JP5038261B2 - Pile construction structure and construction method - Google Patents

Pile construction structure and construction method Download PDF

Info

Publication number
JP5038261B2
JP5038261B2 JP2008218574A JP2008218574A JP5038261B2 JP 5038261 B2 JP5038261 B2 JP 5038261B2 JP 2008218574 A JP2008218574 A JP 2008218574A JP 2008218574 A JP2008218574 A JP 2008218574A JP 5038261 B2 JP5038261 B2 JP 5038261B2
Authority
JP
Japan
Prior art keywords
pile
pile head
fixed
concrete
head
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2008218574A
Other languages
Japanese (ja)
Other versions
JP2010053568A (en
Inventor
健次 昇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kubota Corp
Original Assignee
Kubota Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kubota Corp filed Critical Kubota Corp
Priority to JP2008218574A priority Critical patent/JP5038261B2/en
Publication of JP2010053568A publication Critical patent/JP2010053568A/en
Application granted granted Critical
Publication of JP5038261B2 publication Critical patent/JP5038261B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Description

地中に建てこんだ杭の杭頭部とフーチングを一体化した杭の施工構造及びその施工方法に関する。   The present invention relates to a construction structure and a construction method of a pile in which a pile head and a footing of a pile built in the ground are integrated.

従来、図7に示すように、径方向に重なるように杭頭部1Aよりも大径の鉄製の短筒12を、杭頭部1Aに対して、杭頭部1Aの全周に隙間を開けた状態に囲繞し、その短筒12に縦主筋3の下端部を溶接して、杭頭部1Aと短筒12との間にコンクリート13を充填することによって、フーチング2内で縦主筋3と鋼管杭1とが一体化するように構成してある第1従来技術(例えば、特許文献1参照)があった。また、図8に示すように、鋼管杭1の杭頭部1Aに載置する係止部14に一本の縦主筋部3Aの下端部を一体化すると共に、杭頭部1Aの内方に充填する中詰めコンクリートに下部を埋設する一本の固定鉄筋部6Aの上端部を、係止部14に一体化した補強部材15を、杭頭部1Aの周方向に複数本配置してフーチング2内に杭頭部1Aと共に定着してある第2従来技術があった(例えば、特許文献2参照)。   Conventionally, as shown in FIG. 7, a steel short cylinder 12 having a diameter larger than that of the pile head 1A is formed so as to overlap in the radial direction with a gap formed on the entire circumference of the pile head 1A with respect to the pile head 1A. The lower main bar 3 is welded to the short cylinder 12 and the concrete 13 is filled between the pile head 1A and the short cylinder 12 so that the vertical main bar 3 There was the 1st conventional technology (for example, refer to patent documents 1) constituted so that steel pipe pile 1 may be unified. Moreover, as shown in FIG. 8, while integrating the lower end part of one longitudinal main reinforcement part 3A in the latching | locking part 14 mounted in the pile head 1A of the steel pipe pile 1, it is inward of the pile head 1A. A plurality of reinforcing members 15 in which the upper end portion of one fixed reinforcing bar portion 6A, whose lower portion is embedded in the filling concrete to be filled, are integrated with the engaging portion 14 are arranged in the circumferential direction of the pile head portion 1A, and the footing 2 There was the 2nd prior art currently fixed with pile head 1A in the inside (for example, refer to patent documents 2).

特開平10−266227号公報(図7)Japanese Patent Laid-Open No. 10-266227 (FIG. 7) 特開平5−187028号公報(図8)Japanese Patent Laid-Open No. 5-187028 (FIG. 8)

上述した第1の従来技術では、短筒12に縦主筋の下端部を溶接により一体化してあるために、溶接の熱による劣化が発生し、そのために強度上の品質の保証ができなくなる虞があり、近年特に現場溶接による一体化技術は使えなくなる傾向にある。その上、鋼管杭1と縦主筋3は、短筒12と杭頭部1Aとの短い重なり代で、それらの間に充填されるコンクリート13によって連結されるだけであるために、連結強度不足になりやすい欠点があった。   In the first prior art described above, since the lower end portion of the longitudinal main bar is integrated with the short cylinder 12 by welding, there is a possibility that deterioration due to the heat of welding occurs, so that quality in strength cannot be guaranteed. In recent years, in particular, integration technology by field welding tends to be unusable. In addition, since the steel pipe pile 1 and the longitudinal main bar 3 are simply connected by the concrete 13 filled between the short cylinder 12 and the pile head 1A, the connection strength is insufficient. There was a fault that was easy to become.

また、前記第2の従来技術では、縦主筋部3Aと中詰めコンクリートに埋設する固定鉄筋部6Aとが係止部14を介して予め一体形成してあるために、強度は確保されるものの、1本の縦主筋部3Aと1本の固定鉄筋部6Aとを設けた補強部材15は、杭頭部1Aに対して、その周方向に複数本を配置して夫々が相対的に移動しないように固定してからでないと、フーチング2を打設することが出来ないために、施工性が悪いものであった。   In the second prior art, since the longitudinal main reinforcing bar portion 3A and the fixed reinforcing bar portion 6A embedded in the filling concrete are integrally formed in advance via the locking portion 14, the strength is ensured. The reinforcing member 15 provided with one longitudinal main reinforcing bar portion 3A and one fixed reinforcing bar portion 6A is arranged with respect to the pile head 1A so that a plurality of reinforcing members 15 do not move relative to each other. Since the footing 2 cannot be placed unless it is fixed to the base, the workability is poor.

従って、本発明の目的は、上記問題点を解消し、現場での溶接による一体化施工をせずに、しかも杭と複数の縦主筋との連結強度を大きく、しかも簡単な施工で確保できる杭の施工構造及び施工方法を提供するところにある。   Therefore, the object of the present invention is to eliminate the above-mentioned problems, and without using integrated construction by welding at the site, the pile can be secured with a large connection strength between the plurality of longitudinal main bars and can be secured by simple construction. The construction structure and construction method are provided.

本発明の第1の特徴構成は、地中に建てこんだ杭の杭頭部とフーチングを一体化した杭の施工構造であって、
前記杭頭部に載置する固定プレートを設け、前記杭頭部に前記固定プレートを載置して前記杭頭部内に中詰めコンクリートを充填した状態で、その中詰めコンクリート内に下部を埋設する固定鋼材の上部を前記固定プレートに機械的に一体連結し、複数の縦主筋を、前記杭頭部の外側に配置すると共に、それらの下部を前記固定プレートに機械的に一体連結してあるところにある。
The first characteristic configuration of the present invention is a pile construction structure in which a pile head and a footing of a pile built in the ground are integrated,
A fixed plate to be placed on the pile head is provided, and the fixed plate is placed on the pile head, and the lower part is buried in the filled concrete in a state in which the filled concrete is filled in the pile head. The upper part of the fixed steel material to be mechanically integrally connected to the fixed plate, a plurality of longitudinal main bars are disposed outside the pile head, and the lower parts thereof are mechanically integrally connected to the fixed plate. By the way.

本発明の第1の特徴構成によれば、杭は杭頭部内に配置する複数の固定鋼材と中詰めコンクリートによる付着力により一体化され、その連結強度は、固定鋼材の本数を増やし、長さを長くすることによって簡単に上げることが出来、その固定鋼材と固定プレートを介して縦主筋は、強固に杭と一体連結する。   According to the first characteristic configuration of the present invention, the pile is integrated by a plurality of fixed steel materials arranged in the pile head and adhesive force by the filling concrete, and the connection strength increases the number of the fixed steel materials, It can be easily raised by increasing the length, and the longitudinal main reinforcement is firmly connected to the pile through the fixed steel material and the fixed plate.

また、固定プレートを杭頭部に載置することによって、その固定プレートに連結される複数の縦主筋や複数の固定鋼材が共に自立固定でき、従来のように1本の縦主筋部及び固定鉄筋部を杭頭部の周りに複数本配置して、その上それらが安定した姿勢になるようにするためには、夫々を連結部材等を使って仮固定しなければならないのに比して施工性は格段に良い。   In addition, by placing the fixed plate on the pile head, a plurality of vertical main bars and a plurality of fixed steel members connected to the fixed plate can be fixed independently. In order to arrange multiple parts around the pile head and make them have a stable posture, they are constructed compared to having to temporarily fix them using connecting members etc. Sex is much better.

しかも、固定プレートに縦主筋及び固定鋼材を機械的に固定連結するために、現場で溶接することなく複数の縦主筋や複数の固定鋼材を夫々連結固定でき、強度品質の安定を保証しやすくなった。   In addition, since the vertical main bars and fixed steel materials are mechanically fixedly connected to the fixed plate, it is possible to connect and fix multiple vertical main bars and multiple fixed steel materials without welding on-site, making it easy to guarantee the stability of strength quality. It was.

また、現場での組み立てができることから、組み立て前の部材として輸送できるので、搬送が容易になる。   Moreover, since it can be assembled on site, it can be transported as a member before assembly, so that the conveyance becomes easy.

本発明の第2の特徴構成は、前記固定プレートには、中詰めコンクリートを充填するための貫通孔を設けてあることにある。   A second characteristic configuration of the present invention is that the fixing plate is provided with a through-hole for filling the filling concrete.

本発明の第2の特徴構成によれば、予め複数の固定鋼材を連結しておいた固定プレートを杭頭部に載置した後に、固定プレートに設けた貫通孔を介して杭頭部内にコンクリートを充填することが出来る。   According to the 2nd characteristic structure of this invention, after mounting the fixed plate which connected several fixed steel materials previously in a pile head, in a pile head via the through-hole provided in the fixed plate. Can be filled with concrete.

本発明の第3の特徴構成は、杭を地中に建てこむ第1工程と、前記杭の杭頭部に中詰めコンクリートを充填する第2工程と、固定鋼材を前記中詰めコンクリート内に挿入しながらその固定鋼材を機械的に固定した固定プレートを杭頭部に載置する第3工程と、複数の縦主筋を杭頭部の外側になるように配置してその下部を夫々前記固定プレートに機械的に固定する第4工程と、前記杭頭部及び前記縦主筋を共に埋設するように、コンクリートを打設してフーチングを形成する第5工程とを有することにある。   The third characteristic configuration of the present invention includes a first step of building a pile in the ground, a second step of filling the pile head of the pile with the filling concrete, and inserting a fixed steel material into the filling concrete. And a third step of placing a fixed plate on which the fixed steel material is mechanically fixed on the pile head, and a plurality of vertical main bars arranged on the outside of the pile head, and the lower portions of the fixed plate are respectively fixed to the fixed plate. A fourth step of mechanically fixing the pile head and a fifth step of forming a footing by placing concrete so as to embed the pile head and the longitudinal main bar together.

本発明の第3の特徴構成によれば、例えば杭の内側に中詰めコンクリートを充填した後、鉄筋籠を中詰めコンクリート中に落とし込む工法と比べて、複数本の縦主筋を籠状に組み立てる横方向の組み立て筋を不要として、複数の縦主筋を簡単に杭の杭頭部に固定一体化できる。
しかも、複数の縦主筋は杭の径方向における位置を、フーチングの曲げ強度を上げるべく杭頭部の外側に配置するのに、固定プレートの外径内で自由に決めることが出来、施工性を向上させることが出来る。
According to the third characteristic configuration of the present invention, for example, a method of assembling a plurality of longitudinal main bars in a bowl shape as compared with a method in which, after filling the inside of a pile with filling concrete, the reinforcing bar is dropped into the filling concrete. A plurality of longitudinal main bars can be easily fixed and integrated with the pile heads of the piles without the need for assembly bars in the direction.
Moreover, the multiple longitudinal main bars can be freely determined within the outer diameter of the fixed plate in order to arrange the position in the radial direction of the pile outside the pile head to increase the bending strength of the footing. Can be improved.

本発明の第4の特徴構成は、杭を地中に建てこむ第1工程と、固定鋼材の下部を前記杭の杭頭部内方に挿入しながら予め機械的に前記固定鋼材を連結した固定プレートを、前記杭頭部に載置する第2工程と、複数の縦主筋を前記杭頭部の外方になるように配置してその下部を夫々前記固定プレートに機械的に固定する第3工程と、前記第2工程の後又は前記第3工程の後に前記杭頭部内に前記固定プレートの貫通孔を通して中詰めコンクリートを充填する第4工程と、前記杭頭部及び前記縦主筋を共に埋設するように、コンクリートを打設してフーチングを形成する第5工程とを有することにある。   The 4th characteristic structure of this invention is the 1st process which builds a pile in the ground, and the fixed which connected the said fixed steel material mechanically beforehand, inserting the lower part of a fixed steel material into the pile head inside of the said pile. A second step of placing the plate on the pile head; and a third step in which a plurality of longitudinal main bars are arranged outside the pile head and the lower portions thereof are mechanically fixed to the fixing plate, respectively. A step, a fourth step of filling the pile head with the filling concrete through the through hole of the fixing plate after the second step or after the third step, and the pile head and the longitudinal main bar together A fifth step of placing the concrete to form a footing so as to be buried.

本発明の第4の特徴構成によれば、上記第3の特徴構成と同様に、杭の中詰めコンクリート内に鉄筋籠を落とし込んで縦主筋を杭と一体化する工法と比べて、施工性を向上させることが出来る。   According to the fourth characteristic configuration of the present invention, as in the third characteristic configuration, the workability is improved in comparison with the construction method in which the reinforcing bar is dropped into the pile-filled concrete and the vertical main bar is integrated with the pile. Can be improved.

本発明の第5の特徴構成は、前記固定プレートを前記杭頭部に載置する前に、前記固定プレートに予め前記固定鋼材と前記縦主筋とを機械的に固定することにある。   A fifth characteristic configuration of the present invention is to mechanically fix the fixed steel material and the longitudinal main bars to the fixing plate in advance before placing the fixing plate on the pile head.

本発明の第5の特徴構成によれば、固定プレートを杭頭部に載置するだけで、固定鋼材と縦主筋は、杭頭部に対する所定の位置に配置され、施工性の向上に繋がる。   According to the 5th characteristic structure of this invention, only by mounting a fixed plate in a pile head, a fixed steel material and a longitudinal main reinforcement are arrange | positioned in the predetermined position with respect to a pile head, and it leads to the improvement of workability.

以下に本発明の実施の形態を図面に基づいて説明する。   Embodiments of the present invention will be described below with reference to the drawings.

図1〜3に示すように、本発明に係る杭の施工構造は、平面視で複数本の鋼管杭1が地中に立て込んであり、それらの複数本の鋼管杭1に対し、夫々の杭頭部1Aを一体化するようにフーチング2を設けてある。
前記フーチング2内には、鋼管杭1と一体化して上からの荷重を鋼管杭1に伝達する縦主筋3の複数本を、杭頭部1Aの外側周りに配置してコンクリートに定着してある。
As shown in FIGS. 1 to 3, the pile construction structure according to the present invention has a plurality of steel pipe piles 1 standing in the ground in a plan view. A footing 2 is provided so as to integrate the head 1A.
In the footing 2, a plurality of longitudinal main bars 3 which are integrated with the steel pipe pile 1 and transmit the load from above to the steel pipe pile 1 are arranged around the outside of the pile head 1A and fixed to the concrete. .

前記縦主筋3は、約35mmの径を有し、鋼管杭1と一体化するために、次のように構成してある。
前記杭頭部1Aに載置する鋼板から成る円形の固定プレート4を設け、杭頭部1Aに固定プレート4を載置して杭頭部1A内に中詰めコンクリート5を充填した状態で、その中詰めコンクリート5内に下部を埋設する固定鋼材として、異形棒鋼から成る複数の固定鉄筋6を設け、それらの固定鉄筋6の上部を夫々固定プレート4にナット7を介して一体連結してある。また、複数の縦主筋3を、杭頭部1Aの径方向における外側で、且つ、その周りに夫々均等に100mmピッチ毎に配置すると共に、それらの下部を固定プレート4にナット7を介して一体連結してある。
The longitudinal main bars 3 have a diameter of about 35 mm and are configured as follows in order to be integrated with the steel pipe pile 1.
In the state where a circular fixed plate 4 made of a steel plate placed on the pile head 1A is provided, the fixed plate 4 is placed on the pile head 1A, and the inside concrete 5 is filled in the pile head 1A, A plurality of fixed reinforcing bars 6 made of deformed steel bars are provided as a fixed steel material in which the lower part is embedded in the filling concrete 5, and the upper parts of these fixed reinforcing bars 6 are integrally connected to the fixing plate 4 via nuts 7. Further, the plurality of longitudinal main bars 3 are arranged on the outer side in the radial direction of the pile head 1A and around the pile heads 1B at equal intervals of 100 mm, and the lower parts thereof are integrated with the fixing plate 4 via nuts 7. It is connected.

尚、コンクリートに定着する縦主筋3を長くすることで、結合強度を向上させることができる。   In addition, bond strength can be improved by lengthening the longitudinal main reinforcement 3 fixed to concrete.

前記固定プレート4には、鋼管杭1の径方向で内側に固定鉄筋6の上端部を挿通させる第1挿通孔10を設けてあると共に、外側には縦主筋3の下端部を挿通させる第2挿通孔11を設けてある。また、固定鉄筋6の上端部には、ナット7が螺合する雄ネジ部を形成してあると共に、縦主筋3の下端部には、ナット7が螺合する雄ネジ部を形成してある。そして、第1挿通孔10に固定鉄筋6の上端部を挿通させて固定プレート4の上下裏表に配設したナット7の挟み込みにより固定鉄筋6を固定し、第2挿通孔11には、縦主筋3を挿通させて固定プレート4の上下裏表に配設したナット7の挟み込みにより、縦主筋3を固定してある。   The fixing plate 4 is provided with a first insertion hole 10 through which the upper end portion of the fixed reinforcing bar 6 is inserted inside in the radial direction of the steel pipe pile 1, and a second end through which the lower end portion of the longitudinal main reinforcing bar 3 is inserted. An insertion hole 11 is provided. In addition, a male screw portion into which the nut 7 is screwed is formed at the upper end portion of the fixed reinforcing bar 6, and a male screw portion into which the nut 7 is screwed is formed at the lower end portion of the vertical main reinforcing bar 3. . The upper end portion of the fixed reinforcing bar 6 is inserted into the first insertion hole 10, and the fixed reinforcing bar 6 is fixed by sandwiching the nuts 7 arranged on the upper and lower surfaces of the fixing plate 4. The longitudinal main bars 3 are fixed by inserting nuts 7 inserted through the top and bottom and front and back of the fixing plate 4.

尚、前記杭は、鋼管杭1の他、コンクリート杭、鋼管コンクリート杭であってもよい。
また、前記固定鋼材には、固定鉄筋6の他に、H型鋼、I型鋼、L型鋼であっても良い。
また、前記固定鉄筋6の周囲に環状の帯鉄筋を連結しても良い。
また、前記固定プレートにネジ孔を設け、固定鉄筋6と縦主筋3の雄ネジと螺合し、固定しても良い。
In addition to the steel pipe pile 1, the pile may be a concrete pile or a steel pipe concrete pile.
The fixed steel material may be H-shaped steel, I-shaped steel, or L-shaped steel in addition to the fixed rebar 6.
Further, an annular belt reinforcing bar may be connected around the fixed reinforcing bar 6.
Further, a screw hole may be provided in the fixing plate, and the fixing plate 6 and the male screw of the longitudinal main reinforcing bar 3 may be screwed together and fixed.

前記杭頭部1Aの内方には、中詰めコンクリート5を受止める受板を取り付けてあり、また、杭頭部1Aに対する中詰めコンクリート5の付着力を上げるために、杭頭部1A内面に、ずれ止め部材を一体に付設してある。従って、鋼管杭1と固定鉄筋6は中詰めコンクリート5を介して一体連結され、縦主筋3に作用する上からの荷重や、上方への引抜力が鋼管杭1に伝達するように構成してある。   A receiving plate for receiving the filling concrete 5 is attached to the inside of the pile head 1A, and in order to increase the adhesion of the filling concrete 5 to the pile head 1A, The slip preventing member is integrally provided. Therefore, the steel pipe pile 1 and the fixed reinforcing bar 6 are integrally connected via the filling concrete 5 so that the load from the top acting on the longitudinal main bar 3 and the upward pulling force are transmitted to the steel pipe pile 1. is there.

前記複数の縦主筋3には、それらを取り囲むように上部側で上下一定間隔に、環状の帯鉄筋8が巻かれて一体連結してある。これにより、フーチング2内で上からの荷重による座屈や、径方向外方側へのはらみ現象を防止できるようにしてある。   The plurality of longitudinal main bars 3 are integrally connected with an annular band reinforcing bar 8 wound around the upper side at regular intervals in the upper part so as to surround them. As a result, buckling due to a load from above in the footing 2 and a phenomenon of squeezing outward in the radial direction can be prevented.

次に、鋼管杭1の施工方法を説明する。 Next, the construction method of the steel pipe pile 1 is demonstrated.

〔第1施工方法〕
図4に示すように、鋼管杭1を地中に建てこむ第1工程と、鋼管杭1の杭頭部1Aに中詰めコンクリート5を充填する第2工程(図4(a))と、複数の固定鉄筋6を中詰めコンクリート5内に挿入しながらその固定鉄筋6をナット7を介して固定した固定プレート4を杭頭部1Aに載置する第3工程(図4(b))と、複数の縦主筋3を杭頭部1Aの外側に配置してその下部を夫々固定プレート4にナット7を介して固定する第4工程(図4(c))と、杭頭部1A及び縦主筋3を共に埋設するように、コンクリートを打設してフーチング2を形成する第5工程(図4(d))とが、順次行われる。
[First construction method]
As shown in FIG. 4, the 1st process of building the steel pipe pile 1 in the ground, the 2nd process (FIG. 4 (a)) of filling the pile head 1A of the steel pipe pile 1 with the filling concrete 5 and a plurality of A third step (FIG. 4 (b)) of placing the fixed plate 4 on the pile head 1A while fixing the fixed rebar 6 to the pile head 1A while inserting the fixed rebar 6 into the filling concrete 5; 4th process (FIG.4 (c)) which arrange | positions several vertical main bars 3 on the outer side of the pile head 1A, and fixes the lower part to the fixing plate 4 via the nut 7, respectively, and the pile head 1A and the vertical main bars The fifth step (FIG. 4 (d)) in which concrete is cast to form the footing 2 so as to embed 3 together is sequentially performed.

尚、前記固定プレート4に固定鉄筋6と縦主筋3を固定してから、杭頭部に載置してもよい。
また、中詰めコンクリート5が固まる前に、固定プレート4を載置するので、固定プレート4を移動させて位置決めすることができ、上部のフーチング2内の鉄筋との取り合いの調整が容易になる。
In addition, after fixing the fixed reinforcement 6 and the vertical main reinforcement 3 to the said fixed plate 4, you may mount in a pile head.
Further, since the fixed plate 4 is placed before the filling concrete 5 is hardened, the fixed plate 4 can be moved and positioned, and the adjustment of the engagement with the reinforcing bars in the upper footing 2 is facilitated.

〔第2施工方法〕
図5に示すように、前記固定プレート4には、予めコンクリート充填用の貫通孔9を形成しておく。そして、鋼管杭1を地中に建てこむ第1工程と、固定鉄筋6の下部を鋼管杭1の杭頭部1A内方に挿入しながら予めナット7を介して複数の固定鉄筋6を連結した固定プレート4を、杭頭部1Aに載置する第2工程(図5(a))と、複数の縦主筋3を杭頭部1Aの外方に配置してその下部を夫々固定プレート4にナット7を介して固定する第3工程(図5(c))と、第2工程の後又は第3工程の後に杭頭部1A内に固定プレート4の貫通孔9を通して中詰めコンクリート5を充填する第4工程(図5(b))と、杭頭部1A及び縦主筋3を共に埋設するように、コンクリートを打設してフーチング2を形成する第5工程(図5(d))とが、順次行われる。
[Second construction method]
As shown in FIG. 5, a through hole 9 for filling concrete is formed in the fixed plate 4 in advance. And the 1st process of building the steel pipe pile 1 in the ground, and connecting the some fixed reinforcement 6 via the nut 7 previously, inserting the lower part of the fixed reinforcement 6 in the pile head 1A inside of the steel pipe pile 1 A second step (FIG. 5 (a)) for placing the fixed plate 4 on the pile head 1A, and a plurality of vertical main bars 3 are arranged outside the pile head 1A, and the lower portions thereof are fixed to the fixed plate 4, respectively. The third step (FIG. 5 (c)) to be fixed via the nut 7 and the intermediate concrete 5 is filled into the pile head 1A through the through hole 9 of the fixing plate 4 after the second step or after the third step. The fourth step (FIG. 5 (b)) to be performed, and the fifth step (FIG. 5 (d)) to form the footing 2 by placing concrete so as to embed the pile head 1A and the longitudinal main reinforcement 3 together. Are sequentially performed.

尚、前記固定プレート4に固定鉄筋6と縦主筋3を固定してから、杭頭部に載置してもよい。
また、前記固定プレート4を移動させて位置決めできるので、上部のフーチング2内の鉄筋との取り合いの調整が容易になる。
この工法では、受板を杭頭部の内方に予め設置しておく代わりに、実開平01−65343号公報の円板状体に対応するコンクリート受け皿を、固定鉄筋の最下部に固定しておいてもよい。
In addition, after fixing the fixed reinforcement 6 and the vertical main reinforcement 3 to the said fixed plate 4, you may mount in a pile head.
Moreover, since the said fixed plate 4 can be moved and positioned, adjustment of the engagement with the reinforcing bar in the upper footing 2 becomes easy.
In this construction method, instead of previously setting the receiving plate inside the pile head, a concrete tray corresponding to the disk-shaped body of Japanese Utility Model Laid-Open No. 01-65343 is fixed to the lowermost part of the fixed reinforcing bar. It may be left.

〔別実施の形態〕
図6に示すように、前記縦主筋3を固定プレート4に機械的に一体連結するのに、固定プレート4にメネジ部16を形成しておいて、そのメネジ部16に縦主筋の下端のオネジ部18を螺合連結しても良く、また、固定鉄筋6も同様に、固定プレート4に形成したメネジ部17に固定鉄筋6の上端のオネジ部19を螺合して連結するようにしてあっても良い。
[Another embodiment]
As shown in FIG. 6, in order to mechanically connect the vertical main bar 3 to the fixing plate 4, a female screw part 16 is formed on the fixing plate 4, and the female screw 16 at the lower end of the vertical main bar is formed on the female screw part 16. The portion 18 may be screwed and connected, and the fixed rebar 6 is similarly connected to the female screw portion 17 formed on the fixing plate 4 by screwing and connecting the male screw portion 19 at the upper end of the fixed rebar 6. May be.

尚、上述のように、図面との対照を便利にするために符号を記したが、該記入により本
発明は添付図面の構成に限定されるものではない。また、本発明の要旨を逸脱しない範囲において、種々なる態様で実施し得ることは勿論である。
In addition, as mentioned above, although the code | symbol was written in order to make contrast with drawing convenient, this invention is not limited to the structure of an accompanying drawing by this entry. In addition, it goes without saying that the present invention can be carried out in various modes without departing from the gist of the present invention.

本発明の実施形態で説明する要部の縦断面図The longitudinal cross-sectional view of the principal part demonstrated by embodiment of this invention 本発明の実施形態のフーチングの横断平面図Cross-sectional plan view of footing according to an embodiment of the present invention 本発明の実施形態の杭頭部の横断面図Cross-sectional view of a pile head according to an embodiment of the present invention 本発明の実施形態の第1実施方法を示す作用説明図Action | operation explanatory drawing which shows the 1st implementation method of embodiment of this invention 本発明の実施形態の第2実施方法を示す作用説明図Action explanatory drawing which shows the 2nd implementation method of embodiment of this invention 本発明の別実施形態を示す要部縦断面図The principal part longitudinal cross-sectional view which shows another embodiment of this invention 第1従来技術を示す要部縦断面図Main part longitudinal cross-sectional view showing the first prior art 第2従来技術を示す要部縦断面図Main part longitudinal cross-sectional view showing the second prior art

符号の説明Explanation of symbols

1 鋼管杭
2 杭頭部
3 縦主筋
4 固定プレート
5 中詰めコンクリート
6 固定鉄筋
7 ナット
8 帯鉄筋
9 貫通孔
DESCRIPTION OF SYMBOLS 1 Steel pipe pile 2 Pile head 3 Longitudinal reinforcement 4 Fixing plate 5 Filled concrete 6 Fixed reinforcement 7 Nut 8 Reinforcing bar 9 Through-hole

Claims (5)

地中に建てこんだ杭の杭頭部とフーチングを一体化した杭の施工構造であって、
前記杭頭部に載置する固定プレートを設け、前記杭頭部に前記固定プレートを載置して前記杭頭部内に中詰めコンクリートを充填した状態で、その中詰めコンクリート内に下部を埋設する固定鋼材の上部を前記固定プレートに機械的に一体連結し、複数の縦主筋を、前記杭頭部の外側に配置すると共に、それらの下部を前記固定プレートに機械的に一体連結してある杭の施工構造。
It is a construction structure of a pile that integrates the pile head and footing of the pile built in the ground,
A fixed plate to be placed on the pile head is provided, and the fixed plate is placed on the pile head, and the lower part is buried in the filled concrete in a state in which the filled concrete is filled in the pile head. The upper part of the fixed steel material to be mechanically integrally connected to the fixed plate, a plurality of longitudinal main bars are disposed outside the pile head, and the lower parts thereof are mechanically integrally connected to the fixed plate. Pile construction structure.
前記固定プレートには、中詰めコンクリートを充填するための貫通孔を設けてある請求項1に記載の杭の施工構造。   The pile construction structure according to claim 1, wherein the fixing plate is provided with a through-hole for filling the filling concrete. 請求項1に記載の杭の施工構造を形成するに、杭を地中に建てこむ第1工程と、前記杭の杭頭部に中詰めコンクリートを充填する第2工程と、固定鋼材を前記中詰めコンクリート内に挿入しながらその固定鋼材を機械的に固定した固定プレートを杭頭部に載置する第3工程と、複数の縦主筋を杭頭部の外側になるように配置してその下部を夫々前記固定プレートに機械的に固定する第4工程と、前記杭頭部及び前記縦主筋を共に埋設するように、コンクリートを打設してフーチングを形成する第5工程とを有する杭の施工方法。   In order to form the construction structure of the pile of Claim 1, the 1st process which builds a pile in the ground, the 2nd process which fills the pile head part of the said pile with filling concrete, The fixed steel material is said inside. A third step of placing a fixed plate on which the fixed steel material is mechanically fixed while being inserted into the stuffed concrete is placed on the pile head, and a plurality of vertical main bars are arranged outside the pile head and below that Of a pile having a fourth step of mechanically fixing each of the piles to the fixing plate and a fifth step of placing concrete to form a footing so as to embed the pile head and the longitudinal main bar together. Method. 請求項2記載の杭の施工構造を形成するに、杭を地中に建てこむ第1工程と、固定鋼材の下部を前記杭の杭頭部内方に挿入しながら予め機械的に前記固定鋼材を連結した固定プレートを、前記杭頭部に載置する第2工程と、複数の縦主筋を前記杭頭部の外方になるように配置してその下部を夫々前記固定プレートに機械的に固定する第3工程と、前記第2工程の後又は前記第3工程の後に前記杭頭部内に前記固定プレートの貫通孔を通して中詰めコンクリートを充填する第4工程と、前記杭頭部及び前記縦主筋を共に埋設するように、コンクリートを打設してフーチングを形成する第5工程とを有する杭の施工方法。   To form the construction structure of a pile according to claim 2, a first step of building the pile in the ground and a mechanically fixed steel material in advance while inserting a lower portion of the fixed steel material into the pile head inside the pile. A fixing plate connected to the pile head, a second step of placing the fixing plate on the pile head, and arranging a plurality of longitudinal main bars so as to be outward of the pile head, and lower portions thereof mechanically to the fixing plate, respectively. A third step of fixing, a fourth step of filling the pile head through the through hole of the fixing plate into the pile head after the second step or after the third step, the pile head and the A pile construction method having a fifth step of placing concrete to form a footing so as to embed the longitudinal main bars together. 前記固定プレートを前記杭頭部に載置する前に、前記固定プレートに予め前記固定鋼材と前記縦主筋とを機械的に固定する請求項3又は4に記載の杭の施工方法。   The pile construction method according to claim 3 or 4, wherein the fixed steel material and the longitudinal main bars are mechanically fixed to the fixed plate in advance before placing the fixed plate on the pile head.
JP2008218574A 2008-08-27 2008-08-27 Pile construction structure and construction method Expired - Fee Related JP5038261B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008218574A JP5038261B2 (en) 2008-08-27 2008-08-27 Pile construction structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008218574A JP5038261B2 (en) 2008-08-27 2008-08-27 Pile construction structure and construction method

Publications (2)

Publication Number Publication Date
JP2010053568A JP2010053568A (en) 2010-03-11
JP5038261B2 true JP5038261B2 (en) 2012-10-03

Family

ID=42069765

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008218574A Expired - Fee Related JP5038261B2 (en) 2008-08-27 2008-08-27 Pile construction structure and construction method

Country Status (1)

Country Link
JP (1) JP5038261B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110761314A (en) * 2019-11-21 2020-02-07 上海勘测设计研究院有限公司 Double-layer extrusion type anchor plate for prestressed steel pipe cast-in-place pile and connection structure

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05187028A (en) * 1992-01-14 1993-07-27 Nkk Corp Steel for coupling pile head
JPH10266227A (en) * 1997-03-28 1998-10-06 Asahi Chem Ind Co Ltd Method of connecting ready made pile and foundation slab
JP4693299B2 (en) * 2001-08-09 2011-06-01 旭化成建材株式会社 Column base connection structure
JP2005009300A (en) * 2003-05-27 2005-01-13 Sumitomo Metal Ind Ltd Structure of joining steel pipe to reinforcement and pile head joint portion
JP4450706B2 (en) * 2004-09-17 2010-04-14 新日本製鐵株式会社 Pile-column connection structure and method
JP4778386B2 (en) * 2006-09-27 2011-09-21 日本コンクリート工業株式会社 Construction method of pile head fixing structure in pile

Also Published As

Publication number Publication date
JP2010053568A (en) 2010-03-11

Similar Documents

Publication Publication Date Title
JP6543383B2 (en) Pile head connection structure
KR100864953B1 (en) Frp-concrete composite structure using precast fiber reinforced polymer pipe of double(inner and outer) hollow type and the construction method using the same
JP4844928B2 (en) Pile head joint structure and construction method
KR101029042B1 (en) Precasr pier unit using sheath and pier construction method therewith
JP2008231799A (en) Base isolation structure
JP5333375B2 (en) Segment and manufacturing method thereof
KR101577019B1 (en) Diaphram and reinforcement structure of the concrete filled steel tublar comumn, and the manufacturing method of it
JP4423644B2 (en) Hollow precast pillar
KR20090069151A (en) Prefab apparatus for reinforcing head of pile
JP5038261B2 (en) Pile construction structure and construction method
JP2006083572A (en) Prestressed concrete structure
KR100905031B1 (en) Pile construction method using foundation pile and hollow reinforcing pile
KR101448145B1 (en) Column Integrated Footing
JP2007077639A (en) Prefabricated pile and foundation pile structure
CN112112156A (en) Tubular pile connecting device and connecting method
JP2010144392A (en) Structure and method for connecting pile head of prefabricated pile and footing connecting material together
JP4430496B2 (en) Pile head joint structure and construction method
JP5601787B2 (en) Column structure and construction method of column structure
JP4502192B2 (en) Structure and construction method of column base joints of steel pipe columns
JP2012057431A (en) Structure for connecting pile and steel column
KR101157475B1 (en) Fixing device for block used in retaining wall and method for making retaining wall using the same
KR200448755Y1 (en) Prefab apparatus for reinforcing head of pile
JP2005111977A (en) Method for manufacturing pc wall material and reinforced structure on joint part of pc wall material
JP4518930B2 (en) Pile head joint structure and construction method
JP6871492B2 (en) Pile head reinforcement member and pile head reinforcement structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20110323

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120521

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120607

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120705

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150713

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 5038261

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees