JP4931949B2 - Road surface temporary restoration member and road surface temporary restoration method - Google Patents

Road surface temporary restoration member and road surface temporary restoration method Download PDF

Info

Publication number
JP4931949B2
JP4931949B2 JP2009039133A JP2009039133A JP4931949B2 JP 4931949 B2 JP4931949 B2 JP 4931949B2 JP 2009039133 A JP2009039133 A JP 2009039133A JP 2009039133 A JP2009039133 A JP 2009039133A JP 4931949 B2 JP4931949 B2 JP 4931949B2
Authority
JP
Japan
Prior art keywords
road surface
mat
pin
lining
lining mat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2009039133A
Other languages
Japanese (ja)
Other versions
JP2010095987A (en
JP2010095987A5 (en
Inventor
繁明 関根
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Meiwa Kogyo Co Ltd
Original Assignee
Meiwa Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Meiwa Kogyo Co Ltd filed Critical Meiwa Kogyo Co Ltd
Priority to JP2009039133A priority Critical patent/JP4931949B2/en
Priority to PCT/JP2009/061328 priority patent/WO2010021199A1/en
Priority to KR1020117005522A priority patent/KR101258417B1/en
Priority to US13/059,896 priority patent/US20110142539A1/en
Priority to CN2009801324804A priority patent/CN102131985A/en
Publication of JP2010095987A publication Critical patent/JP2010095987A/en
Publication of JP2010095987A5 publication Critical patent/JP2010095987A5/ja
Application granted granted Critical
Publication of JP4931949B2 publication Critical patent/JP4931949B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C9/00Special pavings; Pavings for special parts of roads or airfields
    • E01C9/08Temporary pavings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)
  • Road Repair (AREA)

Description

本発明は、路面を掘削して、ガス、水道、下水その他の管路工事を行う際に、路面を仮復旧するための覆工部材及び前記覆工部材を使用する路面仮復旧工法に関するものである。   The present invention relates to a lining member for temporarily restoring a road surface when excavating the road surface and performing gas, water, sewage and other pipe work, and a road surface temporary restoration method using the lining member. is there.

路面に新たな配管を埋設する配管工事や、既に埋設されたガス、水道、下水管等の補修・交換が必要となった際における仮配管工事や本配管工事に於いては、溝掘削が行なわれるが、一工程(通常は一日の工事分)毎に掘削した溝を一旦埋め戻し、この埋め戻し上面に、車両走行、歩行に支障が生じないよう仮のアスファルト舗装(仮復旧工事)を施しているものである。   Groove excavation is carried out in piping work to bury new pipes on the road surface, temporary piping work and main piping work when it is necessary to repair or replace already buried gas, water, sewage pipes, etc. However, once excavated trenches are backfilled once in each process (usually for one day's work), temporary asphalt pavement (temporary restoration work) is provided on the backfill surface to prevent hindrance to vehicle running and walking. It is something that has been given.

当該配管工事の終了時に前記の仮復旧工事のアスファルト舗装は全てを除去され、本復旧舗装が行なわれるものである。   At the end of the piping work, all the asphalt pavement of the temporary restoration work is removed, and this restoration pavement is performed.

このように仮復旧工事において使用されるアスファルトは、最終的に産業廃棄物となるもので、工事の効率化、省資源、環境問題等の点から仮復旧工事における仮舗装は好ましくない。   Thus, the asphalt used in the temporary restoration work eventually becomes industrial waste, and temporary paving in the temporary restoration work is not preferable from the viewpoint of efficiency of construction, resource saving, environmental problems, and the like.

この対策として、仮舗装に替えて仮復旧用部材を使用することが提案されている。例えば特許文献1(特開平10−37113号公報)には、仮復旧用部材として押圧部材とゴムマットを採用し、掘削路面(舗装除去面)に、中空棒状体を所定の間隔を置いて略平行状態に並列して連結した押圧部材を置き、その上に掘削路面幅より広いゴムマットを被せる仮復旧路面を開示している。   As a countermeasure, it has been proposed to use a temporary restoration member instead of temporary paving. For example, in Patent Document 1 (Japanese Patent Laid-Open No. 10-37113), a pressing member and a rubber mat are employed as a temporary restoration member, and a hollow rod-shaped body is substantially parallel to the excavation road surface (pavement removal surface) at a predetermined interval. A temporary restoration road surface is disclosed in which a pressing member connected in parallel with the state is placed and a rubber mat wider than the excavation road surface width is placed thereon.

また特許文献2(特開2004−52410号公報)には、仮復旧用部材として模擬路盤材とゴムマットを採用し、模擬路盤材は廃プラスチックで形成し、この模擬路盤材上にゴムマットを敷設しているものである。   Patent Document 2 (Japanese Patent Application Laid-Open No. 2004-52410) employs a simulated roadbed material and a rubber mat as temporary restoration members, the simulated roadbed material is formed of waste plastic, and a rubber mat is laid on the simulated roadbed material. It is what.

特開平10−37113号公報。JP-A-10-37113. 特開2004−52410号公報。Japanese Patent Application Laid-Open No. 2004-52410.

前記の仮復旧のための従来の覆工部材を使用する工法において、特許文献1,2に開示されたとおり、押圧部材・模擬路盤材とゴムマットの二重構造であり、仮復旧路面上の車両走行において、車両重量を押圧部材・模擬路盤材で受け止めるので、特に問題は生じないが、押圧部材は構造が複雑であり、また模擬路盤材も相応の製作費を必要とするため、いずれにしてもコスト上の問題がある。   In the construction method using the conventional lining member for temporary restoration, as disclosed in Patent Documents 1 and 2, it is a dual structure of a pressing member / simulated roadbed material and a rubber mat, and the vehicle on the temporary restoration road surface In traveling, the weight of the vehicle is received by the pressing member / simulated roadbed material, so there is no particular problem, but the structure of the pressing member is complicated, and the simulated roadbed material also requires a corresponding production cost. There is also a cost problem.

また施工においても、掘削幅を押圧部材や模擬路盤材の幅と対応させる必要があり、埋め戻しにおいても、転圧体や模擬路盤体の厚さ分だけ低く埋め戻しを行なう必要があり、埋め戻し高さが高くともまた低くとも段差が生じてしまうもので、その施工性の点で問題がある。   In construction, it is necessary to make the excavation width correspond to the width of the pressing member and simulated roadbed material, and in backfilling, it is necessary to backfill by a thickness corresponding to the thickness of the rolling compactor and simulated roadbed body. Even if the return height is high or low, a step is generated, which is problematic in terms of workability.

また仮復旧状態で車両走行が為されると、埋め戻した土砂は車両重量で転圧され沈下してしまう場合が多い。この沈下によって仮復旧路面に段差が生ずると、車両の快適な走行の障害となってしまうという問題もある。   In addition, when the vehicle travels in a temporarily restored state, the backfilled earth and sand are often crushed by the vehicle weight and subsided. If a step occurs on the temporarily restored road surface due to the subsidence, there is also a problem that the vehicle becomes an obstacle to comfortable driving.

そこで本発明は、簡易な仮復旧部材を採用することで施工を簡素化し、且つ車両走行に対する障害も生じ難い新規な路面仮復旧用部材及び前記部材を使用する路面仮復旧工法を提案したものである。   Therefore, the present invention proposes a new road surface temporary restoration member that simplifies the construction by adopting a simple temporary restoration member and is less likely to cause obstacles to vehicle travel, and a road surface temporary restoration method using the member. is there.

本発明(請求項1,10,12)に係る路面仮復旧用部材は、覆工マットと、ズレ止めピンと、抜け止めピンと、止着体と、固定ピンとを備えたもので、覆工マットが、適宜な堅さを備えた矩形ゴム板又は三角ゴム板或いはその他多辺形ゴム板で形成され、路面の掘削形状に対応する中央部分を厚く形成して中央厚部を設け、前記中央厚部の所定の側辺を、段差を介して裏面を抉る形状で薄く形成して側辺薄部を設けると共に、隅部に近接した中央厚部の適宜箇所に表裏貫通するピン孔を設けてなるものであり、ズレ止めピンが、筒状で且つ覆工マットのピン孔に挿着し、挿着時に覆工マット底面から適宜突出する長さとしたものであり、抜け止めピンが、前記ズレ止めピンの筒部に挿着し、挿着時にズレ止めピンの下方に適宜突出する長さとしたもので、止着体が、適宜形状のベース板部上に、覆工マットのピン孔に装着される係止突部を突設すると共に、適宜箇所に透孔を設けてなり、固定ピンが、前記止着体の透孔から打ち込み可能としたものである。 The temporary road surface restoration member according to the present invention (Claims 1, 10, and 12) includes a lining mat, a slip prevention pin, a retaining pin, a fastening body, and a fixing pin. The central thick part is formed of a rectangular rubber plate or a triangular rubber plate or other multi-sided rubber plate having appropriate rigidity, and a thick central part corresponding to the excavation shape of the road surface is provided to provide a thick central part. A thin side is formed in a shape that folds the back surface through a step to provide a thin side portion, and a pin hole penetrating the front and back is provided at an appropriate location in the central thick portion near the corner. The slip prevention pin is cylindrical and is inserted into the pin hole of the lining mat, and has a length that appropriately protrudes from the bottom surface of the lining mat at the time of insertion, and the retaining pin is the slip prevention pin. The length that is inserted into the cylinder part of the tube and protrudes appropriately below the misalignment pin when inserted. The fastening body is formed by protruding a locking projection to be mounted on the pin hole of the lining mat on the base plate portion having an appropriate shape, and providing a through hole at an appropriate location. However, it can be driven through the through hole of the fastening body.

また本発明(請求項16)に係る路面仮復旧工法は、舗装路面を掘削して所定の工事を行い、当該掘削箇所の仮復旧を行う路面仮復旧工法において、掘削箇所を路面高さ近くまで埋め戻した後、前記覆工マットを、側辺薄部端が舗装路面上に位置するように埋め戻し面を覆うように敷設し、ピン孔に筒状のズレ止めピンを、下方が覆工マット底面から適宜突出するように埋め戻し土中に打ち込むと共に、ズレ止めピンの筒部に、抜け止めピンを下方がズレ止めピンの下端から適宜突出するように埋め戻し土中に打ち込んで覆工マットを固定してなることを特徴とするものである。   Further, the road surface temporary restoration method according to the present invention (Claim 16) is a road surface temporary restoration method for excavating a paved road surface to perform predetermined construction and temporarily recovering the excavated part. After backfilling, the lining mat is laid so as to cover the backfilling surface so that the side thin edge is located on the paved road surface, and the cylindrical slip prevention pin is placed in the pin hole, and the bottom is lining Drive into the backfill soil so that it protrudes appropriately from the bottom of the mat, and squeeze the stopper pin into the backfill soil so that the bottom part protrudes appropriately from the bottom end of the stop pin. The mat is fixed.

更に本発明(請求項17)に係る路面仮復旧工法は、前記の路面仮復旧工法における覆工マットの固定に止着体と固定ピンを採用したもので、隣接する覆工マットの下面に、止着体を配置すると共に、係止突部をピン孔に装着し、舗装面のみを除去した埋め戻し範囲外の掘削地面上に突出位置させた止着体の透孔から固定ピンを土中に打ち込んで覆工マットを固定してなることを特徴とするものである。   Furthermore, the road surface temporary restoration method according to the present invention (Claim 17) employs a fastening body and a fixing pin for fixing the lining mat in the road surface temporary restoration method, and on the lower surface of the adjacent lining mat, Place the fixing body, attach the locking projection to the pin hole and remove the fixed pin from the through hole of the fixing body that protrudes on the excavation ground outside the backfill range where only the pavement surface is removed And the lining mat is fixed.

而して舗装路面を掘削して所定の工事を行った後の掘削箇所仮復旧のために掘削箇所を路面高さ近くまで埋め戻した後に、当該掘削溝の形状(平面形状)に対応して所定の形状・寸法の覆工マットを単独で或いは連繋させて前記掘削溝を覆うもので、特に側辺薄部を舗装路面状に位置させ、中央厚部を埋め戻し箇所の上方に位置させ、ズレ止めピン及び抜け止めピンを埋め戻し土中に打ち込んで覆工マットを固定したり、止着体の係止突部を覆工マットのピン孔に装着して止着体と覆工マットを連結すると共に、止着体を固定ピンで固定することで、埋め戻し箇所の仮復旧が為される。   Therefore, after excavating the paved road surface and performing the predetermined construction, the excavation part is backfilled to near the road surface for temporary restoration, and then corresponding to the shape of the excavation groove (planar shape) Covering the excavation groove by connecting a lining mat of a predetermined shape and size alone or linked, in particular, the side thin part is positioned on the paved road surface, the central thick part is positioned above the backfilling point, Insert the stopper pins and retaining pins back into the soil to fix the lining mat, or attach the locking protrusions of the fixing body to the pin holes of the lining mat to fix the fixing body and lining mat. By connecting and fixing the fastening body with a fixing pin, a temporary restoration of the backfill portion is performed.

また前記の覆工マットの固定に、請求項16記載の発明のように、ズレ止めピンと抜け止めピンを採用する場合には、ズレ止めピンは太く浅く打ち込まれ、打ち込みが容易であり且つ横方向の力が加わっても充分な耐力を備えることになる。また抜け止めピンは細径となるので容易に深く打ち込むことができる。   Further, in the case of adopting a slip-off prevention pin and a retaining pin as in the invention of claim 16 for fixing the lining mat, the slip-off prevention pin is driven thickly and shallowly, and is easy to drive and laterally. Even if this force is applied, sufficient strength is provided. Moreover, since the retaining pin has a small diameter, it can be driven deeply easily.

更に請求項17記載の発明のように、止着体と固定ピンを採用すると、ピン孔に係止突部を装着し、固定ピンを掘削溝の埋め戻し個所ではなく、非掘削個所に打ち込むことで覆工マットが堅固に固定される。   Further, when the fastening body and the fixing pin are employed as in the invention of claim 17, the locking protrusion is attached to the pin hole, and the fixing pin is driven into the non-excavation portion instead of the backfill portion of the excavation groove. The lining mat is firmly fixed.

また本発明(請求項15)に係る路面仮復旧工事用部材は、路面掘削幅に対応すると共に、種々の寸法・形状の請求項1乃至6記載の覆工マットにおける中央厚部形状と対応する形状に形成してなる複数の定規板で構成されるもので、前記定規板は、路面掘削前、掘削溝形状に合わせて適宜形状を選択して並べて敷設し、当該定規板に合わせて路面舗装面の切断並びに溝掘削を行い、当該定規板と対応する覆工マットを使用して路面仮復旧を実現するもので、掘削形状の溝の形状に対応する定規板の並列で路面仮復旧工事における使用すべき覆工マットの形状寸法が定まるもので、埋め戻し個所を覆工マットで確実に覆うことができる。   Further, the road surface temporary restoration work member according to the present invention (Claim 15) corresponds to the road surface excavation width and also corresponds to the central thick part shape in the lining mat according to Claims 1 to 6 having various dimensions and shapes. It is composed of a plurality of ruler plates formed in a shape, and the ruler plate is laid and arranged in accordance with the shape of the excavation groove before digging the road surface, and laid on the road surface according to the ruler plate Cut the surface and excavate the groove, and use the lining mat corresponding to the ruler plate to realize the temporary restoration of the road surface. In the temporary restoration work of the road surface in parallel with the ruler plate corresponding to the shape of the excavated groove The shape and dimension of the lining mat to be used are determined, and the backfill portion can be reliably covered with the lining mat.

更に覆工マットに関しては、覆工マットの四周縁に側辺薄部を設けてなると(請求項2)、主として掘削穴の仮復旧用として単体若しくは補助覆工マットとし併用されるものである。   Further, regarding the lining mat, when the thin side portions are provided at the four peripheral edges of the lining mat (Claim 2), the lining mat is mainly used as a single body or an auxiliary lining mat for temporarily recovering the excavation hole.

また請求項3に係る覆工マットは、三角形の覆工マットにおける底辺縁と頂角部分に側辺薄部を設けてなるもので、掘削溝が曲がって掘削した場合に対応できるようにしたものである。 Further, the lining mat according to claim 3 is provided with a thin side portion at the base edge and the apex portion of the triangular lining mat, and is adapted to cope with a case where the excavation groove is bent and excavated. It is.

また請求項4に係る覆工マットは、覆工マットの適宜周縁に側辺薄部を設けると共に、側辺薄部を形成しない周縁に、側辺薄部下方空隙形状と対応する連設突部を設けてなるもので、前記請求項2記載の覆工マットの補助覆工マットとして使用されるものである。   Further, the covering mat according to claim 4 is provided with a side thin part at an appropriate peripheral edge of the covering mat, and a continuous protrusion corresponding to the side thin part lower gap shape on the peripheral edge not forming the side thin part. And is used as an auxiliary lining mat for the lining mat according to claim 2.

また請求項5に係る覆工マットは、 全体が長尺矩形で、中央厚部が路面掘削溝の幅に対応し、一方側の端面に、下方部分を突出させた連結突部を設けると共に、他方側の端面に、前記連結突部と対応する連結凹部を設けてなるもので、連結突部を隣接する覆工マットの連結凹部に嵌合して覆工マットを一体に縦列連繋するもので、長い掘削溝の場合の仮復旧工事に使用される。   Further, the lining mat according to claim 5 is an elongated rectangle as a whole, the central thick part corresponds to the width of the road surface excavation groove, and provided with a connecting protrusion that protrudes the lower part on one end face, The other end face is provided with a connecting recess corresponding to the connecting protrusion, and the connecting protrusion is fitted to the connecting recess of the adjacent covering mat to integrally connect the covering mats in tandem. Used for temporary restoration work in the case of long excavation grooves.

また請求項6に係る覆工マットは、中央厚部の下面に側縁と平行な浅い凹条部を複数本設けてなるもので、仮復旧後に車両走行によって埋め戻し箇所が転圧され、前記の転圧によって埋め戻し中央厚部分が沈下することになっても、覆工マットの裏面に形成された凹条部によって簡単に下方が膨出するように湾曲して埋め戻し面に馴染むので、車両走行に支障は生じない。   The lining mat according to claim 6 is provided with a plurality of shallow concave portions parallel to the side edges on the lower surface of the central thick portion, and the backfilled portion is rolled by running the vehicle after temporary restoration, Even if the central thickness portion of the backfilling sinks due to the rolling pressure, the concave part formed on the back surface of the lining mat is curved so that the lower part bulges easily and adapts to the backfilling surface. There will be no hindrance to vehicle driving.

また請求項7及び8に係る覆工マットは、内部に補強用金属メッシュ部材を内装し、或いは表面側に硬質ゴム材で形成し、裏面側をやや軟質のゴム材の二層構造としてなるもので、補強することで覆工マットの耐久性が向上する。   Further, the lining mat according to claims 7 and 8 is provided with a reinforcing metal mesh member inside, or formed of a hard rubber material on the front surface side, and has a two-layer structure of a slightly soft rubber material on the back surface side. Thus, the durability of the lining mat is improved by reinforcing.

更に請求項9に係る覆工マットは、表面に小突起又は細突出条或いは細溝等を形成して滑り止め機能を有せしめてなるもので、復旧路面(覆工マット)上の安全歩行を図るものである。   Furthermore, the lining mat according to claim 9 is formed by forming a small protrusion, a narrow protrusion or a narrow groove on the surface to provide a non-slip function, so that a safe walking on the restoration road surface (lining mat) can be performed. It is intended.

またズレ止めピン並びに抜け止めピンを採用した場合に、特にピン孔の上方部及び両ピンの頭部形状を、所定の挿着時に、ズレ止めピン並びに抜け止めピンの頭部が覆工マット上面から非突出状態となるように形成されると共に、走行車両の重量を受け止める充分な平面面積を備える大きさに形成すると(請求項11)、仮復旧後の車両走行によって埋め戻し面の沈下と同時に両ピンも充分な車両重量を受けることになり、覆工マットの下方膨出と一緒に沈圧され、覆工マットの上面から突出することがない。   In addition, when the slip prevention pin and the retaining pin are adopted, the upper part of the pin hole and the head shape of both pins, especially the head shape of the slip stopper pin and the retaining pin, are fixed to the top surface of the lining mat when inserted. When the vehicle is formed in a non-protruding state and has a size having a sufficient plane area to catch the weight of the traveling vehicle (claim 11), the back-up surface is simultaneously depressed by the vehicle traveling after temporary restoration. Both pins also receive sufficient vehicle weight and are sunk together with the downward bulging of the lining mat and do not protrude from the upper surface of the lining mat.

また適宜形状のベース板部上に、所定の隣接覆工マットを端縁部分で連続した際に、隣接覆工マットのピン孔にそれぞれ装着される係止突部を突設した止着体を採用すると(請求項19)、隣接する覆工マットを一体化して固定することになり、車両走行に際しても覆工マット全体が抵抗することになり、マットのズレが防止される。   In addition, a fastening body provided with a protruding projection to be fitted to each pin hole of the adjacent lining mat when a predetermined adjacent lining mat is continued at the edge portion on the base plate portion having an appropriate shape. When employed (claim 19), the adjacent lining mats are integrated and fixed, and the entire lining mat resists even when the vehicle travels, thereby preventing the mat from being displaced.

本発明は上記の構成のとおりであって、舗装路面の仮復旧工事において、従前工法のような転圧体や模擬路盤体を必要とせずに、コスト上も施工上も、より簡素化できたものであり、しかも仮復旧後の車両走行による埋め戻し土砂の更なる転圧に対しても何らの支障を生じさせることなく柔軟に対応できたものである。更に舗装路面に側辺薄部を張り出させているものであるから、埋め戻し土砂のはみ出しが生じない。   The present invention is as described above, and in the temporary restoration work of the pavement road surface, it does not require a rolling element or a simulated roadbed body as in the conventional method, and can be further simplified in terms of cost and construction. In addition, it can flexibly cope with further rolling of the backfill earth and sand caused by running the vehicle after temporary restoration without causing any trouble. Furthermore, since the side thin part is projected on the pavement road surface, the backfill soil does not protrude.

本発明工法の実施形態に示した路面全体の平面図(工事前)。The top view of the whole road surface shown to embodiment of this invention construction method (before construction). 同図(定規板敷設)Figure (laying ruler plate) 同図(路面掘削時)The figure (during road excavation) 同図(覆工マット施工状態)Fig. (Construction of lining mat) 同路面仮復旧用部材(基本形状の覆工マット全体)の説明図。Explanatory drawing of the member for the road surface temporary restoration (whole mat | matte of basic shape). 同覆工マットの断面図。Sectional drawing of the lining mat | matte. 同各部材の要部の斜視図。The perspective view of the principal part of each said member. 同定規板の説明図。Explanatory drawing of an identification board. 同本発明工法の仮復旧個所の断面図(止着体使用)。Sectional drawing of the temporary restoration part of the construction method of the present invention (using a fastening body). 同図9の要部拡大図。The principal part enlarged view of FIG. 同止着体の別例図。The another example figure of the same attachment body. 同図。Figure. 同本発明工法の仮復旧個所の断面図(ズレ止めピン及び抜け止めピン使用)。Sectional drawing of the temporary restoration part of the construction method of the present invention (use of a locking pin and a retaining pin). 同覆工マットの別例の斜視図。The perspective view of another example of the same lining mat. 同マットの説明図(金属メッシュ部材使用の断面図)。Explanatory drawing of the mat (cross-sectional view using a metal mesh member). 同マットの説明図(二層構造の断面図)。Explanatory drawing of the mat (cross-sectional view of a two-layer structure). 同マットの別例の断面図。Sectional drawing of another example of the same mat.

次に本発明の実施形態について説明する。本発明の対象は、主として図1に例示した埋設配管Aの取り換え工事のように、路面Bに長尺の掘削溝Cを掘削した際の仮復旧工事(第一実施形態)、及び埋設機器(分岐管)の交換・設置や建物Dへの引込管設置のための掘削穴Eを掘削した際の仮復旧工事(第二実施形態)を対象としたものである。   Next, an embodiment of the present invention will be described. The subject of the present invention is a temporary restoration work (first embodiment) when a long excavation groove C is excavated on the road surface B, such as a replacement work of the buried pipe A illustrated in FIG. This is intended for temporary restoration work (second embodiment) when excavating the excavation hole E for replacement / installation of branch pipes and installation of lead-in pipes to the building D.

第一実施形態に使用される路面仮復旧用部材は、覆工マット1(1a,1b,1c・・・)と、ズレ止めピン2と、抜け止めピン3と、止着体4,4aと、固定ピン5と、定規板6(6a,6b,6c・・・)とで構成される。   The road surface temporary restoration member used in the first embodiment includes a lining mat 1 (1a, 1b, 1c...), A misalignment pin 2, a retaining pin 3, and fastening bodies 4 and 4a. The fixing pin 5 and the ruler plate 6 (6a, 6b, 6c...) Are configured.

覆工マット1は、従前の路面マットとして使用されている適宜な柔軟性と堅牢性を備えた矩形ゴム板であり、基本的には通常の埋設配管Aの工事において掘削される掘削溝Bより幅広の長尺矩形状であり、長尺側端間に渡って、中央厚部11は、厚くして上方への膨出形状に形成し、両側辺薄部12は、段差を介して徐々に薄く形成し、裏面における両側辺間(中央厚部裏面)を僅かに上方へ湾曲させた凹状面13とし、掘削溝Cを横断する方向全体を上方に膨出する形状にしてなる。   The lining mat 1 is a rectangular rubber plate having appropriate flexibility and robustness that has been used as a conventional road surface mat, and is basically from an excavation groove B excavated in the construction of a normal buried pipe A. It is a wide and long rectangular shape, and the central thick part 11 is thickened and formed in an upwardly bulging shape across the long side ends, and the side thin parts 12 are gradually formed through steps. It is formed in a thin shape, and a concave surface 13 is formed by slightly curving upwards between the sides on the back surface (back surface of the central thick portion), and the entire direction crossing the excavation groove C bulges upward.

また覆工マット1の表面は、細かな突起や突条或いは細溝等を設けて滑り止め粗面14に形成し、裏面には側辺と平行な浅い半円断面形状の凹条部15を複数本設け、更に適宜箇所に表裏貫通するピン孔16を設けてなるものである。また特に端縁17を段差の少ない鋭角形状に形成してなる。   Further, the surface of the lining mat 1 is formed on the rough surface 14 with a fine protrusion, a ridge, or a narrow groove, and the concave portion 15 having a shallow semicircular cross section parallel to the side is formed on the back surface. A plurality of pin holes 16 are provided, and pin holes 16 penetrating the front and back are provided at appropriate places. In particular, the edge 17 is formed in an acute angle shape with few steps.

更に一方側の端面に、下方部分を突出させた連結突部18を設けると共に、他方側の端面に、前記連結突部18と対応する連結凹部19を設けてなる。   Further, a connecting protrusion 18 having a lower portion protruding is provided on one end face, and a connecting recess 19 corresponding to the connecting protrusion 18 is provided on the other end face.

覆工マット1は、前記の基本構成を備えた上で、所定の寸法・形状によって複数形成しておくもので、掘削溝Cの溝長に対応できるように長尺覆工マット1a、短尺覆工マット1bの矩形マットの他、掘削方向の変更個所を覆うための変形覆工マットとして、台形覆工マット1c,三角覆工マット1d、更には掘削溝Cのコーナー個所の適宜な範囲を覆う形状とした矢印型覆工マット1eを形成し、各覆工マット1は、後述する掘削溝Cの形状と一致する各定規板6(6a,6b,6c,6d)と略一致(定規板の幅方向より僅かに狭い幅)する中央厚部11を設けているものである。   The lining mat 1 is provided with the above basic configuration, and a plurality of lining mats 1 are formed in accordance with predetermined dimensions and shapes. The long lining mat 1a and the short covering are provided so as to correspond to the groove length of the excavation groove C. In addition to the rectangular mat of the work mat 1b, as a modified lining mat for covering the place where the excavation direction is changed, the trapezoidal lining mat 1c, the triangular lining mat 1d, and the appropriate range of the corner portion of the excavation groove C are covered. An arrow-type lining mat 1e having a shape is formed, and each lining mat 1 substantially coincides with each ruler plate 6 (6a, 6b, 6c, 6d) that matches the shape of the excavation groove C described later (the ruler plate). A central thick portion 11 having a width slightly narrower than the width direction) is provided.

勿論前記の変形覆工マット1c,1d,1eは、必ずしも全て準備する必要はなく、例えば三角覆工マット1dを、斜辺角度の異なる数種類を準備しこれを組み合わせることで、種々の屈曲掘削溝に対応でき、同様のことは、台形覆工マット1cにも、矢印型覆工マット1eにも言える。   Of course, it is not always necessary to prepare the deformed lining mats 1c, 1d, and 1e. For example, by preparing several types of triangular lining mats 1d having different hypotenuse angles and combining them, various bending excavation grooves can be formed. The same can be said for the trapezoidal lining mat 1c and the arrow type lining mat 1e.

定規板6は、例えば所定の掘削溝幅(基準幅600mm、400mmの2種類)で、各々掘削溝長を2mとして長尺覆工マット1aと対応する長尺定規板6a(図8イ)、掘削溝長を1m,0.5m等とした複数の寸法の異なる短尺覆工マット1bと対応する短尺定規板6b(図8ロ)、更に折曲して掘削される個所に使用される台形覆工マット1c及び三角覆工マット1dに対応する台形定規板6c、並びに三角覆工マット1d及び矢印型覆工マット1eに対応する矢印型定規板6dを形成しておくものである(図8ハ)。 The ruler plate 6 is, for example, a predetermined excavation groove width (two types of reference widths 600 mm and 400 mm), each of which has a excavation groove length of 2 m and corresponds to the long lining mat 1a (FIG. 8a), Short ruler plate 6b (FIG. 8B) corresponding to a plurality of short lining mats 1b having different digging groove lengths of 1 m, 0.5 m, etc., and a trapezoidal cover used for a portion to be further bent and excavated A trapezoidal ruler plate 6c corresponding to the work mat 1c and the triangular lining mat 1d, and an arrow ruler plate 6d corresponding to the triangular lining mat 1d and the arrow lining mat 1e are formed (FIG. 8C). ).

台形覆工マット1c、三角覆工マット1d、矢印型覆工マット1eと、台形定規板6c及び矢印型定規板1dの組み合わせ関係は、図8(ニ)(ホ)(へ)に示すとおりである。   The combinations of the trapezoidal lining mat 1c, the triangular lining mat 1d, the arrow type lining mat 1e, the trapezoidal ruler plate 6c, and the arrow type ruler plate 1d are as shown in FIGS. is there.

また前記の掘削溝Cに使用する覆工マット1の変形例として、連結突部18を備えるが連結凹部19を備えない溝端用覆工マット1Aや、逆に連結突部18を備えず連結凹部19を備える溝端用覆工マット等も予め形成しておき、溝端部分には、前記溝端用覆工マットを使用するようにする。   Further, as a modification of the lining mat 1 used for the excavation groove C, a groove end lining mat 1A having a connecting projection 18 but no connecting recess 19, or conversely a connecting recess having no connecting projection 18 is provided. A groove end covering mat or the like having 19 is formed in advance, and the groove end covering mat is used for the groove end portion.

尚前記覆工マット1は、上面を平らにし、中央厚部11を下方への膨出形状に形成し、両側辺薄部12は、その先端(側端)部分のみが傾斜面に形成したものでも良い。   The lining mat 1 has a flat upper surface, the central thick portion 11 is formed in a bulging shape downward, and the thin side portions 12 on both sides are formed on an inclined surface only at the tip (side end) portion. But it ’s okay.

またピン孔16は、掘削溝Cの範囲内に設けたもので、その上方部分は、後述するズレ止めピン2や抜け止めピン3の頭部21,31や、止着体4,4aの係止突部42の頭部42aが埋め込み状態で収納されると共に、充分な露出面積を備える形状とするものである。   Further, the pin hole 16 is provided in the range of the excavation groove C, and an upper portion of the pin hole 16 is engaged with heads 21 and 31 of a later-described misalignment pin 2 and retainer pin 3 and fixing members 4 and 4a. The head 42a of the stop protrusion 42 is housed in an embedded state and has a shape with a sufficient exposed area.

またズレ止めピン2は筒状に形成され、頭部21が前記ピン孔16の上方部分と対応するラッパ状の開傘形状で、その全長は、覆工マット1のピン孔16に挿着し、挿着時に覆工マット1の底面から適宜突出長(後述するとおり車両走行時に車両から受ける横方向のズレ作用させる力に対して覆工マット1が横ズレしないような充分な長さで、且つ転圧した埋め戻し土中に対して打ち込みが容易に為される程度の長さ)を有するような長さとしたものである。   Further, the misalignment pin 2 is formed in a cylindrical shape, and the head portion 21 has a trumpet-shaped opening shape corresponding to the upper portion of the pin hole 16, and its entire length is inserted into the pin hole 16 of the lining mat 1. , A length that appropriately protrudes from the bottom surface of the lining mat 1 at the time of insertion (a length sufficient to prevent the lining mat 1 from being laterally displaced with respect to a force acting on the lateral displacement received from the vehicle when the vehicle is traveling, as described later, In addition, the length is such that it has a length that can be easily driven into the rolled backfill soil.

抜け止めピン3は、前記のズレ止めピン2の筒部に挿着し、挿着時に頭部31がズレ止めピン2の頭部21内にぴったりと納まる形状で、且つズレ止めピン2の下端からに適宜長さ突出する全長を備えたものである。   The retaining pin 3 is inserted into the cylindrical portion of the misalignment pin 2, and the head 31 fits in the head 21 of the misalignment pin 2 when being inserted, and the lower end of the misalignment pin 2. It is provided with a full length that protrudes appropriately.

止着体4は、ベース板部41の上面に係止突部42を縦列して突設し、所定箇所に透孔43を穿設したもので、係止突部42の突設位置は、後述する掘削溝Cに添って連繋するために覆工マット1の連結突部18と連結凹部19を嵌合した状態における隣接覆工マット1のピン孔16の距離に対応するように設けたものである。   The fixing body 4 is formed by vertically projecting locking projections 42 on the upper surface of the base plate portion 41, and through holes 43 are formed at predetermined locations. The protruding position of the locking projection 42 is as follows. Provided so as to correspond to the distance between the pin holes 16 of the adjacent lining mat 1 in a state where the connecting projection 18 and the connecting recess 19 of the lining mat 1 are fitted in order to be connected along the excavation groove C described later. It is.

また透孔43は、係止突部42から側方に張り出した位置で、掘削溝Cの掘穿に際しての路面Bの舗装除去部分で、且つ非掘削地面(露出地面F)となる範囲に設けるものであり、固定ピン5は、前記の透孔43から露出地面Fに対して打ち込んだ際に、覆工マット1を充分に固着できる耐力を備える長さとしたものである。   Further, the through hole 43 is provided at a position projecting laterally from the locking projection 42 in a range where the pavement removal portion of the road surface B when the excavation groove C is excavated and the non-excavation ground (exposed ground F). The fixing pin 5 has such a length as to have a strength capable of sufficiently fixing the covering mat 1 when driven into the exposed ground F from the through hole 43.

尚止着体の別部材として図12に例示するように、矩形のベース板部41aの上面に係止突部42を縦列して突設し、透孔43を設けていない止着体4aも採用できる。   In addition, as illustrated in FIG. 12 as another member of the fastening body, the fastening body 4a in which the locking projections 42 are projected in a row on the upper surface of the rectangular base plate portion 41a and the through hole 43 is not provided is also provided. Can be adopted.

然して本発明の路面仮復旧工法(第一実施形態)は、舗装路面Bを掘削(掘削溝C)し、掘削溝内の配管Aを取り替えたり設置したりする等の所定の工事を行うに際して、一日の工事終了時に前記掘削溝Cが車両走行や歩行者の障害とならないようにする仮復旧に、前記の仮復旧用部材を使用して行うものである。   However, the road surface temporary restoration method (first embodiment) according to the present invention performs the predetermined construction such as excavating the paved road surface B (excavation groove C) and replacing or installing the pipe A in the excavation groove. The temporary restoration member is used for temporary restoration so that the excavation groove C does not become an obstacle to vehicle travel or pedestrians at the end of a day of construction.

具体的には、掘削溝Cを掘削するために、最初に舗装路面Bの剥離が必要であり、この剥離作業に際しては、路面カッターで切り込みを入れるものであるが、この切り込みに際して、前記した定規板6を掘削溝Cに合わせ、特に掘削溝Cを埋設配管Aの埋設位置に合わせ、溝を屈曲して掘削する必要がある場合などは、寸法・形状の異なる定規板6を組み合わせて並べて路面上に配置固定し(図2)、この路面上の定規板に合わせて路面カッターを移動させて所定の切り込みを入れ、舗装面を剥離し、露出地盤を配管Aの埋設個所まで掘り下げる。   Specifically, in order to excavate the excavation groove C, it is necessary to first peel off the paved road surface B. At the time of this peeling operation, a cut is made with a road surface cutter. When the plate 6 is aligned with the excavation groove C, especially when the excavation groove C is aligned with the embedding position of the embedding pipe A and it is necessary to bend and excavate the groove, the ruler plates 6 having different sizes and shapes are combined and arranged. Arranged and fixed above (FIG. 2), a road surface cutter is moved in accordance with the ruler plate on the road surface, a predetermined cut is made, the pavement surface is peeled off, and the exposed ground is dug down to the buried portion of the pipe A.

路面B部分の剥離された範囲内において、両側縁に非掘削部分Fを残して掘削溝Cを掘削し(図3)、仮復旧時に掘削溝Cに土砂(通常は砂のみを使用する)Gを埋め戻して、埋め戻し箇所を前記の覆工マット1で覆うもので、覆工マット1の裏面の凹状面13の形状に合わせて僅か盛り上がる状態として盛り付ける。   Excavation groove C is excavated within the range where road surface B is peeled, leaving non-excavation portions F on both side edges (FIG. 3), and earth and sand (usually using only sand) G in excavation groove C during temporary restoration The backfill portion is covered with the above-mentioned lining mat 1 and is placed in a slightly raised state according to the shape of the concave surface 13 on the back surface of the lining mat 1.

掘削溝Cを土砂G等で埋め戻した後には、埋め戻し面に覆工マット1を被せるもので、特に側辺薄部12が舗装路面B上に位置するようにする。   After the excavation groove C is backfilled with earth and sand G or the like, the backfill surface is covered with the lining mat 1, and in particular, the side thin portion 12 is positioned on the paved road surface B.

特にこの覆工マット1によって埋め戻し面を覆う際には、前記の定規板6を組み合わせて掘削溝Cが掘削されているので、前記の路面カッター作業に使用した定規板6a,6b,6c・・・の形状・寸法に対応した覆工マット1a,1b,1c・・・を使用すると、埋め戻し掘削溝Cは確実に覆工マット1で覆われることになる。即ち覆工マット1を使用する仮復旧工法は、定規板6の使用によってマット間の隙間や、重なりが生じない状態での完全被覆を実現できることになる。   In particular, when the backfill surface is covered with the lining mat 1, since the excavation groove C is excavated by combining the ruler plate 6, the ruler plates 6a, 6b, 6c used for the road surface cutter work are used. When the lining mats 1a, 1b, 1c,... Corresponding to the shapes and dimensions are used, the backfill excavation groove C is surely covered with the lining mat 1. That is, in the temporary restoration method using the lining mat 1, the use of the ruler plate 6 makes it possible to realize complete covering in a state where there is no gap or overlap between the mats.

言い換えるならば定規板6の完全敷設可能な場合には、仮復旧時の覆工マット1による完全被覆が可能であるから、掘削溝Cの掘削時に、定規板6の組み合わせが、使用する覆工マット1の使用を決定する。   In other words, when the ruler plate 6 can be completely laid, it can be completely covered with the lining mat 1 at the time of temporary restoration. Therefore, when the excavation groove C is excavated, the combination of the ruler plates 6 is used as a lining. Determine the use of mat 1.

この埋め戻し面を覆うように敷設する覆工マット1は、隣接する覆工マット1の連結突部18と連結凹部19を嵌合した状態で一体に連繋していくものであり、覆工マット1の固定手段として、ズレ止めピン2と抜け止めピン3を使用する場合と、止着体4と固定ピン5を使用する場合があり、前者は、埋め戻し個所の端に位置する覆工マット1の固定やその他適宜箇所に使用され、後者は、隣接覆工マット1の連繋個所に使用される。   The lining mat 1 laid so as to cover the backfill surface is integrally connected in a state where the connecting projections 18 and the connecting recesses 19 of the adjacent lining mats 1 are fitted, and the lining mat The fixing means 1 includes the case where the misalignment pin 2 and the retaining pin 3 are used, and the case where the fixing body 4 and the fixing pin 5 are used. The former is a lining mat located at the end of the backfilling place. 1 is used for fixing and other appropriate places, and the latter is used for connecting portions of adjacent lining mats 1.

ズレ止めピン2と抜け止めピン3を使用する場合には、ズレ止めピン2をピン孔16から埋め戻し土砂Gに打ち込み、更に抜け止めピン3をズレ止めピン2の筒状内部から埋め戻し土砂Hに打ち込み、覆工マット1を固定するものである。尚抜け止めピン3が不要であると認められた箇所には、ズレ止めピン2の筒部を塞ぐ盲蓋体を装着するようにしても良い。   When using the slip prevention pin 2 and the retaining pin 3, the slip retaining pin 2 is driven into the backfill sand G from the pin hole 16, and the backstop pin 3 is backfilled from the cylindrical inside of the slip prevention pin 2. It is driven into H and the lining mat 1 is fixed. In addition, you may make it mount | wear with the blind cover body which block | closes the cylinder part of the slippage prevention pin 2 in the location recognized that the retaining pin 3 is unnecessary.

止着体4と固定ピン5を使用する場合は、隣接する覆工マット1の下面に、止着体4を位置させると共に、縦列する係止突部42を隣接する覆工マット1の各ピン孔16に挿通して係止し、ベース板部41の張出部を非掘削部分Fに位置させて、透孔43から固定ピン5を打ち込むことで、覆工マット1は止着体4を介して固定されることになる(図9,10参照)。   When the fastening body 4 and the fixing pin 5 are used, the fastening body 4 is positioned on the lower surface of the adjacent lining mat 1, and each pin of the adjacent lining mat 1 is provided with the engaging protrusions 42 arranged in a row. The lining mat 1 attaches the fastening body 4 by inserting and fixing to the hole 16, positioning the protruding portion of the base plate portion 41 in the non-excavated portion F, and driving the fixing pin 5 through the through-hole 43. (See FIGS. 9 and 10).

また車両走行が著しく少ない個所のように覆工マット1のズレが生じ難い個所は、止着体4aを使用して隣接マットの連結を行うようにしても良い。   Further, in places where the running of the lining mat 1 is unlikely to occur, such as where the vehicle travels extremely little, the adjacent mats may be connected using the fastening body 4a.

このように埋設配管工事における掘削溝Cの仮復旧において、掘削溝Cは土砂Gで埋め戻されると共に、覆工マット1で覆うことになり、仮復旧にアスファルト材を使用する必要が無く、車両走行に対する耐久力も充分で、マット下に転圧体や模擬路盤体を敷設する必要がない。   Thus, in the temporary restoration of the excavation groove C in the buried piping work, the excavation groove C is backfilled with earth and sand G and covered with the lining mat 1, and it is not necessary to use asphalt material for the temporary restoration. It has sufficient durability against running, and there is no need to lay a rolling element or simulated roadbed under the mat.

特に覆工マット1の固定作業においては、大径のズレ止めピン2は浅く打ち込まれ、細径の抜け止めピン3は深く打ち込むことになるので、容易な施工で充分な耐力を備える覆工マット1の固定を実現できたものである。   Particularly in the fixing work of the lining mat 1, the large-diameter misalignment pin 2 is driven shallowly and the small-diameter retaining pin 3 is driven deeply, so that the lining mat has sufficient strength with easy construction. 1 can be fixed.

また止着体4を使用する覆工マット1の固定作業においては、隣接覆工マット1が連結突部18と連結凹部19との嵌合による連繋と相まって、更に止着体4によって隣接する覆工マット1が連結されるので、覆工マット1全体を一体化することができ、より効果的に覆工マット1の固定を実現できる。   Further, in the fixing work of the lining mat 1 using the fastening body 4, the adjacent lining mat 1 is coupled with the connection by the fitting of the connecting projection 18 and the connecting recess 19, and further, the covering covering adjacent by the fastening body 4 is used. Since the work mat 1 is coupled, the entire lining mat 1 can be integrated, and the lining mat 1 can be more effectively fixed.

更に本発明においては、覆工マット1が側辺薄部12を薄く形成していることによって、前記の中央厚部11の沈下状態に移行しても、覆工マット1の端縁17が舗装路面Cから跳ね上がることがなく、車両走行に支障が生ずることがなく、且つ埋め戻し土砂Gのはみ出しも生じない。   Furthermore, in the present invention, since the lining mat 1 is formed with the thin side portions 12, the edge 17 of the lining mat 1 is paved even when the central thick portion 11 is shifted to the subsidence state. The vehicle does not jump up from the road surface C, the vehicle traveling is not hindered, and the backfill earth and sand G does not protrude.

また覆工マット1の中央厚部11を膨出形状に形成したり、覆工マット1の中央厚部11の裏面に凹条部15を形成することで、仮復旧後の車両の覆工マット1上走行に際して、埋め戻し土砂Gに対して更なる転圧が加えられ、埋め戻し土砂Gが沈下してしまっても、本工法の採用によってこの沈下によって派生する問題は解決されるものである。更に雨天に際しては、中央厚部11が膨出しているので、雨水が覆工マット1上に滞留することがない。   Further, by forming the central thick portion 11 of the lining mat 1 into a bulging shape or by forming the concave strip portion 15 on the back surface of the central thick portion 11 of the lining mat 1, the lining mat of the vehicle after temporary restoration 1) Even when the backfilling earth and sand G is subjected to further rolling pressure and the backfilling earth and sand G sinks when traveling on 1, the problem derived from this settlement is solved by adopting this construction method. . Further, when it rains, the central thick portion 11 swells, so that rainwater does not stay on the lining mat 1.

またズレ止めピン2及び抜け止めピン3を採用した場合には、頭部露出面積を相応に大きくしているので、車両走行による車両重量を受けた場合に、覆工マット1と共に下方に押し付けられることになり、覆工マット1の中央厚部11と共に沈圧され、当該状態を維持することになり、覆工マット1が沈下しても、その上面から突出することがない。   Further, when the misalignment pin 2 and the retaining pin 3 are employed, the head exposed area is correspondingly increased, so that when the vehicle weight due to vehicle travel is received, it is pressed downward together with the lining mat 1. That is, the pressure is reduced together with the central thick portion 11 of the lining mat 1 and the state is maintained, and even if the lining mat 1 sinks, it does not protrude from the upper surface.

更に止着体4を採用した場合には、隣接覆工マット1の連繋によって一部の覆工マット1に対して、車両走行によって横ズレ方向の力が加わったとしても、連繋された覆工マット1全体で対応することになり、より耐久力が増加するものである。   Further, when the fastening body 4 is employed, even if a force in the lateral displacement direction is applied to a part of the lining mats 1 due to the linking of the adjacent lining mats 1, the linked linings The mat 1 as a whole responds, and the durability increases.

このように、仮復旧路面上(覆工マット1上)を車両が走行して、本復旧に至るまでの間に、埋め戻し土砂の車両走行による転圧がなされたり、ズレ方向の力が加わっても、何ら支障なく安全に車両を走行させることができたものである。   In this way, rolling of the backfill earth and sand is carried out by the vehicle running on the temporary restoration road surface (on the lining mat 1) until the main restoration, or a force in the displacement direction is applied. However, the vehicle was able to run safely without any trouble.

更に覆工マット1の表面を滑り止め粗面14に形成し、両側辺薄部12の端縁断面を鋭角形状に形成してなると、特に歩道部分となる仮復旧に使用した場合には、マット側辺縁の段差によって歩行者が躓く虞が少なくなり、またマット表面で滑る危険性も少なくなり、安全な歩行が実現するものである。   Further, when the surface of the lining mat 1 is formed on the rough surface 14 to prevent slipping and the edge cross section of the both side thin portions 12 is formed into an acute angle shape, the mat is used particularly for temporary restoration of a sidewalk portion. The step of the side edge reduces the risk of pedestrians traveling and reduces the risk of slipping on the mat surface, thus realizing safe walking.

また路面Bに長い溝ではなく掘削穴Eを形成する配管工事における仮復旧工事(第二実施形態)に使用される路面仮復旧用部材は、覆工マット1B,1Cと、前記第一実施形態と同様に使用されるズレ止めピン2及び抜け止めピン3の組み合わせや、図11に例示した止着体4b及び固定ピン5とで構成される。   Further, the road surface temporary restoration member used in the temporary restoration work (second embodiment) in the piping work for forming the excavation hole E instead of the long groove on the road surface B is the lining mats 1B and 1C and the first embodiment. And a combination of a locking pin 2 and a retaining pin 3 used in the same manner as described above, and a fixing body 4b and a fixing pin 5 illustrated in FIG.

覆工マット1Bは、前記した覆工マット1と同様な材質で形成されるものであるが、中央厚部11aの四周に、段差を介して側辺薄部12aを設けたもので、表面には細かな突起や突条或いは細溝等を設けて滑り止め粗面(図は小突起を形成して実現している)14aに形成し、裏面は僅かに膨出させてなり、中央厚部11aの四隅部分に表裏貫通するピン孔16を設けてなるものである。
The lining mat 1B is formed of the same material as the lining mat 1 described above, but is provided with side thin portions 12a on the four sides of the central thick portion 11a through a step, and on the surface. Is formed on the rough surface 14a (provided by forming small protrusions) with fine protrusions, protrusions or grooves, and the back surface is slightly bulged. Pin holes 16 that pass through the front and back are provided at the four corners of 11a.

また前記の覆工マット1Bに連繋して使用される覆工マット1Cは、三周縁には覆工マット1Bと同様の側辺薄部12aを設けると共に、側辺薄部12aを形成しない周縁に、覆工マット1Bの側辺薄部12aの下方空隙形状と対応する連設突部111を設けてなるものである。   Further, the lining mat 1C used in connection with the lining mat 1B is provided with a side thin portion 12a similar to the lining mat 1B at the three peripheral edges, and at the peripheral edge where the side thin portions 12a are not formed. The continuous protrusion 111 corresponding to the lower gap shape of the side thin part 12a of the lining mat 1B is provided.

尚覆工マット1Bは、中央厚部11aの内部に金属メッシュ部材112を内装して補強したり、表面側に硬質ゴム材113で形成し、裏面側をやや軟質のゴム材114の二層構造として、強度並びに耐久性を高めているものである。勿論前記し第一実施形態の覆工マット1,1Aにおいても適用できるものである。   The lining mat 1B has a two-layer structure in which a metal mesh member 112 is internally reinforced inside the central thick portion 11a, or a hard rubber material 113 is formed on the front surface side, and a soft rubber material 114 is formed on the back surface side. As mentioned above, the strength and durability are enhanced. Of course, the present invention can also be applied to the lining mats 1 and 1A of the first embodiment.

また止着体4bは、図11に例示するようにベース板部41bの上面の一方側に係止突部42bを突設し、他方側に透孔43aを穿設したもので、係止突部42bと透孔43aの位置関係は、前記した止着体4の係止突部42と透孔43と同様である。   Further, as shown in FIG. 11, the fastening body 4b has a locking projection 42b protruding on one side of the upper surface of the base plate portion 41b and a through hole 43a formed on the other side. The positional relationship between the portion 42 b and the through hole 43 a is the same as that of the locking protrusion 42 and the through hole 43 of the above-described fastening body 4.

而して第二実施形態の路面仮復旧工法は、舗装路面Bに矩形の掘削穴Eを掘削し、所定の工事の後に掘削穴Eに土砂Gを埋め戻して、埋め戻し箇所を前記の覆工マット1B,1Cで覆うもので、掘削穴Eが単一矩形穴の場合には、1枚の覆工マット1Bで埋め戻し個所を覆い、前記したズレ止めピン2と抜け止めピン3を使用して覆工マット1Bを固定し、或いは止着体4bと固定ピン5を使用して固着するもので、固着手段(ピン等の打ち込み)は前記した第一実施形態と同様である。   Thus, in the road surface temporary restoration method according to the second embodiment, a rectangular excavation hole E is excavated on the paved road surface B, the earth and sand G is backfilled in the excavation hole E after predetermined construction, and the backfill portion is covered with the above-described covering. When the excavation hole E is a single rectangular hole and covered with the work mats 1B and 1C, the backfilling portion is covered with one cover mat 1B, and the above-described misalignment pin 2 and retaining pin 3 are used. Then, the lining mat 1B is fixed, or is fixed by using the fixing body 4b and the fixing pin 5, and the fixing means (driving of the pin or the like) is the same as in the first embodiment.

また掘削穴Eが建物Dへの引込管設置のように短い溝穴を連続して掘削した場合に、前記の1枚の覆工マット1で、埋め戻し個所の被覆ができない場合には、連設突部111を備えた覆工マット1Cを使用するもので、連結突部111を覆工マット1Bの側辺薄部12aの下方に位置し、上面(滑り止め面)が連続して平らになるように連設し、各々の覆工マット1B,1Cを固定するものである。勿論更に覆工マット1Cを連続敷設することも可能である。   In addition, when the excavation hole E continuously excavates a short slot, as in the case of a lead-in pipe installed in the building D, if the above-mentioned one lining mat 1 cannot cover the backfill portion, continuous The lining mat 1C provided with the projecting protrusion 111 is used, the connecting protrusion 111 is positioned below the side thin portion 12a of the lining mat 1B, and the upper surface (antislip surface) is continuously flattened. In this way, the lining mats 1B and 1C are fixed. Of course, it is also possible to continuously lay the lining mat 1C.

1,1A,1B,1C 覆工マット
1a 長尺覆工マット
1b 短尺覆工マット
1c 台形覆工マット
1d 三角覆工マット
1e 矢印型覆工マット
11,11a 中央厚部
111 連設突部
112 金属メッシュ部材
113 硬質ゴム材
114 軟質ゴム材
12,12a 側辺薄部
13 凹状面
14 滑り止め粗面
15 凹条部
16 ピン孔
17 端縁
18 連結突部
19 連結凹部
2 ズレ止めピン
21 頭部
3 抜け止めピン
31 頭部
4,4a,4b 止着体
41,41a,41b ベース板部
42,42a,42b 係止突部
43,43a 透孔
5 固定ピン
6 定規板
6a 長尺定規
6b 短尺定規板
6c 台形定規板
6d 矢印型定規板
A 埋設配管
B 路面
C 掘削溝
D 建物
E 掘削穴
F 非掘削部分(露出地面)
G 土砂(埋め戻し土砂)
1, 1A, 1B, 1C Lined mat 1a Long lined mat 1b Short lined mat 1c Trapezoid lined mat 1d Triangular lined mat 1e Arrow type lined mat 11, 11a Center thick part 111 Continuous protrusion 112 Metal Mesh member 113 Hard rubber material 114 Soft rubber material 12, 12a Thin side portion 13 Concave surface 14 Non-slip rough surface 15 Concave strip portion 16 Pin hole 17 Edge 18 Connecting protrusion 19 Connecting recess 2 Misalignment pin 21 Head 3 Retaining pin 31 Head 4, 4a, 4b Fastening body 41, 41a, 41b Base plate portion 42, 42a, 42b Locking projection 43, 43a Through hole 5 Fixing pin 6 Ruler plate 6a Long ruler 6b Short ruler plate 6c Trapezoidal ruler plate 6d Arrow type ruler plate A Buried pipe B Road surface C Excavation groove D Building E Excavation hole F Non-excavated part (exposed ground)
G earth and sand (backfill earth and sand)

Claims (20)

適宜な堅さを備えた矩形ゴム板又は三角ゴム板或いはその他多辺形ゴム板で形成され、路面の掘削形状に対応する中央部分を厚く形成して中央厚部を設け、前記中央厚部の所定の側辺を、段差を介して裏面を抉る形状で薄く形成して側辺薄部を設けると共に、隅部に近接した中央厚部の適宜箇所に表裏貫通するピン孔を設けてなる覆工マットからなる路面仮復旧用部材。 It is formed of a rectangular rubber plate or a triangular rubber plate or other multi-sided rubber plate with appropriate rigidity, and a thick central portion corresponding to the excavation shape of the road surface is formed to provide a central thick portion. Covering with a predetermined side that is thinly formed in a shape that folds the back surface through a step to provide a thin side, and a pin hole that penetrates the front and back at an appropriate location in the central thick part near the corner Road surface temporary restoration member made of mat. 矩形の覆工マットの四周縁に側辺薄部を設けてなる請求項1記載の路面仮復旧部材。 Rectangular lining formed by providing the lateral side thin portions to the four peripheral edges of the mat according to claim 1, wherein the road surface provisional restoration element. 三角形の覆工マットにおける底辺縁と頂角部分に側辺薄部を設けてなる請求項1記載の路面仮復旧部材。 Claim 1 road temporary restoration member according to the base edge and apex angle portion of the lining mat formed by providing the side edge thin portion of the triangle. 覆工マットの適宜周縁に側辺薄部を設けると共に、側辺薄部を形成しない周縁に、側辺薄部下方空隙形状と対応する連設突部を設けてなる請求項1又は3記載の路面仮復旧部材。 4. The side lining mat is provided at an appropriate periphery of the lining mat, and a continuous projection corresponding to the side edge thin portion lower gap shape is provided at the periphery not forming the side edge thin part. road surface temporary restoration member. 覆工マットの中央厚部における溝を横切る方向の端縁の一方側に、下方部分を突出させた連結突部を設けると共に、他方側に、前記連結突部と対応する連結凹部を設けてなる請求項1又は3記載の路面仮復旧用部材。   A connecting projection having a lower portion projecting is provided on one side of an edge in a direction crossing the groove in the central thick portion of the lining mat, and a connecting recess corresponding to the connecting projection is provided on the other side. The road surface temporary restoration member according to claim 1 or 3. 全体が長尺矩形で、中央厚部の下面に長尺側縁と平行な浅い凹条部を複数本設けてなる請求項1,2,4,5記載の何れかの路面仮復旧用部材。   The road surface temporary restoration member according to any one of claims 1, 2, 4, and 5, wherein the member is a long rectangle as a whole, and a plurality of shallow concave portions parallel to the long side edge are provided on the lower surface of the central thick portion. 内部に補強用金属メッシュ部材を内装してなる請求項1乃至6記載のれかの路面仮復旧用部材。 What Re of road temporary restoration member formed by interior reinforcing metal mesh member internally claims 1 to 6, wherein. 表面側に硬質ゴム材で形成し、裏面側をやや軟質のゴム材の二層構造としてなる請求項1乃至7記載のれかの路面仮復旧用部材。 Is formed on the surface side of a hard rubber material, the back side somewhat what Re of road temporary restoration member of claims 1 to 7, wherein comprising a two-layer structure of the rubber material soft. 表面に小突起又は細突出条或いは細溝等を形成して滑り止め機能を有せしめてなる請求項1乃至7記載れかの路面仮復旧用部材。 Small projections or fine protruding strip or to form a fine groove or the like formed by allowed have a non-slip function claims 1 to 7, wherein several Re of road temporary recovery member to the surface. 請求項1乃至9記載の何れかの覆工マットと、前記覆工マットにおけるピン孔に挿着し、挿着時に覆工マット中央厚部の底面から適宜突出する長さとした筒状のズレ止めピンと、前記ズレ止めピンの筒部に挿着し、挿着時にズレ止めピンの下方に適宜突出する長さとした抜け止めピンとからなる路面仮復旧用部材。   A lining mat according to any one of claims 1 to 9, and a cylindrical slip stopper that is inserted into a pin hole in the lining mat and has a length that appropriately protrudes from the bottom surface of the central portion of the lining mat at the time of insertion. A road surface temporary restoration member comprising a pin and a retaining pin that is inserted into a cylindrical portion of the misalignment pin and protrudes appropriately below the misalignment pin when being inserted. ピン孔の上方部及び両ピンの頭部形状を、所定の挿着時に、ズレ止めピン並びに抜け止めピンの頭部が覆工マット上面から非突出状態となるように形成すると共に、走行車両の重量を受け止める充分な平面面積を備える大きさに形成してなる請求項10記載の路面仮復旧用部材。   The upper portion of the pin hole and the head shape of both pins are formed such that the heads of the slip prevention pin and the retaining pin are not protruded from the upper surface of the lining mat at the time of predetermined insertion. The road surface temporary restoration member according to claim 10, wherein the member is formed in a size having a sufficient plane area for receiving weight. 請求項1乃至9記載の何れかの覆工マットと、適宜形状のベース板部上に、覆工マットのピン孔に装着される係止突部を突設すると共に、適宜箇所に透孔を設けてなる止着体と、前記透孔から打ち込み可能とした固定ピンとを備えてなる路面仮復旧用部材。   A locking projection to be mounted on a pin hole of the lining mat is provided on the lining mat according to any one of claims 1 to 9 and an appropriately shaped base plate portion, and a through hole is provided at an appropriate location. A road surface temporary restoration member comprising: a fastening body provided; and a fixing pin that can be driven through the through hole. 請求項1乃至9記載の何れかの覆工マットと、適宜形状のベース板部上に、所定の隣接覆工マットを端縁部分で連続した際に、隣接覆工マットのピン孔にそれぞれ装着される係止突部を突設した止着体とを備えてなる路面仮復旧用部材。   The lining mat according to any one of claims 1 to 9 and an appropriately shaped base plate portion, each of which is attached to a pin hole of the adjacent lining mat when the predetermined adjacent lining mat is continuous at the edge portion. A temporary road surface restoration member comprising a fastening body provided with a projecting locking projection. ベース板部を、縦列する係止突部の側方側に張り出させて、当該張出面に透孔を設けてなる止着体と、前記透孔から打ち込み可能とした固定ピンとを備えてなる請求項13記載の路面仮復旧用部材。   A base plate portion is extended to the side of the vertical locking projections, and is provided with a fastening body provided with a through hole on the protruding surface, and a fixing pin that can be driven from the through hole. The road surface temporary restoration member according to claim 13. 路面掘削幅に対応すると共に、種々の寸法・形状の請求項1乃至6記載の覆工マットにおける中央厚部形状と対応する形状に形成してなる複数の定規板で構成される路面仮復旧工事用部材   The road surface temporary restoration work corresponding to the road excavation width and composed of a plurality of ruler plates formed in a shape corresponding to the central thick part shape in the lining mat of various sizes and shapes according to claims 1 to 6. Materials 舗装路面を掘削して所定の工事を行い、当該掘削箇所の仮復旧を行う路面仮復旧工法において、掘削箇所を路面高さ近くまで埋め戻した後、適宜な堅さを備えた矩形ゴム板で形成され、路面の掘削形状に対応する中央厚部分を厚く形成して中央厚部を設け、前記中央厚部の所定の側辺を、段差を介して裏面を抉る形状で薄く形成して側辺薄部を設けると共に、四隅部に近接した中央厚部の適宜箇所に表裏貫通するピン孔を設けてなる覆工マットを、側辺薄部端が舗装路面上に位置するように埋め戻し面を覆うように敷設し、前記ピン孔に筒状のズレ止めピンを、下方が覆工マット底面から適宜突出するように埋め戻し土中に打ち込むと共に、ズレ止めピンの筒部に、抜け止めピンを下方がズレ止めピンの下端から適宜突出するように埋め戻し土中に打ち込んで覆工マットを固定してなることを特徴とする路面仮復旧工法。 In the road surface temporary restoration method, which excavates the paved road surface and performs predetermined work, and temporarily recovers the excavated area, after the back of the excavated area is close to the road surface height, a rectangular rubber plate with appropriate rigidity is used. A thick central portion corresponding to the excavation shape of the road surface is formed to provide a thick central portion, and a predetermined side of the thick central portion is thinly formed so as to fold the back surface through a step. A covering mat with a thin hole and a pin hole penetrating the front and back at an appropriate place in the central thick part close to the four corners, and a backfill surface so that the side thin part end is located on the paved road surface. Lay the cover so that the cylindrical slip stopper pin is inserted into the back hole so that the lower part protrudes appropriately from the bottom of the lining mat, and the stopper pin is attached to the cylindrical portion of the stopper pin. Backfill so that the lower part protrudes appropriately from the lower end of the misalignment pin The road surface provisional recovery method, characterized in that it is formed by fixing the lining mat dedicated to in. 舗装路面を掘削して所定の工事を行い、当該掘削箇所の仮復旧を行う路面仮復旧工法において、掘削箇所を路面高さ近くまで埋め戻した後、適宜な堅さを備えた矩形ゴム板で形成され、路面の掘削形状に対応する中央厚部分を厚く形成して中央厚部を設け、前記中央厚部の所定の側辺を、段差を介して裏面を抉る形状で薄く形成して側辺薄部を設けると共に、四隅部に近接した中央厚部の適宜箇所に表裏貫通するピン孔を設けてなる覆工マットを、側辺薄部端が舗装路面上に位置するように埋め戻し面を覆うように敷設し、適宜形状のベース板部上に覆工マットのピン孔に装着される係止突部を突設すると共に、適宜箇所に透孔を設けてなる止着体を、覆工マットの下面に配置すると共に係止突部をピン孔に装着し、舗装面のみを除去した埋め戻し範囲外の掘削地面上に突出位置させた止着体の透孔から固定ピンを土中に打ち込んで覆工マットを固定してなることを特徴とする路面仮復旧工法。 In the road surface temporary restoration method, which excavates the paved road surface and performs predetermined work, and temporarily recovers the excavated area, after the back of the excavated area is close to the road surface height, a rectangular rubber plate with appropriate rigidity is used. A thick central portion corresponding to the excavation shape of the road surface is formed to provide a thick central portion, and a predetermined side of the thick central portion is thinly formed so as to fold the back surface through a step. A covering mat with a thin hole and a pin hole penetrating the front and back at an appropriate place in the central thick part close to the four corners, and a backfill surface so that the side thin part end is located on the paved road surface. Laying so that the locking projections that are installed in the pin holes of the lining mat are projected on the base plate portion of the appropriate shape and the through holes are provided at appropriate locations. Placed on the bottom surface of the mat and fitted with a locking projection in the pin hole, removing only the paved surface Range of road temporary restoration method, characterized by comprising fixing the lining mat fixing pin from hole drilling ground on the projecting position is not the fastening member is driven into soil back. 側辺薄部端が舗装路面上に位置するように埋め戻し面を覆うように敷設した際に、側辺薄部が埋め戻し面上に位置する場合に、側辺薄部を形成しない周縁に側辺薄部下方空隙形状と対応する連設突部を設けてなる覆工マットを隣接配置して埋め戻し面を覆うと共に、覆工マットの連突部を他方の覆工マットの側辺薄部下方に差し込み隣接覆工マットを連繋してなる請求項16又は17記載の路面仮復旧工法。 When laying so as to cover the backfill surface so that the edge of the side thin part is located on the paved road surface, when the side thin part is located on the backfill surface, the edge that does not form the side thin part with a lining mat formed by providing a continuous設突portion corresponding to the side edges thin men lateral gap shape covering the surface backfill adjacent arranged, the continuously arranged protrusion of the lining mat other lining mat sides 18. The road surface temporary restoration method according to claim 16 or 17, wherein the road surface temporary restoration method is formed by inserting an adjacent lining mat under the thin portion. 溝状の掘削個所の埋め戻し面上に、両端部に連結凹部と連結突部を設けた覆工マットを縦列連結して敷設すると共に、隣接覆工マットの下面に、ベース板部上に所定間隔で縦列する係止突部を突設した止着体を配置し、止着体の係止突部を隣接覆工マットのピン孔に装着して隣接覆工マットを連繋してなる請求項16又は17記載の路面仮復旧工法。   On the backfill surface of the groove-shaped excavation site, lining mats having connecting recesses and connecting protrusions at both ends are connected in tandem and laid on the base plate portion on the lower surface of the adjacent lining mat. A fastening body in which locking projections projecting vertically at intervals are arranged, the locking projections of the fastening body are attached to the pin holes of the adjacent lining mat, and the adjacent lining mat is connected. The road surface temporary restoration construction method according to 16 or 17. 路面掘削前、掘削溝形状に合わせて請求項15記載の定規板を並べて敷設し、当該定規板に合わせて路面舗装面の切断並びに溝掘削を行い、当該定規板と対応する覆工マットを使用してなる請求項16乃至19記載の何れかの路面仮復旧工法。   Prior to road surface excavation, the ruler plates according to claim 15 are laid side by side in accordance with the shape of the excavation groove, the road pavement surface is cut and groove excavation is performed in accordance with the ruler plate, and a lining mat corresponding to the ruler plate is used. The road surface temporary restoration method according to any one of claims 16 to 19.
JP2009039133A 2008-03-18 2009-02-23 Road surface temporary restoration member and road surface temporary restoration method Expired - Fee Related JP4931949B2 (en)

Priority Applications (5)

Application Number Priority Date Filing Date Title
JP2009039133A JP4931949B2 (en) 2008-03-18 2009-02-23 Road surface temporary restoration member and road surface temporary restoration method
PCT/JP2009/061328 WO2010021199A1 (en) 2008-08-22 2009-06-22 Member for temporarily recovering road surface and method for temporarily recovering road surface
KR1020117005522A KR101258417B1 (en) 2008-08-22 2009-06-22 Member for temporarily recovering road surface and method for temporarily recovering road surface
US13/059,896 US20110142539A1 (en) 2008-08-22 2009-06-22 Member for temporarily restoring road surface and method for temporarily restoring road surface
CN2009801324804A CN102131985A (en) 2008-08-22 2009-06-22 Member for temporarily recovering road surface and method for temporarily recovering road surface

Applications Claiming Priority (7)

Application Number Priority Date Filing Date Title
JP2008069533 2008-03-18
JP2008069533 2008-03-18
JP2008213511 2008-08-22
JP2008213511 2008-08-22
JP2008240540 2008-09-19
JP2008240540 2008-09-19
JP2009039133A JP4931949B2 (en) 2008-03-18 2009-02-23 Road surface temporary restoration member and road surface temporary restoration method

Publications (3)

Publication Number Publication Date
JP2010095987A JP2010095987A (en) 2010-04-30
JP2010095987A5 JP2010095987A5 (en) 2011-03-17
JP4931949B2 true JP4931949B2 (en) 2012-05-16

Family

ID=41707078

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009039133A Expired - Fee Related JP4931949B2 (en) 2008-03-18 2009-02-23 Road surface temporary restoration member and road surface temporary restoration method

Country Status (5)

Country Link
US (1) US20110142539A1 (en)
JP (1) JP4931949B2 (en)
KR (1) KR101258417B1 (en)
CN (1) CN102131985A (en)
WO (1) WO2010021199A1 (en)

Families Citing this family (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4931949B2 (en) 2008-03-18 2012-05-16 明和工業株式会社 Road surface temporary restoration member and road surface temporary restoration method
GB201000240D0 (en) 2010-01-08 2010-02-24 Oxford Plastic Sys Ltd Trench cover
US20130047351A1 (en) * 2011-08-31 2013-02-28 Marc Breault Pipeline crossing bridge
CN102535303B (en) * 2012-02-16 2015-04-08 张恒亮 Temporary emergency road surface equipment
US8967904B1 (en) 2012-10-05 2015-03-03 Pioneer Detectable, LLC Tactile plate assembly
KR101454709B1 (en) * 2012-10-08 2014-10-27 정운규 Temporary panel for reconstruction of road and reconstructing method of road using the said
CN104612016B (en) * 2014-12-11 2016-06-08 舜元建设(集团)有限公司 One is town road emergency repair method efficiently
AU2016313174C1 (en) * 2015-08-27 2019-05-16 Newpark Mats & Integrated Services Llc Apparatus and methods for electrically grounding at least one mat in a load-supporting surface
CN105970785B (en) * 2016-06-07 2018-01-09 中国南方航空工业(集团)有限公司 Concrete road surface dell quick repairs device and method
US10744360B2 (en) * 2017-04-04 2020-08-18 Polymer Technologies, Inc. Energy dissipative floor mat, mat system, and manufacturing process
CA2965450C (en) * 2017-04-27 2021-10-12 Busby Enterprises Ltd System, apparatus and related method for raised ground cover mat
FR3095660B1 (en) * 2019-04-30 2021-06-04 Filippo Cunsolo SURFACE COATING DEVICE
CN111472226A (en) * 2020-04-29 2020-07-31 无锡市政设计研究院有限公司 non-Newtonian fluid pillow bag and method for temporarily repairing pavement by using same
CN113174803A (en) * 2021-04-27 2021-07-27 重庆育才工程咨询监理有限公司 Diversion device for highway pavement restoration and pavement restoration method
AU2022316178B2 (en) * 2021-07-23 2024-05-23 Matpro Services Corporation Apparatus and method for repairing mats

Family Cites Families (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2358426A (en) * 1942-06-17 1944-09-19 John W Tompson Safety landing field for airplanes
US3930100A (en) * 1966-10-21 1975-12-30 Charles H Mcdonald Elastomeric cold patch for pavement repair
US4067155A (en) * 1975-08-28 1978-01-10 Grefco, Inc. Sealing system
US4129967A (en) * 1977-06-10 1978-12-19 John D. VanWagoner Apparatus for collecting fluid seepage in a building structure
JPS58145305A (en) * 1982-02-22 1983-08-30 Mitsubishi Electric Corp Synchronizing device
JPS58145305U (en) * 1982-03-26 1983-09-30 産興商事株式会社 Temporary recovery mat
US4445640A (en) * 1982-03-31 1984-05-01 The Goodyear Tire & Rubber Company Highway railway crossing and cap therefor
US4746243A (en) * 1986-05-29 1988-05-24 Eagle-Picher Industries, Inc. Apparatus and method for rapid repair of damaged airfield runways
JPH057708U (en) * 1991-07-12 1993-02-02 株式会社イノアツクコーポレーシヨン Sidewalk temporary lid
US5660498A (en) * 1996-01-16 1997-08-26 Freeman; Roger Patching system and method for repairing roadways
KR20020059403A (en) * 1999-09-17 2002-07-12 데이비드 빈센트 바이른 A Trench Cover Element
US6520714B1 (en) * 2001-08-09 2003-02-18 Jerrold L. Marsik, Jr. Transition surface for roadway
JP2005264693A (en) * 2004-03-15 2005-09-29 Inb Planning:Kk Rubber temporary paving material free of bending deformation and its manufacturing method
JP4931949B2 (en) 2008-03-18 2012-05-16 明和工業株式会社 Road surface temporary restoration member and road surface temporary restoration method

Also Published As

Publication number Publication date
KR101258417B1 (en) 2013-04-26
JP2010095987A (en) 2010-04-30
KR20110052701A (en) 2011-05-18
CN102131985A (en) 2011-07-20
US20110142539A1 (en) 2011-06-16
WO2010021199A1 (en) 2010-02-25

Similar Documents

Publication Publication Date Title
JP4931949B2 (en) Road surface temporary restoration member and road surface temporary restoration method
JP5514846B2 (en) Simple lining board
KR101640449B1 (en) Construction method for open cutting in tunnel portal area
KR101655217B1 (en) Construction method for open cutting in tunnel portal area
JP5762065B2 (en) Separate structure of bicycle lane and pedestrian lane
KR101205553B1 (en) Recycling rubber mat for temporary paving road
JP6159295B2 (en) Manhole repair method
JP4823082B2 (en) Rehabilitation panel, rehabilitation method using the same, and rehabilitated structure
JP3131502U (en) Mountain retaining plate for lining work
JP4564020B2 (en) Curb block
JP4981551B2 (en) Wall structure and construction method thereof
KR200396174Y1 (en) Steel earth plate for easy installation and dismantling
JP6364639B2 (en) Embedded structure and method for constructing embedded structure
JP3120150B1 (en) Road lining method
JP2019167723A (en) Curb-integrated steel drain gutter
JP4767191B2 (en) Mountain retaining member, road surface lining structure including the same, and road surface lining method
JP3450294B2 (en) Supporting structure of lining plate and lining method
KR101657279B1 (en) Permanent embedded anchor type slope ditch water way and slope ditch water way construction method using thereof
KR200424972Y1 (en) Board protecting landslide and construction structure thereof
JP2004232285A (en) Waterproof device and waterproof method of continuous wall
KR20120001074U (en) Support structure of corrugated multi plated tunnel
JP3611937B2 (en) Temporary buried structure of borehole
JP4111398B2 (en) Road repair method to drainage pavement
KR20060034521A (en) Corrugated steel culverts
JP3074307U (en) Gutter block

Legal Events

Date Code Title Description
A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110125

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20110125

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110128

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120207

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120214

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150224

Year of fee payment: 3

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees