JP2862681B2 - Elevator installation method for construction using this equipment - Google Patents

Elevator installation method for construction using this equipment

Info

Publication number
JP2862681B2
JP2862681B2 JP783991A JP783991A JP2862681B2 JP 2862681 B2 JP2862681 B2 JP 2862681B2 JP 783991 A JP783991 A JP 783991A JP 783991 A JP783991 A JP 783991A JP 2862681 B2 JP2862681 B2 JP 2862681B2
Authority
JP
Japan
Prior art keywords
elevator
equipment
construction
hoistway
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP783991A
Other languages
Japanese (ja)
Other versions
JPH04243786A (en
Inventor
健壽 松原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP783991A priority Critical patent/JP2862681B2/en
Publication of JPH04243786A publication Critical patent/JPH04243786A/en
Application granted granted Critical
Publication of JP2862681B2 publication Critical patent/JP2862681B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、建築工事中の建物に付
設されて該建築工事の進行に合わせ順次高くしながら作
業者や建築資材等の運搬に利用される工事用エレベータ
の据付方法に関し、特に建築工事完了後も建物に残され
て本設エレベータとして利用される本設用品使用の工事
用エレベータ据付方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for installing a construction elevator which is attached to a building under construction and used for transporting workers and building materials while the height of the building is gradually increased as the construction proceeds. In particular, the present invention relates to a method of installing a construction elevator using a main article which is left in a building even after completion of construction work and is used as a main elevator.

【0002】[0002]

【従来の技術】近年、法規制の緩和や土地の有効利用か
ら建物の高層化が進む一方、人手不足などから建築作業
能率の向上のために、建築工事現場では建物の鉄骨が最
上階まで組み上げ完了してからエレベータを据付けるの
ではなく、途中階まで鉄骨が立ち上がった時点で当該建
物に工事用エレベータを仮設して、建築作業者や小物資
材などの運搬に利用すると共に、建築工事の進行により
建物の鉄骨が高くなるに伴い該エレベータの昇降行程を
高くして、エレベータのサービス階を増して行く方式が
多くなって来ている。
2. Description of the Related Art In recent years, buildings have been raised to a higher floor due to deregulation and effective use of land, while steelwork of buildings has been assembled to the top floor at building construction sites in order to improve the efficiency of building work due to labor shortages. Instead of installing the elevator after completion, when the steel frame rises to the middle floor, a construction elevator is temporarily installed in the building and used for transporting building workers and small materials, and progress of building construction As the steel frame of the building becomes higher, the method of increasing the elevator ascending and descending steps and increasing the service floor of the elevator is increasing.

【0003】その従来の工事用エレベータとしては、図
2に示すように仮設用品を主体としたライズアップエレ
ベータが一般的である。これは建築工事中の建物にエレ
ベータ昇降路1を構築し、その昇降路1内の上方途中階
に受ビーム2を建物の梁3に横架する状態に仮設し、こ
の受ビーム2上に仮設用機械室4を載置保持する。この
仮設用機械室4はクレーン等により昇降路1内を順次上
昇移動できるように設計した小サイズのもので、この機
械室4内に仮設用品の巻上機5やエレベータ運転制御盤
6等をコンパクトに収納している。またその仮設用機械
室4内の巻上機5の巻上シーブに仮設用ロープ7を巻き
掛けて下方に垂下し、この仮設用ロープ7を介して仮設
用の乗かご8とつり合いおもり9を昇降路1内に吊持
し、これらを巻上機5の駆動により上下動して建築作業
者や小物資材などの運搬を行い得るようにしている。
As a conventional construction elevator, a rise-up elevator mainly composed of temporary articles is generally used as shown in FIG. In this method, an elevator shaft 1 is constructed in a building under construction, and a receiving beam 2 is temporarily installed on the upper halfway floor in the hoistway 1 so as to lie on a beam 3 of the building. Machine room 4 is placed and held. This temporary machine room 4 is of a small size designed to be able to move up and down the hoistway 1 sequentially by a crane or the like. In this machine room 4, a hoisting machine 5 for temporary articles and an elevator operation control panel 6 are installed. It is stored compactly. Further, a temporary rope 7 is wound around a hoisting sheave of a hoisting machine 5 in the temporary machine room 4 and hangs downward, and a temporary car 8 and a counterweight 9 are suspended via the temporary rope 7. They are suspended in the hoistway 1 and are moved up and down by the drive of the hoisting machine 5 so that construction workers and small articles can be transported.

【0004】しかし、こうした仮設用品を主体とした従
来の工事用エレベータ方式においては、建築工事期間中
には便利であるが、建物の鉄骨が最上階まで完成して、
本設エレベータを据付ける時点では、仮設用品を撤去
し、その後に本設用品を据付けなければならず、その撤
去作業並びに本設作業に多くの手間と時間がかかると共
に、その作業期間中はエレベータ稼働サービスができず
不便である。また仮設用品を多く使用するために費用が
多くかかり、建築費の高騰を招く欠点があった。
[0004] However, in the conventional elevator system for construction mainly using temporary articles, although it is convenient during the construction period, the steel frame of the building is completed to the top floor,
At the time of installing the permanent elevator, it is necessary to remove the temporary equipment and then install the permanent equipment.The removal work and the installation work take a lot of time and effort, and during the work period, Operation service is not available, which is inconvenient. In addition, there is a drawback in that a large amount of cost is required to use a large number of temporary articles, resulting in a rise in construction costs.

【0005】そこで、その欠点を解消する方策として、
特公昭52−2177号公報に提唱されている工事用エ
レベータの据付方法がある。この方法では出来るだけ多
くの本設用品を使用することにより、仮設用品の撤去作
業を省略しようとしたもので、本設用のエレベータ機械
室用品を複数個のコンテナに分配収納し、これら複数の
コンテナを昇降路内に配設して、建築工事の進行に伴い
上昇移動させて行くものである。
[0005] Therefore, as a measure to solve the disadvantage,
There is a method of installing a construction elevator proposed in Japanese Patent Publication No. 52-2177. In this method, as many temporary equipment as possible are used, the removal of the temporary equipment is omitted, and the elevator machine room equipment for the temporary installation is distributed and stored in a plurality of containers. Containers are arranged in the hoistway and are moved up and down as the construction work progresses.

【0006】[0006]

【発明が解決しようとする課題】ところで、前記提案の
工事用エレベータ据付方法では、本設用品を多く使用し
ているので、最終的には本設エレベータへの移行が比較
的楽であるが、制御等の複雑な本設のエレベータ機械室
用品(巻上機等の機構装置用品並びにエレベータ運転制
御盤等の電気制御装置用品)を一緒にコンパクトにまと
めて狭い昇降路内に上昇移動可能に設置するには無理が
あり、特にそれらエレベータ機械室用品を昇降路内に平
面的に並べて配置することはとても無理であって、前述
の如く複数個のコンテナに分配収納し、これらを複数段
に積み重ねて昇降路内に密集して配設しなければならな
い。このためにコンテナ個数が多く、昇降路内への配置
並びに上昇移動作業が面倒であると共に、スペース的に
余裕が無く、それら機械室用品の保守・点検が大変であ
る。
By the way, in the above-mentioned proposed method of installing a construction elevator, since a large number of permanent installations are used, it is relatively easy to make a final transition to the permanent elevator. Elevator machine room supplies (mechanical equipment supplies such as hoisting machines and electric control equipment supplies such as elevator operation control panels) are installed together so that they can be moved up and down in narrow hoistways. It is extremely difficult to arrange the elevator machine room supplies in a plane in the hoistway, and it is extremely difficult to distribute and store them in a plurality of containers as described above and stack them in a plurality of stages. Must be densely arranged in the hoistway. For this reason, the number of containers is large, the arrangement in the hoistway and the ascending and moving work are troublesome, and there is no room in space, so that maintenance and inspection of the machine room supplies are difficult.

【0007】また、前記機械室用品の各コンテナを防水
処理しても、昇降路内には上部が建築途中で開放してい
るので雨水が入り、該昇降路内のガイドレールや各種検
知器や乗かご並びにつり合いおもり等の本設用品に雨水
がかかり、建築工事完了頃には損傷や汚損が酷く、本設
エレベータとして使い物にならない問題が発生する。
[0007] Even if each container of the machine room supplies is waterproofed, rainwater enters the hoistway because the upper part is open during construction, and guide rails, various detectors and the like in the hoistway are provided. Rainwater is applied to the equipment such as a car and a counterweight, and when the construction work is completed, damage and stains are severe, causing a problem that the elevator cannot be used as a permanent elevator.

【0008】更には、建築工事現場は高温・多湿の環境
となることが多く、こうした環境条件に敏感なエレベー
タ運転制御盤の基板等の電気制御装置用品のトラブルが
発生する不都合がある。
Further, the construction site often has a high-temperature and high-humidity environment, and there is an inconvenience that electrical control equipment such as a board of an elevator operation control panel, which is sensitive to such environmental conditions, causes trouble.

【0009】本発明は前記事情に鑑みなされ、その第1
の目的とするところは、制御等の複雑な本設用のエレベ
ータ機械室用品の設置並びに上昇移動が簡単で、且つス
ペース的に余裕ができて保守・点検が容易となると共
に、最終的には本設エレベータへの移行が楽にできるよ
うになる本設用品使用の工事用エレベータ据付方法を提
供することにある。
The present invention has been made in view of the above circumstances,
The purpose of the above is to easily install and move the elevator machine room supplies for complicated main construction such as control, as well as to allow sufficient space for maintenance and inspection, and finally, It is an object of the present invention to provide a construction elevator installation method using a permanent installation, which makes it easy to shift to a permanent elevator.

【0010】第2の目的とするところは、本設用のエレ
ベータ機械室用品ばかりか昇降路内用品も建築工事中に
おける雨水等の防水対策が十分で、損傷・汚損防止等の
養生が図れて、最終的にはそのまま本設エレベータとし
て使用できるようになる本設用品使用の工事用エレベー
タ据付方法を提供することにある。
A second object is to provide not only elevator machine room articles for main construction but also articles in the hoistway sufficient for waterproofing against rainwater and the like during construction work, and to prevent damage and contamination. Another object of the present invention is to provide a method of installing a construction elevator using a main article, which can finally be used as a main elevator as it is.

【0011】第3の目的とするところは、高温・多湿の
建築工事現場の環境下であっても、エレベータ運転制御
盤の基板等の電気制御装置用品のトラブルの発生を防止
できる本設用品使用の工事用エレベータ据付方法を提供
することにある。
A third object of the present invention is to use the main equipment which can prevent the trouble of the electric control equipment such as the board of the elevator operation control panel even in the environment of a high-temperature and high-humidity construction work site. It is an object of the present invention to provide a construction elevator installation method.

【0012】[0012]

【課題を解決するための手段及び作用】第1の発明の本
設用品使用の工事用エレベータ据付方法は、前記第1の
目的を達成するために、建築工事中の建物に本設用のエ
レベータ昇降路を構築して行くと共に、本設用のエレベ
ータ機械室用品のうち、巻上機等の機構装置用品とエレ
ベータ運転制御盤等の電気制御装置用品とを分離して各
々ユニット化し、その機構装置用品ユニットを前記昇降
路内の上方適当位置に設置する一方、これと隣接する建
物側に前記電気制御装置用品ユニットを設置し、且つ前
記機構装置用品ユニットの巻上機に巻き掛けたロープを
介し本設用のかご及びつり合いおもりを昇降路内に昇降
駆動可能に設置し、この状態で工事用エレベータとして
利用しながら、建築工事の進行により建物が高くなるに
伴い前記機構装置用品ユニットを昇降路内の上方に順次
移設すると共に、電気制御装置用品ユニットを建物の上
層階に順次移設させ、最終的には建物上部の本設用のエ
レベータ機械室に前記機構装置用品と電気制御装置用品
とを移設することを特徴とする。
According to a first aspect of the present invention, there is provided a method of installing an elevator for use of a construction equipment using a permanent installation in a building under construction in order to achieve the first object. Along with the construction of the hoistway, mechanical equipment such as a hoist and electrical control equipment such as an elevator operation control panel among elevator machine room supplies for main construction are separated and unitized, and the mechanism is constructed. While installing the equipment supply unit at an appropriate position above the hoistway, installing the electric control equipment supply unit on the building side adjacent to the equipment supply unit, and attaching a rope wrapped around a hoist of the mechanism equipment supply unit. A car and counterweight for permanent installation are installed in the hoistway so as to be able to be driven up and down in the hoistway, and while using as an elevator for construction in this state, as the building becomes higher due to the progress of building work, the mechanical device Product units are sequentially transferred to the upper part of the hoistway, and the electrical control device supply units are sequentially transferred to the upper floors of the building. The present invention is characterized in that a control device article is relocated.

【0013】こうした据付方法であれば、制御等の複雑
な本設用のエレベータ機械室用品のうち、巻上機等の機
構装置用品が一つのユニットとして建築工事中の建物の
昇降路内に楽に設置できる一方、エレベータ運転制御盤
等の電気制御装置用品が別のユニットとして隣接する建
物側のフロアなどに楽に設置でき、且つそれらの設置ス
ペースに余裕ができるので保守・点検が容易となる。ま
たその機構装置用品並びに電気制御装置用品をそれぞれ
のユニットごとに順次建築工事の進展に伴い楽に上方に
移設できて、工事用エレベータとして簡便に利用できる
ようになる。そして、最終的には建物上部の本設用のエ
レベータ機械室に前記機構装置用品と電気制御装置用品
とを移設することで、短期間でそのまま本設エレベータ
として利用できるようになる。
According to such an installation method, among the equipment for the elevator machine room for complex installation such as control, the equipment for the mechanical device such as the hoist can be easily installed as one unit in the hoistway of the building under construction. On the other hand, electric control equipment such as an elevator operation control panel can be easily installed as a separate unit on an adjacent building floor or the like, and the space for installing them can be easily provided, so that maintenance and inspection can be facilitated. In addition, the mechanical equipment supplies and the electric control equipment supplies can be easily relocated upward along with the progress of construction work for each unit, and can be easily used as a construction elevator. Finally, by transferring the mechanical device supplies and the electric control device supplies to the permanent elevator machine room at the top of the building, they can be used as a permanent elevator in a short period of time.

【0014】第2の発明は、前述の本設用品使用の工事
用エレベータ据付方法において、建築中の建物の昇降路
内に機構装置用品ユニットの上面を覆う雨避けを設けて
おくことで、建築工事中に昇降路内に雨水等が侵入する
ことがなく、防水対策が十分で、その昇降路内の前記機
構装置用品は勿論のこと、その他の乗かごや各種スイッ
チ類などの昇降路内用品も雨水等で濡れることがなくな
り、且つ昇降路内に雨水等が入らないので隣接する建物
側に設置した電気制御装置用品も雨水等で濡れることが
少なくなる。これにて各種本設用品が工事用エレベータ
として使用中に損傷・汚損されるようなことがなく、そ
のまま最終的に本設エレベータとして支障なく使用でき
るようになる。
According to a second aspect of the present invention, in the above-described method of installing a construction elevator using the main equipment, a rain shield for covering the upper surface of the mechanical equipment supply unit is provided in the hoistway of the building under construction. There is no rainwater or the like entering the hoistway during construction, and sufficient waterproofing measures are taken, and not only the above-mentioned mechanism device supplies in the hoistway, but also other hoistway goods such as cars and various switches. Since it does not get wet with rainwater or the like and rainwater or the like does not enter the hoistway, electric control equipment installed on the adjacent building side is less likely to get wet with rainwater or the like. As a result, there is no possibility that the various main articles are damaged or soiled during use as the construction elevator, and the final article can be finally used as it is without any trouble.

【0015】[0015]

【0016】[0016]

【実施例】以下、本発明の本設用品使用の工事用エレベ
ータ据付方法の一実施例を図1(a)(b)(c)に基
づいて説明する。まず図1(a)に示す如く建築工事中
の建物に本設用のエレベータ昇降路(エレベータシャフ
ト)11を構築して行く。そして建物が適当階高となっ
たら、そのエレベータ昇降路11内の適当階位置に受ビ
ーム12を建物の梁13に横架する状態に仮設する。ま
た本設用のエレベータ機械室用品のうち、巻上機14a
等の機構装置用品14とエレベータ運転制御盤15a等
の電気制御装置用品15とを分離して各々14A及び1
5Aに示す如くユニット化する。なおその機構装置用品
ユニット14Aは各種機構装置用品14をひとまとめに
クレーン等により昇降路11内に引き上げ可能に且つ最
終的には容易に解体可能にコンパクトな枠体に内蔵した
構成とする。また前記電気制御装置用品ユニット15A
はこれも各種電気制御用品15をひとまとめに上方階へ
可般可能に且つ最終的には容易に解体可能にコンパクト
な枠体に内蔵した構成とする。そして前記機構装置用品
ユニット14Aは前記昇降路11内の受ビーム12上に
設置する一方、これと同じ高さの階で隣接する建物側の
フロア16上などに前記電気制御装置用品ユニット15
Aを設置する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of a method of installing an elevator for construction using the present equipment according to the present invention will be described below with reference to FIGS. 1 (a), 1 (b) and 1 (c). First, as shown in FIG. 1A, an elevator hoistway (elevator shaft) 11 for permanent construction is constructed in a building under construction. Then, when the building has an appropriate floor height, the receiving beam 12 is temporarily mounted on the beam 13 of the building at an appropriate floor position in the elevator shaft 11. Also, of the elevator machine room supplies for main construction, the hoisting machine 14a
And the like and the electrical control equipment supplies 15 such as the elevator operation control panel 15a are separated into 14A and 1A respectively.
Unitize as shown in 5A. The mechanism device supply unit 14A has a structure in which various mechanism device supplies 14 are collectively incorporated into a hoistway 11 by a crane or the like and can be easily disassembled in a compact frame. The electric control device supply unit 15A
This also has a structure in which the various electric control articles 15 are incorporated in a compact frame so that they can be moved to the upper floor collectively and finally easily disassembled. The mechanical device supply unit 14A is installed on the receiving beam 12 in the hoistway 11, while the electric control device supply unit 15A is placed on a floor 16 on the adjacent building side at the same height.
A is installed.

【0017】この状態で、前記機構装置用品ユニット1
4Aの巻上機14aの巻上シーブにロープ17を巻き掛
けて昇降路11内下方に垂下し、このロープの一端に本
設用の乗かご18を吊持し、他端に本設用のつり合いお
もり19を吊持して、それら乗かご18とつり合いおも
り19とを昇降路11内に昇降駆動可能に設置する。
In this state, the mechanism device article unit 1
A rope 17 is wound around the hoisting sheave of the 4A hoisting machine 14a and hangs down in the hoistway 11, and a car cage 18 is hung on one end of the rope, and the other end of the rope is hung on the other end. The counterweight 19 is suspended, and the car 18 and the counterweight 19 are installed in the hoistway 11 so as to be capable of driving up and down.

【0018】なお、図中20及び21は昇降路11内に
付設された乗かご及びつり合いおもり用のガイドレー
ル、22,23は昇降路11内底部に立設された衝撃緩
衝用のバファーである。これらはいずれも本設用のもの
である。また図中24は建築用足場、25は移動足場で
ある。
In the drawings, reference numerals 20 and 21 denote guide rails provided in the hoistway 11 for a car and a counterweight, and reference numerals 22 and 23 denote shock-buffering buffers erected on the bottom of the hoistway 11. . These are all for permanent installation. In the figure, reference numeral 24 denotes an architectural scaffold, and reference numeral 25 denotes a moving scaffold.

【0019】以上で低層階までの工事用エレベータの据
付が終了する。この状態で、前記電気制御装置用品15
により制御しながら、機構装置用品14の巻上機14a
の回転駆動によりロープ17を介し乗かご18とつり合
いおもり19を昇降路11内に昇降せて工事用エレベー
タとして稼働運転して、建築作業者や小物資材などの運
搬に利用する。
Thus, the installation of the construction elevator to the lower floor is completed. In this state, the electric control device article 15
The hoisting machine 14a of the mechanism device article 14
The weight 19 is lifted and lowered into the hoistway 11 via the rope 17 by the rotational drive of the elevator, and the weight 19 is operated and operated as a construction elevator to be used for transporting construction workers and small materials.

【0020】この際、前記昇降路11内には前記機構装
置用品ユニット14Aの上面を覆う雨避け26を仮設す
る。この雨避け26は防水養生板で、昇降路11内に蓋
をする状態に水平に取付ける。これで建築工事中におけ
る建物の上方からの雨水等が昇降路11内の雨避け26
より下方に侵入するのを防止して、前記機構装置用品ユ
ニット14Aの各機構装置洋品14や、その他の乗かご
18やつり合いおもり19や各種スイッチ類などの昇降
路内用品が雨水等で濡れないようにすると共に、電気制
御装置用品ユニット15Aを設置した建物側のフロア1
6への昇降路11内からの雨水等の侵入も防止する。
At this time, a rain shield 26 is temporarily provided in the hoistway 11 to cover the upper surface of the mechanical device supply unit 14A. The rain shield 26 is a waterproof curing plate, which is mounted horizontally so as to cover the hoistway 11. With this, rainwater or the like from above the building during the construction work avoids rain in the hoistway 11.
It is prevented from penetrating further downward, and the equipment in the hoistway, such as each of the mechanical equipment western goods 14 of the mechanical equipment supply unit 14A, the other car 18, the counterweight 19, and various switches, is not wet by rainwater or the like. And the floor 1 on the building side where the electric control device supply unit 15A is installed.
Also, intrusion of rainwater and the like from the inside of the hoistway 11 into the shaft 6 is prevented.

【0021】また、前記電気制御装置用品ユニット15
Aが設置された建物側のフロア16は、その周囲の建物
の壁も大部分できていることになるので、雨水の侵入は
少ないが、雨水対策を完璧にすべく該電気制御装置用品
ユニット15Aを防水カバー等の防水養生27により覆
っておくと共に、そのユニット15A内部には温度及び
湿度センサー28を設け、これらセンサー28からの信
号により該ユニット15A内の温度及び湿度を一定範囲
内に維持管理するクーラーなどの空調器(図示せず)を
備える。これにて高温・多湿の建築工事現場の環境下で
あっても、電気制御装置用品15の環境改善を図るよう
にする。
The electric control device supply unit 15
The floor 16 on the building side where A is installed also has a large part of the walls of the surrounding buildings, so that the intrusion of rainwater is small, but the electric control device supply unit 15A for perfecting the measures against rainwater. Is covered with a waterproof cover 27 such as a waterproof cover, and a temperature and humidity sensor 28 is provided inside the unit 15A, and the temperature and humidity in the unit 15A are maintained within a certain range by a signal from these sensors 28. An air conditioner (not shown) such as a cooler is provided. Thus, the environment of the electric control device article 15 can be improved even in the environment of a high-temperature and high-humidity construction site.

【0022】次に、前述の如く低層階のサービスをして
いた工事用エレベータを、建築工事の進行により建物が
高くなるに伴い中層階までライズアップする時には、ま
ず前記昇降路11内に仮設した雨避け26を取り外す。
また昇降路11を高く増設する。この状態で図1(b)
に示す如く機構装置用品ユニット14Aをクレーン29
等により昇降路11内の上方に吊り上げる。この際、受
ビーム12は一旦取り外す。またつり合いおもり19は
昇降路11内下端部に下ろし、乗かご18は機構装置用
品ユニット14Aの下部にワイヤ等によりぶら下げて、
ロープ17を外しておく。この状態で機構装置用品ユニ
ット14を乗かご18と一緒に中層階の位置に吊り上げ
て移動し、そこで再度前記受ビーム12を梁13に横架
して機構装置用品ユニット14を載架保持する。一方、
前記電気制御装置用品ユニット15Aは機構装置用品ユ
ニット14と分離しているので、この電気制御装置用品
ユニット15Aのみでれば昇降路11内で引き上げなく
ともよく、他の揚重リフト(図示せず)でもって建物の
中層階のフロア16aに運搬して移設する。
Next, when the construction elevator, which had been providing the service on the lower floor as described above, was raised to the middle floor as the building became higher as the construction work progressed, the elevator was first temporarily installed in the hoistway 11. Remove rain guard 26.
Also, the hoistway 11 is increased. In this state, FIG.
As shown in FIG.
It is lifted upward in the hoistway 11 by the above method. At this time, the receiving beam 12 is temporarily removed. Also, the counterweight 19 is lowered to the lower end of the inside of the hoistway 11, and the car 18 is hung by a wire or the like below the mechanism device supply unit 14A.
Remove the rope 17. In this state, the mechanism device supply unit 14 is lifted and moved together with the car 18 to the position of the middle floor, whereupon the receiving beam 12 is laid again on the beam 13 and the mechanism device supply unit 14 is mounted and held. on the other hand,
Since the electric control device supply unit 15A is separated from the mechanical device supply unit 14, if only the electric control device supply unit 15A is used, it is not necessary to lift the electric control device supply unit 15 in the hoistway 11, and other lifting lifts (not shown) ) To transport and relocate to the middle floor 16a of the building.

【0023】こうして中層階に移設した機構装置用品ユ
ニット14Aの巻上機14aの巻上シーブに図1(c)
に示す如く長尺化したロープ17aを巻き掛け、このロ
ープ17aに前記乗かご18とつり合いおもり19とを
吊持する。これで中層階までの工事用エレベータとして
運転稼働可能にすると共に、昇降路11内の機構装置用
品ユニット14Aの上面を覆う雨避け26を再度仮設
し、また電気制御装置用品ユニット15A内の温度及び
湿度を空調器により一定範囲内に維持管理する。
The hoisting sheave of the hoisting machine 14a of the mechanism device article unit 14A thus moved to the middle floor is shown in FIG.
The rope 17a, which is elongated as shown in FIG. 1, is wound around the rope 17a, and the car 18 and the counterweight 19 are hung on the rope 17a. This makes it possible to operate as an elevator for construction up to the middle floor, and to temporarily re-install the rain evasion 26 covering the upper surface of the mechanical device supply unit 14A in the hoistway 11, and to control the temperature and the temperature in the electric control device supply unit 15A. Humidity is maintained within a certain range by an air conditioner.

【0024】更に建築工事の進行により建物が高くなっ
て高層階までライズアップする時も前記同様に行う。そ
して建物の鉄骨等の構造体が最上階まで組み上がった最
終的には、その建物の上部に図示しないが本設用のエレ
ベータ機械室を設け、この機械室内に前記機構装置用品
ユニット14Aを引き上げ、そのユニットを解体しなが
ら巻上機等の各種機構装置洋品14を所定の配置に据付
ると共に、電気制御装置用品ユニット15も前記機械室
内に搬入して解体し、そのまま各電気制御装置用品15
を所定の配置に据付る。これで本設エレベータとして運
転稼働できるようになす。
Further, when the building is raised due to the progress of the construction work and rises to a higher floor, the same operation as described above is performed. Finally, when the structure such as the steel frame of the building is assembled to the top floor, an elevator machine room (not shown) for permanent construction is provided at the top of the building, and the mechanism device supply unit 14A is lifted into the machine room. While disassembling the unit, the various mechanical devices such as the hoisting machine 14 are installed in a predetermined arrangement, and the electric control device supply unit 15 is also carried into the machine room and disassembled.
Is installed in a predetermined arrangement. This enables the operation and operation as a permanent elevator.

【0025】[0025]

【発明の効果】本発明の本設用品使用の工事用エレベー
タ据付方法は、前述の如くなしたから、制御等の複雑な
本設用のエレベータ機械室用品のうち、巻上機等の機構
装置用品が一つのユニットとして建築工事中の建物の昇
降路内に楽に設置できる一方、エレベータ運転制御盤等
の電気制御装置用品が別のユニットとして隣接する建物
側に楽に設置でき、且つそれらの設置スペースに余裕が
できるので保守・点検が容易となる。またその機構装置
用品並びに電気制御装置用品をそれぞれのユニットごと
に順次建築工事の進展に伴い楽に上方に移設できて、工
事用エレベータとして簡便に利用でき、最終的には建物
上部の本設用のエレベータ機械室に前記機構装置用品と
電気制御装置用品とを移設することで、短期間でそのま
ま本設エレベータとして利用できる効果が得られる。
As described above, the method for installing an elevator for construction using permanent equipment according to the present invention is as described above. Therefore, among the equipment for an elevator machine room for permanent installation having complicated controls, mechanical devices such as a hoist. Supplies can be easily installed as a single unit in the hoistway of a building under construction, while electrical control equipment such as an elevator operation control panel can be easily installed as a separate unit on the adjacent building side, and their installation space. Maintenance and inspection becomes easy. In addition, the mechanical equipment supplies and electric control equipment supplies can be easily relocated upward along with the progress of construction work for each unit, and can be easily used as construction elevators. By relocating the mechanical device supplies and the electric control device supplies to the elevator machine room, the effect of being able to be used as a permanent elevator in a short time is obtained.

【0026】また、前述の本設用品使用の工事用エレベ
ータ据付方法において、建築中の建物の昇降路内に機構
装置用品ユニットの上面を覆う雨避けを設けておくこと
で、建築工事中に昇降路内への雨水等の侵入を防止で
き、建築工事中における雨水等の防水対策が十分で、そ
の昇降路内の前記機構装置用品は勿論のこと、その他の
乗かごなどの昇降路内用品などの各種本設用品の損傷・
汚損防止等の養生が図れて、最終的にはそのまま本設エ
レベータとして支障なく使用できる効果が得られる。
In the above-described method of installing an elevator for construction using the main equipment, a rain shield that covers the upper surface of the mechanical equipment supply unit is provided in the hoistway of the building under construction, so that the elevator can be moved up and down during the construction work. Intrusion of rainwater etc. into the road can be prevented, waterproof measures against rainwater etc. during construction work are sufficient, and not only the above-mentioned mechanism equipment supplies in the hoistway, but also other goods in the hoistway such as cars etc. Damage to various construction equipment
Curing such as prevention of fouling can be achieved, and finally an effect can be obtained in which the elevator can be used as it is without any problem.

【0027】[0027]

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の本設用品使用の工事用エレベータ据付
方法の一実施例を示すもので、(a)は低層階サービス
エレベータの据付状態図、(b)は中層階サービスエレ
ベータへのライズアップ過程図、(c)は中層階サービ
スエレベータにライズアップした据付状態図。
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 shows an embodiment of a method of installing an elevator for construction using the present equipment according to the present invention, wherein (a) is a state diagram of an installation of a low-rise service elevator, and (b) is a rise to a middle-rise service elevator. The up process diagram, (c) is an installation state diagram raised to the middle floor service elevator.

【図2】従来の工事用エレベータの据付状態図。FIG. 2 is an installation state diagram of a conventional construction elevator.

【符号の説明】[Explanation of symbols]

11…昇降路、14,15…エレベータ機械室用品(1
4a…巻上機、14…機構装置用品、15a…エレベー
タ運転制御盤、15…電気制御装置用品)、14A…機
構装置用品ユニット、15A…電気制御装置用品ユニッ
ト、16,16a…建物側のフロア、17,17a…ロ
ープ、18…かご、19…つり合いおもり、26…雨避
け、28…温度及び湿度センサー。
11 ... hoistway, 14, 15 ... elevator machine room supplies (1
4a: Hoisting machine, 14: Mechanical equipment supplies, 15a: Elevator operation control panel, 15: Electric control equipment supplies), 14A: Mechanical equipment supply units, 15A: Electric control equipment supply units, 16, 16a: Floor on the building side , 17, 17a ... rope, 18 ... basket, 19 ... counterweight, 26 ... rain avoidance, 28 ... temperature and humidity sensor.

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 建築工事中の建物に本設用のエレベータ
昇降路を構築して行くと共に、本設用のエレベータ機械
室用品のうち、巻上機等の機構装置用品とエレベータ運
転制御盤等の電気制御装置用品とを分離して各々ユニッ
ト化し、その機構装置用品ユニットを前記昇降路内の上
方適当位置に設置する一方、これと隣接する建物側に前
記電気制御装置用品ユニットを設置し、且つ前記機構装
置用品ユニットの巻上機に巻き掛けたロープを介し本設
用のかご及びつり合いおもりを昇降路内に昇降駆動可能
に設置し、この状態で工事用エレベータとして利用しな
がら、建築工事の進行により建物が高くなるに伴い前記
機構装置用品ユニットを昇降路内の上方に順次移設する
と共に、電気制御装置用品ユニットを建物の上層階に順
次移設させ、最終的には建物上部の本設用のエレベータ
機械室に前記機構装置用品と電気制御装置用品とを移設
することを特徴とする本設用品使用の工事用エレベータ
据付方法。
1. An elevator hoistway for a permanent installation is constructed in a building under construction, and among the equipment for a main elevator, mechanical equipment such as a hoist and an elevator operation control panel. The electrical control equipment supplies are separated into units, and the mechanism equipment supply units are installed at appropriate positions above the hoistway, while the electric control equipment supply units are installed on the building side adjacent thereto. In addition, a main car and a counterweight are installed in the hoistway so as to be able to be driven up and down via a rope wound around the hoisting machine of the mechanism device supply unit. As the building becomes higher due to the progress of the above, the mechanism device supply units are sequentially moved upward in the hoistway, and the electric control device supply units are sequentially transferred to the upper floors of the building. A method of installing an elevator for construction using permanent equipment, wherein the mechanical equipment and the electrical control equipment are relocated to a permanent elevator machine room at the top of the building.
【請求項2】 請求項1記載の本設用品使用の工事用エ
レベータ据付方法において、建築中の建物の昇降路内に
は機構装置用品ユニットの上面を覆う雨避けを仮設する
ことを特徴とする本設用品使用の工事用エレベータ据付
方法。
2. The method according to claim 1, wherein a rain guard covering the upper surface of the mechanical equipment unit is temporarily provided in the hoistway of the building under construction. Elevator installation method for construction using this equipment.
JP783991A 1991-01-25 1991-01-25 Elevator installation method for construction using this equipment Expired - Fee Related JP2862681B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP783991A JP2862681B2 (en) 1991-01-25 1991-01-25 Elevator installation method for construction using this equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP783991A JP2862681B2 (en) 1991-01-25 1991-01-25 Elevator installation method for construction using this equipment

Publications (2)

Publication Number Publication Date
JPH04243786A JPH04243786A (en) 1992-08-31
JP2862681B2 true JP2862681B2 (en) 1999-03-03

Family

ID=11676781

Family Applications (1)

Application Number Title Priority Date Filing Date
JP783991A Expired - Fee Related JP2862681B2 (en) 1991-01-25 1991-01-25 Elevator installation method for construction using this equipment

Country Status (1)

Country Link
JP (1) JP2862681B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11396442B2 (en) 2020-05-09 2022-07-26 Otis Elevator Company Low cost roped jump lift concept

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ID26036A (en) * 1998-03-04 2000-11-16 Ebara Corp PERFORMANCE SETTINGS PERFORMANCE OF FLUID MACHINES
JP3920527B2 (en) * 2000-04-04 2007-05-30 株式会社日立ビルシステム Elevator for construction
US8291568B2 (en) * 2008-11-28 2012-10-23 Kone Corporation Method of installing an elevator
FI20090389A (en) * 2009-10-23 2011-04-24 Kone Corp A method of making a lift
FI122066B (en) * 2009-12-31 2011-08-15 Kone Corp A method of making a lift
JP5538471B2 (en) * 2012-04-12 2014-07-02 東芝エレベータ株式会社 Lift extension method for construction elevators
JP5538470B2 (en) * 2012-04-12 2014-07-02 東芝エレベータ株式会社 Lift extension method for construction elevators
CN113474276B (en) * 2019-03-05 2023-02-10 株式会社日立制作所 Construction elevator device and speed governor rope extending method for construction elevator device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11396442B2 (en) 2020-05-09 2022-07-26 Otis Elevator Company Low cost roped jump lift concept

Also Published As

Publication number Publication date
JPH04243786A (en) 1992-08-31

Similar Documents

Publication Publication Date Title
KR100302557B1 (en) Control system of elevator
US9617121B2 (en) Installation method for an elevator
JPH07100582B2 (en) Elevator work platform and elevator installation method
JP2862681B2 (en) Elevator installation method for construction using this equipment
JPH0737308B2 (en) Elevator control panel
JP3920527B2 (en) Elevator for construction
JP3994458B2 (en) Operation method of vertical and horizontal transfer device
JP2878936B2 (en) Elevator installation method
JPH07237848A (en) Installation method of elevator
JPH05222834A (en) Ascending or descending continuous suspended scaffolding for multistoried building
JP2859811B2 (en) Equipment transportation method and elevator with transportation basket
WO2023160817A1 (en) An elevator construction arrangement and a method
JP2612258B2 (en) Elevator installation construction method
JP2008001509A (en) Structure for elevator machine room on roof
JPH0234873B2 (en)
JP4454744B2 (en) Temporary elevator device
JP2001080834A (en) Elevator device and inspection and maintenance method of elevator control device
JP2504212B2 (en) Elevator installation method
WO2023160818A1 (en) An elevator construction arrangement and a method
JPH05201648A (en) Installation of elevator
JP2812591B2 (en) How to modify the elevator
JPH0776473A (en) Apparatus and method for installing elevator
JPH04266381A (en) Method of installing elevator
WO2023160819A1 (en) An elevator construction arrangement and a method
JPH05270765A (en) Mobile scaffold device for installation of elevator

Legal Events

Date Code Title Description
FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20071211

Year of fee payment: 9

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 10

Free format text: PAYMENT UNTIL: 20081211

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 10

Free format text: PAYMENT UNTIL: 20081211

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091211

Year of fee payment: 11

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091211

Year of fee payment: 11

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101211

Year of fee payment: 12

LAPS Cancellation because of no payment of annual fees