JP4040901B2 - Three-dimensional intersection construction method and three-dimensional intersection - Google Patents

Three-dimensional intersection construction method and three-dimensional intersection Download PDF

Info

Publication number
JP4040901B2
JP4040901B2 JP2002123444A JP2002123444A JP4040901B2 JP 4040901 B2 JP4040901 B2 JP 4040901B2 JP 2002123444 A JP2002123444 A JP 2002123444A JP 2002123444 A JP2002123444 A JP 2002123444A JP 4040901 B2 JP4040901 B2 JP 4040901B2
Authority
JP
Japan
Prior art keywords
pier
girder
dimensional intersection
construction method
foundation hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2002123444A
Other languages
Japanese (ja)
Other versions
JP2003313813A (en
Inventor
信行 松井
正 吉川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2002123444A priority Critical patent/JP4040901B2/en
Publication of JP2003313813A publication Critical patent/JP2003313813A/en
Application granted granted Critical
Publication of JP4040901B2 publication Critical patent/JP4040901B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Description

【0001】
【発明の属する技術分野】
本発明は、立体交差施工方法および立体交差に関するものである。
【0002】
【従来の技術】
従来、都市部における道路の平面交差は、交通渋滞の大きな原因となっている。交差部の通過交通と右折左折交通を立体化することにより、通過交通を減速あるいは停止させることなく通過させることが可能となる。都市部の幹線においては、これら立体交差をアンダーパスあるいはオーバーパスのどちらかの方法で施工している。
【0003】
従来、オーバーパスの方法で立体交差を施工するには、(1)交通を遮断して施工ヤードとし、その場所で杭あるいはケーソンなどの基礎を構築した後、橋脚・桁を構築する方法がある。また、最近では、(2)道路上に架台を構築し、そこから橋脚・基礎を構築する方法や、ブロック状のプレキャスト函体を組み立てる急速施工法などが提案されている。
【0004】
【発明が解決しようとする課題】
しかしながら、(1)の方法では、施工開始から完成までに、数年の期間を要する。数年の施工期間中、車線規制によって交通を阻害するため、さらなる交通渋滞が発生する。(2)の方法では、道路上での架台の組み立て・撤去の期間が必要となる。
【0005】
本発明は、このような問題に鑑みてなされたもので、その目的とするところは、基礎工事と桁製作を同時に行うことで工期を短縮できる立体交差施工方法、立体交差および橋脚構造を提供することにある。
【0006】
【課題を解決するための手段】
前述した目的を達成するための第1の発明は、移動架台上で桁を作製する工程(a)と、基礎孔に、前記基礎孔の開口部に設けられた支持手段と、前記支持手段に固定された昇降手段と、前記昇降手段に保持されて前記基礎孔内に吊り下げられた吊り治具とを取り付け、1ロット構築するごとに前記昇降手段を用いて前記吊り治具を下降させつつ前記吊り治具上に下部から順にロットごとに橋脚を構築することにより、前記基礎孔内に前記橋脚を建て込工程(b)と、前記移動架台を移動させ、前記橋脚の上方に前記桁を配置する工程(c)と、前記橋脚を前記基礎孔から上昇させ、前記橋脚で前記桁を支持させる工程(d)と、を具備することを特徴とする立体交差施工方法である。
【0007】
工程(a)では、交通の遮断を最小限とできる位置に配置した移動架台上で桁を作製する。工程(b)では、橋脚計画位置に形成された基礎孔内に昇降ジャッキを有する吊り治具を挿入し、昇降ジャッキで前記吊り治具を下降させつつ、吊り治具上に橋脚を構築する。吊り治具は、例えば、複数の吊りロッドの下端部に平板状の接続フレームを固定したものであり、各吊りロッドに昇降ジャッキが設けられる。完成後の橋脚は、基礎孔内に吊下げられた状態となる。
【0008】
工程(c)では、移動架台を用いて、基礎孔内に建て込まれた橋脚の上方に桁を配置する。移動架台は、例えば、架台の下端部にウォータキャスタやエアキャスタを設けたものである。工程(d)では、昇降ジャッキを用いて、橋脚を上載した吊り治具を上昇させ、橋脚に桁を支持させる。
【0009】
第1の発明では、移動架台上で桁を作製し、基礎孔内に橋脚を建て込んで構築した後、移動架台を移動させて橋脚の上方に桁を配置する。そして、橋脚を基礎孔から上昇させ、橋脚で桁を支持させる。
【0010】
第2の発明は、第1の発明の立体交差施工方法で施工されたことを特徴とする立体交差である。
【0012】
基礎孔は、橋脚計画位置の下方の地盤に掘削される。支持手段は、例えば、筒状の支持枠と、支持枠上部に設けられた支持ブラケット等である。支持手段は、昇降手段と吊り治具を介して、橋脚や橋脚上に架設される桁等の重量を支持する。昇降手段には、昇降ジャッキ等を用いる。昇降ジャッキは、支持部材である支持ブラケット等に固定される。吊り治具は、例えば、昇降ジャッキに保持された複数の吊りロッドと、吊りロッドの下端部に設けられたピア接続フレームから成る。橋脚は、ピア接続フレーム上に作製される。昇降ジャッキを用いて、吊り治具を基礎孔内部で昇降させることで、吊り治具上に構築された橋脚が基礎孔から出し入れされる。
【0014】
【発明の実施の形態】
以下、図面に基づいて、本発明の実施例を詳細に説明する。図1は、立体交差道路1の立面図を示す。図1に示すように、立体交差道路1は、中央部桁7、斜路部桁9a、斜路部桁9b、橋脚27、橋脚33等で構成される。
【0015】
図2は、移動架台11上で中央部桁7を形成する工程を示す図である。立体交差道路1を構築するには、まず、路面3の下方の地盤5に適切な基礎工事を施し、橋脚27、橋脚33の計画位置の下方に円筒状の基礎孔15を形成する。また、斜路部桁9aの計画位置の路面3上に移動架台11を設置する。
【0016】
移動架台11は、中央部桁7や斜路部桁9aの製作時には桁製作架台として、移動時には移動架台として使用される。移動架台11は、下部にウォータキャスタ13を有し、中央部桁7や斜路部桁9aを支持できる構造とする。移動時には、ウォータキャスタ13に作動媒体を注入しつつ、タイヤショベルあるいはウインチ等(図示せず)で移動架台11を牽引する。
【0017】
図3、図4は、基礎孔15の断面の立面図である。図3、図4は、図2のA−Aによる断面図を示す。図2に示すように、移動架台11を作業ヤードとして中央部桁7を形成すると同時に、図3、図4に示すように、基礎孔15内部に橋脚27、橋脚33を構築する。
【0018】
基礎孔15内部に橋脚27、橋脚33を構築するには、図3に示すように、まず、基礎孔15の覆工セグメント17の頂部上に、覆工セグメント17より大きな径を有する筒状の支持枠19を取り付ける。支持枠19の下端面の開口部の径は、覆工セグメント17の内径と同じである。支持枠19の上端部には、2つの支持ブラケット21を固定する。支持ブラケット21は、例えば、長方形の枠状の本体20に三角形状の支持部材22が設けられる。支持部材22は、本体20の地盤5と面する側の下部に設けられ、支持部材22のうち水平部材は支持枠19に固定される。
【0019】
2つの支持ブラケット21の本体20には、それぞれ2つの昇降ジャッキ25が固定される。4つの昇降ジャッキ25は、それぞれピア吊りロッド23を保持し、昇降させる。ピア吊りロッド23の下端部には、平板状のピア接続フレーム29が固定される。支持枠19は、支持部材22やピア吊りロッド23等を介して、橋脚27または橋脚33と、架設される桁の重量を支持する。
【0020】
次に、ピア接続フレーム29上に橋脚27、橋脚33を構築する。橋脚27(33)は、下部から順にロットごとに構築される。図3、図4に示すように、橋脚27(33)の下部を構築する際には、1ロット構築するごとに昇降ジャッキ25を用いてピア吊りロッド23、ピア接続フレーム29、橋脚27(33)を下降させる。
【0021】
図5はピアサドル部31を設置した状態の橋脚27、橋脚33の断面図を示す。基礎孔15内部に橋脚27(33)を建て込んで構築した後、図5に示すように、橋脚27(33)の上端にピアサドル部31を固定する。橋脚27(33)は、ピアサドル31固定時に、ピアサドル31の上端が路面3と同じレベルになるようにする。
【0022】
図6は、中央部桁7を橋脚27上に配置する工程を示す図である。ピアサドル部31の設置後、移動架台11を用いて中央部桁7を橋脚27の上方へ移動させ、図6に示す状態とする。前述したように、移動時には、ウォータキャスタ13に作動媒体を注入しつつ、タイヤショベルあるいはウインチ等(図示せず)で移動架台11を牽引する。
【0023】
図7は移動時の移動架台11の断面の概略図を示す。移動架台11は、架台12と、ウォータキャスタ13で構成される。ウォータキャスタ13は、作動媒体の注入管45を有する本体37と、本体37の下部に設けられた複数のキャスタバック41からなる。キャスタバック41は、本体37からの作業媒体の注入口39と、開口部43を有する。
【0024】
本体37の注入管45に、矢印Bに示すように水を注入すると、キャスタバック41が水で膨張する。同時に、キャスタバック41の開口部43から、矢印Cに示すように水が流出し、隣接するキャスタバック41の間の圧力室35に水が満たされる。圧力室35内部の水圧が、移動架台11および中央部桁7の荷重を持ち上げられる状態に達すると、矢印Dに示すように、水が路面1とキャスタバック41との間から均等に逃げていき、移動架台11は路面1から浮いた状態となる。移動架台11は、路面1とキャスタバック41との間に22mm以上程度の空間を確保した状態で牽引される。
【0025】
このとき、例えば、中央部桁7の重量が1200t、移動架台11の重量が100tの場合、移動時の設置圧は約5t/mとなる。このように、ウォータキャスタ13を有する移動架台11により桁を移動させると、荷重の分散が図れ、路面3を特別に養生する必要がなくなる。
【0026】
移動架台11を、橋脚27を建て込み構築した基礎孔15の間に配置し、本体37への注水を停止すると、キャスタバック41は路面1に接地する。
【0027】
図8は、ピアサドル部31上に中央部桁7を仮置きした状態の橋脚27の断面図、図9は、中央部桁7を正規の設置高さまで上昇させる工程を示す図である。図5に示すピアサドル部31の上方に中央部桁7を配置した後、昇降ジャッキ25を用いてピア吊りロッド23を上昇させ、図8に示すように、ピアサドル部31の上端に中央部桁7を仮置きする。そして、図9に示すように、ピアサドル部31に上載した中央部桁7が正規の設置高さに達するまで、ピア吊りロッド23をさらに上昇させる。
【0028】
移動架台11から橋脚27への中央部桁7の荷重の受けかえが完了した後、移動架台11を斜路部桁9aの設置予定位置まで移動させる。
【0029】
図10は、移動架台11上で斜路部桁9aを形成する工程を示す図である。図10に示すように、中央部桁7を正規の設置高さに保持し、矢印E方向の交通を確保した状態で、移動架台11上に斜路部桁9aを形成する。斜路部桁9aの完成後、昇降ジャッキ25を用いてピア吊りロッド23を下降させ、橋脚27を、再度基礎孔15の内部に吊下げる。
【0030】
図11は、基礎孔15内に橋脚27を吊下げた状態の断面立面図である。図11に示すように、橋脚27とピアサドル部31は、基礎孔15内部に配置され、橋脚27に固定されたピアサドル31上には中央部桁7が上載される。また、橋脚33を建て込み構築した基礎孔15でも、橋脚33とピアサドル部31とが基礎孔15内部に配置されている。
【0031】
図11に示す位置まで中央部桁7を下降させた後、移動架台11を用いて斜路部桁9aの位置を調整する。斜路部桁9aは、図11に示すように、橋脚27のピアサドル部31と橋脚33のピアサドル部31の上方に配置される。
【0032】
図12は、中央部桁7および斜路部桁9aを上昇させる工程を示す図である。図11に示す状態から、図8に示す要領で、昇降ジャッキ25を用いてピア吊りロッド23を吊上げ、橋脚27、橋脚33を上昇させる。斜路部桁9aの荷重を移動架台11から橋脚27と橋脚33に受けかえた後、さらに、橋脚27、橋脚33をそれぞれ所定の位置まで上昇させ、中央部桁7および斜路部桁9aを架設する。
【0033】
なお、斜路部桁9bは、他の固定架台等を用いて設置予定位置の路面3上に斜路部桁9aと並行して形成しておき、中央部桁7および斜路部桁9aと同時に架設する。立体交差道路1のその他の部分は、斜路部桁9a、9bや中央部桁7の製作や架設と並行して構築しておく。
【0034】
移動架台11や、斜路部桁9bの作製に使用した固定架台等は、適切な時期に撤去する。また、橋脚27、橋脚33を路面3上に設置した後、基礎孔15にコンクリートを打設する。なお、支持ブラケット21、ピア吊りロッド23等は適宜撤去する。最後に、橋面工や仕上げ工を施し、立体交差道路1を完成する。
【0035】
このように、本実施の形態では、基礎孔15の内部に橋脚27、橋脚33を建て込んで構築しつつ、移動架台11上で中央部桁7を形成する。基礎や橋脚の施工と桁製作を同時に行うことで、工期を短縮できる。
【0036】
また、移動架台11を用いて中央部桁7を橋脚27の上方へ移動させた後、昇降ジャッキ25を用いて、基礎孔15の内部に立て込んだ橋脚27を吊上げる。そして、中央部桁7を橋脚27上に仮設置した状態で、斜路部桁9aを形成する。橋脚27、橋脚33を繰り返し昇降可能な構造とし、作業ヤードで形成された中央部桁7を上昇させた橋脚27上に仮置きすることで、中央部桁7の下方の通行止め期間を大幅に短縮できる。
【0037】
なお、本実施の形態では、中央部桁7と並行して橋脚27と橋脚33を構築したが、橋脚33の構築時期はこれに限らず、中央部桁7と斜路部桁9a、9bの架設までに構築が完了すればよい。また、中央部桁7や斜路部桁9aを形成する際の移動架台11の配置位置は、斜路部桁9aの計画位置の路面3上に限らない。立体交差道路1を構成する桁や橋脚等の部材数は、図1に示す限りではない。
さらに、移動架台11のウォータキャスタ13のかわりにエアキャスタを用いても良い。この場合、作動媒体として水のかわりに気体を用いる。
【0038】
【発明の効果】
以上、詳細に説明したように、本発明によれば、基礎工事と桁製作を同時に行うことで工期を短縮できる立体交差施工方法、立体交差および橋脚構造を提供できる。
【図面の簡単な説明】
【図1】立体交差道路1の立面図
【図2】移動架台11上で中央部桁7を形成する工程を示す図
【図3】基礎孔15の断面の立面図
【図4】基礎孔15の断面の立面図
【図5】ピアサドル部31を設置した状態の橋脚27の断面図
【図6】中央部桁7を橋脚27上に配置する工程を示す図
【図7】移動時の移動架台11の断面の概略図
【図8】ピアサドル部31上に中央部桁7を仮置きした状態の橋脚27の断面図
【図9】中央部桁7を正規の設置高さまで上昇させる工程を示す図
【図10】移動架台11上で斜路部桁9aを形成する工程を示す図
【図11】基礎孔15内に橋脚27を吊下げた状態の断面立面図
【図12】中央部桁7および斜路部桁9aを上昇させる工程を示す図
【符号の説明】
1………立体交差道路
7………中央部桁
9a、9b………斜路部桁
11………移動架台
13………ウォータキャスタ
15………基礎孔
19………支持枠
21………支持ブラケット
23………ピア吊りロッド
25………昇降ジャッキ
27、33………橋脚
29………ピア接続フレーム
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a three-dimensional intersection construction method and a three-dimensional intersection.
[0002]
[Prior art]
Conventionally, road intersections in urban areas have been a major cause of traffic congestion. By making the passing traffic at the intersection and the right turn and left turn traffic three-dimensional, it is possible to pass the passing traffic without decelerating or stopping. On urban trunk lines, these three-dimensional intersections are constructed by either underpass or overpass methods.
[0003]
Conventionally, in order to construct a three-dimensional intersection with the overpass method, (1) there is a method of building a pier / girder after building a foundation such as a pile or a caisson at that place by blocking the traffic into a construction yard. . Recently, (2) a method of constructing a pedestal on a road and constructing piers / foundations therefrom, and a rapid construction method of assembling a block-shaped precast box have been proposed.
[0004]
[Problems to be solved by the invention]
However, in the method (1), a period of several years is required from the start of construction to completion. During the construction period of several years, traffic congestion will occur due to lane restrictions, resulting in further traffic congestion. The method (2) requires a period for assembling / removing the gantry on the road.
[0005]
The present invention has been made in view of such problems, and its object is to provide a three-dimensional intersection construction method, a three-dimensional intersection, and a pier structure that can shorten the work period by simultaneously performing foundation work and girder production. There is.
[0006]
[Means for Solving the Problems]
According to a first aspect of the invention for achieving the above object, a step (a) for producing a girder on a movable gantry, a supporting means provided in the opening of the foundation hole in the foundation hole, A fixed elevating means and a hanging jig held by the elevating means and suspended in the foundation hole are attached, and the lifting jig is lowered using the elevating means every time one lot is constructed. by building piers for each lot in order from the bottom on the lifting jig, the underlying hole in the pier a built write no step (b), moving the moving platform, the digit above the pier A step (c) for placing the bridge pier and the step (d) for raising the bridge pier from the foundation hole and supporting the girder with the bridge pier.
[0007]
In the step (a), a girder is produced on a movable gantry arranged at a position where traffic can be interrupted to the minimum. In the step (b), a suspension jig having a lifting jack is inserted into the foundation hole formed at the planned position of the pier, and the pier is constructed on the suspension jig while the suspension jig is lowered by the lifting jack. The hanging jig is, for example, a plate-like connection frame fixed to the lower ends of a plurality of hanging rods, and a lifting jack is provided on each hanging rod. The completed pier is suspended in the foundation hole.
[0008]
In the step (c), a girder is arranged above the pier built in the foundation hole using a movable frame. For example, the movable gantry is provided with a water caster or an air caster at the lower end of the gantry. In the step (d), the lifting jig on which the pier is mounted is lifted by using a lifting jack, and the girder is supported on the pier.
[0009]
In the first invention, a girder is produced on a movable gantry, and a pier is built in a foundation hole, and then the girder is arranged above the pier by moving the movable gantry. Then, the pier is raised from the foundation hole and the girder is supported by the pier.
[0010]
The second invention is a three-dimensional intersection characterized by being constructed by the three-dimensional intersection construction method of the first invention.
[0012]
The foundation hole is excavated in the ground below the planned pier position. The support means is, for example, a cylindrical support frame and a support bracket provided on the upper part of the support frame. The supporting means supports the weight of a bridge pier or a girder laid on the pier via the lifting means and the hanging jig. A lifting jack or the like is used as the lifting means. The lifting jack is fixed to a support bracket or the like that is a support member. The hanging jig includes, for example, a plurality of hanging rods held by a lifting jack and a peer connection frame provided at the lower end of the hanging rod. The pier is made on the peer connection frame. By using a lifting jack, the suspension jig is moved up and down inside the foundation hole, so that the pier constructed on the suspension jig is taken in and out of the foundation hole.
[0014]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. FIG. 1 shows an elevation view of a three-dimensional intersection road 1. As shown in FIG. 1, the three-dimensional intersection road 1 is composed of a central girder 7, a ramp girder 9a, a ramp girder 9b, a pier 27, a pier 33, and the like.
[0015]
FIG. 2 is a diagram illustrating a process of forming the central beam 7 on the movable gantry 11. In order to construct the three-dimensional intersection road 1, first, appropriate foundation work is performed on the ground 5 below the road surface 3, and the cylindrical foundation hole 15 is formed below the planned positions of the pier 27 and the pier 33. Moreover, the movable mount 11 is installed on the road surface 3 of the planned position of the ramp part girder 9a.
[0016]
The moving gantry 11 is used as a girder manufacturing frame when the central beam 7 and the ramp girder 9a are manufactured, and as a moving frame when moving. The movable gantry 11 has a water caster 13 at the lower part, and has a structure that can support the central part girder 7 and the ramp part girder 9a. At the time of movement, the movable base 11 is pulled by a tire shovel or winch (not shown) while injecting a working medium into the water caster 13.
[0017]
3 and 4 are elevational views of the cross section of the basic hole 15. 3 and 4 are cross-sectional views taken along line AA in FIG. As shown in FIG. 2, the central girder 7 is formed by using the movable gantry 11 as a work yard, and at the same time, as shown in FIGS. 3 and 4, the pier 27 and the pier 33 are built inside the foundation hole 15.
[0018]
In order to construct the pier 27 and the pier 33 in the foundation hole 15, as shown in FIG. 3, first, on the top of the lining segment 17 of the foundation hole 15, a cylindrical shape having a larger diameter than the lining segment 17. A support frame 19 is attached. The diameter of the opening at the lower end surface of the support frame 19 is the same as the inner diameter of the lining segment 17. Two support brackets 21 are fixed to the upper end portion of the support frame 19. For example, the support bracket 21 is provided with a triangular support member 22 on a rectangular frame-shaped main body 20. The support member 22 is provided in the lower part of the main body 20 on the side facing the ground 5, and the horizontal member of the support member 22 is fixed to the support frame 19.
[0019]
Two lifting jacks 25 are fixed to the main bodies 20 of the two support brackets 21, respectively. Each of the four lifting jacks 25 holds and lifts the peer suspension rod 23. A flat peer connection frame 29 is fixed to the lower end of the peer suspension rod 23. The support frame 19 supports the weight of the bridge pier 27 or the pier 33 and the girder installed via the support member 22, the peer suspension rod 23, and the like.
[0020]
Next, the pier 27 and the pier 33 are constructed on the peer connection frame 29. The pier 27 (33) is constructed for each lot in order from the bottom. As shown in FIGS. 3 and 4, when the lower part of the pier 27 (33) is constructed, the pier lifting rod 25 is used to construct the pier 27, the peer connection frame 29, and the pier 27 (33) every time one lot is constructed. ) Is lowered.
[0021]
FIG. 5 is a cross-sectional view of the pier 27 and the pier 33 with the pier saddle portion 31 installed. After the pier 27 (33) is built in the foundation hole 15, the pier saddle portion 31 is fixed to the upper end of the pier 27 (33) as shown in FIG. The pier 27 (33) is configured so that the upper end of the pier saddle 31 is at the same level as the road surface 3 when the pier saddle 31 is fixed.
[0022]
FIG. 6 is a diagram illustrating a process of arranging the central beam 7 on the pier 27. After the installation of the pier saddle 31, the central girder 7 is moved above the pier 27 using the movable gantry 11, and the state shown in FIG. 6 is obtained. As described above, at the time of movement, the movable base 11 is pulled by a tire shovel or winch (not shown) while injecting a working medium into the water caster 13.
[0023]
FIG. 7 shows a schematic diagram of a cross section of the movable mount 11 during movement. The movable gantry 11 includes a gantry 12 and a water caster 13. The water caster 13 includes a main body 37 having a working medium injection pipe 45 and a plurality of caster backs 41 provided at the lower portion of the main body 37. The caster bag 41 has a working medium inlet 39 from the main body 37 and an opening 43.
[0024]
When water is injected into the injection tube 45 of the main body 37 as shown by the arrow B, the caster back 41 expands with water. At the same time, water flows out from the opening 43 of the caster back 41 as shown by the arrow C, and the pressure chamber 35 between the adjacent caster backs 41 is filled with water. When the water pressure in the pressure chamber 35 reaches a state where the load of the movable frame 11 and the central beam 7 can be lifted, water escapes evenly between the road surface 1 and the caster back 41 as indicated by an arrow D. The mobile gantry 11 is in a state of floating from the road surface 1. The movable gantry 11 is pulled in a state where a space of about 22 mm or more is secured between the road surface 1 and the caster back 41.
[0025]
At this time, for example, when the weight of the central girder 7 is 1200 t and the weight of the movable mount 11 is 100 t, the installation pressure at the time of movement is about 5 t / m 2 . In this way, when the girder is moved by the movable gantry 11 having the water casters 13, the load can be dispersed and the road surface 3 need not be specially cured.
[0026]
When the movable frame 11 is disposed between the foundation holes 15 in which the pier 27 is built and constructed, and the water injection to the main body 37 is stopped, the caster back 41 is grounded to the road surface 1.
[0027]
FIG. 8 is a cross-sectional view of the pier 27 in a state where the central girder 7 is temporarily placed on the pier saddle portion 31, and FIG. 9 is a diagram illustrating a process of raising the central girder 7 to a normal installation height. After the central girder 7 is arranged above the pier saddle portion 31 shown in FIG. 5, the peer suspension rod 23 is raised using the lifting jack 25, and as shown in FIG. 8, the central girder 7 is placed on the upper end of the pier saddle portion 31. Is temporarily placed. And as shown in FIG. 9, the peer suspension rod 23 is further raised until the center part girder 7 mounted on the peer saddle part 31 reaches a regular installation height.
[0028]
After the transfer of the load of the central girder 7 from the movable gantry 11 to the pier 27 is completed, the movable gantry 11 is moved to the planned installation position of the ramp portion girder 9a.
[0029]
FIG. 10 is a diagram illustrating a process of forming the ramp portion beam 9 a on the movable mount 11. As shown in FIG. 10, the slanting portion girder 9 a is formed on the movable frame 11 in a state where the central girder 7 is held at a regular installation height and traffic in the direction of arrow E is secured. After completion of the ramp part girder 9 a, the pier suspension rod 23 is lowered using the lifting jack 25, and the pier 27 is suspended again inside the foundation hole 15.
[0030]
FIG. 11 is a sectional elevational view of a state in which the pier 27 is suspended in the foundation hole 15. As shown in FIG. 11, the pier 27 and the pier saddle portion 31 are arranged inside the foundation hole 15, and the central beam 7 is placed on the pier saddle 31 fixed to the pier 27. Even in the foundation hole 15 in which the pier 33 is built and constructed, the pier 33 and the pier saddle portion 31 are arranged inside the foundation hole 15.
[0031]
After the central beam 7 is lowered to the position shown in FIG. 11, the position of the ramp portion beam 9 a is adjusted using the movable frame 11. As shown in FIG. 11, the ramp portion girder 9 a is disposed above the pier saddle portion 31 of the pier 27 and the pier saddle portion 31 of the pier 33.
[0032]
FIG. 12 is a diagram showing a process of raising the central part girder 7 and the ramp part girder 9a. From the state shown in FIG. 11, the pier suspension rod 23 is lifted using the lifting jack 25 to raise the pier 27 and the pier 33 in the manner shown in FIG. 8. After the load of the ramp part girder 9a is received from the movable gantry 11 to the pier 27 and the pier 33, the pier 27 and the pier 33 are further raised to predetermined positions, respectively, and the central part girder 7 and the ramp part girder 9a are installed. .
[0033]
The ramp portion girder 9b is formed in parallel with the ramp portion girder 9a on the road surface 3 at a planned installation position using another fixed frame or the like, and is installed simultaneously with the central portion girder 7 and the ramp portion girder 9a. . The other parts of the three-dimensional intersection road 1 are constructed in parallel with the production and construction of the ramp part girders 9a, 9b and the central part girder 7.
[0034]
The movable gantry 11 and the fixed gantry used for the production of the ramp portion girder 9b are removed at an appropriate time. Moreover, after installing the pier 27 and the pier 33 on the road surface 3, concrete is placed in the foundation hole 15. In addition, the support bracket 21, the peer suspension rod 23, and the like are removed as appropriate. Finally, bridge work and finishing work are performed to complete the three-dimensional intersection road 1.
[0035]
Thus, in the present embodiment, the central girder 7 is formed on the movable gantry 11 while the pier 27 and the pier 33 are built and constructed inside the foundation hole 15. The construction period can be shortened by carrying out construction of the foundation and piers and girder production at the same time.
[0036]
Moreover, after moving the center part girder 7 upwards of the pier 27 using the movable stand 11, the pier 27 stood in the inside of the foundation hole 15 is lifted using the raising / lowering jack 25. FIG. And the ramp part girder 9a is formed in the state which temporarily installed the center part girder 7 on the pier 27. FIG. The bridge pier 27 and the pier 33 can be repeatedly raised and lowered, and the central girder 7 formed in the work yard is temporarily placed on the raised pier 27, so that the period of time during which the central girder 7 is closed is greatly reduced. it can.
[0037]
In this embodiment, the pier 27 and the pier 33 are constructed in parallel with the central girder 7. However, the construction time of the pier 33 is not limited thereto, and the central girder 7 and the ramp girder 9a, 9b are constructed. The construction should be completed by Moreover, the arrangement position of the movable frame 11 when forming the central part girder 7 and the ramp part girder 9a is not limited to the road surface 3 of the planned position of the ramp part girder 9a. The number of members such as girders and bridge piers constituting the three-dimensional intersection road 1 is not limited to that shown in FIG.
Further, an air caster may be used in place of the water caster 13 of the movable mount 11. In this case, gas is used instead of water as the working medium.
[0038]
【The invention's effect】
As described above in detail, according to the present invention, it is possible to provide a three-dimensional intersection construction method, a three-dimensional intersection, and a pier structure that can shorten the work period by simultaneously performing foundation work and girder production.
[Brief description of the drawings]
FIG. 1 is an elevation view of a three-dimensional crossing road. FIG. 2 is a diagram showing a process of forming a central girder 7 on a moving gantry. FIG. 3 is a sectional elevation view of a foundation hole. Fig. 5 is a sectional view of the pier 27 with the pier saddle portion 31 installed. Fig. 6 is a diagram showing a process of placing the central beam 7 on the pier 27. FIG. 8 is a cross-sectional view of the pier 27 with the central girder 7 temporarily placed on the pier saddle portion 31. FIG. 9 is a step of raising the central girder 7 to a normal installation height. FIG. 10 is a diagram showing a process of forming a ramp portion girder 9a on the movable gantry 11. FIG. 11 is a sectional elevation view of a state in which a pier 27 is suspended in the foundation hole 15. FIG. The figure which shows the process of raising the girder 7 and the ramp part girder 9a
1 ......... Crossover road 7 ......... Center part girder 9a, 9b ......... Ramp part girder 11 ......... Moving frame 13 ......... Water caster 15 ......... Base hole 19 ......... Support frame 21 ... ... Support bracket 23 ... Peer hanging rod 25 ... Elevating jacks 27, 33 ... ... Pier 29 ... ... Peer connection frame

Claims (4)

移動架台上で桁を作製する工程(a)と、
基礎孔に、前記基礎孔の開口部に設けられた支持手段と、前記支持手段に固定された昇降手段と、前記昇降手段に保持されて前記基礎孔内に吊り下げられた吊り治具とを取り付け、1ロット構築するごとに前記昇降手段を用いて前記吊り治具を下降させつつ前記吊り治具上に下部から順にロットごとに橋脚を構築することにより、前記基礎孔内に前記橋脚を建て込む工程(b)と、
前記移動架台を移動させ、前記橋脚の上方に前記桁を配置する工程(c)と、
前記橋脚を前記基礎孔から上昇させ、前記橋脚で前記桁を支持させる工程(d)と、
を具備することを特徴とする立体交差施工方法。
A step (a) of producing a girder on a movable frame;
Supporting means provided at the opening of the base hole in the base hole, lifting means fixed to the supporting means, and a hanging jig held by the lifting means and suspended in the base hole The pier is built in the foundation hole by constructing the pier for each lot in order from the bottom on the suspension jig while lowering the suspension jig using the lifting means every time one lot is constructed. Including step (b),
A step (c) of moving the movable gantry and placing the beam above the pier;
Elevating the pier from the foundation hole and supporting the beam with the pier (d);
A three-dimensional intersection construction method characterized by comprising:
前記工程(d)の後、前記基礎孔にコンクリートを打設する工程(e)をさらに具備することを特徴とする請求項1記載の立体交差施工方法。  The three-dimensional intersection construction method according to claim 1, further comprising a step (e) of placing concrete in the foundation hole after the step (d). 前記工程(d)は、前記昇降手段で前記吊り治具を上昇させることを特徴とする請求項1記載の立体交差施工方法。2. The three-dimensional intersection construction method according to claim 1, wherein the step (d) raises the hanging jig by the lifting means . 請求項1から請求項3のいずれかに記載された立体交差施工方法で施工されたことを特徴とする立体交差。  A three-dimensional intersection constructed by the three-dimensional intersection construction method according to any one of claims 1 to 3.
JP2002123444A 2002-04-25 2002-04-25 Three-dimensional intersection construction method and three-dimensional intersection Expired - Fee Related JP4040901B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002123444A JP4040901B2 (en) 2002-04-25 2002-04-25 Three-dimensional intersection construction method and three-dimensional intersection

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002123444A JP4040901B2 (en) 2002-04-25 2002-04-25 Three-dimensional intersection construction method and three-dimensional intersection

Publications (2)

Publication Number Publication Date
JP2003313813A JP2003313813A (en) 2003-11-06
JP4040901B2 true JP4040901B2 (en) 2008-01-30

Family

ID=29538733

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002123444A Expired - Fee Related JP4040901B2 (en) 2002-04-25 2002-04-25 Three-dimensional intersection construction method and three-dimensional intersection

Country Status (1)

Country Link
JP (1) JP4040901B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103410096A (en) * 2013-08-15 2013-11-27 中铁六局集团天津铁路建设有限公司 Box jacking method for performing correction on deflection end by virtue of jack in oblique crossing jacking process
CN109056438A (en) * 2018-09-06 2018-12-21 上海市机械施工集团有限公司 A kind of construction method of overhead road of city ring road transformation

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4519588B2 (en) * 2004-09-14 2010-08-04 鹿島建設株式会社 Three-dimensional intersection construction method
JP4502388B2 (en) * 2005-02-23 2010-07-14 山九株式会社 Transporting heavy items
JP4916272B2 (en) * 2006-10-19 2012-04-11 片山ストラテック株式会社 PC well and bridge construction method
JP5189431B2 (en) * 2008-08-05 2013-04-24 三井住友建設株式会社 Multi-span continuous concrete bridge
CN102182140A (en) * 2011-04-06 2011-09-14 上海朝田实业有限公司 Hydraulic lifting type overpass
CN104018421B (en) * 2014-05-29 2016-01-13 南京航空航天大学 A kind of one-way spiral bridge
CN106894346B (en) * 2017-04-28 2019-10-11 山西省交通科学研究院 A kind of the continuous beam bridge construction method
CN115075149A (en) * 2022-06-20 2022-09-20 中铁二局集团有限公司 Construction method for erecting large downhill bridge by using guide-beam-free transportation and erection integrated machine

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103410096A (en) * 2013-08-15 2013-11-27 中铁六局集团天津铁路建设有限公司 Box jacking method for performing correction on deflection end by virtue of jack in oblique crossing jacking process
CN103410096B (en) * 2013-08-15 2015-06-03 中铁六局集团天津铁路建设有限公司 Box jacking method for performing correction on deflection end by virtue of jack in oblique crossing jacking process
CN109056438A (en) * 2018-09-06 2018-12-21 上海市机械施工集团有限公司 A kind of construction method of overhead road of city ring road transformation
CN109056438B (en) * 2018-09-06 2021-02-23 上海市机械施工集团有限公司 Construction method for transformation of urban elevated ramp

Also Published As

Publication number Publication date
JP2003313813A (en) 2003-11-06

Similar Documents

Publication Publication Date Title
CN110616809B (en) Construction method of suspended building structure
JP4040901B2 (en) Three-dimensional intersection construction method and three-dimensional intersection
CN104264902B (en) Structure for connecting concrete filled steel tubular column with pile foundation
CN111119059B (en) Ultrahigh composite support system for high-pier cast-in-place box girder and construction method
CN110847177A (en) Fixed verticality adjusting and upward floating preventing device and method with steel pipe supporting column serving as structural column
CN107571392A (en) A kind of beam making bench for the construction of transverse tensioning method prestressing force prefabricated small box girder
JP4040900B2 (en) 3D intersection construction method, 3D intersection and moving platform
CN116254783A (en) High-position girder falling construction method suitable for erecting high-speed railway precast box girders
JP4685341B2 (en) Viaduct construction method
JP2004316100A (en) Construction method for building
CN116677061A (en) Municipal rainwater and sewage inspection well integrated prefabricated installation device and construction method thereof
CN211769949U (en) Movable arm type tower crane underframe ballast type foundation
JP3166899B2 (en) Inner formwork for caisson construction and its lift-up method
CN112342932A (en) Line-crossing low-clearance width-splicing cast-in-place box girder support and construction method
JP3981469B2 (en) Construction method of concrete structure
JP4519588B2 (en) Three-dimensional intersection construction method
JP3852686B2 (en) Three-dimensional intersection construction method and three-dimensional intersection
CN215052637U (en) Concrete reverse-hanging template for high-pile wharf
KR100593203B1 (en) a deck supportframe and a construction methed
TWI741347B (en) Reverse construction method with upside down support and non-dismantling formwork system
JP3660657B2 (en) Construction method of viaduct
CN220035392U (en) Integral hoisting fine-adjustment positioning structure for large-tonnage steel pipe pile support
CN114000525B (en) Construction method of underwater tie beam
JP2004169318A (en) Construction method for bridge pier of viaduct
JPH0711620A (en) Construction method of artificial ground

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050111

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070119

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070417

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070615

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20070807

A521 Written amendment

Effective date: 20070905

Free format text: JAPANESE INTERMEDIATE CODE: A523

A911 Transfer of reconsideration by examiner before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A911

Effective date: 20071011

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20071106

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20071108

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 3

Free format text: PAYMENT UNTIL: 20101116

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees