JPH0621964Y2 - Concrete pouring equipment for cast-in-place piles - Google Patents

Concrete pouring equipment for cast-in-place piles

Info

Publication number
JPH0621964Y2
JPH0621964Y2 JP1987090685U JP9068587U JPH0621964Y2 JP H0621964 Y2 JPH0621964 Y2 JP H0621964Y2 JP 1987090685 U JP1987090685 U JP 1987090685U JP 9068587 U JP9068587 U JP 9068587U JP H0621964 Y2 JPH0621964 Y2 JP H0621964Y2
Authority
JP
Japan
Prior art keywords
concrete
pile
inlet pipe
hole
pile hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1987090685U
Other languages
Japanese (ja)
Other versions
JPS63198629U (en
Inventor
愛雄 渡部
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitani Sekisan Co Ltd
Original Assignee
Mitani Sekisan Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitani Sekisan Co Ltd filed Critical Mitani Sekisan Co Ltd
Priority to JP1987090685U priority Critical patent/JPH0621964Y2/en
Publication of JPS63198629U publication Critical patent/JPS63198629U/ja
Application granted granted Critical
Publication of JPH0621964Y2 publication Critical patent/JPH0621964Y2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Underground Or Underwater Handling Of Building Materials (AREA)

Description

【考案の詳細な説明】 (産業上の利用分野) この考案は、基礎杭を現場にて地中に無音、無振動で施
工する際に、杭穴へコンクリートを打設するコンクリー
ト打設装置に関するものである。
[Detailed Description of the Invention] (Industrial application field) The present invention relates to a concrete placing device for placing concrete into a pile hole when constructing a foundation pile in the ground in the ground silently and without vibration. It is a thing.

(従来の技術) 従来、現場でコンクリートを打設し、無音、無振動で杭
を施工する場合に、土質が良好でないときは、バケット
で掘削土を排出し、穴壁の崩壊を防ぐために、穴内に、
ベントナイトを送り込んで充満させた後に、補強材を挿
入し、ついで杭穴内にコンクリートを投入して、前記ベ
ントナイトとコンクリートとを置換し、その後コンクリ
ートを硬化させて、コンクリート杭を構築している。
(Prior art) Conventionally, when concrete is placed on site and the pile is constructed without noise and vibration, if the soil quality is not good, the excavated soil is discharged with a bucket to prevent the hole wall from collapsing. In the hole,
After the bentonite is fed and filled, a reinforcing material is inserted, then concrete is put into the pile hole to replace the bentonite with the concrete, and then the concrete is hardened to construct a concrete pile.

(考案が解決しようとする問題点) しかし、従来法によると、ベントナイトで置換するた
め、その比重が大きく(約1.2〜1.5)、コンクリ
ートの打設が困難になるという問題点がある。
(Problems to be solved by the invention) However, according to the conventional method, since it is replaced with bentonite, its specific gravity is large (about 1.2 to 1.5), and it is difficult to pour concrete. is there.

また、従来法では、杭穴内にベントナイトを充満させた
後、さらにこのベントナイトとコンクリートとを置換す
るので、排出物が穴体積の2倍となり、施工工程が多く
なるのみならず、排出物の処理に手間と費用がかかると
いう問題点がある。このため、穴内をベントナイトで置
換しないで、泥土のまま、コンクリートを強制圧入し
て、置換する手段が要望されているが、コンクリートを
効率よく強制圧入することが困難であった。
Further, in the conventional method, since the pile hole is filled with bentonite and then the bentonite is replaced with concrete, the discharge amount becomes twice the volume of the hole, and not only the number of construction steps increases but also the waste treatment process. There is a problem that it takes time and money. For this reason, there has been a demand for a means for forcibly inserting and replacing concrete in the mud as it is without replacing it with bentonite, but it has been difficult to forcibly insert concrete efficiently.

この考案は、上記問題点を解決することを基本的な目的
とし、穴の内容物比重が高くても、コンクリート打設を
容易かつ効率よく行うことができるコンクリート圧入装
置を提供するものである。
The present invention has as its basic purpose to solve the above problems, and provides a concrete press-fitting device that can easily and efficiently perform concrete pouring even if the specific gravity of the contents of the holes is high.

(問題点を解決するための手段) すなわち、この考案は、杭穴の上端に設置・固定される
ようにすると共に、貫通孔を有する上板及び下板を縦板
で連結して、側方が開放した筒状受け台と、この筒状受
け台の貫通孔へ、上下方向に移動可能であって、回転方
向で係止するように嵌挿されるコンクリート送入管と、
このコンクリート送入管内に、回転可能に嵌挿される螺
旋羽根とからなり、前記コンクリート送入管に軸方向に
沿った突条を形成し、前記上板及び下板の少なくとも一
方に、前記突条を係合できる溝を設けたことを特徴とす
る現場打ち杭用コンクリート打設装置である。
(Means for Solving the Problems) That is, the present invention is designed to be installed and fixed at the upper end of a pile hole, and the upper plate and the lower plate having through holes are connected by a vertical plate to provide a lateral position. A tubular cradle that is open, a through hole of the tubular cradle, a concrete feed pipe that is vertically movable and that is inserted so as to be locked in the rotational direction,
Inside the concrete inlet pipe, a spiral blade that is rotatably fitted is formed, and a ridge extending along the axial direction is formed on the concrete inlet pipe, and the ridge is formed on at least one of the upper plate and the lower plate. It is a concrete pouring device for cast-in-place piles, which is provided with a groove that can engage with.

(作用) この考案によれば、コンクリート送入管内に、コンクリ
ートを送り込み、コンクリート送入管内で螺旋羽根を螺
旋方向とは逆の方向に回転させることにより、コンクリ
ートは、コンクリート送入管内で下方に圧送される。こ
の際に、コンクリート送入管は、筒状受け台に回転方向
で係止されているので、螺旋羽根の回転につられて回転
することはなく、コンクリートが効率よく送られる。し
たがって、コンクリート送入管の下端から、杭穴へコン
クリートが圧入される。
(Operation) According to this invention, concrete is fed into the concrete feed pipe, and the spiral blade is rotated in the direction opposite to the spiral direction in the concrete feed pipe, whereby the concrete moves downward in the concrete feed pipe. Pumped. At this time, since the concrete inlet pipe is locked to the tubular pedestal in the rotation direction, the concrete inlet pipe does not rotate due to the rotation of the spiral blade, and the concrete is efficiently fed. Therefore, the concrete is pressed into the pile hole from the lower end of the concrete inlet pipe.

また、コンクリート送入管を逐次上昇させることによ
り、順次、杭穴の下方部からコンクリートを送り込んで
残存した掘削土砂と置換し、残留掘削土砂が悉く杭穴外
に排出される。
Further, by sequentially raising the concrete inlet pipe, concrete is sequentially fed from the lower part of the pile hole to replace the remaining excavated earth and sand, and the residual excavated earth and sand is discharged outside the pile hole where it is muttered.

なお、杭穴へコンクリートを圧入し、最後に杭穴からコ
ンクリート送入管と、螺旋羽根とが抜き取られた状態
で、コンクリートを硬化させることにより、補強材が配
されたコンクリート杭が構築されることとなる。
It should be noted that concrete is press-fitted into the pile hole, and finally concrete is cured in a state where the concrete feed pipe and the spiral blade are extracted from the pile hole, whereby a concrete pile having a reinforcing material is constructed. It will be.

(実施例) 以下に、この考案の一実施例を、添附図面に基づいて説
明する。
(Embodiment) An embodiment of the present invention will be described below with reference to the accompanying drawings.

コンクリート送入管1は、長尺な円筒体からなり、上端
にはフランジ1aが形成されている。また外周面に、軸
方向に沿って、直径対称的にリブ(突条)2,2が形成
されている(第3図、第4図)。
The concrete inlet pipe 1 is made of a long cylindrical body and has a flange 1a formed at the upper end. Further, ribs (protrusions) 2 and 2 are formed on the outer peripheral surface in a diametrically symmetrical manner along the axial direction (FIGS. 3 and 4).

また、杭穴上端に固定すべき筒状受け台3は、上板3a
と、下板3bとが、複数の縦板3cで連結され、側方が
開放された構成からなるものである。上板3aには、前
記コンクリート送入管1が貫通する貫通孔4aが形成さ
れており、この貫通孔4aに連続して、リブ2,2がそ
れぞれ挿通するスリット(溝)5,5が対向位置に設け
られている。また下板3bには、前記スリット5,5の
外端間の間隔よりも大径な貫通孔4bが形成されている
(第1図、第2図)。
Further, the cylindrical pedestal 3 to be fixed to the upper end of the pile hole is the upper plate 3a.
The lower plate 3b and the lower plate 3b are connected by a plurality of vertical plates 3c, and are laterally open. The upper plate 3a is formed with a through hole 4a through which the concrete inlet pipe 1 penetrates, and slits (grooves) 5 and 5 through which the ribs 2 and 2 respectively pass are opposed to the through hole 4a. It is provided in the position. Further, the lower plate 3b is formed with a through hole 4b having a diameter larger than the distance between the outer ends of the slits 5 and 5 (FIGS. 1 and 2).

さらに、前記コンクリート送入管1内には、回転軸6a
に螺旋条6bが形成された螺旋羽根6(第5図)が回転
可能に嵌挿されており、上記したコンクリート送入管1
と、筒状受け台3と、螺旋羽根6とによりコンクリート
圧入装置が構成されている。
Further, in the concrete inlet pipe 1, a rotary shaft 6a is provided.
A spiral blade 6 (Fig. 5) having a spiral strip 6b formed therein is rotatably fitted therein, and the above concrete feed pipe 1
The tubular pedestal 3 and the spiral blade 6 constitute a concrete press-fitting device.

次に、この装置を用いて、現場で杭を構築する手順につ
いて説明する。
Next, a procedure for constructing a pile on site using this device will be described.

まず、杭打ち位置に、杭穴を形成すべく、オーガロッド
10を配置する。このオーガロッド10は、ロッド先端
側に螺旋羽根11が形成され、先端縁には掘削刃12が
形成されたものである。さらに、螺旋羽根11より上方
のロッドには所定間隔を置いて、複数の練り付けドラム
13が設けられており、前記各ドラム13,13間に板
状の撹拌翼14が放射状に設置されている。
First, the auger rod 10 is arranged at the pile driving position so as to form a pile hole. The auger rod 10 has a spiral blade 11 formed on the rod tip side and an excavating blade 12 formed on the tip edge. Further, a plurality of kneading drums 13 are provided at predetermined intervals on the rod above the spiral blade 11, and plate-shaped stirring blades 14 are radially installed between the drums 13 and 13. .

前記オーガロッド10を回転させながら下降させて、杭
打ち位置を掘削する(台6図)。この掘削の際に、所望
によりオーガロッド10の先端から掘削部分へ清水を注
入する。前記オーガーロッド10による掘削土砂は、泥
土となり、撹拌翼14により撹拌され、練り付けドラム
13により掘削穴壁に練り付けられて、杭穴15が形成
される(第7図)。なお、この杭穴15の上端には、筒
状のケーシング16を嵌挿しておく、前記ケーシング1
6には、上端縁にフランジ16aが形成されており、ま
た、回転止めのために外周に4つのリブ16bが形成さ
れている。前記ケーシング16の嵌挿により、地表付近
の泥塊が杭穴15内に落下したり、杭内壁が崩壊するの
を未然に防止できる。
The auger rod 10 is rotated and lowered to excavate a pile driving position (table 6). During this excavation, if desired, fresh water is injected from the tip of the auger rod 10 into the excavated portion. The earth and sand excavated by the auger rod 10 becomes mud, which is agitated by the agitating blades 14 and kneaded by the kneading drum 13 to the excavation hole wall to form the pile holes 15 (Fig. 7). In addition, a cylindrical casing 16 is fitted and inserted in the upper end of the pile hole 15, the casing 1
6, a flange 16a is formed on the upper end edge, and four ribs 16b are formed on the outer periphery to prevent rotation. By inserting the casing 16, it is possible to prevent the mud block near the surface of the ground from falling into the pile hole 15 and the inner wall of the pile from collapsing.

前記杭穴15の形成後には、オーガロッド1の下端部か
らセメントミルクを供給し(第8図)、残留土砂とセメ
ントミルクとの混合物18により根固めを行い(第9
図)、その後、杭穴15からオーガロッド10を抜き取
り、前記杭穴15へ鉄筋篭17を挿入設置する(第10
図)。さらに、杭穴15の中央部であって鉄筋篭17の
内側に、コンクリート送入管1を配置する(第11
図)。コンクリート送入管1の設置においては、ケーシ
ング16の上部に筒状の送入管受け台3を固定してお
く。コンクリート送入管1は、この受け台3を通して、
杭穴15内に挿入され、そのフランジ1aが上板3aと
当接し、リブ2がスリット5に係合する。なお、コンク
リート送入管1の先端縁には、コンクリート送入管1を
杭穴15内に挿入する際に、杭穴15内の泥土がコンク
リート送入管1内に侵入しないように、テープなどで簡
易蓋(図示しない)を設けておく。この簡易蓋は、コン
クリート送入管1が杭穴15内に挿入する際に、浮力を
生じさせるので、その下端部に、カウンタウェイトを設
けておく。
After the pile holes 15 are formed, cement milk is supplied from the lower end of the auger rod 1 (Fig. 8), and the mixture 18 of the residual soil and cement milk is used for root consolidation (9th).
After that, the auger rod 10 is pulled out from the pile hole 15, and the rebar cage 17 is inserted and installed in the pile hole 15 (No. 10).
Figure). Further, the concrete inlet pipe 1 is arranged at the center of the pile hole 15 and inside the rebar cage 17 (No. 11).
Figure). When installing the concrete inlet pipe 1, the tubular inlet pipe pedestal 3 is fixed to the upper part of the casing 16. The concrete inlet pipe 1 passes through this cradle 3
The flange 1a is inserted into the pile hole 15, the flange 1a contacts the upper plate 3a, and the rib 2 engages with the slit 5. In addition, at the tip edge of the concrete inlet pipe 1, when the concrete inlet pipe 1 is inserted into the pile hole 15, a tape or the like is provided so that the mud in the pile hole 15 does not enter the concrete inlet pipe 1. Install a simple lid (not shown). Since this simple lid causes buoyancy when the concrete inlet pipe 1 is inserted into the pile hole 15, a counterweight is provided at the lower end thereof.

杭穴15内に配置した上記コンクリート送入管1の上部
にホッパー18を取付け、このホッパー18から、コン
クリート送入管1内にコンクリートを注入し、次いで螺
旋羽根6をコンクリート送入管1内で下降させてコンク
リートを押込む。さらに、コンクリート送入管1内にコ
ンクリートを注入し、螺旋羽根6を定位置で図示方向に
回転させて、コンクリートを送入管1の下部を通して杭
穴15内に強制圧入する(第12図)。所定量のコンク
リートを圧入した後、コンクリート送入管1を引き上
げ、ホッパー18を取外す。このコンクリート送入管1
は、図示しないクレーンなどにより仮受けしておく。次
いで、螺旋羽根6を、前記と同方向である図示方向に回
転させながら、杭穴15から引き抜く。仮受けしたコン
クリート送入管1は、約3mを切り取り、再度、送入管
受け台3に設置する。コンクリート送入管1の上部に
は、ホッパー18を取付け、前記と同様にして、螺旋羽
根6の回転により、コンクリートを順次、圧入する。こ
のコンクリートの圧入およびコンクリート送入管1の切
断を繰返して、杭穴15内へ、下方部から順次、コンク
リートを打設する。。このようにして、比較的比重の大
きい杭穴内に、効率よくコンクリートを打設でき、杭穴
15内の残留泥水はコンクリートで置換され、受け台3
の側方の開放部を通して、杭穴15外に排出される。こ
の排出物は、杭穴の体積分であるので、処理量は従来に
比べ、1/2となる。
A hopper 18 is attached to the upper part of the concrete feed pipe 1 arranged in the pile hole 15, concrete is poured into the concrete feed pipe 1 from this hopper 18, and then spiral blades 6 are placed inside the concrete feed pipe 1. Lower and push in concrete. Further, concrete is poured into the concrete inlet pipe 1 and the spiral blade 6 is rotated in the illustrated direction at a fixed position to forcibly press the concrete into the pile hole 15 through the lower portion of the inlet pipe 1 (Fig. 12). . After press-fitting a predetermined amount of concrete, the concrete feed pipe 1 is pulled up and the hopper 18 is removed. This concrete inlet pipe 1
Are temporarily received by a crane (not shown). Next, the spiral blade 6 is pulled out from the pile hole 15 while being rotated in the same direction as the above-described direction. About 3 m of the concrete receiving pipe 1 that has been temporarily received is cut off and installed again on the receiving pipe receiving stand 3. A hopper 18 is attached to the upper part of the concrete inlet pipe 1, and concrete is sequentially pressed in by rotating the spiral blade 6 in the same manner as described above. This press-fitting of concrete and the cutting of the concrete feed pipe 1 are repeated to pour concrete into the pile holes 15 from the lower part in order. . In this way, concrete can be efficiently placed in the pile holes having a relatively large specific gravity, and the residual mud in the pile holes 15 is replaced with concrete, and the pedestal 3
It is discharged to the outside of the pile hole 15 through the open part on the side of the. Since this discharge is the volume of the pile hole, the processing amount is 1/2 that of the conventional one.

コンクリートの打設が終了した(第13図)後、残りの
コンクリート送入管1および螺旋羽根6は杭穴15内か
ら抜き取り、さらに杭穴15からケーシング16を抜き
取る(第14図)。
After the placing of concrete is completed (Fig. 13), the remaining concrete inlet pipe 1 and the spiral blade 6 are extracted from inside the pile hole 15, and the casing 16 is extracted from the pile hole 15 (Fig. 14).

この後コンクリートは経時的に硬化するので、現場にて
コンクリート杭が効率よく構築される。
After this, the concrete hardens over time, so that concrete piles can be efficiently constructed on site.

(考案の効果) この考案によれば、杭穴の上端に設置・固定されるよう
にした貫通孔を有する筒状受け台と、この筒状受け台の
貫通孔へ、上下に移動可能で、コンクリート送入管の突
条(リブ)と筒状受け台の溝(スリット)とを係合させ
て回転方向で係止するように嵌挿されるコンクリート送
入管と、このコンクリート送入管内に回転可能に嵌挿さ
れる螺旋羽根とからなるので、コンクリート送入管は、
螺旋羽根の回転によっても回転することなく、筒状受け
台に支持され、杭穴内容物の比重が比較的大きな場合で
も、杭穴内へコンクリートを確実、かつ効率よく圧入す
ることができるという効果がある。また杭穴の崩壊を未
然に防止することができる。また、筒状受け台は、上板
及び下板を縦板で連結して側方が開放した形状としたの
で、杭穴内の泥水は筒状受け台の側方から容易に杭穴外
に排出できる効果がある。
(Effect of the Invention) According to the present invention, a tubular pedestal having a through hole that is installed and fixed to the upper end of the pile hole, and a through hole of the tubular pedestal can be moved vertically. A concrete inlet pipe inserted so as to engage the ridges (ribs) of the concrete inlet pipe with the grooves (slits) of the tubular pedestal so as to lock in the rotation direction, and to rotate inside this concrete inlet pipe Since it consists of spiral blades that can be inserted as much as possible, the concrete inlet pipe is
Even if it is supported by the tubular pedestal without rotating due to the rotation of the spiral blade, and the specific gravity of the pile hole contents is relatively large, the effect that the concrete can be reliably and efficiently pressed into the pile hole is obtained. is there. Further, it is possible to prevent the pile holes from collapsing. In addition, since the cylindrical pedestal has a shape in which the upper and lower plates are connected by vertical plates and the sides are open, muddy water in the pile holes is easily discharged from the sides of the cylindrical pedestal to the outside of the pile holes. There is an effect that can be done.

【図面の簡単な説明】[Brief description of drawings]

第1図は、この考案の一実施例を示す筒状受け台の平面
図、第2図は同じく正面図、第3図はコンクリート送入
管の正面図、第4図は同じく平面図、第5図は螺旋羽根
の正面図、第6図〜第14図は、この考案の装置を用い
た現場打ちの工程を示す一部断面図であり、第6図はオ
ーガロッドによる掘削時、第7図は掘削終了時、第8図
は根固め時、第9図はオーガロッド抜き取り時、第10
図は鉄筋篭挿入時、第11図はコンクリート送入管配置
時、第12図はコンクリート投入時、第13図はコンク
リート送入管および螺旋羽根抜取った後、第14図はコ
ンクリート硬化時を示すものである。 1……コンクリート送入管 3……筒状受け台、 4a,4b……貫通孔 5……スリット 6……螺旋羽根
FIG. 1 is a plan view of a cylindrical pedestal showing an embodiment of the present invention, FIG. 2 is a front view of the same, FIG. 3 is a front view of a concrete inlet pipe, and FIG. 4 is a plan view of the same. FIG. 5 is a front view of the spiral blade, and FIGS. 6 to 14 are partial cross-sectional views showing the steps of in-situ casting using the device of the present invention. FIG. Fig. 8 is at the end of excavation, Fig. 8 is at the time of root consolidation, Fig. 9 is at the time of removing the auger rod,
The figure shows when the rebar cage is inserted, Fig. 11 shows when the concrete feed pipe is arranged, Fig. 12 shows when concrete is put in, Fig. 13 shows when the concrete feed pipe and spiral blade are removed, and Fig. 14 shows when concrete is hardened. It is shown. 1 ... Concrete inlet pipe 3 ... Cylindrical pedestal, 4a, 4b ... Through hole 5 ... Slit 6 ... Spiral blade

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】杭穴の上端に設置・固定されるようにする
と共に、貫通孔を有する上板及び下板を縦板で連結し
て、側方が開放した筒状受け台と、この筒状受け台の貫
通孔へ、上下方向に移動可能であって、回転方向で係止
するように嵌挿されるコンクリート送入管と、このコン
クリート送入管内に、回転可能に嵌挿される螺旋羽根と
からなり、前記コンクリート送入管に軸方向に沿った突
条を形成し、前記上板及び下板の少なくとも一方に、前
記突条を係合できる溝を設けたことを特徴とする現場打
ち杭用コンクリート打設装置
1. A cylindrical pedestal which is installed and fixed at the upper end of a pile hole and which has upper and lower plates having through holes connected to each other by a vertical plate to form a cylindrical pedestal whose side is open, and this cylindrical pedestal. A concrete feed pipe that is vertically movable into the through hole of the flat pedestal and is inserted so as to be locked in the rotation direction; and a spiral blade that is rotatably fitted in the concrete feed pipe. A cast-in-place pile, comprising a ridge formed along the axial direction on the concrete inlet pipe, and a groove for engaging the ridge provided on at least one of the upper plate and the lower plate. Concrete pouring equipment
JP1987090685U 1987-06-12 1987-06-12 Concrete pouring equipment for cast-in-place piles Expired - Lifetime JPH0621964Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1987090685U JPH0621964Y2 (en) 1987-06-12 1987-06-12 Concrete pouring equipment for cast-in-place piles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1987090685U JPH0621964Y2 (en) 1987-06-12 1987-06-12 Concrete pouring equipment for cast-in-place piles

Publications (2)

Publication Number Publication Date
JPS63198629U JPS63198629U (en) 1988-12-21
JPH0621964Y2 true JPH0621964Y2 (en) 1994-06-08

Family

ID=30950777

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1987090685U Expired - Lifetime JPH0621964Y2 (en) 1987-06-12 1987-06-12 Concrete pouring equipment for cast-in-place piles

Country Status (1)

Country Link
JP (1) JPH0621964Y2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5685772B2 (en) * 2010-08-30 2015-03-18 株式会社テノックス Sediment fall prevention device for construction of hydraulic solidification liquid replacement pile and construction method of hydraulic solidification liquid replacement pile

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60159219A (en) * 1984-01-31 1985-08-20 Ohbayashigumi Ltd Tremie tube handling device
JP2605635Y2 (en) * 1993-07-14 2000-07-31 株式会社ドクター製作所 Doctor blade

Also Published As

Publication number Publication date
JPS63198629U (en) 1988-12-21

Similar Documents

Publication Publication Date Title
JPH0621964Y2 (en) Concrete pouring equipment for cast-in-place piles
JPS584128B2 (en) Pile embedding method
JP2017089382A (en) Pile reinforcement structure constructing method and apparatus therefor
JP6603356B2 (en) Pile reinforcement structure construction method and apparatus
JPH0757947B2 (en) Cast-in-place pile construction method
JPS5924026A (en) Pile formation work
JPH1060879A (en) Building foundation and construction method thereof
JP4200237B2 (en) Construction method of foundation pile
JPH0280710A (en) Preparing cast-in-place concrete pile
JPS62178620A (en) Formation of improved angular ground
JP2004150070A (en) Treatment method for removed soil, and removed soil-treated construction method for foundation pile
JP6796343B2 (en) Construction method of pile reinforcement structure and its equipment
JP2836808B2 (en) Drill stirrer for soil cement pile method
JP7430103B2 (en) Ground improvement method for pile extraction holes
JPH0629509B2 (en) Construction method of field construction pile
JPH01131717A (en) Construction of in-situ pile
JPS6140815B2 (en)
JPH0627405B2 (en) Ready-made pile burying method
JPS61113925A (en) Rod for excavation of pile
JPS63171918A (en) Construction of pile on site
JPH0473491B2 (en)
JPH0324664Y2 (en)
JPS63284317A (en) Execution of cast-in-place pile
JPS59118922A (en) Method and apparatus for erection of pile
JPS63103121A (en) Field piling work