JP2662119B2 - Installation method of underground tank storage device - Google Patents

Installation method of underground tank storage device

Info

Publication number
JP2662119B2
JP2662119B2 JP3265077A JP26507791A JP2662119B2 JP 2662119 B2 JP2662119 B2 JP 2662119B2 JP 3265077 A JP3265077 A JP 3265077A JP 26507791 A JP26507791 A JP 26507791A JP 2662119 B2 JP2662119 B2 JP 2662119B2
Authority
JP
Japan
Prior art keywords
installation
base
underground tank
frame
reinforced concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP3265077A
Other languages
Japanese (ja)
Other versions
JPH0598657A (en
Inventor
隆一 山本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHIKATAN KK
Original Assignee
CHIKATAN KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHIKATAN KK filed Critical CHIKATAN KK
Priority to JP3265077A priority Critical patent/JP2662119B2/en
Publication of JPH0598657A publication Critical patent/JPH0598657A/en
Application granted granted Critical
Publication of JP2662119B2 publication Critical patent/JP2662119B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】この発明は、ガソリン、灯油、重
油等の危険物等を貯蔵するための地下タンク貯蔵装置の
設置工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for installing an underground tank storage device for storing dangerous substances such as gasoline, kerosene, and heavy oil.

【0002】[0002]

【従来の技術】従来、この種の地下タンク貯蔵装置を設
置する場合には、装置の設置箇所の地面に設置穴を掘
り、その設置穴の底部にグリ石を敷き、そのグリ石上に
仮枠の組付け、基盤用の鉄骨の組付け、支柱用の鉄骨の
組付け及びコンクリートの打設を行って、基盤及び支柱
を形成し、この基盤及び支柱が硬化した後、基盤上に地
下タンクを据付け、この状態で設置穴を埋め戻し、その
後、支柱上に仮枠の組付け、鉄筋の組付け及びコンクリ
ートの打設を行って、上盤を形成するという工法が採ら
れていた。
2. Description of the Related Art Conventionally, when installing this kind of underground tank storage device, an installation hole is dug in the ground at a place where the device is installed, a gemstone is laid at the bottom of the installation hole, and a temporary frame is placed on the gemstone. After the installation of the steel frame for the base, the installation of the steel frame for the base, the installation of the steel frame for the support, and the casting of concrete, the base and the support are formed, and after the base and the support are hardened, the underground tank is mounted on the base. In this state, the installation holes were backfilled in this state, and after that, a temporary frame was assembled on the support, the reinforcing bars were assembled, and concrete was cast to form an upper panel.

【0003】ところが、この従来の設置工法において
は、基盤、支柱及び上盤の形成を全て現場施工にて行っ
ているため、設置工事が面倒で長い工期を必要とすると
共に、それらの形成品質を一定に保つことができないと
いう問題があった。
However, in the conventional installation method, since the formation of the base, the support, and the upper panel are all performed by on-site construction, the installation work is troublesome and requires a long construction period, and the formation quality thereof is reduced. There was a problem that it could not be kept constant.

【0004】このような問題点を解消するために、例え
ば特開昭59−41570号公報に示すような地下タン
ク貯蔵装置の設置工法も従来から提案されている。この
設置工法においては、鉄筋コンクリート製の基盤、支柱
及び上盤を工場にて予め製造しておき、それらを地下タ
ンクと共にトラックにより設置現場まで運搬して、施工
順序に従いクレーンで吊り下げながら据付けていくよう
になっている。
In order to solve such a problem, a method of installing an underground tank storage device, for example, as disclosed in Japanese Patent Laid-Open No. 59-41570, has been conventionally proposed. In this installation method, reinforced concrete bases, columns, and upper panels are manufactured in advance at the factory, transported to the installation site by truck together with the underground tank, and installed while hanging with a crane according to the construction order. It has become.

【0005】[0005]

【発明が解決しようとする課題】しかしながら、この従
来の設置工法においては、基盤及び上盤がそれぞれ1枚
の厚手の鉄筋コンクリート板から構成されているため、
例えば1万リットル以上の大容量の地下タンクを設置す
る場合には、基盤及び上盤も大型で大重量になって、ト
ラックによる運搬やクレーンによる吊り下げ作業が困難
になるという問題があった。
However, in this conventional installation method, since the base and the upper plate are each made of one thick reinforced concrete plate,
For example, when a large-capacity underground tank of 10,000 liters or more is installed, there is a problem that the base and the upper panel are also large and heavy, making it difficult to carry by truck or suspend by a crane.

【0006】この発明は、このような従来の技術に存在
する問題点に着目してなされたものであって、その目的
とするところは、地下タンクの設置工事を容易かつ短期
間に行うことができると共に、基盤や支柱の形成品質を
一定に保つことができ、しかも、例えば1万リットル以
上の大容量の地下タンクを設置する場合でも、基盤等の
トラックによる運搬やクレーンによる吊り下げ作業を簡
単に行うことができて、設置工事を支障なく遂行するこ
とができる地下タンク貯蔵装置の設置工法を提供するこ
とにある。
[0006] The present invention has been made in view of the problems existing in such prior art, and it is an object of the present invention to easily and quickly install an underground tank. In addition to being able to maintain the formation quality of the base and the pillars at a constant level, even when installing a large-capacity underground tank of, for example, 10,000 liters or more, it is easy to transport the base and other trucks and suspend the work with a crane. It is an object of the present invention to provide a method for installing an underground tank storage device, which can be carried out without difficulty and can perform the installation work without any trouble.

【0007】[0007]

【課題を解決するための手段】上記の目的を達成するた
めに、第1の発明では、装置の設置箇所に設置穴を掘
り、その設置穴の底部にグリ石を敷くと共に捨てコンク
リートを打設し、その捨てコンクリート上に設置枠を据
付け、その設置枠内に複数の鉄筋コンクリート製の基盤
を据付け固定し、その基盤上に地下タンクを据付けると
共に複数の鉄筋コンクリート製の支柱を立設し、その支
柱上に複数の鉄筋コンクリート製の上盤を据付け、前記
設置穴を埋め戻すことを特徴とするものである。
In order to achieve the above object, in the first invention, an installation hole is dug in a place where the apparatus is installed, and a grindstone is laid at the bottom of the installation hole, and a discarded concrete is poured. Then, an installation frame is installed on the discarded concrete, a plurality of reinforced concrete bases are installed and fixed in the installation frame, an underground tank is installed on the base, and a plurality of reinforced concrete columns are erected. It is characterized in that a plurality of reinforced concrete upper plates are installed on a support, and the installation holes are filled back.

【0008】又、第2の発明では、前記設置枠を四角枠
状に形成し、その対向する長辺部の内側面に勾配をつけ
た案内部を設けたことを特徴とするものである。さら
に、第3の発明では、装置の設置箇所に設置穴を掘り、
その設置穴の底部にグリ石を敷くと共に捨てコンクリー
トを打設し、その捨てコンクリート上に設置枠を据付
け、その設置枠内に複数の鉄筋コンクリート製の基盤を
据付け固定し、その基盤上に地下タンクを据付けると共
に複数の鉄筋コンクリート製の支柱を立設し、この状態
で設置穴を埋め戻した後、前記支柱上に鉄筋コンクリー
ト製の上盤を打設形成することを特徴とするものであ
る。
According to a second aspect of the present invention, the installation frame is formed in a rectangular frame shape, and a sloped guide portion is provided on an inner surface of a long side portion facing the installation frame. Furthermore, in the third invention, an installation hole is dug in the installation location of the device,
Laying grindstone at the bottom of the installation hole and casting discarded concrete, installing an installation frame on the discarded concrete, installing and fixing a plurality of reinforced concrete bases in the installation frame, and placing an underground tank on the basement And a plurality of reinforced concrete columns are erected, the installation holes are backfilled in this state, and then a reinforced concrete upper wall is formed on the columns.

【0009】[0009]

【作用】第1の発明では、基盤、支柱及び上盤を現場施
工にて形成する必要がなく、地下タンクの設置工事を容
易かつ短期間に行うことができると共に、それらの形成
品質を一定に保つことができる。しかも、基盤及び上盤
が複数に分割形成されているため、例えば1万リットル
以上の大容量の地下タンクを設置する場合でも、その基
盤及び上盤等のトラックによる運搬やクレーンによる吊
り下げを簡単に行うことができて、設置工事を支障なく
遂行することができる。
According to the first aspect of the present invention, it is not necessary to form the base, the support and the upper panel by on-site construction, the installation work of the underground tank can be performed easily and in a short time, and their formation quality can be kept constant. Can be kept. In addition, since the base and the upper panel are divided into a plurality of parts, even when installing a large-capacity underground tank of, for example, 10,000 liters or more, it is easy to transport the base and the upper panel by truck or to suspend by a crane. The installation work can be performed without any trouble.

【0010】又、第2の発明では、基盤をクレーンで吊
り下げて設置枠内に据付ける際に、その基盤を設置枠の
内側面に設けられた勾配のついた案内部に沿って、設置
枠内の所定位置に位置決め配置することができて、その
据付け作業を容易かつ短時間に行うことができる。
In the second invention, when the base is hung by a crane and installed in the installation frame, the base is installed along a sloped guide portion provided on the inner surface of the installation frame. It can be positioned and arranged at a predetermined position in the frame, and the installation work can be performed easily and in a short time.

【0011】さらに、第3の発明では、次の作業工程の
開始時期に影響を及ぼす基盤や支柱の形成を現場施工で
行わず、最後の作業工程である上盤の形成のみを現場施
工で行うため、地下タンクの設置工事を容易かつ短期間
に行うことができる。しかも、基盤が複数に分割形成さ
れているため、例えば1万リットル以上の大容量の地下
タンクを設置する場合でも、その基盤等のトラックによ
る運搬やクレーンによる吊り下げ作業を簡単に行うこと
ができ、支柱を立設後、堀った設置穴を早期に埋め戻す
ことができるため安全性が高く、設置工事を支障なく遂
行することができる。
Further, in the third invention, the formation of the base and the supporting columns which affect the start time of the next work process is not performed in the on-site construction, and only the formation of the upper work, which is the last work process, is performed in the on-site construction. Therefore, the installation work of the underground tank can be performed easily and in a short time. In addition, since the base is divided into a plurality of parts, even when installing a large-capacity underground tank of, for example, 10,000 liters or more, the work of transporting the base or the like by truck or hanging it by a crane can be easily performed. After the pillars have been erected, the drilled installation holes can be refilled at an early stage, so that the safety is high and the installation work can be performed without any trouble.

【0012】[0012]

【実施例】【Example】

(第1実施例)以下、第1及び第2の発明を具体化した
地下タンク貯蔵装置の設置工法の第1実施例を、図1〜
図12に基づいて詳細に説明する。
(First Embodiment) Hereinafter, a first embodiment of an installation method of an underground tank storage device embodying the first and second inventions will be described with reference to FIGS.
This will be described in detail with reference to FIG.

【0013】さて、この実施例の設置工法においては、
まず、図2に示すように、地下タンク貯蔵装置を設置す
る箇所の地面に設置穴1を掘り下げる。この設置穴1
は、埋め戻しのときに土砂が十分につまるように装置の
外形寸法よりも前後及び左右にそれぞれ例えば50cm
以上の余裕をとった大きさにし、装置の高さ寸法に後述
するグリ石2の敷設高さ等を見込んだ深さにする。次
に、この設置穴1の底部にグリ石2を敷設する。そし
て、図3に示すように、このグリ石2の上面に捨てコン
クリート3を打設して、その表面を水平にする。
Now, in the installation method of this embodiment,
First, as shown in FIG. 2, an installation hole 1 is dug down in the ground where the underground tank storage device is installed. This installation hole 1
Is, for example, 50 cm each before and after and outside the outer dimensions of the device so that the earth and sand are sufficiently clogged when backfilling
The size is set to have the above margin, and the height of the apparatus is set to a depth that allows for the laying height and the like of the graffite 2 described later. Next, the gemstone 2 is laid on the bottom of the installation hole 1. Then, as shown in FIG. 3, a discarded concrete 3 is cast on the upper surface of the grindstone 2 to level the surface.

【0014】その後、図4に示すように、前記捨てコン
クリート3上に設置枠4を据付けて、所定位置に水平に
配置する。この設置枠4は設置現場において、図5〜図
7に示すように、鉄筋コンクリート製の一対の長辺部5
と一対の短辺部6とを、複数のステンレス製のボルト7
及びナット8により四角枠状に組み付けて構成する。
又、一対の長辺部5の内側面には、前記ボルト7のため
の挿通孔9を形成した両端部分を除いて、勾配のついた
案内部5aが形成されている。そして、この状態で、図
4に鎖線で示すように、設置枠4内の捨てコンクリート
3上に、十分な軟らかさを有する捨てコンモルタル10
を、30mm程度の所定厚さで打設する。
Thereafter, as shown in FIG. 4, an installation frame 4 is installed on the waste concrete 3 and is horizontally arranged at a predetermined position. As shown in FIGS. 5 to 7, the installation frame 4 has a pair of long sides 5 made of reinforced concrete at the installation site.
And a pair of short sides 6 by a plurality of stainless steel bolts 7
And a nut 8 to form a square frame.
A sloped guide portion 5a is formed on the inner side surface of the pair of long side portions 5 except for both end portions where the insertion holes 9 for the bolts 7 are formed. Then, in this state, as shown by a chain line in FIG. 4, the disposal concrete mortar 10 having sufficient softness is placed on the disposal concrete 3 in the installation frame 4.
With a predetermined thickness of about 30 mm.

【0015】次に、図8に示すように、2個の鉄筋コン
クリート製の基盤11を、1個ずつクレーンで吊り下げ
ながら前記設置枠4内に据付けて、捨てコンモルタル1
0上に密着配置する。このとき、2個の基盤11の間に
隙間が生じないように、両基板11を互いに密着させて
位置決めする。なお、この実施例では、設置枠4の長辺
部5の内側面に勾配のついた案内部5aが形成されてい
るため、基盤11をこの案内部5aに沿って設置枠4内
へ容易に嵌合して、所定位置に位置決め配置することが
でき、その据付け作業を簡単かつ短時間に行うことがで
きる。
Next, as shown in FIG. 8, two reinforced concrete bases 11 are installed in the installation frame 4 while being suspended one by one by a crane,
It is placed close to 0. At this time, the two substrates 11 are positioned in close contact with each other so that no gap is formed between the two substrates 11. In this embodiment, since the guide portion 5a having a slope is formed on the inner surface of the long side portion 5 of the installation frame 4, the base 11 can be easily inserted into the installation frame 4 along the guide portion 5a. It can be fitted and positioned at a predetermined position, and the installation work can be performed easily and in a short time.

【0016】前記基盤11は工場において予め所定の大
きさに分割して製造され、トラックにより設置現場まで
運搬される。そして、この基盤11の上面には一対のタ
ンク据付け用の基礎台12が設けられ、その上面中央に
はタンクの外面のアールに合わせた凹所13が形成され
ると共に、上面両側には一対のアンカーボルト14が立
設されている。さらに、基盤11の四隅には支柱立設用
のテーパ状の嵌合孔15が形成され、各嵌合孔15の上
部開口縁には複数のアンカーボルト16が立設されてい
る。
The base 11 is divided into predetermined sizes in a factory and manufactured, and transported by truck to an installation site. A pair of tank mounting bases 12 is provided on the upper surface of the base 11, and a recess 13 is formed at the center of the upper surface to match the radius of the outer surface of the tank, and a pair of tanks is formed on both sides of the upper surface. An anchor bolt 14 is provided upright. Further, tapered fitting holes 15 for supporting columns are formed at the four corners of the base 11, and a plurality of anchor bolts 16 are provided upright at the upper opening edge of each fitting hole 15.

【0017】その後、図9に示すように、地下タンク1
7をクレーンで吊り下げながら、前記基盤11上の基礎
台12の凹所13に据付け、各基礎台12上のアンカー
ボルト14に固定バンド18を取り付けて、地下タンク
17を基盤11上に締付固定する。なお、この地下タン
ク17は工場において密閉円筒状に形成され、トラック
により基盤11等と共に設置現場まで運搬される。そし
て、この地下タンク17の外周上面には一対のハッチ部
19が所定間隔をおいて設けられている。
Thereafter, as shown in FIG.
7 is suspended in a recess 13 of the base 12 on the base 11 while being suspended by a crane, and a fixing band 18 is attached to an anchor bolt 14 on each base 12, and the underground tank 17 is tightened on the base 11. Fix it. The underground tank 17 is formed in a closed cylindrical shape in a factory, and transported by truck to the installation site together with the base 11 and the like. A pair of hatch portions 19 are provided on the outer peripheral upper surface of the underground tank 17 at predetermined intervals.

【0018】次に、図10に示すように、複数の鉄筋コ
ンクリート製の支柱20をクレーンで吊り下げながら各
基盤11の上面四隅に立設する。この支柱20は工場に
おいて製造され、トラックにより基盤11等と共に設置
現場まで運搬される。そして、この支柱20の下端には
テーパ状の嵌合部21及び複数の挿通孔22を有するフ
ランジ部23が設けられ、この嵌合部21を基盤11上
の嵌合孔15に嵌合すると共に、挿通孔22を基盤11
上のアンカーボルト16に挿通して、図示しないナット
を締め付けることにより、支柱20を基盤11上に固定
することができる。又、支柱20の上端にはフランジ部
24を介してテーパ状の嵌合部25が設けられ、その嵌
合部25の上端にはアンカーボルト26が立設されてい
る。
Next, as shown in FIG. 10, a plurality of reinforced concrete columns 20 are erected at the four upper corners of each base 11 while being suspended by a crane. The strut 20 is manufactured in a factory, and transported by truck to the installation site together with the base 11 and the like. Further, a tapered fitting portion 21 and a flange portion 23 having a plurality of insertion holes 22 are provided at the lower end of the support 20, and the fitting portion 21 is fitted into the fitting hole 15 on the base 11 and , Through hole 22 to base 11
The column 20 can be fixed on the base 11 by inserting it through the upper anchor bolt 16 and tightening a nut (not shown). A tapered fitting portion 25 is provided at the upper end of the support 20 via a flange portion 24, and an anchor bolt 26 is provided upright at the upper end of the fitting portion 25.

【0019】その後、図11に示すように、2個の鉄筋
コンクリート製の上盤27を、1個ずつクレーンで吊り
下げながら前記支柱20上に据付ける。この上盤27は
工場において予め所定の大きさに分割して製造され、ト
ラックにより前記基盤11等と共に設置現場まで運搬さ
れる。
Thereafter, as shown in FIG. 11, two reinforced concrete upper boards 27 are mounted on the support column 20 while being suspended one by one by a crane. The upper panel 27 is manufactured in a factory by dividing it into a predetermined size in advance, and transported by truck to the installation site together with the base 11 and the like.

【0020】又、前記上盤27の下面四隅には座部28
が突設され、各座部28には下方に開口するテーパ状の
嵌合孔29及び上方に開口する締付孔30が連通して形
成されている。そして、嵌合孔29を支柱20上の嵌合
部25に嵌合すると共に、締付孔30から支柱20上の
アンカーボルト26に図示しないナットを締め付けるこ
とにより、上盤27を支柱20に固定することができ
る。さらに、上盤27の中央部には前記地下タンク17
上のハッチ部19への連通孔31が形成されると共に、
一側寄りには一対の検知管用の挿通孔32が形成されて
いる。
At four corners of the lower surface of the upper panel 27, seats 28 are provided.
Each seat portion 28 is formed with a tapered fitting hole 29 that opens downward and a fastening hole 30 that opens upward so as to communicate with each other. Then, the fitting hole 29 is fitted to the fitting portion 25 on the support 20, and the upper plate 27 is fixed to the support 20 by fastening a nut (not shown) to the anchor bolt 26 on the support 20 from the fastening hole 30. can do. Furthermore, the underground tank 17 is located at the center of the upper panel 27.
A communication hole 31 to the upper hatch 19 is formed,
A pair of detection tube insertion holes 32 is formed near one side.

【0021】次に、図1及び図12に示すように、前記
上盤27の挿通孔32から検知管33を挿入して、基盤
11に当接固定する。又、上盤27の連通孔31から地
下タンク17のハッチ部19にプロテクタ34を固定
し、そのプロテクタ34の上端に座板35を介して蓋体
36を着脱可能に取着する。さらに、設置枠4と基盤1
1との隙間部分37、地下タンク17の固定バンド18
の締付固定部38、基盤11に対する支柱20の締付固
定部39、一対の上盤27の隙間部分40、上盤27の
締付孔30、検知管用の挿通孔32、及び連通孔31内
の座板35の取付部分41に、それぞれモルタルを詰め
込んで、それらの部分を密閉する。
Next, as shown in FIG. 1 and FIG. 12, a detection tube 33 is inserted through the insertion hole 32 of the upper panel 27, and is fixed to the base 11 in contact therewith. Further, a protector 34 is fixed to the hatch 19 of the underground tank 17 from the communication hole 31 of the upper panel 27, and a lid 36 is detachably attached to the upper end of the protector 34 via a seat plate 35. In addition, installation frame 4 and base 1
1 and the fixed band 18 of the underground tank 17
, The fastening portion 39 of the column 20 with respect to the base 11, the gap 40 between the pair of upper panels 27, the fastening holes 30 of the upper panel 27, the insertion holes 32 for the detection tubes, and the communication holes 31. Each of the mounting portions 41 of the seat plate 35 is filled with mortar, and these portions are sealed.

【0022】その後、図1及び図12に示すように、前
記ハッチ部19内に設けられた図示しない配管接続部
に、オイル管42を接続すると共に油量計を取り付け
る。そして、図1に鎖線で示すように、前記設置穴1に
土砂44を投入して上盤27の上面まで埋め戻しを行
い、装置の設置工事を完了することができる。
Thereafter, as shown in FIG. 1 and FIG. 12, an oil pipe 42 is connected and an oil meter is attached to a pipe connection (not shown) provided in the hatch 19. Then, as shown by a chain line in FIG. 1, earth and sand 44 are put into the installation hole 1 and backfilled to the upper surface of the upper panel 27, thereby completing the installation work of the apparatus.

【0023】以上のように、この第1実施例の設置工法
によれば、基盤11、支柱20及び上盤27を工場で製
造して設置現場に搬入しているため、それらを現場施工
にて形成する必要がなく、地下タンク17の設置工事を
容易かつ短期間に行うことができると共に、それらの形
成品質を一定に保つことができる。又、この実施例の設
置工法においては、基盤11及び上盤27が複数に分割
して形成されているため、例えば1万リットル以上の大
容量の地下タンク17を設置する場合でも、その基盤1
1及び上盤27等のトラックによる運搬やクレーンによ
る吊り下げを簡単に行うことができて、設置工事を支障
なく遂行することができる。 (第2実施例)次に、第3の発明を具体化した地下タン
ク貯蔵装置の設置工法の第2実施例を、図13〜図15
に基づいて説明する。
As described above, according to the installation method of the first embodiment, since the base 11, the support 20, and the upper panel 27 are manufactured in the factory and carried to the installation site, they are installed in the site. There is no need to form, and the installation work of the underground tank 17 can be performed easily and in a short period of time, and the formation quality thereof can be kept constant. Further, in the installation method of this embodiment, since the base 11 and the upper panel 27 are formed by dividing into a plurality, even when installing a large-capacity underground tank 17 of, for example, 10,000 liters or more, the base 1
The truck 1 and the upper panel 27 can be easily transported by a truck or suspended by a crane, and the installation work can be performed without any trouble. (Second Embodiment) Next, a second embodiment of an installation method of an underground tank storage device embodying the third invention will be described with reference to FIGS.
It will be described based on.

【0024】さて、この第2実施例の設置工法において
は、図2〜図10に示す第1実施例の設置工法と同様
に、設置孔1の掘り下げ、グリ石2の敷設、捨てコンク
リート3の打設、設置枠4の据付け、捨てコンモルタル
10の打設、一対の基盤11の据付け、地下タンク17
の据付け、及び複数の支柱20の立設を行う。なお、こ
の第2実施例で使用する支柱20には、第1実施例の場
合と異なって、上端にフランジ部24、嵌合部25及び
アンカーボルト26が設けられておらず、図13に示す
ように、内部の支持鉄筋50が上方へ突出した状態で形
成されている。
In the installation method according to the second embodiment, as in the installation method according to the first embodiment shown in FIGS. 2 to 10, the installation hole 1 is dug down, the grinder 2 is laid, and the waste concrete 3 is removed. Casting, installation of installation frame 4, installation of dumping mortar 10, installation of a pair of bases 11, underground tank 17
Is installed, and the plurality of columns 20 are erected. In addition, unlike the case of the first embodiment, the column 20 used in the second embodiment is not provided with the flange portion 24, the fitting portion 25, and the anchor bolt 26 at the upper end, and is shown in FIG. Thus, the inner supporting rebar 50 is formed in a state of protruding upward.

【0025】そして、この第2実施例においては、前記
支柱20の立設作業に引き続いて、図13に示すよう
に、地下タンク17のハッチ部19にプロテクタ34を
取り付けると共に、ハッチ部19内の配管接続部にオイ
ル管42を接続する。その後、図14に示すように、設
置枠4と基盤11との隙間部分37、地下タンク17の
固定バンド18の締付固定部38、及び基盤11に対す
る支柱20の締付固定部39に、それぞれモルタルを詰
め込んで、それらの部分を密閉する。又、モルタルによ
り基盤11上の所定位置に検知管33を立設固定する。
In the second embodiment, following the erecting operation of the support column 20, a protector 34 is attached to the hatch 19 of the underground tank 17 as shown in FIG. The oil pipe 42 is connected to the pipe connection. Thereafter, as shown in FIG. 14, a gap portion 37 between the installation frame 4 and the base 11, a fastening portion 38 of the fixing band 18 of the underground tank 17, and a fastening portion 39 of the support 20 to the base 11 are respectively provided. Pack the mortar and seal the parts. Further, the detection tube 33 is erected at a predetermined position on the base 11 by mortar.

【0026】この状態で、設置穴1に土砂を投入して埋
め戻しを行う。その後、図14に示すように、グリ石5
1の敷設、仮枠52の据付け、鉄筋53の組付け、及び
コンクリートの打設を行って、前記支柱20の上端部間
に上盤27を形成する。そして、図15に示すように、
上盤27の硬化後に仮枠52を取り外すと共に、プロテ
クタ34に対する蓋体36の取付け等の付属品の取付け
を行うことにより、装置の設置工事を完了することがで
きる。
In this state, earth and sand are put into the installation hole 1 and backfilling is performed. Thereafter, as shown in FIG.
1, installation of the temporary frame 52, installation of the reinforcing bar 53, and casting of concrete, thereby forming the upper panel 27 between the upper ends of the columns 20. Then, as shown in FIG.
After the hardening of the upper panel 27, the temporary frame 52 is removed, and the attachment such as the attachment of the cover 36 to the protector 34 is performed, whereby the installation work of the apparatus can be completed.

【0027】以上のように、この第2実施例の設置工法
によれば、次の作業工程の開始時期に影響を及ぼす基盤
11や支柱20の形成を現場施工で行わず、最後の作業
工程である上盤27の形成のみを現場施工で行っている
ため、地下タンク17の設置工事を容易かつ短期間に行
うことができる。又、この実施例の設置工法において
は、基盤11が複数に分割して形成されているため、例
えば1万リットル以上の大容量の地下タンク17を設置
する場合でも、その基盤11等のトラックによる運搬や
クレーンによる吊り下げを簡単に行うことができて、設
置工事を支障なく遂行することができる。
As described above, according to the installation method of the second embodiment, the formation of the base 11 and the columns 20 which affect the start time of the next operation process is not performed in the on-site construction, but in the last operation process. Since only the formation of a certain upper panel 27 is performed on site, installation work of the underground tank 17 can be performed easily and in a short time. Further, in the installation method of this embodiment, since the base 11 is divided into a plurality of parts, even when a large-capacity underground tank 17 of, for example, 10,000 liters or more is installed, the base 11 or the like uses a truck. It can be easily transported and suspended by a crane, and the installation work can be performed without any trouble.

【0028】なお、この発明は前記実施例の構成に限定
されるものではなく、例えば、地下タンク17の容量に
応じて、基盤11や上盤27を3個以上の適数個に分割
して形成したり、前記勾配のついた案内部5aを短辺部
6にも設けたり等、この発明の趣旨から逸脱しない範囲
で、各部の構成を任意に変更して具体化してもよい。
The present invention is not limited to the configuration of the above-described embodiment. For example, the base 11 and the upper panel 27 are divided into three or more appropriate numbers according to the capacity of the underground tank 17. The configuration of each part may be arbitrarily changed and embodied without departing from the spirit of the present invention, such as forming or providing the inclined guide part 5a also on the short side part 6.

【0029】[0029]

【発明の効果】この発明は、以上説明したように構成さ
れているため、次のような優れた効果を奏する。
Since the present invention is configured as described above, it has the following excellent effects.

【0030】第1の発明によれば、基盤、支柱及び上盤
を現場施工にて形成する必要がなく、地下タンクの設置
工事を容易かつ短期間に行うことができると共に、それ
らの形成品質を一定に保つことができる。しかも、基盤
及び上盤が複数に分割形成されているため、例えば1万
リットル以上の大容量の地下タンクを設置する場合で
も、その基盤及び上盤等のトラックによる運搬やクレー
ンによる吊り下げ作業を簡単に行うことができて、設置
工事を支障なく遂行することができる。
According to the first aspect of the present invention, it is not necessary to form the base, the support, and the upper panel by on-site construction, so that the installation work of the underground tank can be performed easily and in a short time, and the formation quality thereof can be improved. Can be kept constant. Moreover, since the base and the upper panel are divided into a plurality of parts, even when a large-capacity underground tank of, for example, 10,000 liters or more is installed, the work of transporting the base and the upper panel by truck or hanging work by a crane is required. It can be easily performed, and the installation work can be performed without any trouble.

【0031】また、第2の発明によれば、基盤をクレー
ンで吊り下げて設置枠内に据付ける際に、その基盤を設
置枠の内側面に設けられた勾配のついた案内部に沿っ
て、設置枠内の所定位置に位置決め配置することができ
て、その据付け作業を容易かつ短時間に行うことができ
る。
According to the second invention, when the base is suspended by the crane and installed in the installation frame, the base is moved along the inclined guide portion provided on the inner surface of the installation frame. Can be positioned and arranged at a predetermined position in the installation frame, and the installation work can be performed easily and in a short time.

【0032】さらに、第3の発明によれば、次の作業工
程の開始時期に影響を及ぼす基盤や支柱の形成を現場施
工で行わず、最後の作業工程である上盤の形成のみを現
場施工で行うため、地下タンクの設置工事を容易かつ短
期間に行うことができる。しかも、基盤が複数に分割形
成されているため、例えば1万リットル以上の大容量の
地下タンクを設置する場合でも、その基盤等のトラック
による運搬やクレーンによる吊り下げを簡単に行うこと
ができ、支柱の立設後設置穴をすぐに埋め戻すことがで
きるため、穴を堀ったまま放置する期間が短く、安全性
に優れ、設置工事を支障なく遂行することができる。
Further, according to the third aspect of the present invention, the formation of the base and the pillars which affect the start time of the next work process is not performed by on-site construction, and only the formation of the upper work, which is the last work process, is performed by on-site construction. Therefore, installation work of the underground tank can be performed easily and in a short time. Moreover, since the base is divided into a plurality of parts, even when installing a large-capacity underground tank of, for example, 10,000 liters or more, the base can be easily transported by truck or suspended by a crane, Since the installation hole can be immediately refilled after the support column is erected, the period during which the hole is left open is short, the safety is excellent, and the installation work can be performed without any trouble.

【図面の簡単な説明】[Brief description of the drawings]

【図1】この発明を具体化した地下タンク貯蔵装置の設
置工法の第1実施例を示す完成状態の断面図である。
FIG. 1 is a sectional view of a completed state showing a first embodiment of an installation method of an underground tank storage device embodying the present invention.

【図2】その設置工法において、設置穴の掘下げ工程及
びグリ石の敷設工程を示す断面図である。
FIG. 2 is a cross-sectional view showing a step of digging an installation hole and a step of laying grime stone in the installation method.

【図3】捨てコンクリートの打設工程を示す断面図であ
る。
FIG. 3 is a cross-sectional view showing a process of placing discarded concrete.

【図4】設置枠の据付け工程を示す斜視図である。FIG. 4 is a perspective view showing an installation process of an installation frame.

【図5】その設置枠を分解して示す斜視図である。FIG. 5 is an exploded perspective view showing the installation frame.

【図6】図5のA−A線における拡大断面図である。FIG. 6 is an enlarged sectional view taken along line AA of FIG. 5;

【図7】図5のB−B線における拡大断面図である。FIG. 7 is an enlarged sectional view taken along line BB of FIG. 5;

【図8】基盤の据付け工程を示す斜視図である。FIG. 8 is a perspective view showing a step of installing a base.

【図9】地下タンクの据付け工程を示す斜視図である。FIG. 9 is a perspective view showing an underground tank installation process.

【図10】支柱の立設工程を示す斜視図である。FIG. 10 is a perspective view showing a process of erecting a support.

【図11】上盤の据付け工程を示す斜視図である。FIG. 11 is a perspective view showing an upper panel installation process.

【図12】関連部材の組付け工程及び隙間等へのモルタ
ル詰め工程を示す斜視図である。
FIG. 12 is a perspective view showing an assembling step of a related member and a step of mortar filling a gap or the like.

【図13】この発明の地下タンク貯蔵装置の設置工法の
第2実施例を示すもので、特に地下タンクの据付け後に
おける支柱の立設工程及びプロテクタ等の組付け工程を
示す斜視図である。
FIG. 13 is a perspective view showing a second embodiment of the installation method of the underground tank storage device according to the present invention, and particularly showing an upright pillar installation process and an assembling process of a protector and the like after installation of the underground tank.

【図14】隙間等へのモルタル詰め工程及び支柱上への
上盤の形成工程を示す斜視図である。
FIG. 14 is a perspective view showing a step of mortar filling a gap or the like and a step of forming an upper plate on a support.

【図15】完成状態を示す斜視図である。FIG. 15 is a perspective view showing a completed state.

【符号の説明】[Explanation of symbols]

1…設置穴、2…グリ石、3…捨てコンクリート、4…
設置枠、5…長辺部、5a…勾配のついた案内部、11
…基盤、17…地下タンク、20…支柱、27…上盤。
1 ... installation hole, 2 ... grindstone, 3 ... discarded concrete, 4 ...
Installation frame, 5 ... long side, 5a ... sloped guide, 11
... base, 17 ... underground tank, 20 ... prop, 27 ... upper panel.

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 装置の設置箇所に設置穴(1)を掘り、
その設置穴(1)の底部にグリ石(2)を敷くと共に捨
てコンクリート(3)を打設し、その捨てコンクリート
(3)上に設置枠(4)を据付け、その設置枠(4)内
に複数の鉄筋コンクリート製の基盤(11)を据付け固
定し、その基盤(11)上に地下タンク(17)を据付
けると共に複数の鉄筋コンクリート製の支柱(20)を
立設し、その支柱(20)上に複数の鉄筋コンクリート
製の上盤(27)を据付け、前記設置穴(1)を埋め戻
すことを特徴とする地下タンク貯蔵装置の設置工法。
1. An installation hole (1) is dug in an installation place of the device,
Laying stone (2) at the bottom of the installation hole (1) and casting discarded concrete (3), installing an installation frame (4) on the discarded concrete (3), and inside the installation frame (4) A plurality of reinforced concrete bases (11) are installed and fixed on the base, and an underground tank (17) is installed on the base (11), and a plurality of reinforced concrete columns (20) are erected. A method of installing an underground tank storage device, wherein a plurality of reinforced concrete upper panels (27) are installed thereon, and the installation holes (1) are backfilled.
【請求項2】 前記設置枠(4)を四角枠状に形成し、
その対向する長辺部(5)の内側面に勾配をつけた案内
部(5a)を設けたことを特徴とする請求項1の地下タ
ンク貯蔵装置の設置工法。
2. The installation frame (4) is formed in a square frame shape.
2. The installation method for an underground tank storage device according to claim 1, wherein a sloped guide portion (5a) is provided on an inner surface of the opposed long side portion (5).
【請求項3】 装置の設置箇所に設置穴(1)を掘り、
その設置穴(1)の底部にグリ石(2)を敷くと共に捨
てコンクリート(3)を打設し、その捨てコンクリート
(3)上に設置枠(4)を据付け、その設置枠(4)内
に複数の鉄筋コンクリート製の基盤(11)を据付け固
定し、その基盤(11)上に地下タンク(17)を据付
けると共に複数の鉄筋コンクリート製の支柱(20)を
立設し、この状態で設置穴(1)を埋め戻した後、前記
支柱(20)上に鉄筋コンクリート製の上盤(27)を
打設形成することを特徴とする地下タンク貯蔵装置の設
置工法。
3. An installation hole (1) is dug in an installation place of the device,
Laying stone (2) at the bottom of the installation hole (1) and casting discarded concrete (3), installing an installation frame (4) on the discarded concrete (3), and inside the installation frame (4) A plurality of reinforced concrete bases (11) are installed and fixed on the base, an underground tank (17) is installed on the base (11), and a plurality of reinforced concrete columns (20) are erected. (1) After backfilling, a method of installing an underground tank storage device, wherein an upper plate (27) made of reinforced concrete is cast and formed on the column (20).
JP3265077A 1991-10-14 1991-10-14 Installation method of underground tank storage device Expired - Fee Related JP2662119B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3265077A JP2662119B2 (en) 1991-10-14 1991-10-14 Installation method of underground tank storage device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3265077A JP2662119B2 (en) 1991-10-14 1991-10-14 Installation method of underground tank storage device

Publications (2)

Publication Number Publication Date
JPH0598657A JPH0598657A (en) 1993-04-20
JP2662119B2 true JP2662119B2 (en) 1997-10-08

Family

ID=17412282

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3265077A Expired - Fee Related JP2662119B2 (en) 1991-10-14 1991-10-14 Installation method of underground tank storage device

Country Status (1)

Country Link
JP (1) JP2662119B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4809446B2 (en) * 2009-01-22 2011-11-09 株式会社カンケン Septic tank installation structure
JP5000771B2 (en) * 2011-01-31 2012-08-15 株式会社カンケン Septic tank installation structure
JP6931754B2 (en) * 2017-05-29 2021-09-08 ベルテクス株式会社 Protective skeleton and its construction method

Also Published As

Publication number Publication date
JPH0598657A (en) 1993-04-20

Similar Documents

Publication Publication Date Title
JP2662119B2 (en) Installation method of underground tank storage device
US6328503B1 (en) Method for constructing an underground structure
US20020148174A1 (en) Method and system for emplacing prefabricated buildings
JP2879426B2 (en) Underground recharge structure
JP2001241287A (en) Construction method of shaft, assembly method of structural body used for construction method, and assembly device used for assembly method
JPH06105014B2 (en) Installation method of underground tank storage device
KR200473397Y1 (en) The coupling apparatus of a silo tank
JP4420514B2 (en) Basement diving method
CN210238531U (en) Deep foundation pit supporting structure
JPH1122365A (en) Construction method of shaft and device therefor
JPH0346638B2 (en)
CA1137326A (en) Multi-compartment sump and method and apparatus for making same
JPS5911015B2 (en) How to install shoring in the reverse winding method
JPH0115714Y2 (en)
JPH0115715Y2 (en)
JP2003231584A (en) Underground tank storage device, and methods for manufacture and construction thereof
JP3363554B2 (en) Construction method of concrete building
JPH10102519A (en) Manufacture of underground buried liquid storage container
JP4045623B2 (en) Construction method of reinforced concrete underground floor and underground structure constructed by this method
JP2829717B2 (en) Construction method of installation foundation for heavy objects
JPH028102B2 (en)
JPS6121277A (en) Building of underground tank
JPS5925971Y2 (en) Mobile concrete pouring hopper
JP2006118187A (en) Installation method of tank, and foundation structure for tank using the method
JP2000345572A (en) Basement caisson construction method, lower frame member used therefor, internal panel member, external panel member, and separator

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090613

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110613

Year of fee payment: 14

LAPS Cancellation because of no payment of annual fees