JP4300638B2 - Ball lifting device - Google Patents

Ball lifting device Download PDF

Info

Publication number
JP4300638B2
JP4300638B2 JP22064699A JP22064699A JP4300638B2 JP 4300638 B2 JP4300638 B2 JP 4300638B2 JP 22064699 A JP22064699 A JP 22064699A JP 22064699 A JP22064699 A JP 22064699A JP 4300638 B2 JP4300638 B2 JP 4300638B2
Authority
JP
Japan
Prior art keywords
belt
slide member
fixing device
operation piece
guide rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP22064699A
Other languages
Japanese (ja)
Other versions
JP2001046717A (en
Inventor
正博 竹内
芳生 若菜
誠 田結
英勝 竹内
誠市 梁川
Original Assignee
株式会社竹屋
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社竹屋 filed Critical 株式会社竹屋
Priority to JP22064699A priority Critical patent/JP4300638B2/en
Publication of JP2001046717A publication Critical patent/JP2001046717A/en
Application granted granted Critical
Publication of JP4300638B2 publication Critical patent/JP4300638B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Pinball Game Machines (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、駆動源により回転する複数のローラ間を周回せしめられる搬送ベルトと、該搬送ベルトの外周面に対向して設置されるガイドレールに掛け渡して装着される研磨ベルトと、前記ガイドレールの外側面に設置され且つ前記研磨ベルトの上方側を固定するベルト上方固定装置と、を備えた玉揚送装置に関するものである。
【0002】
【従来の技術】
従来、パチンコ玉を揚送する玉揚送装置には、駆動源により回転するローラに周回している搬送ベルト(皮ベルト)と、搬送ベルトに対向しガイドレールの上下端に掛け渡して装着される研磨ベルト(布ベルト)との間にパチンコ玉を挟持した状態で揚送するものが知られている。通常、このような玉揚送装置の研磨ベルトは、ガイドレールの外側面で研磨ベルトの上下端側を挟持固定しているが、研磨ベルトは、玉揚送装置駆動時に搬送ベルトとの間に挟持されるパチンコ玉に影響を受けて研磨ベルトが伸び、玉揚送装置の上方に伸びた分の研磨ベルトがダブついてしまうことがある。このため、特開平9−730号に示されるように、常時研磨ベルトを引っ張ることによって、研磨ベルトのダブつきを無くして、研磨ベルトを常に緊張させた状態に保つことができる玉揚送装置が提案されている。この玉揚送装置は、ガイドレールの外側面に研磨ベルトの上端を常時下方へ付勢する上方固定装置が設けられており、研磨ベルトを緊張した状態に保つようになっている。また、この上方固定装置は、ガイドレールの外側面に突設して形成されるピンと、該ピンを貫通させる長穴を有するスライド板と、該スライド板の上端に形成されて研磨ベルトを挟持固定する挟持部と、前記スライド板を下方に付勢する付勢部材と、で構成されている。
【0003】
【発明が解決しようとする課題】
しかし、上記した上方固定装置を実際に使用する場合、スライド板を上方に持ち上げた状態(付勢部材に抗した位置で維持する状態)で研磨ベルトを引張り(伸びる分を予め減らすため)ながら、挟持部に研磨ベルトの上端を挟持させなければならない。このように、3つの作業を同時に行うことによりなされる研磨ベルトの挟持作業は、両方の手を使用して行っても困難なものとなっている。また、挟持作業が困難であるため、何とか研磨ベルトを装着しても、装着後の研磨ベルトに十分な張力が与えられていない状態で装着されることがあり、この場合には、結局研磨ベルトが玉揚送装置駆動時にダブついてしまうという問題があった。本発明は、上記した事情に鑑みなされたものであり、その目的とするところは、研磨ベルトに十分な張力を与えて装着することが容易に行うことができる玉揚送装置を提供することにある。
【0004】
【課題を解決するための手段】
上記した目的を達成するために、請求項1に係る発明においては、駆動源により回転する複数のローラ間を周回せしめられる搬送ベルトと、該搬送ベルトの外周面に対向して設置されるガイドレールに掛け渡して装着される研磨ベルトと、前記ガイドレールの外側面に設置され且つ前記研磨ベルトの上方側を固定するベルト上方固定装置と、を備えた玉揚送装置において、前記ベルト上方固定装置は、前記ガイドレールの外側面に沿って垂直方向に移動可能で且つ研磨ベルトを開放挟持する挟持部を有するスライド部材と、該スライド部材を下方に付勢する付勢部材と、を備え、前記スライド部材を上方に移動させた位置で停止させるスライド部材停止手段を設けたことを特徴とするものである。このように構成することにより、スライド部材の上方への移動,スライド部材の停止及びスライド部材への研磨ベルトの挟持の操作を同時に行う必要がなく、各操作を順に行うことができるため、研磨ベルトに十分な張力を与えて装着することが容易に行うことができる。
【0005】
また、請求項2に係る発明においては、駆動源により回転する複数のローラ間を周回せしめられる搬送ベルトと、該搬送ベルトの外周面に対向して設置されるガイドレールに掛け渡して装着される研磨ベルトと、前記ガイドレールの外側面に設置され且つ前記研磨ベルトの上方側を固定するベルト上方固定装置と、を備えた玉揚送装置において、前記ベルト上方固定装置は、前記ガイドレールの外側面に沿って垂直方向に移動可能なスライド部材と、該スライド部材を下方に付勢する付勢部材と、前記スライド部材を前記付勢部材の付勢力に抗して上方に移動させる操作片と、を備え、前記操作片は、該操作片を前記付勢部材の付勢力に抗して上方に持ち上げてスライド部材を上方に移動させた状態で、ベルト上方固定装置に研磨ベルトを挿入可能な開放状態と、ベルト上方固定装置に研磨ベルトを挟持させる挟持状態とに変位可能にすると共に、前記ベルト上方固定装置には、前記操作片を前記開放状態及び挟持状態でそれぞれ停止維持するように付勢する弾性部材を設けたことを特徴とするものである。このように構成することにより、操作片でスライド部材を上方に移動させた状態のままで操作片を操作して研磨ベルトをベルト上方固定装置に挿入,挟持した後、スライド部材が付勢部材によって下方に付勢されるため、研磨ベルトに十分な張力を与えて装着することが容易に行うことができる。また、操作片の開放状態時に容易に研磨ベルトをベルト上方固定装置に挿入することができると共に、研磨ベルトの挟持状態時により強固に研磨ベルトを挟持することができる。また、操作片のグラつきを防止することができる。
【0006】
また、請求項3に係る発明においては、駆動源により回転する複数のローラ間を周回せしめられる搬送ベルトと、該搬送ベルトの外周面に対向して設置されるガイドレールに掛け渡して装着される研磨ベルトと、前記ガイドレールの外側面に設置され且つ前記研磨ベルトの上方側を固定するベルト上方固定装置と、を備えた玉揚送装置において、前記ベルト上方固定装置は、前記ガイドレールの外側面に沿って垂直方向に移動可能なスライド部材と、該スライド部材を下方に付勢する付勢部材と、前記スライド部材を前記付勢部材の付勢力に抗して上方に移動させる操作片と、を備え、前記操作片は、該操作片を前記付勢部材の付勢力に抗して上方に持ち上げてスライド部材を上方に移動させた状態で、ベルト上方固定装置に研磨ベルトを挿入可能な開放状態と、ベルト上方固定装置に研磨ベルトを挟持させる挟持状態とに変位可能にすると共に、前記ベルト上方固定装置には、前記スライド部材を上方に移動させた位置で、前記操作片の操作により係止させるスライド部材係止手段を設けたことを特徴とするものである。このように構成することにより、操作片でスライド部材を上方に移動させた状態のままでスライド部材係止手段でスライド部材を係止して操作片を操作し、研磨ベルトをベルト上方固定装置に挿入,挟持した後、スライド部材の係止を解除することにより付勢部材によって下方に付勢されるため、研磨ベルトに十分な張力を与えて装着することが容易に行うことができる。また、スライド部材の上方への移動,スライド部材の係止,研磨ベルトの挟持及びスライド部材のスライド部材係止手段からの取外しまでの一連の操作がすべて操作片により操作可能なため、上記一連の操作を容易に行うことができる。
【0007】
【0008】
【0009】
【発明の実施の形態】
以下、図面を参照して本発明の実施形態について説明する。まず、本実施形態の要部を構成する玉揚送装置の全体の構成について図1を参照して説明する。図1は、玉揚送装置1を後方から見た斜視図である。
【0010】
図において、玉揚送装置1は、厚肉の鋼板で形成された支持台2の上部に支持台2と同じ材質で形成された揚送筒本体3が垂直状に立設され、揚送筒本体3の下部に位置する図示しない駆動用の下部ローラと上部に位置する図示しない上部ローラとの間に掛け渡される皮製の搬送ベルト4が、揚送筒本体3の周囲を周回するようになっている。この揚送筒本体3は、その断面形状が一側面の開口した長方形状であり、この開口面には、図示しない揚送筒カバーが取付ネジによって取り付けられている。この揚送筒カバーは、揚送筒本体3の全長に亘って揚送筒本体3の開口面を覆うように固定されており、前記上部ローラ,下部ローラ等の修理,交換時あるいは揚送筒本体3内のトラブル時などに揚送筒カバーを取り外して修理,交換作業あるいは、トラブルに対する対処を行うことができるものである。
【0011】
また、前記搬送ベルト4は、モータ内蔵の下部ローラの回転により揚送筒本体3の周囲を周回駆動するものである。この搬送ベルト4に張力を付与するために、搬送ベルト4が交互に当接する第1テンションローラ6,第2テンションローラ7及び第3テンションローラ8からなるテンションローラ機構5が、揚送筒本体3の下部に取り付けられている。このテンションローラ機構5の第1テンションローラ6及び第3テンションローラ8は、開放閉塞することが可能となっており、主に、搬送ベルト4の交換作業時に操作される。また、揚送筒本体3の下部には、流入するパチンコ玉を複数列に整列せしめられる導入樋9が固定され、揚送筒本体3の上部には、玉磨き後のパチンコ玉が排出される排出口11が形成されている。
【0012】
しかして、導入樋9から流入されたパチンコ玉は、搬送ベルト4により揚送された後排出口11から排出されるが、その揚送される過程で次に説明するガイドレール21に周設される研磨ベルト16との摩擦力によってパチンコ玉に付着した汚れが拭き取られ、排出口11からは、綺麗にされたパチンコ玉が排出されることとなる。なお、導入樋9には、図1に示すように、導入樋9の傾斜角を調整する傾斜角調整ボルト10が取り付けられている。この傾斜角調整ボルト10には、スプリングが周設されており、内部を流れるパチンコ玉によって導入樋9に無理な力が加わったときでもパチンコ玉がスムーズに整列されるような構造になっている。
【0013】
一方、前記した揚送筒本体3の背面側には、揚送筒本体3の一側面に取り付けられた支持ヒンジ15を介して、ガイドレール21が開閉自在に取り付けられている。この支持ヒンジ15は、揚送筒本体3の垂直方向に亘って数箇所設けられている。また、揚送筒本体3のもう一方の側面には、止め金具13が係止金具14を介して取り付けられており、ガイドレール21には、前記止め金具13に対応する位置にその止め金具13を係止するための係合突起12が設けられている。
【0014】
また、ガイドレール21には、その外側面に研磨ベルト16の上方側を固定するベルト上方固定装置17と研磨ベルト16の下方側を固定するベルト下方固定装置18とが取り付けられ、ガイドレール21の上端に研磨ベルト16を折り返し案内するための図示しない研磨ベルトローラが設けられている。しかして、ベルト下方固定装置18に固定された研磨ベルト16は、ガイドレール21の下端からガイドレール21を周回して前記研磨ベルトローラに掛け渡され、ベルト上方固定装置17に引張固定される。なお、ベルト上方固定装置17による研磨ベルト16の固定については、後に詳述する。
【0015】
また、前述したように、ガイドレール21は、揚送筒本体3に対して開閉自在に取り付けられているため、前記搬送ベルト4や研磨ベルト16の玉揚送装置1への装着は、ガイドレール21を支持ヒンジ15の支点を中心に回転させて開くことにより行うことができる。このようにして搬送ベルト4や研磨ベルト16を装着し、ガイドレール21が閉じられた状態で揚送筒本体3とガイドレール21を止め金具13により係止することによって、搬送ベルト4と研磨ベルト16が対面した状態で維持される。このようにガイドレール21が閉じられ、止め金具13により係止された状態では、揚送筒本体3とガイドレール21との間には、隙間が形成されることとなるが、この隙間は、係止金具14の固着位置を調整することによってその寸法を設定することができ、その設定値に応じて揚送されるパチンコ玉への圧力を変化させることができる。
【0016】
しかして、このように、搬送ベルト4及び研磨ベルト16を装着した状態でガイドレール21を閉じ、係合突起12に止め金具13を係止させてガイドレール21を揚送筒本体3に装着させた後、搬送ベルト4を周回駆動させることにより、搬送ベルト12と研磨ベルト16との間に挟み込まれたパチンコ玉が、研磨ベルト16に汚れを拭き取られながら上昇するものである。
【0017】
なお、営業終了時には、前記ベルト下方固定装置18を弛めて研磨ベルト16が移動し得るようにした状態で、ガイドレール21外側上部の研磨ベルト16を引っ張って、使用前ベルト収納箱19に納められている使用前の研磨ベルト16の未使用面をガイドレール21の内側面に位置させるようにし、その後、ベルト下方固定装置18とベルト上方固定装置17とを順次操作して研磨ベルト16を係止することによって、翌日の研磨に対する準備が終了する。このとき、使用後ベルト収納箱20内に使用後の研磨ベルト16が収納されることとなる。また、この研磨ベルト16の巻取作業は、ガイドレール21を揚送筒本体3から開いた状態で行っても、あるいは閉じたままの状態でも行うことができるが、新規な研磨ベルトに交換する場合には、ガイドレール21を揚送筒本体3から開いた状態で行う必要がある。
【0018】
以上、玉揚送装置1の概要について説明したが、次に、本実施形態の要部を構成するベルト上方固定装置17について図2乃至図5を参照して説明する。図2は、ベルト上方固定装置17の全体を示す斜視図であり、図3は、研磨ベルト16が装着されていない状態のベルト上方固定装置17の側面図であり、図4は、操作片32が開放状態のときのベルト上方固定装置17の側面図であり、図5は、操作片32が研磨ベルト16挟持状態のときのベルト上方固定装置17の側面図である。
【0019】
まず、ベルト上方固定装置17の構成について説明する。図2において、ベルト上方固定装置17は、ガイドレール21の外側表面に沿って上下方向に移動可能なスライド部材26と、該スライド部材26の上部両側方に立設される取付フランジ29の間に嵌入される操作片32と、前記スライド部材26の下部に設けられた付勢部材取付部35に取り付けられる付勢部材37と、前記操作片32の一端側と前記取付フランジ29上方部とに掛け渡される弾性部材としてのスプリング39と、から構成されている。
【0020】
前記スライド部材26は、ステンレス等の板金により形成されるものであり、その水平断面がコの字に形成されて両側方にスライド部材26の水平方向のズレを防止するために前記ガイドレール21の側面と当接するガイド部28が形成されると共に、表面両側方には、ガイドレール21に取り付けられるガイドピン22が嵌入されるスライド長孔27が穿設されている。また、スライド部材26の上方が折り曲げて形成されているため、その上端から上下方向ほぼ中央までは、板材2枚分の板厚となっている。そして、この折り曲げ部分の両側方が更に直角に折り曲げられ、前記取付フランジ29を形成している。この取付フランジ29には、後述する支軸30が挿入される支軸孔42が穿設されている。また、スライド部材26の下部には、前述のように、付勢部材取付部35が設けられており、この付勢部材取付部35の中央部には、付勢部材37を取り付けるための付勢部材取付孔41が穿設されている。
【0021】
また、操作片32は、スライド部材26と同様に、ステンレス等の板金により側面形状ほぼL字状に形成されるものであり、その上部は、鋭角に曲げられ、第1ベルト挟持片33を形成すると共に、この第1ベルト挟持片33の先端部は、研磨ベルト16を挟持するための挟持端部33aを形成している。また、操作片32の下部は、段差状に曲げられ、取手部34を形成すると共に、取手部34の反対側面には、ステンレス等の板金により側面形状ほぼL字状に形成された第2ベルト挟持片43(図3参照)が固着されている。この第2ベルト挟持片43の先端部は、第1ベルト挟持片33と同様に研磨ベルト16を挟持するため挟持端部43a(図3参照)を形成している。更に、第1ベルト挟持片33の折曲部近傍には、後述する支軸30が挿入される図示しない支軸孔が穿設されている。
【0022】
しかして、ベルト上方固定装置17は、以下のように組み立てられる。まず、スライド部材26左右の取付フランジ29の間に操作片32を挿入し、スライド部材26の支軸孔42と操作片32の図示しない支軸孔とを合わせた後、支軸孔42に支軸30を挿入し、支軸30の両端をかしめることにより、操作片32がスライド部材26に回転自在に取り付けられる。次いで、弾性部材としての前記スプリング39の一方の取付部を、取付フランジ29の一側端に穿設された図示しないネジ孔に取付ネジ31で取り付け、スプリング39の他方の取付部を、操作片32の一側端に穿設された図示しないネジ孔に取付ネジ36で取り付けることにより、スプリング39がスライド部材26及び操作片32に取り付けられる。そして、スライド部材26の付勢部材取付部35に穿設された付勢部材取付孔41に、付勢部材37の一方の取付部を挿通させることにより、付勢部材37がスライド部材26に取り付けられる。このスプリング39により、操作片32が図4に示す位置にある場合は、その開放状態が停止維持され、操作片32が図3に示す位置にある場合は、その挟持状態が停止維持される。
【0023】
上記のようにして組み立てられたベルト上方固定装置17をガイドレール21に取り付ける場合、ガイドレール21に穿設された図示しないガイドピン挿入孔とスライド部材26に穿設されたスライド長孔27を合わせた後、ガイドピン挿入孔にガイドピン22を挿入し、ガイドピン22の先端をガイドレール21の裏面側からかしめることにより、ガイドピン22がガイドレール21に固定されると共に、ベルト上方固定装置17がガイドレール21に装着されることとなる。ベルト上方固定装置17がガイドレール21に装着された後、付勢部材37の他方の取付部に付勢部材取付ボス38を挿通し、ガイドレール21に穿設された図示しない付勢部材取付ボス38挿入孔に付勢部材取付ボス38を挿入し、付勢部材取付ボス38の先端をガイドレール21の裏面側からかしめることにより、付勢部材取付ボス38がガイドレール21に固定される。
【0024】
なお、ガイドピン22及び付勢部材取付ボス38のガイドレール21への固定は、ガイドピン22及び付勢部材取付ボス38の先端をかしめる方法ばかりでなく、ガイドピン22及び付勢部材取付ボス38の先端をガイドレール21裏面側から溶着したり、あるいは、取替可能にするため、ガイドピン22及び付勢部材取付ボス38の先端とガイドピン挿入孔及び付勢部材取付ボス38挿入孔にネジを切ることにより、ガイドピン22及び付勢部材取付ボス38をガイドレール21に螺着させる方法でもよい。
【0025】
ところで、スライド部材26の内側幅寸法は、ガイドレール21の幅寸法よりもやや大きく形成され、また、スライド長孔27の幅寸法は、ガイドピン22の径よりもやや大きく形成されているため、上記のように、ベルト上方固定装置17がガイドレール21に取り付けられた際、スライド部材26の側方内側面とガイドレール21の側方外側面との間及びスライド長孔27の側方とガイドピン22側方との間には隙間が形成される。ここで、スライド部材26の垂直方向の中心線とガイドレール21の垂直方向の中心線を合わせて組み立てた場合、スライド部材26とガイドレール21の左右には、同じ寸法(L1とする)の隙間が形成され、また、ガイドピン22の左右には、スライド長孔27の側方との間に同じ寸法(L2とする)の隙間が形成される。このとき、隙間寸法L1,L2がL1<L2となるようにそれぞれの部材が形成されているため、スライド長孔27の側方がガイドピン22に当接する前にスライド部材26の側方内側面がガイドレール21の側方外側面に当接し、スライド長孔27の側方がガイドピン22に当接することがないので、ガイドピン22が損傷することがない。
【0026】
次に、ベルト上方固定装置17の研磨ベルト16の挟持方法について説明する。上記のようにしてガイドレール21に装着されたベルト上方固定装置17は、図3に示すように、付勢部材37の付勢力によって下方に付勢され、スライド長孔27の上端にガイドピン22が当接する位置で停止している。この状態から、取手部34の下端を時計方向に回動することにより、操作片32が支軸30を中心に回転すると共に、挟持端部33a,43aが支軸30を中心に挿入口60を開放し、図4に示すように、操作片32が開放状態となる。このとき、操作片32は、スプリング39により上方に付勢されているため、この開放状態で停止維持されている。この状態で研磨ベルト16を挿入口60に挿入する。研磨ベルト16は、約1週間使用できる分の長さを有し、研磨ベルト16の交換時(1回目)及び研磨ベルト16の研磨面更新時(2回目以降)のいずれの場合も挟持方法は同じであるため、ここでは研磨面更新時について記述する。研磨面更新時には、挿入口60より下方の研磨ベルト16を下方に引っ張り、搬送ベルト4に対向する面に研磨ベルト16の未使用面が来るまで研磨ベルト16を使用前ベルト収納箱19から順次送り出す。研磨ベルト16の未使用面が搬送ベルト4に対向する面に来たところで、緩めてあったベルト下方固定装置18を締め付けることにより、研磨ベルト16の下方をベルト下方固定装置18に固定する。研磨ベルト16の下方をベルト下方固定装置18に固定した後、予め研磨ベルト16の伸びる量を少なくするために下方に引っ張って張力を与えておく。そして操作片32を片方の手で上方に持ち上げる。操作片32を上方に持ち上げることにより、ベルト上方固定装置17全体が付勢部材37の付勢力に抗して上方に移動し、上方に移動したベルト上方固定装置17は、スライド長孔27の下端にガイドピン22が当接する位置で停止することとなる。なお、操作片32を上方に移動させる際には、取手部34をやや下方に戻し、操作片32が斜めになった状態で操作片32全体を支えて上方に移動させる。このとき、操作片32の上方への移動は、片方の手で行えるため、もう一方の手で研磨ベルト16を下方に引っ張ることができる。
【0027】
上記のように、片方の手でベルト上方固定装置17を上方の位置で保持し、もう一方の手で研磨ベルト16を下方に引っ張った状態で、片方の手で上方の位置で保持している操作片32を反時計方向に回動せしめることにより、第1ベルト挟持片33及び第2ベルト挟持片43とスライド部材26との間が閉塞されるため、図5に示すように、挟持端部33a,43aとスライド部材26との間に研磨ベルト16が挟持されることとなる。このとき、操作片32は、スプリング39により操作片32が閉塞する方向に付勢されているため、この挟持状態で停止維持されている。この状態でベルト上方固定装置17及び研磨ベルト16から手を離すと、ベルト上方固定装置17は、付勢部材37によって下方に付勢されるため、研磨ベルト16も下方に引っ張られ、研磨ベルト16に十分な張力が与えられることとなる。
【0028】
以上、ベルト上方固定装置17について詳細に説明してきたが、上記の実施形態(以下、第1実施形態という)では、スライド部材26を上方に移動させた位置において係止されないものを示したが、スライド部材26を上方に移動させた位置において係止されるものであってもよい。このような実施形態(以下、第2実施形態という)について、図6乃至図10を参照して説明する。図6は、第2実施形態に係るベルト上方固定装置17の全体を示す斜視図であり、図7は、研磨ベルト16が装着されない状態の第2実施形態に係るベルト上方固定装置17の側面図であり、図8は、上方に係止され且つ操作片32が開放状態のときの第2実施形態に係るベルト上方固定装置17の側面図であり、図9は、上方に係止され且つ操作片32が研磨ベルト16挟持状態のときの第2実施形態に係るベルト上方固定装置17の側面図であり、図10は、操作片32が研磨ベルト16挟持状態で且つガイドピン40がスライド部材係止孔46から外されたときの第2実施形態に係るベルト上方固定装置17の側面図である。なお、第1実施形態と同一の機能を奏する部品には、同じ符号を付した。
【0029】
第1実施形態と第2実施形態と異なる点は、第1実施形態のスライド部材26とガイドレール21の間にベース部材45を設け、そのベース部材45に操作片32を回転自在に軸支するスライド部材26が上下方向に移動可能に設けられている点である。そこで、第2実施形態に係るベルト上方固定装置17の構成についてさらに詳細に説明する。図6において、ベルト上方固定装置17は、ガイドレール21に密着固定されるベース部材45と、該ベース部材45に穿設されるスライド長孔47に沿って上下方向に移動可能なスライド部材26と、該スライド部材26の上部両側方に立設される取付フランジ29に設けられるガイドピン40と、前記両取付フランジ29の間に嵌入される操作片32と、前記スライド部材26の下部に設けられた付勢部材取付部35(図7参照)に取り付けられる付勢部材37と、該付勢部材37を前記ベース部材45に固定する付勢部材取付ボス38と、前記操作片32の一端側と前記取付フランジ29上方部とに掛け渡される弾性部材としてのスプリング39と、から構成されている。
【0030】
前記ベース部材45は、ステンレス等の板金により形成されるものであり、その両側方には、縦方向全長に亘ってガイドレール21の側面に当接するガイド部49が立設され、このガイド部49の上方には取付フランジ50が立設されている。このガイド部49表面には、ベース部材45をガイドレール21に取り付けるための図示しないボルト孔が穿設され、該ボルト孔に取付ボルト48を螺着することによりベース部材45をガイドレール21に固定している。また、取付フランジ50には、ガイドピン40が挿入される2条のスライド長孔47と、このスライド長孔47の上端と逆L字状に連通するスライド部材係止手段としてのスライド部材係止孔46とが穿設されている。
【0031】
また、スライド部材26は、ベース部材45と同様、ステンレス等の板金により形成されるものであり、水平断面コの字状に折り曲げて形成され、この左右の折り曲げ部分が前記取付フランジ29を形成している。この取付フランジ29には、後述する支軸30(図7参照)が挿入される支軸孔42(図7参照)が1箇所と、ガイドピン40を挿入するための図示しないガイドピン挿入孔が2箇所ずつ穿設されている。また、スライド部材26の下部には、前述のように、付勢部材取付部35が設けられており、この付勢部材取付部35の中央先端部には、付勢部材37を取り付けるための付勢部材取付孔(図示しない)が穿設されている。
【0032】
また、操作片32は、ベース部材45,スライド部材26と同様に、ステンレス等の板金により側面形状ほぼL字状に形成されるものであり、その上部は、鋭角に曲げられ、第1ベルト挟持片33を形成すると共に、この第1ベルト挟持片33の先端部は、研磨ベルト16を挟持するための挟持端部33aを形成している。また、操作片32の下部は、段差状に曲げられ、取手部34を形成すると共に、取手部34の反対側には、ステンレス等の板金により側面形状ほぼL字状に形成された第2ベルト挟持片43(図7参照)が固着されている。この第2ベルト挟持片43の先端部は、第1ベルト挟持片33と同様に研磨ベルト16を挟持するための挟持端部43a(図7参照)を形成している。更に、第1ベルト挟持片33の折曲部近傍には、後述する支軸30(図7参照)が挿入される図示しない支軸孔が穿設されている。
【0033】
しかして、第2実施形態に係るベルト上方固定装置17は、以下のように組み立てられる。まず、スライド部材26左右の取付フランジ29の間に操作片32を挿入し、スライド部材26の支軸孔42と操作片32の図示しない支軸孔とを合わせた後、支軸孔42に支軸30を挿入し、支軸30の両端をかしめることにより、操作片32がスライド部材26に回転自在に取り付けられる。次いで、弾性部材としての前記スプリング39の一方の取付部を、取付フランジ29の一側端に穿設された図示しないネジ孔に取付ネジ31で取り付け、スプリング39の他方の取付部を、操作片32の一側端に穿設された図示しないネジ孔に取付ネジ36で取り付けることにより、スプリング39がスライド部材26及び操作片32に取り付けられる。そして、スライド部材26の付勢部材取付部35に穿設された付勢部材取付孔に、付勢部材37の一方の取付部を挿通させることにより、付勢部材37がスライド部材26に取り付けられる。
【0034】
上記のように、操作片32,スプリング39,付勢部材37を取り付けたスライド部材26をベース部材45左右の取付フランジ50の間に挿入し、取付フランジ29の前記ガイドピン挿入孔とスライド長孔47とを合わせた後、図示しないガイドピン挿入孔にガイドピン40を挿入し、ガイドピン40の先端を取付フランジ29の内側面からかしめることにより、ガイドピン40が取付フランジ29に固定されると共に、スライド部材26がベース部材45に装着されることとなる。次いで、スライド部材26がベース部材45に装着された後、付勢部材37の他方の取付部に付勢部材取付ボス38を挿通し、ベース部材45に穿設された図示しない付勢部材取付ボス38挿入孔に付勢部材取付ボス38を挿入し、付勢部材取付ボス38の先端をベース部材45の裏面側からかしめることにより、付勢部材取付ボス38がベース部材45に固定される。
【0035】
なお、ガイドピン40及び付勢部材取付ボス38の取付フランジ29及びベース部材45へのそれぞれの固定は、ガイドピン40及び付勢部材取付ボス38の先端をかしめる方法ばかりでなく、ガイドピン40及び付勢部材取付ボス38の先端を取付フランジ29及びベース部材45の内側面から溶着したり、あるいは取替可能にするため、ガイドピン40及び付勢部材取付ボス38の先端とガイドピン挿入孔及び付勢部材取付ボス38挿入孔にネジを切ることにより、ガイドピン40及び付勢部材取付ボス38を取付フランジ29及びベース部材45に螺着させる方法でもよい。
【0036】
上記のようにして組み立てられたベルト上方固定装置17をガイドレール21に取り付ける場合、ベース部材45のガイド部49に穿設された図示しない前記ボルト孔とガイドレール21に穿設された図示しないネジ孔を合わせた後、ネジ孔に取付ボルト48を螺着することにより、ベルト上方固定装置17がガイドレール21に装着されることとなる。
【0037】
次に、第2実施形態に係るベルト上方固定装置17の研磨ベルト16の挟持方法について説明する。上記のようにしてガイドレール21に装着されたベルト上方固定装置17は、図7に示すように、付勢部材37の付勢力によって下方に付勢され、スライド長孔47の下端にガイドピン40が当接する位置で停止している。この状態から、取手部34の下端を時計方向に回動することにより、操作片32が支軸30を中心に回転すると共に、挟持端部33a,43aが支軸30を中心に挿入口60を開放し、図8に示すように、操作片32が開放状態となる。この状態で研磨ベルトを挿入口60に挿入する。研磨ベルト16は、約1週間使用できる分の長さを有し、研磨ベルト16の交換時(1回目)及び研磨ベルト16の研磨面更新時(2回目以降)のいずれの場合も挟持方法は同じであるため、ここでは研磨面更新時について記述する。研磨面更新時には、挿入口60より下方の研磨ベルト16を下方に引っ張り、搬送ベルト4に対向する面に研磨ベルト16の未使用面が来るまで研磨ベルト16を使用前ベルト収納箱19から順次送り出す。研磨ベルト16の未使用面が搬送ベルト4に対向する面に来たところで、緩めてあったベルト下方固定装置18を締め付けることにより、研磨ベルト16の下方をベルト下方固定装置18に固定する。研磨ベルト16の下方をベルト下方固定装置18に固定した後、予め研磨ベルト16の伸びる量を少なくするために下方に引っ張って張力を与えておく。そして操作片32を片方の手で上方に持ち上げる。操作片32を上方に持ち上げることにより、スライド部材26が付勢部材37の付勢力に抗して上方に移動し、上方に移動したスライド部材26は、スライド長孔47の上端にガイドピン40が当接する位置で停止することとなる。更に、この状態から、操作片32を手前に引くことにより、図8に示すように、ガイドピン40がスライド部材係止孔46に嵌入するため、ガイドピン40がスライド部材係止孔46に係止された状態でスライド部材26が停止することとなる。このスライド部材係止孔46は、スライド長孔47の上端から斜め下方に向かって穿設されているため、スライド部材26に外力を加えない限りガイドピン40がスライド長孔47に入り込むことはなく、スライド部材26が下方に移動することはない。なお、操作片32を上方に移動させる際には、取手部34をやや下方に戻し、操作片32が斜めになった状態で操作片32全体を支えて上方に移動させる。
【0038】
このように、スライド部材26が上方に移動させた位置で係止されていると共に、操作片32がスプリング39により上方に付勢されているため、取手部34から手を離してもスライド部材26が付勢部材37の付勢力に抗して上方に移動させた状態で停止させることができると共に、操作片32の開放状態を保持することができる。
【0039】
そして、片方の手で研磨ベルト16を下方に引っ張りながらもう一方の手で操作片32を反時計方向に回動せしめることにより、操作片32を回転させ、第1ベルト挟持片33及び第2ベルト挟持片43とスライド部材26との間が閉塞されるため、図9に示すように、挟持端部33a,43aとスライド部材26との間に研磨ベルト16が挟持されることとなる。このとき、操作片32は、スプリング39(図6参照)により操作片32が閉塞する方向に付勢されているため、この挟持状態で停止維持されている。この状態から、操作片32の背面をガイドレール21側に向かって押しこむことにより、図10に示すように、ガイドピン40がスライド部材係止孔46から外れ、その後スライド部材26が付勢部材37によって下方に付勢されるため、研磨ベルト16も下方に引っ張られることとなり、研磨ベルト16に十分な張力が与えられることとなる。なお、研磨ベルト16は、スライド部材26がスライド部材係止孔46に係止されている位置でスライド部材26に挟持されるものであるが、スライド部材26に研磨ベルト16を挟持後、スライド部材26をスライド部材係止孔46からスライド長孔47へ移動させる際に、スライド部材26を一旦上方に移動させるため、研磨ベルト16が若干たわむこととなる。そして、スライド部材26がスライド長孔47へ移動した後、研磨ベルト16のたわみ分だけスライド部材26がスライド長孔47内で下方に下がる。このため、スライド部材26は、スライド長孔47から再びスライド部材係止孔側へ移動することはない。
【0040】
以上、第2実施形態に係るベルト上方固定装置17について詳細に説明してきたが、上記した第1及び第2実施形態に係るベルト上方固定装置17では、スライド部材26の上下方向の移動をガイドピン22,40に沿って行うものを示したが、ガイドピン22,40によらず、別の方法によってスライド部材26の上下動をガイドするものであってもよい。そこで、スライド部材26がガイドピン22,40によらず上下動するベルト上方固定装置17の実施形態(以下、第3実施形態という)について説明する。
【0041】
まず、第3実施形態に係るベルト上方固定装置17の構成について、図11を参照して説明する。図11は、第3実施形態に係るベルト上方固定装置17の全体を示す斜視図である。なお、第1実施形態及び第2実施形態と同一の機能を奏する部品には、同じ符号を付した。
【0042】
図11において、ベルト上方固定装置17は、ガイドレール21に密着固定されるベース部材45と、該ベース部材45表面に固着されるガイド部材55に沿って上下方向に移動可能なスライド部材26と、該スライド部材26の両側方に立設される取付フランジ29の間に嵌入される操作片32と、前記スライド部材26の下部に設けられた付勢部材取付部35に取り付けられる付勢部材37と、該付勢部材37を前記ベース部材45に固定する付勢部材取付ボス38と、前記操作片32の一端側と前記取付フランジ29上方部とに掛け渡されるスプリング39と、から構成されている。
【0043】
前記ベース部材45は、ステンレス等の板金により形成されるものであり、その両側方には、縦方向全長に亘ってガイドレール21の側面に当接するガイド部49が立設されている。このガイド部49表面には、ベース部材45をガイドレール21に取り付けるための図示しないボルト孔が穿設され、該ボルト孔に取付ボルト48を螺着することにより、ベース部材45をガイドレール21に固定している。また、ベース部材45の表面の上部両側端には、L字状のガイド部材55が固着され、ベース部材45とガイド部材55との間に形成される隙間にスライド部材26の両端辺が挿入されるようになっている。また、ベース部材45のほぼ中央には、スライド部材停止片56が突設されている。
【0044】
また、スライド部材26は、ベース部材45と同様、ステンレス等の板金により形成されるものであり、スライド部材26の両側方からやや内側の位置にそれぞれ取付フランジ29が立設され、この取付フランジ29には、後述する支軸30が挿入される支軸孔42が穿設されている。また、スライド部材26の下部には、前述のように、段差状に曲げられて形成された付勢部材取付部35が設けられており、この付勢部材取付部35の中央部には、付勢部材37を取り付けるための付勢部材取付孔41が穿設されている。
【0045】
また、操作片32は、ベース部材45,スライド部材26と同様に、ステンレス等の板金により側面形状ほぼL字状に形成されるものであり、その上部は、鋭角に曲げられ、第1ベルト挟持片33を形成すると共に、この第1ベルト挟持片33の先端部は、研磨ベルト16を挟持するための挟持端部33aを形成している。また、操作片32の下部は、段差状に曲げられ、取手部34を形成すると共に、取手部34の反対側には、ステンレス等の板金により側面形状ほぼL字状に形成された図示しない第2ベルト挟持片が固着されている。この第2ベルト挟持片の先端部は、第1ベルト挟持片33と同様に研磨ベルト16を挟持するための図示しない挟持端部を形成している。更に、第1ベルト挟持片33の折曲部近傍には、後述する支軸30が挿入される図示しない支軸孔が穿設されている。
【0046】
しかして、第3実施形態に係るベルト上方固定装置17は、以下のように組み立てられる。まず、スライド部材26左右の取付フランジ29の間に操作片32を挿入し、スライド部材26の支軸孔42と操作片32の図示しない支軸孔とを合わせた後、支軸孔42に支軸30を挿入し、支軸30の両端をかしめることにより、操作片32がスライド部材26に回転自在に取り付けられる。次いで、弾性部材としての前記スプリング39の一方の取付部を、取付フランジ29の一側端に穿設された図示しないネジ孔に取付ネジ31で取り付け、スプリング39の他方の取付部を、操作片32の一側端に穿設された図示しないネジ孔に取付ネジ36で取り付けることにより、スプリング39がスライド部材26及び操作片32に取り付けられる。そして、スライド部材26の付勢部材取付部35に穿設された付勢部材取付孔41に、付勢部材37の一方の取付部を挿通させることにより、付勢部材37がスライド部材26に取り付けられる。
【0047】
上記のように、操作片32,スプリング39,付勢部材37を取り付けたスライド部材26の両端辺をベース部材45左右に固着されたガイド部材55とベース部材45との間の隙間に挿入することにより、スライド部材26がベース部材45に装着されることとなる。次いで、スライド部材26がベース部材45に装着された後、付勢部材37の他方の取付部に付勢部材取付ボス38を挿通し、ベース部材45に穿設された図示しない付勢部材取付ボス38挿入孔に付勢部材取付ボス38を挿入し、付勢部材取付ボス38の先端をベース部材45の裏面側からかしめることにより、付勢部材取付ボス38がベース部材45に固定される。
【0048】
上記のように、スライド部材26がベース部材45に装着された場合、スライド部材26は、付勢部材37により下方に付勢されるが、スライド部材26の下端がスライド部材停止片56に当接するため、スライド部材26の下端がスライド部材停止片56に当接する位置よりも下方に移動することはない。
【0049】
なお、付勢部材取付ボス38のベース部材45への固定は、付勢部材取付ボス38の先端をかしめる方法ばかりでなく、付勢部材取付ボス38の先端をベース部材45の内側面から溶着したり、あるいは、取替可能にするため、付勢部材取付ボス38の先端と付勢部材取付ボス38挿入孔にネジを切ることにより、付勢部材取付ボス38を取ベース部材45に螺着させる方法でもよい。
【0050】
上記のようにして組み立てられたベルト上方固定装置17をガイドレール21に取り付ける場合、ベース部材45のガイド部49に穿設された図示しない前記ボルト孔とガイドレール21に穿設された図示しないネジ孔を合わせた後、ネジ孔に取付ボルト48を螺着することにより、ベルト上方固定装置17がガイドレール21に装着されることとなる。
【0051】
次に、第3実施形態に係るベルト上方固定装置17の研磨ベルト16の挟持方法について説明するが、第1実施形態に係るベルト固定装置17の研磨ベルト16の装着方法との相違点は僅かであるため、図4及び図5と比較しながら説明する。
【0052】
上記のようにしてガイドレール21に装着されたベルト上方固定装置17のスライド部材26は、付勢部材37の付勢力によって下方に付勢され、スライド部材停止片56にスライド部材26が当接する位置で停止している。この状態から、取手部34の下端を時計方向に回動することにより、操作片32が支軸30を中心に回転すると共に、挟持端部33aが支軸30を中心に開放し、図4に示すように、操作片32が開放状態となる。このとき、操作片32は、スプリング39により上方に付勢されているため、この開放状態で停止維持されている。この状態で研磨ベルトを挿入口60に挿入する。研磨ベルト16は、約1週間使用できる分の長さを有し、研磨ベルト16の交換時(1回目)及び研磨ベルト16の研磨面更新時(2回目以降)のいずれの場合も挟持方法は同じであるため、ここでは研磨面更新時について記述する。研磨面更新時には、挿入口60より下方の研磨ベルト16を下方に引っ張り、搬送ベルト4に対向する面に研磨ベルト16の未使用面が来るまで研磨ベルト16を使用前ベルト収納箱19から順次送り出す。研磨ベルト16の未使用面が搬送ベルト4に対向する面に来たところで、緩めてあったベルト下方固定装置18を締め付けることにより、研磨ベルト16の下方をベルト下方固定装置18に固定する。研磨ベルト16の下方をベルト下方固定装置18に固定した後、予め研磨ベルト16の伸びる量を少なくするために下方に引っ張って張力を与えておく。そして操作片32を片方の手で上方に持ち上げる。操作片32を上方に持ち上げることにより、スライド部材26が付勢部材37の付勢力に抗して上方に移動するが、スライド部材26の上方への移動を規制するものはないため、スライド部材26は、ガイド部材55から離脱しない範囲で上方に移動させることができる。なお、操作片32を上方に移動させる際には、取手部34をやや下方に戻し、操作片32が斜めになった状態で操作片32全体を支えて上方に移動させる。このとき、操作片32の上方への移動は、片方の手でできるため、もう一方の手で研磨ベルト16を下方に引っ張ることができる。
【0053】
上記のように、片方の手でスライド部材26を上方の位置で保持し、もう一方の手で研磨ベルト16を下方に引っ張った状態で、片方の手で上方の位置で保持している。操作片32を反時計方向に回動せしめることにより、第1ベルト挟持片33及び第2ベルト挟持片とスライド部材26との間が閉塞されるため、図5に示すように、挟持端部33aとスライド部材26との間に研磨ベルト16が挟持されることとなる。このとき、操作片32は、スプリング39により操作片32が閉塞する方向に付勢されているため、この挟持状態で停止維持されている。この状態でスライド部材26から手を離すと、スライド部材26は、付勢部材37によって下方に付勢されるため、研磨ベルト16も下方に引っ張られることとなり、研磨ベルト16に十分な張力が与えられることとなる。
【0054】
以上、複数の実施形態に係る玉揚送装置について詳細に説明してきたが、本実施形態においては、駆動源により回転する複数のローラ間を周回せしめられる搬送ベルト4と、該搬送ベルト4の外周面に対向して設置されるガイドレール21に掛け渡して装着される研磨ベルト16と、前記ガイドレール21の外側面に設置され且つ前記研磨ベルト16の上方側を固定するベルト上方固定装置17と、を備えた玉揚送装置1において、前記ベルト上方固定装置17は、前記ガイドレール21の外側面に沿って垂直方向に移動可能なスライド部材26と、該スライド部材26を下方に付勢する付勢部材37と、前記スライド部材26を前記付勢部材37の付勢力に抗して上方に移動させる操作片32と、を備え、前記操作片32は、該操作片32を前記付勢部材37の付勢力に抗して上方に持ち上げてスライド部材26を上方に移動させた状態で、ベルト上方固定装置17に研磨ベルト16を挿入可能な開放状態と、ベルト上方固定装置17に研磨ベルト16を挟持させる挟持状態とに変位可能にしたことを特徴とするものである。このように構成することにより、操作片32でスライド部材26を上方に移動させた状態のままで操作片32を操作して研磨ベルト16をベルト上方固定装置17に挿入,挟持した後、スライド部材26が付勢部材37によって下方に付勢されるため、研磨ベルト16に十分な張力を与えて装着することが容易に行うことができる。
【0055】
また、本実施形態においては、前記ベルト上方固定装置17には、前記スライド部材26を上方に移動させた位置で係止させるスライド部材係止手段を設けたことにより、操作片32でスライド部材26を上方に移動させた状態のままでスライド部材係止手段でスライド部材を係止して操作片32を操作し、研磨ベルト16をベルト上方固定装置17に挿入,挟持した後、スライド部材26の係止を解除することにより付勢部材37によって下方に付勢されるため、研磨ベルト16に十分な張力を与えて装着することが容易に行うことができる。
【0056】
また、本実施形態においては、前記スライド部材係手段は、前記操作片32の操作により係止させることにより、スライド部材26の上方への移動,スライド部材26の係止,研磨ベルト16の挟持及びスライド部材26のスライド部材係止手段からの取外しまでの一連の操作がすべて操作片32により操作可能なため、上記一連の操作を容易に行うことができる。
【0057】
また、本実施形態においては、前記ベルト上方固定装置17には、前記操作片32を前記開放状態及び挟持状態でそれぞれ停止維持するように付勢する弾性部材を設けたことにより、操作片32の開放状態時に容易に研磨ベルト16をベルト上方固定装置17に挿入することができると共に、研磨ベルト16の挟持状態時により強固に研磨ベルト16を挟持することができる。また、操作片32のグラつきを防止することができる。
【0058】
更に、本実施形態においては、駆動源により回転する複数のローラ間を周回せしめられる搬送ベルト4と、該搬送ベルト4の外周面に対向して設置されるガイドレール21に掛け渡して装着される研磨ベルト16と、前記ガイドレール21の外側面に設置され且つ前記研磨ベルト16の上方側を固定するベルト上方固定装置17と、を備えた玉揚送装置1において、前記ベルト上方固定装置17は、前記ガイドレール21の外側面に沿って垂直方向に移動可能で且つ研磨ベルト16を開放挟持する挟持部を有するスライド部材26と、該スライド部材26を下方に付勢する付勢部材37と、を備え、前記スライド部材26を上方に移動させた位置で係止させるスライド部材係止手段を設けたことを特徴とするものである。このように構成することにより、スライド部材26の上方への移動,スライド部材26の係止及びスライド部材26への研磨ベルト16の挟持の操作を同時に行う必要がなく、各操作を順に行うことができるため、研磨ベルト16に十分な張力を与えて装着することが容易に行うことができる。
【0059】
なお、第2実施形態において、スライド部材26を上方で停止させるスライド部材係止手段としてガイドピン40をスライド部材係止孔46に嵌入させるものを示したが、スライド部材26が上方で停止するものであればよく、例えば、ベース部材45表面上を出没する突起物をベース部材45に設け、スライド部材26が上方に移動した時点で、突起物が突出してスライド部材26の下端を支えるようなものや、スライド部材26とベース部材45にピンを貫通させるようなものや、スライド部材26を挟持するようなものであってもよい。
【0060】
また、第2実施形態で示したスライド部材26のスライド部材係止手段は、第1実施形態及び第3実施形態に適用してもよい。
【0061】
また、第2実施形態又は第3実施形態において、ベース部材45をガイドレール21両側面に取付ボルト48を螺着して装着したものを示したが、両側面にレールが形成されたガイドレールを用い、このレールにベース部材45を装着することによりベース部材45を上下動可能にできるため、ベース部材45の取付位置調整や取付位置変更が可能となる。また、ベルト上方固定装置17は、樹脂で形成したものであってもよい。
【0062】
更に、第1実施形態乃至第3実施形態において、研磨ベルト16を開放挟持する挟持部として操作片32を示したが、研磨ベルト16を開放挟持するものであればよく、例えば、従来技術の欄に記載した出願に開示される挟持部のようにベルトを挟持するものや、万力のような機構を用いたものでもよい。また、研磨ベルト16を挟持するための挟持片が2つ(第1ベルト挟持片33,第2ベルト挟持片43)形成されている操作片32を示したが、研磨ベルト16を固定させるものであればよく、例えば、1つ又は3つ以上の挟持片が形成されるものや、挟持端部が鋸歯状又はローレット状に形成されたものであってもよい。また、付勢部材37としてスプリングを示したが、スプリングに限らず、スライド部材26を下方に付勢するものであればよく、例えば重りで荷重をかけてスライド部材26を付勢するものや、ゴム,板バネ等の弾性部材を利用してスライド部材26を付勢するものであってもよい。また、付勢部材37の取付位置は、スライド部材26を鉛直方向に付勢できる位置であればよく、例えば、スライド部材の表面両端又は側面の片方あるいは両方に付勢部材37が取付られるものであってもよい。また、第1実施形態において、スライド長孔27及びガイドピン22をガイドレール21表面側にそれぞれ2箇所ずつ設けたものを示したが、スライド長孔27及びガイドピン22がガイドレール21の両側面に設けられるものであってもよく、また、1箇所あるいは3箇所以上設けられるものであってもよい。更に、研磨ベルト16は、玉揚送装置1のほぼ全長に亘って設けられるものを示したが、玉揚送装置1に適宜長さに亘って設けられていればよく、例えば、ガイドレール21を全長に亘って上下2つに分割して構成し、分割した片側のガイドレール21にのみ研磨ベルト16が設けられるものであってもよい。
【0063】
【発明の効果】
以上、説明したところから明らかなように、請求項1に係る発明においては、駆動源により回転する複数のローラ間を周回せしめられる搬送ベルトと、該搬送ベルトの外周面に対向して設置されるガイドレールに掛け渡して装着される研磨ベルトと、前記ガイドレールの外側面に設置され且つ前記研磨ベルトの上方側を固定するベルト上方固定装置と、を備えた玉揚送装置において、前記ベルト上方固定装置は、前記ガイドレールの外側面に沿って垂直方向に移動可能で且つ研磨ベルトを開放挟持する挟持部を有するスライド部材と、該スライド部材を下方に付勢する付勢部材と、を備え、前記スライド部材を上方に移動させた位置で停止させるスライド部材停止手段を設けたことを特徴とするものである。このように構成することにより、スライド部材の上方への移動,スライド部材の停止及びスライド部材への研磨ベルトの挟持の操作を同時に行う必要がなく、各操作を順に行うことができるため、研磨ベルトに十分な張力を与えて装着することが容易に行うことができる。
【0064】
また、請求項2に係る発明においては、駆動源により回転する複数のローラ間を周回せしめられる搬送ベルトと、該搬送ベルトの外周面に対向して設置されるガイドレールに掛け渡して装着される研磨ベルトと、前記ガイドレールの外側面に設置され且つ前記研磨ベルトの上方側を固定するベルト上方固定装置と、を備えた玉揚送装置において、前記ベルト上方固定装置は、前記ガイドレールの外側面に沿って垂直方向に移動可能なスライド部材と、該スライド部材を下方に付勢する付勢部材と、前記スライド部材を前記付勢部材の付勢力に抗して上方に移動させる操作片と、を備え、前記操作片は、該操作片を前記付勢部材の付勢力に抗して上方に持ち上げてスライド部材を上方に移動させた状態で、ベルト上方固定装置に研磨ベルトを挿入可能な開放状態と、ベルト上方固定装置に研磨ベルトを挟持させる挟持状態とに変位可能にすると共に、前記ベルト上方固定装置には、前記操作片を前記開放状態及び挟持状態でそれぞれ停止維持するように付勢する弾性部材を設けたことを特徴とするものである。このように構成することにより、操作片でスライド部材を上方に移動させた状態のままで操作片を操作して研磨ベルトをベルト上方固定装置に挿入,挟持した後、スライド部材が付勢部材によって下方に付勢されるため、研磨ベルトに十分な張力を与えて装着することが容易に行うことができる。また、操作片の開放状態時に容易に研磨ベルトをベルト上方固定装置に挿入することができると共に、研磨ベルトの挟持状態時により強固に研磨ベルトを挟持することができる。また、操作片のグラつきを防止することができる。
【0065】
また、請求項3に係る発明においては、駆動源により回転する複数のローラ間を周回せしめられる搬送ベルトと、該搬送ベルトの外周面に対向して設置されるガイドレールに掛け渡して装着される研磨ベルトと、前記ガイドレールの外側面に設置され且つ前記研磨ベルトの上方側を固定するベルト上方固定装置と、を備えた玉揚送装置において、前記ベルト上方固定装置は、前記ガイドレールの外側面に沿って垂直方向に移動可能なスライド部材と、該スライド部材を下方に付勢する付勢部材と、前記スライド部材を前記付勢部材の付勢力に抗して上方に移動させる操作片と、を備え、前記操作片は、該操作片を前記付勢部材の付勢力に抗して上方に持ち上げてスライド部材を上方に移動させた状態で、ベルト上方固定装置に研磨ベルトを挿入可能な開放状態と、ベルト上方固定装置に研磨ベルトを挟持させる挟持状態とに変位可能にすると共に、前記ベルト上方固定装置には、前記スライド部材を上方に移動させた位置で、前記操作片の操作により係止させるスライド部材係止手段を設けたことを特徴とするものである。このように構成することにより、操作片でスライド部材を上方に移動させた状態のままでスライド部材係止手段でスライド部材を係止して操作片を操作し、研磨ベルトをベルト上方固定装置に挿入,挟持した後、スライド部材の係止を解除することにより付勢部材によって下方に付勢されるため、研磨ベルトに十分な張力を与えて装着することが容易に行うことができる。また、スライド部材の上方への移動,スライド部材の係止,研磨ベルトの挟持及びスライド部材のスライド部材係止手段からの取外しまでの一連の操作がすべて操作片により操作可能なため、上記一連の操作を容易に行うことができる。
【0066】
【0067】
【図面の簡単な説明】
【図1】 玉揚送装置を後方から見た斜視図である。
【図2】 第1実施形態に係るベルト上方固定装置の全体を示す斜視図である。
【図3】 研磨ベルトが装着されていない状態の第1実施形態に係るベルト上方固定装置の側面図である。
【図4】 操作片が開放状態のときの第1実施形態に係るベルト上方固定装置の側面図である。
【図5】 操作片が研磨ベルト挟持状態のときの第1実施形態に係るベルト上方固定装置の側面図である。
【図6】 第2実施形態に係るベルト上方固定装置の全体を示す斜視図である。
【図7】 研磨ベルトが装着されない状態の第2実施形態に係るベルト上方固定装置の側面図である。
【図8】 上方に係止され且つ操作片が開放状態のときの第2実施形態に係るベルト上方固定装置の側面図である。
【図9】 上方に係止され且つ操作片が研磨ベルト挟持状態のときの第2実施形態に係るベルト上方固定装置の側面図である。
【図10】 操作片が研磨ベルト挟持状態で且つガイドピンがスライド部材係止孔から外されたときの第2実施形態に係るベルト上方固定装置の側面図である。
【図11】 第3実施形態に係るベルト上方固定装置の全体を示す斜視図である。
【符号の説明】
1 玉揚送装置
3 揚送筒本体
4 搬送ベルト
5 テンションローラ機構
15 支持ヒンジ
16 研磨ベルト
17 ベルト上方固定装置
18 ベルト下方固定装置
19 使用前ベルト収納箱
20 使用後ベルト収納箱
21 ガイドレール
22 ガイドピン
26 スライド部材
27 スライド長孔
28 ガイド部
29 取付フランジ
30 支軸
32 操作片
33 第1ベルト挟持片
33a 挟持端部
34 取手部
35 付勢部材取付部
36 取り付けネジ
37 付勢部材
38 付勢部材取付ボス
39 スプリング
40 ガイドピン
41 付勢部材取り付け孔
42 支軸孔
43 第2ベルト挟持片
43a 挟持端部
45 ベース部材
46 スライド部材係止孔
47 スライド長孔
48 取付ボルト
49 ガイド部
50 取付フランジ
55 ガイド部材
56 スライド部材停止片
[0001]
BACKGROUND OF THE INVENTION
  The present invention includes a conveying belt that is circulated between a plurality of rollers that are rotated by a driving source, a polishing belt that is mounted on a guide rail that is installed to face the outer peripheral surface of the conveying belt, and the guide rail. And a belt upper fixing device that is installed on the outer surface of the belt and fixes the upper side of the polishing belt.
[0002]
[Prior art]
  Conventionally, a ball lifting device that lifts pachinko balls is mounted on a conveyor belt (skin belt) that circulates around a roller that is rotated by a drive source, and spans the upper and lower ends of the guide rail so as to face the conveyor belt. It is known that a pachinko ball is sandwiched between a polishing belt (cloth belt) to be transported. Normally, the polishing belt of such a ball feeding device has the upper and lower ends of the polishing belt sandwiched and fixed on the outer surface of the guide rail, but the polishing belt is interposed between the conveying belt when the ball lifting device is driven. The polishing belt may be stretched by being affected by the pinched pachinko balls, and the polishing belt may be doubled as it extends above the ball lifting device. For this reason, as shown in JP-A-9-730, there is provided a ball lifting device capable of constantly holding the polishing belt in a tensioned state by eliminating the dubbing of the polishing belt by constantly pulling the polishing belt. Proposed. This ball lifting device is provided with an upper fixing device that constantly urges the upper end of the polishing belt downward on the outer surface of the guide rail so as to keep the polishing belt in a tensioned state. In addition, the upper fixing device includes a pin formed by projecting on the outer surface of the guide rail, a slide plate having a long hole through which the pin passes, and an upper end of the slide plate, which holds and fixes the polishing belt. And a biasing member that biases the slide plate downward.
[0003]
[Problems to be solved by the invention]
  However, when actually using the above-described upper fixing device, while pulling the polishing belt in a state where the slide plate is lifted upward (maintained at a position against the biasing member) (to reduce the amount of extension in advance), The upper end of the polishing belt must be held in the holding portion. As described above, the sandwiching operation of the polishing belt, which is performed by simultaneously performing the three operations, is difficult even when performed using both hands. In addition, since the clamping work is difficult, even if the polishing belt is somehow attached, it may be attached in a state where sufficient tension is not applied to the attached polishing belt. However, there was a problem that it would be stuck when the ball lifting device was driven. The present invention has been made in view of the above-described circumstances, and an object of the present invention is to provide a ball lifting device that can be easily mounted by applying sufficient tension to the polishing belt. is there.
[0004]
[Means for Solving the Problems]
  In order to achieve the above-described object, in the invention according to claim 1, a conveying belt that is circulated between a plurality of rollers that are rotated by a driving source, and a guide rail that is installed facing the outer peripheral surface of the conveying belt. The ball upper fixing device, comprising: a polishing belt that is mounted over the belt; and a belt upper fixing device that is installed on an outer surface of the guide rail and fixes an upper side of the polishing belt. Comprises a slide member that is movable in the vertical direction along the outer surface of the guide rail and that has a holding portion that opens and holds the polishing belt, and a biasing member that biases the slide member downward, At the position where the slide member is moved upwardStopSliding memberStopMeans is provided. With this configuration, the slide member is moved upward, the slide memberStopFurther, it is not necessary to perform the operation of sandwiching the polishing belt on the slide member at the same time, and each operation can be performed in order, so that it is possible to easily attach the polishing belt with sufficient tension.
[0005]
  In the invention according to claim 2, the belt is mounted on a conveyor belt that is circulated between a plurality of rollers that are rotated by a drive source, and a guide rail that is installed to face the outer peripheral surface of the conveyor belt. A ball lifting device comprising: a polishing belt; and a belt upper fixing device that is installed on an outer surface of the guide rail and fixes an upper side of the polishing belt. The belt upper fixing device is provided on the outer side of the guide rail. A slide member movable in the vertical direction along the side surface; a biasing member that biases the slide member downward; an operation piece that moves the slide member upward against the biasing force of the biasing member; The operation piece is inserted into the belt upper fixing device in a state where the operation piece is lifted upward against the urging force of the urging member and the slide member is moved upward. An open state capable, displaceably in the clamping state to sandwich the abrasive belt to the belt upper restraint deviceIn addition, the belt upper fixing device is provided with an elastic member that urges the operation piece to be stopped and maintained in the opened state and the clamped state, respectively.It is characterized by this. With this configuration, after the slide member is moved upward with the operation piece, the operation piece is operated to insert and hold the polishing belt into the belt upper fixing device, and then the slide member is moved by the biasing member. Since it is biased downward, it can be easily attached with sufficient tension applied to the polishing belt.Further, the polishing belt can be easily inserted into the belt upper fixing device when the operation piece is opened, and the polishing belt can be more firmly held when the polishing belt is held. In addition, it is possible to prevent the operation piece from being blurred.
[0006]
  In the invention according to claim 3,A conveyor belt that is circulated between a plurality of rollers that are rotated by a driving source, an abrasive belt that is mounted on a guide rail that is installed opposite to the outer peripheral surface of the conveyor belt, and an outer surface of the guide rail. A ball lifting device comprising a belt upper fixing device installed and fixing an upper side of the polishing belt, wherein the belt upper fixing device is a slide that is movable in a vertical direction along an outer surface of the guide rail. A member, an urging member that urges the slide member downward, and an operation piece that moves the slide member upward against the urging force of the urging member. An open state in which the polishing belt can be inserted into the belt upper fixing device in a state where the piece is lifted upward against the biasing force of the biasing member and the slide member is moved upward, and the belt upper fixing device While the displaceable grinding belt and sandwiching state to be sandwiched,In the belt upper fixing device, the slide member is moved upward.By operating the operation pieceProvided with slide member locking means to lockIt is characterized by this. Configure like thisThus, after the slide member is moved upward by the operation piece, the slide member is locked by the slide member locking means, the operation piece is operated, and the polishing belt is inserted and clamped in the belt upper fixing device. Since the slide member is unlocked and is urged downward by the urging member, it is possible to easily attach the polishing belt with sufficient tension.In addition, since the series of operations from the slide member upward movement, the slide member locking, the sandwiching of the polishing belt, and the removal of the slide member from the slide member locking means can all be operated by the operation piece, Operation can be performed easily.
[0007]
[0008]
[0009]
DETAILED DESCRIPTION OF THE INVENTION
  Hereinafter, embodiments of the present invention will be described with reference to the drawings. First, the whole structure of the ball feeding apparatus which comprises the principal part of this embodiment is demonstrated with reference to FIG. FIG. 1 is a perspective view of the ball lifting device 1 as viewed from the rear.
[0010]
  In the figure, a ball lifting device 1 has a lifting cylinder body 3 formed of the same material as that of a support base 2 on a support base 2 formed of a thick steel plate. A leather-made conveyor belt 4 laid between a driving lower roller (not shown) located at the lower portion of the main body 3 and an upper roller (not shown) located at the upper portion so as to circulate around the feeding cylinder main body 3. It has become. The lifting cylinder main body 3 has a rectangular shape with an opening on one side surface, and a lifting cylinder cover (not shown) is attached to the opening surface with an attachment screw. The lifting cylinder cover is fixed over the entire length of the lifting cylinder body 3 so as to cover the opening surface of the lifting cylinder body 3, and when the upper roller and the lower roller are repaired or replaced, or the lifting cylinder In the event of a trouble in the main body 3, the lifting tube cover can be removed to repair, replace, or deal with the trouble.
[0011]
  The transport belt 4 is driven to rotate around the feeding cylinder body 3 by the rotation of the lower roller built in the motor. In order to apply tension to the conveyor belt 4, a tension roller mechanism 5 including a first tension roller 6, a second tension roller 7, and a third tension roller 8 with which the conveyor belt 4 abuts alternately is provided with a feeding cylinder body 3. It is attached to the bottom of the. The first tension roller 6 and the third tension roller 8 of the tension roller mechanism 5 can be opened and closed, and are mainly operated when the transport belt 4 is replaced. In addition, an introduction rod 9 for fixing the inflowing pachinko balls in a plurality of rows is fixed to the lower part of the lifting cylinder body 3, and the pachinko balls after polishing are discharged to the upper part of the lifting cylinder body 3. A discharge port 11 is formed.
[0012]
  Thus, the pachinko balls that have flowed in from the introduction rod 9 are lifted by the conveyor belt 4 and then discharged from the discharge port 11. In the process of being lifted, the pachinko balls are provided around a guide rail 21 described below. The dirt adhering to the pachinko balls is wiped off by the frictional force with the polishing belt 16, and the cleaned pachinko balls are discharged from the discharge port 11. As shown in FIG. 1, an inclination angle adjusting bolt 10 that adjusts the inclination angle of the introduction rod 9 is attached to the introduction rod 9. The inclination angle adjusting bolt 10 is provided with a spring so that the pachinko balls are smoothly aligned even when an excessive force is applied to the introduction rod 9 by the pachinko balls flowing inside. .
[0013]
  On the other hand, a guide rail 21 is attached to the back side of the above-described lifting cylinder body 3 through a support hinge 15 attached to one side surface of the lifting cylinder body 3 so as to be freely opened and closed. The support hinges 15 are provided at several locations in the vertical direction of the feed cylinder body 3. A stopper 13 is attached to the other side surface of the lifting cylinder body 3 via a stopper 14, and the guide rail 21 has a stopper 13 at a position corresponding to the stopper 13. An engaging projection 12 is provided for locking the.
[0014]
  A belt upper fixing device 17 that fixes the upper side of the polishing belt 16 and a belt lower fixing device 18 that fixes the lower side of the polishing belt 16 are attached to the guide rail 21. A polishing belt roller (not shown) is provided at the upper end to guide the polishing belt 16 back. Thus, the polishing belt 16 fixed to the belt lower fixing device 18 circulates around the guide rail 21 from the lower end of the guide rail 21, is wound around the polishing belt roller, and is tensioned and fixed to the belt upper fixing device 17. The fixing of the polishing belt 16 by the belt upper fixing device 17 will be described in detail later.
[0015]
  Further, as described above, since the guide rail 21 is attached to the lifting cylinder body 3 so as to be freely opened and closed, the mounting of the conveying belt 4 and the polishing belt 16 to the ball lifting device 1 is performed by the guide rail. 21 can be performed by rotating it around the fulcrum of the support hinge 15. In this way, the transport belt 4 and the polishing belt 16 are mounted, and the transporting cylinder body 3 and the guide rail 21 are locked by the stopper 13 in a state where the guide rail 21 is closed, so that the transport belt 4 and the polishing belt are fixed. 16 is maintained facing each other. When the guide rail 21 is closed and locked by the stopper 13 in this way, a gap is formed between the feed cylinder body 3 and the guide rail 21. The dimension can be set by adjusting the fixing position of the locking metal fitting 14, and the pressure on the pachinko balls to be fed can be changed according to the set value.
[0016]
  Thus, the guide rail 21 is closed with the conveying belt 4 and the polishing belt 16 attached in this manner, and the stopper 13 is engaged with the engaging protrusion 12 so that the guide rail 21 is attached to the lifting cylinder body 3. After that, when the conveyor belt 4 is driven to rotate, the pachinko balls sandwiched between the conveyor belt 12 and the polishing belt 16 rise while the dirt is wiped off by the polishing belt 16.
[0017]
  At the end of business, with the belt lower fixing device 18 loosened so that the polishing belt 16 can move, the polishing belt 16 on the outer upper side of the guide rail 21 is pulled and stored in the belt storage box 19 before use. The unused surface of the used polishing belt 16 before use is positioned on the inner surface of the guide rail 21, and then the belt lower fixing device 18 and the belt upper fixing device 17 are sequentially operated to engage the polishing belt 16. By stopping, the preparation for the next day's polishing is completed. At this time, the used polishing belt 16 is stored in the used belt storage box 20. In addition, the winding operation of the polishing belt 16 can be performed with the guide rail 21 opened from the feeding cylinder body 3 or with the guide rail 21 being closed, but it can be replaced with a new polishing belt. In some cases, the guide rail 21 needs to be opened in the state where the guide rail 21 is opened from the lifting cylinder body 3.
[0018]
  The outline of the ball lifting device 1 has been described above. Next, the belt upper fixing device 17 constituting the main part of the present embodiment will be described with reference to FIGS. 2 to 5. FIG. 2 is a perspective view showing the entire belt upper fixing device 17, FIG. 3 is a side view of the belt upper fixing device 17 in a state where the polishing belt 16 is not mounted, and FIG. FIG. 5 is a side view of the belt upper fixing device 17 when the operation piece 32 is sandwiched between the polishing belts 16.
[0019]
  First, the configuration of the belt upper fixing device 17 will be described. In FIG. 2, the belt upper fixing device 17 is provided between a slide member 26 that can move in the vertical direction along the outer surface of the guide rail 21 and mounting flanges 29 that are erected on both upper sides of the slide member 26. The operation piece 32 to be inserted, the urging member 37 attached to the urging member attachment portion 35 provided at the lower part of the slide member 26, and one end side of the operation piece 32 and the upper portion of the attachment flange 29 are hung. And a spring 39 as an elastic member to be passed.
[0020]
  The slide member 26 is formed of a sheet metal such as stainless steel, and the horizontal section of the slide member 26 is formed in a U-shape so that the slide rail 26 can be prevented from being displaced horizontally on both sides. A guide portion 28 that contacts the side surface is formed, and a slide long hole 27 into which a guide pin 22 attached to the guide rail 21 is inserted is formed on both sides of the surface. Further, since the upper portion of the slide member 26 is bent, the thickness from the upper end to the substantially vertical center is the thickness of two plates. Then, both sides of the bent portion are further bent at a right angle to form the mounting flange 29. The mounting flange 29 has a support hole 42 into which a support 30 described later is inserted. Further, as described above, the urging member mounting portion 35 is provided at the lower portion of the slide member 26, and the urging force for mounting the urging member 37 is provided at the center of the urging member mounting portion 35. A member mounting hole 41 is formed.
[0021]
  Similarly to the slide member 26, the operation piece 32 is formed in a substantially L-shaped side surface by a sheet metal such as stainless steel, and the upper part thereof is bent at an acute angle to form the first belt clamping piece 33. At the same time, the tip of the first belt clamping piece 33 forms a clamping end 33 a for clamping the polishing belt 16. Further, the lower part of the operation piece 32 is bent in a step shape to form a handle portion 34, and a second belt formed on the opposite side surface of the handle portion 34 by a sheet metal such as stainless steel in a substantially L-shaped side surface shape. The clamping piece 43 (see FIG. 3) is fixed. The tip of the second belt clamping piece 43 forms a clamping end 43a (see FIG. 3) for clamping the polishing belt 16 in the same manner as the first belt clamping piece 33. Further, in the vicinity of the bent portion of the first belt clamping piece 33, a support shaft hole (not shown) into which a support shaft 30 described later is inserted is formed.
[0022]
  Thus, the belt upper fixing device 17 is assembled as follows. First, the operation piece 32 is inserted between the left and right mounting flanges 29 of the slide member 26, and the support hole 42 of the slide member 26 is aligned with the support hole (not shown) of the operation piece 32, and then the support hole 42 is supported. The operation piece 32 is rotatably attached to the slide member 26 by inserting the shaft 30 and caulking both ends of the support shaft 30. Next, one attachment portion of the spring 39 as an elastic member is attached to a screw hole (not shown) formed in one end of the attachment flange 29 with an attachment screw 31, and the other attachment portion of the spring 39 is attached to the operation piece. The spring 39 is attached to the slide member 26 and the operation piece 32 by being attached to a screw hole (not shown) drilled in one end of the 32 with the attachment screw 36. The biasing member 37 is attached to the slide member 26 by inserting one mounting portion of the biasing member 37 into the biasing member mounting hole 41 formed in the biasing member mounting portion 35 of the slide member 26. It is done. When the operation piece 32 is in the position shown in FIG. 4, the open state is stopped and maintained by the spring 39, and when the operation piece 32 is in the position shown in FIG. 3, the holding state is stopped and maintained.
[0023]
  When the belt upper fixing device 17 assembled as described above is attached to the guide rail 21, a guide pin insertion hole (not shown) formed in the guide rail 21 and a slide long hole 27 formed in the slide member 26 are aligned. After that, by inserting the guide pin 22 into the guide pin insertion hole and caulking the tip of the guide pin 22 from the back side of the guide rail 21, the guide pin 22 is fixed to the guide rail 21 and the belt upper fixing device. 17 is attached to the guide rail 21. After the belt upper fixing device 17 is mounted on the guide rail 21, the biasing member mounting boss 38 is inserted into the other mounting portion of the biasing member 37, and the biasing member mounting boss (not shown) formed in the guide rail 21 is formed. The biasing member mounting boss 38 is fixed to the guide rail 21 by inserting the biasing member mounting boss 38 into the 38 insertion hole and caulking the tip of the biasing member mounting boss 38 from the back side of the guide rail 21.
[0024]
  The guide pin 22 and the biasing member mounting boss 38 are fixed to the guide rail 21 not only by the method of caulking the tips of the guide pin 22 and the biasing member mounting boss 38 but also the guide pin 22 and the biasing member mounting boss 38. In order to weld or replace the tip of the guide rail 21 from the back side of the guide rail 21, the tip of the guide pin 22 and the biasing member mounting boss 38 and the guide pin insertion hole and the biasing member mounting boss 38 are inserted into the insertion hole. Alternatively, the guide pin 22 and the urging member mounting boss 38 may be screwed onto the guide rail 21 by cutting the screw.
[0025]
  By the way, the inner width dimension of the slide member 26 is formed slightly larger than the width dimension of the guide rail 21, and the width dimension of the slide long hole 27 is formed slightly larger than the diameter of the guide pin 22. As described above, when the belt upper fixing device 17 is attached to the guide rail 21, it is between the side inner side surface of the slide member 26 and the side outer side surface of the guide rail 21 and the side of the slide long hole 27 and the guide. A gap is formed between the side of the pin 22. Here, when the vertical center line of the slide member 26 and the vertical center line of the guide rail 21 are assembled and assembled, the left and right sides of the slide member 26 and the guide rail 21 have the same dimension (L1). In addition, a gap having the same dimension (referred to as L2) is formed between the left and right sides of the guide pin 22 and the side of the slide long hole 27. At this time, since the respective members are formed so that the gap dimensions L1 and L2 satisfy L1 <L2, the side inner side surface of the slide member 26 before the side of the slide long hole 27 abuts on the guide pin 22 is formed. Is in contact with the lateral outer surface of the guide rail 21 and the side of the slide long hole 27 is not in contact with the guide pin 22, so that the guide pin 22 is not damaged.
[0026]
  Next, a method for holding the polishing belt 16 of the belt upper fixing device 17 will be described. As shown in FIG. 3, the belt upper fixing device 17 attached to the guide rail 21 as described above is urged downward by the urging force of the urging member 37, and the guide pin 22 is attached to the upper end of the slide long hole 27. Is stopped at the position where it contacts. From this state, by rotating the lower end of the handle portion 34 in the clockwise direction, the operation piece 32 rotates around the support shaft 30, and the holding end portions 33 a and 43 a open the insertion port 60 around the support shaft 30. As shown in FIG. 4, the operation piece 32 is opened. At this time, since the operating piece 32 is biased upward by the spring 39, it is stopped and maintained in this open state. In this state, the polishing belt 16 is inserted into the insertion port 60. The polishing belt 16 has a length that can be used for about one week, and the clamping method is used both when the polishing belt 16 is replaced (first time) and when the polishing surface of the polishing belt 16 is updated (second time and later). Since it is the same, the case of polishing surface update is described here. When renewing the polishing surface, the polishing belt 16 below the insertion port 60 is pulled downward, and the polishing belt 16 is sequentially sent out from the pre-use belt storage box 19 until the unused surface of the polishing belt 16 comes to the surface facing the conveying belt 4. . When the unused surface of the polishing belt 16 comes to the surface facing the conveying belt 4, the lower belt fixing device 18 that has been loosened is tightened to fix the lower portion of the polishing belt 16 to the belt lower fixing device 18. After the lower part of the polishing belt 16 is fixed to the belt lower fixing device 18, in order to reduce the amount of the polishing belt 16 to be stretched, it is pulled downward to give tension. Then, the operation piece 32 is lifted upward with one hand. By lifting the operating piece 32 upward, the entire belt upper fixing device 17 moves upward against the urging force of the urging member 37, and the belt upper fixing device 17 that has moved upward moves the lower end of the slide long hole 27. It stops at the position where the guide pin 22 contacts. When the operation piece 32 is moved upward, the handle portion 34 is returned slightly downward, and the entire operation piece 32 is supported and moved upward while the operation piece 32 is inclined. At this time, since the operation piece 32 can be moved upward with one hand, the polishing belt 16 can be pulled downward with the other hand.
[0027]
  As described above, the belt upper fixing device 17 is held at the upper position with one hand, and the polishing belt 16 is pulled downward with the other hand and held at the upper position with one hand. By rotating the operation piece 32 counterclockwise, the space between the first belt holding piece 33 and the second belt holding piece 43 and the slide member 26 is closed, so that the holding end portion as shown in FIG. The polishing belt 16 is sandwiched between 33a, 43a and the slide member 26. At this time, since the operation piece 32 is urged by the spring 39 in a direction in which the operation piece 32 is closed, the operation piece 32 is stopped and maintained in this sandwiched state. When the hand is released from the belt upper fixing device 17 and the polishing belt 16 in this state, the belt upper fixing device 17 is urged downward by the urging member 37, so that the polishing belt 16 is also pulled downward, and the polishing belt 16. Sufficient tension will be applied.
[0028]
  As described above, the belt upper fixing device 17 has been described in detail. In the above-described embodiment (hereinafter referred to as the first embodiment), the slide member 26 is not locked at the position where it is moved upward. It may be locked at the position where the slide member 26 is moved upward. Such an embodiment (hereinafter referred to as a second embodiment) will be described with reference to FIGS. FIG. 6 is a perspective view showing the entire belt upper fixing device 17 according to the second embodiment, and FIG. 7 is a side view of the belt upper fixing device 17 according to the second embodiment in a state where the polishing belt 16 is not attached. 8 is a side view of the belt upper fixing device 17 according to the second embodiment when it is locked upward and the operation piece 32 is in an open state, and FIG. 9 is locked upward and operated. FIG. 10 is a side view of the belt upper fixing device 17 according to the second embodiment when the piece 32 is sandwiched between the polishing belts 16, and FIG. It is a side view of belt upper fixing device 17 concerning a 2nd embodiment when it removes from stop hole 46. In addition, the same code | symbol was attached | subjected to the components which show | play the same function as 1st Embodiment.
[0029]
  The difference between the first embodiment and the second embodiment is that a base member 45 is provided between the slide member 26 and the guide rail 21 of the first embodiment, and the operation piece 32 is rotatably supported on the base member 45. The slide member 26 is provided so as to be movable in the vertical direction. Therefore, the configuration of the belt upper fixing device 17 according to the second embodiment will be described in more detail. In FIG. 6, the belt upper fixing device 17 includes a base member 45 that is closely fixed to the guide rail 21, and a slide member 26 that is movable in the vertical direction along a slide long hole 47 formed in the base member 45. The guide pin 40 provided on the mounting flange 29 erected on both sides of the upper portion of the slide member 26, the operation piece 32 inserted between the both mounting flanges 29, and the lower portion of the slide member 26. An urging member 37 attached to the urging member attaching portion 35 (see FIG. 7), an urging member attaching boss 38 for fixing the urging member 37 to the base member 45, and one end side of the operation piece 32; And a spring 39 as an elastic member spanning the upper portion of the mounting flange 29.
[0030]
  The base member 45 is formed of a sheet metal such as stainless steel. On both sides of the base member 45, a guide portion 49 that abuts against the side surface of the guide rail 21 over the entire length in the vertical direction is provided. A mounting flange 50 is erected above. A bolt hole (not shown) for attaching the base member 45 to the guide rail 21 is formed on the surface of the guide portion 49, and the base member 45 is fixed to the guide rail 21 by screwing the attachment bolt 48 into the bolt hole. is doing. Further, the mounting flange 50 has two slide long holes 47 into which the guide pins 40 are inserted, and slide member locking as a slide member locking means that communicates with the upper end of the slide long hole 47 in an inverted L shape. A hole 46 is formed.
[0031]
  Similarly to the base member 45, the slide member 26 is formed of a sheet metal such as stainless steel, and is formed by being bent into a U-shaped horizontal cross section, and the left and right bent portions form the mounting flange 29. ing. The mounting flange 29 has one support shaft hole 42 (see FIG. 7) into which a support shaft 30 (see FIG. 7) described later is inserted, and a guide pin insertion hole (not shown) for inserting the guide pin 40. Two holes are drilled. Further, as described above, the urging member mounting portion 35 is provided at the lower portion of the slide member 26, and an urging member 37 is attached to the center front end portion of the urging member mounting portion 35. A biasing member mounting hole (not shown) is formed.
[0032]
  Similarly to the base member 45 and the slide member 26, the operation piece 32 is formed in a substantially L-shaped side surface by a sheet metal such as stainless steel, and the upper part thereof is bent at an acute angle to hold the first belt. While forming the piece 33, the front-end | tip part of this 1st belt clamping piece 33 forms the clamping end part 33a for clamping the grinding | polishing belt 16. As shown in FIG. Further, the lower part of the operation piece 32 is bent in a step shape to form a handle portion 34, and on the opposite side of the handle portion 34, a second belt formed in a substantially L-shaped side surface by a sheet metal such as stainless steel. The clamping piece 43 (see FIG. 7) is fixed. The tip of the second belt clamping piece 43 forms a clamping end 43 a (see FIG. 7) for clamping the polishing belt 16 in the same manner as the first belt clamping piece 33. Further, in the vicinity of the bent portion of the first belt holding piece 33, a support shaft hole (not shown) into which a support shaft 30 (see FIG. 7) described later is inserted is formed.
[0033]
  Therefore, the belt upper fixing device 17 according to the second embodiment is assembled as follows. First, the operation piece 32 is inserted between the left and right mounting flanges 29 of the slide member 26, and the support hole 42 of the slide member 26 is aligned with the support hole (not shown) of the operation piece 32, and then the support hole 42 is supported. The operation piece 32 is rotatably attached to the slide member 26 by inserting the shaft 30 and caulking both ends of the support shaft 30. Next, one attachment portion of the spring 39 as an elastic member is attached to a screw hole (not shown) formed in one end of the attachment flange 29 with an attachment screw 31, and the other attachment portion of the spring 39 is attached to the operation piece. The spring 39 is attached to the slide member 26 and the operation piece 32 by being attached to a screw hole (not shown) drilled in one end of the 32 with the attachment screw 36. The biasing member 37 is attached to the slide member 26 by inserting one mounting portion of the biasing member 37 through the biasing member mounting hole formed in the biasing member mounting portion 35 of the slide member 26. .
[0034]
  As described above, the slide member 26 to which the operation piece 32, the spring 39, and the biasing member 37 are attached is inserted between the left and right mounting flanges 50 of the base member 45, and the guide pin insertion hole and the slide long hole of the mounting flange 29 are inserted. 47, the guide pin 40 is inserted into a guide pin insertion hole (not shown), and the guide pin 40 is fixed to the mounting flange 29 by caulking the tip of the guide pin 40 from the inner surface of the mounting flange 29. At the same time, the slide member 26 is attached to the base member 45. Next, after the slide member 26 is mounted on the base member 45, the biasing member mounting boss 38 is inserted into the other mounting portion of the biasing member 37, and the biasing member mounting boss (not shown) formed in the base member 45 is inserted. The urging member mounting boss 38 is inserted into the 38 insertion hole, and the urging member mounting boss 38 is fixed to the base member 45 by caulking the tip of the urging member mounting boss 38 from the back surface side of the base member 45.
[0035]
  The guide pin 40 and the urging member mounting boss 38 are fixed to the mounting flange 29 and the base member 45 not only by the method of caulking the guide pin 40 and the urging member mounting boss 38 but also by the guide pin 40. In order to weld or replace the front end of the biasing member mounting boss 38 from the inner surface of the mounting flange 29 and the base member 45, the front end of the guide pin 40 and the biasing member mounting boss 38 and the guide pin insertion hole are provided. Alternatively, the guide pin 40 and the biasing member mounting boss 38 may be screwed to the mounting flange 29 and the base member 45 by cutting a screw in the biasing member mounting boss 38 insertion hole.
[0036]
  When the belt upper fixing device 17 assembled as described above is attached to the guide rail 21, the bolt hole (not shown) drilled in the guide portion 49 of the base member 45 and the screw (not shown) drilled in the guide rail 21. After the holes are aligned, the belt upper fixing device 17 is attached to the guide rail 21 by screwing the mounting bolts 48 into the screw holes.
[0037]
  Next, a method for holding the polishing belt 16 of the belt upper fixing device 17 according to the second embodiment will be described. The belt upper fixing device 17 attached to the guide rail 21 as described above is urged downward by the urging force of the urging member 37 as shown in FIG. Is stopped at the position where it contacts. From this state, by rotating the lower end of the handle portion 34 in the clockwise direction, the operation piece 32 rotates about the support shaft 30, and the clamping end portions 33 a and 43 a open the insertion port 60 about the support shaft 30. The operation piece 32 is opened as shown in FIG. In this state, the polishing belt is inserted into the insertion port 60. The polishing belt 16 has a length that can be used for about one week, and the clamping method is used both when the polishing belt 16 is replaced (first time) and when the polishing surface of the polishing belt 16 is updated (second time and later). Since it is the same, the case of polishing surface update is described here. When renewing the polishing surface, the polishing belt 16 below the insertion port 60 is pulled downward, and the polishing belt 16 is sequentially sent out from the pre-use belt storage box 19 until the unused surface of the polishing belt 16 comes to the surface facing the conveying belt 4. . When the unused surface of the polishing belt 16 comes to the surface facing the conveying belt 4, the lower belt fixing device 18 that has been loosened is tightened to fix the lower portion of the polishing belt 16 to the belt lower fixing device 18. After the lower part of the polishing belt 16 is fixed to the belt lower fixing device 18, in order to reduce the amount of the polishing belt 16 to be stretched, it is pulled downward to give tension. Then, the operation piece 32 is lifted upward with one hand. By lifting the operation piece 32 upward, the slide member 26 moves upward against the biasing force of the biasing member 37, and the slide member 26 moved upward has a guide pin 40 at the upper end of the slide long hole 47. It stops at the position where it abuts. Further, by pulling the operation piece 32 forward from this state, the guide pin 40 is fitted into the slide member locking hole 46 as shown in FIG. The slide member 26 is stopped in the stopped state. Since the slide member locking hole 46 is formed obliquely downward from the upper end of the slide long hole 47, the guide pin 40 does not enter the slide long hole 47 unless an external force is applied to the slide member 26. The slide member 26 does not move downward. When the operation piece 32 is moved upward, the handle portion 34 is returned slightly downward, and the entire operation piece 32 is supported and moved upward while the operation piece 32 is inclined.
[0038]
  As described above, the slide member 26 is locked at the position where it is moved upward, and the operation piece 32 is biased upward by the spring 39, so that the slide member 26 is released even if the hand is released from the handle portion 34. Can be stopped in a state of being moved upward against the urging force of the urging member 37, and the open state of the operation piece 32 can be maintained.
[0039]
  Then, by pulling the polishing belt 16 downward with one hand and rotating the operation piece 32 counterclockwise with the other hand, the operation piece 32 is rotated, and the first belt holding piece 33 and the second belt are rotated. Since the gap between the holding piece 43 and the slide member 26 is closed, the polishing belt 16 is held between the holding end portions 33a and 43a and the slide member 26 as shown in FIG. At this time, since the operation piece 32 is urged by the spring 39 (see FIG. 6) in the direction in which the operation piece 32 is closed, the operation piece 32 is kept stopped in this sandwiched state. From this state, by pushing the back surface of the operation piece 32 toward the guide rail 21 side, the guide pin 40 is detached from the slide member locking hole 46 as shown in FIG. 37, the polishing belt 16 is also pulled downward, and sufficient tension is applied to the polishing belt 16. The polishing belt 16 is clamped by the slide member 26 at a position where the slide member 26 is locked to the slide member locking hole 46. After the polishing belt 16 is clamped by the slide member 26, the slide member When the belt 26 is moved from the slide member locking hole 46 to the slide long hole 47, the slide belt 26 is once moved upward, so that the polishing belt 16 is slightly bent. Then, after the slide member 26 moves to the slide long hole 47, the slide member 26 falls downward within the slide long hole 47 by the amount of deflection of the polishing belt 16. For this reason, the slide member 26 does not move again from the slide long hole 47 to the slide member locking hole side.
[0040]
  As described above, the belt upper fixing device 17 according to the second embodiment has been described in detail. However, in the belt upper fixing device 17 according to the first and second embodiments described above, the vertical movement of the slide member 26 is guided by a guide pin. Although what is performed along 22 and 40 was shown, you may guide the vertical motion of the slide member 26 by another method irrespective of the guide pins 22 and 40. FIG. Therefore, an embodiment of the belt upper fixing device 17 in which the slide member 26 moves up and down regardless of the guide pins 22 and 40 (hereinafter referred to as a third embodiment) will be described.
[0041]
  First, the configuration of the belt upper fixing device 17 according to the third embodiment will be described with reference to FIG. FIG. 11 is a perspective view showing the entire belt upper fixing device 17 according to the third embodiment. In addition, the same code | symbol was attached | subjected to the components which show | play the same function as 1st Embodiment and 2nd Embodiment.
[0042]
  In FIG. 11, the belt upper fixing device 17 includes a base member 45 that is closely fixed to the guide rail 21, a slide member 26 that is movable in the vertical direction along a guide member 55 that is fixed to the surface of the base member 45, and An operation piece 32 inserted between mounting flanges 29 erected on both sides of the slide member 26, and an urging member 37 attached to an urging member attachment portion 35 provided at the lower part of the slide member 26 The urging member mounting boss 38 for fixing the urging member 37 to the base member 45, and a spring 39 spanned between one end side of the operation piece 32 and the upper portion of the mounting flange 29. .
[0043]
  The base member 45 is formed of a sheet metal such as stainless steel, and guide portions 49 that abut on the side surfaces of the guide rail 21 are provided upright on both sides of the base member 45. A bolt hole (not shown) for attaching the base member 45 to the guide rail 21 is formed on the surface of the guide portion 49, and the base member 45 is attached to the guide rail 21 by screwing the attachment bolt 48 into the bolt hole. It is fixed. In addition, L-shaped guide members 55 are fixed to the upper both side ends of the surface of the base member 45, and both end sides of the slide member 26 are inserted into a gap formed between the base member 45 and the guide member 55. It has become so. In addition, a slide member stop piece 56 projects from the substantially center of the base member 45.
[0044]
  Similarly to the base member 45, the slide member 26 is formed of a sheet metal such as stainless steel, and mounting flanges 29 are erected at positions slightly inside from both sides of the slide member 26. A support shaft hole 42 into which a support shaft 30 described later is inserted is formed. Further, as described above, an urging member mounting portion 35 formed by being bent in a stepped shape is provided at the lower portion of the slide member 26. A biasing member mounting hole 41 for mounting the biasing member 37 is formed.
[0045]
  Similarly to the base member 45 and the slide member 26, the operation piece 32 is formed in a substantially L-shaped side surface by a sheet metal such as stainless steel, and the upper part thereof is bent at an acute angle to hold the first belt. While forming the piece 33, the front-end | tip part of this 1st belt clamping piece 33 forms the clamping end part 33a for clamping the grinding | polishing belt 16. As shown in FIG. Further, the lower part of the operation piece 32 is bent in a step shape to form a handle portion 34, and on the opposite side of the handle portion 34, a side surface shape is formed in a substantially L shape by a sheet metal such as stainless steel (not shown). Two belt clamping pieces are fixed. The tip of the second belt clamping piece forms a clamping end (not shown) for clamping the polishing belt 16 in the same manner as the first belt clamping piece 33. Further, in the vicinity of the bent portion of the first belt clamping piece 33, a support shaft hole (not shown) into which a support shaft 30 described later is inserted is formed.
[0046]
  Thus, the belt upper fixing device 17 according to the third embodiment is assembled as follows. First, the operation piece 32 is inserted between the left and right mounting flanges 29 of the slide member 26, and the support hole 42 of the slide member 26 is aligned with the support hole (not shown) of the operation piece 32, and then the support hole 42 is supported. The operation piece 32 is rotatably attached to the slide member 26 by inserting the shaft 30 and caulking both ends of the support shaft 30. Next, one attachment portion of the spring 39 as an elastic member is attached to a screw hole (not shown) formed in one end of the attachment flange 29 with an attachment screw 31, and the other attachment portion of the spring 39 is attached to the operation piece. The spring 39 is attached to the slide member 26 and the operation piece 32 by being attached to a screw hole (not shown) drilled in one end of the 32 with the attachment screw 36. The biasing member 37 is attached to the slide member 26 by inserting one mounting portion of the biasing member 37 into the biasing member mounting hole 41 formed in the biasing member mounting portion 35 of the slide member 26. It is done.
[0047]
  As described above, both end sides of the slide member 26 to which the operation piece 32, the spring 39, and the biasing member 37 are attached are inserted into the gap between the base member 45 and the guide member 55 fixed to the left and right of the base member 45. Thus, the slide member 26 is attached to the base member 45. Next, after the slide member 26 is mounted on the base member 45, the biasing member mounting boss 38 is inserted into the other mounting portion of the biasing member 37, and the biasing member mounting boss (not shown) formed in the base member 45 is inserted. The urging member mounting boss 38 is inserted into the 38 insertion hole, and the urging member mounting boss 38 is fixed to the base member 45 by caulking the tip of the urging member mounting boss 38 from the back surface side of the base member 45.
[0048]
  As described above, when the slide member 26 is mounted on the base member 45, the slide member 26 is urged downward by the urging member 37, but the lower end of the slide member 26 contacts the slide member stop piece 56. Therefore, the lower end of the slide member 26 does not move downward from the position where the lower end of the slide member 26 contacts the slide member stop piece 56.
[0049]
  The biasing member mounting boss 38 is fixed to the base member 45 not only by the method of caulking the tip of the biasing member mounting boss 38 but also by welding the tip of the biasing member mounting boss 38 from the inner surface of the base member 45. In order to enable or replace the biasing member mounting boss 38, the tip of the biasing member mounting boss 38 and the biasing member mounting boss 38 are inserted into the base member 45 by cutting screws. It is also possible to make it.
[0050]
  When the belt upper fixing device 17 assembled as described above is attached to the guide rail 21, the bolt hole (not shown) drilled in the guide portion 49 of the base member 45 and the screw (not shown) drilled in the guide rail 21. After the holes are aligned, the belt upper fixing device 17 is attached to the guide rail 21 by screwing the mounting bolts 48 into the screw holes.
[0051]
  Next, a method for sandwiching the polishing belt 16 of the belt upper fixing device 17 according to the third embodiment will be described, but the difference from the method for mounting the polishing belt 16 of the belt fixing device 17 according to the first embodiment is slight. Therefore, the description will be made in comparison with FIG. 4 and FIG.
[0052]
  The slide member 26 of the belt upper fixing device 17 mounted on the guide rail 21 as described above is urged downward by the urging force of the urging member 37, and the position where the slide member 26 contacts the slide member stop piece 56. Has stopped at. From this state, by rotating the lower end of the handle portion 34 in the clockwise direction, the operation piece 32 rotates about the support shaft 30 and the holding end portion 33a opens about the support shaft 30. FIG. As shown, the operation piece 32 is opened. At this time, since the operating piece 32 is biased upward by the spring 39, it is stopped and maintained in this open state. In this state, the polishing belt is inserted into the insertion port 60. The polishing belt 16 has a length that can be used for about one week, and the clamping method is used both when the polishing belt 16 is replaced (first time) and when the polishing surface of the polishing belt 16 is updated (second time and later). Since it is the same, the case of polishing surface update is described here. When renewing the polishing surface, the polishing belt 16 below the insertion port 60 is pulled downward, and the polishing belt 16 is sequentially sent out from the pre-use belt storage box 19 until the unused surface of the polishing belt 16 comes to the surface facing the conveying belt 4. . When the unused surface of the polishing belt 16 comes to the surface facing the conveying belt 4, the lower belt fixing device 18 that has been loosened is tightened to fix the lower portion of the polishing belt 16 to the belt lower fixing device 18. After the lower portion of the polishing belt 16 is fixed to the belt lower fixing device 18, in order to reduce the amount of the polishing belt 16 that extends, a tension is applied by pulling downward. Then, the operation piece 32 is lifted upward with one hand. By lifting the operating piece 32 upward, the slide member 26 moves upward against the biasing force of the biasing member 37, but there is nothing that restricts the upward movement of the slide member 26. Can be moved upward within a range that does not leave the guide member 55. When the operation piece 32 is moved upward, the handle portion 34 is returned slightly downward, and the entire operation piece 32 is supported and moved upward while the operation piece 32 is inclined. At this time, since the operation piece 32 can be moved upward with one hand, the polishing belt 16 can be pulled downward with the other hand.
[0053]
  As described above, the slide member 26 is held at the upper position with one hand, and the polishing belt 16 is pulled downward with the other hand, and held at the upper position with one hand. By rotating the operation piece 32 counterclockwise, the space between the first belt holding piece 33 and the second belt holding piece and the slide member 26 is closed, and as shown in FIG. 5, the holding end portion 33a. The polishing belt 16 is sandwiched between the slide member 26 and the slide member 26. At this time, since the operation piece 32 is urged by the spring 39 in a direction in which the operation piece 32 is closed, the operation piece 32 is stopped and maintained in this sandwiched state. When the hand is released from the slide member 26 in this state, the slide member 26 is urged downward by the urging member 37, so that the polishing belt 16 is also pulled downward, and sufficient tension is applied to the polishing belt 16. Will be.
[0054]
  As described above, the ball lifting device according to the plurality of embodiments has been described in detail. In the present embodiment, the conveyor belt 4 that is circulated between a plurality of rollers that are rotated by a driving source, and the outer periphery of the conveyor belt 4. A polishing belt 16 mounted on a guide rail 21 installed opposite to the surface; a belt upper fixing device 17 installed on the outer surface of the guide rail 21 and fixing the upper side of the polishing belt 16; The belt upper fixing device 17 includes a slide member 26 that is movable in the vertical direction along the outer surface of the guide rail 21, and biases the slide member 26 downward. An urging member 37 and an operation piece 32 that moves the slide member 26 upward against the urging force of the urging member 37, and the operation piece 32 includes the operation piece 32. An open state in which the polishing belt 16 can be inserted into the belt upper fixing device 17 and the belt upper fixing device 17 in a state in which the sliding member 26 is moved upward against the urging force of the urging member 37. Further, the polishing belt 16 can be displaced to a clamping state in which the polishing belt 16 is clamped. With such a configuration, the slide member 26 is operated with the operation piece 32 moved upward, and the operation piece 32 is operated to insert and hold the polishing belt 16 into the belt upper fixing device 17. Since 26 is urged downward by the urging member 37, it is possible to easily attach the polishing belt 16 with sufficient tension.
[0055]
  In the present embodiment, the belt upper fixing device 17 is provided with slide member locking means for locking the slide member 26 at the position where the slide member 26 is moved upward. The slide member is locked by the slide member locking means and the operation piece 32 is operated, and the polishing belt 16 is inserted and clamped in the belt upper fixing device 17 while the slide member 26 is moved upward. Since the biasing member 37 is biased downward by releasing the locking, it is possible to easily attach the polishing belt 16 with sufficient tension.
[0056]
  Further, in the present embodiment, the slide member engaging means is engaged by operating the operation piece 32 to move the slide member 26 upward, engage the slide member 26, hold the polishing belt 16, and Since a series of operations until the slide member 26 is removed from the slide member locking means can be operated by the operation piece 32, the series of operations can be easily performed.
[0057]
  In the present embodiment, the belt upper fixing device 17 is provided with an elastic member that urges the operation piece 32 so as to stop and maintain the operation piece 32 in the opened state and the clamped state. The polishing belt 16 can be easily inserted into the belt upper fixing device 17 in the opened state, and the polishing belt 16 can be clamped more firmly when the polishing belt 16 is clamped. In addition, the operation piece 32 can be prevented from being blurred.
[0058]
  Furthermore, in the present embodiment, the belt is mounted so as to span a conveyor belt 4 that is circulated between a plurality of rollers that are rotated by a driving source, and a guide rail 21 that is installed to face the outer peripheral surface of the conveyor belt 4. In the ball lifting device 1 including a polishing belt 16 and a belt upper fixing device 17 that is installed on the outer surface of the guide rail 21 and fixes the upper side of the polishing belt 16, the belt upper fixing device 17 includes: A slide member 26 that is movable in the vertical direction along the outer surface of the guide rail 21 and that has a holding portion that opens and holds the polishing belt 16, and a biasing member 37 that biases the slide member 26 downward, And a slide member locking means for locking the slide member 26 at a position moved upward. With this configuration, it is not necessary to simultaneously perform the upward movement of the slide member 26, the locking of the slide member 26, and the sandwiching of the polishing belt 16 to the slide member 26, and the respective operations can be performed sequentially. Therefore, it is possible to easily attach the polishing belt 16 with sufficient tension.
[0059]
  In the second embodiment, as the slide member locking means for stopping the slide member 26 upward, the guide pin 40 is inserted into the slide member locking hole 46. However, the slide member 26 stops upward. For example, a protrusion that protrudes and protrudes on the surface of the base member 45 is provided on the base member 45, and the protrusion protrudes to support the lower end of the slide member 26 when the slide member 26 moves upward. Alternatively, a pin may be inserted through the slide member 26 and the base member 45, or a slide member 26 may be sandwiched.
[0060]
  The slide member locking means of the slide member 26 shown in the second embodiment may be applied to the first embodiment and the third embodiment.
[0061]
  Further, in the second embodiment or the third embodiment, the base member 45 is shown in which the mounting bolts 48 are screwed and attached to both side surfaces of the guide rail 21. However, the guide rail having rails formed on both side surfaces is shown. Since the base member 45 can be moved up and down by mounting the base member 45 on the rail, the mounting position of the base member 45 can be adjusted and the mounting position can be changed. Further, the belt upper fixing device 17 may be made of resin.
[0062]
  Furthermore, in the first to third embodiments, the operation piece 32 is shown as a holding portion for opening and holding the polishing belt 16, but any operation piece 32 may be used as long as the polishing belt 16 is opened and held. It may be one that clamps the belt, such as the clamping part disclosed in the application described in 1), or one that uses a mechanism such as a vise. In addition, although the operation piece 32 in which two clamping pieces (the first belt clamping piece 33 and the second belt clamping piece 43) for clamping the polishing belt 16 are formed is shown, the polishing belt 16 is fixed. For example, one or three or more sandwiching pieces may be formed, or a sandwiching end may be formed in a sawtooth shape or a knurled shape. Moreover, although the spring was shown as the urging member 37, it is not limited to the spring, and any member that urges the slide member 26 downward may be used. For example, a member that urges the slide member 26 by applying a load with a weight, The slide member 26 may be biased using an elastic member such as rubber or a leaf spring. Moreover, the attachment position of the urging member 37 may be a position where the slide member 26 can be urged in the vertical direction. For example, the urging member 37 is attached to both ends of the surface of the slide member or one or both of the side surfaces. There may be. Further, in the first embodiment, the slide long hole 27 and the guide pin 22 are provided at two positions on the surface side of the guide rail 21, respectively. May be provided, or may be provided at one place or three or more places. Further, the polishing belt 16 is shown to be provided over almost the entire length of the ball lifting device 1, but it is sufficient that the polishing belt 16 is provided over the ball lifting device 1 over an appropriate length. For example, the guide rail 21 It is also possible to divide the upper and lower parts into two parts along the entire length, and the abrasive belt 16 may be provided only on the divided one guide rail 21.
[0063]
【The invention's effect】
  As is apparent from the above description, in the invention according to claim 1, the conveyor belt that is circulated between the plurality of rollers that are rotated by the drive source, and the outer circumferential surface of the conveyor belt are installed. In a ball lifting apparatus comprising: a polishing belt that is mounted over a guide rail; and a belt upper fixing device that is installed on an outer surface of the guide rail and fixes an upper side of the polishing belt. The fixing device includes a slide member that is movable in the vertical direction along the outer surface of the guide rail and has a holding portion that opens and holds the polishing belt, and a biasing member that biases the slide member downward. In a position where the slide member is moved upwardStopSliding memberStopMeans is provided. With this configuration, the slide member is moved upward, the slide memberStopFurther, it is not necessary to perform the operation of sandwiching the polishing belt on the slide member at the same time, and each operation can be performed in order, so that it is possible to easily attach the polishing belt with sufficient tension.
[0064]
  In the invention according to claim 2, the belt is mounted on a conveyor belt that is circulated between a plurality of rollers that are rotated by a drive source, and a guide rail that is installed to face the outer peripheral surface of the conveyor belt. A ball lifting device comprising: a polishing belt; and a belt upper fixing device that is installed on an outer surface of the guide rail and fixes an upper side of the polishing belt. The belt upper fixing device is provided on the outer side of the guide rail. A slide member movable in the vertical direction along the side surface; a biasing member that biases the slide member downward; an operation piece that moves the slide member upward against the biasing force of the biasing member; The operation piece is inserted into the belt upper fixing device in a state where the operation piece is lifted upward against the urging force of the urging member and the slide member is moved upward. An open state capable, displaceably in the clamping state to sandwich the abrasive belt to the belt upper restraint deviceIn addition, the belt upper fixing device is provided with an elastic member that urges the operation piece to be stopped and maintained in the opened state and the clamped state, respectively.It is characterized by this. With this configuration, after the slide member is moved upward with the operation piece, the operation piece is operated to insert and hold the polishing belt into the belt upper fixing device, and then the slide member is moved by the biasing member. Since it is biased downward, it can be easily attached with sufficient tension applied to the polishing belt.Further, the polishing belt can be easily inserted into the belt upper fixing device when the operation piece is opened, and the polishing belt can be more firmly held when the polishing belt is held. In addition, it is possible to prevent the operation piece from being blurred.
[0065]
  In the invention according to claim 3,A conveyor belt that is circulated between a plurality of rollers that are rotated by a driving source, an abrasive belt that is mounted on a guide rail that is installed opposite to the outer peripheral surface of the conveyor belt, and an outer surface of the guide rail. A ball lifting device comprising a belt upper fixing device installed and fixing an upper side of the polishing belt, wherein the belt upper fixing device is a slide that is movable in a vertical direction along an outer surface of the guide rail. A member, an urging member that urges the slide member downward, and an operation piece that moves the slide member upward against the urging force of the urging member. An open state in which the polishing belt can be inserted into the belt upper fixing device in a state where the piece is lifted upward against the biasing force of the biasing member and the slide member is moved upward, and the belt upper fixing device While the displaceable grinding belt and sandwiching state to be sandwiched,In the belt upper fixing device, the slide member is moved upward.By operating the operation pieceProvided with slide member locking means to lockIt is characterized by this. Configure like thisThus, after the slide member is moved upward by the operation piece, the slide member is locked by the slide member locking means, the operation piece is operated, and the polishing belt is inserted and clamped in the belt upper fixing device. Since the slide member is unlocked and is urged downward by the urging member, it is possible to easily attach the polishing belt with sufficient tension.In addition, since the series of operations from the slide member upward movement, the slide member locking, the sandwiching of the polishing belt, and the removal of the slide member from the slide member locking means can all be operated by the operation piece, Operation can be performed easily.
[0066]
[0067]
[Brief description of the drawings]
FIG. 1 is a perspective view of a ball lifting device as viewed from the rear.
FIG. 2 is a perspective view showing the entire belt upper fixing device according to the first embodiment.
FIG. 3 is a side view of the belt upper fixing device according to the first embodiment in a state where no abrasive belt is attached.
FIG. 4 is a side view of the belt upper fixing device according to the first embodiment when the operation piece is in an open state.
FIG. 5 is a side view of the belt upper fixing device according to the first embodiment when the operation piece is sandwiched between polishing belts.
FIG. 6 is a perspective view showing an entire belt upper fixing device according to a second embodiment.
FIG. 7 is a side view of the belt upper fixing device according to the second embodiment in a state where the polishing belt is not attached.
FIG. 8 is a side view of the belt upper fixing device according to the second embodiment when it is locked upward and the operation piece is open.
FIG. 9 is a side view of the belt upper fixing device according to the second embodiment when it is locked upward and the operation piece is sandwiched between polishing belts.
FIG. 10 is a side view of the belt upper fixing device according to the second embodiment when the operation piece is sandwiched between the abrasive belts and the guide pin is removed from the slide member locking hole.
FIG. 11 is a perspective view showing an entire belt upper fixing device according to a third embodiment.
[Explanation of symbols]
  1 Ball lifting device
  3 Lifting cylinder body
  4 Conveyor belt
  5 Tension roller mechanism
  15 Support hinge
  16 Abrasive belt
  17 Belt upper fixing device
  18 Belt lower fixing device
  19 Belt storage box before use
  20 Belt storage box after use
  21 Guide rail
  22 Guide pin
  26 Slide member
  27 Slide hole
  28 Guide section
  29 Mounting flange
  30 Spindle
  32 Operation piece
  33 1st belt clamping piece
  33a clamping end
  34 Toride Department
  35 Biasing member mounting part
  36 mounting screws
  37 Biasing member
  38 Biasing member mounting boss
  39 Spring
  40 guide pins
  41 Biasing member mounting hole
  42 Spindle hole
  43 Second belt clamping piece
  43a clamping end
  45 Base member
  46 Slide member locking hole
  47 Slide long hole
  48 Mounting bolt
  49 Guide part
  50 Mounting flange
  55 Guide member
  56 Slide member stop piece

Claims (3)

駆動源により回転する複数のローラ間を周回せしめられる搬送ベルトと、該搬送ベルトの外周面に対向して設置されるガイドレールに掛け渡して装着される研磨ベルトと、前記ガイドレールの外側面に設置され且つ前記研磨ベルトの上方側を固定するベルト上方固定装置と、を備えた玉揚送装置において、
前記ベルト上方固定装置は、前記ガイドレールの外側面に沿って垂直方向に移動可能で且つ研磨ベルトを開放挟持する挟持部を有するスライド部材と、該スライド部材を下方に付勢する付勢部材と、を備え、
前記スライド部材を上方に移動させた位置で停止させるスライド部材停止手段を設けたことを特徴とする玉揚送装置。
A conveyor belt that is circulated between a plurality of rollers that are rotated by a driving source, an abrasive belt that is mounted on a guide rail that is installed opposite to the outer peripheral surface of the conveyor belt, and an outer surface of the guide rail. A ball lifting device provided with a belt upper fixing device installed and fixing an upper side of the polishing belt,
The belt upper fixing device includes a slide member that is movable in a vertical direction along the outer surface of the guide rail and has a holding portion that opens and holds the polishing belt, and a biasing member that biases the slide member downward. With
Ball pumped apparatus characterized in that a slide member stop means for stopping at a position obtained by moving the slide member upwards.
駆動源により回転する複数のローラ間を周回せしめられる搬送ベルトと、該搬送ベルトの外周面に対向して設置されるガイドレールに掛け渡して装着される研磨ベルトと、前記ガイドレールの外側面に設置され且つ前記研磨ベルトの上方側を固定するベルト上方固定装置と、を備えた玉揚送装置において、
前記ベルト上方固定装置は、前記ガイドレールの外側面に沿って垂直方向に移動可能なスライド部材と、該スライド部材を下方に付勢する付勢部材と、前記スライド部材を前記付勢部材の付勢力に抗して上方に移動させる操作片と、を備え、
前記操作片は、該操作片を前記付勢部材の付勢力に抗して上方に持ち上げてスライド部材を上方に移動させた状態で、ベルト上方固定装置に研磨ベルトを挿入可能な開放状態と、ベルト上方固定装置に研磨ベルトを挟持させる挟持状態とに変位可能にすると共に、
前記ベルト上方固定装置には、前記操作片を前記開放状態及び挟持状態でそれぞれ停止維持するように付勢する弾性部材を設けたことを特徴とする玉揚送装置。
A conveyor belt that is circulated between a plurality of rollers that are rotated by a driving source, an abrasive belt that is mounted on a guide rail that is installed opposite to the outer peripheral surface of the conveyor belt, and an outer surface of the guide rail. A ball lifting device provided with a belt upper fixing device installed and fixing an upper side of the polishing belt,
The belt upper fixing device includes a slide member that is movable in a vertical direction along the outer surface of the guide rail, an urging member that urges the slide member downward, and an urging member that attaches the slide member to the urging member. An operation piece that moves upward against the force,
The operation piece is in an open state in which a polishing belt can be inserted into the belt upper fixing device in a state where the operation piece is lifted upward against the urging force of the urging member and the slide member is moved upward. While being displaceable to the clamping state in which the polishing belt is clamped by the belt upper fixing device ,
The ball uppering device is provided with an elastic member that urges the operation piece to stop and maintain the operation piece in the opened state and the clamped state, respectively .
駆動源により回転する複数のローラ間を周回せしめられる搬送ベルトと、該搬送ベルトの外周面に対向して設置されるガイドレールに掛け渡して装着される研磨ベルトと、前記ガイドレールの外側面に設置され且つ前記研磨ベルトの上方側を固定するベルト上方固定装置と、を備えた玉揚送装置において、
前記ベルト上方固定装置は、前記ガイドレールの外側面に沿って垂直方向に移動可能なスライド部材と、該スライド部材を下方に付勢する付勢部材と、前記スライド部材を前記付勢部材の付勢力に抗して上方に移動させる操作片と、を備え、
前記操作片は、該操作片を前記付勢部材の付勢力に抗して上方に持ち上げてスライド部材を上方に移動させた状態で、ベルト上方固定装置に研磨ベルトを挿入可能な開放状態と、ベルト上方固定装置に研磨ベルトを挟持させる挟持状態とに変位可能にすると共に、
前記ベルト上方固定装置には、前記スライド部材を上方に移動させた位置で、前記操作片の操作により係止させるスライド部材係止手段を設けたことを特徴とする玉揚送装置。
A conveyor belt that is circulated between a plurality of rollers that are rotated by a driving source, an abrasive belt that is mounted on a guide rail that is installed opposite to the outer peripheral surface of the conveyor belt, and an outer surface of the guide rail. A ball lifting device provided with a belt upper fixing device installed and fixing an upper side of the polishing belt,
The belt upper fixing device includes a slide member that is movable in a vertical direction along the outer surface of the guide rail, an urging member that urges the slide member downward, and an urging member that attaches the slide member to the urging member. An operation piece that moves upward against the force,
The operation piece is in an open state in which a polishing belt can be inserted into the belt upper fixing device in a state where the operation piece is lifted upward against the urging force of the urging member and the slide member is moved upward. While being displaceable to the clamping state in which the polishing belt is clamped by the belt upper fixing device,
The belt Above fixing unit, wherein the slide member at a position moved upward, balls pumped device you characterized in that a slide member locking means engaged by the operation of the operation piece.
JP22064699A 1999-08-04 1999-08-04 Ball lifting device Expired - Fee Related JP4300638B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP22064699A JP4300638B2 (en) 1999-08-04 1999-08-04 Ball lifting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP22064699A JP4300638B2 (en) 1999-08-04 1999-08-04 Ball lifting device

Publications (2)

Publication Number Publication Date
JP2001046717A JP2001046717A (en) 2001-02-20
JP4300638B2 true JP4300638B2 (en) 2009-07-22

Family

ID=16754239

Family Applications (1)

Application Number Title Priority Date Filing Date
JP22064699A Expired - Fee Related JP4300638B2 (en) 1999-08-04 1999-08-04 Ball lifting device

Country Status (1)

Country Link
JP (1) JP4300638B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002210204A (en) * 2001-01-17 2002-07-30 Takeya Co Ltd Ball lifting device

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4670501B2 (en) * 2005-06-23 2011-04-13 株式会社竹屋 Ball lifting device
JP5057681B2 (en) * 2006-03-29 2012-10-24 シルバー電研株式会社 Abrasive cloth holding mechanism of ball polishing and lifting machine

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002210204A (en) * 2001-01-17 2002-07-30 Takeya Co Ltd Ball lifting device

Also Published As

Publication number Publication date
JP2001046717A (en) 2001-02-20

Similar Documents

Publication Publication Date Title
JP4300638B2 (en) Ball lifting device
US4932696A (en) Fastening system for window or the like
JP4670501B2 (en) Ball lifting device
JP4461543B2 (en) Tamaki hoisting device
JP4923346B2 (en) Tamaki hoisting device
JP4285088B2 (en) Polishing and lifting equipment
CN211453231U (en) Paper tape wear-resisting test machine
JP4483281B2 (en) Game media lifting device
JP3952516B2 (en) Tamaki hoisting device
JP4415641B2 (en) Lifting device
JP3770209B2 (en) Tamaki hoisting device
JP3926458B2 (en) Pachinko ball polishing equipment
JP2002210204A (en) Ball lifting device
JP3962957B2 (en) Tamaki hoisting device
JP3867813B2 (en) Ball lifting device
JPH11169549A (en) Game ball lifting device
JP4183453B2 (en) Power sprayer with hose loosening prevention mechanism
JP4202159B2 (en) Abrasive cloth clamping device
JP4243821B2 (en) Game media lifting device
JP3769776B2 (en) Tamaki hoisting device
JP2002045556A (en) Ball lifting device
JP4470255B2 (en) Tamaki hoisting device
JP2002058858A (en) Ball polishing/lifting device
JP3915904B2 (en) Ball lifting device
JP6772532B2 (en) Ball lifting device

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060719

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20081021

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20081218

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20090331

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120501

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4300638

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20090413

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130501

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140501

Year of fee payment: 5

LAPS Cancellation because of no payment of annual fees