JP4226516B2 - How to change the pass schedule in a plate rolling machine - Google Patents

How to change the pass schedule in a plate rolling machine Download PDF

Info

Publication number
JP4226516B2
JP4226516B2 JP2004156724A JP2004156724A JP4226516B2 JP 4226516 B2 JP4226516 B2 JP 4226516B2 JP 2004156724 A JP2004156724 A JP 2004156724A JP 2004156724 A JP2004156724 A JP 2004156724A JP 4226516 B2 JP4226516 B2 JP 4226516B2
Authority
JP
Japan
Prior art keywords
rolling
rolled material
pass schedule
mill
pass
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2004156724A
Other languages
Japanese (ja)
Other versions
JP2005334934A (en
Inventor
都 西野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kobe Steel Ltd
Original Assignee
Kobe Steel Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kobe Steel Ltd filed Critical Kobe Steel Ltd
Priority to JP2004156724A priority Critical patent/JP4226516B2/en
Publication of JP2005334934A publication Critical patent/JP2005334934A/en
Application granted granted Critical
Publication of JP4226516B2 publication Critical patent/JP4226516B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Control Of Metal Rolling (AREA)

Description

本発明は、厚板圧延装置でのパススケジュール変更方法に関するものである。   The present invention relates to a method for changing a pass schedule in a thick plate rolling apparatus.

従来から、厚板圧延装置で複数の圧延材を連続的に圧延するに際し、その生産性を向上するために数々の技術が開示されている。
特許文献1には、厚板圧延装置において、当該圧延材とこの当該圧延材に先行して圧延される先行圧延材とを連続的に圧延するにあたり、先行圧延材の進行のずれや当該材の進行のずれを、所定のタイミングでモニタリングし、前記ずれ量が所定値を超えた場合に、粗圧延機の圧延回数を増減する等して、先行圧延材と当該圧延材とのピッチ(時間ピッチ)を最適なものに維持する技術が開示されている。
Conventionally, a number of techniques have been disclosed in order to improve productivity when continuously rolling a plurality of rolled materials with a thick plate rolling apparatus.
In Patent Document 1, in continuous rolling of the rolled material and the preceding rolled material that is rolled prior to the rolled material in a thick plate rolling apparatus, the progress of the preceding rolled material or the progress of the material The deviation of the progress is monitored at a predetermined timing, and when the deviation exceeds a predetermined value, the pitch between the preceding rolled material and the rolled material (time pitch) is increased or decreased, for example, by increasing or decreasing the number of rolling of the rough rolling mill. ) Has been disclosed.

この技術を図10に示すようなパススケジュールの圧延に適用した例を考える。
このパススケジュールは、先行圧延材を粗圧延機で所定回数だけ圧延し、その後、粗圧延機の下流側に配置された冷却装置で所定温度まで冷却し、さらに、冷却装置の下流側に配置された仕上げ圧延機で所定回数圧延を行うものである。当該圧延材も先行圧延材と略同様な工程をもって先行圧延材の所定時間後に圧延される。
このようなパススケジュールを有する先行圧延材が何らかの原因で遅延した際に、特許文献1の技術を適用した結果が図11である。すなわち、先行圧延材の遅れに対応するように、当該圧延材を冷却装置の場所に水冷を止めた状態で待機させ、仕上げ圧延機での先行圧延材と当該圧延材との時間ピッチを最小としている。換言すれば、先行圧延材の後端部と当該圧延材の先端部とが圧延に支障のない範囲でもっとも近接する状況となっている。
Consider an example in which this technique is applied to rolling of a pass schedule as shown in FIG.
In this pass schedule, the preceding rolled material is rolled a predetermined number of times by a rough rolling mill, and then cooled to a predetermined temperature by a cooling device disposed on the downstream side of the rough rolling mill, and further disposed on the downstream side of the cooling device. Rolling is performed a predetermined number of times by a finishing mill. The rolled material is also rolled after a predetermined time of the preceding rolled material in the same process as the preceding rolled material.
FIG. 11 shows the result of applying the technique of Patent Document 1 when the preceding rolled material having such a pass schedule is delayed for some reason. That is, in order to cope with the delay of the preceding rolled material, the rolled material is kept waiting at the cooling device in a state where water cooling is stopped, and the time pitch between the preceding rolled material and the rolled material in the finish rolling mill is minimized. Yes. In other words, the rear end portion of the preceding rolled material and the front end portion of the rolled material are in a state of being closest to each other as long as there is no hindrance to rolling.

また、図12に示す如く、先行圧延材の遅延時間に対応するように、粗圧延機での圧延回数を増やして、仕上げ圧延機での先行圧延材と当該圧延材との時間ピッチを最小とするようにすることも可能である。この場合には、仕上げ圧延機での圧延パス回数は少なくなる。
特公平8−18057号公報(第3頁〜第5頁、図1)
Further, as shown in FIG. 12, the number of rolling in the rough rolling mill is increased so as to correspond to the delay time of the preceding rolling material, and the time pitch between the preceding rolling material and the rolling material in the finishing rolling mill is minimized. It is also possible to do so. In this case, the number of rolling passes in the finish rolling mill is reduced.
Japanese Patent Publication No. 8-18057 (pages 3 to 5, FIG. 1)

しかしながら、特許文献1に記載された「先行圧延材と当該圧延材との時間ピッチを最短に維持する」技術は、すべての厚板圧延に有効なものではない。
例えば、近年、ユーザーニーズの厳格化に伴い、単に仕上げ圧延最終パスの出側板温度を目標値に一致させるだけでなく、粗圧延工程での板温度を目標値に一致させる圧延が要求されている。
例えば、図2は、粗圧延途中で当該圧延材に対する水冷を行うパススケジュールを示しているものである。この圧延において、図13のAに示すように、先行圧延材が予定よりも早く進んだ場合を考える。
However, the technique of “maintaining the time pitch between the preceding rolled material and the rolled material to the shortest” described in Patent Document 1 is not effective for all plate rolling.
For example, in recent years, along with tightening of user needs, is simply finish rolling but also the delivery side temperature of the final pass to match the target value, the required rolling of Ru to match the target value of the plate temperature in the rough rolling step ing.
For example, FIG. 2 is present the lines Upa scan schedule water cooling for rough rolling midway in the rolled material. In this rolling, as shown to A of FIG. 13, the case where a preceding rolling material advanced earlier than planned is considered.

特許文献1に記載された技術では、干渉を起こさない範囲で圧延材間の時間ピッチを最短にするために、粗圧延途中であって冷却装置での温度調整が行われていない当該圧延材を、仕上げ圧延機に移送するように指示することになる(図13のB)。しかしながら、前記当該圧延材は、冷却実施板厚より厚い段階で仕上げ圧延機に移送されているため、仕上げ圧延機での圧延途中で冷却実施板厚に達し、空冷による温度調節を行う必要性が生じる。ところが、空冷による冷却は、水冷時に比べ大幅に時間がかかり、仕上げ圧延終了時刻は非常に遅くなり、特許文献1の技術の適用は生産性の向上に全く寄与しない状況になっている。   In the technique described in Patent Document 1, in order to minimize the time pitch between the rolled materials within a range that does not cause interference, the rolled material that is not subjected to temperature adjustment in the cooling device during rough rolling is used. Then, it is instructed to transfer to the finishing mill (B in FIG. 13). However, since the rolled material is transferred to the finish rolling mill at a stage thicker than the cooling execution plate thickness, it is necessary to reach the cooling execution plate thickness during rolling in the finishing rolling mill and perform temperature adjustment by air cooling. Arise. However, the cooling by air cooling takes much time compared to the time of water cooling, and the finish rolling end time becomes very late, and the application of the technique of Patent Document 1 does not contribute to the improvement of productivity at all.

この状況を回避するために、仕上げ圧延終了後の圧延材を冷却装置に逆送りし水冷したとしても、急激な冷却が行われることになり、当該圧延材にひずみが生じるなどの不都合が発生する。
そこで、本発明は、上記問題点に鑑み、先行圧延材のパススケジュールが変動したとしても、当該圧延材の仕上げ圧延を最も早く終了するようにして生産性の向上を図ることが可能な厚板圧延装置でのパススケジュール変更方法を提供することを目的とする。
In order to avoid this situation, even if the rolled material after finish rolling is fed back to the cooling device and cooled with water, rapid cooling is performed and inconveniences such as distortion occur in the rolled material. .
Therefore, in view of the above problems, the present invention is a thick plate capable of improving productivity by finishing finish rolling of the rolled material earliest even if the pass schedule of the preceding rolled material changes. An object of the present invention is to provide a method for changing a pass schedule in a rolling mill.

前記目的を達成するため、本発明においては以下の技術的手段を講じた。
すなわち、本発明における課題解決のための技術的手段は、粗圧延機と仕上圧延機とを有する厚板圧延装置で、当該圧延材とこの当該圧延材に先行して圧延される先行圧延材との2つの圧延材を連続的に圧延するにあたり、先行圧延材のパススケジュールが変動した際に、それに応じて当該圧延材のパススケジュールを変更する厚板圧延装置のパススケジュール変更方法において、前記当該圧延材の仕上げ圧延終了時刻が最も早くなるパススケジュールを計算し、この計算で求められたパススケジュールを当該圧延材のパススケジュールとしている。
In order to achieve the above object, the present invention takes the following technical means.
That is, the technical means for solving the problems in the present invention is a thick plate rolling device having a rough rolling mill and a finish rolling mill, and the rolled material and the preceding rolled material that is rolled prior to the rolled material, In the continuous rolling of the two rolled materials, when the pass schedule of the preceding rolled material fluctuates, the path schedule changing method of the thick plate rolling apparatus that changes the pass schedule of the rolled material accordingly, A pass schedule in which the finish rolling finish time of the rolled material is the earliest is calculated, and the pass schedule obtained by this calculation is used as the pass schedule of the rolled material.

これによれば、先行圧延材のパススケジュールが変動した際であっても、当該圧延材の仕上げ圧延終了時刻が最も早くなるように当該圧延材を仕上げ圧延機に移送し、短時間に当該圧延材の圧延を終了することができ、生産性の向上を図ることが可能となる。
かかるパススケジュールの計算は、先行圧延材が予定されたパススケジュールから一定以上ずれた時に行うとよい。また、粗圧延機から仕上げ圧延機への移送タイミングを計算するものであるため、当該圧延材の粗圧延が完了する前に行われなくてはいけない。つまり、粗圧延が行われている状況下である必要がある。
According to this, even when the pass schedule of the preceding rolled material changes, the rolled material is transferred to the finishing mill so that the finish rolling finish time of the rolled material becomes the earliest, and the rolling is performed in a short time. The rolling of the material can be finished, and the productivity can be improved.
The calculation of the pass schedule may be performed when the preceding rolled material deviates from the scheduled pass schedule by a certain amount or more. Moreover, since the transfer timing from the rough rolling mill to the finish rolling mill is calculated, it must be performed before the rough rolling of the rolled material is completed. That is, it is necessary to be in a situation where rough rolling is performed.

さらに、パススケジュールの計算は、当該圧延材を粗圧延機から仕上げ圧延機へ移送するタイミングを算出し、それに伴いパススケジュールを変更するものであるため、粗圧延機の下流側、換言すれば粗圧延機と仕上げ圧延機との間に当該圧延材が存在する時をねらって行うべきである。圧延材が圧延機の下流側に位置するのは、粗圧延機での最初の圧延を1パス目と考えた場合、奇数パス目である。
これらのことより、前記移送タイミングの計算を、当該圧延材が粗圧延機で圧延中であって且つ先行圧延材のパススケジュール変動が一定量以上に達した状況下で、当該圧延材の奇数パス目終了毎に行うようにした。
Furthermore, the calculation of the pass schedule involves calculating the timing for transferring the rolled material from the roughing mill to the finishing mill and changing the pass schedule accordingly. This should be done when the rolling material is present between the rolling mill and the finish rolling mill. The rolling material is positioned on the downstream side of the rolling mill in the odd-numbered pass when the first rolling in the rough rolling mill is considered as the first pass.
From these, the calculation of the transfer timing is performed under the condition that the rolling material is being rolled by a roughing mill and the path schedule fluctuation of the preceding rolling material reaches a certain amount or more, and the odd number of passes of the rolling material. This is done at the end of each eye.

これによれば、当該圧延材のパススケジュールを変更する必要性が生じた時期を確実に捕らえて、移送タイミングを決定することができるようになる。
パススケジュール計算の考え方としては、まず、図3のp4の位置において、先行圧延材9の進みが検出されたとすると、まず、当該圧延材8の現行パス以降の圧延を、当該圧延材8の板厚が予め与えられた粗圧延機5での最小板厚となるまで粗圧延機5で行うと仮定する。図3のp5の位置が最小板厚となる圧延パスであるとすると、図3のp6,p7,p8,p9,p10の5つが前記仮定されたパスとなる。
According to this, it becomes possible to reliably capture the time when the necessity of changing the pass schedule of the rolled material occurs and to determine the transfer timing.
As a concept of pass schedule calculation, first, assuming that the advance of the preceding rolled material 9 is detected at the position p4 in FIG. 3, first, rolling of the rolled material 8 after the current pass is performed. It is assumed that the roughing is performed in the roughing mill 5 until the thickness reaches the minimum thickness in the roughing mill 5 given in advance. Assuming that the rolling path at which the position p5 in FIG. 3 is the minimum plate thickness, five paths p6, p7, p8, p9, and p10 in FIG. 3 are the assumed paths.

次に,図3におけるp6のパス間で粗圧延機から仕上げ圧延機への移送が実施されるとし、当該圧延材のパススケジュールを再計算すると同時に,p6で移送した場合の当該材の仕上げ圧延完了の予想時刻T6を計算する。
同様に、図中のp7,p8,p9,p10のパス間についても,図3の点線矢印の如く、そのパス間にて移送が実施されるという条件で,当該材のパススケジュールを再計算すると同時に,それぞれのパス間で移送した場合の当該材の仕上げ圧延完了の予測時刻T7,T8,T9,T10を計算する。
Next, it is assumed that the transfer from the roughing mill to the finish rolling mill is performed between the passes of p6 in FIG. 3, and the pass rolling schedule of the rolled material is recalculated and at the same time the finish rolling of the material is transferred at p6. An expected completion time T6 is calculated.
Similarly, if the path schedule of the material is recalculated between the paths p7, p8, p9, and p10 in the figure under the condition that transfer is performed between the paths as indicated by the dotted arrows in FIG. At the same time, predicted times T7, T8, T9, and T10 of completion of finish rolling of the material when transferred between the passes are calculated.

次に、T6〜T10の中から、先行圧延材と当該圧延材とが干渉しない範囲で完了時刻が最も早いもの(T8)を選び、この奇数パスが移送タイミングとなるように、当該圧延材の圧延パススケジュールを変更するようにすればよい。
すなわち、前記パススケジュールの計算は、前記パススケジュールの計算は、当該圧延材の板厚が予め与えられた粗圧延機での最小板厚となるまで、現在パス以降の圧延を粗圧延機で行うと仮定した上で、それぞれの奇数パス間で当該圧延材を仕上げ圧延機に移送した場合の仕上げ圧延終了時刻を算出し、これら算出された仕上げ圧延終了時刻のうち、もっとも早い仕上げ圧延終了時刻を実現する奇数パスを、当該圧延材の粗圧延機5ら仕上げ圧延機への移送タイミングとするとよい。
Next, from T6 to T10, the one with the earliest completion time (T8) is selected in a range in which the preceding rolled material and the rolled material do not interfere with each other, so that the odd-numbered path becomes the transfer timing. What is necessary is just to change a rolling pass schedule.
That is, the calculation of the pass schedule is performed using the roughing mill after the current pass until the plate thickness of the rolling material reaches the minimum thickness in the roughing mill given in advance. Assuming that, the finish rolling end time is calculated when the rolled material is transferred to the finish rolling mill between each odd number of passes, and among these calculated finish rolling end times, the earliest finish rolling end time is calculated. The odd number path to be realized may be the transfer timing of the rolled material from the rough rolling mill 5 to the finishing rolling mill.

この技術的手段によれば、評価関数などの難しい数学的手法を用いることなく、最も早い仕上げ圧延終了時刻を実現する移送タイミングを算出することが可能となる。
なお、最も好ましい本発明における課題解決のための技術的手段は、粗圧延機と仕上げ圧延機とを有する厚板圧延装置で、当該圧延材とこの当該圧延材に先行して圧延される先行圧延材との2つの圧延材を連続的に圧延するにあたり、先行圧延材のパススケジュールが変動した際に、それに応じて当該圧延材のパススケジュールを変更する厚板圧延装置のパススケジュール変更方法において、前記当該圧延材の仕上げ圧延終了時刻が最も早くなるパススケジュールを計算し、この計算で求められたパススケジュールを当該圧延材のパススケジュールとするものであって、前記パススケジュールの計算は、当該圧延材が粗圧延機で圧延中であって且つ先行圧延材のパススケジュール変動が一定量以上に達した状況下で、当該圧延材の奇数パス目終了毎に行われ、且つ、前記パススケジュールの計算は、当該圧延材の板厚が予め与えられた粗圧延機での最小板厚となるまで、現在パス以降の圧延を粗圧延機で行うと仮定した上で、それぞれの奇数パス間で当該圧延材を仕上げ圧延機に移送した場合の仕上げ圧延終了時刻を算出し、これら算出された仕上げ圧延終了時刻のうち、もっとも早い仕上げ圧延終了時刻を実現する奇数パスを、当該圧延材の粗圧延機から仕上げ圧延機への移送タイミングとすることを特徴とする。
According to this technical means, it is possible to calculate the transfer timing that realizes the earliest finish rolling end time without using a difficult mathematical method such as an evaluation function.
The most preferable technical means for solving the problem in the present invention is a thick plate rolling device having a roughing mill and a finish rolling mill, and the rolling material and the preceding rolling rolled before the rolling material. In continuously rolling two rolled materials with a material, when the pass schedule of the preceding rolled material fluctuates, the path schedule changing method of the thick plate rolling apparatus changes the pass schedule of the rolled material accordingly, A pass schedule in which the finish rolling finish time of the rolled material is the earliest is calculated, and the pass schedule obtained by this calculation is used as the pass schedule of the rolled material, and the calculation of the pass schedule is performed by the rolling When the material is being rolled by a roughing mill and the fluctuation of the pass schedule of the preceding rolled material reaches a certain amount or more, the odd-numbered pass of the rolled material And the calculation of the pass schedule is performed when the rolling after the current pass is performed by the roughing mill until the thickness of the rolled material reaches the minimum thickness in the roughing mill given in advance. Assuming that the finish rolling end time is calculated when the rolled material is transferred to the finish mill between each odd number of passes, and the earliest finish rolling end time among the calculated finish rolling end times is realized. The odd-numbered path to be used is the transfer timing of the rolled material from the roughing mill to the finishing mill.

本発明によれば、先行圧延材及び当該圧延材を連続的に圧延する厚板圧延装置において、先行圧延材のパススケジュールが変動したとしても、当該圧延材の仕上げ圧延を最も早く終了するようにでき、生産性の向上を図ることが可能となる。   According to the present invention, in the plate rolling apparatus for continuously rolling the preceding rolled material and the rolled material, even if the pass schedule of the preceding rolled material fluctuates, finish rolling of the rolled material is finished earliest. It is possible to improve productivity.

以下、本発明にかかる厚板圧延装置1のパススケジュール変更方法を、図を基に以下説明する。
図1には、厚板圧延装置1の概略が示されており、かかる厚板圧延装置1は上流側に圧延材を加熱する加熱炉2を有し、加熱炉2の下流側には一対のワークロール3と一対のバックアップロール4とを備える粗圧延機(粗ミル)5が備えられている。粗圧延機5の下流側には、圧延材に水や空気を吹き付けたりして温度を調整する冷却装置6が配設され、冷却装置6の下流側には、一対のワークロール3と一対のバックアップロール4とを備える仕上げ圧延機(仕上げミル)7が設けられている。
Hereinafter, the pass schedule changing method of the thick plate rolling device 1 according to the present invention will be described with reference to the drawings.
FIG. 1 shows an outline of a thick plate rolling apparatus 1. The thick plate rolling apparatus 1 has a heating furnace 2 for heating a rolled material on the upstream side, and a pair of downstream side of the heating furnace 2. A rough rolling mill (coarse mill) 5 including a work roll 3 and a pair of backup rolls 4 is provided. A cooling device 6 that adjusts the temperature by spraying water or air on the rolled material is disposed on the downstream side of the rough rolling mill 5. A pair of work rolls 3 and a pair of work rollers 3 are disposed on the downstream side of the cooling device 6. A finishing rolling mill (finishing mill) 7 having a backup roll 4 is provided.

厚板圧延装置1においては、当該圧延材8と当該圧延材8に先だって圧延が行われる先行圧延材9との2つの圧延材が、予め設定されたパススケジュールに基づいて連続的に圧延されるようになっている。
図2のAは先行圧延材9のパススケジュールを示しており、加熱炉2で所定温度に加熱された先行圧延材9は、粗圧延機5に導入され、複数パスだけリバース圧延が行われる。その後、冷却装置6で冷却された上で、仕上げ圧延機7に移送されてリバース圧延され、厚板圧延が完了することになる。
In the thick plate rolling device 1, two rolled materials, the rolled material 8 and a preceding rolled material 9 that is rolled prior to the rolled material 8, are continuously rolled based on a preset pass schedule. It is like that.
FIG. 2A shows a pass schedule of the preceding rolled material 9, and the preceding rolled material 9 heated to a predetermined temperature in the heating furnace 2 is introduced into the roughing mill 5, and reverse rolling is performed for a plurality of passes. Then, after cooling with the cooling device 6, it is transferred to the finish rolling mill 7 and reverse rolled, and the plate rolling is completed.

この先行圧延材9に追従するように、当該圧延材8も、図2のBの如く、加熱炉2から粗圧延機5に搬送されリバース圧延される。当該圧延材8は、粗圧延工程で、粗圧延を実施する板厚域において指定された板厚の板温度を目標値に一致させる圧延を行うものであるため、粗圧延の途中にいったん冷却装置6に搬送され温度調整される。その後、再度、粗圧延機5で所定パスだけ圧延を施され、さらに冷却装置6で温度調整された後、仕上げ圧延機7で圧延が行われる。
なお、本実施形態の説明では、圧延材8,9が粗圧延機5の処理終了後、仕上げ圧延機7の処理に移ることを「移送」と呼ぶ。ゆえに、粗圧延機5から離れて冷却装置6へ運ばれた後、再び粗圧延機5に戻る場合は、すべて粗圧延機5での処理と解釈し、移送とは呼ばず「搬送」と表現する。
The rolled material 8 is also conveyed from the heating furnace 2 to the rough rolling mill 5 and reverse-rolled so as to follow the preceding rolled material 9 as shown in FIG. The rolled material 8 is a rough rolling step, the plate thickness of the plate temperature specified in the thickness range of implementing the rough rolling is performed a rolling of Ru to match the target value, once in the middle of the rough rolling The temperature is adjusted by being conveyed to the cooling device 6. Thereafter, rolling is performed again for a predetermined pass by the rough rolling mill 5, the temperature is adjusted by the cooling device 6, and then rolling is performed by the finish rolling mill 7.
In the description of the present embodiment, the transfer of the rolled materials 8 and 9 to the processing of the finish rolling mill 7 after the processing of the rough rolling mill 5 is referred to as “transfer”. Therefore, when it moves away from the rough rolling mill 5 to the cooling device 6 and returns to the rough rolling mill 5 again, it is interpreted as processing in the rough rolling mill 5 and expressed as “conveyance” instead of transfer. To do.

当該圧延材8を圧延する際に、先行圧延材9の圧延実績が何らかの原因で当初パススケジュールからズレたりする場合がある。その時には、前記当該圧延材8の仕上げ圧延終了時刻が最も早くなるパススケジュールを再計算し、この計算で求められたパススケジュールを当該圧延材8のパススケジュールとするようにしている。
なお、先行圧延材9が一定量だけ遅延もしくは進んだりすることを、どのタイミングで検出し、それに基づいてパススケジュール再計算するかは、非常に重要な事項である。
本実施形態では、先行圧延材9が予定されたパススケジュールから予め設定された所定量以上ずれた時に行うようにしている。
When rolling the rolled material 8, there is a case where the rolling results of the prior rolling material 9 or displaced from the initial pass schedule for some reason. At that time, the pass schedule in which the finish rolling finish time of the rolled material 8 becomes the earliest is recalculated, and the pass schedule obtained by this calculation is set as the pass schedule of the rolled material 8.
In addition, it is a very important matter to detect at which timing that the preceding rolled material 9 is delayed or advanced by a certain amount and to recalculate the pass schedule based on it.
In the present embodiment, the process is performed when the preceding rolled material 9 deviates from a scheduled pass schedule by a predetermined amount or more.

また、粗圧延機5から仕上げ圧延機7への移送タイミングを計算するものであるため、当該圧延材8の粗圧延が完了する前に行うようにしている。つまり、粗圧延が行われている状況下である必要がある。さらに、粗圧延機5の下流側、換言すれば粗圧延機5と仕上げ圧延機7との間に当該圧延材8が存在する時をねらって行うべきである。圧延材が圧延機の下流側に位置するのは、粗圧延機5での最初の圧延を1パス目と考えた場合、奇数パス目である。
整理すると、
(a)先行圧延材9の当初パススケジュールからのズレ量が一定値以上に達した時点以降のパス間
(b)当該圧延材8の板厚が移送時の板厚(移送厚)の下限値以上であるパス間
(c)粗圧延の1パス目を基準とした場合の奇数パス終了時のパス間
の全てを満たすパス間において、パススケジュールの見直しを行うようする。
Moreover, since the transfer timing from the rough rolling mill 5 to the finish rolling mill 7 is calculated, it is performed before the rough rolling of the rolled material 8 is completed. That is, it is necessary to be in a situation where rough rolling is performed. Furthermore, it should be performed aiming at the time when the rolling material 8 exists downstream of the rough rolling mill 5, in other words, between the rough rolling mill 5 and the finish rolling mill 7. The rolling material is located on the downstream side of the rolling mill in the odd-numbered pass when the first rolling in the rough rolling mill 5 is considered as the first pass.
Organize
(A) Between passes after the time when the amount of deviation from the initial pass schedule of the preceding rolled material 9 reaches a certain value or more (b) The lower limit value of the thickness (transfer thickness) of the rolled material 8 when it is transferred Between the passes as described above (c) The pass schedule is reviewed between passes satisfying all of the passes at the end of odd-numbered passes when the first pass of rough rolling is used as a reference.

前記(a)の条件は、例えば、当該圧延材8よりも下流側にある各設備,すなわち冷却装置6と仕上げ圧延機7での先行圧延材9の処理完了時刻の予測値を計算し、それぞれの予定値との差のうち絶対値の最大のものを選び、それが一定値以上に達したことで判断するようにすることが好ましい。
前記パススケジュール再計算を行うにあたっては、当該圧延材8を、現在パス以降全て粗圧延機5で行うと仮定すると共に、それぞれの奇数パス間で仕上げ圧延機7に移送した場合の仕上げ圧延終了時刻を予測し、これら算出された仕上げ圧延終了時刻のうち、もっとも早い仕上げ圧延終了時刻を実現する奇数パスを、当該圧延材8の粗圧延機5から仕上げ圧延機7への移送タイミングとするようにしている。
The condition (a) is, for example, calculating predicted values of the processing completion time of the preceding rolled material 9 in each equipment, that is, the cooling device 6 and the finish rolling mill 7 on the downstream side of the rolled material 8, respectively. It is preferable to select the largest absolute value among the differences from the planned value and to make a judgment when it reaches a certain value or more.
In performing the recalculation of the pass schedule, it is assumed that the rolled material 8 is all carried out by the roughing mill 5 after the current pass, and the finish rolling finish time when the rolling material 8 is transferred to the finishing mill 7 between the respective odd passes. The odd-numbered path that realizes the earliest finish rolling end time among these calculated finish rolling end times is used as the transfer timing of the rolled material 8 from the rough rolling mill 5 to the finish rolling mill 7. ing.

例えば、図3に示すように、当該圧延材8を圧延するに際し、先行圧延材9が図3のAの如く進んだ場合を考える(2点鎖線が当初のパススケジュール)。
図3のp4の位置において、先行圧延材9の進みが検出されたとすると、まず、当該圧延材8の現行パス以降の圧延を、当該圧延材8の板厚が予め与えられた粗圧延機5での最小板厚となるまで粗圧延機5で行うと仮定する。図3のp5の位置が最小板厚となる圧延パスであるとすると、図3のp6,p7,p8,p9,p10の5つが前記仮定されたパスとなる。
For example, as shown in FIG. 3, upon which rolling the rolled material 8, the preceding rolled material 9 Consider the case advanced as A in FIG. 3 (two-dot chain line initial pass schedule).
Assuming that the advance of the preceding rolled material 9 is detected at the position p4 in FIG. 3, first, the rough rolling mill 5 in which the thickness of the rolled material 8 is given in advance for rolling after the current pass of the rolled material 8. It is assumed that the roughing is performed by the roughing mill 5 until the minimum sheet thickness is reached. Assuming that the rolling path at which the position p5 in FIG. 3 is the minimum plate thickness, five paths p6, p7, p8, p9, and p10 in FIG. 3 are the assumed paths.

次に,図3におけるp6のパス間で粗圧延機5から仕上げ圧延機7への移送が実施されたとし、当該圧延材8のパススケジュールを再計算すると共に、p6で移送した場合の当該圧延材の仕上げ圧延完了の予想時刻T6を算出する。
同様に、p7,p8,p9,p10のパス間についても、図3の点線矢印で示す如く、各パス間で移送が実施されるという条件のもと、当該圧延材をそれぞれのパス間で移送した場合の仕上げ圧延完了予測時刻T7,T8,T9,T10を計算する。当然、各パスでの移送において、移送された当該圧延材8は、先行圧延材9と必要最低限の間隔が確保されているものとなっている。
Next, assuming that the transfer from the roughing mill 5 to the finish rolling mill 7 was performed between the passes of p6 in FIG. 3, the rolling schedule in the case where the rolling schedule 8 was recalculated and transferred at p6 was recalculated. An expected time T6 for completion of finish rolling of the material is calculated.
Similarly, between the passes of p7, p8, p9, and p10, the rolled material is transferred between the respective passes under the condition that the transfer is performed between the passes as shown by the dotted arrows in FIG. In this case, finish rolling completion prediction times T7, T8, T9, and T10 are calculated. Naturally, in the transfer in each pass, the transferred rolled material 8 has a minimum necessary distance from the preceding rolled material 9.

例えば、前記T6〜T10の中で、T8がもっとも早い時刻であったとする。その場合、p8にて移送を行うという条件で、当該圧延材8のパススケジュールを再計算し、この計算結果を新たなパススケジュール(図3のB、図4のB)とするようにする。
一方、先行圧延材9のズレに対して、先行圧延材9と当該圧延材8との時間ピッチが最短となるような制御方法を用いた際には、図4のCのようになり、結果的に最終圧延完了時間は遅くなる。つまり、本発明にかかる技術は、前記最短ピッチ制御方法に比べ、仕上げ圧延完了までにかかる時間を大幅に短縮するものとなっている。
For example, it is assumed that T8 is the earliest time among T6 to T10. In that case, the pass schedule of the rolled material 8 is recalculated on the condition that the transfer is performed at p8, and the calculation result is set as a new pass schedule (B in FIG. 3 and B in FIG. 4).
On the other hand, when a control method is used such that the time pitch between the preceding rolled material 9 and the rolled material 8 is the shortest with respect to the deviation of the preceding rolled material 9, the result is as shown in FIG. In particular, the final rolling completion time is delayed. That is, the technique according to the present invention significantly shortens the time required to complete the finish rolling as compared with the shortest pitch control method.

このようなパススケジュールの再計算方法を用いることで、評価関数などの難しい数学的手法を用いることなく、最も早い仕上げ圧延終了時刻を実現する移送タイミングを決定し、容易にパススケジュールを再計算することが可能となる。
図5には、パススケジュールの別例が示してある。本パススケジュールでは、当該圧延材8は冷却装置6で冷却されずに、粗圧延機5から直接仕上げ圧延機7へ移送され、仕上げ圧延機7で空冷により温度調整されるものとなっている。
このパススケジュールにおいて、図6のAに示すように、先行圧延材9が何らかの原因で遅延した場合を考える(当初パススケジュールは2点鎖線)。このような先行圧延材9の遅延をカバーするために、先行圧延材9と当該圧延材8との時間間隔を最短にするようなパススケジュールを計算した場合が、図中の破線(図6のC)で示してある(従来技術の適用)。
By using this pass schedule recalculation method, it is possible to easily recalculate the pass schedule by determining the transfer timing that achieves the earliest finish rolling end time without using difficult mathematical methods such as evaluation functions. It becomes possible.
In FIG. 5, there is shown another example of a path schedule. In this pass schedule, the rolled material 8 is not cooled by the cooling device 6 but directly transferred from the rough rolling mill 5 to the finishing rolling mill 7, and the temperature is adjusted by air cooling in the finishing rolling mill 7.
In this pass schedule, as shown in FIG. 6A, consider a case where the preceding rolled material 9 is delayed for some reason (the initial pass schedule is a two-dot chain line). In order to cover such a delay of the preceding rolled material 9, a case where a pass schedule that minimizes the time interval between the preceding rolled material 9 and the rolled material 8 is calculated is shown by a broken line in FIG. C) (application of the prior art).

この場合、当該圧延材8は、遅延した先行圧延材9との間隔ピッチを所定のものにするために、粗圧延機5において所定時間だけウェイティング状態となり、その後、仕上げ圧延機7に移送され圧延・冷却が行われるようになる。結局、仕上げ圧延終了時間は遅くなる。
一方、本発明にかかる技術を適用した場合には、当該圧延材8のパススケジュールは、図6のBのようになる。このパススケジュールでは、当該圧延材8の冷却を仕上げ圧延機7近傍で行うことにこだわらず、仕上げ圧延終了時刻を最も早いものにするため、冷却装置6の位置で冷却を行うようにしている。したがって、当該圧延材8の待ち時間を作ることなく効率的なパススケジュールが組まれるようになっている。
In this case, the rolled material 8 is in a waiting state for a predetermined time in the roughing mill 5 in order to make the interval pitch with the delayed preceding rolled material 9 predetermined, and then transferred to the finishing mill 7 and rolled.・ Cooling starts. Eventually, the finish rolling finish time is delayed.
On the other hand, when the technique according to the present invention is applied, the pass schedule of the rolled material 8 is as shown in FIG. In this pass schedule, the rolling material 8 is not cooled in the vicinity of the finish rolling mill 7 but is cooled at the position of the cooling device 6 in order to make the finish rolling finish time the earliest. Therefore, an efficient pass schedule can be established without creating a waiting time for the rolled material 8.

以上述べたパススケジュール変更方法は、図1に示した制御手段10により計算される。制御手段10は、プロコン(プロセスコンピュータ)等で構成されており、計算結果が厚板圧延装置1に反映されるものとなっている。
例えば、先行圧延材9と当該圧延材8との圧延工程において、図7のようなパススケジュールが組まれていたとする。
前記制御手段10においては、図8に示すスケジュール変更トリガ処理が一定周期(例えば1分ごと)で、図7に示したパススケジュールに対する先行圧延材9のズレ量を監視するものとなっており、その値が閾値αを越えたと判断した時点で、スケジュール変更トリガ処理は終了し、当該圧延材8のパススケジュール再計算を行うスケジュール変更処理(図9)を起動するものとなっている。
The path schedule changing method described above is calculated by the control means 10 shown in FIG. The control means 10 is composed of a process computer (process computer) or the like, and the calculation result is reflected in the thick plate rolling apparatus 1.
For example, it is assumed that a pass schedule as shown in FIG. 7 is set in the rolling process of the preceding rolled material 9 and the rolled material 8.
In the control means 10, the schedule change trigger process shown in FIG. 8 is to monitor the amount of deviation of the preceding rolled material 9 with respect to the pass schedule shown in FIG. When it is determined that the value exceeds the threshold value α, the schedule change trigger process ends, and the schedule change process (FIG. 9) that performs recalculation of the pass schedule of the rolled material 8 is started.

前記スケジュール変更トリガ処理は、まず、先行圧延材9に対する冷却設備での冷却処理が完了する時刻rTsc(予測値)を計算する。このとき、既に冷却処理を完了している場合、実績時刻を採取するようにする。(S71)
次に、先行圧延材9に対する仕上げ圧延機7でのリバース圧延が完了する時刻rTsfを予測するようにする。(S72)
それら求められた値を基にして、冷却処理完了時刻の偏差 dTsc = | Tsc ・ rTsc | を求めると共に、仕上げ圧延機処理完了時刻の偏差 dTsf = | Tsf ・ rTsf | を求めるようにする。なお、 Tscは、当初パススケジュールでの冷却処理の完了時刻であり、Tsfは、当初パススケジュールでの仕上げ圧延機処理の完了時刻である。(S73、S74)
以上、求まった冷却処理完了時刻の偏差dTscと、仕上げ圧延機完了時刻の偏差dTsfとの内、最も大きいものdTs (= max(dTsc, dTsf))を抽出し、かかるdTsを、先行圧延材9のパススケジュールのズレ量とする。(S75)
前記パススケジュールズレ量dTsと、予め定めた閾値αを比較し、dTs > αであるならば、当該圧延材8のパススケジュールを変更する「スケジュール変更処理」を起動するようにする。(S77)
スケジュール変更処理は、図9に示すような手順で行われる。
In the schedule change trigger process, first, a time rTsc (predicted value) at which the cooling process for the preceding rolled material 9 in the cooling facility is completed is calculated. At this time, if the cooling process has already been completed, the actual time is collected. (S71)
Next, the time rTsf at which the reverse rolling in the finish rolling mill 7 for the preceding rolled material 9 is completed is predicted. (S72)
Based on the obtained values, the deviation dTsc = | Tsc · rTsc | of the cooling processing completion time is obtained, and the deviation dTsf = | Tsf · rTsf | of the finishing mill processing completion time is obtained. Tsc is the completion time of the cooling process in the initial pass schedule, and Tsf is the completion time of the finish rolling mill process in the initial pass schedule. (S73, S74)
As described above, the largest dTs (= max (dTsc, dTsf)) is extracted from the obtained deviation dTsc of the cooling processing completion time and the deviation dTsf of the finish rolling mill completion time, and this dTs is extracted as the preceding rolling material 9 The amount of deviation in the pass schedule. (S75)
The pass schedule deviation amount dTs is compared with a predetermined threshold value α. If dTs> α, a “schedule change process” for changing the pass schedule of the rolled material 8 is started. (S77)
The schedule change process is performed according to the procedure shown in FIG.

まず、次の条件を満たすパス間 (p1〜pk)を求める。(S81)
(a)先行圧延材9の予定変更が一定値以上に達した時点以降
(b)当該圧延材8の板厚が、当該圧延材8に対して与えられた移送厚(移送時の板厚)の下限値以上
(c)粗圧延の1パス目を基準とした場合の奇数パス終了時
次に、piパス(i=7ならば、p7パス)にて、粗圧延機5から仕上圧延機への移送を行うとして、当該圧延材8のパススケジュールを再計算し、この結果を基に当該圧延材8の仕上圧延完了時刻(Ti)の予測値を計算する。(S82、S83)
以上の処理をi=1〜k間で繰り返し、T1〜Tkを計算する。
First, an interval between paths (p1 to pk) that satisfies the following condition is obtained. (S81)
(A) After the scheduled change of the preceding rolled material 9 reaches a certain value or more (b) The thickness of the rolled material 8 is given to the rolled material 8 (the thickness at the time of transfer) (C) At the end of the odd pass when the first pass of rough rolling is used as a reference Next, from the rough rolling mill 5 to the finishing mill in a pi pass (if i = 7, p7 pass) , The pass schedule of the rolled material 8 is recalculated, and the predicted value of the finish rolling completion time (Ti) of the rolled material 8 is calculated based on this result. (S82, S83)
The above process is repeated between i = 1 to k to calculate T1 to Tk.

これらT1〜Tkの中で最小のものを選び,それに該当するパス間を移送タイミングとし、決定された移送タイミングにて当該圧延材8のパススケジュールを変更するようにする。(S84、S85)
なお、本発明は、上記実施の形態に限定されるものではない。
すなわち、本発明は、当該圧延材8が温度調整を行わない場合であっても適用可能である。
The smallest one of these T1 to Tk is selected, and the interval between the corresponding passes is set as the transfer timing, and the pass schedule of the rolled material 8 is changed at the determined transfer timing. (S84, S85)
The present invention is not limited to the above embodiment.
Namely, the present invention is applicable to a case where the rolled material 8 does not perform temperature adjustment.

厚板圧延装置の概略を示す図である。It is a figure which shows the outline of a thick plate rolling apparatus. 度制御を行う圧延の予定パススケジュールを示した図である。Is a diagram showing the planned pass schedule of rolling performing temperature control. 本発明にかかるパススケジュールの変更方法を説明する図である。It is a figure explaining the change method of the path schedule concerning this invention. 図2のパススケジュールを変更した結果を示す図である(先行圧延材が進んだ場合)。It is a figure which shows the result of having changed the pass schedule of FIG. 2 (when a preceding rolling material advances). 度制御を行う圧延の予定パススケジュールを示した図である。Is a diagram showing the planned pass schedule of rolling performing temperature control. 図5のパススケジュールを変更した結果を示す図である(先行圧延材が遅延した場合)。It is a figure which shows the result of having changed the pass schedule of FIG. 5 (when a preceding rolling material is delayed). 予定パススケジュールの詳細を示した図である。It is the figure which showed the detail of the plan path schedule. スケジュール変更トリガ処理のフローチャートである。It is a flowchart of a schedule change trigger process. スケジュール変更処理のフローチャートである。It is a flowchart of a schedule change process. 厚板圧延装置における典型的なパススケジュールを示した図である。It is the figure which showed the typical pass schedule in a plate rolling apparatus. 従来技術を用いて図10のパススケジュールを変更した結果を示す図である(先行圧延材が遅延した場合)。It is a figure which shows the result of having changed the pass schedule of FIG. 10 using a prior art (when a preceding rolling material is delayed). 従来技術を用いて図10のパススケジュールを変更した結果を示す図である(先行圧延材が遅延した場合)。It is a figure which shows the result of having changed the pass schedule of FIG. 10 using a prior art (when a preceding rolling material is delayed). 従来技術を用いて図2のパススケジュールを変更した結果を示す図である(先行圧延材が進んだ場合)。It is a figure which shows the result of having changed the pass schedule of FIG. 2 using a prior art (when a preceding rolling material progresses).

符号の説明Explanation of symbols

1 厚板圧延装置
5 粗圧延機
7 仕上げ圧延機
8 当該圧延材
9 先行圧延材
DESCRIPTION OF SYMBOLS 1 Thick plate rolling apparatus 5 Rough rolling mill 7 Finishing rolling mill 8 The said rolling material 9 Prior rolling material

Claims (1)

粗圧延機と仕上げ圧延機とを有する厚板圧延装置で、当該圧延材とこの当該圧延材に先行して圧延される先行圧延材との2つの圧延材を連続的に圧延するにあたり、先行圧延材のパススケジュールが変動した際に、それに応じて当該圧延材のパススケジュールを変更する厚板圧延装置のパススケジュール変更方法において、
前記当該圧延材の仕上げ圧延終了時刻が最も早くなるパススケジュールを計算し、この計算で求められたパススケジュールを当該圧延材のパススケジュールとするものであって、
前記パススケジュールの計算は、当該圧延材が粗圧延機で圧延中であって且つ先行圧延材のパススケジュール変動が一定量以上に達した状況下で、当該圧延材の奇数パス目終了毎に行われ、
且つ、前記パススケジュールの計算は、当該圧延材の板厚が予め与えられた粗圧延機での最小板厚となるまで、現在パス以降の圧延を粗圧延機で行うと仮定した上で、それぞれの奇数パス間で当該圧延材を仕上げ圧延機に移送した場合の仕上げ圧延終了時刻を算出し、これら算出された仕上げ圧延終了時刻のうち、もっとも早い仕上げ圧延終了時刻を実現する奇数パスを、当該圧延材の粗圧延機から仕上げ圧延機への移送タイミングとすることを特徴とする厚板圧延装置のパススケジュール変更方法。
In the thick plate rolling machine having a rough rolling mill and a finish rolling mill, in order to continuously roll the two rolled materials of the rolled material and the preceding rolled material rolled prior to the rolled material, the preceding rolling is performed. In the path schedule change method of the plate rolling apparatus that changes the pass schedule of the rolled material accordingly when the pass schedule of the material changes,
Calculating a pass schedule in which the finish rolling finish time of the rolled material is the earliest, and setting the pass schedule obtained by this calculation as the pass schedule of the rolled material ,
The calculation of the pass schedule is performed at every end of the odd-numbered pass of the rolled material in a situation where the rolled material is being rolled by a roughing mill and the fluctuation of the pass schedule of the preceding rolled material reaches a certain amount or more. I,
In addition, the calculation of the pass schedule is based on the assumption that the rolling after the current pass is performed in the roughing mill until the thickness of the rolled material reaches the minimum thickness in the roughing mill given in advance. The finish rolling end time when the rolled material is transferred to the finishing mill between the odd-numbered passes is calculated, and among the calculated finish rolling end times, the odd-numbered pass that realizes the earliest finish rolling end time is calculated. A method for changing a pass schedule of a thick plate rolling apparatus, characterized in that it is a transfer timing of a rolled material from a rough rolling mill to a finishing rolling mill .
JP2004156724A 2004-05-26 2004-05-26 How to change the pass schedule in a plate rolling machine Expired - Lifetime JP4226516B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004156724A JP4226516B2 (en) 2004-05-26 2004-05-26 How to change the pass schedule in a plate rolling machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004156724A JP4226516B2 (en) 2004-05-26 2004-05-26 How to change the pass schedule in a plate rolling machine

Publications (2)

Publication Number Publication Date
JP2005334934A JP2005334934A (en) 2005-12-08
JP4226516B2 true JP4226516B2 (en) 2009-02-18

Family

ID=35489047

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004156724A Expired - Lifetime JP4226516B2 (en) 2004-05-26 2004-05-26 How to change the pass schedule in a plate rolling machine

Country Status (1)

Country Link
JP (1) JP4226516B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5229069B2 (en) * 2009-04-01 2013-07-03 新日鐵住金株式会社 Method for determining rolling pass schedule of thick steel plate and method for manufacturing thick steel plate
JP5625816B2 (en) * 2010-11-29 2014-11-19 Jfeスチール株式会社 Thick steel plate manufacturing apparatus and water cooling time setting method for cooling device in thick steel plate manufacturing apparatus
CN110665974B (en) * 2019-10-15 2022-08-09 上海宝钢工业技术服务有限公司 Implementation method for material preparation roller of rolling line finish rolling working roller

Also Published As

Publication number Publication date
JP2005334934A (en) 2005-12-08

Similar Documents

Publication Publication Date Title
JP7067537B2 (en) Warp prediction method, warp control method, hot-rolled steel sheet manufacturing method, warp prediction model generation method, and hot-rolling equipment in the hot-rolling process.
JP7176507B2 (en) Hot rolling warpage prediction method, warpage control method, hot rolled steel sheet manufacturing method, warpage prediction model generation method, and hot rolling equipment
KR100604503B1 (en) Method and apparatus for controlling sheet shape in sheet rolling
KR102043529B1 (en) Method for controlling coil width and apparatus thereof
JP4226516B2 (en) How to change the pass schedule in a plate rolling machine
JP6428932B2 (en) Leading end plate width controller
JP4349255B2 (en) Pass schedule setting method and thick steel plate manufacturing method
JP3826801B2 (en) Mill Pacing Method for Hot Rolling Line
JP6075309B2 (en) Heating furnace control method and control apparatus
JP7405106B2 (en) Leveling control method, leveling control device, and hot rolling equipment in hot rolling
JPH06190422A (en) Temper rolling method
JP2006095592A (en) Extension rate control method in temper rolling mill
JP3470627B2 (en) Automatic extraction method of heating furnace in hot rolling
JP5581600B2 (en) Determination method of heating furnace extraction interval
JPH067823A (en) Method for extracting rolled stock from heating furnace in hot rolling
JPH0818057B2 (en) Control method of material input pitch in thick steel plate rolling line
JP5266941B2 (en) Rolling material conveyance control method in hot rolling line
JP2021109185A (en) Control method for rolling device, control device for rolling device, and manufacturing method for steel plate
JP2010172927A (en) Method of controlling terminal warp of rolled material
JP2006272439A (en) Production method of thick steel strip and its manufacturing apparatus
JP4305156B2 (en) Heat treatment method for steel sheet
JP2000237811A (en) Width controller for hot-rolling mill
KR101193868B1 (en) Method for roughing mill of taper slab
JP6733612B2 (en) Rolling line control device
JP2004255409A (en) Method for rolling steel sheet

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060925

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080822

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080902

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20081029

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20081125

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20081126

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111205

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4226516

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121205

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131205

Year of fee payment: 5

EXPY Cancellation because of completion of term