JP3583307B2 - Construction management system in ground improvement method - Google Patents
Construction management system in ground improvement method Download PDFInfo
- Publication number
- JP3583307B2 JP3583307B2 JP01630799A JP1630799A JP3583307B2 JP 3583307 B2 JP3583307 B2 JP 3583307B2 JP 01630799 A JP01630799 A JP 01630799A JP 1630799 A JP1630799 A JP 1630799A JP 3583307 B2 JP3583307 B2 JP 3583307B2
- Authority
- JP
- Japan
- Prior art keywords
- screw rod
- ground
- amount
- management system
- construction management
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は深層混合処理工法の範疇に属する地盤改良工法に適用する施工管理システムに関する。
【0002】
【従来の技術】
深層混合処理工法は、セメントスラリー等の地盤改良材を原地盤に注入して土砂と撹拌混合することにより改良杭を原地盤に多数形成し、以て原地盤の強度を増大せしめることを基本とする地盤改良工法である。
【0003】
図5はそのような深層混合処理工法に適用される処理機1とそれに適用される施工管理システムの概要図である。処理機1は先端部に撹拌羽根2を備えたスクリューロッド3をベースマシン4により鉛直に支持し、駆動装置5によりスクリューロッド3を回転させて改良対象範囲の最深部まで貫入させた後、スクリューロッド3の先端部に設けてある吐出口から地盤改良材としてのセメントスラリーを地中に注入しつつ、かつ注入したセメントスラリーと土砂とを撹拌羽根2により撹拌混合しながらスクリューロッド3を引き抜くことで改良杭を形成するように構成されている。
【0004】
また、その処理機1により改良杭を形成する場合における施工管理システムは、スラリー流量計6、スクリューロッド3の軸回転計7、駆動装置5の電流検出計8、スクリューロッド3の深度計9および昇降速度計10を備え、それら各センサによる検出値を管理装置11に入力して、セメントスラリーの注入量、スクリューロッド3の回転数、到達深度、貫入速度および引き抜き速度を管理項目として監視するように構成されている。符号12はベースマシン4に設置されているオペレーションモニタ、13はデータ保存用のパソコンである。
【0005】
【発明が解決しようとする課題】
ところで、上記のような従来一般の深層混合処理工法では、地盤改良材としてのセメントスラリーを原地盤に対して多量に注入するため原地盤の体積が増大することが不可避であり、それに起因して原地盤が盛り上がったり周辺地盤に対して悪影響を及ぼすことが懸念され、そのための対策が必要である。
【0006】
そこで、上記のような深層混合処理工法における周辺地盤に対する悪影響を防止するための対策として、セメントスラリーの注入量相当分の土砂を原地盤から排土することで原地盤の体積膨張を回避するという排土式の深層混合処理工法も検討されているが、その場合において排土量を監視して適正に管理し得る有効な施工管理システムは未だ確立されていない。
【0007】
【課題を解決するための手段】
上記事情に鑑み、請求項1の発明は、先端部に撹拌羽根を有するスクリューロッドを地中に貫入せしめ、該スクリューロッドを通して地中に地盤改良材を注入して前記撹拌羽根の回転により土砂と撹拌混合しつつ該スクリューロッドを引き抜くとともに、地盤改良材の注入量相当分の土砂を前記スクリューロッドにより地中から排土する地盤改良工法を実施するに際して適用されて、前記スクリューロッドの深度、回転数、貫入速度および引き抜き速度、地盤改良材の注入量を検出して監視する施工管理システムにおいて、前記回転数に基づいて前記スクリューロッドによる推定排土量を演算し、その推定排土量を管理項目として監視する構成としたことを特徴とするものである。
【0008】
請求項2の発明の施工管理システムは、推定排土量を地盤改良材の注入量と比較して施工の良否を判定するように構成したものである。
【0009】
【発明の実施の形態】
以下、本発明の施工管理システムの具体的な実施形態について図1を参照して説明する。本実施形態の施工管理システムが適用される地盤改良工法は、図5に示した改良機1による排土式の深層混合処理工法である。つまり、その改良機1は原地盤の体積膨張を回避するべくスクリューロッド3を引き抜く際にセメントスラリーの注入量相当分の土砂を排土するものとされ、それに伴い、本実施形態の施工管理システムは、図5に示した従来の施工管理システムを基本としつつ、その管理項目に「排土量」を付加して改良機1による排土量を監視し、それを適正に維持することで原地盤の変位(盛り上がりや周辺地盤への悪影響)を防止するように構成されている。さらに、本実施形態の施工管理システムではセメントスラリーと土砂との撹拌混合状態を定量的に把握してそれを適正に管理するべく「羽根切り回数」も管理項目として付加している。
【0010】
すなわち、本実施形態の施工管理システムは、図1にその概要を示すように、品質管理上の管理項目として「材料」、「配合」、「混合(羽根切り回数)」、出来形管理上の管理項目として「打設位置」、「打設深度」、「着底」、地盤の変位管理上の管理項目として「排土量」を設定している。それら各管理項目のうち「材料」、「配合」、「打設位置」、「打設深度」、「着底」については図5に示した従来の施工管理システムと共通するものであり、「混合(羽根切り回数)」および「排土量」は本実施形態において付加した管理項目である。
【0011】
従来と共通する管理項目のうち、「材料」は地盤改良材としてのセメントスラリーの状態(セメント量や水量)を管理するもの、「配合」はスラリー流量計6により検出されるスラリー注入量と昇降速度計10により検出されるスクリューロッド3の昇降速度とにより単位深度当たりの注入量が適正であるか否かを管理するもの、「打設位置」はトランシット等による測量により改良杭の形成位置を管理するもの、「打設深度」は深度計9によりスクリューロッド3の位置を検出してそれを管理するもの、「着底」は電流計8により検出される駆動装置5の作動状態と昇降速度計10により検出される貫入速度とからスクリューロッド3の先端が改良対象範囲の最深部に達したか否かを管理するものである。
【0012】
また、本実施形態において付加した管理項目のうち、「排土量」は軸回転計7により検出されるスクリューロッド3の回転数と、スクリュー形状および排土係数とにより推定排土量を演算し、それがスラリー注入量と同等になるように管理するものである。
【0013】
本実施形態においては推定排土量の演算は次のようにして行う。推定排土量Vはスクリュー断面積SとスクリューピッチPと回転数Nの関数であり、その比例定数を排土係数Kとして
V=K・S・P・N
V:推定排土量(m3)
K:排土係数
S:スクリュー断面積(m2)
P:スクリューピッチ(m)
N:回転数(回)
で表される。スクリュー断面積SとスクリューピッチPは改良機固有の定数であるから、排土係数Kの値を決定すれば回転数Nを測定することのみで推定排土量Vを演算できる。排土係数Kの値は、改良機を用いた実測試験を行って図2に示すような実測排土量V1とS×P×Nの値との関係を表す近似式を決定することにより、改良仕様と土質条件ごとに予め求めることができる。
【0014】
上記のようにして予め求めておいた排土係数Kとスクリュー断面積S、スクリューピッチPとを管理装置11に入力しておけば、軸回転計7により検出した回転数Nを管理装置11に入力することのみで上式により推定排土量Vを求めることができる。そして、本実施形態の施工管理システムにおいては、1本の改良杭を施工するごとにその推定排土量Vを演算し、それをスラリー流量計6により検出されるスラリー注入量と比較して施工良否の判定を行うようにされている。なお、回転数Nを調節すれば推定排土量Vを増減することができるから、必要であれば推定排土量Vが適正になるように刻々と制御することも可能である。
【0015】
また、本実施形態において付加した他の管理項目である「羽根切り回数」は、スクリューロッド3が単位長さ引き抜かれる際に各撹拌羽根2による羽根切りがなされた回数を示す値であり、次式で表されるものである。
【0016】
T=M×n/v
T:羽根切り回数(回/m)
M:撹拌羽根の総枚数(枚)
n:回転数(回/分)
v:引き抜き速度(m/分)
【0017】
上式における撹拌羽根2の総枚数Mは改良機固有の定数であるから、軸回転計7により検出される回転数nと速度計9により検出される引き抜き速度vとにより羽根切り回数Tを上式に基づき求めることができる。
【0018】
上記の各管理項目は管理装置(コンピューター)11に入力されて評価すなわち施工の良否の判定がなされ、それに基づき必要に応じて修正施工がなされる。そしてオフコン(パソコン)に施工データが保存され、必要に応じて適宜の管理データ、たとえば図3に示すような「施工結果表」や図4に示すような「杭打設日報」がプリントアウトされる。
【0019】
以上で説明した本実施形態の施工管理仕システムによれば、排土式の深層混合処理工法による地盤改良に際して従来と同様の品質管理と出来形管理を行い得ることに加え、推定排土量を演算してそれをスラリー注入量と同等になるような管理を行うことが可能であり、原地盤の変位を有効にかつ合理的に防止できる効果がある。
【0020】
加えて、本実施形態の施工管理システムにおいては、羽根切り回数の管理を行うことでセメントスラリーと土砂との撹拌混合の度合いを定量的に把握できるので、優れた地盤改良効果を得ることができる。
【0021】
【発明の効果】
請求項1の発明の施工管理システムは、スクリューロッドの回転数に基づいて推定排土量を演算してそれを管理項目とするので、排土量を適正に管理することができ、その結果、原地盤の変位を有効にかつ合理的に防止できる効果がある。
【0022】
請求項2の発明の施工管理システムは、推定排土量を地盤改良材の注入量と比較して施工良否を判定することにより、施工信頼性を十分に確保することができ、修正施工の必要性が明確になる。
【図面の簡単な説明】
【図1】本発明の実施形態である施工管理システムの概要を示す図である。
【図2】同システムにおいて用いる排土係数の決定法を示す図である。
【図3】同システムにおける管理データの一例を示す図である。
【図4】同システムにおける管理データの他の例を示す図である。
【図5】従来の深層混合処理工法における処理機と施工管理システムの概要を示す図である。
【符号の説明】
1 改良機
2 撹拌羽根
3 スクリューロッド
6 スラリー流量計
7 軸回転計
8 電流検出計
9 深度計
10 速度計
11 管理装置[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a construction management system applied to a ground improvement method belonging to the category of the deep mixing treatment method.
[0002]
[Prior art]
The deep mixing method is based on increasing the strength of the original ground by injecting a ground improvement material such as cement slurry into the original ground and mixing it with earth and sand to form a large number of improved piles on the original ground. This is a ground improvement method.
[0003]
FIG. 5 is a schematic diagram of a
[0004]
The construction management system in the case of forming an improved pile by the
[0005]
[Problems to be solved by the invention]
By the way, in the conventional general deep mixing treatment method as described above, it is inevitable that the volume of the original ground increases because a large amount of cement slurry as a ground improvement material is injected into the original ground. There is a concern that the original ground will rise or adversely affect the surrounding ground, and countermeasures are needed.
[0006]
Therefore, as a measure to prevent the adverse effect on the surrounding ground in the deep mixing method as described above, the volume expansion of the raw ground is avoided by discharging earth and sand equivalent to the injection amount of the cement slurry from the raw ground. Although an earth removal type deep mixing method is also being studied, an effective construction management system that can monitor and properly manage the earth removal amount has not been established yet.
[0007]
[Means for Solving the Problems]
In view of the above circumstances, the invention of
[0008]
The construction management system according to the second aspect of the invention is configured to determine the quality of the construction by comparing the estimated earth removal amount with the injection amount of the ground improvement material.
[0009]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, a specific embodiment of the construction management system of the present invention will be described with reference to FIG. The ground improvement method to which the construction management system of the present embodiment is applied is an earth removal type deep mixing treatment method using the
[0010]
That is, as shown in FIG. 1, the construction management system according to the present embodiment includes “material”, “mixing”, “mixing (number of blade cutting)” as management items in quality control, and As the management items, “placement position”, “placement depth”, “landing”, and “discharge amount” are set as management items for managing the displacement of the ground. Among these management items, “material”, “mixing”, “placement position”, “placement depth”, and “landing” are common to the conventional construction management system shown in FIG. “Mixing (blade cutting frequency)” and “discharge amount” are management items added in the present embodiment.
[0011]
Among the management items common to the conventional ones, “material” manages the state of cement slurry (amount of cement and water) as a soil improvement material, and “mixing” indicates the amount of slurry injection detected by the
[0012]
In the management items added in the present embodiment, the “discharge amount” is an estimated discharge amount calculated from the rotation speed of the
[0013]
In the present embodiment, the calculation of the estimated earth removal amount is performed as follows. The estimated soil removal amount V is a function of the screw cross-sectional area S, the screw pitch P, and the number of revolutions N, and the proportionality constant is defined as V = K · S · P · N
V: Estimated earth removal amount (m 3 )
K: soil removal coefficient S: screw cross-sectional area (m 2 )
P: Screw pitch (m)
N: Number of rotations (times)
It is represented by Since the screw cross-sectional area S and the screw pitch P are constants specific to the improved machine, if the value of the soil removal coefficient K is determined, the estimated soil removal amount V can be calculated only by measuring the rotation speed N. The value of dumping factor K, by determining the approximate expression representing the relationship between the value of the measured earth discharging amount V 1 and S × P × N as shown in FIG. 2 by performing actual measurement test using the improved machine Can be obtained in advance for each improved specification and soil condition.
[0014]
If the soil removal coefficient K, the screw cross-sectional area S, and the screw pitch P determined in advance as described above are input to the management device 11, the rotation speed N detected by the
[0015]
Further, “management number of blades”, which is another management item added in the present embodiment, is a value indicating the number of times blades are cut by each
[0016]
T = M × n / v
T: Number of blade cutting (times / m)
M: Total number of stirring blades (sheets)
n: Number of rotations (times / minute)
v: Drawing speed (m / min)
[0017]
Since the total number M of the
[0018]
Each of the above management items is input to the management device (computer) 11 and evaluated, that is, the quality of the construction is determined, and based on the result, the correction construction is performed as necessary. Then, the construction data is stored in the office computer (PC), and if necessary, appropriate management data, for example, a “construction result table” as shown in FIG. 3 and a “pile driving daily report” as shown in FIG. 4 are printed out. You.
[0019]
According to the construction management system of the present embodiment described above, in addition to being able to perform the same quality control and workmanship management as in the past when soil improvement by the deep mixing processing method of the earth removal type, the estimated earth removal amount is It is possible to perform management so that it is equivalent to the slurry injection amount, and there is an effect that displacement of the original ground can be effectively and rationally prevented.
[0020]
In addition, in the construction management system of the present embodiment, the degree of agitation and mixing of the cement slurry and the earth and sand can be quantitatively grasped by managing the number of times of blade cutting, so that an excellent ground improvement effect can be obtained. .
[0021]
【The invention's effect】
The construction management system according to the first aspect of the present invention calculates the estimated amount of earth removal based on the rotation speed of the screw rod and uses the calculated amount as a management item, so that the amount of earth removal can be appropriately managed, and as a result, There is an effect that displacement of the original ground can be effectively and rationally prevented.
[0022]
The construction management system according to the second aspect of the present invention can determine the quality of the construction by comparing the estimated amount of earth removal with the amount of the ground improvement material injected, thereby ensuring sufficient construction reliability and necessitating repair work. Sex becomes clear.
[Brief description of the drawings]
FIG. 1 is a diagram showing an outline of a construction management system according to an embodiment of the present invention.
FIG. 2 is a diagram showing a method of determining a soil removal coefficient used in the system.
FIG. 3 is a diagram showing an example of management data in the same system.
FIG. 4 is a diagram showing another example of management data in the system.
FIG. 5 is a diagram showing an outline of a processing machine and a construction management system in a conventional deep mixing processing method.
[Explanation of symbols]
DESCRIPTION OF
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP01630799A JP3583307B2 (en) | 1999-01-25 | 1999-01-25 | Construction management system in ground improvement method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP01630799A JP3583307B2 (en) | 1999-01-25 | 1999-01-25 | Construction management system in ground improvement method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2000212951A JP2000212951A (en) | 2000-08-02 |
JP3583307B2 true JP3583307B2 (en) | 2004-11-04 |
Family
ID=11912889
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP01630799A Expired - Lifetime JP3583307B2 (en) | 1999-01-25 | 1999-01-25 | Construction management system in ground improvement method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3583307B2 (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4885326B1 (en) * | 2011-05-26 | 2012-02-29 | 清水建設株式会社 | Ground improvement method |
JP4885325B1 (en) * | 2011-05-26 | 2012-02-29 | 清水建設株式会社 | Construction management system for ground improvement method |
WO2012161282A1 (en) * | 2011-05-26 | 2012-11-29 | 株式会社不動テトラ | Ground improvement method, and system for managing construction in ground improvement method |
JP2013167139A (en) * | 2012-02-17 | 2013-08-29 | Tenox Corp | Soil improvement method and soil improving device |
JP6293352B1 (en) * | 2017-12-13 | 2018-03-14 | 株式会社大林組 | Ground improvement method and ground improvement device |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4368650B2 (en) * | 2003-10-17 | 2009-11-18 | 株式会社技研製作所 | Pile rotary press machine and pile rotary press method using it |
JP5777424B2 (en) * | 2011-07-01 | 2015-09-09 | 旭化成建材株式会社 | Ground excavation method |
JP6062781B2 (en) * | 2013-03-26 | 2017-01-18 | 五洋建設株式会社 | Mechanical stirring vacuum compaction method |
CN105887793B (en) * | 2015-01-05 | 2018-06-15 | 李泽唐 | A kind of method and device of checking winds and fixing drifting sand based on turbulent flow |
JP6166833B1 (en) * | 2016-11-17 | 2017-07-19 | あおみ建設株式会社 | Management equipment for deep mixing equipment |
JP7150656B2 (en) * | 2019-03-29 | 2022-10-11 | 株式会社不動テトラ | Ground Displacement Control Method for Slurry Agitation Deep Mixing Method |
-
1999
- 1999-01-25 JP JP01630799A patent/JP3583307B2/en not_active Expired - Lifetime
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4885326B1 (en) * | 2011-05-26 | 2012-02-29 | 清水建設株式会社 | Ground improvement method |
JP4885325B1 (en) * | 2011-05-26 | 2012-02-29 | 清水建設株式会社 | Construction management system for ground improvement method |
WO2012161282A1 (en) * | 2011-05-26 | 2012-11-29 | 株式会社不動テトラ | Ground improvement method, and system for managing construction in ground improvement method |
JP2013167139A (en) * | 2012-02-17 | 2013-08-29 | Tenox Corp | Soil improvement method and soil improving device |
JP6293352B1 (en) * | 2017-12-13 | 2018-03-14 | 株式会社大林組 | Ground improvement method and ground improvement device |
JP2019105084A (en) * | 2017-12-13 | 2019-06-27 | 株式会社大林組 | Ground improvement method and ground improvement device |
Also Published As
Publication number | Publication date |
---|---|
JP2000212951A (en) | 2000-08-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3583307B2 (en) | Construction management system in ground improvement method | |
JP4478187B2 (en) | Ground improvement machine | |
JP3437108B2 (en) | Management method of ground improvement method and management device of ground improvement machine | |
JP4885325B1 (en) | Construction management system for ground improvement method | |
JP4885326B1 (en) | Ground improvement method | |
WO2012161282A1 (en) | Ground improvement method, and system for managing construction in ground improvement method | |
JP6153591B2 (en) | Ground survey method and ground survey device | |
JP2019031839A (en) | Method for determining arrival at support layer and determination support system | |
JP2010133140A (en) | Rotary penetrating pile construction system | |
JP3430148B2 (en) | Ground improvement construction method and construction management device | |
KR100777377B1 (en) | Automatic Control System for Insert Limit of Casing Pipe In Soft Ground Improvement and Method thereof | |
JP3788728B2 (en) | Device that displays the construction status of the ground improvement method | |
JPS6367319A (en) | Hardness index gauge | |
JP3126909B2 (en) | Automatic soil augmentation control method of soil cement column in foundation ground | |
JPS5817996A (en) | Apparatus for detecting filled sand and mud in cutter chamber of shield drilling machine | |
JP3002075B2 (en) | Excavator rope replacement alarm | |
JP2002266343A (en) | Method for controlling soil improving method, and apparatus for controlling soil improving machine | |
JP2895677B2 (en) | Ground hardness judgment device | |
JP7090320B2 (en) | Arithmetic logic unit, excavator, calculation method, and computer program | |
JP2789219B2 (en) | Construction management equipment in mixed processing method | |
KR200396374Y1 (en) | Automatic Control System for Insert Limit of Casing Pipe In Soft Ground Improvement | |
CN115897560A (en) | Intelligent cement-soil mixing pile construction equipment and construction method thereof | |
JPH0742695B2 (en) | Ground improvement method and ground improvement machine | |
JPH064994B2 (en) | Excavation management method | |
JP2023040533A (en) | Discharged slurry amount management system for penetration auxiliary water construction, and soil removal type deep layer mixing method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20040624 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20040713 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20040728 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100806 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100806 Year of fee payment: 6 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100806 Year of fee payment: 6 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100806 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130806 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130806 Year of fee payment: 9 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130806 Year of fee payment: 9 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130806 Year of fee payment: 9 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130806 Year of fee payment: 9 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |