JPH028102B2 - - Google Patents

Info

Publication number
JPH028102B2
JPH028102B2 JP11619883A JP11619883A JPH028102B2 JP H028102 B2 JPH028102 B2 JP H028102B2 JP 11619883 A JP11619883 A JP 11619883A JP 11619883 A JP11619883 A JP 11619883A JP H028102 B2 JPH028102 B2 JP H028102B2
Authority
JP
Japan
Prior art keywords
beams
floor
pillars
fixed
underground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP11619883A
Other languages
Japanese (ja)
Other versions
JPS6010063A (en
Inventor
Kimio Kakubari
Takeo Uchida
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hazama Ando Corp
Original Assignee
Hazama Gumi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hazama Gumi Ltd filed Critical Hazama Gumi Ltd
Priority to JP11619883A priority Critical patent/JPS6010063A/en
Publication of JPS6010063A publication Critical patent/JPS6010063A/en
Publication of JPH028102B2 publication Critical patent/JPH028102B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 本発明は、地下階の梁材を構真柱に架設する地
下階梁材の架構工法に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method of constructing a basement floor beam for constructing a basement floor beam on a structural pillar.

従来、地下階の構築工法の1つとして逆打ち工
法がある。
Conventionally, there is a reverse construction method as one of the construction methods for underground floors.

この工法は、建物の地上部と地下部とを並行し
て構築できる利点があるが、反面次のような欠点
があつた。
This construction method has the advantage of being able to construct the above-ground and underground parts of a building in parallel, but it has the following drawbacks.

(イ) 1階床を構築した後、地下階の構築作業はほ
ぼ密閉された地下作業となるため、作業性は悪
く、特に地下階をSRC造とした場合、地下階
の鉄骨梁材は、1階床の仮設開口部を通じてク
レーン等で吊り降ろし、横引き作業を行つた
後、所定の構真柱に固着しなければならず、し
かも地下階のスラブ、梁、柱の構築作業は煩雑
とならざるを得なかつた。
(b) After constructing the first floor, the construction work for the basement floor is done underground in a nearly sealed area, so work efficiency is poor.Especially when the basement floor is made of SRC construction, the steel beam materials for the basement floor are After being lowered with a crane or the like through a temporary opening in the first floor and then pulled horizontally, it had to be fixed to the designated structural pillars, and the construction work of the slabs, beams, and columns on the basement floor was complicated. I had no choice but to do so.

(ロ) 階高のほぼ半分の位置(梁材より1mから
1.5mの下部)に打継ぎ部ができるため、その
部分には流し込み部を有する複雑な型枠を必要
とし、しかも止水処理のために、無収縮モルタ
ルを注入しており、多くの手間と時間を費やし
ていた。
(b) At approximately half of the floor height (from 1m above the beam)
Because a joint is created at the bottom of the 1.5 m (1.5 m) part, a complicated formwork with a pouring part is required for that part, and non-shrinking mortar is injected to stop water, which requires a lot of time and effort. I was wasting my time.

このようなことから、従来の地下階の構築作業
は工期の短縮、工費の低減に大きな障害となつて
いた。
For these reasons, conventional underground floor construction work has been a major obstacle to shortening the construction period and reducing construction costs.

本発明の目的は、地下階梁材を従来の逆打ち工
法よりも格段に簡単かつ能率的に架構でき、また
地下階全体の構築工期の短縮化、工費の低減を図
るとともに、施工階スラブの上端と直上階スラブ
の下端との間を一度にコンクリート打設すること
が可能な地下階梁材の架構工法を提供することに
ある。
The purpose of the present invention is to make it possible to construct basement floor beams much more easily and efficiently than the conventional reverse construction method, to shorten the construction period and cost of the entire basement floor, and to improve the structure of the construction floor slab. To provide a method for constructing a basement floor beam material, which allows concrete to be placed between the upper end and the lower end of a slab directly above the floor at one time.

本発明は、梁材を下降案内するガイドレールが
設けられた構真柱を用い、先ずこれを地中孔内に
立設し、相対向する両構真柱の地上突出部間で上
記ガイドレールの滑合案内部と干渉しない箇所に
2階梁材を架構固着して、両構真柱を所定の間隔
に保持し、所要深さだけ掘削作業を行つた後、全
地下階の梁材及び1階梁材を、地上において順
次、下階のものより上記ガイドレールに沿つて下
降させ、両構真柱間に固着することなく順次段差
的に吊持又は仮固定する。
The present invention uses a structural pillar provided with a guide rail that guides the beam downward, and first installs the structural pillar in an underground hole, and connects the above-mentioned guide rail between the ground protrusions of both opposing structural pillars. After fixing the second floor beams to the frame in places where they do not interfere with the sliding guides, keeping the true pillars of both structures at a specified distance, and excavating to the required depth, the beams and beams for all basement floors are The first floor beams are sequentially lowered from the lower floor along the guide rail on the ground, and suspended or temporarily fixed in steps without being fixed between the two structural pillars.

次いで、掘削作業が進行した場所より、全地下
階の梁材及び1階梁材を同じくガイドレールに沿
つて下降させ、構真柱間に固着することなく吊持
又は仮固定して1階梁材を両構真柱に固着した
後、上記と同様に、掘削作業の進行とともに梁材
の下降、梁材の吊持又は仮固定を繰り返し、全地
下階の梁材を上階のものより順次両構真柱に固着
し、最終的に地下階全体の躯体を構築する。
Next, from where the excavation work has progressed, all the underground floor beams and the first floor beams are lowered along the same guide rails, suspended or temporarily fixed between the structure pillars, and the first floor beams are removed. After fixing the materials to the main pillars of both structures, in the same way as above, as the excavation work progresses, the beams are lowered, suspended, or temporarily fixed repeatedly, and the beams on all basement floors are sequentially installed starting from those on the upper floors. It will be fixed to the main pillars of both structures, and will eventually construct the frame of the entire basement floor.

以下に本発明の一実施例を図面を参照して詳細
に説明する。
An embodiment of the present invention will be described in detail below with reference to the drawings.

第1図に示すように、本実施例は、山止め壁材
1が土圧に耐えうる強度を有し、自立できる場
合、又はアースアンカー工法を講じ山止め支持材
(特に切梁)が不要な場合を想定した例で、次の
(1)〜(4)の順序で構真柱を立設するとともに2階梁
材を架構する。
As shown in Fig. 1, this example is suitable for cases where the heaping wall material 1 has the strength to withstand earth pressure and can stand on its own, or when the earth anchor construction method is used and no heaping support material (particularly struts) is required. In this example, we assume the following case.
Erect the structural pillars in the order of (1) to (4) and construct the beams for the second floor.

(1) 所定位置に掘削された所定深さの孔2…内に
所定長さの構真柱3を挿入して地上において仮
固定治具4によつて仮固定し、この状態で各孔
2内にコンクリート5を打設して各構真柱3の
下端部を固定する。
(1) Insert a structural pillar 3 of a predetermined length into a hole 2 of a predetermined depth excavated at a predetermined position and temporarily fix it on the ground with a temporary fixing jig 4. In this state, each hole 2 Concrete 5 is placed inside to fix the lower end of each structural pillar 3.

なお、構真柱3として、本例では、第5図に
示すように角パイプ状柱材を用いているが、丸
パイプ状柱材や十字状柱材などを用いてもよ
い。
In this example, a square pipe-shaped pillar material is used as the structural pillar 3, as shown in FIG. 5, but a round pipe-shaped pillar material, a cross-shaped pillar material, etc. may also be used.

構真柱3の各側面には、そのほぼ全長にそれ
ぞれ2本のガイドレール6,6が平行に突設さ
れている。
On each side of the structural pillar 3, two guide rails 6, 6 are protruded in parallel over almost the entire length thereof.

(2) 相対向する両構真柱3,3の地上突出部間
に、第1,5,6図に示すように両ガイドレー
ル6,6間の滑合案内部と干渉しない箇所にお
いて1対の2階梁材7,7を平行に架構固着す
る。
(2) Between the above-ground protruding parts of the two opposing structure pillars 3, 3, as shown in Figures 1, 5, and 6, one pair is installed at a location that does not interfere with the sliding guide part between the guide rails 6, 6. The second floor beams 7, 7 are fixed to the frame in parallel.

なお、このとき、ガイドレール6,6の上端
部に切欠部6′,6′(第6図)を形成し、この
切欠部6′,6′において2階梁材7,7の端縁
を構真柱3の側面に溶接して、両2階梁材7,
7の間隔(内法寸法)をガイドレール6,6の
間隔とほぼ等しくしておくのが望ましい。
At this time, notches 6', 6' (Fig. 6) are formed at the upper ends of the guide rails 6, 6, and the edges of the second floor beams 7, 7 are formed at these notches 6', 6'. Welded to the sides of the structural pillars 3, both second floor beams 7,
It is desirable that the interval (inner dimension) between the guide rails 7 and 7 be approximately equal to the interval between the guide rails 6, 6.

また、2階梁材7,7をこのように構真柱
3,3に固着することは、機能性(特に梁材の
滑合作業時の容易性と安全性確保のためのスラ
ブ型枠兼用鋼製床板の設置)をよくするため
で、2階梁材には、みぞ形鋼を用いるのが最も
望ましいが、I形鋼、H形鋼、L形鋼などの他
の形鋼であつてもよい。
In addition, by fixing the second floor beams 7, 7 to the structural pillars 3, 3 in this way, it is possible to improve functionality (in particular, it can also be used as a slab formwork to ensure ease and safety when sliding the beams together). This is to improve the installation of steel floor plates), and it is most desirable to use groove-shaped steel for the second floor beam material, but other shaped steel such as I-beams, H-beams, and L-beams may also be used. Good too.

(3) 仮固定治具4…を取り外す。(3) Remove temporary fixing jig 4.

かくして、相対向する構真柱3,3の上端部
は、2階梁材7,7によつて一定の間隔に保持
されるもので、次に第2図に示すように、地中
梁材8、地下2階梁材9、地下1階梁材10及
び1階梁材11を両構真柱3,3間に位置さ
せ、1階梁材11を次の(4)〜(7)の順次で両構真
柱3,3に固着する。
Thus, the upper ends of the structural pillars 3, 3 facing each other are held at a constant distance by the second floor beams 7, 7, and then, as shown in FIG. 8. Place the beams 9 for the second basement floor, the beams 10 for the first basement floor, and the beams 11 for the first floor between the two main pillars 3, 3, and move the first floor beams 11 to the following (4) to (7). It is fixed to both structure pillars 3 and 3 in sequence.

(4) 掘削作業を開始し、所定の深さまで掘削され
た場所より、先ず地中梁材8の両端を、地上に
おいてクレーン12等で吊持しながら、両構真
柱3,3のガイドレール6,6の間の滑合案内
部に上端より滑合させ、これらガイドレール
6,6に沿つて下降させて第6図に示すように
1対の2階梁材7,7間を通過させる。同様
に、地下2階梁材9、地下1階梁材10、1階
梁材11を順次通過させ、これら4本の梁材8
〜11を例えばチエーンブロツク13…のチエ
ーン13′…によつて2階梁材7の下方にすだ
れ状に吊持しておく。
(4) Start the excavation work, and from the place excavated to a predetermined depth, first, while suspending both ends of the underground beam 8 on the ground with a crane 12 etc., remove the guide rails of the main pillars 3, 3 of both structures. 6, 6 from the upper end, and lower along these guide rails 6, 6 to pass between a pair of second floor beam members 7, 7 as shown in Fig. 6. . Similarly, the second basement floor beam 9, the first basement floor beam 10, and the first floor beam 11 are passed through in sequence, and these four beams 8
- 11 are suspended below the second floor beam 7 by chains 13' of chain blocks 13, for example, in the form of a blind.

(5) 掘削作業がさらに進行した後、最上部のチエ
ーンブロツク13,13を操作して1階梁材1
1をガイドレール6,6に沿つて所定の架構位
置まで下降させる。地下の梁材8〜10は、1
階梁材11の下降にともない同じくガイドレー
ル6,6に沿つて同時に下降する。
(5) After the excavation work has progressed further, operate the top chain blocks 13 and 13 to remove the first floor beam 1.
1 is lowered along guide rails 6, 6 to a predetermined frame position. Underground beam materials 8 to 10 are 1
As the floor beam material 11 descends, it also descends simultaneously along the guide rails 6, 6.

(6) 地中梁材8の両端部を仮受け治具14,14
によつて両構真柱3,3の中途に仮固定する。
すなわち、第7図に示すように、仮受け治具1
4をボルト15を用いてガイドレール6,6に
取り付けるとともに、この仮受け治具14上に
地中梁材8を乗載してボルト16によつて仮受
け治具14に仮固定する。
(6) Temporarily hold both ends of the underground beam material 8 with jigs 14, 14.
Temporarily fix it in the middle of the main pillars 3, 3 of both structures.
That is, as shown in FIG. 7, the temporary receiving jig 1
4 is attached to the guide rails 6, 6 using bolts 15, and the underground beam material 8 is mounted on this temporary receiving jig 14 and temporarily fixed to the temporary receiving jig 14 with bolts 16.

なお、地中梁材8を両構真柱3,3の中途に
仮固定しておくのは、上記のように既に架構固
着した2階梁材7,7と相俟つて、架構中の両
構真柱3,3相互の動きを拘束し、両構真柱
3,3の中途部分での捩れやそりを防止するた
めである。
In addition, temporarily fixing the underground beams 8 midway between the true pillars 3, 3 of both structures, together with the second floor beams 7, 7, which have already been fixed to the structure as described above, This is to restrain the movement of the structural pillars 3, 3 relative to each other and to prevent twisting or warping at the midway portions of both the structural pillars 3, 3.

(7) 1階梁材11を所定の架構位置に位置決めし
てその両端を両構真柱3,3に溶接する。この
とき、第8図に示すように1階梁材11のフラ
ンジ部分11aの両側面とガイドレール6,6
の内面とを溶接した後、構真柱3の側面と1階
梁材11のフランジ部分11aの端面及びウエ
ブ部分11bの端面とを溶接すれば、溶接歪み
による構真柱3の捩れやそりを極力低減するこ
とができる。
(7) Position the first floor beam material 11 at a predetermined frame position and weld both ends to both structure pillars 3, 3. At this time, as shown in FIG. 8, both sides of the flange portion 11a of the first floor beam 11
After welding the inner surface of the structural column 3, the side surface of the structural column 3 is welded to the end face of the flange portion 11a and the end face of the web portion 11b of the first floor beam material 11, thereby preventing twisting or warping of the structural column 3 due to welding distortion. It can be reduced as much as possible.

なお、梁材8〜11の挿入が終了した場所よ
り、2階スラブコンクリート17を打設すれ
ば、地上階の基準作業床とすることができるの
で、地上階、地下階の各動線が分離でき、かつ
地上階の構築作業を安全に行うことができる。
しかも、2階スラブ面での面剛性が向上できる
ため、構真柱3の最上部位置での保持をより正
確、強固なものとすることができる。
In addition, if the second floor concrete slab 17 is cast from the place where the beams 8 to 11 have been inserted, it can be used as the standard working floor for the ground floor, so the flow lines for the ground floor and basement floor are separated. construction work on the ground floor can be carried out safely.
Moreover, since the surface rigidity of the second floor slab surface can be improved, the structural pillar 3 can be held at the top position more accurately and firmly.

上記の通り1階梁材11を架構固着した後、第
3図に示すように、1階梁材11上に所定のスラ
ブ用型枠(一例として鋼製床板を想定した)を設
置して1階スラブコンクリート18を打設し、さ
らに掘削した後、梁材8〜10を下降させ、地中
梁材8を上記と同様に仮固定して地下1階梁材1
0を両構真柱3,3に溶接する。次に、地下1階
梁材10上に所定のスラブ用型枠を設置して地下
1階スラブコンクリート19を打設する。地下2
階梁材9については上記と同様の作業を行う。
After fixing the first floor beams 11 to the frame as described above, as shown in FIG. After pouring the floor slab concrete 18 and further excavating, the beams 8 to 10 are lowered, the underground beams 8 are temporarily fixed in the same manner as above, and the underground first floor beams 1
0 to both structural pillars 3, 3. Next, a predetermined formwork for a slab is installed on the beam material 10 for the first basement floor, and the slab concrete 19 for the first basement floor is poured. Underground 2
Regarding the floor beam material 9, the same work as above is performed.

なお、スラブ用型枠を設置した後、スラブ用鉄
筋を配置し、コンクリートを打設すれば作業床
(スラブ)が形成できるため、スラブ用型枠と同
時に梁用型枠及び柱用型枠を設置し、しかも支保
工の下部は掘削面であつた従来の逆打ち工法に比
べて、型枠組立作業は単純化され、工期の短縮が
図れる。
In addition, after installing the slab formwork, the work floor (slab) can be formed by placing slab reinforcing bars and pouring concrete, so it is necessary to install the beam formwork and column formwork at the same time as the slab formwork. Compared to the conventional reverse construction method, in which the lower part of the shoring is an excavated surface, the formwork assembly work is simplified and the construction period can be shortened.

上記の通りスラブコンクリートを打設し、所定
のコンクリート強度に達したならば、第4図に示
すように、柱20、梁21、耐力壁22の型枠を
組み立て、直上階のスラブの所定位置に設けた貫
通孔よりコンクリートを流し込み、柱、梁、耐力
壁のコンクリートを打設する。
After pouring slab concrete as described above and reaching the specified concrete strength, as shown in Figure 4, formwork for the columns 20, beams 21, and load-bearing walls 22 is assembled, and the concrete is placed in the specified position on the slab on the floor immediately above. Pour concrete through the through-holes provided in the building and place concrete for columns, beams, and load-bearing walls.

最下階では、地中梁材8を両構真柱3,3に溶
接した後、耐圧盤23のコンクリートを打設す
る。次に、柱20、耐力壁22、梁21、スラブ
24のコンクリートを打設する。
On the lowest floor, after welding the underground beam material 8 to both structural pillars 3, 3, concrete for the pressure board 23 is poured. Next, concrete is placed for the columns 20, load-bearing walls 22, beams 21, and slabs 24.

柱、梁、耐力壁のコンクリート打設は、いずれ
も直上階スラブに設けられた貫通孔よりコンクリ
ートを流し込むことによつて行うので、コンクリ
ート打設作業は極めて簡単かつ安全であり、しか
も施工階スラブの上端から直上階スラブの下端の
間には打継ぎ部がないため、止水処理作業は非常
に簡単である。
Concrete pouring for columns, beams, and load-bearing walls is done by pouring concrete through through holes provided in the floor slab directly above, making concrete pouring work extremely easy and safe. Since there is no joint between the upper end and the lower end of the floor slab directly above, water stoppage treatment is very easy.

なお、上述した実施例は、構真柱3の各側面に
設けた2本のガイドレール16,16間に、梁材
11(または8,9,10)の端部を滑合させ、
下降させる場合を想定したが、第9図に示すよう
に構真柱3の各側面に1本のガイドレール16を
設けた場合には、梁材11(または8,9,1
0)の端部にスリツト25を設け、このスリツト
25をガイドレール16に滑合させて梁材を下降
させる。なお、この場合、梁材を構真柱3に固着
するには、第10図に示すように梁材のウエブ部
11bとガイドレール16とを、連結板26,2
6によつて挾持するとともにボルト接合し、梁材
11(または8,9,10)のフランジ部11a
の端面と構真柱3の側面とを溶接する。
In addition, in the embodiment described above, the ends of the beam members 11 (or 8, 9, 10) are slidably fitted between the two guide rails 16, 16 provided on each side of the structural pillar 3,
Although we assumed the case of lowering the beam, if one guide rail 16 is provided on each side of the structural pillar 3 as shown in FIG.
A slit 25 is provided at the end of 0), and the slit 25 is slid onto the guide rail 16 to lower the beam. In this case, in order to fix the beam to the structural pillar 3, as shown in FIG.
The flange portion 11a of the beam material 11 (or 8, 9, 10) is clamped by 6 and bolted together.
The end face of the structure pillar 3 and the side surface of the structural pillar 3 are welded.

以上詳述した通り本発明によれば、1階梁材及
び全地下階の梁材を両構真柱のガイドレールに沿
つて下降させ、上階の梁材より順次、両構真柱に
架構固着するので、梁材の架構作業を簡単かつ能
率的に行える。また作業の安全性も高い。
As detailed above, according to the present invention, the beams on the first floor and all basement floors are lowered along the guide rails of the main columns of both structures, and the beams of the upper floors are sequentially placed on the main columns of both structures. Since it is firmly fixed, the work of constructing beams can be done easily and efficiently. Also, work safety is high.

【図面の簡単な説明】[Brief explanation of drawings]

第1〜4図は本発明の一実施例の架構順序を示
す説明図、第5,6図は構真柱と2階梁材の関係
を示す斜視図及び一部切欠き側面図、第7図は地
中梁材の仮固定状態を示す斜視図、第8図は1階
梁材の固着状態を示す水平断面図、第9,10図
は他の例を示し、第9図はガイドレールと梁材の
関係を示す水平断面図、第10図は梁材の固着状
態を示す水平断面図である。 16……ガイドレール、3……構真柱、2……
孔、7……2階梁材、8……地中梁材、9……地
下2階梁材、10……地下1階梁材、11……1
階梁材。
Figures 1 to 4 are explanatory diagrams showing the structural order of an embodiment of the present invention, Figures 5 and 6 are perspective views and partially cutaway side views showing the relationship between the structural pillars and second floor beams, and Figures 7 The figure is a perspective view showing the temporarily fixed state of underground beams, Fig. 8 is a horizontal sectional view showing the fixed state of first floor beams, Figs. 9 and 10 show other examples, and Fig. 9 is a guide rail. FIG. 10 is a horizontal sectional view showing the relationship between the beam material and the beam material, and FIG. 10 is a horizontal sectional view showing the fixed state of the beam material. 16... Guide rail, 3... Structure pillar, 2...
Hole, 7...2nd floor beam material, 8...underground beam material, 9...2nd basement floor beam material, 10...1st basement floor beam material, 11...1
Floor beam material.

Claims (1)

【特許請求の範囲】[Claims] 1 ガイドレールが設けられた構真柱を地中孔内
に立設し、相対向する両構真柱の地上突出部で上
記ガイドレールの滑合案内部と干渉しない箇所に
2階梁材を架構固着し、両構真柱の間の地盤の掘
削作業が進行した後、全地下階の梁材及び1階梁
材を、順次、下階のものより上記ガイドレールの
滑合案内部に滑合させるとともにそれに沿つて下
降させ、両構真柱間に固着することなく順次段差
的に吊持又は一部梁材の仮固定を行い、さらに掘
削作業の進行とともに、全地下階の梁材及び1階
梁材を同じくガイドレールに沿つて下降させ、両
構真柱間に固着することなく吊持又は一部梁材の
仮固定を行つた後、所定架構位置に達した1階梁
材を両構真柱に架構固着し、以下順次、掘削作
業、梁材の下降、梁材の吊持又は一部梁材の仮固
定を繰り返し行うとともに、上階の梁材から順次
所定架構位置に固着することを特徴とする地下階
梁材の架構工法。
1. A structure pillar equipped with a guide rail is installed in an underground hole, and second-floor beams are installed at the above-ground protruding parts of both opposing structure pillars that do not interfere with the sliding guide part of the guide rail. After the frame is fixed and the excavation work on the ground between the two main pillars has progressed, the beams of all the basement floors and the beams of the first floor are sequentially slid onto the sliding guide part of the guide rail, starting from the one on the lower floor. Then, as the excavation work progresses, the beams and beams of all the basement floors are suspended and temporarily fixed at different levels without being stuck between the main pillars of both structures. After lowering the first floor beams along the same guide rails and suspending them or temporarily fixing some of the beams without sticking them between the true columns of both structures, the first floor beams reached the predetermined frame position. The frame was fixed to the main pillars of both structures, and then excavation work, lowering of the beams, suspension of the beams, and temporary fixing of some beams were repeated in sequence, and the beams of the upper floors were fixed in place in order. A construction method for underground floor beams that is characterized by:
JP11619883A 1983-06-29 1983-06-29 Construction of underground stair beam material Granted JPS6010063A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11619883A JPS6010063A (en) 1983-06-29 1983-06-29 Construction of underground stair beam material

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11619883A JPS6010063A (en) 1983-06-29 1983-06-29 Construction of underground stair beam material

Publications (2)

Publication Number Publication Date
JPS6010063A JPS6010063A (en) 1985-01-19
JPH028102B2 true JPH028102B2 (en) 1990-02-22

Family

ID=14681260

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11619883A Granted JPS6010063A (en) 1983-06-29 1983-06-29 Construction of underground stair beam material

Country Status (1)

Country Link
JP (1) JPS6010063A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0463601U (en) * 1990-10-11 1992-05-29

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0730564B2 (en) * 1987-06-11 1995-04-05 大成建設株式会社 Construction method of underground structure
JPS63312439A (en) * 1987-06-11 1988-12-20 清水建設株式会社 Underground construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0463601U (en) * 1990-10-11 1992-05-29

Also Published As

Publication number Publication date
JPS6010063A (en) 1985-01-19

Similar Documents

Publication Publication Date Title
KR200417438Y1 (en) Bracket structure for girder and slab construction
KR100605514B1 (en) Bracket support type downward construction system and construction method using the same
KR200398231Y1 (en) 1way-supporting bracket for girder and slab construction
KR200372315Y1 (en) Moving-fabricated supporting bracket structure of downward construction system
JP3251567B2 (en) Construction method of open caisson bottom
KR20060117746A (en) A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof
JPS6137692Y2 (en)
JPH028102B2 (en)
KR200402363Y1 (en) Structure for concreting work of column
JPH0361810B2 (en)
JPS63280153A (en) Underground inverted lining method
JPH11140892A (en) Method for excavating ground and method for constructing underground structure using the same
KR101409249B1 (en) Top Down Construction method Using Method Of Steel Hybrid Girder Construction
JPH04293824A (en) Construction method for large span underground structure
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JP2894217B2 (en) Building structural frame
RU34952U1 (en) Reinforced concrete drill string
JP2794330B2 (en) Method of erection of girder beam for underground structure
JP3238510B2 (en) Construction method of preceding slab floor
JPS61134422A (en) Method of building precast concrete underground continuous wall
JPH04185816A (en) Construction of beam in underground wall
KR20060028889A (en) Structure for plastic slab deck system and downward construction method using the same
JP3567387B2 (en) How to build an underground skeleton
JP3236092B2 (en) Steel frame reinforced concrete reverse driving method
JPS63277342A (en) Reverse execution of underground story