CN106839775A - A kind of modular manufacturing method of heating furnace and the heating furnace manufactured with the method - Google Patents

A kind of modular manufacturing method of heating furnace and the heating furnace manufactured with the method Download PDF

Info

Publication number
CN106839775A
CN106839775A CN201710158036.6A CN201710158036A CN106839775A CN 106839775 A CN106839775 A CN 106839775A CN 201710158036 A CN201710158036 A CN 201710158036A CN 106839775 A CN106839775 A CN 106839775A
Authority
CN
China
Prior art keywords
furnace
radiation
headwall
wall
place
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710158036.6A
Other languages
Chinese (zh)
Inventor
郭国义
师厚云
刘杰
苌凤祥
傅建华
杨晓锋
谢朝晖
王澄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NINGBO LIANTONG EQUIPMENT MANUFACTURING Co Ltd
Original Assignee
NINGBO LIANTONG EQUIPMENT MANUFACTURING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NINGBO LIANTONG EQUIPMENT MANUFACTURING Co Ltd filed Critical NINGBO LIANTONG EQUIPMENT MANUFACTURING Co Ltd
Priority to CN201710158036.6A priority Critical patent/CN106839775A/en
Publication of CN106839775A publication Critical patent/CN106839775A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D1/00Casings; Linings; Walls; Roofs
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D1/00Casings; Linings; Walls; Roofs
    • F27D2001/0046Means to facilitate repair or replacement or prevent quick wearing
    • F27D2001/0053Furnace constructed in modules

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Tunnel Furnaces (AREA)

Abstract

A kind of modular manufacturing method of heating furnace disclosed by the invention, comprises the following steps:Modules, radiation burst prefabrication, basement process, radiation burst lining, furnace bottom is installed, and side headwall is installed, shaped steel, inside wall boiler tube is connected between inside wall, inside wall to install, external wall and external wall boiler tube are installed, and opposite side headwall is installed, and furnace roof module is installed, radiation comb welding heat treatment, radiation turns convection pass installation, and furnace bottom, radiation turn convection pass lining, baker, flow module is installed, chimney is installed, oil transfer line welding heat treatment, and flow module auxiliary frame frame, ladder landing platform are installed, Hydrostatic test, outer surface treatment, mark;The advantage of the invention is that:The advantage of modular manufacturing is given full play to, shortens the manufacturing cycle, reduce manufacturing cost, improve workmanship.

Description

A kind of modular manufacturing method of heating furnace and the heating furnace manufactured with the method
Technical field
The present invention relates to heating furnace manufacturing technology field, the modular manufacturing method and use of specifically a kind of heating furnace The heating furnace of the method manufacture.
Background technology
Modernization some large scale equipments parameter it is high, part is more, volume is big, weight is big, it is impossible to manufactory manufacture after Transport device to live, and the shortcomings of having long in time limit, equipment quality hardly possible is controlled of constructing at the scene;With module supply business Specialized and traffic condition improve constantly, domestic major petrochemical projects are all carrying out different degrees of modularization, with true Guarantee the quality and the cycle, compared with making in site, modularization has following advantage:
1)More preferable working environment
The condition of work of factory floor manufacture is far superior to field condition, smaller by weather, such environmental effects, and not by existing Build when solid space limitation, can multimode simultaneously manufactured, there is no work high above the ground after modularization, operating efficiency is significantly Improve, total lever factor can shorten 4-5 month.
2)More superior manufacturing equipment
In specialized workshop manufacturing process, more superior frock equipment can be used, be conducive to improving operating efficiency and system (making such as to large-scale steel structure introduces CO to make precision2The high-efficiency welding method such as gas shielded arc welding and submerged-arc welding, use special machine Device is cut and is eliminated rust, and there are sandblasting paint shop, large-scale heat treatment, exposure room and the professional blanking equipment of specialty in factory);
Workshop manufactures, and has special manufacture of steel structure platform, and weldquality is easy to control, and flatness, linearity is conveniently adjusted. The sandblasting paint shop of specialty, thoroughly, roughness is up to standard for sandblasting, and paint is uniform, attractive in appearance, and is lost small.
One of key of heating furnace manufacture is exactly to weld, and the welding of pressure parts and steel construction is most important, indoor welding Following advantage is welded with compared to in-site installation open air:
1. environment temperature can be controlled effectively, reach the temperature required by welding;
2. wind speed can be controlled effectively, it may be necessary to set draught exclusion device, relatively outdoor more simple;
3. welding is protected from weather influences, it may be necessary to take measures to make humidity during welding to reach standard requirement;
4. welder is under conditions of welding surroundings are excellent, and beneficial to playing the due technical ability of welder, and labour intensity is than big out of doors Amplitude reduction, raises labour productivity, it is ensured that product quality;
5. indoor welding can also preferably set safety prevention measure, it is ensured that safety in production.
3)Job engineering efficiency higher
Module supply business has special organization and professional contingent, and orderly the carrying out of energy efficiently produces.With site operation phase Than, it is not necessary to total bag and owner to live various places, road, the management such as the coordination of hydroelectric facility etc. and HSE.
4)Committed step better quality controls (lining, welding of tubes)
Workshop manufacture (can such as change operation difficulty high for the welding of the important components such as boiler tube is createed than live more favorable condition Vertical position welding and fixed weldering is for the low downhand welding of operation difficulty and rotates weldering, conveniently take interior argon filling, preheating and heat treatment measure etc.), Be conducive to improving welding quality, reduce reclamation work amount;
Workshop manufacture can reduce that lining construction is outdoor and work high above the ground difficulty, can be put down using the irrealizable castable of making in site Lining, improves lining quality.
5)It is easy to quality control
In addition to the manufacturing equipment and inspection equipment that have specialty, manufactory has also carried out pre-assembled, can not only check final size, (such as whether rationally design of node, node diagram is either with or without statement to also help discovery design document imperfection or unaccommodated details With the presence or absence of situation about being difficult to carry out etc. in clear, manufacture), scattered material to asking that Assembling just finds is evaded to greatest extent Topic, is corrected in time.
6)Work on the spot amount is reduced, and is easy to control the construction period
Modular manufacturing not by the wind, the influence of the outside environmental elements such as rain, snow, typhoon, the manufacturing cycle is short.Modularization greatly reduces existing Field installation period, the scene only once jacking work in place of integral module main equipment.For scene changing without construction site Expansion project, construction period short grassroot project, and can short construction period Petrochemical Enterprises (north frost place), modularization It is first-selected.
7)Expense is relatively reduced
Expense aspect qualitative analysis:It is assumed that workman is identical with manager-related factors, expense aspect qualitative analysis is carried out.
Installation fee:The prefabricated expense of factory modularization has very big reduction relative to in-site installation expense:
1. the site operation ratio cost of labor that is prefabricated in the factory is high;
2. prefabrication efficiency is improved, can effective reduces cost;
3. prefabrication, Assembling can save live place and take and space expenses, rule of thumb 100,000,000 yuan of contract output values, greatly Generally need 10,000 square metres of in-situ precast places;The temporary facility expense such as storehouse, office can be saved simultaneously;
Prefabrication, Assembling workmen is reduced, and the in-site installation cycle greatly reduces, and the management of owner can be greatly reduced Personnel and administration fee.
The content of the invention
The technical problems to be solved by the invention are directed to the present situation of prior art, there is provided can shorten the manufacturing cycle, subtract Few manufacturing cost, the heating furnace for improving a kind of modular manufacturing method of heating furnace of workmanship and being manufactured with the method.
The present invention solve the technical scheme that is used of above-mentioned technical problem for:
A kind of modular manufacturing method of heating furnace, comprises the following steps:
Step one, prefabrication:Modules, radiation burst prefabrication;
Step 2, basement process:Base is processed according to design drawing, after basic maintenance is qualified, to bearing on concrete pedestal Position carries out line setting-out, and then bearing is positioned on concrete pedestal;
Step 3, radiation burst lining:The radiation burst of prefabrication is transported to assembling place, is placed in around body of heater, to removing The radiation burst that radiation turns outside convection pass carries out lining;
Step 4, furnace bottom are installed:Furnace bottom is lifted on bearing, after furnace bottom lifting is in place, furnace bottom installed height mark is checked and is put down Face degree;
Step 5, side headwall are installed:The side headwall of two furnace chambers is hung in into furnace bottom module respectively, headwall adjusts good position, Method being fallen with messenger wire and detecting headwall and furnace bottom perpendicularity, then headwall is fixed with furnace bottom spot welding, furnace wall outside is using on headwall Hanger sets cable wind rope and is fixed on ground anchor point, the setting of furnace wall inside cable wind rope, by headwall top and furnace roof interface The mode of the interim hanger of place's welding, is set on the shackle plate that cable wind rope is fixed on furnace bottom, piecemeal joint face core drill according to The bolt hole of the bolt hole drill furnace bottom module opened on headwall, is then twisted bolt, and bolt need not be tightened, so as to subsequently to furnace chamber Steel construction carries out size adjusting;
Shaped steel, inside wall boiler tube is connected between step 6, inside wall, inside wall to install:To be lifted per a piece of inside wall in place, install After fixation, the connection shaped steel between inside wall is installed in place, is then again installed in place the boiler tube in inside wall;
Step 7, external wall and external wall boiler tube are installed:By external wall lifting in place, install it is fixed after, then again by external wall Boiler tube is installed in place;
Step 8, opposite side headwall are installed:The opposite side headwall of two furnace chambers is hung in into installation, cable wind rope is set;
Step 9, furnace roof module are installed:When furnace roof module is installed, using the tube type lifting eye set on vertical shaft, lifting in place, is adjusted After good position, it is welded at joint face, with core drill according on the bolt hole drill side wall opened of furnace roof module, headwall on interface Bolt hole, tighten bolt;
Step 10, radiation comb welding heat treatment:After furnace roof is installed, you can carry out the weldering of connecting tube between radiation comb Connect;
Step 11, radiation turn convection pass installation:Radiation is turned into convection pass lifting in place, during installation, adjustment radiation turns right The angle steel flange circle at flow flue two ends, after position adjustment is good, angle steel flange is screwed on bolt, and weldering is sealed between interface, and radiation turns right Angle steel flange circle on flow flue is welded with wallboard;
Step 12, furnace bottom, radiation turn convection pass lining:Lining is carried out to furnace bottom, the fine blanket of pottery is clogged at burst face and with close Sealing is clung, while turning convection pass to radiation carries out benefit lining;
Step 13, baker:Furnace operation is carried out to heating furnace;
Step 14, to flow module install:After the lifting to flow module can be carried out after baker end-of-job, first will be right during lifting Stream mould one is lifted in place, and after adjustment good position, joint face tightens bolt, and convection current mould two, convection current mould three is similarly lifted successively;
Step 15, chimney are installed:After by chimney lifting in place, the lower end of chimney is connected with to flow module;
The welding heat treatment of step 10 six, oil transfer line:Carry out installation, the welding of oil transfer line;
Step 10 seven, to flow module auxiliary frame frame, ladder landing platform install:Bolt company is to flow module auxiliary frame frame and ladder landing platform Connect, auxiliary frame frame and body of heater junction are 2 pieces of connecting plates, scene core drill according to the perforate on auxiliary frame frame bolt hole drill stove Connecting plate on body, is then twisted bolt;
Step 10 eight, Hydrostatic test:Hydraulic pressure test is carried out according to water pressure test requirement;
The treatment of step 10 nine, outer surface, mark:Body of heater outer surface paints, identifies.
It is optimization above-mentioned technical proposal, the concrete measure taken also includes:
In above-mentioned step two, each upper surface of support sets 4 groups of taper liner blocks and absolute altitude centering, upper surface absolute altitude is carried out to upper surface Deviation is controlled in ± 1mm.
In above-mentioned step three, during lining, in addition to radiation turns convection pass, remaining body of heater burst lining surrounding is reserved 5mm gaps;Radiation turns the reserved 100mm surpluses of lining of convection pass and side wall connecting place, to be irradiated to turn after convection pass installs Lining is mended again.
In above-mentioned step four, the control of furnace bottom installed height mark is controlled in≤3mm in ± 1mm, furnace bottom flatness.
In above-mentioned step five, before headwall is installed, at the headwall back side in engineering workshop section steel reinforcement;After headwall is erected, Dismantle reinforcing shaped steel, rain-proof is costed with tarpaulin.
In above-mentioned step six, reinforcing shaped steel is fixed per a piece of burst inside wall two ends bolt, and in inside wall point Weld hanger on the burst channel-section steel at piece two ends, the scaffold around body of heater stays a breach, the indentation, there along short transverse station people, When body of heater burst hangs in the indentation, there, the workman for standing in this place dismantles the bolt on shaped steel, and reinforcing utilizes another with shaped steel Loop wheel machine falls to walk to remove another inside wall of reinforcing.
In above-mentioned step six, described reinforcing uses HW300X300 shaped steel with shaped steel.
In above-mentioned step eight, after opposite side headwall is installed in place, each face furnace wall is adjusted, it is vertical to fall detection furnace wall with line Degree, it is ensured that furnace wall is vertical, every face furnace wall flatness≤3mm, furnace space diagonal difference≤4mm, body of heater height tolerance ± 2mm。
In above-mentioned step eight, after furnace wall is adjusted, joint face bolt is tightened, fasten cable wind rope.
In above-mentioned step ten six, when oil transfer line is installed, the reserved 50mm regulations surplus of oil transfer line, orientation is adjusted at the scene for the treatment of Afterwards, cut off according to actual conditions.
A kind of modular manufacturing method of heating furnace of the invention and the heating furnace manufactured with the method, by by heating furnace Modularization, by modules, radiation burst prefabrication after, then be transported to assembling place carry out basement process, lining, assembling, baking Stove, to flow module installation, chimney installation, Hydrostatic test, outer surface treatment, mark, give full play to the excellent of modular manufacturing Point, shortens the manufacturing cycle, reduces manufacturing cost, improves workmanship.
Brief description of the drawings
Fig. 1 is flow chart of the invention;
Fig. 2 is the structural representation of heating furnace of the present invention;
Fig. 3 is A portions enlarged drawing in Fig. 2;
Fig. 4 is the structural representation of main part (removing chimney) in Fig. 2;
Fig. 5 is B portions enlarged drawing in Fig. 4.
Specific embodiment
The present invention is described in further detail below in conjunction with accompanying drawing embodiment.
Figure grade explanation:Base 1, furnace chamber module 2, furnace bottom module 21, furnace roof module 22, inside wall 23, external wall 24, end Shaped steel 3 is connected between wall 25, radiation comb 26, inside wall, convection current cigarette is turned to flow module group 4, convection bank 41, oil transfer line 5, radiation Road 6, chimney 7, access hole 71, inspection platform 72, maintenance platform 81, ladder 82.
It is as shown in Figure 1 flow chart of the invention,
A kind of modular manufacturing method of heating furnace, comprises the following steps:
Step one, prefabrication:Modules, radiation burst prefabrication;
Step 2, basement process:Base is processed according to design drawing, after basic maintenance is qualified, to bearing on concrete pedestal Position carries out line setting-out, and then bearing is positioned on concrete pedestal;Each upper surface of support sets 4 groups of taper liner blocks to upper table Face carries out absolute altitude centering, and upper surface absolute altitude deviation control is in ± 1mm;
Step 3, radiation burst lining:The radiation burst of prefabrication is transported to assembling place, is placed in around body of heater, to removing The radiation burst that radiation turns outside convection pass carries out lining;Burst side wall should be placed on putting down that channel-section steel or H steel are set up during lining On platform, furnace bottom wouldn't lining, the independent lining of each burst of side wall;During lining, in addition to radiation turns convection pass, remaining body of heater burst Lining surrounding reserves 5mm gaps, and radiation turns convection pass with the reserved 100mm surpluses of the lining of side wall connecting place, to be irradiated turn Convection pass mends lining again after installing;
Step 4, furnace bottom are installed:Furnace bottom is lifted on bearing with unification 50 tons of truck cranes of platform again with 50 tons of crawler cranes, furnace bottom After lifting is in place, the control of furnace bottom installed height mark is checked in ± 1mm, furnace bottom flatness is controlled in≤3mm;Two furnace bottoms of furnace chamber are simultaneously Row are installed, and such as also need whole Transporting after heating furnace assembling, then needed before furnace bottom is installed, and pallet for transporting is installed on into furnace bottom steel knot On structure, pallet for transporting is lifted in place together with furnace bottom;
Step 5, side headwall are installed:Before headwall is installed, at the headwall back side in engineering workshop section steel reinforcement;With 50 tons of crawler belts The side headwall of two furnace chambers is hung in furnace bottom module by loop wheel machine respectively, headwall adjustment good position, with messenger wire fall method detect headwall with Furnace bottom perpendicularity, then fixes headwall with furnace bottom spot welding, and furnace wall outside sets cable wind rope and is fixed on using the hanger on headwall On ground anchor point, the setting of furnace wall inside cable wind rope, by way of the interim hanger of welding at headwall top and furnace roof interface, Set on the shackle plate that cable wind rope is fixed on furnace bottom, piecemeal joint face core drill is according to the bolt hole drill stove opened on headwall The bolt hole of bed die block, is then twisted bolt, and bolt need not be tightened, subsequently to carry out size adjusting to furnace chamber steel construction;End After wall is erected, reinforcing shaped steel of dismantling costs rain-proof with tarpaulin;
Shaped steel, inside wall boiler tube is connected between step 6, inside wall, inside wall to install:To be lifted per a piece of inside wall in place, install After fixation, the connection shaped steel between inside wall is installed in place, is then again installed in place the boiler tube in inside wall;Per a piece of burst Inside wall two ends bolt fixes reinforcing shaped steel (HW300X300 shaped steel), and on the burst channel-section steel inside wall burst two ends Welding hanger, the scaffold around body of heater stays a breach, and the indentation, there hangs in the breach along short transverse station people, body of heater burst During place, the workman for standing in this place dismantles the bolt on shaped steel, and reinforcing shaped steel falls using another loop wheel machine removes reinforcing Another inside wall;The setting of cable wind rope is with above-mentioned headwall;
Boiler tube should be noted when installing:
A. when boiler tube is installed, install successively from the bottom up, it should be noted that boiler tube can not touch lining, in case lining is broken;
B. during Tube sling, monolithic boiler tube is hung in into burner hearth, boiler tube is located between two boiler tube hooks, by burst boiler tube Gently shift two boiler tubes hook onto, adjust the distance of boiler tube length direction, loop wheel machine is come loose slowly;
C. boiler tube must be closely sturdy with boiler tube hook, and distance of the boiler tube away from liner surface is consistent, and furnace tube outer wall edge must be On one plumb line.
Step 7, external wall and external wall boiler tube are installed:By external wall lifting in place, install it is fixed after, then again will be outer Side wall boiler tube is installed in place;
Step 8, opposite side headwall are installed:The opposite side headwall of two furnace chambers is hung in into installation, setting cable wind rope be (cable wind rope Method to set up is with above-mentioned headwall);After opposite side headwall is installed in place, each face furnace wall is adjusted, detection furnace wall perpendicularity is fallen with line, protected Card furnace wall is vertical, every face furnace wall flatness≤3mm, furnace space diagonal difference≤4mm, body of heater height tolerance ± 2mm, furnace wall After adjusting, joint face bolt is tightened, fasten cable wind rope;
Step 9, furnace roof module are installed:When furnace roof module is installed, using the tube type lifting eye set on vertical shaft, lifting in place, is adjusted After good position, it is welded at joint face, with core drill according on the bolt hole drill side wall opened of furnace roof module, headwall on interface Bolt hole, tighten bolt;
Step 10, radiation comb welding heat treatment:After furnace roof is installed, you can carry out the weldering of connecting tube between radiation comb Connect;
Step 11, radiation turn convection pass installation:Radiation is turned into convection pass lifting in place, during installation, adjustment radiation turns right The angle steel flange circle at flow flue two ends, after position adjustment is good, angle steel flange is screwed on bolt, and weldering is sealed between interface, and radiation turns right Angle steel flange circle on flow flue is welded with wallboard;
Step 12, furnace bottom, radiation turn convection pass lining:Lining is carried out to furnace bottom, the fine blanket of pottery is clogged at burst face and with close Sealing is clung, while turning convection pass to radiation carries out benefit lining;
Step 13, baker:Furnace operation is carried out to heating furnace;
Step 14, to flow module install:After the lifting to flow module can be carried out after baker end-of-job, first will be right during lifting Stream mould one is lifted in place, and after adjustment good position, joint face tightens bolt, and convection current mould two, convection current mould three is similarly lifted successively;
Step 15, chimney are installed:After by chimney lifting in place, the lower end of chimney is connected with to flow module;
The welding heat treatment of step 10 six, oil transfer line:Carry out installation, the welding of oil transfer line;When oil transfer line is installed, oil transfer line is reserved 50mm adjusts surplus, after orientation is adjusted at scene, is cut off according to actual conditions;
Step 10 seven, to flow module auxiliary frame frame, ladder landing platform install:Bolt company is to flow module auxiliary frame frame and ladder landing platform Connect, auxiliary frame frame and body of heater junction are 2 pieces of connecting plates, scene core drill according to the perforate on auxiliary frame frame bolt hole drill stove Connecting plate on body, is then twisted bolt;
Step 10 eight, Hydrostatic test:Hydraulic pressure test is carried out according to water pressure test requirement;
The treatment of step 10 nine, outer surface, mark:Body of heater outer surface paints, identifies.
The assembling of heating furnace can be completed at project scene, if project scene does not possess assembling condition, it is also possible to overall After being completed, whole Transporting to project scene.For example, run in early stage, in order to cost-effective, can be assembled on harbour Afterwards, overall shipment is transported to destination.
As shown in Figures 2 to 5,
A kind of heating furnace of the modular manufacturing method manufacture of heating furnace, includes base 1, and two are arranged at intervals with base 1 Furnace chamber module 2, connects between inside wall is provided between two inside walls of furnace chamber module 2 and shaped steel 3 is connected between shaped steel 3, inside wall Top be provided with to flow module group 4, furnace chamber module 2 and it is described turn convection pass 6 to being provided with radiation between flow module group 4, To being connected with chimney 7 in flow module group 4;Furnace chamber module 2 by furnace bottom module 21, furnace roof module 22, inside wall 23, external wall 24 with And both sides headwall 25 is constituted and closes furnace chamber, and radiation comb 26 is provided with the inner surface of inside wall 23 and external wall 24;Convection current mould Convection bank 41 is provided with block group 4, is connected by oil transfer line 5 between convection bank 41 and the radiation comb 26;Furnace chamber Maintenance platform 81 and ladder 82 are provided with outside module 2, to flow module group 4 by first pair of flow module, second pair of flow module and the Three pairs of flow module compositions.
Radiation comb 26 is in continuous S-shaped structure setting;Access hole 71 is provided with chimney 7, the periphery of chimney 7 is provided with inspection Equating platform 72.
Highly preferred embodiment of the present invention has been illustrated, and the various change or remodeling made by those of ordinary skill in the art are not Can depart from the scope of the present invention.

Claims (10)

1. a kind of modular manufacturing method of heating furnace, it is characterized in that:Comprise the following steps:
Step one, prefabrication:Modules, radiation burst prefabrication;
Step 2, basement process:Base is processed according to design drawing, after basic maintenance is qualified, to bearing on concrete pedestal Position carries out line setting-out, and then bearing is positioned on concrete pedestal;
Step 3, radiation burst lining:The radiation burst of prefabrication is transported to assembling place, is placed in around body of heater, to removing The radiation burst that radiation turns outside convection pass carries out lining;
Step 4, furnace bottom are installed:Furnace bottom is lifted on bearing, after furnace bottom lifting is in place, furnace bottom installed height mark is checked and is put down Face degree;
Step 5, side headwall are installed:The side headwall of two furnace chambers is hung in into furnace bottom module respectively, headwall adjusts good position, Method being fallen with messenger wire and detecting headwall and furnace bottom perpendicularity, then headwall is fixed with furnace bottom spot welding, furnace wall outside is using on headwall Hanger sets cable wind rope and is fixed on ground anchor point, the setting of furnace wall inside cable wind rope, by headwall top and furnace roof interface The mode of the interim hanger of place's welding, is set on the shackle plate that cable wind rope is fixed on furnace bottom, piecemeal joint face core drill according to The bolt hole of the bolt hole drill furnace bottom module opened on headwall, is then twisted bolt, and bolt need not be tightened, so as to subsequently to furnace chamber Steel construction carries out size adjusting;
Shaped steel, inside wall boiler tube is connected between step 6, inside wall, inside wall to install:To be lifted per a piece of inside wall in place, install After fixation, the connection shaped steel between inside wall is installed in place, is then again installed in place the boiler tube in inside wall;
Step 7, external wall and external wall boiler tube are installed:By external wall lifting in place, install it is fixed after, then again by external wall Boiler tube is installed in place;
Step 8, opposite side headwall are installed:The opposite side headwall of two furnace chambers is hung in into installation, cable wind rope is set;
Step 9, furnace roof module are installed:When furnace roof module is installed, using the tube type lifting eye set on vertical shaft, lifting in place, is adjusted After good position, it is welded at joint face, with core drill according on the bolt hole drill side wall opened of furnace roof module, headwall on interface Bolt hole, tighten bolt;
Step 10, radiation comb welding heat treatment:After furnace roof is installed, you can carry out the weldering of connecting tube between radiation comb Connect;
Step 11, radiation turn convection pass installation:Radiation is turned into convection pass lifting in place, during installation, adjustment radiation turns right The angle steel flange circle at flow flue two ends, after position adjustment is good, angle steel flange is screwed on bolt, and weldering is sealed between interface, and radiation turns right Angle steel flange circle on flow flue is welded with wallboard;
Step 12, furnace bottom, radiation turn convection pass lining:Lining is carried out to furnace bottom, the fine blanket of pottery is clogged at burst face and with close Sealing is clung, while turning convection pass to radiation carries out benefit lining;
Step 13, baker:Furnace operation is carried out to heating furnace;
Step 14, to flow module install:After the lifting to flow module can be carried out after baker end-of-job, first will be right during lifting Stream mould one is lifted in place, and after adjustment good position, joint face tightens bolt, and convection current mould two, convection current mould three is similarly lifted successively;
Step 15, chimney are installed:After by chimney lifting in place, the lower end of chimney is connected with to flow module;
The welding heat treatment of step 10 six, oil transfer line:Carry out installation, the welding of oil transfer line;
Step 10 seven, to flow module auxiliary frame frame, ladder landing platform install:Bolt company is to flow module auxiliary frame frame and ladder landing platform Connect, auxiliary frame frame and body of heater junction are 2 pieces of connecting plates, scene core drill according to the perforate on auxiliary frame frame bolt hole drill stove Connecting plate on body, is then twisted bolt;
Step 10 eight, Hydrostatic test:Hydraulic pressure test is carried out according to water pressure test requirement;
The treatment of step 10 nine, outer surface, mark:Body of heater outer surface paints, identifies.
2. the modular manufacturing method of a kind of heating furnace according to claim 1, it is characterized in that:In described step two, Each upper surface of support sets 4 groups of taper liner blocks and absolute altitude centering is carried out to upper surface, and upper surface absolute altitude deviation control is in ± 1mm.
3. the modular manufacturing method of a kind of heating furnace according to claim 2, it is characterized in that:In described step three, During lining, in addition to radiation turns convection pass, remaining body of heater burst lining surrounding reserves 5mm gaps;Radiation turn convection pass with The reserved 100mm surpluses of the lining of side wall connecting place, it is to be irradiated to turn to mend lining again after convection pass is installed.
4. the modular manufacturing method of a kind of heating furnace according to claim 3, it is characterized in that:In described step four, The control of furnace bottom installed height mark is controlled in≤3mm in ± 1mm, furnace bottom flatness.
5. the modular manufacturing method of a kind of heating furnace according to claim 4, it is characterized in that:In described step five, Before headwall is installed, at the headwall back side in engineering workshop section steel reinforcement;After headwall is erected, reinforcing shaped steel of dismantling is taken with tarpaulin Upper rain-proof.
6. the modular manufacturing method of a kind of heating furnace according to claim 5, it is characterized in that:In described step six, Reinforcing shaped steel is fixed per a piece of burst inside wall two ends bolt, and is welded on the burst channel-section steel inside wall burst two ends and is hung Ear, the scaffold around body of heater stays a breach, the indentation, there along short transverse station people, when body of heater burst hangs in the indentation, there, The workman for standing in this place dismantles the bolt on shaped steel, and reinforcing shaped steel falls to walk to remove another of reinforcing using another loop wheel machine Inside wall.
7. the modular manufacturing method of a kind of heating furnace according to claim 6, it is characterized in that:In described step eight, After opposite side headwall is installed in place, each face furnace wall is adjusted, detection furnace wall perpendicularity is fallen with line, it is ensured that furnace wall is vertical, per face furnace wall Flatness≤3mm, furnace space diagonal difference≤4mm, body of heater height tolerance ± 2mm.
8. the modular manufacturing method of a kind of heating furnace according to claim 7, it is characterized in that:In described step eight, After furnace wall is adjusted, joint face bolt is tightened, fasten cable wind rope.
9. the modular manufacturing method of a kind of heating furnace according to claim 8, it is characterized in that:Described step ten six In, when oil transfer line is installed, the reserved 50mm regulations surplus of oil transfer line after orientation is adjusted at scene, cuts off according to actual conditions.
10. the heating furnace that a kind of modular manufacturing method of heating furnace according to claim 1 is manufactured, it is characterized in that:Bag Base (1) is included, two furnace chamber modules (2), two inside walls of furnace chamber module (2) have been arranged at intervals with described base (1) Between be provided between inside wall to connect to be connected between shaped steel (3), described inside wall and be provided with to flow module group above shaped steel (3) (4) it is provided with radiation between, described furnace chamber module (2) and (4) to flow module group and turns convection pass (6), described is right Chimney (7) is connected with flow module group (4);Described furnace chamber module (2) is by furnace bottom module (21), furnace roof module (22), inner side Wall (23), external wall (24) and both sides headwall (25) constitute closing furnace chamber, described inside wall (23) and external wall (24) Radiation comb (26) is provided with inner surface;It is described to being provided with convection bank (41), described convection current in flow module group (4) It is connected by oil transfer line (5) between tube bank (41) and radiation comb (26);Dimension is provided with outside described furnace chamber module (2) Shield platform (81) and ladder (82), it is described to flow module group (4) by first pair of flow module, second pair of flow module and the 3rd pair Flow module is constituted.
CN201710158036.6A 2017-03-16 2017-03-16 A kind of modular manufacturing method of heating furnace and the heating furnace manufactured with the method Pending CN106839775A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710158036.6A CN106839775A (en) 2017-03-16 2017-03-16 A kind of modular manufacturing method of heating furnace and the heating furnace manufactured with the method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710158036.6A CN106839775A (en) 2017-03-16 2017-03-16 A kind of modular manufacturing method of heating furnace and the heating furnace manufactured with the method

Publications (1)

Publication Number Publication Date
CN106839775A true CN106839775A (en) 2017-06-13

Family

ID=59145156

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710158036.6A Pending CN106839775A (en) 2017-03-16 2017-03-16 A kind of modular manufacturing method of heating furnace and the heating furnace manufactured with the method

Country Status (1)

Country Link
CN (1) CN106839775A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107201829A (en) * 2017-07-07 2017-09-26 中化二建集团有限公司 Large tubular drying machine coal chute beam rotary type installs construction method
CN107829560A (en) * 2017-10-30 2018-03-23 中国三冶集团有限公司 A kind of flue top plate rapid constructing method
CN108356520A (en) * 2018-04-09 2018-08-03 宁波连通设备集团有限公司 Atmospheric pressure kiln manufacturing process and the atmospheric pressure kiln manufactured with the technique
CN109022657A (en) * 2018-08-09 2018-12-18 上海二十冶建设有限公司 The installation method of dry-off oven device for blast furnace under a kind of restricted clearance
CN109207699A (en) * 2018-09-12 2019-01-15 中国二十冶集团有限公司 Annealing furnace shell modularization installation method
CN109764688A (en) * 2019-01-18 2019-05-17 彭志坚 A kind of cylinder-shaped vertical cooling equipment of outer furnace of modularization furnace
CN112320596A (en) * 2020-11-06 2021-02-05 中国成达工程有限公司 Rapid installation method of horizontal furnace tube
CN113513921A (en) * 2020-04-09 2021-10-19 中国石化工程建设有限公司 Industrial furnace radiation section modular construction method
CN115306163A (en) * 2022-09-14 2022-11-08 中化二建集团有限公司 Modularized construction method for tubular heating furnace in petrochemical engineering

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0143697A2 (en) * 1983-11-16 1985-06-05 B T U Engineering Corporation Modular V-CVD diffusion furnace
CN105486086A (en) * 2015-12-29 2016-04-13 茂名重力石化机械制造有限公司 Heating furnace with module liner

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0143697A2 (en) * 1983-11-16 1985-06-05 B T U Engineering Corporation Modular V-CVD diffusion furnace
CN105486086A (en) * 2015-12-29 2016-04-13 茂名重力石化机械制造有限公司 Heating furnace with module liner

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘国辉等: "基于加热炉模块化安装技术研究", 《价值工程》 *
吴亦挥: "加热炉模块化施工技术在石化装置中的应用", 《化工装备技术》 *
陈孙艺: "大型圆筒加热炉模块的异地安装技术", 《化工与医药工程》 *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107201829A (en) * 2017-07-07 2017-09-26 中化二建集团有限公司 Large tubular drying machine coal chute beam rotary type installs construction method
CN107829560A (en) * 2017-10-30 2018-03-23 中国三冶集团有限公司 A kind of flue top plate rapid constructing method
CN108356520B (en) * 2018-04-09 2020-04-07 宁波连通设备集团有限公司 Manufacturing process of normal pressure heating furnace and normal pressure heating furnace manufactured by same
CN108356520A (en) * 2018-04-09 2018-08-03 宁波连通设备集团有限公司 Atmospheric pressure kiln manufacturing process and the atmospheric pressure kiln manufactured with the technique
CN109022657A (en) * 2018-08-09 2018-12-18 上海二十冶建设有限公司 The installation method of dry-off oven device for blast furnace under a kind of restricted clearance
CN109207699A (en) * 2018-09-12 2019-01-15 中国二十冶集团有限公司 Annealing furnace shell modularization installation method
CN109764688A (en) * 2019-01-18 2019-05-17 彭志坚 A kind of cylinder-shaped vertical cooling equipment of outer furnace of modularization furnace
CN109764688B (en) * 2019-01-18 2020-08-25 彭志坚 Cylindrical vertical cooling equipment for outer furnace of modular furnace
CN113513921A (en) * 2020-04-09 2021-10-19 中国石化工程建设有限公司 Industrial furnace radiation section modular construction method
CN113513921B (en) * 2020-04-09 2023-05-30 中国石化工程建设有限公司 Modularized construction method for radiation section of industrial furnace
CN112320596A (en) * 2020-11-06 2021-02-05 中国成达工程有限公司 Rapid installation method of horizontal furnace tube
CN112320596B (en) * 2020-11-06 2022-06-07 中国成达工程有限公司 Rapid installation method of horizontal furnace tube
CN115306163A (en) * 2022-09-14 2022-11-08 中化二建集团有限公司 Modularized construction method for tubular heating furnace in petrochemical engineering

Similar Documents

Publication Publication Date Title
CN106839775A (en) A kind of modular manufacturing method of heating furnace and the heating furnace manufactured with the method
WO2017219920A1 (en) Building based on large-space structure body and freestanding type external envelope structure, and construction method
CN101435276B (en) Cabin top steel beam hydraulic hoisting and positioning apparatus of cylinder cabin structure building and construction method thereof
CN206233576U (en) For the hydraulic pressure lift turnover formwork construction device of bundled-tube structure chimney
CN102235107B (en) Hydraulic lifting construction method for chimney steel inner cylinder
CN114232805B (en) Construction method of ultrahigh-height large-span steel concrete beam hanging structure
CN104976894A (en) Integral modular structure of industrial furnace and construction method
CN206616184U (en) Coke oven loss flue dust dust gathering arrester supporting construction
CN104674665A (en) Installation method for corridor bridge of large space steel structure
CN203654702U (en) Operating platform for construction of reinforced concrete chimney
CN113265952A (en) Hoisting method for integral prefabrication of steel cover beam
CN110159057B (en) Mounting and construction method for smoke pipe of technically improved factory building
CN108914963A (en) Assembled arcading barricade
CN206540421U (en) A kind of heating furnace with integral module structure
CN208415293U (en) Integral prefabricated assembled main transformer foundation for indoor substation
CN114109123A (en) Construction method of chimney barrel body
CN110616706B (en) Construction method for layering binding in large-diameter pile foundation reinforcing steel bar hole
CN103727791A (en) Modular structure of radiation section of industrial furnace
CN101831916B (en) Method for mounting large-size sleeve bolt framework in combined type
CN107487713B (en) integral combination hoisting and positioning process for upper part of water behind pi-shaped boiler
CN205119788U (en) Assembled tunnel cave
CN100489410C (en) Technique for inner lining construction for unopened hot-blast stove furnace jacket
CN110878589A (en) Electric lifting reverse construction method for absorption tower
CN112171183B (en) Narrow space steel funnel assembling construction method based on three-dimensional model
CN210598373U (en) Chimney steel inner tube installing the system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170613

RJ01 Rejection of invention patent application after publication