Prior art keywords
rope
floor
opening
scaffold
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP6531192A
Other languages
Japanese (ja)
Inventor
Noboru Kimura
登 木村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Elevator and Building Systems Corp
Original Assignee
Toshiba Elevator Technos KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Elevator Technos KK filed Critical Toshiba Elevator Technos KK
Priority to JP6531192A priority Critical patent/JPH05270765A/en
Publication of JPH05270765A publication Critical patent/JPH05270765A/en
Pending legal-status Critical Current

Links

Landscapes

  • Movable Scaffolding (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

PURPOSE:To provide possibility of opening floor slates installed in stages one over another through winching-up of a rope for opening and facilitate installation and movement of a scaffold device by forming the slabs in double opening structure, and fixing branches of this common opening rope which cart be taken up by a winch, CONSTITUTION:A mobile scaffold 1 is equipped with a vertical pillar 5 and a horizontal frame 6, formed with a height corresponding to a plurality of storeys in an elevator shaft, and supported by a receptacle beam 4 on the corresponding floor at a beam 3 at the uppermost part. A working floor is divided in two segments, and their outer ends are supported rotatably by a shaft, and a rope for opening is fixed to the inner end part. This rope is formed by attaching branches 11 to the main rope 10 which is dangling, and the top of the main rope 10 is wound fast on a winch 12 through a pulley 15. The working floor is opened up by taking up the opening rope 10 with rotation of the winch 12. This scaffold 1 is lifted by a hook 8 of a lifting facility, moved in the elevator shaft, and installed in place.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、昇降路内のエレベータ
ー機器据付用の移動足場に関する。
FIELD OF THE INVENTION The present invention relates to a mobile scaffold for installing elevator equipment in hoistways.

【0002】[0002]

【従来の技術】従来のエレベータ据付用移動足場につい
て図4、図5を参照して説明する。
2. Description of the Related Art A conventional moving scaffold for elevator installation will be described with reference to FIGS.

【0003】一般にエレベーターの据付けにおいて、建
物の途中階に移動足場を固定し、その移動足場の高さ分
に対して、昇降路の機器の取付け作業が実施されてい
る。特に、高層用エレベータの場合はこの移動足場を用
いて、順次下から上に、建物の構築に従って、昇降路内
機器の取付けを行うのが一般である。
Generally, in the installation of an elevator, a moving scaffold is fixed to an intermediate floor of a building, and the hoistway equipment is attached to the height of the moving scaffold. In particular, in the case of a high-rise elevator, it is general to use the moving scaffolding to sequentially install the equipment in the hoistway from bottom to top according to the construction of the building.

【0004】移動足場1は吊り元2、ビーム3、受梁
4、縦柱5、水平枠6、作業床7で構成されている。
The moving scaffold 1 is composed of a suspension base 2, a beam 3, a receiving beam 4, a vertical column 5, a horizontal frame 6, and a work floor 7.

【0005】この移動足場1が架設されている階層分の
機器の取付作業が完了すると、建物が先行している上階
部へ揚重設備のフック8で吊り元2に通した主掛けワイ
ヤを介して、移動足場を上階部へ吊り上げて、次の予定
場所の受梁に架設してビーム3を固定し、同様に移動足
場の高さの範囲の昇降路内機材の取付け作業を行う。
When the installation work of the equipment for the floors on which the moving scaffold 1 is erected is completed, the main wire passed through the suspension source 2 by the hook 8 of the lifting equipment is moved to the upper floor where the building precedes. The moving scaffolding is lifted to the upper floor via the above, and the beam 3 is fixed by being erected on the receiving beam at the next planned place, and similarly, the work for mounting the equipment in the hoistway within the height range of the moving scaffolding is performed.

【0006】建物の最後の躯体工事が完了するまで、エ
レベーターの据付工事は同様の施工を繰り返し昇降路内
の機器取付け作業を行う。
Until the final building work of the building is completed, the installation work of the elevator is repeated in the same manner to install the equipment in the hoistway.

【0007】[0007]

【発明が解決しようとする課題】従来の移動足場1の場
合では、昇降路内の機器を取付けたのち、移動足場1を
上方階に移動させ、下方階で使用した作業用機器等を揚
重する必要が生じる。このとき、揚重設備の吊りフック
8を、作業床7を取り外して移動足場1の中を通過させ
て下降させなければならない。
In the case of the conventional mobile scaffold 1, after mounting the equipment in the hoistway, the mobile scaffold 1 is moved to the upper floor and the working equipment used on the lower floor is lifted. Need to do so. At this time, the lifting hook 8 of the lifting equipment must be removed by removing the work floor 7 and passing through the moving scaffold 1 to descend.

【0008】又下階にある昇降路内取付機器を揚重する
作業の場合も同様で、移動足場の作業床6を全段数或い
は一部を撤去、又は片側に移動し、確実に作業床の落下
防止の固定が必要である。
Also, in the case of lifting the equipment installed in the hoistway on the lower floor, the same is true, and the working floor 6 of the moving scaffold is completely removed or partially removed or moved to one side to surely Fall prevention must be fixed.

【0009】このような一連の作業は、全て作業員が移
動足場の最上部の床7から、順次下方階へ撤去又は片側
への移動、そして落下防止の固定作業を行ってる。
In such a series of operations, all the workers perform the removal work from the uppermost floor 7 of the moving scaffolding to the lower floor in sequence or moving to one side, and the fixing work for preventing fall.

【0010】これらの作業は常に昇降路内高所での作業
であるので、墜落などの危険があり、上部から順に下部
へ移動しながらの作業は危険性が高く、特に最下部の作
業床7を撤去又は片側に移動するときは、墜落等に細心
の注意を払わなければならない。
Since these works are always carried out at a high place in the hoistway, there is a risk of crashing, and the work while moving from the upper part to the lower part in sequence is highly dangerous, and especially the work floor 7 at the bottom. When removing or moving to one side, you must pay close attention to a fall.

【0011】本発明は上記に鑑み、移動足場内で作業者
がこの様な危険な作業を行わずに済むような作業床撤去
方法により、足場作業の安全性を向上させることが目的
である。
In view of the above, it is an object of the present invention to improve the safety of scaffolding work by a work floor removing method that does not require the worker to perform such dangerous work in a moving scaffold.

【0012】[0012]

【課題を解決するための手段】上記目的を達成するため
本発明は、移動足場の作業床を開放させるロープを用い
た作業床開放装置を設ける。
To achieve the above object, the present invention provides a work floor opening device using a rope for opening the work floor of a moving scaffold.

【0013】即ち、移動足場の作業床を2分割して観音
開きにし、床に開放ロープを付けて、このロープを上部
ビーム上に設けた巻上機により巻き上げる。
That is, the work floor of the moving scaffold is divided into two parts to form a double door, an open rope is attached to the floor, and the rope is wound by a hoist provided on the upper beam.

【0014】[0014]

【作用】上記構成の作業床開放装置により、巻上げ機に
より開放ロープの主ロープを引き込むと、各床に取付け
た枝ロープにより作業床は引っ張られて回転し、床が開
放する。
When the main rope of the open rope is pulled by the hoisting machine by the work floor opening device having the above-mentioned construction, the work floor is pulled and rotated by the branch ropes attached to each floor, and the floor is opened.

【0015】[0015]

【実施例】図1〜図3に示す実施例に基づいて本発明を
説明する。
DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described based on the embodiments shown in FIGS.

【0016】移動足場1は縦柱5と水平枠6で昇降路内
複数階床分の高さに構成し、これを最上部のビーム3に
より対応する階床の受梁4に架設する。
The movable scaffold 1 is constructed by a vertical column 5 and a horizontal frame 6 so as to have a height corresponding to a plurality of floors in the hoistway, and the beams 3 are mounted on the receiving beams 4 of the corresponding floors by the uppermost beam 3.

【0017】作業床を2分割し、一端を軸で支持して回
転可能にし、他端に開放ロープを付ける。開放ロープは
上から下に垂れ下げた主ロープ10に枝ロープ11を付
け、枝ロープ11を観音開きの作業床7に付ける。主ロ
ープ10の上端は滑車15、を介して巻上げ機12に巻
き付けておく。
The work floor is divided into two parts, one end of which is supported by a shaft to be rotatable, and the other end of which is provided with an open rope. As for the open rope, the branch rope 11 is attached to the main rope 10 that is hung from the top to the bottom, and the branch rope 11 is attached to the work floor 7 having a double door. The upper end of the main rope 10 is wound around the hoist 12 via a pulley 15.

【0018】巻上げ機12は電動機と減速機からなり、
巻上げ機の回転により開放ロープが巻き込まれて、作業
床7、7は上方に開く。
The hoisting machine 12 comprises an electric motor and a speed reducer,
The rotation of the hoist winds the open rope, and the work floors 7, 7 open upward.

【0019】上記構成により、移動足場の作業床の開放
は、巻き上げ機の駆動により機械的に、作業床を開放す
るので、作業は安全確実に行える。
With the above structure, the work floor of the moving scaffold is opened mechanically by driving the hoist, so that the work can be performed safely and reliably.

【0020】[0020]

【発明の効果】本発明により、昇降路内での移動足場を
用いた場合の作業時間が短縮し、安全性の確保が容易と
なる。即ち、従来のように移動足場の中を手作業で作業
床を開放する危険な作業がなくなり、作業時間の短縮と
本質安全化を提供でき、安全管理に大きな効果がある。
According to the present invention, the working time when using a moving scaffold in a hoistway can be shortened, and safety can be easily ensured. That is, unlike the conventional case, the dangerous work of manually opening the work floor in the moving scaffold is eliminated, the work time can be shortened and the essential safety can be provided, which is a great effect on safety management.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明による移動足場の正面図、1 is a front view of a mobile scaffold according to the present invention, FIG.

【図2】図1の作業床を閉じたときの正面図である。FIG. 2 is a front view when the work floor of FIG. 1 is closed.

【図3】開放ロープの構成を示す正面図である。FIG. 3 is a front view showing a configuration of an open rope.

【図4】従来の移動足場の正面図、FIG. 4 is a front view of a conventional mobile scaffold,

【図5】図5の動作説明図である。5 is an operation explanatory diagram of FIG. 5;

【符号の説明】[Explanation of symbols]

3…ビーム 4…受梁 5…柱 6…水平枠 7…作業床 8…クレーンの揚重フック 10…主ロープ 11…枝ロープ 3 ... Beam 4 ... Receiving beam 5 ... Pillar 6 ... Horizontal frame 7 ... Working floor 8 ... Crane lifting hook 10 ... Main rope 11 ... Branch rope

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 数階床分の高さの複数本の柱に、床板を
付けた水平な枠を前記階床数相当分を設けて移動足場を
構成し、その上部ビームを、階床の受梁に掛けて、昇降
路内に吊下げたエレベータ据付用移動足場装置におい
て、 前記床板を観音開きに形成し、外端を軸で支持し、内端
にロープを付け、これら各床板に付けた前記ロープを纏
めて移動足場上部に設けた巻上機に巻付けて、床板を開
放することを特徴とするエレベータ据付用移動足場装
置。
1. A movable scaffold is constructed by providing a horizontal frame with a floor plate on a plurality of columns having a height of several floors, the number of which corresponds to the number of floors, to form a moving scaffold, the upper beam of which is In a mobile scaffolding device for elevator installation, which is hung on a beam and suspended in a hoistway, the floor plate is formed in a double door, the outer end is supported by a shaft, a rope is attached to the inner end, and each of these floor plates is attached. A mobile scaffolding device for elevator installation, characterized in that the rope is collected and wound around a hoisting machine provided on an upper part of the mobile scaffolding to open a floor board.
JP6531192A 1992-03-23 1992-03-23 Mobile scaffold device for installation of elevator Pending JPH05270765A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6531192A JPH05270765A (en) 1992-03-23 1992-03-23 Mobile scaffold device for installation of elevator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6531192A JPH05270765A (en) 1992-03-23 1992-03-23 Mobile scaffold device for installation of elevator

Publications (1)

Publication Number Publication Date
JPH05270765A true JPH05270765A (en) 1993-10-19

Family

ID=13283238

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6531192A Pending JPH05270765A (en) 1992-03-23 1992-03-23 Mobile scaffold device for installation of elevator

Country Status (1)

Country Link
JP (1) JPH05270765A (en)

Similar Documents

Publication Publication Date Title
JPH07100582B2 (en) Elevator work platform and elevator installation method
US20090223751A1 (en) Method and apparatus for installing an elevator without machine room during construction of a building, and use of a hoisting machine
JP2620123B2 (en) Temporary lifting equipment for construction work
JP3844944B2 (en) Demolition method of construction elevator
JPH05270765A (en) Mobile scaffold device for installation of elevator
JPH09278325A (en) Construction work elevator lifting method and construction work elevator device
JP2612258B2 (en) Elevator installation construction method
JPH0733355A (en) Installation method for elevator
JPH11117523A (en) Lifting work platform for elevator parking and method using the same
JPH02300081A (en) Installation work method for elevator
JPH021066B2 (en)
JPH0747453B2 (en) Elevator installation method
JPH0336184A (en) Home elevator
JP2006001739A (en) Installation method of rise-up elevator
JP2939064B2 (en) Elevator installation template
JPS6374884A (en) Method of remodeling elevator
JPS5912064A (en) Method of construction of installation of elevator
JPH0840666A (en) Method for installing elevator
JPH01256484A (en) Installation practice for elevator
JPH059354B2 (en)
JPH04266381A (en) Method of installing elevator
JPH057307B2 (en)
JPH0776473A (en) Apparatus and method for installing elevator
JPH0859132A (en) Lifting of load
JP2001316057A (en) Method and device for weight lifting in elevator