JP3937974B2 - Machine support method - Google Patents

Machine support method Download PDF

Info

Publication number
JP3937974B2
JP3937974B2 JP2002233266A JP2002233266A JP3937974B2 JP 3937974 B2 JP3937974 B2 JP 3937974B2 JP 2002233266 A JP2002233266 A JP 2002233266A JP 2002233266 A JP2002233266 A JP 2002233266A JP 3937974 B2 JP3937974 B2 JP 3937974B2
Authority
JP
Japan
Prior art keywords
steel temporary
steel
beams
temporary beam
machine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2002233266A
Other languages
Japanese (ja)
Other versions
JP2004068550A (en
Inventor
正吉 田中
Original Assignee
石川島運搬機械株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 石川島運搬機械株式会社 filed Critical 石川島運搬機械株式会社
Priority to JP2002233266A priority Critical patent/JP3937974B2/en
Publication of JP2004068550A publication Critical patent/JP2004068550A/en
Application granted granted Critical
Publication of JP3937974B2 publication Critical patent/JP3937974B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は機械支持方法に関するものである。
【0002】
【従来の技術】
近年、工場で生産した鉄筋コンクリート構造部材を、ビル建築現場で順に組み立ててビル躯体を構築する工法が実施されている。
【0003】
図4は鉄筋コンクリート構造部材の一例を示すものであり、この構造部材は、上下に延びる複数の鉄筋1の中間部分を、コンクリート柱状体に埋め込んで鉄筋1の両端部分を露出させた柱材2と、基端部分が鉄筋1に固着され且つ横向きに延びる複数の鉄筋3の基端寄り部分を、コンクリート突出部に埋め込んで前記のコンクリート柱状体に一体化した梁受4とを備えている。
【0004】
ビル躯体の構築にあたっては、図5に示すように、躯体構築場所の外方に設置したクレーン5により、柱材2を順に接続して4箇所に主柱6を立設しながら、相対する梁受4に梁材7の各端部を接続する。
【0005】
上記梁材7は、図4に示すように、横向きに延びる複数の鉄筋8の中間部分を、コンクリート梁状体に埋め込んだもので、梁受4に対する梁材7の接続は、鉄筋3、鉄筋8の相互の溶接と、コンクリート柱状体とコンクリート突出部との間の空隙へのコンクリートの充填とで達成される。
【0006】
クレーン5は、クライミング方式のものを用いており、躯体高さの増大に対応するようにマスト9を順に接続して揚程を確保し、また、マスト9の所定箇所をサポート10によりビル躯体に連結して、クレーン5を支持している。
【0007】
【発明が解決しようとする課題】
しかしながら、ビル建築現場の周囲に既設の建物があると、ビル躯体の構築に最適な位置にクレーン5を設置できず、これにより、ビル建設を効率よく行なうことができない。
【0008】
また、クレーン5がビル躯体の中央部分に位置するように、クレーン5をビル躯体に組み込んだ梁材7に支持させることも考えられるが、コンクリートで表層部分が形成されている梁材7と柱材2の間に、荷重支持用の補強材を介在させることは現実的ではない。
【0009】
本発明は上述した実情に鑑みてなしたもので、鉄筋コンクリート構造の躯体が機械の荷重を支持できるようにすることを目的としている。
【0010】
【課題を解決するための手段】
上記目的を達成するため、本発明の機械支持方法では、横方向へ突出する梁受を設けた鉄筋コンクリート構造の柱材を順に接続して4箇所に主柱を立設しつつ、相対する梁受に梁材の各端部を接続して建物躯体を構築する際に、所定の2本の主柱の間に第1の鋼製仮設梁を介在させて、該第1の鋼製仮設梁の各端部を相対している梁受の上面に載置し、他の2本の主柱の間に第2の鋼製仮設梁を介在させて、該第2の鋼製仮設梁の各端部を相対している梁受の上面に載置したうえ、第1、第2の鋼製仮設梁に機械架台を搭載し、第1、第2の鋼製仮設梁の機械架台を搭載した後に、第3の鋼製仮設梁の各端部を第1の鋼製仮設梁の上方で相対している梁受の上面に載置し、第4の鋼製仮設梁の各端部を第2の鋼製仮設梁の上方で相対している梁受の上面に載置したうえ、第1、第2の鋼製仮設梁上の機械架台を第3、第4の鋼製仮設梁に搭載し、第3、第4の鋼製仮設梁の機械架台を搭載した後に、第1の鋼製仮設梁の各端部を第3の鋼製仮設梁の上方で相対している梁受の上面に載置し、第2の鋼製仮設梁の各端部を第4の鋼製仮設梁の上方で相対している梁受の上面に載置したうえ、第3、第4の鋼製仮設梁上の機械架台を第1、第2の鋼製仮設梁に搭載する作業を順次繰り返す。
【0011】
本発明の機械支持方法においては、主柱に対して一体的に形成され且つ所定の強度を有する梁受に、第1、第2の鋼製仮設梁を掛け渡し、第1、第2の鋼製仮設梁へ機械架台を搭載して、機械の荷重を主柱に伝達し、主柱に対して一体的に形成され且つ所定の強度を有する梁受に、第3、第4の鋼製仮設梁を掛け渡し、第1、第2の鋼製仮設梁に搭載されている機械架台を、第3、第4の鋼製仮設梁へ移し替えて、機械の荷重を主柱に伝達し、第1、第2の鋼製仮設梁を梁受に掛け渡して当該鋼製仮設梁へ機械架台を搭載する作業、及び第3、第4の鋼製仮設梁を梁受に掛け渡して当該第3、第4の鋼製仮設梁に機械架台を搭載する作業を交互に行ない、鋼製仮設梁を2本ずつ交互に使用しながら機械の荷重を主柱に伝達する。
【0012】
【発明の実施の形態】
以下、本発明の実施の形態を、図示例とともに説明する。
【0013】
図1乃至図3は本発明の機械支持方法の実施の形態の一例であり、図中、図4及び図5と同一の符号を付したものは同一物を表している。
【0014】
この機械支持方法では、当初、ビル建築現場に投入したレッカーなどにより、横方向へ突出する梁受4を設けた鉄筋コンクリート構造の柱材2を順に接続し、躯体構築場所内の所定位置の4箇所に主柱6を立設し、また、相対する梁受4に梁材7の各端部を接続して建物躯体の下層階部分を構築する。
【0015】
その後、所定の2本の主柱6の間に第1の鋼製仮設梁11を介在させて、該第1の鋼製仮設梁11の各端部を相対している梁受4の上面に載置し、他の2本の主柱6の間に第2の鋼製仮設梁12を介在させて、該第2の鋼製仮設梁12の各端部を相対している梁受4の上面に載置する。
【0016】
この第1、第2の鋼製仮設梁11,12の上にクライミング方式のクレーンの架台13を搭載し、該架台13の上にクレーンを組み立てる。
【0017】
架台13は、架台本体14と、その前後端部に設けられ且つ横方向へ突出可能な伸縮構造の4本の支持脚15とを備えている。
【0018】
この架台13を各鋼製仮設梁11,12上に搭載するときには、支持脚15の伸縮機能を活用して、当該支持脚15の先端部が各鋼製仮設梁11,12上面の最適箇所に位置するように支持脚15の長さを設定する。
【0019】
以後、クレーンにより、鉄筋コンクリート構造の柱材2を順に接続して主柱6を立設し、また、相対する梁受4に梁材7の各端部を接続して建物躯体の第2の構築段階の階層部分を構築する。
【0020】
所期の階層部分を構築した後、更に、所定の2本の主柱6の間に、第3の鋼製仮設梁16の各端部を、第1の鋼製仮設梁11の上方で相対している所定の階層の梁受4の上面に載置し、第4の鋼製仮設梁17の各端部を、第2の鋼製仮設梁12の上方で相対している所定の階層の梁受4の上面に載置する(図1参照)。
【0021】
次いで、クレーンの昇降装置を利用してマスト9を上昇させることにより、該マスト9を介して架台13を引き上げ、第3、第4の鋼製仮設梁16,17上面に搭載する。
【0022】
このとき、支持脚15の長さを短縮して、架台13の上昇中の途中階層の梁材7と支持脚15の先端部が干渉しないようにする。
【0023】
更に、クレーンにより、鉄筋コンクリート構造の柱材2を順に接続して主柱6を立設し、また、相対する梁受4に梁材7の各端部を接続して建物躯体の第3の構築段階の階層部分を構築する。
【0024】
上層の階へクレーンの据え付け位置を移動させる必要がある場合には、第1の鋼製仮設梁11を前記の設定位置から引き上げ、当該鋼製仮設梁11の各端部を第3の鋼製仮設梁16の上方で相対している所定の階層の梁受4の上面に載置し、第2の鋼製仮設梁12を前記の設定位置から引き上げ、当該鋼製仮設梁12の各端部を第4の鋼製仮設梁17の上方で相対している所定階層の梁受4の上面に載置する。
【0025】
次いで、前述したマスト9の引き上げ作業を再び行なうことによって、第3、第4の鋼製仮設梁16,17上面にある架台13を、上層の階に移設した第1、第2の鋼製仮設梁11,12上面に搭載する。
【0026】
以後、上述した作業を繰り返すことによって、建物躯体の構築を進捗させる。
【0027】
このように、図1乃至図3に示す本発明の機械支持方法においては、鉄筋コンクリート構造の柱材2に対して一体的に形成され且つ所定の強度を有する梁受4の上面に、第1、第2の鋼製仮設梁11,12、あるいは第3、第4の鋼製仮設梁16,17を掛け渡し、これら鋼製仮設梁11,12,16,17上面に搭載される架台13の荷重を、各鋼製仮設梁11,12,16,17及び梁受4を介して主柱6へ伝達するので、鉄筋コンクリート構造の躯体で、クレーンなどの機械を支持することができる。
【0028】
なお、本発明の機械支持方法は上述した実施の形態のみに限定されるものではなく、本発明の要旨を逸脱しない範囲内において種々変更を加え得ることは勿論である。
【0029】
【発明の効果】
以上述べたように、本発明の機械支持方法においては、鉄筋コンクリート構造の主柱に対して一体的に形成され且つ所定の強度を有する梁受に、一対の鋼製仮設梁を掛け渡し、当該鋼製仮設梁へ機械架台を搭載することによって、機械架台からの荷重を鋼製仮設梁を介して主柱へ伝達するので、鉄筋コンクリート構造の躯体で、機械の荷重を支持できるという優れた効果を奏し得る。
【図面の簡単な説明】
【図1】 本発明の機械支持方法の実施の形態の一例を示す概念図である。
【図2】 図1のII−II矢視図である。
【図3】 図1のIII−III矢視図である。
【図4】 鉄筋コンクリート構造部材の一例を示す概念図である。
【図5】 従来の鉄筋コンクリート構造部材によるビル躯体構築作業の一例を示す概念図である。
【符号の説明】
2 柱材
4 梁受
6 主柱
7 梁材
11 第1の鋼製仮設梁
12 第2の鋼製仮設梁
13 架台(機械架台)
16 第3の鋼製仮設梁
17 第4の鋼製仮設梁
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a machine support method.
[0002]
[Prior art]
In recent years, a method of constructing a building frame by sequentially assembling reinforced concrete structural members produced in a factory at a building construction site has been implemented.
[0003]
FIG. 4 shows an example of a reinforced concrete structural member. This structural member includes a column member 2 in which intermediate portions of a plurality of reinforcing bars 1 extending vertically are embedded in a concrete columnar body and both end portions of the reinforcing bar 1 are exposed. The base end portion is fixed to the reinforcing bar 1 and includes a beam receiver 4 in which the base end portions of the plurality of reinforcing bars 3 extending in the lateral direction are embedded in the concrete projecting portion and integrated with the concrete columnar body.
[0004]
In building the building frame, as shown in FIG. 5, the crane 5 installed outside the building building place is connected to the column members 2 in order, and the main columns 6 are erected at four locations while facing the beams. Each end of the beam member 7 is connected to the support 4.
[0005]
As shown in FIG. 4, the beam member 7 is formed by embedding intermediate portions of a plurality of reinforcing bars 8 extending in the lateral direction in a concrete beam. The connection of the beam member 7 to the beam receiver 4 is performed by the reinforcing bars 3 and the reinforcing bars. 8 mutual welding and filling of the concrete into the gap between the concrete column and the concrete protrusion.
[0006]
The crane 5 is of a climbing type, and the mast 9 is connected in order so as to correspond to the increase in the height of the frame to secure the lift, and a predetermined portion of the mast 9 is connected to the building frame by the support 10. The crane 5 is supported.
[0007]
[Problems to be solved by the invention]
However, if there is an existing building around the building construction site, the crane 5 cannot be installed at an optimum position for building the building frame, and the building construction cannot be performed efficiently.
[0008]
In addition, it is conceivable that the crane 5 is supported by the beam member 7 incorporated in the building frame so that the crane 5 is positioned at the center part of the building frame. It is not realistic to interpose a load supporting reinforcement between the materials 2.
[0009]
The present invention has been made in view of the above-described circumstances, and an object of the present invention is to enable a reinforced concrete structural frame to support the load of a machine.
[0010]
[Means for Solving the Problems]
In order to achieve the above object, in the machine support method of the present invention, the reinforced concrete structure column members provided with the beam supports protruding in the lateral direction are connected in order, and the main columns are erected at the four locations while the beam supports facing each other. When constructing a building frame by connecting each end of the beam material to the first steel temporary beam, the first steel temporary beam is interposed between two predetermined main columns. Each end is placed on the upper surface of the opposite beam support, and a second steel temporary beam is interposed between the other two main columns, and each end of the second steel temporary beam is placed. After placing the machine stand on the first and second steel temporary beams and mounting the first and second steel temporary beam machine stands on , Each end of the third steel temporary beam is placed on the upper surface of the beam receiver facing above the first steel temporary beam, and each end of the fourth steel temporary beam is Opposite of steel temporary beams The first and second steel temporary beams are mounted on the third and fourth steel temporary beams, and the third and fourth steel temporary beam machines are mounted on the upper surface of the support. After mounting the gantry, each end of the first steel temporary beam is placed on the upper surface of the beam support facing above the third steel temporary beam, and each end of the second steel temporary beam is placed. The end is placed on the upper surface of the beam support facing the upper side of the fourth steel temporary beam, and the mechanical mount on the third and fourth steel temporary beams is made of the first and second steel beams. Repeatedly install the temporary beams.
[0011]
In the machine support method according to the present invention, the first and second steel temporary beams are bridged over the beam support that is integrally formed with the main column and has a predetermined strength. A third and fourth steel temporary installation is carried out on a beam support which is mounted integrally with the main column and has a predetermined strength by mounting a machine mount on the temporary beam and transmitting the load of the machine to the main column. The beam is routed, the machine base mounted on the first and second steel temporary beams is transferred to the third and fourth steel temporary beams, and the load of the machine is transmitted to the main column. 1. Overhanging the second steel temporary beam over the beam support and mounting the mechanical mount on the steel temporary beam; and the third and fourth steel temporary beams over the beam support The work of mounting the machine stand on the fourth steel temporary beam is alternately performed, and the load of the machine is transmitted to the main column while using the two steel temporary beams alternately.
[0012]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
[0013]
1 to 3 show an example of an embodiment of a machine support method according to the present invention. In the figures, the same reference numerals as those in FIGS. 4 and 5 denote the same components.
[0014]
In this machine support method, the reinforced concrete structure pillars 2 provided with the beam supports 4 protruding in the lateral direction are connected in order by a wrecker or the like initially introduced at the building construction site, and four places at predetermined positions in the building construction site are connected. A main pillar 6 is erected, and each end of the beam 7 is connected to the opposite beam receiver 4 to construct a lower floor portion of the building frame.
[0015]
Thereafter, a first steel temporary beam 11 is interposed between two predetermined main pillars 6, and the respective ends of the first steel temporary beam 11 are opposed to the upper surface of the beam receiver 4 facing each other. The beam receiver 4 is mounted and the second steel temporary beam 12 is interposed between the other two main pillars 6 and the ends of the second steel temporary beam 12 are opposed to each other. Place on top.
[0016]
A climbing crane gantry 13 is mounted on the first and second steel temporary beams 11 and 12, and the crane is assembled on the gantry 13.
[0017]
The gantry 13 includes a gantry body 14 and four support legs 15 that are provided at the front and rear ends of the gantry body and have a telescopic structure that can protrude in the lateral direction.
[0018]
When the gantry 13 is mounted on the steel temporary beams 11 and 12, the extensible function of the support leg 15 is utilized so that the tip of the support leg 15 is located at the optimum position on the upper surface of the steel temporary beam 11 and 12. The length of the support leg 15 is set so as to be positioned.
[0019]
After that, the main column 6 was erected by connecting the column members 2 of the reinforced concrete structure in order with a crane, and each end of the beam member 7 was connected to the opposite beam receiver 4 to construct the second building frame. Build the hierarchical part of the stage.
[0020]
After constructing the desired layer portion, each end of the third steel temporary beam 16 is further moved relative to the upper portion of the first steel temporary beam 11 between the two predetermined main pillars 6. The end of the fourth steel temporary beam 17 is placed on the upper surface of the beam receiver 4 of a predetermined level, and the end of the fourth steel temporary beam 12 is opposed to the upper side of the second steel temporary beam 12. It mounts on the upper surface of the beam receiver 4 (refer FIG. 1).
[0021]
Subsequently, the mast 9 is lifted using the crane lifting device, whereby the gantry 13 is pulled up via the mast 9 and mounted on the upper surfaces of the third and fourth steel temporary beams 16 and 17.
[0022]
At this time, the length of the support leg 15 is shortened so that the beam member 7 in the middle of the rise of the gantry 13 and the tip of the support leg 15 do not interfere with each other.
[0023]
Further, the main column 6 is erected by connecting the column members 2 of the reinforced concrete structure in order by a crane, and each end of the beam member 7 is connected to the opposite beam receiver 4 to construct a third building frame. Build the hierarchical part of the stage.
[0024]
When it is necessary to move the crane installation position to the upper floor, the first steel temporary beam 11 is lifted from the set position, and each end of the steel temporary beam 11 is made of the third steel. It is placed on the upper surface of the beam receiver 4 at a predetermined level facing above the temporary beam 16, the second steel temporary beam 12 is lifted from the set position, and each end of the steel temporary beam 12 is placed. Is placed on the upper surface of the beam receiver 4 at a predetermined level facing above the fourth steel temporary beam 17.
[0025]
Next, the first and second steel temporary installations in which the frame 13 on the upper surfaces of the third and fourth steel temporary beams 16 and 17 are moved to the upper floor by performing the above-described lifting operation of the mast 9 again. Mounted on the upper surface of the beams 11 and 12.
[0026]
Thereafter, the construction of the building frame is advanced by repeating the above-described work.
[0027]
As described above, in the machine support method of the present invention shown in FIGS. 1 to 3, the first, The second steel temporary beams 11, 12 or the third and fourth steel temporary beams 16, 17 are passed over and the load of the mount 13 mounted on the upper surface of these steel temporary beams 11, 12, 16, 17 is loaded. Is transmitted to the main column 6 through the steel temporary beams 11, 12, 16, 17 and the beam receiver 4, so that a machine such as a crane can be supported by the reinforced concrete structure.
[0028]
It should be noted that the machine support method of the present invention is not limited to the above-described embodiment, and various changes can be made without departing from the scope of the present invention.
[0029]
【The invention's effect】
As described above, in the machine support method of the present invention, a pair of steel temporary beams are spanned over a beam receiver that is integrally formed with the main column of the reinforced concrete structure and has a predetermined strength. By mounting the machine base on the temporary steel beam, the load from the machine base is transmitted to the main column via the steel temporary beam, so that the reinforced concrete structure can support the load of the machine. obtain.
[Brief description of the drawings]
FIG. 1 is a conceptual diagram showing an example of an embodiment of a machine support method of the present invention.
FIG. 2 is a view taken in the direction of arrows II-II in FIG.
FIG. 3 is a view taken in the direction of arrows III-III in FIG.
FIG. 4 is a conceptual diagram showing an example of a reinforced concrete structural member.
FIG. 5 is a conceptual diagram showing an example of building building construction work by a conventional reinforced concrete structural member.
[Explanation of symbols]
2 Column material 4 Beam support 6 Main column 7 Beam material 11 First steel temporary beam 12 Second steel temporary beam 13 Mounting platform (mechanical mounting)
16 Third steel temporary beam 17 Fourth steel temporary beam

Claims (1)

横方向へ突出する梁受を設けた鉄筋コンクリート構造の柱材を順に接続して4箇所に主柱を立設しつつ、相対する梁受に梁材の各端部を接続して建物躯体を構築する際に、所定の2本の主柱の間に第1の鋼製仮設梁を介在させて、該第1の鋼製仮設梁の各端部を相対している梁受の上面に載置し、他の2本の主柱の間に第2の鋼製仮設梁を介在させて、該第2の鋼製仮設梁の各端部を相対している梁受の上面に載置したうえ、第1、第2の鋼製仮設梁に機械架台を搭載し、第1、第2の鋼製仮設梁の機械架台を搭載した後に、第3の鋼製仮設梁の各端部を第1の鋼製仮設梁の上方で相対している梁受の上面に載置し、第4の鋼製仮設梁の各端部を第2の鋼製仮設梁の上方で相対している梁受の上面に載置したうえ、第1、第2の鋼製仮設梁上の機械架台を第3、第4の鋼製仮設梁に搭載し、第3、第4の鋼製仮設梁の機械架台を搭載した後に、第1の鋼製仮設梁の各端部を第3の鋼製仮設梁の上方で相対している梁受の上面に載置し、第2の鋼製仮設梁の各端部を第4の鋼製仮設梁の上方で相対している梁受の上面に載置したうえ、第3、第4の鋼製仮設梁上の機械架台を第1、第2の鋼製仮設梁に搭載する作業を順次繰り返すことを特徴とする機械支持方法。  Build the building frame by connecting each end of the beam material to the opposite beam supports while connecting the pillars of the reinforced concrete structure with the beam supports protruding in the horizontal direction in order to erect the main pillar at four places. In doing so, a first steel temporary beam is interposed between two predetermined main pillars, and each end of the first steel temporary beam is placed on the upper surface of the beam supports facing each other. Then, a second steel temporary beam is interposed between the other two main pillars, and each end of the second steel temporary beam is placed on the upper surface of the opposite beam support. After the first and second steel temporary beams are mounted on the machine frame and the first and second steel temporary beams are mounted on the machine frame, each end of the third steel temporary beam is connected to the first steel temporary beam. The steel temporary beam is placed on the upper surface of the beam support facing the upper side of the steel temporary beam, and each end of the fourth steel temporary beam is placed on the upper surface of the second steel temporary beam. On the upper surface, on the first and second steel temporary beams After mounting the machine mount on the third and fourth steel temporary beams and mounting the third and fourth steel temporary beam mechanical mounts, each end of the first steel temporary beam is connected to the third steel temporary beam. The upper surface of the beam receiver which is placed on the upper surface of the beam support facing above the steel temporary beam, and each end of the second steel temporary beam is opposed to the upper surface of the fourth steel temporary beam. A machine support method characterized by sequentially repeating the work of mounting the machine mounts on the third and fourth steel temporary beams on the first and second steel temporary beams.
JP2002233266A 2002-08-09 2002-08-09 Machine support method Expired - Lifetime JP3937974B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002233266A JP3937974B2 (en) 2002-08-09 2002-08-09 Machine support method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002233266A JP3937974B2 (en) 2002-08-09 2002-08-09 Machine support method

Publications (2)

Publication Number Publication Date
JP2004068550A JP2004068550A (en) 2004-03-04
JP3937974B2 true JP3937974B2 (en) 2007-06-27

Family

ID=32018431

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002233266A Expired - Lifetime JP3937974B2 (en) 2002-08-09 2002-08-09 Machine support method

Country Status (1)

Country Link
JP (1) JP3937974B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4504747B2 (en) * 2004-06-25 2010-07-14 三井住友建設株式会社 Building construction method using tower crane
JP2006248675A (en) * 2005-03-10 2006-09-21 Shimizu Corp Tower crane support structure

Also Published As

Publication number Publication date
JP2004068550A (en) 2004-03-04

Similar Documents

Publication Publication Date Title
JP3952843B2 (en) Construction method of tower structure
JP6289046B2 (en) Temporary stand
KR101891942B1 (en) Earthquake reinforcement method of existing structure
JP2010265727A (en) Method for demolishing building using floor climbing type tower crane
JP5294104B2 (en) Tower crane support structure
JP2790986B2 (en) Bridge pier construction method and construction method
JP5190035B2 (en) Construction method of seismic isolation structure
JP5365854B2 (en) Tower crane support structure and climbing method
JP2011012464A (en) Method of constructing base isolating structure, and temporary supporting structure for base isolating device
JP3937974B2 (en) Machine support method
JP2001010780A (en) Climbing tower crane and its climbing method
JP2004316100A (en) Construction method for building
JP6849491B2 (en) Exposed column base structure of steel columns and its construction method
JP5003253B2 (en) RC beam construction method
KR100769552B1 (en) Method of bent construction for temporary bridge
JP6917720B2 (en) How to build a composite suspended structure
JP6441689B2 (en) How to install seismic isolation structures
JP2021116153A (en) Supporting platform for tower crane and climbing method using the same
JP2018096163A (en) Method of constructing building
JP2009299346A (en) Construction method of building
JP6720761B2 (en) How to build a ramen structure
JPH0932120A (en) Method of construction of structure
JP3903315B2 (en) Preservation method of existing outer wall structure
JP2017203303A (en) Construction method of composite foundation structure
JP3125205B2 (en) Construction method of temporary side wall

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050809

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20061221

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20061226

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070219

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070313

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070319

R150 Certificate of patent or registration of utility model

Ref document number: 3937974

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100406

Year of fee payment: 3

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100406

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110406

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110406

Year of fee payment: 4

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120406

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130406

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130406

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140406

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term