JP2612258B2 - Elevator installation construction method - Google Patents

Elevator installation construction method

Info

Publication number
JP2612258B2
JP2612258B2 JP61182802A JP18280286A JP2612258B2 JP 2612258 B2 JP2612258 B2 JP 2612258B2 JP 61182802 A JP61182802 A JP 61182802A JP 18280286 A JP18280286 A JP 18280286A JP 2612258 B2 JP2612258 B2 JP 2612258B2
Authority
JP
Japan
Prior art keywords
car frame
hoistway
guide rail
work
hoisting machine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP61182802A
Other languages
Japanese (ja)
Other versions
JPS6341387A (en
Inventor
利治 白水
Original Assignee
株式会社 日立ビルシステムサービス
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社 日立ビルシステムサービス filed Critical 株式会社 日立ビルシステムサービス
Priority to JP61182802A priority Critical patent/JP2612258B2/en
Publication of JPS6341387A publication Critical patent/JPS6341387A/en
Application granted granted Critical
Publication of JP2612258B2 publication Critical patent/JP2612258B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は、高層建築物に用いられるエレベータに好適
な据付工事工法に関する。
Description: TECHNICAL FIELD The present invention relates to an installation construction method suitable for an elevator used for a high-rise building.

(従来技術) 一般に高層用エレベータ据付工事においては、建物本
体の施工工程に合せて昇降路内の作業を行なうが、例え
ば、30階建の建物の場合、まず下の10階床分、次に中間
の11〜20階床分、最後に上の21〜30階床分に分けて、昇
降路内のガイドレール、配線、乗場の出入口装置などの
設置作業を、下の区間から順次行なう。従来、この昇降
路内の作業のため、ゴンドラを昇降路内で運行し、この
ゴンドラに作業者が乗込んで1昇降路内の作業を行なつ
た。そして、昇降路内の作業終了後、このゴンドラを撤
去してから、乗かごを設置した。また、この昇降路内で
の設置位置の基準線として、ピアノ線を昇降路に張設
し、乗場の出入口装置などの位置決めを行なつた。
(Prior art) In general, in elevator installation work for high-rise buildings, work in the hoistway is performed in accordance with the construction process of the building itself. For example, in the case of a 30-story building, first for the lower 10 floors, then Installation work such as guide rails in the hoistway, wiring, and entrance / exit devices for landings will be performed sequentially from the lower section, divided into the middle 11 to 20 floors and finally the upper 21 to 30 floors. Conventionally, a gondola was operated in the hoistway for work in the hoistway, and an operator got on the gondola to perform work in one hoistway. After the work in the hoistway was completed, the gondola was removed and a car was installed. Also, a piano wire was installed on the hoistway as a reference line for the installation position in the hoistway, and positioning of the entrance / exit device of the hall was performed.

(発明が解決しようとする問題点) 上記の従来技術では、昇降路内のガイドレール、配
線、乗場の出入口装置などの設置作業に要する日数に加
え、作業用ゴンドラの設置および撤去作業に余分の日数
を要した。また、昇降路内の設置位置の基準線として張
設されたピアノ線により、乗場の出入口装置等の位置決
め作業を行なうことがむずかしく、多くの労力を要し
た。
(Problems to be Solved by the Invention) In the above prior art, in addition to the number of days required for installation work of guide rails in the hoistway, wiring, entrance / exit device of the hall, etc., extra time is required for installation and removal of the work gondola. It took days. Further, it was difficult to perform the positioning work of the entrance / exit device of the hall, etc., with the piano wire stretched as a reference line of the installation position in the hoistway, and much labor was required.

なお、これらの問題解決の1手段として、特公昭59-1
2595号公報に示す工法が提案されているが、この工法で
は、建物の最上階を組立てるまで昇降路内の作業が行な
えず、従つて建物本体の工期に合せて、エレベータ据付
工事を終わらせることは極めてむずかしいという問題が
あつた。
As a means of solving these problems, Japanese Patent Publication No. Sho 59-1
No. 2595 proposes a construction method, but in this construction method, work in the hoistway cannot be performed until the top floor of the building is assembled, so the elevator installation work must be completed according to the construction period of the building body Had the problem of being extremely difficult.

本発明の目的は、ゴンドラ等の余分の昇降体を設ける
ことなく、しかも、建物本体の工期に合せて効率良く据
付工事を行なうことのできるエレベータ据付工事工法を
提供するにある。
An object of the present invention is to provide an elevator installation construction method capable of efficiently performing installation work according to the construction period of a building main body without providing an extra elevating body such as a gondola.

(問題点を解決するための手段) 本発明のこうした目的は、昇降路の中間階位置に本設
用の巻上機を芯出しを行ない設置する第1の工程と、昇
降路の側壁に下部ガイドレールを固定した後、この下部
ガイドレールに沿って上昇、下降動作が可能な状態に本
接用のかご枠を組込み、次いで、かご枠を上昇させなが
らこのかご枠に乗っている作業者がガイドレールの続き
の部分を昇降路の中間階位置まで順次立設するととも
に、かご枠および予めガイドレールに組み込んだ吊り合
い重りを、前記巻上機を介してワイヤロープで互いに連
結する第2の工程と、この巻上機により前記かご枠を運
行し、このかご枠に乗っている作業者が、第2の工程で
立設したガイドレールを昇降路壁に固定する作業を含む
前記中間階より下方の前記昇降路内の作業を行なう第3
の工程と、前記巻上機を、昇降路の上階位置へ移動し
て、再び芯出しを行ない設置する第4の工程と、前記か
ご枠および前記吊り合い重りを連結する前記ワイヤロー
プを巻替える第5の工程と、第4の工程で移動した前記
巻上機により、前記かご枠を再び運行し、このかご枠に
乗つている作業者が、前記上階より下方の前記昇降路内
の作業を行なう第6の工程と、これらの第4〜第6の工
程を、前記巻上機を前記昇降路上部にある機械室に設置
するまで、1回以上、順次行なった後、前記かご枠を基
に、乗かごを組立てる第7の工程からなるエレベータ据
付工事工法により達成される。
(Means for Solving the Problems) An object of the present invention is to provide a first step of centering and installing a permanent hoist at an intermediate floor position of a hoistway, After fixing the guide rail, the car frame for final contact is assembled so that it can move up and down along this lower guide rail, and then the worker riding this car frame while raising the car frame A second portion for connecting a continuation portion of the guide rail to the intermediate floor position of the hoistway in order and connecting the car frame and the hanging weight previously incorporated in the guide rail to each other with a wire rope via the hoist. And the step of operating the car frame by the hoisting machine, and the worker riding on the car frame performs the operation of fixing the guide rail erected in the second step to the hoistway wall from the intermediate floor. Work in the hoistway below 3rd to do
And a fourth step of moving the hoisting machine to the upper floor position of the hoistway, re-centering and installing, and winding the wire rope connecting the car frame and the hanging weight. The fifth step to be replaced, and the hoist moved in the fourth step, the car frame is operated again, and an operator riding on the car frame is in the hoistway below the upper floor. The sixth step of performing the operation and the fourth to sixth steps are sequentially performed one or more times until the hoist is installed in the machine room above the hoistway, and then the car frame Is achieved by an elevator installation method comprising a seventh step of assembling the car.

(作用) 本発明のエレベータ据付工事工法はこうした構成を備
えているので、次のように実施される。まず、本設用の
巻上機を昇降路の中間階位置に芯出しを行なって設置す
る。次に、昇降路の側壁に下部ガイドレールを固定した
後、この下部ガイドレールに沿って上昇、下降動作が可
能な状態に本設用のかご枠を組込む。作業者は、この本
設用のかご枠に乗り込んで、このかご枠を上昇させなが
ら、ガイドレールの続きの部分を昇降路の中間階位置ま
で順次立設する。また、そのかご枠および予めガイドレ
ールに組み込んだ吊り合い重りが前記巻上機を介してワ
イヤロープで互いに連結される。次いで、作業者がかご
枠に乗り、その巻上機によりかご枠を運行して、すでに
立設したガイドレールを昇降路壁に固定する作業を含む
各種昇降路内の作業を前記中間階位置より下方の区域で
行なう。次に巻上機を上階位置へ移動してから再びかご
枠を運行することにより、作業者は再びかご枠に乗込ん
で、この上階位置より下方の昇降路内において、設置作
業を行なうことができる。このように、建物の高さに応
じて昇降路が作業の便宜のために区分されているので、
上記の如く昇降路内の作業および巻上機の移動を、昇降
路の下方より上方へ順次くり返すことにより、最終的に
巻上機を昇降路上部にある機械室に設置することができ
る。
(Operation) Since the elevator installation construction method of the present invention has such a configuration, it is implemented as follows. First, a hoist for permanent installation is set up at the middle floor position of the hoistway. Next, after the lower guide rail is fixed to the side wall of the hoistway, the car frame for permanent installation is assembled in a state in which it is possible to ascend and descend along the lower guide rail. The operator gets on the car frame for permanent installation, and raises the car frame to sequentially set up the continuation portion of the guide rail to the middle floor position of the hoistway. Further, the car frame and the hanging weight previously incorporated in the guide rail are connected to each other by a wire rope via the hoist. Next, the operator rides on the car frame, operates the car frame by the hoist, and performs various works in the hoistway including the work of fixing the already erected guide rail to the hoistway wall from the intermediate floor position. Perform in the lower area. Next, by moving the hoist to the upper floor position and then operating the car frame again, the operator gets on the car frame again and performs installation work in the hoistway below the upper floor position. be able to. In this way, since the hoistway is divided according to the height of the building for convenience of work,
As described above, the work in the hoistway and the movement of the hoist are sequentially repeated upward from below the hoistway, so that the hoist can be finally installed in the machine room at the upper part of the hoistway.

従つて、本設用のかご枠および巻上機を、作業用とし
ても用いることができ、すなわち、ゴンドラ等を用いる
ことが不要となるので、建物本体の工期に合わせて効率
の良いエレベータ据付工事を行なうことができる。
Accordingly, the elevator car frame and the hoist can be used for work, that is, there is no need to use a gondola or the like, so that efficient elevator installation work can be performed according to the construction period of the building body. Can be performed.

また、昇降路に立設されたガイドレールにより、かご
枠の上下動作は案内され、横振れが少ないので、このか
ご枠との位置関係により、乗場の出入口装置、配線など
の位置決めを、従来より効率良く行なえる。
In addition, the vertical movement of the car frame is guided by the guide rails set up in the hoistway, and there is little lateral swing.Therefore, the positioning of the landing doorway device, wiring, etc., based on the positional relationship with the car frame, has been It can be done efficiently.

(実施例) 以下、本発明の一実施例を図に基づき説明する。第2
図は、この一実施例になるエレベータ据付工事工法の主
要作業およびこれらの順序を示し、第1図は、第2図に
おける第10番目までの作業が終了した状態にある、工事
中の昇降路の要部斜視図である。まず、第1図におい
て、1は昇降路、3は中間階床2の開口部、4は昇降路
1上部にある機械室N床面の開口部である。次に、本実
施例を作業順序に沿つて順次説明する。
Example An example of the present invention will be described below with reference to the drawings. Second
The figure shows the main works of the elevator installation construction method according to this embodiment and the order thereof. FIG. 1 shows the hoistway under construction in which the work up to the tenth in FIG. 2 has been completed. FIG. First, in FIG. 1, 1 is a hoistway, 3 is an opening in the middle floor 2, and 4 is an opening in the machine room N floor above the hoistway 1. Next, this embodiment will be described sequentially according to the working order.

(1)昇降路1の中間階床2の開口部3より物が落下す
ることを防止するため、この開口部3に鉄板や足場板な
どで間仕切を設ける。
(1) In order to prevent an object from falling from the opening 3 of the intermediate floor 2 of the hoistway 1, a partition is provided in the opening 3 with an iron plate or a scaffold plate.

(2)この昇降路1の中間階床2の位置に仮機械室Aを
設けるが、設置物の位置決めのため、後に設置するガイ
ドレール8,9やかご枠10などの設置位置の基準線をけが
く。
(2) A temporary machine room A is provided at the intermediate floor 2 of the hoistway 1, and a reference line for the installation position of the guide rails 8, 9 and the car frame 10, which will be installed later, is used for positioning the installation object. Scribble.

(3)専用ウインチ(図示せず)により、台座5、巻上
機6、および制御盤7などの荷揚げを行ない、順次芯出
しを行なつてから設置する。
(3) The pedestal 5, the hoisting machine 6, the control panel 7 and the like are unloaded by a dedicated winch (not shown), and the pedestal 5, the centering machine and the like are sequentially aligned and then installed.

(4)ガイドレール8,9の設置基準となるピアノ線(図
示せず)を、仮機械室Aおよび昇降路1底の間に張設す
る。
(4) A piano wire (not shown) serving as a reference for setting the guide rails 8 and 9 is stretched between the temporary machine room A and the bottom of the hoistway 1.

(5)このピアノ線を基準として位置決めを行ないなが
ら、下部ガイドレール8,9を昇降路1側壁に固定する。
(5) The lower guide rails 8 and 9 are fixed to the side wall of the hoistway 1 while positioning with reference to the piano wire.

(6)これらの下部ガイドレール8と係合し、これらに
沿つて上昇、下降動作が可能な状態にかご枠10を組込
み、同様に、他の下部ガイドレール9に吊り合い重り11
を組込む。
(6) The car frame 10 is assembled so as to engage with these lower guide rails 8 and be capable of ascending and descending along these lower rails 8, and likewise be hung on the other lower guide rails 9 and weighed 11.
Incorporate.

(7)専用ウインチによりかご枠10を上昇させながら、
このかご枠10に乗込んだ作業者は、ガイドレール8,9の
続きの部分を、仮機械室Aまで、順次立設した後、かご
枠10を昇降路1底まで下降させる。
(7) While raising the car frame 10 by the special winch,
The operator who gets into the car frame 10 sequentially sets up the continuation portions of the guide rails 8 and 9 to the temporary machine room A, and then lowers the car frame 10 to the bottom of the hoistway 1.

(8)かご枠10に作業運転用の操作盤(図示せず)を備
えるとともに、この操作盤と制御盤7を操作ケーブル
(図示せず)で結ぶ。
(8) An operation panel (not shown) for work operation is provided on the car frame 10, and the operation panel and the control panel 7 are connected by an operation cable (not shown).

(9)専用ウインチにより、昇降路1底にある吊り合い
重り11を、第1図に示す位置まで吊上げて保持してお
き、一方、巻上機6にワイヤロープ12を掛けるととも
に、巻上機6を動作させながら、このワイヤロープ12の
一端を吊り合い重り11に、次いで他端をかご枠10にそれ
ぞれ連結する。
(9) The lifting weight 11 at the bottom of the hoistway 1 is lifted and held by the dedicated winch to the position shown in FIG. 1, while the wire rope 12 is hung on the hoist 6 and the hoist While operating 6, one end of the wire rope 12 is connected to the hanging weight 11, and the other end is connected to the car frame 10, respectively.

(10)巻上機6によりかご枠10を上昇させながら、この
かご枠10に乗込んだ作業者は、先の(7)の作業で立設
したガイドレール8,9を、先の(4)の作業張設したピ
アノ線を基準として位置決めを行なつた上で、昇降路1
側壁に固定する。
(10) While raising the car frame 10 by the hoisting machine 6, the operator who got on the car frame 10 moves the guide rails 8, 9 erected in the previous operation (7) to the previous (4). )) After performing positioning based on the stretched piano wire,
Fix to the side wall.

(11)同様に、かご枠10を運行しながら、このかご枠10
に乗込んだ作業者は、ガイドレール8により案内される
かご枠10の位置を基準として、乗場の出入口装置の位置
決めを行なつた上で、固定する。
(11) Similarly, while operating the car frame 10, the car frame 10
The operator who has entered the parking lot positions and fixes the entrance / exit device of the landing with reference to the position of the car frame 10 guided by the guide rail 8.

(12)この(11)の作業と同様に、昇降路1内の他の機
器、配線、配管などの取付けを行なう。なお、これで、
仮機械室A下方の作業区間において、一連の設置作業が
終了した。
(12) Similar to the operation of (11), other devices, wiring, piping, etc. in the hoistway 1 are attached. By the way,
In the work section below the temporary machine room A, a series of installation work was completed.

(13)チエーンブロツクなどにより、かご枠10および吊
り合い重り11の仮固定を行なう。
(13) Temporarily fix the car frame 10 and the hanging weight 11 with a chain block or the like.

(14)ワイヤロープ12を取外す。(14) Remove the wire rope 12.

(15)仮機械室Aに備えられた制御盤7、巻上機6、台
座5、間仕切などを取外し、専用ウインチにより上階へ
荷揚げを行なう。
(15) Remove the control panel 7, the hoisting machine 6, the pedestal 5, the partition, etc., provided in the temporary machine room A, and discharge them to the upper floor by the dedicated winch.

以上で仮機械室A下方の作業区間において、一連の設
置、移動作業が終了したので、続いて、この上の作業区
間においても、上記の(1)〜(4)および(7)〜
(15)の一連の作業を順次行なう。また、建物の高さに
応じて、さらに多くの作業区間に昇降路1が分かれてい
る場合には、昇降路1上部まで、これらの一連の作業を
順次くり返す。そして最終段階として、巻上機6など
を、昇降路1上部にある機械室Nに荷揚げを行なつた
後、昇降路1の最上部区間においても、(1)〜(4)
および(7)〜(12)の作業を行なつた後、 (16)かご枠10を基に、かご天井や側板などを取付けて
乗かごを組立てるとともに、吊り合い重り11にもこれら
の重さに等しい重りを追加する。
As described above, a series of installation and moving operations have been completed in the work section below the temporary machine room A. Subsequently, in the work section above this, the above (1) to (4) and (7) to
Perform a series of operations in (15). Further, when the hoistway 1 is divided into more work sections according to the height of the building, a series of these operations are sequentially repeated up to the upper part of the hoistway 1. Then, as a final stage, after the hoisting machine 6 and the like are unloaded into the machine room N above the hoistway 1, also in the uppermost section of the hoistway 1, (1) to (4)
And (7) to (12), and (16) assemble the car by attaching the car ceiling and side plates based on the car frame 10, and suspending the weight 11 Add a weight equal to.

(17)試運転、調整を行ない、この据付工事を完了す
る。
(17) Perform trial run and adjustment to complete this installation work.

このように構成した工法にあっては、従来、作業用に
設置したゴンドラ等の余分の昇降体が不要となり、その
結果、この設置、撤去に要した日数が低減できるととも
に、建物本体の施工の進展に合わせてエレベータの据付
工事を進めて行くことができるので、建物本体の工期に
合わせて効率よくエレベータの据付工事を実施すること
ができる。特に、ガイドレールの設置作業を行なうに際
しては、昇降路の側壁に下部ガイドレールを固定した
後、この下部ガイドレールに本設用のかご枠を組込んで
かご枠を上昇させながらこのかご枠に乗っている作業者
がガイドレールの続きの部分を昇降路の中間階位置まで
順次立設するようにしているので、エレベータの据付工
事の初期段階から本設用のかご枠を有効に利用でき、し
かも、ガイドレールの設置作業は、かご枠に乗って安全
に行える。また、従来は、乗場の出入口装置なども張設
されたピアノ線により、位置決め作業を行なつていた
が、この実施例ではかご枠10の位置を基準として用いる
ことができ、従来の作業に要した労力を削減できる。
In the construction method constructed in this way, extra lifting bodies such as gondola previously installed for work are not required, and as a result, the number of days required for installation and removal can be reduced, and the construction Since the installation work of the elevator can be advanced in accordance with the progress, the installation work of the elevator can be efficiently performed according to the construction period of the building body. In particular, when installing the guide rails, after fixing the lower guide rail to the side wall of the hoistway, incorporate the car frame for permanent installation into this lower guide rail, and raise the car frame to this car frame. Workers on the guide rails continually set up the continuation of the guide rails up to the middle floor position of the hoistway, so that the car frame for main construction can be used effectively from the initial stage of elevator installation work, In addition, the installation work of the guide rail can be performed safely on the car frame. Also, in the past, the positioning work was performed using a piano wire that also stretched the entrance / exit device of the hall, but in this embodiment, the position of the car frame 10 can be used as a reference, which is necessary for the conventional work. Effort can be reduced.

なお、作業の状況や必要に応じて、これらの作業順序
を多少、変えてもよい。例えば、(12)の作業を、最終
段階でまとめて行なうこともできる。
Note that the order of these operations may be slightly changed according to the status of the operation or the need. For example, the operation (12) can be performed collectively at the final stage.

また、この実施例では、制御盤7を昇降路1内に設置
したが、この昇降路1外の適宜な位置に設けてもよい。
Further, in this embodiment, the control panel 7 is installed in the hoistway 1, but may be provided at an appropriate position outside the hoistway 1.

(発明の効果) 本発明によれば、従来、作業用に設置したゴンドラが
不要となり、その結果、この設置、撤去に要した日数が
低減できるとともに、建物本体の施工の進展に合わせて
エレベータの据付工事を進めて行くことができるので、
建物本体の工期に合わせて効率よくエレベータの据付工
事を実施することができる。
(Effects of the Invention) According to the present invention, a gondola conventionally installed for work is not required, and as a result, the number of days required for installation and removal can be reduced, and the elevator can be installed in accordance with the progress of the construction of the building body. Since you can proceed with the installation work,
Elevator installation can be carried out efficiently in accordance with the construction period of the building body.

本発明では、ガイドレールの設置作業を行なうに際
し、昇降路の側壁に下部ガイドレールを固定した後、こ
の下部ガイドレールに本設用のかご枠を組込んでかご枠
を上昇させながらこのかご枠に乗っている作業者がガイ
ドレールの続きの部分を昇降路の中間階位置まで順次立
設するようにしているので、エレベータの据付工事の初
期段階から本設用のかご枠を有効に利用でき、しかも、
ガイドレールの設置作業は、かご枠に乗って安全に行え
る。
In the present invention, when performing the installation work of the guide rail, after fixing the lower guide rail to the side wall of the hoistway, the car frame for assembling is installed in the lower guide rail and the car frame is raised while the car frame is raised. The workers on the elevators are to erected the continuation of the guide rails up to the middle floor of the hoistway, so that the elevator car frame can be used effectively from the initial stage of elevator installation. And
The installation work of the guide rail can be done safely on the car frame.

【図面の簡単な説明】[Brief description of the drawings]

第1図は第2図における第10番目までの作業が終了した
状態にある昇降路の要部斜視図である。第2図は本発明
の一実施例になるエレベータ据付工事工法の主要作業お
よびこれらの順序を示す図である。 1……昇降路、2……建物階床、6……巻上機、8,9…
…ガイドレール、10……かご枠、11……吊り合い重り、
12……ワイヤロープ、N……機械室。
FIG. 1 is a perspective view of a main part of a hoistway in a state where the tenth work in FIG. 2 has been completed. FIG. 2 is a diagram showing the main works of an elevator installation construction method according to one embodiment of the present invention and their order. 1 ... hoistway, 2 ... building floor, 6 ... hoisting machine, 8, 9 ...
… Guide rail, 10… Cage frame, 11… Hanging weight,
12 ... wire rope, N ... machine room.

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】昇降路の中間階位置に本設用の巻上機を芯
出しを行ない設置する第1の工程と、昇降路の側壁に下
部ガイドレールを固定した後、この下部ガイドレールに
沿って上昇、下降動作が可能な状態に本設用のかご枠を
組込み、次いで、かご枠を上昇させながらこのかご枠に
乗っている作業者がガイドレールの続きの部分を昇降路
の中間階位置まで順次立設するとともに、かご枠および
予めガイドレールに組み込んだ吊り合い重りを、前記巻
上機を介してワイヤロープで互いに連結する第2の工程
と、この巻上機により前記かご枠を運行し、このかご枠
に乗っている作業者が、第2の工程で立設したガイドレ
ールを昇降路壁に固定する作業を含む前記中間階より下
方の前記昇降路内の作業を行なう第3の工程と、前記巻
上機を、昇降路の上階位置へ移動して、再び芯出しを行
ない設置する第4の工程と、前記かご枠および前記吊り
合い重りを連結する前記ワイヤロープを巻替える第5の
工程と、第4の工程で移動した前記巻上機により、前記
かご枠を再び運行し、このかご枠に乗つている作業者
が、前記上階より下方の前記昇降路内の作業を行なう第
6の工程と、これらの第4〜第6の工程を、前記巻上機
を前記昇降路上部にある機械室に設置するまで、1回以
上、順次行なった後、前記かご枠を基に、乗かごを組立
てる第7の工程からなるエレベータ据付工事工法。
1. A first step of centering and installing a permanent hoisting machine at an intermediate floor position of a hoistway, and fixing a lower guide rail to a side wall of the hoistway. The car frame for permanent construction is assembled so that it can be raised and lowered along the car frame, and then, while raising the car frame, the worker riding this car frame moves the continuation of the guide rail to the middle floor of the hoistway. A second step of sequentially connecting the car frame and the hanging weight previously incorporated in the guide rail to each other with a wire rope via the hoisting machine; and A third operator who operates and rides on the car frame performs an operation in the hoistway below the intermediate floor, including an operation of fixing the guide rail erected in the second step to the hoistway wall. And the hoisting machine The fourth step of moving to the floor position, re-centering and installing, the fifth step of rewinding the wire rope connecting the car frame and the hanging weight, and the fourth step A sixth step in which the car frame is operated again by the hoisting machine, and an operator riding on the car frame performs work in the hoistway below the upper floor; The sixth step is performed one or more times until the hoisting machine is installed in the machine room above the hoistway. The sixth step is to assemble a car based on the car frame. Elevator installation construction method.
JP61182802A 1986-08-05 1986-08-05 Elevator installation construction method Expired - Fee Related JP2612258B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP61182802A JP2612258B2 (en) 1986-08-05 1986-08-05 Elevator installation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP61182802A JP2612258B2 (en) 1986-08-05 1986-08-05 Elevator installation construction method

Publications (2)

Publication Number Publication Date
JPS6341387A JPS6341387A (en) 1988-02-22
JP2612258B2 true JP2612258B2 (en) 1997-05-21

Family

ID=16124677

Family Applications (1)

Application Number Title Priority Date Filing Date
JP61182802A Expired - Fee Related JP2612258B2 (en) 1986-08-05 1986-08-05 Elevator installation construction method

Country Status (1)

Country Link
JP (1) JP2612258B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002060158A (en) * 2000-08-22 2002-02-26 Mitsubishi Electric Corp Installation method for elevator
JP4841171B2 (en) * 2004-05-20 2011-12-21 フジテック株式会社 Rise-up elevator installation method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3851736A (en) * 1973-03-20 1974-12-03 Westinghouse Electric Corp Apparatus and method for installing elevator hoistway equipment

Also Published As

Publication number Publication date
JPS6341387A (en) 1988-02-22

Similar Documents

Publication Publication Date Title
JPH07100582B2 (en) Elevator work platform and elevator installation method
JP6586490B2 (en) Mobile lifting scaffolds with load lifting devices, construction methods using them, and installation methods thereof
JP2612258B2 (en) Elevator installation construction method
JP2878936B2 (en) Elevator installation method
JPH021066B2 (en)
JP3920527B2 (en) Elevator for construction
JPS6026051Y2 (en) Construction elevator machine room
JP2930911B2 (en) Elevator installation method
JPH05262475A (en) Installation method of elevator
JP2877593B2 (en) Elevator installation method
JP3253441B2 (en) Elevator installation method
JPH0840666A (en) Method for installing elevator
JPH0132153B2 (en)
JPH0747453B2 (en) Elevator installation method
JPS5912064A (en) Method of construction of installation of elevator
JPS5912595B2 (en) Elevator installation construction method
JPH03267283A (en) Installing method for elevator
JP2674392B2 (en) Hydraulic elevator installation method
JPH057307B2 (en)
JPH0747452B2 (en) Elevator installation method
JPH02300081A (en) Installation work method for elevator
JP2003253887A (en) Construction equipment and construction method
JPH04266381A (en) Method of installing elevator
JP2001316057A (en) Method and device for weight lifting in elevator
JPH0776473A (en) Apparatus and method for installing elevator

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees