JP2952836B2 - Construction method of building - Google Patents

Construction method of building

Info

Publication number
JP2952836B2
JP2952836B2 JP20211791A JP20211791A JP2952836B2 JP 2952836 B2 JP2952836 B2 JP 2952836B2 JP 20211791 A JP20211791 A JP 20211791A JP 20211791 A JP20211791 A JP 20211791A JP 2952836 B2 JP2952836 B2 JP 2952836B2
Authority
JP
Japan
Prior art keywords
artificial ground
structures
constructed
temporary gantry
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP20211791A
Other languages
Japanese (ja)
Other versions
JPH055367A (en
Inventor
英男 下村
顕二郎 秋山
伊知郎 草間
武紀 熊谷
陽児 諸井
修司 奥田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP20211791A priority Critical patent/JP2952836B2/en
Publication of JPH055367A publication Critical patent/JPH055367A/en
Application granted granted Critical
Publication of JP2952836B2 publication Critical patent/JP2952836B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は既存構造物の上方に建築
物を施工するための方法に関する。
BACKGROUND OF THE INVENTION The present invention relates to a method for constructing a building above an existing structure.

【0002】[0002]

【従来の技術】近年、地上に設けられている既存の構造
物、たとえば建築物、道路、鉄道の線路や駅舎等、の上
方空間の有効利用を図るべく、それら構造物をまたぐ形
態の大規模な高層建築物を設けることが検討されてい
る。従来、そのような建築物を設けるには、既存構造物
を仮設の養生床により覆ったうえで、既存構造物の周囲
に配したクレーンなどの建設機械を用いて既存構造物の
上方に新たな建築物の躯体を施工する、という工法を採
用することが一般的である。
2. Description of the Related Art In recent years, in order to effectively utilize the space above existing structures provided on the ground, for example, buildings, roads, railroad tracks, station buildings, and the like, large-scale structures spanning those structures have been proposed. It is being studied to provide a high-rise building. Conventionally, to provide such a building, an existing structure is covered with a temporary curing floor, and a new crane or other construction machine is used to construct a new structure above the existing structure. It is common to adopt a construction method of constructing a building frame.

【0003】[0003]

【発明が解決しようとする課題】ところで、上記従来の
工法は、既存構造物の周囲から作業を行なうものである
ことから、既存構造物の周辺に十分な作業スペースを確
保できない場合には適用できないものであり、このた
め、そのような場合にも適用可能な有効な施工方法の提
供が要望されていた。
However, the above-mentioned conventional method is not applicable when a sufficient working space cannot be secured around the existing structure because the work is performed from around the existing structure. Therefore, it has been demanded to provide an effective construction method applicable to such a case.

【0004】[0004]

【課題を解決するための手段】本発明は上記事情に鑑み
てなされたもので、地上に設けられている既存構造物の
上方に建築物を施工するに当たり、前記既存構造物を挟
んでその両側に互いに平行に対向する対の構造体を設
け、それら構造体の上部相互間に前記既存構造物の上方
を覆う人工地盤を架け渡して、その人工地盤上に前記建
築物を設けることとする。そして、前記構造体および前
記人工地盤を施工するに当たっては、まず、施工するべ
き構造体相互間にわたる長さの仮設構台をそれら構造体
の一端側に位置させてそれら構造体と直交するように設
ける。次いで、その仮設構台上から作業を行なうことに
より仮設構台に隣接する位置に前記構造体を所定長さだ
け施工するとともに、その構造体の長さ寸法に相当する
幅寸法の人工地盤ユニットを仮設構台上において組み立
ててそれを施工済みの構造体上に送り出すことによって
それらの間に架け渡す。その後、構造体相互間に架け渡
した人工地盤ユニット上から作業を行なうことによって
施工済みの構造体に連続させて所定長さの構造体をさら
に施工する工程と、構造体相互間に架け渡した人工地盤
ユニットの後部側に連結する形態で他の人工地盤ユニッ
トを仮設構台上において組み立てる工程と、それら連結
した人工地盤ユニットを施工済みの構造体上に送り出す
工程とを繰り返すことにより、前記仮設構台を出発点と
して前記構造体および前記人工地盤を所定長さづつ順次
施工していく。
SUMMARY OF THE INVENTION The present invention has been made in view of the above circumstances, and when a building is constructed above an existing structure provided on the ground, both sides of the existing structure are sandwiched therebetween. , A pair of structures facing each other in parallel to each other is provided, and an artificial ground covering the existing structure is bridged between the upper parts of the structures, and the building is provided on the artificial ground. In constructing the structure and the artificial ground, first, a temporary gantry having a length extending between the structures to be constructed is provided at one end of the structures so as to be orthogonal to the structures. . Then, by performing work from the temporary gantry, the structure is constructed by a predetermined length at a position adjacent to the temporary gantry, and an artificial ground unit having a width dimension corresponding to the length dimension of the temporary gantry is provided. Assembled above and spanned between them by sending it onto the constructed structure. Thereafter, by performing work from the artificial ground unit bridged between the structures, a process of continuously constructing a structure of a predetermined length by continuing to the already-structured structure, and bridging between the structures. By repeating the step of assembling another artificial ground unit on the temporary gantry in the form of being connected to the rear side of the artificial ground unit, and the step of sending out the connected artificial ground unit onto the constructed structure, the temporary gantry With the starting point, the structure and the artificial ground are sequentially constructed by a predetermined length.

【0005】[0005]

【作用】既存構造物を人工地盤により覆ったうえで、そ
の人工地盤上に新たな建築物を設けることにより、人工
地盤が既存構造物に対する養生床となるとともに作業用
足場となり、既存構造物を支障なく使用しながら安全に
作業を行ない得る。また、仮設構台上においてユニット
を組み立てて連結しては送り出していくといういわゆる
スライド工法により人工地盤の施工を行ない、かつ、人
工地盤を支持する構造体の施工を仮設構台上および施工
済みの人工地盤上から行なうことにより、ほとんど全て
の作業を仮設構台上および施工済みの人工地盤上から行
なうことができ、既存構造物の周囲にはさほどの作業ス
ペースを必要としない。
[Function] After the existing structure is covered with artificial ground, and a new building is provided on the artificial ground, the artificial ground becomes a curing floor for the existing structure and also serves as a work scaffold. You can work safely while using safely. In addition, construction of the artificial ground is carried out by the so-called slide method of assembling, connecting and sending out the units on the temporary gantry, and the construction of the structure supporting the artificial ground is performed on the temporary gantry and the constructed artificial ground. By performing from above, almost all the work can be performed on the temporary gantry and on the constructed artificial ground, and does not require much working space around the existing structure.

【0006】[0006]

【実施例】以下、本発明の実施例を図面を参照して説明
する。本実施例の施工方法は、図6に示すように、地上
に設けられている既存構造物1の上方にそれをまたぐ形
態の建築物2を施工するに際して、既存構造物1を挟ん
でその両側に互いに平行に対向する対の構造体3、3を
設け、それら構造体3、3の上部相互間に既存構造物1
の上方を覆う人工地盤4を架け渡して、その人工地盤4
上に上層階の躯体を設けるようにしたものである。
Embodiments of the present invention will be described below with reference to the drawings. As shown in FIG. 6, the construction method according to the present embodiment, when constructing a building 2 having a form that straddles an existing structure 1 provided on the ground, sandwiches the existing structure 1 on both sides thereof. Are provided with a pair of structures 3 facing each other in parallel with each other, and the existing structure 1
The artificial ground 4 covering the upper part of the
The upper floor has a frame on the upper floor.

【0007】上記建築物2を施工するには、まず、図1
に示すような仮設構台5を設ける。この仮設構台5は、
施工するべき構造体3、3相互間にわたる長さのものと
し、それら構造体3、3の一端側に位置させてそれら構
造体3、3と直交するように設ける。この仮設構台5上
の両端部には、後述する人工地盤ユニット4aをスライ
ドさせるためのレール50を予め設けておく。そして、
この仮設構台5を出発点として、前記構造体3、3およ
び前記人工地盤4を所定長さづつ順次施工していく。
In order to construct the building 2, first, FIG.
A temporary gantry 5 as shown in FIG. This temporary gantry 5
The structures 3, 3 to be constructed have a length extending between them, and are provided at one end of the structures 3, 3 so as to be orthogonal to the structures 3, 3. At both ends of the temporary gantry 5, rails 50 for sliding an artificial ground unit 4a described later are provided in advance. And
Starting from the temporary gantry 5, the structures 3, 3 and the artificial ground 4 are sequentially constructed by a predetermined length.

【0008】すなわち、まず、その仮設構台5上に掘削
機やクレーン等の建設機械6を搭載し、それを用いて仮
設構台5上から作業を行なうことにより、図2に示すよ
うに、仮設構台5に隣接する位置に上記の構造体3、3
を所定長さだけ施工する(ここで施工された構造体を符
号3a、3aで示す)を施工する。なお、本実施例にお
ける構造体3は施工するべき建築物2の低層部の外壁と
なるものであるが、それらの上部間に人工地盤4を架け
渡すことができるものであれば一連の杭や柱あるいは地
中連続壁等を構造体とすることでも良い。また、上記構
造体3a、3aの施工と相前後して仮設構台5上におい
て人工地盤ユニット4aを組み立てる。この人工地盤ユ
ニット4aは、施工するべき人工地盤4が複数に分割さ
れた形態のものであって、その幅寸法が上記構造体3
a、3aの長さ寸法に相当するものとされている。な
お、本実施例における人工地盤ユニット4aは長大スパ
ンのトラス7に床版8を取り付けた構造のものである
が、所望のスパン長および強度が得られるものであれば
他の形式のものでも良い。また、この人工地盤ユニット
4aは、掘削機やクレーン等の上記建設機械6を搭載可
能な強度を有するものとしておく。
That is, first, a construction machine 6 such as an excavator or a crane is mounted on the temporary gantry 5 and the work is performed from the temporary gantry 5 using the same, as shown in FIG. 5 at the position adjacent to 5
Is carried out for a predetermined length (the structures constructed here are indicated by reference numerals 3a and 3a). The structure 3 in the present embodiment is an outer wall of a low-rise part of the building 2 to be constructed. However, if the artificial ground 4 can be bridged between them, a series of piles or The structure may be a pillar or an underground continuous wall. The artificial ground unit 4a is assembled on the temporary gantry 5 immediately before and after the construction of the structures 3a, 3a. The artificial ground unit 4a has a configuration in which the artificial ground 4 to be constructed is divided into a plurality of sections, and the width of the
a and 3a correspond to the length dimension. Although the artificial ground unit 4a in this embodiment has a structure in which the floor slab 8 is attached to the long span truss 7, other types may be used as long as the desired span length and strength can be obtained. . Further, the artificial ground unit 4a has a strength capable of mounting the construction machine 6 such as an excavator or a crane.

【0009】そして、油圧ジャッキ等のスライド駆動源
により人工地盤ユニット4aをレール50により案内し
て前方に押し出すことにより、図3に示すように、その
人工地盤ユニット4aを上記で施工した構造体3a、3
a上に送り出してそれらの間に架け渡す。
Then, the artificial ground unit 4a is guided by the rail 50 and pushed forward by a slide drive source such as a hydraulic jack, so that the artificial ground unit 4a is constructed as shown in FIG. , 3
a and send it over them.

【0010】その後、図4に示すように、構造体3a、
3a相互間に架け渡した上記の人工地盤ユニット4a上
に搭載した建設機械6により、その人工地盤ユニット4
a上から作業を行なうことによって施工済みの構造体3
a、3aの前方に連続させて所定長さの構造体3b、3
bをさらに施工するとともに、人工地盤ユニット4aの
後部側に連結する形態で他の人工地盤ユニット4bを仮
設構台5上において組み立てる。そして、それら連結し
た人工地盤ユニット4a、4bを上記と同様にして施工
済みの構造体3a、3a、3b、3b上に送り出してい
く。
[0010] Thereafter, as shown in FIG.
The construction machine 6 mounted on the above-mentioned artificial ground unit 4a bridged between the artificial ground units 4a
a Structure 3 already constructed by performing work from above
a, structures 3b, 3a of a predetermined length
b, and another artificial ground unit 4b is assembled on the temporary gantry 5 so as to be connected to the rear side of the artificial ground unit 4a. Then, the connected artificial ground units 4a and 4b are sent out onto the constructed structures 3a, 3a, 3b and 3b in the same manner as described above.

【0011】以上の手順を繰り返すことによって構造体
3および人工地盤4を所定長さづつ順次施工していき、
それらが完成した後に、図5に示すように人工地盤4上
に上層階の躯体を施工して建築物2を完成させる。
By repeating the above procedure, the structure 3 and the artificial ground 4 are sequentially constructed by a predetermined length,
After these are completed, the building of the upper floor is constructed on the artificial ground 4 as shown in FIG.

【0012】上記方法によれば、人工地盤4が既存構造
物1に対する養生床となるとともに作業足場となるの
で、既存構造物1を支障なく使用しながら安全に工事を
行なうことができる。また、構造体3を仮設構台5上や
施工済みの人工地盤4上から施工するようにし、かつ、
人工地盤ユニット4a、4b、…を仮設構台5上におい
て組み立てて施工済みのものの後方に連結してはそれら
をスライドさせていくようにしたことにより、ほとんど
全ての作業を仮設構台5上および施工済みの人工地盤4
上において行なうことができ、したがって、仮設構台5
の設置スペースを確保する以外は既存構造物1の周囲に
さほどの作業スペースを必要とせず、周囲に十分な作業
スペースが確保できない場合にも適用可能である。
According to the above method, the artificial ground 4 serves as a curing floor for the existing structure 1 and also serves as a work scaffold, so that the construction can be performed safely while using the existing structure 1 without any trouble. In addition, the structure 3 is constructed from the temporary gantry 5 or the constructed artificial ground 4, and
By assembling the artificial ground units 4a, 4b,... On the temporary gantry 5 and connecting them to the rear of the already-constructed ones and sliding them, almost all the work is performed on the temporary gantry 5 and on the completed gantry 5. Artificial ground 4
On the temporary gantry 5
Other than securing the installation space, a large work space is not required around the existing structure 1, and the present invention can be applied to a case where a sufficient work space cannot be secured around the existing structure 1.

【0013】なお、図7に示すように、最初の人工地盤
ユニット4aの両端部に前方に突出するような張り出し
部40を設けておいて、その張り出し部40上に建設機
械6を搭載して作業を行なうようにすれば、構造体3の
施工をより容易に行なうことができる。
As shown in FIG. 7, projecting portions 40 projecting forward are provided at both ends of the first artificial ground unit 4a, and the construction machine 6 is mounted on the projecting portions 40. If the work is performed, the construction of the structure 3 can be performed more easily.

【0014】[0014]

【発明の効果】以上で詳細に説明したように、本発明方
法によれば、既存構造物の両側に設けた構造体間に人工
地盤を架け渡してその人工地盤上に建築物を設けるよう
にしたので、既存構造物を支障なく使用しながら安全に
工事を行なうことができることは勿論のこと、構造体お
よび人工地盤を仮設構台上および施工済みの人工地盤上
から順次施工するようにしたので、仮設構台の設置スペ
ースを確保する以外は既存構造物の周囲にさほどの作業
スペースを必要としないという利点があり、したがっ
て、周囲に十分な作業スペースが確保できない場合に採
用して好適である。
As described in detail above, according to the method of the present invention, an artificial ground is bridged between structures provided on both sides of an existing structure, and a building is provided on the artificial ground. So, of course, it is possible to safely perform construction while using existing structures without hindrance, as well as to construct the structure and artificial ground sequentially on the temporary gantry and the constructed artificial ground, There is an advantage that a large working space is not required around the existing structure except for securing the installation space for the temporary gantry. Therefore, it is suitable for use when a sufficient working space cannot be secured around the existing structure.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明方法の実施例を示すもので、仮設構台を
設けた状態を示す図である。
FIG. 1 is a view showing an embodiment of the method of the present invention and showing a state where a temporary gantry is provided.

【図2】同じく、構造体を設けるとともに仮設構台上で
人工地盤ユニットを組み立てた状態を示す図である。
FIG. 2 is a view showing a state in which a structural body is provided and an artificial ground unit is assembled on a temporary gantry.

【図3】同じく、構造体間に人工地盤ユニットを架け渡
した状態を示す図である。
FIG. 3 is a view showing a state in which an artificial ground unit is bridged between structures.

【図4】同じく、構造体をさらに設けた状態を示す図で
ある。
FIG. 4 is a view showing a state in which a structure is further provided.

【図5】同じく、人工地盤上に上層階の躯体を施工して
いる状態を示す図である。
FIG. 5 is a diagram showing a state in which a skeleton of an upper floor is being constructed on artificial ground.

【図6】本発明方法により施工された建築物の例を示す
図である。
FIG. 6 is a diagram showing an example of a building constructed by the method of the present invention.

【図7】本発明方法の他の実施例を示すもので、張り出
し部を有する人工地盤ユニット上から構造体を施工して
いる状態を示す図である。
FIG. 7 is a view showing another embodiment of the method of the present invention, showing a state where a structure is being constructed from an artificial ground unit having an overhang portion.

【符号の説明】[Explanation of symbols]

1 既存構造物 2 建築物 3、3a 構造体 4 人工地盤 4a、4b 人工地盤ユニット 5 仮設構台。 Reference Signs List 1 Existing structure 2 Building 3, 3a Structure 4 Artificial ground 4a, 4b Artificial ground unit 5 Temporary gantry.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 熊谷 武紀 東京都港区芝浦一丁目2番3号 清水建 設株式会社内 (72)発明者 諸井 陽児 東京都港区芝浦一丁目2番3号 清水建 設株式会社内 (72)発明者 奥田 修司 東京都港区芝浦一丁目2番3号 清水建 設株式会社内 (58)調査した分野(Int.Cl.6,DB名) E04H 1/00 E04G 21/14 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Takeki Kumagai 1-3-2 Shibaura, Minato-ku, Tokyo Inside Shimizu Corporation (72) Inventor Yoji Moroi 1-2-3 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Shuji Okuda 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (58) Field surveyed (Int.Cl. 6 , DB name) E04H 1/00 E04G 21/14

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 地上に設けられている既存構造物の上方
に建築物を施工する方法であって、前記既存構造物を挟
んでその両側に互いに平行に対向する対の構造体を設
け、それら構造体の上部相互間に前記既存構造物の上方
を覆う人工地盤を架け渡して、その人工地盤上に前記建
築物を設けるようになし、前記構造体および前記人工地
盤を施工するに当たっては、まず、施工するべき構造体
相互間にわたる長さの仮設構台をそれら構造体の一端側
に位置させてそれら構造体と直交するように設け、次い
で、その仮設構台上から作業を行なうことにより仮設構
台に隣接する位置に前記構造体を所定長さだけ施工する
とともに、その構造体の長さ寸法に相当する幅寸法の人
工地盤ユニットを仮設構台上において組み立ててそれを
施工済みの構造体上に送り出すことによってそれらの間
に架け渡し、その後、構造体相互間に架け渡した人工地
盤ユニット上から作業を行なうことによって施工済みの
構造体に連続させて所定長さの構造体をさらに施工する
工程と、構造体相互間に架け渡した人工地盤ユニットの
後部側に連結する形態で他の人工地盤ユニットを仮設構
台上において組み立てる工程と、それら連結した人工地
盤ユニットを施工済みの構造体上に送り出す工程とを繰
り返すことにより、前記仮設構台を出発点として前記構
造体および前記人工地盤を所定長さづつ順次施工してい
くことを特徴とする建築物の施工方法。
1. A method for constructing a building above an existing structure provided on the ground, comprising: providing a pair of structures facing each other in parallel on both sides of the existing structure, An artificial ground covering the upper part of the existing structure is bridged between the upper parts of the structures, and the building is provided on the artificial ground.In constructing the structure and the artificial ground, first, A temporary gantry having a length extending between the structures to be constructed is provided at one end of the structures so as to be orthogonal to the structures, and then the work is performed from the temporary gantry to form the temporary gantry. At the adjacent position, the structure is constructed for a predetermined length, and an artificial ground unit having a width corresponding to the length of the structure is assembled on a temporary gantry, and is assembled on the constructed structure. A step of bridging between them by sending them out, and then performing a work from the artificial ground unit bridged between the structures so as to be continuous with the already constructed structure and further construct a structure of a predetermined length And a step of assembling another artificial ground unit on the temporary gantry in a form to be connected to the rear side of the artificial ground unit bridged between the structures, and sending out the connected artificial ground unit onto the constructed structure A construction method for a building, comprising repeating the steps to sequentially construct the structure and the artificial ground by a predetermined length starting from the temporary gantry.
JP20211791A 1991-06-25 1991-06-25 Construction method of building Expired - Fee Related JP2952836B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP20211791A JP2952836B2 (en) 1991-06-25 1991-06-25 Construction method of building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP20211791A JP2952836B2 (en) 1991-06-25 1991-06-25 Construction method of building

Publications (2)

Publication Number Publication Date
JPH055367A JPH055367A (en) 1993-01-14
JP2952836B2 true JP2952836B2 (en) 1999-09-27

Family

ID=16452247

Family Applications (1)

Application Number Title Priority Date Filing Date
JP20211791A Expired - Fee Related JP2952836B2 (en) 1991-06-25 1991-06-25 Construction method of building

Country Status (1)

Country Link
JP (1) JP2952836B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI636980B (en) * 2013-07-19 2018-10-01 獨立行政法人產業技術綜合研究所 Method for producing cyclic carbonate

Also Published As

Publication number Publication date
JPH055367A (en) 1993-01-14

Similar Documents

Publication Publication Date Title
JP2952836B2 (en) Construction method of building
JP3025227B2 (en) Bridge construction method
JP2001193278A (en) Construction method for structure having inside space, and climbing scaffolding
JPH06200625A (en) Frame method of arch truss construction
JP2001164757A (en) Work method for building
JP3053938B2 (en) Double striking method
JP3725818B2 (en) How to install seismic isolation devices on existing pillars
JPH074049A (en) Construction method of building
JP3192543B2 (en) Building demolition method
JP2817591B2 (en) Construction method of steel reinforced concrete building
JP2529067B2 (en) Crane flexible climbing method
JP2919827B1 (en) All-weather temporary scaffolding device and method of using all-weather temporary scaffolding device
JP2668217B2 (en) Arch-shaped large space roof construction method
JP2668218B2 (en) Arch-shaped large space roof construction method
JP3115942B2 (en) Building construction method
JP2871468B2 (en) How to build a building
JP3183160B2 (en) Existing column reinforcement method
JP3364185B2 (en) Temporary scaffold for assembling wooden ramen and method of assembling wooden ramen using the temporary scaffold
JP2622313B2 (en) How to build a building
JP3281972B2 (en) Reinforcing unit and method of constructing reinforced concrete building using the same
JP2994205B2 (en) Structural assembly method
JP2581248B2 (en) Building construction method
JP2876991B2 (en) Steel frame method for high-rise buildings
JPS6073916A (en) Construction method for underground floor
JPS6355569B2 (en)

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19990525

LAPS Cancellation because of no payment of annual fees