JP2791829B2 - How to build a continuous underground wall - Google Patents

How to build a continuous underground wall

Info

Publication number
JP2791829B2
JP2791829B2 JP22664890A JP22664890A JP2791829B2 JP 2791829 B2 JP2791829 B2 JP 2791829B2 JP 22664890 A JP22664890 A JP 22664890A JP 22664890 A JP22664890 A JP 22664890A JP 2791829 B2 JP2791829 B2 JP 2791829B2
Authority
JP
Japan
Prior art keywords
underground wall
guide block
continuous
continuous underground
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP22664890A
Other languages
Japanese (ja)
Other versions
JPH04108909A (en
Inventor
政男 荒井
浩 大矢
誠一 原田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP22664890A priority Critical patent/JP2791829B2/en
Publication of JPH04108909A publication Critical patent/JPH04108909A/en
Application granted granted Critical
Publication of JP2791829B2 publication Critical patent/JP2791829B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】 〈産業上の利用分野〉 本発明は、水中に橋脚、トンネルの立坑、換気塔等の
構造物を製作するために、水上より連続して水底地盤内
に構築する連続地中壁の構築方法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION <Industrial Application Field> The present invention relates to a continuous construction of a pier, a shaft of a tunnel, a ventilation tower, and the like in order to manufacture a structure such as a bridge pier, a tunnel shaft, a ventilation tower, and the like on the underwater ground continuously from above the water. It relates to a method of constructing an underground wall.

〈従来の技術〉 水中に橋脚、トンネルの立坑、換気塔等を構築する
際、地中に連続して壁を構築する必要がある。
<Conventional technology> When constructing a pier, a tunnel shaft, a ventilation tower, and the like underwater, it is necessary to continuously construct a wall in the ground.

従来、このような場合、水上より水底地盤内に連続し
て地中壁を築造する方法をとっていた。
Conventionally, in such a case, a method of continuously constructing an underground wall from the surface of the water to the underwater ground has been adopted.

まず、仕切鋼材等により水底地盤から水面まで必要範
囲締め切る。
First, the necessary range from the bottom to the water surface is closed with a partition steel or the like.

その間の水を土砂、人工地盤等によって置換すること
により人工地盤を製作し、連続地中壁を構築するといっ
たものであった。
The artificial ground was manufactured by replacing the water during that time with earth and sand, artificial ground, etc., and a continuous underground wall was constructed.

〈本発明が解決しようとする問題点〉 上記のような従来の技術を利用した場合、次のような
問題点が発生する。
<Problems to be Solved by the Present Invention> When the above-described conventional technology is used, the following problems occur.

(イ)連続地中壁を築造する場合は、仕切鋼材等により
水底地盤から水面まで必要範囲締め切る。
(B) When constructing a continuous underground wall, the necessary range from the bottom to the water surface is to be closed using partition steel or the like.

そして、その間の水を土砂、人工地盤等により置換し
た後、人工地盤を製作して連続地中壁の工事を行う。
Then, after the water in the meantime is replaced with earth and sand, artificial ground, etc., artificial ground is manufactured and construction of the continuous underground wall is performed.

そのため、連続地中壁工事前の準備作業に時間がかか
り、同時に経済面においても問題が生じた。
For this reason, preparation work before the construction of the continuous underground wall takes time, and at the same time, there is a problem in terms of economy.

(ロ)仕切られた水を土砂、人工地盤等に置換する際、
周囲の水を汚染する可能性があり、環境問題となる恐れ
がある。
(B) When replacing partitioned water with earth and sand, artificial ground, etc.,
The surrounding water may be contaminated, which may cause environmental problems.

(ハ)人工地盤の製作範囲は、連続地中壁の築造範囲の
数倍の面積を必要とする。
(C) The production area of the artificial ground requires several times the area of the construction area of the continuous underground wall.

そのため、専有面積が広くなり、通行する船舶航行の
支障となる等の不都合な問題がおこる。
As a result, the occupied area becomes large, which causes inconveniences such as hindering navigation of the passing ship.

〈本発明の目的〉 本発明は上記のような問題を解決するためになされた
もので施工が容易で、施工面積をとらず、環境保全を考
慮に入れた連続地中壁の構築方法の提供を目的とする。
<Object of the present invention> The present invention has been made in order to solve the above-mentioned problems, is easy to construct, does not take up a construction area, and provides a method for constructing a continuous underground wall in consideration of environmental conservation. With the goal.

〈問題を解決するための手段〉 本願は、中空状のガイドブロックを連続設置して水底
地盤内に構築する連続地中壁の構築方法において、前記
ガイドブロック内を安定液に置換した後に水底地盤を掘
削し、掘削溝に鉄筋籠等を建て込んだ後にコンクリート
を打ち込み、以上で完成する地中壁をガイドブロック1
つおきに、上記と同じ工程で構築し、前記2枚の地中壁
の間の中空ガイドブロックに、上記と同じ工程で地中壁
を構築し、上記3枚の地中壁の構築工程を更に繰り返す
ことにより連続地中壁を形成することを特徴とする連続
地中壁の構築方法である。
<Means for Solving the Problem> The present application relates to a method of constructing a continuous underground wall in which hollow guide blocks are continuously installed and constructed in a submarine ground. Is excavated, concrete is poured into the excavation trench after reinforcing bars are built, and the underground wall completed as above is guided by guide block 1.
Every other time, the underground wall is constructed in the same process as above, and the underground wall is constructed in the hollow guide block between the two underground walls in the same process as described above. A continuous underground wall construction method characterized by forming a continuous underground wall by repeating further.

<本発明の構成> 以下、本発明を詳細に説明する。<Configuration of the Present Invention> Hereinafter, the present invention will be described in detail.

(イ)全体の構成 本発明の連続地中壁1の構築方法は、まず、中空状の
ガイドブロック2を連続して水底地盤内に構築し、前記
ガイドブロック2内側の水底地盤Aを掘削し、掘削溝に
鉄筋籠等を建て込み、コンクリートBを打ち込むことに
より1つの地中壁1aを完成させる。
(A) Overall Configuration According to the method of constructing the continuous underground wall 1 of the present invention, first, the hollow guide block 2 is continuously constructed in the underwater ground, and the underwater ground A inside the guide block 2 is excavated. Then, a steel cage or the like is erected in the excavation groove, and concrete B is driven in, thereby completing one underground wall 1a.

次に、上記の過程を利用して、ガイドブロック2cを1
つとばした隣のガイドブロック2bに地中壁1bを構築し、
更に上記の過程を利用して、前記2枚の地中壁1a、1b間
のガイドブロック2cに地中壁1cを構築する。
Next, using the above process, the guide block 2c is
Build the underground wall 1b on the next adjacent guide block 2b,
Further, the underground wall 1c is constructed on the guide block 2c between the two underground walls 1a and 1b by using the above process.

上記の3枚の連続地中壁1a、1c、1bの構築工程を繰り
返すことにより連続地中壁1を形成する。
The continuous underground wall 1 is formed by repeating the construction process of the three continuous underground walls 1a, 1c, and 1b.

(ロ)ガイドブロックの設置 第1〜11図に本発明の連続地中壁の構築方法の実施例
を示す。
(B) Installation of guide block FIGS. 1 to 11 show an embodiment of a method of constructing a continuous underground wall according to the present invention.

ガイドブロック2は、縦に長い枠体で、鋼材あるいは
PC部材等から成る。
The guide block 2 is a vertically long frame, made of steel or
It consists of PC members and the like.

前記ガイドブロック2をクレーン船等により運搬し、
水上より吊り込んだ状態から、必要な長さl(根入長
さ)だけ水底地盤Aに根入させた形で設置する。
The guide block 2 is carried by a crane ship or the like,
From the state of being suspended from above the water, it is installed so as to be embedded in the underwater ground A by a required length 1 (inset length).

更に、構築予定の連続地中壁1の面積に応じて、追加
的なガイドブロックを前記ガイドブロック2の横に連続
設置し、隣接する各ガイドブロックを公知の接合方法を
利用して接合する。
Further, according to the area of the continuous underground wall 1 to be constructed, additional guide blocks are continuously installed beside the guide blocks 2, and adjacent guide blocks are joined using a known joining method.

(ハ)水底地盤の掘削 第2〜6図に、第1地中壁の構築工程を示す。(C) Excavation of underwater ground FIGS. 2 to 6 show a construction process of the first underground wall.

ガイドブロック2を設置した後、ガイドブロック2内
の水を安定液3に置換する。
After installing the guide block 2, the water in the guide block 2 is replaced with the stabilizing liquid 3.

次に、ガイドブロック2aに地中壁1aを構築する。 Next, the underground wall 1a is constructed on the guide block 2a.

構築方法は、まず、安定液3に置換したガイドブロッ
ク2a内に公知の掘削装置4を設置する。
In the construction method, first, a known excavator 4 is installed in the guide block 2 a replaced with the stabilizing liquid 3.

そして、前記の掘削装置4を作動させ、ガイドブロッ
ク2a内側の水底地盤Aを下向に一定の深さだけ掘削す
る。
Then, the excavator 4 is operated to excavate the water bottom ground A inside the guide block 2a downward by a certain depth.

その際、掘削装置4の拡巾ビットにより、ガイドブロ
ック2a隔壁部の底部部分を拡巾掘削する。
At this time, the widening bit of the excavator 4 performs widening excavation of the bottom part of the partition wall of the guide block 2a.

(ホ)コンクリート打設 所定深度まで掘削が完成した後、第5図のように、鉄
筋又は、鋼材等の鉄筋籠5を建て込む。
(E) Concrete placement After the excavation is completed to a predetermined depth, as shown in Fig. 5, a reinforcing bar basket 5 made of a reinforcing bar or a steel material is built.

その鉄筋籠5を建て込んだ位置上部より、コンクリー
ト打設管又は、ホース等を使用してコンクリートBを打
設する。
Concrete B is cast from above the position where the reinforcing bar 5 is built using a concrete casting pipe or a hose.

以上で1枚の地中壁1aが完成する。 Thus, one underground wall 1a is completed.

(ト)第2地中壁の構築 次に、連続して地中壁を構築するために2枚目の地中
壁1bの構築工程を第7、8図に示す。
(G) Construction of Second Underground Wall Next, FIGS. 7 and 8 show a construction process of the second underground wall 1b in order to continuously construct the underground wall.

上記の工程で完成した地中壁1aの隣の中空状のガイド
ブロック2bを1つはさみ、その隣のガイドブロック2cに
2枚目の地中壁1cを構築する。
One hollow guide block 2b adjacent to the underground wall 1a completed in the above process is sandwiched, and a second underground wall 1c is constructed on the adjacent guide block 2c.

地中壁1cを構築するまでの過程における掘削よりコン
クリートB打設までの工程は、上記の地中壁1aの構築と
同様であるため省略する。
The steps from the excavation to the construction of the concrete B in the process up to the construction of the underground wall 1c are the same as the construction of the underground wall 1a, and will not be described.

以上で、間に中空状のガイドブロック2bをはさんだ2
枚のコンクリートの地中壁1a、1cが完成する。
With the above, a hollow guide block 2b is sandwiched between 2
The concrete underground walls 1a and 1c are completed.

(チ)第3地中壁の構築 次に、第9、10図に、第3地中壁の構築工程を示す。(H) Construction of Third Underground Wall Next, FIGS. 9 and 10 show a construction process of the third underground wall.

上記で完成した2枚のコンクリートの地中壁1a、1cを
連結するために、前記2の地中壁1a、1cの間のガイドブ
ロック2bに3枚目の地中壁1bを構築する。
In order to connect the two concrete underground walls 1a and 1c completed as described above, a third underground wall 1b is constructed on the guide block 2b between the two underground walls 1a and 1c.

その掘削よりコンクリートBの打設までの工程は、上
記の2枚の地中壁1a、1cと同様であるため省略する。
The steps from the excavation to the placement of the concrete B are the same as those of the above two underground walls 1a and 1c, and thus the description thereof is omitted.

以上でガイドブロック3個分の連続地中壁が完成し
た。
Thus, a continuous underground wall for three guide blocks was completed.

そして、上記の作業を繰り返すことにより、第11図の
ように更に広範囲な連続地中壁を構築する。
Then, by repeating the above operation, a further wide continuous underground wall is constructed as shown in FIG.

〈その他の実施例〉 以下、本発明のその他の実施例に関して説明する。<Other Examples> Hereinafter, other examples of the present invention will be described.

第3壁、即ち、中間の壁を構築する際、ガイドブロッ
ク内の水底地盤の掘削に拡幅カッターを利用することに
より、両サイドの壁のコンクリートまで横方向に切削し
ながら掘削することもできる。
When constructing the third wall, that is, the intermediate wall, by using a widening cutter to excavate the underground in the guide block, it is also possible to excavate while cutting laterally to concrete on both side walls.

〈本発明の効果〉 本発明によれば、次のような効果を得ることができ
る。
<Effects of the Present Invention> According to the present invention, the following effects can be obtained.

(イ)本発明のガイドブロックは、他の場所で製作し、
現場で設置するのみである。
(A) The guide block of the present invention is manufactured in another place,
It is only installed on site.

従って、人工の地盤等を製作する必要がないため、工
期が短縮されるばかりでもなく、経済性も向上する。
Therefore, since it is not necessary to manufacture an artificial ground or the like, not only the construction period is shortened, but also the economic efficiency is improved.

(ロ)本発明は、ガイドブロック内の水を安定液と置換
すればよいだけである。
(B) In the present invention, it is only necessary to replace the water in the guide block with the stabilizing liquid.

従って、周囲の水を汚染する心配がなく、環境保全に
最適である。
Therefore, there is no need to worry about contaminating surrounding water, which is optimal for environmental protection.

(ハ)ガイドブロックの設置面積は、連続地中壁に施工
面積にほぼ等しい範囲でよく、専有面積も狭くできる。
(C) The installation area of the guide block may be approximately equal to the construction area of the continuous underground wall, and the occupied area can be reduced.

従って、従来のように人工地盤の製作範囲が、連続地
中壁の築造範囲の数倍の面積を必要とするということは
ない。
Accordingly, unlike the related art, the production area of the artificial ground does not require an area several times larger than the construction area of the continuous underground wall.

更に、専有面積が狭くなるので、通行する船舶航行の
支障となったりすることがない。
Further, since the occupied area is reduced, there is no hindrance to navigation of the passing ship.

【図面の簡単な説明】[Brief description of the drawings]

第1図:ガイドブロックの斜視図 第2図:水底地盤設置後のガイドブロックの正面図 第3図:掘削時のガイドブロックの正面図 第4図:掘削後のガイドブロックの正面図 第5図:鉄筋籠設置後のガイドブロックの正面図 第6図:第1地中壁完成時の正面図 第7図:第2地中壁用掘削時のガイドブロックの正面図 第8図:第2地中壁完成時の正面図 第9図:第3地中壁用掘削時のガイドブロックの正面図 第10図:第3地中壁完成時の正面図 第11図:連続地中壁完成時の正面図 FIG. 1: A perspective view of the guide block FIG. 2: A front view of the guide block after installation on the underwater ground FIG. 3: A front view of the guide block during excavation FIG. 4: A front view of the guide block after excavation FIG. : Front view of guide block after installation of reinforcing bars Fig. 6: Front view of first underground wall when completed Fig. 7: Front view of guide block during excavation for second underground wall Fig. 8: Second ground Figure 9: Front view of the guide block during excavation for the 3rd underground wall Figure 9: Front view of the 3rd underground wall when the underground wall is completed Fig. 11: When the continuous underground wall is completed Front view

───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 昭58−146619(JP,A) 特開 昭57−130621(JP,A) (58)調査した分野(Int.Cl.6,DB名) E02D 5/18 - 5/20 E02D 19/04────────────────────────────────────────────────── ─── Continuation of the front page (56) References JP-A-58-146691 (JP, A) JP-A-57-130621 (JP, A) (58) Fields investigated (Int. Cl. 6 , DB name) E02D 5/18-5/20 E02D 19/04

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】中空状のガイドブロックを連続設置して水
底地盤内に構築する連続地中壁の構築方法において、 前記ガイドブロック内を安定液に置換した後に水底地盤
を掘削し、 掘削溝に鉄筋籠等を建て込んだ後にコンクリートを打ち
込み、 以上で完成する地中壁をガイドブロック1つおきに、上
記と同じ工程で構築し、 前記2枚の地中壁の間の中空ガイドブロックに、上記と
同じ工程で地中壁を構築し、 上記3枚の地中壁の構築工程を更に繰り返すことにより
連続地中壁を形成することを特徴とする連続地中壁の構
築方法。
1. A method for constructing a continuous underground wall in which hollow guide blocks are continuously installed and constructed in a submarine ground, wherein the guide block is replaced with a stable liquid, and then the submarine ground is excavated. Concrete is driven in after the reinforcing bars are built, and the underground wall completed as described above is constructed every other guide block by the same process as described above. In the hollow guide block between the two underground walls, A method of constructing a continuous underground wall, comprising: constructing an underground wall in the same process as described above, and forming a continuous underground wall by further repeating the three underground wall building steps.
JP22664890A 1990-08-30 1990-08-30 How to build a continuous underground wall Expired - Lifetime JP2791829B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP22664890A JP2791829B2 (en) 1990-08-30 1990-08-30 How to build a continuous underground wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP22664890A JP2791829B2 (en) 1990-08-30 1990-08-30 How to build a continuous underground wall

Publications (2)

Publication Number Publication Date
JPH04108909A JPH04108909A (en) 1992-04-09
JP2791829B2 true JP2791829B2 (en) 1998-08-27

Family

ID=16848477

Family Applications (1)

Application Number Title Priority Date Filing Date
JP22664890A Expired - Lifetime JP2791829B2 (en) 1990-08-30 1990-08-30 How to build a continuous underground wall

Country Status (1)

Country Link
JP (1) JP2791829B2 (en)

Also Published As

Publication number Publication date
JPH04108909A (en) 1992-04-09

Similar Documents

Publication Publication Date Title
CN105649094B (en) A kind of deep water foundation bearing platform construction three wall steel cofferdams and its construction method
JP2791829B2 (en) How to build a continuous underground wall
JPH1136338A (en) Construction method of underground structure
JP2001271365A (en) Construction method for underground structure
JPH10299009A (en) Method for building basement in house
JPS6117696A (en) Construction of underground head
JP2874906B2 (en) Shaft construction method
JPH06257169A (en) Small-scale basement
JP2949623B1 (en) How to build a tunnel
JPH03250117A (en) Construction method of bottom enlarged continuous wall
JPH10121465A (en) Continuos underground wall engineering method
JPH11158891A (en) Construction of basement for residence
JPS5972319A (en) Underground continuous wall work utilizing soil pillar-row wall
JPH0261573B2 (en)
JPS6290447A (en) Construction work of basement
JPH03169912A (en) Construction of sheathing wall
JPS6013086B2 (en) Construction method of underground continuous wall
JPH06346465A (en) Foundation structure and its construction
JPH0649987B2 (en) Underground continuous wall foundation construction method
JPH05321244A (en) Method of constructing self-standing sheathing wall
JPH0376922A (en) Construction of continuous underground wall and steel panel therefor
JPS63312417A (en) Water construction of continuous wall using steel caisson
JPS62211418A (en) Construction of continuous wall
JPS62244915A (en) Constructon work for continuous wall
JPS62242020A (en) Method for constructing underground structure