JP2544683B2 - How to build an underground structure - Google Patents

How to build an underground structure

Info

Publication number
JP2544683B2
JP2544683B2 JP2302869A JP30286990A JP2544683B2 JP 2544683 B2 JP2544683 B2 JP 2544683B2 JP 2302869 A JP2302869 A JP 2302869A JP 30286990 A JP30286990 A JP 30286990A JP 2544683 B2 JP2544683 B2 JP 2544683B2
Authority
JP
Japan
Prior art keywords
anchor
frame body
ground
frame
jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2302869A
Other languages
Japanese (ja)
Other versions
JPH04176911A (en
Inventor
北村  精男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Giken Seisakusho Co Ltd
Original Assignee
Giken Seisakusho Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Giken Seisakusho Co Ltd filed Critical Giken Seisakusho Co Ltd
Priority to JP2302869A priority Critical patent/JP2544683B2/en
Publication of JPH04176911A publication Critical patent/JPH04176911A/en
Application granted granted Critical
Publication of JP2544683B2 publication Critical patent/JP2544683B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は地下倉庫などの地下構造物を構築する方法に
関する。
TECHNICAL FIELD The present invention relates to a method for constructing an underground structure such as an underground warehouse.

(従来の技術) 地下構造物を構築する場合、外殻となる箱形の枠体を
地盤内に造成している。従来、この箱形の枠体の築造は
地盤を掘削し、この掘削部分にコンクリートを打設し、
養生することで行われていた。すなわち従来の地下構造
物の構築は以下の手順を必要とした。
(Prior Art) When constructing an underground structure, a box-shaped frame body serving as an outer shell is constructed in the ground. Conventionally, the construction of this box-shaped frame body excavated the ground, placed concrete in this excavated part,
It was done by curing. That is, the construction of the conventional underground structure required the following procedures.

予定の箱形の枠体よりも幾分、大きな寸法で地盤を掘
削する。
Excavate the ground with a size slightly larger than the planned box-shaped frame.

掘削された底部に栗石を敷き、捨てコンクリートを打
設し、墨出しを行った後、床面のための底版用の配筋を
行う。
Crushed stones are laid on the excavated bottom, waste concrete is placed, and after marking is done, reinforcement for bottom slabs for floors is performed.

底版用のコンクリートを打設し養生させる。Place concrete for bottom slab and let it cure.

枠体のための壁版用の配筋を行う。The wall reinforcement for the frame is performed.

壁版用の型枠を組む。Assemble the formwork for the wall plate.

この型枠にコンクリートを打設し養生させる。Concrete is poured into this formwork and cured.

型枠を取外すと共に、外周部分の地盤を埋戻す。Remove the formwork and refill the ground around the outer periphery.

また、構造物に近接する場合や一定の深さでオープン
カットができない敷地では土留壁を設ける必要があっ
た。
In addition, it was necessary to install a retaining wall on the site near the structure or on the site where open cutting cannot be done at a certain depth.

(発明が解決しようとする課題) 上述した従来の構築方法では、工程数が多く、施工現
場でのコンクリートの養生を必要とするため工期が長期
間となっていた。また、地盤の掘削では予定寸法よりも
大きな掘削(余掘り)を必要とし、現場敷地にある程度
の余裕が必要であると共に、掘削が深い場合には土留壁
を打ち込む余分な作業が必要であった。しかも掘削時に
は周囲地盤の沈下を生じ易く、枠体構築後に外周部分の
埋戻しが必要で、この埋戻し部分の地盤沈下も生じ易か
った。
(Problems to be Solved by the Invention) In the above-described conventional construction method, the number of steps is large and the curing of concrete at the construction site is required, so that the construction period is long. In addition, excavation of the ground required excavation larger than the planned size (excess excavation), a certain amount of space was required on the site site, and when excavation was deep, extra work was required to drive the retaining wall. . Moreover, subsidence of the surrounding ground is likely to occur during excavation, and backfilling of the outer peripheral portion is required after construction of the frame body, and subsidence of the backfilled portion is also likely to occur.

本発明はこのような従来技術の問題点に鑑みてなされ
たものであり、工程数の少ない簡単な施工で短期間に枠
体を構築することができ、土留壁を必要とせず、しかも
地盤沈下などの周囲地盤への悪影響のない地下構造物の
構築方法を提供することを目的としている。
The present invention has been made in view of the above problems of the prior art, and it is possible to construct a frame body in a short period of time by a simple construction with a small number of steps, without requiring a retaining wall, and in addition to subsidence. The purpose is to provide a method for constructing an underground structure that does not adversely affect the surrounding ground.

(課題を解決するための手段) 上記目的を達成するため本発明は、下端が解放された
箱形の枠体の内部から地盤にアンカーを螺進し、その後
ジャッキを介してアンカー上部に架橋部材を取り付け、
該架橋部材と枠体との間にスペーサーを介在させた状態
でアンカーを反力として枠体を地盤内に埋め込むことを
特徴とする。
(Means for Solving the Problems) In order to achieve the above object, according to the present invention, an anchor is screwed to the ground from the inside of a box-shaped frame whose lower end is opened, and then a bridge member is connected to an upper part of the anchor via a jack. Attached
It is characterized in that the frame body is embedded in the ground by using the anchor as a reaction force with the spacer interposed between the bridging member and the frame body.

そして、これに次いで前記埋設された枠体に隣接して
新たな枠体を前記と同様な方法で埋め込むことを特徴と
する。
Then, next to this, a new frame body is embedded adjacent to the embedded frame body in the same manner as described above.

また、下端が解放された箱形の枠体の内部から地盤に
アンカーを螺進し、その後アンカーの上部に連結した架
橋部材と枠体上部に載置したジャッキとを連結した状態
でアンカーを反力として枠体を地盤内に埋め込むことを
特徴とする。
In addition, the anchor is screwed into the ground from the inside of the box-shaped frame body whose lower end is opened, and then the bridge member connected to the upper part of the anchor and the jack placed on the upper part of the frame are connected to each other. It is characterized by embedding the frame body in the ground as a force.

そして、これに次いで前記埋設された枠体に隣接して
新たな枠体を前記と同様な方法で埋め込むことを特徴と
する。
Then, next to this, a new frame body is embedded adjacent to the embedded frame body in the same manner as described above.

(作用) 地盤内に埋め込まれたアンカーを反力として、枠体を
地盤に埋設するだけで、地下構造物の壁版を構築するこ
とができる。枠体は工場等であらかじめ所定寸法となる
ように作製されたものを使用でき、現場でのコンクリー
ト打設、養生が不要となると共に、枠体埋設以前の地盤
掘削も不要となる。
(Operation) By using the anchor embedded in the ground as a reaction force, the wall slab of the underground structure can be constructed only by burying the frame body in the ground. As the frame body, it is possible to use a frame body which has been manufactured to have a predetermined size in advance in a factory or the like, which eliminates the need for concrete pouring and curing on the site, and the ground excavation before the frame body is buried.

さらに、ジャッキ作動量が不足の場合でも、枠体を完
全に埋設することができるため作業効率がよく、また、
枠体をバランスよく圧入することができるため圧入時の
傾きの調整等が容易である。
Furthermore, even if the jack operation amount is insufficient, the frame body can be completely buried, resulting in good work efficiency.
Since the frame can be press-fitted in a well-balanced manner, it is easy to adjust the inclination when press-fitting.

(実施例) 第1図(a)〜(g)は枠体埋設の基本工程を示すも
ので、図中符号1は鉄筋コンクリートによって箱形に作
成された枠体である。この枠体1は下端部および上端部
が開放された矩形状に成形されており、あらかじめ工場
内で予定寸法に仕上げられたものを施工現場に運搬して
使用される。しかし、板状のコンクリート壁体を工場で
作製し、このコンクリート壁体を現場で箱形に組み立て
ても良い。枠体1の下端部は先尖形状に成形し地盤内の
進入を容易としている。また、壁体をPCコンクリートと
すれば、強度が大きく壁厚も薄くできる。
(Example) FIGS. 1 (a) to 1 (g) show a basic step of burying a frame body, in which reference numeral 1 is a box body made of reinforced concrete in a box shape. The frame 1 is formed in a rectangular shape with an open lower end and an upper end, and a frame that has been finished to a predetermined size in a factory is transported to a construction site for use. However, it is also possible to manufacture a plate-shaped concrete wall body at a factory and assemble the concrete wall body in a box shape on site. The lower end of the frame 1 is formed in a pointed shape to facilitate entry into the ground. In addition, if the wall is made of PC concrete, the strength is high and the wall thickness can be thin.

図中符号2は、ロッド3下部にスクリュー4を有した
オーガスクリューなどのアンカーである。このアンカー
2は枠体1の内部から地盤内に埋め込まれて地盤への枠
体1圧入時の反力として使用する。架橋部材5は、枠体
1の所定部位に掛け渡され、枠体1を地盤へ圧入するジ
ャッキ6を立設状態で取り付けている。ジャッキ6はそ
のピストンロッド6aの先端部がジョイント7を介してア
ンカー2のロッド3に連結されている。
Reference numeral 2 in the figure is an anchor such as an auger screw having a screw 4 at the lower portion of the rod 3. The anchor 2 is embedded in the ground from the inside of the frame 1 and is used as a reaction force when the frame 1 is pressed into the ground. The bridging member 5 is attached to a predetermined portion of the frame body 1, and a jack 6 for press-fitting the frame body 1 into the ground is attached in an upright state. The jack 6 has a piston rod 6 a whose distal end is connected to the rod 3 of the anchor 2 via a joint 7.

このように、架橋部材5が枠体1に掛け渡され、この
架橋部材5に取り付けたジャッキ6がアンカー2に連結
しているため、架橋部材5およびジャッキ6を介して枠
体1とアンカー2とが連結した構造となっている。な
お、枠体1に対するアンカー2の設置数およびその設置
位置は、枠体1が傾くことなく、全体が均一に地盤に圧
入できるように設定される。
In this way, since the bridging member 5 is stretched over the frame 1 and the jack 6 attached to the bridging member 5 is connected to the anchor 2, the frame 1 and the anchor 2 are connected via the bridging member 5 and the jack 6. It has a structure in which and are connected. The number of anchors 2 to be installed on the frame 1 and the installation positions thereof are set so that the entire frame 1 can be pressed into the ground uniformly without tilting.

第2図および第3図はこの一例を示し、第2図の図示
例では、枠体1の四隅部分に架橋部材5を斜め方向に掛
け渡し、この架橋部材5の中央部分にアンカー2を位置
して設置している。一方、第3図の図示例では、枠体1
の長辺間に架橋部材5を平行に掛け渡し、各架橋部材5
の略3等分位置にアンカー2を位置して設置している。
このようなアンカー2の設置数及び設置位置は図示例に
限られるものではなく、適宜変更が可能である。
2 and 3 show this example. In the example shown in FIG. 2, the bridging members 5 are slid over the four corners of the frame 1 and the anchor 2 is positioned at the central portion of the bridging members 5. Has been installed. On the other hand, in the example shown in FIG.
The bridging members 5 are laid in parallel between the long sides of the
Anchor 2 is located and installed in approximately three equal positions.
The number of anchors 2 and the positions of the anchors 2 are not limited to those shown in the drawing, but can be changed as appropriate.

次に、第1図に基づき、枠体埋設の基本工程を説明す
る。まず、アンカー2を枠体1内に位置するように地盤
に埋め込む。このアンカー2の埋め込みはそのロッド3
に装着した掘削機Mを作動することで行われ、アンカー
2は、そのスクリュー4が螺進して地盤深く埋め込まれ
る(第1図(a))。次に、枠体1の所定部位に架橋部
材5を掛け渡すと共に、この架橋部材5にジャッキ6を
取り付け、そのピストンロッド6aとアンカー2のロッド
3とをジョイント7で結合させる(第1図(b))。
Next, the basic steps of burying the frame will be described with reference to FIG. First, the anchor 2 is embedded in the ground so as to be located in the frame body 1. The anchor 2 is embedded in the rod 3
This is performed by operating the excavator M mounted on the anchor 2, and the screw 4 of the anchor 2 is screwed into the anchor 2 to be embedded deep in the ground (Fig. 1 (a)). Next, the bridging member 5 is laid over a predetermined portion of the frame body 1, the jack 6 is attached to the bridging member 5, and the piston rod 6a and the rod 3 of the anchor 2 are joined by the joint 7 (see FIG. b)).

これで枠体1とアンカー2とが連結した構造となり、
この状態でピストンロッド6aのロッド長の短縮方向にジ
ャッキ6を作動させる。この作動により、地盤内のアン
カー2を反力として架橋部材5が枠体1を強固に押圧す
るため、枠体1が地盤内に圧入される(第1図
(c))。
With this, the structure in which the frame 1 and the anchor 2 are connected,
In this state, the jack 6 is operated in the direction of shortening the rod length of the piston rod 6a. By this operation, the bridging member 5 firmly presses the frame 1 by using the anchor 2 in the ground as a reaction force, so that the frame 1 is pressed into the ground (FIG. 1 (c)).

この枠体1の圧入量はジャッキ6のピストンロッド6a
のストローク長により決定されるもので、最大ストロー
クでも枠体1が地盤内に完全に埋め込まれない場合は、
ピストンロッド6aの伸長方向にジャッキ6を作動させ
る。これによりジャッキ6と一体化されている架橋部材
5が上方に持ち上げられる(第1図(d))。その後、
架橋部材5を枠体1に当接するまで下降してジャッキ6
と架橋部材5との位置変更を行った後、これらを連結す
る(第1図(e))。そして、この状態で再びピストン
ロッド6aの短縮方向にジャッキ6を作動させ、アンカー
2を反力としながら架橋部材5によって枠体1を押し下
げ地盤に埋め込む(第1図(f))。この枠体1の埋め
込みにより、地盤内に地下構造物の壁体が造成される。
従って枠体1内の地盤を掘削することにより(第1図
(g))、枠体1内部の空間8に対して底版のためのコ
ンクリート打設等を行うことができ、地下構造物の構築
が可能となる。
The press-fitting amount of this frame 1 is the piston rod 6a of the jack 6.
It is determined by the stroke length of, and when the frame body 1 is not completely embedded in the ground even with the maximum stroke,
The jack 6 is operated in the extension direction of the piston rod 6a. As a result, the bridging member 5 integrated with the jack 6 is lifted upward (FIG. 1 (d)). afterwards,
The bridging member 5 is lowered until it abuts on the frame 1 and the jack 6
After changing the positions of the bridging member 5 and the bridging member 5, they are connected (FIG. 1 (e)). Then, in this state, the jack 6 is operated again in the direction of shortening the piston rod 6a, and the frame body 1 is pushed down by the bridging member 5 while making the anchor 2 a reaction force and embedded in the ground (FIG. 1 (f)). By embedding the frame body 1, a wall body of an underground structure is created in the ground.
Therefore, by excavating the ground in the frame 1 (Fig. 1 (g)), it is possible to place concrete for the bottom slab in the space 8 inside the frame 1 and construct an underground structure. Is possible.

このように、アンカー2を反力として枠体1を地盤に
埋め込んで地下構造物の壁体を作成するため、型枠組
み、コンクリート打設が不要となり、工程数を削減する
ことができる。さらに、あらかじめ工場で作製した枠体
を使用できるため養生も不要となり、工期を大幅に短縮
できる。しかも枠体の埋設以前には地盤を掘削する必要
がなく、掘削に基づく埋め戻しが不要となり地盤沈下等
の悪影響もなくなる。また、現場敷地の余裕も不要とな
り、狭い場所での施工が可能となる。
In this way, the frame body 1 is embedded in the ground by using the anchor 2 as a reaction force to form the wall body of the underground structure, so that the formwork and the concrete pouring are unnecessary, and the number of steps can be reduced. Further, since the frame body manufactured in advance at the factory can be used, no curing is required, and the construction period can be greatly shortened. Moreover, it is not necessary to excavate the ground before the burying of the frame body, and there is no need for backfilling based on the excavation, and adverse effects such as ground subsidence are eliminated. In addition, there is no need for additional space on site and construction can be performed in a narrow space.

第4図は本発明の1実施例を示す。この実施例はジャ
ッキ6の1回の作動で枠体1が完全に地盤に埋設されな
い場合の方法を示すもので、上記第1図(d)の工程に
続いて行われる。すなわち第1図(d)の後、枠体1と
架橋部材5との間に、スペーサであるやっとこ9を挿入
するものであり(第4図(a))、このスペーサである
やっとこ9を介して架橋部材5の押圧力を枠体1に伝達
させる。そして、このスペーサであるやっとこ9の挿入
後、ジャッキ6を短縮作動させると、枠体1がスペーサ
であるやっとこ9によって押し込まれるため、地盤内に
圧入することができる(第4図(b))。
FIG. 4 shows an embodiment of the present invention. This embodiment shows a method in the case where the frame body 1 is not completely buried in the ground by one operation of the jack 6, and is carried out following the step of FIG. 1 (d). That is, after FIG. 1 (d), a spacer Yatoko 9 is inserted between the frame 1 and the bridging member 5 (FIG. 4A). The pressing force of the bridging member 5 is transmitted to the frame body 1. Then, when the jack 6 which is the spacer is inserted and the jack 6 is shortened, the frame body 1 is pushed by the spacer 9 which is the spacer, so that it can be press-fitted into the ground (FIG. 4 (b)). .

第5図および第6図は本発明の他の実施例を示す。こ
の実施例もジャッキ6の作動量不足を補うもので、第5
図に示すように、アンカー2のロッド3が枠体1よりも
高くなる長尺となっている。またジャッキ6が枠体1を
直接押圧するように枠体1上に設置され、これらジャッ
キ6が連結部材10により連結されている。そして、この
連結部材10にアンカー2のロッド3上部が挿入されてア
ンカー2と連結部材10との連結が行われている。
5 and 6 show another embodiment of the present invention. This embodiment also compensates for the insufficient working amount of the jack 6, and
As shown in the figure, the rod 3 of the anchor 2 is elongated so that it is higher than the frame body 1. Further, the jacks 6 are installed on the frame body 1 so as to directly press the frame body 1, and these jacks 6 are connected by the connecting member 10. The upper part of the rod 3 of the anchor 2 is inserted into the connecting member 10 to connect the anchor 2 and the connecting member 10.

このような状態で全てのジャッキ6を伸長方向に同期
作動させると、枠体1はアンカー2を反力としたジャッ
キ6の押圧により地盤内に圧入される。この圧入はジャ
ッキ6のピストンロッド6aの最大ストローク長で停止す
る。第6図(a)、(b)はその後の工程を示し、同図
(a)はアンカー2のロッド3と連結部材10との連結を
解除し、ジャッキ6を短縮方向に作動させたものであ
り、連結部材10はジャッキ6の作動と共にロッド3に沿
って下方に移動する。そして、この移動の後、ロッド3
と連結部材10とを再結合させて、ジャッキ6を伸長方向
に作動させることにより、アンカー2を反力とした枠体
1の圧入を続行することができる。
When all the jacks 6 are operated synchronously in the extension direction in such a state, the frame body 1 is pressed into the ground by the pressing of the jacks 6 with the anchor 2 as a reaction force. This press-fitting stops at the maximum stroke length of the piston rod 6a of the jack 6. FIGS. 6 (a) and 6 (b) show the subsequent steps. FIG. 6 (a) shows that the connection between the rod 3 of the anchor 2 and the connecting member 10 is released, and the jack 6 is operated in the shortening direction. The connecting member 10 moves downward along the rod 3 as the jack 6 operates. And after this movement, rod 3
By reconnecting the connection member 10 with the connection member 10 and operating the jack 6 in the extension direction, the press-fitting of the frame body 1 using the anchor 2 as a reaction force can be continued.

一方、第6図(b)はジャッキ6と連結部材10との連
結を解除してジャッキ6を短縮方向に作動させたもので
あり、連結部材10に対してジャッキ6が下降する。この
下降の後、ジャッキ6と連結部材10とを再び連結しジャ
ッキ6を伸長方向に作動させると、アンカー2を反力と
して枠体1が地盤に圧入される。このような第6図
(a)、(b)のいずれかの方法を使用することによ
り、枠体1を完全に地盤内に埋設させることができる。
この場合にも、上記第4図に示したようにやっとこを併
用してもよい。
On the other hand, FIG. 6 (b) shows that the connection between the jack 6 and the connecting member 10 is released and the jack 6 is operated in the shortening direction, and the jack 6 is lowered with respect to the connecting member 10. After this descent, when the jack 6 and the connecting member 10 are connected again and the jack 6 is operated in the extending direction, the frame 1 is pressed into the ground by using the anchor 2 as a reaction force. The frame body 1 can be completely embedded in the ground by using any one of the methods shown in FIGS. 6 (a) and 6 (b).
In this case, too, as shown in FIG.

次に、枠体を隣接して埋設する方法を第7図及び第8
図に示す。本発明では埋設する枠体を3基とした。すな
わち第1枠体11を上記と同様の方法で圧入し、次いで第
2枠体12、第3枠体13を隣接して圧入する。その後、枠
体11、12、13内部の地盤を掘削しながら、枠体同士をボ
ルトや溶接等で連結固定していく。このとき各枠体の側
板にあらかじめ開口した連通部15、15・・により、枠体
11、12、13の内部が連通状態となる。そのため、圧入時
に大きな反力を必要としない比較的小さな枠体の接続に
より、大きな空間を作ることができる。連続圧入する枠
体の数に制限はなく、本発明による枠体の圧入にも、前
記各実施例に示したすべての方法が使用できる。
Next, a method of burying the frame bodies adjacently will be described with reference to FIGS.
Shown in the figure. In the present invention, the number of embedded frame bodies is three. That is, the first frame 11 is press-fitted in the same manner as described above, and then the second frame 12 and the third frame 13 are press-fitted adjacently. After that, while excavating the ground inside the frame bodies 11, 12, and 13, the frame bodies are connected and fixed to each other by bolts or welding. At this time, the frame body is formed by the communication portions 15, 15 ... Pre-opened on the side plates of each frame body.
The insides of 11, 12, and 13 are in communication. Therefore, a large space can be created by connecting a relatively small frame that does not require a large reaction force at the time of press fitting. There is no limitation on the number of frames to be continuously press-fitted, and all the methods shown in the above-mentioned embodiments can be used for press-fitting the frame according to the present invention.

(発明の効果) 以上説明したように本発明は、あらかじめ箱形に作製
された枠体をアンカーの反力で地盤内に埋設して、地下
構造物とするため、以下に示す効果を有する。
(Effects of the Invention) As described above, the present invention has the following effects because a box-shaped frame body is embedded in the ground by the reaction force of the anchor to form an underground structure.

土留壁を設ける必要がない。There is no need to install a retaining wall.

枠体が地下構造物の壁体となり、壁体を造成するため
の型枠組み、配筋、コンクリート打設が不要となるた
め、工程数が削減されて効率が良い。
The frame becomes the wall of the underground structure, and there is no need for a formwork, bar arrangement, or concrete pouring to construct the wall, so the number of steps is reduced and efficiency is improved.

あらかじめ作製された枠体を使用するため、養生の必
要がなく、上記と併せて、工期を大幅に短縮すること
ができる。
Since a prefabricated frame is used, there is no need for curing, and in addition to the above, the construction period can be greatly shortened.

枠体の埋設以前に地盤を掘削する必要がなく、掘削に
起因する外周部分の埋め戻しが不要となると共に、地盤
沈下もなくなる。
It is not necessary to excavate the ground before burying the frame body, and it is not necessary to backfill the outer peripheral portion due to the excavation, and the ground subsidence is also eliminated.

余掘りが不要となるため、現場敷地の余裕が少ない狭
い場所や構造物に近接して構築することができる。
Since over-digging is not necessary, it can be built close to a narrow place or structure where there is little room on site.

小さな枠体の連続圧入により、大きな空間を有する枠
体を得ることができる。
A frame body having a large space can be obtained by continuously press-fitting a small frame body.

ジャッキ作動量が不足の場合でも枠体を完全に埋設す
ることができるため作業効率がよい。
Even if the jack operation amount is insufficient, the frame body can be completely buried, resulting in good work efficiency.

ジャッキ作動量が不足の場合でも枠体をバランスよく
圧入することができ、圧入時の傾きの調整等が容易であ
る。
Even if the jack operation amount is insufficient, the frame body can be press-fitted in a well-balanced manner, and it is easy to adjust the inclination during press-fitting.

【図面の簡単な説明】[Brief description of drawings]

図面は枠体埋設の基本工程及び本発明の実施例を示すも
ので、第1図(a)〜(g)は構築方法を工程順に示す
断面図、第2図および第3図は枠体とアンカーとの位置
関係の各例を示す平面図、第4図(a)、(b)は本発
明の1実施例を工程順に説明する断面図、第5図は他の
実施例を示す断面図、第6図(a)、(b)はその後の
工程をそれぞれ示す断面図、第7図は枠体の埋設状態を
表す斜視図、第8図は同断面図である。 1、11……枠体、2……アンカー 5……架橋部材、6……ジャッキ 9……やっとこ、10……連結部材
The drawings show the basic steps of embedding a frame and an embodiment of the present invention. FIGS. 1 (a) to (g) are sectional views showing the construction method in the order of steps, and FIGS. 2 and 3 show a frame. 4A and 4B are cross-sectional views illustrating one embodiment of the present invention in the order of steps, and FIG. 5 is a cross-sectional view illustrating another embodiment. 6 (a) and 6 (b) are cross-sectional views showing the subsequent steps, respectively, FIG. 7 is a perspective view showing an embedded state of the frame body, and FIG. 8 is the same cross-sectional view. 1, 11 …… Frame, 2 …… Anchor 5 …… Cross-linking member, 6 …… Jack 9 …… Yamato, 10 …… Coupling member

Claims (4)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】下端が解放された箱形の枠体の内部から地
盤にアンカーを螺進し、その後ジャッキを介してアンカ
ー上部に架橋部材を取り付け、該架橋部材と枠体との間
にスペーサーを介在させた状態でアンカーを反力として
枠体を地盤内に埋め込む地下構造物の構築方法。
1. An anchor is screwed to the ground from the inside of a box-shaped frame body whose lower end is opened, and then a bridge member is attached to the upper part of the anchor via a jack, and a spacer is provided between the bridge member and the frame body. A method for constructing an underground structure in which the frame body is embedded in the ground by using the anchor as a reaction force with the interposition of the anchor.
【請求項2】下端が解放された箱形の枠体の内部から地
盤にアンカーを螺進し、その後アンカーの上部に連結し
た架橋部材と枠体上部に載置したジャッキとを連結した
状態でアンカーを反力として枠体を地盤内に埋め込む地
下構造物の構築方法。
2. An anchor is screwed to the ground from the inside of a box-shaped frame body whose lower end is open, and then a bridging member connected to the upper part of the anchor and a jack placed on the upper part of the frame are connected. A method of constructing an underground structure in which the frame is embedded in the ground using the anchor as a reaction force.
【請求項3】下端が解放された箱形の枠体の内部から地
盤にアンカーを螺進し、その後ジャッキを介してアンカ
ー上部に架橋部材を取り付け、該架橋部材と枠体との間
にスペーサーを介在させた状態でアンカーを反力として
枠体を地盤内に埋め込み、次いで前記埋設された枠体に
隣接して新たな枠体を前記と同様な方法で埋め込む地下
構造物の構築方法。
3. An anchor is screwed to the ground from the inside of a box-shaped frame body whose lower end is opened, and then a bridge member is attached to the upper part of the anchor via a jack, and a spacer is provided between the bridge member and the frame body. A method for constructing an underground structure in which a frame body is embedded in the ground by using an anchor as a reaction force with the intervening interposition, and then a new frame body is embedded adjacent to the embedded frame body in the same manner as described above.
【請求項4】下端が解放された箱形の枠体の内部から地
盤にアンカーを螺進し、その後アンカーの上部に連結し
た架橋部材と枠体上部に載置したジャッキとを連結した
状態でアンカーを反力として枠体を地盤内に埋め込み、
次いで前記埋設された枠体に隣接して新たな枠体を前記
と同様な方法で埋め込む地下構造物の構築方法。
4. An anchor is screwed to the ground from the inside of a box-shaped frame whose lower end is open, and then a bridging member connected to the upper part of the anchor and a jack placed on the upper part of the frame are connected. Embed the frame body in the ground with the anchor as a reaction force,
Next, a method for constructing an underground structure, in which a new frame is embedded adjacent to the buried frame in the same manner as described above.
JP2302869A 1990-11-08 1990-11-08 How to build an underground structure Expired - Fee Related JP2544683B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2302869A JP2544683B2 (en) 1990-11-08 1990-11-08 How to build an underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2302869A JP2544683B2 (en) 1990-11-08 1990-11-08 How to build an underground structure

Publications (2)

Publication Number Publication Date
JPH04176911A JPH04176911A (en) 1992-06-24
JP2544683B2 true JP2544683B2 (en) 1996-10-16

Family

ID=17914084

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2302869A Expired - Fee Related JP2544683B2 (en) 1990-11-08 1990-11-08 How to build an underground structure

Country Status (1)

Country Link
JP (1) JP2544683B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010067680A (en) * 2001-03-07 2001-07-13 권이현 Clamp-off aufban method for the facilities using earth-anchor
EP2744033B1 (en) 2012-12-07 2015-02-18 Obrist Powertrain GmbH Battery

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4987110A (en) * 1972-12-26 1974-08-21
JPH0672517B2 (en) * 1989-03-11 1994-09-14 株式会社機動技研 How to build a shaft

Also Published As

Publication number Publication date
JPH04176911A (en) 1992-06-24

Similar Documents

Publication Publication Date Title
KR102159832B1 (en) Construction method of basic construction of buildings
KR20190083466A (en) Retaining wall and construction method thereof
JP2544683B2 (en) How to build an underground structure
JPH05230845A (en) L-shaped block retaining wall structure and construction method thereof
JP3760304B2 (en) Building foundation construction method
KR101733928B1 (en) panel type retaining wall with a continuous beam structure
KR101017127B1 (en) Connecting Structure between Foundation and Pier, and Construction Method thereof
US4875807A (en) Method and means for basement construction
JPH0684690B2 (en) Building basement extension method
KR20090042395A (en) Retainning wall and its construction method
JPH08177059A (en) Footing block, and integrated method for constructing continuous footing employing footing block
JP2002138497A (en) Seismic base isolation building construction of existing building
JPH10299003A (en) Foundation work using precast concrete member
JP2892807B2 (en) How to build a basement
JPH09111776A (en) Basement and construction method thereof
JP2001164559A (en) Construction method of continuous underground wall guide wall making use of l-type precast member
JP2699819B2 (en) Construction method of precast reinforced concrete foundation block
JP2552860B2 (en) Basement method
JPH0892970A (en) Foundation structure
JP3284009B2 (en) Building with basement
JPH03228921A (en) Execution method for concrete foundation work
KR100386696B1 (en) Foundation concrete pouring method of building structure
JP2906003B2 (en) Construction method of precast retaining wall
JPH11323966A (en) Footing block for retaining wall
JPH022764Y2 (en)

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees