JP3887479B2 - Temporary nourishment and building construction method using the same - Google Patents
Temporary nourishment and building construction method using the same Download PDFInfo
- Publication number
- JP3887479B2 JP3887479B2 JP06364698A JP6364698A JP3887479B2 JP 3887479 B2 JP3887479 B2 JP 3887479B2 JP 06364698 A JP06364698 A JP 06364698A JP 6364698 A JP6364698 A JP 6364698A JP 3887479 B2 JP3887479 B2 JP 3887479B2
- Authority
- JP
- Japan
- Prior art keywords
- building
- temporary
- living body
- panel unit
- support member
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、ビル等を構築するときに用いて好適な仮設養生体およびそれを用いた建物の施工方法に関するものである。
【0002】
【従来の技術】
周知のように、ビル等の建物を施工するに際しては、その外周部に作業足場を確保するために仮設養生体が設けられることが通常である。仮設養生体は、作業足場の確保以外にも、落下養生や外部への塵埃の飛散防止、防音等を目的として建物全体を覆うシート等の遮蔽体の取付、等のためにも利用されるものである。
【0003】
従来一般の仮設養生体は、いわゆる枠組足場を用いて地上より立設する形態のものが最も一般的であるが、これではビル等を構築する場合には足場の組立・解体に多大な手間とコストがかかる。このため、仮設養生体を地上ではなく施工中の建物に支持させて設置し、施工の進捗にともなって仮設養生体全体を順次上方へ盛り替えていくという工法も用いられつつある。
【0004】
【発明が解決しようとする課題】
ところで上述したような従来の仮設養生体およびそれを用いた施工方法には、以下のような問題が存在する。
すなわち、ビル等の建物を構築するに際して用いる仮設養生体は、これを上方に盛り替えるために、各階において仮設養生体の組立・解体を繰り返していたのでは、言うまでもなく多大な手間が掛かり、工期長期化およびコスト上昇を招くという問題がある。
【0005】
このため、自ら上方に昇るためのクライミング機能を備えた複数本の支柱(いわゆるマスト)を施工中の建物上に立て、仮設養生体をこれら支柱上で支持することにより、仮設養生体自体にクライミング機能を備えさせる方法が採用されている。しかし、この方法でも、仮設養生体全体が非常に大型で大重量なものとなるばかりか、システムとしてのコストが非常に高くなってしまうという問題がある。
【0006】
また、他の方法として、仮設養生体をクレーンで吊り上げて盛り替える方法もあるが、この方法においても、仮設養生体を躯体に固定したり取り外したりするのに手間とコストがかかるという問題がある。しかも、仮設養生体の盛替中には、クレーンによる資材搬送作業等が行えず、工事が中断されて工期長期化を招く原因となる。しかも仮設養生体を吊り上げている間は横風が大きく影響するため、強風時等には盛替作業を行えないという問題もある。
【0007】
これ以外にも、仮設養生体を建物に支持させるには、例えば建物の側面にアンカー部材等を取り付ける方法があるが、これではアンカー部材の取付・撤去を建物の外側において行わなければならず、余分な手間が掛かるという問題がある。
【0008】
また、仮設養生体を建物に支持させる他の方法として、図11(a)に示すように、仮設養生体1に、建物Bに向けて延出する支持部材3等を設け、支持部材3の先端部を建物Bのバルコニー4に固定する方法もある。しかし、図11(b)に示すように、この方法においては、仮設養生体1をクレーンやホイスト5等で吊り上げるときに、支持部材3がバルコニー4に干渉してしまうため、支持部材3を一旦取り外したり、あるいは支持部材3がバルコニー4に干渉しないよう仮設養生体1を回避させて上昇させなければならず、いずれも手間が掛かるものとなっていた。
【0009】
さらに、従来より前記支持部材3等で仮設養生体1を建物Bに支持させるときには、建物Bのバルコニー4の立ち上がり部4aを利用して支持部材3を固定していたが、立ち上がり部4aの上面や側面は必ずしも水平面・垂直面ではなく、そのような場合には支持部材3を確実に建物B側に固定することが困難であった。また立ち上がり部4aの表面にタイル等が張られている場合には、支持部材3を固定するときに傷を付ける可能性があるため、その部分だけタイル等を後施工しなければならない等の面倒もあった。
【0010】
本発明は、以上のような点を考慮してなされたもので、容易かつ確実に盛替作業を行うことのできる仮設養生体およびそれを用いた建物の施工方法を提供することを課題とする。
【0011】
【課題を解決するための手段】
請求項1に係る発明は、構築中の建物を覆うように設けられて、工事進捗に伴って漸次上方へ盛り替えられる仮設養生体であって、該仮設養生体は、前記建物上部の施工現場の少なくとも側面を覆う養生体本体と、該養生体本体を建物に支持させる支持部材とを具備してなり、前記養生体本体が、定められた大きさを有した複数枚のパネルユニットを組み合わせることによって構成されていることを特徴としている。
【0012】
このようにして複数枚のパネルユニットで養生体本体を構成することにより、仮設養生体の盛替時にはパネルユニットを一枚ずつ盛り替えればよい。
【0013】
また、前記各パネルユニットが、足場用パイプ等の仮設材によって構成されていることを特徴としている。
【0014】
このようにして足場用パイプ等の仮設材を用いることにより、パネルユニットの大きさを自由に設定することが容易である。また、各パネルユニットを非常に低コストで製作できる。
【0015】
また、前記養生体本体を構成する複数枚の前記パネルユニットが互いに隣接する部分には、互いに隣接する一方の前記パネルユニットの側端部に上下方向に延在するガイドレールが設けられ、他方の前記パネルユニットの側端部に前記ガイドレールに沿った方向にのみ移動自在とされたスライド部材が設けられて、これら互いに隣接する二枚のパネルユニットが上下方向に相対移動可能に連結されていることを特徴としている。
【0016】
これにより、各パネルユニットを上方に盛り替えるときには、当該パネルユニットが、隣接するパネルユニットにガイドレールとスライド部材とを介して上下方向に相対移動可能に連結されているため、隣接するパネルユニットにガイドされて上方に移動されることとなる。
【0017】
また、前記支持部材は、水平面内において回転自在な状態で、一端側が前記養生体本体に折り畳み可能に連結されるとともに、他端側が前記養生体本体側から前記建物側に向けて延出して、前記建物に着脱自在に固定される構成となっていることを特徴としている。
【0018】
これにより、養生体本体を上方に盛り替えるときに支持部材を水平回転させて養生体本体側に折り畳めば、建物側の突起物等との干渉を避けることができる。
【0019】
また、支持部材の他端側には、建物に形成された上方に立ち上がる立ち上がり部の上端部に固定される固定用金物が備えられていることを特徴とする。
これにより、養生体本体を立ち上がり部に対して支持部材および固定用金物を介して安定に支持固定することができる。
【0020】
しかも、前記固定用金物は、前記立ち上がり部の上面および両側面に沿って位置するフレームに、前記立ち上がり部の上面に当接する押さえボルトと、前記立ち上がり部の側面に当接する側部当接部材と、該側部当接部材と相対向する位置に配設されて前記側部当接部材側に向けて進退する締付部材とが設けられた構成とされ、前記側部当接部材が前記フレームに揺動自在に取り付けられ、前記押さえボルトが、前記フレームに一体に溶接されたナットと、このナットに螺合したボルト部材と、ボルト部材の先端部に揺動可能に設けられた支圧プレートとから構成されていることを特徴としている。
このような固定金物によれば、各階の立ち上がり部のレベル誤差等がある場合にも、立ち上がり部のレベルに応じて押さえボルトを調整することによって、固定用金物を確実にセットすることができる。
【0021】
請求項2に係る発明は、前記盛替手段が、前記構築中の建物上で水平移動自在な台車に、一方向に延びるアームが備えられるとともに、該アームの先端部には、前記仮設養生体を吊り上げるホイスト機構が備えられた構成となっていることを特徴としている。
【0022】
これにより、仮設養生体自体に盛替手段を備える必要がなく、また資材搬送用のクレーン等を利用する必要もない。また台車を移動させることによって、例えば養生体本体が複数枚のパネルユニットから構成される場合等には、最小限の台数の盛替手段で養生体本体の盛替作業を行うことができる。
請求項3に係る発明は、前記盛替手段が、前記固定用金物と前記パネルユニットとの間に介装されて該パネルユニットを吊り上げるホイスト機構により構成されていることを特徴としている。
このような盛替手段によっても各パネルユニットの盛替作業を行うことが可能である。
請求項4に係る発明は、前記支持部材が、鉛直方向に延在して前記パネルユニットの鉛直フレームに対して水平面内において回転自在に連結された基部と、該基部から水平方向に延出する延出部と、該延出部を補強する補強材とからなる略L字状とされていることを特徴としている。
これにより、支持部材を簡単な構成でパネルユニットに対して水平面内において回転させて折り畳むことができる。
請求項5に係る発明は、前記支持部材が、鉛直方向に延在して前記パネルユニットの鉛直フレームに対して水平面内において回転自在に連結された基部と、該基部の下端部から水平方向に延出する延出部と、前記基部の上端部と前記延出部の先端部との間に斜めに架設されて延出部を補強する補強材とからなる三角形状とされていることを特徴としている。
これにより、支持部材の強度を大幅に高めて仮設養生体を建物から離す必要がある場合等に好適に用いることができる。
【0023】
請求項6に係る発明は、請求項1〜5のいずれかに記載の仮設養生体を用いた建物の施工方法であって、前記仮設養生体を、前記支持部材で前記建物に支持させ、その内側で前記建物を下方から上方に向けて構築していき、建物の施工の進捗にともなって前記養生体本体を上方に盛り替えるときには、前記養生体本体を構成する前記パネルユニットを一枚ずつ上方に盛り替えていく構成とし、前記各パネルユニットを盛り替えるには、盛替手段で一枚の前記パネルユニットの荷重を支持した後に、該パネルユニットに備えられた前記支持部材を水平面内において回転させて養生体本体側に折り畳み、次いで前記盛替手段で前記パネルユニットを上方に吊り上げ、しかる後に前記支持部材を伸ばして該パネルユニットを前記建物に支持させることを特徴としている。
【0024】
このようにして、パネルユニットを一枚ずつ上方に盛り替えることによって、横風等の影響を避けることができる。また、盛替手段も小型のもので済む。さらに、支持部材を水平面内において回転させて養生体本体側に折り畳むことによって、建物側の突起物等との干渉を避けることができる。
【0025】
【発明の実施の形態】
以下、本発明に係る仮設養生体およびそれを用いた建物の施工方法の実施の形態の一例を、図1ないし図8を参照して説明する。
なお、本発明の仮設養生体における固定用金物の詳細については、固定用金物32’として後述(段落0061および図9参照)するが、以下の実施の形態においては、それとはやや構成の異なる固定用金物32を参考例としてその基本構成および機能について説明する。
これらの図において、符号Bは構築すべき建物、10は建物Bを施工するに際して用いる仮設養生体、をそれぞれ示している。
【0026】
図1および図2に示すように、仮設養生体10は、施工中の建物B(図2参照)の上部施工階の側面を覆う養生体本体11を主体構成としている。
図1に示したように、養生体本体11は、上下方向に所定長を有した略長方形のパネルユニット12を横方向に複数枚連結することによって構成されている。
【0027】
各パネルユニット12は、等間隔毎に上下方向に延在するよう配置された鉛直フレーム13,13,…と、水平方向に延在するよう配置されてこれら鉛直フレーム13,13,…に交差する水平フレーム14,14,…と、これら鉛直フレーム13および水平フレーム14間に架設された補強用のブレース材15,15,…とから構成されている。
【0028】
これら鉛直フレーム13,水平フレーム14,ブレース材15には、足場用の単管パイプ等の仮設材Kが用いられ、これらが互いに交差して連結される部分では、単管パイプ用のクランプ金具Cが用いられている。
【0029】
また、鉛直フレーム13,13,…のうち、両側端部に位置するものを除いた他のものには、これに沿って、上下方向に延在する角パイプからなる補強材16が配設されている。この補強材16は、これに交差する水平フレーム14にクランプ金具Cにより連結されている。そして、二本の補強材16,16が上下に連結される部分には角パイプからなる連結部補強材17が一体に設けられている。
【0030】
図2に示したように、このような各パネルユニット12には、建物Bの側面に面する側の所定位置に、足場取付用のブラケット18と、このブラケット18上に掛け渡された足場板19とが設けられている。
【0031】
また、各パネルユニット12の、建物Bに面する側の反対面側には、メッシュシートや養生シートS等が張設されている。
【0032】
ここで、例えば図1において中央に位置するパネルユニット12Aには、その両側端部に位置する鉛直フレーム13Aに沿ってガイドレール(連結手段)21が備えられている。図3に示すように、ガイドレール21は、平断面視C字状をなした鋼製のチャンネル材等からなり、これには、水平方向に延出する取付部材22,22,…の一端が上下方向所定間隔ごとに一体に設けられている。そして、各取付部材22の他端には、単管パイプ用のクランプ金具Cが一体に取り付けられており、前記ガイドレール21は、これらのクランプ金具Cを介して鉛直フレーム13Aに取り付けられている。
ここでは、図1に示したように、ガイドレール21は各鉛直フレーム13Aの上部と下部にそれぞれ設けられている。
【0033】
そして、上記ガイドレール21を備えたパネルユニット12Aに隣接するパネルユニット12Bには、その両側端部(図1には一方の側端部のみを図示してある)に位置する鉛直フレーム13Aに沿ってスライド部材(連結手段)24が備えられている。
図4に示すように、スライド部材24は、例えば平断面視矩形で、前記ガイドレール21の内側に収められた状態で、その長さはガイドレール21よりも十分に短く、かつその断面方向の外径寸法はガイドレール21の内周面と所定のクリアランスが形成されるよう設定されている。これによりスライド部材24は、ガイドレール21の内側においてこれに沿って上下方向に相対移動可能となっている。そして、スライド部材24には、水平方向に延出する取付部材25の一端が一体に設けられ、その他端には単管パイプ用のクランプ金具Cが一体に取り付けられている。スライド部材24は、取付部材25とクランプ金具Cとを介して鉛直フレーム13Aに取り付けられている。図1に示したように、このスライド部材24は、各鉛直フレーム13Aに上下方向所定間隔毎に複数設けられている。これにより、スライド部材24は、ガイドレール21に対し、その内側に収められた状態で上下方向に相対移動自在とされた構成となっている。
【0034】
このようにして、養生体本体11を構成するため互いに隣接するパネルユニット12A,12Bは、一方のパネルユニット12Aに設けられたガイドレール21と、他方のパネルユニット12Bに設けられたスライド部材24とによって、上下方向に相対移動可能に連結されている。そして、例えばパネルユニット12Aが上下動するときには、パネルユニット12Aの両側のガイドレール21が、それぞれ隣接するパネルユニット12Bのスライド部材24によってガイドされ、これによりこのパネルユニット12Aはその両側端部がガイドされた状態で上下動することとなる。逆に、パネルユニット12Bが上下動するときには、両側のスライド部材24がこれに隣接するパネルユニット12Aのガイドレール21にガイドされ、パネルユニット12Bはその両側端部がガイドされた状態で上下動することとなる。
【0035】
また、図5に示すように、パネルユニット12の所定位置には、このパネルユニット12を建物Bに支持させるための支持部材30が備えられている。支持部材30は、鉛直方向に延在する基部30aと、この基部30aから水平方向に延出する延出部30bと、延出部30bを補強する補強材30cとからなる略L字状で、その一端部側の基部30aが鉛直フレーム13にジョイント金物Dを介して水平面内で回転自在に連結されている。これにより、支持部材30は、水平方向に延出する延出部30bが水平面内で回転自在となり、パネルユニット12に対して折り畳み可能な構成となっている。
【0036】
支持部材30の延出部30bの先端部には、各パネルユニット12を建物Bに支持させるため、建物Bのバルコニー4の先端部に形成されて上方に立ち上がる立ち上がり部31に着脱自在に固定される固定用金物32が設けられている。図5および図6に示すように、固定用金物32は、ウェブとその両端部のフランジとからなるH型鋼を利用したフレーム33に、上部支圧部材(上部当接部材)34,側部支圧部材(側部当接部材)35,ジャッキ部材(締付部材)36が備えられた構成からなっている。
【0037】
図6に示したように、上部支圧部材34は、立ち上がり部31の上面に沿って位置するフレーム33の水平部33a(ウェブの部分)に設けられている。また、側部支圧部材35は、立ち上がり部31の外側面に沿って位置するフレーム33の鉛直部33b(一方のフランジの部分)に設けられている。そして、これら上部支圧部材34,側部支圧部材35は、例えば矩形で板状の支圧プレート34a,35aと、その両端部に一体に形成された支持部34b,34b、35b,35bからなり、支持部34b,34b、35b,35bには、それぞれ所定の位置に所定寸法の内径を有した支持孔37が形成されている。
【0038】
一方、フレーム33の水平部33aと鉛直部33bには、それぞれ、所定位置に軸状の取付部材38が一体に溶接されている。この取付部材38の両端部には、それぞれ図示しないネジ孔にボルト39がねじ込まれ、その頭部がフレーム33から突出するようになっている。このボルト39の頭部は、その外径が前記支持孔37よりも所定寸法小さく設定されている。
【0039】
そして、上部支圧部材34,側部支圧部材35は、その両側の支持部34b,34b、35b,35bの支持孔37,37が、フレーム33に固定されたボルト39,39の頭部に係止されることにより、フレーム33に取り付けられた構成となっている。このとき、支持孔37よりもボルト39の頭部が小径であるので、上部支圧部材34,側部支圧部材35は、それぞれボルト39の軸線回りに揺動自在となっており、その結果、立ち上がり部31の上面および外側面に当接することとなる支圧プレート34a,35aの向きが変更可能となっている。
【0040】
また、前記ジャッキ部材36は、フレーム33の鉛直部33c(他方のフランジの部分)に、側部支圧部材35と相対向するよう設けられている。ジャッキ部材36は、フレーム33の鉛直部33cに一体に溶接されたナット36aと、このナット36aに螺合したジャッキボルト36bと、このジャッキボルト36bの先端部にボールジョイント(図示なし)を介して揺動可能に設けられた支圧プレート36cとから構成されている。ジャッキボルト36bは、その基端部側を工具で回転させることによって、その軸線方向、すなわち側部支圧部材35に向けて進退移動するようになっている。
【0041】
図5に示したように、このような固定用金物32は、上部支圧部材34を建物Bのバルコニー4の立ち上がり部31の上面に当接させ、側部支圧部材35を立ち上がり部31の一側面に当接させた状態で、ジャッキ部材36のジャッキボルト36bをねじ込み、先端部の支圧プレート36cを立ち上がり部31の他側面に押し付けることによって、立ち上がり部31に固定されるようになっている。このとき、上部支圧部材34と側部支圧部材35は、それぞれフレーム33に揺動自在に設けられ、またジャッキ部材36の支圧プレート36cもジャッキボルト36bに揺動自在に設けられている。したがって、立ち上がり部31の上面,側面が水平面,鉛直面に対して傾斜していても、上部支圧部材34,側部支圧部材35,支圧プレート36cが立ち上がり部31の上面,側面に倣って揺動し、確実に当接するようになっている。しかも、上部支圧部材34の支圧プレート34a,側部支圧部材35の支圧プレート35a,支圧プレート36cは、それぞれ立ち上がり部31に当接する側が平面をなしているので、立ち上がり部31に対して面接触するようになっている。
【0042】
この構成からなる固定用金物32は、鉄骨クランプ40,40を介して支持部材30の延出部30bに沿って移動可能に取り付けられており、これにより固定用金物32を延出部30bの任意の位置に固定できるようになっている。
【0043】
次に、このような構成からなる仮設養生体10を上方に盛り替えるための盛替装置について説明する。
図2に示したように、盛替装置(盛替手段)45は、下面に車輪46,46,…を備えて走行移動自在な台車47と、この台車47の一端部に備えられた固定用ジャッキ48と、台車47の一端部から水平方向に延出するアーム49と、アーム49の先端部に備えられたホイスト機構50とから構成されている。ホイスト機構50は、先端にフック51を備えたワイヤー52と、このワイヤー52を巻き取り・繰り出しするウインチ53とから構成されている。なお、この盛替装置45は、モータ等の駆動機構54で車輪46を回転駆動させることによって、施工中の建物Bの各階の床面上で自走可能となっている。
【0044】
続いて、上記構成からなる仮設養生体10を用いた建物Bの施工方法について説明する。
建物Bを施工しているときには、仮設養生体10は少なくとも施工階の外周を覆うよう設置する。これには、養生体本体11を構成する複数枚のパネルユニット12を、それぞれ、各支持部材30を建物Bに向けて伸ばし、その先端部の固定用金物32をバルコニー4の立ち上がり部31に固定する。すると、各パネルユニット12は、それぞれそれ自体が建物Bに固定された状態となる。さらに、図1に示したように、互いに隣接するパネルユニット12,12どうしは、ガイドレール21とスライド部材24とによって互いに連結された状態となる。そして、各パネルユニット12の外周面に養生シートS等を張設することにより、建物Bの施工階は、その外周が全周にわたって養生されることとなる。
【0045】
そして、施工の進捗に伴い、仮設養生体10を上方に盛り替えるときには、基本的に、仮設養生体10の養生体本体11を構成する複数枚のパネルユニット12を、一枚ずつ盛り替えるようにする。これには、まず、図2に示したように、盛替装置45を建物Bの外周面側に移動させ、盛り替えるべきパネルユニット12に対向させ、固定用ジャッキ48を伸ばして固定する。次いで、アーム49の先端部を、バルコニー4の立ち上がり部31よりも外側で、かつパネルユニット12よりも内側となるよう位置させ、ホイスト機構50のワイヤー52を伸ばしてフック51を下げ、このフック51をパネルユニット12の所定位置に係止させる。
【0046】
次いで、図5に示した各支持部材30の先端部の固定用金物32において、ジャッキ部材36のジャッキボルト36bを緩め、バルコニー4の立ち上がり部31への固定を解除する。
【0047】
続いて、盛替装置45のホイスト機構50のウインチ53を作動させてワイヤー52を巻き取り、これによってフック51が係止されたパネルユニット12を上昇させる。このとき、図1に示したように、このパネルユニット12は、ガイドレール21とスライド部材24とがスライド自在に連結されているので、隣接する両側のパネルユニット12にガイドされた状態で上昇することとなる。
【0048】
そして、図7に示すように、固定用金物32がバルコニー4の立ち上がり部31から外れ、その上方に位置した状態で、ウインチ53の作動を一旦停止させる。この状態で各支持部材30を水平方向に90°回転させてパネルユニット12側に折り畳むことによりパネルユニット12に沿わせた状態とする。
【0049】
この後、ウインチ53を再作動させ、パネルユニット12を、盛り替えるべき所定の位置よりも若干上方の位置まで上昇させる。そして、ウインチ53を停止させた後、各支持部材30を広げ、建物B側に向けて突出させた状態とする。この状態で、ウインチ53を作動させて、今度はワイヤー52を繰り出してパネルユニット12を下降させる。そして、図8に示すように、各支持部材30の先端部の固定用金物32が上階のバルコニー4の立ち上がり部31にはまり込み、図6に示した上部支圧部材34の支圧プレート34aが立ち上がり部31の上面に当接した時点で、ウインチ53の作動を停止させる。次いで、ジャッキ部材36のジャッキボルト36bを締め付け、固定用金物32を立ち上がり部31に確実に固定する。
【0050】
そして、盛替装置45のホイスト機構50のフック51をこのパネルユニット12から取り外し、ワイヤー52を巻き取ることによって、このパネルユニット12の盛替作業が完了する。
【0051】
しかる後には、上記と同様にしてパネルユニット12を一枚ずつ順次上方に盛り替えていき、総てのパネルユニット12の盛替が完了した時点で、盛替装置45をクレーン等で上階に盛り替える。これにより、仮設養生体10の盛替作業が完了したこととなる。この後は、新たな施工階の施工と、仮設養生体10の盛替とを交互に繰り返していくことにより、建物Bを最上階まで構築していく。
【0052】
上述した仮設養生体10および建物Bの施工方法では、仮設養生体10が、複数枚のパネルユニット12からなる養生体本体11と、この養生体本体11を建物Bに支持させるため折り畳み可能とされた支持部材30と、養生体本体11を盛り替えるため建物B上において自走可能とされた盛替装置45とを備えてなる構成となっている。そして、このような仮設養生体10を施工中の建物Bに設け、施工の進捗にともなって仮設養生体10を盛り替えるときには、盛替装置45でパネルユニット12を一枚ずつ吊り上げて盛り替える構成となっている。
このようにして、パネルユニット12を一枚ずつ上方に盛り替えることによって、盛替作業を効率良く行うことができる。したがって、工事全体の短工期化と低コスト化に貢献することができる。また、横風等の影響も最小限に抑えることができるので、工期の長期化を防止するとともに作業安全性を確保することができる。また、このように簡易な構成からなる仮設養生体10は、特に中小規模のビル等にも好適に用いることが可能である。
【0053】
また、各パネルユニット12が、足場用パイプ等の仮設材Kによって形成された構成となっている。
これにより、各パネルユニット12を非常に安価で製作することができ、これによっても低コスト化への貢献が可能である。さらに、パネルユニット12を軽量なものとすることができるので、盛替作業を容易に行うことができ、これを持ち上げるための機器も、クレーン等の大掛かりなものでなく、簡易な盛替装置45で可能である。したがって、本来資材搬送用のものであるクレーン等の占有を回避し、工事全体を効率良く行うことができる。また、仮設材Kを用いることにより、パネルユニット12の大きさを自由に設定することが容易であり、したがって、建物Bの大きさや形状等に応じて容易に対応することができるので、この仮設養生体10を他の現場にも転用することが可能であり、より一層コストパフォーマンスに優れたものとすることができる。
【0054】
さらに、複数枚のパネルユニット12が互いに隣接する部分には、一方のパネルユニット12の側端部にガイドレール21が設けられ、他方のパネルユニット12の側端部にスライド部材24が設けられた構成となっている。
これにより、互いに隣接するパネルユニット12,12は、上下方向に相対移動可能に連結された構成となり、各パネルユニット12を上方に盛り替えるときには、その両側端部を隣接するパネルユニット12,12でガイドすることができる。したがって、各パネルユニット12を安定した状態で確実に盛り替えることができ、強風等による影響を最小限に抑え、工期の長期化を抑えるとともに作業安全性を確保することができる。しかも、このようなガイドレール21やスライド部材24は、建物B側に取り付ける必要がないことから、余計な手間を省くことができる。
【0055】
加えて、支持部材30が水平方向に回転自在とされて折り畳み可能となっているので、パネルユニット12の吊り上げ時に支持部材30がバルコニー4などの突起物と干渉することもなく、吊り上げ作業を容易に行うことができる。しかも、この支持部材30の先端部には固定用金物32が備えられて、支持部材30の先端部が建物Bに着脱自在に固定できる構成となっている。したがって、建物B側には、仮設養生体10を固定するためのアンカー部材やブラケット等を一切取り付ける必要がなく、仮設養生体10の建物Bへの固定を容易に行うことができ、この点においても作業の効率化を図ることができる。
【0056】
しかも、固定用金物32は、フレーム33に、上部支圧部材34と、側部支圧部材35と、ジャッキ部材36とが設けられた構成とされて、上部支圧部材34と側部支圧部材35とがフレーム33に揺動自在に取り付けられた構成となっている。
これにより、ジャッキ部材36のジャッキボルト36bを操作するのみで、固定用金物32を建物Bのバルコニー4の立ち上がり部31に容易に固定することができる。また、上部支圧部材34と側部支圧部材35とがフレーム33に揺動自在に取り付けられているので、立ち上がり部31の表面が水平面や鉛直面でない場合にも、上部支圧部材34と側部支圧部材35とを立ち上がり部31の表面に確実に当接させることができ、固定用金物32を確実に固定することができる。しかも、上部支圧部材34の支圧プレート34a,側部支圧部材35の支圧プレート35a,ジャッキ部材36の支圧プレート36cが立ち上がり部31に面接触する構成となっているので、立ち上がり部31にタイル等が貼着されている場合にも、これを破損したり傷を付けたりするのを防止することができる。
【0057】
さらに、この固定用金物32は、鉄骨クランプ40,40を介して支持部材30の延出部30bに取り付けられており、延出部30bの長さ方向の任意の位置に固定できるようになっている。これによりこの仮設養生体10を他の現場に転用するとき等には、固定用金物32の位置を変更することによって、仮設養生体10と建物Bとの位置が変わる場合にも対応が可能となっている。
【0058】
また、仮設養生体10には、養生体本体11を上方に盛り替えていくための専用の盛替装置45が備えられている。これにより、仮設養生体10自体にマスト等のクライミング手段を備える必要がなく、仮設養生体10全体を軽量かつ簡易な構成とすることができ、短工期化および低コスト化に貢献できる。また資材搬送用のクレーン等を利用する必要もないので、機器使用の効率化を図ることができる。さらに、複数枚のパネルユニット12から構成される養生体本体11を盛り替えるときには、この盛替装置45を移動させることによって、最小限の台数の盛替装置45でパネルユニット12、すなわち養生体本体11の盛替作業を行うことができ、より一層の作業の効率化およびそれによる低コスト化を図ることができる。
【0059】
なお、上記実施の形態においてあげた構成は、本願発明の主旨を逸脱しない限り、他の構成に変更可能である。すなわち、例えば各パネルユニット12の構造や使用材料等は適宜の仮設材を用いれば良く、仮設養生体10の規模によっては、パネルユニット12を単管パイプではなく枠組み足場を用いて構成してもよい。
【0060】
また、支持部材30の形状や使用材料についても、同様に何ら限定するものではない。例えば、図9に示すように、支持部材30’を、鉛直方向に延在する基部30a’と、この基部30a’の下端部から水平方向に延出する延出部30b’と、延出部30b’を補強するため基部30a’の上端部と延出部30b’の先端部との間に斜めに架設された補強材30c’とからなる構成のものとしても良い。このような支持部材30’によれば、上記実施の形態で示した支持部材30(図5参照)よりも強度が大幅に高められ、これによって仮設養生体10を建物Bから離す必要がある場合等に好適に用いることができる。
【0061】
但し、固定用金物については、以上で説明した参考例としての固定用金物32に代えて、図9に示す固定用金物32’を採用する。この固定用金物32’は、上部支圧部材34(図6参照)に代えて、押さえボルト60が備えられたものである。押さえボルト60は、ジャッキ部材36と同様の構造で、フレーム33に一体に溶接されたナット60aと、このナット60aに螺合したボルト部材60bと、ボルト部材60bの先端部に揺動可能に設けられた支圧プレート60cとから構成されている。このような押さえボルト60を備えた固定用金物32’では、各階のバルコニー4の立ち上がり部31のレベル誤差等がある場合にも、立ち上がり部31のレベルに応じて押さえボルト60を調整することによって、固定用金物32’を確実にセットすることができる。
【0062】
加えて、上記実施の形態では固定用金物32をバルコニー4の立ち上がり部31に固定する構成としたが、もちろん他の部分に固定しても良い。
さらに、上部支圧部材34,側部支圧部材35は、固定用金物32を取り付ける立ち上がり部31の形状によっては、いずれか一方のみを揺動可能とする構成としても良い。
【0063】
同様に、盛替装置45の構成についても、建物Bの施工階において移動可能であればその構成を何ら問うものではない。
【0064】
また、例えば建物Bの床のコンクリート強度が不十分である場合等には、盛替装置45に代えて図10に示すような盛替手段を採用しても良い。これは、固定用金物32のフレーム33に支柱フレーム65を一体に設けておき、これをバルコニー4の立ち上がり部31に取り付ける。そして、この支柱フレーム65に係止金具66を用いて盛替手段としてのホイスト機構50のウインチ53を取り付け、各パネルユニット12の鉛直フレーム13には掛止ワイヤー67を用いてフック51を係止させる。また、ワイヤー52の途中には、滑車68,69をセットする。このとき、滑車69は、固定用金物32に取り付けられた金具70に取り付けるようにする。このように、固定用金物32とパネルユニット12との間に盛替手段としてのホイスト機構50をセットすることによっても各パネルユニット12の盛替作業を行うことが可能である。
【0065】
もちろん、仮設養生体10の規模やクレーンの使用状況等によっては、各パネルユニット12をクレーン等、他の盛替手段で盛り替えるようにしても良い。
【0066】
これ以外にも、本発明の主旨を逸脱しない範囲内であれば、いかなる構成を採用しても良く、また上記したような構成、すなわち、パネルユニット12,支持部材30,固定用金物32,盛替装置45等の構成を適宜選択的に組み合わせて用いる構成としても良いのは言うまでもない。
【0067】
【発明の効果】
以上説明したように、請求項1に係る仮設養生体によれば、仮設養生体は、養生体本体と、これを建物に支持させる支持部材とを具備してなり、養生体本体が複数枚のパネルユニットを組み合わせることによって構成された構成となっている。このように仮設養生体のユニット化を図ることにより、仮設養生体の盛替時にはパネルユニットを一枚ずつ盛り替えればよく、盛替作業を効率良く行うことができる。したがって、工事全体の短工期化と低コスト化に貢献することができる。また、このように簡易な構成からなる仮設養生体は、特に中小規模のビル等にも好適に用いることが可能である。
【0068】
また、各パネルユニットが、足場用パイプ等の仮設材によって形成された構成となっている。このようにして仮設材を用いることにより、パネルユニットの大きさを自由に設定することが容易であり、したがって、建物の大きさや形状等に応じて容易に対応することができる。また、各パネルユニットを非常に安価で製作することができ、これによっても低コスト化への貢献が可能である。さらに、パネルユニットを軽量なものとすることもできるので、盛替作業を容易に行うことができ、これを持ち上げるための機器も、クレーン等の大掛かりなものでなく、ホイスト等の簡易な機器で可能である。したがって、クレーン等の占有を回避し、工事全体を効率良く行うことができる。
【0069】
また、複数枚のパネルユニットが互いに隣接する部分には、一方のパネルユニットの側端部にガイドレールが設けられ、他方のパネルユニットの側端部にスライド部材が設けられることによって、これら二枚のパネルユニットが上下方向に相対移動可能に連結された構成となっている。これにより、各パネルユニットを上方に盛り替えるときには、その両側端部が隣接するパネルユニットにガイドされることとなる。したがって、各パネルユニットを安定した状態で確実に盛り替えることができ、強風等による影響を最小限に抑え、工期の長期化を抑えるとともに作業安全性を確保することができる。しかも、このようなガイドレールやスライド部材は、建物側に取り付ける必要がないことから、余計な手間を省くことができる。
【0070】
また、仮設養生体は、養生体本体と支持部材とを具備し、支持部材は、水平面内において回転自在な状態で一端側が養生体本体に折り畳み可能に連結され、他端側が建物に着脱自在に固定される構成となっている。これにより、養生体本体を上方に盛り替えるときには、支持部材を水平回転させて折り畳むことにより、建物側の突起物等との干渉を避けることができ、盛替作業を容易に行うことができる。また、養生体本体を建物に支持させるときに、建物側にアンカー部材等を取り付ける必要がなく、建物への固定を容易に行うことができ、この点においても作業の効率化を図ることができる。
【0071】
さらに、仮設養生体の養生体本体を建物に支持させるための支持部材には固定用金物が備えられているので、養生体本体を立ち上がり部に対して支持部材および固定用金物を介して安定に支持固定することができる。
しかも、固定用金物は立ち上がり部の上面および両側面に沿って位置するフレームに、押さえボルトと側部当接部材と締付部材とが設けられた構成とされ、側部当接部材がフレームに揺動自在に取り付けられ、押さえボルトがフレームに一体に溶接されたナットと、このナットに螺合したボルト部材と、ボルト部材の先端部に揺動可能に設けられた支圧プレートとから構成されている。
このような固定金物によれば、各階の立ち上がり部のレベル誤差等がある場合にも、立ち上がり部のレベルに応じて押さえボルトを調整することによって、固定用金物を確実にセットすることができる。
【0072】
請求項2に係る仮設養生体によれば、仮設養生体の養生体本体を上方に盛り替えていくための盛替手段として、建物上で水平移動自在な台車のアームに、仮設養生体を吊り上げるホイスト機構を備える構成となっている。これにより、仮設養生体自体に盛替手段を備える必要がなく、仮設養生体自体を軽量かつ簡易な構成とすることができ、短工期化および低コスト化に貢献できる。また資材搬送用のクレーン等を利用する必要もないので、機器使用の効率化を図ることができる。さらに、例えば養生体本体が複数枚のパネルユニットから構成される場合等には、このような台車を移動させることによって対応が可能であるので、最小限の台数の盛替手段で養生体本体の盛替作業を効率良く行うことが可能である。
請求項3に係る発明によれば、盛替手段が固定用金物と前記パネルユニットとの間に介装されて該パネルユニットを吊り上げるホイスト機構により構成されているので、このような盛替手段によっても各パネルユニットの盛替作業を行うことが可能である。
請求項4に係る発明によれば、支持部材が、鉛直方向に延在して前記パネルユニットの鉛直フレームに対して水平面内において回転自在に連結された基部と、該基部から水平方向に延出する延出部と、該延出部を補強する補強材とからなる略L字状とされているので、支持部材を簡単な構成でパネルユニットに対して水平面内において回転させて折り畳むことができる。
請求項5に係る発明によれば、支持部材が、鉛直方向に延在して前記パネルユニットの鉛直フレームに対して水平面内において回転自在に連結された基部と、該基部の下端部から水平方向に延出する延出部と、前記基部の上端部と前記延出部の先端部との間に斜めに架設されて延出部を補強する補強材とからなる三角形状とされているので、支持部材の強度を大幅に高めて仮設養生体を建物から離す必要がある場合等に好適に用いることができる。
【0073】
請求項6に係る建物の施工方法によれば、仮設養生体の内側で建物を構築していき、養生体本体を上方に盛り替えるときには、盛替手段でパネルユニットの荷重を支持した後に、支持部材を水平面内において回転させて養生体本端側に折り畳み、次いで盛替手段でパネルユニットを上方に吊り上げ、しかる後に支持部材を伸ばしてパネルユニットを建物に支持させることによって、パネルユニットを一枚ずつ上方に盛り替えていく構成となっている。
このようにして、パネルユニットを一枚ずつ上方に盛り替えることによって、盛替作業を効率良く行うことができる。したがって、工事全体の短工期化と低コスト化に貢献することができる。また、横風等の影響も最小限に抑えることができるので、工期の長期化を防止するとともに作業安全性を確保することができる。また、盛替手段も小型のもので済むので、この点においても作業を効率良く行うことができる。さらに、支持部材を水平面内において回転させて折り畳むことによって、パネルユニットの盛替時に建物側の突起物等との干渉を避けることができ、作業を容易に行うことができる。
【図面の簡単な説明】
【図1】 本発明に係る仮設養生体の一例を示す図であって、仮設養生体を建物に取り付けた状態を示す立面図である。
【図2】 同仮設養生体を建物に取り付けた状態を示す側断面図である。
【図3】 同仮設養生体に備えたガイドレールを示す立面図および平断面図である。
【図4】 同仮設養生体に備えたスライド部材を示す立面図および平断面図である。
【図5】 同仮設養生体の建物への固定構造を示す側断面図である。
【図6】 同仮設養生体の固定に用いる固定用金物を示す立面図および下面図である。
【図7】 同仮設養生体の盛替方法を示す工程図であって、仮設養生体を持ち上げて建物から取り外した状態を示す図である。
【図8】 同、仮設養生体を上階に盛り替えた状態を示す図である。
【図9】 本発明に係る仮設養生体の他の一例を示す図であって、仮設養生体の建物への他の固定構造を示す側断面図である。
【図10】 同、仮設養生体の他の盛替方法を示す側断面図である。
【図11】 従来の仮設養生体の盛り替え方法の一例を示す工程図である。
【符号の説明】
10 仮設養生体
11 養生体本体
12 パネルユニット
13 鉛直フレーム
21 ガイドレール(連結手段)
24 スライド部材(連結手段)
30、30’ 支持部材
30a、30a’ 基部
30b、30b’ 延出部
30c、30c’ 補強材
32、32’ 固定用金物
33 フレーム
34 上部支圧部材(上部当接部材)
35 側部支圧部材(側部当接部材)
36 ジャッキ部材(締付部材)
45 盛替装置(盛替手段)
47 台車
49 アーム
50 ホイスト機構(盛替手段)
60 押さえボルト
60a ナット
60b ボルト部材
60c 支圧プレート
B 建物
K 仮設材[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a temporary living body suitable for use in building a building and the like, and a building construction method using the same.
[0002]
[Prior art]
As is well known, when a building such as a building is constructed, a temporary living body is usually provided on the outer periphery of the building in order to secure a working scaffold. Temporary living organisms are used not only for securing working scaffolds, but also for the purpose of drop curing, prevention of dust scattering to the outside, and installation of shields such as sheets that cover the entire building for the purpose of soundproofing, etc. It is.
[0003]
Conventionally, general temporary living organisms are most commonly installed on the ground using a so-called framework scaffold, but this requires a great deal of labor to assemble and disassemble the scaffold when building a building or the like. costly. For this reason, a construction method is being used in which a temporary living body is installed not on the ground but supported on a building under construction, and the entire temporary living body is rearranged sequentially upward as the construction progresses.
[0004]
[Problems to be solved by the invention]
By the way, the following temporary problems and the construction method using the same have the following problems.
In other words, the temporary living body used when building a building or the like has been repeatedly assembled and disassembled on each floor in order to rearrange it upwards. There is a problem of incurring longer time and higher costs.
[0005]
For this reason, climbing on the temporary living body itself by standing a plurality of struts (so-called masts) equipped with a climbing function for ascending upward on the building under construction and supporting the temporary living body on these struts A method of providing a function is adopted. However, even with this method, there is a problem that the temporary living body as a whole becomes very large and heavy, and the cost of the system becomes very high.
[0006]
In addition, as another method, there is a method in which the temporary living body is lifted with a crane and rearranged, but this method also has a problem that it takes time and cost to fix or remove the temporary living body from the housing. . In addition, during the replacement of the temporary living body, the material transfer operation by the crane cannot be performed, and the construction is interrupted, leading to a prolonged construction period. In addition, while the temporary living body is being lifted, the crosswind is greatly affected, so that there is a problem that the replacement work cannot be performed in a strong wind.
[0007]
In addition to this, in order to support the temporary living body in the building, for example, there is a method of attaching an anchor member or the like to the side of the building, but in this, the anchor member must be attached and removed outside the building, There is a problem that it takes extra time.
[0008]
In addition, as another method of supporting the temporary living body in the building,FIG.As shown in (a), there is also a method in which a temporary support body 1 is provided with a
[0009]
Further, conventionally, when the temporary living body 1 is supported on the building B by the
[0010]
The present invention has been made in consideration of the above points, and it is an object of the present invention to provide a temporary living body capable of performing refilling work easily and reliably and a method for constructing a building using the temporary living body. .
[0011]
[Means for Solving the Problems]
The invention according to claim 1 is a temporary living organism that is provided so as to cover a building under construction and that is gradually rearranged upward as construction progresses, and the temporary living organism is a construction site in the upper part of the building A living body main body covering at least a side surface of the body and a support member for supporting the living body main body on a building, wherein the body body is combined with a plurality of panel units having a predetermined size. It is characterized by comprising.
[0012]
In this way, by configuring the biological body with a plurality of panel units, the panel units may be replaced one by one when the temporary biological body is replaced.
[0013]
Also,Each said panel unit is comprised by temporary materials, such as a pipe for scaffolds, It is characterized by the above-mentioned.
[0014]
By using temporary materials such as scaffolding pipes in this way, it is easy to freely set the size of the panel unit. Moreover, each panel unit can be manufactured at a very low cost.
[0015]
Also,A guide rail extending in the vertical direction is provided at a side end portion of one of the panel units adjacent to each other at a portion where the plurality of panel units constituting the living body are adjacent to each other, and the other panel A slide member that is movable only in the direction along the guide rail is provided at the side end of the unit, and these two adjacent panel units are connected so as to be movable relative to each other in the vertical direction. It is a feature.
[0016]
Thus, when each panel unit is rearranged upward, the panel unit is connected to the adjacent panel unit so as to be relatively movable in the vertical direction via the guide rail and the slide member. It is guided and moved upward.
[0017]
The support member is rotatable in a horizontal plane.The one end side is foldably connected to the body, and the other end extends from the body side toward the building and is detachably fixed to the building. It is characterized by.
[0018]
This allows the support member to beRotate horizontally to the bodyIf it is folded, it is possible to avoid interference with protrusions on the building side.
[0019]
In addition, the other end side of the support member is provided with a fixing hardware that is fixed to the upper end portion of the rising portion that rises upward formed in the building.It is characterized by that.
Thereby, the living body main body can be stably supported and fixed to the rising portion via the support member and the fixing hardware.
[0020]
Moreover,The fixing hardware includes, on a frame positioned along the upper surface and both side surfaces of the rising portion, a holding bolt that contacts the upper surface of the rising portion, a side contact member that contacts the side surface of the rising portion, A tightening member disposed at a position opposite to the side contact member and moving forward and backward toward the side contact member is provided, and the side contact member swings against the frame. A nut that is movably attached and the holding bolt is integrally welded to the frame, a bolt member that is screwed to the nut, and a support plate that is swingably provided at the tip of the bolt member It is characterized by being composed.
According to such a fixed hardware, even when there is a level error or the like of the rising portion of each floor, the fixing hardware can be surely set by adjusting the holding bolt according to the level of the rising portion.
[0021]
Claim 2In the invention according to the present invention, the refilling means is provided with an arm extending in one direction on a cart that is horizontally movable on the building under construction, and a hoist that lifts the temporary living body at a tip portion of the arm It is characterized by having a mechanism.
[0022]
Thereby, it is not necessary to provide the replacement means in the temporary living body itself, and it is not necessary to use a crane for transporting materials. Further, by moving the carriage, for example, when the biological body is composed of a plurality of panel units, the biological body can be replaced with a minimum number of replacement units.
Claim 3According to the present invention, the refilling means is configured by a hoist mechanism that is interposed between the fixing hardware and the panel unit to lift the panel unit.
It is possible to perform the replacement work of each panel unit also by such replacement means.
Claim 4According to the invention, the support member extends in the vertical direction and is connected to the vertical frame of the panel unit so as to be rotatable in a horizontal plane, and an extension portion extending from the base portion in the horizontal direction And a reinforcing material that reinforces the extending portion.
Accordingly, the support member can be folded by being rotated in a horizontal plane with respect to the panel unit with a simple configuration.
Claim 5According to the invention, the support member extends in a horizontal direction from a lower end portion of the base portion that extends in the vertical direction and is rotatably connected to the vertical frame of the panel unit in a horizontal plane. It is characterized by having a triangular shape composed of an extending portion and a reinforcing material that is obliquely installed between the upper end portion of the base portion and the distal end portion of the extending portion and reinforces the extending portion.
Thereby, it can use suitably, when it is necessary to raise the intensity | strength of a supporting member significantly and to separate a temporary living body from a building.
[0023]
Claim 6The invention according toClaims 1-5A building construction method using the temporary living body according to any one of the above, wherein the temporary living body is supported by the building with the support member, and the building is constructed from the bottom to the top inside. When the living body is rearranged upward as the construction of the building progresses, the panel units constituting the living body are rearranged one by one upward, and each panel unit is For reordering, after supporting the load of the one panel unit by the reordering means, the support member provided in the panel unit is rotated in a horizontal plane and folded to the side of the biological body, and then the reordering The panel unit is lifted upward by means, and then the support member is extended to support the panel unit on the building.
[0024]
In this way, the effect of cross winds can be avoided by rearranging the panel units one by one upward. Further, the replacement means can be small. In addition, the support memberRotate in a horizontal plane to the body sideBy folding, it is possible to avoid interference with protrusions on the building side.
[0025]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, an example of an embodiment of a temporary living body and a building construction method using the same according to the present invention will be described with reference to FIGS. 1 to 8.
The details of the fixing hardware in the temporary living body of the present invention will be described later as the fixing
In these drawings, symbol B indicates a building to be constructed, and numeral 10 indicates a temporary living body used when constructing the building B.
[0026]
As shown in FIGS. 1 and 2, the
As shown in FIG. 1, the living body main body 11 is configured by connecting a plurality of substantially
[0027]
Each
[0028]
The
[0029]
Further, among the
[0030]
As shown in FIG. 2, each
[0031]
Further, a mesh sheet, a curing sheet S, and the like are stretched on the opposite side of each
[0032]
Here, for example, the panel unit 12A located at the center in FIG. 1 is provided with guide rails (connecting means) 21 along the
Here, as shown in FIG. 1, the guide rails 21 are provided at the upper and lower portions of each
[0033]
The
As shown in FIG. 4, the
[0034]
In this way, the
[0035]
As shown in FIG. 5, a
[0036]
In order to support each
[0037]
As shown in FIG. 6, the
[0038]
On the other hand, a shaft-shaped
[0039]
The
[0040]
The
[0041]
As shown in FIG. 5, such a fixing
[0042]
The fixing
[0043]
Next, a reordering device for reordering the
As shown in FIG. 2, the refilling device (refilling means) 45 includes a
[0044]
Then, the construction method of the building B using the
When constructing the building B, the
[0045]
And when the
[0046]
Next, in the fixing
[0047]
Subsequently, the
[0048]
Then, as shown in FIG. 7, the operation of the
[0049]
Thereafter, the
[0050]
Then, the
[0051]
After that, the
[0052]
In the construction method for the
Thus, the reordering operation can be performed efficiently by rearranging the
[0053]
In addition, each
Thereby, each
[0054]
Further, a
Thereby, the
[0055]
In addition, the support member 30It can be rotated horizontallySince it is foldable, the
[0056]
Moreover, the fixing
Accordingly, the fixing
[0057]
Further, the fixing
[0058]
In addition, the
[0059]
The configuration described in the above embodiment can be changed to other configurations without departing from the gist of the present invention. That is, for example, the structure and materials used for each
[0060]
Also,Support member 30Similarly, the shape and materials used are not limited in any way. For example, as shown in FIG. 9, the
[0061]
However, for the fixing hardware, a fixing
[0062]
In addition, although the fixing
Furthermore, the
[0063]
Similarly, as for the configuration of the
[0064]
For example, when the concrete strength of the floor of the building B is insufficient, the refilling device 45Instead ofAs shown in FIG.Replacement meansMay be adopted.this is,A
[0065]
Of course, each
[0066]
Other than this, any configuration may be adopted as long as it does not depart from the gist of the present invention, and the configuration as described above, that is, the
[0067]
【The invention's effect】
As described above, according to the temporary living body according to claim 1, the temporary living body includes the living body main body and the support member that supports the living body to the building, and the living body body includes a plurality of living body bodies. It is configured by combining panel units. Thus, by unitizing a temporary living body, the panel unit should be replaced one by one at the time of replacement of a temporary living body, and the replacement work can be performed efficiently. Therefore, it is possible to contribute to shortening the construction period and reducing the cost of the entire construction. In addition, the temporary living body having such a simple configuration can be suitably used particularly for a small and medium-sized building.
[0068]
Also,Each panel unit is configured by a temporary material such as a pipe for scaffolding. By using the temporary material in this way, it is easy to freely set the size of the panel unit, and accordingly, it is possible to easily cope with the size and shape of the building. In addition, each panel unit can be manufactured at a very low cost, and this can also contribute to cost reduction. Furthermore, since the panel unit can be made lightweight, the refilling work can be easily performed, and the equipment for lifting it is not a large one such as a crane, but a simple equipment such as a hoist. Is possible. Therefore, occupation of a crane etc. can be avoided and the whole construction can be performed efficiently.
[0069]
Also,When two or more panel units are adjacent to each other, a guide rail is provided at the side end of one panel unit, and a slide member is provided at the side end of the other panel unit. The units are connected so as to be relatively movable in the vertical direction. As a result, when each panel unit is rearranged upward, both end portions thereof are guided by the adjacent panel unit. Therefore, each panel unit can be reliably replaced in a stable state, the influence of strong winds or the like can be minimized, the construction period can be prolonged, and work safety can be ensured. And since such a guide rail and a slide member do not need to be attached to the building side, an extra effort can be saved.
[0070]
Also,The temporary nurturing body includes a nurturing body and a support member,In a state where it can rotate in a horizontal planeOne end side is foldably connected to the biological body, and the other end side is detachably fixed to the building. As a result, when changing the body of the biological body upward,Rotate horizontallyBy folding, it is possible to avoid interference with building-side protrusions and the like, and refilling work can be easily performed. In addition, when the body is supported on the building, there is no need to attach an anchor member or the like to the building side, and it can be easily fixed to the building, and also in this respect, work efficiency can be improved. .
[0071]
Furthermore, since the support member for supporting the biological body of the temporary living body on the building is provided with a fixing hardware, the biological body is stable with respect to the rising portion via the supporting member and the fixing hardware. It can be supported and fixed.
Moreover,The fixing hardware is configured such that a holding bolt, a side contact member, and a tightening member are provided on a frame positioned along the upper surface and both side surfaces of the rising portion, and the side contact member swings on the frame. It is composed of a nut that is freely attached and a holding bolt is integrally welded to the frame, a bolt member that is screwed to the nut, and a support plate that is swingably provided at the tip of the bolt member. .
According to such a fixed hardware, even when there is a level error or the like of the rising portion of each floor, the fixing hardware can be surely set by adjusting the holding bolt according to the level of the rising portion.
[0072]
Claim 2According to the temporary living body according to the present invention, a hoist mechanism for lifting the temporary living body to the arm of a cart that can be moved horizontally on the building is used as a refilling means for rearranging the living body of the temporary living body upward. It is configured to be equipped. Thereby, it is not necessary to provide a replacement means in the temporary living body itself, and the temporary living body itself can have a light and simple configuration, which can contribute to shortening the construction period and reducing the cost. Moreover, since it is not necessary to use a crane for transporting materials, it is possible to improve the efficiency of equipment use. Furthermore, for example, when the living body is composed of a plurality of panel units, it is possible to cope by moving such a carriage. The refilling work can be performed efficiently.
Claim 3According to the invention according to the present invention, the reordering means is constituted by the hoist mechanism that is interposed between the fixing hardware and the panel unit and lifts the panel unit. It is possible to perform the unit replacement work.
Claim 4According to the invention, the support member extends in the vertical direction and is connected to the vertical frame of the panel unit so as to be rotatable in a horizontal plane, and the extension extending from the base in the horizontal direction. Since it is made into the substantially L shape which consists of a part and the reinforcement material which reinforces this extension part, a support member can be rotated in a horizontal surface with respect to a panel unit with a simple structure, and can be folded.
Claim 5According to the invention, the support member extends in the horizontal direction from the lower end portion of the base portion that extends in the vertical direction and is rotatably connected to the vertical frame of the panel unit in a horizontal plane. Since the support member is formed in a triangular shape including an extending portion, and a reinforcing member that is obliquely installed between the upper end portion of the base portion and the distal end portion of the extending portion and reinforces the extending portion, It can be suitably used when it is necessary to greatly increase the strength and separate the temporary living body from the building.
[0073]
Claim 6According to the building construction method according to the present invention, when the building is built inside the temporary living body and the body is rearranged upward, the load of the panel unit is supported by the refilling means, and then the supporting member is placed on the horizontal plane. Rotate it inside and fold it to the end of the living body, then lift the panel unit upward with refilling means, and then extend the support member to support the panel unit in the building, so that the panel unit is moved upward one by one It is structured to be reordered.
In this way, the reordering operation can be efficiently performed by rearranging the panel units one by one upward. Therefore, it is possible to contribute to shortening the construction period and reducing the cost of the entire construction. In addition, since the influence of cross wind and the like can be minimized, it is possible to prevent the construction period from being prolonged and to ensure work safety. In addition, since the refilling means is small, the work can be efficiently performed in this respect. Furthermore, by rotating the support member in a horizontal plane and folding it, it is possible to avoid interference with projections on the building side when the panel unit is replaced, and work can be performed easily.
[Brief description of the drawings]
FIG. 1 is a view showing an example of a temporary living body according to the present invention, and is an elevation view showing a state where the temporary living body is attached to a building.
FIG. 2 is a side sectional view showing a state in which the temporary living body is attached to a building.
FIG. 3 is an elevation view and a plan sectional view showing a guide rail provided in the temporary living body.
FIG. 4 is an elevational view and a plan sectional view showing a slide member provided in the temporary living body.
FIG. 5 is a side sectional view showing a structure for fixing the temporary living body to a building.
FIG. 6 is an elevation view and a bottom view showing a fixing hardware used for fixing the temporary living body.
FIG. 7 is a process diagram showing a replacement method of the temporary living body, and shows a state where the temporary living body is lifted and removed from the building.
FIG. 8 is a diagram showing a state in which the temporary living body is changed to the upper floor.
FIG. 9 is a view showing another example of the temporary living body according to the present invention, and is a side sectional view showing another fixing structure of the temporary living body to the building.
FIG. 10 is a side sectional view showing another replacement method for the temporary living body.
FIG. 11 is a process diagram showing an example of a conventional method for replacing a temporary living body.
[Explanation of symbols]
10 Temporary nutrition
11 Nutrient body
12 Panel unit
13 Vertical frame
21 Guide rail (connecting means)
24 Slide member (connection means)
30,30 ' Support member
30a, 30a 'base
30b, 30b 'extension
30c, 30c 'reinforcement
32,32 ' Fixing hardware
33 frames
34 Upper bearing member (upper contact member)
35 Side support member (side contact member)
36 Jack member (clamping member)
45 Refilling device (refilling means)
47 trolley
49 arms
50 Hoist mechanism(Refilling means)
60 holding bolt
60a nut
60b Bolt member
60c bearing plate
B Building
K temporary material
Claims (6)
該仮設養生体は、前記建物上部の施工現場の少なくとも側面を覆う養生体本体と、
該養生体本体を建物に支持させる支持部材と、
該養生体本体を上方に盛り替えていくための盛替手段とを具備してなり、
前記養生体本体が、定められた大きさを有した複数枚のパネルユニットを組み合わせることによって構成されているとともに、
前記各パネルユニットが、足場用パイプ等の仮設材によって構成され、
かつ、前記養生体本体を構成する複数枚の前記パネルユニットどうしが互いに隣接する部分には、互いに隣接する一方の前記パネルユニットの側端部に上下方向に延在するガイドレールが設けられているとともに、他方の前記パネルユニットの側端部には前記ガイドレールに沿った方向にのみ移動自在とされたスライド部材が設けられて、これら互いに隣接する二枚のパネルユニットが上下方向に相対移動可能に連結され、
前記支持部材が、水平面内において回転自在な状態で一端側が前記養生体本体に折り畳み可能に連結されるとともに、他端側が前記養生体本体側から前記建物側に向けて延出して、前記建物に着脱自在に固定される構成とされ、
かつ、該支持部材の他端側には、前記建物に形成された上方に立ち上がる立ち上がり部の上端部に固定される固定用金物が備えられ、
前記固定用金物は、前記立ち上がり部の上面および両側面に沿って位置するフレームに、前記立ち上がり部の上面に当接する押さえボルトと、前記立ち上がり部の側面に当接する側部当接部材と、該側部当接部材と相対向する位置に配設されて前記側部当接部材側に向けて進退する締付部材とが設けられた構成とされ、前記側部当接部材が前記フレームに揺動自在に取り付けられ、前記押さえボルトが、前記フレームに一体に溶接されたナットと、このナットに螺合したボルト部材と、ボルト部材の先端部に揺動可能に設けられた支圧プレートとから構成されていることを特徴とする仮設養生体。A temporary living organism that is provided so as to cover the building under construction and is gradually relocated upward as the construction progresses,
The temporary living body is a living body body that covers at least the side surface of the construction site above the building,
A support member for supporting the biological body in a building;
A refilling means for refilling the living body main body upward,
The biological body is configured by combining a plurality of panel units having a predetermined size,
Each of the panel units is composed of a temporary material such as a pipe for scaffolding,
And the guide rail extended in the up-down direction is provided in the side edge part of one said panel unit adjacent to the mutually adjacent part of the said panel units which comprise the said living body main body mutually. In addition, a slide member that is movable only in the direction along the guide rail is provided at the side end portion of the other panel unit, and these two adjacent panel units can be relatively moved in the vertical direction. Connected to
The support member is rotatably connected in a horizontal plane, and one end side is foldably connected to the living body main body, and the other end side extends from the living body main body side toward the building side. It is configured to be detachably fixed,
And, on the other end side of the support member, a fixing hardware fixed to the upper end portion of the rising portion that rises upward formed in the building is provided,
The fixing hardware includes, on a frame positioned along the upper surface and both side surfaces of the rising portion, a holding bolt that contacts the upper surface of the rising portion, a side contact member that contacts the side surface of the rising portion, A tightening member disposed at a position opposite to the side contact member and moving forward and backward toward the side contact member is provided, and the side contact member swings against the frame. A nut that is movably attached and the holding bolt is integrally welded to the frame, a bolt member that is screwed to the nut, and a support plate that is swingably provided at the tip of the bolt member Temporary nourishment living body characterized by being constituted.
前記盛替手段が、前記構築中の建物上で水平移動自在な台車に、一方向に延びるアームが備えられるとともに、該アームの先端部には前記仮設養生体を吊り上げるホイスト機構が備えられた構成となっていることを特徴とする仮設養生体。The temporary living organism according to claim 1 ,
A configuration in which the refilling means is provided with an arm extending in one direction on a cart that is horizontally movable on the building under construction, and a hoist mechanism that lifts the temporary nutrition is provided at the tip of the arm. Temporary nourishment living body characterized by becoming.
前記盛替手段が、前記固定用金物と前記パネルユニットとの間に介装されて該パネルユニットを吊り上げるホイスト機構により構成されていることを特徴とする仮設養生体。The temporary living organism according to claim 1 ,
Temporary living body, wherein the refilling means is constituted by a hoist mechanism that is interposed between the fixing hardware and the panel unit and lifts the panel unit.
前記支持部材が、鉛直方向に延在して前記パネルユニットの鉛直フレームに対して水平面内において回転自在に連結された基部と、該基部から水平方向に延出する延出部と、該延出部を補強する補強材とからなる略L字状とされていることを特徴とする仮設養生体。The temporary living organism according to any one of claims 1 to 3 ,
A base portion extending in a vertical direction and rotatably connected to a vertical frame of the panel unit in a horizontal plane; an extension portion extending horizontally from the base portion; and the extension Temporary nourishment body characterized by being made into the substantially L shape which consists of a reinforcing material which reinforces a part.
前記支持部材が、鉛直方向に延在して前記パネルユニットの鉛直フレームに対して水平面内において回転自在に連結された基部と、該基部の下端部から水平方向に延出する延出部と、前記基部の上端部と前記延出部の先端部との間に斜めに架設されて延出部を補強する補強材とからなる三角形状とされていることを特徴とする仮設養生体。The temporary living organism according to any one of claims 1 to 3 ,
A base that extends in the vertical direction and is rotatably connected to the vertical frame of the panel unit in a horizontal plane; and an extension that extends in a horizontal direction from a lower end of the base; A temporary nurturing body having a triangular shape comprising a reinforcing material that is obliquely installed between an upper end portion of the base portion and a distal end portion of the extension portion and reinforces the extension portion.
前記仮設養生体を、前記支持部材で前記建物に支持させ、その内側で前記建物を下方から上方に向けて構築していき、建物の施工の進捗にともなって前記養生体本体を上方に盛り替えるときには、前記養生体本体を構成している前記パネルユニットを一枚ずつ上方に盛り替えていき、前記各パネルユニットを盛り替えるには、前記盛替手段で一枚の前記パネルユニットの荷重を支持した後に、該パネルユニットに備えられた前記支持部材を水平面内において回転させて養生体本体側に折り畳み、次いで前記盛替手段で前記パネルユニットを上方に吊り上げ、しかる後に前記支持部材を水平面内において回転させてその先端部に設けた固定用金物を建物に対して係合させることにより該パネルユニットを前記建物に支持させることを特徴とする建物の施工方法。 It is the construction method of the building using the temporary living body according to any one of claims 1 to 5 ,
The temporary living body is supported on the building by the support member, and the building is constructed from the lower side to the upper side, and the living body body is rearranged upward as the construction of the building progresses. Sometimes, the panel units constituting the living body are rearranged one by one upward, and in order to rearrange each panel unit, the load of one panel unit is supported by the reordering means. After that, the support member provided in the panel unit is rotated in the horizontal plane and folded to the side of the biological body, and then the panel unit is lifted upward by the refilling means, and then the support member is moved in the horizontal plane. The panel unit is supported by the building by rotating and engaging a fixing hardware provided at the tip thereof with the building. Construction method of the object.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP06364698A JP3887479B2 (en) | 1998-03-13 | 1998-03-13 | Temporary nourishment and building construction method using the same |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP06364698A JP3887479B2 (en) | 1998-03-13 | 1998-03-13 | Temporary nourishment and building construction method using the same |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH11256833A JPH11256833A (en) | 1999-09-21 |
JP3887479B2 true JP3887479B2 (en) | 2007-02-28 |
Family
ID=13235334
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP06364698A Expired - Fee Related JP3887479B2 (en) | 1998-03-13 | 1998-03-13 | Temporary nourishment and building construction method using the same |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3887479B2 (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4651857B2 (en) * | 2001-05-22 | 2011-03-16 | 西松建設株式会社 | Building demolition method |
JP6009332B2 (en) * | 2012-11-30 | 2016-10-19 | 戸田建設株式会社 | Fixing device for self-elevating external curing device and its installation method |
CN117886229A (en) * | 2024-03-13 | 2024-04-16 | 河南省第二建设集团有限公司 | Multifunctional integrated rail type lifting mechanism |
-
1998
- 1998-03-13 JP JP06364698A patent/JP3887479B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH11256833A (en) | 1999-09-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US5255489A (en) | Construction apparatus for buildings and constructing method therewith | |
JP2008527222A (en) | Equipment used for building construction | |
JP5394334B2 (en) | Construction method of work floor for work at height | |
JP2008150159A (en) | Jib crane | |
JP2593349B2 (en) | Crane device and method of using the same | |
JP2006240878A (en) | Simple crane apparatus | |
JP3887479B2 (en) | Temporary nourishment and building construction method using the same | |
US7367461B2 (en) | Movable girder mounted jib | |
KR100894498B1 (en) | Self movable crane system with a boom | |
KR100293687B1 (en) | Concrete delivery device and its installation method | |
JP2008214062A (en) | Lifting device and structural material mounting method | |
JP4914130B2 (en) | Climbing crane | |
JP4352219B2 (en) | Crane equipment | |
JP4456745B2 (en) | Work floor | |
CN218091896U (en) | Movable scaffold operation platform | |
JPH10245189A (en) | Omnidirectional moving crane used for high rise building construction | |
JP3595361B2 (en) | crane | |
JPH0328066Y2 (en) | ||
JPH1088786A (en) | Scaffold for columnar structure | |
JPH08338127A (en) | Internally assembled scaffold construction | |
JP5196214B2 (en) | Crane floor climbing system and crane floor climbing method | |
JPH1178873A (en) | Device and method for installing structure member | |
JPH0729107Y2 (en) | Simple crane | |
JP2005029364A6 (en) | Crane equipment | |
CN116810742A (en) | Rotatable platform for assembling door leaf steel frame |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20050708 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050712 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050829 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060808 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20061010 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20061031 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20061127 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101201 Year of fee payment: 4 |
|
LAPS | Cancellation because of no payment of annual fees |