JP4225399B2 - Waste treatment facility - Google Patents
Waste treatment facility Download PDFInfo
- Publication number
- JP4225399B2 JP4225399B2 JP2001150374A JP2001150374A JP4225399B2 JP 4225399 B2 JP4225399 B2 JP 4225399B2 JP 2001150374 A JP2001150374 A JP 2001150374A JP 2001150374 A JP2001150374 A JP 2001150374A JP 4225399 B2 JP4225399 B2 JP 4225399B2
- Authority
- JP
- Japan
- Prior art keywords
- waste
- facility
- shaft
- incineration
- platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Processing Of Solid Wastes (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、一般廃棄物等を焼却など処理するための施設に関するものである。
【0002】
【従来の技術】
企業や一般家庭から出される一般廃棄物のうち、可燃物については、清掃工場で焼却処理が行われており、従来、かかる処理施設は地上式のもので、例えば都市内および郊外等に広大に敷地を確保し、図4に示すようにここの地上部にごみ焼却場となる建屋50を構築し、建屋50の内部にごみの受入供給設備、焼却炉またはガス化溶融炉を使用した焼却処理設備、排ガス処理設備などのその他の設備を設置している。そして、進入路51から廃棄物を搬入し、建屋50内の設備で焼却などの処理後、灰およびスラグ等の焼却処理残渣を搬出路52から搬出している。
【0003】
ところで、近年、ごみの排出量が増加し、ごみ対策が緊急かつ重要な課題になっている。しかし、従来型の地上式のごみ焼却場では、ある程度のまとまった広さの用地が必要であるため、市街地周辺ではその確保が困難である。
【0004】
また、大気汚染、臭気などによる環境の悪化、ごみ収集車の通行による交通問題、景観などの周辺環境の悪化などの問題があり、建設に対する周辺住民の理解が十分に得にくく、焼却などの処理施設の建設が困難な場合が多い。
【0005】
そこで、市街地から離れた丘陵地・山岳地に焼却場を建設するようになってきているが、この場合、建設地用の平坦部を造成するために大規模な法面が出現し、景観への影響や地上部の改変による生態系への影響が懸念される。
【0006】
かかる不都合を解消し、焼却などの処理施設の設置のための用地確保が従来に比べ容易で、周囲の環境、景観に及ぼす影響がほとんどない廃棄物処理施設として、従来周知の例えば地下発電所、トンネル、地下石油備蓄施設などを建設する際に用いている技術を採用して、山岳部の地下に大空洞を掘削し、ここに焼却などの処理設備を設置する施設が先に提案されている。
【0007】
図5はその一例を示し、特開平7-116627号公報にも記載のように、横坑式のもので、斜面の地形を利用し、水平に掘削した横坑式の進入路51に続けてプラットホーム54、ごみピット55と焼却炉等の機械設備56を収容する複数の横坑式地下空洞53を設け、それらを連絡トンネル60で結ぶ構造であり、横坑式地下空洞53には排気ならびに換気立坑57と連絡立坑58が連続して構築される。
【0008】
図6は他の例を示し、特開平9-196331号公報にも記載のように、立坑式のもので、斜面の地形を利用し、進入路51、プラットホーム54、ごみピット55の地下空洞と、焼却炉ならびにガス化溶融炉などの機械設備を配設する立坑59を設け、それらを連絡トンネル60で結ぶ構造となっている。
【0009】
そして、横坑式、立坑式ともに、管理施設や外気を利用して熱交換を行う冷却塔、蒸気復水器などの設備等を地上ならびに地上レベルに設置している。これにより、地上部の必要面積・改変範囲を小さくできる。
【0010】
【発明が解決しようとする課題】
地下に大空洞を掘削する方法では、土砂地盤では建設が困難であり、硬岩または軟岩地盤が適しており、建設可能な地盤が制限される。そして、硬岩地盤の場合は、吹き付けコンクリート・ロックボルト程度の支保で足りるが、軟岩地盤の場合は覆工コンクリート等さらに支保を増強する必要があり、空洞方式としての施工性がよくない。
【0011】
また、横坑式の場合は、地下空洞の土被りは目安として20m以上、空洞相互の離れも空洞幅の2倍以上必要であり、地下における所要面積が地上建屋式に比較してかなり大きいものを要する。建設コストも地上建屋式に比較して少なくとも同等以上となる。
【0012】
立坑式の場合は、焼却炉などの機械設備を立坑内に設置するため、横坑式に比較して地下における所要面積は小さくなるが、地上式に比較して建設コストは横坑式と同じように少なくとも同等以上となる。
【0013】
また、機械配置の制約から、プラットホーム54のレベルと立坑上部平坦部分3の高度差が30m程度要し、この高度差を確保できないと、プラットホーム54への進入路が長くなってしまったり、ごみピットから立坑内の焼却炉への搬送コンベアに傾斜がついてしまうなどの不都合が生じる。このため、プラットホームレベルと立坑上部平坦部の高度差を30m程度確保できることが立地条件となり、地形的制約がある。
【0014】
本発明の目的は前記従来例の不都合を解消し、地上部の必要面積・改変範囲を小さくできるという地下式の特性を活かしつつ、建設コスト低減を図ることができ、立坑式の場合のようにプラットホームレベルと立坑上部平坦部との間に所要の高度差を確保する必要もなく立地可能な場所を増大できる廃棄物処理施設を提供することにある。
【0015】
【課題を解決するための手段】
本発明は前記目的を達成するため、地表を開削工法により掘削して形成した開削部と、該開削部の底部から下方に並行させて掘削した立坑とで、廃棄物処理設備を設置する空間を形成し、前記開削部に、受入供給設備として、進入路に続く箇所にプラットホームを設け、このプラットホームの直下にごみピットを設け、受入供給設備の両側に焼却処理設備として、ごみピットに接する箇所にごみホッパを配設し、該ごみホッパの出口に焼却炉を配置し、前記開削部の下方に連続して構築された立坑内には、焼却炉の下方に位置させて、焼却以降の工程であるガス冷却・排ガス処理工程の設備を配設し、立坑内に配置したこれらガス冷却・排ガス処理工程の設備は連絡通路で連絡することを要旨とするものである。
【0016】
請求項1記載の本発明によれば、廃棄物処理施設の上部分は開削式で、その下方部分を立坑式とし、開削式と立坑式との組合せとしたので横坑式や従来型の立坑式の場合に比較して建設コストを低減できる。また、平面形状としての所要面積を小さくでき、地上部の必要面積・改変範囲も地上式に比較して必要最小限に止めることができるから、周囲の環境、景観に及ぼす影響を小さくできる。
【0017】
そして、所要容積の大きい設備である受入供給設備や焼却処理設備とを開削部に設置でき、それ以外の設備をその下方の地下空間である立坑内に配置でき、立坑の上部に開削部が位置することにより、施設全体を立坑式とした場合のように受入供給設備であるプラットホームレベルと立坑上部平坦部との間に所要の高度差を確保する必要もなく立地可能な場所を増大できる。
【0018】
【発明の実施の形態】
以下、図面について本発明の実施の形態を詳細に説明する。図1は本発明の廃棄物処理施設の実施形態を示す説明図で、本発明の概略から説明する。本発明は地表、すなわち地形の平坦部分3を開削工法により掘削して開削部1を形成し、該開削部1に続けてその底部から下方を掘削して立坑2を形成し、この開削部1と立坑2とで廃棄物処理設備を設置するのに必要な地下空間を形成する。
【0019】
そして、開削部1には所要容積の大きい設備である受入供給設備と焼却処理設備等を設置し、立坑2内にはガス冷却・排ガス処理設備などの設備を設置する。また、開削部1に設置する設備の上部は地上に突出し、ここには管理室19などを設ける。
【0020】
図2は、本発明をストーカ式焼却システムに実施した各種設備の配置例を示し、図示の例では開削部1の底部から2つの立坑2を並行させて掘削し、開削部1には、廃棄物の受入供給設備として、進入路51に続く箇所にプラットホーム4を設け、このプラットホーム4の直下にごみピット5を設ける。図中6は水平に横移動するごみクレーンを示す。
【0021】
かかる受入供給設備の両側に焼却処理設備を配置する。この焼却処理設備は、ごみピット5に接する箇所にごみホッパ7を配設し、該ごみホッパ7の出口にストーカ式焼却炉8を配置する。図中9はストーカ式焼却炉8の上方に設置したボイラで、下方には落じんコンベア10、灰押出機11を配設し、落じんコンベア10の側方でごみピット5の側に灰クレーン12を配置した。
【0022】
立坑2が2つあることから、ごみピット5の下方両側に配設されることになった灰クレーン12は、灰出しコンベア連絡トンネル13で連絡する。
【0023】
前記ストーカ式焼却炉8の外側にエコノマイザ14を設置する。
【0024】
以上のようにして受入供給設備と焼却処理設備とを開削部1に設置する。そして、ストーカ式焼却炉8の上方には各種機器の室として、プラットホーム4に並べて中央制御室15、電気室16、蒸気タービン発電機室17、脱臭装置室18などを設置し、中央制御室15、電気室16の上部に管理室19を設ける。
【0025】
開削部1の下方に連続して構築された立坑2内には、ストーカ式焼却炉8の下方に位置させて、焼却以降の工程であるガス冷却・排ガス処理工程の設備を配設する。具体的には例えば、ガス冷却塔(減温塔)20、集塵器(バグフィルタ)21、誘引送風機22などの設備からなり、2つの立坑2内に配置したこれらガス冷却・排ガス処理工程の設備は連絡通路23で連絡する。これにより、従来の地上式ではストーカ式焼却炉8と同一の平面レベルに配置されていたガス冷却・排ガス処理工程の設備を、ストーカ式焼却炉8の下方に立体的に配置することができ、平面形状としての所要面積が小さくなる。
【0026】
なお、蒸気復水器は外気を利用して熱交換を行うため、屋外に露出して設置する。
【0027】
かかる施設を利用して廃棄物を焼却処理するには、ごみを積載した清掃車は進入路51からプラットホーム4に進入し、投入扉からシュート部を経由してプラットホーム4の真下のごみピット5内に投入する。このとき、ごみピット5内に落下するごみは、落差が大きいので自然に攪拌作用が生じる。
【0028】
ごみピット5内に投入されたごみはごみクレーン6で掴まれて、ごみホッパ7に直接投入され、ここからストーカ式焼却炉8に送りだされて焼却される。焼却灰はごみピット5の横の灰ピット(図示は省略した)に貯留し、コンベアで移送し、プラットホーム4の横の灰出スペース(図示は省略した)から搬出する。一方、飛灰は立坑2内をコンベアで移送して、これも灰出スペースから搬出する。
【0029】
また、灰溶融設備を進入路51の横に設置し、焼却灰や飛灰を溶融し、生成されたスラグおよび処理灰固化物を搬出する。
【0030】
なお、焼却の際に発生する排ガスは、処理後に立坑2の最下部から誘引送風機22で煙道を経由して地上に立つ煙突に送られる。
【0031】
図3は本発明を焼却システムの1形態例である流動床式ガス化溶融システムを用い、2系列構成とした場合の各種設備の配置例を示し、基本構成は図2に示したストーカ式焼却システムの場合と同様であり、図示の例では開削部1の底部から2つの立坑2を並行させて掘削し、開削部1に、所要容積の大きい廃棄物の受入供給設備と、流動床式ガス化溶融方式を用いた焼却処理設備等を配設し、立坑2内にはその他の設備を配設する。
【0032】
廃棄物の受入供給設備は進入路51に続く箇所にプラットホーム4、該プラットホーム4に設置されたごみ投入扉25、ごみシュート部24、ごみピット5、ごみクレーン6、ごみホッパ7等から構成され、ごみはこの順で受け入れられ焼却設備に供給される。
【0033】
かかる受入供給設備の両側に焼却の処理設備を配置する。この焼却処理設備は、ごみホッパ7の下流のガス化炉26、溶融炉27、該溶融炉27の下流の廃熱ボイラ28、押込送風機を設置したファン室29などから構成される。
【0034】
以上のようにして受入供給設備と焼却処理設備とを開削部1に設置し、該受入供給設備と焼却処理設備の上方には各種機器等の室として、中央制御室15、電気室32、ボイラー機械室33、脱臭装置室18、薬品受入室34、換気ファン室35などを設置し、電気室32、換気ファン室35、プラットホーム4の上部に管理室19を設ける。
【0035】
開削部1の下方に連続して構築された2つの立坑2内には、焼却などの処理以降の工程であるガス冷却・排ガス処理工程の設備を配設する。具体的には例えば、ガス冷却設備としてガス式空気加熱器36、エコノマイザ14、ガス冷却塔(減温塔)20、排ガス処理設備として集塵器(バグフィルタ)21、触媒反応装置37、誘引送風機22などを設置する。2つの立坑2は連絡通路23で連絡される。これにより、従来の地上式では溶融炉27と同一の平面レベルに配置されていたガス冷却・排ガス処理工程の設備を、焼却処理設備が設置される開削部の下方の立坑2内の複数階に立体的に配置することができ、平面形状としての所要面積が小さくなる。
【0036】
なお、蒸気復水器38は外気を利用して熱交換を行うため、熱交換により加熱された該外気が直接大気へ排出可能なよう最上部に露出して設置する。
【0037】
図中39は、焼却処理施設内で発生したプラント排水を処理するための排水処理室を示す。
【0038】
かかる施設を利用して廃棄物を焼却処理するには、ごみを積載した清掃車は進入路51からプラットホーム4に進入し、ごみ投入扉25からごみシュート部24を経由してプラットホーム4の真下のごみピット5内に投入する。このとき、ごみピット5内に落下するごみは、落差が大きいので自然に攪拌作用が生じる。
【0039】
ごみピット5内に投入されたごみはごみクレーン6で掴まれて、ごみホッパ7に直接投入され、ここからガス化炉26に送りだされてごみがガス化され、下流の溶融炉27に送られ、該溶融炉27内で1300℃ないし1500℃で高温燃焼され、可燃分は焼却され灰分は溶融スラグ化される。ガス化炉26下から排出される炉下残渣、溶融炉27から排出されるスラグは、図示しない煙道コンベアシャフトに敷設されたコンベアを通じて地表近くに設置された不燃物処理設備(図示せず)に送られ、鉄分、アルミニウム分を選別回収する。
【0040】
集塵器(バグフィルタ)21で捕集される飛灰は、立坑2内を空気輸送により移送し、飛灰処理設備で薬剤処理する。最終的に排出されるスラグ・鉄分・アルミニウム分・処理灰はプラットホーム4の階に設けられた灰出スペースに設置されたバンカで一時貯留し、搬出入トンネルから搬出する。
【0041】
なお、焼却処理の際に発生する排ガスは、処理後に立坑2の最下部から誘引送風機22で煙道を経由して地上に立つ煙突(図示せず)に送られる。
【0042】
図7は本発明の他の実施形態を示し、開削部1の上部の一部または大部分に盛土などを施工し、この盛土部61を公園または駐車場などに利用することもできる。なお、前記した設備の配置例は一例であり、これに限定されるものではない。
【0043】
【発明の効果】
以上述べたように本発明の廃棄物処理施設は、周囲の景観や生態系に与える影響を小さくでき、地上部の必要面積・改変範囲を小さくできるという地下式の特性を活かしつつ、これに地上式を組み合わせることにより建設コスト低減を図ることができ、従来型の立坑式のみの場合のようにプラットホームレベルと立坑上部平坦部との間に所要の高度差を確保する必要もなく立地可能な場所を増大できるものである。
【図面の簡単な説明】
【図1】 本発明の廃棄物処理施設の実施の形態を示す説明図である。
【図2】 本発明の廃棄物処理施設をストーカ式焼却システムに実施した場合の縦断正面図である。
【図3】 本発明の廃棄物処理施設を流動床式ガス化溶融システムに実施した場合の縦断正面図である。
【図4】 地上建屋式の廃棄物処理施設の説明図である。
【図5】 横坑式の廃棄物処理施設の説明図である。
【図6】 立坑式の廃棄物処理施設の説明図である。
【図7】 本発明の廃棄物処理施設の他の実施の形態を示す説明図である。
【符号の説明】
1…開削部 2…立坑
3…平坦部分 4…プラットホーム
5…ごみピット 6…ごみクレーン
7…ごみホッパ 8…ストーカ式焼却炉
9…ボイラ 10…落じんコンベア
11…灰押出機 12…灰クレーン
13…灰出しコンベア連絡トンネル 14…エコノマイザ
15…中央制御室 16…電気室
17…蒸気タービン発電気室 18…脱臭装置室
19…管理室 20…ガス冷却塔(減温塔)
21…集塵器(バグフィルタ) 22…誘引送風機
23…連絡通路 24…ごみシュート部
25…ごみ投入扉 26…ガス化炉
27…溶融炉 28…廃熱ボイラ
29…ファン室 32…電気室
33…ボイラー機械室 34…薬品受入室
35…換気ファン室 36…ガス式空気加熱器
37…触媒反応装置 38…蒸気復水器
39…排水処理室 50…建屋
51…進入路 52…搬出路
53…横坑式地下空洞 54…プラットホーム
55…ごみピット 56…機械設備
57…排気ならびに換気立坑 58…連絡立坑
59…立坑 60…連絡トンネル
61…盛土部[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a facility for treating general waste or the like by incineration.
[0002]
[Prior art]
Of the general waste generated by companies and households, combustible materials are incinerated at a wastewater treatment plant. Conventionally, such treatment facilities are ground-based, and are widely used in cities and suburbs, for example. As shown in Fig. 4, a
[0003]
By the way, in recent years, the amount of waste discharged has increased, and countermeasures for waste have become an urgent and important issue. However, a conventional ground-type waste incineration site requires a certain amount of land, so it is difficult to secure it around urban areas.
[0004]
In addition, there are problems such as environmental degradation due to air pollution and odor, traffic problems due to the passage of garbage trucks, deterioration of the surrounding environment such as landscapes, etc. It is often difficult to construct facilities.
[0005]
Therefore, incineration sites are being constructed in hilly and mountainous areas that are far from the city, but in this case, a large slope appears to create a flat part for the construction site, leading to the landscape. There are concerns about the impact on the ecosystem due to the impact of the above and the modification of the above-ground part.
[0006]
As a waste treatment facility that eliminates such inconvenience and is easy to secure land for the installation of treatment facilities such as incineration compared to the past and has little effect on the surrounding environment and landscape, a well-known underground power plant, for example, A facility that uses technology used when constructing tunnels, underground oil storage facilities, etc., excavating a large cavity in the basement of a mountainous area and installing treatment equipment such as incineration there has been proposed previously. .
[0007]
FIG. 5 shows an example of this. As described in Japanese Patent Application Laid-Open No. 71-162727, it is of a horizontal shaft type, and uses a slope topography and continues to a horizontal shaft
[0008]
FIG. 6 shows another example, as described in Japanese Patent Laid-Open No. 9-196331, which is of a vertical shaft type, using the topography of the slope, and the underground cavities of the
[0009]
In both the horizontal shaft type and the vertical shaft type, facilities such as a management facility, a cooling tower that performs heat exchange using outside air, and a steam condenser are installed on the ground and on the ground level. Thereby, the required area and modification range of the above-ground part can be made small.
[0010]
[Problems to be solved by the invention]
In the method of excavating a large cavity underground, construction is difficult on earth and sand ground, hard rock or soft rock ground is suitable, and the ground that can be built is limited. In the case of hard rock ground, it is sufficient to support sprayed concrete and rock bolts. However, in the case of soft rock ground, it is necessary to further strengthen the support such as lining concrete, and the workability as a hollow system is not good.
[0011]
In addition, in the case of the horizontal shaft type, the earth covering of the underground cavities should be 20m or more as a guide, and the distance between the cavities should be more than twice the width of the cavities, and the required underground area is considerably larger than the above ground building type Cost. The construction cost is at least equal to or higher than the ground building type.
[0012]
In the case of the vertical shaft type, mechanical equipment such as an incinerator is installed in the vertical shaft, so the required underground area is smaller than that of the horizontal shaft type, but the construction cost is the same as that of the horizontal shaft type. As such, it will be at least equivalent.
[0013]
In addition, due to restrictions on machine layout, the difference in level between the level of the
[0014]
The object of the present invention is to solve the disadvantages of the conventional example, and to reduce the construction cost while taking advantage of the underground type characteristics that can reduce the required area and modification range of the above-ground part, as in the case of the vertical type It is an object of the present invention to provide a waste treatment facility that can increase the place where it can be located without having to secure a required height difference between the platform level and the vertical portion of the vertical shaft.
[0015]
[Means for Solving the Problems]
In order to achieve the above-mentioned object, the present invention provides a space for installing a waste treatment facility between an excavation part formed by excavating the ground surface by an excavation method and a vertical shaft excavated in parallel downward from the bottom of the excavation part. In the excavation part, a platform is provided as a receiving supply facility at a location following the approach path, a waste pit is provided immediately below the platform, and an incineration treatment facility is provided on both sides of the receiving supply facility at a location in contact with the waste pit. A waste hopper is disposed, an incinerator is disposed at the outlet of the waste hopper, and the shaft constructed continuously below the excavation part is positioned below the incinerator, and in the processes after incineration. The gist of the present invention is that a certain gas cooling / exhaust gas treatment process facility is arranged, and these gas cooling / exhaust gas treatment process facilities arranged in the shaft are communicated by a communication passage .
[0016]
According to the first aspect of the present invention, the upper part of the waste treatment facility is an open type, and the lower part is a vertical type, and a combination of an open type and a vertical type is employed. The construction cost can be reduced compared to the case of the formula. In addition, the required area as a planar shape can be reduced, and the required area and modification range of the above-ground part can be minimized as compared with the above-ground type, so that the influence on the surrounding environment and landscape can be reduced.
[0017]
And the receiving supply equipment and incineration processing equipment, which have large required capacity, can be installed in the excavation part, and other equipment can be placed in the shaft below the underground space, and the excavation part is located above the shaft. By doing so, the place which can be located can be increased without having to ensure a required altitude difference between the platform level which is the receiving and supplying equipment and the vertical portion of the vertical shaft as in the case where the entire facility is a vertical type.
[0018]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. FIG. 1 is an explanatory view showing an embodiment of the waste treatment facility of the present invention, which will be described from the outline of the present invention. In the present invention, the ground surface, that is, the
[0019]
The open-
[0020]
FIG. 2 shows an example of the arrangement of various facilities in which the present invention is implemented in a stoker type incineration system. In the illustrated example, two
[0021]
Incineration facilities are arranged on both sides of the receiving and supplying facility. In this incineration processing facility, a
[0022]
Since there are two
[0023]
An
[0024]
As described above, the receiving supply facility and the incineration processing facility are installed in the
[0025]
In the
[0026]
In addition, the steam condenser is exposed outside because it uses the outside air for heat exchange.
[0027]
In order to incinerate the waste using such facilities, the garbage truck loaded with garbage enters the platform 4 from the
[0028]
Garbage thrown into the
[0029]
In addition, an ash melting facility is installed beside the
[0030]
The exhaust gas generated during incineration is sent from the bottom of the
[0031]
FIG. 3 shows an example of the arrangement of various facilities when the present invention uses a fluidized bed gasification and melting system, which is one embodiment of the incineration system, and has a two-line configuration, and the basic configuration is the stoker type incineration shown in FIG. As in the case of the system, in the example shown in the figure, two
[0032]
The facility for receiving and supplying waste is composed of a platform 4 at a place following the
[0033]
Incineration processing facilities are arranged on both sides of the receiving and supplying facility. This incineration processing equipment includes a
[0034]
As described above, the receiving supply facility and the incineration processing facility are installed in the
[0035]
In the two
[0036]
Since the steam condenser 38 performs heat exchange using outside air, the steam condenser 38 is installed exposed at the top so that the outside air heated by heat exchange can be directly discharged to the atmosphere.
[0037]
39 in the figure indicates a waste water treatment chamber for treating plant waste water generated in the incineration treatment facility.
[0038]
In order to incinerate waste using such facilities, a garbage truck loaded with garbage enters the platform 4 from the
[0039]
Garbage thrown into the
[0040]
Fly ash collected by the dust collector (bag filter) 21 is transported through the
[0041]
The exhaust gas generated during the incineration process is sent from the bottom of the
[0042]
FIG. 7 shows another embodiment of the present invention, and embankment or the like is applied to a part or most of the upper part of the
[0043]
【The invention's effect】
As described above, the waste treatment facility of the present invention can reduce the impact on the surrounding landscape and ecosystem, while taking advantage of the underground characteristics of reducing the required area and modification range of the above-ground part. The construction cost can be reduced by combining the two types, and the location can be located without having to secure the required height difference between the platform level and the vertical part of the vertical shaft as in the case of the conventional vertical shaft type only. Can be increased.
[Brief description of the drawings]
FIG. 1 is an explanatory diagram showing an embodiment of a waste treatment facility of the present invention.
FIG. 2 is a longitudinal front view when the waste treatment facility of the present invention is implemented in a stoker-type incineration system.
FIG. 3 is a longitudinal front view when the waste treatment facility of the present invention is implemented in a fluidized bed gasification melting system.
FIG. 4 is an explanatory diagram of a ground building type waste treatment facility.
FIG. 5 is an explanatory diagram of a horizontal shaft type waste treatment facility.
FIG. 6 is an explanatory diagram of a vertical waste disposal facility.
FIG. 7 is an explanatory view showing another embodiment of the waste treatment facility of the present invention.
[Explanation of symbols]
DESCRIPTION OF
11 ...
13 ... Tash out
15 ...
17 ... Steam
19 ...
21 ... Dust collector (bug filter) 22 ... Attracting blower
23 ...
25 ...
27 ... Melting
29 ...
33 ...
35…
37 ... Catalytic reactor 38 ... Steam condenser
39…
51 ...
53… Horizontal
55…
57… Exhaust and
59 ...
61 ... banking
Claims (1)
前記開削部に、受入供給設備として、進入路に続く箇所にプラットホームを設け、このプラットホームの直下にごみピットを設け、受入供給設備の両側に焼却処理設備として、ごみピットに接する箇所にごみホッパを配設し、該ごみホッパの出口に焼却炉を配置し、
前記開削部の下方に連続して構築された立坑内には、焼却炉の下方に位置させて、焼却以降の工程であるガス冷却・排ガス処理工程の設備を配設し、立坑内に配置したこれらガス冷却・排ガス処理工程の設備は連絡通路で連絡することを特徴とした廃棄物処理施設。The excavation part formed by excavating the ground surface by the excavation method and the shaft excavated in parallel downward from the bottom of the excavation part, forming a space for installing waste treatment equipment,
In the excavation part, a platform is provided at the location following the approach path as a receiving supply facility, a waste pit is provided directly below the platform, and a waste hopper is disposed at both sides of the receiving supply facility as an incineration processing facility at a location in contact with the waste pit. Disposing an incinerator at the exit of the waste hopper,
In the shaft constructed continuously below the excavation part, it is positioned below the incinerator, and the gas cooling / exhaust gas treatment process equipment, which is a process after the incineration, is disposed in the shaft. A waste treatment facility characterized in that these gas cooling and exhaust gas treatment process facilities are connected via a communication passage .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001150374A JP4225399B2 (en) | 2001-05-21 | 2001-05-21 | Waste treatment facility |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001150374A JP4225399B2 (en) | 2001-05-21 | 2001-05-21 | Waste treatment facility |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2002339384A JP2002339384A (en) | 2002-11-27 |
JP4225399B2 true JP4225399B2 (en) | 2009-02-18 |
Family
ID=18995399
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2001150374A Expired - Fee Related JP4225399B2 (en) | 2001-05-21 | 2001-05-21 | Waste treatment facility |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4225399B2 (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2952632B1 (en) * | 2009-11-13 | 2012-05-25 | Soletanche Freyssinet | PURIFYING STATION FOR THE TREATMENT OF WASTEWATER |
CN114737601A (en) * | 2022-03-10 | 2022-07-12 | 上海市政工程设计研究总院(集团)有限公司 | Cascaded utility tunnel personnel access & exit structure of hidden type |
-
2001
- 2001-05-21 JP JP2001150374A patent/JP4225399B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JP2002339384A (en) | 2002-11-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4750962B2 (en) | Waste treatment system | |
US4852504A (en) | Waste fuel incineration system | |
JP4225399B2 (en) | Waste treatment facility | |
US6887389B2 (en) | Method and apparatus for recycling sewage sludge utilizing spent water-softener lime | |
US3456604A (en) | Incinerator | |
JP3518711B2 (en) | Garbage incineration plant | |
KR0154364B1 (en) | Method and apparatus for incinerator | |
JP2899667B2 (en) | Waste treatment facility | |
US3478707A (en) | Waste incineration process | |
JP3141094B2 (en) | Waste treatment facility | |
KR100577927B1 (en) | Waste treatment facility with pyrolysis reactor | |
JPH0824817A (en) | Waste treatment facilities | |
US6745707B2 (en) | Method of disposing of combustible materials | |
KR20230085252A (en) | The Multiple Total Wastes Compressed air and Hydrogen-furnishing-injection Vertical Shaft-kiln duplicated furnace and Long one-spot closed-vacuum duplicated Incinerator Systems Closed Entire Consolidated Burning-out Plant | |
JPH11351547A (en) | Waste treating facility | |
JP3723345B2 (en) | Incineration ash final treatment system | |
JP5544536B2 (en) | Waste disposal site | |
JPH06331119A (en) | Incinerating facility | |
JP3174834B2 (en) | Waste treatment facility | |
JPH1078209A (en) | Incinerator for sewage dehydrated sludge | |
JP2002316138A (en) | Apparatus for treating refuse unsuitable for combustion | |
JPH07280229A (en) | Large-sized incinerating furnace and stack used therefor | |
KR0158231B1 (en) | Method and apparatus for dust | |
JP2004209348A (en) | Waste disposal apparatus | |
JP2001227185A (en) | Construction procedure of refuse disposal facility |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040120 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20060221 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060606 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060803 |
|
A711 | Notification of change in applicant |
Free format text: JAPANESE INTERMEDIATE CODE: A711 Effective date: 20060908 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A821 Effective date: 20060908 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20061205 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20070125 |
|
A911 | Transfer to examiner for re-examination before appeal (zenchi) |
Free format text: JAPANESE INTERMEDIATE CODE: A911 Effective date: 20070327 |
|
A912 | Re-examination (zenchi) completed and case transferred to appeal board |
Free format text: JAPANESE INTERMEDIATE CODE: A912 Effective date: 20070525 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20081119 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111205 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111205 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121205 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121205 Year of fee payment: 4 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121205 Year of fee payment: 4 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20141205 Year of fee payment: 6 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313117 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |