars 12 held by the other reinforcing bar holding parts 21 is set as in the above-described embodiment. Adjust the stretch. The adjustment is performed by rotating the engaging member 32 using a nut with a ratchet (not shown). In addition, after adjusting the space | interval of the axial direction reinforcing bar 12 on a work floor, you may lift with the cable 6 extended | stretched from a pair of hoist 5 of the ceiling rail 4 mentioned above.

また、図17から図19は帯鉄筋13・14の吊り込み時及び鉄筋設置時(最大間隔調整時)を示したものである。
この場合、図示下端部のストッパー39側の鉄筋保持部21を先行既設鉄筋13A(または先行既設鉄筋14A)に固定した後、他の鉄筋保持部21に保持された帯鉄筋13(または帯鉄筋14)の間隔を伸張調整する。その調整は、ラチェットにより行う。なお、帯鉄筋13(14)の間隔調整を作業床で行ってから、吊り上げても良い。
FIGS. 17 to 19 show the time when the reinforcing bars 13 and 14 are suspended and when the reinforcing bars are installed (when the maximum interval is adjusted).
In this case, after fixing the reinforcing bar holding part 21 on the stopper 39 side at the lower end of the figure to the preceding existing reinforcing bar 13A (or the preceding existing reinforcing bar 14A), the band reinforcing bar 13 (or the band reinforcing bar 14 held by the other reinforcing bar holding part 21). ). The adjustment is performed by a ratchet. In addition, after performing the space | interval adjustment of the belt reinforcement 13 (14) on a work floor, you may lift.

以上のように、実施形態1の鉄筋組立用冶具20によれば、遊合部材33に対し一端部を連結したリンク34・35の中間部に、送りねじ31と平行配置した案内軸51を遊合したため、ストッパー39と反対側の端部の係合部材32が送りねじ31の回転に連動して移動することで、その間のリンク34・35の中間部の案内軸51に沿った伸縮動作を伴って遊合部材33の間隔が等間隔を保ちながら変更される。   As described above, according to the reinforcing bar assembling jig 20 of the first embodiment, the guide shaft 51 arranged in parallel with the feed screw 31 is idled at the intermediate part of the links 34 and 35 having one end connected to the loose coupling member 33. As a result, the engaging member 32 at the end opposite to the stopper 39 moves in conjunction with the rotation of the feed screw 31 so that the expansion and contraction operation along the guide shaft 51 at the intermediate portion of the links 34 and 35 therebetween is performed. Along with this, the interval between the loose members 33 is changed while maintaining an equal interval.

従って、高構造物の補強工法における鉄筋組立において、軸方向鉄筋12、帯鉄筋13・14を冶具20により設計鉄筋間隔に精度良くセットして、鉄筋組立が連続的にできるため、工期を大幅に短縮できるものとなる。   Therefore, in rebar assembly in the reinforcement method for high structures, the axial rebar 12 and the strip rebars 13 and 14 can be set to the designed rebar spacing with the jig 20 with high accuracy and the rebar assembly can be performed continuously. It can be shortened.

(実施形態2)
図20から図25は本発明を適用した鉄筋組立用冶具の実施形態2の構成として軸方向鉄筋の吊り込み時及び鉄筋設置時(最大間隔調整時)を示したもので、前述した実施形態と同様、6はケーブル、20は鉄筋組立用冶具、21は鉄筋保持部、31は送りねじ、32は係合部材、33は遊合部材、34・35はリンクであって、39はストッパーである。
(Embodiment 2)
20 to 25 show the configuration of the second embodiment of the reinforcing bar assembly jig to which the present invention is applied, when the axial reinforcing bar is suspended and when the reinforcing bar is installed (when the maximum interval is adjusted). Similarly, 6 is a cable, 20 is a reinforcing bar assembly jig, 21 is a reinforcing bar holding part, 31 is a feed screw, 32 is an engaging member, 33 is a loose member, 34 and 35 are links, and 39 is a stopper. .

すなわち、実施形態2の鉄筋組立用冶具20は、図示のように、送りねじ31の一端部にナットによるストッパー39を固定して、このストッパー39と係合部材32との間において送りねじ31上に遊合する複数個(図示例では5個)の遊合部材33を設けている。そして、係合部材32とストッパー39側の遊合部材33に対し短い方のリンク34の一端部を連結して、他の遊合部材33に対し長い方のリンク35の中間部を互いに交差させて連結している。従って、フルタイプのパンタグラフ式リンク機構となっている。   That is, the reinforcing bar assembly jig 20 according to the second embodiment fixes a stopper 39 with a nut to one end of the feed screw 31 as shown in the drawing, and the feed screw 31 is placed between the stopper 39 and the engaging member 32. A plurality of (five in the illustrated example) idler members 33 are provided. Then, one end of the shorter link 34 is connected to the engaging member 32 and the loose member 33 on the stopper 39 side, and the middle portion of the longer link 35 is crossed with respect to the other loose member 33. Are connected. Therefore, it is a full type pantograph type link mechanism.

以上において、前述した実施形態1と同様に、図20、図21で左端部のストッパー39側の鉄筋保持部21を先行既設鉄筋12Aに固定した後、他の鉄筋保持部21に保持された軸方向鉄筋12の間隔を伸張調整する。その調整は、ラチェットにより行う。なお、帯鉄筋13(14)の間隔調整を作業床で行ってから、吊り上げても良い。   In the above, similarly to the first embodiment described above, after the reinforcing bar holding part 21 on the left end stopper 39 side in FIGS. 20 and 21 is fixed to the preceding existing reinforcing bar 12A, the shaft held by the other reinforcing bar holding part 21 The distance between the directional reinforcing bars 12 is adjusted. The adjustment is performed by a ratchet. In addition, after performing the space | interval adjustment of the belt reinforcement 13 (14) on a work floor, you may lift.

また、図26から図31は帯鉄筋13・14の吊り込み時及び鉄筋設置時(最大間隔調整時)を示したものである。
この場合、図示下端部のストッパー39側の鉄筋保持部21を先行既設鉄筋13A(または先行既設鉄筋14A)に固定した後、他の鉄筋保持部21に保持された帯鉄筋13(または帯鉄筋14)の間隔を伸張調整する。その調整は、ラチェットにより行う。なお、帯鉄筋13(14)の間隔調整を作業床で行ってから、吊り上げても良い。
FIG. 26 to FIG. 31 show the time when the reinforcing bars 13 and 14 are suspended and when the reinforcing bars are installed (when the maximum interval is adjusted).
In this case, after fixing the reinforcing bar holding part 21 on the stopper 39 side at the lower end of the figure to the preceding existing reinforcing bar 13A (or the preceding existing reinforcing bar 14A), the band reinforcing bar 13 (or the band reinforcing bar 14 held by the other reinforcing bar holding part 21). ). The adjustment is performed by a ratchet. In addition, after performing the space | interval adjustment of the belt reinforcement 13 (14) on a work floor, you may lift.

以上のように、実施形態2の鉄筋組立用冶具20によれば、遊合部材33に対し長い方のリンク35を交差させてその中間部を結合してなるパンタグラフ式のリンク機構としたため、ストッパー39と反対側の端部の係合部材32が送りねじ31の回転に連動して移動することで、その間のパンタグラフ式のリンク34・35の伸縮動作を伴って遊合部材33の間隔が等間隔を保ちながら変更される。   As described above, according to the reinforcing bar assembling jig 20 of the second embodiment, since the longer link 35 intersects the loose coupling member 33 and the intermediate portion is joined, the stopper structure is used. Since the engaging member 32 at the end opposite to 39 moves in conjunction with the rotation of the feed screw 31, the gap between the loose members 33 is equalized with the expansion and contraction of the pantograph-type links 34 and 35 therebetween. It is changed while keeping the interval.

従って、前述した実施形態1と同様、高構造物の補強工法における鉄筋組立において、軸方向鉄筋12、帯鉄筋13・14を冶具20により設計鉄筋間隔に精度良くセットして、鉄筋組立が連続的にできるため、工期を大幅に短縮できるものとなる。   Therefore, as in the first embodiment, in the rebar assembly in the reinforcement method for a high structure, the axial rebar 12 and the strip rebars 13 and 14 are accurately set to the designed rebar interval by the jig 20 so that the rebar assembly is continuous. Therefore, the construction period can be greatly shortened.

(実施形態3)
図32から図34は本発明を適用した鉄筋組立用冶具20の実施形態3の構成として軸方向鉄筋の吊り込み時及び鉄筋設置時(最大間隔調整時)を示したもので、前述した実施形態1と同様、6はケーブル、20は鉄筋組立用冶具、21は鉄筋保持部、31は送りねじ、32は係合部材、33は遊合部材、34・35はリンク、39はストッパー、51は案内軸、52は第2の遊合部材、53は第2のストッパーである。
(Embodiment 3)
FIGS. 32 to 34 show the configuration of the third embodiment of the reinforcing bar assembly jig 20 to which the present invention is applied when the axial reinforcing bar is suspended and when the reinforcing bar is installed (when the maximum interval is adjusted). Similar to 1, 6 is a cable, 20 is a reinforcing bar assembly jig, 21 is a reinforcing bar holding part, 31 is a feed screw, 32 is an engaging member, 33 is a loose member, 34 and 35 are links, 39 is a stopper, 51 is A guide shaft, 52 is a second idler member, and 53 is a second stopper.

すなわち、実施形態3の鉄筋組立用冶具20は、図示のように、長さの短い送りねじ31の一端部にナットによるストッパー39を固定して、このストッパー39と係合部材32との間において送りねじ31上に遊合する1個の遊合部材33を設けている。この遊合部材33と係合部材32とに一組のリンク34・35の一端部を連結する。さらに、係合部材32に対して遊合部材33と反対側にリンク34・35を延長して設けている。
以上の係合部材32及び遊合部材33の位置に対応するとともに、その延長線上の位置に対応して、リンク34・35の回動連結部の一側面に鉄筋保持部21の保持金具22が取り付けられている。
That is, in the reinforcing bar assembly jig 20 of the third embodiment, as shown in the drawing, a stopper 39 by a nut is fixed to one end portion of a feed screw 31 having a short length, and between the stopper 39 and the engaging member 32. One loose member 33 that engages on the feed screw 31 is provided. One end of a pair of links 34 and 35 is connected to the loose member 33 and the engaging member 32. Further, links 34 and 35 are provided on the opposite side of the engaging member 33 with respect to the engaging member 32.
Corresponding to the positions of the engaging member 32 and the loose member 33 described above, the holding metal fitting 22 of the reinforcing bar holding part 21 is provided on one side surface of the rotation connecting part of the links 34 and 35 corresponding to the position on the extension line. It is attached.

そして、送りねじ31と平行に配置した案内軸51をリンク34・35の中間部に遊合する。具体的には、ストッパー39側の対をなす一組のリンク34・35の一端部の間に、送りねじ31上の係合部材32及び遊合部材33をそれぞれ回動自在に組み付けて、全ての対をなすリンク34・35の中間部の間に、案内軸51上に遊合する鞘材による第2の遊合部材52をそれぞれ回動自在に組み付けている。また、案内軸51の両端部にナットによる第2のストッパー53をそれぞれ固定する。ここで、図示例において、案内軸51は、送りねじ31の5倍以上の長さを有している。   Then, the guide shaft 51 disposed in parallel with the feed screw 31 is loosely engaged with the intermediate portion of the links 34 and 35. Specifically, the engaging member 32 and the idler member 33 on the feed screw 31 are rotatably assembled between one end portions of the pair of links 34 and 35 forming a pair on the stopper 39 side. Between the intermediate portions of the links 34 and 35 forming the pair, second loose members 52 made of a sheath material loosely mated on the guide shaft 51 are respectively assembled rotatably. Moreover, the 2nd stopper 53 by a nut is fixed to the both ends of the guide shaft 51, respectively. Here, in the illustrated example, the guide shaft 51 has a length five times or more that of the feed screw 31.

以上において、図示左端部の第2のストッパー53側の鉄筋保持部21を先行既設鉄筋12Aに固定した後、前述した実施形態1と同様に、他の鉄筋保持部21に保持された軸方向鉄筋12の間隔を伸張調整する。その調整は、ナットによる係合部材32を図示しないラチェットで回転操作することにより行う。   In the above, after the reinforcing bar holding part 21 on the second stopper 53 side at the left end in the figure is fixed to the preceding existing reinforcing bar 12A, the axial reinforcing bar held by the other reinforcing bar holding part 21 is the same as in the first embodiment. 12 is extended and adjusted. The adjustment is performed by rotating the engaging member 32 using a nut with a ratchet (not shown).

すなわち、係合部材32が送りねじ31上を移動することで、遊合部材33との間のリンク34・35が伸縮動作すると同時に、他方に延長して設けたリンク34・35の伸縮動作を伴って、係合部材32及び遊合部材33の位置に対応し、さらに、その延長線上の位置に対応したリンク34・35の回動連結部の鉄筋保持部21の間隔が等間隔を保ちながら変更される。
なお、軸方向鉄筋12の間隔調整を作業床で行ってから、前述した天井レール4の一対のホイスト5から繰り出されるケーブル6により吊り上げても良い。
That is, when the engaging member 32 moves on the feed screw 31, the links 34 and 35 to and from the idler member 33 expand and contract, and at the same time, the links 34 and 35 extended to the other extend and retract. Accordingly, the intervals of the reinforcing bar holding portions 21 of the rotation connecting portions of the links 34 and 35 corresponding to the positions of the engaging member 32 and the loosely engaging member 33 and corresponding to the positions on the extension line are kept constant. Be changed.
In addition, after adjusting the space | interval of the axial direction reinforcing bar 12 on a work floor, you may lift with the cable 6 extended | stretched from a pair of hoist 5 of the ceiling rail 4 mentioned above.

また、図35から図37は帯鉄筋13・14の吊り込み時及び鉄筋設置時(最大間隔調整時)を示したものである。
この場合、図示下端部のストッパー39側の鉄筋保持部21を先行既設鉄筋13A(または先行既設鉄筋14A)に固定した後、他の鉄筋保持部21に保持された帯鉄筋13(または帯鉄筋14)の間隔を伸張調整する。その調整は、ラチェットにより行う。なお、帯鉄筋13(14)の間隔調整を作業床で行ってから、吊り上げても良い。
FIGS. 35 to 37 show the time when the rebars 13 and 14 are suspended and when the reinforcing bars are installed (when the maximum interval is adjusted).
In this case, after fixing the reinforcing bar holding part 21 on the stopper 39 side at the lower end of the figure to the preceding existing reinforcing bar 13A (or the preceding existing reinforcing bar 14A), the band reinforcing bar 13 (or the band reinforcing bar 14 held by the other reinforcing bar holding part 21). ). The adjustment is performed by a ratchet. In addition, after performing the space | interval adjustment of the belt reinforcement 13 (14) on a work floor, you may lift.

以上のように、実施形態3の鉄筋組立用冶具20によれば、遊合部材33と係合部材32とに一端部を連結し、かつ、係合部材32に対して遊合部材33と反対側に延長して設けたリンク34・35の中間部に、送りねじ31と平行配置した案内軸51を遊合したため、係合部材32が送りねじ31の回転に連動して移動することで、リンク34・35の中間部の案内軸51に沿った伸縮動作を伴ってその回動連結部に設けた鉄筋保持部21の間隔が等間隔を保ちながら変更される。   As described above, according to the reinforcing bar assembling jig 20 of the third embodiment, one end is connected to the loose member 33 and the engagement member 32, and opposite to the loose member 33 with respect to the engagement member 32. Since the guide shaft 51 arranged in parallel with the feed screw 31 is engaged with the intermediate portion of the links 34 and 35 provided extending to the side, the engaging member 32 moves in conjunction with the rotation of the feed screw 31. The space | interval of the reinforcement holding | maintenance part 21 provided in the rotation connection part is changed with the expansion-contraction operation | movement along the guide shaft 51 of the intermediate part of link 34 * 35, maintaining an equal interval.

従って、高構造物の補強工法における鉄筋組立において、軸方向鉄筋12、帯鉄筋13・14を冶具20により設計鉄筋間隔に精度良くセットして、鉄筋組立が連続的にできるため、工期を大幅に短縮できるものとなる。   Therefore, in rebar assembly in the reinforcement method for high structures, the axial rebar 12 and the strip rebars 13 and 14 can be set to the designed rebar spacing with the jig 20 with high accuracy and the rebar assembly can be performed continuously. It can be shortened.

次に、図38は実施形態3の短尺の送りねじ31による送り作用を示したもので、図示のように、送りねじ31のねじ溝ピッチ5mmとして、リンク34・35の全体が10回転で250mm縮まるとした場合、リンク34・35の一端部に備えた鉄筋保持部51による鉄筋間隔は10回転で50mm縮まることになる。   Next, FIG. 38 shows the feeding action by the short feed screw 31 of the third embodiment. As shown in the figure, the thread groove pitch of the feed screw 31 is 5 mm, and the entire links 34 and 35 are 250 mm in 10 rotations. When it shrinks, the reinforcing bar interval by the reinforcing bar holding part 51 provided at one end of the links 34 and 35 is reduced by 50 mm in 10 rotations.

これに対し、図39は実施形態2の長尺の送りねじによる送り作用を示したもので、図示のように、送りねじ31のねじ溝ピッチ5mmとして、リンク34・35の全体が50回転で250mm縮まるとした場合、リンク34・35の中間部に備えた鉄筋保持部51による鉄筋間隔は50回転で50mm縮まることになる。
また、実施形態1の長尺の送りねじによる送り作用についても同様である。
On the other hand, FIG. 39 shows the feeding action by the long feed screw of the second embodiment. As shown in the drawing, the thread groove pitch of the feed screw 31 is 5 mm, and the entire links 34 and 35 are rotated 50 times. If it is reduced by 250 mm, the reinforcing bar interval by the reinforcing bar holding part 51 provided in the intermediate part of the links 34 and 35 is reduced by 50 mm at 50 rotations.
The same applies to the feeding action of the long feed screw of the first embodiment.

なお、以上の実施形態の他、各構成部品の形状や個数等も任意であり、その他、具体的な細部構造等についても適宜に変更可能であることは勿論である。   In addition to the above-described embodiments, the shape and number of each component are arbitrary, and it is needless to say that specific detailed structures can be appropriately changed.

高構造物の耐震補強工法の一例の構成を示すもので、橋脚の耐震補強におけるジベル筋施工を示した概略側面図(a)及び同正面図(b)である。The structure of an example of the seismic reinforcement method of a high structure is shown, The schematic side view (a) and the same front view (b) which showed the construction of the gibber reinforcement in the seismic reinforcement of a bridge pier are shown. 図1の施工に続く軸方向鉄筋・帯鉄筋施工を示した概略側面図(a)及び同正面図(b)である。It is the schematic side view (a) and the same front view (b) which showed the axial direction reinforcement and the band reinforcement construction following the construction of FIG. 図2の施工に続く型枠・コンクリート打設を示した概略側面図(a)及び同正面図(b)である。It is the schematic side view (a) and the same front view (b) which showed the formwork and concrete placement following the construction of FIG. 図3の施工に続く型枠脱型を示した概略側面図(a)及び同正面図(b)である。It is the schematic side view (a) and the same front view (b) which showed the mold form demolding following construction of FIG. 図2の軸方向鉄筋・帯鉄筋施工における軸方向鉄筋組立方法を示した概略側面図(a)及び同正面図(b)である。It is the schematic side view (a) and the same front view (b) which showed the axial direction reinforcing bar assembly method in the axial direction reinforcing bar and belt reinforcing bar construction of FIG. 図5の冶具部分の拡大斜視図である。It is an expansion perspective view of the jig part of FIG. 図6の冶具による鉄筋保持を示した斜視図(a)で、その冶具の収縮調整を示した図(b)、その冶具による先行既設鉄筋への固定と鉄筋間隔調整を矢印で示した図(c)、先行既設鉄筋への軸方向鉄筋の圧接を示した図(d)である。FIG. 6A is a perspective view showing the reinforcement holding by the jig of FIG. 6A, and FIG. 6B is a diagram showing the shrinkage adjustment of the jig; FIG. c) It is the figure (d) which showed the press contact of the axial direction reinforcement to the preceding existing reinforcement. 図2の軸方向鉄筋・帯鉄筋施工における帯鉄筋組立方法を示した概略側面図(a)及び同正面図(b)である。It is the schematic side view (a) and the same front view (b) which showed the band reinforcement assembly method in the axial direction reinforcing bar and band reinforcement construction of FIG. 帯鉄筋の配置を示した平面図(a)で、平面視コ字状の帯鉄筋の冶具による保持箇所を示した図(b)、直線状の帯鉄筋の冶具による保持箇所を示した図(c)である。A plan view (a) showing the arrangement of the band reinforcing bars, a diagram (b) showing the U-shaped band reinforcing bar jig holding position in a plan view, and a diagram showing the holding position of the linear band reinforcing bar jig ( c). 図8(b)の冶具部分の拡大斜視図である。It is an expansion perspective view of the jig part of FIG.8 (b). 図10の保持方式と異なる保持方式を示した図(a)及び(b)である。It is the figure (a) and (b) which showed the holding system different from the holding system of FIG. 昇降足場上の鉄筋取込みガイドを示した斜視図である。It is the perspective view which showed the reinforcing bar taking-in guide on a raising / lowering scaffold. 図12の冶具による先行既設鉄筋への固定を示した斜視図である。It is the perspective view which showed fixation to the prior | preceding existing reinforcement by the jig of FIG. 本発明を適用した鉄筋組立用冶具の実施形態1の構成を示すもので、軸方向鉄筋の吊り込み時を示した正面図(a)と、その鉄筋設置時(最大間隔調整時)を示した正面図(b)である。1 shows a configuration of a first embodiment of a reinforcing bar assembling tool to which the present invention is applied, and shows a front view (a) showing when an axial reinforcing bar is suspended and a time when the reinforcing bar is installed (when a maximum interval is adjusted). It is a front view (b). 図14の鉄筋組立用冶具部の拡大図(a)(b)である。It is an enlarged view (a) (b) of the jig part for a reinforcing bar assembly of FIG. 図15の鉄筋組立用冶具部の縦断側面図(a)及び平面図(b)である。It is the vertical side view (a) and top view (b) of the jig part for reinforcing bar assembly of FIG. 帯鉄筋の吊り込み時を示した正面図(a)と、その鉄筋設置時(最大間隔調整時)を示した正面図(b)である。It is the front view (a) which showed the time of suspension of a belt reinforcement, and the front view (b) which showed the time of the reinforcement installation (at the time of maximum space adjustment). 図17の鉄筋組立用冶具部の拡大図(a)(b)である。It is an enlarged view (a) (b) of the jig part for reinforcing bar assembly of FIG. 図18の鉄筋組立用冶具部の縦断側面図(a)及び平面図(b)である。It is the vertical side view (a) and top view (b) of the jig part for a reinforcing bar assembly of FIG. 本発明を適用した鉄筋組立用冶具の実施形態2の構成を示すもので、軸方向鉄筋の吊り込み時を示した正面図(a)と、その鉄筋設置時(最大間隔調整時)を示した正面図(b)である。The structure of Embodiment 2 of the reinforcing bar assembling tool to which the present invention is applied is shown, and a front view (a) showing when the axial reinforcing bar is suspended and a time when the reinforcing bar is installed (when the maximum interval is adjusted) are shown. It is a front view (b). 図20の鉄筋組立用冶具部の拡大図(a)(b)である。It is an enlarged view (a) (b) of the jig part for reinforcing bar assembly of FIG. 図21の鉄筋組立用冶具部の縦断側面図(a)及び平面図(b)である。It is the vertical side view (a) and top view (b) of the jig part for a reinforcing bar assembly of FIG. 図20(b)の斜視図である。It is a perspective view of FIG.20 (b). 図21(b)の表裏方向から見た斜視図(a)(b)である。It is the perspective view (a) (b) seen from the front and back direction of FIG.21 (b). 図24の端部拡大図(a)(b)である。It is an edge part enlarged view (a) (b) of FIG. 帯鉄筋の吊り込み時を示した正面図(a)と、その鉄筋設置時(最大間隔調整時)を示した正面図(b)である。It is the front view (a) which showed the time of suspension of a belt reinforcement, and the front view (b) which showed the time of the reinforcement installation (at the time of maximum space adjustment). 図26の鉄筋組立用冶具部の拡大図(a)(b)である。It is an enlarged view (a) (b) of the jig part for a reinforcing bar assembly of FIG. 図27の鉄筋組立用冶具部の縦断側面図(a)及び平面図(b)である。It is the vertical side view (a) and top view (b) of the jig part for reinforcing bar assembly of FIG. 図26(b)の斜視図である。FIG. 27 is a perspective view of FIG. 図27(b)の表裏方向から見た斜視図(a)(b)である。It is the perspective view (a) (b) seen from the front and back direction of FIG.27 (b). 図30の端部拡大図(a)(b)である。It is an edge part enlarged view (a) (b) of FIG. 本発明を適用した鉄筋組立用冶具の実施形態3の構成を示すもので、軸方向鉄筋の吊り込み時を示した正面図(a)と、その鉄筋設置時(最大間隔調整時)を示した正面図(b)である。The structure of Embodiment 3 of the reinforcing bar assembling tool to which the present invention is applied is shown, and a front view (a) showing when the axial reinforcing bar is suspended and the reinforcing bar installation (when the maximum interval is adjusted) are shown. It is a front view (b). 図32の鉄筋組立用冶具部の拡大図(a)(b)である。It is an enlarged view (a) (b) of the jig part for reinforcing bar assembly of FIG. 図33の鉄筋組立用冶具部の縦断側面図(a)及び平面図(b)である。It is the vertical side view (a) and top view (b) of the jig part for a reinforcing bar assembly of FIG. 帯鉄筋の吊り込み時を示した正面図(a)と、その鉄筋設置時(最大間隔調整時)を示した正面図(b)である。It is the front view (a) which showed the time of suspension of a belt reinforcement, and the front view (b) which showed the time of the reinforcement installation (at the time of maximum space adjustment). 図35の鉄筋組立用冶具部の拡大図(a)(b)である。It is an enlarged view (a) (b) of the jig part for reinforcing bar assembly of FIG. 図36の鉄筋組立用冶具部の縦断側面図(a)及び平面図(b)である。FIG. 37 is a longitudinal sectional side view (a) and a plan view (b) of the reinforcing bar assembling jig part of FIG. 36. 実施形態3の短尺の送りねじによる送り作用を示した線図である。It is the diagram which showed the feed effect | action by the short feed screw of Embodiment 3. FIG. 実施形態2の長尺の送りねじによる送り作用を示した線図である。It is the diagram which showed the feed effect | action by the long feed screw of Embodiment 2. FIG.

符号の説明Explanation of symbols

1 コンクリート橋脚(高構造物)
2 マスト(支柱)
3 ワークプラットホーム(昇降足場)
4 天井レール
5 ホイスト
6 ケーブル
11 ジベル筋
12 軸方向鉄筋
12A 先行既設鉄筋
12B 先行既設鉄筋
13 直線状の帯鉄筋
13A 先行既設鉄筋
14 平面視コ字状の帯鉄筋
14A 先行既設鉄筋
15 型枠
16 打設コンクリート
20 鉄筋組立用冶具
21 鉄筋保持部
22 保持金具
23 ボルト
24 鉄筋保持部
25 保持金具
26 保持金具
27 鉄筋保持部
28 保持金具
29 ストッパピン
30 間隔調整部
31 送りねじ
32 係合部材
33 遊合部材
34 リンク
35 リンク
36 固定プレート
37 固定部材
39 ストッパー
40 鉄筋取込みガイド
41 傾斜ガイド板
42 曲線ガイド板
51 案内軸
52 第2の遊合部材
53 第2のストッパー
1 Concrete pier (high structure)
2 Mast
3 Work platform (elevating scaffold)
4 Ceiling rail 5 Hoist 6 Cable 11 Givel bar 12 Axial reinforcing bar 12A Pre-existing reinforcing bar 12B Pre-existing reinforcing bar 13 Linear strip reinforcing bar 13A Pre-existing reinforcing bar 14 U-shaped strip reinforcing bar 14A Pre-existing reinforcing bar 15 Formwork 16 Concrete 20 Reinforcing bar assembly jig 21 Reinforcing bar holding part 22 Holding metal part 23 Bolt 24 Reinforcing bar holding part 25 Holding metal part 26 Retaining metal part 27 Reinforcing bar holding part 28 Holding metal part 29 Stopper pin 30 Spacing adjustment part 31 Feed screw 32 Engaging member 33 Free play Member 34 Link 35 Link 36 Fixing plate 37 Fixing member 39 Stopper 40 Reinforcing bar take-in guide 41 Inclined guide plate 42 Curved guide plate 51 Guide shaft 52 Second play member 53 Second stopper

Claims (7)

送りねじと、
この送りねじの一端部に固定するストッパーと、
前記送りねじ上にねじ係合する係合部材と、
前記ストッパーと係合部材との間において前記送りねじ上に遊合する複数個の遊合部材と、
前記係合部材と遊合部材にそれぞれ設けられ、鉄筋を1本ずつ保持する鉄筋保持部と、
前記係合部材に対して前記遊合部材を順に連結するリンク機構と、を備え、
前記遊合部材に対し前記リンク機構のリンクの一端部を連結して、
前記送りねじと平行に配置され、前記リンクの中間部に遊合する案内軸を備えることを特徴とする鉄筋組立用冶具。
A lead screw;
A stopper fixed to one end of the feed screw;
An engagement member that engages with the screw on the feed screw;
A plurality of idler members loosely engaged on the feed screw between the stopper and the engaging member;
Reinforcing bar holding portions that are respectively provided on the engaging member and the loose member and hold the reinforcing bars one by one;
A link mechanism for sequentially connecting the loose members to the engaging members;
Connecting one end of the link of the link mechanism to the loose member;
A rebar assembly jig comprising a guide shaft arranged in parallel with the feed screw and loosely engaged with an intermediate portion of the link.
送りねじと、
この送りねじの一端部に固定するストッパーと、
前記送りねじ上にねじ係合する係合部材と、
前記ストッパーと係合部材との間において前記送りねじ上に遊合する複数個の遊合部材と、
前記係合部材と遊合部材にそれぞれ設けられ、鉄筋を1本ずつ保持する鉄筋保持部と、
前記係合部材に対して前記遊合部材を順に連結するリンク機構と、を備え、
前記遊合部材に対し前記リンク機構のリンクの中間部を結合してなることを特徴とする鉄筋組立用冶具。
A lead screw;
A stopper fixed to one end of the feed screw;
An engagement member that engages with the screw on the feed screw;
A plurality of idler members loosely engaged on the feed screw between the stopper and the engaging member;
Reinforcing bar holding portions that are respectively provided on the engaging member and the loose member and hold the reinforcing bars one by one;
A link mechanism for sequentially connecting the loose members to the engaging members;
A reinforcing bar assembling jig, wherein an intermediate portion of a link of the link mechanism is coupled to the loose member.
前記遊合部材に対し前記リンクが交差して結合されていることを特徴とする請求項2に記載の鉄筋組立用冶具。   The reinforcing bar assembling jig according to claim 2, wherein the link is crossed and coupled to the loose member. 送りねじと、
この送りねじの一端部に固定するストッパーと、
前記送りねじ上にねじ係合する係合部材と、
前記ストッパーと係合部材との間において前記送りねじ上に遊合する遊合部材と、
前記係合部材に対して前記遊合部材を連結し、かつ、前記遊合部材と反対側に延長して設けられるリンク機構と、
前記係合部材と遊合部材と、前記リンク機構の前記遊合部材と反対側に延長して設けられる複数個のリンクにそれぞれ設けられ、鉄筋を1本ずつ保持する鉄筋保持部と、
前記送りねじと平行に配置され、前記リンク機構のリンクの中間部に遊合する案内軸と、を備え、
前記遊合部材に対し前記リンク機構のリンクの一端部を連結して、
前記リンク機構の前記遊合部材と反対側に延長して設けられる複数個のリンクの一端部に前記鉄筋保持部を備えることを特徴とする鉄筋組立用冶具。
A lead screw;
A stopper fixed to one end of the feed screw;
An engagement member that engages with the screw on the feed screw;
An idler member loosely engaged on the feed screw between the stopper and the engaging member;
A link mechanism that connects the engaging member to the engaging member and extends to the opposite side of the engaging member;
Reinforcing bar holding portions that are respectively provided on a plurality of links provided to extend on the side opposite to the loosening member of the link mechanism, and that hold the reinforcing bars one by one;
A guide shaft that is arranged in parallel with the feed screw and loosely engages an intermediate portion of the link of the link mechanism,
Connecting one end of the link of the link mechanism to the loose member;
A reinforcing bar assembling jig comprising the reinforcing bar holding portion at one end of a plurality of links provided to extend to the opposite side of the loose coupling member of the link mechanism.
前記案内軸は、前記送りねじの2倍以上長尺であることを特徴とする請求項4に記載の鉄筋組立用冶具。   The rebar assembly jig according to claim 4, wherein the guide shaft is at least twice as long as the feed screw. 前記リンクの中間部に、前記案内軸上に遊合する第2の遊合部材を備えることを特徴とする請求項1または4に記載の鉄筋組立用冶具。   The reinforcing bar assembling tool according to claim 1 or 4, further comprising a second loose member that loosely engages with the guide shaft at an intermediate portion of the link. 前記案内軸の先端部に、前記リンクの移動を規制する第2のストッパーが設けられていることを特徴とする請求項1または4に記載の鉄筋組立用冶具。   The reinforcing bar assembling jig according to claim 1 or 4, wherein a second stopper for restricting movement of the link is provided at a distal end portion of the guide shaft.
JP2008178636A 2008-07-09 2008-07-09 Rebar assembly jig Active JP5254686B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008178636A JP5254686B2 (en) 2008-07-09 2008-07-09 Rebar assembly jig

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008178636A JP5254686B2 (en) 2008-07-09 2008-07-09 Rebar assembly jig

Publications (2)

Publication Number Publication Date
JP2010018974A JP2010018974A (en) 2010-01-28
JP5254686B2 true JP5254686B2 (en) 2013-08-07

Family

ID=41704142

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008178636A Active JP5254686B2 (en) 2008-07-09 2008-07-09 Rebar assembly jig

Country Status (1)

Country Link
JP (1) JP5254686B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610289A (en) * 2018-12-21 2019-04-12 中冶天工集团有限公司 A kind of production method of hyperboloid steel box-girder moulding bed
CN110205896A (en) * 2019-06-03 2019-09-06 中国建筑土木建设有限公司 Concrete pavement connecting bar installation device and method for road construction by applying same

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0340983Y2 (en) * 1985-09-10 1991-08-28
JP3676489B2 (en) * 1996-04-16 2005-07-27 日本ビニロン株式会社 Bar arrangement indexing device
JP4521024B2 (en) * 2007-11-14 2010-08-11 東日本旅客鉄道株式会社 Reinforcing bar assembly method and reinforcing bar assembly jig for reinforcing structure of high structure

Also Published As

Publication number Publication date
JP2010018974A (en) 2010-01-28

Similar Documents

Publication Publication Date Title
JP4521024B2 (en) Reinforcing bar assembly method and reinforcing bar assembly jig for reinforcing structure of high structure
JP4377506B2 (en) Bridge erection device and bridge erection method
JP4777319B2 (en) Bridge erection method
JP5937898B2 (en) Construction method of box girder bridge
JP2009287312A (en) Bridge construction apparatus
SG183614A1 (en) Reinforcing structure and reinforcing method for reinforcement cage
CN104831632B (en) A kind of bridge cable tower entablature and sill construction method
JP2013155600A (en) Bridge pier of composite steel pipe-concrete structure
CN109629449B (en) Mounting and positioning support and alignment method for steel-concrete combined section of arch foot of steel box arch bridge
JP5254686B2 (en) Rebar assembly jig
JP2010133084A (en) Method of constructing hollow high structure
JP5421143B2 (en) Overhead crane installation equipment
JP3988938B2 (en) Raising the tower
JP5693869B2 (en) Bridge girder construction method
CN212224665U (en) Prefabricated post guiding device and prestressing force frame construction&#39;s guide installation device of taking one&#39;s place
CN110878549B (en) Dam gallery construction method
KR100293687B1 (en) Concrete delivery device and its installation method
CN108797350B (en) Tower column inner and outer stiff skeleton device and construction method thereof
JP4421421B2 (en) Columnar structure construction method and suspension jig
JP2009209625A (en) Cable conveying apparatus
JP4058104B1 (en) How to lift heavy objects
CN113789725B (en) Suspension bridge construction method and lifting device
JP7158304B2 (en) Transport system and installation method
JP4421420B2 (en) Columnar structure construction method and suspension jig
CN217438905U (en) Arch bridge oblique pile reinforcement cage segment structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20110523

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120928

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20130416

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20130418

R150 Certificate of patent or registration of utility model

Ref document number: 5254686

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20160426

Year of fee payment: 3

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250