JP2023040533A - Discharged slurry amount management system for penetration auxiliary water construction, and soil removal type deep layer mixing method - Google Patents

Discharged slurry amount management system for penetration auxiliary water construction, and soil removal type deep layer mixing method Download PDF

Info

Publication number
JP2023040533A
JP2023040533A JP2021147579A JP2021147579A JP2023040533A JP 2023040533 A JP2023040533 A JP 2023040533A JP 2021147579 A JP2021147579 A JP 2021147579A JP 2021147579 A JP2021147579 A JP 2021147579A JP 2023040533 A JP2023040533 A JP 2023040533A
Authority
JP
Japan
Prior art keywords
water
planned
construction
amount
actual
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2021147579A
Other languages
Japanese (ja)
Inventor
信洋 土屋
Nobuhiro Tsuchiya
哲也 小森田
Tetsuya Komorida
強 高橋
Tsuyoshi Takahashi
勝己 大古利
Katsumi Okori
洋 仁田尾
Hiroshi Nitao
勝司 山下
Katsuji Yamashita
直哉 又吉
Naoya Matayoshi
拓也 河合
Takuya Kawai
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Tenox Corp
Shimizu Corp
Fudo Tetra Corp
Aomi Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Tenox Corp
Shimizu Corp
Fudo Tetra Corp
Aomi Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Tenox Corp, Shimizu Corp, Fudo Tetra Corp, Aomi Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP2021147579A priority Critical patent/JP2023040533A/en
Publication of JP2023040533A publication Critical patent/JP2023040533A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

To perform improved soil mixing processing in which a slurry amount discharged into a ground in a pull-out construction with respect to a penetration auxiliary water amount is managed with high accuracy and to reasonably develop strength at the time of blend planning in a ground improvement.SOLUTION: A discharged slurry amount management system for a penetration auxiliary water construction comprises: a quality management unit 20A in which a planned slurry water-cement ratio, a planned slurry amount, a planned penetration auxiliary water amount, a planned penetration speed, and a planned correction water cement ratio (a sum of a planned compound water and a planned penetration auxiliary water) that are obtained in planning a construction are inputted; a construction measurement unit 20B for measuring a real construction depth, a real penetration speed, and a real penetration auxiliary water amount in constructing; a construction management unit 20C for obtaining a real correction water-cement ratio based on the real construction depth, the real penetration speed, and the real penetration auxiliary water amount measured by the construction measurement unit 20B; and a calculation unit 20D for comparing the planned correction water-cement ratio with the real correction water-cement ratio and calculating a real slurry amount and pull-out speed in a pull-out construction of a rotation rod.SELECTED DRAWING: Figure 2

Description

本発明は、貫入補助水施工に対する吐出スラリー量管理システム、及び排土式深層混合処理工法に関する。 TECHNICAL FIELD The present invention relates to a discharge slurry amount management system for intrusion auxiliary water construction and a soil removal type deep mixing treatment method.

従来、都市部における地盤改良工法では、近接施工となるケースが多く、周囲地盤の変位を抑えた変位低減型の工法が求められており、例えば特許文献1に示されるような2軸の回転軸を有する処理機を用いた排土式深層混合処理工法が知られている。
特許文献1は、2軸の回転軸を貫入する際に、固化材の供給量に相当する土量を積極的に排土した後、回転軸の引抜き時に貫入した地盤に固化材を供給して撹拌混合することで、固化材の供給に伴う地盤膨張を防止して周辺地盤に変位が生じることを回避する変位低減型の地盤改良工法である。この場合には、貫入時に固化材を供給しないので、固化材が混入されずに元の地盤のまま排土される。
Conventionally, in the ground improvement method in urban areas, there are many cases of close construction, and there is a demand for a displacement reduction type construction method that suppresses the displacement of the surrounding ground. is known.
In Patent Document 1, when penetrating the two rotating shafts, the amount of soil corresponding to the supply amount of the solidifying material is positively discharged, and then the solidifying material is supplied to the ground that has penetrated when the rotating shaft is pulled out. This is a displacement-reducing ground improvement method that prevents ground expansion due to the supply of solidifying material and avoids displacement of the surrounding ground by stirring and mixing. In this case, since no solidifying material is supplied at the time of penetration, the original ground is discharged without being mixed with the solidifying material.

さらに、大径の撹拌翼で改良面積を大きくした大径改良を可能とした2軸の地盤改良工法を実施されるケースもあり、この場合には施工費を低減できる利点がある。大径の撹拌翼で貫入施工を行うときには、貫入抵抗が大きくなることから、貫入速度が低下し、施工能率が低下する傾向にあった。そのため特許文献2では、貫入時には例えば下段吐出口より水を吐出して流動化を促進することにより、貫入抵抗を減少させ施工速度を確保するとともに、引抜き時において上段吐出口よりスラリーを吐出し、撹拌混合することで改良体を造成することも行われている。 Furthermore, there are cases where a biaxial ground improvement method is implemented that enables large-diameter improvement by increasing the improvement area with a large-diameter stirring blade, and in this case, there is an advantage that construction costs can be reduced. When performing penetration work with a large-diameter impeller, the penetration resistance increased, so the penetration speed decreased and the work efficiency tended to decrease. Therefore, in Patent Document 2, during penetration, for example, water is discharged from the lower discharge port to promote fluidization, thereby reducing the penetration resistance and ensuring the construction speed, and at the time of withdrawal, slurry is discharged from the upper discharge port. It is also practiced to create an improved product by stirring and mixing.

近年では、実施工において計画時の地盤抵抗を上回り貫入補助水が計画時よりも大量に吐出すことを必要とするケースもあり、この場合には引抜き時に地盤に添加する固化材量が多くなり固化材のスラリー量を即時に正確に算出することが必要となる傾向にあった。 In recent years, there are cases in the implementation work that exceed the ground resistance at the time of planning and require a larger amount of intrusion supplementary water to be discharged than at the time of planning. It tends to be necessary to calculate the slurry amount of the solidifying material immediately and accurately.

特許第4885325号公報Japanese Patent No. 4885325

しかしながら、貫入時の地盤抵抗を定量的に事前に把握することは困難であり、計画貫入補助水量を超えたケースを多数想定し、吐出する固化材のスラリー量を引抜き速度とプラントから供給するスラリー量の組合せで配合試験の水セメント比に合わせて設定する必要があった。さらに計画貫入補助水量を超えた貫入補助水量に対して即時にオペレーターが判断する必要があり、正確性とスラリー量の管理の困難さという点で問題があった。 However, it is difficult to quantitatively grasp the ground resistance at the time of penetration in advance. It was necessary to set the combination of amounts according to the water-cement ratio of the blending test. In addition, it is necessary for the operator to make an immediate judgment on the amount of auxiliary water for intrusion that exceeds the planned amount of auxiliary water for intrusion, and there are problems in terms of accuracy and difficulty in managing the amount of slurry.

また標準装備の管理システムでは、貫入時点の施工深度における貫入速度と貫入補助水量はディスプレイに表示されるのみで、記録として確認できるのは引抜きが終わり、施工が完了した時点で施工記録として全深度を出力できるのみであった。このため、貫入補助水が計画値をオーバーした時点の貫入速度とプラントからの貫入補助水供給量(リットル/分)を手書きで記録し、引抜き施工時点で当該深度に到達した際にプラントからのスラリー供給量と引抜き速度を調整するという操作を行う必要があり、正確性で問題があった。複数深度で調整する操作が必要になった場合は、対応が困難になることも考えられた。 In addition, in the standard equipment management system, the penetration speed and penetration supplementary water amount at the construction depth at the time of penetration are only displayed on the display, and you can check the record as a construction record when the extraction is completed and construction is completed. could only output For this reason, manually record the penetration speed and the amount of penetration supplementary water supplied from the plant (liters/minute) when the penetration auxiliary water exceeds the planned value. It was necessary to adjust the amount of slurry supplied and the drawing speed, and there was a problem with accuracy. It was also thought that it would be difficult to deal with when it became necessary to adjust at multiple depths.

本発明は、上述する問題点に鑑みてなされたもので、貫入補助水量に対して引抜き施工時の地盤に吐出するスラリー量を精度よく管理した改良土混合処理を行うことができ、地盤改良における配合計画時の強度を合理的に発現することができる貫入補助水施工に対する吐出スラリー量管理システム、及び排土式深層混合処理工法を提供することを目的とする。 The present invention has been made in view of the above-mentioned problems, and it is possible to perform improved soil mixing treatment in which the amount of slurry discharged into the ground during pulling work is accurately controlled with respect to the amount of intrusion auxiliary water. It is an object of the present invention to provide a discharge slurry amount management system for penetrating auxiliary water construction and a soil removal type deep mixing treatment method that can rationally express the strength at the time of mixing planning.

上記目的を達成するため、本発明に係る貫入補助水施工に対する吐出スラリー量管理システムは、排土式深層混合処理機に設けられる回転ロッドを改良地盤に貫入させる際に、プラントで製造したスラリーを地盤に混合させるとともに、前記回転ロッドの貫入時に貫入補助水を地盤に向けて吐出することによる改良土を管理する貫入補助水施工に対する吐出スラリー量管理システムであって、施工計画時に得られる計画スラリー水セメント比、計画スラリー量、計画貫入補助水量、計画貫入速度、及び計画配合水と計画貫入補助水とを合わせた計画修正水セメント比が入力される品質管理部と、施工時において、実施工深度、実貫入速度、及び実貫入補助水量を測定する施工計測部と、前記施工計測部で測定された前記実施工深度、前記実貫入速度、及び前記実貫入補助水量に基づいて実修正水セメント比を得る施工管理部と、前記計画修正水セメント比と前記実修正水セメント比とを比較して、前記回転ロッドの引抜き施工時における供給する実スラリー量、及び引抜き速度を算定する算定部と、を備えていることを特徴としている。 In order to achieve the above object, a discharge slurry amount management system for penetrating auxiliary water construction according to the present invention is a slurry produced in a plant when penetrating a rotating rod provided in a soil removal type deep mixing treatment machine into improved ground. A discharge slurry amount management system for penetration auxiliary water construction that manages improved soil by mixing it with the ground and discharging the penetration auxiliary water toward the ground when the rotating rod penetrates, and is a planned slurry obtained at the time of construction planning. The quality control department where the water-cement ratio, planned slurry volume, planned intrusion auxiliary water quantity, planned intrusion speed, and planned modified water-cement ratio that combines planned mixed water and planned intrusion auxiliary water are input, and during construction, the execution work A construction measurement unit that measures the depth, actual penetration speed, and actual penetration auxiliary water amount, and the actual modified water cement based on the actual construction depth, the actual penetration speed, and the actual penetration auxiliary water amount measured by the construction measurement unit. a construction management unit that obtains the ratio; and a calculation unit that compares the planned corrected water-cement ratio and the actual corrected water-cement ratio to calculate the actual amount of slurry to be supplied and the drawing speed during the drawing operation of the rotating rod. , is provided.

また、本発明に係る排土式深層混合処理工法は、排土式深層混合処理機に設けられる回転ロッドを改良地盤に貫入させる際に、プラントで製造したスラリーを地盤に混合させるとともに、前記回転ロッドの貫入時に貫入補助水を地盤に向けて吐出することによって改良する排土式深層混合処理工法であって、施工計画時に得られる計画スラリー水セメント比、計画スラリー量、計画貫入補助水量、計画貫入速度、及び計画配合水と計画貫入補助水とを合わせた計画修正水セメント比を求める工程と、施工時において、実施工深度、実貫入速度、及び実貫入補助水量を測定する工程と、予め測定された前記実施工深度、前記実貫入速度、及び前記実貫入補助水量に基づいて実修正水セメント比を得る工程と、前記計画修正水セメント比と前記実修正水セメント比とを比較して、前記回転ロッドの引抜き施工時における実スラリー量、及び引抜き速度を求める工程と、を備えていることを特徴としている。 Further, in the soil removal type deep mixing treatment method according to the present invention, when the rotating rod provided in the soil removal type deep mixing treatment machine is penetrated into the improved ground, the slurry produced in the plant is mixed into the ground, and the rotation A soil discharge type deep mixing treatment method that is improved by discharging penetration auxiliary water toward the ground when the rod penetrates, the planned slurry water cement ratio, planned slurry amount, planned penetration auxiliary water amount, plan A step of determining the penetration speed and the planned corrected water-cement ratio that combines the planned mixed water and the planned penetration auxiliary water, a step of measuring the implementation depth, the actual penetration speed, and the actual penetration auxiliary water amount at the time of construction, and in advance A step of obtaining an actual corrected water-cement ratio based on the measured working depth, the actual penetration speed, and the actual penetration auxiliary water amount, and comparing the planned corrected water-cement ratio and the actual corrected water-cement ratio , and obtaining the actual amount of slurry and the drawing speed during the drawing operation of the rotating rod.

本発明では、地盤に吐出する固化材のスラリー量を、管理装置により測定された貫入補助水量の施工情報により引抜き時の施工速度とプラントからのスラリー供給量を自動的に算定し効率よく供給することができ、地盤改良における正確な強度を発揮できる
つまり、貫入補助水施工に対する改良土配合試験により求められる設計基準強度を実現できる、計画スラリー水セメント比、計画スラリー量、計画貫入補助水量、計画貫入速度、計画配合水と計画補助水を合わせた計画修正水セメント比の条件を入力する。実施工において、管理計器により測定入力される実施工深度、実貫入速度、実貫入補助水量から実修正水セメント比を算定する。実補助水量が計画よりも多く実修正水セメント比が計画修正水セメント比よりも大なる場合は、計画修正水セメント比の値となるよう実スラリー量を算定する。実スラリー量を実現できる、プラントから供給するスラリー量と引抜き速度を管理値としてオペレーターに表示し、引抜き施工の状態を管理計器から自動で読み取り照査判定し記録することができる。これにより、本発明では、貫入補助水量に対して引抜き施工時の地盤に吐出するスラリー量を精度よく管理した改良土混合処理を行うことができ、地盤改良における配合計画時の強度を合理的に発現することができる。
In the present invention, the amount of slurry of the solidifying material to be discharged to the ground is automatically calculated and supplied efficiently by automatically calculating the construction speed at the time of pulling out and the amount of slurry supplied from the plant based on the construction information of the penetration auxiliary water amount measured by the management device. In other words, the planned slurry-to-cement ratio, planned slurry volume, planned intrusion supplementary water volume, and planned Enter the conditions for the intrusion rate and the planned modified water-cement ratio, which is the sum of the planned mixed water and the planned auxiliary water. In the implementation work, the actual corrected water-cement ratio is calculated from the implementation depth, actual penetration speed, and actual penetration supplementary water volume measured and input by the control instrument. When the actual auxiliary water amount is larger than the plan and the actual corrected water-cement ratio is larger than the planned corrected water-cement ratio, the actual slurry amount is calculated so as to be the value of the planned corrected water-cement ratio. The amount of slurry supplied from the plant and the withdrawal speed, which can realize the actual amount of slurry, are displayed to the operator as control values, and the state of the extraction work can be automatically read from the control instrument, checked, judged, and recorded. As a result, in the present invention, it is possible to perform an improved soil mixing process that accurately manages the amount of slurry discharged into the ground during pulling work with respect to the amount of intrusion auxiliary water, and the strength at the time of mixing planning in ground improvement can be rationally achieved. can be expressed.

また、本発明に係る貫入補助水施工に対する吐出スラリー量管理システムは、前記算定部では、前記実貫入補助水量が前記計画貫入補助水量よりも多くなり、前記実修正水セメント比が前記計画修正水セメント比よりも大きくなる場合には、前記実修正水セメント比が計画修正水セメント比の値になるように前記実スラリー量が算定されることを特徴としてもよい。 Further, in the discharge slurry amount management system for intrusion auxiliary water construction according to the present invention, in the calculation unit, the actual intrusion auxiliary water amount is larger than the planned intrusion auxiliary water amount, and the actual corrected water-cement ratio is the planned corrected water If it is larger than the cement ratio, the actual slurry amount may be calculated so that the actual corrected water-cement ratio becomes the value of the planned corrected water-cement ratio.

また、本発明に係る排土式深層混合処理工法では、施工前に、排土式深層混合処理機によって施工される改良土の配合を試験する改良土配合試験が行われ、改良土配合試験において、前記計画修正水セメント比が求められることを特徴としてもよい。 In addition, in the soil removal type deep mixing treatment method according to the present invention, before construction, an improved soil mixing test for testing the composition of the improved soil applied by the soil removal type deep mixing treatment machine is performed, and in the improved soil mixing test , wherein the planned modified water-cement ratio is determined.

本発明では、回転ロッドの貫入時に改良土配合試験方法によって得られた結果に基づく補助水量を管理することで、地盤改良時における周辺地盤の変位を小さく抑えることができ、強度発現を実現する引抜き吐出時のスラリー量を自動に瞬時で規定管理できるため、排土式で変位低減型の深層混合処理に好適となり、排土式2軸深層混合処理工法を効果的に採用することができる。 In the present invention, by managing the amount of supplementary water based on the results obtained by the improved soil composition test method when the rotating rod penetrates, it is possible to suppress the displacement of the surrounding ground during ground improvement, and the pulling that realizes strength development. Since the amount of slurry at the time of discharge can be automatically and instantaneously regulated and managed, it is suitable for soil removal type displacement reduction type deep mixing treatment, and the earth removal type biaxial deep mixing treatment method can be effectively adopted.

本発明の貫入補助水施工に対する吐出スラリー量管理システム、及び排土式深層混合処理工法によれば、貫入補助水量に対して引抜き施工時の地盤に吐出するスラリー量を精度よく管理した改良土混合処理を行うことができ、地盤改良における配合計画時の強度を合理的に発現することができる。 According to the discharged slurry amount management system for intrusion auxiliary water construction and the soil removal type deep mixing treatment method of the present invention, the amount of slurry discharged into the ground during pulling construction is accurately controlled with respect to the amount of intrusion auxiliary water Mixing improved soil It can be processed, and the strength at the time of mixing planning in ground improvement can be rationally expressed.

(a)~(f)は、本発明の第1の実施の形態による排土式深層混合処理工法の工程を示す図である。(a) to (f) are diagrams showing the steps of the soil removal type deep mixing treatment method according to the first embodiment of the present invention. 管理システムの構成を示す概要図である。1 is a schematic diagram showing the configuration of a management system; FIG. 施工管理の内容を示す施工管理項目図である。It is a construction management item diagram showing the contents of construction management. 本発明の第1の実施の形態による改良土配合試験方法と排土式深層混合処理工法の作業工程を示すフロー図である。FIG. 2 is a flow chart showing the working process of the improved soil mixing test method and the soil removal type deep layer mixing treatment method according to the first embodiment of the present invention. 本発明の第2の実施の形態による改良土配合試験方法と排土式深層混合処理工法の作業工程の作業工程を示すフロー図である。FIG. 10 is a flow chart showing the work steps of the improved soil mixing test method and the soil removal type deep layer mixing treatment method according to the second embodiment of the present invention.

以下、本発明の実施の形態による貫入補助水施工に対する吐出スラリー量管理システム、及び排土式深層混合処理工法について、図面に基づいて説明する。 Hereinafter, a discharge slurry amount management system for intrusion auxiliary water construction and a soil removal type deep mixing treatment method according to an embodiment of the present invention will be described based on the drawings.

(第1の実施の形態)
図1及び図2に示すように、本実施の形態の貫入時補助水施工に対する吐出スラリー量管理システム(以下、単に管理システム20という)は、排土式深層混合処理機1に設けられる回転ロッド11を改良地盤に貫入させる際に、プラントで製造した固化材のスラリーを地盤Gに混合させるとともに、回転ロッド11の貫入時に貫入補助水を地盤Gに向けて吐出することによる改良土を管理するためのものである。
そして、本実施の形態の排土式深層混合処理工法は、上述した管理システム20によって得られた結果(実スラリー量)を用いて、排土式深層混合処理機1の回転ロッド11を引抜き施工時にスラリーを吐出することによって深層混合処理を行う施工方法である。
また、第1の実施の形態では、排土式深層混合処理機1によって施工される改良土の配合を試験する第1の改良土配合試験方法を適用している。
(First embodiment)
As shown in FIGS. 1 and 2, the discharge slurry amount management system (hereinafter simply referred to as management system 20) for construction of supplementary water during penetration according to the present embodiment is a rotating rod provided in the soil removal type deep mixing treatment machine 1 When penetrating 11 into the improved ground, the slurry of the solidification material produced in the plant is mixed with the ground G, and the improved soil is managed by discharging penetration auxiliary water toward the ground G when the rotating rod 11 penetrates. It is for
In the soil removal type deep mixing treatment method of the present embodiment, the result (actual slurry amount) obtained by the above-described management system 20 is used to pull out the rotating rod 11 of the soil removal type deep mixing treatment machine 1. It is a construction method that performs deep mixing treatment by sometimes discharging slurry.
Moreover, in the first embodiment, the first improved soil mixing test method for testing the mixing of the improved soil constructed by the soil discharge type deep mixing treatment machine 1 is applied.

図1(a)~(f)に示すように、排土式深層混合処理機1は、先端部に撹拌翼12を備え並列に配置された2軸の回転ロッド11、11と、これら2軸の回転ロッド11、11の各外周面に設けられたスパイラル13と、回転ロッド11、11の先端部から地盤Gに固化材を噴出する固化材吐出口14と、を備えている。 As shown in FIGS. 1(a) to 1(f), the soil removal type deep mixing processor 1 includes two rotating rods 11, 11 arranged in parallel with a stirring blade 12 at the tip, and these two shafts spirals 13 provided on the outer peripheral surfaces of the rotating rods 11, 11;

各回転ロッド11は、それぞれ先端部に掘削翼15を備え、それぞれ専用の駆動モータ16によって独立に駆動される。そして、これら回転ロッド11、11の回転方向は、貫入時、引き抜き時においてスパイラル13を回転して排土する方向とする。なお、引き抜き時には、2軸の回転ロッド11、11同士の中央に掘削土を集めた状態で排土する。 Each rotating rod 11 has an excavating wing 15 at its tip and is independently driven by a dedicated driving motor 16 . The direction of rotation of these rotating rods 11, 11 is the direction in which the spiral 13 is rotated and soil is discharged during penetration and extraction. At the time of extraction, the excavated soil is collected in the center of the two rotating rods 11, 11 and discharged.

撹拌翼12は、2軸の回転ロッド11、11の先端部側においてそれぞれ複数段(図示例では4段)で設けられている。各回転ロッド11に設けられる撹拌翼12の撹拌径は、例えば1600mmのものを採用することができる。 The stirring blades 12 are provided in a plurality of stages (four stages in the illustrated example) on the tip end sides of the biaxial rotating rods 11 , 11 . The stirring diameter of the stirring blades 12 provided on each rotating rod 11 can be, for example, 1600 mm.

固化材吐出口14は、各回転ロッド11、11の撹拌翼12近傍に設けられている。そして、回転ロッド11の内部には、軸方向全体にわたって流路(不図示)が設けられており、それら流路の上端部に供給された固化材が固化材吐出口14まで流通する構成となっている。具体的には、ロッド貫入時の改良部先端処理時には固化材を下段側の固化材吐出口14から吐出し、引き抜き時には固化材を上段側の固化材吐出口14から吐出することが基本となっている。なお、本実施の形態のように2軸の回転ロッド11、11の場合には、下段側と上段側の固化材吐出口14を切り替えて使用する。 The solidifying material discharge port 14 is provided in the vicinity of the stirring blade 12 of each of the rotating rods 11 , 11 . Flow paths (not shown) are provided throughout the axial direction inside the rotating rod 11 , and the solidifying material supplied to the upper end of these flow paths flows to the solidifying material discharge port 14 . ing. Specifically, the solidifying material is discharged from the solidifying material discharge port 14 on the lower side when the tip of the improved portion is processed when the rod is inserted, and the solidifying material is discharged from the solidifying material discharge port 14 on the upper side when the rod is pulled out. ing. In the case of the biaxial rotating rods 11, 11 as in the present embodiment, the solidifying material discharge ports 14 on the lower side and the upper side are switched for use.

次に、貫入補助水施工に対する管理システム20について、図2及び図3を用いて具体的に説明する。 Next, the management system 20 for intrusion auxiliary water construction will be specifically described with reference to FIGS. 2 and 3. FIG.

管理システム20は、排土式深層混合処理機1に設けられる回転ロッド11を改良地盤に貫入させる際に、プラントで製造したスラリーを地盤Gに混合させるとともに、回転ロッド11の貫入時に貫入補助水を地盤Gに向けて吐出することによる改良土を管理する貫入補助水施工に適用される。管理システム20は、施工機側(排土式深層混合処理機1側)に設けられる機器に対して、プラント側に設けられる機器及び管理室側に設けられる機器が有線又は無線により接続されている。 The management system 20 mixes the slurry produced in the plant into the ground G when the rotating rod 11 provided in the earth removal type deep mixing treatment machine 1 is penetrated into the improved ground, and the penetration auxiliary water when the rotating rod 11 penetrates It is applied to penetrating auxiliary water construction that manages improved soil by discharging toward the ground G. In the management system 20, the equipment provided on the plant side and the equipment provided on the management room side are connected by wire or wirelessly to the equipment provided on the construction machine side (the soil removal type deep mixing treatment machine 1 side). .

管理システム20は、施工計画時に管理する品質管理部20Aと、施工時に管理する施工計測部20B、施工管理部20C、及び算定部20Dと、を備えている。 The management system 20 includes a quality control section 20A that manages construction planning, a construction measurement section 20B that manages construction, a construction management section 20C, and a calculation section 20D.

品質管理部20Aには、施工計画時に得られる計画スラリー水セメント比、計画スラリー量、計画貫入補助水量、計画貫入速度、及び計画配合水と計画補助水とを合わせた計画修正水セメント比が入力される。排土式深層混合処理機1による貫入施工時には、品質管理部で入力された計画修正水セメント比に基づいて貫入スラリーが吐出される。 In the quality control section 20A, the planned slurry water-cement ratio obtained at the time of construction planning, the planned slurry amount, the planned intrusion auxiliary water amount, the planned intrusion speed, and the planned modified water-cement ratio obtained by combining the planned mixed water and the planned auxiliary water are input. be done. At the time of penetration construction by the excavation type deep mixing treatment machine 1, penetration slurry is discharged based on the planned corrected water-cement ratio input by the quality control department.

施工機側には、システム計測盤21と、排土式深層混合処理機1の運転席に設けられる施工管理装置22と、が設けられている。システム計測盤21と施工管理装置22とは、互いに後述する施工計測部20Bで検出した計測データ等のデータDが送受信される。 On the construction machine side, a system measurement panel 21 and a construction management device 22 provided at the driver's seat of the soil removal type deep mixing treatment machine 1 are provided. The system measurement panel 21 and the construction management device 22 mutually transmit and receive data D such as measurement data detected by a construction measurement unit 20B, which will be described later.

システム計測盤21は、施工計測部20Bとして設けられる計測機器で検出された計測データが集約される。施工計測部20Bは、施工機(排土式深層混合処理機1)で施工される回転ロッド11の先端部の深度(実施工深度)や昇降速度(実貫入速度)を計測する深度・速度検出計23と、回転ロッド11の回転数を計測する回転検出計24と、回転ロッド11を駆動する駆動モータ16の電流値を計測する電流検出計25と、を備えている。また、施工計測部20Bは、回転ロッド11を貫入するときの貫入補助水量を測定する流量計等の機器(図示省略)が設けられている。 The system measurement panel 21 aggregates the measurement data detected by the measurement equipment provided as the construction measurement unit 20B. The construction measurement unit 20B is a depth and speed detection that measures the depth (implementation depth) and lifting speed (actual penetration speed) of the tip of the rotating rod 11 that is constructed by the construction machine (earth removal type deep mixing treatment machine 1). a total 23 , a rotation detector 24 for measuring the number of rotations of the rotating rod 11 , and a current detector 25 for measuring the current value of the drive motor 16 that drives the rotating rod 11 . In addition, the construction measuring unit 20B is provided with a device (not shown) such as a flow meter for measuring the intrusion auxiliary water volume when the rotating rod 11 penetrates.

これら深度・速度検出計23、回転検出計24、及び電流検出計25で検出された測定値はシステム計測盤21に集約されて施工管理装置22へ送られる。施工管理装置22は、施工管理部20Cと、算定部20Dと、を有している。
施工管理部20Cでは、施工計測部20Bで測定された実施工深度、実貫入速度、及び実貫入補助水量に基づいて実修正水セメント比が得られる。
Measured values detected by the depth/speed detector 23 , the rotation detector 24 , and the current detector 25 are collected in the system measurement panel 21 and sent to the construction management device 22 . The construction management device 22 has a construction management section 20C and a calculation section 20D.
The construction management unit 20C obtains the actual corrected water-cement ratio based on the actual depth of work, the actual intrusion speed, and the actual intrusion auxiliary water amount measured by the construction measurement unit 20B.

算定部20Dは、品質管理部20Aで得られた計画修正水セメント比と施工管理部で得られた実修正水セメント比とを比較して、回転ロッド11の引抜き施工時における実スラリー量、及び引抜き速度が算定される。例えば、算定部20Dでは、実貫入補助水量が計画貫入補助水量よりも多くなり、実修正水セメント比が計画修正水セメント比よりも大きくなる場合には、実修正水セメント比が計画修正水セメント比の値になるように実スラリー量を算定することができる。 The calculation unit 20D compares the planned corrected water-cement ratio obtained by the quality control unit 20A and the actual corrected water-cement ratio obtained by the construction control unit, and calculates the actual amount of slurry during the drawing construction of the rotating rod 11, and A withdrawal speed is calculated. For example, in the calculation unit 20D, when the actual intrusion auxiliary water amount is larger than the planned intrusion auxiliary water amount and the actual corrected water-cement ratio is larger than the planned corrected water-cement ratio, the actual corrected water-cement ratio becomes the planned corrected water-cement ratio. The actual slurry amount can be calculated so as to achieve the ratio value.

プラントは、排土式深層混合処理機1を使用した貫入補助水施工において、排土式深層混合処理機1の回転ロッド11を貫入した後に引き抜く際に、排土式深層混合処理機1から地盤G中に注入されるスラリーを製造する。
プラント側には、一対の補助水・スラリー流量計26(26A、26B)が設けらている。これら補助水・スラリー流量計26A、26Bは、補助水とスラリーの流量を検出するものである。補助水・スラリー流量計26A、26Bのそれぞれで計測された流量値は施工機側のシステム計測盤21に集約されて施工管理装置22へ送られる。
In the construction of penetration auxiliary water using the soil removal type deep mixing treatment machine 1, the plant removes the ground from the earth removal type deep mixing treatment machine 1 when pulling out after penetrating the rotating rod 11 of the earth removal type deep mixing treatment machine 1. Prepare slurry to be injected into G.
A pair of auxiliary water/slurry flow meters 26 (26A, 26B) are provided on the plant side. These auxiliary water/slurry flowmeters 26A and 26B detect the flow rates of auxiliary water and slurry. The flow rate values measured by the auxiliary water/slurry flowmeters 26A and 26B are collected in the system measurement panel 21 on the construction machine side and sent to the construction management device 22 .

管理室側には、例えば日報作成用のコンピュータ27やプリンタ28が設けられている。コンピュータ27は、施工管理装置22に接続され、データDのやり取りができるようになっている。また、プリンタ28では、コンピュータ27で作成された管理結果等が出力される。 For example, a computer 27 and a printer 28 for creating daily reports are provided on the management room side. The computer 27 is connected to the construction management device 22 so that data D can be exchanged. Also, the printer 28 outputs the management results and the like created by the computer 27 .

次に、管理システム20の管理項目や管理内容について、図2及び図3に基づいてさらに具体的に説明する。
本実施の形態の管理システム20では、材料の品質、改良体の出来形、変位を管理する。
Next, the management items and management contents of the management system 20 will be described more specifically with reference to FIGS. 2 and 3. FIG.
The management system 20 of this embodiment manages the quality of the material, the finished shape of the improved body, and the displacement.

図3に示すように、材料の品質については、貫入補助水施工で使用されプラントで製造されるスラリーの材料、スラリーの配合、混合(スラリーの混練状態)が管理される。
スラリーの材料の管理内容は、材料の計量であり、計量器を用いて検定される。計量器で検定された材料の検定値は、例えばデジタル印字表等でコンピュータ27に送られる。
スラリーの配合の管理内容は、貫入補助水または固化材スラリー流量計(図2に示す補助水・スラリー流量計26A)と処理機昇降速度計(図2に示す深度・速度検出計23)を使用して検出された改良土1m当りのセメント量の確認である。
スラリーの混練状態の管理内容は、排土式深層混合処理機1(処理機)の軸回転計(回転検出計24)によって混練性能の確認である。
As shown in FIG. 3, with regard to the quality of materials, the slurry materials, slurry blending, and mixing (slurry kneading state) used in penetration auxiliary water construction and produced in the plant are managed.
The content of control of the slurry material is the weighing of the material, which is verified using a weighing machine. The test values of the material tested by the scale are sent to the computer 27 in the form of a digital printed table, for example.
Slurry blending is managed using a penetrating auxiliary water or solidifying material slurry flow meter (auxiliary water/slurry flow meter 26A shown in Figure 2) and a processor lift speed meter (depth/speed detector 23 shown in Figure 2). This is confirmation of the amount of cement per 1m3 of improved soil detected by
The content of management of the kneading state of the slurry is confirmation of the kneading performance by the shaft rotation meter (rotation detector 24) of the soil removal type deep mixing treatment machine 1 (treatment machine).

改良体の出来形については、排土式深層混合処理機1による打設位置、打設深度、着底(着底状態)とされている。打設位置の管理内容は、例えばトータルステーション等の測量機器を使用して処理杭1本ごとの打設位置を確認することである。打設深度の管理内容は、処理機深度計(図2に示す深度・速度検出計23)によって検出される処理杭1本ごとの打設深度を確認することである。着底状態の管理内容は、処理機回転モータの油圧計または電流計(図2に示す電流検出計25)、及び処理機昇降速度計(図2に示す深度・速度検出計23)によって検出される所定深度に到達したことの確認である。 The finished shape of the improved body is determined by the placing position, placing depth, and bottoming (bottoming state) by the earth-removing deep-layer mixer 1 . The content of management of the driving position is to confirm the driving position of each treated pile using a surveying instrument such as a total station. The content of management of the driving depth is to confirm the driving depth of each treated pile detected by the processing machine depth gauge (depth/speed detector 23 shown in FIG. 2). The content of the management of the bottoming state is detected by the oil pressure gauge or ammeter (current detector 25 shown in FIG. 2) of the processing machine rotating motor and the processing machine lifting speed meter (depth/speed detector 23 shown in FIG. 2). It is confirmation that the predetermined depth has been reached.

改良体の変位の管理内容は、処理機回転計(図2に示す回転検出計24)、及びスクリュー形状等に基づいて処理杭1本ごとの排土量を確認することである。 The content of managing the displacement of the improved body is to confirm the amount of discharged soil for each treated pile based on the processing machine tachometer (rotation detector 24 shown in FIG. 2) and the shape of the screw.

管理システム20では、管理内容である材料の品質、改良体の出来形、変位は、コンピュータ27に送られ施工評価され、施工に適している場合(=YES)にはパソコン(PC)で日報が作成され、不適な場合(=NO)には修正する施工が行われる。 In the management system 20, the quality of the material, the finished shape of the improved body, and the displacement, which are the contents of management, are sent to the computer 27 and evaluated for construction. It is created, and if it is inappropriate (=NO), construction to correct it is performed.

ここで、管理システム20によって管理されるスラリーの水セメント比の考え方について以下に示す。
施工計画時の配合は、以下の5つである。
配合セメント質量:C配合(kg)
配合水質量 :W配合(kg)
配合水セメント比:W配合/C配合
計画貫入補助水量 :W計画補助(kg)
計画修正水セメント比:(W配合+W計画補助水)/C配合
貫入施工時の配合は、以下の2つである。
実貫入補助水量 :W施工補助水(kg)>W配合
実修正水セメント比 :(W配合+W施工補助水)/C配合>(W配合+W計画補助水)/C配合
引抜き施工時の配合は、以下の3つである。
実セメント質量 :C引抜 (kg)>C配合
実水セメント比 :W引抜/C引抜=W配合/C配合
引抜き修正水セメント比:(W引抜+W施工補助水)/C引抜=(W配合+W計画補助水)/C配合
Here, the concept of the slurry water-cement ratio managed by the management system 20 will be described below.
The following five formulations were used during construction planning.
Blended cement mass: C blended (kg)
Blended water mass: W blended (kg)
Blended water cement ratio: W blended /C blended
Planned intrusion supplementary water volume: W plan supplement (kg)
Plan modified water cement ratio: (W mix + W plan auxiliary water )/C mix
The following two formulations are used for penetration construction.
Actual intrusion auxiliary water amount: W construction auxiliary water (kg) > W blend
Actual modified water-cement ratio: (W mixture + W construction auxiliary water )/C mixture > (W mixture + W planning auxiliary water )/C mixture
The following three formulations are used for drawing construction.
Actual cement mass: C extraction (kg) > C mix
Actual water cement ratio: W extraction /C extraction = W mixture /C mixture
Extraction modified water-cement ratio: (W extraction + W construction auxiliary water ) / C extraction = (W composition + W planning auxiliary water ) / C composition

次に、上述した管理システム20を用いた第1の改良土配合試験方法、及び第1の排土式深層混合処理工法について、図面に基づいて具体的に説明する。
第1の排土式深層混合処理工法は、施工計画時に得られる計画スラリー水セメント比、計画スラリー量、計画貫入補助水量、計画貫入速度、及び計画配合水と計画貫入補助水とを合わせた計画修正水セメント比を求める工程と、施工時において、実施工深度、実貫入速度、及び実貫入補助水量を測定する工程と、予め測定された実施工深度、実貫入速度、及び実貫入補助水量に基づいて実修正水セメント比を得る工程と、計画修正水セメント比と実修正水セメント比とを比較して、回転ロッド11の引抜き施工時における実スラリー量、及び引抜き速度を求める工程と、を有している。
Next, the first improved soil mixing test method and the first soil removal type deep mixing treatment method using the management system 20 described above will be specifically described based on the drawings.
The first soil removal type deep mixing treatment method is a plan that combines the planned slurry water cement ratio, planned slurry amount, planned penetration auxiliary water amount, planned penetration speed, and planned mixed water and planned penetration auxiliary water obtained at the time of construction planning. The process of obtaining the corrected water-cement ratio, the process of measuring the working depth, the actual penetration speed, and the actual penetration auxiliary water amount during construction, and the previously measured working depth, the actual penetration speed, and the actual penetration auxiliary water amount. and a step of comparing the planned corrected water-cement ratio and the actual corrected water-cement ratio to determine the actual amount of slurry and the drawing speed during the drawing operation of the rotating rod 11. have.

先ず、図4を用いて第1の改良土配合試験方法について説明する。
ステップS1において、規定量の試料土と、回転ロッド11(図1参照)の貫入時に地盤Gに向けて吐出される所定の補助水量の水とを混合する。その後、ステップS1で混合した試料土と所定量の補助水とを10分間で一次撹拌を行い(ステップS2)、規定量の含水比試料土を作成する(ステップS3)。なお、このときの一次撹拌に要する時間は、通常、地盤工学会基準JGS0821-2009に定める10分程度である。
First, the first improved soil mixing test method will be described with reference to FIG.
In step S1, a prescribed amount of sample soil is mixed with a prescribed auxiliary amount of water discharged toward the ground G when the rotary rod 11 (see FIG. 1) penetrates. After that, the sample soil mixed in step S1 and a predetermined amount of auxiliary water are subjected to primary agitation for 10 minutes (step S2) to prepare a specified amount of water content sample soil (step S3). The time required for the primary stirring at this time is usually about 10 minutes defined by the Japanese Geotechnical Society standard JGS0821-2009.

次に、ステップS4では、ステップS3で作成した規定量の含水比試料土に対して硬化材を混合する。その後、混合した規定量の含水比試料土と硬化材とを10分間で二次撹拌を行い(ステップS5)、改良土供試体を作成する(ステップS6)。なお、このときの二次撹拌に要する時間は、通常、地盤工学会基準JGS0821-2009に定める10分程度である。
ここまでのステップS1~S6が、第1の改良土配合試験方法による作業フローとなる。
Next, in step S4, a hardening material is mixed with the specified amount of the water content ratio sample soil prepared in step S3. After that, the water content ratio sample soil and the hardening material of the mixed specified amount are subjected to secondary agitation for 10 minutes (Step S5) to prepare an improved soil specimen (Step S6). The time required for the secondary stirring at this time is usually about 10 minutes as defined by the Japanese Geotechnical Society standard JGS0821-2009.
Steps S1 to S6 up to this point constitute the work flow according to the first modified soil mixing test method.

次に、第1の排土式深層混合処理工法について具体的に説明する。
第1の排土式深層混合処理工法では、先ず、ステップS7において、上述した第1の改良土配合試験方法により作成された改良土供試体で強度試験を実施し配合を分析する。すなわち、ステップS7で作成された改良土供試体の配合を変化させて強度試験を行い、貫入補助水量と配合の組み合わせを選定する。
Next, the first soil removal type deep layer mixing treatment method will be specifically described.
In the first soil removal type deep mixing treatment method, first, in step S7, a strength test is performed on the improved soil specimen prepared by the above-described first improved soil mixing test method to analyze the mixing. That is, the composition of the improved soil test piece prepared in step S7 is changed and the strength test is performed to select the combination of the intrusion auxiliary water amount and the composition.

その後、ステップS8において、改良土供試体の分析結果に基づいて図1に示す排土式深層混合処理機1の回転ロッド11の貫入施工時の貫入補助水量を設定する。次いで、後述する施工時において、図1に示す撹拌翼12に設けられる固化材吐出口14から地盤Gに向けて水を吐出し流動化を促進するための補助水量(前記ステップS8で設定した貫入補助水量)を掘削深度毎に制御しながら貫入することにより施工する。 After that, in step S8, based on the analysis result of the modified soil test piece, the penetrating supplementary water amount at the time of penetrating work of the rotating rod 11 of the earth-discharging-type deep-seating treatment machine 1 shown in FIG. 1 is set. Next, during construction, which will be described later, water is discharged from the solidifying material discharge port 14 provided on the stirring blade 12 shown in FIG. Supplementary water volume) is controlled for each excavation depth.

具体的な施工としては、先ず、図2に示す管理システム20において計画配合の施工条件である計画スラリー水セメント比、計画スラリー量、計画貫入補助水量、計画貫入速度、及び計画配合水と計画補助水とを合わせた計画修正水セメント比を品質管理部に入力する。 As a specific construction, first, in the management system 20 shown in FIG. Enter the planned modified water-cement ratio combined with water into the quality control department.

次に、図1(a)、(b)に示すように、排土式深層混合処理機1を所定の施工位置に位置決めした後、2軸の回転ロッド11、11をそれぞれ回転させて地盤Gに貫入していく。その際、実貫入速度を考慮して回転ロッド11、11の回転量を適正に制御してそれぞれのスパイラル13により排土を行う。このとき、撹拌翼12に設けられる固化材吐出口14から地盤Gに向けて水を吐出し、流動化を促進するための貫入補助水量(前記ステップS8で設定した貫入補助水量)を掘削深度毎に制御しながら貫入する。 Next, as shown in FIGS. 1(a) and 1(b), after positioning the soil removal type deep mixing treatment machine 1 at a predetermined construction position, the two-axis rotating rods 11 and 11 are rotated to remove the ground G. penetrate into. At that time, the amount of rotation of the rotating rods 11, 11 is appropriately controlled in consideration of the actual intrusion speed, and the soil is discharged by each spiral 13. At this time, water is discharged from the solidifying material discharge port 14 provided in the stirring blade 12 toward the ground G, and the penetration auxiliary water amount (penetration auxiliary water amount set in step S8) for promoting fluidization is adjusted for each excavation depth. Penetrate in a controlled way.

掘削深度毎の吐出された貫入補助水量は、図2のプラント側の補助水・スラリー流量計26Aにより計測され施工管理装置に施工と同時に記録される。そして、施工管理装置22の施工管理部20Cにおいて予め測定された実施工深度、実貫入速度、及び実施工で吐出された実貫入補助水量から実修正水セメント比を算定する。
その後、算定部20Dにおいて計画修正水セメント比と前記実修正水セメント比とを比較して、実修正水セメント比を計画時に一致させるように引抜き施工時に吐出スラリー量を算定し、プラントから供給される実スラリー量と引抜き速度とを規定し引抜き施工時に施工管理値として管理される。
The amount of intrusion auxiliary water discharged for each excavation depth is measured by the auxiliary water/slurry flow meter 26A on the plant side in FIG. 2 and recorded in the construction management device at the same time as the construction. Then, the construction management unit 20C of the construction management device 22 calculates the actual modified water-cement ratio from the previously measured construction depth, actual penetration speed, and actual penetration auxiliary water amount discharged during construction.
Thereafter, the calculation unit 20D compares the planned corrected water-cement ratio with the actual corrected water-cement ratio, calculates the amount of slurry to be discharged at the time of pulling construction so that the actual corrected water-cement ratio matches the time of planning, and is supplied from the plant. The actual slurry amount and the drawing speed are specified and managed as construction control values during the drawing work.

そして、図1(c)に示すように、回転ロッド11、11の先端(掘削翼15)が所定の改良下端深度に到達したときに貫入を停止する。 Then, as shown in FIG. 1(c), the penetration is stopped when the tips (excavation blades 15) of the rotating rods 11, 11 reach a predetermined improved bottom depth.

次いで、図1(d)、(e)に示すように、回転ロッド11、11を改良領域P中の途中まで引き抜く。このときの各回転ロッド11は、上述した吐出スラリー量の固化材を固化材吐出口14より吐出させながら回転ロッド11、11及び撹拌翼12を貫入時の回転を維持したまま引き上げることで、1スパンあたりの改良領域Pの地盤改良が完了する(図1(f)参照)。
この際、引抜き速度とプラントから送るスラリー量は図2の施工管理装置22に示され、図3の施工管理計(流量計、昇降速度計)からの測定量として施工管理装置22にて評価判断する。
Next, as shown in FIGS. 1(d) and 1(e), the rotating rods 11, 11 are pulled out halfway through the improvement area P. Then, as shown in FIGS. At this time, each rotating rod 11 discharges the solidifying material in the amount of discharge slurry from the solidifying material discharge port 14, and pulls up the rotating rods 11 and 11 and the stirring blade 12 while maintaining the rotation at the time of penetration. The ground improvement of the improvement area P per span is completed (see FIG. 1(f)).
At this time, the withdrawal speed and the amount of slurry sent from the plant are shown in the construction management device 22 in FIG. do.

そして、所望深度までの改良体が施工された後、図1(f)に示すように排土式深層混合処理機1の装置全体を地上に引き上げて次の施工位置まで移動させ、上述した改良土配合試験方法により得られた貫入補助水量に基づいて図1(a)~(f)の工程を同様に繰り返して他の改良体を施工する。 Then, after the improved body is constructed to the desired depth, as shown in FIG. Based on the intrusion auxiliary water amount obtained by the soil mixing test method, the steps of FIGS.

上述のように本実施の形態による貫入補助水施工に対する吐出スラリー量管理システム、及び排土式深層混合処理工法では、地盤Gに吐出する水の補助水量を精度よく管理した改良土混合処理を行うことができ、改良強度を確実に発現するためのスラリー量管理が即時にできるため、地盤改良における正確な強度を把握することができる。 As described above, in the discharge slurry amount management system and the soil discharge type deep mixing treatment method for intrusion auxiliary water construction according to the present embodiment, improved soil mixing treatment is performed in which the auxiliary water amount discharged to the ground G is accurately controlled. Since it is possible to control the amount of slurry in order to develop the improved strength reliably, it is possible to grasp the correct strength in ground improvement.

(第2の実施の形態)
次に、第2の実施の形態による貫入時補助水施工に対する吐出スラリー量管理システム、及び排土式深層混合処理工法について、図5に示すフロー図に基づいて説明する。
第2の実施の形態では、排土式深層混合処理機1によって施工される改良土の配合を試験する第2の改良土配合試験方法を適用したものである。本試験方法で改良土の配合を試験する排土式深層混合処理機1(図1参照)は上述した第1の実施の形態と同様である。また、第2の実施の形態においても、第1の実施の形態で用いた図1~図4を参照して説明する。
(Second embodiment)
Next, a discharge slurry amount management system for auxiliary water construction during penetration and a soil removal type deep mixing treatment method according to the second embodiment will be described based on the flowchart shown in FIG. 5 .
In the second embodiment, the second improved soil mixing test method for testing the mixing of the improved soil constructed by the soil discharge type deep mixing treatment machine 1 is applied. The soil discharge type deep mixing treatment machine 1 (see FIG. 1) for testing the blending of improved soil in this test method is the same as that of the first embodiment described above. Also, the second embodiment will be described with reference to FIGS. 1 to 4 used in the first embodiment.

先ず、ステップS10において、規定量の試料土を作成する。
一方で、回転ロッド11(図1参照)の貫入速度と地盤Gに向けて吐出される所定の貫入補助水量を設定する(ステップS11)。その後、ステップS11で設定した貫入速度で撹拌される対象土に投入される貫入補助水量を算定する(ステップS12)。具体的には、改良対象土の体積当たり貫入補助水量を算定する。そして、ステップS13において、投入される貫入補助水量から排土率を設定して排土量を算定する。さらに、排土後の改良対象土量に対する規定配合(水セメント比)から、セメント添加量と配合水量を算定する(ステップS14)。
First, in step S10, a specified amount of sample soil is prepared.
On the other hand, the penetration speed of the rotary rod 11 (see FIG. 1) and the predetermined amount of auxiliary penetration water discharged toward the ground G are set (step S11). After that, the penetration auxiliary water amount to be thrown into the target soil that is agitated at the penetration speed set in step S11 is calculated (step S12). Specifically, the intrusion supplementary water volume per volume of the soil to be improved is calculated. Then, in step S13, the discharged soil amount is calculated by setting the discharged soil rate based on the amount of intrusion supplementary water that is supplied. Further, the amount of cement to be added and the amount of water to be mixed are calculated from the prescribed mixture (water-cement ratio) for the amount of soil to be improved after soil removal (step S14).

その後、ステップS15において、算定されたセメント添加量、配合水量と貫入補助水量から、修正した水セメント比(修正水セメント比)を算定する。ステップS10で作成した規定量の試料土に対して修正水セメント比の硬化材を混合する(ステップS16)。その後、ステップS10で混合した規定量の試料土と、修正水セメント比の硬化材とを10分間撹拌を行い(ステップS17)、改良土供試体を作成する(ステップS18)。
なお、このときの撹拌に要する時間は、通常、地盤工学会基準JGS0821-2009に定める10分程度である。
ここまでのステップS10~S18が、第2の改良土配合試験方法による作業フローとなる。
After that, in step S15, a corrected water-cement ratio (corrected water-cement ratio) is calculated from the calculated cement addition amount, mixing water amount, and intrusion supplementary water amount. A hardener having a corrected water-cement ratio is mixed with the specified amount of sample soil prepared in step S10 (step S16). Thereafter, the prescribed amount of sample soil mixed in step S10 and the hardening material with the corrected water-cement ratio are stirred for 10 minutes (step S17) to prepare an improved soil specimen (step S18).
The time required for stirring at this time is usually about 10 minutes as defined by the Japanese Geotechnical Society standard JGS0821-2009.
Steps S10 to S18 up to this point constitute the work flow according to the second improved soil mixing test method.

次に、第2の排土式深層混合処理工法では、先ず、ステップS19において、上述した第2改良土配合試験方法により作成された改良土供試体で強度試験を実施し配合を分析する。具体的には、ステップS19で作成された改良土供試体の配合を変化させて強度試験を行い、貫入補助水量と配合の組み合わせを選定する。 Next, in the second soil removal type deep mixing treatment method, first, in step S19, a strength test is performed on the improved soil specimen prepared by the above-described second improved soil mixing test method to analyze the mixing. Specifically, the composition of the improved soil test piece prepared in step S19 is changed and a strength test is performed to select a combination of penetration auxiliary water amount and composition.

その後、ステップS20において、改良土供試体の分析結果に基づいて図1に示す排土式深層混合処理機1の回転ロッド11の貫入施工時の計画貫入補助水量を設定する。次いで、後述する施工時において、撹拌翼12に設けられる固化材吐出口14から地盤Gに向けて水を吐出し流動化を促進するための補助水量(ステップS20で設定した計画貫入補助水量)を掘削深度毎に制御しながら貫入することにより施工する。
実施工での実貫入補助水量に基づく引抜き時のスラリー量管理の具体的な施工としては、上述した第1の実施の形態と同様であるのでここでは詳しい説明を省略する。
After that, in step S20, based on the analysis result of the improved soil test piece, a planned intrusion supplementary water amount at the time of penetrating work of the rotary rod 11 of the soil removal type deep mixing treatment machine 1 shown in FIG. 1 is set. Next, at the time of construction, which will be described later, an auxiliary water amount (planned intrusion auxiliary water amount set in step S20) for discharging water from the solidifying material discharge port 14 provided in the stirring blade 12 toward the ground G and promoting fluidization is set. It is constructed by penetrating while controlling each excavation depth.
The specific construction of slurry amount management at the time of drawing based on the actual intrusion auxiliary water amount in the actual construction is the same as in the above-described first embodiment, so detailed description will be omitted here.

第2の実施の形態では、試料土の性状は現地の性状のまま試験を行うことができる。混合する硬化材に対して、規定の配合に対する配合水に貫入時の貫入補助水量を加算し、排土量を考慮して新たに水セメント量を修正して計算する。この修正水セメント量で配合した硬化材を試料土と混合することで改良土供試体を作成し、作成された改良土供試体を分析した分析結果に基づいて排土式深層混合処理機1の撹拌翼12の貫入施工時の補助水量を設定することができる。 In the second embodiment, the test can be performed with the properties of the sample soil as they are at the site. For the hardening material to be mixed, add the penetration supplementary water amount at the time of penetration to the formulation water for the specified formulation, and consider the amount of discharged soil and newly correct the amount of water cement to calculate. By mixing the hardening material mixed with this corrected amount of water cement with the sample soil, an improved soil test piece was created, and based on the analysis results of analyzing the prepared improved soil test piece, the soil discharge type deep mixing treatment machine 1 It is possible to set the amount of auxiliary water when the impeller 12 is penetrated.

このように本第2の実施の形態では、事前に補助水による土質性状の変化(水分の増加、土粒子分の減少)を反映した配合試験を行って管理することができる。とくに、本実施の形態では、上述したように回転ロッド11の貫入時に補助水を吐出するため含水比が高くなった混合土が排出されるが、吐出される水の補助水量が好適な量に精度よく管理されるため、地盤改良時における周辺地盤の変位を小さく抑えることができる。 As described above, in the second embodiment, it is possible to conduct a mixing test in advance to reflect changes in soil properties (increase in water content, decrease in soil particle content) caused by supplementary water, and control. In particular, in the present embodiment, as described above, since the auxiliary water is discharged when the rotary rod 11 penetrates, the mixed soil with a high water content is discharged, but the auxiliary water amount of the discharged water is reduced to a suitable amount. Because it is managed with high accuracy, displacement of the surrounding ground during ground improvement can be kept small.

また、改良土供試体の作成方法については、従来規定されている作成方法(地盤工学会基準JGS0821-2009、「安定処理土の締固めをしない供試体作製方法」)によることができるため、他の試験結果とも比較検証ができ再現性もあり、試験結果を保証することができる。 In addition, as for the preparation method of the improved soil specimen, it is possible to use the conventional preparation method (Geotechnical Society Standard JGS0821-2009, "Method for preparation of specimen without compaction of stabilized soil"). The test results can be compared and verified with reproducibility, and the test results can be guaranteed.

以上、本発明による貫入補助水施工に対する吐出スラリー量管理システム、及び排土式深層混合処理工法の実施の形態について説明したが、本発明は上記の実施の形態に限定されるものではなく、その趣旨を逸脱しない範囲で適宜変更可能である。 As described above, the embodiment of the discharge slurry amount management system and the soil removal type deep mixing treatment method for construction of intrusion auxiliary water according to the present invention has been described, but the present invention is not limited to the above embodiment. It can be changed as appropriate without departing from the spirit.

例えば、上述した実施の形態では、管理システム20において、算定部20Dでは、実貫入補助水量が計画貫入補助水量よりも多くなり、実修正水セメント比が計画修正水セメント比よりも大きくなる場合には、実修正水セメント比が計画修正水セメント比の値になるように実スラリー量が算定されるように管理しているが、このような管理方法に限定されることはない。 For example, in the above-described embodiment, in the management system 20, when the actual intrusion supplementary water amount is greater than the planned intrusion supplementary water amount and the actual corrected water-cement ratio is larger than the planned corrected water-cement ratio, the calculation unit 20D manages the amount of actual slurry so that the actual corrected water-cement ratio becomes the value of the planned corrected water-cement ratio, but is not limited to such a management method.

また、本実施形態では、施工前に、排土式深層混合処理機1によって施工される改良土の配合を試験する改良土配合試験が行われ、改良土配合試験において、前記計画修正水セメント比が求められる方法を採用しているが、改良土配合試験を実施しない施工方法であってもよい。 Further, in this embodiment, before construction, an improved soil mixing test for testing the mixing of the improved soil applied by the soil discharge type deep mixing treatment machine 1 is performed, and in the improved soil mixing test, the planned corrected water cement ratio Although a method that requires is adopted, a construction method that does not conduct an improved soil mixing test may be used.

また、本実施の形態では、排土式深層混合処理機1として、回転ロッド11が2軸で設けられ、撹拌翼12は撹拌径が1600mm以上の太径の装置を採用しているが、これに限定されることはなく、撹拌径が例えば1000mm~1300mmのものを用いるようにしてもよい。例えば、貫入時の抵抗が大きいと想定される地盤では、上述した1600mm以上でない撹拌径のものを採用することも可能である。 Further, in this embodiment, as the soil discharge type deep mixing treatment machine 1, the rotary rod 11 is provided with two shafts, and the stirring blade 12 has a large diameter device with a stirring diameter of 1600 mm or more. , and a stirring diameter of, for example, 1000 mm to 1300 mm may be used. For example, it is possible to adopt the above-mentioned stirring diameter of not more than 1600 mm in the ground which is assumed to have a large resistance at the time of penetration.

その他、本発明の趣旨を逸脱しない範囲で、上記した実施の形態における構成要素を周知の構成要素に置き換えることは適宜可能である。 In addition, it is possible to appropriately replace the components in the above-described embodiments with well-known components without departing from the scope of the present invention.

1 排土式深層混合処理機
11 回転ロッド
20 管理システム(吐出スラリー量管理システム)
20A 品質管理部
20B 施工計測部
20C 施工管理部
20D 算定部
21 システム計測盤
22 施工管理装置
23 深度・速度検出計
24 回転検出計
25 電流検出計
26、26A、26B 補助水・スラリー流量計
27 コンピュータ
G 地盤
1 earth-discharging type deep mixing processor 11 rotating rod 20 management system (dispensed slurry amount management system)
20A Quality Control Department 20B Construction Measurement Department 20C Construction Management Department 20D Calculation Department 21 System measurement panel 22 Construction management device 23 Depth/speed detector 24 Rotation detector 25 Current detector 26, 26A, 26B Auxiliary water/slurry flow meter 27 Computer G Ground

Claims (4)

排土式深層混合処理機に設けられる回転ロッドを改良地盤に貫入させる際に、プラントで製造したスラリーを地盤に混合させるとともに、前記回転ロッドの貫入時に貫入補助水を地盤に向けて吐出することによる改良土を管理する貫入補助水施工に対する吐出スラリー量管理システムであって、
施工計画時に得られる計画スラリー水セメント比、計画スラリー量、計画貫入補助水量、計画貫入速度、及び計画配合水と計画貫入補助水とを合わせた計画修正水セメント比が入力される品質管理部と、
施工時において、実施工深度、実貫入速度、及び実貫入補助水量を測定する施工計測部と、
前記施工計測部で測定された前記実施工深度、前記実貫入速度、及び前記実貫入補助水量に基づいて実修正水セメント比を得る施工管理部と、
前記計画修正水セメント比と前記実修正水セメント比とを比較して、前記回転ロッドの引抜き施工時における実スラリー量、及び引抜き速度を算定する算定部と、
を備えていることを特徴とする貫入補助水施工に対する吐出スラリー量管理システム。
When the rotating rod provided in the earth-discharging type deep mixing treatment machine is penetrated into the improved ground, the slurry produced in the plant is mixed with the ground, and the penetration auxiliary water is discharged toward the ground when the rotating rod penetrates. A discharge slurry amount management system for intrusion auxiliary water construction that manages improved soil by
A quality control department that inputs the planned slurry water-cement ratio, planned slurry volume, planned intrusion supplementary water quantity, planned intrusion speed, and planned modified water-cement ratio that combines planned mixed water and planned intrusion supplementary water obtained at the time of construction planning; ,
A construction measurement unit that measures the depth of construction, the actual penetration speed, and the amount of auxiliary water for actual penetration during construction,
a construction management unit that obtains an actual modified water-cement ratio based on the actual depth of construction measured by the construction measurement unit, the actual intrusion speed, and the actual intrusion auxiliary water amount;
a calculation unit that compares the planned corrected water-cement ratio and the actual corrected water-cement ratio to calculate the actual amount of slurry and the drawing speed during the drawing operation of the rotating rod;
A discharge slurry amount management system for intrusion auxiliary water construction, characterized by comprising:
前記算定部では、前記実貫入補助水量が前記計画貫入補助水量よりも多くなり、前記実修正水セメント比が前記計画修正水セメント比よりも大きくなる場合には、前記実修正水セメント比が計画修正水セメント比の値になるように前記実スラリー量が算定されることを特徴とする請求項1に記載の貫入補助水施工に対する吐出スラリー量管理システム。 In the calculation unit, when the actual intrusion auxiliary water amount is larger than the planned intrusion auxiliary water amount and the actual corrected water-cement ratio is larger than the planned corrected water-cement ratio, the actual corrected water-cement ratio is set to the planned 2. The discharge slurry amount management system for penetration auxiliary water construction according to claim 1, wherein the actual slurry amount is calculated so as to have a corrected water-cement ratio value. 排土式深層混合処理機に設けられる回転ロッドを改良地盤に貫入させる際に、プラントで製造したスラリーを地盤に混合させるとともに、前記回転ロッドの貫入時に貫入補助水を地盤に向けて吐出することによって改良する排土式深層混合処理工法であって、
施工計画時に得られる計画スラリー水セメント比、計画スラリー量、計画貫入補助水量、計画貫入速度、及び計画配合水と計画貫入補助水とを合わせた計画修正水セメント比を求める工程と、
施工時において、実施工深度、実貫入速度、及び実貫入補助水量を測定する工程と、
予め測定された前記実施工深度、前記実貫入速度、及び前記実貫入補助水量に基づいて実修正水セメント比を得る工程と、
前記計画修正水セメント比と前記実修正水セメント比とを比較して、前記回転ロッドの引抜き施工時における実スラリー量、及び引抜き速度を求める工程と、
を有していることを特徴とする排土式深層混合処理工法。
When the rotating rod provided in the earth-discharging type deep mixing treatment machine is penetrated into the improved ground, the slurry produced in the plant is mixed with the ground, and the penetration auxiliary water is discharged toward the ground when the rotating rod penetrates. A soil removal type deep mixing treatment method improved by
A step of obtaining a planned slurry water-cement ratio obtained at the time of construction planning, a planned slurry amount, a planned intrusion auxiliary water amount, a planned intrusion speed, and a planned modified water-cement ratio that is a combination of the planned mixed water and the planned intrusion auxiliary water;
At the time of construction, a step of measuring the actual depth of work, the actual penetration speed, and the actual penetration supplementary water volume;
a step of obtaining an actual modified water-cement ratio based on the previously measured working depth, the actual intrusion speed, and the actual intrusion auxiliary water amount;
a step of comparing the planned corrected water-cement ratio and the actual corrected water-cement ratio to determine the actual amount of slurry and the drawing speed during the drawing operation of the rotating rod;
A soil removal type deep layer mixing treatment method characterized by having
施工前に、排土式深層混合処理機によって施工される改良土の配合を試験する改良土配合試験が行われ、
改良土配合試験において、前記計画修正水セメント比が求められることを特徴とする請求項3に記載の排土式深層混合処理工法。
Before construction, an improved soil mix test was conducted to test the mixture of the improved soil to be applied by the soil removal type deep mixing treatment machine.
4. The soil removal type deep mixing treatment method according to claim 3, wherein the planned modified water-cement ratio is obtained in an improved soil mixing test.
JP2021147579A 2021-09-10 2021-09-10 Discharged slurry amount management system for penetration auxiliary water construction, and soil removal type deep layer mixing method Pending JP2023040533A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2021147579A JP2023040533A (en) 2021-09-10 2021-09-10 Discharged slurry amount management system for penetration auxiliary water construction, and soil removal type deep layer mixing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2021147579A JP2023040533A (en) 2021-09-10 2021-09-10 Discharged slurry amount management system for penetration auxiliary water construction, and soil removal type deep layer mixing method

Publications (1)

Publication Number Publication Date
JP2023040533A true JP2023040533A (en) 2023-03-23

Family

ID=85632291

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021147579A Pending JP2023040533A (en) 2021-09-10 2021-09-10 Discharged slurry amount management system for penetration auxiliary water construction, and soil removal type deep layer mixing method

Country Status (1)

Country Link
JP (1) JP2023040533A (en)

Similar Documents

Publication Publication Date Title
KR101765312B1 (en) Apparatus and method for soft soil improving ungi automated management system
JP6699135B2 (en) Electric resistivity detector and quality control method for soil cement body
JP2009275369A (en) Soil improving machine
JP2015212476A (en) Property measurement evaluation method of excavated soil in chamber for use in earth pressure shield tunneling, shield machine, and plastic fluidity test device of earth and sand
JP4885326B1 (en) Ground improvement method
CN109708987A (en) The test method of soil body abrasion property coefficient after a kind of sand-pebble layer sediment improvement
JP3437108B2 (en) Management method of ground improvement method and management device of ground improvement machine
JP4885325B1 (en) Construction management system for ground improvement method
JP2023040533A (en) Discharged slurry amount management system for penetration auxiliary water construction, and soil removal type deep layer mixing method
WO2012161282A1 (en) Ground improvement method, and system for managing construction in ground improvement method
JP3583307B2 (en) Construction management system in ground improvement method
JP7269137B2 (en) Quality prediction method of improved body
JP3432802B2 (en) Trencher type ground improvement machine, its construction management device and ground improvement method
JP2000160548A (en) Solidifying material injection control method in mechanically agitating deep layer mixing processing work
JP6640820B2 (en) Improved soil compounding test method for auxiliary water construction at the time of intrusion, and earth removal type deep mixing treatment method
JP2020183677A (en) Ground improvement method and ground improvement device using hydraulic measurement
JP2001317034A (en) Improved soil sampler and soil improvement stirring machine
CN112513376B (en) Method and apparatus for setting W/C in deep mixing processing method
JP2022096460A (en) Improved soil blending test method when working on high fluidity marginal viscosity soil, and soil discharging deep layer mixing method
JP7112820B2 (en) SOIL IMPROVEMENT SYSTEM AND QUALITY CONTROL METHOD
JP5139406B2 (en) Ground improvement machine
JP3325989B2 (en) Method of forming solidified soil
CN107064183A (en) A kind of method based on the CT graphical analysis concrete cracking origin causes of formation
JP7470030B2 (en) Test method for improved soil mix for extrusion during penetration and extraction, and soil discharge deep mixing treatment method
JP2021161720A (en) Quality prediction method and quality control method of improvement body