JP4829872B2 - Pillow wood for tunnel - Google Patents

Pillow wood for tunnel Download PDF

Info

Publication number
JP4829872B2
JP4829872B2 JP2007328413A JP2007328413A JP4829872B2 JP 4829872 B2 JP4829872 B2 JP 4829872B2 JP 2007328413 A JP2007328413 A JP 2007328413A JP 2007328413 A JP2007328413 A JP 2007328413A JP 4829872 B2 JP4829872 B2 JP 4829872B2
Authority
JP
Japan
Prior art keywords
tunnel
pillow
timber
arch member
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2007328413A
Other languages
Japanese (ja)
Other versions
JP2009150107A (en
Inventor
与志雄 西田
敦 谷口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2007328413A priority Critical patent/JP4829872B2/en
Publication of JP2009150107A publication Critical patent/JP2009150107A/en
Application granted granted Critical
Publication of JP4829872B2 publication Critical patent/JP4829872B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

本発明は、シールド工事に使用するトンネル用枕木材に関する。   The present invention relates to a pillow timber for use in shield construction.

シールドトンネルの施工では、例えば特許文献1に示すように、シールドマシンに後続して、トンネルT内にレールRを敷設し、工事に必要な機材や機器類を台車により搬送する施工方法が一般的に行われている(図5参照)。このようなレールRは、セグメントSの内面に横架された水平部材である枕木100により支持されている。   In the construction of a shield tunnel, for example, as shown in Patent Document 1, a construction method in which a rail R is laid in a tunnel T following a shield machine, and equipment and devices necessary for the construction are conveyed by a carriage is common. (See FIG. 5). Such a rail R is supported by a sleeper 100 which is a horizontal member laid across the inner surface of the segment S.

大断面トンネルの施工では、トンネルの掘削に伴い、多量の掘削残土が発生するため、多量の掘削残土を処分する処分場を確保するのが困難であるとともに、残土処分の運搬や改質処理等に費用が嵩むという問題点を有していた。
また、大断面の切羽での掘削やセグメントの組立て作業に手間が掛かるため、工事が長期化するという問題点を有していた。
In the construction of large-section tunnels, a large amount of excavated soil is generated along with the excavation of the tunnel, so it is difficult to secure a disposal site to dispose of a large amount of excavated soil, as well as transportation and reforming of residual soil disposal. However, there is a problem that the cost increases.
In addition, it takes time for excavation with large cross-section faces and assembly work of segments, which has the problem that the construction work is prolonged.

そのため、例えば特許文献2に示す施工方法のように、トンネルの掘削作業と並行して、トンネルの後方において路床の施工を行うことでトンネル施工の工期短縮を図るとともに、トンネルの掘進に伴い発生した掘削土を地上において固化材を添加して改質処理を施した後、再度坑内に搬入してトンネル内の路床材として再利用することにより、掘削残土の有効利用を図る場合がある。   Therefore, for example, as in the construction method shown in Patent Document 2, in parallel with the excavation work of the tunnel, the roadbed is constructed behind the tunnel to shorten the construction period of the tunnel construction. In some cases, after the excavated soil is subjected to a reforming treatment by adding a solidifying material on the ground, it is carried into the mine again and reused as a roadbed material in a tunnel, thereby effectively utilizing the excavated residual soil.

特開平10−280900号公報JP-A-10-280900 特開2007−191859号公報JP 2007-191859 A

このようにトンネルの掘削作業と路床の施工とを並行して行うトンネル施工においては、路床の施工を、シールド掘進機の後続設備(台車やレール等)の下で行う必要がある。そのため、後続設備を支持する枕木は、下方での路床の施工が可能となるように、高い箇所に取り付ける必要がある。   As described above, in tunnel construction in which tunnel excavation work and roadbed construction are performed in parallel, it is necessary to perform roadbed construction under the subsequent equipment (cart, rail, etc.) of the shield machine. Therefore, it is necessary to attach the sleepers that support the following equipment to a high place so that the road bed can be installed below.

ところが、円形断面のトンネル内の高い箇所に枕木を設置すると、枕木のスパン長が長くなるため、枕木の長手方向中間部に枕木を支持するための支持部材を配置したり、枕木の断面形状を大きくする等の処置を施すことで長スパンに耐え得る強度を備える構成とする必要がある。しかしながら、支持部材による補強は、枕木の構造が複雑になり、その組立て作業に手間が掛かるため、枕木の転用時の切り回し作業に影響を及ぼすとともに、支持部材が路床の施工の妨げとなる。一方、枕木の断面形状を大きくすることは、仮設部材である枕木の材料費が高価になるとともに、枕木のハンドリング性が悪化することで、トンネルの掘進に伴い前方へと移設される枕木のトンネル内での切り回し作業に支障をきたす。   However, if a sleeper is installed at a high position in a tunnel with a circular cross section, the span length of the sleeper becomes long.Therefore, a support member for supporting the sleeper is arranged at the longitudinal intermediate portion of the sleeper, or the cross shape of the sleeper is changed. It is necessary to have a structure that can withstand a long span by taking measures such as increasing the size. However, the reinforcement by the support member complicates the structure of the sleeper and requires time for assembling the sleeper. Therefore, the support member affects the turning work when the sleeper is diverted, and the support member hinders the construction of the roadbed. . On the other hand, increasing the cross-sectional shape of a sleeper increases the material cost of the sleeper, which is a temporary member, and deteriorates the handleability of the sleeper, so that the sleeper tunnel moved forward as the tunnel advances It interferes with the cutting work inside.

本発明は、前記の問題点を解決するためになされたものであり、安価であるとともに容易にトンネル内に架設することが可能なトンネル用枕木材を提案することを課題とする。   The present invention has been made to solve the above-described problems, and an object thereof is to propose a pillow wood for a tunnel that is inexpensive and can be easily installed in a tunnel.

前記課題を解決するために、本発明のトンネル用枕木材は、トンネル坑内に設置される工事用仮設材を支持するためのトンネル用枕木材であって、トンネルの内径よりも小さい弦長を有し、上向きの円弧となるように前記トンネルに横架されるアーチ部材を備えることを特徴としている。   In order to solve the above-mentioned problem, the tunnel pillow timber of the present invention is a tunnel pillow timber for supporting a temporary construction material installed in a tunnel mine and has a chord length smaller than the inner diameter of the tunnel. And an arch member horizontally mounted on the tunnel so as to form an upward arc.

かかるトンネル用枕木材によれば、アーチ状の部材により構成されていることで、トンネル用枕木材への作用荷重としては、軸力が増加して曲げモーメントとせん断力が低減される。そのため、例えば、トンネル用枕木材の鋼材仕様を低減することが可能となり、枕木材の接続構造も簡易となるため、材料費の低減化が可能となる。さらに、トンネル用枕木材の軽量化により取り扱い性が向上するため、トンネル内における枕木材の切り回し作業や組立て、搬送等も容易となるため、作業性の向上を図ることができる。ここで、工事用仮設材とは、例えば、レール、レール状の鋼材、覆工板、足場板等、トンネル工事に伴い必要に応じて設置される各種仮設材をいう。   According to such a pillow wood for a tunnel, since it is configured by an arch-shaped member, an axial load increases and a bending moment and a shearing force are reduced as an acting load on the tunnel pillow wood. Therefore, for example, it becomes possible to reduce the steel material specification of the pillow timber for the tunnel, and the connection structure of the pillow timber is simplified, so that the material cost can be reduced. Furthermore, since the handling efficiency is improved by reducing the weight of the pillow timber for the tunnel, the work of cutting, assembling, and transporting the pillow timber in the tunnel is facilitated, so that the workability can be improved. Here, the temporary material for construction refers to various temporary materials that are installed as needed in connection with tunnel construction, such as rails, rail-shaped steel materials, lining plates, scaffolding plates, and the like.

また、前記アーチ部材が、その両端面が前記トンネルの内面に突き当てられた状態で横架すれば、アーチ部材に作用する軸力を直接セグメント(トンネル内面)に伝達する構成となる。そのため、ブラケット等の取付部材を省略することが可能となる。   Further, if the arch member is laid horizontally with both end faces thereof being abutted against the inner surface of the tunnel, the axial force acting on the arch member is directly transmitted to the segment (tunnel inner surface). Therefore, it is possible to omit a mounting member such as a bracket.

また、前記トンネル用枕木材の前記アーチ部材が、少なくとも1箇所の折れ点を有し、折り畳み可能であれば、トンネル用枕木材の輸送時に、トンネル用枕木材の寸法(弦長)を短くすることが可能となるため、トンネル内でのハンドリングが容易となり、トンネル用枕木材の切り回し作業が容易となる。   Further, if the arch member of the tunnel pillow wood has at least one folding point and can be folded, the size (string length) of the tunnel pillow wood is shortened when the tunnel pillow wood is transported. Therefore, handling in the tunnel is facilitated, and the cutting work of the tunnel lumber is facilitated.

また、前記トンネル用枕木材が、前記アーチ部材に接続された巻き上げ手段を有しており、前記アーチ部材が前記巻上げ手段により折り畳まれるものであれば、アーチ部材の端部を折り畳んだ状態で固定することが可能となるため、トンネル用枕木材の移設時の取り扱い性能が向上するとともに、安全性が確保される。   In addition, if the tunnel timber has winding means connected to the arch member, and the arch member is folded by the winding means, the end of the arch member is fixed in a folded state. Therefore, the handling performance at the time of relocating the tunnel timber is improved, and safety is ensured.

また、前記トンネル用枕木材が、前記アーチ部材の上方に固定された水平部材を有していれば、レールの敷設をより簡易に行うことが可能なため、好適である。   In addition, it is preferable that the tunnel timber has a horizontal member fixed above the arch member because the rail can be laid more easily.

本発明のトンネル用枕木材によれば、安価であるとともに容易に架設することができるため、トンネル施工をより簡易かつ安価に行うことが可能となる。   According to the pillow timber for a tunnel of the present invention, since it is inexpensive and can be easily installed, tunnel construction can be performed more simply and inexpensively.

以下、本発明の好適な実施の形態について、図面を参照して説明する。説明において、同一要素には同一の符号を用い、重複する説明は省略する。
本実施形態では、図1に示すように、シールド工法による大断面トンネルの施工において、トンネルTの坑内に設置される仮設のレールR(工事用仮設材)を支持するためのトンネル用枕木材1について説明する。
DESCRIPTION OF EXEMPLARY EMBODIMENTS Hereinafter, preferred embodiments of the invention will be described with reference to the drawings. In the description, the same reference numerals are used for the same elements, and redundant descriptions are omitted.
In this embodiment, as shown in FIG. 1, a tunnel pillow 1 for supporting a temporary rail R (temporary construction material) installed in a tunnel T tunnel in construction of a large-section tunnel by a shield method. Will be described.

トンネルTは、図2に示すように、シールドマシンMによる地山Gの切削とともに、シールドマシンMの背後においてセグメントSを組み立てることにより形成されるものであって、トンネルT坑内へのセグメントピースの搬送は、シールドマシンMに後続してトンネルTの坑内に敷設されたレールR上を走行する台車を利用して行う。   As shown in FIG. 2, the tunnel T is formed by assembling the segment S behind the shield machine M together with the cutting of the natural ground G by the shield machine M. The conveyance is performed using a carriage that runs on the rail R laid in the tunnel T after the shield machine M.

本実施形態に係るトンネルTの施工では、図2に示すように、トンネルTの切削に伴い発生した掘削土砂を路床材として使用することで、掘削残土の削減を図っている。   In the construction of the tunnel T according to the present embodiment, as shown in FIG. 2, the excavated soil is generated by using the excavated earth and sand generated along with the cutting of the tunnel T as a roadbed material.

本実施形態に係るトンネル用枕木材1は、図1に示すように、上向きの円弧となるように、トンネルT(セグメント2)に横架されるアーチ部材10と、アーチ部材10の上面に一体に固定された水平部材11とを備えている。   As shown in FIG. 1, a tunnel timber 1 according to the present embodiment is integrated with an arch member 10 that is horizontally mounted on a tunnel T (segment 2) so as to form an upward arc, and an upper surface of the arch member 10. And a horizontal member 11 fixed thereto.

アーチ部材10は、弦長LがトンネルTの内径Tよりも小さく、また、その曲率がセグメントの曲率より大きくなるように形成されている。
アート部材10を構成する材料は限定されるものではなく、例えば、H形鋼、溝型鋼、角形鋼管等の鋼材の中から適宜選定して使用することが可能である。
Arch member 10 is smaller than the inner diameter T D of the chord length L of the tunnel T, also, the curvature thereof is formed to be larger than the curvature of the segment.
The material which comprises the art member 10 is not limited, For example, it can select and use suitably from steel materials, such as H-shaped steel, a groove type steel, and a square steel pipe.

アーチ部材10は、トンネルTに設置した状態で、その両端面がトンネルTを構成するセグメントSの内面に突き当てられた状態で横架されていることで、トンネル用枕木材1に作用する上載荷重を軸力により受け持つ。   The arch member 10 is placed on the tunnel T, and the both ends of the arch member 10 are laid on the inner surface of the segment S constituting the tunnel T. The load is handled by the axial force.

アーチ部材10は、本体部10aと本体部10aの両端に折り畳み可能に取り付けられた折曲部10bとにより構成されており、各折曲部10bの近傍に、前記アーチ部材10に接続された巻き上げ手段12,12を有している。   The arch member 10 includes a main body portion 10a and folding portions 10b that are foldably attached to both ends of the main body portion 10a, and is wound up in the vicinity of each folding portion 10b and connected to the arch member 10. Means 12 and 12 are provided.

本体部10aと折曲部10bとは、互いの端面が突き合わされた状態でアーチ部材10のトンネルTへの架設が可能に構成されている。そして、本体部10aと折曲部10bとは、この突き合せ面の下端において回転可能に連結されており、折曲部10bは、巻き上げ手段12,12を操作することにより折り畳まれるように構成されている。   The main body portion 10a and the bent portion 10b are configured such that the arch member 10 can be installed on the tunnel T in a state where the end faces of each other are abutted. And the main-body part 10a and the bending part 10b are rotatably connected in the lower end of this abutting surface, and the bending part 10b is comprised so that it can be folded by operating the winding means 12 and 12. ing.

アーチ部材10は、その端面(折曲部10bの本体部10aと反対側の端面)が、路床Tの上面よりも高く、かつ、トンネルTの内径T(内法)が最大となる高さよりも低い位置に配置された状態で、トンネルTの坑内に架設される。
なお、本実施形態では、アーチ部材10の端面とセグメントSとの当接面に、ウレタンパット等のあて板を介在させるものとし、セグメントSの保護を図るとともに、トンネル用枕木材1の前後方向の転びを防止する。
Arch member 10 has its end face (end face of the body portion 10a of the bent portion 10b opposite) is higher than the upper surface of the subgrade T R, and the inner diameter T D of the tunnel T (inner size) is maximized In a state of being arranged at a position lower than the height, it is installed in the tunnel T tunnel.
In the present embodiment, a contact plate such as a urethane pad is interposed between the end surface of the arch member 10 and the segment S, so that the segment S is protected and the tunnel wood 1 for the longitudinal direction of the timber 1 is used. Prevent falling.

本実施形態では、巻き上げ手段12として、手巻きウィンチを採用している。巻き上げ手段12は、水平部材11の端部と、本体部10aの両端と、にそれぞれ設置されており、各巻き上げ手段12から延長されたワイヤーの先端は折曲部10bに接続されている。これにより、巻き上げ手段12による、折れ点における折曲部10bの折り畳みと引き伸ばし(展開)の操作が可能となっている。   In the present embodiment, a manual winding winch is employed as the winding means 12. The winding means 12 is installed at the end of the horizontal member 11 and both ends of the main body 10a, and the tip of the wire extended from each winding means 12 is connected to the bent portion 10b. Thereby, the folding means 12 can be folded and stretched (deployed) by the winding means 12 at the folding point.

水平部材11は、H形鋼、溝型鋼、角形鋼管等の鋼材からなる部材であって、本実施形態では、本体部10aの弦長Lと同等の長さに構成されている。なお、水平部材11の長さは、トンネルTの半径よりも短ければ限定されるものではない。   The horizontal member 11 is a member made of a steel material such as an H-shaped steel, a grooved steel, or a square steel pipe, and is configured to have a length equivalent to the chord length L of the main body 10a in the present embodiment. The length of the horizontal member 11 is not limited as long as it is shorter than the radius of the tunnel T.

水平部材11は、その長手方向(トンネル断面に対する横方向)の中間部が、アーチ部材10の長手方向の中間部に固定されているとともに、本体部10a(アーチ部材10)の端部に立設された支持材14により水平部材11の両端部が固定されている。
なお、水平部材11のアーチ部材10への固定方法は限定されるものではなく、適宜設定することが可能である。
The horizontal member 11 has an intermediate portion in the longitudinal direction (lateral direction with respect to the tunnel cross section) fixed to the intermediate portion in the longitudinal direction of the arch member 10 and is erected at the end of the main body portion 10a (arch member 10). Both ends of the horizontal member 11 are fixed by the support member 14 thus formed.
Note that the method for fixing the horizontal member 11 to the arch member 10 is not limited, and can be set as appropriate.

水平部材11の両端部には、それぞれ折曲部10bに連結された巻上げ手段12が設置されている。
トンネル用枕木材1をトンネルT内に設置した状態で、水平部材11の上面には、トンネル軸に沿って敷設されたレールRが上載されて、台車の走行が可能に構成されている。
また、水平部材11の両端と、トンネルTのセグメントSとの隙間には、着脱式足場15が架設されている。
At both ends of the horizontal member 11, winding means 12 connected to the bent portions 10b are installed.
In the state where the tunnel pillow 1 is installed in the tunnel T, a rail R laid along the tunnel axis is placed on the upper surface of the horizontal member 11 so that the carriage can run.
In addition, a detachable scaffold 15 is installed in the gap between both ends of the horizontal member 11 and the segment S of the tunnel T.

次に、図2乃至図4を参照して、本実施形態のトンネル用枕木材1を利用したトンネル施工について説明する。   Next, with reference to FIG. 2 thru | or FIG. 4, the tunnel construction using the pillow wood 1 for tunnels of this embodiment is demonstrated.

トンネルTの施工は、地山Gの切削と並行して、セグメントSの組立ておよび路床Tの埋め戻しを行う。 Construction of the tunnel T, in parallel with the cutting of natural ground G, performs backfill assembly and subgrade T R of the segment S.

図2に示すように、地山の切削は、設計された掘削断面に応じた形状からなるシールドマシンMを利用して行い、セグメントSの組立ては、シールドマシンMの背後において、掘進に伴って行う。   As shown in FIG. 2, the natural ground is cut using a shield machine M having a shape corresponding to the designed excavation cross section, and the assembly of the segment S is performed behind the shield machine M along with excavation. Do.

また、路床Tの埋め戻しは、地山Gの切削に伴い発生した掘削土砂を、シールドマシンの背後に配設された改良プラントPにより改良した後、この改良土砂をトンネル用枕木材1の下方において埋め戻すことにより行う。
なお、路床材として使用する掘削土砂の改良プラントPは、トンネルTの坑外に設置されていてもよく、掘削土砂を一端坑外に搬送して、改良処理を施した後、トンネルTの坑内に搬送して埋め戻す構成としてもよい。また、路床Tは、コンクリート部材や鋼製部材からなる床板および壁部材により構成してもよく、埋め戻しにより形成される場合に限定されるものではない。
Moreover, the backfill subgrade T R, the excavated earth and sand generated due to the cutting of natural ground G, was improved by improved plant P which is disposed behind the shield machine for tunnel sleepers material the improved soil 1 This is done by backfilling below.
The excavation earth and sand improvement plant P used as a roadbed material may be installed outside the tunnel T. After the excavation earth and sand are transported to the outside of the tunnel and subjected to the improvement treatment, the tunnel T It is good also as a structure conveyed and buried in a mine. Further, roadbed T R may be constituted by floor and wall members made of concrete members and steel members, it is not limited to when it is formed by the backfill.

セグメントS等のトンネルTの掘進に伴い必要となる各資材は、完成後の路床T上と、路床Tの施工個所の上方に架設されたトンネル用枕木材1上とに敷設されたレールRを走行する台車Dにより、トンネルTの切羽方向に輸送される。 Each material required with the excavation of the tunnel T of Segment S is laid and on the subgrade T R after completion, in the upper roadbed T tunnel sleepers material 1 which is laid over the construction point of the R It is transported in the direction of the face of the tunnel T by a carriage D traveling on the rail R.

トンネル用枕木材1は、シールドマシンMによる掘進および路床Tの施工の進捗状況に応じて、随時坑口側の枕木材1を切羽側に移設することにより、トンネル施工の進捗状況に応じた台車Dの走行面を形成している。 Tunnel sleepers material 1, depending on the progress of the construction of excavation and subgrade T R by the shield machine M, by relocating the sleepers member 1 at any time wellhead side working face side, in accordance with the progress of the tunnel construction A traveling surface of the carriage D is formed.

トンネル用枕木材1は、図2に示すように、折曲部10bが折り畳まれた状態で、台車Dを介して輸送される。このとき、トンネル用枕木1は、その長手方向がトンネル1の軸方向に沿った向きにより輸送される。   As shown in FIG. 2, the tunnel pillow 1 is transported via the carriage D in a state where the bent portion 10 b is folded. At this time, the tunnel sleeper 1 is transported in a direction in which the longitudinal direction is along the axial direction of the tunnel 1.

トンネル用枕木材1がシールドマシン後方の設置箇所の近傍まで輸送されたら、台車DからクレーンCに移し替えて、所定の設置箇所まで輸送する。   When the tunnel pillow 1 is transported to the vicinity of the installation location behind the shield machine, it is transferred from the carriage D to the crane C and transported to a predetermined installation location.

トンネル用枕木材1が所望の位置に到達したら、図3(a)に示すように、トンネル用枕木1を90°回転させて、トンネル用枕木材1の長手方向がトンネルTの横断方向と一致するような状態とする。そして、作業足場16上の作業員による巻き上げ手段12の操作が可能となる位置まで、トンネル用枕木材1を下降させる。   When the tunnel sleeper 1 reaches the desired position, the tunnel sleeper 1 is rotated by 90 ° as shown in FIG. 3A, and the longitudinal direction of the tunnel sleeper 1 coincides with the transverse direction of the tunnel T. It will be in a state that The tunnel pillow 1 is lowered to a position on the work scaffold 16 where the operator can operate the hoisting means 12.

トンネル用枕木1を下降させたら、図3(b)に示すように、巻き上げ手段12を操作して折曲部10bを引上げることで、折曲部10bの端面と本体部10aの端面とを当接させて、アーチ部材10を伸長させる。   When the tunnel sleeper 1 is lowered, as shown in FIG. 3 (b), the winding means 12 is operated to pull up the bent portion 10b so that the end face of the bent portion 10b and the end face of the main body portion 10a are moved. The arch member 10 is extended by contact.

さらにトンネル用枕木材1を下降させることで、セグメントSの内面にアーチ部材10の端面を当接させて、トンネル用枕木材1をセグメントSの内面に架設する。トンネル用枕木材1をセグメントSに架設したら、着脱式足場15を設置する。   Further, the tunnel pillow 1 is lowered to bring the end face of the arch member 10 into contact with the inner surface of the segment S, and the tunnel pillow 1 is installed on the inner surface of the segment S. When the tunnel pillow 1 is installed on the segment S, the detachable scaffold 15 is installed.

シールドマシンMによる地山Gの掘削の進捗および路床材の施工の進捗に伴い、最後尾のトンネル用枕木材1、図2に示すように、レールR上を走行する台車Dを利用して切羽側へと搬送される。   With the progress of the excavation of the natural ground G by the shield machine M and the progress of the construction of the road floor material, as shown in FIG. It is transported to the face side.

トンネル用枕木材1の取り外しは、図2および図4(a)に示すように、路床Tの上に設置されたクレーンCを利用して行う。 Removal of the tunnel for the sleeper member 1, as shown in FIGS. 2 and 4 (a), performed by using a crane C which is installed on the roadbed T R.

トンネル用枕木材1は、図4(a)に示すように、クレーンCにより上昇させられた後、作業員が巻き上げ手段12を操作することにより、折曲部10bを折り畳まれる。そして、折曲部10bの折り畳みが完了したら、図4(b)に示すように、少なくとも作業員と接触することがない高さまでトンネル用枕木材1を上昇させた後、当該トンネル用枕木材1の向きを90°回転させてトンネル軸方向と一致させる。   As shown in FIG. 4A, the tunnel pillow 1 is lifted by the crane C, and then the operator operates the winding means 12 to fold the bent portion 10b. Then, when the folding of the bent portion 10b is completed, as shown in FIG. 4B, the tunnel pillow wood 1 is raised to at least a height that does not come into contact with the worker, and then the tunnel pillow wood 1 Is rotated by 90 ° to coincide with the tunnel axis direction.

図2に示すように、トンネル用枕木材1は、その長手方向がトンネル軸方向を向いた状態で、台車Dに移し変えられた後、切羽方向へと輸送されて、所定の位置に設置される。   As shown in FIG. 2, the tunnel timber 1 is transferred to the carriage D in a state in which the longitudinal direction thereof is directed to the tunnel axis direction, and is then transported in the face direction and installed at a predetermined position. The

以上の作業を繰り返すことにより、トンネル用枕木材1の移設を行う。   By repeating the above operations, the tunnel pillow 1 is moved.

以上、本実施形態にかかるトンネル用枕木材1によれば、トンネル用枕木材1に作用する荷重を、アーチ部材10の軸力により受け持つため、優れた耐力を発現する。そのため、従来の水平部材のみからなるトンネル用枕木材と比較して鋼材の使用を低減させることが可能となる。故に、トンネル用枕木材の材料費の低減が可能となるとともに、トンネル用枕木材の軽量化によりハンドリング性が向上し、作業性の向上を図ることが可能となる。   As described above, according to the tunnel timber 1 according to this embodiment, the load acting on the tunnel timber 1 is handled by the axial force of the arch member 10, so that excellent proof stress is expressed. For this reason, it is possible to reduce the use of steel compared to conventional pillow timber made of only horizontal members. Therefore, it is possible to reduce the material cost of the tunnel timber, and to improve the handling by improving the weight of the tunnel timber, thereby improving the workability.

また、アーチ部材10は、その両端面がトンネルTの内面に突き当てられた状態で横架されるため、アーチ部材10に作用する軸力を直接セグメントS(トンネルTの壁面)に伝達する構造が構成される。そのため、ブラケット等の特殊な取付部材を省略して、トンネル用枕木材1を架設することができるため、安価であるとともに作業性にも優れている。   Further, since the arch member 10 is horizontally mounted with its both end faces being in contact with the inner surface of the tunnel T, a structure for transmitting the axial force acting on the arch member 10 directly to the segment S (the wall surface of the tunnel T). Is configured. Therefore, a special mounting member such as a bracket can be omitted and the tunnel pillow 1 can be installed, so that it is inexpensive and excellent in workability.

また、アーチ部材10が折れ点を有しており、折曲部10bを折り畳んだ状態で輸送することが可能なため、トンネル用枕木材1の着脱および輸送時のハンドリング性が向上し、作業性に優れている。   Moreover, since the arch member 10 has a fold point and can be transported in a state in which the bent portion 10b is folded, the handling of the timber 1 for the tunnel pillow 1 is improved and the workability is improved. Is excellent.

また、アーチ部材10の折り畳みは、巻き上げ手段12を介して行うため、作業が容易であるとともに作業員の安全性も確保できる。   Further, since the arch member 10 is folded through the winding means 12, the work is easy and the safety of the worker can be ensured.

また、レールRの敷設はアーチ部材10の上面に固定された水平部材11を利用して行うため、レールRの位置決めや固定が容易である。   Further, since the rail R is laid using the horizontal member 11 fixed to the upper surface of the arch member 10, the rail R can be easily positioned and fixed.

また、アーチ部材10の円弧をセグメントSの円弧よりも大きくするとともに、アーチ部材10の端面の設置箇所を路床Tの表面よりも高い位置に設定されているため、路床の施工に支障をきたすことなく、また、セグメントS等の輸送にも悪影響を及ぼすことがない。 Also, with larger than the arc of the arc segments S of the arch member 10, because it is set at a position higher than the surface of the subgrade T R the installation location of the end face of the arch member 10, hinder the construction of roadbed Without adversely affecting the transportation of the segment S or the like.

以上、本発明について、好適な実施形態について説明したが、本発明は前記の実施形態に限られず、本発明の趣旨を逸脱しない範囲で適宜設計変更が可能である。
例えば、前記実施形態では、アーチ部材が2箇所において折れ点を有する構成としたが、アーチ部材の折れ点の数は限定されるものではなく、適宜設定することが可能である。
As mentioned above, although preferred embodiment was described about this invention, this invention is not limited to the said embodiment, A design change is possible suitably in the range which does not deviate from the meaning of this invention.
For example, in the above-described embodiment, the arch member is configured to have break points at two locations, but the number of break points of the arch member is not limited and can be set as appropriate.

巻き上げ手段の設置箇所、構成、数等は限定されるものではなく、適宜設定することが可能である。また、巻き上げ手段は必要に応じて設置すればよく、必ずしも設置する必要はない。   The installation location, configuration, number, and the like of the winding means are not limited and can be set as appropriate. Further, the winding means may be installed as necessary, and is not necessarily installed.

また、水平部材は、必要に応じて設置すればよく、水平部材を省略して、アーチ部材の上面に直接レールを敷設する構成としてもよい。また、前記実施形態では、水平部材として1本の鋼材をアーチ部材の上面に固定するものとしたが、2本の鋼材をアーチ部材から側方に延設するように固定してもよい。さらに、水平部材が、アーチ部材と同様に折れ点を有していることで、ハンドリング性の向上を図るものであってもよい。   Further, the horizontal member may be installed as necessary, and the horizontal member may be omitted and the rail may be laid directly on the upper surface of the arch member. Moreover, in the said embodiment, although one steel material was fixed to the upper surface of an arch member as a horizontal member, you may fix so that two steel materials may extend sideways from an arch member. Further, the horizontal member may have a break point similarly to the arch member, so that the handling property may be improved.

また、トンネル用枕木材の設置箇所、設置間隔等は、適宜設定することが可能である。
また、クレーンや台車の形式等も限定されるものではなく、適宜公知の機種から選定して使用すればよい。
Moreover, the installation location, installation interval, etc. of the tunnel timber can be set as appropriate.
Further, the type of crane or carriage is not limited, and any known model may be selected and used as appropriate.

また、前記実施形態では、シールドトンネルの施工において本発明のトンネル用枕木材を使用する場合について説明したが、TBMや山岳トンネル等にも使用可能である。
また、トンネルの断面形状は円形に限定されるものではなく、例えば、矩形、楕円形、複円形、馬蹄形等であってもよい。
Moreover, although the said embodiment demonstrated the case where the pillow wood for tunnels of this invention was used in construction of a shield tunnel, it can be used also for TBM, a mountain tunnel, etc.
Moreover, the cross-sectional shape of the tunnel is not limited to a circle, and may be, for example, a rectangle, an ellipse, a double circle, or a horseshoe.

また、前記実施形態では、アーチ部材の端面をセグメントの表面にウレタンパット等からなるあて板を介して突き合わせるものとしたが、あて板は必要に応じて介在させればよく、必ずしも配置する必要はない。また、あて板を構成する材料は限定されるものではなく、適宜選定して使用すればよい。
また、トンネル用枕木材1の前後方向の転びを防止する部材として、アンカーピン等、あて板以外の部材を使用してもよい。
In the above embodiment, the end surface of the arch member is abutted against the surface of the segment through a contact plate made of urethane pad or the like. However, the contact plate may be interposed as necessary and is necessarily arranged. There is no. Moreover, the material which comprises an address plate is not limited, What is necessary is just to select suitably and use.
Moreover, you may use members other than a guard plate, such as an anchor pin, as a member which prevents the pillow wood 1 for tunnels to roll in the front-back direction.

また、前記実施形態では、トンネル用枕木材にレールを敷設する場合について説明したが、トンネル用枕木材が支持する部材はレールに限定されるものではなく、例えば、レール状の鋼材、覆工板、足場板等、その他の工事用仮設材であってもよい。   Further, in the above embodiment, the case where the rail is laid on the tunnel timber is described. However, the member supported by the tunnel timber is not limited to the rail. For example, a rail-shaped steel material or a lining plate is used. Other construction temporary materials such as scaffolding plates may be used.

本発明の好適な実施形態に係るトンネル用枕木材を示す正面図である。It is a front view which shows the pillow wood for tunnels which concerns on suitable embodiment of this invention. 本発明の好適な実施形態に係るトンネル用枕木材の移設方法を示す断面図である。It is sectional drawing which shows the transfer method of the pillow timber for tunnels which concerns on suitable embodiment of this invention. (a)および(b)は図1に示すトンネル用枕木材の取り付け方法を示す正面図である。(A) And (b) is a front view which shows the attachment method of the pillow wood for tunnels shown in FIG. (a)および(b)は図1に示すトンネル用枕木材の取り外し方法を示す正面図である。(A) And (b) is a front view which shows the removal method of the pillow wood for tunnels shown in FIG. 従来のトンネル用枕木材を示す正面図である。It is a front view which shows the conventional pillow wood for tunnels.

符号の説明Explanation of symbols

1 トンネル用枕木材
10 アーチ部材
11 水平部材
12 巻き上げ手段
13 止水用継手板
L 弦長
R レール(工事用仮設材)
S セグメント
T トンネル
路床
DESCRIPTION OF SYMBOLS 1 Pillow wood for tunnels 10 Arch member 11 Horizontal member 12 Winding means 13 Joint plate for water stop L String length R Rail (temporary material for construction)
S Segment T tunnel T R subgrade

Claims (5)

トンネル坑内に設置される工事用仮設材を支持するためのトンネル用枕木材であって、
トンネルの内径よりも小さい弦長を有し、上向きの円弧となるように前記トンネルに横架されるアーチ部材を備えることを特徴とするトンネル用枕木材。
Tunnel timber for supporting temporary construction materials installed in the tunnel mine,
A pillow timber for a tunnel, comprising an arch member that has a chord length smaller than the inner diameter of the tunnel and is laid across the tunnel so as to form an upward arc.
前記アーチ部材は、その両端面が前記トンネルの内面に突き当てられた状態で横架されることを特徴とする、請求項1に記載のトンネル用枕木材。   The timber for a tunnel according to claim 1, wherein the arch member is horizontally mounted in a state in which both end surfaces thereof are abutted against the inner surface of the tunnel. 前記アーチ部材が、少なくとも1箇所の折れ点を有し、折り畳み可能であることを特徴とする、請求項1または請求項2に記載のトンネル用枕木材。   The timber for a tunnel according to claim 1 or 2, wherein the arch member has at least one folding point and is foldable. 前記アーチ部材に接続された巻き上げ手段を有しており、
前記アーチ部材が、前記巻上げ手段により折り畳まれることを特徴とする、請求項3に記載のトンネル用枕木材。
Having hoisting means connected to the arch member;
The timber for a tunnel according to claim 3, wherein the arch member is folded by the winding means.
前記アーチ部材の上方に水平部材が固定されていることを特徴とする、請求項1乃至請求項4のいずれか1項に記載のトンネル用枕木材。   5. The tunnel pillow according to claim 1, wherein a horizontal member is fixed above the arch member. 6.
JP2007328413A 2007-12-20 2007-12-20 Pillow wood for tunnel Expired - Fee Related JP4829872B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007328413A JP4829872B2 (en) 2007-12-20 2007-12-20 Pillow wood for tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007328413A JP4829872B2 (en) 2007-12-20 2007-12-20 Pillow wood for tunnel

Publications (2)

Publication Number Publication Date
JP2009150107A JP2009150107A (en) 2009-07-09
JP4829872B2 true JP4829872B2 (en) 2011-12-07

Family

ID=40919527

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007328413A Expired - Fee Related JP4829872B2 (en) 2007-12-20 2007-12-20 Pillow wood for tunnel

Country Status (1)

Country Link
JP (1) JP4829872B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6840819B1 (en) * 2019-11-07 2021-03-10 大成建設株式会社 Work floor and support pillar construction method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2788955B2 (en) * 1990-08-31 1998-08-20 清水建設株式会社 Track laying method and track laying device in shield construction
JP3725962B2 (en) * 1997-03-31 2005-12-14 株式会社イズミ Temporary sleeper structure for shield tunnel construction
JP4699218B2 (en) * 2006-01-17 2011-06-08 阪神高速道路株式会社 Invert roadbed construction method
JP2008248605A (en) * 2007-03-30 2008-10-16 Ihi Corp Mount with rail and its laying method
JP2008248604A (en) * 2007-03-30 2008-10-16 Ihi Corp Method of advancing shield machine and shield machine

Also Published As

Publication number Publication date
JP2009150107A (en) 2009-07-09

Similar Documents

Publication Publication Date Title
JP4504910B2 (en) Dolly and method of erection of temporary pier using it
KR101111594B1 (en) Method for constructing underground structure
JP5477898B2 (en) Construction equipment and construction method for foundation work of directly elevated viaduct
CN108301332A (en) The detachable steel trestle construction method of beret slice
JP2005083014A (en) Pre-cast tunnel method and member conveyor used therefor
JP2006028881A (en) Self-propelled pc floor slab erecting machine and pc floor slab erecting method
JP6416474B2 (en) Structure construction method and support device
JP4559370B2 (en) Girder erection method by erection gutter from the side of bridge
JP4829872B2 (en) Pillow wood for tunnel
CN204126655U (en) The anti-electric lining trolley of double track tunnel newly-built hangar tunnel lining construction
JP6529378B2 (en) Invert construction method, tunnel construction method and Teruha crane for tunnel
JP2015052212A (en) Pier construction method and steel pipe pile construction method
DE102007014104B4 (en) Method for expanding a tunnel and apparatus for carrying out the method
JP2007321429A (en) Underground structure construction method
JP5187969B2 (en) Overhead viaduct construction equipment and construction method
KR100844147B1 (en) 2 arch-tunnel with asymmetry support wall and construction method of the same
CN104372746B (en) The prefabricated post stretching Simple T-Girders note concrete form support of railroad bridge and mounting process thereof
JP5292019B2 (en) Pile construction device and cast-in-place concrete pile construction method
JP3864377B2 (en) Existing tunnel widening method
JP6428014B2 (en) Construction method of back strut
JP2020159061A (en) Method for constructing work pit intersection in mountain tunnel construction
JP4243418B2 (en) Invert segment for tunnel and shield tunnel lining structure using the segment
JP2005105528A (en) Slope frame traveling type construction facility, slope frame traveling type hole digging facility, and hole digging method for slope frame crossing part by use of slope frame traveling type hole digging facility
JP6387778B2 (en) Suspension jig used when building the core material of the underground continuous wall, the method of building the core material of the underground continuous wall, and the system for building the core material of the underground continuous wall
JP4694523B2 (en) Construction method of road tunnel in shield tunnel

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20100315

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20110831

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20110906

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20110916

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20170922

Year of fee payment: 6

R150 Certificate of patent or registration of utility model

Ref document number: 4829872

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees