JP2622313B2 - How to build a building - Google Patents
How to build a buildingInfo
- Publication number
- JP2622313B2 JP2622313B2 JP4338191A JP4338191A JP2622313B2 JP 2622313 B2 JP2622313 B2 JP 2622313B2 JP 4338191 A JP4338191 A JP 4338191A JP 4338191 A JP4338191 A JP 4338191A JP 2622313 B2 JP2622313 B2 JP 2622313B2
- Authority
- JP
- Japan
- Prior art keywords
- floor
- temporary
- temporary gantry
- gantry
- building
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Movable Scaffolding (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION
【0001】[0001]
【産業上の利用分野】本発明は鉄骨造、鉄骨鉄筋コンク
リート造等の構造による複層の地上建築物の柱、梁、床
等の構造部材を機械装置によって構築する建築物の構築
方法に係るものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a building in which a structural member such as a pillar, a beam, a floor, etc. of a multi-layered ground building having a structure such as a steel frame or a steel reinforced concrete structure is constructed by a mechanical device. It is.
【0002】[0002]
【従来の技術】従来この種の方法として、仮設上屋を支
持する大型ジヤツキを短縮させて、同仮設上屋の下に本
設柱を設置してこれを下部の本設柱に固定したのち、同
本設柱の頂部に前記大型ジヤツキを伸長して載架し、前
記仮設上屋の荷重を再び下方に伝達し、これを1柱づつ
繰返して所定の本数の本設柱を設置し、同本設柱間に梁
を結合して全体の一層分の架構を組立てる方法が提案さ
れている。2. Description of the Related Art Conventionally, as a method of this type, a large-sized jack supporting a temporary shed is shortened, a permanent pillar is installed under the temporary shed, and this is fixed to a lower permanent pillar. The large jack is extended and mounted on the top of the main pillar, the load of the temporary shed is transmitted downward again, and this is repeated one by one to install a predetermined number of permanent pillars, A method has been proposed in which a beam is connected between the main columns to assemble an entire frame.
【0003】また仮設上屋のクライミング装置及び荷重
伝達用真柱及び側柱を組合わせ、これを交互に引上げて
本設柱を挿入していく方法が提案されている。更にまた
建物の平面的にコアーとなる部分を部を先行して施工
し、この部分より最終的に本設屋根となる構造体を懸吊
し、同構造体を順次引き上げながら柱梁等の構築を行う
方法が提案されている。Further, a method has been proposed in which a climbing device for a temporary shed, a true pillar for transmitting a load, and a side pillar are combined and alternately pulled up to insert a permanent pillar. Furthermore, the part that will become the core of the building will be constructed in advance of the part, the structure that will eventually become the permanent roof will be suspended from this part, and the pillar will be constructed while sequentially lifting the structure Have been proposed.
【0004】[0004]
【発明が解決しようとする課題】前記第1及び第2の例
においては、構築機械を梁下で懸吊させる仮設上屋の荷
重の支持は、大型ジヤツキ、真柱、側柱等の仮設機械、
柱等で一旦支持し、仮設屋の下部に1階分の柱を挿入す
る形で設置していくため施工が繁雑になり、しかも柱は
必ず1階分の長さしか設置できない。In the first and second examples, the temporary shed, which suspends the construction machine under the beam, supports the load on a temporary machine such as a large jack, a right pillar, a side pillar, or the like. ,
It is once supported by pillars and the like, and the installation is complicated by installing the pillars of the first floor at the bottom of the temporary building, so that the construction is complicated, and the pillars can always be installed only for the length of one floor.
【0005】また第3の例においては、コア部分を従来
の工法で施工したのち、同コア部分をガイドとして残り
の部分を引上げることとなり、建築物全体の機械化、同
時施工ができない。本発明は前記従来技術の有する問題
点に鑑みて提案されたもので、その目的とする処は、建
築物の構築を機械化し、仮設費と組立費を軽減し、省力
化を図り、天候に左右されることなく作業を遂行しうる
建築物の構築方法を提供する点にある。In the third example, after the core portion is constructed by the conventional construction method, the remaining portion is pulled up by using the core portion as a guide, so that the mechanization and simultaneous construction of the entire building cannot be performed. The present invention has been proposed in view of the problems of the prior art described above, and its object is to mechanize the construction of buildings, reduce temporary and assembly costs, reduce labor, save weather, An object of the present invention is to provide a method for constructing a building capable of performing work without being affected by the influence.
【0006】[0006]
【課題を解決するための手段】前記の目的を達成するた
め、本発明に係る建築物の構築方法によれば、最終的に
本設の梁となる屋上階と最上階の各床組との間に、本設
柱より突設された梁端部に支持されて上昇するセルフク
ライミング装置を取付けてなる仮設構台を構成し、同仮
設構台における上梁の上面及び下梁の下面に夫々レール
を敷設するとともに同各レール上を走行またはレール下
に懸吊される資材搬送、部材組立及び接合用機器を装架
し、同機器によって柱、梁、床等の部材を組立て、一層
分の組立作業が完了すると前記セルフクライミング装置
を介して前記仮設構台を上昇させて前記の組立作業を繰
返し、以下前記の組立作業を反覆して所要階数の部材を
組立て、最終的に前記仮設構台を屋上階及び最上階の梁
として柱に接合するものである。In order to achieve the above object, according to the construction method of a building according to the present invention, each of a pair of a top floor and a top floor which finally becomes a main beam is connected. In the meantime, a temporary gantry is installed, which is equipped with a self-climbing device that is supported and raised at the beam end protruding from the main pillar, and rails are respectively provided on the upper surface of the upper beam and the lower surface of the lower beam in the temporary gantry. Laying and running equipment on each rail or hanging under each rail, mounting equipment for material assembly, joining and joining, and assembling members such as columns, beams, floors, etc. with this equipment, assembling work for one layer When the completion is completed, the temporary gantry is raised via the self-climbing device, and the assembling operation is repeated.Then, the above-mentioned assembling operation is repeated to assemble members of a required number of floors. Connect to pillar as top floor beam It is intended.
【0007】[0007]
【作用】本発明によれば、最終的に本設の梁となる屋上
階の床組と最上階の床組との間に、本設柱より突設され
た梁端部に支持されて上昇するクライミング装置を介装
して架設構台を構成し、同梁における上梁の上面と下梁
の下面に敷設したレールに資材、搬送、部材組立及び接
合用機器を移動自在に装架し、同機器を走行させるとと
もに架設構台を仮設ステージとして地上面より順次、
梁、床、壁等の部材の構築を行ない、複数階分の長さの
柱を上方に接合しつつ同柱をガイド支柱として、前記ク
ライミング装置を介して前記仮設ステージを上昇させな
がら建築物を構築し、最上階に到達したとき、前記仮設
構台の上下床組を柱に固定して夫々屋上階の梁及び最上
階の梁とすることによって、建築物全体を構築するもの
である。According to the present invention, between the floor set on the rooftop floor and the floor set on the top floor, which are ultimately the main beams, the beam is supported by the beam ends protruding from the main columns and raised. A climbing device is interposed to form an erecting gantry, and materials, transport, member assembly and joining equipment are movably mounted on rails laid on the upper surface of the upper beam and the lower surface of the lower beam. Run the equipment and use the erection gantry as a temporary stage from the ground surface,
Construction of members such as beams, floors, walls, etc., while joining columns of multiple floors length upwards, using the same pillars as guide posts, raising the temporary stage via the climbing device, When the building is constructed and reaches the top floor, the entire building is constructed by fixing the upper and lower floor sets of the temporary gantry to pillars to form a rooftop floor beam and a top floor beam, respectively.
【0008】[0008]
【実施例】以下本発明を図示の実施例について説明す
る。図1は本方法によって構築される建築物の平面図及
び仮設ステージを構成する仮設構台及び同仮設構台に設
置されるクレーンまたは部材取付機器類を示す平面図、
第2図は地表部分における仮設構台及びクレーン等の機
器の位置関係を示す立面図である。BRIEF DESCRIPTION OF THE DRAWINGS FIG. FIG. 1 is a plan view of a building constructed by the present method, a plan view showing a temporary gantry constituting a temporary stage, and cranes or member mounting devices installed on the temporary gantry;
FIG. 2 is an elevational view showing the positional relationship between temporary gantry and equipment such as cranes on the ground surface.
【0009】而して図1における本設柱C、図2の本設
柱第1ユニツトC1は同一のもので、基礎工事完了の後
に、すべての柱設置位置に柱を立設する。次に図2にお
いて点線Aで示す高さ位置を梁下として、仮設ステージ
を構成する仮設構台Sの組立を行う。同仮設構台Sは屋
上階の梁1、2及び最上階の梁3、4となる上下の床組
より構成され仮設構台Sにはセルフクライミング装置
K、K′が柱Cの近くの必要な個所に設置され、柱Cよ
り突設されたブラケツト状の梁端部に後述のように仮設
構台Sの荷重を支持させて仮設構台Sのクライミングを
行う。The main pillar C in FIG. 1 and the first main unit C1 in FIG. 2 are the same, and after the foundation work is completed, the pillars are erected at all the pillar installation positions. Next, the temporary gantry S constituting the temporary stage is assembled with the height position indicated by the dotted line A in FIG. The temporary gantry S is composed of upper and lower floors which are the beams 1 and 2 on the roof floor and the beams 3 and 4 on the top floor. The temporary gantry S is climbed by supporting the load of the temporary gantry S on a bracket-shaped beam end protruding from the column C as described later.
【0010】仮設構台Sとセルフクライミング装置K、
K′が完成した後、同クライミング装置K、K′を少し
上昇させ梁下に懸吊される作業機械W及びこれを走行さ
せるレールRの取りつけを行う。更に梁上に設置され
る、作業機械W及びこれを走行させるレールRの取りつ
けも同時に行う。この取付けが完了しセルフクライミン
グ装置K、梁下及び梁上の作業機械Wがすべて正常な機
能を発揮できるように調整、整備が完了すると建築物の
建設が開始される。[0010] The temporary gantry S and the self-climbing device K,
After completion of K ', the climbing devices K and K' are slightly raised, and the work machine W suspended under the beam and the rail R for running the same are mounted. Further, the work machine W and the rail R for running the work machine W installed on the beam are simultaneously mounted. When this installation is completed and adjustment and maintenance are completed so that the self-climbing device K and the work machine W under and above the beam can all perform their normal functions, construction of the building is started.
【0011】先づ仮設構台Sが図2の位置で1層目の柱
C又は壁等のコンクリート用型枠の設置(図示せず)P
C版(図示せず)の設置が必要であれば梁下の作業機械
Wにより作業を行い、完了後にセルフクライミング装置
Kの作動により仮設構台Sを図3の位置まで1階分の高
さだけ上昇させる。本設柱第1ユニツトC1は1階分〜
3階分の長さのものを必要に応じて設定するので、柱第
2ユニツトC2の接合が必要になった時点で図3に示す
ように梁上の作業機械W1によって同ユニツトC2の吊
り込み及び前記ユニツトC1に対する接合を行い、同各
ユニツトを上方へ継接していく。First, when the temporary gantry S is located at the position shown in FIG. 2, a concrete form such as a pillar C or a wall of the first layer is installed (not shown) P
If it is necessary to install a C-plate (not shown), work is performed by the work machine W below the beam, and after completion, the temporary gantry S is moved up to the position of FIG. To raise. The first unit C1 of the main pillar is 1st floor ~
Since the length of three floors is set as necessary, when the joining of the second column unit C2 becomes necessary, the unit C2 is suspended by the work machine W1 on the beam as shown in FIG. Then, the unit C1 is joined, and each unit is joined upward.
【0012】図3に示す位置における作業は前記柱Cの
接合の他梁下の作業機械W、2階部分の梁、床階段等の
部材Gの組立接合及び1階の柱Cのコンクリート打設、
2階床面のコンクリート打設を行う。更に図4に示す位
置に仮設構台Sが上昇すると、前記図3に示す位置にお
ける作業と同時に、既に構造体Bとして工事が完了した
部分の仕上工事、設備工事等が作業ロボツトFによって
行われる。The work at the position shown in FIG. 3 is performed by assembling and joining members G such as a work machine W under the beam, a beam on the second floor, a floor stair, etc., and a concrete casting of the column C on the first floor in addition to the joint of the column C. ,
Concrete is placed on the second floor. Further, when the temporary gantry S is raised to the position shown in FIG. 4, the work robot F performs the finishing work and the equipment work for the portion where the construction has already been completed as the structure B at the same time as the work at the position shown in FIG.
【0013】このように図4に示す作業を同時に行いつ
つ梁下の作業機械Wの行う作業が完了すると仮設構台S
は順次上階へと作業を進め最上層に達した時にセルフク
ライミング装置K、K′を取り外し屋上階の梁1、及び
2、最上階の梁3及び4を夫々柱Cに接合固定して構造
体Bの工事を完了するのでセルフクライミング装置K、
K′、梁下、梁上の作業機械W及びレールRを取り外し
て建物外に搬出する。When the work performed by the work machine W under the beam is completed while simultaneously performing the work shown in FIG. 4, the temporary gantry S
Works sequentially to the upper floor, and when the uppermost floor is reached, the self-climbing devices K and K 'are removed, and the beams 1 and 2 on the roof floor and the beams 3 and 4 on the top floor are joined and fixed to the columns C, respectively. Since the construction of body B is completed, self-climbing device K,
K ', the work machine W under the beam and the work machine W and the rail R on the beam are removed and carried out of the building.
【0014】仕上、設備工事等は続行して建物を完成さ
せる。以上本発明の構築方法の概要について説明した
が、次に各部の機構について説明する。図5、7、8、
12、13、14、15においてセルフクライミング装
置Kは仮設構台Sの上部の梁1又は下部の梁3に接合さ
れた補助桁5又は6に支持された受梁7及び8に、両側
面に長手方向に亘ってラチエツト9が取りつけられたロ
ツド10の上端及び下端を固定し、仮設構台Sのクライ
ミングに必要な荷重を安全に伝達するように構成されて
いる。Finishing, facility construction, etc. are continued to complete the building. The outline of the construction method of the present invention has been described above. Next, the mechanism of each unit will be described. Figures 5, 7, 8,
In 12, 13, 14 and 15, the self-climbing device K is provided with supporting beams 7 and 8 supported by auxiliary girders 5 or 6 joined to the upper beam 1 or the lower beam 3 of the temporary gantry S. The upper end and the lower end of the rod 10 to which the ratchet 9 is attached are fixed in all directions, so that the load required for climbing the temporary gantry S can be safely transmitted.
【0015】柱Cに突設されたブラケツト状の梁端部1
1に架設された受梁12上に設置されたジヤツキ下受梁
13には左右一対になった爪14、14′が軸15、1
5′によって回転可能に取りつけられている。前記一対
の爪14、14′はバネ(図示せず)によって互いに近
接する方向に倒れかかるように押しつけられているの
で、ラチエツト9をはさみ込んで押えつけている。又、
ジヤツキ16、16′はジヤツキ下受梁13上に固定さ
れジヤツキ16、16′の上部にはジヤツキ上受梁1
7、17′が固定され、このジヤツキ上受梁17、1
7′にも爪18、18′、軸19、19′バネ(図示せ
ず)がジヤツキ下受梁13と同様に取りつけられ、ラチ
エツト9をはさみ込んでいる。(図7及び図8参照)従
ってロツド10が上昇する際、ラチエツト9は爪14、
14′、18、18′を乗り越えるが、乗り越えた後は
ラチエツト9に爪、14、14′、18、18′が噛止
して、ロツド10を固定する。A bracket-shaped beam end 1 protruding from a column C
A pair of right and left claws 14 and 14 ′ is mounted on a shaft 15, 1
It is rotatably mounted by 5 '. The pair of claws 14, 14 'are pressed by springs (not shown) so as to fall down in a direction approaching each other, so that the ratchet 9 is sandwiched and pressed. or,
The jacks 16 and 16 'are fixed on the lower deck support 13 and the upper decks 1 and 16 are located above the jacks 16 and 16'.
7 and 17 'are fixed.
The pawls 18 and 18 'and the shafts 19 and 19' springs (not shown) are attached to the 7 'in the same manner as the lower jack support 13 and sandwich the ratchet 9. (See FIGS. 7 and 8) Therefore, when the rod 10 is raised, the ratchet 9 is
After climbing over 14 ', 18, and 18', claws 14, 14, 14 ', 18, and 18' engage the ratchet 9 to fix the rod 10.
【0016】ジヤツキ下受梁13には、電動駆動による
油圧装置20が取りつけられジヤツキ16、16′に圧
力油を供給し、セルフクライミング装置Kを駆動させる
が1本の柱Cに2ケのセルフクライミング装置K、K′
がある場合は片方の油圧装置20を省略して単一の油圧
装置20で両方のジヤツキ16、16′に対する圧力油
供給を行うことも可能であり、この方式の方が接近した
位置での場合は圧力差が発生せず、仮設構台Sの梁1、
2、3、4間に無用の曲げ応力が発生するのを防止でき
る。なお油圧装置20が付設されていない方のセルフク
ライミング装置をK′とする。A hydraulic device 20 driven by electric drive is mounted on the lower jack support 13 to supply pressure oil to the jacks 16 and 16 'to drive the self-climbing device K. Climbing device K, K '
In this case, it is also possible to omit one hydraulic device 20 and supply pressure oil to both the jacks 16, 16 'with a single hydraulic device 20. Does not generate a pressure difference, the beam 1 of the temporary gantry S,
Unnecessary bending stress can be prevented from being generated between 2, 3, and 4. The self-climbing device not provided with the hydraulic device 20 is designated as K '.
【0017】以上のシステムによって、先づ図7の位置
にジヤツキユニツトJ、J′を設置し、油圧装置20を
駆動してジヤツキ16、16′を伸長させると受梁12
に支持されジヤツキ下受梁13、ジヤツキ16、16′
の下部は柱に突設された梁端部11及び受柱12を介し
て柱Cに固定されて不動であるから、ジヤツキ16、1
6′の上部が上方に伸長することとなる。爪18、1
8′はラチエツト9に噛合しているため荷重を支えロツ
ド10全体が上昇することになる。これは受梁7、補助
桁5、6を介して仮設構台S全体が上に押し上げられる
ことである。この時爪14、14′は不動でラチエツト
9全体が上昇するので、ラチエツト9の1ストローク分
だけ上昇すると爪14、14′は1つ下のラチエツトに
噛止することになる。全部の爪14、14′が次のラチ
エツト9に確実に噛止したことをリミツトスイツチ等
(図示せず)により確認した後、ジヤツキ16、16′
を短縮すると爪18、18′に噛合されたラチエツト9
及びロツド10は一緒に下降するので、爪、14、1
4′とラチエツト9との間隙はなくなり遂に爪14、1
4′とラチエツト9が噛合し荷重を爪14、14′で支
えるようになる。更にジヤツキ16、16′を短縮する
と爪18、18′はラチエツト9から離れ支持荷重は無
くなる。更にジヤツキ16、16′を短縮させジヤツキ
上受梁17を下降させて、爪18、18′をラチエツト
9の1ストローク下に引き込む。全部の爪18、18′
が次のラチエツト9の下に確実に移動したことをリミツ
トスイツチ等(図示せず)により確認した後、再びジヤ
ツキを伸長して爪18、18′を上昇させる。これがラ
チエツト1段分上昇のサイクル工程であり、これを必要
なラチエツト9の段数回繰り返えす事により所定の高さ
まで仮設ステージSを上昇させることができる。(図1
2乃至図15参照)図、14、15は上昇完了点の状態
を示す。 ラチエツト9の段きざみは全部の装置につい
て精度よく加工できるので、1段分の上昇過程における
差はラチエツト9の段きざみの寸法を超えることはあり
得ないし、各柱Cのセルフクライミング装置は夫々油圧
装置20を独立させ、電気的に駆動しているので、支持
する荷重による上昇速度に大きな差が生じない。従って
水平位置の制御機構を設置しなくても鉄骨構造の場合充
分に安全性の確保が可能である。According to the above system, the jack units J and J 'are first installed at the positions shown in FIG. 7 and the hydraulic unit 20 is driven to extend the jacks 16 and 16'.
Supported by the jack lower support 13, the jacks 16, 16 '
Is fixed to the column C via the beam end 11 and the receiving column 12 projecting from the column and is immovable.
The upper part of 6 'will extend upward. Claws 18, 1
8 'meshes with the ratchet 9 to support the load and the whole rod 10 rises. This means that the entire temporary gantry S is pushed up via the receiving beam 7 and the auxiliary girders 5 and 6. At this time, since the pawls 14 and 14 'are not moved and the entire ratchet 9 rises, if the ratchet 9 is moved up by one stroke, the pawls 14 and 14' are engaged with the ratchet below. After confirming by a limit switch or the like (not shown) that all the claws 14 and 14 'are completely engaged with the next ratchet 9, the jacks 16 and 16' are provided.
Is shortened, the ratchet 9 meshed with the claws 18, 18 'is obtained.
And the rod 10 descend together, so that the claws, 14, 1
The gap between the 4 'and the ratchet 9 disappears and the claws 14, 1
The 4 'and the ratchet 9 mesh with each other, and the load is supported by the claws 14, 14'. When the jacks 16, 16 'are further shortened, the pawls 18, 18' separate from the ratchet 9 and the supporting load is eliminated. Further, the jacks 16 and 16 'are shortened, and the upper jacket receiving beam 17 is lowered to pull the claws 18 and 18' one stroke below the ratchet 9. All claws 18, 18 '
Is confirmed by a limit switch or the like (not shown) after it is surely moved under the next ratchet 9, and then the jack is extended again to raise the claws 18, 18 '. This is a cycle step of raising the ratchet one stage, and by repeating this several times of the necessary number of ratchets 9, the temporary stage S can be raised to a predetermined height. (Figure 1
FIGS. 2 to 15) FIGS. 14, 15 show the state of the ascending completion point. Since the steps of the ratchet 9 can be accurately machined for all the devices, the difference in the ascending process of one step cannot exceed the size of the steps of the ratchet 9, and the self-climbing device of each column C has a hydraulic pressure. Since the device 20 is made independent and electrically driven, there is no large difference in the ascending speed due to the supporting load. Therefore, sufficient safety can be ensured in the case of a steel frame structure without installing a horizontal position control mechanism.
【0018】かくして1階分の上昇が完了すると、ジヤ
ツキ16、16′、油圧装置等を含むジヤツキシステム
J、油圧装置をつけないジヤツキシステムJ′を最初の
位置にもどすために、一旦仮設構台Sの荷重を、図5、
及び図9に示す受梁21で1度柱Cに受けさせる。この
点については後述する。セルフクライミング装置Kが上
昇用荷重から解放された後、図14及び図15において
爪14、14′、18、18′は適宜治具(図示せず)
によって互いに開くように回転させ、ラチエツト9から
確実に離脱させる。ワイヤー22、ローラ23を介して
ホイスト24を駆動させてジヤツキシステムJ、J′を
上方に距離L1分だけ引き上げ、爪14、14′、1
8、18′に取りつけた爪開き用治具を取り外し、ラチ
エツト9に爪14、14′、18、18′を噛合させ次
回の上昇に備える。When the first floor has been lifted, the jacks 16, 16 ', the jacking system J including the hydraulic device, and the jacking system J' without the hydraulic device are temporarily set in order to return to the initial position. The load on the gantry S is shown in FIG.
The column C is once received by the receiving beam 21 shown in FIG. This will be described later. After the self-climbing device K is released from the lifting load, the claws 14, 14 ', 18, and 18' are appropriately set with jigs (not shown) in FIGS.
, So as to open each other, and securely detach from the ratchet 9. The hoist 24 is driven via the wire 22 and the roller 23 to raise the jacking systems J and J 'upward by the distance L1, and the claws 14, 14', 1
The nail opening jigs attached to 8, 18 'are removed, and the claws 14, 14', 18, 18 'are engaged with the ratchet 9 to prepare for the next ascent.
【0019】これが1階分上昇の1工程である。次に前
述の仮設構台5の荷重の受梁21による一時あづけ機構
について説明すると、図5、及び図9において梁2、4
が梁端11の上端まで上昇するまでは、受梁は21′の
状態としておくが、上昇が完了し、梁2、4を僅か上方
に位置させて受梁21′は柱Cの反対側より柱Cに向っ
てジヤツキ(図示せず)その他の手段で水平に21で示
す位置まで移動させ梁端部11に支持せしめた状態とし
てボルト25で梁2、4に締めつけ、仮設構台Sの荷重
を安全建築物の架構に伝達して安定させる、この状態で
作業機械Wの稼働を行い構築を行う。仮設構台Sの上昇
に際しては受梁21より21′の状態とする。This is one step of ascending one floor. Next, a mechanism for temporarily attaching the temporary gantry 5 with the load receiving beam 21 will be described. In FIGS.
The beam is kept in the state of 21 'until the beam rises to the upper end of the beam end 11, but the lifting is completed, and the beams 2, 4 are positioned slightly above, and the beam 21' is moved from the opposite side of the column C from the opposite side. It is moved to a position indicated by 21 horizontally by a jack (not shown) or other means toward the column C and is supported on the beam end 11 and tightened on the beams 2 and 4 with bolts 25 to reduce the load on the temporary gantry S. In this state, the work machine W is operated and constructed by transmitting it to the frame of the safe building and stabilizing it. When the temporary gantry S is lifted, the temporary gantry S is set at a position 21 'from the receiving beam 21.
【0020】次に前記作業機械及びレールについて説明
すると、図1においては作業機械W及びレールRを仮設
構台Sの上面及び下面の両面を共通のものとして表現さ
れ、作業機械Wは、吊り込み、搬送、組立、接合等を行
ない、人力による直接起動、遠隔操作、自動運転を行う
ロボツト等各種作業を行う機械をレールR上を走行又は
レールR下を懸吊走行させて工事を行う。Next, the work machine and the rail R will be described. In FIG. 1, the work machine W and the rail R are expressed by using both the upper and lower surfaces of the temporary gantry S in common. Carrying, assembling, joining, etc., and performing work such as a robot that performs various operations such as a robot that performs direct start, remote control, and automatic operation by human power, runs on the rail R or runs under the rail R for construction.
【0021】次に仮設構台Sの最終処理について説明す
ると、図6、9、10、11において梁1、3はセルフ
クライミング装置Kを撤去したあと、補完梁26を梁端
部11との間に挿入し、ボルト止め溶接等の接合処理し
て本設の建物用の梁とする、又梁2、4はそのままボル
ト止め溶接等により接合を行いボルト25の取り外しを
行い、受梁21を撤去し、構造体として完成させる。Next, the final processing of the temporary gantry S will be described. In FIGS. 6, 9, 10, and 11, the beams 1 and 3 are provided with the complementary beam 26 and the beam end 11 after the self-climbing device K is removed. It is inserted and joined by bolting welding or the like to form a main building beam. The beams 2 and 4 are directly joined by bolting welding or the like, the bolt 25 is removed, and the receiving beam 21 is removed. To complete the structure.
【0022】なお、図5、6、7、9、10、11にお
いて区間aは仮設構台Sの部分、区間bは本設柱cの部
分区間Cは補完梁26を表わしている。In FIGS. 5, 6, 7, 9, 10, and 11, section a represents the portion of the temporary gantry S, section b represents the partial section C of the main column c, and the complementary beam 26 represents the complementary beam 26.
【0023】[0023]
【発明の効果】本発明によれば前記したように、建築物
構築作業中における仮設ステージとなる仮設構台は、本
設の屋上階と最上階の床として使用されるので、工事完
了後地上に回収する資材は建設用機器類のみとなり、著
しく施工が簡略化され、また仮受柱が不要となるので、
経済性に優れ、安全性が高い。According to the present invention, as described above, the temporary gantry serving as the temporary stage during the construction work of the building is used as the floor of the main rooftop and the top floor, so that the temporary gantry can be placed on the ground after the completion of the construction. The only materials to be collected are construction equipment, which significantly simplifies construction and eliminates the need for temporary pillars.
Excellent economy and high safety.
【0024】また本発明によれば、柱は複数階の長さの
ものを自由に選択できるので、接合個所が削減され、施
工精度、作業性、経済性が大幅に改善される。更にまた
施工時、前記仮設構台が常に最上層に位置するので雨天
においても作業が行なわれ、また前記仮設構台の下部を
走行する各種機器は屋内型の仕様となり故障の発生を軽
減し、工費を節減しうるものである。Further, according to the present invention, the columns can be freely selected to have a length of a plurality of floors, so that the number of joints is reduced, and the construction accuracy, workability and economy are greatly improved. Furthermore, at the time of construction, since the temporary gantry is always located on the uppermost layer, work is performed even in rainy weather.In addition, various devices traveling under the temporary gantry have indoor-type specifications to reduce the occurrence of failures and reduce construction costs. It can save money.
【図1】本発明の方法によって構築される建築物の平面
及び仮設構台とこれに設置される機械との関係を示す平
面図である。FIG. 1 is a plan view showing the relationship between a plane of a building constructed by a method of the present invention, a temporary gantry, and machines installed on the temporary gantry.
【図2】地表部分における仮設構台及び建設機器の位置
関係を示す立面図である。FIG. 2 is an elevation view showing a positional relationship between a temporary gantry and construction equipment on a ground surface portion.
【図3】仮設構台が1階分上昇した状態を示す立面図で
ある。FIG. 3 is an elevation view showing a state in which a temporary gantry has risen by one floor.
【図4】仮設構台が更に1階分上昇した段階で、その下
部における施工状態を説明する立面図である。FIG. 4 is an elevation view illustrating a construction state of a lower part of the temporary gantry when the temporary gantry is further raised by one floor.
【図5】柱、仮設構台、セルフクライミング装置の関係
を示す平面図である。FIG. 5 is a plan view showing a relationship between a pillar, a temporary gantry, and a self-climbing device.
【図6】仮設構台最上層まで到達し、セルフクライミン
グ装置を取り外した後、柱と梁とを接合した状態を示す
平面図である。FIG. 6 is a plan view showing a state in which a column and a beam are joined after reaching a top of a temporary gantry, removing a self-climbing device, and removing the self-climbing device.
【図7】仮設構台の上昇する前の状態を示す立面図であ
る。FIG. 7 is an elevation view showing a state before the temporary gantry is raised.
【図8】図7の矢視イ−イ図である。FIG. 8 is a view taken along the arrow in FIG. 7;
【図9】図5の矢視ロ−ロ図及び図7の矢視ハ−ハ、ニ
−ニ図である。9 is a roll view as seen in the direction of the arrow in FIG.
【図10】図6の矢視ホ−ホ図である。FIG. 10 is a view as viewed from the direction of the arrow in FIG. 6;
【図11】図6の矢視ヘ−ヘ図である。FIG. 11 is a view taken in the direction of arrows in FIG. 6;
【図12】仮設構台が階の中間まで上昇した状態を示す
立面図である。FIG. 12 is an elevational view showing a state where the temporary gantry has risen to the middle of the floor.
【図13】図12の矢視ト−ト図である。FIG. 13 is a view as viewed from the direction of the arrow in FIG. 12;
【図14】仮設構台が次の階まで上昇を完了した状態を
示す立面図である。FIG. 14 is an elevation view showing a state in which the temporary gantry has completed ascending to the next floor.
【図15】図14の矢視チ−チ図である。FIG. 15 is a view in the arrow direction of FIG. 14;
B 構造体 C 本設柱 C1 本設柱第1ユニツト C2 本設柱第2ユニツト F 作業ロボツト G 部材 J ジヤツキユニツト J′ ジヤツキユニツト K セルフクライミング装置 K′ セルフクライミング装置 R レール S 仮設構台 W 作業機械 1 屋上階の梁 2 最上階の梁 3 最上階の梁 4 最上階の梁 5 補助桁 6 補助桁 7 受梁 8 受梁 9 ラチエツト 10 ロツド 11 梁端部 12 受梁 13 ジヤツキ下受梁 14 爪 14′爪 15 軸 15′軸 16 ジヤツキ 16′ジヤツキ 17 受梁 17′受梁 18 爪 18′爪 19 軸 19′軸 20 油圧装置 21 受梁 21′受梁 22 ワイヤー 23 ローラ 24 ホイスト 25 ボルト 26 補完梁 B Structure C Main column C1 Main column first unit C2 Main column second unit F Working robot G member J Jack unit J 'Jack unit K Self climbing device K' Self climbing device R Rail S Temporary gantry W Work machine 1 Roof Floor beam 2 Top floor beam 3 Top floor beam 4 Top floor beam 5 Auxiliary girder 6 Auxiliary girder 7 Receiving beam 8 Receiving beam 9 Ratchet 10 Rod 11 Beam end 12 Receiving beam 13 Lower receiving beam 14 Claw 14 ′ Claw 15 Axis 15 'Axis 16 Jack 16' Jack 17 Receiving beam 17 'Receiving beam 18 Claw 18' Claw 19 Axis 19 'Axis 20 Hydraulic device 21 Receiving 21' Receiving beam 22 Wire 23 Roller 24 Hoist 25 Bolt 26 Complementary beam
───────────────────────────────────────────────────── フロントページの続き (72)発明者 中田 昌眞 東京都渋谷区千駄ヶ谷四丁目6番15号 株式会社フジタ内 (72)発明者 永易 修 東京都渋谷区千駄ヶ谷四丁目6番15号 株式会社フジタ内 (72)発明者 野々山 登 東京都渋谷区千駄ヶ谷四丁目6番15号 株式会社フジタ内 (56)参考文献 特開 平4−237764(JP,A) 特開 平4−146345(JP,A) 特開 平4−94390(JP,A) 特開 平3−257236(JP,A) 特開 平3−81434(JP,A) ────────────────────────────────────────────────── ─── Continuing on the front page (72) Inventor Masamasa Nakata 4-6-115 Sendagaya, Shibuya-ku, Tokyo Fujitanai Co., Ltd. (72) Osamu Nagayasu 4-6-115 Sendagaya, Shibuya-ku, Tokyo Co., Ltd. In Fujita (72) Inventor Noboru Nonoyama 4-6-15 Sendagaya, Shibuya-ku, Tokyo Fujita Incorporated (56) References JP-A-4-237764 (JP, A) JP-A-4-146345 (JP, A JP-A-4-94390 (JP, A) JP-A-3-257236 (JP, A) JP-A-3-81434 (JP, A)
Claims (1)
の各床組との間に、本設柱より突設された梁端部に支持
されて上昇するセルフクライミング装置を取付けてなる
仮設構台を構成し、同仮設構台における上梁の上面及び
下梁の下面に夫々レールを敷設するとともに同各レール
上を走行またはレール下に懸吊される資材搬送、部材組
立及び接合用機器を装架し、同機器によって柱、梁、床
等の部材を組立て、一層分の組立作業が完了すると前記
セルフクライミング装置を介して前記仮設構台を上昇さ
せて前記の組立作業を繰返し、以下前記の組立作業を反
覆して所要階数の部材を組立て、最終的に前記仮設構台
を屋上階及び最上階の梁として柱に接合することを特徴
とする建築物の構築方法。1. A self-climbing device, which is supported by an end of a beam protruding from a main pillar, and is mounted between a roof group and a floor group that finally become a main beam. A temporary gantry is constructed, and rails are respectively laid on the upper surface of the upper beam and the lower surface of the lower beam in the temporary gantry, and the material is transported on each rail or suspended under the rail. Mount the equipment, assemble the pillars, beams, floor and other members by the same equipment, when the assembly work for one layer is completed, raise the temporary gantry via the self-climbing device and repeat the assembly work, A method of constructing a building, comprising: assembling members of a required number of floors by repeating the above-mentioned assembling work, and finally joining the temporary gantry to a pillar as a beam on a rooftop floor and a top floor.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4338191A JP2622313B2 (en) | 1991-03-08 | 1991-03-08 | How to build a building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4338191A JP2622313B2 (en) | 1991-03-08 | 1991-03-08 | How to build a building |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH04281961A JPH04281961A (en) | 1992-10-07 |
JP2622313B2 true JP2622313B2 (en) | 1997-06-18 |
Family
ID=12662240
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP4338191A Expired - Fee Related JP2622313B2 (en) | 1991-03-08 | 1991-03-08 | How to build a building |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2622313B2 (en) |
-
1991
- 1991-03-08 JP JP4338191A patent/JP2622313B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH04281961A (en) | 1992-10-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CA1329633C (en) | Construction apparatus and construction method | |
JP2622313B2 (en) | How to build a building | |
CN110924630A (en) | Integrated steel structure hoistway with waiting hall and construction process thereof | |
CN216811161U (en) | Modular structure of airport terminal corridor | |
JP3078931B2 (en) | Climbing stage method and chimney construction method for tubular structures | |
JP3040309B2 (en) | Construction method of multi-layer suspension structure | |
JP2002235443A (en) | Intermediate story steel frame traveling construction method | |
JPH074049A (en) | Construction method of building | |
JP3177735B2 (en) | An erect scaffold used to reinforce the perimeter of existing buildings | |
JP3192543B2 (en) | Building demolition method | |
JPH08333898A (en) | Trestle for vertically and horizontally conveying building blocks | |
JPH0833032B2 (en) | Construction method of building frame | |
JP2683171B2 (en) | Construction transport scaffolding equipment | |
JP3115942B2 (en) | Building construction method | |
JP2761526B2 (en) | How to build structures | |
JP2835880B2 (en) | High-rise building frame construction method | |
JP3439545B2 (en) | Construction method of multi-story parking lot | |
JPS6237439A (en) | Traveling method | |
JPS5847803A (en) | Bridge crane | |
JP3543247B2 (en) | Temporary living support bracket | |
JP2761528B2 (en) | How to build structures | |
JP2627705B2 (en) | Automatic frame assembly method | |
JPH0791603A (en) | Assembly parallel progressing method for large suspension type boiler | |
CN118257351A (en) | Non-pressure construction method for cantilever steel truss lower hanging inclined suspender construction process | |
JPH0633609A (en) | Top house system for constructing operation of building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |