JP2016145483A - Repairing method of wall surface for setting up watchman passage in tunnel - Google Patents

Repairing method of wall surface for setting up watchman passage in tunnel Download PDF

Info

Publication number
JP2016145483A
JP2016145483A JP2015022796A JP2015022796A JP2016145483A JP 2016145483 A JP2016145483 A JP 2016145483A JP 2015022796 A JP2015022796 A JP 2015022796A JP 2015022796 A JP2015022796 A JP 2015022796A JP 2016145483 A JP2016145483 A JP 2016145483A
Authority
JP
Japan
Prior art keywords
wall surface
tile
locking
tile panel
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2015022796A
Other languages
Japanese (ja)
Other versions
JP5761701B1 (en
Inventor
田島 洋
Hiroshi Tajima
洋 田島
勝代 小貫
Katsuyo Konuki
勝代 小貫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hiro Corp KK
Original Assignee
Hiro Corp KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hiro Corp KK filed Critical Hiro Corp KK
Priority to JP2015022796A priority Critical patent/JP5761701B1/en
Application granted granted Critical
Publication of JP5761701B1 publication Critical patent/JP5761701B1/en
Publication of JP2016145483A publication Critical patent/JP2016145483A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

PROBLEM TO BE SOLVED: To enable repairing in a short period, such as while waiting for hardening after a formwork is arranged in the front surface of a wall surface and mortar is filled therein, when the setup wall surface of a watchman passage in the tunnel is damaged.SOLUTION: A damaged part of a wall surface w is peeled and removed, and two or more tile panels 1 are disposed at intervals of about 3 mm while controlling unevenness with an anchor bolt b1 fixed in the wall surface w in the front side. A swelling prevention rod 2 is installed directly in the front surface of the tile panel 1 or installed in the front surface after bonding and disposing a leakage prevention plate 7 in the connection part of the adjacent tile panel 1. The swelling prevention rod 2 is inserted and locked in a locking hole 51h of lower part holding means 5 where an unevenness adjusting part 22 of the lower part is temporarily fixed in the lower wall surface w. The upper part of the swelling prevention rod 2 is held with clamping means 4. Then, the mortar with high mobility and no contraction is injected and filled between the wall surface w and the tile panel 1. After hardening, the swelling prevention rod 2, the leakage prevention plate 7, the clamping means 4 and the lower part holding means 5 are removed, and the repair work is completed.SELECTED DRAWING: Figure 3

Description

本発明は、トンネル内の側部に位置する監視員通路を路面から立ち上げる壁面が経年劣化その他の理由により損傷を生じた場合又はそのおそれが生じた場合に、これを補修する、トンネル内の監視員通路を立ち上げる壁面の補修方法に関するものである。   The present invention repairs a wall in the tunnel, which is located on the side of the tunnel when the wall rising from the road surface is damaged due to aging or other reasons, or when there is a risk of such damage. The present invention relates to a method for repairing a wall surface for setting up a supervisor passage.

監視員通路を路面から立ち上げる壁面を含む、トンネル内の全壁面は、トンネル内を通行する種々の自動車の排気ガス等による劣悪な環境の中にあり、劣化が速く進む傾向がある。壁面を構成する各部の劣化が進むと、該壁面を構成するタイルの剥離等が生じるおそれがあり、その結果、路面上にタイル又はその破片等が落下するに至ると、これらにより、重大な交通事故を引き起こすおそれある。それ故、このような事故を未然に防止するため、速やかに劣化した壁面を補修する必要がある。   All wall surfaces in the tunnel, including the wall surface that raises the surveillance passage from the road surface, are in a poor environment due to exhaust gases of various automobiles passing through the tunnel, and tend to deteriorate rapidly. As the deterioration of each part constituting the wall surface, the tiles constituting the wall surface may be peeled off. As a result, if the tile or its fragments fall on the road surface, these may cause serious traffic. May cause an accident. Therefore, in order to prevent such an accident, it is necessary to repair the deteriorated wall surface promptly.

従来、このようなトンネル内の壁面、特に監視員通路を立ち上げる路面に面したタイル壁面の補修は、補修対象壁面のうちの劣化した部位を、衝撃を加える等によって剥離除去した上で、該壁面の前面に一定の間隔を空けて型枠を構築し、その間にモルタルを打設して該壁面の前面に新たなモルタル下地層を形成し、更に該モルタル下地層の前面に個別のタイル、若しくは基板に複数のタイルを貼り付けてなるタイルパネルを取り付けることで行われてきた。   Conventionally, repairing a wall surface in such a tunnel, particularly a tile wall surface facing a road surface where a supervisor passage is set up, removes and removes a deteriorated portion of the wall surface to be repaired by applying an impact, etc. Forming a formwork with a certain interval on the front surface of the wall surface, placing mortar between them to form a new mortar ground layer on the front surface of the wall surface, and further, individual tiles on the front surface of the mortar ground layer, Or it has been performed by attaching a tile panel formed by attaching a plurality of tiles to a substrate.

上記の型枠は、補修対象壁面にアンカーボルトを固設し、更に該補修対象壁面の最下部に接する縁石上又は路面上に何らかの支持部材を固定した上で、それらのアンカーボルト及び支持部材を利用して仮固定するようにしていたものである。なお、該支持部材の縁石上又は路面上への固定は、該縁石等にアンカーボルト等を打ち込むことが認められていないため、これで固定することはできない。それ故、該支持部材の縁石等への固定は、接着剤等を用いて行うが、該支持部材を確実に縁石等に固定するためには接着力の高い接着剤を用いる必要がある。上記の型枠を除去する際には、当然、該支持部材を取り外す必要があるが、その際に、縁石等に接着剤が残留してしまう問題がある。   In the above-mentioned formwork, anchor bolts are fixed to a wall surface to be repaired, and further, a support member is fixed on a curb or a road surface in contact with the lowermost part of the wall surface to be repaired, and then the anchor bolt and the support member are attached. It was intended to be temporarily fixed using. The support member cannot be fixed on the curb or road surface because it is not permitted to drive anchor bolts or the like into the curb or the like. Therefore, the support member is fixed to the curbstone or the like using an adhesive or the like, but it is necessary to use an adhesive having a high adhesive strength in order to securely fix the support member to the curbstone or the like. When removing the above-mentioned formwork, of course, it is necessary to remove the support member, but at that time, there is a problem that the adhesive remains on the curbstone or the like.

トンネル内の監視員通路を路面から立ち上げる壁面の補修方法については、以上の方法以外に知られているものはない。この補修方法に参考となると思われる従来技術の文献としては、トンネル覆工構築法を提案する特許文献1がある。   There is no other known method for repairing the wall surface that raises the observer passage in the tunnel from the road surface. Patent Document 1 that proposes a tunnel lining construction method is a prior art document that is considered to be a reference for this repair method.

このトンネル覆工構築法は、トンネルの地山面に対向させて、周方向に複数に分割した型枠兼用のプレキャストコンクリート版であって、その地山面への対向面に底部が堰板部となって閉じているコンクリート充填部を開口したプレキャストコンクリート版を建込み、該プレキャストコンクリート版を、支持アームを介して該地山面に対向する所定位置に固設し、次いで、該地山面と該プレキャストコンクリート版との間に流動性の良い急硬化コンクリートを注入充填する、という方法である。   This tunnel lining construction method is a precast concrete slab that is also used as a formwork and is divided into a plurality of pieces in the circumferential direction so as to face the ground surface of the tunnel, and the bottom is the weir plate part on the surface facing the ground surface A precast concrete plate having an open concrete filling portion that is closed, and the precast concrete plate is fixed at a predetermined position facing the natural ground surface via a support arm, and then the natural ground surface And rapidly filling concrete with good fluidity between the precast concrete plate and the precast concrete plate.

このトンネル覆工構築法におけるプレキャストコンクリート版を型枠兼用とする考え方は、前記の監視員通路を路面から立ち上げる壁面の補修方法にも応用できる。すなわち、該型枠兼用として用いるプレキャストコンクリート版の技術思想を、従来技術の補修方法におけるタイルパネルに適用し、該タイルパネルを型枠兼用として用いる。このようにすれば、補修対象壁面の前面に所定間隔で型枠兼用であるタイルパネルを配置し、かつ、支持アームを介してこれをその状態に固定し、次いで、該タイルパネルと補修対象壁面との間に流動性の良い急硬化モルタルを注入することにより、その後の型枠の除去やタイルの取り付け工程を必要としないで、スピーディに壁面の補修を完了させることができるようになる。   The idea that the precast concrete slab is also used as a formwork in this tunnel lining construction method can be applied to the wall surface repairing method for raising the above-mentioned supervisor passage from the road surface. That is, the technical idea of the precast concrete plate used as the mold is applied to the tile panel in the repair method of the prior art, and the tile panel is used as the mold. If it does in this way, the tile panel which is also used as a formwork at a predetermined interval is arranged on the front surface of the wall surface to be repaired, and this is fixed to the state via the support arm, and then the tile panel and the wall surface to be repaired By injecting rapid-curing mortar with good fluidity between the two, the wall surface can be repaired quickly without the need for subsequent removal of the formwork or tile mounting.

しかし、特許文献1において、支持アームに関しては何の説明もなく、その構成は全く不明である。従って、従来技術の補修方法における支持部材の固定に関する問題点と同様の問題があり、この点の問題は全く解決されない。すなわち、タイルパネルの取り付けに関しては全くその説明がないのと同様であり、特許文献1からは、その取付方法として適切な手段を見出しがたい。   However, in Patent Document 1, there is no explanation about the support arm, and its configuration is completely unknown. Therefore, there is a problem similar to the problem related to fixing of the support member in the repair method of the prior art, and this problem cannot be solved at all. That is, it is the same as that there is no description about the attachment of the tile panel, and it is difficult to find an appropriate means as the attachment method from Patent Document 1.

特開平05−98893号公報JP 05-98893 A

本発明は、トンネル内の監視員通路を路面から立ち上げるタイル壁面が経年劣化その他の理由により損傷を生じた場合又はそのおそれが生じた場合に、これを補修するトンネル内の監視員通路を立ち上げる壁面の補修方法において、これを、該補修対象壁面の損傷を生じた部位又はそのおそれの生じた部位をそのままで又は剥離除去した上で、補修対象壁面の前面に適切な間隔で型枠を兼ねたタイルパネルを配置し、該タイルパネルと該補修対象壁面との間に流動性のモルタルを注入充填することで、スピーディにその補修作業を完了させること、タイルパネルを補修対象壁面側に固定することとすることにより、路面側に全く悪影響を与えないようにすること、及び補修対象壁面に凹凸があっても不陸を調整して適切にタイルパネルを取り付けることを解決の課題とするものである。   In the present invention, when the tile wall rising from the road surface in the tunnel is damaged due to aging or other reasons, or when there is a risk of it, the observer path in the tunnel is repaired. In the method of repairing the wall surface to be raised, this is done by leaving the part of the wall to be repaired damaged or the part that is likely to be damaged as it is or after removing and removing the formwork at an appropriate interval on the front surface of the wall to be repaired. A tile panel is also placed, and fluid mortar is injected and filled between the tile panel and the wall surface to be repaired, so that the repair work can be completed quickly, and the tile panel is fixed to the wall surface to be repaired. To prevent any adverse effects on the road surface side, and to adjust the unevenness even if there is unevenness on the wall surface to be repaired, and take tile panels appropriately. It is an object of solving the kick.

本発明の1は、トンネル内の監視員通路を立ち上げる路面に面するタイル貼り壁面の損傷を生じた部位又はそのおそれの生じた部位をそのままで又は剥離除去した上で、該壁面の前面側に所定間隔をあけて複数枚の型枠兼用のタイルパネルを配置し、次いで、該壁面と該各タイルパネルとの間に高流動性かつ無収縮性のモルタルを注入充填して補修する、トンネル内の監視員通路立ち上げ壁面の補修方法であって、前記各タイルパネルを、前記壁面に取り付けたアンカーボルトで不陸を調整しつつ該壁面から所定の間隔を空けて取り付け、更に前記各タイルパネルの前面側に、前記モルタルの注入充填時にその注入圧力で該タイルパネルが外方に膨出するのを防止すべく、これを抑える縦向きの複数の膨出防止棒を設置し、かつ該膨出防止棒の上部は監視員通路の手摺りの支柱に配した上部保持手段で外方に移動するのを防止すべく保持し、該膨出防止棒の下部は該各タイルパネルの下方で前記壁面に仮固定した下部保持手段で外方に移動するのを防止すべく保持することとしたトンネル内の監視員通路を立ち上げる壁面の補修方法である。   1 of the present invention is the same as the front side of the wall surface of the tiled wall surface facing the road surface where the observer path in the tunnel is raised or the portion where the fear is generated is removed as it is or after being removed. A plurality of tile panels that are also used as molds are arranged at predetermined intervals in the tunnel, and then repaired by injecting and filling high-fluidity and non-shrinkable mortar between the wall surfaces and the tile panels. A method for repairing a wall surface of a start-up of an observer's passage, wherein each tile panel is attached at a predetermined interval from the wall surface while adjusting unevenness with an anchor bolt attached to the wall surface, and each tile panel is further attached. On the front side of the panel, in order to prevent the tile panel from bulging outward due to the pouring pressure at the time of pouring and filling the mortar, a plurality of vertical anti-bulging bars for suppressing this are installed, and Bulge prevention stick The upper part is held to prevent it from moving outward by the upper holding means arranged on the post of the handrail in the observer passage, and the lower part of the bulge prevention bar is temporarily fixed to the wall surface below each tile panel. This is a method of repairing the wall surface for raising the observer passage in the tunnel that is held to prevent the lower holding means from moving outward.

本発明の2は、本発明の1のトンネル内の監視員通路を立ち上げる壁面の補修方法において、前記上部保持手段を、前記監視員通路の路面側に配してある手摺りの支柱に路面と反対側から当接させて路面と平行に配した係止補助棒と、一方の係止端を該係止補助棒側に、他方の係止端を前記膨出防止棒の上部側に、それぞれ係止して、該両係止端で該膨出防止棒と該係止補助棒側とを挟持保持するように配するクランプ手段とで構成し、前記下部保持手段を、前記タイルパネルの下端直下から前方に延びる係止板部であって、複数の係止穴が該タイルパネルの面方向と平行な方向に連設開口してあり、該係止穴が、前記膨出防止棒の下部の、下方に向かって該タイルパネル側に向かって斜めにカットした形状の不陸調整部を挿入可能であるように構成したものである係止板部と、該係止板部の内端から垂下する、前記壁面へ取り付けるための取付板部とで構成したものである。   According to a second aspect of the present invention, in the method for repairing a wall surface of the tunnel according to the first aspect of the present invention, the upper holding means is attached to a handrail column disposed on the road surface side of the supervisor passage. A locking auxiliary rod that is in contact with the opposite side of the road and arranged parallel to the road surface, one locking end on the locking auxiliary rod side, and the other locking end on the upper side of the bulging prevention rod, Clamping means arranged so as to be respectively held so as to sandwich and hold the bulging prevention bar and the side of the auxiliary locking bar at both locking ends, and the lower holding means is formed on the tile panel. A locking plate portion extending forward from directly below the lower end, wherein a plurality of locking holes are continuously opened in a direction parallel to the surface direction of the tile panel, and the locking holes are formed on the bulge preventing rod. It is possible to insert the uneven adjustment part of the lower part, which is cut obliquely toward the tile panel toward the bottom. A locking plate portion is obtained by configuration, depending from the inner end of the locking plate portion, which is constituted by a mounting plate portion for mounting to the wall.

本発明の3は、本発明の1又は2のトンネル内の監視員通路を立ち上げる壁面の補修方法において、隣接する両側のタイルパネルの背面に当接する連結板部であって、その両側の部位にそれぞれ連結穴を開口した連結板部と、該連結板部の下端から後方に延長する延長板部と、該延長板部の後端から垂下する絡み片とで連結補強部材を構成し、前記隣接する両側のタイルパネルの背面に該連結補強部材の連結板部の両側部をそれぞれ当接させ、かつ前記各連結穴を通じて該各タイルパネルに形成してある連結穴に挿入したボルト・ナットで両者を連結すると共に、その後に、該タイルパネルと壁面との間に注入充填されるモルタルに前記絡み片を絡み埋設させるように構成したものである。   A third aspect of the present invention is a connecting plate portion that contacts the back surfaces of adjacent tile panels in the wall surface repairing method for raising the observer passage in the tunnel according to the first or second aspect of the present invention. A connecting reinforcing member comprising a connecting plate part having a connecting hole opened therein, an extension plate part extending backward from the lower end of the connecting plate part, and an entanglement piece hanging from the rear end of the extension plate part, Bolts and nuts inserted into connecting holes formed in the tile panels through the connecting holes, with both side portions of the connecting plate portion of the connecting reinforcing member being in contact with the back surfaces of adjacent tile panels on both sides While connecting both, it is comprised so that the said entanglement piece may be entangled and embedded in the mortar poured and filled between this tile panel and a wall surface after that.

本発明の4は、本発明の1、2又は3のトンネル内の監視員通路を立ち上げる壁面の補修方法において、隣接する両側のタイルパネルの間に、前記壁面と該タイルパネルとの間へのモルタルの注入に先立って充填剤を充填し、かつ該隣接するタイルパネルの前面側に、該隣接するタイルパネルの間から前記壁面とタイルパネルとの間に注入されるモルタルが漏出することとなるのを防止するために、漏出防止板を配することとしたものである。   4 of the present invention is the method of repairing a wall surface for setting up a supervisor passage in the tunnel of 1, 2 or 3 according to the present invention, between the adjacent tile panels between the wall surface and the tile panel. Prior to the injection of the mortar, and the mortar injected between the wall surface and the tile panel leaks between the adjacent tile panels on the front side of the adjacent tile panel. In order to prevent this from happening, a leakage prevention plate is provided.

本発明の5は、本発明の4のトンネル内の監視員通路を立ち上げる壁面の補修方法において、前記膨出防止棒を、前記隣接する二つのタイルパネルの連結部を含む前面側に配する前記漏出防止板の前面側に当接させ、該膨出防止棒を該漏出防止板を介して該タイルパネルの膨出防止のために作用させるようにすることで、該膨出防止棒に、該漏出防止板のタイルパネルへの圧接とタイルパネルの膨出防止作用とを兼用させることとしたものである。   According to a fifth aspect of the present invention, in the wall surface repairing method for raising the observer passage in the tunnel according to the fourth aspect of the present invention, the bulging prevention rod is arranged on the front side including the connecting portion of the two adjacent tile panels. By contacting the front surface side of the leakage prevention plate and causing the bulging prevention rod to act to prevent the tile panel from bulging through the leakage prevention plate, The pressure-contact of the leakage prevention plate to the tile panel is combined with the bulge prevention action of the tile panel.

本発明の1のトンネル内の監視員通路を立ち上げる壁面の補修方法によれば、該壁面に損傷を生じている場合に、その損傷部位を除去した上で又は除去せずに、その前面に所定間隔で所要のタイルパネルを設置し、これを型枠兼用として該タイルパネルと該壁面との間に高流動性かつ無収縮のモルタルを注入充填することにより、型枠の除去及びその後のタイルの取り付け作業を必要とせずに、スピーディに該壁面の補修を行うことができる。   According to the repair method of a wall surface that raises the observer passage in the tunnel of 1 of the present invention, when the wall surface is damaged, with or without removing the damaged portion, A required tile panel is installed at a predetermined interval, and this is also used as a mold, and a highly fluid and non-shrinkable mortar is injected and filled between the tile panel and the wall surface, thereby removing the mold and subsequent tiles. The wall surface can be repaired speedily without the need for mounting work.

また、本発明の1のトンネル内の監視員通路を立ち上げる壁面の補修方法によれば、型枠兼用のタイルパネルは、前記補修対象壁面に取り付けたアンカーボルトで不陸を調整しつつ該壁面の前面に所定の間隔で設置するものであるが、該タイルパネルは、その外面側に、縦向きの複数の膨出防止棒を配置し、該膨出防止棒の上部は監視員通路の手摺りに取り付けた上部保持手段で固定し、下部は該各タイルパネルの下方に位置させて前記壁面に仮固定した下部保持手段で固定するものであるため、該アンカーボルトと該壁面との間にモルタルを注入充填する際に、該タイルパネルがその背後側からのモルタルの注入圧力を受けても該膨出防止棒によってその膨出が防止され、該タイルパネルは適切な不陸状態を保持することができる。   Moreover, according to the repair method of the wall surface which raises the observer channel | path in the tunnel of 1 of this invention, a tile panel used as a formwork is adjusted to the wall surface while adjusting the unevenness with the anchor bolt attached to the wall surface to be repaired. The tile panel has a plurality of vertically extending bulge prevention rods arranged on the outer surface side of the tile panel, and the upper portion of the bulge prevention rods is a hand of a supervisor passage. The upper holding means attached to the slide is fixed, and the lower part is positioned below the tile panels and fixed by the lower holding means temporarily fixed to the wall surface. When the mortar is injected and filled, even if the tile panel is subjected to mortar injection pressure from the back side of the tile panel, the expansion prevention bar prevents the expansion of the tile panel, and the tile panel maintains an appropriate non-landing state. be able to.

また、前記のように、前記タイルパネルは、上部を監視員通路の手摺りに取り付けた上部保持手段で、下部を該タイルパネルの下方に位置させて前記壁面に仮固定した下部保持手段で、それぞれ仮保持した前記膨出防止棒で膨出が防止されるものであるため、モルタル注入の際の注入圧で該タイルパネルが膨出することを、路面又は縁石に傷を付けたり、汚したりすることなく、確実に防止することができるものである。   Further, as described above, the tile panel is an upper holding means attached to the handrail of the supervisor passage, and a lower holding means temporarily fixed to the wall surface with the lower part positioned below the tile panel, Since the bulge prevention rods that are temporarily held are prevented from bulging, the tile panel bulges due to the injection pressure at the time of mortar injection. This can be surely prevented.

本発明の2のトンネル内の監視員通路を立ち上げる壁面の補修方法によれば、前記膨出防止棒の下部を、前記タイルパネルの前面に配した状態で、該タイルパネル側に向かってかつ下方に向かって斜めにカットした状態の不陸調整部に構成し、かつ前記下部保持手段を、前記膨出防止棒の下部の不陸調整部を保持する係止板部であって、該膨出防止棒の下部の不陸調整部を挿入するための複数の係止穴が該タイルパネルの面方向と平行な方向に連設開口してある係止板部と、該係止板部の内端(後端)から垂下する、前記壁面へ取り付けるための取付板部とで構成したものであるため、取付対象である壁面にその横方向に凹凸があって該下部保持手段がその凹凸に沿った形状に変形しつつ取り付けられることとなったとしても、前記膨出防止棒の前記係止板部の係止穴への挿入深さを適切に調整することで、前記タイルパネルを適切な不陸状態で抑えることを確保することができる。   According to the wall surface repairing method for raising the supervisor passage in the tunnel of 2 of the present invention, the lower part of the bulging prevention bar is arranged on the front surface of the tile panel, and toward the tile panel side. The lower holding means is a locking plate portion that holds the non-land adjustment part at the lower part of the bulging prevention rod, and is configured as a non-land adjustment part cut obliquely downward. A locking plate portion in which a plurality of locking holes for inserting the unevenness adjusting portion at the lower portion of the stick-out prevention bar are continuously opened in a direction parallel to the surface direction of the tile panel, and the locking plate portion Since it is composed of a mounting plate portion that hangs from the inner end (rear end) and is attached to the wall surface, the wall surface to be mounted has unevenness in the lateral direction, and the lower holding means is in the unevenness. Even if it is attached while deforming along the shape, the bulge prevention The engagement of the stop plate insertion depth into locking hole by appropriately adjusting, it is possible to ensure suppressing the tile panels in a suitable uneven surface state of the.

本発明の3のトンネル内の監視員通路を立ち上げる壁面の補修方法によれば、隣接する両側のタイルパネルを連結補強部材の連結板部により背面側で連結するものであり、これによって左右両側のタイルパネルが強固に連結され、更にこのようなタイルパネルの連結設置の後に、該タイルパネルと壁面との間にモルタルを注入充填すると、充填されたモルタル中に、該連結板部の下端から後方に延長する延長板部の後端から更に垂下する絡み片が絡み埋設することとなり、該タイルパネルの壁面への結合は、モルタルとの単なる接合を越えてより強化されたものとなる。   According to the wall surface repairing method for raising the observer passage in the tunnel of 3 of the present invention, the adjacent tile panels on the both sides are connected on the back side by the connecting plate portion of the connecting reinforcing member. After the tile panel is firmly connected, and after the tile panel is connected and installed, when mortar is injected and filled between the tile panel and the wall surface, from the lower end of the connection plate portion into the filled mortar. The entanglement piece further hanging down from the rear end of the extension plate portion extending backward is entangled and buried, and the bonding of the tile panel to the wall surface is further strengthened beyond simple joining with the mortar.

本発明の4のトンネル内の監視員通路を立ち上げる壁面の補修方法によれば、隣接する両側のタイルパネルの隙間を埋める充填剤を充填した上で、更に該両タイルパネルの隙間部分を含むその前面に漏出防止板を配置したため、タイルパネルと壁面との間にモルタルを注入充填した場合に、そのモルタルが両側のタイルパネルの隙間から外部に漏出するような問題を確実に回避することができる。   According to the repair method of the wall surface for raising the observer passage in the tunnel of 4 of the present invention, after filling the filler filling the gap between the adjacent tile panels, the gap portion between the two tile panels is further included. Since the leakage prevention plate is arranged on the front surface, when mortar is injected and filled between the tile panel and the wall surface, it is possible to reliably avoid the problem that the mortar leaks outside through the gap between the tile panels on both sides. it can.

本発明の5のトンネル内の監視員通路を立ち上げる壁面の補修方法によれば、前記漏出防止板は、これを前記タイルパネルの前面側に配して、モルタルの注入圧によって該タイルパネルが外方に膨出するのを抑えるための二本以上の膨出防止棒を、該漏出防止板の前面側に配し、これを介して該タイルパネルの膨出を防止するようにしたことにより、該漏出防止板と該タイルパネルとを同時に抑えることとなり、特別に他の手段を用意することなく、簡単にかつ確実に前記漏出防止板を抑えることができる。   According to the method of repairing a wall surface for raising a supervisor passage in a tunnel of 5 of the present invention, the leakage prevention plate is disposed on the front side of the tile panel, and the tile panel is caused by the injection pressure of mortar. By arranging two or more bulging prevention rods to suppress outward bulging on the front side of the leakage prevention plate, and preventing the tile panel from bulging through this The leakage prevention plate and the tile panel are suppressed at the same time, and the leakage prevention plate can be suppressed easily and reliably without preparing any other means.

(a)は、本発明の一実施例のトンネル内の監視員通路を立ち上げる壁面の補修方法の最終段階でモルタルの硬化を待つ状態を示した平面図、(b)は、正面図、(c)は、側面断面図である。(A) is a plan view showing a state of waiting for the mortar to harden at the final stage of the wall surface repairing method for raising the supervisor passage in the tunnel of one embodiment of the present invention, (b) is a front view, ( c) is a side sectional view. 図1(b)の中央部付近の拡大図である。It is an enlarged view of the central part vicinity of FIG.1 (b). 図1(c)の拡大図である。It is an enlarged view of FIG.1 (c). 図1(a)の中央部付近の拡大図である。It is an enlarged view of the central part vicinity of Fig.1 (a). 図1(a)の中央から外れた部位付近の拡大図である。It is an enlarged view of the site | part vicinity from the center of Fig.1 (a). (a)は、損傷を生じた壁面の損傷部位を剥離除去した状態の平面断面図、(b)は、正面図である。(A) is a plane sectional view in the state where the damaged part of the wall surface which caused damage was peeled and removed, and (b) is a front view. (a)は、補修対象の壁面の前面に所定間隔を空けてタイルパネルを設置した状態の平面断面図、(b)は、正面図、(c)は、側面断面図である。(A) is a plane sectional view in a state where tile panels are installed at a predetermined interval in front of the wall surface to be repaired, (b) is a front view, and (c) is a side sectional view. (a)は、図7(a)の中央部付近の拡大図、(b)は、図7(b)の中央部付近の拡大図である。(A) is an enlarged view of the vicinity of the central portion of FIG. 7 (a), and (b) is an enlarged view of the vicinity of the central portion of FIG. 7 (b). 図7(c)の拡大図である。It is an enlarged view of FIG.7 (c). タイルパネルの正面図である。It is a front view of a tile panel. (a)は、タイルパネルの右側部分の拡大平面図、(b)は、右側部分の一部切欠拡大正面図、(c)は、一部切欠拡大右側面図である。(A) is an enlarged plan view of the right side portion of the tile panel, (b) is a partially cutaway enlarged front view of the right side portion, and (c) is a partially cutaway enlarged right side view. (a)は、膨出防止棒の一部切欠拡大左側面図、(b)は、一部切欠拡大正面図、(c)は、左側面図、(d)は、拡大平面図である。(A) is a partially cutaway enlarged left side view of the bulging prevention rod, (b) is a partially cutaway enlarged front view, (c) is a left side view, and (d) is an enlarged plan view. (a)は、下部保持手段の上下反転状態の一部切欠拡大正面図、(b)は、上下反転状態の一部切欠拡大平面図、(c)は、上下反転状態の拡大側面図、(d)は、上下反転状態の正面図である。(A) is a partially cutaway enlarged front view of the lower holding means in the upside down state, (b) is a partially cutout enlarged plan view of the upside down state, (c) is an enlarged side view of the upside down state, d) is a front view of the upside down state. (a)は、連結補強部材の平面図、(b)は、正面図、(c)は、右側面図である。(A) is a top view of a connection reinforcement member, (b) is a front view, (c) is a right view. 補修対象の壁面を示すためのトンネルの概要図である。It is a schematic diagram of the tunnel for showing the wall surface for repair.

以下、発明を実施するための形態を実施例に基づいて添付図を参照しつつ詳細に説明する。   DESCRIPTION OF EMBODIMENTS Hereinafter, embodiments for carrying out the present invention will be described in detail based on examples with reference to the accompanying drawings.

まず初めに本発明のトンネル内の監視員通路を立ち上げる壁面の補修方法を実施するために用いる主要な部材である、タイルパネル1と、膨出防止棒2と、上部保持手段を構成する係止補助棒3及びクランプ手段4と、下部保持手段5と、連結補強部材6と、漏出防止板7とを説明する。   First, the tile panel 1, the bulging prevention rod 2, and the upper holding means, which are the main members used for carrying out the wall surface repairing method for raising the observer passage in the tunnel of the present invention, are constructed. The stop auxiliary rod 3 and the clamping means 4, the lower holding means 5, the connection reinforcing member 6, and the leakage preventing plate 7 will be described.

前記タイルパネル1は、この実施例では、特に図10及び図11に示すように、複数のタイル11、11、・・・と、これらを前面に縦横に配列したセメントボード(基板)12と、上下隣接する複数のタイル11、11、・・・の幅狭目地中に配する中間係止金具13aと、アンカーボルトb1を取り付けうる幅広目地中に配する中関係止金具13bと、該中間係止金具13a、13bを前記セメントボード12に取り付け固定するためのリベット部材14と、前記セメントボード12の最上部又は最下部に配され、その最上部又は最下部の複数のタイル11、11、・・・の上縁又は下縁、及び該セメントボード12の上部小口又は下部小口を同時に抱える上下部係止金具15と、で構成したものである。   In this embodiment, the tile panel 1 is a plurality of tiles 11, 11,..., And a cement board (substrate) 12 in which these are arranged vertically and horizontally on the front surface, as shown in FIGS. An intermediate locking bracket 13a disposed in the narrow joint of the plurality of tiles 11, 11,... Adjacent to each other, an intermediate fastening member 13b disposed in the wide joint to which the anchor bolt b1 can be attached, and the intermediate member A rivet member 14 for attaching and fixing the fasteners 13a, 13b to the cement board 12, and a plurality of tiles 11, 11,. The upper and lower edges of the cement board 12 and the upper and lower locking brackets 15 that simultaneously hold the upper edge or the lower edge of the cement board 12 are configured.

前記タイル11は、図10に示すように、一般的な四辺形のセラミック製のそれであり、特別の加工は施していない。また前記セメントボード12は横長長方形の公知の基板部材であり、小口を除いてその外面には防水用のシーラーが施してある。   As shown in FIG. 10, the tile 11 is made of a general quadrilateral ceramic and is not specially processed. The cement board 12 is a well-known board member having a horizontally long rectangular shape, and a waterproof sealer is provided on the outer surface thereof except for the small edge.

前記中間係止金具13a、13bは、特に図11に示すように、ステンレススチールで一体に形成した上方のタイル11の下縁を抱える下縁係止片、下方のタイル11の上縁を抱える上縁係止片及びそれらの間に凹状に構成した取付片からなるものである。該取付片は、詳細には、側面から見て、前記下縁係止片の下端と上縁係止片の上端からコ字形に後退した形状のものであり、前記幅狭目地中に配する中間係止金具13aの取付片は前記リベット部材14を取り付けうる程度の幅狭に、前記幅広目地中に配する中間係止金具13bの取付片は、アンカーボルトb1を取り付けうる程度に幅広に、それぞれ構成してあるものである。前者の中間係止金具13aの取付片には、その長さ方向に沿って前記リベット部材14を取り付けるための係止穴を連設開口し、後者の中間係止金具13bの取付片には、その長さ方向に沿って前記リベット部材14を取り付けるための係止穴を連設開口し、更にその係止穴の適宜数毎に該係止穴を、アンカーボルトb1を取り付けうる大径係止穴に構成しておくものとする。   As shown in FIG. 11 in particular, the intermediate locking brackets 13a and 13b are formed of stainless steel integrally with a lower edge locking piece that holds the lower edge of the upper tile 11 and an upper edge that holds the upper edge of the lower tile 11. It consists of an edge locking piece and a mounting piece configured in a concave shape between them. Specifically, the mounting piece has a shape that is recessed in a U-shape from the lower end of the lower edge locking piece and the upper end of the upper edge locking piece when viewed from the side, and is disposed in the narrow joint. The attachment piece of the intermediate locking fitting 13a is narrow enough to attach the rivet member 14, and the attachment piece of the intermediate locking fitting 13b arranged in the wide joint is wide enough to attach the anchor bolt b1. Each is configured. The attachment piece of the former intermediate locking fitting 13a is provided with a locking hole for attaching the rivet member 14 along its length direction, and the attachment piece of the latter intermediate locking fitting 13b includes A locking hole for attaching the rivet member 14 is continuously opened along the length direction, and the large-diameter locking capable of attaching the anchor bolt b1 is provided for each appropriate number of the locking holes. It shall be configured in the hole.

なお、以上の中間係止金具13a、13bは、図10及び図11に示すように、その中央仮装線を対称軸として上下が対象となる構成となっているものである。   In addition, as shown in FIG.10 and FIG.11, the above intermediate | middle latching metal fittings 13a and 13b become a structure for which the upper and lower sides are made into object by setting the center temporary fitting line as a symmetry axis.

前記上下部係止金具15は、図10及び図11に示すように、前記セメントボード12の最上部又は最下部に配し、その最上部又は最下部の複数のタイル11、11、・・・の上縁又は下縁を係止する上下縁係止片、前記セメントボード12の上部小口又は下部小口を被覆しかつ係止する被覆係止片、前記上下縁係止片及び前記被覆係止片の間から垂下又は直立し、最上部又は最下部のタイル11、11、・・・と前記セメントボード12との間に挿入する複数の係止舌片を備えたものである。   As shown in FIGS. 10 and 11, the upper and lower portion locking metal fittings 15 are arranged at the uppermost or lowermost part of the cement board 12, and a plurality of tiles 11, 11,. Upper and lower edge locking pieces for locking the upper edge or lower edge of the board, a covering locking piece for covering and locking the upper or lower edge of the cement board 12, the upper and lower edge locking pieces and the covering locking piece Are provided with a plurality of locking tongues inserted between the cement board 12 and the uppermost or lowermost tiles 11, 11...

そして、実施例のタイルパネル1は、図10及び図11に示すように、セメントボード12の前面にタイル11、11、・・・を縦横に配列し、該タイル11、11、・・・を、前記中間係止金具13a、13a、・・・、13b、13b、・・・と、上下部係止金具15、15と、前記中間係止金具13a、13a、・・・、13b、13b、・・・をセメントボード12に固定するリベット部材14、14、・・・とで固定することで構成したものである。   And the tile panel 1 of an Example arrange | positions the tiles 11, 11, ... vertically and horizontally on the front surface of the cement board 12, as shown in FIG.10 and FIG.11. , 13b, 13b,..., Upper and lower portion locking brackets 15 and 15, and intermediate locking brackets 13a, 13a,..., 13b, 13b,. Are fixed by rivet members 14, 14,... That are fixed to the cement board 12.

なお、上下隣接するタイル11、11、・・・の間の目地は、図10に示すように、最上部のタイル11、11、・・・とその直下のタイル11、11、・・・との間の目地、最下部のタイル11、11、・・・とその直上のタイル11、11、・・・との間の目地及び中央の目地は幅広に構成し、その間には前記中間係止金具13bを配置し、それ以外の目地は幅狭に構成し、その間には前記中間係止金具13aを配置し、それぞれの取付片に開口した係止穴を利用して前記リベット部材14で、これらの中間係止金具13a、13a、・・・、13b、13b、・・・をセメントボード12に固定し、これらを介してタイル11、11、・・・をセメントボード12に固定したものである。   As shown in FIG. 10, the joint between the upper and lower adjacent tiles 11, 11,..., And the tiles 11, 11,. The joint between the lowermost tiles 11, 11,... And the tiles 11, 11,. The metal fitting 13b is arranged, and the other joints are configured to be narrow, the intermediate locking metal fitting 13a is arranged between them, and the rivet member 14 is utilized using the locking holes opened in the respective attachment pieces. These intermediate locking brackets 13a, 13a,..., 13b, 13b,... Are fixed to the cement board 12, and the tiles 11, 11,. is there.

言うまでも無く、最上部のタイル11、11、・・・の上縁は、前記上下部係止金具15の上下縁係止片で抱えられ、前記セメントボード12の上部小口は前記上下部係止金具15の被覆係止片で抱えられ、かつ前記上下部係止金具15は、その係止舌片が、最上部のタイル11、11、・・・と前記セメントボード12との間に挿入状態となってその位置に固定状態となる。最上部のタイル11、11、・・・の上縁と前記セメントボード12の上部小口はこうして相互に結合状態となる。最下部のタイル11、11、・・・の上縁及び前記セメントボード12の下部小口も、上下対称状態で、同様に、前記上下部係止金具15で固定状態にされる。   Needless to say, the upper edge of the uppermost tile 11, 11,... Is held by the upper and lower edge locking pieces of the upper and lower part locking metal fitting 15, and the upper edge of the cement board 12 is the upper and lower part engaging member. The upper and lower portion locking fitting 15 is held between the top tiles 11, 11,... And the cement board 12. It becomes a state and becomes a fixed state at that position. The upper edge of the uppermost tile 11, 11,... And the upper edge of the cement board 12 are thus connected to each other. The upper edge of the lowermost tiles 11, 11,... And the lower edge of the cement board 12 are also in a vertically symmetrical state, and are similarly fixed by the upper and lower portion locking fittings 15.

なお、該タイル11、11、・・・は、該セメントボード12に縦横に配置する際にその背面に接着剤を配しておくこととし、前記上下部係止金具15の係止舌片は、該タイル11、11、・・・と該セメントボード12との間に該接着剤が硬化しないうちに挿入する。   The tiles 11, 11,... Are arranged on the cement board 12 in the vertical and horizontal directions with an adhesive disposed on the back thereof, and the locking tongues of the upper and lower locking brackets 15 are Are inserted between the tiles 11, 11,... And the cement board 12 before the adhesive is cured.

この実施例では、以上のようなタイルパネル1を採用したが、これに限定されるものではない。基板にタイルを他の構成の金具類を用いて取り付けたタイルパネル、またはタイルを基板に金具と接着剤を用いて接合固定したタイルパネル等を採用することが可能である。更には、好ましくはないが、基板の前面にタイルを縦横に配置して単に相互を接着結合したものでも採用可能である。ただし、いずれの場合でも、所要の位置のタイルの目地が、アンカーボルトを取り付けうる幅となっている必要はある。   In this embodiment, the tile panel 1 as described above is employed, but the present invention is not limited to this. It is possible to employ a tile panel in which tiles are attached to a substrate using metal fittings having other configurations, or a tile panel in which tiles are bonded and fixed to a substrate using metal fittings and an adhesive. Furthermore, although it is not preferable, it is also possible to employ one in which tiles are arranged vertically and horizontally on the front surface of the substrate and are simply adhesively bonded to each other. However, in any case, the joint of the tile at the required position needs to be wide enough to attach the anchor bolt.

前記膨出防止棒2は、図3等に示すように、壁面wの前面に一定間隔を空けて配したタイルパネル1、1、・・・の前面側にその膨出を防止すべく、上下方向を向けてクッション材21を介して接合状態に配する部材であり、図12に示すように、平面視で、使用時に壁面wと直交する方向に長い長方形の角形である、角筒状の長尺金属部材である。その下部は、同図及び図3等に示すように、使用状態で、下方に向かうに従って前記タイルパネル1、1、・・・側に向かうように斜めにカットした形状の不陸調整部22を備えたものである。なお、前記クッション材21は、弾力性を有する帯状の部材であり、同図に示すように、この実施例では、膨出防止棒2のタイルパネル1との接合面側に予め接合固定しておく。   As shown in FIG. 3 and the like, the bulge prevention bar 2 is arranged in the vertical direction to prevent the bulge from being formed on the front side of the tile panels 1, 1,. It is a member that is arranged in a joined state with the cushion material 21 facing the direction, and as shown in FIG. 12, in a plan view, a rectangular rectangular shape that is long in the direction perpendicular to the wall surface w when used. It is a long metal member. As shown in FIG. 3 and FIG. 3 and the like, the lower portion is provided with an uneven adjustment portion 22 having a shape that is obliquely cut toward the tile panel 1, 1,... It is provided. The cushion material 21 is a belt-like member having elasticity, and in this embodiment, the cushion material 21 is bonded and fixed in advance to the joint surface side of the bulging prevention rod 2 with the tile panel 1 as shown in FIG. deep.

この実施例では、膨出防止棒2は、以上のように構成したが、下部に前記の構成の不陸調整部22を有するものであれば、他の構成のそれも採用可能である。   In this embodiment, the bulging prevention rod 2 is configured as described above. However, as long as it has the unevenness adjusting portion 22 having the above-described configuration at the lower portion, it can be employed in other configurations.

前記上部保持手段の一部を構成する係止補助棒3は、図1〜図5に示すように、端面から見て正方形の角筒状の金属部材をそれとして採用したものである。もっともこの係止補助棒3は、これに限定されず、使用時に、監視員通路の路面側に位置する部位から立ち上がる手摺りの支柱cの路面と反対側の部位に該路面と平行に配して、これを介して前記クランプ手段4の他方の係止端42を該支柱cに係止できる、十分な強度を有する長尺部材であれば、例えば、円筒状の金属部材、内部の充実した金属棒、その他の構成の部材を採用することも可能である。   As shown in FIGS. 1 to 5, the auxiliary locking rod 3 that constitutes a part of the upper holding means employs a square rectangular tube-shaped metal member as viewed from the end face. However, the auxiliary locking rod 3 is not limited to this, and is arranged in parallel with the road surface at a site opposite to the road surface of the column c of the handrail that rises from the site located on the road surface side of the supervisor passage when in use. For example, a cylindrical metal member having a sufficient strength can be used as long as it is a long member having sufficient strength that can lock the other locking end 42 of the clamping means 4 to the support column c via this. It is also possible to employ a metal bar or other member having a configuration.

前記上部保持手段の他の一部を構成するクランプ手段4は、図1〜図5に示すように、一方の係止端41、他方の係止端42、各々の基部41a、42aの間隔を伸縮自在に繋ぐ調整ボルト部材43及び上記各基部41a、42aに配したグリップ片からなり、前記調整ボルト部材43を一定方向に回転(短縮回転)させると、前記基部41a、42aの間隔が短縮し、他方向に回転(伸張回転)させると、該間隔が伸張するように動作するようになっている。   As shown in FIGS. 1 to 5, the clamping means 4 constituting the other part of the upper holding means has an interval between one locking end 41, the other locking end 42, and the base portions 41 a and 42 a. An adjustment bolt member 43 that is stretchably connected and a grip piece disposed on each of the base portions 41a and 42a. When the adjustment bolt member 43 is rotated (shortened rotation) in a certain direction, the interval between the base portions 41a and 42a is shortened. When it is rotated in the other direction (extension rotation), it operates so as to extend the interval.

前記クランプ手段4は、この実施例では、以上の構成のそれを採用したが、一方の係止端41と他方の係止端42との間隔を自由に伸縮し得、設定した間隔を保持しうる構成であれば、特定のそれに限定されない。自由に種々の構成のそれを採用することができる。   In this embodiment, the clamp means 4 adopts the above-described configuration, but the distance between one locking end 41 and the other locking end 42 can be freely expanded and contracted, and the set distance is maintained. The configuration is not limited to a specific one as long as it can be configured. Any of various configurations can be freely adopted.

前記下部保持手段5は、図3〜図5、図9及び図13に示すように、使用状態で、前記タイルパネル1、1、・・・の下端下から前方に延びる係止板部51と、該係止板部51の内端(後端)から垂下する、前記壁面wへ取り付けるための取付板部52とで構成した、側面視でL形の長尺金属板材である。   As shown in FIGS. 3 to 5, 9, and 13, the lower holding means 5 includes a locking plate 51 that extends forward from below the lower ends of the tile panels 1,. , A long metal plate having an L shape in side view, which is constituted by an attachment plate portion 52 that is suspended from the inner end (rear end) of the locking plate portion 51 and is attached to the wall surface w.

以上の係止板部51は、図4、図5及び図13に示すように、その長さ方向に沿って複数の係止穴51h、51h、・・・を連設開口したものである。該各係止穴51hは、該係止板部51の長さ方向に直交する方向の寸法を、前記膨出防止棒2の不陸調整部22の最下部から最上部までの調整用寸法の全範囲を越える寸法に構成する。また該各係止穴51h、51h、・・・の該係止板部51の長さ方向に沿った方向の寸法を、使用時の該膨出防止棒2の同方向の寸法以上の寸法に構成する。   As shown in FIGS. 4, 5, and 13, the above locking plate portion 51 has a plurality of locking holes 51 h, 51 h,... Each of the locking holes 51h has a dimension in a direction perpendicular to the length direction of the locking plate part 51, and is an adjustment dimension from the lowermost part to the uppermost part of the unevenness adjusting part 22 of the bulging prevention rod 2. Configure the dimensions to exceed the entire range. Further, the dimension of each of the locking holes 51h, 51h,... Along the length direction of the locking plate portion 51 is set to a dimension larger than the dimension in the same direction of the bulging prevention rod 2 in use. Configure.

前記取付板部52は、図1、図2、図8及び図13に示すように、その長さ方向に沿ってその略中央部に横長の取付穴52h、52h、・・・を連設開口しておく。該各取付穴52h、52h、・・・は、同図に示すように、前記壁面wに接合した取付板部52を、それらを通じて挿入した仮止め用アンカーボルトb2、b2、・・・で該壁面wに仮固定することができるように、該仮止め用アンカーボルトb2、b2、・・・を挿通するのに適した幅寸法としておく。   As shown in FIGS. 1, 2, 8 and 13, the mounting plate 52 is provided with continuous mounting holes 52 h, 52 h,... Keep it. As shown in the figure, the mounting holes 52h, 52h,... Are provided with anchoring bolts b2, b2,. In order to be able to be temporarily fixed to the wall surface w, a width dimension suitable for inserting the temporary fixing anchor bolts b2, b2,.

前記連結補強部材6は、図2〜図4、図8、図9及び図14に示すように、使用時に、隣接する両側のタイルパネル1、1の背面側に当接する連結板部61と、該連結板部61の下端から後方に延長する延長板部62と、該延長板部62の後端両側から垂下する二つの絡み片63、63とで構成したものである。   As shown in FIGS. 2 to 4, 8, 9, and 14, the connection reinforcing member 6 includes a connection plate portion 61 that comes into contact with the back side of the tile panels 1 and 1 on both sides when used, The extension plate portion 62 extends rearward from the lower end of the connecting plate portion 61 and two entanglement pieces 63, 63 hang down from both sides of the rear end of the extension plate portion 62.

以上の連結板部61は、特に図14に示すように、その両側の各部位で、隣接する両側のタイルパネル1、1の各近接する端部付近の背面に接合固定して両者を連結する手段である。この連結板部61の中央部には円形穴が開口してあり、両側中央寄りにはそれぞれ幅の広い横長の結合穴61haが開口してあり、両側外方寄りにはそれぞれ幅の狭い横長の結合穴61hbが開口してある。いずれもこれらを利用してボルト・ナットbn、bnで該連結板部61と両側のタイルパネル1、1とを連結するための手段である。   In particular, as shown in FIG. 14, the connecting plate portion 61 described above is joined and fixed to the back surfaces near the adjacent end portions of the adjacent tile panels 1 and 1 at both sides thereof to connect the two. Means. A circular hole is opened at the center of the connecting plate 61, a wide horizontally long coupling hole 61ha is opened near the center of both sides, and a narrow horizontally long hole is formed near the outside of both sides. A coupling hole 61hb is opened. Both of these are means for connecting the connecting plate portion 61 and the tile panels 1 and 1 on both sides with bolts and nuts bn and bn.

前記延長板部62は、同図に示すように、前記連結板部61の下端から使用時における後方に直角に折り曲げて延長した部材であり、これは、前記絡み片63、63を使用時に良好にモルタルm中に絡み埋設させる趣旨で延長するものである。   As shown in the figure, the extension plate portion 62 is a member that is bent and extended at a right angle from the lower end of the connecting plate portion 61 to the rear at the time of use, which is good when the entangled pieces 63 and 63 are used. It is extended for the purpose of entangled in the mortar m.

前記二つの絡み片63、63は、以上に述べ、図3及び図4に示すように、使用時に、モルタルm中に絡み埋設し、前記延長板部62及び連結板部61を介して、タイルパネル1、1を強固にモルタルmに結合させる趣旨のものである。前記連結補強部材6は、従って、隣接する二つのタイルパネル1、1を結合すると同時に、モルタルmに対しても強固に結合させるようにする趣旨を持ったものである。   As described above and shown in FIGS. 3 and 4, the two entanglement pieces 63, 63 are entangled and embedded in the mortar m during use, and are connected to the tile through the extension plate portion 62 and the connection plate portion 61. The panel 1 or 1 is firmly bonded to the mortar m. Accordingly, the connection reinforcing member 6 has a purpose of firmly bonding the two adjacent tile panels 1 and 1 to the mortar m at the same time.

前記漏出防止板7は、図2〜図4に示すように、隣接する両側のタイルパネル1、1の前面側にその間を閉じるように配して、該隣接するタイルパネル1、1の隙間から、タイルパネル1、1、・・・と背後の壁面wとの間に注入充填するモルタルmが漏出するのを防止するための板状部材である。この実施例では、内面側に剥離剤を塗布したコンパネを採用し、隣接する両側のタイルパネル1、1の隙間を最上部から最下部まで一枚のそれで閉じるべく用いる。またこの漏出防止板7のタイルパネル1、1への接合状態は、該タイルパネル1、1の膨出防止のために用いる前記膨出防止棒2、2を該漏出防止板7の外面側に配することにして、タイルパネル1、1と同時に保持する。   As shown in FIGS. 2 to 4, the leakage prevention plate 7 is arranged on the front side of the adjacent tile panels 1, 1 so as to close the space between the adjacent tile panels 1, 1. These are plate-like members for preventing the mortar m to be injected and filled between the tile panels 1, 1,... In this embodiment, a panel having a release agent applied on the inner surface side is adopted, and the gap between the adjacent tile panels 1 and 1 is used to close with a single sheet from the top to the bottom. Further, the leakage prevention plate 7 is joined to the tile panels 1 and 1 in such a manner that the bulging prevention rods 2 and 2 used for preventing the tile panels 1 and 1 from bulging are placed on the outer surface side of the leakage prevention plate 7. The tile panels 1 and 1 are held at the same time.

本発明のトンネル内の監視員通路を立ち上げる壁面の補修方法は以上の各部材を用いて実施する。本発明の適用対象は、図15に示すように、トンネル内の監視員通路kを立ち上げる、路面に面した壁面wである。該壁面wに損傷を生じた場合又はそのおそれが生じた場合には、損傷の生じた部位又はそのおそれの生じた部位をそのままで又は剥離除去した上で、該壁面wの前面側に所定間隔をあけて複数枚のタイルパネル1、1、・・・を配置する。この実施例では、図6に示すように、損傷の生じている部位や脆弱な部位を除去した上で、図7〜図9に示すように、該壁面wの前面側にタイルパネル1、1、・・・を配置することとしたものである。   The wall surface repairing method for raising the observer passage in the tunnel of the present invention is carried out using the above-described members. As shown in FIG. 15, the application target of the present invention is a wall surface w facing the road surface, which starts up a supervisor passage k in the tunnel. When the wall w is damaged or when there is a risk, the damaged part or the part where the risk has occurred may be left as it is or after being peeled off and removed at a predetermined interval on the front side of the wall w. A plurality of tile panels 1, 1,. In this embodiment, as shown in FIG. 6, after removing damaged parts and fragile parts, tile panels 1, 1 on the front side of the wall surface w as shown in FIGS. , ... are arranged.

なお、この実施例では、タイルパネル1の縦方向の寸法は、補修対象の壁面wの高さ方向の寸法に対応するものとし、縦方向には一枚で、横方向に必要なだけの複数枚のタイルパネル1、1、・・・を配置することとしたものである。   In this embodiment, the vertical dimension of the tile panel 1 corresponds to the height dimension of the wall surface w to be repaired. The tile panels 1, 1,... Are arranged.

前記壁面wの損傷を生じた部位及び脆弱な部位の除去は、適当な打撃力で対応部位を打撃する等の既存の技術により該当部位を剥離することで行ったものである。   The removal of the damaged part and the weak part of the wall surface w is performed by peeling the corresponding part by an existing technique such as hitting the corresponding part with an appropriate striking force.

また前記タイルパネル1、1、・・・の壁面wの前面への取り付けは、図2、図3、図8及び図9に示すように、原則として、アンカーボルトb1、b1、・・・により行う。タイルパネル1、1、・・・は、図3及び図4に示すように、壁面wに設置してある既存のタイルt、t、・・・又は取り付けてあったタイルt、t、・・・の前面から、この実施例では、約3mm程の間隔sを空けて配置し、前記アンカーボルトb1、b1、・・・で固定する。壁面wには、設置するタイルパネル1、1、・・・に配したタイル11、11、・・・の幅広の横目地に配した中間係止金具13b、13b、・・・の大径係止穴の位置に対応させて下穴を形成しておく。   In addition, as shown in FIGS. 2, 3, 8, and 9, the tile panels 1, 1,... Are attached to the front surface of the wall surface w by anchor bolts b1, b1,. Do. As shown in FIGS. 3 and 4, the tile panels 1, 1,... Are existing tiles t, t,... Installed on the wall surface w, or tiles t, t,. In this embodiment, from the front side, the gap s of about 3 mm is disposed and fixed with the anchor bolts b1, b1,. On the wall surface w, a large-diameter member of intermediate locking fittings 13b, 13b,... Arranged on the wide horizontal joints of the tiles 11, 11,. A pilot hole is formed corresponding to the position of the blind hole.

なお、前記中間係止金具13bの大径係止穴のうち、背後の壁面wの対応する部位が脆弱化していて、大きく削除されている場合は、その部位については下穴を形成しておくことができないが、後述するように、一部だけでも下穴を形成し得、アンカーボルトb1、b1、・・・を固定することが可能な部位があれば、不都合ではない。タイルパネル1、1、・・・は、その面と直交する外方への力がかかった場合には、前記膨出防止棒2、2、・・・によってそれが膨出しないように、すなわち、前記間隔sが維持され、不陸が適切に調節された状態が維持されるように保持されており、他方、これと逆方向の力は、掛かる可能性が殆ど無く、モルタルmで固定されるようになるまで仮保持できれば良いからである。   In addition, in the large-diameter locking hole of the intermediate locking metal fitting 13b, when the corresponding part of the rear wall surface w is weakened and greatly deleted, a pilot hole is formed for that part. However, as will be described later, it is not inconvenient if a part of the pilot hole can be formed, and the anchor bolts b1, b1,. The tile panel 1, 1,... Is prevented from bulging by the bulging prevention rods 2, 2,. The distance s is maintained and the unevenness is maintained in an appropriately adjusted state, while the force in the opposite direction is hardly applied and is fixed by the mortar m. This is because it is sufficient if it can be temporarily held until it becomes.

もっともこの実施例では、必要に応じて、タイルパネル1、1、・・・の背後の壁面wの対応する部位が脆弱化していて、大きく削除されている場合は、特に図3及び図5に示すように、対応する中間係止金具13b、13b、・・・の大径係止穴には、前面側から長ボルトb3、b3、・・・を挿入し、ナットでその頭部をタイルパネル1、1、・・・に固定し、後方に延びた該長ボルトb3、b3、・・・の後部には調整長ナットを螺合し、全体としての長さを調節し、該長ナットの後端を該壁面wの削除面に当接させ、突っ張り状態とすることにより、タイルパネル1、1、・・・の調節した不陸状態を維持するようにすることとした。   However, in this embodiment, if the corresponding part of the wall surface w behind the tile panels 1, 1,... Is weakened and greatly deleted as necessary, particularly in FIGS. As shown, long bolts b3, b3,... Are inserted from the front side into the large-diameter locking holes of the corresponding intermediate locking fittings 13b, 13b,. , 1,... Fixed to the rear part of the long bolts b 3, b 3,... The rear end is brought into contact with the deleted surface of the wall surface w so as to be in a stretched state so that the adjusted uneven state of the tile panels 1, 1,.

他方、タイルパネル1、1、・・・には、その中間係止金具13bの大径係止穴にアンカーボルトb1、b1、・・・の先端側を取り付けておく。該アンカーボルトb1、b1、・・・は、その先端部と途中のナットとで、タイルパネル1、1、・・・のセメントボード12及び中間係止金具13bの取付片を挟持する状態にしてタイルパネル1、1、・・・に固定しておく。当然、アンカーボルトb1、b1、・・・は、タイルパネル1、1、・・・の背後側に延長する状態に配する。   On the other hand, on the tile panels 1, 1,..., The tip ends of the anchor bolts b1, b1,. The anchor bolts b1, b1,... Are in a state of sandwiching the attachment pieces of the cement board 12 and the intermediate locking fitting 13b of the tile panels 1, 1,. It is fixed to the tile panels 1, 1,. Naturally, the anchor bolts b1, b1,... Are arranged in a state extending to the back side of the tile panels 1, 1,.

以上のタイルパネル1、1、・・・は、以上のようにしてこれに取り付けてあるアンカーボルトb1、b1、・・・を、壁面wの所定位置に開口してある下穴に挿入し、当該のアンカーボルトb1、b1、・・・に応じた操作、例えば、ねじ込み又は打ち込むことで該アンカーボルトb1、b1、・・・を該下穴に固定し、これによって該壁面wに固設する。該下穴へのアンカーボルトb1、b1、・・・の打ち込み深さ又はねじ込み深さを調節することで、該タイルパネル1、1、・・・の不陸を調節する。また該壁面wと該タイルパネル1、1、・・・との隙間の間隔sを、この実施例では、3mm程度に調節する。   The above tile panels 1, 1,... Are inserted into the prepared holes opened at predetermined positions on the wall surface w, and anchor bolts b1, b1,. The anchor bolts b1, b1,... Are fixed to the pilot holes by screwing or driving, for example, according to the anchor bolts b1, b1,. . By adjusting the driving depth or screwing depth of the anchor bolts b1, b1,... Into the pilot holes, the unevenness of the tile panels 1, 1,. Further, the gap interval s between the wall surface w and the tile panels 1, 1,... Is adjusted to about 3 mm in this embodiment.

この間隔sは、この実施例では、以上のように、3mm程度に設定したが、これに限定されない。この間隔sは、この間隔s内に注入充填するモルタルmの流動性との関係で設定するものであり、密に注入充填可能な最低限度以上に設定すれば良い。ただし、できるだけ狭いことが好ましい。   In this embodiment, the interval s is set to about 3 mm as described above, but is not limited thereto. This interval s is set in relation to the fluidity of the mortar m to be injected and filled in the interval s, and may be set to a minimum level or more that allows dense injection and filling. However, it is preferably as narrow as possible.

こうして、タイルパネル1、1、・・・を壁面wの前面に、不陸を調節し、これを優先しながら該壁面wとタイルパネル1、1、・・・との隙間の間隔sを約3mm程度に設定して取り付けた後、図7〜図9に示すように、隣接する各タイルパネル1、1を、前記連結補強部材6で連結する。該連結補強部材6は、その連結板部61の両側のそれぞれを、隣接するタイルパネル1、1の背面側で、前記中間係止金具13bの配してあるタイル11、11、・・・の広幅横目地に対応する部位に当接させる。そうした上で、両側のタイルパネル1、1の各中間係止金具13bの取付片に開口した大径係止穴と前記連結補強部材6の連結板部61の両側に開口してある幅狭の横長の各結合穴とを対応させ、それぞれにタイルパネル1、1の前面側からボルトを挿入し、裏面側に突出した該ボルトにナットを螺合する。こうして二つのボルト・ナットbn、bn及び連結補強部材6の連結板部61を介して隣接する両側のタイルパネル1、1を連結する。   In this way, the tile panel 1, 1,... Is adjusted to the front surface of the wall surface w, the unevenness is adjusted, and the gap s between the wall surface w and the tile panels 1, 1,. After setting and attaching to about 3 mm, as shown in FIGS. 7 to 9, the adjacent tile panels 1 and 1 are connected by the connection reinforcing member 6. The connection reinforcing member 6 has tiles 11, 11,... On both sides of the connection plate portion 61 on the back side of the adjacent tile panels 1, 1 on which the intermediate locking metal fitting 13 b is arranged. It is made to contact | abut to the site | part corresponding to a wide horizontal joint. In addition, a large-diameter locking hole opened in the attachment piece of each intermediate locking metal fitting 13b of the tile panels 1 and 1 on both sides and a narrow opening opened on both sides of the connection plate portion 61 of the connection reinforcing member 6 are provided. The horizontally long coupling holes are made to correspond to each other, bolts are inserted into the tile panels 1 and 1 from the front side, and nuts are screwed into the bolts protruding to the back side. In this way, the adjacent tile panels 1 and 1 on both sides are connected via the two bolts and nuts bn and bn and the connecting plate portion 61 of the connecting reinforcing member 6.

この状態で、同図に示すように、該連結補強部材6の延長板部62は、背後側に延長状態になっており、その後端から二つの絡み片63、63が垂下状態となっていることになる。なお、このような隣接するタイルパネル1、1の連結は、損傷部位及び脆弱部位を剥離除去した壁面wに対応する部位で行う。また、このような隣接する相互のタイルパネル1、1の連結は、対象の壁面wの全範囲にタイルパネル1、1、・・・を設置した後に、または隣接するタイルパネル1、1を設置する毎に行う。   In this state, as shown in the figure, the extension plate portion 62 of the connection reinforcing member 6 is extended to the rear side, and the two entangled pieces 63 and 63 are suspended from the rear end. It will be. In addition, the connection of such adjacent tile panels 1 and 1 is performed in the site | part corresponding to the wall surface w which peeled and removed the damage site | part and the weak site | part. Moreover, the connection of such adjacent tile panels 1 and 1 is performed after installing the tile panels 1, 1,... Over the entire range of the target wall surface w or installing the adjacent tile panels 1, 1. Do it every time.

このように隣接するタイルパネル1、1を連結した後に、そのような隣接するタイルパネル1、1の間にはシーリング材と呼ばれる充填剤を充填しておく。   After connecting the adjacent tile panels 1 and 1 in this way, a filler called a sealing material is filled between the adjacent tile panels 1 and 1.

また、前記タイルパネル1、1、・・・を設置した後、その直下の位置に下部保持手段5を設置する。この実施例では、この段階で、この下部保持手段5を壁面wの上記位置に設置することとしたが、前記充填剤の充填前でも良いし、前記連結補強部材6による各隣接するタイルパネル1、1の連結の前であっても良い。更にタイルパネル1、1の設置前に壁面wに設置しておいても不都合ではない。なお、下部保持手段5は、タイルパネル1、1、・・・の上下方向の位置決めのためには、最後に述べた該タイルパネル1、1、・・・の設置前に壁面wに取り付けておくという手順が適切であることになる。   Further, after the tile panels 1, 1,... Are installed, the lower holding means 5 is installed at a position immediately below the tile panels. In this embodiment, at this stage, the lower holding means 5 is installed at the position of the wall surface w. However, it may be before the filler is filled, or each adjacent tile panel 1 by the connection reinforcing member 6 may be used. It may be before one connection. Furthermore, it is not inconvenient if it is installed on the wall surface w before the tile panels 1 and 1 are installed. The lower holding means 5 is attached to the wall surface w before installation of the tile panels 1, 1,. This is the appropriate procedure.

前記下部保持手段5は、図7〜図9に示すように、その取付板部52を、その上端から前方に延びる係止板部51が壁面wに設置した前記タイルパネル1、1、・・・の直下に位置することとなるように、位置決めしつつ該壁面wに接合し、開口してある横長の取付穴52h、52h、・・・を利用して仮止め用アンカーボルトb2、b2、・・・で該壁面wに仮止め固定する。なお、該壁面wの対応する位置には、下穴を開口しておき、前記取付穴52h、52h、・・・を通じて挿入した仮止め用アンカーボルトb2、b2、・・・を、それに応じた打ち込み又はねじ込み等の操作により該下穴に仮止めして該取付板部52を該壁面wに仮固定できるようにしておく。   As shown in FIGS. 7 to 9, the lower holding means 5 includes the tile panel 1, 1,... In which a mounting plate 52 is provided on a wall surface w with a locking plate 51 extending forward from the upper end thereof.・ Joint to the wall surface w while positioning so as to be positioned directly below, and using the horizontally long mounting holes 52h, 52h,..., Temporary anchor bolts b2, b2, .. Are temporarily fixed to the wall surface w. In addition, a pilot hole is opened in the corresponding position of the wall surface w, and the temporary fixing anchor bolts b2, b2,... Inserted through the mounting holes 52h, 52h,. The mounting plate 52 is temporarily fixed to the wall surface w by temporarily fixing the pilot hole to the pilot hole by driving or screwing.

また、以上の下部保持手段5の取り付けの際に、特に図9に示すように、タイルパネル1、1、・・・の下端直下に、該タイルパネル1、1、・・・と壁面wとの隙間に、注入充填するモルタルmが漏出しないようにするためのゴムパッキンpを配置し、前記係止板部51で該ゴムパッキンpをその位置に保持するようにする。   Further, when attaching the lower holding means 5 as described above, particularly as shown in FIG. 9, the tile panels 1, 1,... A rubber packing p for preventing the mortar m to be injected and filled from leaking out is disposed in the gap, and the rubber packing p is held at that position by the locking plate portion 51.

他方、前記監視員通路kの路面側の縁付近に立ち上げてある手摺りの支柱c、c、・・・には、図1〜図5に示すように、その路面と反対側の部位に前記係止補助棒3を接合状態に配置しておく。該係止補助棒3は、このように手摺りの支柱c、c、・・・と接する状態に配置すると、路面及び壁面wの面方向と概ね平行な向きになる。なお、この係止補助棒3の設置は、以下に述べるクランプ手段4、4、・・・で前記膨出防止棒2、2、・・・の上部を支持する操作を行う時点までに設置しておけば良い。   On the other hand, as shown in FIG. 1 to FIG. 5, a handrail column c, c,... Raised up near the road surface side edge of the supervisor passage k is located on the opposite side of the road surface. The locking auxiliary rod 3 is arranged in a joined state. When the auxiliary locking rod 3 is arranged in contact with the handrail support columns c, c,... In this way, the locking auxiliary rod 3 is in a direction substantially parallel to the surface direction of the road surface and the wall surface w. The locking auxiliary rod 3 is installed by the time when an operation for supporting the upper portions of the bulging prevention rods 2, 2,. Just keep it.

この後、前記膨出防止棒2、2、・・・を適切な横方向の間隔で、前記タイルパネル1、1、・・・の前面に配設する。なお、隣接するタイルパネル1、1の連結部については、前記漏出防止板7をその前面に接合状態に配置した上で、その前面側に前記膨出防止棒2、2、・・・を設置する。該膨出防止棒2、2、・・・は、この場合は、該漏出防止板7を介してタイルパネル1、1、・・・の前面側に配することになる。   After this, the bulging prevention rods 2, 2,... Are arranged on the front surface of the tile panels 1, 1,. In addition, about the connection part of the adjacent tile panels 1 and 1, after arrange | positioning the said leakage prevention board 7 in the joining state to the front surface, the said bulging prevention stick | rod 2, 2, ... is installed in the front side. To do. In this case, the bulging prevention rods 2, 2,... Are arranged on the front side of the tile panels 1, 1,.

該膨出防止棒2、2、・・・は、図1〜図5に示すように、前記クッション材21を前記タイルパネル1、1、・・・の前面側に当接する向きで配する。前記のように、隣接するタイルパネル1、1の連結部付近では、言うまでも無く、該タイルパネル1、1の前面側に配した前記漏出防止板7の前面側に前記クッション材21を当接した状態に配する。   As shown in FIGS. 1 to 5, the bulging prevention rods 2, 2,... Are arranged in a direction in which the cushion material 21 is in contact with the front side of the tile panels 1, 1,. Needless to say, in the vicinity of the connecting portion between the adjacent tile panels 1 and 1 as described above, the cushion material 21 is applied to the front surface side of the leakage prevention plate 7 disposed on the front surface side of the tile panels 1 and 1. Arrange for contact.

該膨出防止棒2、2、・・・は、同図に示すように、その下部の不陸調整部22をタイルパネル1、1、・・・の下端下に仮固定してある下部保持手段5の係止板部51に開口した係止穴51h、51h、・・・のうちの対応する位置のそれに挿入係止する。該不陸調整部22は、下方に向かうに従って該タイルパネル1、1、・・・側に向かうように斜めにカットした構成となっているので、該膨出防止棒2、2、・・・を深く押し下げ挿入すれば、そのクッション材21を接合した面は壁面w側に移動し、浅く押し下げ挿入すれば、そのクッション材21を接合した面は壁面wから離れた位置に位置することになる。   As shown in the figure, the bulging prevention rods 2, 2,... Are held at a lower portion by temporarily fixing the unevenness adjusting portion 22 below the lower ends of the tile panels 1, 1,. The locking holes 51h, 51h,... Opened in the locking plate portion 51 of the means 5 are inserted and locked in the corresponding positions. Since the unevenness adjusting part 22 is configured to be obliquely cut toward the tile panels 1, 1,... As it goes downward, the bulge prevention rods 2, 2,. Is inserted deeply, the surface to which the cushion material 21 is joined moves to the wall surface w side, and if it is pushed down and inserted shallowly, the surface to which the cushion material 21 is joined is located at a position away from the wall surface w. .

前記のように、タイルパネル1、1、・・・は、前記アンカーボルトb1、b1、・・・及び長ボルトb3、b3、・・・で、不陸を適切に調節し、これを優先しながら壁面wの前面に概ね3mm程度の間隔を空けて配置してあり、他方、前記下部保持手段5は、該壁面wに直接に仮固定してあり、それ故、壁面wの凹凸にならった状態にならざるを得ない。従って、該膨出防止棒2、2、・・・に不陸調整部22がないと、これを、不陸を調節してあるタイルパネル1、1、・・・の前面に適切に当接状態に配することができない。しかし該膨出防止棒2、2、・・・には不陸調整部22を設けてあるので、前記のように、最下部に位置する該不陸調整部22を前記下部保持手段5の係止板部51の係止穴51h、51h、・・・に適切な深さで挿入係止させれば、該膨出防止棒2、2、・・・の前記クッション材21を接合した面の不陸方向の位置関係を適切に調整できる。それ故、適切な不陸状態でタイルパネル1、1、・・・を外部から抑えることができる。   As described above, the tile panels 1, 1,... Appropriately adjust the unevenness with the anchor bolts b1, b1,... And the long bolts b3, b3,. However, the lower holding means 5 is temporarily fixed directly on the wall surface w, and thus is uneven on the wall surface w. It must be in a state. Therefore, if the bulge prevention rods 2, 2,... Are not provided with the unevenness adjusting portion 22, they are properly brought into contact with the front surfaces of the tile panels 1, 1,. Cannot be placed in the state. However, since the bulge prevention rods 2, 2,... Are provided with the unevenness adjusting portion 22, the unevenness adjusting portion 22 located at the lowermost portion is engaged with the lower holding means 5 as described above. If the locking holes 51h, 51h,... Of the stopper plate 51 are inserted and locked at an appropriate depth, the surface of the bulging prevention rods 2, 2,. The positional relationship in the non-landing direction can be adjusted appropriately. Therefore, the tile panels 1, 1,... Can be suppressed from the outside in an appropriate uneven state.

また、前記下部保持手段5は、前記壁面wに取り付けてあるものであり、路面や路面上の縁石に配してあるものではない。それ故、該路面や該縁石に傷を付けたり、汚したりするおそれもない。   Moreover, the said lower holding means 5 is attached to the said wall surface w, and is not distribute | arranged to the curbstone on a road surface or a road surface. Therefore, there is no possibility of scratching or soiling the road surface or the curb.

前記膨出防止棒2、2、・・・の上部は、前記クランプ手段4、4、・・・により、その適切なタイルパネル1、1、・・・の抑え状態で、支持する。   The upper portions of the bulging prevention rods 2, 2,... Are supported by the clamp means 4, 4,.

該クランプ手段4、4、・・・は、図3〜図5に示すように、その他方の係止端42、42、・・・を、前記監視員通路kの手摺りの支柱c、c、・・・に係止した係止補助棒3の監視員通路k側の部位に当接係止し、一方の係止端41、41、・・・を、前記膨出防止棒2、2、・・・の上部の通路側の面に当接係止させる。該一方の係止端41、41、・・・と該他方の係止端42、42、・・・との間隔が、前記係止補助棒3の該当部位と前記膨出防止棒2、2、・・・の該当部位との間隔より広い場合及び狭い場合は、前記調整ボルト部材43を短縮回転又は伸張回転させて、適切な間隔になるように調節し、前記膨出防止棒2、2、・・・の上部を、タイルパネル1、1、・・・を適切な不陸状態に保持すべく、支持できるようにする。   As shown in FIGS. 3 to 5, the clamping means 4, 4,... Are connected to the other locking ends 42, 42,. ,... Are in contact with and locked to the part on the side of the monitoring staff passage k of the locking auxiliary rod 3 locked to the one of the locking ends 41, 41,. Are brought into contact with and locked to the passage-side surface of the upper part of. The distance between the one locking end 41, 41,... And the other locking end 42, 42,. ..,... Wider than or narrower than the corresponding part, the adjusting bolt member 43 is shortened or extended and adjusted to an appropriate distance, and the bulging prevention rods 2, 2 are adjusted. ,... Can be supported to hold the tile panels 1, 1,.

このように準備した後、タイルパネル1、1、・・・と壁面wとの間に、当然、損傷を生じて剥離除去した部位を含めて、高流動性かつ無収縮のモルタルmを注入充填する。この注入充填は一般の技法による。   After preparing in this way, between the tile panels 1, 1,... And the wall surface w, of course, including high-fluidity and non-shrinkable mortar m, including the site where damage has occurred and removed. To do. This injection filling is by common techniques.

注入されたモルタルmは、高流動性なので、図1〜図5に示すように、狭い空間にも十分に行き渡ることになるが、隣接する各タイルパネル1、1間には充填剤(シーリング材)が充填してあり、更にその前面側には前記漏出防止板7が配してあるので、該モルタルmがその間から漏出することはない。またタイルパネル1、1、・・・の下端下には、該タイルパネル1、1、・・・と壁面wとの隙間を塞ぐゴムパッキンpが配置してあるので、前記のように注入されるモルタルmが下端の隙間から漏出するようなこともない。   Since the injected mortar m has high fluidity, as shown in FIGS. 1 to 5, the mortar m is sufficiently distributed even in a narrow space. However, a filler (sealing material) is provided between adjacent tile panels 1 and 1. ) And the leakage prevention plate 7 is disposed on the front side thereof, so that the mortar m does not leak from the space. Further, a rubber packing p that closes the gap between the tile panels 1, 1,... And the wall surface w is disposed below the lower ends of the tile panels 1, 1,. The mortar m is not leaked from the gap at the lower end.

またモルタルmの注入充填の際に、その強い注入圧が、タイルパネル1、1、・・・の背面に掛かっても、前記のように、該タイルパネル1、1、・・・の前面側には、前記膨出防止棒2、2、・・・が配してあるので、該タイルパネル1、1、・・・の膨出は防止される。適切な不陸状態が確実に維持される。   Further, even when the injection pressure of mortar m is applied to the back surface of the tile panel 1, 1,..., As described above, the front side of the tile panel 1, 1,. Is provided with the bulge prevention rods 2, 2,..., So that the tile panels 1, 1,. Appropriate unevenness is reliably maintained.

モルタルmの注入充填後、該モルタルmが硬化した後、前記クランプ手段4、4、・・・を取り外し、前記膨出防止棒2、2、・・・を、前記下部保持手段5の係止板部51の係止穴51h、51h、・・・の対応するそれらから抜き取り、タイルパネル1、1の連結部前面に配した前記漏出防止板7を取り除く。また前記係止補助棒3を手摺りの支柱c、c、・・・の監視員通路k側から除去する。更に前記下部保持手段5を仮固定用のアンカーボルトb2、b2、・・・を抜き取って壁面wの最下部から除去し、同時に、前記ゴムパッキンpもタイルパネル1、1、・・・の最下部内側の部位から除去する。   After the mortar m has been injected and filled, after the mortar m has hardened, the clamping means 4, 4,... Are removed, and the bulging prevention rods 2, 2,. .. Are extracted from the corresponding ones of the locking holes 51h, 51h,... Of the plate portion 51, and the leakage prevention plate 7 disposed on the front surface of the connecting portion of the tile panels 1 and 1 is removed. Further, the auxiliary locking bar 3 is removed from the side of the monitoring staff passage k of the handrail support columns c, c,. Further, the lower holding means 5 is removed from the lowermost part of the wall surface w by removing the anchor bolts b2, b2,... For temporary fixing, and at the same time, the rubber packing p is also attached to the bottom of the tile panels 1, 1,. Remove from the lower inner part.

こうして、この実施例のトンネル内の監視員通路を立ち上げる壁面の補修方法はスピーディに完了することになる。   In this way, the wall surface repairing method for raising the supervisor passage in the tunnel of this embodiment is completed quickly.

本発明のトンネル内の監視員通路を立ち上げる壁面の補修方法は、トンネル内の監視員通路を立ち上げる壁面の補修の分野及びこれに利用する部材の製造業の分野で有効に利用することができる。   The method of repairing a wall surface for raising an observer passage in a tunnel according to the present invention can be effectively used in the field of repairing a wall surface for raising an observer passage in a tunnel and the manufacturing industry of members used therefor. it can.

1 タイルパネル
11 タイル
12 セメントボード(基板)
13a 中間係止金具
13b 中関係止金具
14 リベット部材
15 上下部係止金具
2 膨出防止棒
21 クッション材
22 不陸調整部
3 係止補助棒
4 クランプ手段
41 一方の係止端
41a 一方の係止端の基部
42 他方の係止端
42a 他方の係止端の基部
43 調整ボルト部材
5 下部保持手段
51 係止板部
51h 係止穴
52 取付板部
52h 横長の取付穴
6 連結補強部材
61 連結板部
61ha 幅の広い横長の結合穴
61hb 幅の狭い横長の結合穴
62 延長板部
63 絡み片
7 漏出防止板
b1 アンカーボルト
b2 仮止め用アンカーボルト
b3 長ボルト
bn ボルト・ナット
c 手摺りの支柱
m モルタル
p ゴムパッキン
s 壁面とタイルパネルとの隙間の間隔
t 既存のタイル
w 壁面
1 tile panel 11 tile 12 cement board (substrate)
13a Intermediate locking bracket 13b Middle relational locking bracket 14 Rivet member 15 Upper / lower locking bracket 2 Swelling prevention bar 21 Cushion material 22 Uneven adjustment part 3 Locking auxiliary bar 4 Clamping means 41 One locking end 41a One engagement Stop base 42 The other locking end 42a The other locking end base 43 Adjusting bolt member 5 Lower holding means 51 Locking plate 51h Locking hole 52 Mounting plate 52h Horizontal mounting hole 6 Connection reinforcement member 61 Connection Plate portion 61ha Wide and wide joint hole 61hb Narrow and wide joint hole 62 Extension plate portion 63 Entanglement piece 7 Leakage prevention plate b1 Anchor bolt b2 Anchor bolt for temporary fixing b3 Long bolt bn Bolt / nut c Handrail support m Mortar p Rubber packing s Spacing between wall and tile panel t Existing tile w Wall

本発明の2は、本発明の1のトンネル内の監視員通路を立ち上げる壁面の補修方法において、前記上部保持手段を、前記監視員通路の路面側に配してある手摺りの支柱に路面と反対側から当接させて路面と平行に配した係止補助棒と、一方の係止端を該係止補助棒側に、他方の係止端を前記膨出防止棒の上部側に、それぞれ係止して、該両係止端で該膨出防止棒と該係止補助棒側とを挟持保持するように配するクランプ手段とで構成し、前記下部保持手段を、前記タイルパネルの下端直下から前方に延びる係止板部であって、複数の係止穴が該タイルパネルの面方向と平行な方向に連設開口してあり、該係止穴が、前記膨出防止棒の、不陸を調節してある前記タイルパネルの前面に当接状態に配するために下方に向かって該タイルパネル側に向かって斜めにカットした形状の下部を挿入可能であるように構成したものである係止板部と、該係止板部の内端から垂下する、前記壁面へ取り付けるための取付板部とで構成したものである。
According to a second aspect of the present invention, in the method for repairing a wall surface of the tunnel according to the first aspect of the present invention, the upper holding means is attached to a handrail column disposed on the road surface side of the supervisor passage. A locking auxiliary rod that is in contact with the opposite side of the road and arranged parallel to the road surface, one locking end on the locking auxiliary rod side, and the other locking end on the upper side of the bulging prevention rod, Clamping means arranged so as to be respectively held so as to sandwich and hold the bulging prevention bar and the side of the auxiliary locking bar at both locking ends, and the lower holding means is formed on the tile panel. A locking plate portion extending forward from directly below the lower end, wherein a plurality of locking holes are continuously opened in a direction parallel to the surface direction of the tile panel, and the locking holes are formed on the bulge preventing rod. , to the tile panel side downward to arrange the abutment on the front of the tile panel which had been adjusted to uneven surface Constituted by a locking plate portion is obtained by configured to be inserted at the bottom of the shape cut into selfish obliquely, a mounting plate portion for hanging from the inner end of the locking plate attached to the wall surface It is a thing.

Claims (5)

トンネル内の監視員通路を立ち上げる路面に面するタイル貼り壁面の損傷を生じた部位又はそのおそれの生じた部位をそのままで又は剥離除去した上で、該壁面の前面側に所定間隔をあけて複数枚の型枠兼用のタイルパネルを配置し、次いで、該壁面と該各タイルパネルとの間に高流動性かつ無収縮性のモルタルを注入充填して補修する、トンネル内の監視員通路立ち上げ壁面の補修方法であって、
前記各タイルパネルを、前記壁面に取り付けたアンカーボルトで不陸を調整しつつ該壁面から所定の間隔を空けて取り付け、更に前記各タイルパネルの前面側に、前記モルタルの注入充填時にその注入圧力で該タイルパネルが外方に膨出するのを防止すべく、これを抑える縦向きの複数の膨出防止棒を設置し、かつ該膨出防止棒の上部は監視員通路の手摺りの支柱に配した上部保持手段で外方に移動するのを防止すべく保持し、該膨出防止棒の下部は該各タイルパネルの下方で前記壁面に仮固定した下部保持手段で外方に移動するのを防止すべく保持することとしたトンネル内の監視員通路を立ち上げる壁面の補修方法。
The damaged part of the tiled wall facing the road surface where the observer passage in the tunnel is raised or the part where the risk has occurred may be left as it is or after peeling and removed, with a predetermined interval on the front side of the wall. A plurality of tile panels that are also used as formwork are placed, and then a high-flow and non-shrinkable mortar is injected and filled between the wall surface and each tile panel for repairing, and an observer's passage in the tunnel is installed. A method of repairing a raised wall,
Each tile panel is attached at a predetermined interval from the wall surface while adjusting the unevenness with anchor bolts attached to the wall surface, and further, the injection pressure at the time of pouring and filling the mortar on the front surface side of each tile panel. In order to prevent the tile panel from bulging outward, a plurality of vertical bulge prevention rods for restraining the tile panel are installed, and the upper portion of the bulge prevention rod is a handrail support column of the supervisor passage The upper holding means arranged on the upper side is held to prevent outward movement, and the lower part of the bulging prevention bar is moved downward by the lower holding means temporarily fixed to the wall surface below each tile panel. A method of repairing the wall that raises the observer passage in the tunnel that is to be held to prevent this.
前記上部保持手段を、前記監視員通路の路面側に配してある手摺りの支柱に路面と反対側から当接させて路面と平行に配した係止補助棒と、一方の係止端を該係止補助棒側に、他方の係止端を前記膨出防止棒の上部側に、それぞれ係止して、該両係止端で該膨出防止棒と該係止補助棒側とを挟持保持するように配するクランプ手段とで構成し、
前記下部保持手段を、前記タイルパネルの下端直下から前方に延びる係止板部であって、複数の係止穴が該タイルパネルの面方向と平行な方向に連設開口してあり、該係止穴が、前記膨出防止棒の下部の、下方に向かって該タイルパネル側に向かって斜めにカットした形状の不陸調整部を挿入可能であるように構成したものである係止板部と、該係止板部の内端から垂下する、前記壁面へ取り付けるための取付板部とで構成したものである請求項1のトンネル内の監視員通路を立ち上げる壁面の補修方法。
The upper holding means is brought into contact with a handrail support post arranged on the road surface side of the supervisor passage from the opposite side of the road surface, and a locking auxiliary bar arranged parallel to the road surface, and one locking end. The other locking end is locked to the upper side of the bulging prevention rod on the side of the locking auxiliary rod, and the bulging prevention rod and the side of the locking auxiliary rod are connected to both the locking ends. It consists of clamping means arranged to hold and hold,
The lower holding means is a locking plate portion extending forward from directly below the lower end of the tile panel, and a plurality of locking holes are continuously opened in a direction parallel to the surface direction of the tile panel. A locking plate portion configured such that a blind hole can be inserted into the bottom portion of the bulging prevention rod, which is shaped to be obliquely cut toward the tile panel toward the bottom. 2. A method for repairing a wall surface for raising an observer passage in a tunnel according to claim 1, wherein the repair plate portion is suspended from an inner end of the locking plate portion and attached to the wall surface.
隣接する両側のタイルパネルの背面に当接する連結板部であって、その両側の部位にそれぞれ連結穴を開口した連結板部と、該連結板部の下端から後方に延長する延長板部と、該延長板部の後端から垂下する絡み片とで連結補強部材を構成し、
前記隣接する両側のタイルパネルの背面に該連結補強部材の連結板部の両側部をそれぞれ当接させ、かつ前記各連結穴を通じて該各タイルパネルに形成してある連結穴に挿入したボルト・ナットで両者を連結すると共に、その後に、該タイルパネルと壁面との間に注入充填されるモルタルに前記絡み片を絡み埋設させるように構成した請求項1又は2のトンネル内の監視員通路を立ち上げる壁面の補修方法。
It is a connecting plate part that contacts the back of the tile panels on both sides adjacent to each other, a connecting plate part that opens a connecting hole in each side part thereof, an extension plate part that extends rearward from the lower end of the connecting plate part, A connecting reinforcing member is constituted by an entangled piece hanging from the rear end of the extension plate part,
Bolts and nuts inserted into connecting holes formed in the tile panels through the connecting holes, with both side portions of the connecting plate portion of the connecting reinforcing member being in contact with the back surfaces of the adjacent tile panels on both sides. And connecting the two at the same time, and then setting up an observer passage in the tunnel according to claim 1 or 2, wherein the entanglement piece is entangled and embedded in a mortar poured and filled between the tile panel and the wall surface. How to repair the wall to be raised.
隣接する両側のタイルパネルの間に、前記壁面と該タイルパネルとの間へのモルタルの注入に先立って充填剤を充填し、かつ該隣接するタイルパネルの前面側に、該隣接するタイルパネルの間から前記壁面とタイルパネルとの間に注入されるモルタルが漏出することとなるのを防止するために、漏出防止板を配することとした請求項1、2又は3のトンネル内の監視員通路を立ち上げる壁面の補修方法。   Between adjacent tile panels, a filler is filled prior to the injection of mortar between the wall surface and the tile panel, and on the front side of the adjacent tile panel, The guard in the tunnel according to claim 1, 2 or 3, wherein a leakage prevention plate is arranged to prevent leakage of mortar injected between the wall surface and the tile panel. How to repair the wall that raises the passage. 前記膨出防止棒を、前記隣接する二つのタイルパネルの連結部を含む前面側に配する前記漏出防止板の前面側に当接させ、該膨出防止棒を該漏出防止板を介して該タイルパネルの膨出防止のために作用させるようにすることで、該膨出防止棒に、該漏出防止板のタイルパネルへの圧接とタイルパネルの膨出防止作用とを兼用させることとした請求項4のトンネル内の監視員通路を立ち上げる壁面の補修方法。   The bulge prevention rod is brought into contact with the front side of the leakage prevention plate disposed on the front side including the connecting portion of the two adjacent tile panels, and the bulge prevention rod is interposed through the leakage prevention plate. By making it act to prevent the tile panel from bulging, the bulge-preventing rod is used to combine the pressure-contact of the leak-proof plate to the tile panel and the tile panel bulge-preventing action. Repair method of the wall which raises the observer passage in the tunnel of item 4.
JP2015022796A 2015-02-09 2015-02-09 How to repair the wall that raises the observer passage in the tunnel Active JP5761701B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2015022796A JP5761701B1 (en) 2015-02-09 2015-02-09 How to repair the wall that raises the observer passage in the tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2015022796A JP5761701B1 (en) 2015-02-09 2015-02-09 How to repair the wall that raises the observer passage in the tunnel

Publications (2)

Publication Number Publication Date
JP5761701B1 JP5761701B1 (en) 2015-08-12
JP2016145483A true JP2016145483A (en) 2016-08-12

Family

ID=53887756

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015022796A Active JP5761701B1 (en) 2015-02-09 2015-02-09 How to repair the wall that raises the observer passage in the tunnel

Country Status (1)

Country Link
JP (1) JP5761701B1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6904937B2 (en) * 2018-10-09 2021-07-21 西日本高速道路エンジニアリング中国株式会社 How to repair the reinforced concrete vertical wall of the tunnel guard passage

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0791048A (en) * 1993-09-20 1995-04-04 Shimizu Corp System form
JP2011252354A (en) * 2010-06-03 2011-12-15 Okasan Co Ltd Form structure and construction method using the same structure
JP2012144869A (en) * 2011-01-07 2012-08-02 Kcon Kk Tile wall repair method of damaged vertical wall of tunnel monitor passage
JP2013032620A (en) * 2011-08-01 2013-02-14 Kfc Ltd Wall structure and construction method of the same
JP2014148825A (en) * 2013-02-01 2014-08-21 Central Nippon Expressway Co Ltd Wall structure in road tunnel and construction method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0791048A (en) * 1993-09-20 1995-04-04 Shimizu Corp System form
JP2011252354A (en) * 2010-06-03 2011-12-15 Okasan Co Ltd Form structure and construction method using the same structure
JP2012144869A (en) * 2011-01-07 2012-08-02 Kcon Kk Tile wall repair method of damaged vertical wall of tunnel monitor passage
JP2013032620A (en) * 2011-08-01 2013-02-14 Kfc Ltd Wall structure and construction method of the same
JP2014148825A (en) * 2013-02-01 2014-08-21 Central Nippon Expressway Co Ltd Wall structure in road tunnel and construction method thereof

Also Published As

Publication number Publication date
JP5761701B1 (en) 2015-08-12

Similar Documents

Publication Publication Date Title
JP6908988B2 (en) How to build a connected structure of precast structural member and time-curing material
JP6845501B2 (en) Vertical member installation structure, vertical member installation method, and precast vertical member
WO2004065694A1 (en) System for transferring loads between cast-in-place slabs
JP5688937B2 (en) Repair panel
JP4448066B2 (en) Flexible waterproof joint and its construction method
KR102070026B1 (en) Construction method of inspection passage for bridge
KR101598275B1 (en) Method of construction of line type supports at large section tunnel having low flat rate
JP5761701B1 (en) How to repair the wall that raises the observer passage in the tunnel
JP2008038426A (en) Flexible water stop joint and its construction method
JP5907447B1 (en) Steel column base
HRP20230322T1 (en) Anchoring element and method for mounting an anchor rail in a construction element made of concrete
JP2003328381A (en) Flexible rubber joint and its mounting structure and its constructing method
KR101624864B1 (en) An up-and-down joint construction device for concrete Structure
JP6473670B2 (en) Structural restoration method
WO2008136690A1 (en) Armour joint assembly support apparatus
JP4079435B2 (en) Construction method of PC inclined formwork and dam body for dam construction
JP6057325B2 (en) Repair structure and repair method for existing waterways
JP5455943B2 (en) Foundation structure of movable home fence device and foundation construction method of movable home fence device
JP5166134B2 (en) Installation structure of ultra-high-strength fiber reinforced concrete plates in concrete structures
JP2002213194A (en) Method for reinforcing/repairing lining concrete
JPH09278354A (en) Fastener of crane rail and laying construction method
JP5034980B2 (en) Building construction method and formwork with joint members
JP6904937B2 (en) How to repair the reinforced concrete vertical wall of the tunnel guard passage
JP2003321913A (en) Method for repairing handrail and attachment device for new handrail
JP3188848U7 (en)

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20150519

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20150602

R150 Certificate of patent or registration of utility model

Ref document number: 5761701

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250