JP2716919B2 - Turbine building construction method - Google Patents

Turbine building construction method

Info

Publication number
JP2716919B2
JP2716919B2 JP4346976A JP34697692A JP2716919B2 JP 2716919 B2 JP2716919 B2 JP 2716919B2 JP 4346976 A JP4346976 A JP 4346976A JP 34697692 A JP34697692 A JP 34697692A JP 2716919 B2 JP2716919 B2 JP 2716919B2
Authority
JP
Japan
Prior art keywords
mat
turbine building
construction
turbine
circulating water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP4346976A
Other languages
Japanese (ja)
Other versions
JPH06193293A (en
Inventor
孝三 山ノ井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP4346976A priority Critical patent/JP2716919B2/en
Publication of JPH06193293A publication Critical patent/JPH06193293A/en
Application granted granted Critical
Publication of JP2716919B2 publication Critical patent/JP2716919B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明はタービン建屋の建設工法
に係り、特に建設期間を短縮させるタービン建屋建設工
法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method of a turbine building, and more particularly to a construction method of a turbine building for shortening a construction period.

【0002】[0002]

【従来の技術】原子力発電所に建設されるタービン建屋
(以下T/Bと称す)1は通常図6に示すように、基礎
部のT/Bマット2上に建設される。このT/Bマット
2の下方に復水器3に接続される循環水配管(以下CW
Pと称す)4が埋設され、このCWP4は、人造岩であ
るマンメイドロック(Man Made Rock、以
下MMRと称す)5に囲まれている。
2. Description of the Related Art A turbine building (hereinafter referred to as T / B) 1 to be constructed in a nuclear power plant is usually constructed on a T / B mat 2 at a foundation as shown in FIG. A circulating water pipe (hereinafter CW) connected to the condenser 3 below the T / B mat 2
PWP 4 is buried, and this CWP 4 is surrounded by a man-made rock (Man Made Rock, hereinafter referred to as MMR) 5 which is an artificial rock.

【0003】図7は、T/Bマット2の平面図であり、
説明の便宜上四つの区画A,B,C,Dに分けられ、図
8は、図7に示されるT/Bマット2のY−Y線に沿う
断面図である。
FIG. 7 is a plan view of the T / B mat 2.
It is divided into four sections A, B, C, and D for convenience of explanation, and FIG. 8 is a cross-sectional view of the T / B mat 2 shown in FIG.

【0004】CWP4は、T/Bマット2のB部下方の
MMR5に埋設される。CWP4は、T/B1の敷地が
掘削された後、各スプールごとに搬入・設置され、設置
場所にて組み立て・溶接が行われ、CWP4が構成され
る。そしてCWP4の組立て完了後にMMR5が打設さ
れ、その上にT/Bマット2が打設される。
The CWP 4 is embedded in the MMR 5 below the B portion of the T / B mat 2. After excavating the site of T / B1, CWP4 is carried in and installed for each spool, and assembling and welding are performed at the installation location, thereby forming CWP4. After the assembly of the CWP 4 is completed, the MMR 5 is cast, and the T / B mat 2 is cast thereon.

【0005】次に、T/Bマット2上にペデスタル6が
設置される。このペデスタル6の立設とともにT/B1
の建設工事が進められる。そしてT/B1上に鉄骨7の
建方を行い、オペレーションフロア8より上階壁を設け
る。その後、鉄骨7の最終建方の前に天井クレーン9の
上架・組み立てを行う。天井クレーン9を組み立てた後
にクレーン9の作動試験を行い、この天井クレーン9を
タービン本体10の組立てに使用する。
Next, a pedestal 6 is set on the T / B mat 2. T / B1 with the pedestal 6 standing
Construction work is underway. Then, the steel frame 7 is constructed on the T / B 1, and an upper floor wall is provided above the operation floor 8. Thereafter, the overhead crane 9 is mounted and assembled before the final construction of the steel frame 7. After assembling the overhead crane 9, an operation test of the crane 9 is performed, and the overhead crane 9 is used for assembling the turbine body 10.

【0006】最後に、ペデスタル6の設置完了後に復水
器3の組立てを行い、この復水器3をタービン本体10
に接続させている。
[0006] Finally, after the pedestal 6 has been installed, the condenser 3 is assembled, and the condenser 3 is attached to the turbine body 10.
Connected to

【0007】[0007]

【発明が解決しようとする課題】しかしながら、図7の
B部はCWP4をMMR5に埋設するため、B部を他の
A,C,D部より深く掘削しなければならない。B部の
掘削の完了後、CWP4を各スプールごとに搬入して組
み立て、CWP4の組立てが完了しないとB部のMMR
5の打設が行なえず、その間他のA,C,D部のT/B
マット2の打設作業は滞ることになる。
However, the portion B in FIG. 7 has to be excavated deeper than the other portions A, C and D in order to bury the CWP 4 in the MMR 5. After the excavation of the part B is completed, the CWP4 is loaded into each spool and assembled. If the assembly of the CWP4 is not completed, the MMR of the part B is required.
5 could not be cast, and during that time T / B of other A, C, D parts
The operation of placing the mat 2 will be delayed.

【0008】CWP4は各スプールごとに分かれて搬入
・設置されるため、組立てに大きな作業スペースを必要
とし、溶接作業に多くの労力と時間を必要とする。
[0008] Since the CWP 4 is loaded and installed separately for each spool, a large work space is required for assembling, and much labor and time are required for welding work.

【0009】そしてB部のMMR5打設が終了するまで
T/Bマット2は打設できず、そのためT/Bマット2
上に立設されるべきペデスタル6の設置が遅れ、その結
果、鉄骨7の建方,天井クレーン9の組み立て・試験,
復水器3の組み立て等、建設作業全体の工程に遅れが生
ずる。
[0009] The T / B mat 2 cannot be cast until the MMR5 casting of the portion B is completed.
The installation of the pedestal 6 to be erected on the top was delayed, and as a result, the construction of the steel frame 7, the assembly / test of the overhead crane 9,
Delays occur in the entire construction work such as the assembly of the condenser 3.

【0010】この遅れは、T/B建築側とタービン機器
等の機械取付け側との作業スケジュールの調整を複雑に
し、原子力発電所等の全体工期におけるクリティカルパ
スとなり、建設工期が長期化する最大の原因となってい
る。
[0010] This delay complicates the adjustment of the work schedule between the T / B building side and the machine mounting side of turbine equipment and the like, becomes a critical path in the entire construction period of the nuclear power plant and the like, and is the largest in which the construction period is prolonged. Cause.

【0011】本発明は上述した事情を考慮してなされた
もので、タービン建屋の建設工数を低減し、建設工期を
短縮させるとともに、作業の安全性、能率を向上させる
タービン建屋の建設工法を提供することを目的とする。
The present invention has been made in view of the above circumstances, and provides a construction method of a turbine building which reduces the number of construction steps of the turbine building, shortens the construction period, and improves work safety and efficiency. The purpose is to do.

【0012】[0012]

【課題を解決するための手段】本発明に係るタービン建
屋の建設工法は、上述した課題を解決するために、請求
項1に記載したように、マット下循環水配管を大ブロッ
ク化し、タービン建屋マット下部での循環水配管工事と
循環水配管周辺の人造岩打設工事とを別途に平行して立
上げ、タービン建屋のペデスタル部のマット部を早期に
完成させるものである。
According to the construction method of a turbine building according to the present invention, in order to solve the above-mentioned problem, as described in claim 1, the circulating water pipe under the mat is made large and the turbine building is constructed. The circulating water piping work at the lower part of the mat and the artificial rock setting work around the circulating water piping are started separately in parallel, and the mat part of the pedestal part of the turbine building is completed early.

【0013】[0013]

【作用】上記の構成を有する本発明においては、マット
下循環水配管を大ブロック化し、タービン建屋マット下
部での循環水配管工事と循環水配管周辺の人造岩打設工
事とを別途に平行して立上げ、タービン建屋のペデスタ
ル部マット部を早期に完成させることにより、タービン
建屋の建築側の循環水配管周辺の人造岩工事を循環水配
管工事の完了を待たずに行えることになり、ペデスタル
の設置およびその後に続く作業を能率よく行え、タービ
ン建屋建設の建設工期を短縮できる。
In the present invention having the above structure, the circulating water piping below the mat is made into a large block, and the circulating water piping work under the mat of the turbine building and the artificial rock placing work around the circulating water piping are separately performed in parallel. The pedestal mat of the turbine building will be completed at an early stage, and artificial rock work around the circulating water piping on the building side of the turbine building can be performed without waiting for the completion of the circulating water piping work. Installation and subsequent work can be performed efficiently, and the construction period of turbine building construction can be shortened.

【0014】[0014]

【実施例】以下、本発明の実施例を図面に基づいて説明
する。
Embodiments of the present invention will be described below with reference to the drawings.

【0015】図1は、本発明を適用した原子力発電所に
建設されるタービン建屋(T/B)11の断面図であ
り、図2(A)および(B)は、T/B11のコンクリ
ート基礎部に埋設されるマット下循環水配管(CWP)
14aの組立・敷設状態をそれぞれ示す正面図および側
面図である。図3は、T/Bマット12a,12bの平
面図である。図3では、説明の便宜上T/Bマット12
a,12bを四つの区画に分け、それぞれA1,B1,
C1,D1と付す。図4は図3に示すT/Bマット12
a,12bのX−X線に沿う断面図である。
FIG. 1 is a sectional view of a turbine building (T / B) 11 constructed in a nuclear power plant to which the present invention is applied. FIGS. 2 (A) and 2 (B) show concrete foundations of the T / B 11. Circulating water pipe (CWP) buried in the part
It is the front view and side view which each show the assembly and laying state of 14a. FIG. 3 is a plan view of the T / B mats 12a and 12b. In FIG. 3, for convenience of explanation, the T / B mat 12
a, 12b are divided into four sections, and A1, B1,
Labeled C1 and D1. FIG. 4 shows the T / B mat 12 shown in FIG.
It is sectional drawing which follows the XX line of a and 12b.

【0016】図1において、T/B11はT/Bマット
12a,12b上に建設されるようになっている。T/
Bマット12bの下方にCWP14a,14bが設置さ
れる。CWP14a,14bは、予め外部にて二つのブ
ロックに大ブロック化されている。
In FIG. 1, a T / B 11 is constructed on T / B mats 12a and 12b. T /
The CWPs 14a and 14b are installed below the B mat 12b. The CWPs 14a and 14b are previously divided into two large blocks outside.

【0017】T/Bマット12a,12bの下部に設置
されたCWP14a,14bやその周囲には、人造岩と
してのMMR15a,15bが打設され、CWP14
a,14bは、MMR15a,15bに囲まれるように
なっている。
The MWPs 15a and 15b as artificial rocks are cast on the CWPs 14a and 14b provided under the T / B mats 12a and 12b and around the CWPs 14a and 14b.
a and 14b are surrounded by the MMRs 15a and 15b.

【0018】図3において、T/Bマット12a,12
bの上にはペデスタル16a,16bが設置され、ペデ
スタル16a,16bの設置完了後には復水器13が取
付けられ、組み立てられる。この復水器13にCWP1
4a,14bが接続されるようになっている。
In FIG. 3, T / B mats 12a and 12
The pedestals 16a and 16b are installed on the b. After the installation of the pedestals 16a and 16b is completed, the condenser 13 is attached and assembled. This condenser 13 has CWP1
4a and 14b are connected.

【0019】T/B11はコンクリート躯体や鉄骨17
により建築され、T/B11の上部にはオペレーション
フロア18が設けられる。鉄骨17の上部には天井クレ
ーン19が設けられている。
T / B 11 is a concrete frame or steel frame 17.
The operation floor 18 is provided above the T / B 11. An overhead crane 19 is provided above the steel frame 17.

【0020】復水器13上部にはタービン本体20が設
置され、このタービン本体20は復水器13と接続され
る。タービン本体20で仕事をした蒸気が復水器13に
案内され、この復水器13で冷却されて復水となるよう
になっている。
A turbine body 20 is installed above the condenser 13, and the turbine body 20 is connected to the condenser 13. The steam that has worked in the turbine body 20 is guided to the condenser 13 and is cooled by the condenser 13 to be condensed.

【0021】次に、タービン建屋11の建設工程の手順
を図5を参照して説明する。
Next, the procedure of the construction process of the turbine building 11 will be described with reference to FIG.

【0022】T/B11の敷地を掘削し、掘削が完了し
た後、CWP14a,14bを大型揚重機にて所定の位
置に搬入・設置し、組立て・溶接の作業をする。この場
合、CWP14a,14bは予め外部で大きく二つのブ
ロックに組立てられているため、溶接作業が一ヶ所にな
り、設置位置での組立て・溶接作業は軽減,短縮される
とともに、作業スペースの省スペース化が図れ、他の空
いたスペースを利用してT/B11の建築側の垂直MM
R15aの打設を行うことができる。
After excavating the site of the T / B 11 and completing the excavation, the CWPs 14a and 14b are carried in and set at predetermined positions by a large-sized hoist, and assembled and welded. In this case, since the CWPs 14a and 14b are pre-assembled outside into two large blocks, the welding work is reduced to one place, and the assembling and welding work at the installation position is reduced and shortened, and the working space is reduced. Vertical MM on the building side of T / B11 using other vacant space
R15a can be cast.

【0023】したがって、CWP14a,14bの設置
・組立て・溶接作業中に、CWP14a,14bの周り
の(図3のA1,C1,D1部分)の垂直MMR15a
の打設作業を同時に平行して行なうことができる。この
垂直MMR15aの打設終了後、B1部を除いてT/B
マット12aの打設を行い、T/B11のペデスタル部
マット部12aを早期に完成させることができる。
Therefore, during installation, assembly and welding of the CWPs 14a and 14b, the vertical MMRs 15a around the CWPs 14a and 14b (portions A1, C1 and D1 in FIG. 3).
Can be performed simultaneously in parallel. After the completion of the vertical MMR 15a, T / B
The mat 12a is cast and the pedestal mat portion 12a of the T / B 11 can be completed early.

【0024】この様に、A1,C1,D1部のT/Bマ
ット12aの打設はCWP14a,14bのMMR15
bの打設作業完了を待たずに行えるので、作業時間の短
縮が計れる。これにより、A1,C1部分のT/B11
のペデスタル部マット部12aを早期に完成させること
ができる。
As described above, the placement of the T / B mat 12a in the A1, C1, and D1 portions is performed by the MMR 15 of the CWPs 14a and 14b.
Since the operation can be performed without waiting for the completion of the placing operation b, the operation time can be reduced. Thereby, T / B11 of A1, C1 part
The pedestal mat portion 12a can be completed early.

【0025】図3のA1,C1,D1部分のT/Bマッ
ト12aの打設終了後、A1,C1部分にペデスタル1
6aを設置する。このペデスタル16aの設置作業と平
行してT/B11のコンクリート躯体の建設工事に着手
し、この建屋工事の終了とともに鉄骨17の建方を開始
し、オペレーションフロア18より上階壁を設ける。そ
して鉄骨17の最終建方の前に天井クレーン19の上架
・組み立てを行う。天井クレーン19を組み立てた後に
天井クレーン19の作動試験を行い、この天井クレーン
19をタービン本体20の組立てに使用する。
After the placement of the T / B mat 12a at the A1, C1, and D1 portions in FIG. 3, the pedestal 1 is placed at the A1 and C1 portions.
6a is installed. In parallel with the work of installing the pedestal 16a, the construction work of the concrete frame of the T / B 11 is started. At the end of the construction work, the construction of the steel frame 17 is started, and the upper floor wall is provided from the operation floor 18. Then, before the final construction of the steel frame 17, the overhead crane 19 is mounted and assembled. After assembling the overhead crane 19, an operation test of the overhead crane 19 is performed, and the overhead crane 19 is used for assembling the turbine body 20.

【0026】一方、T/Bマット12bのB1部分は、
CWP14a,14bの設置作業完了後にMMR15b
の打設を行ない、その後T/Bマット12bの打設を行
なう。T/Bマット12bの打設完了後に、T/Bマッ
ト12bのB1部分にペデスタル16bを設置する。
On the other hand, the B1 portion of the T / B mat 12b is
MMR 15b after installation work of CWP 14a, 14b is completed
And then the T / B mat 12b. After the placement of the T / B mat 12b is completed, the pedestal 16b is placed on the B1 portion of the T / B mat 12b.

【0027】しかして、ペデスタル16a,16bの設
置(立設)作業は、T/B11のコンクリート躯体の建
設工事と並行して行われ、ペデスタル16a,16bの
設置完了後に復水器13の組立てを行なう。
The installation (standing) of the pedestals 16a and 16b is performed in parallel with the construction of the concrete skeleton of the T / B 11, and after the pedestals 16a and 16b have been installed, the condenser 13 is assembled. Do.

【0028】組み立てられた復水器13は、タービン本
体20に接続してタービン機器の据付けを完了し、ター
ビン建屋の建設作業を終了させることができる。
The assembled condenser 13 is connected to the turbine body 20 to complete the installation of the turbine equipment, thereby completing the construction of the turbine building.

【0029】[0029]

【発明の効果】以上説明したように、本発明に係るター
ビン建屋建設工法によれば、マット下循環水配管を大ブ
ロック化し、タービン建屋マット下部での循環水配管工
事と循環水配管周辺の人造岩打設工事とを別途に平行し
て立上げ、タービン建屋のペデスタル部のマット部を早
期に完成させることにより、タービン建屋の建築側の循
環水配管周辺の人造岩打設工事を循環水配管工事の完了
を待たずに行えることになり、ペデスタルの設置および
その後に続く作業を能率よく行え、タービン建屋の建設
建設工期を短縮できる。
As described above, according to the construction method of the turbine building according to the present invention, the circulating water piping under the mat is made to be a large block, and the circulating water piping work under the mat of the turbine building and the artificial construction around the circulating water piping are performed. Starting the rock construction work separately and in parallel, the mat part of the pedestal part of the turbine building was completed at an early stage, and the artificial rock placement work around the construction water circulation pipe on the turbine building construction side was completed. Since the work can be performed without waiting for the completion of the construction, the installation of the pedestal and the subsequent work can be performed efficiently, and the construction period of the turbine building can be shortened.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明を適用したタービン建屋の一実施例を示
す断面図。
FIG. 1 is a sectional view showing an embodiment of a turbine building to which the present invention is applied.

【図2】(A)および(B)は、マット下循環水配管の
組立・敷設状態をそれぞれ示す正面図および側面図。
FIGS. 2 (A) and (B) are a front view and a side view, respectively, showing an assembled / laid state of a circulating water pipe below a mat.

【図3】本発明に係るタービン建屋マットの平面図。FIG. 3 is a plan view of a turbine building mat according to the present invention.

【図4】図3に示すタービン建屋マットのX−X線に沿
う断面図。
FIG. 4 is a cross-sectional view of the turbine building mat shown in FIG. 3, taken along line XX.

【図5】タービン建屋の建設工程の手順を示す図。FIG. 5 is a diagram showing a procedure of a construction process of a turbine building.

【図6】タービン建屋の従来例を示す断面図。FIG. 6 is a sectional view showing a conventional example of a turbine building.

【図7】従来のタービン建屋マットの平面図。FIG. 7 is a plan view of a conventional turbine building mat.

【図8】図7に示す従来のタービン建屋マットのY−Y
線に沿う断面図。
FIG. 8 is a sectional view of the conventional turbine building mat shown in FIG.
Sectional view along the line.

【符号の説明】[Explanation of symbols]

1,11 タービン建屋(T/B) 2,12a,12b タービン建屋マット(T/Bマッ
ト) 3,13 復水器 4,14a,14b 循環水配管(CWP) 5,15a,15b 人造岩(MMR) 6,16a,16b ペデスタル 7,17 鉄骨 8、18 オペレーションフロア 9,19 天井クレーン 10,20 タービン本体
1,11 Turbine building (T / B) 2,12a, 12b Turbine building mat (T / B mat) 3,13 Condenser 4,14a, 14b Circulating water pipe (CWP) 5,15a, 15b Artificial rock (MMR) 6,16a, 16b Pedestal 7,17 Steel frame 8,18 Operation floor 9,19 Overhead crane 10,20 Turbine body

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 原子力発電所構内に配置されるタービン
建屋の建設において、マット下循環水配管を大ブロック
化し、タービン建屋マット下部での循環水配管工事と循
環水配管周辺の人造岩打設工事とを別途に平行して立上
げ、タービン建屋のペデスタル部マット部を早期に完成
させることを特徴とするタービン建屋建設工法。
In the construction of a turbine building to be arranged in a nuclear power plant yard, a circulating water pipe below the mat is made into a large block, and a circulating water pipe is constructed below the mat of the turbine building and an artificial rock is poured around the circulating water pipe. The turbine building construction method is characterized in that the pedestal mat part of the turbine building is completed at an early stage in parallel with the start-up of the turbine building.
JP4346976A 1992-12-25 1992-12-25 Turbine building construction method Expired - Fee Related JP2716919B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4346976A JP2716919B2 (en) 1992-12-25 1992-12-25 Turbine building construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4346976A JP2716919B2 (en) 1992-12-25 1992-12-25 Turbine building construction method

Publications (2)

Publication Number Publication Date
JPH06193293A JPH06193293A (en) 1994-07-12
JP2716919B2 true JP2716919B2 (en) 1998-02-18

Family

ID=18387089

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4346976A Expired - Fee Related JP2716919B2 (en) 1992-12-25 1992-12-25 Turbine building construction method

Country Status (1)

Country Link
JP (1) JP2716919B2 (en)

Also Published As

Publication number Publication date
JPH06193293A (en) 1994-07-12

Similar Documents

Publication Publication Date Title
JP4164857B2 (en) Reconstruction method using existing underground structure
US5119598A (en) Method of construction of top slab for a nuclear containment building
JP2716919B2 (en) Turbine building construction method
JPH11337675A (en) Reactor-containment vessel and its building method
JP3015415B2 (en) Nuclear power plant construction method
JPS6137692Y2 (en)
JP2624851B2 (en) Circulating water piping construction method
JP3098107B2 (en) Underground beam construction method
JP3319458B2 (en) Temporary receiving method of existing building by flat beam reinforcement
JPH08105122A (en) Underground and aboveground simultaneous execution method of structure
JPS63308B2 (en)
JP2001193290A (en) Seismic isolation method for existing building
JPH08313674A (en) Method for building reactor building
JP2940451B2 (en) How to build underground structures
JP2945707B2 (en) Installation method of pedestal supporting reactor pressure vessel
JP3171716B2 (en) Foundation construction method on inclined surface
JPH0565717A (en) Prefabrication work of reinforcing bar for foundation
JPS6073916A (en) Construction method for underground floor
KR0148710B1 (en) Platform for constructing an atomic energy power plant and method of constructing the same
JPH11229408A (en) Installation method of apparatus
JP3023760U (en) Foundation pile
JP3110059B2 (en) Containment vessel construction method for nuclear power plants
JPS6356370B2 (en)
JPH0428855B2 (en)
JPH0765313B2 (en) Underground construction method

Legal Events

Date Code Title Description
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20071107

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081107

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091107

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101107

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101107

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111107

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121107

Year of fee payment: 15

LAPS Cancellation because of no payment of annual fees