JP2745442B2 - Foundation structure of building - Google Patents

Foundation structure of building

Info

Publication number
JP2745442B2
JP2745442B2 JP4125477A JP12547792A JP2745442B2 JP 2745442 B2 JP2745442 B2 JP 2745442B2 JP 4125477 A JP4125477 A JP 4125477A JP 12547792 A JP12547792 A JP 12547792A JP 2745442 B2 JP2745442 B2 JP 2745442B2
Authority
JP
Japan
Prior art keywords
building
bundle
foundation
foundation structure
level adjustment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP4125477A
Other languages
Japanese (ja)
Other versions
JPH0657759A (en
Inventor
讓 入江
清 田中
典克 正
達雄 岡島
敏勝 市之瀬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sekisui Chemical Co Ltd
Original Assignee
Sekisui Chemical Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sekisui Chemical Co Ltd filed Critical Sekisui Chemical Co Ltd
Priority to JP4125477A priority Critical patent/JP2745442B2/en
Publication of JPH0657759A publication Critical patent/JPH0657759A/en
Application granted granted Critical
Publication of JP2745442B2 publication Critical patent/JP2745442B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は建物の基礎構造に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a foundation structure of a building.

【0002】[0002]

【従来の技術】従来、建物の基礎構造として、特開昭
4−47311号公報に記載のプレキャストコンクリー
ト布基礎構造がある。この従来技術は、建物の床梁に沿
って配置されるプレキャストパネルを地盤上に配置した
レベル調整用くさび上に載置し、該くさびの出し入れに
よって該プレキャストパネルの天端レベルを調整した
後、該プレキャストパネルの基部回りに基礎フーチング
型枠を取付け、コンクリートを現場打ちして基礎フーチ
ングを形成するものである。
Conventionally, as the basis structure of the building, JP-A-5
There is a precast concrete cloth foundation structure described in 4-47311. In this prior art, a precast panel arranged along a floor beam of a building is placed on a wedge for level adjustment arranged on the ground, and after adjusting the top level of the precast panel by taking in and out the wedge, A foundation footing formwork is attached around the base of the precast panel, and concrete is cast in place to form a foundation footing.

【0003】[0003]

【発明が解決しようとする課題】然しながら、従来技術
には、下記〜の問題点がある。 布基礎の基礎フーチング幅は建物荷重により異なるも
のとなるから、種々なる建物プランに対する対応が複雑
になる。即ち、プラン対応性が悪い。
However, the prior art has the following problems. Since the width of the foundation footing of the cloth foundation varies depending on the building load, the correspondence to various building plans becomes complicated. That is, plan compatibility is poor.

【0004】布基礎の立上り部となるプレキャストパ
ネルは大型重量物であり、大型の吊上げ機械を必要とす
る。また、プレキャストパネルは自立不能であり、立て
起こし困難であり、水平方向の位置決め、天端レベルの
調整も困難である。即ち、設置作業性が悪い。
[0004] The precast panel, which is the rising portion of the fabric foundation, is a large heavy object and requires a large lifting machine. Also, the precast panel is not self-supporting, is difficult to stand up, and is difficult to position in the horizontal direction and adjust the top end level. That is, the installation workability is poor.

【0005】基礎フーチング型枠の管理、型枠残材の
片付手間が多大である。即ち、現場施工性が悪い。
[0005] It takes a lot of time to manage the basic footing formwork and to clean up the remaining formwork material. That is, on-site workability is poor.

【0006】上記、により基礎施工の工期が長
い。 布基礎であるがために、軟弱地盤への対応に困難があ
る他、床下配管性、床下換気性が悪い。
Due to the above, the construction period of the foundation work is long. Because it is a cloth foundation, it is difficult to deal with soft ground, and poor underfloor piping and underfloor ventilation.

【0007】本発明は、建物の基礎構造において、建物
プランに対する対応性、設置作業性、現場施工性、工
期、軟弱地盤への対応性等を向上することを目的とす
る。
SUMMARY OF THE INVENTION It is an object of the present invention to improve the compatibility with a building plan, installation workability, on-site construction, construction period, compatibility with soft ground, and the like in a foundation structure of a building.

【0008】[0008]

【課題を解決するための手段】請求項1に記載の本発明
は、建物の基礎構造において、建物床面内における柱位
置の直下に設置されて建物荷重を集中的に受けるプレキ
ャストコンクリート束と、建物床面の外周に沿って設置
されて建物荷重を負担しない側板と、側板内の束回りを
含む全域にコンクリートを現場打ちされて形成されるべ
た基礎とを有してなるようにしたものである。
Means for Solving the Problems The present invention according to claim 1, in basic structure of the building, the precast concrete beam Ru receiving intensive installation has been building load immediately below the column location in the building floor surface the A side plate that is installed along the outer periphery of the building floor and does not bear the building load, and a solid foundation that is formed by casting concrete in the entire area including the bundle around the side plate. It is.

【0009】請求項2に記載の本発明は、請求項1記載
の本発明において更に、前記束が、べた基礎のベース配
筋と繋がる定着筋を備えてなるようにしたものである。
According to a second aspect of the present invention, in the first aspect of the present invention, the bundle further includes a fixing bar connected to a base reinforcing bar of the solid foundation.

【0010】請求項3に記載の本発明は、請求項1に記
載の本発明において更に、前記束が、天端上方から下端
下方に貫通して螺着される3本以上のレベル調整ボルト
を備え、各レベル調整ボルトの下端部は地盤上に配置し
た受金上に載置されてなるようにしたものである。
According to a third aspect of the present invention, in the first aspect of the present invention, the bundle further comprises three or more level adjusting bolts which are screwed from the upper end to the lower end. In addition, the lower end of each level adjusting bolt is mounted on a metal receiver arranged on the ground.

【0011】請求項4に記載の本発明は、請求項3に記
載の本発明において更に、前記レベル調整ボルトの上端
部に吊りフックが設けられてなるようにしたものであ
る。
According to a fourth aspect of the present invention, in the third aspect of the present invention, a suspension hook is provided at an upper end of the level adjusting bolt.

【0012】[0012]

【作用】請求項1に記載の本発明によれば、下記〜
の作用がある。 建物荷重は柱から集中的に束に作用し、ひいてはべた
基礎にて支持される。このとき、束の幅寸法は略一定と
することができ、種々なる建物プランに対する対応が単
純になる。即ち、プラン対応性が良い。
According to the first aspect of the present invention, the following:
Has the effect of Building loads act on the bundles intensively from the columns and are thus supported on solid foundations. At this time, the width of the bundle can be made substantially constant, and the correspondence to various building plans is simplified. That is, plan compatibility is good.

【0013】 プレキャストコンクリート束は小型軽量
であり、大型の吊上げ機械を必要としない。また、束は
小型軽量であることに加え、自立性が良く、立て起こし
容易であり、水平方向の位置決め、天端レベルの調整も
容易である。即ち、設置作業性が良い。
[0013] Precast concrete bundles are small and lightweight
And does not require a large lifting machine.Also, the bunch
In addition to being small and lightweight, it has good autonomy and
Easy, horizontal positioning and top level adjustment
Easy.That is, the installation workability is good.

【0014】側板を型枠として使用できるから、型枠
の管理、型枠残材の片付手間を省ける。即ち、現場施工
性が良い。
Since the side plate can be used as a formwork, the work of managing the formwork and clearing the remaining formwork can be omitted. That is, the on-site workability is good.

【0015】上記、により基礎施工の工期を短縮
できる。 べた基礎であるがために、建物荷重を広く地盤に分散
でき、軟弱地盤への対応が良い。また、床下を分断する
布基礎がないから、床下配管性、床下換気性が良い。
By the above, the construction period of the foundation work can be shortened. Because it is a solid foundation, building loads can be widely distributed over the ground, and it is suitable for soft ground. In addition, since there is no cloth foundation for dividing the underfloor, the underfloor piping and the underfloor ventilation are good.

【0016】尚、建物床面の外周に位置する側板は、
現場打ちコンクリートにて形成されるものでないから、
モルタル仕上げ等を施すことなく、それ自体を化粧材と
して使用でき、見え掛り仕上り品質を向上できる。
The side plates located on the outer periphery of the building floor surface are:
Because it is not made of cast-in-place concrete,
Without using a mortar finish or the like, it can be used as a cosmetic material itself, and the apparent finish quality can be improved.

【0017】請求項2に記載の本発明によれば、下記
の作用がある。 束の定着筋とべた基礎のベース配筋との絡み合いを介
して、束がべた基礎に立設される。従って、束に作用す
る荷重を確実にべた基礎に伝えることができ、品質を安
定にする。
According to the present invention, the following effects are obtained. The bundle is erected on the solid foundation through the entanglement between the anchors of the bundle and the base reinforcement of the solid foundation. Therefore, the load acting on the bundle can be reliably transmitted to the solid foundation, and the quality is stabilized.

【0018】請求項3に記載の本発明によれば、下記
の作用がある。 束は 3本以上のレベル調整ボルトを脚の如くにして自
立できる。また、レベル調整ボルトの束下端から突出す
る下端部を受金上で軽快に滑らせることができ、水平方
向の位置決めが容易である。また、各レベル調整ボルト
を螺動せしめ、該ボルトの束下端からの突出量を調整す
ることにより、天端レベルの調整が容易となる。従っ
て、設置作業性を向上できる。
According to the third aspect of the present invention, the following operations are provided. The bundle can be self-supporting with three or more level adjustment bolts like legs. Further, the lower end portion of the level adjusting bolt protruding from the lower end of the bundle can be slid lightly on the receiving metal, and horizontal positioning is easy. Further, by adjusting each level adjusting bolt by screwing and adjusting the amount of projection of the bolt from the lower end of the bundle, adjustment of the top end level becomes easy. Therefore, the installation workability can be improved.

【0019】請求項4に記載の本発明によれば、下記
の作用がある。 レベル調整ボルトの上端部に吊りフックを設けること
により、束の吊上げ据付け作業性を向上できる。また、
上記のレベル調整ボルトの螺動操作を束の天端上方レ
ベルにて行なうことができ、作業者は腰高にて容易に天
端レベルを調整できる。
According to the fourth aspect of the present invention, the following operations are provided. By providing the suspension hook at the upper end of the level adjustment bolt, the work of lifting and installing the bundle can be improved. Also,
The screwing operation of the level adjusting bolt can be performed at the level above the top end of the bundle, and the operator can easily adjust the top end level at waist height.

【0020】[0020]

【実施例】図1は本発明の一実施例を示す模式図、図2
はプレキャストコンクリート束を示す模式図、図3は図
2の要部断面図、図4は側板を示す模式図、図5はプレ
キャストコンクリート束の据付け過程を示す模式図、図
6は建物の基礎を示す平面図、図7は建物ユニットを示
す模式図、図8は本発明の他の実施例を示す模式図であ
る。
FIG. 1 is a schematic view showing an embodiment of the present invention, and FIG.
Is a schematic view showing a precast concrete bundle, FIG. 3 is a sectional view of a main part of FIG. 2, FIG. 4 is a schematic view showing a side plate, FIG. 5 is a schematic view showing an installation process of the precast concrete bundle, and FIG. FIG. 7 is a schematic view showing a building unit, and FIG. 8 is a schematic view showing another embodiment of the present invention.

【0021】図6の基礎10は、例えば図7の建物ユニ
ット11(木質ユニットでも良い)を組合わせて構成さ
れる建物を支持し、その荷重を地盤に伝える。
The foundation 10 shown in FIG. 6 supports a building constructed by combining, for example, the building unit 11 (or a wooden unit) shown in FIG. 7, and transmits the load to the ground.

【0022】建物ユニット11は、床梁12、天井梁1
3、柱14を箱型に接合した骨組構造体である。
The building unit 11 includes a floor beam 12 and a ceiling beam 1.
3. A frame structure in which the pillars 14 are joined in a box shape.

【0023】然るに、基礎10は、図1(A)、(B)
に示す如く、建物床面内における柱14の直下に設置さ
れるプレキャストコンクリート束(以下PC束)21
と、建物床面の外周に沿って設置される側板22と、側
板22内のPC束21回りを含む全域にコンクリートを
現場打ちされて形成されるべた基礎23とを有して構成
される。PC束21、側板22は工場にて予め製造され
た後、現場に搬入され使用される。
However, the foundation 10 is shown in FIGS. 1 (A) and 1 (B).
As shown in the figure, a precast concrete bundle (hereinafter referred to as a PC bundle) 21 installed immediately below the pillar 14 in the building floor surface
And a side plate 22 installed along the outer periphery of the floor of the building, and a solid foundation 23 formed by casting concrete on the entire area including around the PC bundle 21 in the side plate 22. After the PC bundle 21 and the side plate 22 are manufactured in a factory in advance, they are carried to the site and used.

【0024】このとき、PC束21は、図2(A)に示
す如く、平滑な天端を備えるとともに、建物ユニット1
1と緊結するアンカーボルト21Aを備えている。
At this time, the PC bundle 21 has a smooth top end as shown in FIG.
1 is provided with an anchor bolt 21 </ b> A which is tightly connected to the anchor bolt 21.

【0025】また、PC束21は、図1(C)、図2
(A)に示す如く、べた基礎23のベース配筋24と繋
る定着筋25を備えている。尚、基礎10の全体もしく
は一部において、PC束21をべた基礎23上に載せる
場合には、定着筋25は不要である。
The PC bundle 21 is shown in FIGS.
As shown in FIG. 1A, an anchoring bar 25 is provided which is connected to a base bar 24 of the solid foundation 23. When the PC bundle 21 is placed on the solid base 23 on the whole or a part of the base 10, the fixing streaks 25 are unnecessary.

【0026】また、PC束21は、図2(A)、
(B)、図3に示す如く、天端上方から下端下方に貫通
して螺着される 3本以上のレベル調整ボルト26を備
え、各レベル調整ボルト26の下端部は地盤上に配置し
た平板状の受金27上に載置される。そして、レベル調
整ボルト26の上端部には吊りフック26Aが設けられ
る。
Further, the PC bundle 21 is shown in FIG.
(B), as shown in FIG. 3, three or more level adjustment bolts 26 are screwed through from the upper end to the lower end, and the lower end of each level adjustment bolt 26 is a flat plate disposed on the ground. It is placed on the receiving money 27 in the shape of a letter. A suspending hook 26A is provided at the upper end of the level adjusting bolt 26.

【0027】尚、レベル調整ボルト26はPC束21に
埋設済のボルト挿入パイプ28の下端ナット29に螺着
する。ボルト挿入パイプ28の下端部には座金30、ナ
ット29が予め溶接一体化されている。座金30は吊り
荷重をコンクリートに伝えるためのものである。
The level adjusting bolt 26 is screwed to a lower end nut 29 of a bolt insertion pipe 28 embedded in the PC bundle 21. A washer 30 and a nut 29 are welded and integrated at the lower end of the bolt insertion pipe 28 in advance. The washer 30 is for transmitting a hanging load to concrete.

【0028】また、受金27は図2(C)の杭状の受金
31に代えることができる。受金31は地盤の所定位置
に打ち込まれ、レベル調整ボルト26の下端部を調芯的
に支える凹状頂面32を備える。
The receiving money 27 can be replaced with a pile-shaped receiving money 31 shown in FIG. The receiving metal 31 is driven into a predetermined position on the ground, and has a concave top surface 32 that supports the lower end of the level adjusting bolt 26 in a centered manner.

【0029】側板22は、図4(A)に示す換気孔33
を備えるもの、図4(B)に示す点検孔34を備えるも
の、図4(C)に示すコンクリート押え専用のもの等を
適宜選択使用できる。図1(A)は換気孔33を備えた
側板22の適用例、図8はコンクリート押え専用の側板
22の適用例である。
The side plate 22 is provided with a ventilation hole 33 shown in FIG.
4B, an inspection hole 34 shown in FIG. 4B, a concrete holder shown in FIG. 4C, etc. can be appropriately selected and used. FIG. 1A is an application example of the side plate 22 having the ventilation hole 33, and FIG. 8 is an application example of the side plate 22 dedicated to the concrete presser.

【0030】次に、基礎10の施工手順について説明す
る。 (1) PC束21を建物床面内における柱位置の直下に搬
入する。このとき、吊りフック26Aが用いられる(図
5(A)参照)。そして、レベル調整ボルト26の下端
部を地盤上に配置した受金27上に載せる。
Next, the procedure for constructing the foundation 10 will be described. (1) The PC bundle 21 is carried in just below the pillar position on the floor of the building. At this time, the hanging hook 26A is used (see FIG. 5A). Then, the lower end of the level adjustment bolt 26 is placed on the receiving metal 27 arranged on the ground.

【0031】(2) レベル調整ボルト26の下端部を受金
27上で滑らせることにてPC束21の水平方向の位置
出しを行なう。また、レベル調整ボルト26を螺動する
ことにてPC束21の天端レベルを調整する(図5
(B)、(C)参照)。
(2) The horizontal position of the PC bundle 21 is determined by sliding the lower end of the level adjusting bolt 26 on the metal receiving 27. The top end level of the PC bundle 21 is adjusted by screwing the level adjustment bolt 26 (FIG. 5).
(See (B) and (C)).

【0032】(3)建物床面の外周に沿って側板22を
設置する。 (4)側板22内のPC束21回りを含む全域にベース
配筋24を設置し、ここにコンクリートを現場打ちし、
べた基礎23を形成する。その後、PC束21のレベル
調整ボルト26を取り外す。尚、べた基礎23の打設コ
ンクリートはPC束21の下端にまで充填されないか
ら、レベル調整ボルト26の取り外しが可能となるので
ある。
(3) The side plate 22 is installed along the outer periphery of the building floor. (4) Base on the whole area including around the PC bundle 21 in the side plate 22
Reinforcing bar 24 is installed, concrete is cast in place here ,
The solid foundation 23 is formed. After that, the level adjusting bolt 26 of the PC bundle 21 is removed. In addition, since the cast concrete of the solid foundation 23 is not filled up to the lower end of the PC bundle 21, the level adjustment bolt 26 can be removed.

【0033】尚、本発明の実施によれば、基礎10の工
期は2日で足り、第1日目は鋤取、砂利敷、遣方、PC
束21設置、側板22設置であり、第2日目はベース配
筋24設置、べた基礎23の打設、埋め戻しであった。
According to the practice of the present invention, the construction period of the foundation 10 is only two days, and the first day is a plow, a gravel lay, a method of use, and a PC.
The bundle 21 was installed and the side plate 22 was installed. On the second day, the base reinforcement 24 was installed, the solid foundation 23 was placed, and backfilling was performed.

【0034】そして、建物床面積70m2 について、現場
工数は従来の10人工に対し、本発明により 4人工とする
ことができた。
With the floor area of the building of 70 m 2 , the number of man-hours required in the field can be reduced to four according to the present invention, compared to the conventional ten man-made.

【0035】以下、本実施例の作用について説明する。 建物荷重は柱14から集中的に束21に作用し、ひい
てはべた基礎23にて支持される。このとき、束21の
幅寸法は略一定とすることができ、種々なる建物プラン
に対する対応が単純になる。即ち、プラン対応性が良
い。
The operation of this embodiment will be described below. The building load acts on the bundle 21 intensively from the columns 14 and is thus supported by the solid foundation 23. At this time, the width dimension of the bundle 21 can be made substantially constant, and the correspondence to various building plans is simplified. That is, plan compatibility is good.

【0036】プレキャストコンクリート束21は小型
軽量であり、大型の吊上げ機械を必要としない。また、
束21は小型軽量であることに加え、自立性が良く、立
て起こし容易であり、水平方向の位置決め、天端レベル
の調整も容易である。即ち、設置作業性が良い。
The precast concrete bundle 21 is small and lightweight, and does not require a large lifting machine. Also,
The bundle 21 is small and lightweight, and has good self-sustainability.
Easy to raise, horizontal positioning, top level
Is easy to adjust. That is, the installation workability is good.

【0037】側板22を型枠として使用できるから、
型枠の管理、型枠残材の片付け手間を省ける。即ち、現
場施工性が良い。
Since the side plate 22 can be used as a mold,
The management of the formwork and the trouble of clearing the remaining formwork material can be omitted. That is, the on-site workability is good.

【0038】上記、により基礎施工の工期を短縮
できる。 べた基礎23であるがために、建物荷重を広く地盤に
分散でき、軟弱地盤への対応が良い。また、床下を分断
する布基礎がないから、床下配管性、床下換気性が良
い。
With the above, the construction period of the foundation work can be shortened. Because of the solid foundation 23, the building load can be widely dispersed on the ground, and it is suitable for soft ground. In addition, since there is no cloth foundation for dividing the underfloor, the underfloor piping and the underfloor ventilation are good.

【0039】尚、建物床面の外周に位置する側板22
は、現場打ちコンクリートにて形成されるものでないか
ら、モルタル仕上げ等を施すことなく、それ自体を化粧
材として使用でき、見え掛り仕上り品質を向上できる。
The side plate 22 located on the outer periphery of the building floor surface
Since is not formed by cast-in-place concrete, it can be used as a decorative material itself without applying mortar finish or the like, and the apparent finish quality can be improved.

【0040】また、側板22は換気孔33、点検孔34
等を備えることにより、それらの納まりが良く、見え掛
り仕上り品質を向上できる。
The side plate 22 has a ventilation hole 33 and an inspection hole 34.
And the like, the fit is good, and the apparent finish quality can be improved.

【0041】束21の定着筋25とべた基礎23のベ
ース配筋24との絡み合いを介して、束21がべた基礎
23に立設される。従って、束21に作用する荷重を確
実にべた基礎23に伝えることができ、品質を安定にす
る。
The bundle 21 is erected on the solid base 23 through the entanglement between the fixing streaks 25 of the bundle 21 and the base reinforcement 24 of the solid foundation 23. Therefore, the load acting on the bundle 21 can be reliably transmitted to the solid foundation 23, and the quality is stabilized.

【0042】束21は 3本以上のレベル調整ボルト2
6を脚の如くにして自立できる。また、レベル調整ボル
ト26の束下端から突出する下端部を受金27上で軽快
に滑らせることができ、水平方向の位置決めが容易であ
る。また、各レベル調整ボルト26を螺動せしめ、該ボ
ルト26の束下端からの突出量を調整することにより、
天端レベルの調整が容易となる。従って、設置作業性を
向上できる。
The bundle 21 has three or more level adjusting bolts 2
6 can be self-supporting like a leg. Further, the lower end portion of the level adjusting bolt 26 protruding from the lower end of the bundle can be slid lightly on the receiving metal 27, and horizontal positioning is easy. Also, by screwing each level adjustment bolt 26 and adjusting the amount of protrusion of the bolt 26 from the lower end of the bundle,
The top level can be easily adjusted. Therefore, the installation workability can be improved.

【0043】レベル調整ボルト26の上端部に吊りフ
ック26Aを設けることにより、束21の吊上げ据付け
作業性を向上できる。また、上記のレベル調整ボルト
26の螺動操作を束21の天端上方レベルにて行なうこ
とができ、作業者は腰高にて容易に天端レベルを調整で
きる。
By providing the suspension hook 26A at the upper end of the level adjustment bolt 26, the workability of lifting and installing the bundle 21 can be improved. Further, the screwing operation of the level adjusting bolt 26 can be performed at a level above the top end of the bundle 21, and the operator can easily adjust the top level at waist height.

【0044】[0044]

【発明の効果】以上のように本発明によれば、建物の基
礎構造において、建物プランに対する対応性、設置作業
性、現場施工性、工期、軟弱地盤への対応性等を向上す
ることができる。
As described above, according to the present invention, in the foundation structure of a building, it is possible to improve responsiveness to a building plan, installation workability, on-site workability, construction period, responsiveness to soft ground, and the like. .

【図面の簡単な説明】[Brief description of the drawings]

【図1】図1は本発明の一実施例を示す模式図である。FIG. 1 is a schematic diagram showing one embodiment of the present invention.

【図2】図2はプレキャストコンクリート束を示す模式
図である。
FIG. 2 is a schematic view showing a precast concrete bundle.

【図3】図3は図2の要部断面図である。FIG. 3 is a sectional view of a main part of FIG. 2;

【図4】図4は側板を示す模式図である。FIG. 4 is a schematic view showing a side plate.

【図5】図5はプレキャストコンクリート束の据付け過
程を示す模式図である。
FIG. 5 is a schematic view showing an installation process of a precast concrete bundle.

【図6】図6は建物の基礎を示す平面図である。FIG. 6 is a plan view showing a foundation of a building.

【図7】図7は建物ユニットを示す模式図である。FIG. 7 is a schematic diagram showing a building unit.

【図8】図8は本発明の他の実施例を示す模式図であ
る。
FIG. 8 is a schematic diagram showing another embodiment of the present invention.

【符号の説明】[Explanation of symbols]

10 基礎 14 柱 21 プレキャストコンクリート束 22 側板 23 べた基礎 24 ベース配筋 25 定着筋 26 レベル調整ボルト 26A 吊りフック 27 受金 10 Foundation 14 Pillar 21 Precast Concrete Bundle 22 Side Plate 23 Solid Foundation 24 Base Reinforcement 25 Fixing Reinforcement 26 Level Adjustment Bolt 26A Suspension Hook 27 Receipt

───────────────────────────────────────────────────── フロントページの続き (72)発明者 岡島 達雄 愛知県愛知郡長久手町長湫山野田32− 182 (72)発明者 市之瀬 敏勝 愛知県名古屋市千種区高見1−23−3 (56)参考文献 特開 平4−209234(JP,A) ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Tatsuo Okajima 32-182, Chuchuyama Noda, Nagakute-cho, Aichi-gun, Aichi Prefecture JP-A-4-209234 (JP, A)

Claims (4)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 建物の基礎構造において、 建物床面内における柱位置の直下に設置されて建物荷重
を集中的に受けるプレキャストコンクリート束と、 建物床面の外周に沿って設置されて建物荷重を負担しな
側板と、 側板内の束回りを含む全域にコンクリートを現場打ちさ
れて形成されるべた基礎とを有してなることを特徴とす
る建物の基礎構造。
In a foundation structure of a building, a building load is installed immediately below a column position in a building floor.
And precast concrete beams Ru received intensive and, Do not bear the building load is placed along the outer periphery of the building floor
Infrastructure of the building, characterized and have side plates, to become and a solid basis is formed by cast-in-place concrete in whole comprising a bundle around the side plate.
【請求項2】 前記束が、べた基礎のベース配筋と繋が
る定着筋を備えてなる請求項1記載の建物の基礎構造。
2. The foundation structure of a building according to claim 1, wherein the bundle includes anchoring bars connected to a base reinforcement of a solid foundation.
【請求項3】 前記束が、天端上方から下端下方に貫通
して螺着される3本以上のレベル調整ボルトを備え、各
レベル調整ボルトの下端部は地盤上に配置した受金上に
載置されてなる請求項1記載の建物の基礎構造。
3. The bundle includes three or more level adjustment bolts that are screwed through from the top end to the bottom end, and the lower end of each level adjustment bolt is mounted on a metal receiver disposed on the ground. The foundation structure of a building according to claim 1, which is mounted.
【請求項4】 前記レベル調整ボルトの上端部に吊りフ
ックが設けられてなる請求項3記載の建物の基礎構造。
4. The foundation structure of a building according to claim 3, wherein a suspension hook is provided at an upper end of the level adjustment bolt.
JP4125477A 1992-04-20 1992-04-20 Foundation structure of building Expired - Fee Related JP2745442B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4125477A JP2745442B2 (en) 1992-04-20 1992-04-20 Foundation structure of building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4125477A JP2745442B2 (en) 1992-04-20 1992-04-20 Foundation structure of building

Publications (2)

Publication Number Publication Date
JPH0657759A JPH0657759A (en) 1994-03-01
JP2745442B2 true JP2745442B2 (en) 1998-04-28

Family

ID=14911062

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4125477A Expired - Fee Related JP2745442B2 (en) 1992-04-20 1992-04-20 Foundation structure of building

Country Status (1)

Country Link
JP (1) JP2745442B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0892970A (en) * 1994-09-28 1996-04-09 Natl House Ind Co Ltd Foundation structure
JP7032253B2 (en) * 2018-07-02 2022-03-08 積水化学工業株式会社 Foundation structure of the building

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2939499B2 (en) * 1990-06-08 1999-08-25 積水ハウス株式会社 Precast concrete panel and manufacturing method thereof

Also Published As

Publication number Publication date
JPH0657759A (en) 1994-03-01

Similar Documents

Publication Publication Date Title
US5664377A (en) Apparatus and method to a ground surface foundation
JP2745442B2 (en) Foundation structure of building
JP3107716B2 (en) Soil retaining wall
JP2004100157A (en) Retaining wall structure and its construction method
JPH09151463A (en) Column-integrated column base anchoring foundation structire and work execution method therefor
JP2567631Y2 (en) Level adjuster for steel foundation beams
JP3116990B2 (en) Precast reinforced concrete foundation structure
JP3827907B2 (en) Solid foundation construction method
JPH08158341A (en) Joining structure of pile and beam
JPH0971946A (en) Foundation
JPH08218392A (en) Foundation and building method thereof
JP3110341B2 (en) Construction formwork and method of fabric foundation or fence for housing
JP4204702B2 (en) Building method and building structure
KR100590178B1 (en) Fixing apparatus of cast using a dirt wall
JP2784450B2 (en) Reinforced concrete foundation
JPS6215292Y2 (en)
JP3249076B2 (en) Building floor and foundation structure
JPH084026A (en) Foundation structure and execution method of foundation
JPH0336326A (en) Method of execution for foundation
JP3098107B2 (en) Underground beam construction method
JPH02248527A (en) Constructing foundation structure
JPH09158205A (en) Construction method for precast reinforced concrete foundation, and construction ruler
JPH04128430A (en) Concrete foundation
JP3005885B2 (en) How to build the foundation of a structure
JPS59199935A (en) Disposable mold frame panel construction method

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19980113

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080213

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090213

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090213

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100213

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100213

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110213

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120213

Year of fee payment: 14

LAPS Cancellation because of no payment of annual fees