JP3937974B2 - Machine support method - Google Patents
Machine support method Download PDFInfo
- Publication number
- JP3937974B2 JP3937974B2 JP2002233266A JP2002233266A JP3937974B2 JP 3937974 B2 JP3937974 B2 JP 3937974B2 JP 2002233266 A JP2002233266 A JP 2002233266A JP 2002233266 A JP2002233266 A JP 2002233266A JP 3937974 B2 JP3937974 B2 JP 3937974B2
- Authority
- JP
- Japan
- Prior art keywords
- steel temporary
- steel
- beams
- temporary beam
- machine
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は機械支持方法に関するものである。
【0002】
【従来の技術】
近年、工場で生産した鉄筋コンクリート構造部材を、ビル建築現場で順に組み立ててビル躯体を構築する工法が実施されている。
【0003】
図4は鉄筋コンクリート構造部材の一例を示すものであり、この構造部材は、上下に延びる複数の鉄筋1の中間部分を、コンクリート柱状体に埋め込んで鉄筋1の両端部分を露出させた柱材2と、基端部分が鉄筋1に固着され且つ横向きに延びる複数の鉄筋3の基端寄り部分を、コンクリート突出部に埋め込んで前記のコンクリート柱状体に一体化した梁受4とを備えている。
【0004】
ビル躯体の構築にあたっては、図5に示すように、躯体構築場所の外方に設置したクレーン5により、柱材2を順に接続して4箇所に主柱6を立設しながら、相対する梁受4に梁材7の各端部を接続する。
【0005】
上記梁材7は、図4に示すように、横向きに延びる複数の鉄筋8の中間部分を、コンクリート梁状体に埋め込んだもので、梁受4に対する梁材7の接続は、鉄筋3、鉄筋8の相互の溶接と、コンクリート柱状体とコンクリート突出部との間の空隙へのコンクリートの充填とで達成される。
【0006】
クレーン5は、クライミング方式のものを用いており、躯体高さの増大に対応するようにマスト9を順に接続して揚程を確保し、また、マスト9の所定箇所をサポート10によりビル躯体に連結して、クレーン5を支持している。
【0007】
【発明が解決しようとする課題】
しかしながら、ビル建築現場の周囲に既設の建物があると、ビル躯体の構築に最適な位置にクレーン5を設置できず、これにより、ビル建設を効率よく行なうことができない。
【0008】
また、クレーン5がビル躯体の中央部分に位置するように、クレーン5をビル躯体に組み込んだ梁材7に支持させることも考えられるが、コンクリートで表層部分が形成されている梁材7と柱材2の間に、荷重支持用の補強材を介在させることは現実的ではない。
【0009】
本発明は上述した実情に鑑みてなしたもので、鉄筋コンクリート構造の躯体が機械の荷重を支持できるようにすることを目的としている。
【0010】
【課題を解決するための手段】
上記目的を達成するため、本発明の機械支持方法では、横方向へ突出する梁受を設けた鉄筋コンクリート構造の柱材を順に接続して4箇所に主柱を立設しつつ、相対する梁受に梁材の各端部を接続して建物躯体を構築する際に、所定の2本の主柱の間に第1の鋼製仮設梁を介在させて、該第1の鋼製仮設梁の各端部を相対している梁受の上面に載置し、他の2本の主柱の間に第2の鋼製仮設梁を介在させて、該第2の鋼製仮設梁の各端部を相対している梁受の上面に載置したうえ、第1、第2の鋼製仮設梁に機械架台を搭載し、第1、第2の鋼製仮設梁の機械架台を搭載した後に、第3の鋼製仮設梁の各端部を第1の鋼製仮設梁の上方で相対している梁受の上面に載置し、第4の鋼製仮設梁の各端部を第2の鋼製仮設梁の上方で相対している梁受の上面に載置したうえ、第1、第2の鋼製仮設梁上の機械架台を第3、第4の鋼製仮設梁に搭載し、第3、第4の鋼製仮設梁の機械架台を搭載した後に、第1の鋼製仮設梁の各端部を第3の鋼製仮設梁の上方で相対している梁受の上面に載置し、第2の鋼製仮設梁の各端部を第4の鋼製仮設梁の上方で相対している梁受の上面に載置したうえ、第3、第4の鋼製仮設梁上の機械架台を第1、第2の鋼製仮設梁に搭載する作業を順次繰り返す。
【0011】
本発明の機械支持方法においては、主柱に対して一体的に形成され且つ所定の強度を有する梁受に、第1、第2の鋼製仮設梁を掛け渡し、第1、第2の鋼製仮設梁へ機械架台を搭載して、機械の荷重を主柱に伝達し、主柱に対して一体的に形成され且つ所定の強度を有する梁受に、第3、第4の鋼製仮設梁を掛け渡し、第1、第2の鋼製仮設梁に搭載されている機械架台を、第3、第4の鋼製仮設梁へ移し替えて、機械の荷重を主柱に伝達し、第1、第2の鋼製仮設梁を梁受に掛け渡して当該鋼製仮設梁へ機械架台を搭載する作業、及び第3、第4の鋼製仮設梁を梁受に掛け渡して当該第3、第4の鋼製仮設梁に機械架台を搭載する作業を交互に行ない、鋼製仮設梁を2本ずつ交互に使用しながら機械の荷重を主柱に伝達する。
【0012】
【発明の実施の形態】
以下、本発明の実施の形態を、図示例とともに説明する。
【0013】
図1乃至図3は本発明の機械支持方法の実施の形態の一例であり、図中、図4及び図5と同一の符号を付したものは同一物を表している。
【0014】
この機械支持方法では、当初、ビル建築現場に投入したレッカーなどにより、横方向へ突出する梁受4を設けた鉄筋コンクリート構造の柱材2を順に接続し、躯体構築場所内の所定位置の4箇所に主柱6を立設し、また、相対する梁受4に梁材7の各端部を接続して建物躯体の下層階部分を構築する。
【0015】
その後、所定の2本の主柱6の間に第1の鋼製仮設梁11を介在させて、該第1の鋼製仮設梁11の各端部を相対している梁受4の上面に載置し、他の2本の主柱6の間に第2の鋼製仮設梁12を介在させて、該第2の鋼製仮設梁12の各端部を相対している梁受4の上面に載置する。
【0016】
この第1、第2の鋼製仮設梁11,12の上にクライミング方式のクレーンの架台13を搭載し、該架台13の上にクレーンを組み立てる。
【0017】
架台13は、架台本体14と、その前後端部に設けられ且つ横方向へ突出可能な伸縮構造の4本の支持脚15とを備えている。
【0018】
この架台13を各鋼製仮設梁11,12上に搭載するときには、支持脚15の伸縮機能を活用して、当該支持脚15の先端部が各鋼製仮設梁11,12上面の最適箇所に位置するように支持脚15の長さを設定する。
【0019】
以後、クレーンにより、鉄筋コンクリート構造の柱材2を順に接続して主柱6を立設し、また、相対する梁受4に梁材7の各端部を接続して建物躯体の第2の構築段階の階層部分を構築する。
【0020】
所期の階層部分を構築した後、更に、所定の2本の主柱6の間に、第3の鋼製仮設梁16の各端部を、第1の鋼製仮設梁11の上方で相対している所定の階層の梁受4の上面に載置し、第4の鋼製仮設梁17の各端部を、第2の鋼製仮設梁12の上方で相対している所定の階層の梁受4の上面に載置する(図1参照)。
【0021】
次いで、クレーンの昇降装置を利用してマスト9を上昇させることにより、該マスト9を介して架台13を引き上げ、第3、第4の鋼製仮設梁16,17上面に搭載する。
【0022】
このとき、支持脚15の長さを短縮して、架台13の上昇中の途中階層の梁材7と支持脚15の先端部が干渉しないようにする。
【0023】
更に、クレーンにより、鉄筋コンクリート構造の柱材2を順に接続して主柱6を立設し、また、相対する梁受4に梁材7の各端部を接続して建物躯体の第3の構築段階の階層部分を構築する。
【0024】
上層の階へクレーンの据え付け位置を移動させる必要がある場合には、第1の鋼製仮設梁11を前記の設定位置から引き上げ、当該鋼製仮設梁11の各端部を第3の鋼製仮設梁16の上方で相対している所定の階層の梁受4の上面に載置し、第2の鋼製仮設梁12を前記の設定位置から引き上げ、当該鋼製仮設梁12の各端部を第4の鋼製仮設梁17の上方で相対している所定階層の梁受4の上面に載置する。
【0025】
次いで、前述したマスト9の引き上げ作業を再び行なうことによって、第3、第4の鋼製仮設梁16,17上面にある架台13を、上層の階に移設した第1、第2の鋼製仮設梁11,12上面に搭載する。
【0026】
以後、上述した作業を繰り返すことによって、建物躯体の構築を進捗させる。
【0027】
このように、図1乃至図3に示す本発明の機械支持方法においては、鉄筋コンクリート構造の柱材2に対して一体的に形成され且つ所定の強度を有する梁受4の上面に、第1、第2の鋼製仮設梁11,12、あるいは第3、第4の鋼製仮設梁16,17を掛け渡し、これら鋼製仮設梁11,12,16,17上面に搭載される架台13の荷重を、各鋼製仮設梁11,12,16,17及び梁受4を介して主柱6へ伝達するので、鉄筋コンクリート構造の躯体で、クレーンなどの機械を支持することができる。
【0028】
なお、本発明の機械支持方法は上述した実施の形態のみに限定されるものではなく、本発明の要旨を逸脱しない範囲内において種々変更を加え得ることは勿論である。
【0029】
【発明の効果】
以上述べたように、本発明の機械支持方法においては、鉄筋コンクリート構造の主柱に対して一体的に形成され且つ所定の強度を有する梁受に、一対の鋼製仮設梁を掛け渡し、当該鋼製仮設梁へ機械架台を搭載することによって、機械架台からの荷重を鋼製仮設梁を介して主柱へ伝達するので、鉄筋コンクリート構造の躯体で、機械の荷重を支持できるという優れた効果を奏し得る。
【図面の簡単な説明】
【図1】 本発明の機械支持方法の実施の形態の一例を示す概念図である。
【図2】 図1のII−II矢視図である。
【図3】 図1のIII−III矢視図である。
【図4】 鉄筋コンクリート構造部材の一例を示す概念図である。
【図5】 従来の鉄筋コンクリート構造部材によるビル躯体構築作業の一例を示す概念図である。
【符号の説明】
2 柱材
4 梁受
6 主柱
7 梁材
11 第1の鋼製仮設梁
12 第2の鋼製仮設梁
13 架台(機械架台)
16 第3の鋼製仮設梁
17 第4の鋼製仮設梁[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a machine support method.
[0002]
[Prior art]
In recent years, a method of constructing a building frame by sequentially assembling reinforced concrete structural members produced in a factory at a building construction site has been implemented.
[0003]
FIG. 4 shows an example of a reinforced concrete structural member. This structural member includes a
[0004]
In building the building frame, as shown in FIG. 5, the
[0005]
As shown in FIG. 4, the
[0006]
The
[0007]
[Problems to be solved by the invention]
However, if there is an existing building around the building construction site, the
[0008]
In addition, it is conceivable that the
[0009]
The present invention has been made in view of the above-described circumstances, and an object of the present invention is to enable a reinforced concrete structural frame to support the load of a machine.
[0010]
[Means for Solving the Problems]
In order to achieve the above object, in the machine support method of the present invention, the reinforced concrete structure column members provided with the beam supports protruding in the lateral direction are connected in order, and the main columns are erected at the four locations while the beam supports facing each other. When constructing a building frame by connecting each end of the beam material to the first steel temporary beam, the first steel temporary beam is interposed between two predetermined main columns. Each end is placed on the upper surface of the opposite beam support, and a second steel temporary beam is interposed between the other two main columns, and each end of the second steel temporary beam is placed. After placing the machine stand on the first and second steel temporary beams and mounting the first and second steel temporary beam machine stands on , Each end of the third steel temporary beam is placed on the upper surface of the beam receiver facing above the first steel temporary beam, and each end of the fourth steel temporary beam is Opposite of steel temporary beams The first and second steel temporary beams are mounted on the third and fourth steel temporary beams, and the third and fourth steel temporary beam machines are mounted on the upper surface of the support. After mounting the gantry, each end of the first steel temporary beam is placed on the upper surface of the beam support facing above the third steel temporary beam, and each end of the second steel temporary beam is placed. The end is placed on the upper surface of the beam support facing the upper side of the fourth steel temporary beam, and the mechanical mount on the third and fourth steel temporary beams is made of the first and second steel beams. Repeatedly install the temporary beams.
[0011]
In the machine support method according to the present invention, the first and second steel temporary beams are bridged over the beam support that is integrally formed with the main column and has a predetermined strength. A third and fourth steel temporary installation is carried out on a beam support which is mounted integrally with the main column and has a predetermined strength by mounting a machine mount on the temporary beam and transmitting the load of the machine to the main column. The beam is routed, the machine base mounted on the first and second steel temporary beams is transferred to the third and fourth steel temporary beams, and the load of the machine is transmitted to the main column. 1. Overhanging the second steel temporary beam over the beam support and mounting the mechanical mount on the steel temporary beam; and the third and fourth steel temporary beams over the beam support The work of mounting the machine stand on the fourth steel temporary beam is alternately performed, and the load of the machine is transmitted to the main column while using the two steel temporary beams alternately.
[0012]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
[0013]
1 to 3 show an example of an embodiment of a machine support method according to the present invention. In the figures, the same reference numerals as those in FIGS. 4 and 5 denote the same components.
[0014]
In this machine support method, the reinforced
[0015]
Thereafter, a first steel
[0016]
A
[0017]
The
[0018]
When the
[0019]
After that, the
[0020]
After constructing the desired layer portion, each end of the third steel
[0021]
Subsequently, the
[0022]
At this time, the length of the
[0023]
Further, the
[0024]
When it is necessary to move the crane installation position to the upper floor, the first steel
[0025]
Next, the first and second steel temporary installations in which the
[0026]
Thereafter, the construction of the building frame is advanced by repeating the above-described work.
[0027]
As described above, in the machine support method of the present invention shown in FIGS. 1 to 3, the first, The second steel
[0028]
It should be noted that the machine support method of the present invention is not limited to the above-described embodiment, and various changes can be made without departing from the scope of the present invention.
[0029]
【The invention's effect】
As described above, in the machine support method of the present invention, a pair of steel temporary beams are spanned over a beam receiver that is integrally formed with the main column of the reinforced concrete structure and has a predetermined strength. By mounting the machine base on the temporary steel beam, the load from the machine base is transmitted to the main column via the steel temporary beam, so that the reinforced concrete structure can support the load of the machine. obtain.
[Brief description of the drawings]
FIG. 1 is a conceptual diagram showing an example of an embodiment of a machine support method of the present invention.
FIG. 2 is a view taken in the direction of arrows II-II in FIG.
FIG. 3 is a view taken in the direction of arrows III-III in FIG.
FIG. 4 is a conceptual diagram showing an example of a reinforced concrete structural member.
FIG. 5 is a conceptual diagram showing an example of building building construction work by a conventional reinforced concrete structural member.
[Explanation of symbols]
2
16 Third steel
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002233266A JP3937974B2 (en) | 2002-08-09 | 2002-08-09 | Machine support method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002233266A JP3937974B2 (en) | 2002-08-09 | 2002-08-09 | Machine support method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2004068550A JP2004068550A (en) | 2004-03-04 |
JP3937974B2 true JP3937974B2 (en) | 2007-06-27 |
Family
ID=32018431
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002233266A Expired - Lifetime JP3937974B2 (en) | 2002-08-09 | 2002-08-09 | Machine support method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3937974B2 (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4504747B2 (en) * | 2004-06-25 | 2010-07-14 | 三井住友建設株式会社 | Building construction method using tower crane |
JP2006248675A (en) * | 2005-03-10 | 2006-09-21 | Shimizu Corp | Tower crane support structure |
-
2002
- 2002-08-09 JP JP2002233266A patent/JP3937974B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JP2004068550A (en) | 2004-03-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3952843B2 (en) | Construction method of tower structure | |
JP6289046B2 (en) | Temporary stand | |
KR101891942B1 (en) | Earthquake reinforcement method of existing structure | |
JP2010265727A (en) | Method for demolishing building using floor climbing type tower crane | |
JP5294104B2 (en) | Tower crane support structure | |
JP2790986B2 (en) | Bridge pier construction method and construction method | |
JP5190035B2 (en) | Construction method of seismic isolation structure | |
JP5365854B2 (en) | Tower crane support structure and climbing method | |
JP2011012464A (en) | Method of constructing base isolating structure, and temporary supporting structure for base isolating device | |
JP3937974B2 (en) | Machine support method | |
JP2001010780A (en) | Climbing tower crane and its climbing method | |
JP2004316100A (en) | Construction method for building | |
JP6849491B2 (en) | Exposed column base structure of steel columns and its construction method | |
JP5003253B2 (en) | RC beam construction method | |
KR100769552B1 (en) | Method of bent construction for temporary bridge | |
JP6917720B2 (en) | How to build a composite suspended structure | |
JP6441689B2 (en) | How to install seismic isolation structures | |
JP2021116153A (en) | Supporting platform for tower crane and climbing method using the same | |
JP2018096163A (en) | Method of constructing building | |
JP2009299346A (en) | Construction method of building | |
JP6720761B2 (en) | How to build a ramen structure | |
JPH0932120A (en) | Method of construction of structure | |
JP3903315B2 (en) | Preservation method of existing outer wall structure | |
JP2017203303A (en) | Construction method of composite foundation structure | |
JP3125205B2 (en) | Construction method of temporary side wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050809 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20061221 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20061226 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20070219 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20070313 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20070319 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 3937974 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100406 Year of fee payment: 3 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100406 Year of fee payment: 3 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110406 Year of fee payment: 4 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110406 Year of fee payment: 4 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120406 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130406 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130406 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140406 Year of fee payment: 7 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |