JP4606665B2 - Road construction method - Google Patents

Road construction method Download PDF

Info

Publication number
JP4606665B2
JP4606665B2 JP2001258898A JP2001258898A JP4606665B2 JP 4606665 B2 JP4606665 B2 JP 4606665B2 JP 2001258898 A JP2001258898 A JP 2001258898A JP 2001258898 A JP2001258898 A JP 2001258898A JP 4606665 B2 JP4606665 B2 JP 4606665B2
Authority
JP
Japan
Prior art keywords
floor slab
pile
temporary
rigid floor
main body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2001258898A
Other languages
Japanese (ja)
Other versions
JP2003064601A (en
Inventor
正 吉田
正嗣 山本
智彦 酒匂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2001258898A priority Critical patent/JP4606665B2/en
Publication of JP2003064601A publication Critical patent/JP2003064601A/en
Application granted granted Critical
Publication of JP4606665B2 publication Critical patent/JP4606665B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Railway Tracks (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、路面電車や鉄道線路等の車両走行路や道路の下方に地下構造物を構築することを想定した路下施工法に関するものである。
【0002】
【従来の技術】
日本の交通における主役は、現在、自動車、バス、鉄道であるが、近年、海外を中心にして環境問題への対応や建設コスト低減などを理由に路面電車が新たにLRT(Light Rail Transit:軽快電車)という形で注目されている。LRTは従来の路面電車の発展形であり、街路上を走行する点では路面電車と同じだが、車道と分離した専用軌道走行を基本としており、走行速度・加減速度等の性能が路面電車に比較して大きく向上している。
【0003】
一方、都市の道路下には、上下水道、ガス、電力、通信、地下鉄、地下道、共同溝、地下通路、地下駐車場、地下駐輪場などの多くの構造物が存在、または計画されているが、この輻輳する地中部に対して、さらに、近年、都市景観の向上を目的とした送電線・電話線の地中埋設化や諸設備の共同溝への収納化の促進が行われている。また、一度設置・構築した地下構築物であっても、長期的には劣化に伴う補修や目的に応じた補強が必要になる。
【0004】
そこで、路面電車やLRTなどの軌道が敷設されている道路下に、また一般道路下に地下構造物(上下水道、ガス、電力、通信、地下鉄、地下道、共同溝、地下通路、地下駐車場、地下駐輪場など)を新設あるいは補修する場合、路面電車やLRTや自動車などの交通を妨げずに、地下構造物の構築工事を行うことが社会的に求められている。
【0005】
図21〜図25は、この地下構造物の構築工事の施工法の従来例を示す一例で、図21において1は路面電車やLRTなどの車両、2はアスファルトなどによる道路の舗装部で、車両1の軌道としては、舗装部2の下面に枕木3を設置し、この枕木3の上にレール4を敷設している。
【0006】
このように舗装部2に車両1の軌道が敷設された道路に対して、軌道の下方の地中に地下構造物5(上下水道、ガス、電力、通信、地下鉄、地下道、共同溝、地下通路、地下駐車場、地下駐輪場など)を構築する場合、第1工程として、図22に示すようにレール4にそってその両外側の舗装部2を部分的に掘削して撤去し、この撤去部を介して下方に仮受杭6を設置する。この仮受杭6は土留壁と兼用する場合もある。
【0007】
次に、第2工程として図23に示すように、軌道縦断方向に、順次、レール4間の舗装部2をさらに撤去し、そして、枕木3、砕石道床等を撤去してから、その下部の土砂掘削を行い、次いで、対向する仮受杭6の対向面側に桁受鋼材7を取り付け、桁受鋼材7に通し桁8の端部を差し込んで、桁受鋼材7間に通し桁8を架設する。ここで、レール4の受け替えを行って、レール4を固定する。この一連の工程(第2工程)を縦断方向に順次繰り返していく。
【0008】
次に第3工程として図24に示すように、桁受鋼材7および通し桁8に囲まれた内側の内部土砂を掘削し、地下構造物5を構築、または、補修、設置を行う。この場合、必要に応じてさらに土留めを行い、また、仮覆工板9を設置する。
【0009】
以上のようにして地下構造物5の構築が終了すれば、第4工程として図25に示すように埋戻し10を行い、さらに軌道縦断方向に順次、桁受鋼材7、通し桁8を撤去した後、再び、枕木3を設置し、レール4を固定する。そして、仮受杭6を引き抜き、最後に路面に舗装11を施して復旧する。
【0010】
かかる第1工程から第4工程の全工程において、第1、第3工程では多くの場合、路面電車などの車両1の走行を停止しての作業となり、また、第2、第4工程では車両1の走行を停止しての作業となる。
【0011】
【発明が解決しようとする課題】
路面電車やLRTなどの軌道が敷設されている道路下に、軌道直下に位置させて地下構造物を構築しようとする場合、従来の施工法では、図24に示す下部の内部掘削に先行するレールの受け替え工事に多くの施工手間(工費、工程)を要してしまう。このため、路線営業を維持した状態でのレール受け替え工事は、夜間のキ電停止を伴うごく限られた時間内に仮復旧までを完了しなくてはならないものとなり、作業時間的にも厳しい工事となり、これが工期増大やコスト増大に至っている。
【0012】
また、本受け替え工事は、何らかの制約条件(道路幅が狭いなど)により地下構造物構築時にレール位置を横にずらすことが不可能または困難な場合には避けることができない。
【0013】
本発明の目的は前記従来例の不都合を解消し、路面電車やLRTなどの軌道が敷設されている道路下に、軌道直下に位置させて地下構造物を構築しようとする場合、軌道の受け替え工事を簡略化できて地下構造物構築の施工手間を低減し、車両の走行に及ぼす影響が少なく、車両の軌道を敷設する際に、その軌道直下に地下構造物の構築が予め計画されている場合に特に有効な路下施工法を提供することにある。
【0014】
【課題を解決するための手段】
本発明は前記目的を達成するため、剛性床版は、アスファルトなどによる道路の舗装部と同一面に埋設されるもので、工場製作のプレキャスト床版であり、レールを敷設するための溝条を本体の上面に形成し、長さ方向にそってその側部に後述の仮受杭との連結部として、複数の連結用のインサート式ナットまたはボルトナットを適宜間隔で埋設し、本体の端面には、長さ方向に順次結合される他の本体との結合の位置合わせのための突出ピンと、他の本体に突設した該突出ピンが挿入される孔とを本体の長さ方向の左右両側よりに位置させて設けたもので、この剛性床版で構成された路面の下方を掘削する際には、前記剛性床版の両側部にボルトインサート方式またはボルトナット方式で仮受杭を連結し、剛性床版と仮受杭で荷重を支持し、仮受杭と剛性床版に囲まれた内側の内部土砂を掘削し、地下構造物を構築、または、補修、設置を行い、地下構造物の構築が終了すれば、埋戻しを行い、さらに仮受杭を剛性床版との連結部から取り外し、仮受杭を引き抜くことを要旨とするものである。
【0015】
(削除)
【0016】
請求項1記載の本発明によれば、路面を剛性床版で構成してあるから、路面下方を掘削する際には、従来のように路面の舗装・枕木・砕石道床等の撤去を行う必要がなく、仮受杭位置の舗装部だけを部分撤去すればよく、レールの受け替え工事を簡略化できて、ほぼそのままの状態で、仮受杭を設置できる。よって、夜間のキ電停止を伴うごく限られた時間内に仮復旧までを完了することが容易となるだけでなく、何らかの制約条件(道路幅が狭いなど)により路面下方掘削時にレール位置を横にずらすことが不可能または困難な場合にも施工が可能となり、施工手間の低減、工期短縮、建設コストの低減を図ることができる。
【0017】
前記作用に加えて、剛性床版をプレキャスト製とすることで、製作が容易であり、品質も確保でき、現場ではかかる剛性床版を連結するだけでよく施工性もよい。
【0018】
(削除)
【0019】
【発明の実施の形態】
以下、図面について本発明の実施の形態を詳細に説明する。図1は本発明の路下施工法の実施の形態を示す説明図、図2〜図4は同上路下施工法の第1工程から第3工程を示す工程図で、図中、図21〜図25に示した従来例と同一の構成要素には同一の参照符号を付してある。
【0020】
本発明では、路面電車やLRTなどの車両1が走行する走行路の道床を剛性床版12で構成する。この剛性床版12は、アスファルトなどによる道路の舗装部2と同一面に埋設されるもので、基本的なタイプの一例として、図5に示すように工場製作のプレキャスト床版とする。この場合の材質は、例えば、PC(プレストレストコンクリート)、RC(鉄筋コンクリート)、ST(鋼)、合成構造(鋼+コンクリート)、SRC(鉄骨鉄筋コンクリート)などとすることができる。
【0021】
図5に示すタイプの剛性床版12は、軌道が単線タイプのものとして、レール4を敷設するための溝条14を本体13の上面に2条形成し、長さ方向にそってその側部に仮受杭6との連結部として、複数(図示の例では2個)の連結用のインサート式ナット15を適宜間隔で埋設した。
【0022】
また、本体13の端面には、長さ方向に順次結合される他の本体13との結合の位置合わせのための突出ピン16と、他の本体13に突設した該突出ピン16が挿入される孔17とを本体13の長さ方向の左右両側よりに位置させて設ける。この位置合わせのための手段(構造)は例を示すものであり、他の方法でも構わない。
【0023】
図6に示すタイプは軌道が複線タイプのものであり、基本構造は図5に示した単線タイプと同様であるが、本体13の上面に形成するレール4を敷設するための溝条14が4条となる。また、側部に長さ方向に形成する連結用のインサート式ナット15の配設間隔も単線タイプよりも小さくなり、同じ長さの本体13に対して3個埋設した。なお、この個数は必要強度に応じて設定する。
【0024】
(削除)
【0025】
図7、図8は仮受杭6との連結部構造を示し、図7に示すタイプはインサート式ナット15で前記図5、図6に示したものと同一のフラット(平滑)タイプであり、このインサート式ナット15は頭部が本体13の側部が突出することなく、同一面になるように埋設される。図8に示すタイプはコ字形の連結金具15aを突設した突出タイプである。
【0026】
次に、前記した図5、図7に示すフラットタイプの連結用のインサート式ナット15を備える剛性床版12を走行路の道床として設置してある箇所の直下において、地下構造物(上下水道、ガス、電力、通信、地下鉄、地下道、共同溝、地下通路、地下駐車場、地下駐輪場など)を構築する場合を、図2〜図4について説明する。
【0027】
第1工程として図2に示すように仮受杭6の設置位置の舗装部2のみを部分撤去し、撤去部分を介して地上から仮受杭6を地中に挿入して設置する。この仮受杭6の固定は、剛性床版12の側部の連結部に仮受杭6を連結することで行う。この第1工程の作業は、車両1の走行の安全が確保できればキ電停止でなくとも作業可能である。
【0028】
剛性床版12と仮受杭6との連結は、図7に示したインサート式ナット15による場合は、該インサート式ナット15に仮受杭6の側部を当接し、仮受杭6に形成したボルト孔をインサート式ナット15に合致させ、両者をボルト・ナットによって結合する。
【0029】
仮受杭6は例えばH形鋼によるものとし、インサート式ナット15と仮受杭6との接合部の施工誤差の対処方法として、例えば図9に示すように、剛性床版12と仮受杭6との離隔に対しては、調整プレートや図示のような断面ロ字形の調整ピース18を用いる。この調整ピース18は剛性床版12との接合面と、その対向面とにボルト孔を穿設したもので、ボルトでインサート式ナット15に連結すれば、この状態で調整ピース18が剛性床版12の側部から側方に突出する。
【0030】
よって、突出した調整ピース18の外側面にボルト・ナット19によってH形鋼による仮受杭6を連結する。他のインサート式ナット15にも同様にして調整ピース18を結合し、該調整ピース18にH形鋼による仮受杭6を連結する。
【0031】
そして、H形鋼による隣接する仮受杭6間に例えば木製の矢板20を差し入れ、該矢板20で土留めする。
【0032】
また、インサート式ナット15と仮受杭6との孔ズレによる施工誤差に対しては、調整ピース18や仮受杭6に形成するボルト孔をバカ孔に形成し、結合時には大ワッシャーを使用することでこれに対処する。この場合、インサート式ナット15には連結のためのボルトは面直にしか入らないため、孔ズレには調整ピース18が有効な施工誤差吸収手段となる。
【0033】
前記した図9の場合は、仮受杭6をH形鋼で構成し、これに木製の矢板20を組み合わせて土留壁としたが、図10に示すように、鋼矢板21を剛性床版12に埋設のインサート式ナット15に結合し、この鋼矢板21に仮受杭と土留壁との機能を付与させてもよい。この場合も、剛性床版12と鋼矢板21との離隔や孔ズレなどを調整するには調整ピースを使用する。
【0034】
剛性床版12と仮受杭6との連結部構造として、図8に示すコ字形の連結金具15aを突設した突出タイプでは、連結金具15aの外側面に仮受杭6を当接し、連結金具15aの外側面に形成したボルト孔を介して仮受杭6をボルトナットで連結する。
【0035】
この突出タイプにおける施工誤差の対処方法としては、前記したフラットタイプに比較してボルトインサート方式ではなく、ボルトナット方式であることから、テーパーワッシャーを使用すればボルトの若干の斜め締結は可能となる。なお、離隔には調整プレートなどで、また、孔ズレにはバカ孔と大ワッシャーで対処し、フラットタイプに比較して調整ピースを必要としない場合が多い。他方、連結金具15aが剛性床版12に予め突設してあるから、舗装部2の撤去ボリュームは大きくなる。
【0036】
前記した例は、剛性床版12の本体13の側部をフラット面に形成し、このフラット面の外側に仮受杭6を連結したが、図11〜図14に示すように剛性床版12を仮受杭6の設置ガイド付きのものとすることもできる。かかるタイプの剛性床版12の第1例としては、図11、図12に示すように仮受杭6との連結部に、H型鋼などによる仮受杭6が収納される平面コ字形の切欠き凹部22を形成した。
【0037】
図中23は、前記切欠き凹部22内に仮受杭6をセットした後に切欠き凹部22の開口を閉塞する仮受杭連結用の細長形状のプレートで、該プレート23には仮受杭6を固定するためのボルト孔23aが穿設してある。図中24は開口の両側に位置させて本体13の側部に形成され、前記プレート23を固定するためのインサートである。
【0038】
かかる切欠き凹部22を設けた剛性床版12にH形鋼などのよる仮受杭6を連結するには、切欠き凹部22内に仮受杭6をセットした後、剛性床版12の側面にプレート23を当接して開口を閉塞し、該プレート23をボルトでインサート24に固定するとともに、ボルト・ナット19を用いてボルト孔23aを介してプレート23に仮受杭6の側部を固定する。これにより、仮受杭6が剛性床版12に連結される。
【0039】
図13、図14は設置ガイド付きの剛性床版12の第2例を示し、ボルト孔25aが穿設してあるプレート25を剛性床版12の本体13の側部に、該剛性床版12の成型時に予め一体に埋設しておくものである。この場合は、切欠き凹部22内に上方からH形鋼などのよる仮受杭6を差し込んだ後、前記第1例と同様にしてボルト・ナット19を用いてボルト孔25aを介してプレート25に仮受杭6の側部を固定する。これにより、仮受杭6が剛性床版12に連結される。
【0040】
この設置ガイド付きの剛性床版12を使用すれば、仮受杭6の設置位置が切欠き凹部22で示されるから、この切欠き凹部22内に仮受杭6を差し入れるだけで、所定の結合位置に仮受杭6が設置され、剛性床版12の側部における仮受杭6の位置決めが容易になる。
【0041】
次に第2工程として図3に示すように、仮受杭6と剛性床版12に囲まれた内側の内部土砂を掘削し、地下構造物5(上下水道、ガス、電力、通信、地下鉄、地下道、共同溝、地下通路、地下駐車場、地下駐輪場など)を構築、または、補修、設置を行う。この場合、必要に応じてさらに土留めを行う。この工程は多くの場合キ電停止作業となるが、レール4の受け替えを簡略化でき、工期短縮を図れる。
【0042】
また、下部掘削の際には、レール4の道床である剛性床版12の耐荷力が、仮受杭6の間を結ぶ横方向(および縦断方向)において列車荷重・自動車荷重・床版荷重を支持する。
【0043】
以上のようにして地下構造物5の構築が終了すれば、第3工程として図4に示すように埋戻し10を行い、さらに仮受杭6を剛性床版12との連結部から取り外し、仮受杭6を引き抜き、最後に路面に舗装11を施して復旧する。この工程はキ電停止作業となる。前記した実施形態は、剛性床版12をプレキャスト床版とした場合であるが、これを現場打設コンクリートにより構築することもでき、その場合の工程もプレキャスト床版と同様である。
【0044】
図15〜図20は剛性床版12の上面に設けたレール4を敷設するための溝条14の構造を示すもので、第1例を図15、図16について説明する。レール4の締結方式としては板バネ方式や線バネ方式などが考えられるが、ここでは板バネ方式を採用した場合について説明する。この第1例は溝条14の幅をある程度大きく形成する場合で、溝条14は底部両側を長さ方向にそって拡幅し、拡幅部14aに形成しておく。
【0045】
そして、レール4の両側に広がる脚部4aのうちの一方の側(図示の例では左側)を拡幅部14aに差し入れるかたちで、溝条14の一方の側に寄せ、かつ、溝条14との間に緩衝材26を介在させてレール4を配設する。
【0046】
溝条14の右側の残余の空間に板バネ式のレール締結金具27を配設し、該レール締結金具27でレール4の右側の脚部4aを押さえて固定する。図中29は、レール締結金具27を溝条14に固定するためのインサート式ナットを示し、該インサート式ナット29の周囲にはスパイラル筋28が配設される。図中30はレール締結金具27とインサート式ナット29との間に介装する当て鋼板を示す。
【0047】
図17、図18は溝条14の構造の第2例を示し、基本構造は第1例と同様であるが、溝条14の幅を、レール4の頭部のみが露出する程度に幅狭に形成し、レール締結金具27の配設箇所のみ溝条14の一方の側の本体13を箱抜き31によって方形に拡幅し、ここにレール締結金具27を設置した。レール締結金具27の構造および締結方法は第1例と同様である。
【0048】
図19、図20は溝条14の構造の第3例を示し、基本構造は第2例と同様であるが、レール締結金具27をレール4の左右両側に設置する場合で、これに対応させてレール締結金具27の設置箇所の溝条14を箱抜き31によって方形に拡幅した。
【0049】
本発明はこのような構造の溝条14およびレール締結手段を備えるもので、剛性床版12へのレール4の敷設、受け替えも容易に短時間で行える。
【0050】
そして、軌道が敷設される際に、軌道直下に地下構造物の構築が将来計画されている場合は、レール4の道床を剛性床版12で構築しておくことで、将来のレール受け替え工事を簡略化できる。
【0051】
また、路面電車やLRTの建設時以外の、一般の自動車道などにも本発明は有効であり、例えば路面の再舗装を行う時点で、老朽化や規模拡大を理由に既存の地下構造物の補修、補強または再設置が計画されている場合にも実施できる。
【0052】
【発明の効果】
以上述べたように本発明の路下施工法は、路面電車やLRTなどの軌道が敷設されている道路下や自動車道の道路下などに、軌道直下に位置させて地下構造物を構築、補修しようとする場合、道床を剛性床版としてこの耐荷力が、仮受杭6の間を結ぶ横方向(および縦断方向)において列車荷重・自動車荷重・床版荷重を支持するから、軌道の受け替え工事を簡略化できて路面電車などを営業したままの状態で施工でき、交通への影響を最小限に止めることができるから、地下構造物構築の施工手間を低減し、車両の走行に及ぼす影響が少なく、また、必要建設資材や廃材(舗装等の撤去材)の量も極端に低減でき、これに伴い環境保全へも貢献でき、軌道敷設から地下構造物構築までのトータルの建設コストも低減できるものである。さらに補修までを含むLCC(ライフサイクルコスト)も低減可能となる。
【図面の簡単な説明】
【図1】 本発明の路下施工法の実施形態を示す説明図である。
【図2】 本発明の路下施工法の実施形態を示す第1工程の説明図である。
【図3】 本発明の路下施工法の実施形態を示す第2工程の説明図である。
【図4】 本発明の路下施工法の実施形態を示す第3工程の説明図である。
【図5】 本発明の路下施工法で使用する単線タイプの剛性床版の斜視図である。
【図6】 本発明の路下施工法で使用する複線タイプの剛性床版の斜視図である。
【図7】 本発明の路下施工法で使用するフラットタイプの連結部を有する剛性床版の斜視図である。
【図8】 本発明の路下施工法で使用する突出タイプの連結部を有する剛性床版の斜視図である。
【図9】 本発明の路下施工法の連結例の第1例を示す斜視図である。
【図10】 本発明の路下施工法の連結例の第2例を示す斜視図である。
【図11】 本発明の路下施工法で使用するガイド付きタイプの連結部を有する剛性床版の第1例の斜視図である。
【図12】 本発明の路下施工法で使用するガイド付きタイプの連結部を有する剛性床版の第1例の平面図である。
【図13】 本発明の路下施工法で使用するガイド付きタイプの連結部を有する剛性床版の第2例の斜視図である。
【図14】 本発明の路下施工法で使用するガイド付きタイプの連結部を有する剛性床版の第2例の平面図である。
【図15】 本発明の路下施工法で使用する剛性床版のレール敷設用の溝条の第1例を示す斜視図である。
【図16】 本発明の路下施工法で使用する剛性床版のレール敷設用の溝条の第1例を示す縦断正面図である。
【図17】 本発明の路下施工法で使用する剛性床版のレール敷設用の溝条の第2例を示す斜視図である。
【図18】 本発明の路下施工法で使用する剛性床版のレール敷設用の溝条の第2例を示す縦断正面図である。
【図19】 本発明の路下施工法で使用する剛性床版のレール敷設用の溝条の第3例を示す斜視図である。
【図20】 本発明の路下施工法で使用する剛性床版のレール敷設用の溝条の第3例を示す縦断正面図である。
【図21】 従来の路下施工法を示す説明図である。
【図22】 従来の路下施工法の第1工程の説明図である。
【図23】 従来の路下施工法の第2工程の説明図である。
【図24】 従来の路下施工法の第3工程の説明図である。
【図25】 従来の路下施工法の第4工程の説明図である。
【符号の説明】
1…車両 2…舗装部
3…枕木 4…レール
4a…脚部
5…地下構造物 6…仮受杭
7…桁受鋼材 8…通し桁
9…仮覆工板 10…埋戻し
11…舗装 12…剛性床版
13…本体 14…溝条
14a…拡幅部
15…インサート式ナット 15a…連結金具
16…突出ピン
17…孔 18…調整ピース
19…ボルト・ナット 20…矢板
21…鋼矢板 22…切欠き凹部
23…プレート 23a…ボルト孔
24…インサート 25…プレート
25a…ボルト孔 26…緩衝材
27…レール締結金具 28…スパイラル筋
29…インサート式ナット 30…鋼板
31…箱抜き
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a road construction method that assumes the construction of an underground structure below a vehicle traveling road or road such as a tram or railroad track.
[0002]
[Prior art]
Currently, automobiles, buses, and railroads are the main players in Japan's transportation, but in recent years, streetcars have been newly developed for the purpose of dealing with environmental problems and reducing construction costs mainly in overseas countries. It is attracting attention in the form of trains. The LRT is a development of the conventional tram, which is the same as the tram in that it travels on the street, but it is based on a dedicated track that is separate from the roadway. Compared with the tram, performance such as running speed and acceleration / deceleration is comparable. It has improved greatly.
[0003]
On the other hand, many structures such as water and sewage systems, gas, power, communications, subways, underground passages, common grooves, underground passages, underground parking lots, underground bicycle parking lots exist or are planned, In recent years, it has been promoted to embed underground transmission lines and telephone lines and to store various facilities in common grooves for the purpose of improving urban landscape. In addition, even underground structures that have been installed and constructed once need to be repaired due to deterioration and reinforced according to their purpose.
[0004]
Under the roads where trams such as trams and LRTs are laid, and underground roads (under water and sewage, gas, electric power, communications, subways, underground passages, common grooves, underground passages, underground parking lots, When an underground bicycle parking lot is newly established or repaired, it is socially required to construct an underground structure without obstructing traffic such as trams, LRTs, and automobiles.
[0005]
21 to 25 show an example of a conventional construction method for constructing this underground structure. In FIG. 21, 1 is a vehicle such as a tram or LRT, 2 is a road pavement made of asphalt, etc. As the track 1, a sleeper 3 is installed on the lower surface of the pavement 2, and a rail 4 is laid on the sleeper 3.
[0006]
In this way, with respect to the road where the track of the vehicle 1 is laid on the pavement 2, the underground structure 5 (waterworks, gas, power, communication, subway, underpass, common ditch, underground passage) , Underground parking lots, underground bicycle parking lots, etc.) As a first step, as shown in FIG. 22, the pavement portions 2 on both outer sides are partially excavated and removed along the rails 4 as shown in FIG. The temporary pile 6 is installed below via This temporary pile 6 may also be used as a retaining wall.
[0007]
Next, as shown in FIG. 23, as a second step, the pavement 2 between the rails 4 is further removed sequentially in the longitudinal direction of the track, and the sleepers 3, the crushed stone bed, etc. are removed, and then the lower part thereof is removed. Sediment excavation is performed, and then a girder steel material 7 is attached to the opposing surface side of the opposing temporary support pile 6, the end of the through beam 8 is inserted into the girder steel material 7, and the through girder 8 is inserted between the girder steel materials 7. Erection. Here, the rail 4 is replaced and the rail 4 is fixed. This series of steps (second step) is sequentially repeated in the longitudinal direction.
[0008]
Next, as shown in FIG. 24, as a third step, the inner internal earth and sand surrounded by the girder steel material 7 and the through girder 8 is excavated, and the underground structure 5 is constructed or repaired and installed. In this case, earthing is further performed as necessary, and a temporary lining plate 9 is installed.
[0009]
When the construction of the underground structure 5 is completed as described above, the backfill 10 is performed as shown in FIG. 25 as the fourth step, and the girder steel 7 and the through girder 8 are sequentially removed in the longitudinal direction of the track. Then, the sleepers 3 are installed again, and the rails 4 are fixed. Then, the temporary support pile 6 is pulled out, and finally the pavement 11 is applied to the road surface and restored.
[0010]
In all the steps from the first step to the fourth step, the first and third steps are often performed by stopping the traveling of the vehicle 1 such as a tram, and the second and fourth steps are performed by the vehicle. The operation is to stop the traveling of No. 1.
[0011]
[Problems to be solved by the invention]
When an underground structure is to be constructed under a road on which a track such as a tram or LRT is laid, the rail prior to the internal excavation shown in FIG. It takes a lot of construction work (construction cost, process) for the replacement work. For this reason, the rail replacement work while maintaining the route business must complete the temporary restoration within a very limited time with the stoppage of power at night. This is construction work, which has led to an increase in construction period and cost.
[0012]
In addition, this replacement work cannot be avoided if it is impossible or difficult to shift the rail position to the side during construction of the underground structure due to some restrictions (such as narrow road width).
[0013]
The object of the present invention is to eliminate the inconveniences of the conventional example, and to replace an underground structure when an underground structure is to be constructed under a road on which a track such as a tram or LRT is laid. Construction work can be simplified and the construction work of the underground structure can be reduced, and there is little influence on the running of the vehicle. When the track of the vehicle is laid, the construction of the underground structure is planned directly under the track. It is to provide a road construction method that is particularly effective in cases.
[0014]
[Means for Solving the Problems]
In order to achieve the above object, the present invention is a precast floor slab that is embedded in the same plane as a road pavement made of asphalt or the like, and has a groove for laying rails. Formed on the upper surface of the main body, along the length direction, a plurality of insert-type nuts or bolt nuts are embedded at appropriate intervals as a connection portion with a later-described provisional pile, and on the end surface of the main body The right and left sides of the length direction of the main body include a projecting pin for aligning the position with the other main body that is sequentially coupled in the length direction and a hole into which the projecting pin projecting from the other main body is inserted. which was provided by positioning more, when drilling under the road surface, which is constituted by the rigid slab is provisionally受杭connected by bolts insert method or bolt threaded assembly on both sides of the rigid slab The load is supported by the rigid floor slab and the support pile. Excavate the inner sediments surrounded by temporary piles and rigid floor slabs to construct or repair or install the underground structure. The gist is to remove the receiving pile from the connecting portion with the rigid floor slab and pull out the temporary receiving pile.
[0015]
(Delete)
[0016]
According to the first aspect of the present invention, since the road surface is composed of a rigid floor slab, when excavating below the road surface, it is necessary to remove the pavement, sleepers, crushed stone bed, etc. of the road surface as in the past. There is no need to remove only the pavement at the position of the provisional pile, and the rail replacement work can be simplified, and the provisional pile can be installed almost as it is. Therefore, not only is it easy to complete temporary restoration within a very limited time with the stoppage of power at night, but the rail position can be changed horizontally when excavating below the road surface due to some restrictions (such as narrow road width). Construction is possible even when it is impossible or difficult to shift, and it is possible to reduce construction labor, shorten the construction period, and reduce construction costs.
[0017]
In addition to the above-described operation, the rigid floor slab is made of precast, so that the manufacture is easy and the quality can be secured, and it is only necessary to connect the rigid floor slab on the site and the workability is good.
[0018]
(Delete)
[0019]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. FIG. 1 is an explanatory view showing an embodiment of a road construction method according to the present invention, and FIGS. 2 to 4 are process diagrams showing a first process to a third process of the road construction method. The same components as those in the conventional example shown in FIG. 25 are denoted by the same reference numerals.
[0020]
In the present invention, the road bed on the traveling road on which the vehicle 1 such as a tram or LRT travels is constituted by the rigid floor slab 12. The rigid floor slab 12 is embedded on the same surface as the road pavement 2 made of asphalt or the like. As an example of a basic type, a precast floor slab manufactured by a factory is used as shown in FIG. The material in this case can be, for example, PC (prestressed concrete), RC (reinforced concrete), ST (steel), composite structure (steel + concrete), SRC (steel reinforced concrete), and the like.
[0021]
The rigid floor slab 12 of the type shown in FIG. 5 has a track of a single wire type, and two grooves 14 for laying the rail 4 are formed on the upper surface of the main body 13, and its side portions along the length direction. In addition, a plurality (two in the illustrated example) of connecting insert nuts 15 are embedded at appropriate intervals as connecting portions with the temporary support piles 6.
[0022]
Further, a projecting pin 16 for positioning the coupling with the other main body 13 sequentially coupled in the length direction and the projecting pin 16 projecting from the other main body 13 are inserted into the end surface of the main body 13. The holes 17 are provided so as to be located on both the left and right sides in the length direction of the main body 13. This means (structure) for alignment shows an example, and other methods may be used.
[0023]
The type shown in FIG. 6 is a double-track type track, and the basic structure is the same as the single-wire type shown in FIG. 5, but there are four grooves 14 for laying the rail 4 formed on the upper surface of the main body 13. It becomes an article. Further, the interval between the insertion-type nuts 15 for connection formed in the lengthwise direction on the side portion is also smaller than that of the single wire type, and three are embedded in the main body 13 having the same length. This number is set according to the required strength.
[0024]
(Delete)
[0025]
7 and 8 show the connecting portion structure with the temporary pile 6, and the type shown in FIG. 7 is the same flat (smooth) type as shown in FIG. 5 and FIG. The insert-type nut 15 is embedded so that the head is flush with the side of the main body 13 without protruding. The type shown in FIG. 8 is a protruding type in which a U-shaped connecting metal fitting 15a is protruded.
[0026]
Next, immediately below the location where the rigid floor slab 12 having the flat type connecting insert type nut 15 shown in FIG. 5 and FIG. The case of constructing gas, electric power, communication, subway, underground passage, common ditch, underground passage, underground parking lot, underground bicycle parking, etc. will be described with reference to FIGS.
[0027]
As a 1st process, as shown in FIG. 2, only the pavement part 2 of the installation position of the provisional pile 6 is partially removed, and the provisional pile 6 is inserted and installed in the ground through the removal part. The provisional pile 6 is fixed by connecting the provisional pile 6 to a connecting portion on the side of the rigid floor slab 12. The work in the first step can be performed without stopping the power supply if the safety of traveling of the vehicle 1 can be ensured.
[0028]
When the rigid slab 12 and the temporary pile 6 are connected by the insert type nut 15 shown in FIG. 7, the side of the temporary pile 6 is brought into contact with the insert type nut 15 to form the temporary pile 6. The bolt hole thus fitted is matched with the insert-type nut 15, and both are coupled by bolts and nuts.
[0029]
The temporary pile 6 is made of, for example, H-shaped steel. As a method of dealing with the construction error of the joint between the insert nut 15 and the temporary pile 6, for example, as shown in FIG. For the separation from 6, an adjustment plate or an adjustment piece 18 having a square cross section as shown in the figure is used. This adjustment piece 18 has a bolt hole drilled in the joint surface with the rigid floor slab 12 and the opposite surface. If it is connected to the insert nut 15 with a bolt, the adjustment piece 18 is in this state. Projects laterally from the 12 sides.
[0030]
Accordingly, the provisional pile 6 made of H-shaped steel is connected to the outer surface of the protruding adjustment piece 18 by the bolt and nut 19. Similarly, the adjustment piece 18 is connected to the other insert-type nut 15, and the provisional pile 6 made of H-shaped steel is connected to the adjustment piece 18.
[0031]
Then, for example, a wooden sheet pile 20 is inserted between adjacent temporary piles 6 made of H-shaped steel, and earthed with the sheet pile 20.
[0032]
Also, for construction errors due to hole misalignment between the insert-type nut 15 and the temporary support pile 6, a bolt hole formed in the adjustment piece 18 or the temporary support pile 6 is formed in a fool hole, and a large washer is used at the time of connection. To deal with this. In this case, since the bolt for connection is inserted into the insert type nut 15 only in a straight surface, the adjustment piece 18 is an effective construction error absorbing means for hole misalignment.
[0033]
In the case of FIG. 9 described above, the temporary pile 6 is made of H-shaped steel, and a wooden sheet pile 20 is combined with this to form a retaining wall. However, as shown in FIG. Further, the steel sheet pile 21 may be provided with the functions of a temporary pile and a retaining wall by being connected to an embedded nut 15. In this case as well, an adjustment piece is used to adjust the separation between the rigid floor slab 12 and the steel sheet pile 21 and the hole displacement.
[0034]
As a connecting part structure between the rigid floor slab 12 and the temporary support pile 6, in the protruding type in which a U-shaped connection fitting 15a shown in FIG. 8 is protruded, the temporary support pile 6 is brought into contact with the outer surface of the connection fitting 15a. The temporary support pile 6 is connected with a bolt nut through a bolt hole formed in the outer surface of the metal fitting 15a.
[0035]
As a method of dealing with the construction error in this projecting type, it is not a bolt insert method but a bolt nut method compared to the flat type described above, so if a taper washer is used, a slight diagonal fastening of the bolt becomes possible. . It is to be noted that an adjustment plate or the like is used for the separation, and a hole and a large washer are used for the hole displacement, and an adjustment piece is often not required as compared with the flat type. On the other hand, since the connecting fitting 15a is projected in advance on the rigid floor slab 12, the removal volume of the pavement 2 is increased.
[0036]
In the above-described example, the side portion of the main body 13 of the rigid floor slab 12 is formed into a flat surface, and the temporary support pile 6 is connected to the outside of the flat surface. However, as shown in FIGS. Can be provided with an installation guide for the temporary support pile 6. As a first example of this type of rigid floor slab 12, as shown in FIGS. 11 and 12, a planar U-shaped cutting in which a temporary pile 6 made of H-shaped steel or the like is accommodated in a connecting portion with the temporary pile 6 A notch 22 was formed.
[0037]
In the figure, reference numeral 23 denotes an elongated plate for connecting a provisional pile that closes the opening of the notch recess 22 after the provisional pile 6 is set in the notch recess 22. Bolt holes 23a for fixing the bolts are formed. In the figure, reference numeral 24 denotes an insert for fixing the plate 23, which is formed on both sides of the opening and formed on the side of the main body 13.
[0038]
In order to connect the temporary pile 6 made of H-shaped steel or the like to the rigid floor slab 12 provided with the notched recess 22, the temporary pile 6 is set in the notched concave 22 and then the side surface of the rigid floor slab 12 is provided. The plate 23 is brought into contact with the opening 23 to close the opening, and the plate 23 is fixed to the insert 24 with bolts, and the side portion of the temporary pile 6 is fixed to the plate 23 through bolt holes 23a using bolts and nuts 19. To do. Thereby, the temporary pile 6 is connected to the rigid floor slab 12.
[0039]
FIGS. 13 and 14 show a second example of a rigid floor slab 12 with an installation guide. A plate 25 having a bolt hole 25a is formed on the side of the main body 13 of the rigid floor slab 12, and the rigid floor slab 12 is provided. It is embedded in advance at the time of molding. In this case, after inserting the provisional pile 6 made of H-shaped steel or the like into the notch recess 22 from above, the plate 25 is connected to the plate 25 through the bolt hole 25a using the bolt / nut 19 as in the first example. The side part of the temporary pile 6 is fixed to. Thereby, the temporary pile 6 is connected to the rigid floor slab 12.
[0040]
If the rigid floor slab 12 with this installation guide is used, the installation position of the temporary support pile 6 is indicated by the notch recess 22. The temporary pile 6 is installed at the coupling position, and positioning of the temporary pile 6 on the side portion of the rigid floor slab 12 becomes easy.
[0041]
Next, as shown in FIG. 3 as a second step, the inner soil and sand inside the temporary pile 6 and the rigid floor slab 12 are excavated, and the underground structure 5 (waterworks, gas, power, communication, subway, Build, repair, or install underpasses, common grooves, underground walkways, underground parking lots, underground bicycle parking lots, etc. In this case, earthing is further performed as necessary. In many cases, this process is a key stop operation, but the replacement of the rail 4 can be simplified and the construction period can be shortened.
[0042]
Also, when excavating the lower part, the load bearing capacity of the rigid floor slab 12 that is the road bed of the rail 4 is the train load, automobile load, and floor slab load in the lateral direction (and longitudinal direction) connecting the temporary piles 6. To support.
[0043]
When the construction of the underground structure 5 is completed as described above, the backfill 10 is performed as shown in FIG. 4 as the third step, and the temporary support pile 6 is removed from the connecting portion with the rigid floor slab 12, Pull the receiving pile 6 and finally pave the road surface 11 and restore it. This process is a key stop operation. The above-described embodiment is a case where the rigid floor slab 12 is a precast floor slab, but it can also be constructed by on-site cast concrete, and the process in that case is the same as the precast floor slab.
[0044]
FIGS. 15-20 show the structure of the groove 14 for laying the rail 4 provided on the upper surface of the rigid floor slab 12, and a first example will be described with reference to FIGS. The fastening method of the rail 4 may be a leaf spring method, a wire spring method, or the like. Here, a case where the leaf spring method is employed will be described. This first example is a case where the width of the groove 14 is formed to be somewhat large. The groove 14 is widened along the length direction on both sides of the bottom portion, and is formed in the widened portion 14a.
[0045]
Then, one side (left side in the illustrated example) of the leg portions 4a extending on both sides of the rail 4 is inserted into the widened portion 14a so as to be brought to one side of the groove 14 and the groove 14 The rail 4 is disposed with a cushioning material 26 interposed therebetween.
[0046]
A leaf spring type rail fastening bracket 27 is disposed in the remaining space on the right side of the groove 14, and the leg portion 4 a on the right side of the rail 4 is pressed and fixed by the rail fastening bracket 27. In the figure, reference numeral 29 denotes an insert type nut for fixing the rail fastening bracket 27 to the groove 14, and a spiral line 28 is disposed around the insert type nut 29. In the figure, reference numeral 30 denotes a contact steel plate interposed between the rail fastening bracket 27 and the insert type nut 29.
[0047]
17 and 18 show a second example of the structure of the groove 14 and the basic structure is the same as that of the first example, but the width of the groove 14 is narrow so that only the head of the rail 4 is exposed. The main body 13 on one side of the groove 14 was widened in a square shape by the box opening 31 only at the place where the rail fastening bracket 27 was disposed, and the rail fastening bracket 27 was installed here. The structure and fastening method of the rail fastening bracket 27 are the same as in the first example.
[0048]
19 and 20 show a third example of the structure of the groove 14 and the basic structure is the same as that of the second example. However, the rail fastening bracket 27 is installed on both the left and right sides of the rail 4, and it is made to correspond to this. Then, the groove 14 at the location where the rail fastening bracket 27 is installed was widened to a square by the box opening 31.
[0049]
The present invention includes the groove 14 and the rail fastening means having such a structure, and the rail 4 can be laid and replaced on the rigid floor slab 12 easily in a short time.
[0050]
And when the construction of underground structures is planned in the future when the track is laid, the future rail replacement work can be done by building the road bed of the rail 4 with the rigid floor slab 12 Can be simplified.
[0051]
The present invention is also effective for general motorways other than during construction of streetcars and LRTs. For example, at the time of re-paving the road surface, the existing underground structure is deteriorated due to aging or scale expansion. It can also be carried out if repair, reinforcement or re-installation is planned.
[0052]
【The invention's effect】
As described above, the road construction method of the present invention constructs and repairs underground structures by placing them directly under the track, such as under the roads where trams, LRTs, etc. are laid or under the roads of motorways. When trying to do so, the load carrying capacity is assumed to be a rigid floor slab, and this load-bearing force supports the train load, automobile load, and slab load in the lateral direction (and longitudinal direction) connecting the temporary support piles 6. The construction can be simplified and the streetcars can be operated while they are in operation, and the impact on traffic can be minimized. In addition, the amount of necessary construction materials and waste materials (removal materials such as pavement) can be drastically reduced, which can contribute to environmental conservation and reduce the total construction cost from track laying to construction of underground structures. It can be done. Furthermore, LCC (life cycle cost) including repair can be reduced.
[Brief description of the drawings]
FIG. 1 is an explanatory diagram showing an embodiment of a road construction method according to the present invention.
FIG. 2 is an explanatory diagram of a first step showing an embodiment of a road construction method of the present invention.
FIG. 3 is an explanatory view of a second step showing an embodiment of the road construction method of the present invention.
FIG. 4 is an explanatory diagram of a third step showing an embodiment of the road construction method of the present invention.
FIG. 5 is a perspective view of a single-wire type rigid floor slab used in the road construction method of the present invention.
FIG. 6 is a perspective view of a double track type rigid floor slab used in the road construction method of the present invention.
FIG. 7 is a perspective view of a rigid floor slab having a flat type connecting portion used in the road construction method of the present invention.
FIG. 8 is a perspective view of a rigid floor slab having a protruding type connecting portion used in the road construction method of the present invention.
FIG. 9 is a perspective view showing a first example of a connection example of a road construction method according to the present invention.
FIG. 10 is a perspective view showing a second example of the connection example of the road construction method of the present invention.
FIG. 11 is a perspective view of a first example of a rigid floor slab having a guide-type connecting portion used in the road construction method of the present invention.
FIG. 12 is a plan view of a first example of a rigid floor slab having a guide-type connecting portion used in the road construction method of the present invention.
FIG. 13 is a perspective view of a second example of a rigid floor slab having a guide-type connecting portion used in the road construction method of the present invention.
FIG. 14 is a plan view of a second example of a rigid floor slab having a guide-type connecting portion used in the road construction method of the present invention.
FIG. 15 is a perspective view showing a first example of a groove for laying a rail of a rigid floor slab used in the road construction method of the present invention.
FIG. 16 is a longitudinal front view showing a first example of a groove for laying a rail of a rigid floor slab used in a road construction method of the present invention.
FIG. 17 is a perspective view showing a second example of a groove for laying a rail of a rigid floor slab used in the road construction method of the present invention.
FIG. 18 is a longitudinal front view showing a second example of the groove for laying the rail of the rigid floor slab used in the road construction method of the present invention.
FIG. 19 is a perspective view showing a third example of a groove for laying a rail of a rigid floor slab used in the road construction method of the present invention.
FIG. 20 is a longitudinal front view showing a third example of a groove for laying a rail of a rigid floor slab used in the road construction method of the present invention.
FIG. 21 is an explanatory view showing a conventional road construction method.
FIG. 22 is an explanatory diagram of a first step of a conventional road construction method.
FIG. 23 is an explanatory diagram of a second step of the conventional road construction method.
FIG. 24 is an explanatory diagram of a third step of the conventional roadside construction method.
FIG. 25 is an explanatory diagram of a fourth step of the conventional road construction method.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 ... Vehicle 2 ... Pavement part 3 ... Sleeper 4 ... Rail 4a ... Leg part 5 ... Underground structure 6 ... Temporary pile 7 ... Girder receiving steel material 8 ... Through girder 9 ... Temporary lining board 10 ... Backfill
11 ... Pavement 12 ... Rigid floor slab
13 ... Body 14 ... Groove
14a ... Widening part
15 ... Insert type nut 15a ... Connecting bracket
16 ... protruding pin
17 ... hole 18 ... adjustment piece
19 ... Bolt / Nut 20 ... Sheet
21… Steel sheet pile 22… Notch recess
23 ... Plate 23a ... Bolt hole
24… Insert 25… Plate
25a ... Bolt hole 26 ... Buffer material
27 ... Rail fastening bracket 28 ... Spiral muscle
29 ... Insert type nut 30 ... Steel plate
31 ... unboxing

Claims (1)

剛性床版は、アスファルトなどによる道路の舗装部と同一面に埋設されるもので、工場製作のプレキャスト床版であり、レールを敷設するための溝条を本体の上面に形成し、長さ方向にそってその側部に後述の仮受杭との連結部として、複数の連結用のインサート式ナットまたはボルトナットを適宜間隔で埋設し、本体の端面には、長さ方向に順次結合される他の本体との結合の位置合わせのための突出ピンと、他の本体に突設した該突出ピンが挿入される孔とを本体の長さ方向の左右両側よりに位置させて設けたもので、この剛性床版で構成された路面の下方を掘削する際には、前記剛性床版の両側部にボルトインサート方式またはボルトナット方式で仮受杭を連結し、剛性床版と仮受杭で荷重を支持し、仮受杭と剛性床版に囲まれた内側の内部土砂を掘削し、地下構造物を構築、または、補修、設置を行い、地下構造物の構築が終了すれば、埋戻しを行い、さらに仮受杭を剛性床版との連結部から取り外し、仮受杭を引き抜くことを特徴とした路下施工法。 The rigid floor slab is embedded on the same surface as the road pavement made of asphalt, etc., and is a factory-prepared precast floor slab. Grooves for laying rails are formed on the upper surface of the main body, and the length direction Accordingly, a plurality of connecting insert-type nuts or bolt nuts are embedded at appropriate intervals as connecting portions to a later-described temporary receiving pile on the side portion, and are sequentially coupled to the end surface of the main body in the length direction. Protruding pins for alignment of the coupling with other main body and holes into which the protruding pins protruding from the other main body are inserted are positioned from both the left and right sides in the length direction of the main body, When excavating below the road surface composed of this rigid floor slab, a temporary support pile is connected to both sides of the rigid floor slab using a bolt insert method or a bolt and nut method, and a load is applied between the rigid floor slab and the temporary support pile. Supporting the inner side surrounded by temporary piles and rigid slabs Excavate the inner earth and sand, build or repair and install the underground structure, and when the construction of the underground structure is completed, perform backfilling, and remove the temporary pile from the joint with the rigid floor slab, A road construction method characterized by pulling out a temporary pile.
JP2001258898A 2001-08-29 2001-08-29 Road construction method Expired - Fee Related JP4606665B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001258898A JP4606665B2 (en) 2001-08-29 2001-08-29 Road construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001258898A JP4606665B2 (en) 2001-08-29 2001-08-29 Road construction method

Publications (2)

Publication Number Publication Date
JP2003064601A JP2003064601A (en) 2003-03-05
JP4606665B2 true JP4606665B2 (en) 2011-01-05

Family

ID=19086341

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001258898A Expired - Fee Related JP4606665B2 (en) 2001-08-29 2001-08-29 Road construction method

Country Status (1)

Country Link
JP (1) JP4606665B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4540632B2 (en) * 2003-02-12 2010-09-08 鉄建建設株式会社 Erection girder
JP4136959B2 (en) * 2003-02-12 2008-08-20 鉄建建設株式会社 "How to build underground structures and installation girder"
JP6046479B2 (en) * 2012-12-18 2016-12-14 鹿島建設株式会社 Articulated track block and construction method for connecting track block supporting girder
JP6770763B2 (en) * 2018-08-09 2020-10-21 株式会社オーイケ Rail foundation construction method and rail foundation block
JP2020026354A (en) * 2019-09-12 2020-02-20 株式会社オーイケ Construction method for rail foundation and rail foundation block

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60253612A (en) * 1984-05-28 1985-12-14 Kawasaki Steel Corp Construction of structure
JPH05302338A (en) * 1992-04-24 1993-11-16 Maeda Corp Underground construction method
JPH08253946A (en) * 1995-03-17 1996-10-01 Fujita Corp Reverse placing method for concrete of underground structure under road
JP2001073667A (en) * 1999-09-03 2001-03-21 East Japan Railway Co Construction of underground structure using working beam-cum-floor board
JP2001207401A (en) * 2000-01-21 2001-08-03 Taisei Corp Method of constructing grade separated crossing
JP2001214405A (en) * 2000-02-02 2001-08-07 East Japan Railway Co Girder for construction work

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60253612A (en) * 1984-05-28 1985-12-14 Kawasaki Steel Corp Construction of structure
JPH05302338A (en) * 1992-04-24 1993-11-16 Maeda Corp Underground construction method
JPH08253946A (en) * 1995-03-17 1996-10-01 Fujita Corp Reverse placing method for concrete of underground structure under road
JP2001073667A (en) * 1999-09-03 2001-03-21 East Japan Railway Co Construction of underground structure using working beam-cum-floor board
JP2001207401A (en) * 2000-01-21 2001-08-03 Taisei Corp Method of constructing grade separated crossing
JP2001214405A (en) * 2000-02-02 2001-08-07 East Japan Railway Co Girder for construction work

Also Published As

Publication number Publication date
JP2003064601A (en) 2003-03-05

Similar Documents

Publication Publication Date Title
Michas Slab track systems for high-speed railways.
US8430333B2 (en) Prefabricated module for the track of a self-guided urban transport vehicle on tyres
KR100571525B1 (en) Expansion method of a bridge using concrete structure
CN113338093B (en) Method for rebuilding and expanding existing railway and newly-built railway of port area freight yard in conflict
JP4606665B2 (en) Road construction method
CN102493288A (en) Prefabricated L-shaped retaining structure
KR102068441B1 (en) Temporary Strcuture of Underpass Traverse Construction for Traffic Facilities and Tunnel Construction Method Using by This
JP2008127900A (en) Concrete track slab
CN112095370A (en) Prefabricated tramcar roadbed and track integrated structure and construction method
JP6144726B2 (en) Rehabilitation method for mountain road tunnels on expressway and suspension pier for rehabilitation method
KR101262755B1 (en) Plate girder railway bridge having integrated cross beam and construction method using the same
EA006338B1 (en) Fixed track for rail vehicles and method for production thereof
KR20130009391A (en) Method for manufacturing concrete block for railway track and method for laying railway track using concrete block manufactured by the same method
CN102628278B (en) 'U-pipe pier' urban underground railroad
JP2000008304A (en) Pedestal for rail road work beam and execution method of pedestal for rail road work beam
KR102435459B1 (en) Structure And Method For Constructing Track Of Mountain train
KR101234091B1 (en) Method of underground railway crossing over direct installation of precast concrete slab
JP4148607B2 (en) Construction method of underground structure using floor girder for construction girder
JP2006112086A (en) Structure of bridge and method for rebuilding bridge
JP4020918B2 (en) Bridge structure of girder bridge
CN111549583A (en) Level crossing structure of rail transit
CN111877054A (en) Prefabricated plate type track structure convenient for rapid construction and construction method thereof
CN219410389U (en) Ballastless crossing plate and crossing structure with ballastless preventing function
CN212533539U (en) Level crossing structure of rail transit
JP3854545B2 (en) Box-type transportation

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20071225

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20091020

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20091215

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20100210

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20100413

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20100611

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20101005

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20101006

R150 Certificate of patent or registration of utility model

Ref document number: 4606665

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131015

Year of fee payment: 3

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees