JP4099293B2 - Tunnel interior board direct installation method and equipment - Google Patents
Tunnel interior board direct installation method and equipment Download PDFInfo
- Publication number
- JP4099293B2 JP4099293B2 JP21039499A JP21039499A JP4099293B2 JP 4099293 B2 JP4099293 B2 JP 4099293B2 JP 21039499 A JP21039499 A JP 21039499A JP 21039499 A JP21039499 A JP 21039499A JP 4099293 B2 JP4099293 B2 JP 4099293B2
- Authority
- JP
- Japan
- Prior art keywords
- tunnel interior
- tunnel
- interior plate
- plate
- formwork
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Lining And Supports For Tunnels (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、トンネル内に打設した二次覆工用コンクリート表面の防護と美観を向上させるためのトンネル内装板を、二次覆工用コンクリート打設と同時施工することができるトンネル内装板の直打設工法およびその装置に関するものである。なお、本明細書中、「打設」とは、養生硬化してない流動性コンクリートを型枠と、トンネル内壁面または一次覆工用コンクリートと、の間に充填させることをいう。
【0002】
【従来の技術】
元来、トンネル壁面(二次覆工させたコンクリートの表面)との輝度差から視線誘導を促し、ドライバーの視認性を向上させ、自動車の安定走行を支援すると共に、トンネル壁面の漏水、配管の露出、トンネル壁面の不揃いを被覆することによりトンネル壁面の防護と美観を向上させる措置として、通常トンネル壁面の下方部分に、白色系塗装を施したトンネル内装板を施工し(取付け)ていた。
【0003】
その工程は、まずトンネル壁面である二次覆工用コンクリートの表面に固定金具を固着させた後、各固定金具にそれぞれトンネル内装板を固定させたり、あるいは固定金具を使用することなく、トンネル内装板を貼着用モルタルを介して直に二次覆工用コンクリートの表面に固定していた。
【0004】
【発明が解決しようとする課題】
従来、トンネル内装板の施工は、二次覆工用コンクリートの打設後に別途行われていたため、トンネルの全長が長い程その工期も長くなり、一年近くかかる場合もあり、施工期間が長いことが問題となっていた。
【0005】
また、各固定金具に、個々にトンネル内装板を固定したり、貼着用モルタルを介して個々にトンネル内装板を固定していたため、作業能率が良くないことが問題となっていた。
【0006】
また、トンネル内は、湧水や高い湿度、冬季の凍結防止剤、自動車の排気ガス等もあり、汚損し易く、金属の腐食が進行する環境であるため、固定金具が腐食したり、貼着用モルタルが劣化すると共に、自動車からの衝撃、清掃作業時の清掃具の圧力等によりトンネル内装板の表面が汚損するため、永年使用中、固定金具の取替え、トンネル内装板の洗浄、取替え等を何度も行う必要があり、この維持管理に大きな負担が掛かることが問題となっていた。
【0007】
また、固定金具の取替え、トンネル内装板の洗浄、取替え等の補修工事において、トンネル内の片側車線を止めて行う必要があり、このため交通渋滞となり、トンネル内装板の補修工事の際にも容易に施工可能な工法が強く要望されている。
【0008】
本発明は、この要望に対処すべく、型枠へのトンネル内装板の止着がし易く、二次覆工用コンクリート打設と同時施工ができるトンネル内装板の直打設工法およびその装置を提供することを目的とするものである。
【0009】
【課題を解決するための手段】
本発明は、トンネル内に打設した二次覆工用コンクリートの表面にトンネル内装板を取付ける工法および装置において、トンネル内に二次覆工用コンクリートを打設する型枠の外周面に、基板に内装板を多数固着させ、かつ基板の適所に止着孔を貫通させてなるトンネル内装板を、トンネル内装板の表面を型枠に当接させると共に、トンネル内装板の止着孔に型枠内側から、先端に傾倒自在の引寄体を着脱自在に装着させた止着金具の引寄体を、挿入後、引寄体を自重により垂直方向に傾倒させてトンネル内装板に係止させ、止着金具を型枠内側に引寄せてトンネル内装板を型枠に密着させた後、止着金具を型枠内側に固定することにより、トンネル内装板を型枠に止着させた後、トンネル内に型枠を介して二次覆工用コンクリートを打設し、二次覆工用コンクリートの養生硬化後、止着金具の先端から引寄体を分離し、型枠を脱型させることにより、引寄体を二次覆工用コンクリート内に埋設すると共に、二次覆工用コンクリートの表面にトンネル内装板を直に取付けることを特徴とするもの、または型枠内側からトンネル内装板の止着孔への止着金具の引寄体の挿入において、止着金具を挿入チューブに内挿させた後、挿入チューブと共に引寄体をトンネル内装板の止着孔に挿入させた後、挿入チューブのみをトンネル内装板の止着孔から抜出すことにより、引寄体を自重により垂直方向に傾倒させることを特徴とするもの、またはトンネル内装板の型枠外周面への当接において、型枠外周下方に配設させた突出板上にトンネル内装板を載置させた後、このトンネル内装板の上方に順次トンネル内装板を積上げ、各トンネル内装板を型枠に止着後、二次覆工用コンクリートを打設することを特徴とするもの、またはトンネル内装板の型枠外周面への当接において、型枠外周に略格子状に配設させた突出板の各区画内にトンネル内装板を載置させた後、各トンネル内装板を型枠に止着後、二次覆工用コンクリートを打設することを特徴とするもの、またはトンネル内装板の基板を、柔軟性素材により成形し、型枠外周面への密着性を向上させ、打設した二次覆工用コンクリートのトンネル内装板表面への浸出を防止することを特徴とするものである。
【0010】
【発明の実施の形態】
本発明に係るトンネル内装板の直打設装置は、図1〜図8に示すように、型枠16、トンネル内装板18および止着金具28からなるものであり、その構造を以下に詳述する。
【0011】
型枠16は、トンネル12内に二次覆工用コンクリート14を打設するためのものであり、正面略半円状で、移動機構(図示略)を装備している。
【0012】
トンネル内装板18は、基板20表面に内装板22を多数固着させ、かつ基板20の適所に止着孔24を貫通させてある。
【0013】
本例において、トンネル内装板18は、基板20がガラス繊維混入の柔軟性コンクリート板であり、内装板22がタイルであり、隣接する各内装板22間に目地26が形成され、この目地26上に止着孔24を貫通させてある。
【0014】
止着金具28は、先端に傾倒自在の引寄体30を着脱自在に装着させたものである。
【0015】
本例において、引寄体30は平板であり、止着金具28先端と軸着させることにより、自重により垂直方向に傾倒自在の構造とし、また引寄体30の着脱手段はネジ機構32によるものである。
【0016】
また、止着金具28の引寄体30を、トンネル内装板18の止着孔24へ挿入し、挿入後引寄体30を自重により垂直方向に傾倒させ易くするために、止着金具28を内挿し、止着金具24と共に止着孔24へ挿入する挿入チューブ34が設けられている。
【0017】
この挿入チューブ34を採用することにより、予め止着金具28を内挿した後、トンネル内装板18の止着孔24へ止着金具28と共に挿入チューブ34を挿入した後、挿入チューブ34のみを型枠16内側に抜出すことにより、容易に引寄体30を自重により垂直方向に傾倒させ、トンネル内装板18へ係止させることができる。
【0018】
また、型枠16へのトンネル内装板18の止着作業を効率的に行うため、型枠16の外周下方に突出板36が出没自在に配設されている。
【0019】
この突出板36は型枠16にトンネル内装板18を当接させる際、外側に突出させた後、この突出させた突出板36上に上下方向の位置の基準となる最下段のトンネル内装板18を載置させ、このトンネル内装板18上に順次トンネル内装板18を積上げて、型枠16へのトンネル内装板18の当接作業を行い、各トンネル内装板18の型枠16への止着作業完了後、型枠16内へ収納し、次工程である二次覆工用コンクリート打設作業に備える。
【0020】
このトンネル内装板18の止着作業完了後、型枠16内へ突出板36を収納するのは、型枠16外側に突出板36を突出させた状態で二次覆工用コンクリート14を打設すると、養生硬化後、型枠16脱型時に二次覆工用コンクリート表面に突出板36の痕跡が凹部として残存し、美観を損なうばかりか、強度低下の要因となるため、二次覆工用コンクリート14の打設前に型枠16内に収納し、打設した二次覆工用コンクリート表面を平滑にし、強度低下を防止するためである。
【0021】
また、各トンネル内装板18の止着孔24がそれぞれ所定位置に貫通され、かつ突出板36上に上下方向の位置の基準となる最下段のトンネル内装板18を載置させるため、止着孔24の上下方向の位置ズレは生ずることがないが、止着孔24の左右方向の位置ズレを調整するために型枠16内側に以下の調整機構38が装備されている。
【0022】
予め型枠16周面には、トンネル内装板18の止着孔24に対応する長孔40が穿孔され、この長孔40に対応する型枠16内部に、止着金具28の挿通孔42を貫通させた支持板44を、移動自在に配設させることにより調整機構38が構成されている。
【0023】
この調整機構38により、まず支持板44を型枠16の長孔40内を左右方向に移動させ、型枠16の外周面に当接させたトンネル内装板18の止着孔24の位置に対応させ、支持板44の挿通孔42、型枠16の長孔40およびトンネル内装板18の止着孔24を合致させた後、型枠16の内側から止着金具28をトンネル内装板18の止着孔24へ挿入させることが可能となり、止着金具28の各孔42,40,24への挿入が極めて容易になる。
【0024】
この際、型枠16の外周面に穿孔された長孔40は、トンネル内装板18の型枠16への止着時に、トンネル内装板18により完全に被覆されるため、打設された二次覆工用コンクリート14が型枠16内部に浸入することはない。
【0025】
なお、図中46は各トンネル内装板18の外周縁に装着されたシール部材、48は内装板22表面に貼付された保護シート、50は止着金具24の外周面に形成されたネジ部、52は止着金具24のネジ部50に対応する止着ナット、54は止着金具24を支持板44へ支持させるための座板、56はトンネル内壁面を示す。
【0026】
本装置を使用してトンネル12内の二次覆工用コンクリート14の表面にトンネル内装板18を直に取付ける工法を以下に詳述する。
【0027】
まず、型枠16をトンネル12の所定位置まで移動させる。
【0028】
この際、型枠16のトンネル坑口側(トンネル掘削側と反対側)は、既二次覆工用コンクリート打設部(図示略)と重合させる。
【0029】
次に、型枠16の外周下方の突出板36を外側に突出させ、予めトンネル12内のトンネル内壁面56の近部に運び込まれたトンネル内装板18を、突出させた突出板36上に、載置させ、型枠16の外周面にトンネル内装板18を当接させる。
【0030】
次に、基準となる最下段のトンネル内装板18上に、順次各トンネル内装板18を積上げる。
【0031】
この際、上下、左右に隣接する各トンネル内装板18間は、シール部材46により確実にシールされ、打設される二次覆工用コンクリート14のトンネル内装板18表面への浸出および型枠16内への浸入を防止することができる。
【0032】
次に、型枠16内側の支持板44を移動させ、支持板44の挿通孔42を、型枠16の外周面に当接させた各トンネル内装板18の止着孔24に合致させて位置させる。
【0033】
この支持板44の挿通孔42と、トンネル内装板18の止着孔24と、の位置調整作業は各トンネル内装板18に対して個別に行う。
【0034】
次に、型枠16の内側から挿入チューブ34に内挿させた止着金具28を、支持板44の挿通孔42、型枠16の長孔40を経てトンネル内装板18の止着孔24へ挿入させた後、挿入チューブ34のみを型枠16内側に抜出し、止着金具28の先端の引寄体30を自重により垂直方向に傾倒させ、トンネル内装板18へ係止させる。
【0035】
この際、止着金具28は挿入チューブ34に内挿されているため、挿通孔42、長孔40および止着孔24への、止着金具28の挿入が容易となると共に、挿入チューブ34のみを各孔44、40、24から抜出すことにより、止着金具28の先端の引寄体30を容易に自重により垂直方向に傾倒させることができる。
【0036】
次に、トンネル内装板18を、止着金具28を介して型枠16内側に引寄せることにより、型枠16の外周面にトンネル内装板18を密着させる。
【0037】
この際、トンネル内装板18の基板20が柔軟性コンクリート板であるため、型枠16外周面へ確実に密着し、打設した二次覆工用コンクリート14のトンネル内装板18表面への浸出をより効果的に防止することができる。
【0038】
次に、型枠16内側において、止着金具28を、座板54を介して支持板44に、止着金具28のネジ部50に止着ナット52を螺着させることにより、支持固定する。
【0039】
次に、各トンネル内装板18の型枠16への止着作業完了後、打設した二次覆工用コンクリート表面を平滑にし、強度低下を防止するため、突出板36を型枠16内へ収納する。
【0040】
次に、型枠16のトンネル妻側(トンネル掘削側)周縁を確実に被覆(妻止め)する。
【0041】
次に、トンネル内壁面56と型枠16との間に二次覆工用コンクリート14を打設させ、養生硬化させる。
【0042】
次に、止着金具28を、先端の引寄体30との着脱手段であるネジ機構32を解除することにより、引寄体30から分離する。
【0043】
この引寄体30を止着金具28の先端から分離するのは、引寄体30がトンネル内装板18と共に養生硬化した二次覆工用コンクリート14内に埋設状態となるため、このままの状態では型枠16脱型作業ができなくなり、この脱型作業を行うためである。
【0044】
また、引寄体30を分離させた止着金具28は、支持板44から取外し、次回使用に備えて新たな引寄体30を取付ける。
【0045】
次に、型枠16を脱型させる。
【0046】
この際、型枠16の外周面にトンネル内装板18が止着されているため、二次覆工用コンクリート14打設時に、トンネル内装板18の基板20側が二次覆工用コンクリート14内に埋設された状態となり、二次覆工用コンクリート14の養生硬化完了後、打設した二次覆工用コンクリート14の表面に、トンネル内装板18が固着される。
【0047】
また、型枠16の脱型時、型枠16の外周面に止着されたトンネル内装板18は、基板20が養生硬化した二次覆工用コンクリート14に固着され、この固着力が強大であるため、トンネル内装板18は型枠16から容易に剥離する。
【0048】
次に、二次覆工用コンクリート14の表面に固着されたトンネル内装板18の内装板22の表面側の保護シート48を除去すると共に、トンネル内装板18の表面を洗浄する。
【0049】
前記工程により、型枠16が設置された個所に、二次覆工用コンクリート14の打設と共に、トンネル内装板18の施工が完了する。
【0050】
このトンネル内装板18の施工を、トンネル妻側へ向けて順次型枠16を移動させて行い、トンネル12の全長にわたり行う。
【0051】
また、図9〜図11に本発明に係る装置の別の例が示してある。
【0052】
本例は、三角突条型の突出板36を型枠16の外周に略格子状に配設させたものであり、トンネル内装板18の型枠16の外周面への当接において、突出板36により形成された各区画58内にトンネル内装板18をそれぞれ載置させた後、各トンネル内装板18を型枠16に止着金具28を介して止着後、二次覆工用コンクリート14を打設するものである。
【0053】
この際、前例と同様、打設した二次覆工用コンクリート表面を平滑にし、強度低下を防止するため、トンネル内装板18の型枠16への止着作業完了後、突出板36を型枠16内へ収納させるために出没自在とすることが望ましいが、突出板36の型枠16からの突出長を短くし、型枠脱型時のトンネル内装板18および打設した二次覆工用コンクリート表面へのダメージを最小限に抑える配慮をすることにより、必ずしも突出板36は出没自在としなくてもよい。
【0054】
また、本例において、トンネル内装板18は突出板36により形成された各区画58内にそれぞれ1個ずつ載置させるため、型枠16の上下左右方向に対してトンネル内装板18の位置ズレがなく、正確にトンネル内装板18の直打設作業が行え、また前例のように型枠16に調整機構38を設ける必要がない。
【0055】
なお、両例において、トンネル内装板18を柔軟性を有しないコンクリート板とすることは自由であり、また内装板22はタイルに限定されることはなく、壁面パネル等の板材を使用することは自由である。
【0056】
また、トンネル内装板18の止着孔24への止着金具28の挿入は、挿入チューブ34へ内挿させて挿入するものであるが、挿入チューブ34を省略して止着金具28をそのままトンネル内装板18の止着孔24へ挿入することは自明のことである。
【0057】
また、型枠16外周上方からワイヤー等を使用してトンネル内装板18を吊持させることにより、突出板36を省略できることは自明のことである。
【0058】
また、型枠16外周へのトンネル内装板18の止着は、先端に傾倒自在の引寄体30を着脱自在に装着させた止着金具28によるものであるが、型枠16内側からボルトをトンネル内装板18へ貫通させ、作業者が型枠16とトンネル内壁面56との間でボルトにナットを止着させることにより、止着金具28に代えてボルトを使用することが可能となる。
【0059】
また、前例において、型枠16へのトンネル内装板18の当接作業は、型枠16の外周下方の出没自在に突出させた突出板36を利用するものであるが、突出板36の型枠16からの突出長を短くし、型枠脱型時のトンネル内装板18および打設した二次覆工用コンクリート14表面へのダメージを最小限に抑える配慮をすることにより、必ずしも突出板36は出没自在としなくてもよい。
【0060】
また、トンネル内装板18の型枠16への止着個所は主に型枠16の下方部分であるが、型枠16の他の個所へも止着させることは自由である。
【0061】
また、後例において、突出板36は三角突条型であるが、矩形型、等その他の形状の突条とすることは自由であり、また上下左右方向に直線状に配設させてあるが、所定間隔を隔てて点在させることは自明のことである。
【0062】
また、両例は略半円形のトンネル等のコンクリート打設におけるものであるが、円形のトンネル、例えば海中トンネル、下水道等にも利用できる。
【0063】
【発明の効果】
本発明に係るトンネル内装板の直打設工法およびその装置によれば、二次覆工用コンクリートを打設するための型枠の外周面に、トンネル内装板を、型枠内側からトンネル内装板の止着孔に、先端に傾倒自在の引寄体を備えた止着金具を挿入させ、引寄体を自重により垂直方向に傾倒させて係止させ、止着金具を型枠内側に引寄せることにより、密着させ、二次覆工用コンクリート打設と同時にトンネル内装板の施工をするため、型枠へのトンネル内装板の止着作業が極めて容易であり、また二次覆工と別にトンネル内装板の施工を行う必要がなく、トンネル内装板の施工期間を大幅に短縮できる。
【0064】
また、トンネル内装板を直に二次覆工用コンクリートの表面に取付けることにより、従来使用していた固定金具、貼着用モルタルを省くことができるため、固定金具の腐食、貼着用モルタルの劣化によるトンネル内装板の損傷が皆無となるばかりか、固定金具の取替え、トンネル内装板の取替え等の補修工事の回数が激減し、維持管理に掛かる負担を激減させることができる。
【0065】
また、トンネル内装板の止着孔への止着金具の引寄体の挿入において、止着金具を挿入チューブに内挿させることにより、トンネル内装板の止着孔への、止着金具の挿入が容易となると共に、挿入チューブのみを止着孔から抜出すことにより、止着金具の引寄体を容易に自重により垂直方向に傾倒させることができる。
【0066】
また、トンネル内装板の型枠外周面への当接時に、型枠外周下方に配設させた突出板上に載置させた後、このトンネル内装板の上方に順次トンネル内装板を積上げ、各トンネル内装板を型枠に止着後、二次覆工用コンクリートを打設することより、突出板上に上下方向の位置の基準となる最下段のトンネル内装板が載置されるため、トンネル内装板の止着孔の上下方向の位置ズレが生ずることがない。
【0067】
また、トンネル内装板の型枠外周面への当接において、型枠外周に略格子状に配設させた突出板の各区画内にトンネル内装板を載置させた後、各トンネル内装板を型枠に止着後、二次覆工用コンクリートを打設することにより、トンネル内装板が突出板により形成された各区画内にそれぞれ1個ずつ載置されるため、型枠の上下左右方向に対してトンネル内装板の位置ズレがなく、正確にトンネル内装板の直打設作業を行うことができる。
【0068】
また、トンネル内装板の基板を、柔軟性素材により成形することにより、型枠外周面への密着性を向上させ、打設した二次覆工用コンクリートのトンネル内装板表面への浸出を防止することができる。
【図面の簡単な説明】
【図1】本発明に係るトンネル内装板の直打設装置を示す要部拡大側面図。
【図2】同、正面図。
【図3】トンネル内装板の正面図。
【図4】同、側面図。
【図5】図4のA部拡大正面図。
【図6】止着金具および挿入チューブの分解正面図。
【図7】トンネル内装板の型枠への止着作業工程を示す正面図。
【図8】本発明のトンネル内装板の直打設工程を示す簡略正面図。
【図9】本発明に係るトンネル内装板の直打設装置の別の例を示す要部拡大正面図。
【図10】同、側面図。
【図11】図10のB部拡大図。
【符号の説明】
12 トンネル
14 二次覆工用コンクリート
16 型枠
18 トンネル内装板
20 基板
22 内装板
24 支持孔
28 止着金具
30 引寄体
34 挿入チューブ
36 突出板
56 トンネル内壁面
58 区画[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a tunnel interior board that can be constructed simultaneously with concrete placement for secondary lining, in order to improve the protection and aesthetics of the concrete surface for secondary lining placed in the tunnel. The present invention relates to a direct placement method and an apparatus therefor. In the present specification, “laying” means filling fluid concrete that is not cured and hardened between the mold and the inner wall surface of the tunnel or the concrete for primary lining.
[0002]
[Prior art]
Originally, it promotes line-of-sight guidance from the brightness difference from the tunnel wall (secondary lining concrete surface), improves driver visibility, supports stable driving of the automobile, As a measure to improve the protection and aesthetics of the tunnel wall surface by covering the exposure and unevenness of the tunnel wall surface, a tunnel interior board with white coating was usually applied (attached) to the lower part of the tunnel wall surface.
[0003]
The process is as follows. First, fixing brackets are fixed to the surface of the concrete for secondary lining, which is the tunnel wall surface, and then the tunnel interior plate is fixed to each fixing bracket or without using the fixing bracket. The plate was fixed directly to the surface of the concrete for secondary lining through the mortar to which the plate was attached.
[0004]
[Problems to be solved by the invention]
Traditionally, the construction of tunnel interior plates was done separately after placing concrete for secondary lining, so the longer the tunnel, the longer the construction period, which may take up to one year, and the construction period is long. Was a problem.
[0005]
Moreover, since the tunnel interior board was individually fixed to each fixing bracket, or the tunnel interior board was individually fixed through the attaching mortar, there was a problem that work efficiency was not good.
[0006]
In addition, there are spring water, high humidity, anti-freezing agent in winter, automobile exhaust gas, etc. in the tunnel, which is easily contaminated and the environment where metal corrosion progresses. As the mortar deteriorates and the surface of the tunnel interior plate is soiled by the impact from the automobile, the pressure of the cleaning tool during the cleaning work, etc. It was necessary to do this again and again, and it was a problem that a heavy burden was placed on this maintenance.
[0007]
In addition, it is necessary to stop the lane on one side of the tunnel for repair work such as replacement of fixing brackets, cleaning of tunnel interior plates, replacement, etc., resulting in traffic congestion and easy repair of tunnel interior plates. There is a strong demand for a construction method that can be used in the future.
[0008]
In order to cope with this demand, the present invention is directed to a tunnel interior board direct placing method and an apparatus thereof which can be easily attached to a formwork and can be installed simultaneously with concrete placement for secondary lining. It is intended to provide.
[0009]
[Means for Solving the Problems]
The present invention relates to a method and an apparatus for attaching a tunnel interior plate to a surface of a secondary lining concrete placed in a tunnel, and a substrate on the outer peripheral surface of a mold for placing the secondary lining concrete in the tunnel. A large number of interior plates are fixed to each other, and a tunnel interior plate is formed by passing through fastening holes at appropriate positions on the substrate. The surface of the tunnel interior plate is brought into contact with the formwork, and the formwork is attached to the fastening holes of the tunnel interior plate. From the inside, after inserting the attachment body of the fastening metal fitting that can be attached to the tip detachably at the tip, after the insertion body is tilted in the vertical direction by its own weight and locked to the tunnel interior plate, After the fastening bracket is drawn inside the formwork to bring the tunnel interior plate into close contact with the formwork, the fastening plate is fixed to the inside of the formwork to secure the tunnel interior plate to the formwork, and then the tunnel Place concrete for secondary lining through the formwork inside. After curing and curing the secondary lining concrete, the attracting body is separated from the tip of the fastening bracket, and the formwork is removed, so that the attracting body is embedded in the secondary lining concrete. In the case where the tunnel interior plate is directly attached to the surface of the concrete for the next lining, or in the insertion of the attachment body of the fastening bracket from the inside of the formwork to the fastening hole of the tunnel interior plate, the fastening bracket Is inserted into the insertion tube, and then the attracting body is inserted into the fixing hole of the tunnel interior plate together with the insertion tube, and then only the insertion tube is pulled out from the fixing hole of the tunnel interior plate. In which the tunnel interior plate is tilted in the vertical direction by its own weight, or the tunnel interior plate is placed on the protruding plate disposed below the outer periphery of the mold frame when the tunnel interior plate is in contact with the outer surface of the mold frame. After this tunnel interior plate The tunnel interior plates are stacked one after another, and each tunnel interior plate is fixed to the mold, and then concrete for secondary lining is cast, or the tunnel interior plate abuts against the outer periphery of the mold In this case, after placing the tunnel interior plate in each section of the projecting plate disposed in a substantially grid pattern on the outer periphery of the mold, after fixing the tunnel interior plate to the mold, the concrete for secondary lining is applied. A concrete tunnel interior board for secondary lining, which is characterized by being cast, or a tunnel interior board formed from a flexible material to improve adhesion to the outer periphery of the formwork. It is characterized by preventing leaching to the surface.
[0010]
DETAILED DESCRIPTION OF THE INVENTION
As shown in FIGS. 1 to 8, the direct placement device for a tunnel interior board according to the present invention comprises a
[0011]
The
[0012]
In the tunnel
[0013]
In this example, the
[0014]
The
[0015]
In this example, the attracting
[0016]
In order to make it easier to tilt the attracting
[0017]
By adopting this
[0018]
Further, in order to efficiently fix the tunnel
[0019]
The projecting
[0020]
After completion of the fixing operation of the tunnel
[0021]
Further, the fastening holes 24 of the respective tunnel
[0022]
A
[0023]
By this
[0024]
At this time, since the
[0025]
In the figure, 46 is a seal member attached to the outer peripheral edge of each tunnel
[0026]
A method of attaching the tunnel
[0027]
First, the
[0028]
At this time, the tunnel pit side (the side opposite to the tunnel excavation side) of the
[0029]
Next, the projecting
[0030]
Next, the tunnel
[0031]
At this time, the tunnel
[0032]
Next, the
[0033]
Position adjustment work of the
[0034]
Next, the fastening metal fitting 28 inserted into the
[0035]
At this time, since the fastening fitting 28 is inserted into the
[0036]
Next, the tunnel
[0037]
At this time, since the
[0038]
Next, on the inner side of the
[0039]
Next, after completion of the fixing operation of each tunnel
[0040]
Next, the periphery of the
[0041]
Next, the concrete 14 for secondary lining is placed between the tunnel
[0042]
Next, the fastening fitting 28 is separated from the attracting
[0043]
The reason why the attracting
[0044]
The
[0045]
Next, the
[0046]
At this time, since the tunnel
[0047]
Further, when the
[0048]
Next, the
[0049]
Through the above steps, the construction of the tunnel
[0050]
The tunnel
[0051]
9 to 11 show another example of the apparatus according to the present invention.
[0052]
In this example, a triangular protrusion
[0053]
At this time, in the same manner as in the previous example, in order to smooth the cast concrete surface for secondary lining and prevent the strength from being lowered, after the fixing operation of the tunnel
[0054]
Further, in this example, since the tunnel
[0055]
In both examples, the tunnel
[0056]
In addition, the insertion of the
[0057]
In addition, it is obvious that the protruding
[0058]
Further, the tunnel
[0059]
In the previous example, the abutment operation of the tunnel
[0060]
Moreover, although the fixing | fixed part of the tunnel
[0061]
In the following example, the protruding
[0062]
Both examples are for concrete casting such as a substantially semicircular tunnel, but can also be used for circular tunnels such as underwater tunnels and sewers.
[0063]
【The invention's effect】
According to the direct placement construction method and apparatus for a tunnel interior board according to the present invention, the tunnel interior board is placed on the outer peripheral surface of the formwork for placing secondary lining concrete from the inside of the formwork. Insert a fastening bracket with a tiltable attracting body at the tip into the fastening hole, tilt the attracting body in the vertical direction by its own weight and lock it, and pull the fastening bracket toward the inside of the formwork Since the tunnel interior plate is installed at the same time as the concrete placement for the secondary lining and the tunnel interior plate is installed, it is extremely easy to fix the tunnel interior plate to the formwork. There is no need to install interior panels, and the construction period for tunnel interior panels can be greatly reduced.
[0064]
In addition, by attaching the tunnel interior board directly to the surface of the concrete for secondary lining, it is possible to eliminate the fixing bracket and sticking mortar used in the past. Not only is there no damage to the tunnel interior plate, but the number of repair work such as replacement of the fixtures and replacement of the tunnel interior plate is drastically reduced, and the burden on maintenance can be drastically reduced.
[0065]
In addition, when inserting the anchor fitting member into the fixing hole of the tunnel interior plate, the fixing bracket is inserted into the insertion hole of the tunnel interior plate by inserting the fixing bracket into the insertion tube. In addition, by pulling out only the insertion tube from the fastening hole, the attracting body of the fastening bracket can be easily tilted in the vertical direction by its own weight.
[0066]
Further, when the tunnel interior plate is brought into contact with the outer peripheral surface of the formwork, after being placed on the protruding plate disposed below the outer periphery of the formwork, the tunnel interior plates are sequentially stacked above the tunnel interior plate. After the tunnel interior plate is fixed to the formwork, the concrete for the secondary lining is placed, so that the lowermost tunnel interior plate, which serves as a reference for the vertical position, is placed on the protruding plate. There is no displacement in the vertical direction of the fastening holes of the interior plate.
[0067]
In addition, when the tunnel interior plate is brought into contact with the outer peripheral surface of the formwork, after the tunnel interior plate is placed in each section of the projecting plate disposed in a substantially lattice pattern on the outer periphery of the formwork, After fixing to the formwork, by placing concrete for secondary lining, one tunnel interior board is placed in each section formed by the projecting board, so the top, bottom, left and right direction of the formwork On the other hand, there is no misalignment of the tunnel interior plate, and the tunnel interior plate can be directly placed directly.
[0068]
In addition, by forming the tunnel interior board substrate from a flexible material, the adhesion to the outer periphery of the formwork is improved, and leaching of the placed concrete for secondary lining to the tunnel interior board surface is prevented. be able to.
[Brief description of the drawings]
FIG. 1 is an enlarged side view of an essential part showing a direct placement apparatus for a tunnel interior board according to the present invention.
FIG. 2 is a front view of the same.
FIG. 3 is a front view of a tunnel interior board.
FIG. 4 is a side view of the same.
FIG. 5 is an enlarged front view of a part A in FIG. 4;
FIG. 6 is an exploded front view of a fastening fitting and an insertion tube.
FIG. 7 is a front view showing a process of fixing a tunnel interior plate to a formwork.
FIG. 8 is a simplified front view showing a direct placement process of a tunnel interior board according to the present invention.
FIG. 9 is an enlarged front view of an essential part showing another example of a direct placement apparatus for a tunnel interior board according to the present invention.
FIG. 10 is a side view of the same.
11 is an enlarged view of portion B in FIG.
[Explanation of symbols]
12
Claims (10)
トンネル(12)内に二次覆工用コンクリート(14)を打設する型枠(16)の外周面に、基板(20)に内装板(22)を多数固着させ、かつ基板(20)の適所に止着孔(24)を貫通させてなるトンネル内装板(18)を、トンネル内装板(18)の表面を型枠(16)に当接させると共に、トンネル内装板(18)の止着孔(24)に型枠(16)内側から、先端に傾倒自在の引寄体(30)を着脱自在に装着させた止着金具(28)の引寄体(30)を、挿入後、引寄体(30)を自重により垂直方向に傾倒させてトンネル内装板(18)に係止させ、止着金具(28)を型枠(16)内側に引寄せてトンネル内装板(18)を型枠(16)に密着させた後、止着金具(28)を型枠(16)内側に固定することにより、トンネル内装板(18)を型枠(16)に止着させた後、
トンネル(12)内に型枠(16)を介して二次覆工用コンクリート(14)を打設し、二次覆工用コンクリート(14)の養生硬化後、
止着金具(28)の先端から引寄体(30)を分離し、型枠(16)を脱型させることにより、引寄体(30)を二次覆工用コンクリート(14)内に埋設すると共に、二次覆工用コンクリート(14)の表面にトンネル内装板(18)を直に取付けることを特徴とするトンネル内装板の直打設工法。In the method of attaching the tunnel interior plate (18) to the surface of the concrete (14) for secondary lining placed in the tunnel (12),
A large number of interior plates (22) are fixed to the substrate (20) on the outer peripheral surface of the formwork (16) for placing the concrete (14) for secondary lining in the tunnel (12), and the substrate (20) The tunnel interior plate (18) with the fastening hole (24) penetrated in place, the surface of the tunnel interior plate (18) abuts the formwork (16), and the tunnel interior plate (18) is secured. After inserting the attracting body (30) of the fastening bracket (28) with the tiltable attracting body (30) detachably attached to the tip from the inside of the mold (16) into the hole (24), pull it Tilt the body (30) in the vertical direction by its own weight and lock it to the tunnel interior plate (18), and pull the fastening bracket (28) to the inside of the formwork (16) to mold the tunnel interior plate (18). After closely attaching to the frame (16), after fixing the tunnel interior plate (18) to the formwork (16) by fixing the fastening bracket (28) to the inside of the formwork (16),
After placing the concrete for secondary lining (14) through the formwork (16) in the tunnel (12), curing the secondary lining concrete (14),
The attracting body (30) is separated from the tip of the fastening bracket (28) and the formwork (16) is removed from the mold so that the attracting body (30) is embedded in the concrete for secondary lining (14). In addition, the tunnel interior board direct installation method, characterized in that the tunnel interior board (18) is directly attached to the surface of the secondary lining concrete (14).
基板(20)に内装板(22)を多数固着させ、かつ基板(20)の適所に止着孔(24)を貫通させてなるトンネル内装板(18)と、
先端に傾倒自在の引寄体(30)を着脱自在に装着させた止着金具(28)と、
トンネル(12)内に二次覆工用コンクリート(14)を打設する型枠(16)と、からなり、
トンネル(12)内に二次覆工用コンクリート(14)を打設する型枠(16)の外周面に、トンネル内装板(18)を、トンネル内装板(18)の表面を型枠(16)に当接させると共に、トンネル内装板(18)の止着孔(24)に型枠(16)内側から止着金具(28)の引寄体(30)を挿入後、引寄体(30)を自重により垂直方向に傾倒させてトンネル内装板(18)に係止させ、止着金具(28)を型枠(16)内側に引寄せてトンネル内装板(18)を型枠(16)に密着させた後、止着金具(28)を型枠(16)内側に固定することにより、トンネル内装板(18)を型枠(16)に止着させた後、
トンネル(12)内に型枠(16)を介して二次覆工用コンクリート(14)を打設し、二次覆工用コンクリート(14)の養生硬化後、
止着金具(28)の先端から引寄体(30)を分離し、型枠(16)を脱型させることにより、引寄体(30)を二次覆工用コンクリート(14)内に埋設すると共に、二次覆工用コンクリート(14)の表面にトンネル内装板(18)を直に取付けることを特徴とするトンネル内装板の直打設装置。In the device for attaching the tunnel interior plate (18) to the surface of the concrete (14) for secondary lining placed in the tunnel (12),
A tunnel interior plate (18) in which a large number of interior plates (22) are fixed to the substrate (20), and a fastening hole (24) is passed through an appropriate position of the substrate (20);
A fastening bracket (28) with a freely tiltable attracting body (30) attached to the tip;
A formwork (16) for placing secondary lining concrete (14) in the tunnel (12),
The tunnel interior plate (18) is placed on the outer peripheral surface of the formwork (16) for placing the secondary lining concrete (14) in the tunnel (12), and the surface of the tunnel interior plate (18) is placed on the formwork (16 ), And after inserting the attracting body (30) of the fastening bracket (28) from the inside of the mold (16) into the fastening hole (24) of the tunnel interior plate (18), the attracting body (30 ) Is tilted in the vertical direction by its own weight and locked to the tunnel interior plate (18), and the fastening bracket (28) is pulled inside the formwork (16) to bring the tunnel interior plate (18) into the formwork (16). After fixing the tunnel interior plate (18) to the formwork (16) by fixing the fastening bracket (28) to the inside of the formwork (16),
After placing the concrete for secondary lining (14) in the tunnel (12) through the formwork (16), curing the secondary lining concrete (14),
The attracting body (30) is separated from the tip of the fastening bracket (28) and the formwork (16) is removed from the mold so that the attracting body (30) is embedded in the concrete for secondary lining (14). And a tunnel interior board direct placement device, wherein the tunnel interior board (18) is directly attached to the surface of the secondary lining concrete (14).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP21039499A JP4099293B2 (en) | 1999-07-26 | 1999-07-26 | Tunnel interior board direct installation method and equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP21039499A JP4099293B2 (en) | 1999-07-26 | 1999-07-26 | Tunnel interior board direct installation method and equipment |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2001032689A JP2001032689A (en) | 2001-02-06 |
JP4099293B2 true JP4099293B2 (en) | 2008-06-11 |
Family
ID=16588610
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP21039499A Expired - Fee Related JP4099293B2 (en) | 1999-07-26 | 1999-07-26 | Tunnel interior board direct installation method and equipment |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4099293B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4312643B2 (en) * | 2004-03-31 | 2009-08-12 | 財団法人鉄道総合技術研究所 | Reinforcement method of block lining tunnel and its structure |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3556737B2 (en) * | 1995-07-03 | 2004-08-25 | 株式会社仲田建設 | Tiled panel mounting structure |
JP3278371B2 (en) * | 1997-01-27 | 2002-04-30 | 岐阜工業株式会社 | Direct casting method of tunnel interior plate and its equipment |
JPH11131988A (en) * | 1997-10-30 | 1999-05-18 | Kajima Corp | Inner surface resin covering material for cast-in-place shield tunnel, construction method for inner surface resin-covered cast-in-place shield tunnel, and inner surface resin-covered cast-in-place shield tunnel |
-
1999
- 1999-07-26 JP JP21039499A patent/JP4099293B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JP2001032689A (en) | 2001-02-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4448066B2 (en) | Flexible waterproof joint and its construction method | |
JP4099293B2 (en) | Tunnel interior board direct installation method and equipment | |
JP3728728B2 (en) | Column and steel pipe pile positioning device | |
JP4175658B2 (en) | Construction method of composite panel on concrete outer wall of reinforced concrete building | |
JPH0834017A (en) | Repair lining technique for wall surface of concrete skeleton/and repair lining structure | |
JP4283419B2 (en) | Method and apparatus for fixing concrete for tunnel lining | |
JP2000096989A (en) | Air bleeder device in secondary lining of tunnel | |
JP3278371B2 (en) | Direct casting method of tunnel interior plate and its equipment | |
JP4201229B2 (en) | Construction method of underground concrete wall using buried formwork | |
JP2000110347A (en) | Concrete placing method by form equipped with box-out form and its device | |
JPS5830946Y2 (en) | Anchor structure for replacement sash | |
JP4036731B2 (en) | Tunnel fireproof structure and construction method thereof | |
JP3047096B2 (en) | Water heater mounting structure | |
CN115506603B (en) | Construction method of special-shaped steel skeleton high-performance concrete outer wall integrated heat-insulation board system | |
CN217299661U (en) | Prefabricated hood | |
KR100464594B1 (en) | The method of constructing the prefabricated step on reinforced concrete building | |
JP2016145483A (en) | Repairing method of wall surface for setting up watchman passage in tunnel | |
JP3610184B2 (en) | Conveyance structure with panels of tunnel-like structure | |
JP3073086B2 (en) | Gas cock mounting method and device | |
JP3110925B2 (en) | Wall driving plumbing method | |
JP2007092291A (en) | Fireproof internal trimming structure of tunnel and its construction method | |
JPH0853920A (en) | Repairing furring strips of existing wall and repairing structure of existing wall | |
JP3369436B2 (en) | Piping construction method | |
JPH0124305Y2 (en) | ||
JPH04176923A (en) | Mounting method for faucet |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20040217 |
|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20060725 |
|
A711 | Notification of change in applicant |
Free format text: JAPANESE INTERMEDIATE CODE: A711 Effective date: 20061005 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A821 Effective date: 20061005 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20080215 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20080226 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20080317 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110321 Year of fee payment: 3 |
|
LAPS | Cancellation because of no payment of annual fees |