JP2638725B2 - Construction method of refuse incinerator facilities - Google Patents

Construction method of refuse incinerator facilities

Info

Publication number
JP2638725B2
JP2638725B2 JP32585192A JP32585192A JP2638725B2 JP 2638725 B2 JP2638725 B2 JP 2638725B2 JP 32585192 A JP32585192 A JP 32585192A JP 32585192 A JP32585192 A JP 32585192A JP 2638725 B2 JP2638725 B2 JP 2638725B2
Authority
JP
Japan
Prior art keywords
crane
construction
building
frame
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP32585192A
Other languages
Japanese (ja)
Other versions
JPH06173479A (en
Inventor
幸一 口池
信武 向井
求 竹内
泰司 山田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Eichi Ii Shii Kk
Hitachi Zosen Corp
Original Assignee
Eichi Ii Shii Kk
Hitachi Zosen Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Eichi Ii Shii Kk, Hitachi Zosen Corp filed Critical Eichi Ii Shii Kk
Priority to JP32585192A priority Critical patent/JP2638725B2/en
Publication of JPH06173479A publication Critical patent/JPH06173479A/en
Application granted granted Critical
Publication of JP2638725B2 publication Critical patent/JP2638725B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Vertical, Hearth, Or Arc Furnaces (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、清掃工場プラントの建
設において、建屋とその内部に据え付けられるごみピッ
トやごみ焼却炉、廃熱ボイラー、集塵器などを建設する
ごみ焼却炉設備の建設工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a refuse incinerator facility for constructing a garbage pit, a refuse incinerator, a waste heat boiler, a dust collector, etc. installed in a building and a garbage plant in the construction of an incineration plant. About.

【0002】[0002]

【従来の技術】ごみ焼却設備において、主要な部分は焼
却炉とボイラーで、これらは10〜18トン程度にブロ
ック化した重量機器材料部材を30個前後搬入して組み
立てられており、通常は2〜4基の焼却炉が並設され
る。その他の集塵器や制御機器は、1〜2トン程度の軽
量機器材料部材を多数搬入して組み立てられている。こ
れら機器材料部材を建屋内に搬入して据え付ける場合、
従来では大別してクローズ工法とオープン工法があっ
た。
2. Description of the Related Art The main parts of a refuse incineration plant are an incinerator and a boiler, which are assembled by carrying around 30 heavy equipment material members blocked into about 10 to 18 tons. Up to four incinerators will be installed side by side. Other dust collectors and control devices are assembled by carrying a large number of lightweight device material members of about 1 to 2 tons. When carrying these equipment materials into the building and installing them,
Conventionally, there were a closed method and an open method.

【0003】まず、クローズ工法は、図9に示すよう
に、最初に建屋21をほぼ建設し、建屋21の天井部に
重量物を搬送可能な20〜30トン(15トン×2台)
×2〜4系列)テルハ式重ホイストクレーン22と、3
〜4トン程度のテルハ式軽ホイストクレーン23とを設
置し、建屋21内および建屋外側に搬送したブロック状
の機器材料部材をこれらホイストクレーン22,23に
より設置位置まで搬入して据え付け、組み立てを行って
いた。
[0003] First, as shown in FIG. 9, the closed construction method firstly constructs a building 21 almost, and 20-30 tons (15 tons × 2) capable of transporting heavy objects to the ceiling of the building 21.
× 2-4 series) Telha type heavy hoist crane 22 and 3
About 4 tons of Telha-type light hoist crane 23 are installed, and the block-shaped equipment material members conveyed to the inside of the building 21 and the outside of the building are transported to the installation position by the hoist cranes 22 and 23 for installation and assembly. I was

【0004】オープン工法は、図10,図11に示すよ
うに、屋根31a部分の施工を残して建屋31を建設し
た後、350〜400トン程度の能力を備えた大型重ク
ローラークレーン(移動式クレーン)32を使用して、
建屋31近傍に搬送したブロック状の機器材料部材を建
屋31上方から未施工の屋根31a部分を介して搬入
し、据え付け組み立てを行ないもこの搬入作業終了後、
屋根31aを施工していた。なお、このオーブン工法に
おいては、クローラークレーン使用位置の建屋建設は後
回しにして、必要以上に高い能力のクローラークレーン
を使用することなく、また長いクレームブームを必要と
しないように配慮されて工事が進められていた。
In the open construction method, as shown in FIGS. 10 and 11, after the building 31 is constructed while leaving the roof 31a, a large heavy crawler crane (mobile crane) having a capacity of about 350 to 400 tons is provided. Using 32)
The block-shaped equipment material member conveyed to the vicinity of the building 31 is carried in from the upper part of the building 31 through the unconstructed roof 31a, and after the completion of the carrying-in work after performing the installation and assembly,
The roof 31a was being constructed. In this oven method, the construction of the building at the location where the crawler crane is used will be postponed, and the construction will proceed without using a crawler crane with an unnecessarily high capacity and not requiring a long claim boom. Had been.

【0005】[0005]

【発明が解決しようとする課題】しかし、上記クローズ
工法においては、建屋がほぼ完成してから焼却炉やボイ
ラーの据え付けを行うため、 a.建屋の工期と、焼却炉据え付け工期の総和が設備全
体の工期で、全体の工期が長くなり、建設コストが高
い。 b.建屋の天井部に大型のテルハ式ホイストクレーンを
設置するため、このクレーンの荷重に耐えることができ
る強度を建屋に持たせる必要があり、建屋の建設コスト
が高い。 という問題があった。
However, in the above-mentioned closed method, an incinerator or a boiler is installed after the building is almost completed. The sum of the construction period of the building and the installation period of the incinerator is the construction period of the entire equipment, and the overall construction period becomes longer and the construction cost is higher. b. Since a large Telha-type hoist crane is installed on the ceiling of the building, it is necessary to provide the building with strength capable of withstanding the load of the crane, and the construction cost of the building is high. There was a problem.

【0006】また、オープン工法は、クローラクレーン
を使用するため、 a.機器搬入範囲の屋根を除く建屋の工期と、焼却炉等
設備機器の据え付け工期と、機器搬入範囲の屋根の工期
との総和が全体の工期で、全体の工程工期が長い。 b.大型重クローラークレーンを使用する期間(2か月
程度)が長く、安全性が低い。 c.焼却炉等設備機器の搬入が終わるまで、雨覆いが無
い現場での作業となるので、天候に左右されて作業効率
が悪い。 d.焼却炉等設備機器の搬入後の組み立て据え付け作業
と、屋根の工事を同時進行する場合、安全対策が難しく
それに要するコストが高い。 という問題があった。
In the open method, a crawler crane is used. The sum of the construction period of the building excluding the roof in the equipment loading range, the installation period of the equipment such as the incinerator, and the construction period of the roof in the equipment loading range is the total construction period, and the entire construction period is long. b. The long period (about 2 months) of using a large heavy crawler crane is long and the safety is low. c. Until the installation of incinerators and other equipment is completed, work will be performed at the site without a rain cover, and the work efficiency will be poor depending on the weather. d. When the assembly and installation work after carrying in the incinerators and other equipment and the roof construction work proceed simultaneously, safety measures are difficult and the costs involved are high. There was a problem.

【0007】本発明は、上記問題点を解決して、建設工
期の短縮と安全作業を図り作業効率を向上して、建設コ
ストを低減できるごみ焼却炉設備の建設工法を提供する
ことを目的とする。
An object of the present invention is to solve the above-mentioned problems and to provide a construction method of a refuse incinerator facility capable of shortening the construction period, improving work efficiency and improving construction efficiency and reducing construction costs. I do.

【0008】[0008]

【課題を解決するための手段】上記問題点を解決するた
めに本発明のごみ焼却炉設備の建設工法は、車両乗り入
れ部を備えた躯体の土間をコンクリート打設により構築
する土間工事工程を行った後、コンクリート養生後の車
両乗り入れ部に乗り入れた移動式クレーンを使用してボ
イラー架構を設置する架構構築工程を行い、さらに前記
移動式クレーンにより前記ボイラー架構上部のクレーン
架構部に重量機器材料部材を搬入可能な重ホイストクレ
ーンを設置するクレーン設置工程を行ない、前記架構構
築工程およびクレーン設置工程と同時に、建屋の躯体と
屋根を建設する建屋建設工程を同時進行させ、移動式ク
レーンを搬出後、車両乗り入れ部に搬入した機器材料部
材を前記重ホイストクレーンを使用して搬入し据え付け
および構築を行う焼却炉設備据付工程を実施すると同時
に、前記建屋建設工程も並行して行うものである。
In order to solve the above-mentioned problems, a construction method of a refuse incinerator facility of the present invention includes a soil-filling construction step of constructing a soil-filled space of a frame having a vehicle entrance by concrete casting. After that, a frame construction step of installing a boiler frame using a mobile crane that has entered the vehicle entrance after the concrete curing is performed, and the heavy crane frame above the boiler frame is further moved by the mobile crane to a heavy equipment material member. Perform a crane installation process of installing a heavy hoist crane that can carry in, simultaneously with the frame construction process and the crane installation process, simultaneously proceed with the building construction process of building the building frame and roof, and after unloading the mobile crane, Using the heavy hoist crane, the equipment material members carried into the vehicle entrance are carried in, installed and constructed. At the same time implementing the 却炉 equipment installation process, the building construction process also is performed in parallel.

【0009】[0009]

【作用】上記建設工法によれば、重量機器材料部材およ
び軽量機器材料部材を搬入可能なホイストクレーンをボ
イラー架構に設けたので、従来のクローズ工法のように
建屋に設けるのに比べて、焼却炉設備据付工程に並行し
て建屋建設工程を実施できるとともに、建屋に大きい荷
重がかからず強度を大きくする必要がない。また、オー
プン工法において安全性の低い大型重クローラークレー
ンを長期間使用するのに比べて、ボイラー架構の構築は
小型軽移動式クレーンで短期間の使用で実施することが
でき、焼却炉設備据付工程中に建屋建設工程を同時並行
して進行することができる。
According to the construction method described above, a hoist crane capable of carrying a heavy equipment material member and a light equipment material member is provided in a boiler frame. The building construction process can be performed in parallel with the equipment installation process, and there is no need to increase the strength because a large load is not applied to the building. Also, compared to using a heavy-duty crawler crane with low safety in the open construction method for a long period of time, the construction of the boiler frame can be carried out with a small and light mobile crane in a short period of time, and the incinerator equipment installation process During the building construction process can proceed in parallel.

【0010】したがって、コンクリート土間工事工程以
外およびクレーン設置工程時の工事部分以外の進行時
に、建屋の建設を並行して進行することができるので、
工期を大幅に短縮できるとともに、ボイラー架構を利用
してホイストクレーンを設置するので、建屋に他の荷重
が付加されることもなく、建設コストを低減することが
できる。
Therefore, the construction of the building can proceed in parallel with the process other than the concrete soil work process and the work other than the construction portion during the crane installation process.
The construction period can be greatly reduced, and the hoist crane is installed using the boiler frame, so that no other load is added to the building and the construction cost can be reduced.

【0011】[0011]

【実施例】以下、本発明に係るごみ焼却設備の建設工法
の一実施例を図1〜図9に基づいて説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS One embodiment of the construction method of a refuse incineration plant according to the present invention will be described below with reference to FIGS.

【0012】まず、図1〜図3を参照して建設するごみ
焼却炉設備の概要を説明する。13は躯体2のごみ搬入
部2aからごみ収集車からごみを投入するごみピット
で、2基が設けられ、このごみピット13の側部に2基
の焼却炉12が設置されるとともに、焼却炉12上部に
ボイラー5が設けられている。これら焼却炉12から車
両乗り入れ部1を介して排ガスの冷却塔10と集塵器1
1が設置されている。14は焼却炉12から排出される
焼却灰を溜める灰ピットである。
First, an outline of a refuse incinerator facility to be constructed will be described with reference to FIGS. Reference numeral 13 denotes a garbage pit for introducing garbage from a garbage truck from the garbage loading section 2a of the skeleton 2. Two garbage pits are provided. The boiler 5 is provided on the upper part 12. Exhaust gas cooling tower 10 and dust collector 1 from these incinerators 12 via vehicle entrance 1
1 is installed. Reference numeral 14 denotes an ash pit for storing incineration ash discharged from the incinerator 12.

【0013】施工前に、土建工程との混在作業を避ける
ために、焼却炉およびボイラー構成材等の機器、装置類
の組み立ては現場では行わず、他の場所で行ってブロッ
ク化、プレハブ化およびユニット化を促進させ、10〜
18トン程度にブロック化した重量機器材料部材と、そ
の他1〜2トン程度の軽量機器材料部材とに分け、その
搬入および据え付け方法が効率的に行われる。
Before construction, in order to avoid work mixed with the civil engineering process, assembling of equipment and devices such as incinerators and boiler components is not performed on site, but is performed in other places to make blocks, prefabricated, and so on. Promote unitization,
A heavy equipment material member divided into about 18 tons and a light equipment material member of about 1 to 2 tons are separately provided, and the loading and installation method is efficiently performed.

【0014】次に、建設工程を順を追って説明する。 (1)図4に示すように、車両乗り入れ部(土間)1を
有する躯体(土間と壁体を含む)2をコンクリート打設
により形成する〔土間工事工程〕。この車両乗り入れ部
1は下記の軽クローラークレーン(移動式クレーン)3
を乗り入れ可能な強度を確保している。
Next, the construction process will be described step by step. (1) As shown in FIG. 4, a skeleton (including soil and wall) 2 having a vehicle entrance (soil) 1 is formed by concrete casting (soil construction process). The vehicle entry section 1 includes a light crawler crane (mobile crane) 3 described below.
It has enough strength to get in.

【0015】(2)図5に示すように、コンクリートの
養生後、車両乗り入れ部1に45トン級(1トン級機器
材料部材吊下用)の軽クローラークレーン3を乗り入
れ、トレーラーにより搬入した炉体鉄骨4をこのクロー
ラークレーン3により構築位置に搬入して組み立て据え
付ける。さらに図6に示すように、クローラークレーン
3により構築された炉体鉄骨4上に、ボイラー架構5a
クレーン用架構部5bおよびを搬入して組み立てる〔架
構構築工程〕。このボイラー架構5aは、従来のボイラ
ー架構に比べて背が高く設定されて、上部がクレーン用
架構部5bに構成されている。
(2) As shown in FIG. 5, after curing the concrete, a 45-ton class (for suspending a 1-ton class equipment material member) light crawler crane 3 enters the vehicle entrance 1, and the furnace is carried in by a trailer. The body steel frame 4 is carried into the construction position by the crawler crane 3 and assembled and installed. Further, as shown in FIG. 6, a boiler frame 5a is placed on a furnace steel frame 4 constructed by the crawler crane 3.
The crane frame portion 5b is loaded and assembled (frame construction step). The boiler frame 5a is set to be taller than a conventional boiler frame, and the upper portion is configured as a crane frame 5b.

【0016】(3)さらに図6に示すように、前記クロ
ーラークレーン3を使用して、クレーン用架構部5bに
搬入端部が車両乗り入れ部1上方に張り出すホイスト走
行レール6aを取り付けるとともに、このホイスト走行
レール6aにホイスト本体6bを装着して、重量機器材
料部材を搬入可能な2基ずつ二組の15トン級のテルハ
式重ホイストクレーン6を設置し〔クレーン設置工
程〕、さらに図7に示すように、クレーン用架構5aの
天井部に雨天兼用安全板7を取り付ける。また、この雨
天兼用安全板7により、クレーン用架構5a上方の屋根
取り付け作業とクレーン用架構5a下方の焼却炉12お
よびボイラー5の組立作業を分離してそれぞれ安全に行
うことができる。
(3) Further, as shown in FIG. 6, the crawler crane 3 is used to attach a hoist running rail 6a whose carrying end protrudes above the vehicle entrance 1 to the crane frame 5b. The hoist body 6b is mounted on the hoist running rail 6a, and two sets of 15 ton class Telha type heavy hoist cranes 6 each capable of carrying heavy equipment material members are installed [crane installation process]. As shown in the figure, the rainy weather safety plate 7 is attached to the ceiling of the crane frame 5a. In addition, the work for mounting the roof above the frame 5a for the crane and the operation for assembling the incinerator 12 and the boiler 5 below the frame 5a for the crane can be separated and safely performed by the rain / safety plate 7, respectively.

【0017】(4)上記架構構築工程およびクレーン設
置工程と並行して、建屋8の側壁8a等を施工し、架構
構築工程およびクレーン設置工程と関係しない箇所にお
いて屋根8bの構築〔建屋建設工程〕も行う。さらに図
1に示すように、冷却塔10や集塵器11設置位置の上
方の屋根8bを設置後、屋根8bにホイスト走行レール
9aの搬入端部が建屋8の外側に張り出して外部から軽
量機器材料部材を搬入可能な3〜4トン級の軽ホイスト
クレーン9を配設する。
(4) In parallel with the frame construction step and the crane installation step, the side walls 8a and the like of the building 8 are constructed, and the roof 8b is constructed at a location unrelated to the frame construction step and the crane installation step (building construction step). Also do. Further, as shown in FIG. 1, after the roof 8 b is installed above the installation position of the cooling tower 10 and the dust collector 11, the carry-in end of the hoist running rail 9 a protrudes outside the building 8 on the roof 8 b, and lightweight equipment is externally provided. A light hoist crane 9 of 3 to 4 ton class capable of carrying material members is provided.

【0018】(5)図7に示すように、ブロック化、ユ
ニット化された前記焼却炉およびボイラー構成材等の重
量および軽量機器材料部材をトレーラーにより車両乗り
入れ部1に搬入し、重ホイストクレーン6により据え付
け位置に搬入して据え付け、図8に示すように、焼却炉
12において炉体鉄骨4上にホッパー12aおよびコン
ベヤ(図示せず)を設けるとともに、火格子12bを組
み立て、さらに炉体を構築後、ボイラー架構5a内にボ
イラー5を組み立てる。また同時に、軽ホイストクレー
ン9を使用して建屋8の外から軽量機器材料部材を搬入
し、冷却塔10や集塵器11を並行して据え付ける〔焼
却炉設備据付工程〕。
(5) As shown in FIG. 7, the heavy and light equipment materials such as the incinerator and the boiler components which are made into blocks and unitized are carried into the vehicle entrance 1 by a trailer, and the heavy hoist crane 6 As shown in FIG. 8, a hopper 12a and a conveyor (not shown) are provided on the furnace body steel frame 4 in the incinerator 12, and a grate 12b is assembled to further construct a furnace body as shown in FIG. Thereafter, the boiler 5 is assembled in the boiler frame 5a. At the same time, a lightweight equipment material member is carried in from the outside of the building 8 using the light hoist crane 9, and the cooling tower 10 and the dust collector 11 are installed in parallel (incinerator equipment installation step).

【0019】上記実施例によれば、土間工事工程が終了
してコンクリートが養生された後には、車両乗り入れ部
1以外の箇所で、車両乗り入れ部1で行う架構構築工程
およびクレーン設置工程に抵触しない範囲で、架構構築
工程、クレーン設置工程および焼却炉設備据付工程と並
行して、建屋建設工程を同時進行させることができるの
で、その工期を従来に比べて大幅に短縮することができ
る。
According to the above-described embodiment, after the concrete work is completed after the soil work process is completed, the frame construction process and the crane installation process performed in the vehicle entry unit 1 at locations other than the vehicle entry unit 1 do not conflict with each other. Within this range, the building construction process can be performed simultaneously with the frame construction process, the crane installation process, and the incinerator facility installation process, so that the construction period can be significantly shortened as compared with the related art.

【0020】また、高さを少し高くしてクレーン用架構
部5bを設けたボイラー架構5aを利用して、重ホイス
トクレーン6を設けたので、従来のクローズ工法のよう
に、建屋8に重ホイストクレーンを設置するのに比べ
て、建屋8の強度を大きくする必要がなく、建屋8の材
料コストを大幅に低減することができ、またオープン工
法のように重クローラークレーンを長期間使用するのに
比べて、安全性を大幅に向上することができる。
Further, since the heavy hoist crane 6 is provided by using the boiler frame 5a provided with the frame portion 5b for the crane at a slightly higher height, the heavy hoist crane 6 is mounted on the building 8 as in the conventional closed construction method. Compared to installing a crane, it is not necessary to increase the strength of the building 8, and the material cost of the building 8 can be greatly reduced. In comparison, safety can be greatly improved.

【0021】[0021]

【発明の効果】以上に述べたごとく本発明のごみ焼却設
備の建設工法によれば、重量機器材料部材および軽量機
器材料部材を搬入可能なホイストクレーンをボイラー架
構に設けたので、従来のクローズ工法のように建屋に設
けるのに比べて、焼却炉設備据付工程に並行して建屋建
設工程を実施できるとともに、建屋に大きい荷重がかか
らず強度を大きくする必要がない。また、オープン工法
において安全性の低い大型重クローラークレーンを長期
間使用するのに比べて、ボイラー架構の構築は小型軽移
動式クレーンで短期間の使用で実施することができ、焼
却炉設備据付工程中に建屋建設工程を同時並行して進行
することができる。
As described above, according to the construction method of the refuse incineration plant of the present invention, a hoist crane capable of carrying a heavy equipment material member and a light equipment material member is provided on a boiler frame, and therefore, a conventional closed construction method is used. As compared with the case of installing in a building as described above, the building construction process can be performed in parallel with the incinerator facility installation process, and a large load is not applied to the building, and it is not necessary to increase the strength. Also, compared to using a heavy-duty crawler crane with low safety in the open construction method for a long period of time, the construction of the boiler frame can be carried out with a small and light mobile crane in a short period of time, and the incinerator equipment installation process During the building construction process can proceed in parallel.

【0022】したがって、土間工事工程以外およびクレ
ーン設置工程時の工事部分以外の進行時に、建屋の建設
を並行して進行することができるので、工期を大幅に短
縮できるとともに、ボイラー架構を利用してホイストク
レーンを設置するので、建屋に他の荷重が付加されるこ
ともなく、建設コストを低減することができる。
Therefore, the construction of the building can be performed in parallel during the operation other than the earthwork construction process and the construction portion during the crane installation process, so that the construction period can be greatly reduced and the boiler frame can be used. Since the hoist crane is installed, no other load is added to the building, and the construction cost can be reduced.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係る建設工法により建設されたごみ焼
却設備を示す全体縦断面図である。
FIG. 1 is an overall longitudinal sectional view showing a refuse incineration facility constructed by a construction method according to the present invention.

【図2】図1に示すA−A断面図である。FIG. 2 is a sectional view taken along line AA shown in FIG.

【図3】図1に示すB−B断面図である。FIG. 3 is a sectional view taken along line BB shown in FIG.

【図4】同建設工法の土間工事工程を示す断面図であ
る。
FIG. 4 is a cross-sectional view showing a soil construction process of the construction method.

【図5】同建設工法の架構構築工程を示す切欠き斜視図
である。
FIG. 5 is a cutaway perspective view showing a frame construction step of the construction method.

【図6】同建設工法のクレーン設置工程を示す斜視図で
ある。
FIG. 6 is a perspective view showing a crane installation step of the construction method.

【図7】同建設工法の焼却炉設備据付工程の搬入状態を
示す斜視図である。
FIG. 7 is a perspective view showing a state of carrying in the incinerator facility installation step of the construction method.

【図8】同建設工法の焼却炉設備据付工程における焼却
炉組立状態を示す斜視図である。
FIG. 8 is a perspective view showing an incinerator assembly state in an incinerator facility installation process of the construction method.

【図9】従来のクローズ工法を示すごみ焼却設備の全体
縦断面図である。
FIG. 9 is an overall vertical sectional view of a refuse incineration plant showing a conventional closing method.

【図10】従来のオープン工法を示すごみ焼却設備の全
体縦断面図である。
FIG. 10 is an overall vertical sectional view of a refuse incineration plant showing a conventional open method.

【図11】従来のオープン工法における作業を示す斜視
図である。
FIG. 11 is a perspective view showing an operation in a conventional open construction method.

【符号の説明】 1 車両乗り入れ部 2 躯体 3 軽クローラークレーン 4 炉体鉄骨 5 ボイラー 5a ボイラー架構 5b クレーン用架構部 6 重ホイストクレーン 6a ホイスト走行レール 6b ホイスト本体 7 雨天兼用安全板 8 建屋 8a 側壁 8b 屋根 9 軽ホイストクレーン[Description of Signs] 1 Vehicle entry part 2 Body 3 Light crawler crane 4 Furnace steel frame 5 Boiler 5a Boiler frame 5b Crane frame 6 Heavy hoist crane 6a Hoist running rail 6b Hoist body 7 Rain / safety plate 8 Building 8a Side wall 8b Roof 9 light hoist crane

───────────────────────────────────────────────────── フロントページの続き (72)発明者 竹内 求 大阪府大阪市此花区桜島1丁目4番6号 日立造船エンジニアリング株式会社内 (72)発明者 山田 泰司 大阪府大阪市此花区桜島1丁目4番6号 日立造船エンジニアリング株式会社内 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Motomu Takeuchi 1-4-6 Sakurajima, Konohana-ku, Osaka-shi, Osaka Inside Hitachi Zosen Engineering Co., Ltd. (72) Yasushi Yamada 1-4-4 Sakurajima, Konohana-ku, Osaka-shi, Osaka No. 6 Inside Hitachi Zosen Engineering Co., Ltd.

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 車両乗り入れ部を備えた躯体の土間をコ
ンクリート打設により構築する土間工事工程を行った
後、コンクリート養生後の車両乗り入れ部に乗り入れた
移動式クレーンを使用してボイラー架構を設置する架構
構築工程を行い、さらに前記移動式クレーンにより前記
ボイラー架構上部のクレーン架構部に重量機器材料部材
を搬入可能な重ホイストクレーンを設置するクレーン設
置工程を行ない、前記架構構築工程およびクレーン設置
工程と同時に、建屋の躯体と屋根を建設する建屋建設工
程を同時進行させ、移動式クレーンを搬出後、車両乗り
入れ部に搬入した機器材料部材を前記重ホイストクレー
ンを使用して搬入し据え付けおよび構築を行う焼却炉設
備据付工程を実施すると同時に、前記建屋建設工程も並
行して行うことを特徴とするごみ焼却炉設備の建設工
法。
After performing a dirt construction process of constructing a dirt of a skeleton having a vehicle entrance by concrete casting, a boiler frame is installed by using a mobile crane that has entered the vehicle entrance after the concrete has been cured. A crane installation step of installing a heavy hoist crane capable of carrying heavy equipment material members into the crane frame section above the boiler frame by the movable crane is performed, and the frame construction step and the crane installation step are performed. At the same time, the building construction process of constructing the building frame and roof is proceeded simultaneously, and after the mobile crane is carried out, the equipment material members carried into the vehicle entrance are carried in using the heavy hoist crane for installation and construction. At the same time as performing the incinerator equipment installation process, the building construction process is also performed in parallel. Construction method of refuse incinerator facilities.
JP32585192A 1992-12-07 1992-12-07 Construction method of refuse incinerator facilities Expired - Lifetime JP2638725B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP32585192A JP2638725B2 (en) 1992-12-07 1992-12-07 Construction method of refuse incinerator facilities

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP32585192A JP2638725B2 (en) 1992-12-07 1992-12-07 Construction method of refuse incinerator facilities

Publications (2)

Publication Number Publication Date
JPH06173479A JPH06173479A (en) 1994-06-21
JP2638725B2 true JP2638725B2 (en) 1997-08-06

Family

ID=18181331

Family Applications (1)

Application Number Title Priority Date Filing Date
JP32585192A Expired - Lifetime JP2638725B2 (en) 1992-12-07 1992-12-07 Construction method of refuse incinerator facilities

Country Status (1)

Country Link
JP (1) JP2638725B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3608796B2 (en) * 1995-09-18 2005-01-12 株式会社 日立製作所 Nuclear power plant construction method and nuclear power plant
CN110440272B (en) * 2019-08-09 2020-08-21 湖南省工业设备安装有限公司 Incinerator installation method
CN117211533A (en) * 2023-08-31 2023-12-12 上海宝冶集团有限公司 Method for determining comprehensive installation construction sequence of steel structure of earthing heavy roof of power plant

Also Published As

Publication number Publication date
JPH06173479A (en) 1994-06-21

Similar Documents

Publication Publication Date Title
CN106839775A (en) A kind of modular manufacturing method of heating furnace and the heating furnace manufactured with the method
JP2638725B2 (en) Construction method of refuse incinerator facilities
CN108979198A (en) A kind of skyscraper tears building machine open and its tears building method open
JP4896645B2 (en) Temporary house for coke oven and coke oven equipment provided with the same
US5716165A (en) Process and installation for garbage disposal
JP3078805B1 (en) Construction method of nuclear power facilities
JP2007217104A (en) Waste processing facility
JP3212231B2 (en) Plant construction method and construction equipment
JPH09281268A (en) Method for constructing turbine building of atomic power plant
CN213444753U (en) Mobile trolley structure for building hoisting platform
JP3212233B2 (en) Power plant construction method using overhead crane
JPH0718881A (en) Method for demolishing underground skeleton
KR200164728Y1 (en) The waste-introducing place of the waste-burning plate
CN220598491U (en) Outdoor elevator foundation structure of assembled steel construction
CN219828845U (en) Slag inlet structure of slag pool
CN213294446U (en) Multifunctional lifting lug and lifting device
JP4225399B2 (en) Waste treatment facility
RU1838554C (en) Method for repairs of smoke stacks
CN2846353Y (en) Bucket elevator in storehouse
Buzatu et al. Environmental Impact Assessment of Buildings with Steel-Intensive Façade Systems–A Case Study
JP2907017B2 (en) Construction of large-scale structures
JPS6340034A (en) Construction of building having ceiling running crane
JP2536347B2 (en) Building construction method using traveling crane
JP2000177804A (en) Garbage receiving and storing facility in garbage treatment facility
GB1604829A (en) Method of erecting building walls wall panel units building walls and buildings