JP3163066B2 - Drill stirrer for soil cement pile method - Google Patents

Drill stirrer for soil cement pile method

Info

Publication number
JP3163066B2
JP3163066B2 JP26158498A JP26158498A JP3163066B2 JP 3163066 B2 JP3163066 B2 JP 3163066B2 JP 26158498 A JP26158498 A JP 26158498A JP 26158498 A JP26158498 A JP 26158498A JP 3163066 B2 JP3163066 B2 JP 3163066B2
Authority
JP
Japan
Prior art keywords
soil cement
pile
drilling
earth
shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP26158498A
Other languages
Japanese (ja)
Other versions
JP2000087346A (en
Inventor
克彦 佐藤
Original Assignee
株式会社トラバース
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社トラバース filed Critical 株式会社トラバース
Priority to JP26158498A priority Critical patent/JP3163066B2/en
Publication of JP2000087346A publication Critical patent/JP2000087346A/en
Application granted granted Critical
Publication of JP3163066B2 publication Critical patent/JP3163066B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、ソイルセメント
杭工法に於いて使用する削孔攪拌機に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a hole stirrer used in a soil cement pile method.

【0002】[0002]

【従来の技術及び発明が解決しようとする課題】ソイル
セメント杭工法は(1)現地盤を一旦空堀した後、削孔
にセメントミルクを注入しながらセメントミルクと土砂
を攪拌混合する工法、(2)現地盤を予め空堀すること
なく、削孔、セメントミルクの注入、セメントミルクと
土砂の攪拌混合を同時に行なう方法の2通りに大別され
るが、何れの場合も注入するセメントミルクの容量に相
当する容量の土砂が地盤から溢出し、しかもこの土砂は
セメント分を含んでいるので、溢出した土砂は環境を汚
染するための産業廃棄物として処理されることになり、
処分に費用が掛かり、コスト高を招いている。
2. Description of the Related Art The soil cement pile method is as follows: (1) A method of stirring and mixing cement milk and earth and sand while pouring cement milk into a drilling hole after once digging a site plate; ) The drilling, cement milk injection, and the simultaneous mixing and mixing of the cement milk and earth and sand can be roughly classified into two methods, without drilling the site in advance. A considerable volume of sediment spilled out of the ground, and this sediment contained cement, so the spilled out sediment would be treated as industrial waste to pollute the environment,
Disposal is costly, leading to high costs.

【0003】この対策として(1)の方法では、空堀の
際、注入ミルクの容量分だけの土砂を排土することが知
られている。そして、この工法は比較的大規模の杭工事
の際に採用されるものであり、空堀とセメントミルクの
注入、混合攪拌とに最低2種の機械を必要とする。この
事前の排土処理を(2)の比較的小規模の杭工事に応用
しようとすれば、排土のために、更に掘削機を導入する
ことが必要となり、一層のコスト高は避けられない。
As a countermeasure against this, in the method (1), it is known that earth is removed by an amount corresponding to the volume of the injected milk at the time of emptying. This method is used for pile construction on a relatively large scale, and requires at least two types of machines for empty moat, injection of cement milk, and mixing and stirring. If this preliminary earth removal process is applied to the relatively small-scale pile construction of (2), it is necessary to introduce a further excavator for earth removal, and further cost increase is inevitable. .

【0004】そこで出願人は、特開平8-158357号で、掘
削軸先端の攪拌羽根に攪拌羽根よりも遙に大面積の排土
羽根を着脱自在に装着することを提案している。即ち、
特開平8-158357号によれば、 先ず排土羽根を掘削軸に装着したままで所定深さまで
掘削した後、掘削軸を引き上げて排土羽根により排土を
行なう。(この場合の排土量が、セメントミルク注入に
より、セメントミルクと土砂の攪拌、混合によって増加
する混合土砂の量となる。) 前記の排土操作の後、排土羽根を取り外し再び掘削回
転軸を挿入して、掘削しながらセメントミルクを注入
し、攪拌、混合してソイルセメントの杭を造成してい
く。この時、前述したように排土した量に匹敵するだけ
のセメントミルクを注入する。このようにしてソイルセ
メント杭は造成される。 深い杭では、を数回に分割して行なう。
The applicant has proposed in Japanese Patent Application Laid-Open No. 8-158357 that a discharge blade having a much larger area than the stirring blade is detachably mounted on the stirring blade at the tip of the excavating shaft. That is,
According to Japanese Patent Application Laid-Open No. 8-158357, first, excavation is performed to a predetermined depth while the discharging blade is mounted on the excavating shaft, and then the excavating shaft is pulled up to perform discharging by the discharging blade. (The earth removal amount in this case is the amount of mixed earth and sand that is increased by stirring and mixing of the cement milk and earth and sand by injecting the cement milk.) After the earth removal operation, the earth removal blade is removed and the excavation rotary shaft is again rotated. Insert cement milk while digging, stir and mix to create a pile of soil cement. At this time, as described above, cement milk equivalent to the discharged amount is injected. In this way, a soil cement pile is created. In deep piles, the work is divided into several parts.

【0005】ここに、セメントミルクの注入に先行して
行なわれる排出土砂の量やセメントミルクの注入開始の
時点は、対象地盤の状態、セメントミルクの注入量、ソ
イルセメント杭の杭頭レベルによって、事前に計算して
おく必要がある。
[0005] Here, the amount of discharged earth and sand to be performed prior to the injection of the cement milk and the time of the start of the injection of the cement milk depend on the condition of the target ground, the injection amount of the cement milk, and the pile head level of the soil cement pile. It must be calculated in advance.

【0006】しかし攪拌、混合したままの土砂は、一般
にザクザクしたポーラスな状態であるのが普通で、計算
どおりに施工するとセメントミルクとの混合土砂は隆
起、溢出する傾向にある。隆起、溢出しないように加減
すれば、ザクザクしたポーラスに近い杭ができ、杭の上
部荷重を支持するのに強度上問題を生ずる。
[0006] However, the earth and sand that has been stirred and mixed is generally in a crisp and porous state, and when applied as calculated, the earth and sand mixed with cement milk tends to rise and overflow. If it is adjusted so that it does not protrude or overflow, a pile close to a crisp porous can be formed, and there is a problem in strength in supporting the upper load of the pile.

【0007】本願発明はこの点に着目して特開平8-1583
57号から派生した発明である。セメントミルクを注入し
て土砂と攪拌、混合すると下方から上方に向かって土砂
が隆起、溢出しようとし地盤を反力とした力を生ずる。
そこで、この隆起、溢出を強制的に拘束して、ソイルセ
メント杭を圧密し強固な杭を造成すると同時に、余分に
溢出する土砂及び混合土砂を防ぎ、環境上も良好な状態
を保つことを課題とする。
The present invention is based on this point, and
This is an invention derived from No. 57. When the cement milk is poured and stirred and mixed with the earth and sand, the earth and sand rises upward from below and tends to overflow, generating a force that makes the ground a reaction force.
Therefore, it is necessary to forcibly restrain the uplift and overflow, to consolidate the soil cement piles to create a strong pile, and to prevent extra overflowing sediment and mixed sediment, and to maintain a good environmental condition. And

【0008】[0008]

【課題を解決するための手段】掘削軸先端の攪拌羽根
に、攪拌羽根より遙に大面積の排土羽根を脱着自在に装
着したソイルセメント杭用削孔攪拌機において、螺旋形
状をして掘削軸に遊合し、スライドリーダに支持され掘
削軸を自在に包持する振れ止め手段と、掘削軸と自在に
係合し掘削軸と共に回転したり、しなかったりし得る係
合手段からなるプッシュウイングを備えた構造とする。
SUMMARY OF THE INVENTION In a drilling stirrer for a soil cement pile, a drilling agitator for a soil cement pile in which a discharging blade having a much larger area than the stirring blade is detachably mounted on the stirring blade at the tip of the drilling shaft. And a push wing that is supported by a slide leader and that freely holds the excavating shaft, and an engaging device that freely engages with the excavating shaft and rotates with or without the excavating shaft. With a structure.

【0009】[0009]

【発明の実施の形態】以下図面に基づいて、発明の実施
の形態を説明する。図1は、本発明のソイルセメント杭
工法用削孔攪拌機に取着するプッシュウイング1の斜視
図である。掘削軸2に遊合する円筒形部材3の頂部に2
枚のリング状の板で構成される振れ止め係止部4を形成
し、円筒形部材3の下方に、螺旋状のウイング板5を形
成する。円筒形部材3の最下部に、掘削軸2と係合して
共に回転するように、切り溝6を設け、掘削軸2にはそ
の切り溝6に係止する板状の突起7を設ける。
Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 is a perspective view of a push wing 1 attached to a drilling and stirring machine for a soil cement pile method according to the present invention. The top of the cylindrical member 3 that fits into the excavation axis 2
A steady rest locking portion 4 composed of a ring-shaped plate is formed, and a spiral wing plate 5 is formed below the cylindrical member 3. A cut groove 6 is provided at the lowermost portion of the cylindrical member 3 so as to engage with the excavation shaft 2 and rotate together with the excavation shaft 2, and the excavation shaft 2 is provided with a plate-shaped projection 7 to be engaged with the cut groove 6.

【0010】図2は、振れ止め金具8の上面図の一例で
あり、一端は削孔攪拌機のリーダに機械的に固着され、
他端は図の矢印のように腕9が開閉可能で、ピンで止め
るようになっている。
FIG. 2 is an example of a top view of the steady rest 8, one end of which is mechanically fixed to a leader of a drilling and stirring machine.
At the other end, the arm 9 can be opened and closed as shown by the arrow in the figure, and is stopped by a pin.

【0011】図2の振れ止め金具8の腕9が図1の振れ
止め係止部4の2枚のリング状の板で構成される溝部に
嵌まって、プッシュウイング1の振れ止め機能か発揮さ
れる。この振れ止めの方法は周知手段である。
The arm 9 of the steady rest 8 shown in FIG. 2 fits into the groove formed by the two ring-shaped plates of the steady rest locking portion 4 of FIG. Is done. This steadying method is a well-known means.

【0012】図3は、本発明の削孔攪拌機の全体図であ
りプッシュウイング1の取着状態を示す図である。スラ
イド式削孔攪拌機は、狭隘な場所で地盤改良する場合に
用いられる周知のものである。符号8は振れ止め金具で
あり、符号10は第一スライドリーダであり、符号11
は第二スライドリーダである。符号12は掘削羽根であ
り符号13はモーターである。符号14はセメントミル
ク注入管である。
FIG. 3 is an overall view of the drill stirrer according to the present invention, showing a state where the push wing 1 is attached. 2. Description of the Related Art A slide drilling stirrer is a well-known type used for ground improvement in a narrow place. Reference numeral 8 indicates a steady rest, reference numeral 10 indicates a first slide reader, and reference numeral 11
Is a second slide reader. Reference numeral 12 denotes a cutting blade, and reference numeral 13 denotes a motor. Reference numeral 14 denotes a cement milk injection tube.

【0013】次にソイルセメント杭の施行法を順を追っ
て述べプッシュウイングを説明する。図3で、先ず40cm
〜50cm削孔し排土しておく。この場合特開平8-158357号
に開示した排土羽根を応用して効率よく排土する。削孔
の初期には振れ止め金具8をセットして、地上から長く
出た掘削軸の安定を図る。
Next, the method of applying the soil cement pile will be described step by step, and the push wing will be described. In FIG. 3, first, 40 cm
Drill up to 50cm and excavate. In this case, the earth is efficiently discharged by applying the earth discharging blade disclosed in JP-A-8-158357. At the beginning of the drilling, the steady rest 8 is set to stabilize the excavation shaft protruding long from the ground.

【0014】図4は、削孔中の図であり、第二スライド
リーダ11に沿って第一スライドリーダ10が降下しな
がら、削孔は進む。途中計算された位置でミルクの注入
を始める。振れ止めは地面近くまで降下する。
FIG. 4 is a view during drilling. The drilling proceeds while the first slide leader 10 descends along the second slide leader 11. Start injecting milk at the calculated position on the way. The steady rest descends close to the ground.

【0015】図5は、所定の位置まで削孔した図であ
り、振れ止め10を解除しリーダを少し水平に後退さ
せ、ウイング板5が振れ止め金具8をかわし、その下部
に位置するまで削孔を続ける。ウイング板5が振れ止め
金具8の下方に位置する状態で再び振れ止め金具8をセ
ットする。
FIG. 5 is a view in which a hole is drilled to a predetermined position. The steady rest 10 is released, the leader is retracted slightly horizontally, and the wing plate 5 fends off the steady rest 8 and is cut until it is positioned below. Continue the hole. With the wing plate 5 positioned below the steady rest 8, the steady rest 8 is set again.

【0016】この場合、ウイング板5は、螺旋状をして
おり掘削軸2の板状の突起7と円筒形部材3の切り溝6
が係合しているので掘削軸2と共に回転しながら地盤に
進入する。
In this case, the wing plate 5 is spiral and has a plate-like projection 7 of the excavating shaft 2 and a cut groove 6 of the cylindrical member 3.
Engages with the excavation shaft 2 and enters the ground.

【0017】そして予め計算された深さで、第一スライ
ドリーダ10の頂部付近にあるモーターはプッシュし得
るように配設されていて、このモーターをプッシュし
て、掘削軸を5cm 〜6cm 押し下げるとプッシュウイング
1の切り溝6から、掘削軸2に設けた板状の突起7の係
合がはずれ、プッシュウイング1の回転は止まると同時
に削孔攪拌は進む。そして排土は、どんどん隆起しよう
とするが、スライドリーダ10に機械的に取着され振れ
止め金具8で固定された、プッシュウイング1に阻まれ
て、圧密されることになる。
At a pre-calculated depth, the motor near the top of the first slide reader 10 is arranged to be pushable, and when this motor is pushed to lower the excavation axis by 5 cm to 6 cm. The plate-shaped projection 7 provided on the excavation shaft 2 is disengaged from the cut groove 6 of the push wing 1, and the rotation of the push wing 1 stops, and simultaneously the drilling and stirring proceeds. Then, the earth is swelled more and more. However, the earth is blocked by the push wing 1 mechanically attached to the slide leader 10 and fixed by the steady rest 8 to be compacted.

【0018】ここに、セメントミルクの注入に先行して
行なわれる排出土砂の量やセメントミルクの注入開始の
時点は、対象地盤の状態、セメントミルクの注入量、ソ
イルセメント杭の杭頭レベルによって、事前に計算して
おく必要がある。
Here, the amount of discharged earth and sand to be performed prior to the injection of the cement milk and the time of the start of the injection of the cement milk depend on the condition of the target ground, the injection amount of the cement milk, and the pile head level of the soil cement pile. It must be calculated in advance.

【0019】このようにして、余分な排土を出さないの
で産業廃棄物もなく環境衛生もよく、ザクザクしたポー
ラスなソイルセメント杭ではなく、圧密された強固な杭
を施工することができる。
[0019] In this manner, since no extra earth is discharged, there is no industrial waste and environmental hygiene is good, and it is possible to construct not a cramped porous soil cement pile but a compact and strong pile.

【0020】[0020]

【発明の効果】本発明の効果は次の通りである。 (1)本発明の削孔攪拌機を使用することにより、プッ
シュウイングで隆起溢出しようとする土砂を押さえ込む
ので、環境汚染の虞のあるセメントミルクやセメント含
有土砂を排出することなく、ソイルセメント杭を造成す
ることができる。 (2)またプッシュウイングで隆起溢出しようとする土
砂を押さえ込むので、掘削攪拌によりザクザクしたポー
ラスに近い杭が圧密され、杭の上部荷重を支持するのに
十分な強度のソイルセメント杭を造成することができ
る。
The effects of the present invention are as follows. (1) By using the drilling stirrer of the present invention, the sediment that tends to overflow by the push wing is suppressed, so that the soil cement pile can be removed without discharging cement milk or cement-containing sediment that may cause environmental pollution. Can be created. (2) In addition, since the sediment that is about to protrude is held down by the push wing, the pile close to the crispy pore is compacted by excavation and agitation, and a soil cement pile with sufficient strength to support the upper load of the pile is created. Can be.

【図面の簡単な説明】[Brief description of the drawings]

【図1】ソイルセメント杭工法用削孔攪拌機に取着する
プッシュウイング1の斜視図である。
FIG. 1 is a perspective view of a push wing 1 attached to a hole stirrer for a soil cement pile method.

【図2】振れ止め金具の一例の上面図である。FIG. 2 is a top view of an example of a steady rest.

【図3】本発明の削孔攪拌機の全体図でありプッシュウ
イング1の取着状態を示す図である。
FIG. 3 is an overall view of a hole stirrer according to the present invention, showing an attached state of a push wing 1;

【図4】本発明の削孔攪拌機での掘削中の図である。FIG. 4 is a diagram during excavation with the drilling and stirring machine of the present invention.

【図5】本発明の削孔攪拌機で所定の位置まで削孔し
て、プッシュウイングが作用している図である。
FIG. 5 is a diagram in which a hole is drilled to a predetermined position by the hole stirrer of the present invention, and a push wing is acting.

【符号の説明】[Explanation of symbols]

1……プッシュウイング、2……掘削軸、3……プッシ
ュウイングの円筒形部材、4……プッシュウイングの振
れ止め係止部、5……ウイング板、6……プッシュウイ
ングに設けた切り溝、7……切り溝6に嵌入する板状突
起、8……振れ止め金具、9……振れ止め金具の腕、1
0……第一スライドリーダ、11……第二スライドリー
ダ、12……掘削羽根、13……モーター、14……セ
メントミルク注入管
DESCRIPTION OF SYMBOLS 1 ... Push wing, 2 ... Excavation axis, 3 ... Push wing cylindrical member, 4 ... Push wing anti-sway locking part, 5 ... Wing plate, 6 ... Cut groove provided on push wing , 7 ... plate-like projections to be fitted into the cut grooves 6, 8 ... anti-sway fittings, 9 ... arms of the anti-sway fittings, 1
0: first slide leader, 11: second slide leader, 12: excavating blade, 13: motor, 14: cement milk injection pipe

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 掘削軸先端の攪拌羽根に、攪拌羽根より
遙に大面積の排土羽根を脱着自在に装着したソイルセメ
ント杭用削孔攪拌機において、螺旋形状をして掘削軸に
遊合し、スライドリーダに支持され掘削軸を自在に包持
する振れ止め手段と、掘削軸と自在に係合し掘削軸と共
に回転したり、しなかったりし得る係合手段からなるプ
ッシュウイングを備えたことを特徴とするソイルセメン
ト杭工法用削孔攪拌機。
1. A drilling and stirring machine for a soil cement pile in which a discharging blade having a much larger area than the stirring blade is detachably mounted on the stirring blade at the tip of the drilling shaft. And a push wing that is supported by a slide leader and freely holds the excavating shaft, and an engaging device that freely engages with the excavating shaft and rotates or does not rotate with the excavating shaft. A hole stirrer for soil cement pile construction.
JP26158498A 1998-09-16 1998-09-16 Drill stirrer for soil cement pile method Expired - Fee Related JP3163066B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP26158498A JP3163066B2 (en) 1998-09-16 1998-09-16 Drill stirrer for soil cement pile method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP26158498A JP3163066B2 (en) 1998-09-16 1998-09-16 Drill stirrer for soil cement pile method

Publications (2)

Publication Number Publication Date
JP2000087346A JP2000087346A (en) 2000-03-28
JP3163066B2 true JP3163066B2 (en) 2001-05-08

Family

ID=17363959

Family Applications (1)

Application Number Title Priority Date Filing Date
JP26158498A Expired - Fee Related JP3163066B2 (en) 1998-09-16 1998-09-16 Drill stirrer for soil cement pile method

Country Status (1)

Country Link
JP (1) JP3163066B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5597232B2 (en) * 2012-08-30 2014-10-01 株式会社トラバース Ground improvement device and residual soil discharge suppression body of ground improvement device
JP7480381B1 (en) 2023-03-13 2024-05-09 小野田ケミコ株式会社 Soil improvement device, soil removal method in soil improvement method, and spiral rod used therein

Also Published As

Publication number Publication date
JP2000087346A (en) 2000-03-28

Similar Documents

Publication Publication Date Title
JPH10204876A (en) Soil improvement method by using pile
JP6273333B1 (en) Method for forming soil cement pile
JP2008075266A (en) Method of constructing pile
JPH07119462B2 (en) Ground improvement agitator and ground improvement method using the same
KR102222835B1 (en) Ground improvement method for organic soil
JP3163066B2 (en) Drill stirrer for soil cement pile method
JPH01260117A (en) Pile driving work
JP2005009240A (en) Method for installing soil hardened matter on-site-manufactured pile and prefabricated pile
JP3931298B2 (en) Hollow pipe pile core misalignment prevention device and hollow pipe pile core misalignment prevention construction method
KR19980020441A (en) Pile foundation construction method and device
JP3530960B2 (en) Attachment for drilling and stirring
JP2836808B2 (en) Drill stirrer for soil cement pile method
JP2645322B2 (en) Construction method of soil cement composite pile
JP2004300847A (en) Construction method for columnar foundation improvement body using steel pipe pile
JPH0757947B2 (en) Cast-in-place pile construction method
JP3182674B2 (en) Construction method of agitated mixing reinforcement
JP3747338B2 (en) Ground improvement method
JPH08144263A (en) Soil improvement method
CN114908734A (en) Nail type cement soil gravel pile forming operation method
JPS6043490B2 (en) Pile driving method
JPH081062B2 (en) Agitator for excavator
JPH0621964Y2 (en) Concrete pouring equipment for cast-in-place piles
JPH0424321A (en) Clamshell excavator, method of forming underground wall
JPH0988058A (en) Ground improvement method
JP2004003131A (en) Method of constructing soil cement pile

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20010213

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090223

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100223

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110223

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110223

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120223

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120223

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130223

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140223

Year of fee payment: 13

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees