JPS5912595B2 - Elevator installation construction method - Google Patents
Elevator installation construction methodInfo
- Publication number
- JPS5912595B2 JPS5912595B2 JP53095484A JP9548478A JPS5912595B2 JP S5912595 B2 JPS5912595 B2 JP S5912595B2 JP 53095484 A JP53095484 A JP 53095484A JP 9548478 A JP9548478 A JP 9548478A JP S5912595 B2 JPS5912595 B2 JP S5912595B2
- Authority
- JP
- Japan
- Prior art keywords
- car frame
- construction method
- work
- car
- hoistway
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
Description
【発明の詳細な説明】
本発明は、エレベータの据付は工事法に関し、その目的
とする所は、安全で且つ作業者の疲労少なく、作業効率
を著しく高める工事方法を提供するにある。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to construction methods for installing elevators, and its purpose is to provide a construction method that is safe, reduces worker fatigue, and significantly increases work efficiency.
従来のエレベータ据付は工事法は、一般的に第1図に示
す如く昇降路内に井桁状に組上げた鋼管または木材1の
上に、作業位置に応じて作業板2を渡し、この上で乗場
部品の取付けあるいは昇降路内配管、配線の取付けを行
ない、その後井桁状に組上げた足場を取外し、乗かご枠
や重りの取付けを行なうという固定足場工法が行なわれ
ていた。Conventional elevator installation is generally carried out by passing a work plate 2 on top of steel pipes or wood 1 assembled in a cross-shaped structure in the hoistway, as shown in Figure 1, depending on the work position, and then placing the work plate 2 on top of this. A fixed scaffolding method was used in which parts were installed or the hoistway piping and wiring were installed, and then the scaffolding set up in a cross-shaped structure was removed and the car frame and weights were installed.
この固定足場工法は、低層建築にエレベータを据付ける
場合は簡便で効率的な工法であるといえるが、対象とな
る建築物が高層になるに従い、作業者の上下移動(階段
を使うのが一般的であるが場合によっては固定足場を直
接登り降りする。This fixed scaffolding method can be said to be a simple and efficient construction method when installing elevators in low-rise buildings, but as the buildings in question become higher-rise, workers can move up and down (usually using stairs). In some cases, climbing directly up and down fixed scaffolding is required.
)の労力が増大して作業効率を著しく阻害することにな
る。) will increase labor and will significantly impede work efficiency.
また井桁状に組上げた足場での作業であるため犬なる危
険を伴う等の欠点があった。In addition, since the work was done on scaffolding set up in the shape of parallel cross-sections, there were drawbacks such as the danger of dogs.
本発明の目的は、作業効率を向上すると共に、安全性の
高い工事方法を提供するにある。An object of the present invention is to provide a construction method that improves work efficiency and is highly safe.
本発明は、機械室の芯出しを行ない本設の巻上機の設置
を行なう工程と、昇降路内で本設のかご枠およびおもり
を組立てこのかご枠、前記巻上機、おもりをロープ掛け
する工程と、前記巻上機により前記本設のかご枠を上下
動し乗場部品の取付けおよび昇降路内配置、配置を行な
う工程と、前記本設のかご枠への天井、側板組込みおよ
びかご廻り配線を行なう工程とからなる工事法である。The present invention involves a process of centering the machine room and installing the main hoist, assembling the main car frame and weight in the hoistway, and hanging the car frame, the hoist, and the weight with a rope. a step of moving the permanent car frame up and down using the hoisting machine to attach landing parts and arranging and arranging it in the hoistway; a step of assembling the ceiling and side panels to the main car frame and around the car; This is a construction method that includes the process of wiring.
以下本発明方法を具体化した第2図乃至第4図に基づき
説明する。The method of the present invention will be explained below based on FIGS. 2 to 4 which embody the method.
第2図は、本発明になる一例工法を主要作業順序に別記
したものを示し、第2図において2重枠取りをした作業
が動くかご枠上で行なわれる。FIG. 2 shows an example of the construction method according to the present invention, with the main work sequence separately described. In FIG. 2, the double frame work is carried out on a movable car frame.
更に詳しく本発明の工法を次に示す。The construction method of the present invention will be described in more detail below.
まず巻上機を設置する機械室の芯出しく乗かご中心やガ
イドレールの位置などの基準線をケガク)を行なった後
、専用のウィンチにより機械室関係品の荷上げを行ない
巻上機を設置する。First, mark the reference lines such as the center of the centering cage and the position of the guide rail in the machine room where the hoist will be installed, then use a special winch to lift up the machine room related items and install the hoist. Install.
次いでかとおよび重もり用ガイドレールの設置基準とな
るピアノ線を機械室から昇降路底に向けて張り渡す。Next, the piano wire that serves as the installation standard for the heel and weight guide rails is stretched from the machine room to the bottom of the hoistway.
次にこのピアノ線を基準に移動足場を用いてガイドレー
ル取付ブラケットを昇降路壁に固定する。Next, using this piano wire as a reference, the guide rail mounting bracket is fixed to the hoistway wall using a moving scaffold.
しかる後ガイドレールを連結しながらウィンチで吊り上
げ先に設置しであるピアノ線を基準に芯出しを行ない、
上端を固定し、続いて要所、要所(作業時かご枠が前後
、左右に動かない範囲で取付ピッチは荒い作業効率が良
い。After that, while connecting the guide rail, use a winch to lift it up and set it at the destination, and center it using the piano wire as a reference.
Fix the top end, then move to important points (the installation pitch is rough within the range where the car frame does not move back and forth or left and right during work, which is good for work efficiency).
)をレール取付ブラケットを介して昇降路壁に固定する
。) to the hoistway wall via the rail mounting bracket.
第3図は、レールの固定を完了した状態を示す図で、第
3図において、3は重り側、4はかご側のガイドレール
、5は昇降壁に固定されたブラケット、6はブラケット
5に締付けられレールを固定するクリップ、7は移動足
場、8を巻上機台を示す。Fig. 3 is a diagram showing the state in which the rails have been fixed. In Fig. 3, 3 is the guide rail on the weight side, 4 is the guide rail on the car side, 5 is the bracket fixed to the lifting wall, and 6 is the bracket 5. A clip is tightened to fix the rail, 7 is a movable scaffold, and 8 is a hoisting machine stand.
上記レールの固定を完了した後、機械室関係品(巻上機
、制御盤等)を取付け、低速運転用回路を結線する。After completing the fixing of the rails above, install the machine room related parts (hoisting machine, control panel, etc.) and connect the low-speed operation circuit.
次いでかご枠(かご天井および側板は作業のじゃまにな
るので最終段階で取付ける。Next, the car frame (the car ceiling and side panels will get in the way of the work, so attach them at the final stage.
)および重りを搬入して組立て、ロープ掛けする。) and weights are brought in, assembled, and roped.
次に機械室から据付用テープをかご枠に配線し、足場の
作業を完了する。Next, install tape is wired from the machine room to the car frame, completing the scaffolding work.
第4図が完成した足場の状態で、第4図において、9は
制御盤、10が巻上機、11がかご枠、12が重り、1
3がロープ、14が操作用ケーブルを示す。Figure 4 shows the completed scaffolding. In Figure 4, 9 is a control panel, 10 is a hoisting machine, 11 is a car frame, 12 is a weight, 1
3 indicates a rope, and 14 indicates an operating cable.
この足場完成後、かご枠上に作業者が乗り込み、かご枠
を低速で上下させ、ガイドレールの正規ピッチでの固定
、乗場部品の取付け、昇降炉内配管、配線を行なう。After the scaffolding is completed, a worker climbs onto the car frame, moves the car frame up and down at low speed, fixes the guide rails at the correct pitch, attaches the landing parts, and connects the pipes and wiring inside the elevator.
この作業終了後、かご枠にかご天井、側板の取付けおよ
び重りの追加(先に行った重りの組立時は、かご天井、
側板の重量分だけ少なく積込んであった。After completing this work, attach the car ceiling and side panels to the car frame, and add weights (when assembling the weights previously, the car ceiling,
The load was less than the weight of the side plates.
)を行ない、エレベータの据付は作業を完了する。) to complete the elevator installation.
以上が本発明の工法の一実施例の説明で、この例では第
2図に示す如くガイドレールの調整固定を10番目の作
業として行なうようにしたが、6番目の作業時同時に行
なってもよい。The above is an explanation of one embodiment of the construction method of the present invention. In this example, the adjustment and fixing of the guide rail is performed as the 10th work as shown in Fig. 2, but it may be performed at the same time as the 6th work. .
また7番目と8番目の作業は、これが反対でもよい。Also, the seventh and eighth tasks may be reversed.
本発明によれば、従来最終的に行なったかご枠の据付け
を先に行ない、このかご枠に乗って作業を行なうように
したので、極めて安全且つ疲労なく作業を行なうことが
できるばかりか、固定足場の取付け、取外しが全く不要
となり、極めて効率的な作業を行なうことができる。According to the present invention, the car frame, which was the final step in the conventional art, is installed first, and the work is carried out by riding on this car frame, which not only makes it possible to work extremely safely and without fatigue, but also to secure the car frame securely. There is no need to install or remove scaffolding at all, making work extremely efficient.
またかご枠を足場として利用するため、従来の如き固定
足場の鋼管等が全く不要となり、格安な据付は法である
。In addition, since the car frame is used as a scaffold, there is no need for conventional fixed scaffolding such as steel pipes, making installation inexpensive.
更に従来の工法では、横桁の取付く位置が定まっており
、従ってずれた位置では不安定な姿勢で作業しなければ
ならないが、本工法では、かご枠の上下動により極めて
容易に所定位置に移行でき、常に安定した動作業を行な
うことができる。Furthermore, in conventional construction methods, the installation position of the cross beam is fixed, and if the crossbeam is installed in a misaligned position, work must be done in an unstable posture, but with this construction method, the car frame can be moved up and down, making it extremely easy to position it in the specified position. It is possible to perform stable operation at all times.
等多くの顕著な効果を達成する。etc. achieve many remarkable effects.
第1図は、従来の代表的据付は法の固定足場工法の全体
を示す昇降炉縦断面図、第2図は、本発明の一実施例工
法の作業順序を示す図、第3図は本発明の中間工程であ
るレール取付けを完了した状態を示す図、第4図はかご
枠据付けまでを完了した状態を示す図である。
3.4・・・・・・ガイドレール、5・・・・・・ブラ
ケット、6・・・・・・固定クリップ、7・・・・・・
移動足場、8・・・・・・巻上機台、9・・・・・・制
御盤、10・・・・・・巻上機、11・・・・・・かご
枠、12・・・・・・重り、13・・・・・・ロープ、
14・・・・・・操作用ケーブル。Fig. 1 is a vertical cross-sectional view of a lift furnace showing the overall fixed scaffold construction method, which is a typical conventional installation method. Fig. 2 is a diagram showing the work order of an embodiment of the construction method of the present invention. FIG. 4 is a diagram showing a state in which the rail installation, which is an intermediate step of the invention, has been completed, and FIG. 4 is a diagram showing a state in which the car frame installation has been completed. 3.4...Guide rail, 5...Bracket, 6...Fixing clip, 7...
Moving scaffold, 8...Hoisting machine stand, 9...Control panel, 10...Hoisting machine, 11...Car frame, 12... ...Weight, 13...Rope,
14... Operation cable.
Claims (1)
う工程と、昇降路内で本設のかご枠およびおもりを組立
てこのかご枠、前記巻上機、おもりをロープ掛けする工
程と、前記巻上機により前記本設のかご枠を上下動し乗
場部品の取付けおよび昇降路内配管、配線を行なう工程
と、前記本設のかご枠への天井、側板組込みおよびかご
廻り配線を行なう工程とからなるエレベータ据付は工事
法。1. The process of centering the machine room and installing the main hoist, and the process of assembling the main car frame and weight in the hoistway and hanging the car frame, the hoist, and the weight with ropes. , a process of moving the permanent car frame up and down by the hoisting machine, installing landing parts, piping and wiring in the hoistway, and assembling the ceiling and side panels to the permanent car frame and wiring around the car. Elevator installation, which consists of processes, is the construction method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP53095484A JPS5912595B2 (en) | 1978-08-07 | 1978-08-07 | Elevator installation construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP53095484A JPS5912595B2 (en) | 1978-08-07 | 1978-08-07 | Elevator installation construction method |
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP8330271A Division JPS5245099B2 (en) | 1971-10-22 | 1971-10-22 |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS5440449A JPS5440449A (en) | 1979-03-29 |
JPS5912595B2 true JPS5912595B2 (en) | 1984-03-24 |
Family
ID=14138875
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP53095484A Expired JPS5912595B2 (en) | 1978-08-07 | 1978-08-07 | Elevator installation construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS5912595B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62105209A (en) * | 1985-10-31 | 1987-05-15 | Mitsui Seiki Kogyo Kk | Moving balance device for heavy body by motor |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2640949B1 (en) * | 1988-12-22 | 1991-03-15 | Otis Elevator Co | |
US5065843A (en) * | 1990-05-16 | 1991-11-19 | Otis Elevator Company | Method for installing elevator system components |
-
1978
- 1978-08-07 JP JP53095484A patent/JPS5912595B2/en not_active Expired
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62105209A (en) * | 1985-10-31 | 1987-05-15 | Mitsui Seiki Kogyo Kk | Moving balance device for heavy body by motor |
Also Published As
Publication number | Publication date |
---|---|
JPS5440449A (en) | 1979-03-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH07100582B2 (en) | Elevator work platform and elevator installation method | |
JPS5912595B2 (en) | Elevator installation construction method | |
JPH08245116A (en) | Installation engineering of elevator | |
JPH021066B2 (en) | ||
JP2612258B2 (en) | Elevator installation construction method | |
JPH05201648A (en) | Installation of elevator | |
JPH03267283A (en) | Installing method for elevator | |
JPH0132153B2 (en) | ||
JPH01127585A (en) | Method of installation construction of elevator | |
JPH0430213Y2 (en) | ||
JPH0733355A (en) | Installation method for elevator | |
JPS5847783A (en) | Device for installing elevator | |
JP3301923B2 (en) | Elevator work scaffolding equipment | |
JPH02305785A (en) | Elevator installation process and working floor device for elevator installation | |
JPH11117523A (en) | Lifting work platform for elevator parking and method using the same | |
JPH10218527A (en) | Temporary elevator and installing method thereof | |
JPH057307B2 (en) | ||
JPS61127586A (en) | Method of installation construction of skew elevator | |
JPS6296288A (en) | Installing device for elevator | |
JPH02300081A (en) | Installation work method for elevator | |
JPH0840666A (en) | Method for installing elevator | |
JPS5912064A (en) | Method of construction of installation of elevator | |
JPS6145876A (en) | Device for installing elevator | |
JPS5934633B2 (en) | Construction elevator installation method | |
JPH0470231B2 (en) |