JP2567559B2 - Bridge construction method using precast girders - Google Patents

Bridge construction method using precast girders

Info

Publication number
JP2567559B2
JP2567559B2 JP5120007A JP12000793A JP2567559B2 JP 2567559 B2 JP2567559 B2 JP 2567559B2 JP 5120007 A JP5120007 A JP 5120007A JP 12000793 A JP12000793 A JP 12000793A JP 2567559 B2 JP2567559 B2 JP 2567559B2
Authority
JP
Japan
Prior art keywords
temporary beam
temporary
pier
bridge
precast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP5120007A
Other languages
Japanese (ja)
Other versions
JPH06330508A (en
Inventor
俊輔 白井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP5120007A priority Critical patent/JP2567559B2/en
Publication of JPH06330508A publication Critical patent/JPH06330508A/en
Application granted granted Critical
Publication of JP2567559B2 publication Critical patent/JP2567559B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、橋梁を施工する工法の
内、桁をプレキャスト部材で行う場合の施工方法に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method for constructing a bridge using a precast member among construction methods for constructing a bridge.

【0002】[0002]

【従来の技術】従来、同工法で施工する場合、施工すべ
き橋脚間に予めワイヤを張り渡しておき、プレキャスト
桁を順次ワイヤに吊り送り出すか、手延べ式で梁を順次
既設部分から送り出し、所要の橋脚間に予め掛け渡した
状態で、その仮設梁から吊るあるいは載せる等の適当な
方法でプレキャスト桁を順次送り出す施工方法によって
いた。
2. Description of the Related Art Conventionally, when constructing with the same construction method, wires are preliminarily stretched between the piers to be constructed, and precast girders are sequentially hung on the wires, or beams are sequentially dispatched from the existing part by hand, The construction method was to send out precast girders one by one by suspending or placing them from the temporary beams with the required bridge piers in advance.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、張った
ワイヤから吊り下げる方法では、ワイヤのたわみ等が問
題となり、また手延べ式の仮設梁では、梁そのものを仮
設するのに時間がかかった。
However, in the method of suspending from a stretched wire, the deflection of the wire becomes a problem, and in the case of a hand-stretched temporary beam, it takes time to temporarily install the beam itself.

【0004】本発明は、形式としては仮設梁によってプ
レキャスト桁を仮設するものであって、所要の橋脚間の
仮設梁の掛け渡し時間を短縮することを目的としてなさ
れたものである。
The present invention has a form in which a precast girder is temporarily installed by means of a temporary beam, and its purpose is to shorten the time required to bridge the temporary beam between required piers.

【0005】[0005]

【課題を解決するための手段】上記目的を達成するため
に本発明では、仮設梁を橋脚間で仮設梁に設けたピンを
介して着脱可能に、かつピンを支点として垂直方向に旋
回可能に支持し、仮設梁の移設の際には、仮設梁を掛け
渡した橋脚の内、施工順位で後方に位置する橋脚におけ
るピンを支点として仮設梁を垂直方向に旋回させ、旋回
支点となったピンの橋脚とその橋脚の施工順位でさらに
後方に位置する橋脚とで橋脚とで仮設梁を支持し、その
仮設梁を用いてプレキャスト桁の架設を行うものとす
る。
In order to achieve the above object, according to the present invention, a temporary beam can be attached and detached between piers via a pin provided on the temporary beam, and can be vertically swung with the pin as a fulcrum. When supporting and moving the temporary beam, the temporary beam is pivoted in the vertical direction with the pin of the bridge pier located rearward in the construction order among the piers spanning the temporary beam as the fulcrum. The pier and the pier located further rearward in the construction order of the pier will support the temporary beam with the pier, and the precast girder will be erected using the temporary beam.

【0006】本発明を実施するに際し、仮設梁を掛け渡
すのは、橋脚近くに立設した柱間であってもよい。ま
た、旋回力をできるだけ小さいもので足りるようにする
ために、仮設梁の旋回側支点端にカウンターウエイトを
取り付けるようにするとよい。また、仮設梁は橋脚の両
側に1つずつ計2つ設けるものであり、移設の際には2
つの仮設梁を連結しておいて同時に旋回を行うようにす
るとよい。また、仮設梁は移設の時は自重及び移設に際
して作用する必要最小限の荷重に対して強度をもつだけ
のものにして、後で適当に補強する方法をとってもよ
い。
In carrying out the present invention, the temporary beams may be bridged between columns that are erected near the bridge piers. Further, in order to make the turning force as small as possible, a counterweight may be attached to the turning-side fulcrum end of the temporary beam. Also, two temporary beams will be installed, one on each side of the pier.
It is advisable to connect two temporary beams so that they can rotate simultaneously. Further, the temporary beam may be made to have strength only for its own weight at the time of relocation and the minimum load required for relocation, and may be appropriately reinforced later.

【0007】[0007]

【作用】旋回による移設であるので、短時間に仮設梁の
移設を行うことができる。仮設梁を用いてプレキャスト
桁を搬送するには、荷を昇降させる機能をもつもの、例
えば走行式の門型クレーンを仮設梁上のガイドレール上
を走行し、門型クレーンでプレキャスト桁を吊って目的
の位置まで搬送し、プレキャスト桁を吊り降ろして仮設
梁に直接あるいは仮設梁に取付けたブラケット等で支持
する。
Since the transfer is performed by turning, the temporary beam can be transferred in a short time. In order to convey the precast girder using the temporary beam, one that has the function of raising and lowering the load, for example, a traveling type gate crane is run on the guide rail on the temporary beam and the precast girder is hung by the gate crane. Carry it to the desired position, suspend the precast girder, and support it directly on the temporary beam or with a bracket attached to the temporary beam.

【0008】[0008]

【実施例】施工中の全体図を図1及び図2に示す。各橋
脚1A、1B、1Cには予め仮設梁4を受けるブラケッ
ト2を設けておく。仮設梁4の両端部付近にピン5が設
けてあり、図では仮設梁4が橋脚1Aと1Bの間に掛け
渡されている。仮設梁4のピン5の各ブラケット2の上
が欠けた形状のU字型の受け3にはめ合い支持されてい
る。ただし、荷重条件によっては別に固定点を増す等の
対策を採る。
[Examples] An overall view during construction is shown in Figs. A bracket 2 for receiving the temporary beam 4 is provided in advance on each pier 1A, 1B, 1C. Pins 5 are provided near both ends of the temporary beam 4, and the temporary beam 4 is bridged between the piers 1A and 1B in the figure. Each bracket 2 of the pin 5 of the temporary beam 4 is fitted and supported by a U-shaped receiver 3 in which the top of each bracket 2 is cut off. However, measures such as increasing the number of fixed points will be taken depending on the load conditions.

【0009】橋脚1Aと1Bの間に掛け渡されている仮
設梁4を橋脚1Bと1Cの間に掛けかえる方法を図4及
び図5に模式的に示す。まず、図4に示すように、仮設
梁4の橋脚1B側にカウンタウエイト6を取付ける。次
いで、図5に示すように、施工順位で後方の橋脚1Bの
ピン回りに仮設梁4を旋回させる。施工順位で前方の橋
脚1A側のピン5が仮設梁4の回転に伴って施工順位で
さらに後方の橋脚1Cのブラケット2のU字型の受け3
にはめ合った状態で、カウンタウエイト6を外す。
4 and 5 schematically show a method of replacing the temporary beam 4 bridged between the bridge piers 1A and 1B between the bridge piers 1B and 1C. First, as shown in FIG. 4, the counterweight 6 is attached to the pier 1B side of the temporary beam 4. Next, as shown in FIG. 5, the temporary beam 4 is turned around the pin of the rear pier 1B in the construction order. The pin 5 on the front pier 1A side in the construction order is a U-shaped receiver 3 of the bracket 2 of the pier 1C further rearward in the construction order as the temporary beam 4 rotates.
The counterweight 6 is removed while it is fitted to.

【0010】ピン5とブラケット2のU地型の受け3
は、ピン回りに仮設梁4を回転させるはめ合い部におい
て外れ止め等を施すのがよく、作業終了時に全てのピン
部に同様の処置をするのが望ましい。また、ピン回りで
仮設梁4を回転する回転装置の能力その他の条件によっ
てはカウンタウエイト6を取り付けてなくてもよい場合
がある。
U-shaped receiver 3 for pin 5 and bracket 2
It is preferable that the fitting portion for rotating the temporary beam 4 around the pins is provided with a stopper so that it is desirable to apply the same treatment to all the pin portions at the end of the work. Further, depending on the ability of the rotating device for rotating the temporary beam 4 around the pin and other conditions, the counterweight 6 may not be attached.

【0011】仮設梁4は図2に示すように橋脚1の両側
に1つずつ計2つ設けるものであり、各々を前記の方法
により移設するが、2つの仮設梁4を連結しておいて同
時に作業を行ってもよい。この場合、連結の強度によっ
て図3に示すブラケット2の形状でよい。また、ブラケ
ット2は橋脚1とは独立に自立していてもよい。また、
仮設梁は、移設の時に自重及び移設に際して作用する必
要最小限の荷重に対して強度をもつだけのものにして、
後で適当に補強する方法をとってもよい。
Two temporary beams 4 are provided on each side of the pier 1 as shown in FIG. 2, and each of them is relocated by the above method. You may work at the same time. In this case, the shape of the bracket 2 shown in FIG. 3 may be used depending on the strength of the connection. Moreover, the bracket 2 may be independent of the pier 1 and independent. Also,
Temporary beams should be strong enough to withstand their own weight at the time of relocation and the minimum load that acts during relocation,
You may take the method of reinforcing appropriately later.

【0012】図6及び図7に仮設梁によりプレキャスト
桁を搬送する方法を示す。仮設梁4の上面にガイドレー
ル7が敷設してあり、そのレール7上を転動する車輪9
を有する門型クレーン8のウインチ10でプレキャスト
桁6を吊り下げ、目的の位置まで運び、吊り降ろす。吊
り降ろしたプレキャスト桁6は、仮設梁4に取付けたブ
ラケット等で支持する。プレキャスト桁を搬送する搬送
装置は、図示は省略するが荷を昇降させる機能を持つ台
車なら所期の目的を果す。
6 and 7 show a method of transporting a precast girder by means of a temporary beam. A guide rail 7 is laid on the upper surface of the temporary beam 4, and a wheel 9 rolling on the rail 7
The precast girder 6 is hung by the winch 10 of the gate type crane 8 having the above, carried to the target position, and hung down. The suspended precast girder 6 is supported by a bracket or the like attached to the temporary beam 4. The transport device for transporting the precast girder serves the intended purpose if it is a dolly having a function of raising and lowering the load, although not shown.

【0013】[0013]

【発明の効果】本発明は、プレキャスト桁による橋梁の
施工法において、橋脚間に掛け渡してプレキャスト桁の
搬送を行う仮設梁の移設を、橋脚または別に設けた柱に
おける仮設梁のピンを支点として旋回により行うもので
あるので、仮設梁の掛け替え時間を大巾に短縮すること
ができる。また、プレキャスト桁の搬送は仮設梁上を走
行する台車によって行われるので、橋脚間に張り渡した
ワイヤによる場合のようにワイヤのたるみ等による不都
合を生じない。
INDUSTRIAL APPLICABILITY The present invention relates to a method of constructing a bridge using precast girders, in which the transfer of the temporary beams for carrying the precast girders over the piers is carried out by using the pins of the temporary beams on the piers or columns separately provided as fulcrums. Since it is performed by turning, the time for changing the temporary beam can be greatly shortened. In addition, since the precast girder is transported by a trolley that travels on a temporary beam, there is no inconvenience due to slack of the wire as in the case of a wire stretched between piers.

【図面の簡単な説明】[Brief description of drawings]

【図1】プレキャスト桁による橋梁の施工を示す側面
図。
FIG. 1 is a side view showing construction of a bridge using a precast girder.

【図2】図1のA矢視図。FIG. 2 is a view on arrow A in FIG.

【図3】ブラケットの他の例を示す正面図。FIG. 3 is a front view showing another example of the bracket.

【図4】仮設梁の移設方法を示し、移設前の側面図。FIG. 4 is a side view showing a method of relocating a temporary beam, which is a pre-relocation state.

【図5】図4の仮設梁の移設中の側面図。5 is a side view of the temporary beam of FIG. 4 during transfer.

【図6】仮設梁を用いてプレキャスト桁を搬送する方法
を示す正面図。
FIG. 6 is a front view showing a method of transporting a precast girder using a temporary beam.

【図7】図6の側面図。FIG. 7 is a side view of FIG. 6;

【符号の説明】[Explanation of symbols]

1・・・橋脚 2・・・ブラケット 3・・・U字型の受け 4・・・仮設梁 5・・・ピン 6・・・カウンタウエイト 7・・・ガイドレール 8・・・門型クレーン 9・・・車輪 10・・・ウインチ 1 ... Pier 2 ... Bracket 3 ... U-shaped receiver 4 ... Temporary beam 5 ... Pin 6 ... Counterweight 7 ... Guide rail 8 ... Gate crane 9 ... Wheels 10 ... Winches

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 橋脚間に仮設梁を掛け渡し、その仮設梁
上を移動させてプレキャスト桁を橋脚間に架設するプレ
キャスト桁による橋梁の施工方法において、上記仮設梁
を橋脚間または橋脚近くに立設した柱間で仮設梁に設け
たピンを介して着脱可能に、かつピンを支点として垂直
方向に旋回可能に支持し、仮設梁の移設の際には、仮設
梁を掛け渡した橋脚または柱の内、施工順位で後方に位
置する橋脚または柱におけるピンを支点として仮設梁を
垂直方向に旋回させ、旋回支点となったピンの橋脚また
は柱とその橋脚または柱の施工順位でさらに後方に位置
する橋脚または柱として仮設梁を支持し、その仮設梁を
用いてプレキャスト桁の架設を行うことを特徴とするプ
レキャスト桁による橋梁の施工方法。
1. A method for constructing a bridge using precast girders, wherein a temporary beam is bridged between bridge piers and moved on the temporary beam to build a precast girder between the piers. The piers or columns on which the temporary beams are bridged are detachably supported between the installed columns via the pins provided on the temporary beams and pivotally supported in the vertical direction with the pins as fulcrums. Among them, the temporary beam is pivoted in the vertical direction using the pin of the pier or pillar located at the rear in the construction order as the fulcrum, and the pier or pillar of the pin that became the pivot fulcrum and the pier or pillar located further behind in the construction order of the pier or pillar A method of constructing a bridge using precast girders, characterized in that a temporary beam is supported as a bridge pier or a pillar, and the precast girder is erected using the temporary beam.
JP5120007A 1993-05-21 1993-05-21 Bridge construction method using precast girders Expired - Lifetime JP2567559B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5120007A JP2567559B2 (en) 1993-05-21 1993-05-21 Bridge construction method using precast girders

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5120007A JP2567559B2 (en) 1993-05-21 1993-05-21 Bridge construction method using precast girders

Publications (2)

Publication Number Publication Date
JPH06330508A JPH06330508A (en) 1994-11-29
JP2567559B2 true JP2567559B2 (en) 1996-12-25

Family

ID=14775601

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5120007A Expired - Lifetime JP2567559B2 (en) 1993-05-21 1993-05-21 Bridge construction method using precast girders

Country Status (1)

Country Link
JP (1) JP2567559B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102943440A (en) * 2012-11-06 2013-02-27 天津二十冶建设有限公司 Method for constructing bridges

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102943440A (en) * 2012-11-06 2013-02-27 天津二十冶建设有限公司 Method for constructing bridges

Also Published As

Publication number Publication date
JPH06330508A (en) 1994-11-29

Similar Documents

Publication Publication Date Title
JP5198973B2 (en) Bridge overhang installation device and installation method
JP2009191458A (en) Construction apparatus for bridge, construction method for floor slab, and construction method for bridge
JP3709220B2 (en) crane
JP3026184B2 (en) Bridge erection equipment
JP2894226B2 (en) Bridge construction method
JP2567559B2 (en) Bridge construction method using precast girders
JP4489872B2 (en) Bridge erection method and apparatus
JP2567560B2 (en) Bridge construction method using precast girders
JP4619518B2 (en) Elevated structure construction method, erection device, and construction device
JP2002332613A (en) Bridge removal working machine
SU1030462A1 (en) Method of installation of prefabricated reinforcing beam of suspended and guy-rope bridges
JP3718033B2 (en) Precast block erection device
JPH08259177A (en) Handling device of pipe
CN110904810B (en) Rapid erecting system for high-speed railway box girder
JP2690345B2 (en) Bridge construction method and equipment
JPH1181242A (en) Precast block installation device
JPH01310003A (en) Bridge building method and device thereof
JPH10331599A (en) Carrying system of lining segment for tunnel construction
JPH06185017A (en) Bridge girder erection method and device thereof
JPH0668165B2 (en) Concrete transport method and device
JPH09144498A (en) Shifting device for segment and transferring method of segment
JPH01310002A (en) Bridge building method and equipment thereof
JPH053473Y2 (en)
JP2775206B2 (en) Material transport equipment for building construction
JPH053474Y2 (en)