JP3126097B2 - Basic structure of two-stage parking device - Google Patents

Basic structure of two-stage parking device

Info

Publication number
JP3126097B2
JP3126097B2 JP07035243A JP3524395A JP3126097B2 JP 3126097 B2 JP3126097 B2 JP 3126097B2 JP 07035243 A JP07035243 A JP 07035243A JP 3524395 A JP3524395 A JP 3524395A JP 3126097 B2 JP3126097 B2 JP 3126097B2
Authority
JP
Japan
Prior art keywords
concrete
ground
base plate
anchor bolt
parking device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP07035243A
Other languages
Japanese (ja)
Other versions
JPH08226244A (en
Inventor
伸雄 神谷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Aisan Industry Co Ltd
Original Assignee
Aisan Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Aisan Industry Co Ltd filed Critical Aisan Industry Co Ltd
Priority to JP07035243A priority Critical patent/JP3126097B2/en
Publication of JPH08226244A publication Critical patent/JPH08226244A/en
Application granted granted Critical
Publication of JP3126097B2 publication Critical patent/JP3126097B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、二段駐車装置のベース
プレートに形成された複数のアンカボルト孔に挿通され
て同ベースプレートを固定する複数のアンカボルトが、
ベースプレートのアンカボルト孔に挿通される上端部を
除き埋設固着された二段駐車装置の基礎構造に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a plurality of anchor bolts which are inserted into a plurality of anchor bolt holes formed in a base plate of a two-stage parking device to fix the base plate.
The present invention relates to a basic structure of a two-stage parking device buried and fixed except for an upper end portion inserted into an anchor bolt hole of a base plate.

【0002】[0002]

【従来の技術】先ず、この種の基礎構造を介して地面上
に据え付けられる二段駐車装置の一例を図6及び図7に
より説明すれば、車両を搭載するパレット13は、ベー
スプレート10に立設した1対の支柱11により昇降可
能に案内支持されたアーム組立体12により支持され
て、モータ(図示省略)により昇降される。これによ
り、上昇したパレット13下側の空間にも別の車両を駐
車することができるようになっている。支柱11は、使
用状態では、カバー15により覆われている。
2. Description of the Related Art First, an example of a two-stage parking device installed on the ground through such a basic structure will be described with reference to FIGS. 6 and 7. The pallet 13 for mounting a vehicle is mounted on a base plate 10 upright. It is supported by an arm assembly 12 that is guided and supported by a pair of columns 11 so as to be able to move up and down, and is moved up and down by a motor (not shown). Thus, another vehicle can be parked in the space below the raised pallet 13. The support 11 is covered with a cover 15 in a use state.

【0003】このような二段駐車装置は、基礎1のコン
クリート2に埋設固着した4本のアンカボルト6のコン
クリート2から上方に突出する上端部にベースプレート
10に形成した4個のアンカボルト孔14a,14b,
14cを挿通し、ナットにより締め付けることにより据
え付けられる。
[0003] Such a two-stage parking device comprises four anchor bolt holes 14a formed in a base plate 10 at the upper end of four anchor bolts 6 embedded and fixed in the concrete 2 of the foundation 1 and projecting upward from the concrete 2. , 14b,
14c is inserted and fastened with a nut.

【0004】従来のこのような基礎1は、図8及び図9
に示すように、地面Gを所定深さまで掘り、割栗石を敷
いて突き固めて形成した砕石層4上に、アンカボルト6
の埋設深さよりも厚いコンクリート2を打つことにより
形成している。このコンクリート2は格子状に配置して
交差部を針金により結束した異形鉄筋3を厚さ方向中間
部に埋設して全面的に補強している。鉄筋3はアンカボ
ルト6を設ける各ボルト設置位置5a,5b,5cを避
けて配置し、この各位置にボルト埋設孔を形成してアン
カボルト6を埋設固定している。例えば図6に示すよう
に、コンクリート2の大きさは、幅がパレット13とほ
ゞ同じで長さがベースプレート10の幅よりやや大であ
るが、長さはパレット13とほゞ同じとしてもよい。な
おアンカボルト6としてはストライクアンカボルト及び
ケミカルアンカボルト(何れも詳細は後述)を使用し、
コンクリート2は必要により型枠を用いて施工する。
[0004] Such a conventional foundation 1 is shown in Figs.
As shown in the figure, the ground G is dug to a predetermined depth, and the anchor bolt 6
Is formed by hitting concrete 2 which is thicker than the burial depth. The concrete 2 has a deformed reinforcing bar 3 which is arranged in a lattice and whose intersection is bound by a wire, is buried in a middle portion in the thickness direction, and is entirely reinforced. The reinforcing bar 3 is arranged so as to avoid the bolt installation positions 5a, 5b, 5c where the anchor bolts 6 are provided, and a bolt burying hole is formed at each of these positions to fix the anchor bolt 6 in place. For example, as shown in FIG. 6, the size of the concrete 2 is almost the same as the pallet 13 and the length is slightly larger than the width of the base plate 10, but the length may be almost the same as the pallet 13. . As the anchor bolt 6, a strike anchor bolt and a chemical anchor bolt (both will be described in detail later) are used.
Concrete 2 is installed using a formwork as needed.

【0005】[0005]

【発明が解決しようとする課題】上記従来技術の基礎
は、コンクリート全体をアンカボルトの埋設深さよりも
厚くして全面的に鉄筋3により補強しているので、補強
を設ける基礎工事面積が大きくなると共にコンクリート
及び補強鉄筋の量が多くなり、従って基礎工事に要する
コストが大になるという問題があった。本発明は必要な
強度を確保しながら補強を設ける基礎工事面積を少なく
して、基礎工事に要するコストを低下させることを目的
とする。
In the foundation of the prior art described above, the entire concrete is thicker than the anchor bolt burying depth and is entirely reinforced by the reinforcing bar 3, so that the foundation work area for providing the reinforcement is large. At the same time, there is a problem in that the amount of concrete and reinforcing steel bars increases, and thus the cost required for foundation work increases. SUMMARY OF THE INVENTION An object of the present invention is to reduce the area required for foundation work by reducing the foundation work area where reinforcement is provided while securing necessary strength.

【0006】[0006]

【課題を解決するための手段】このために、本発明によ
る二段駐車装置の基礎構造は、二段駐車装置のベースプ
レートより広い範囲にわたり地面上に設けられて補強用
鉄筋を有しないコンクリート層と、ベースプレートの各
アンカボルト孔に対応する各ボルト設置位置付近を中心
として地面中に埋設され上端部がコンクリート層と連結
された複数のコンクリート短柱と、各ボルト設置位置付
近を中心としてほゞ対称的にかつほゞ垂直に配置され各
下部が地面中に打ち込まれると共にこの下部を除く各上
部がコンクリート短柱と一体的に結合された複数の垂直
鉄筋と、各ボルト設置位置付近を中心としてほゞ対称的
にかつ下方が広がる八字状に配置され各下部が地面中に
打ち込まれると共にこの下部を除く各上部がコンクリー
ト短柱と一体的に結合された複数の傾斜鉄筋と、各コン
クリート短柱の中心部となる各ボルト設置位置に埋設固
着されて上端部がコンクリート短柱の上面から突出する
複数のアンカボルトを備えたことを特徴とするものであ
る。
To this end, the basic structure of the two-stage parking device according to the present invention comprises a concrete layer provided on the ground over a wider area than the base plate of the two-stage parking device and having no reinforcing steel. , Multiple concrete short pillars buried in the ground centered around each bolt installation position corresponding to each anchor bolt hole of the base plate and connected to the concrete layer at the top, and almost symmetrical around each bolt installation position A plurality of vertical reinforcing bars that are arranged vertically and almost vertically, each lower part is driven into the ground, and each upper part excluding the lower part is integrally connected to the concrete short pillar, and around the bolt installation position.配置 The lower part is driven into the ground symmetrically and the lower part spreads out and each lower part is driven into the ground and each upper part except this lower part is integrated with the concrete short pillar It is characterized in that it comprises a plurality of combined inclined rebars and a plurality of anchor bolts buried and fixed at each bolt installation position which is the center of each concrete short column and whose upper end protrudes from the upper surface of the concrete short column. Things.

【0007】[0007]

【作用】地面中に埋設されて上端部がコンクリート層と
連結されたコンクリート短柱の中心部には各アンカボル
トが埋設固着され、その上端部はコンクリート短柱の上
面から突出される。二段駐車装置のベースプレートは、
この上端部に各アンカボルト孔が挿通されて固定され
る。各コンクリート短柱は地面中に埋設されるだけでな
く、上部がそれぞれ各コンクリート短柱23に一体的に
結合された各複数の垂直鉄筋及び傾斜鉄筋は下部が地面
中に打ち込まれて地面に対する結合強度が補強されるの
で、各コンクリート短柱の地面に対する結合強度は充分
大となる。
The anchor bolts are buried and fixed at the center of the concrete short pillar buried in the ground and the upper end is connected to the concrete layer, and the upper end protrudes from the upper surface of the concrete short pillar. The base plate of the two-stage parking device is
Each anchor bolt hole is inserted through this upper end and fixed. Each concrete short pillar is not only buried in the ground, but also a plurality of vertical reinforcing bars and inclined reinforcing bars whose upper parts are integrally connected to the respective concrete short pillars 23 are connected to the ground by driving the lower part into the ground. Since the strength is reinforced, the bonding strength of each short concrete column to the ground is sufficiently large.

【0008】[0008]

【実施例】以下に図1〜図5に示す実施例により本発明
による二段駐車装置の基礎構造の説明をする。本発明に
より据え付けられる二段駐車装置は、先に従来技術と関
連して述べた、図6及び図7に示すものと同じである。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The basic structure of a two-stage parking device according to the present invention will be described below with reference to the embodiments shown in FIGS. The two-stage parking device installed according to the present invention is the same as that shown in FIGS. 6 and 7 described above in connection with the prior art.

【0009】図1及び図2に示すように、本実施例の基
礎20の構造は、従来よりも薄いコンクリート層21
と、後述するアンカボルト31,36を埋設固着する4
個のコンクリート短柱23よりなっている。コンクリー
ト層21はアンカボルト31,36の埋設深さよりも肉
厚が薄く補強用鉄筋を有しないものであり、二段駐車装
置のベースプレート10よりも広い範囲にわたって設け
られる。本実施例のコンクリート層21は、幅はパレッ
ト13の幅とほゞ同じで、長さはベースプレート10の
幅の約2倍としたが、幅はこれと同じで長さをパレット
13とほゞ同じとし、あるいは更に広い範囲にわたりコ
ンクリート層21を設けてもよい。このコンクリート層
21は砕石層22上に設けられる。
As shown in FIGS. 1 and 2, the structure of the foundation 20 of the present embodiment has a concrete layer 21 which is thinner than the conventional one.
4 for burying and fixing anchor bolts 31 and 36 described later.
It is made up of individual concrete short columns 23. The concrete layer 21 has a smaller thickness than the anchor bolts 31 and 36 and has no reinforcing steel, and is provided over a wider range than the base plate 10 of the two-stage parking device. Although the width of the concrete layer 21 of this embodiment is substantially the same as the width of the pallet 13 and the length thereof is about twice the width of the base plate 10, the width is the same and the length is almost the same as that of the pallet 13. The same or a wider concrete layer 21 may be provided. The concrete layer 21 is provided on the crushed stone layer 22.

【0010】各コンクリート短柱23は二段駐車装置の
ベースプレート10に設けた各アンカボルト孔14a,
14b,14c(図7参照)に対応する各ボルト設置位
置29a,29b,29c付近を中心として地面G中に
埋設されており、各上端部はコンクリート層21と連結
されている。各コンクリート短柱23は地面G中に埋設
される下部を太くした略円柱状で、それぞれ各4本の垂
直鉄筋24及び傾斜鉄筋25の上半部が一体的に埋設固
着されている。各垂直鉄筋24は、コンクリート短柱2
3の中心となる各ボルト設置位置29a,29b,29
c付近を中心としてほゞ対称的にかつほゞ垂直に配置さ
れ、コンクリート短柱23から突出する各下半部は地面
G中に打ち込まれている。各傾斜鉄筋25は、上端が各
垂直鉄筋24の上端に針金26により結束されて下方外
向きに延びる点を除き、垂直鉄筋24と同様、上半部が
コンクリート短柱23に一体的に結合され、コンクリー
ト短柱23から突出する各下半部は地面G中に打ち込ま
れている。各鉄筋24,25はコンクリート短柱23の
中心部を除く周辺部内にあり、またコンクリート短柱2
3から上方には突出していない。
Each concrete short pillar 23 is provided with an anchor bolt hole 14a, provided in the base plate 10 of the two-stage parking device.
The bolts are buried in the ground G around the bolt installation positions 29a, 29b, and 29c corresponding to the bolts 14b and 14c (see FIG. 7), and each upper end is connected to the concrete layer 21. Each concrete short pillar 23 has a substantially cylindrical shape with a thicker lower portion embedded in the ground G, and upper halves of four vertical reinforcing bars 24 and inclined reinforcing bars 25 are integrally embedded and fixed. Each vertical reinforcing bar 24 is a concrete short column 2
3 bolt installation positions 29a, 29b, 29 at the center of 3
Each lower half protruding from the concrete short pillar 23 is driven into the ground G substantially symmetrically and substantially vertically around the vicinity of c. The upper half of each inclined rebar 25 is integrally connected to the concrete short column 23 similarly to the vertical rebar 24 except that the upper end is bound to the upper end of each vertical rebar 24 by a wire 26 and extends downward and outward. The respective lower halves projecting from the concrete short columns 23 are driven into the ground G. Reinforcing bars 24 and 25 are located in the periphery of concrete short pillar 23 except for the center, and concrete short pillar 2
3 does not protrude upward.

【0011】各コンクリート短柱23の中心部となる各
ボルト設置位置29a,29b,29cには、各1本の
アンカボルト31,36が埋設固着され、各上端部はコ
ンクリート短柱23の上面から突出している。ベースプ
レート10の各アンカボルト孔のうち中央に位置するア
ンカボルト孔14aに対応するコンクリート短柱23中
心のボルト設置位置29aには、位置決めの目的で引き
抜き強度が弱いストライクアンカボルト31が設置さ
れ、その他のアンカボルト孔14b,14cに対応する
コンクリート短柱23中心のボルト設置位置29b,2
9cには、引き抜き強度が強いケミカルアンカボルト3
6が設置される。
One anchor bolt 31, 36 is embedded and fixed at each bolt installation position 29 a, 29 b, 29 c which is the center of each concrete short column 23. It is protruding. A strike anchor bolt 31 having a weak pull-out strength for positioning purpose is installed at a bolt installation position 29a at the center of the concrete short pillar 23 corresponding to the anchor bolt hole 14a located at the center among the anchor bolt holes 14a of the base plate 10. Bolt installation position 29b, 2 at the center of concrete short column 23 corresponding to anchor bolt holes 14b, 14c
9c is a chemical anchor bolt 3 with strong pull-out strength.
6 is installed.

【0012】次に上記実施例の二段駐車装置の基礎構造
の具体的施工工程を、図1〜図5により説明する。先ず
地面Gを従来よりも浅い所定深さまで掘り、その底に割
栗石を敷き突き固めて砕石層22を形成する。この砕石
層22上に型枠を設け、その中にセメントと砂を配合し
骨材として砂利を加えて水で練ったコンクリートを流し
込み、硬化を待って型枠を外して、コンクリート層21
を形成する。コンクリート層21は比較的薄く60〜8
0mm程度であり、鉄筋を設けないので、この施工はきわ
めて簡単である。この状態ではコンクリート短柱23は
設けられていない。またコンクリート層21は厚さ60
mm以上の既設のコンクリート層があれば、それを利用し
てもよい。
Next, the concrete construction steps of the basic structure of the two-stage parking device of the above embodiment will be described with reference to FIGS. First, the ground G is dug to a predetermined depth shallower than in the past, and crushed stone is laid on the bottom thereof and crushed to form a crushed stone layer 22. A formwork is provided on the crushed stone layer 22, cement and sand are mixed therein, gravel is added as an aggregate, and concrete kneaded with water is poured. After the concrete is hardened, the formwork is removed and the concrete layer 21 is removed.
To form The concrete layer 21 is relatively thin, 60 to 8
This construction is extremely simple because it is about 0 mm and no reinforcing bars are provided. In this state, the concrete short columns 23 are not provided. The concrete layer 21 has a thickness of 60
If there is an existing concrete layer of mm or more, it may be used.

【0013】次にアンカボルト孔14a,14b,14
cに合わせたテンプレートを用いて、チョークなどによ
りこのコンクリート層21上に4つのボルト設置位置2
9a,29b,29cをけがき、各設置位置を中心とし
てコンクリート短柱23のための4つの堀削孔27の上
部開口27aに相当する円をけがく。そして図3(a)に
示すように、はつり工具によりコンクリート層21に上
部開口27aを明け、小スコップにより砕石層22及び
地面Gを堀削して短柱形成孔27を形成し、底に左官砂
を敷き突き固めて砂層28を形成する。本実施例では、
短柱形成孔27の上部開口27aの直径は200mm、深
さはコンクリート層21表面から250mm、短柱形成孔
27の下部27bは上部開口27aよりも太くその直径
は300mmである。
Next, anchor bolt holes 14a, 14b, 14
The four bolt installation positions 2 on this concrete layer 21 by using a template matched to
9a, 29b, and 29c are scribed, and circles corresponding to the upper openings 27a of the four excavation holes 27 for the concrete short columns 23 are scribed centering on each installation position. Then, as shown in FIG. 3 (a), an upper opening 27a is opened in the concrete layer 21 with a hanging tool, and the crushed stone layer 22 and the ground G are excavated with a small scoop to form a short column forming hole 27. Sand is laid and squeezed to form a sand layer 28. In this embodiment,
The diameter of the upper opening 27a of the short column forming hole 27 is 200 mm, the depth is 250 mm from the surface of the concrete layer 21, and the lower portion 27b of the short column forming hole 27 is thicker than the upper opening 27a and has a diameter of 300 mm.

【0014】次いで図3(b)に示すように、円周方向に
延びる多数の凹凸を外周面に形成した直径が10mmで長
さが550mmの4本の棒状の異形鉄筋24を、ボルト設
置位置29a,29b,29cを中心として点対称にか
つ垂直に配置して、ハンマーにより異形鉄筋24の下部
を短柱形成孔27の底面の地面G中に打ち込む。また同
一形状寸法の4本の傾斜異形鉄筋25を、垂直異形鉄筋
24の上端部から外向き斜め下方に向けて、同様に地面
G中に打ち込む。両鉄筋24,25は、何れも上端がコ
ンクリート層21の上面から10mm下がった位置となる
まで打ち込まれ、両上端部は多少交差されて針金26に
より結束される。
Next, as shown in FIG. 3 (b), four rod-shaped deformed reinforcing bars 24 each having a diameter of 10 mm and a length of 550 mm having a large number of irregularities extending in the circumferential direction formed on the outer peripheral surface are attached to the bolt installation position. The lower portion of the deformed reinforcing bar 24 is hammered into the ground G on the bottom surface of the short column forming hole 27 by arranging it vertically and symmetrically with respect to the centers 29a, 29b and 29c. In addition, four inclined deformed reinforcing bars 25 having the same shape and size are similarly driven into the ground G outward and diagonally downward from the upper end of the vertical deformed reinforcing bar 24. Both rebars 24 and 25 are driven in until the upper ends thereof are located 10 mm below the upper surface of the concrete layer 21, and the upper ends are slightly crossed and bound by wires 26.

【0015】次いで図3(c) に示すように、各短柱形成
孔27内に普通ポルトランドセメントと左官砂を配合し
て水で練ったモルタルが短柱形成孔27内に流し込まれ
る。養生期間(例えば夏場で5日間、冬場で7日間)が
経過して完全に硬化すれば、上端部がコンクリート層2
1と連結され、下半部が地面G中に打ち込まれた各4本
の垂直異形鉄筋24及び傾斜異形鉄筋25の下半部を除
く上半部が一体的に結合されたコンクリート短柱23が
得られる。このように各コンクリート短柱23は下部を
太くして地面G中に埋設されるだけでなく、各上部が各
コンクリート短柱23に一体的に結合された各複数の垂
直鉄筋24及び傾斜鉄筋25は下部が地面G中に打ち込
まれて地面Gに対する結合強度が補強されるので、各コ
ンクリート短柱23の地面Gに対する結合強度は充分大
となる。
Next, as shown in FIG. 3 (c), mortar obtained by mixing ordinary Portland cement and plaster sand and mixing with water is poured into each short column forming hole 27. After the curing period (for example, 5 days in summer and 7 days in winter) elapses, the upper end portion becomes concrete layer 2
The concrete short pillar 23 is connected to 1 and has an upper half except for the lower half of the four vertically deformed reinforcing bars 24 and the inclined deformed reinforcing bars 25 whose lower half is driven into the ground G. can get. As described above, each concrete short pillar 23 is not only buried in the ground G with a thick bottom, but also each of the plurality of vertical reinforcing bars 24 and the inclined reinforcing bars 25 whose upper portions are integrally connected to each concrete short pillar 23. Since the lower part is driven into the ground G to reinforce the bonding strength to the ground G, the bonding strength of each short concrete pillar 23 to the ground G is sufficiently large.

【0016】次に各コンクリート短柱23の中央に固定
するアンカボルト31,36及びその埋設工程を図4及
び図5により説明する。先ず、二段駐車装置のベースプ
レート10をコンクリート層21及びコンクリート短柱
23上に載せ、各アンカボルト孔14a,14b,14
cと各コンクリート短柱23の中心のボルト設置位置2
9a,29b,29cが一致するように位置決めする。
Next, the anchor bolts 31 and 36 fixed to the center of each concrete short column 23 and the embedding process thereof will be described with reference to FIGS. First, the base plate 10 of the two-stage parking device is placed on the concrete layer 21 and the concrete short columns 23, and the respective anchor bolt holes 14a, 14b, 14
c and the bolt installation position 2 at the center of each concrete short column 23
Positioning is performed so that 9a, 29b and 29c coincide.

【0017】ベースプレート10中央のアンカボルト孔
14aに対応するストライクアンカボルト31をケミカ
ルアンカボルト36よりも先に設置するので、その埋設
工程を図4により説明する。ストライクアンカボルト3
1は、図3の(b) 及び(c) に示すように、同軸的に設け
たピン32を備えており、これ打ち込めば軸方向スリッ
トにより複数に分割されたストライクアンカボルト31
の先端部31aがピン32の先端部32aにより押し開
かれるものであり、ストライクアンカボルト31の先端
部31aの外周には円周方向の凹凸が設けられている。
先ず図4(a) に示すように、ドリルによりコンクリート
短柱23の中心にアンカボルト孔14aと同心に所定の
ボルト埋設孔30(本実施例では直径17mm、深さ90
mm)を穿孔し、金属ブラシで切り粉を落とし、ブロワで
切り粉を完全に除去する。
Since the strike anchor bolt 31 corresponding to the anchor bolt hole 14a at the center of the base plate 10 is installed before the chemical anchor bolt 36, the embedding process thereof will be described with reference to FIG. Strike anchor bolt 3
As shown in FIGS. 3 (b) and 3 (c), 1 has a pin 32 provided coaxially, and when it is driven in, a strike anchor bolt 31 divided into a plurality of parts by an axial slit.
Is opened by the tip 32a of the pin 32, and the outer periphery of the tip 31a of the strike anchor bolt 31 is provided with circumferential irregularities.
First, as shown in FIG. 4 (a), a predetermined bolt burial hole 30 (in this embodiment, a diameter of 17 mm and a depth of 90 mm) is drilled at the center of the concrete short column 23 concentrically with the anchor bolt hole 14a.
mm), remove the chips with a metal brush, and completely remove the chips with a blower.

【0018】次いで図4(b) に示すように、所定位置に
ナット33とワッシャ33aを螺合したストライクアン
カボルト31を、その先端部31aがボルト埋設孔30
内の所定の深さに達するよう、ベースプレート10のア
ンカボルト孔14aを通して挿入する。そしてピン32
の上端をハンマ34により打ち込めば、図3(c) に示す
ように、ストライクアンカボルト31は先端部31aが
開いてボルト埋設孔30内面に係合されて固着される。
この状態でナット33を締め付けてベースプレート10
が動かない程度に固定する。本実施例のストライクアン
カボルト31は外径が16mm、長さが150mmで、ベー
スプレート10上面からの突出量は25mmである。
Next, as shown in FIG. 4 (b), a strike anchor bolt 31 in which a nut 33 and a washer 33a are screwed into a predetermined position, and a tip portion 31a of which has a bolt burying hole 30a.
Is inserted through the anchor bolt hole 14a of the base plate 10 so as to reach a predetermined depth. And pin 32
When the upper end of the strike anchor 34 is driven in with the hammer 34, the strike anchor bolt 31 is opened and the front end 31a is opened and engaged with the inner surface of the bolt buried hole 30, as shown in FIG. 3 (c).
In this state, the nut 33 is tightened and the base plate 10
So that it does not move. The strike anchor bolt 31 of this embodiment has an outer diameter of 16 mm, a length of 150 mm, and an amount of protrusion from the upper surface of the base plate 10 of 25 mm.

【0019】次に3本のケミカルアンカボルト36の埋
設工程を図5により説明する。通常のスタッドボルトで
あるケミカルアンカボルト36を固着するアンカカプセ
ル37は、複数のくびれを外周面に形成したガラスのカ
プセル内に未硬化のエポキシアクリレート樹脂等の接着
剤を封入し、外側のくびれ部内に硬化剤を設けたもので
ある。先ず図5(a) に示すように、ドリルによりコンク
リート短柱23中心にアンカボルト孔14b,14cと
同心に所定のボルト埋設孔35(直径19mm、深さ14
0mm)を穿孔し、ストライクアンカボルト31の場合と
同様、切り粉を完全に除去する。
Next, the step of embedding the three chemical anchor bolts 36 will be described with reference to FIG. An anchor capsule 37 for fixing a chemical anchor bolt 36, which is a normal stud bolt, encloses an adhesive such as an uncured epoxy acrylate resin in a glass capsule having a plurality of constrictions formed on an outer peripheral surface, and forms an inner constricted portion. Is provided with a curing agent. First, as shown in FIG. 5 (a), a predetermined bolt embedding hole 35 (diameter 19 mm, depth 14 mm) is drilled concentrically with the anchor bolt holes 14b and 14c in the center of the concrete short column 23 by drilling.
0 mm), and chips are completely removed as in the case of the strike anchor bolt 31.

【0020】次いで図5(b) に示すように、ボルト埋設
孔35内にアンカカプセル37(直径16.5mm、長さ
120mm)を挿入し、図5(c) に示すようにストッパ3
8を嵌挿したケミカルアンカボルト36をアンカボルト
孔14bから挿入して、ハンマ39により打ち込む。こ
れによりアンカカプセル37のガラスが砕けて接着剤と
硬化剤と砕けたガラス細片は混合され、その混合物37
Aは図3(d) に示すように、ボルト埋設孔35とケミカ
ルアンカボルト36の間に充填される。所定の養生時間
(例えば0℃では160分、30℃では20分)が経過
すれば混合物37Aが硬化してケミカルアンカボルト3
6はコンクリート短柱23に埋設固着される。この状態
でナット33を締め付けてベースプレート10をしっか
りと固定する。ボルト設置位置29bに設けるケミカル
アンカボルト36は外径が16mm、長さが200mmで、
ベースプレート10上面からの突出量は25mmである。
ベースプレート10の先端となるアンカボルト孔14c
は図5(a) の二点鎖線に示すように座ぐりが設けられ、
このボルト設置位置29cに設けるケミカルアンカボル
ト36は外径が16mm、長さが175mmで、その先端は
ベースプレート10の上面とほゞ同じ高さである。
Next, as shown in FIG. 5B, an anchor capsule 37 (16.5 mm in diameter and 120 mm in length) is inserted into the bolt buried hole 35, and the stopper 3 is inserted as shown in FIG. 5C.
The chemical anchor bolt 36 into which 8 is inserted is inserted from the anchor bolt hole 14b and is driven in with the hammer 39. Thereby, the glass of the anchor capsule 37 is crushed, and the crushed glass flakes are mixed with the adhesive, the hardener and the mixture 37.
A is filled between the bolt burial hole 35 and the chemical anchor bolt 36 as shown in FIG. After a predetermined curing time (for example, 160 minutes at 0 ° C. and 20 minutes at 30 ° C.), the mixture 37A hardens and the chemical anchor bolt 3
6 is embedded and fixed to the short concrete pillar 23. In this state, the nut 33 is tightened to firmly fix the base plate 10. The chemical anchor bolt 36 provided at the bolt installation position 29b has an outer diameter of 16 mm and a length of 200 mm.
The protrusion amount from the upper surface of the base plate 10 is 25 mm.
Anchor bolt hole 14c serving as a tip of base plate 10
Is provided with a spot facing as shown by a two-dot chain line in FIG.
The chemical anchor bolt 36 provided at the bolt installation position 29c has an outer diameter of 16 mm and a length of 175 mm, and its tip is almost the same height as the upper surface of the base plate 10.

【0021】以上により各アンカボルト31,36は、
各コンクリート短柱23の中心部となる各ボルト設置位
置29a,29b,29cに埋設固着されて、各上端部
はコンクリート短柱23の上面から突出される。ベース
プレート10の先端となるボルト設置位置29cを除く
ボルト設置位置29a及び29bのアンカボルト31,
36の上端は、二段駐車装置の支柱11を覆うカバー1
5内に位置している。
As described above, each of the anchor bolts 31 and 36 is
The concrete short pillars 23 are buried and fixed at the respective bolt installation positions 29a, 29b, 29c, which are central portions thereof, and the respective upper ends protrude from the upper surface of the concrete short pillars 23. The anchor bolts 31 at the bolt installation positions 29a and 29b except for the bolt installation position 29c which is the tip of the base plate 10,
The upper end of the cover 36 covers the support 11 of the two-stage parking device.
5 is located within.

【0022】[0022]

【発明の効果】上述のように、本発明によれば、補強を
設ける基礎工事はアンカボルトを埋設する各コンクリー
ト短柱付近だけであるので、このような基礎工事の面積
が減少すると共にコンクリート及び補強鉄筋の使用量が
少なくなり、従って基礎工事に要するコストを低下させ
ることができる。しかも、各コンクリート短柱は垂直鉄
筋及び傾斜鉄筋により地面に対する必要な結合強度が確
保されるので、ベースプレートの取付強度が低下するこ
とはない。
As described above, according to the present invention, since the foundation work for providing reinforcement is only near each concrete short column in which anchor bolts are buried, the area of such foundation work is reduced and concrete and The amount of reinforcing steel used is reduced, so that the cost required for foundation work can be reduced. In addition, since each concrete short pillar has a required bonding strength to the ground by the vertical reinforcing bars and the inclined reinforcing bars, the mounting strength of the base plate does not decrease.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明による二段駐車装置の基礎構造の一実
施例を示す全体平面図である。
FIG. 1 is an overall plan view showing an embodiment of a basic structure of a two-stage parking device according to the present invention.

【図2】 図1の2−2断面図である。FIG. 2 is a sectional view taken along line 2-2 of FIG.

【図3】 図1に示す実施例のコンクリート短柱及びそ
の補強の施工工程の説明図である。
FIG. 3 is an explanatory view of a concrete short pillar of the embodiment shown in FIG. 1 and a construction process of its reinforcement.

【図4】 ストライクアンカボルトの施工工程の説明図
である。
FIG. 4 is an explanatory view of a construction process of a strike anchor bolt.

【図5】 ケミカルアンカボルトの施工工程の説明図で
ある。
FIG. 5 is an explanatory view of a process for installing a chemical anchor bolt.

【図6】 本発明により据え付けられる二段駐車装置の
一例の全体斜視図である。
FIG. 6 is an overall perspective view of an example of a two-stage parking device installed according to the present invention.

【図7】 図6に示す二段駐車装置のベースプレートの
平面図である。
FIG. 7 is a plan view of a base plate of the two-stage parking device shown in FIG.

【図8】 従来技術による二段駐車装置の基礎構造の一
例を示す全体平面図である。
FIG. 8 is an overall plan view showing an example of a basic structure of a two-stage parking device according to the related art.

【図9】 図8に示す基礎構造の横断面図である。9 is a cross-sectional view of the basic structure shown in FIG.

【符号の説明】[Explanation of symbols]

10…ベースプレート、14a,14b,14c…アン
カボルト孔、21…コンクリート層、23…コンクリー
ト短柱、24…垂直鉄筋、25…傾斜鉄筋、29a,2
9b,29c…ボルト設置位置、31,36…アンカボ
ルト、G…地面。
DESCRIPTION OF SYMBOLS 10 ... Base plate, 14a, 14b, 14c ... Anchor bolt hole, 21 ... Concrete layer, 23 ... Concrete short column, 24 ... Vertical rebar, 25 ... Inclined rebar, 29a, 2
9b, 29c: bolt installation position, 31, 36: anchor bolt, G: ground.

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 二段駐車装置のベースプレートを固定す
る複数のアンカボルトが前記ベースプレートに形成され
たアンカボルト孔に挿通される上端部を除き埋設固着さ
れた二段駐車装置の基礎構造において、前記ベースプレ
ートより広い範囲にわたり地面上に設けられて補強用鉄
筋を有しないコンクリート層と、前記各アンカボルト孔
に対応する各ボルト設置位置付近を中心として前記地面
中に埋設され上端部が前記コンクリート層と連結された
複数のコンクリート短柱と、前記各ボルト設置位置付近
を中心としてほゞ対称的にかつほゞ垂直に配置され各下
部が前記地面中に打ち込まれると共にこの下部を除く各
上部が前記コンクリート短柱と一体的に結合された複数
の垂直鉄筋と、前記各ボルト設置位置付近を中心として
ほゞ対称的にかつ下方が広がる八字状に配置され各下部
が前記地面中に打ち込まれると共にこの下部を除く各上
部が前記コンクリート短柱と一体的に結合された複数の
傾斜鉄筋と、前記各コンクリート短柱の中心部となる前
記各ボルト設置位置に埋設固着されて上端部が同コンク
リート短柱の上面から突出する複数のアンカボルトを備
えたことを特徴とする二段駐車装置の基礎構造。
1. The basic structure of a two-stage parking device, wherein a plurality of anchor bolts for fixing a base plate of the two-stage parking device are buried and fixed except for an upper end portion inserted into an anchor bolt hole formed in the base plate. A concrete layer provided on the ground over a wider area than the base plate and having no reinforcing steel, and an upper end buried in the ground around the vicinity of each bolt installation position corresponding to each anchor bolt hole, and an upper end portion is formed of the concrete layer. A plurality of short concrete pillars connected to each other, and each of the lower parts are driven into the ground while being arranged substantially symmetrically and substantially vertically about the vicinity of each of the bolt installation positions, and each upper part excluding this lower part is made of the concrete. A plurality of vertical reinforcing bars integrally connected to the short pillars; A plurality of inclined rebars each of which is arranged in an eight-letter shape and whose lower part is driven into the ground and whose upper part excluding this lower part is integrally connected to the concrete short pillar, and a central part of each concrete short pillar And a plurality of anchor bolts buried and fixed at the respective bolt installation positions and having upper ends protruding from the upper surface of the concrete short pillar.
JP07035243A 1995-02-23 1995-02-23 Basic structure of two-stage parking device Expired - Fee Related JP3126097B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP07035243A JP3126097B2 (en) 1995-02-23 1995-02-23 Basic structure of two-stage parking device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP07035243A JP3126097B2 (en) 1995-02-23 1995-02-23 Basic structure of two-stage parking device

Publications (2)

Publication Number Publication Date
JPH08226244A JPH08226244A (en) 1996-09-03
JP3126097B2 true JP3126097B2 (en) 2001-01-22

Family

ID=12436404

Family Applications (1)

Application Number Title Priority Date Filing Date
JP07035243A Expired - Fee Related JP3126097B2 (en) 1995-02-23 1995-02-23 Basic structure of two-stage parking device

Country Status (1)

Country Link
JP (1) JP3126097B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101492138B1 (en) * 2014-01-07 2015-02-10 민덕주 Single column type double-stage parking machine

Also Published As

Publication number Publication date
JPH08226244A (en) 1996-09-03

Similar Documents

Publication Publication Date Title
JP3126097B2 (en) Basic structure of two-stage parking device
JP4420697B2 (en) Standing structure of steel pipe columns
JP3671344B2 (en) Joint structure between foundation pile and column base and its construction method
JP3889497B2 (en) Molding method for concrete basement
JP3029343U (en) Form tool for mortar material injection in exposed elastic fixed column base method
JP2588990B2 (en) Concrete formwork
JP3445017B2 (en) Machine foundation and its construction method
JPH08189041A (en) Unit anchor and shape-steel footing beam
JP2833764B2 (en) Pillar fixing method for steel columns
JPH1113067A (en) Burying construction method for supplementary stud in reverse concreting construction method
JPH08144581A (en) Foundation structure for fence
JP2002088775A (en) Foundation structure equipped with anchor bolt and method for constructing the same
KR200224744Y1 (en) Concrete base device for support
JP3678695B2 (en) Fixing method of column to concrete foundation
JPH0689588B2 (en) Installation method of handrails to attached buildings such as balconies and balconies
JP2650449B2 (en) Gate construction method
JP2579944Y2 (en) Load-bearing wall assembly structure
JP3629684B2 (en) Sound insulation wall foundation block
JPH0376929A (en) Steel-framed foundation
JPH0522576Y2 (en)
JPH06330529A (en) Mounting method of cast-in-place concrete strip footing and precast concrete wall slab
JP2891107B2 (en) SRC column base anchoring structure
JP2517735Y2 (en) Precast concrete foundation
JP3138982B2 (en) Building with mixed structure and its construction method
JPH01163320A (en) Method and apparatus for fixing anchor bolt

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20001003

LAPS Cancellation because of no payment of annual fees