CN109610289A - A kind of production method of hyperboloid steel box-girder moulding bed - Google Patents
A kind of production method of hyperboloid steel box-girder moulding bed Download PDFInfo
- Publication number
- CN109610289A CN109610289A CN201811570353.XA CN201811570353A CN109610289A CN 109610289 A CN109610289 A CN 109610289A CN 201811570353 A CN201811570353 A CN 201811570353A CN 109610289 A CN109610289 A CN 109610289A
- Authority
- CN
- China
- Prior art keywords
- moulding bed
- column
- girder
- outer arc
- partition
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2/00—Bridges characterised by the cross-section of their bearing spanning structure
- E01D2/04—Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
A kind of production method of hyperboloid steel box-girder moulding bed includes the following steps: 1. to make moulding bed outer arc reference line on assembly platform, makes moulding bed outer arc curve in platform at a distance from reference line according to outer arc, partition crosspoint in moulding bed figure.Similarly, camber line in moulding bed, road axis and inner arc reference line, spacer lines are made in platform according to moulding bed figure size;2. determining the position of inside and outside arc moulding bed column, moulding bed column should be centered on partition and road axis intersection point at road axis;3. column bottom plate and platform welding are marked column center;4. calculating the height of moulding bed column;5. making moulding bed girder steel;6. successively installing column and moulding bed beam on bottom plate;7. welding rib of slab on moulding bed beam;8. setting up bridging and diagonal brace between column transverse and longitudinal.The present invention fits like a glove with Deck coordinate, guarantees that Deck reaches design requirement, to guarantee steel box-girder production precision and construction quality, improves steel box girder construction speed.
Description
Technical field
The invention belongs to municipal road construction field, in particular to a kind of production method of hyperboloid steel box-girder moulding bed.
Background technique
Currently, due to being limited to the influence of City Terrain in urban road construction, make leap between road, bridge at
For certainty.Steel structure bridge has the characteristics that lightweight, high-strength, speed of application is fast and the feature of environmental protection is strong, and municipal administration in recent years is newly-built
It is widely used in reconstruction project.Wherein, hyperboloid steel box-girder is suitable for being limited (such as hillside) or elevated ramp class by landform
How the science of bridge building of steel construction guarantees that Deck becomes hyperboloid steel since bridge floor is arc and vertically and horizontally has the gradient
The key of box girder construction.
Summary of the invention
The object of the invention is that providing a kind of production method of hyperboloid steel box-girder moulding bed, which uses
Dress method controls the exactitude position at each position of hyperboloid steel box-girder with the construction moulding bed technology that combines, to can ensure that engineering matter
Amount, reaches one-pass molding.
As above design, the technical scheme is that a kind of production method of hyperboloid steel box-girder moulding bed, feature exist
In: include the following steps:
1. making a reference line outside outer arc and the easement curve of road axis plane projection in steel box-girder top plate, by benchmark
Size between line and outer arc curve and partition intersection point marks, and according to ruler lateral between the design drawing outer arc provided and partition intersection point
It is very little, it determines the plane coordinates anchor point X, Y coordinates of moulding bed outer arc, similarly, determines the plane coordinates anchor point of moulding bed inner arc;
2. being longitudinal datum mark with outer arc end point and partition intersection point, outer arc and partition phase are made according to bridge head fall
The vertical dimension of each point is handed over, to determine the Z-direction coordinate of moulding bed outer arc;It is calculated with outer arc datum mark according to bridge floor cross fall
Inner arc end point, end road axis, end web center line and diaphragm plate crosspoint vertical dimension, and press head fall
The vertical dimension that inner arc, road axis are intersected to each point with partition calculates;Similarly, web line is calculated to intersect with partition respectively
The vertical dimension of point, road axis, web line vertical dimension should subtract calculated bridge floor according to actual needs and laterally encircle in advance
Angle value;
3. spacer lines are made a little, to put using this as column along inside and outside arc and spacer lines crosspoint to the extension of moulding bed outside direction
Bottom plate side center, and base plate center line should coincide with spacer lines, determines the position of inside and outside arc moulding bed column with this, in road
Moulding bed column should be centered on partition and road axis intersection point at heart line;
4. by column bottom plate and platform welding, and getting cross hairs on bottom plate, column center is marked;
5. using the intersection point of moulding bed outer arc and partition as datum mark, the inner arc 1., 2. provided according to step, outer arc, road
Center line and spacer lines crosspoint longitudinal size subtract moulding bed deck-molding and column base plate thickness gauge calculates the height of moulding bed column;
6. according to step 1., 2. in spacer lines length blanking make moulding bed girder steel;
7. by column, according to bottom plate position line and height, successively installation group is welded, column install after along partition direction by moulding bed
Beam group is soldered on column;
8. leading to along rib of slab is respectively welded in camber line at camber line, road axis and box girder web inside and outside top plate on moulding bed beam
Transit survey adjustment rib of slab absolute altitude is crossed, keeps moulding bed vertical and horizontal gradient and steel box-girder top plate vertical and horizontal gradient completely the same.
9. setting up bridging and diagonal brace between column transverse and longitudinal.
Outer rim point of contact 1m of the reference line of above-mentioned steps 1. apart from steel box-girder top plate outer arc.
Above-mentioned bridging and diagonal brace are made using not small with the bis- back equal leg angles of 40*4.
Above-mentioned column bottom plate is made of steel plate, thickness >=10mm.
Above-mentioned moulding bed column uses H profile steel.
The each point coordinate points that outer arc, center line, web line intersect with diaphragm plate in the moulding bed that the present invention makes of upside-down method of hull-section construction
With after steel box-girder roof formed interior outer arc, road axis and web space of lines coordinate it is consistent, when construction, makes steel box-girder top plate
It is laid on moulding bed and guarantees to be bonded completely with moulding bed, to guarantee that steel box girder bridge face line style reaches design requirement, be finally reached
The purpose for controlling steel box girder bridge face line style, improves speed of application and construction quality.
Detailed description of the invention
Fig. 1 is the positioning schematic diagram of moulding bed plane;
Fig. 2 is the schematic diagram of moulding bed outer arc Z-direction coordinate;
Fig. 3 is the schematic diagram of road-center longitudinal size;
Fig. 4 is the schematic diagram of moulding bed inner arc longitudinal size;
Fig. 5 is the positioning schematic diagram of moulding bed column;
Fig. 6 is the A-A sectional view of Fig. 5.
In figure: 1- assembly platform;2- column bottom plate;3- moulding bed column;4- moulding bed beam;5- rib of slab;6- box girder web;In 7-
Arc plate;8- outer arc plate;9- bearing diagonal;10- road-center datum plate;11- partition and spacer lines.
Specific embodiment
For that can further appreciate that the contents of the present invention, feature and effect, make below by specific embodiment further detailed
State, following implementation be it is descriptive, be not restrictive, this does not limit the scope of protection of the present invention.
A kind of production method of hyperboloid steel box-girder moulding bed, specific implementation step are as follows:
Step 1: preparing an assembly platform, steel structure platform or concrete platform is can be used in platform, and the flatness of platform is not
Greater than 5mm, create conditions conducive to the accurate control of subsequent operation.
Step 2: the steel box-girder top plate plant tilting figure provided according to design drawing is it is found that in steel box-girder top plate in outer arc and road
Heart line plane projection is easement curve, therefore can make a reference line in projection plane extra curvature, and reference line is apart from outer arc outer rim
Point of contact 1m marks the size between reference line and outer arc curve and diaphragm plate intersection point, and the outer arc provided according to design drawing with every
Lateral dimension between plate intersection point determines the plane coordinates anchor point (X, Y coordinates) of moulding bed outer arc, similarly, determines the flat of moulding bed inner arc
Areal coordinate anchor point.(see attached drawing 1)
It is longitudinal datum mark (height 500mm) with outer arc end point and partition intersection point, goes out according to bridge head fall
Arc intersects the vertical dimension of each point with partition, to determine the Z-direction coordinate of moulding bed outer arc (see attached drawing 2).With outer arc datum mark, according to
Bridge floor cross fall calculates the perpendicular of inner arc end point, end road axis, end web center line and diaphragm plate crosspoint
To size, and press head fall, the vertical dimension that inner arc, road axis intersect to each point with partition calculate (see attached drawing 3,
4) vertical dimension that web line intersects each point with partition, can be similarly calculated, road axis, web line vertical dimension should subtract
Calculated bridge floor transverse direction camber value according to actual needs.
Make a little step 3: spacer lines are extended 50mm to moulding bed outside direction along inside and outside arc and spacer lines crosspoint, with this point
As column bottom plate side center, and base plate center line should be coincided with spacer lines (see attached drawing 5), determine that interior outer arc moulding bed is vertical with this
The position of column, moulding bed column should be centered on partition and road axis intersection point at road axis.
Step 4: by column bottom plate and platform welding, and cross hairs is got on bottom plate, column center is marked, to stand
Column installation positioning.Column bottom plate is made of steel plate, and thickness is not less than 10mm, and moulding bed column uses the H-type qualified by checking computations
Steel.
Step 5: using the intersection point of moulding bed outer arc and partition as datum mark, the inner arc provided according to step 2, outer arc, road
Lu Zhizheng line and spacer lines crosspoint longitudinal size subtract moulding bed deck-molding and column base plate thickness gauge calculates the height of moulding bed column.
Step 6: making moulding bed beam according to spacer lines length blanking in step 2, moulding bed beam uses the H qualified by checking computations
Fashioned iron or channel steel.
Step 7: according to bottom plate position line and height, successively installation group is welded by the column of blanking well cutting.Column installs
Afterwards, moulding bed beam group is soldered on column (see attached drawing 6) along partition direction.
8th step makes the rib of slab of 100*200 to adjust moulding bed beam column absolute altitude installation error, on moulding bed beam along top plate
Rib of slab (see attached drawing 6) is respectively welded in camber line at outer camber line, road axis and box girder web, adjusts rib of slab by transit survey
Absolute altitude (cutting the part for being higher by corresponding absolute altitude) keeps moulding bed vertical and horizontal gradient and steel box-girder top plate vertical and horizontal gradient completely the same.
Step 9: setting up bridging and diagonal brace between column transverse and longitudinal, increase the stability of moulding bed.Bridging and diagonal brace
It is made using not small with the bis- back equal leg angles of 40*4.
Step 10: installing hyperboloid steel box-girder on the moulding bed made.
The present invention guarantees that Deck reaches and sets by making the space curved surface moulding bed to fit like a glove with Deck coordinate
Meter requires, to guarantee steel box-girder production precision and construction quality, improves steel box girder construction speed.
The present invention is not limited to embodiments described above.Above the description of specific embodiment is intended to describe and say
Bright technical solution of the present invention, above-mentioned specific embodiment are only to illustrate, and are not restrictive.This hair is not being departed from
In the case of bright objective and scope of the claimed protection, those skilled in the art can also do under the inspiration of the present invention
The specific transformation of many forms out, within these are all belonged to the scope of protection of the present invention.
Claims (5)
1. a kind of production method of hyperboloid steel box-girder moulding bed, characterized by the following steps:
1. make a reference line outside outer arc and the easement curve of road axis plane projection in steel box-girder top plate, by reference line with
Size between outer arc curve and partition intersection point marks, and according to lateral dimension between the design drawing outer arc provided and partition intersection point, really
Determine the plane coordinates anchor point X, Y coordinates of moulding bed outer arc, similarly, determines the plane coordinates anchor point of moulding bed inner arc;
2. being longitudinal datum mark with outer arc end point and partition intersection point, outer arc is made according to bridge head fall and is intersected respectively with partition
The vertical dimension of point, to determine the Z-direction coordinate of moulding bed outer arc;Inner arc is calculated according to bridge floor cross fall with outer arc datum mark
End point, end road axis, end web center line and diaphragm plate crosspoint vertical dimension, and by head fall will in
The vertical dimension that arc, road axis intersect each point with partition calculates;Similarly, it calculates web line and intersects each point with partition
Vertical dimension, road axis, web line vertical dimension should subtract calculated bridge floor transverse direction camber value according to actual needs;
3. spacer lines are made a little, to put using this as column bottom plate along inside and outside arc and spacer lines crosspoint to the extension of moulding bed outside direction
Side center, and base plate center line should coincide with spacer lines, and the position of inside and outside arc moulding bed column, road axis are determined with this
Locating moulding bed column should be centered on partition and road axis intersection point;
4. by column bottom plate and platform welding, and getting cross hairs on bottom plate, column center is marked;
5. using the intersection point of moulding bed outer arc and partition as datum mark, the inner arc 1., 2. provided according to step, outer arc, road-center
Line and spacer lines crosspoint longitudinal size subtract moulding bed deck-molding and column base plate thickness gauge calculates the height of moulding bed column;
6. according to step 1., 2. in spacer lines length blanking make moulding bed girder steel;
7. by column, according to bottom plate position line and height, successively installation group is welded, column install after along partition direction by moulding bed beam group
It is soldered on column;
8. along rib of slab is respectively welded in camber line at camber line, road axis and box girder web inside and outside top plate on moulding bed beam, pass through through
Latitude instrument measurement adjustment rib of slab absolute altitude, keeps moulding bed vertical and horizontal gradient and steel box-girder top plate vertical and horizontal gradient completely the same.
9. setting up bridging and diagonal brace between column transverse and longitudinal.
2. a kind of production method of hyperboloid steel box-girder moulding bed according to claim 1, it is characterised in that: above-mentioned steps are 1.
Outer rim point of contact 1m of the reference line apart from steel box-girder top plate outer arc.
3. a kind of production method of hyperboloid steel box-girder moulding bed according to claim 1, it is characterised in that: above-mentioned bridging
It is made using not small with the bis- back equal leg angles of 40*4 with diagonal brace.
4. a kind of production method of hyperboloid steel box-girder moulding bed according to claim 1, it is characterised in that: above-mentioned column bottom
Plate is made of steel plate, thickness >=10mm.
5. a kind of production method of hyperboloid steel box-girder moulding bed according to claim 1, it is characterised in that: above-mentioned moulding bed is vertical
Column uses H profile steel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811570353.XA CN109610289A (en) | 2018-12-21 | 2018-12-21 | A kind of production method of hyperboloid steel box-girder moulding bed |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811570353.XA CN109610289A (en) | 2018-12-21 | 2018-12-21 | A kind of production method of hyperboloid steel box-girder moulding bed |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109610289A true CN109610289A (en) | 2019-04-12 |
Family
ID=66011075
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811570353.XA Pending CN109610289A (en) | 2018-12-21 | 2018-12-21 | A kind of production method of hyperboloid steel box-girder moulding bed |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109610289A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111441254A (en) * | 2020-04-08 | 2020-07-24 | 中国五冶集团有限公司 | On-site pre-assembled jig frame for steel box girder bridge and installation method thereof |
CN111910518A (en) * | 2019-05-08 | 2020-11-10 | 贵州跃龙钢构有限公司 | Manufacturing process of novel steel structure bridge |
CN112411390A (en) * | 2020-11-30 | 2021-02-26 | 中交路桥建设有限公司 | Concrete bracket for bridge deck of steel-concrete composite beam and construction method thereof |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010018974A (en) * | 2008-07-09 | 2010-01-28 | Totetsu Kogyo Co Ltd | Implement for placing of reinforcement |
CN104120658A (en) * | 2014-08-01 | 2014-10-29 | 武船重型工程股份有限公司 | Machining method of space warping bridge and space warping bridge |
CN104912258A (en) * | 2015-04-17 | 2015-09-16 | 宝钢钢构有限公司 | Making method of isosceles trapezoid variable cross section bending member |
CN107745227A (en) * | 2017-09-26 | 2018-03-02 | 中亿丰建设集团股份有限公司 | The more curve special steel bridge arch processing methods in space |
KR20180047258A (en) * | 2016-10-31 | 2018-05-10 | 현대건설주식회사 | Jig device for a steel reinforcement |
CN108252524A (en) * | 2017-12-22 | 2018-07-06 | 上海市机械施工集团有限公司 | A kind of assembly moulding bed and a kind of hyperbola truss assembling method |
-
2018
- 2018-12-21 CN CN201811570353.XA patent/CN109610289A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010018974A (en) * | 2008-07-09 | 2010-01-28 | Totetsu Kogyo Co Ltd | Implement for placing of reinforcement |
CN104120658A (en) * | 2014-08-01 | 2014-10-29 | 武船重型工程股份有限公司 | Machining method of space warping bridge and space warping bridge |
CN104912258A (en) * | 2015-04-17 | 2015-09-16 | 宝钢钢构有限公司 | Making method of isosceles trapezoid variable cross section bending member |
KR20180047258A (en) * | 2016-10-31 | 2018-05-10 | 현대건설주식회사 | Jig device for a steel reinforcement |
CN107745227A (en) * | 2017-09-26 | 2018-03-02 | 中亿丰建设集团股份有限公司 | The more curve special steel bridge arch processing methods in space |
CN108252524A (en) * | 2017-12-22 | 2018-07-06 | 上海市机械施工集团有限公司 | A kind of assembly moulding bed and a kind of hyperbola truss assembling method |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111910518A (en) * | 2019-05-08 | 2020-11-10 | 贵州跃龙钢构有限公司 | Manufacturing process of novel steel structure bridge |
CN111441254A (en) * | 2020-04-08 | 2020-07-24 | 中国五冶集团有限公司 | On-site pre-assembled jig frame for steel box girder bridge and installation method thereof |
CN112411390A (en) * | 2020-11-30 | 2021-02-26 | 中交路桥建设有限公司 | Concrete bracket for bridge deck of steel-concrete composite beam and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109515252B (en) | Trackless measurement construction method for subway contact network | |
CN109610289A (en) | A kind of production method of hyperboloid steel box-girder moulding bed | |
AU2006219886B2 (en) | Method and system for controlling a construction machine | |
AU649339B2 (en) | A method for determining the deviations of the actual position of a track section | |
CN109702364A (en) | A kind of ultra-wide steel box-girder transverse multi-section division assembling method | |
US11981362B2 (en) | Method and measuring vehicle for determining an actual position of a track | |
CN109297453B (en) | Linear measurement method for arc-shaped template of lining trolley | |
CN211452338U (en) | Trackless fixed point device and trackless fixed point system for rail transit | |
CN112411387A (en) | Lofting method of continuous steel beam pier support | |
CN102493665B (en) | Location installing method of sector embedded part | |
CN113897821A (en) | Subway track slab fine adjustment system and method | |
JP2007211586A (en) | System and method for inserting element into underground | |
JP5235458B2 (en) | Guideway side wall installation method, measurement system, adjustment system and installation system | |
CN108425321B (en) | Installation method of novel variable-cross-section bridge linear control device | |
CN110144828A (en) | The linear control method of the location structure of steel box girder assembling, support construction and bridge | |
CN110241735B (en) | Positioning and adjusting device and method for main tower cable guide pipe of cable-stayed bridge | |
JP2009221738A5 (en) | ||
CN107841949B (en) | A kind of building technology of inverted trapezoidal Bridge beam assembly moulding bed | |
CN115077486A (en) | Template measuring device for vertical ship lift construction and application method thereof | |
CN111021720B (en) | Bidirectional inclined traveling crane disc track formwork construction method | |
CN207862710U (en) | A kind of high-speed railway track plate adjuster | |
CN111041996A (en) | Construction method for installing stay cable and cable pipe by axial method | |
CN101013531A (en) | Method for preparing landform of model and apparatus thereof | |
CN205556725U (en) | Elevation detection auxiliary device is built by laying bricks or stones to blast furnace carbon brick | |
RU147033U1 (en) | RAILWAY CORRECTION SYSTEM |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190412 |
|
RJ01 | Rejection of invention patent application after publication |