JP3339616B2 - Piping connection unit, jig for assembling piping connection unit, and piping connection device - Google Patents

Piping connection unit, jig for assembling piping connection unit, and piping connection device

Info

Publication number
JP3339616B2
JP3339616B2 JP21484696A JP21484696A JP3339616B2 JP 3339616 B2 JP3339616 B2 JP 3339616B2 JP 21484696 A JP21484696 A JP 21484696A JP 21484696 A JP21484696 A JP 21484696A JP 3339616 B2 JP3339616 B2 JP 3339616B2
Authority
JP
Japan
Prior art keywords
pipe
connection unit
pipe connection
frame
roller
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP21484696A
Other languages
Japanese (ja)
Other versions
JPH09163537A (en
Inventor
孝雄 岸
輝雄 山下
敏緒 渡辺
修 大野
忠昭 津野
義昭 村上
宏 植野
敬信 花岡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kurimoto Ltd
Kansai Electric Power Co Inc
Original Assignee
Kurimoto Ltd
Kansai Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kurimoto Ltd, Kansai Electric Power Co Inc filed Critical Kurimoto Ltd
Priority to JP21484696A priority Critical patent/JP3339616B2/en
Publication of JPH09163537A publication Critical patent/JPH09163537A/en
Application granted granted Critical
Publication of JP3339616B2 publication Critical patent/JP3339616B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Electric Cable Installation (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、電力ケーブル保護
管その他の配管を掘削溝内で相互に接続するための装
置、およびその方法に関するものである。本発明は、特
に湧水地域での配管埋設作業に適するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an apparatus and a method for interconnecting power cable protection pipes and other pipes in a trench. The present invention is particularly suitable for a pipe burial operation in a spring area.

【0002】[0002]

【従来の技術】送電線や通信線は、地下に埋設した管の
中に挿通されることが多い。そしてこの種の埋設管で
は、一般に一つの掘削溝内に多数の管が埋設される。従
来技術の管の埋設方法は、次の通りである。すなわち地
面に鋼矢板を対向して打ち、溝を掘削する。そして掘削
溝内に管を下ろす。管は掘削溝内で例えば平行に三列に
並べられ、さらに数本がある程度の長さに接続される。
次に管の上に管枕と称されるスペーサを置き、当該管枕
の上に、別の三列の管を積み上げて二段目の配管を敷設
し、最初の段と同様に管同士をある程度の長さに接続す
る。後は順次管枕を介して管を所定の段数に積み上げつ
つ、接続していく。そして所定の区画に管を敷設し終わ
ると、掘削溝を埋め戻す。
2. Description of the Related Art Transmission lines and communication lines are often inserted into pipes buried underground. In this type of buried pipe, a large number of pipes are generally buried in one excavation trench. The prior art method of burying a pipe is as follows. That is, a steel sheet pile is struck against the ground and a trench is excavated. Then lower the pipe into the trench. The pipes are arranged in, for example, three rows in parallel in the trench, and several are connected to a certain length.
Next, a spacer called a pipe pillow is placed on the pipe, another three rows of pipes are stacked on the pipe pillow, the second pipe is laid, and the pipes are connected to each other as in the first row. Connect to a certain length. Thereafter, the pipes are sequentially connected via a pipe pillow while being stacked in a predetermined number of stages. When the pipe is laid in the predetermined section, the excavation trench is filled back.

【0003】[0003]

【発明が解決しようとする課題】従来技術の管の埋設方
法は、単純かつ確実な方法であり、普遍的に実施されて
いる。しかしながら、従来技術の管の埋設方法は、作業
者が掘削溝内に入って作業することが必須であるため、
湧水地域での作業が困難であると言う欠点がある。
The prior art method of burying pipes is a simple and reliable method and is universally practiced. However, the prior art method of burying pipes requires an operator to work inside the digging trench,
There is a drawback that it is difficult to work in spring areas.

【0004】すなわち管を埋設する場所によっては、地
下水位が高い所があり、溝を掘った際、溝内に水が溜ま
り、作業者が掘削溝内に下りることが困難となる。この
様な場合の対策としては、掘削溝の底、すなわち鋼矢板
の間にグラウトを充填し、底からの湧水を止めると共
に、ポンプで掘削溝内を排水する方法がとられる。
[0004] That is, depending on the place where the pipe is buried, there are places where the groundwater level is high, and when the trench is dug, water accumulates in the trench, making it difficult for the operator to descend into the trench. As a countermeasure in such a case, a method of filling grout at the bottom of the excavation groove, that is, between the steel sheet piles, stopping spring water from the bottom, and draining the inside of the excavation groove with a pump is used.

【0005】しかしながら、これらの方法によるとグラ
ウトの充填に多大な費用がかかるばかりでなく、工期が
長くなってしまう問題がある。またグラウトを利用する
工法は、移動水が有る場合に、止水の信頼性が低下する
と言う問題があり、完全に止水を行うには多量のグラウ
トを要する問題がある。さらに鋼矢板を深く打ち込む工
法や、鋼矢板で囲まれた中にグラウトを充填する方法で
は、鋼矢板の撤去後に空隙充填グラウトが必要であると
言う問題がある。
[0005] However, according to these methods, there is a problem that not only a large cost is required for filling the grout, but also the construction period becomes long. Further, the construction method using grout has a problem that the reliability of water stoppage decreases when there is moving water, and there is a problem that a large amount of grout is required to completely stop water stoppage. Further, in the method of driving a steel sheet pile deeply or the method of filling grout in the area surrounded by the steel sheet pile, there is a problem that a void filling grout is required after removing the steel sheet pile.

【0006】そこで本発明は、従来技術の上記した問題
点に注目し、グラウト等を使用しなくても湧水地域で配
管埋設作業を行うことができ、工期が短い配管接続ユニ
ットおよび配管接続装置を提供することを目的とするも
のである。また併せて本発明は、湧水地域においても、
掘削溝内の配管の接続が可能な配管接続方法を提供する
ことを目的とするものである。
Therefore, the present invention pays attention to the above-mentioned problems of the prior art, and can perform a pipe burying operation in a spring water area without using grout or the like, and has a short connection period and a pipe connection unit and a pipe connection device. The purpose is to provide. In addition, the present invention also in the spring area,
It is an object of the present invention to provide a pipe connection method capable of connecting pipes in an excavation trench.

【0007】[0007]

【課題を解決するための手段】上記した目的を達成する
ための請求項1に記載の発明は、形成された掘削溝内に
吊り降ろされる配管接続ユニットであって、掘削溝と平
行して二本の軌道が地上に設けられ、配管接続ユニット
は、複数の管が所定の間隔に結束された配管結束部と、
移動台車部を有し、前記配管結束部は内面にスライド部
を有する枠体と、切り欠きを有する複数の管枕と、複数
の管より成り、管枕は前記スライド部と嵌合しつつ前記
枠体に積み重ね状に嵌め込まれ、管は管枕の間に挟ま
れ、切り欠きによって保持され、移動台車部は、前記地
上に設けられた二本の軌道と係合す る下向きに取り付け
られたローラを有し、配管結束部と、移動台車部は、配
管結束部が移動台車部から垂下状態に連結手段を介して
結合されていることを特徴とする配管接続ユニットであ
る。
According to claim 1 for achieving the above object, there is provided a means for solving] invention, in the formed excavated groove
A pipe connection unit to be suspended,
Two tracks are set up on the ground, and the piping connection unit
A pipe bundling part in which a plurality of pipes are bound at predetermined intervals,
It has a moving bogie part, the pipe binding part is composed of a frame having a slide part on the inner surface, a plurality of pipe pillows having notches, and a plurality of pipes, and the pipe pillow is fitted with the slide part while fitted to form stacked frame, the tube is sandwiched between the tubes pillow is held by the notch, the cart unit, the ground
Attached to two of the trajectory and engaging a downward that match that provided in the upper
, The pipe binding part and the moving carriage part are arranged
The tube bundling part is suspended from the moving bogie part via the connecting means.
It is a piping connection unit characterized by being connected.

【0008】同様の課題を解決するための発明は、軌道
を持たない掘削溝に吊り降ろされ、ローラに代わって地
上に設けられたキャスターを有し、当該キャスターは、
任意に方向を変えることができるものであることを特徴
とする請求項1に記載の配管接続ユニットである。また
上記した配管接続ユニットを組み立てる治具の発明は、
台座と垂直部材を有し、台座には前記枠体を所定の間隔
で仮止めする仮止め部材が設けられていることを特徴と
する。
[0008] The invention for solving the same problem is based on an orbit.
Suspended in an excavation trench without
Having a caster provided above, the caster comprising:
The feature is that the direction can be changed arbitrarily
The pipe connection unit according to claim 1 . Also, the invention of a jig for assembling the above-mentioned piping connection unit,
It has a pedestal and a vertical member, and the pedestal is provided with a temporary fixing member for temporarily fixing the frame at predetermined intervals.

【0009】また上記した発明に改良を加えた態様とし
、前記連結手段、取り付け位置が変更可能であって
もよい。
[0009] Further, according to an aspect of the present invention, an improvement is added.
Te, the connection means, the attachment position is a modifiable
Is also good.

【0010】また配管接続装置の発明は、請求項1に記
載の配管接続ユニットを、掘削溝内で移動させて配管を
接続する配管接続装置において、フレームと、当接部材
と、押圧装置より成り、フレームは地上に敷設された軌
道と係合する移動用ローラと、掘削溝内に垂下される支
持部と、補助軌道を有し、当接部材は、配管接続ユニッ
トの各配管端面に当接可能な押さえ面と、補助ローラを
備え、当接部材は補助ローラが補助軌道と係合した状態
でフレームから掘削溝内に垂下され、押圧装置は前記支
持部と押さえ面の間に配されて当接部材を移動可能であ
ることを特徴とする配管接続装置である。
The invention of the pipe connection device is described in claim 1.
Move the piping connection unit on the
In a pipe connection device to be connected, a frame and a contact member
The frame consists of a rail laid on the ground.
A transfer roller for engaging the road and a support suspended in the digging trench;
Holding part and an auxiliary track, and the contact member is a piping connection unit.
The holding surface, which can abut each pipe end face,
With the auxiliary roller engaged with the auxiliary track
The frame is suspended from the frame into the excavation groove, and the pressing device is
The contact member is movable between the holding part and the holding surface.
A pipe connection device characterized in that:

【0011】さらにもう一つの配管接続装置の発明は、
複数の配管が所定の間隔に結束された配管接続ユニット
を、掘削溝内で移動させて配管を接続する配管接続装置
において、フレームと、当接部材と、押圧装置より成
り、フレームは地上に敷設された軌道と係合する移動用
ローラと、掘削溝内に垂下される支持部と、補助軌道を
有し、当接部材は、配管接続ユニットの各配管端面に当
接可能な押さえ面と、補助ローラを備え、当接部材は補
助ローラが補助軌道と係合した状態でフレームから掘削
溝内に垂下され、押圧装置は前記支持部と押さえ面の間
に配されて当接部材を移動可能であることを特徴とする
ものである。
[0011] Still another invention of a pipe connection device is as follows.
In a pipe connection device that connects a pipe by moving a pipe connection unit in which a plurality of pipes are bound at predetermined intervals in a digging groove, the frame includes a frame, a contact member, and a pressing device, and the frame is laid on the ground. A roller for movement to be engaged with the set track, a support portion suspended in the excavation groove, and an auxiliary track, the contact member has a pressing surface capable of contacting each pipe end surface of the pipe connection unit, An auxiliary roller is provided, the contact member is suspended from the frame into the excavation groove in a state where the auxiliary roller is engaged with the auxiliary track, and a pressing device is disposed between the support portion and the pressing surface to move the contact member. It is characterized by being.

【0012】さらに実施形態の一例として、地上には掘
削溝と平行に二本の軌道を敷設し、複数の配管が所定の
間隔に結束されていると共に二本の軌道と係合する係合
部を備えた配管接続ユニットを前記掘削溝内に吊り降ろ
し、係合部を二本の軌道と係合し、配管接続ユニットを
掘削溝内で前進させて各配管の先端を既設配管の後端に
接続することができる。ここで係合部とは、例えばロー
ラを含む概念である。
Further, as an example of the embodiment , two tracks are laid on the ground in parallel with the excavation groove, a plurality of pipes are bound at a predetermined interval, and an engaging portion is engaged with the two tracks. Hanging the pipe connection unit provided with the inside of the excavation groove, engaging the engaging portion with the two tracks, advance the pipe connection unit in the excavation groove, the tip of each pipe to the rear end of the existing pipe Can be connected. Here, the engaging portion is a concept including, for example, a roller.

【0013】上記した配管接続ユニットは、掘削溝内に
降ろし、ローラ又はキャスターによって配管接続ユニッ
トを支承し、該配管接続ユニットを掘削溝内で前進させ
て各配管の先端を既設配管の後端に接続することによっ
て工事を行うことができる。
[0013] The above-mentioned pipe connection unit is lowered into an excavation groove, and supported by a roller or a caster, and the pipe connection unit is advanced in the excavation groove so that the tip of each pipe is attached to the rear end of the existing pipe. By connecting
Work can be done.

【0014】また上記した発明に改良を加えた実施態様
は、管の開放側端部に、配管接続ユニットの各管の開口
を覆うキャップが装着されることを特徴とする。
Further embodiments <br/> obtained by improving the invention described above, the open end of the tube, a cap covering the opening of each tube of the piping connection unit, characterized in that it is fitted.

【0015】請求項1,2記載の発明は、多数の配管を
所定の間隔に結束したもので、掘削溝内での配管の移動
を容易にする。すなわち請求項1,2記載の配管接続ユ
ニットでは、管枕はスライド部と嵌合しつつ枠体に積み
重ね状に嵌め込まれている。従って管枕は、互いにずれ
ることなく所定の位置にある。また管は管枕の間に挟ま
れ、切り欠きによって保持されているので、管がずれる
ことはない。本発明の配管接続ユニットの組み立ては、
枠体のスライド部に管枕の一部を嵌合しつつ、管枕を枠
体に挿入し、続いて管を管枕の上に置き、さらにつづい
て他の管枕を枠体に挿入する。
According to the first and second aspects of the present invention, a large number of pipes are bound at a predetermined interval, thereby facilitating the movement of the pipes in the excavation trench. That is, in the pipe connection unit according to the first and second aspects, the pipe pillow is fitted in the frame in a stacked manner while being fitted to the slide portion. Thus, the tube pillows are in place without displacement. Also, since the tube is sandwiched between the tube pillows and held by the notches, the tube does not shift. Assembly of the pipe connection unit of the present invention,
While fitting a part of the pipe pillow to the sliding portion of the frame, insert the pipe pillow into the frame, then place the pipe on the pipe pillow, and then insert another pipe pillow into the frame. .

【0016】請求項記載の発明は、このように管と管
枕を互い違いに積み重ねる際に使用されるものである。
代表的な手順は、次の通りである。すなわち台座に所定
の間隔を置いて仮止め部材により枠体を仮固定する。次
に管枕を枠体に挿入する。さらに続いて管枕の上に管を
載置するが、このとき管の先端を垂直部材に当接させ
る。後は順次管枕を挿入すると共に管を垂直部材に当接
しつつ管枕上に載置していく。こうして組み立てられた
配管接続ユニットは、管の端面が同一面内に揃ってい
る。
The invention according to claim 3 is used when the pipes and the pipe pillows are alternately stacked.
A typical procedure is as follows. That is, the frame is temporarily fixed by the temporary fixing member at predetermined intervals on the pedestal. Next, the tube pillow is inserted into the frame. Subsequently, the tube is placed on the tube pillow, with the tip of the tube abutting on the vertical member. Thereafter, the pipe pillows are sequentially inserted, and the pipes are placed on the pipe pillow while abutting on the vertical members. In the pipe connection unit thus assembled, the pipe end faces are aligned in the same plane.

【0017】また、地上を走行するキャスター又は地上
の軌道と係合するローラを備えた移動台車部を持ち、
移動台車部を動かすことによって、掘削溝内の配管接続
ユニットを容易に移動させることができる。本発明で
は、配管を結合し、配管が落下しない程度に埋め戻され
た後は、連結手段を切り離す。
[0017] Chi lifting the movable carrier portion with a caster or ground track engaging rollers running on the ground, by moving the movable carriage portion, to easily move the pipe connection unit of the excavation groove be able to. In the present invention, after the pipes are joined and the pipes are backfilled to the extent that they do not drop, the connecting means is disconnected.

【0018】また連結部材によって移動台車部と配管結
束部が連結され、さらにこの連結部材、取り付け位置
が変更可能である場合は、既設配管の埋設深さに合わせ
て配管結束部の垂下位置を任意に変更することができ
る。
[0018] Further, when the movable bogie section and the pipe binding section are connected by a connecting member, and when the mounting position of this connecting member can be changed, the hanging position of the pipe binding section is adjusted in accordance with the burial depth of the existing pipe. It can be changed arbitrarily.

【0019】請求項4,5記載の発明は、複数の配管が
所定の間隔に結束された配管接続ユニットを、掘削溝内
で移動させるもので、まず、フレームを地上に設けられ
た軌道上に乗せる。この時、フレームの支持部や、当接
部材は、掘削溝の中に垂下された状態となる。そして移
動用ローラを介して装置全体を走行させ、当接部材を掘
削溝内の所定の位置まで移動させる。次に移動用ローラ
をロックする等の方策により、フレームを固定する。続
いて押圧装置を作動させて当接部材を押圧する。本発明
では、当接部材は補助軌道の上にあり、且つ押圧用ロー
ラによって補助軌道の上を移動可能であるため、押圧装
置の作動によって当接部材は補助軌道に沿って前方に移
動する。そして押さえ面を配管接続ユニットの端面に当
接して配管接続ユニットを移動させることができる。
According to the fourth and fifth aspects of the present invention, a pipe connection unit in which a plurality of pipes are bound at a predetermined interval is moved in an excavation trench. First, a frame is placed on a track provided on the ground. Put on. At this time, the support portion of the frame and the contact member are in a state of being suspended in the excavation groove. Then, the entire apparatus is run via the moving roller, and the contact member is moved to a predetermined position in the excavation groove. Next, the frame is fixed by measures such as locking the moving roller. Subsequently, the pressing device is operated to press the contact member. In the present invention, since the contact member is on the auxiliary track and can be moved on the auxiliary track by the pressing roller, the operation of the pressing device causes the contact member to move forward along the auxiliary track. Then, the holding surface can be brought into contact with the end face of the pipe connection unit to move the pipe connection unit.

【0020】さらに地上に掘削溝と平行に軌道を敷設す
る方法では、この軌道を利用して、配管接続ユニットを
移動させる。そして配管接続ユニットの各配管の先端を
既設配管の後端に接続する。
Further, in the method of laying a track parallel to the excavation trench on the ground, the pipe connection unit is moved using this track. Then, the tip of each pipe of the pipe connection unit is connected to the rear end of the existing pipe.

【0021】また、複数の配管が所定の間隔に結束され
ている配管接続ユニットを掘削溝内に降ろし、地面上を
移動するキャスターによって配管接続ユニットを支承
し、該配管接続ユニットを掘削溝内で前進させて各配管
の先端を既設配管の後端に接続することもできる
Further, down the pipe connection unit in which a plurality of pipes are bundled in a predetermined interval in the excavation groove, bearing a pipe connection unit by casters for moving on the ground, the piping connection unit Drilling groove By moving the pipe forward, the tip of each pipe can be connected to the rear end of the existing pipe.

【0022】また管の開放側端部に、配管接続ユニット
の各管の開口を覆うキャップ装着すると、管内に埃や
砂が入ることが防止される。
Further to the open end of the tube, mounting the cap covering the opening of each tube of the piping connection unit result, it is possible to prevent the dust and sand from entering the tube.

【0023】[0023]

【発明の実施の形態】以下に本発明の具体的実施形態を
管の埋設を例に説明する。図1は、本発明の具体的実施
形態の配管接続ユニットを掘削溝に吊り下ろす際の斜視
図である。図2は、図1の配管接続ユニットの上部の斜
視図である。図3は、本発明の具体的実施形態の配管接
続ユニット組み立て治具の斜視図である。図4は、図3
の配管接続ユニット組み立て治具を使用した配管接続ユ
ニットの組み立て手順を示す斜視図である。図5は、図
1の配管接続ユニットを掘削溝に配置した際の斜視図で
ある。図6は、本発明の具体的実施形態の配管接続装置
の斜視図である。図7は、図6の円内の拡大図である。
図8は、本発明の具体的実施形態の配管接続方法の一工
程を示す掘削溝内の説明図である。図9は、本発明の配
管接続方法を応用した配管埋設工事の手順を示すフロー
チャート図である。図10は、図8の工程の後の工程を
示す掘削溝内の説明図である。図11は、本発明の具体
的実施形態の配管接続方法の一工程を示す配管接続ユニ
ットおよびキャップの斜視図である。図12は、本発明
の具体的実施形態の配管接続方法の一工程を示す配管接
続ユニットおよびキャップの要部の斜視図である。図1
3は、本発明の変形例を示す一部断面斜視図である。図
14は、本発明の変形例を示す掘削溝内の説明図であ
る。
BEST MODE FOR CARRYING OUT THE INVENTION Hereinafter, a specific embodiment of the present invention will be described with an example of burying a pipe. Drawing 1 is a perspective view at the time of hanging a piping connection unit of a concrete embodiment of the present invention in a digging trench. FIG. 2 is a perspective view of the upper part of the piping connection unit of FIG. FIG. 3 is a perspective view of a piping connection unit assembling jig according to a specific embodiment of the present invention. FIG. 4 shows FIG.
It is a perspective view which shows the assembly procedure of the piping connection unit using the piping connection unit assembly jig of this. FIG. 5 is a perspective view when the pipe connection unit of FIG. 1 is arranged in a digging trench. FIG. 6 is a perspective view of a pipe connection device according to a specific embodiment of the present invention. FIG. 7 is an enlarged view of the inside of the circle in FIG.
FIG. 8 is an explanatory diagram of the inside of the excavation trench showing one step of the pipe connection method according to the specific embodiment of the present invention. FIG. 9 is a flowchart showing a procedure of a pipe burying work to which the pipe connection method of the present invention is applied. FIG. 10 is an explanatory diagram of the inside of the excavation trench showing a step after the step of FIG. 8. FIG. 11 is a perspective view of a pipe connection unit and a cap showing one step of a pipe connection method according to a specific embodiment of the present invention. FIG. 12 is a perspective view of a main part of a pipe connection unit and a cap showing one step of a pipe connection method according to a specific embodiment of the present invention. FIG.
FIG. 3 is a partially sectional perspective view showing a modification of the present invention. FIG. 14 is an explanatory diagram showing the inside of a digging trench showing a modification of the present invention.

【0024】本実施形態の配管接続方法を説明するに当
たり、まず本方法に使用する配管接続ユニットと、配管
接続装置について説明する。本実施形態で使用する配管
接続ユニット1は、図1の通りであり、大きく分けて配
管結束部2と移動台車部3から構成され、両者が連結手
段、例えば連結部材5を介して結合されたものである。
順次説明すると、配管結束部2は、管6が3列8段(2
4本)にわたって結束されたものであり、各管6は平行
かつ両端を揃えて配置されている。管6は、例えば電力
ケーブル保護管で、その材質は例えばFRP(繊維強化
プラスチック)である。管6の一方の端部には、他の管
との連結用の管継手8が予め取り付けられている。
In describing the pipe connection method of the present embodiment, first, a pipe connection unit and a pipe connection device used in the method will be described. The pipe connection unit 1 used in the present embodiment is as shown in FIG. 1 and is roughly divided into a pipe binding section 2 and a moving carriage section 3, both of which are connected via a connecting means, for example, a connecting member 5. Things.
Explaining one by one, the pipe bundling part 2 is composed of three rows and eight stages (2 rows).
Four tubes), and each tube 6 is arranged in parallel and with both ends aligned. The tube 6 is, for example, a power cable protection tube, and its material is, for example, FRP (fiber reinforced plastic). At one end of the pipe 6, a pipe joint 8 for connection to another pipe is attached in advance.

【0025】配管結束部2は、本実施形態では管6の
他、枠体10と管枕11、12とからなる。すなわち枠
体10は、図2,図4の様に溝形鋼を素材として上方が
開口された全体形状が「コ」の字型に形成されたもので
ある。そして上記した溝形鋼は、スライド部すなわち凹
溝13をいずれも内側に対向させて溶接されており、枠
体10を間隔をあけて2個使用する。また枠体10の上
端部には、それぞれ2個の孔14が設けられている(図
2参照)。
In the present embodiment, the pipe binding section 2 comprises a frame 10 and pipe pillows 11, 12 in addition to the pipe 6. That is, as shown in FIGS. 2 and 4, the frame 10 is formed of a channel steel as a raw material, and the entire shape of the frame 10 whose upper side is opened is formed in a U-shape. The above-mentioned channel steels are welded so that all of the sliding portions, that is, the concave grooves 13 face the inside, and two frame bodies 10 are used at intervals. Further, two holes 14 are provided at the upper end of the frame body 10 (see FIG. 2).

【0026】一方、管枕11,12は、いずれも合成樹
脂の射出成形によって成形された薄いブロック状の部材
である。配管結束部2を構成する管枕11,12の内、
上下端の管枕11は図4に示す様に、一方の面に円弧状
の切り欠き15が等間隔に3個設けられ、また中間部に
配されている管枕12にも、上下の面に同様の切り欠き
15が3個づつ設けられている。これらの切り欠き15
の半径は、上記した管6の外周円のそれとほぼ等しい。
管枕11の幅は、枠体10の向かい合う凹溝13間の長
さにほぼ等しい。さらに管枕11の厚さは、凹溝13の
幅、すなわち溝形鋼の溝幅にほぼ等しい。
On the other hand, each of the tube pillows 11 and 12 is a thin block-shaped member formed by injection molding of a synthetic resin. Of the pipe pillows 11 and 12 constituting the pipe binding unit 2,
As shown in FIG. 4, the upper and lower tube pillows 11 are each provided with three arc-shaped notches 15 on one surface at equal intervals, and the tube pillows 12 disposed in the middle portion are also provided with upper and lower surfaces. Are provided with three notches 15 each. These notches 15
Is substantially equal to that of the outer circumference of the tube 6 described above.
The width of the tube pillow 11 is substantially equal to the length between the opposed concave grooves 13 of the frame 10. Furthermore, the thickness of the tube pillow 11 is substantially equal to the width of the concave groove 13, that is, the groove width of the channel steel.

【0027】配管結束部2は、枠体10に管枕11,1
2と、例えば3列の管6が互い違いに積み重ねられて配
置されたものであり、各管6は、管枕11,12の切り
欠き部15に挟まれていて、横方向の動きが規制されて
いる。さらに枠体10等による管6の結束は、管6の2
か所で行われているので、各管6は、平行に配置されて
いる。管枕11,12の側部は、いずれも枠体10の凹
溝13と嵌合した状態で積み重ねられており、管枕1
1、12が相対的に移動することはない。
The pipe binding portion 2 is provided on the frame 10 with pipe pillows 11 and 1.
2 and, for example, three rows of tubes 6 are alternately stacked and arranged. Each tube 6 is sandwiched between cutout portions 15 of the tube pillows 11 and 12, and the movement in the lateral direction is restricted. ing. Further, the binding of the tube 6 by the frame 10 and the like
Since it is performed in several places, each tube 6 is arranged in parallel. Both side portions of the tube pillows 11 and 12 are stacked in a state where they are fitted into the concave grooves 13 of the frame body 10.
1 and 12 do not move relatively.

【0028】移動台車部3は、図1および図2の様に、
2本の梁材20と、2本の桟材21が梯子状に組み立て
られ、さらに両者の結合部位の近くから、下側に4本の
垂直材22が溶接されたものである。また梁材20のそ
れぞれの端部近くには、走行ローラ23が取り付けられ
ている。走行ローラ23の梁材20の長手方向における
取り付け間隔は、後述する主軌道71の間隔に等しい。
また垂直材22の下端近くには、孔25がそれぞれ2個
づつ設けられている。
As shown in FIG. 1 and FIG.
Two beam members 20 and two bar members 21 are assembled in a ladder shape, and four vertical members 22 are welded to the lower side from near a joint portion between the two. A traveling roller 23 is attached near each end of the beam member 20. The mounting interval of the running roller 23 in the longitudinal direction of the beam 20 is equal to the interval of a main track 71 described later.
Near the lower end of the vertical member 22, two holes 25 are provided.

【0029】本実施形態の配管接続ユニット1は、配管
結束部2の上端部が移動台車部3の垂直材22に結合さ
れ、配管結束部2が移動台車部3から垂下されたもので
あり、両者の結合は、連結部材5を介して行われてい
る。連結部材5は、4つの孔27が設けられた帯状の鋼
板である。
In the pipe connection unit 1 of the present embodiment, the upper end of the pipe binding section 2 is connected to the vertical member 22 of the movable trolley section 3, and the pipe binding section 2 is suspended from the movable trolley section 3. The connection between the two is performed via a connecting member 5. The connecting member 5 is a strip-shaped steel plate provided with four holes 27.

【0030】連結部材5の取り付けは、それぞれ2本を
一組としたボルト等の一時締結要素28によって行われ
ている。すなわちボルト28は、移動台車部3の垂直材
22と連結部材5の間で1本締結され、さらに連結部材
5と配管結束部2の上端との間で1本のボルト28が締
結される。従って配管結束部2と移動台車部3との取り
付けおよび取り外しは単に数本のボルト28の付け外し
で足り、極めて容易である。さらに連結部材5には4個
の孔27が設けられ、一方枠体10と垂直材22にも2
個づつの孔14,25が設けられているのに対して、上
記した通り2本のボルト28によって連結部材5の結合
が行われるので、孔14,25へのボルトの挿入位置を
選択することにより、連結部材5の取り付け位置を変更
することができる。その結果、配管結束部2の吊り下げ
深さを変更することができる。
The attachment of the connecting member 5 is performed by a temporary fastening element 28 such as a set of two bolts. That is, one bolt 28 is fastened between the vertical member 22 of the movable carriage 3 and the connecting member 5, and one bolt 28 is fastened between the connecting member 5 and the upper end of the pipe binding portion 2. Therefore, the attachment and detachment of the pipe binding unit 2 and the movable carriage unit 3 is only very simple by attaching and detaching several bolts 28, which is extremely easy. Further, the connecting member 5 is provided with four holes 27, while the frame 10 and the vertical member 22 are also provided with two holes.
While the individual holes 14 and 25 are provided, the connecting member 5 is connected by the two bolts 28 as described above, so that the position for inserting the bolts into the holes 14 and 25 can be selected. Thereby, the attachment position of the connecting member 5 can be changed. As a result, the hanging depth of the pipe binding portion 2 can be changed.

【0031】配管接続ユニット1の組み立て方法は任意
であるが、図3に示すような配管接続ユニット組み立て
治具30を利用することが便利である。配管接続ユニッ
ト組み立て治具30は、台座31に垂直部材32が設け
られたものである。台座31は、鋼材によって枠状に溶
接されたものであり、幅方向の長さは、前述の枠体10
のそれに等しい。また台座31の側面に二つを一組とす
る孔35が多数設けられている。そして孔35は、所定
の二組が選択され、2つ(両側面を合計すると4つ)の
仮止め部材すなわち、位置決め部材34がボルト48で
取り付けられている。位置決め部材34は、長方形をし
た板状の部材であり、一方の側面から、当該側面の約3
分の1の長さの位置決め片39が垂直方向に形成されて
いる。位置決め部材34は、位置決め片39同士の間隔
が枠体10同士の間隔、言い換えると移動台車部3の垂
直材22の間隔に等しい位置に取り付けられる。
Although the method of assembling the pipe connection unit 1 is optional, it is convenient to use a pipe connection unit assembly jig 30 as shown in FIG. The piping connection unit assembling jig 30 has a pedestal 31 provided with a vertical member 32. The pedestal 31 is welded in a frame shape by a steel material.
Equal to that of A large number of holes 35 are provided on the side surface of the pedestal 31. Two predetermined pairs of holes 35 are selected, and two (four in total on both side surfaces) temporary fixing members, ie, positioning members 34 are attached with bolts 48. The positioning member 34 is a rectangular plate-like member.
A positioning piece 39 having a length of one-half is formed in the vertical direction. The positioning member 34 is attached at a position where the distance between the positioning pieces 39 is equal to the distance between the frame bodies 10, in other words, the distance between the vertical members 22 of the movable bogie unit 3.

【0032】垂直部材32は、同じく鋼材によって作ら
れたものであり、長方形の枠36の中に、3本の縦部材
33が平行に取り付けられて、壁状を形成している。ま
た垂直状態を維持するために、補助脚26が枠36に溶
接されている。配管接続ユニット組み立て治具30は、
垂直部材32と台座31がボルト38によって取り付け
られており、運搬時には両者は分離される。
The vertical member 32 is also made of steel, and has three rectangular members 33 mounted in parallel in a rectangular frame 36 to form a wall. The auxiliary leg 26 is welded to the frame 36 to maintain the vertical state. The piping connection unit assembling jig 30 includes:
The vertical member 32 and the pedestal 31 are attached by bolts 38, and they are separated during transportation.

【0033】配管接続ユニット1の上記配管接続ユニッ
ト組み立て治具30を利用した組み立て方法を説明する
と、次の通りである。すなわち配管接続ユニット1の枠
体10を予め制作しておいて、枠体10を位置決め部材
34に当接させ、枠体10を仮固定する。仮固定は、枠
体10を台座31あるいは位置決め部材34にボルト止
めして行うことが望ましい。前述の様に、位置決め部材
34は、移動台車部3の垂直材22の間隔に等しい位置
に取り付けられているので、枠体10を仮固定すること
により、枠体10は所定の間隔に配置される事となる。
そして枠体10の上端の開口から、最下端の管枕11、
すなわち片面のみに切り欠き15が設けられた管枕11
を挿入する。管枕11の挿入は、管枕11の側部を枠体
10の凹溝13と係合させ、凹溝13を滑らせて下方向
に落込むことにより行う。
The method of assembling the pipe connection unit 1 using the pipe connection unit assembling jig 30 will be described below. That is, the frame 10 of the pipe connection unit 1 is produced in advance, and the frame 10 is brought into contact with the positioning member 34 to temporarily fix the frame 10. It is preferable that the temporary fixing is performed by bolting the frame 10 to the pedestal 31 or the positioning member 34. As described above, since the positioning member 34 is attached at a position equal to the interval between the vertical members 22 of the movable bogie unit 3, the frame 10 is temporarily fixed, so that the frame 10 is arranged at a predetermined interval. It will be.
Then, from the opening at the upper end of the frame body 10, the lowermost tube pillow 11,
That is, the tube pillow 11 provided with the notch 15 on only one side
Insert The insertion of the tube pillow 11 is performed by engaging a side portion of the tube pillow 11 with the concave groove 13 of the frame body 10 and sliding the concave groove 13 downward.

【0034】次いで管6を管枕11の切り欠き15に配
置する。この時、管6の各端部は、垂直部材32のいず
れかの部位と当接させておく。本実施形態においては、
縦部材33(溝形鋼)の背中面と当接している。そして
次に、中間の管枕12を先の管枕11と同様に枠体10
に挿入し、当該管枕12を先の管枕11および管6に積
み重ねる。さらに続いて2段目の管6を管枕12の上に
重ねる。この時も、先の場合と同様に、管6の各端部
は、垂直部材32のいずれかの部位と当接させる。以下
順次管枕12と管6を積み重ね、管6が例えば8段積み
重ねられたところで最後の管枕11を装着する。
Next, the pipe 6 is arranged in the notch 15 of the pipe pillow 11. At this time, each end of the tube 6 is kept in contact with any part of the vertical member 32. In the present embodiment,
It is in contact with the back surface of the vertical member 33 (channel steel). Then, the intermediate pipe pillow 12 is connected to the frame 10 in the same manner as the previous pipe pillow 11.
And the tube pillow 12 is stacked on the tube pillow 11 and the tube 6. Subsequently, the second-stage tube 6 is placed on the tube pillow 12. At this time, as in the above case, each end of the tube 6 is brought into contact with any part of the vertical member 32. Thereafter, the tube pillow 12 and the tube 6 are sequentially stacked, and the last tube pillow 11 is mounted when the tubes 6 are stacked, for example, in eight stages.

【0035】この時の管6の積み重ね状態は、いずれの
管6も、その端部が、垂直部材32に当接されているの
で、すべての管6の端部は揃った状態となっている。管
6および管枕11の装着を終えると、枠体10に連結部
材5を介して移動台車部3を結合する。そして枠体10
の仮固定を解除する。
At this time, the stacked state of the tubes 6 is such that the ends of all the tubes 6 are in contact with the vertical members 32, so that the ends of all the tubes 6 are aligned. . When the mounting of the pipe 6 and the pipe pillow 11 is completed, the movable bogie unit 3 is connected to the frame 10 via the connecting member 5. And the frame 10
Release the temporary fixation.

【0036】次に本実施形態の配管接続方法で利用する
装置の構造を図6ないし図8を参照しながら説明する。
本実施形態で利用する配管接続装置40は、フレーム4
1と、当接部材42と、4本の油圧シリンダー(押圧装
置)43より成る。フレーム41は、水平部49と支持
部44によって構成されている。水平部49の形状は、
一本の梁部材45と、2本の横梁部材46、及び2本の
補助梁37によって「C」形に組み合わされ、さらに補
助梁37と梁部材45の間には、補助軌道50が渡され
ている。水平部49の形状を上述の様に「C」形にし
て、一方に開口部を設けた理由は、後記するように、掘
削溝70内に配管接続ユニット1を吊り下ろす際、配管
接続ユニット1の管6の端部が当たらない様にするため
である。
Next, the structure of the apparatus used in the pipe connection method of the present embodiment will be described with reference to FIGS.
The pipe connection device 40 used in the present embodiment includes a frame 4
1, a contact member 42, and four hydraulic cylinders (pressing devices) 43. The frame 41 includes a horizontal portion 49 and a support portion 44. The shape of the horizontal part 49 is
One beam member 45, two horizontal beam members 46, and two auxiliary beams 37 are combined in a “C” shape, and an auxiliary track 50 is passed between the auxiliary beam 37 and the beam member 45. ing. The reason that the shape of the horizontal portion 49 is the “C” shape as described above and the opening is provided on one side is that the pipe connection unit 1 is suspended in the excavation groove 70 as described later. This is to prevent the end of the tube 6 from hitting.

【0037】水平部49の構成で特記するべきは、梁部
材45の両端と、2本の補助梁37の端部に、走行ロー
ラ53が設けられている点である。走行ローラ53の梁
部材45の長手方向における取り付け間隔は、後述する
主軌道71の間隔にほぼ等しい。また梁部材45および
補助梁37の端部には、枠状部材51が配置されてい
る。枠状部材51の中間部には、短いL形鋼52が溶接
され、さらに該L形鋼52には、前記枠状部材51から
少しの間を開けてもう一つのL形鋼58が溶接されてい
る。そして枠状部材51およびL形鋼52,58によっ
て主軌道71が抱かれた状態となっている。また枠状部
材51には、貫通孔が設けられて2個のナット54が溶
接され、さらにナット54にはボルト55が嵌合してい
る(図7参照)。そしてボルト55を締め込むことによ
り、ボルト55の先端が主軌道71の側面に押し当てら
れ、フレーム41の走行が阻止される。尚、梁部材45
と枠状部材51との関係は、梁部材45の上に、枠状部
材51の上部材59が載せられているに過ぎず、両者は
相互に固定されていない。
What should be particularly noted in the configuration of the horizontal portion 49 is that running rollers 53 are provided at both ends of the beam member 45 and at the ends of the two auxiliary beams 37. The mounting interval of the traveling roller 53 in the longitudinal direction of the beam member 45 is substantially equal to the interval of a main track 71 described later. At the ends of the beam member 45 and the auxiliary beam 37, a frame-shaped member 51 is disposed. A short L-shaped steel 52 is welded to an intermediate portion of the frame-shaped member 51, and another L-shaped steel 58 is welded to the L-shaped steel 52 at a short distance from the frame-shaped member 51. ing. The main track 71 is held by the frame member 51 and the L-shaped steels 52 and 58. Further, a through hole is provided in the frame member 51, and two nuts 54 are welded, and a bolt 55 is fitted to the nut 54 (see FIG. 7). Then, by tightening the bolt 55, the tip of the bolt 55 is pressed against the side surface of the main track 71, and the running of the frame 41 is prevented. The beam member 45
The only relationship between the frame member 51 and the upper member 59 is that the upper member 59 of the frame member 51 is placed on the beam member 45, and they are not fixed to each other.

【0038】支持部44は、水平部49の梁部材45の
中間部から垂下アーム56によって垂下され、下部に鋼
材で格子状部57が構成されたものである。支持部44
と水平部49の間は、上述の連結部材5と同様の連結部
材60(図8に図示)によって連結されており、連結部
材60の取り付け孔を変更することにより、支持部44
の垂下深さを変更することができる。
The support portion 44 is suspended from a middle portion of the beam member 45 of the horizontal portion 49 by a suspending arm 56, and has a lattice portion 57 made of steel at the lower portion. Support 44
The connecting portion 60 and the horizontal portion 49 are connected by a connecting member 60 (shown in FIG. 8) similar to the connecting member 5 described above.
The droop depth can be changed.

【0039】当接部材42の形状は、前記した支持部4
4に類似するものであり、垂下アーム61と格子状部6
2を有する。また両者の間は連結部材64(図8に図
示)によって結合されている。当接部材42が支持部4
4と相違する点は、当接部材42の上部には、補助ロー
ラ63が設けられ、該補助ローラ63によって補助軌道
50からつり下げられている点である。従って当接部材
42は、支持部44に対して近接および離反が可能であ
る。またもう一つの相違点は、格子状部62の前面に板
66が張られて押さえ面65が形成されている点であ
る。4本の油圧シリンダー43は、いずれもフレーム4
1の支持部44と当接部材42の間にバランス良く配さ
れている。従って油圧シリンダー43を駆動することに
より、当接部材42は平行移動する。
The shape of the contact member 42 is the same as that of the support portion 4 described above.
4 and the hanging arm 61 and the grid-like portion 6
2 The two are connected by a connecting member 64 (shown in FIG. 8). When the contact member 42 is the support portion 4
4 in that an auxiliary roller 63 is provided above the contact member 42 and is suspended from the auxiliary track 50 by the auxiliary roller 63. Therefore, the contact member 42 can approach and separate from the support portion 44. Another difference is that a plate 66 is stretched on the front surface of the lattice portion 62 to form a holding surface 65. Each of the four hydraulic cylinders 43 is a frame 4
The first support portion 44 and the contact member 42 are arranged in a well-balanced manner. Therefore, by driving the hydraulic cylinder 43, the contact member 42 moves in parallel.

【0040】次に本発明の実施形態の配管接続方法につ
いて、一般的な配管埋設工事の手順を追って説明する。
本実施形態で説明する配管埋設工事の工程は、図9のフ
ローチャート図の通りである。すなわち最初に公知の手
段によって、図1,図5の様に鋼矢板69を打ち込むと
共に溝を掘削する(工程1)。尚この時、地下水位の高
い地域であれは、掘削溝70内に湧水する事となる。続
いて図5の様に、掘削溝70と平行して、地上に2本の
主軌道71を敷設する(工程2)。
Next, the pipe connection method according to the embodiment of the present invention will be described in the order of general pipe burial work.
The steps of the pipe burying work described in the present embodiment are as shown in the flowchart of FIG. That is, first, a steel sheet pile 69 is driven and a groove is excavated as shown in FIGS. 1 and 5 by a known means (step 1). At this time, even in an area where the groundwater level is high, water will spring in the excavation trench 70. Subsequently, as shown in FIG. 5, two main tracks 71 are laid on the ground in parallel with the excavation trench 70 (step 2).

【0041】これらの作業と平行して所定の機材を現場
に運搬する。機材は、それぞれ分解した状態で運搬し、
現場でこれらを組み立てる(工程3)。より具体的に
は、配管接続ユニットの組み立て治具30は、台座31
と、垂直部材32を分解して運搬し、現場で両者をボル
ト止めする。また配管接続装置40は、フレーム41の
水平部49と支持部44、当接部材42の垂下アーム6
1,格子状部62および油圧シリンダー43を別々に分
けて運搬し、現場でこれらを組み立てる。
In parallel with these operations, predetermined equipment is transported to the site. Equipment is transported in a disassembled state,
These are assembled on site (step 3). More specifically, the assembly jig 30 of the pipe connection unit includes a pedestal 31.
The vertical member 32 is disassembled and transported, and both are bolted on site. The pipe connection device 40 includes a horizontal portion 49 of the frame 41, the support portion 44, and the hanging arm 6 of the contact member 42.
1. The grid portion 62 and the hydraulic cylinder 43 are separately transported separately and assembled on site.

【0042】まず配管接続装置40を掘削溝70内に吊
り降ろし、走行ローラ53を主軌道71に係合させる
(工程4)。続いて配管接続ユニット1を組み立てる
(工程5)。配管接続ユニット1の組み立ては、前述の
様に配管接続ユニット組み立て治具30を使用して配管
結束部2を組み立て、さらに移動台車部3と配管結束部
2を連結部材5を介して結合する。ここで、管6の接続
部分には滑剤を塗布しておくことが望ましい。
First, the pipe connecting device 40 is suspended in the excavation groove 70, and the running roller 53 is engaged with the main track 71 (step 4). Subsequently, the pipe connection unit 1 is assembled (Step 5). To assemble the pipe connection unit 1, the pipe binding unit 2 is assembled using the pipe connection unit assembly jig 30 as described above, and the movable carriage unit 3 and the pipe binding unit 2 are connected via the connecting member 5. Here, it is desirable to apply a lubricant to the connection portion of the pipe 6.

【0043】そして図1の様に配管接続ユニット1にス
リング73を掛け、クレーン75で吊り、ゆっくりと掘
削溝70内に下ろす(工程6)。尚、配管接続ユニット
1を掘削溝70内に下ろす方法は、他の方法でも可能で
ある。配管接続ユニット1の吊り降ろし位置は、既設配
管と配管接続装置40の間である。配管接続ユニット1
を吊り下ろす際に、配管接続ユニット1の走行ローラ2
3を主軌道71に係合させる。そして吊り降ろした配管
接続ユニット1の地上部分を主軌道71に沿って既設の
配管接続ユニットに向かって押し、走行ローラ23を転
がして、配管接続ユニット1を走行させ、配管接続ユニ
ット1の各管6の先端を既設配管の後端にできるだけ近
づける(工程7)。
Then, as shown in FIG. 1, the sling 73 is hung on the pipe connection unit 1, suspended by the crane 75, and slowly lowered into the excavation groove 70 (step 6). It should be noted that the method of lowering the pipe connection unit 1 into the excavation groove 70 may be another method. The hanging position of the pipe connection unit 1 is between the existing pipe and the pipe connection device 40. Piping connection unit 1
When suspending, the traveling roller 2 of the pipe connection unit 1
3 is engaged with the main track 71. Then, the suspended portion of the pipe connection unit 1 is pushed along the main track 71 toward the existing pipe connection unit, and the traveling roller 23 is rolled to cause the pipe connection unit 1 to travel, and each pipe of the pipe connection unit 1 is moved. 6 is brought as close as possible to the rear end of the existing pipe (Step 7).

【0044】続いて先に吊り降ろした配管接続装置40
の地上部分を地上から主軌道71に沿って押し、走行ロ
ーラ53を走行させて、当接部材42をできるだけ配管
接続ユニット1の後端に近づける(工程8)。そしてそ
の位置で配管接続装置40を動かないように固定する
(工程9)。すなわち走行ローラ53近くに設けられた
ボルト55を締め込み、ボルト55の先端を強く主軌道
71の側面に押し当てて、フレーム41を主軌道71に
固定する。また必要に応じて反力発生部材77を支持部
材44の後ろに配し、フレーム41の移動を阻止する。
この時の掘削溝70内の様子は、図8の通りである。
Subsequently, the pipe connection device 40 previously suspended
Is pushed along the main track 71 from the ground, and the running roller 53 is run to bring the contact member 42 as close as possible to the rear end of the pipe connection unit 1 (Step 8). Then, the pipe connection device 40 is fixed so as not to move at that position (step 9). That is, the bolt 55 provided near the running roller 53 is tightened, and the end of the bolt 55 is pressed strongly against the side surface of the main track 71 to fix the frame 41 to the main track 71. In addition, the reaction force generating member 77 is arranged behind the support member 44 as necessary to prevent the frame 41 from moving.
The inside of the excavation groove 70 at this time is as shown in FIG.

【0045】そしてこの状態で、図10に示すように油
圧シリンダー43を作動させ、シリンダを伸長させる。
その結果当接部材42は、油圧シリンダー43に押さ
れ、補助ローラ63が補助軌道50上を走行し、当接部
材42が平行に前進する。そして当接部材42は配管接
続ユニット1の後端と当接し、これを前方に押圧する。
さらに油圧シリンダ43を伸長させると、配管接続ユニ
ット1は、走行ローラ23が主軌道71上を走行し、各
管6の先端は、既設配管(先に埋設した配管接続ユニッ
ト1の管6)の後端と当接する。すなわち配管接続ユニ
ット1は、各管6が所定の間隔で平行に結合されたもの
であるから、配管接続ユニット1を既設のそれと同一の
軌道71に載置して走行させることにより、当該配管接
続ユニット1の各管6の先端は、既設の配管接続ユニッ
ト1の各管6の後端と当接する。そしてさらに配管接続
ユニット1が前進すると、配管接続ユニット1は、既設
配管の後端に取り付けられた管継手8の中に押し込ま
れ、管の接続が完了する(工程10)。
In this state, the hydraulic cylinder 43 is operated to extend the cylinder as shown in FIG.
As a result, the contact member 42 is pushed by the hydraulic cylinder 43, the auxiliary roller 63 travels on the auxiliary track 50, and the contact member 42 advances in parallel. And the contact member 42 contacts the rear end of the pipe connection unit 1 and presses this forward.
When the hydraulic cylinder 43 is further extended, in the pipe connection unit 1, the traveling roller 23 travels on the main track 71, and the tip of each pipe 6 is connected to the existing pipe (the pipe 6 of the pipe connection unit 1 embedded earlier). Contact the rear end. That is, since the pipe connection unit 1 is formed by connecting the pipes 6 in parallel at a predetermined interval, the pipe connection unit 1 is mounted on the same track 71 as the existing one and travels to connect the pipes. The tip of each pipe 6 of the unit 1 contacts the rear end of each pipe 6 of the existing piping connection unit 1. When the pipe connection unit 1 further advances, the pipe connection unit 1 is pushed into the pipe joint 8 attached to the rear end of the existing pipe, and the connection of the pipe is completed (Step 10).

【0046】その後、油圧シリンダー43を収縮させて
当接部材42を配管接続ユニット1から外し、ボルト5
5を緩めてフレーム41の固定を解除する。そして配管
接続装置40を先と反対方向に押して大きく後退させ
る。その後は、上述の配管接続ユニット1の組み立て工
程以下を繰り返す(工程11)。尚、配管接続ユニット
1の組み立て工程だけを別途に行い、所定の状態に組み
立てられた配管接続ユニット1を多数作りだめておいて
も良く、この様な場合には、管ユニットの吊降ろし工程
に進むこととなる。そして配管の長さが所定の長さに達
すると、図11の様にキャップ80を掘削溝70内に吊
り下ろす(工程12)。ここでキャップ80は、鋼材で
箱状に作られたものであり、垂直面部に図11,12の
様にクッション材81が配置されたものである。キャッ
プ80の箱状部およびクッション材81は、配管接続ユ
ニット1の各管6の開口を同時に全て覆うことができる
大きさである。
Thereafter, the hydraulic cylinder 43 is contracted to remove the contact member 42 from the pipe connection unit 1, and the bolt 5
5 is released to release the fixing of the frame 41. Then, the pipe connection device 40 is pushed in the direction opposite to the previous direction and is largely retracted. Thereafter, the above-described steps of assembling the pipe connection unit 1 and thereafter are repeated (step 11). It should be noted that only the assembling process of the pipe connection unit 1 may be separately performed, and a large number of the pipe connection units 1 assembled in a predetermined state may be prepared. It will proceed. When the length of the pipe reaches a predetermined length, the cap 80 is suspended in the excavation groove 70 as shown in FIG. 11 (step 12). Here, the cap 80 is made of a steel material in the shape of a box, and has a cushion 81 on a vertical surface as shown in FIGS. The box-shaped portion of the cap 80 and the cushion material 81 are large enough to simultaneously cover all the openings of the pipes 6 of the pipe connection unit 1.

【0047】キャップ80は、配管接続装置40を利用
して配管接続ユニット1の後端部に押しつけられる。す
なわちキャップ80は、上端部の桟材82が配管接続ユ
ニット1の管6上に載置され、その状態で背後から配管
接続装置40によって押しつけられる。配管接続装置4
0の使用方法および作用は配管接続ユニット1を押圧す
る場合と全く同一である。
The cap 80 is pressed against the rear end of the pipe connection unit 1 using the pipe connection device 40. That is, the cap 80 has the crosspiece 82 at the upper end placed on the pipe 6 of the pipe connection unit 1, and in this state, is pressed by the pipe connection device 40 from behind. Piping connection device 4
The method of use and the function of 0 are exactly the same as when the piping connection unit 1 is pressed.

【0048】キャップ80が装着されると所定の固定具
83で、管6の後端にキャップ80が固定される。本実
施形態で、上記した様に、配管の後端にキャップ80を
装着する理由は、埋め戻しの際に管6の内部に砂が入る
ことを防ぐためである。続いて配管接続ユニット1が土
によって支持される程度、より具体的には管頂程度まで
掘削溝70を一部埋め戻す(工程13)。但し最も端部
のキャップ80付近は、次期の工事のために埋めずに置
く。尚、工期が長くなる場合には、当該部分について
も、一時的に埋め戻しておく。そして配管接続ユニット
1の配管結束部2および移動台車部3を結合する連結部
材5のボルト28を外し、移動台車部3を配管結束部2
から分離する(工程14)。
When the cap 80 is attached, the cap 80 is fixed to the rear end of the tube 6 with a predetermined fixing member 83. In the present embodiment, as described above, the reason why the cap 80 is attached to the rear end of the pipe is to prevent sand from entering the inside of the pipe 6 at the time of backfilling. Subsequently, the excavation groove 70 is partially backfilled to the extent that the pipe connection unit 1 is supported by the soil, more specifically, to the level of the pipe top (step 13). However, the vicinity of the end cap 80 is left unfilled for the next construction. When the construction period is long, the relevant portion is temporarily backfilled. Then, the bolt 28 of the connecting member 5 that connects the pipe binding unit 2 of the pipe connection unit 1 and the movable truck unit 3 is removed, and the movable truck unit 3 is connected to the pipe binding unit 2.
(Step 14).

【0049】そして主軌道71を撤去し(工程15)、
掘削溝70を埋め戻し(工程16)、鋼矢板69を撤去
して一連の配管埋設工事を終了する(工程17)。次期
工事の際には、既設の配管接続ユニット1のキャップ8
0を吊り上げ、前述の工事を行う(工程18)。
Then, the main orbit 71 is removed (step 15).
The excavation groove 70 is backfilled (step 16), the steel sheet pile 69 is removed, and a series of pipe burying work is completed (step 17). At the time of the next construction, the cap 8 of the existing piping connection unit 1
0 is lifted and the above-mentioned construction is performed (step 18).

【0050】以上の一連の工事は、すべて作業者が地上
に居て行うことができる。そのため掘削溝70内に湧水
があっても、必ずしもこれを排水する必要はない。以上
の実施形態では、配管接続ユニット1の配管結束部2と
移動台車部3は、連結部材5を介して結合したが、連結
部材5を略して両者を直接ボルトで結合しても良い。ま
た本実施形態では、連結部材5の接続孔を選択すること
によって、配管結束部2の垂下深さを調節する構成を開
示したが、連結部材5を長さの異なるものを多数用意
し、掘削溝の深さに応じて適当な長さの連結部材5を選
定し、配管結束部2の垂下深さを調節することも可能で
ある。配管接続装置40に利用した連結部材60,64
についても同様である。
The above series of works can all be performed by workers on the ground. Therefore, even if there is spring water in the excavation groove 70, it is not always necessary to drain the spring water. In the above embodiment, the pipe binding unit 2 of the pipe connection unit 1 and the movable trolley unit 3 are connected via the connecting member 5, but the connecting member 5 may be omitted and both may be directly connected by bolts. Further, in the present embodiment, the configuration in which the hanging depth of the pipe binding portion 2 is adjusted by selecting the connecting hole of the connecting member 5 is disclosed. However, a large number of connecting members 5 having different lengths are prepared and excavation is performed. It is also possible to select a connecting member 5 having an appropriate length according to the depth of the groove, and to adjust the hanging depth of the pipe binding portion 2. Connecting members 60 and 64 used in the pipe connection device 40
The same applies to.

【0051】本実施形態では、走行ローラ23等は、い
ずれも車輪状のローラを図示したが、勿論これ以外の形
状のものも利用可能である。より具体的には、コロ状の
ローラ、樽状のローラ、或いは球状のローラについても
適用することができる。
In the present embodiment, the running rollers 23 and the like are all wheel-shaped rollers, but of course other shapes can be used. More specifically, the present invention can be applied to a roller having a roller shape, a roller having a barrel shape, or a spherical roller.

【0052】配管接続装置40の押圧装置は、最も一般
的なものとして油圧シリンダーを開示したが、この他、
空気シリンダーや、ネジ式ジャッキ(モータによって可
動のもの)、トグル機構等の応用も可能である。ただ、
現実的には駆動源として油圧が最も一般的であり、感電
の心配も無く、推進力も強力である点から、実施形態に
示す様な油圧シリンダーを押圧装置として採用すること
が推奨され、さらに当接部材を平行に移動させると言う
観点から、油圧シリンダーは4本用いることが望まし
い。配管接続装置40のフレームの固定手段は、本実施
形態の方策の他、クランプ等を利用することも可能であ
る。
As the pressing device of the pipe connection device 40, a hydraulic cylinder has been disclosed as the most general one.
Applications such as pneumatic cylinders, screw-type jacks (movable by a motor), and toggle mechanisms are also possible. However,
In practice, hydraulic pressure is the most common drive source, and there is no fear of electric shock and strong propulsion.Therefore, it is recommended to use a hydraulic cylinder as shown in the embodiment as a pressing device. From the viewpoint of moving the contact member in parallel, it is desirable to use four hydraulic cylinders. As a fixing means of the frame of the pipe connection device 40, a clamp or the like can be used in addition to the measure of the present embodiment.

【0053】配管接続装置40の当接部材42は表面に
板66を設けた構成を開示したが、管6の後端部に均等
に当接する面(押さえ面)が存在すれば、表面の板を省
略して格子状の状態であっても良い。以上の実施形態
は、管の埋設工事を例に説明したが、本発明は他の種類
の配管埋設にも適用可能である。
The contact member 42 of the pipe connection device 40 has a structure in which a plate 66 is provided on the surface. However, if a surface (pressing surface) that evenly contacts the rear end of the pipe 6 exists, the plate of the surface may be provided. May be omitted to form a lattice-like state. Although the above embodiment has been described with reference to the example of pipe burial work, the present invention can be applied to other types of pipe burial.

【0054】以上の実施形態は、掘削溝70と平行し
て、地上に2本の主軌道71を敷設し、その主軌道71
に沿って、配管接続ユニット1および配管接続装置40
の走行ローラ23,53を走行させ、各管6の先端を既
設配管の後端にできるだけ近づける様にしたものであ
る。したがって、上記の実施形態では主軌道71上を走
行ローラ23,53が移動するため、曲線状の配管はし
づらい。
In the above embodiment, two main tracks 71 are laid on the ground in parallel with the excavation trench 70, and the main tracks 71
Along the pipe connection unit 1 and the pipe connection device 40
The traveling rollers 23 and 53 are moved so that the front end of each pipe 6 is brought as close as possible to the rear end of the existing pipe. Therefore, in the above embodiment, since the traveling rollers 23 and 53 move on the main track 71, it is difficult to form a curved pipe.

【0055】すなわち、配管が曲線の場合、配管接続ユ
ニット1および配管接続装置40は曲線上(同心円)に
移動走行させる必要が生じる。よって、主軌道71は曲
線でなければならない。しかしながら主軌道71の曲線
化は、現場施工性の煩雑さ、あるいは走行ローラ23,
53の脱輪等の不都合が生じることが考えられる。
That is, when the pipe is curved, the pipe connection unit 1 and the pipe connection device 40 need to move and run on a curve (concentric circle). Therefore, the main trajectory 71 must be curved. However, the curving of the main track 71 is complicated due to the complicated workability at the site, or the running roller 23,
It is conceivable that inconveniences such as the 53 being removed from the wheel may occur.

【0056】そこで、曲線状の配管を埋設する場合は、
上記の実施形態の変形例として、図13および図14に
示す様に、主軌道71を敷設せず、且つ配管接続ユニッ
ト1および配管接続装置40が任意の方向に移動できる
ようにするキャスター91,92を備えたものとする。
配管接続ユニット1のキャスター91は、上記の実施形
態の走行ローラ23に替わるもので、移動台車部3の梁
部材20の端部付近に取り付ける。キャスター91は、
コロ95がフォーク96によって支持されたものであ
り、コロ95が転がると共にフォーク96も自由回転を
許し、任意に走行方向を変えることができる。またキャ
スター91は、ブレーキ97を有し、当該ブレーキ97
でコロ95をロックすることができる。
Therefore, when burying a curved pipe,
As a modification of the above embodiment, as shown in FIGS. 13 and 14, casters 91, which do not lay the main track 71 and allow the pipe connection unit 1 and the pipe connection device 40 to move in any direction, 92 are provided.
The caster 91 of the pipe connection unit 1 is used in place of the traveling roller 23 of the above-described embodiment, and is mounted near the end of the beam member 20 of the movable bogie unit 3. The casters 91
The roller 95 is supported by a fork 96. As the roller 95 rolls, the fork 96 also allows free rotation, and the traveling direction can be arbitrarily changed. The caster 91 has a brake 97, and the brake 97
The roller 95 can be locked with.

【0057】配管接続装置40のキャスター92は、上
記の実施形態の走行ローラ53に替わるもので、梁部材
45の両端と2本の補助梁37の端部とが接合する部分
に取り付ける。配管接続装置40のキャスター92は、
前記した配管接続ユニット1のキャスター91と同一構
造である。変形例の他の構成は、当接部材42の上部に
補助ローラ63を設け、該補助ローラ63によって当接
部材42が補助軌道50から吊り下げられる点を含め、
上記の実施形態と同一である。
The casters 92 of the pipe connection device 40 are used in place of the traveling rollers 53 of the above-described embodiment, and are attached to portions where both ends of the beam member 45 and the ends of the two auxiliary beams 37 are joined. The caster 92 of the pipe connection device 40
The structure is the same as that of the caster 91 of the pipe connection unit 1 described above. Other configurations of the modified example include an auxiliary roller 63 provided above the contact member 42, including a point that the contact member 42 is suspended from the auxiliary track 50 by the auxiliary roller 63.
This is the same as the above embodiment.

【0058】また、変形例の配管接続方法も、図9のフ
ローチャート図に示した上記の実施形態と基本的に同じ
である。ただ、変形例においては、上記の実施形態の様
な移動台車部3や配管接続装置40の走行ローラ53を
主軌道71に係合させる工程4は、移動台車部3や配管
接続装置40のキャスター91,92を地面上に置く工
程となる。ただし路面が軟弱な場合には、キャスター9
2が土中に潜るので、予め地面上に鉄板98(図14参
照)を敷くことが望ましい。また鉄板98を敷く際に
は、垂直方向の高さ合わせをしておく必要がある。そし
て、掘削溝70内に配管接続ユニット1を下ろす工程6
の後、配管接続ユニット1のキャスター91を地面上ま
たは鉄板98上に置いた状態で、配管接続ユニット1の
各管6の先端を既設配管の後端にできるだけ近づける
(工程7)。
Further, the piping connection method of the modified example is basically the same as the above-described embodiment shown in the flowchart of FIG. However, in the modified example, the step 4 of engaging the traveling roller 53 of the movable bogie unit 3 and the pipe connection device 40 with the main track 71 as in the above-described embodiment is performed by the caster of the movable bogie unit 3 and the pipe connection device 40. This is a step of placing the 91 and 92 on the ground. However, if the road surface is soft, casters 9
Since 2 is submerged in the soil, it is desirable to lay an iron plate 98 (see FIG. 14) on the ground in advance. When laying the iron plate 98, it is necessary to adjust the height in the vertical direction. Then, step 6 of lowering the pipe connection unit 1 into the excavation groove 70
Thereafter, with the casters 91 of the pipe connection unit 1 placed on the ground or on the iron plate 98, the tip of each pipe 6 of the pipe connection unit 1 is brought as close as possible to the rear end of the existing pipe (Step 7).

【0059】ここで特記するべきは、曲線上の掘削溝7
0内に曲線状の配管を接続する場合であっても、キャス
ター91,92によって配管ユニット1および配管接続
装置40を曲線上に移動走行させることができるという
点である。キャスター91,92は主軌道71上を移動
するものではないため、脱輪することがないだけでな
く、主軌道71を現場施工する手間も省ける。
It should be noted here that the excavation groove 7 on the curve
Even in the case where a curved pipe is connected within 0, the pipe unit 1 and the pipe connection device 40 can be moved and run on a curve by the casters 91 and 92. Since the casters 91 and 92 do not move on the main track 71, not only do not lose their wheels, but also the time and effort for constructing the main track 71 on site can be saved.

【0060】その後、上記の実施形態の工程8から工程
10の様にして管を接続する。すなわち、配管接続装置
40のキャスター92をロックした状態で、油圧シリン
ダー43を伸長させることにより、補助ローラ63が補
助軌道50上を走行し、当接部材42を前進させ、当接
部材42が配管接続ユニット1の後端と当接するように
する。さらに油圧シリンダー43を伸長させると、配管
接続ユニット1のキャスター91が地面上を走行し、各
管6の先端が既設配管の後端と当接した後、中に押し込
まれて管の接続が完了する。
Thereafter, the pipes are connected as in steps 8 to 10 of the above embodiment. That is, by extending the hydraulic cylinder 43 in a state where the casters 92 of the pipe connection device 40 are locked, the auxiliary roller 63 travels on the auxiliary track 50, advances the contact member 42, and the contact member 42 The connection unit 1 is brought into contact with the rear end. When the hydraulic cylinder 43 is further extended, the casters 91 of the pipe connection unit 1 run on the ground, and the ends of the respective pipes 6 come into contact with the rear ends of the existing pipes. I do.

【0061】その後、上記の実施形態の工程11から工
程18で説明した様に、組み立て工程を繰り返した後、
配管が所定の長さに達すると、キャップを配管接続ユニ
ット1の後端部に押しつけ(図11参照)、掘削溝70
を埋め戻す。尚、本変形例においては、主軌道71の撤
去作業は必要ないが、地面に鉄板98を敷設した場合に
は、鉄板98を撤去する必要がある。尚、上記したキャ
スターを利用した実施形態は、曲線状の配管を接続する
場合を例に説明したが、勿論、キャスターを利用した実
施形態は、直線状の配管を接続する場合にも活用可能で
ある。
Thereafter, as described in the steps 11 to 18 of the above embodiment, after repeating the assembling steps,
When the pipe reaches a predetermined length, the cap is pressed against the rear end of the pipe connection unit 1 (see FIG. 11), and
Backfill. In this modification, the work of removing the main track 71 is not necessary, but when the iron plate 98 is laid on the ground, the iron plate 98 needs to be removed. In the embodiment using the casters described above, the case where curved pipes are connected has been described as an example, but, of course, the embodiment using casters can also be used when connecting straight pipes. is there.

【0062】[0062]

【発明の効果】請求項1,2記載の配管接続ユニットで
は、管枕はスライド部と嵌合しつつ枠体に積み重ね状に
嵌め込まれているので、管枕は互いにずれることなく所
定の位置関係を維持する。また本発明の配管接続ユニッ
トによると管がずれることもない。従って本発明の配管
接続ユニットは、掘削溝内への吊り下げや、掘削溝内で
の移動が容易であると言う効果がある。
According to the pipe connection unit according to the first and second aspects, the pipe pillows are fitted in the frame body in a stacked manner while being fitted to the slide portion, so that the pipe pillows are not shifted from each other in a predetermined positional relationship. To maintain. Further, according to the pipe connection unit of the present invention, the pipe does not shift. Therefore, the pipe connection unit of the present invention has an effect that it can be easily suspended in a digging groove or moved in the digging groove.

【0063】また本発明の配管接続ユニットでは、枠体
のスライド部に管枕の一部を嵌合しつつ、管枕を枠体に
挿入し、続いて管を管枕の上に置き、さらに続いて他の
管枕を枠体に挿入することにより組み立てを行うことが
できるので、組み立て作業が極めて容易である。
In the piping connection unit of the present invention, the pipe pillow is inserted into the frame while fitting a part of the pipe pillow to the sliding portion of the frame, and then the pipe is placed on the pipe pillow. Subsequently, assembly can be performed by inserting another pipe pillow into the frame, so that the assembling work is extremely easy.

【0064】また請求項1,2記載の発明は、キャスタ
ーやローラによって地上の軌道上を走らせて配管接続ユ
ニットを移動させることができるので、掘削溝内の配管
結束部を容易に移動させることができる効果がある。ま
た本発明の配管接続ユニットでは、配管結束部と移動台
車部は、連結手段によって結合されているので、両者の
分離が容易であり、移動台車部の再利用が可能である効
果がある。
Further, according to the first and second aspects of the present invention, the pipe connection unit can be moved by running on a track on the ground by means of casters and rollers, so that the pipe binding portion in the excavation groove can be easily moved. There is an effect that can be done. Further, in the pipe connection unit of the present invention, since the pipe tying portion and the movable trolley are connected by the connecting means, there is an effect that the two can be easily separated and the movable trolley can be reused.

【0065】請求項記載の発明によると、配管接続ユ
ニットは、管の端面が同一面に揃うと言う効果がある。
According to the third aspect of the present invention, the pipe connection unit has an effect that the end faces of the pipes are flush with each other.

【0066】請求項4,5記載の配管接続装置による
と、作業者が掘削溝の内部に入ること無く配管接続ユニ
ットを押圧することができる効果がある。
According to the pipe connection device of the fourth and fifth aspects, there is an effect that the operator can press the pipe connection unit without entering the inside of the excavation groove.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の具体的実施形態の配管接続ユニットを
掘削溝に吊り下ろす際の斜視図である。
FIG. 1 is a perspective view when a pipe connection unit according to a specific embodiment of the present invention is suspended in an excavation trench.

【図2】図1の配管接続ユニットの上部の斜視図であ
る。
FIG. 2 is a perspective view of an upper portion of the piping connection unit of FIG.

【図3】本発明の具体的実施形態の配管接続ユニット組
み立て治具の斜視図である。
FIG. 3 is a perspective view of a piping connection unit assembling jig according to a specific embodiment of the present invention.

【図4】図3の配管接続ユニット組み立て治具を使用し
た配管接続ユニットの組み立て手順を示す斜視図であ
る。
FIG. 4 is a perspective view showing a procedure of assembling a pipe connection unit using the pipe connection unit assembly jig of FIG. 3;

【図5】図1の配管接続ユニットを掘削溝に配置した際
の斜視図である。
FIG. 5 is a perspective view when the pipe connection unit of FIG. 1 is arranged in a digging trench.

【図6】本発明の具体的実施形態の配管接続装置の斜視
図である。
FIG. 6 is a perspective view of a pipe connection device according to a specific embodiment of the present invention.

【図7】図6の円内の拡大図である。FIG. 7 is an enlarged view inside the circle of FIG. 6;

【図8】本発明の具体的実施形態の配管接続方法の一工
程を示す掘削溝内の説明図である。
FIG. 8 is an explanatory diagram inside a digging trench showing one step of a pipe connection method according to a specific embodiment of the present invention.

【図9】本発明の配管接続方法を応用した配管埋設工事
の手順を示すフローチャート図である。
FIG. 9 is a flowchart showing a procedure of pipe burying work to which the pipe connection method of the present invention is applied.

【図10】図8の工程の後の工程を示す掘削溝内の説明
図である。
FIG. 10 is an explanatory view of the inside of the excavation trench showing a step after the step of FIG. 8;

【図11】本発明の具体的実施形態の配管接続方法の一
工程を示す配管接続ユニットおよびキャップの斜視図で
ある。
FIG. 11 is a perspective view of a pipe connection unit and a cap showing one step of a pipe connection method according to a specific embodiment of the present invention.

【図12】本発明の具体的実施形態の配管接続方法の一
工程を示す配管接続ユニットおよびキャップの要部の斜
視図である。
FIG. 12 is a perspective view of a main part of a pipe connection unit and a cap showing one step of a pipe connection method according to a specific embodiment of the present invention.

【図13】本発明の変形例の配管接続ユニットを掘削溝
に配置した際の一部断面斜視図である。
FIG. 13 is a partial cross-sectional perspective view when a pipe connection unit according to a modified example of the present invention is arranged in an excavation groove.

【図14】本発明の変形例を示す掘削溝内の説明図であ
る。
FIG. 14 is an explanatory diagram showing the inside of a digging trench showing a modification of the present invention.

【符号の説明】[Explanation of symbols]

1 配管接続ユニット 2 配管結束部 3 移動台車部 5 連結部材 6 管 10 枠体 11,12 管枕 13 スライド部 15 切り欠き 23 走行ローラ 28 ボルト 30 配管接続ユニット組み立て治具 31 台座 36 補助ローラ 40 配管接続装置 41 フレーム 42 当接部材 43 油圧シリンダー(押圧装置) 44 支持部 50 補助軌道 53 走行ローラ 55 ボルト 60 連結部材 63 補助ローラ 70 掘削溝 71 主軌道 80 キャップ 81 クッション材 91 キャスター 92 キャスター DESCRIPTION OF SYMBOLS 1 Piping connection unit 2 Piping bundling part 3 Moving trolley part 5 Connecting member 6 Pipe 10 Frame body 11, 12 Pipe pillow 13 Slide part 15 Notch 23 Running roller 28 Bolt 30 Piping connection unit assembly jig 31 Pedestal 36 Auxiliary roller 40 Piping Connection device 41 Frame 42 Contact member 43 Hydraulic cylinder (pressing device) 44 Support section 50 Auxiliary track 53 Running roller 55 Bolt 60 Connecting member 63 Auxiliary roller 70 Drilling groove 71 Main track 80 Cap 81 Cushion material 91 Caster 92 Caster

フロントページの続き (72)発明者 岸 孝雄 大阪市北区中之島3丁目3番22号 関西 電力株式会社内 (72)発明者 山下 輝雄 大阪市北区中之島3丁目3番22号 関西 電力株式会社内 (72)発明者 渡辺 敏緒 大阪市北区中之島3丁目3番22号 関西 電力株式会社内 (72)発明者 大野 修 大阪市北区中之島3丁目3番22号 関西 電力株式会社内 (72)発明者 津野 忠昭 大阪市北区本庄東二丁目9番18号 関電 興業株式会社内 (72)発明者 村上 義昭 大阪市北区本庄東二丁目9番18号 関電 興業株式会社内 (72)発明者 植野 宏 大阪市北区本庄東二丁目9番18号 関電 興業株式会社内 (72)発明者 花岡 敬信 大阪市西区北堀江一丁目12番19号 株式 会社栗本鐵工所内 (56)参考文献 特開 昭60−192188(JP,A) 特開 平5−344623(JP,A) 実開 平5−74121(JP,U) 実開 昭55−78160(JP,U) 実開 平7−16542(JP,U) 実公 昭60−29292(JP,Y2) 特公 昭43−23193(JP,B1) 実公 昭13−19611(JP,Y1) (58)調査した分野(Int.Cl.7,DB名) H02G 1/06 - 1/08 H02G 9/06 - 9/10 F16L 1/00 Continued on the front page (72) Inventor Takao Kishi 3-3-22 Nakanoshima, Kita-ku, Osaka-shi Kansai Electric Power Co., Inc. (72) Inventor Teruo Yamashita 3-2-2, Nakanoshima, Kita-ku, Osaka-Kansai Electric Power Co., Inc. (72) Inventor Toshio Watanabe 3-3-22 Nakanoshima, Kita-ku, Osaka-shi Inside Kansai Electric Power Co., Inc. (72) Inventor Osamu 3-2-2 Nakanoshima, Kita-ku, Osaka City, Kansai Electric Power Co., Inc. (72) Inventor Tadaaki Tsuno 2-9-18 Honjohigashi, Kita-ku, Osaka-shi Kanden Kogyo Co., Ltd. (72) Inventor Yoshiaki Murakami 2-9-1, Honjohigashi 2-chome, Kita-ku, Osaka-shi Kanden Kogyo Co., Ltd. (72) Inventor Hiroshi Ueno 2-18-18 Honjo Higashi, Kita-ku, Osaka-shi Kanden Kogyo Co., Ltd. (72) Inventor Takanobu Hanaoka 1-112-19 Kitahorie, Nishi-ku, Osaka-shi Kurimoto Iron Works Co., Ltd. (56) References JP 60-192188 (JP, A) JP-A-5-344623 (JP, A) JP-A 5-74121 (JP, U) JP-A 55-78160 (J , U) Japanese Utility Model Hei 7-16542 (JP, U) Japanese Utility Model No. 60-29292 (JP, Y2) Japanese Patent Publication No. 43-23193 (JP, B1) Japanese Utility Model No. 13-19611 (JP, Y1) (58) Field surveyed (Int.Cl. 7 , DB name) H02G 1/06-1/08 H02G 9/06-9/10 F16L 1/00

Claims (5)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 形成された掘削溝内に吊り降ろされる配
管接続ユニットであって、掘削溝と平行して二本の軌道
が地上に設けられ、配管接続ユニットは、複数の管が所
定の間隔に結束された配管結束部と、移動台車部を有
し、前記配管結束部は内面にスライド部を有する枠体
と、切り欠きを有する複数の管枕と、複数の管より成
り、管枕は前記スライド部と嵌合しつつ前記枠体に積み
重ね状に嵌め込まれ、管は管枕の間に挟まれ、切り欠き
によって保持され、移動台車部は、前記地上に設けられ
た二本の軌道と係合する下向きに取り付けられたローラ
を有し、配管結束部と、移動台車部は、配管結束部が移
動台車部から垂下状態に連結手段を介して結合されてい
ことを特徴とする配管接続ユニット。
An arrangement suspended from a formed excavation trench.
A pipe connection unit that has two tracks parallel to the
Is installed on the ground, and the piping connection unit is
It has a pipe binding part bound at regular intervals and a
The pipe binding portion includes a frame having a slide portion on an inner surface, a plurality of pipe pillows having a notch, and a plurality of pipes, and the pipe pillows are stacked on the frame while being fitted with the slide portion. The tube is sandwiched between the tube pillows and held by the notch, and the moving trolley is provided on the ground.
-Mounted roller that engages two tracks
The pipe binding section and the movable trolley section are
It is connected via a connecting means in a hanging state from the moving bogie part.
Pipe connection unit, characterized in that that.
【請求項2】 軌道を持たない掘削溝に吊り降ろされ、
ローラに代わって地上に設けられたキャスターを有し、
当該キャスターは、任意に方向を変えることができるも
のであることを特徴とする請求項1に記載の配管接続ユ
ニット。
(2) being suspended in an excavation groove having no track,
Having casters provided on the ground instead of rollers,
The caster can change direction arbitrarily
The pipe connection unit according to claim 1, wherein
knit.
【請求項3】 請求項1又は2記載の配管接続ユニット
を組み立てる治具であって、台座と垂直部材を有し、台
座には前記枠体を所定の間隔で仮止めする仮止め部材が
設けられていることを特徴とする配管接続ユニットの組
み立て治具。
3. A jig for assembling a pipe connection unit according to claim 1, having a base and vertical member, temporarily fixing member for temporarily fixing the frame body at a predetermined interval is provided in the base A jig for assembling a pipe connection unit.
【請求項4】 請求項1に記載の配管接続ユニットを、
掘削溝内で移動させて配管を接続する配管接続装置にお
いて、フレームと、当接部材と、押圧装置より成り、フ
レームは地上に敷設された軌道と係合する移動用ローラ
と、掘削溝内に垂下される支持部と、補助軌道を有し、
当接部材は、配管接続ユニットの各配管端面に当接可能
な押さえ面と、補助ローラを備え、当接部材は補助ロー
ラが補助軌道と係合した状態でフレームから掘削溝内に
垂下され、押圧装置は前記支持部と押さえ面の間に配さ
れて当接部材を移動可能であることを特徴とする配管接
続装置。
4. The piping connection unit according to claim 1,
A pipe connection device that connects the pipe by moving it in the
A frame, an abutting member, and a pressing device.
The lame is a moving roller that engages the track laid on the ground
And a support part suspended in the excavation groove, and an auxiliary track,
The contact member can contact each pipe end face of the pipe connection unit
With an auxiliary roller and an abutment member
Into the digging trench from the frame with the
The pressing device is disposed between the supporting portion and the pressing surface.
Wherein the contact member can be moved by
Connection device.
【請求項5】 複数の配管が所定の間隔に結束された配
管接続ユニットを、掘削溝内で移動させて配管を接続す
る配管接続装置において、フレームと、当接部材と、押
圧装置より成り、フレームは地上に敷設された軌道と係
合する移動用ローラと、掘削溝内に垂下される支持部
と、補助軌道を有し、当接部材は、配管接続ユニットの
各配管端面に当接可能な押さえ面と、補助ローラを備
え、当接部材は補助ローラが補助軌道と係合した状態で
フレームから掘削溝内に垂下され、押圧装置は前記支持
部と押さえ面の間に配されて当接部材を移動可能である
ことを特徴とする配管接続装置。
5. A pipe connection device for connecting a pipe by moving a pipe connection unit in which a plurality of pipes are bound at a predetermined interval in an excavation groove, comprising a frame, a contact member, and a pressing device, The frame has a moving roller that engages with the track laid on the ground, a support that hangs down in the excavation groove, and an auxiliary track, and the contact member can contact each pipe end surface of the pipe connection unit. A holding surface and an auxiliary roller, the abutting member is suspended from the frame into the excavation groove with the auxiliary roller engaged with the auxiliary track, and a pressing device is disposed between the support portion and the pressing surface. A pipe connection device wherein a contact member is movable.
JP21484696A 1995-08-18 1996-08-14 Piping connection unit, jig for assembling piping connection unit, and piping connection device Expired - Fee Related JP3339616B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP21484696A JP3339616B2 (en) 1995-08-18 1996-08-14 Piping connection unit, jig for assembling piping connection unit, and piping connection device

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP7-210636 1995-08-18
JP21063695 1995-08-18
JP21484696A JP3339616B2 (en) 1995-08-18 1996-08-14 Piping connection unit, jig for assembling piping connection unit, and piping connection device

Publications (2)

Publication Number Publication Date
JPH09163537A JPH09163537A (en) 1997-06-20
JP3339616B2 true JP3339616B2 (en) 2002-10-28

Family

ID=26518172

Family Applications (1)

Application Number Title Priority Date Filing Date
JP21484696A Expired - Fee Related JP3339616B2 (en) 1995-08-18 1996-08-14 Piping connection unit, jig for assembling piping connection unit, and piping connection device

Country Status (1)

Country Link
JP (1) JP3339616B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4562038B2 (en) * 2005-10-27 2010-10-13 日本電信電話株式会社 Repair method of protective pipe with cable installed
JP4562037B2 (en) * 2005-10-27 2010-10-13 日本電信電話株式会社 Repair method of protective pipe with cable installed
JP6076661B2 (en) * 2012-09-19 2017-02-08 西松建設株式会社 Laying apparatus and method for laying pipelines
JP7290052B2 (en) * 2019-03-20 2023-06-13 中国電力株式会社 Cable laying aid and cable laying aid installation method
CN113864573A (en) * 2021-10-27 2021-12-31 江苏龙英管道新材料有限公司 Prefabricated overhead soft heat-insulation pipe system, manufacturing method and transportation and installation method

Also Published As

Publication number Publication date
JPH09163537A (en) 1997-06-20

Similar Documents

Publication Publication Date Title
KR101474515B1 (en) Earth retaining wall using support and panel, method for constructing the same
JP3339616B2 (en) Piping connection unit, jig for assembling piping connection unit, and piping connection device
KR101721579B1 (en) Excavation Propulsion Apparatus of Underground Concrete Structure on Segement Construction Base
JP3453553B2 (en) Continuous construction method of precast concrete column wall members
KR100667170B1 (en) Underdrain structure for passage using pipe roller pushing method and that equipment method
US5522678A (en) Ground anchors
US3638438A (en) Trench-forming, pipelaying and trench wall supporting machine
JPH1046580A (en) Earth retaining temporarily arranged form and underground piping execution work method using it
CN115110973A (en) Connecting channel pipe jacking construction backrest system and using method thereof
KR102105229B1 (en) Temporary facility construction method for underground construction fo railroad track lower pass
JPH0519380Y2 (en)
JP5970305B2 (en) Pipe laying method
JPH0415360B2 (en)
JP3782180B2 (en) Support structure using sheet piles for earth retaining bells
CN115030069B (en) Diversion box culvert construction method for penetrating through existing rail lower base body
JP3516261B2 (en) Large diameter pipe laying method and equipment by open shield method
JPH08169682A (en) Rail base and its repairing method
CN216555659U (en) Jacking pipe auxiliary jacking device
JP3824384B2 (en) Construction method of shaft and apparatus used in the method
CN211733646U (en) Narrow section pipeline mounting structure of pipe laying
JPH0230509Y2 (en)
JPH0339128B2 (en)
KR101479266B1 (en) Construction method for non open cut tunnel by using of roll type roof plate
JPH0360975B2 (en)
JP3053270U (en) Support member receiving piece used for simple earth retaining method

Legal Events

Date Code Title Description
S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: R3D04

LAPS Cancellation because of no payment of annual fees