CN103410096B - Box jacking method for performing correction on deflection end by virtue of jack in oblique crossing jacking process - Google Patents

Box jacking method for performing correction on deflection end by virtue of jack in oblique crossing jacking process Download PDF

Info

Publication number
CN103410096B
CN103410096B CN201310357697.3A CN201310357697A CN103410096B CN 103410096 B CN103410096 B CN 103410096B CN 201310357697 A CN201310357697 A CN 201310357697A CN 103410096 B CN103410096 B CN 103410096B
Authority
CN
China
Prior art keywords
jacking
jack
casing
correction
deflection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310357697.3A
Other languages
Chinese (zh)
Other versions
CN103410096A (en
Inventor
王金海
米万富
刘伟
李强
邢纪伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Sixth Group Co Ltd
Tianjin Railway Construction Co Ltd of China Railway Sixth Group Co Ltd
Original Assignee
China Railway Sixth Group Co Ltd
Tianjin Railway Construction Co Ltd of China Railway Sixth Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Sixth Group Co Ltd, Tianjin Railway Construction Co Ltd of China Railway Sixth Group Co Ltd filed Critical China Railway Sixth Group Co Ltd
Priority to CN201310357697.3A priority Critical patent/CN103410096B/en
Publication of CN103410096A publication Critical patent/CN103410096A/en
Application granted granted Critical
Publication of CN103410096B publication Critical patent/CN103410096B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention discloses a box jacking method for performing correction on a deflection end by virtue of a jack in an oblique crossing jacking process. The method comprises the following steps: arranging a column of guard piles in foundation soil on each of two sides of a box to be jacked along the jacking path on two sides of an existing railway, wherein each adjacent two guard piles are arranged in a staggered mode; arranging a zigzag crown cantilever on the top of each column of guard piles, and forming multiple jack holes in the inner side face, which is close to the box body, of the crown cantilever; arranging lifting jacks in the jack holes; jacking the box body according to a traditional jacking method; and starting the lifting jacks in the jack holes in the crown cantilever on the deflection side when the center line of the box body deviates from a designed center line, and continuously jacking until the box body is jacked in place. The method has an obvious correction effect, correction can be performed by jacking and adjusting the jacking force of the lifting jacks according to the deflection amount, and the correction effect can be observed after jacking is ended; in addition, the correction precision is high, the jack opening number for correction can be inversely calculated according to the deflection torque calculated according to the box jacking process; moreover, the correction facility is simple in structure and convenient in operation.

Description

Top pick is utilized to carry out the box-body jacking method of rectifying a deviation in deflection end in oblique jack-in process
Technical field
The invention belongs to construction of railways technical field, particularly relate in a kind of oblique jack-in process and utilize top pick to carry out the box-body jacking method of rectifying a deviation in deflection end.
Background technology
Along with the develop rapidly of urban construction, volume of transport is also in continuous increase.When existing railway and highway grade crossing, common way builds frame bridge under existing railway, alleviates with this traffic congestion phenomenon caused because rail track passes in city.When some frame bridge or because service life is long or when cannot meet the requirement of traffic because inner width is too small, displace old frame bridge with regard to needing with new frame bridge.Method of replacing conventional is at present jacking, and this method is that limit removal of old framework bridge and the soil body lateral dominance jack (also claiming top pick) dug out below this bridge will form joint or the jacking below existing railway from existing railway one or both sides of more piece casing of frame bridge main body.But by the impact of the factor such as earth clearance, existing highway, the angle between box-body jacking design center line and existing railway is more and more less, thus increases jacking construction difficulty, namely in this case jacking time casing very easily there is Midline deviation problem.In order to prevent this problem, the main method for correcting error adopted has at present: box back base plate both sides uneven cloth top set pick; 2, the casing both sides basil is uneven eats soil, and namely casing to which lateral deviation turns and just carries out excavating to the soil body at this side edge angle place more; 3, the uneven excavation of the base plate front end soil body.
But in practice of construction process, between actual top power and theory calculate top power, often there is larger deviation, directly will affect the layout of jack during jacking like this; And underground soil property may be reported inconsistent with geological mapping in jack-in process, therefore arrange that the directive significance of jack will reduce according to theory calculate top power; In addition, arrange jack one-sided at box back base plate in jack-in process, the method utilizing top, this side of lifting power to offset deflection torque easily damages finished tank, increases casing wall Vertical Cracks thus more; In addition, utilize the mode of the basil and the uneven shoveling of base plate effect in work progress directly perceived not, and concrete digging degree is unfavorable for grasping.
Summary of the invention
In order to solve the problem, the object of the present invention is to provide in a kind of oblique jack-in process and utilizing top pick to carry out the box-body jacking method of rectifying a deviation in deflection end.
In order to achieve the above object, the box-body jacking method utilizing top pick to carry out rectifying a deviation in deflection end in oblique jack-in process provided by the invention comprises the following step carried out in order:
The box-body jacking method utilizing top pick to carry out rectifying a deviation in deflection end in oblique jack-in process provided by the invention comprises the following step carried out in order:
1) existing railway treating jacking place is reinforced according to conventional reinforcement means;
2) in the jacking region of existing railway both sides, along jacking route, a row fender pile is set respectively in the foundation soil of casing both sides treating jacking, and adjacent two root guard stake setting interlaced with each other, then the Guan Liang of an indention is set at the top of every row fender pile, on Guan Liang, on the medial surface of casing, be recessed to form multiple pick nest thus, thus all fender piles in these row are linked to be entirety;
3) in each pick nest, at least two correction jack are arranged side by side;
4) multiple stage jacking jack and rear back beam are set in the base plate rear end both sides of casing, then limit removal of old framework bridge and dig out the opposite side jacking casing of top power along jacking direction to existing railway that this jack of soil body lateral dominance below this bridge applies;
5) when the center line off-design center line of casing, open be positioned at deflection side Guan Liang on the jack of pick nest, the front end pick of jack is made to be against on the lateral surface of this side box body, the quantity opening pick is determined according to bias size, to apply reverse deflection torque to casing, thus casing is rectified a deviation;
6) continue jacking, and adjust the top power of jack at any time along with top Cheng Zengchang, until casing puts in place along the jacking of jacking direction.
In described often row fender pile, the staggered distance of adjacent two root guard stakes is the radius of fender pile.
The box-body jacking method utilizing top pick to carry out rectifying a deviation in deflection end in oblique jack-in process provided by the invention to treat that the fender pile of jacking casing both sides is crisscross arranged, and the Guan Liang of fender pile upper end is made zigzag, the jack pair casing deflection end in the pick nest being arranged on formation on Guan Liang is utilized to increase opposite force, to rectify a deviation fast to casing, experiment proves that not only rectifying effect is obvious, and can rectify a deviation according to the top power of jacking limit, amount of deflection size limit adjustment jack, jacking terminates to observe rectifying effect; In addition, correction precision is higher, and what the deflection torque inverse that can calculate according to casing top journey to rectify a deviation opens pick quantity; In addition, correction facility structure is simple, easy to operate, is convenient to arrange and adjustable length, therefore can increases substantially speed of application.
Accompanying drawing explanation
Fig. 1-Fig. 5 utilizes top pick to carry out the box-body jacking method work progress schematic diagram of rectifying a deviation in deflection end in oblique jack-in process provided by the invention.
Fig. 6 is the fender pile, Guan Liang and the correction jack structure stereogram that arrange when utilizing this construction method to construct.
Fig. 7 is the fender pile, Guan Liang and the correction jack structure top view that arrange when utilizing this construction method to construct.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the box-body jacking method utilizing top pick to rectify a deviation in deflection end in oblique jack-in process provided by the invention is described in detail.
As shown in Fig. 1-Fig. 7, the box-body jacking method utilizing top pick to carry out rectifying a deviation in deflection end in oblique jack-in process provided by the invention comprises the following step carried out in order:
1) existing railway treating jacking place is reinforced according to conventional reinforcement means;
2) in the jacking region of existing railway 6 both sides, along jacking route, a row fender pile 2 is set respectively in the foundation soil of casing 1 both sides treating jacking, and adjacent two root guard stake 2 setting interlaced with each other, then the hat beam 3 of an indention is set at the top of every row fender pile 2, on hat beam 3, on the medial surface of casing 1, be recessed to form multiple pick nest 4 thus, thus all fender piles 2 in these row are linked to be entirety;
3) in each pick nest 4, at least two correction jack 5 are arranged side by side;
4) multiple stage jacking jack and rear back beam are set in the base plate rear end both sides of casing 1, then limit removal of old framework bridge and dig out top power that this jack of soil body lateral dominance below this bridge applies along jacking direction to the opposite side jacking casing 1 of existing railway 6;
5) when the center line off-design center line of casing 1, open be positioned at deflection side hat beam 3 on the jack 5 of pick nest 4, the front end pick of jack 5 is made to be against on the lateral surface of this side box body 1, the quantity opening pick is determined according to bias size, to apply reverse deflection torque to casing 1, thus casing 1 is rectified a deviation;
6) continue jacking, and adjust the top power of jack 5 at any time along with top Cheng Zengchang, until casing 1 puts in place along the jacking of jacking direction.
In described often row fender pile 2, the staggered distance of adjacent two root guard stakes 2 is the radius of fender pile 2.
In addition, can also open the jack 5 in the jack 5 diagonally opposing corner place pick nest 4 opened with above-mentioned deflection side during correction, to increase deflection torque, effect is more obvious simultaneously.

Claims (2)

1. utilize top pick to carry out a box-body jacking method of rectifying a deviation in deflection end in oblique jack-in process, it is characterized in that: described jacking comprises the following step carried out in order:
1) existing railway treating jacking place is reinforced according to conventional reinforcement means;
2) in the jacking region of existing railway (6) both sides, along jacking route, a row fender pile (2) is set respectively in the foundation soil of casing (1) both sides treating jacking, and adjacent two root guard stake (2) settings interlaced with each other, then the Guan Liang (3) of an indention is set at the top of every row fender pile (2), on the medial surface of the upper close casing (1) of Guan Liang (3), be recessed to form multiple pick nest (4) thus, thus all fender piles (2) in these row are linked to be entirety;
3) in each pick nest (4), at least two correction jack (5) are arranged side by side;
4) multiple stage jacking jack and rear back beam are set in the base plate rear end both sides of casing (1), then limit removal of old framework bridge and dig out top power that this jack of soil body lateral dominance below this bridge applies along jacking direction to the opposite side jacking casing (1) of existing railway (6);
5) when the center line off-design center line of casing (1), open the jack (5) of the upper pick nest (4) of the Guan Liang (3) being positioned at deflection side, the front end pick of jack (5) is made to be against on the lateral surface of this side box body (1), to apply reverse deflection torque to casing (1), thus casing (1) is rectified a deviation;
6) continue jacking, and adjust the top power of correction jack (5) at any time along with top Cheng Zengchang, until casing (1) puts in place along the jacking of jacking direction.
2. jacking according to claim 1, is characterized in that: in described often row fender pile (2), the staggered distance of adjacent two root guard stakes (2) is the radius of fender pile (2).
CN201310357697.3A 2013-08-15 2013-08-15 Box jacking method for performing correction on deflection end by virtue of jack in oblique crossing jacking process Active CN103410096B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310357697.3A CN103410096B (en) 2013-08-15 2013-08-15 Box jacking method for performing correction on deflection end by virtue of jack in oblique crossing jacking process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310357697.3A CN103410096B (en) 2013-08-15 2013-08-15 Box jacking method for performing correction on deflection end by virtue of jack in oblique crossing jacking process

Publications (2)

Publication Number Publication Date
CN103410096A CN103410096A (en) 2013-11-27
CN103410096B true CN103410096B (en) 2015-06-03

Family

ID=49603133

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310357697.3A Active CN103410096B (en) 2013-08-15 2013-08-15 Box jacking method for performing correction on deflection end by virtue of jack in oblique crossing jacking process

Country Status (1)

Country Link
CN (1) CN103410096B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115450118B (en) * 2022-08-14 2024-08-27 中铁十局集团第八工程有限公司 Jacking construction device and construction method for underpass high-speed motor train test line diagonal frame bridge

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1033203A (en) * 1988-08-19 1989-05-31 北京市第二市政工程公司 Monitor and rectification equipment and direction-controlling method are contained in the top
JP4040901B2 (en) * 2002-04-25 2008-01-30 鹿島建設株式会社 Three-dimensional intersection construction method and three-dimensional intersection
CN101935988A (en) * 2010-08-24 2011-01-05 攀钢集团冶金工程技术有限公司 Box culvert structure and jacking method of box culvert for penetrating roadbed
CN101963061A (en) * 2010-10-19 2011-02-02 浙江省建工集团有限责任公司 Construction method for underground box culvert of existing railway line
CN102031757A (en) * 2011-01-06 2011-04-27 李家稳 Method for constructing bottom plate guide layer of jacked-in frame bridge
CN102277880A (en) * 2011-04-21 2011-12-14 中铁六局集团有限公司 Large-sized box jacking control construction method capable of enhancing accuracy
CN102359069A (en) * 2011-07-05 2012-02-22 中铁十局集团有限公司 Existing line reinforcing method in under-crossing railway frame bridge small-included angle large-height inclined jacking construction
CN102979041A (en) * 2012-12-26 2013-03-20 中铁七局集团郑州工程有限公司 Soft overhead reinforcing jacking method for construction of span box bridge of jacking block of underpass turnout group of railway

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1033203A (en) * 1988-08-19 1989-05-31 北京市第二市政工程公司 Monitor and rectification equipment and direction-controlling method are contained in the top
JP4040901B2 (en) * 2002-04-25 2008-01-30 鹿島建設株式会社 Three-dimensional intersection construction method and three-dimensional intersection
CN101935988A (en) * 2010-08-24 2011-01-05 攀钢集团冶金工程技术有限公司 Box culvert structure and jacking method of box culvert for penetrating roadbed
CN101963061A (en) * 2010-10-19 2011-02-02 浙江省建工集团有限责任公司 Construction method for underground box culvert of existing railway line
CN102031757A (en) * 2011-01-06 2011-04-27 李家稳 Method for constructing bottom plate guide layer of jacked-in frame bridge
CN102277880A (en) * 2011-04-21 2011-12-14 中铁六局集团有限公司 Large-sized box jacking control construction method capable of enhancing accuracy
CN102359069A (en) * 2011-07-05 2012-02-22 中铁十局集团有限公司 Existing line reinforcing method in under-crossing railway frame bridge small-included angle large-height inclined jacking construction
CN102979041A (en) * 2012-12-26 2013-03-20 中铁七局集团郑州工程有限公司 Soft overhead reinforcing jacking method for construction of span box bridge of jacking block of underpass turnout group of railway

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
"北京五环路下穿铁路立交桥小夹角大吨位顶进施工技术";于福通;《铁道标准设计》;20070930(第9期);第22-24页 *
"既有线框构桥拆旧顶新工艺的探讨";张大虎;《铁道标准设计》;20060630(第6期);第84-85、99页 *

Also Published As

Publication number Publication date
CN103410096A (en) 2013-11-27

Similar Documents

Publication Publication Date Title
CN201850505U (en) Rigid-flexible transition structure capable of preventing bumping at bridge-head
CN103821039B (en) Correcting method for high speed railway ballastless track subgrade in soft soil area
CN102808381B (en) High-water-level silty-soil underneath-pass multi-track railway frame bridge jacking and butting construction method
CN102352590A (en) Method for splicing highfill roadbed by adopting pile-sheet retaining wall
CN109868691B (en) Deformation-adjustable high-speed railway roadbed structure, construction method and settlement deformation adjustment method
CN104652279A (en) Box culvert advancing construction method for building new frame bridge above existing subway structure
CN105804119A (en) Underground corridor structure with dual-purpose pile foundations and construction method of underground corridor structure
CN202945519U (en) Reinforced structure for controlling embankment settlement during operational period
CN105696426A (en) Construction method for treating adjacent existing railway line soft soil foundation and roadbed structure thereof
CN103388311B (en) Jacking method performing deviation correction at deflecting end through steel supports during oblique crossing jacking
CN104294769A (en) Built abutment structure reinforced through combination of pile supplementing and abutment cap enlarging and construction method
CN204825533U (en) Adopt existing circuit reinforcerment system of D type roof beam
CN103821040B (en) For the error-correction structure of soft clay area operation ballastless track of high-speed railway roadbed
CN104594371A (en) Reinforcing structure of existing foundation bottom plate and construction method thereof
CN105672144A (en) Medium-small span old bridge reinforcement and jointing-widening structure and construction method thereof
CN103410096B (en) Box jacking method for performing correction on deflection end by virtue of jack in oblique crossing jacking process
CN102817298B (en) Construction method on frozen soil
CN207672341U (en) A kind of adjustable High Speed Railway Subgrade of deformation
CN204097889U (en) A kind of piling and the built bridge abutment structure of increase platform cap composite reinforcement
CN204940298U (en) A kind of Composite Enclosure Structure of base pit engineering
CN111622234B (en) Unloading type thin-wall box-type retaining wall supported by obliquely and vertically combined steel pipe pile and construction process
CN104164839A (en) Construction method for broadening box culvert
CN206600176U (en) A kind of novel tunnel inverted arch self-propelled trestle
CN113235639A (en) Existing line lower row pile enclosure structure and construction method thereof
CN102031757B (en) Method for constructing bottom plate guide layer of jacked-in frame bridge

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant