JP2023079536A JP2021193040A JP2021193040A JP2023079536A JP 2023079536 A JP2023079536 A JP 2023079536A JP 2021193040 A JP2021193040 A JP 2021193040A JP 2021193040 A JP2021193040 A JP 2021193040A JP 2023079536 A JP2023079536 A JP 2023079536A
Authority
JP
Japan
Prior art keywords
information
task
management
construction
task management
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2021193040A
Other languages
Japanese (ja)
Other versions
JP7411623B2 (en
Inventor
雅之 山邊
Masayuki Yamabe
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Valqua Ltd
Original Assignee
Valqua Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Valqua Ltd filed Critical Valqua Ltd
Priority to JP2021193040A priority Critical patent/JP7411623B2/en
Priority to TW111140627A priority patent/TW202324228A/en
Publication of JP2023079536A publication Critical patent/JP2023079536A/en
Application granted granted Critical
Publication of JP7411623B2 publication Critical patent/JP7411623B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Vehicle Cleaning, Maintenance, Repair, Refitting, And Outriggers (AREA)

Abstract

To improve efficiency of periodic repair or inspection and improve operation quality.SOLUTION: A construction management method using a computer includes the steps of: creating, by an information processing unit (processing unit 10), two or more task management tables (26) specified with management functions, using task information recorded on a database (task information DB 24); inputting, by an information input unit (14), actual performance information for each task to a specific task management table; reflecting, by the information processing unit, the actual performance information acquired from the information input unit to one of or two or more of other task management tables; and presenting, by an information presentation unit (16), one of or two or more of the task management tables that represent transition of the actual performance information.SELECTED DRAWING: Figure 1

Description

本開示は、たとえば石油精製プラントの定修工事や検査を含む工事計画などの管理を行う管理技術に関する。
The present disclosure relates to a management technique for managing construction plans including regular maintenance work and inspections of oil refining plants, for example.

熱交換システムを含む石油精製プラント設備における定修工事、もしくは定修工事に必要な準備工事がプラントを運用するオーナー会社から協力会社に発注される。斯かる定修工事ではプラントの運転を停止して実行するため、迅速な処理が必要である上、工事の進捗、定修後の検査などを含む安心・安全のための管理が不可欠である。 Regular maintenance work for petroleum refining plant facilities including heat exchange systems, or preparatory work necessary for regular maintenance work, is ordered from the owner company that operates the plant to the cooperating company. In such periodic maintenance work, the operation of the plant is stopped before it is executed, so prompt processing is required, and in addition, management for security and safety, including the progress of the construction work and inspections after the periodic maintenance, is essential.

保守点検などの進捗管理に関し、リスト作成要求を受けたリスト作成手段が確認事項データベースにある保守点検事項を選出してチェックリストを作成し、このチェックリストを端末装置に配信し、このチェックリストに従って実施した保守点検や測定事項などの確認事項について端末装置を通してサーバ装置に取り込んで確認事項データベースに記憶し、要求により端末装置に配信することが知られている(たとえば、特許文献1)。 Regarding progress management of maintenance and inspection, the list creation means that receives the list creation request selects the maintenance and inspection items in the check item database, creates a checklist, distributes this checklist to the terminal device, and follows this checklist. It is known that confirmation items such as performed maintenance inspections and measurement items are taken into a server device through a terminal device, stored in a confirmation item database, and distributed to the terminal device upon request (for example, Patent Document 1).

工事の進捗管理に関し、建設工事にあっては、記憶手段が複数の工程からなる工事計画、工事計画の進捗情報、人または重機を含むリソースの投入計画を蓄積し、実績情報取得手段が各工程の進捗率と、リソースの投入実績とを取得し、歩掛り検討手段がリソースの投入実績から換算される実績歩掛りとリソースの投入計画から換算される計画歩掛りとを比較して工事の今後の歩掛りを決定し、仕事量算出手段が今後の歩掛りに基づいて残り物量や作業量を算出することが知られている(たとえば、特許文献2)。 Regarding construction progress management, in construction work, the storage means accumulates a construction plan consisting of a plurality of processes, progress information on the construction plan, and resource input plans including people and heavy machinery, and the actual information acquisition means accumulates each process. The progress rate and the resource input result are acquired, and the rate review means compares the actual rate converted from the resource input result and the planned rate converted from the resource input plan, and determines the future rate of construction. It is known that the amount of work is determined and the amount of work calculation means calculates the amount of leftovers and the amount of work based on the future commission (for example, Patent Document 2).

建設工事の進捗管理に関し、工事計画支援システムと、検査予定に関するデータを蓄積する検査予定データベース、検査予定と実績を統合した検査進捗データを蓄積する検査予実データベースとを有し、検査の進捗状況を工事進捗の物量に換算した工事進捗データを、工事計画支援システムに伝送する進捗確認システムとを組み合わせ、区画別工程と前事進捗データを統合させ、工事進捗を表すチャート稲妻表示を付した工程表を表示することが知られている(たとえば、特許文献3)。 Regarding the progress management of construction work, we have a construction plan support system, an inspection schedule database that accumulates data related to inspection schedules, and an inspection schedule actual database that accumulates inspection progress data that integrates inspection schedules and actual results. Combined with a progress confirmation system that transmits construction progress data converted to physical quantity of construction progress to the construction plan support system, integrates the process by section and preliminary progress data, and charts showing construction progress A process chart with a lightning bolt display. is known (for example, Patent Document 3).

特開2004-227307号公報Japanese Unexamined Patent Application Publication No. 2004-227307 特開2013-45308号公報JP 2013-45308 A 特開2010-282496号公報JP 2010-282496 A

石油精製プラントに含まれる熱交換システムの定修工事等では、発注者がプラントを運用するオーナー会社、その受注者が工事処理およびその管理を請け負う協力会社である。定修工事の対象が熱交換システムであれば、そのシステムには仕様が異なるなどの複数の熱交換器の他、多数の併設機器が含まれる。定修工事は熱交換システムを停止して行うことから、その停止期間を最小化するための工事期間が求められる。その他、システム仕様、定修のためのコストなどの要素も検討事項として加わる。 In regular maintenance work of a heat exchange system included in a petroleum refining plant, the orderer is the owner company that operates the plant, and the contractor is the cooperating company that undertakes construction processing and management. If the target of regular maintenance work is a heat exchange system, the system includes multiple heat exchangers with different specifications, as well as a large number of parallel devices. Since turnaround work is carried out with the heat exchange system stopped, a construction period is required to minimize the period of stoppage. In addition, factors such as system specifications and costs for regular maintenance are added as considerations.

定修工事の発注者においては、その進捗管理に加え、その進捗に応じた検査などが主要な処理事項である。これに対し、受注者は、発注者のコンセプト、定修対象であるシステムの全体像を把握し、定修計画を策定して工事処理を実行し、発注者の検査を随時に受けて定修工事を完了することが求められる。
定修工事には工事の進捗、報告、検査許可、確認などの複数の工程が存在する。たとえば、ひとつの機器の定修工事が完了すれば、その完了の報告を受けた受注者から検査許可を受け、その検査結果が基準を満たすなど、合格域に達しなければ、次の工程に進むことができない。これは安全面からすれば優れた管理であるが、発注者の検査担当に工事の進捗が委ねられるなどの課題もある。発注者と受注者との間での情報共有が不可欠であるが、これが不十分であると、検査機器の位置の探索などのベーシックな点で工程間の時間的ロスを誘発するという課題がある。
For the orderer of regular maintenance work, in addition to the progress management, inspections according to the progress are major items to be handled. In response to this, the contractor grasps the concept of the ordering party and the overall picture of the system that is subject to periodic maintenance, formulates a periodic maintenance plan, executes the construction process, and undergoes periodic inspections by the ordering party at any time. Construction is required to be completed.
Regular maintenance work includes multiple processes such as progress of construction, reporting, permission for inspection, and confirmation. For example, when regular maintenance work for one piece of equipment is completed, inspection permission is obtained from the contractor who received the completion report. I can't. This is excellent management from a safety point of view, but there are also issues such as entrusting the progress of construction to the person in charge of inspection by the ordering party. Information sharing between the ordering party and the contractor is essential, but if this is insufficient, there is a problem of inducing time loss between processes in basic points such as searching for the location of inspection equipment. .

定修工事の管理では、たとえば工程、進捗状況、工事の品質などの管理種別があり、これらについてそれぞれ作成した管理シートを利用している。そのため1の作業項目に対する管理を行う場合でも、管理種別ごとの管理シートを探し出し、それぞれに同一または関連する事項を記入する必要があった。また、このように別々に作成された管理シートに対して関連付けを行うには手作業で多数の工程を経る必要がある。石油生成プラントにある多数の設備や機器もしくは管理箇所ごとに管理シートが用いられるため、これらの関連性の探索や設定には膨大な労力が必要となる。
また定修工事の管理には、多数の作業項目があるため、複数の管理シートの読み出しにおいて人為的なミスが生じる可能性が高くなるという課題がある。
そして、工事者や管理者が工事の進捗などのステータス情報の他、工事の進捗に関して確認に手間取ると、工事を遅延化させてしまうという課題がある。
In the management of regular maintenance work, for example, there are management types such as process, progress, and construction quality, and management sheets created for each of these are used. Therefore, even when managing one work item, it is necessary to find a management sheet for each management type and enter the same or related items in each sheet. In addition, it is necessary to manually go through a large number of steps to associate the separately created management sheets. Since a management sheet is used for each of a large number of facilities and devices in the petroleum production plant or for each management point, an enormous amount of labor is required to search for and set relationships between these.
In addition, since there are many work items in the management of regular maintenance work, there is a problem that there is a high possibility that human error will occur in reading multiple management sheets.
In addition, if the construction worker or manager takes time to check the status information such as the progress of the construction work as well as the progress of the construction work, there is a problem of delaying the construction work.

斯かる課題について、特許文献1ないし特許文献3に開示された構成では本開示が提示する課題を解決することはできない。 With respect to such problems, the structures disclosed in Patent Documents 1 to 3 cannot solve the problems presented by the present disclosure.

本開示の発明者は、熱交換システムなどの定修工事の管理に関し、複数の管理機能の間でタスクごとの実績情報を共有させることで、進捗管理などの負荷の軽減、定修の時間短縮とともに、信頼性を高めることができるとの知見を得た。 The inventor of the present disclosure relates to the management of regular maintenance work such as a heat exchange system, and by sharing performance information for each task among multiple management functions, it is possible to reduce the load such as progress management and shorten the time required for regular maintenance. In addition, the knowledge that the reliability can be improved was obtained.

そこで、本開示の目的は、上記課題及び上記知見に鑑み、定修工事や検査などの効率化とともに作業品質の向上を図ることにある。
Therefore, in view of the above problems and findings, an object of the present disclosure is to improve the efficiency of regular maintenance work, inspections, and the like, and to improve work quality.

上記目的を達成するため、本開示の工事管理方法の一側面は、コンピュータを用いた工事管理方法であって、情報処理部が、データベースに記録されたタスク情報を利用して、管理機能で特定した二以上のタスク管理テーブルを作成する工程と、情報入力部が、特定の前記タスク管理テーブルにタスクごとの実績情報を入力する工程と、前記情報処理部が、前記情報入力部から取得した前記実績情報を他の前記タスク管理テーブルの何れかまたは二以上に反映させる工程と、情報提示部が、前記実績情報の変遷を表す前記タスク管理テーブルの何れかまたは二以上を提示する工程とを含む。 In order to achieve the above object, one aspect of the construction management method of the present disclosure is a construction management method using a computer, in which an information processing unit uses task information recorded in a database to specify a task specified by a management function. an information input unit inputting performance information for each task into the specific task management table; and an information processing unit acquiring the including a step of reflecting performance information in one or more of the other task management tables; and a step of an information presenting unit presenting one or more of the task management tables representing changes in the performance information. .

この工事管理方法において、前記情報処理部は、前記タスク管理テーブルに対する少なくとも閲覧、入力、改定の処理を許可する権限を設定し、該権限と管理者の階級情報とを関連付ける工程を含む。 In this construction management method, the information processing section includes a step of setting authority for permitting at least viewing, inputting, and revision processing for the task management table, and associating the authority with manager's rank information.

この工事管理方法において、前記情報処理部が、特定の前記タスク管理テーブル内のタスク情報に関連付けられた他の前記タスク管理テーブル内のタスク情報に対し、前記実績情報または前記実績情報に基づいて生成された情報を入力する工程を含む。 In this construction management method, the information processing unit generates the task information in the other task management table associated with the task information in the specific task management table based on the performance information or the performance information. entering the information provided.

上記目的を達成するため、本開示の工事管理システムの一側面は、二以上のタスク情報が格納されたデータベースと、前記データベースに記録されたタスク情報を利用して、管理機能で特定した二以上のタスク管理テーブルを作成する情報処理部と、特定の前記タスク管理テーブルにタスクごとの実績情報を入力する情報入力部とを備え、前記情報処理部が、前記情報入力部から取得した前記実績情報を他の前記タスク管理テーブルの何れかまたは二以上に反映させる。
この工事管理システムにおいて、さらに、前記情報処理部が、前記タスク管理テーブルに対する少なくとも閲覧、入力、改定を許可する権限を設定し、該権限と管理者の階級とを関連付ける。
In order to achieve the above object, one aspect of the construction management system of the present disclosure is a database storing two or more pieces of task information, and using the task information recorded in the database, the two or more pieces specified by the management function and an information input unit for inputting performance information for each task into the specific task management table, wherein the information processing unit receives the performance information acquired from the information input unit is reflected in one or more of the other task management tables.
In this construction management system, the information processing section further sets authority to permit at least viewing, inputting, and revision of the task management table, and associates the authority with the rank of the manager.

この工事管理システムにおいて、さらに、前記実績情報の変遷を表す前記タスク管理テーブルの何れかまたは二以上を提示する情報提示部を備える。 This construction management system further includes an information presenting unit that presents one or more of the task management tables representing changes in the performance information.

上記目的を達成するため、本開示のプログラムの一側面は、コンピュータによって実行されるプログラムであって、データベースに記録されたタスク情報を利用して、管理機能で特定した二以上のタスク管理テーブルを作成する機能と、情報入力部により入力された特定の前記タスク管理テーブルにタスクごとの実績情報を取得する機能と、前記情報入力部から取得した前記実績情報を他の前記タスク管理テーブルの何れかまたは二以上に反映させる機能と、前記実績情報の変遷を表す前記タスク管理テーブルの何れかまたは二以上を情報提示部に提示する機能とを前記コンピュータに実行させる。 In order to achieve the above object, one aspect of the program of the present disclosure is a program executed by a computer, which uses task information recorded in a database to create two or more task management tables specified by the management function. a function to acquire performance information for each task in the specific task management table input by the information input unit; and a function to store the performance information acquired from the information input unit in any of the other task management tables Alternatively, the computer is caused to execute a function of reflecting on two or more and a function of presenting one or more of the task management tables representing changes in the performance information to the information presenting unit.

このプログラムにおいて、前記タスク管理テーブルに対する少なくとも閲覧、入力、改定の処理を許可する権限を設定し、該権限と管理者の階級情報とを関連付ける機能を前記コンピュータに実行させる。 This program causes the computer to execute a function of setting authority for permitting at least viewing, inputting, and revision processing for the task management table, and associating the authority with manager's rank information.

このプログラムにおいて、特定の前記タスク管理テーブル内のタスク情報に関連付けられた他の前記タスク管理テーブル内のタスク情報を読み出す機能と、前記実績情報を読み出し、または前記実績情報に基づいて入力情報を生成する機能と、他の前記タスク管理テーブルに対して前記実績情報または前記入力情報を入力する機能とを前記コンピュータに実行させる。 In this program, a function of reading task information in other task management tables associated with task information in a specific task management table, and reading the performance information or generating input information based on the performance information and a function of inputting the performance information or the input information to the other task management table.

上記目的を達成するため、本開示の工事管理装置の一側面は、コンピュータにより工事を管理する工事管理装置であって、装置筐体と、二以上のタスク情報が格納されたデータベースを備える記憶部と、前記データベースに記録されたタスク情報を利用して、管理機能で特定した二以上のタスク管理テーブルを作成する情報処理部と、特定の前記タスク管理テーブルにタスクごとの実績情報を入力する情報入力部とを備え、前記情報処理部が、前記情報入力部から取得した前記実績情報を他の前記タスク管理テーブルの何れかまたは二以上に反映させる。 In order to achieve the above object, one aspect of the construction management device of the present disclosure is a construction management device that manages construction work using a computer, and includes a device housing and a storage unit that includes a database that stores two or more pieces of task information. an information processing unit that uses the task information recorded in the database to create two or more task management tables specified by the management function; and information that inputs performance information for each task into the specified task management table. an input unit, wherein the information processing unit reflects the performance information acquired from the information input unit in one or more of the other task management tables.

上記目的を達成するため、本開示の記録媒体の一側面によれば、上記の工事管理方法に含まれる前記データベースおよび前記タスク管理テーブル、上記工事管理システムに含まれる前記データベースおよび前記タスク管理テーブル、上記プログラムの何れかまたは二以上を格納している。
To achieve the above object, according to one aspect of the recording medium of the present disclosure, the database and the task management table included in the construction management method, the database and the task management table included in the construction management system, Any one or two or more of the above programs are stored.

本発明によれば、次のような効果が得られる。 ADVANTAGE OF THE INVENTION According to this invention, the following effects are acquired.

(1) 自動生成した管理機能ごとのタスク管理テーブル間において、特定のタスク管理テーブルに対して入力した実績情報を他のタスク管理テーブルに反映させることで、情報入力の作業負荷が軽減でき、プラントの定修工事や検査のタスク間の時間ロスの解消、作業の効率化を図ることができる。 (1) Between the automatically generated task management tables for each management function, by reflecting the performance information entered for a specific task management table in other task management tables, the information input work load can be reduced and the plant It is possible to eliminate time loss between regular maintenance work and inspection tasks and improve work efficiency.

(2) 1つのタスクの管理結果を関連付けられたタスク管理テーブル間に自動で反映させることで、タスク管理テーブルの探索処理や入力対象の確認作業負荷などを軽減できる。 (2) By automatically reflecting the management results of one task between the associated task management tables, it is possible to reduce the workload of searching the task management tables and checking the input targets.

(3) 定修工事や検査の準備に要する時間を短縮でき、工程における進捗情報などの把握が容易になり、その迅速化によって工事および検査の作業品質を高めることができる。
(3) The time required for regular maintenance work and preparation for inspection can be shortened, making it easier to grasp progress information in the process, and the speed up can improve the work quality of construction and inspection.

第1の実施形態に係る工事管理システムの構成例を示す図である。It is a figure which shows the structural example of the construction management system which concerns on 1st Embodiment. タスク管理テーブルの生成機能を示す図である。FIG. 10 is a diagram showing a task management table generation function; 工事管理機能部による実績情報の反映機能を示す図である。It is a figure which shows the reflection function of performance information by a construction management function part. 管理者の認証処理および権限情報の付与の一例を示す図である。FIG. 10 is a diagram illustrating an example of administrator authentication processing and granting of authority information; タスク管理テーブルIの構成例を示す図である。3 is a diagram showing a configuration example of a task management table I; FIG. タスク管理テーブルIIの構成例を示す図である。FIG. 10 is a diagram showing a configuration example of a task management table II; タスク管理テーブルIIIの構成例を示す図である。FIG. 10 is a diagram showing a configuration example of a task management table III; タスク管理テーブルIVの構成例を示す図である。FIG. 10 is a diagram showing a configuration example of a task management table IV; 実績情報の入力および他のタスク管理テーブルへの反映状態の一例を示す図である。FIG. 10 is a diagram showing an example of input of performance information and a state of reflection to another task management table; 付属付情報の構成例を示す図である。It is a figure which shows the structural example of attachment information. 実績情報の入力および他のタスク管理テーブルへの反映状態の他の例を示す図である。FIG. 10 is a diagram showing another example of the input of performance information and the state of reflection to other task management tables; 工事管理処理の一例を示すフローチャートである。It is a flow chart which shows an example of construction management processing. 第2の実施形態に係る工事管理システムの構成例を示す図である。It is a figure which shows the structural example of the construction management system which concerns on 2nd Embodiment. 実績情報の入力および他のタスク管理テーブルへの反映状態の一例を示す図である。FIG. 10 is a diagram showing an example of input of performance information and a state of reflection to another task management table; 工事管理処理の一例を示すフローチャートである。It is a flow chart which shows an example of construction management processing.

〔第1の実施形態〕
図1は、第1の実施形態に係る工事管理システムの構成例を示している。図1に示す構成は一例であり、本開示の技術は斯かる構成に限定されない。
[First embodiment]
FIG. 1 shows a configuration example of a construction management system according to the first embodiment. The configuration shown in FIG. 1 is an example, and the technology of the present disclosure is not limited to such a configuration.

この工事管理システム2は、たとえば石油精製プラントに設置される熱交換システムの定修工事などにおいて、検査前の工事や検査処理、その後の復旧処理などの工程、進捗、検査結果の記録などの管理に用いる帳票類の生成や、工事や検査などを実行する管理者への通知機能を備える。またこの工事管理システム2は、生成された複数の帳票類間の関連するタスクに対し、管理者によって入力された工事の進捗や検査結果などの実績情報を自動的に反映させる機能を備える。これらの帳票類の生成処理や実績情報の反映処理、管理者間での情報共有管理処理は、管理サーバ4を構成するコンピュータによって実行される。この工事管理システム2は、たとえば図1に示すように、管理サーバ4と情報端末6がネットワーク8を利用して通信し、工事管理処理に必要な入力情報と管理情報などの通知情報のやりとりを行っている。 This construction management system 2 manages processes such as construction before inspection, inspection processing, recovery processing after that, progress, inspection results, etc. Equipped with a function to generate documents used for construction and to notify administrators who execute construction and inspections. The construction management system 2 also has a function of automatically reflecting performance information, such as construction progress and inspection results, input by the manager, to related tasks among a plurality of generated forms. A computer that constitutes the management server 4 executes the generation processing of these forms, the reflection processing of performance information, and the information sharing management processing among administrators. In this construction management system 2, for example, as shown in FIG. 1, a management server 4 and an information terminal 6 communicate with each other using a network 8 to exchange input information necessary for construction management processing and notification information such as management information. Is going.

<管理サーバ4>
管理サーバ4は、本開示の工事管理装置の一例であり、定修工事やプラント設備の検査処理などに用いる複数の管理テーブルを生成するとともに、これらの管理テーブル間で工事情報や検査情報などを含む実績情報の反映処理を行う装置である。この管理サーバ4は、プロセッサやメモリ、入出力部(I/O)、通信部などを備えたコンピュータであって、たとえば処理部10や記憶部12、情報入力部14、情報提示部16が構成されている。
プロセッサは、メモリに格納されたOS(Operating System)や工事管理プログラムなど、各種プログラムの演算処理を実行する機能部であり、処理部10を構成する。
メモリは、ROM(Read-Only Memory)、RAM(Random-Access Memory)などの記憶素子で構成されており、本開示の記録媒体の一例である。メモリは、たとえばOSや工事管理プログラムなどの演算処理を行うワークエリアが構成されるほか、生成するテーブルやデータベースなどを格納する記憶部12が構成される。
入出力部(I/O)は、情報入力部14や情報提示部16が接続され、プロセッサの制御により管理サーバ4への入力情報の取込みや情報の出力を行うインターフェースである。
通信部は、プロセッサの制御により情報端末6との通信や、図示しない情報源との通信を行う。この通信は無線または有線の何れであってもよい。
<Management Server 4>
The management server 4 is an example of the construction management apparatus of the present disclosure, and generates a plurality of management tables used for regular maintenance work and inspection processing of plant equipment, and also exchanges construction information, inspection information, etc. between these management tables. It is a device that performs reflection processing of performance information including. The management server 4 is a computer equipped with a processor, a memory, an input/output unit (I/O), a communication unit, etc., and is composed of, for example, a processing unit 10, a storage unit 12, an information input unit 14, and an information presentation unit 16. It is
The processor is a functional unit that executes arithmetic processing of various programs such as an OS (Operating System) and a construction management program stored in the memory, and constitutes the processing unit 10 .
The memory is composed of storage elements such as ROM (Read-Only Memory) and RAM (Random-Access Memory), and is an example of the recording medium of the present disclosure. The memory includes, for example, a work area for performing arithmetic processing such as an OS and a construction management program, and also includes a storage unit 12 for storing generated tables, databases, and the like.
The input/output unit (I/O) is an interface to which the information input unit 14 and the information presentation unit 16 are connected and which takes in input information to the management server 4 and outputs information under the control of the processor.
The communication unit communicates with the information terminal 6 and an information source (not shown) under the control of the processor. This communication can be either wireless or wired.

処理部10は、たとえば工事管理プログラムの演算処理により、管理テーブルの自動生成処理を行うテーブル生成機能部20と、情報端末6を通じて入力される情報を特定の管理テーブル内に格納するとともに、この情報を関連する管理テーブルに反映させる機能を含む工事管理機能部22が構成される。
記憶部12には、たとえば定修工事や検査の工程やその項目を表すタスク情報が格納されたタスク情報データベース(DB)24や、テーブル生成機能部20で生成され、工事や検査の進捗や品質などをタスク情報ごとに管理するタスク管理テーブル26が格納される。
The processing unit 10 stores information input through a table generation function unit 20 that automatically generates a management table and an information terminal 6 in a specific management table, and stores this information in a specific management table. A construction management function unit 22 is configured that includes a function of reflecting the information in the related management table.
The storage unit 12 includes, for example, a task information database (DB) 24 that stores task information representing the processes and items of regular maintenance work and inspection, and a table generation function unit 20 that stores the progress and quality of the work and inspection. A task management table 26 that manages each task information is stored.

情報入力部14は、管理サーバ4に対して直接または情報端末6を介して入力する情報、管理者のID番号などの認証情報を入力する手段の一例であり、たとえばキーボードやタッチパネルなどの操作手段や情報端末6と通信する機能部を含む。
情報提示部16は、工事管理の進捗や結果情報などの表示やタスク管理テーブル26などの通知情報を表示する手段の一例であり、たとえばLCD(Liquid Crystal Display)などの情報提示機器を構成する。
The information input unit 14 is an example of means for inputting information directly or via the information terminal 6 to the management server 4 and authentication information such as an administrator's ID number. and information terminal 6.
The information presentation unit 16 is an example of means for displaying progress and result information of construction management and notification information such as the task management table 26, and constitutes an information presentation device such as an LCD (Liquid Crystal Display).

<情報端末6>
情報端末6は割り当てられた機能を以て、第1の端末30と複数の第2の端末32(=作業者端末32-1、32-2、・・・、32-m)とに分類できる。この情報端末6には、たとえば携帯電話機やモバイルPC(Personal Computer)、その他、検査作業に利用する専用端末装置などが含まれる。第1の端末30は工事の品質管理や検査処理を担当する第1の管理者に割り当てられ、第2の端末32は工事の施工を担当する第2の管理者に割り当てられる。これらの管理者はたとえば、プラントオーナーや定修工事や検査を担当する協力会社にあって、その管理権限を有する企業、人などである。
<Information terminal 6>
The information terminals 6 can be classified into a first terminal 30 and a plurality of second terminals 32 (=worker terminals 32-1, 32-2, . . . , 32-m) according to assigned functions. The information terminal 6 includes, for example, a mobile phone, a mobile PC (Personal Computer), and a dedicated terminal device used for inspection work. The first terminal 30 is assigned to a first manager who is in charge of quality control and inspection processing of construction work, and the second terminal 32 is assigned to a second manager who is in charge of construction work. These administrators are, for example, the plant owner, a subcontractor in charge of regular maintenance work and inspection, and a company or person who has the management authority.

第1の端末30は、処理部302、情報提示部304、情報入力部306などを装置筐体内に備える。処理部302はプロセッサ、記憶部および入出力部を備え、管理サーバ4と連係して記憶部にあるOSや工事管理プログラムを実行する。情報提示部304は、管理サーバ4から通知されたタスク管理テーブル26などの通知情報を表示させる液晶モニタなどを備える。情報入力部306は、キーボードやマウスなどの他、タッチセンサなどを含む。 The first terminal 30 includes a processing unit 302, an information presentation unit 304, an information input unit 306, etc. inside the device housing. The processing unit 302 includes a processor, a storage unit, and an input/output unit, and cooperates with the management server 4 to execute the OS and construction management program stored in the storage unit. The information presentation unit 304 includes a liquid crystal monitor or the like for displaying notification information such as the task management table 26 notified from the management server 4 . Information input unit 306 includes a keyboard, a mouse, a touch sensor, and the like.

第2の端末32には、たとえば処理部322、情報入力・提示部324などを装置筐体内に備える。処理部322はプロセッサ、記憶部および入出力部を備え、管理サーバ4と連係して記憶部にあるOSや工事管理プログラムを実行する。情報入力・提示部324は情報選択などの情報入力や情報提示に用いられる。情報入力・提示部324の画面部には第1の端末30と同様に、工事・検査に関わる通知情報などが表示される。 The second terminal 32 includes, for example, a processing unit 322, an information input/presentation unit 324, and the like in the device housing. The processing unit 322 includes a processor, a storage unit, and an input/output unit, and cooperates with the management server 4 to execute the OS and construction management program stored in the storage unit. The information input/presentation unit 324 is used for information input such as information selection and information presentation. The screen portion of the information input/presentation unit 324 displays notification information related to construction/inspection, etc., in the same manner as the first terminal 30 .

<ネットワーク8>
ネットワーク8は、たとえば有線または無線により管理サーバ4と管理者の情報端末6との間でデータ通信させる手段の一例である。このネットワーク8は、たとえば公衆回線を利用してもよく、またはプラント内のみでアクセス可能に制限されたプライベート回線などを利用すればよい。
<Network 8>
The network 8 is an example of means for data communication between the management server 4 and the information terminal 6 of the administrator, for example, by wire or wirelessly. This network 8 may use, for example, a public line, or a private line that is accessible only within the plant.

<テーブル生成機能部について>
図2は、テーブル生成機能部の構成例を示している。
テーブル生成機能部20は、たとえば図2に示すように、タスク情報DB24に格納されたタスク情報を利用して、設定された管理機能ごとにタスク管理テーブル26を生成する。この工事管理処理では、たとえば4つの管理機能について、4つのタスク管理テーブル(I~IV)26-1、26-2、26-3、26-4を生成する。タスク管理テーブル26は、プラント設備にある機器、または機器を構成する部品もしくは機能構成部など、工事の管理対象ごとにそれぞれ生成される。
タスク情報は、たとえば脚場組立や保温解体、防食塗装、補修など、定修工事において行う作業工程や、プラント設備の検査処理項目などであり、工事や検査の開始や完了、進捗状況などのチェックを行う管理項目の一例である。
<Regarding the table generation function part>
FIG. 2 shows a configuration example of the table generation function unit.
For example, as shown in FIG. 2, the table generation function unit 20 uses the task information stored in the task information DB 24 to generate a task management table 26 for each set management function. In this construction management process, for example, four task management tables (I to IV) 26-1, 26-2, 26-3, 26-4 are generated for four management functions. The task management table 26 is generated for each construction management object, such as a device in the plant facility, or a component or functional component that constitutes the device.
Task information includes, for example, work processes to be performed in regular maintenance work, such as scaffolding assembly, thermal insulation dismantling, anti-corrosion coating, and repairs, and inspection processing items for plant equipment. This is an example of a management item for performing

タスク情報DB24は、定修工事や検査で行う全てのタスク情報が格納されるとともに、タスク情報に対して対応する機器情報、管理機能情報などが関連付けられて格納されている。そしてタスク管理テーブル26の作成処理において、テーブル生成機能部20は、たとえば入力もしくは設定された機器情報および管理機能情報に関連するタスク情報を読み出し、その情報を各タスク管理テーブル26に格納していく。 The task information DB 24 stores all task information to be performed in regular maintenance work and inspections, and also stores device information, management function information, etc. corresponding to the task information in association with each other. Then, in the process of creating the task management table 26, the table generation function unit 20 reads, for example, task information related to the input or set device information and management function information, and stores the information in each task management table 26. .

なお、ここでは、4つの管理機能について、対応するタスク管理テーブル(I~IV)26-1、26-2、26-3、26-4が生成される場合を示したがこれに限らない。管理機能は、プラント設備ごとに設定してもよく、またはプラントオーナーや工事の施工会社が任意に設定するほか、法律の規定などに基づいて義務化された工事や検査内容に基づいて管理機能の数を設定すればよい。
そのほか、テーブル生成機能部20には、たとえば図示しないタスク情報テーブルやタスク情報の選択処理に利用する実行タスク選択テーブルを備えてもよい。このタスク情報テーブルは、たとえば実行するタスク情報が管理機能ごとに収集されており、タスク管理テーブル26の自動生成に利用するデータテーブルの一例である。
実行タスク選択テーブルは、タスク情報テーブルに格納されたタスク情報に対して、機器ごとにタスク情報を選択させるテーブルの一例である。
It should be noted that although the case where the corresponding task management tables (I to IV) 26-1, 26-2, 26-3, and 26-4 are generated for the four management functions is shown here, the present invention is not limited to this. The management function may be set for each plant facility, or may be set arbitrarily by the plant owner or the construction company. You can set the number.
In addition, the table generation function unit 20 may include, for example, a task information table (not shown) and an execution task selection table used for selection processing of task information. This task information table is an example of a data table used for automatically generating the task management table 26, in which task information to be executed is collected for each management function, for example.
The execution task selection table is an example of a table for selecting task information for each device from the task information stored in the task information table.

<工事管理機能部について>
図3は、工事管理機能部による実績情報の反映機能を示している。図3に示すタスク管理テーブルの数や実績情報の内容および反映先情報などは一例である。
工事管理機能部22は、定修工事や検査において生じる実績情報について情報を共有させる機能を備える。この工事管理処理では、たとえば図3に示すように、工事管理処理の対象として、特定の機器について設定された4つのタスク管理テーブル(I~IV)26-11、26-21、26-31、26-41間で実績情報を反映させる状態を示している。
各タスク管理テーブル(I~IV)26-11、26-21、26-31、26-41には、たとえばタスク情報に対して入力された実績情報について、反映先を示す指示情報が設定されている。この指示情報は、テーブル生成機能部20に予め設定されるほか、タスク情報に設定されてもよい。
<About the construction management function department>
FIG. 3 shows the performance information reflecting function by the construction management function unit. The number of task management tables, the contents of performance information, the reflection destination information, and the like shown in FIG. 3 are examples.
The construction management function unit 22 has a function of sharing information about performance information generated in regular maintenance work and inspections. In this construction management process, for example, as shown in FIG. 26-41 shows the state in which the performance information is reflected.
In each of the task management tables (I to IV) 26-11, 26-21, 26-31, and 26-41, for example, instruction information indicating where to reflect performance information input for task information is set. there is This instruction information is preset in the table generation function unit 20, and may be set in task information.

工事管理機能部22は、たとえば設定された指示情報に基づき、タスク管理テーブルI26-11に対して入力された実績情報である検査・許可情報をタスク管理テーブル(II~IV)26-21、26-31、26-41のいずれか、または全部に反映させる。また工事管理機能部22は、たとえばタスク管理テーブルIV26-41に対して入力された実績情報である工事情報をタスク管理テーブル(I~III)26-11、26-21、26-31のいずれか、または全部に反映させる。 For example, based on the set instruction information, the construction management function unit 22 stores the inspection/permission information, which is the performance information input to the task management table I26-11, into the task management tables (II to IV) 26-21 and 26. -31, 26-41, or all of them. Also, the construction management function unit 22 stores the construction information, which is the performance information input to the task management table IV26-41, in one of the task management tables (I to III) 26-11, 26-21, and 26-31. , or reflected in all.

<管理者の権限情報について>
図4は、管理者の認証処理および権限情報の付与について示している。図4に示す構成は一例である。
この工事管理システム2では、たとえばプラント施設の敷地内の入場時などに名前や所属会社名などのID(Identification)の入力や身分証などの提示により認証処理を行うとともに、定修工事や検査の対象機器もしくは対象機能部においても認証処理を行う。この認証処理では、管理者が定修工事や検査などの実施を行える者か、タスク管理テーブル26に対して実績情報の入力を行う権限を有する者かの判断を行う。
<Regarding administrator authority information>
FIG. 4 shows administrator authentication processing and granting of authority information. The configuration shown in FIG. 4 is an example.
In this construction management system 2, for example, when entering the premises of a plant facility, an ID (Identification) such as a name or company name is entered, or an identification card is presented to perform authentication processing. Authentication processing is also performed in the target device or target function unit. In this authentication process, it is determined whether the administrator is a person who can carry out regular maintenance work or inspections, or a person who has the authority to input performance information to the task management table 26 .

作業対象の機器34には、たとえば図4Aに示すように、機器34の筐体などに直接またはその付近にIDタグ36が設置されている。このIDタグ36は、たとえば二次元コードなどで構成されており、端末32のカメラなどで読み取ることで、管理サーバ4や図示しないデータベースなどにアクセスして、機器情報やこの機器情報に関連付けられた作業情報などを取得可能になっている。
工事管理機能部22では、たとえばIDタグ36を読み取った端末32が管理サーバ4にアクセスすると、端末32に格納された管理者のID情報などを参照するほか、あらためて管理者に対して認証に必要な情報を入力させる。そして工事管理機能部22は、たとえば認証処理が完了すると、管理者の階級に応じた権限を付与する。この権限の付与では、たとえば図4Bに示すように権限テーブル38を利用すればよい。この権限テーブル38には、たとえば認証した管理者の階級情報と工事管理処理の権限情報が関係付けられている。この権限情報は、たとえば少なくとも定修工事や検査において実行可能な処理の範囲やタスク管理テーブル26に対して実績情報の入力が可能か否かを表している。
For example, as shown in FIG. 4A, an ID tag 36 is installed directly on or near the housing of the equipment 34 to be worked on. The ID tag 36 is composed of, for example, a two-dimensional code, and is read by the camera of the terminal 32 or the like to access the management server 4 or a database (not shown). Work information etc. can be obtained.
For example, when the terminal 32 that has read the ID tag 36 accesses the management server 4, the construction management function unit 22 refers to the ID information of the manager stored in the terminal 32, and also asks the manager again for authentication. information. Then, for example, when the authentication process is completed, the construction management function unit 22 grants authority according to the manager's rank. For granting this authority, for example, an authority table 38 may be used as shown in FIG. 4B. In this authority table 38, for example, rank information of authenticated managers and authority information for construction management processing are associated. This authority information indicates, for example, at least the range of executable processing in regular maintenance work and inspection, and whether or not performance information can be input to the task management table 26 .

次に、定修工事や検査において利用される機能ごとのタスク管理テーブルの構成について説明する。 Next, the configuration of the task management table for each function used in regular maintenance work and inspection will be described.

<タスク管理テーブルI>
図5は、タスク管理テーブルIの構成例を示している。図5に示す構成は一例である。
このタスク管理テーブルIは、たとえば検査の進捗状態の管理に用いられる検査進捗管理表の一例であり、機器やプラント設備ごとに複数のデータ26-11、26-12、・・・26-1Nを備える。タスク管理テーブルIには、たとえばタスク情報部40、装置名部41、反映部42、工事情報部43、管理情報入力部44、完了監視部45、権限部46が含まれる。
<Task management table I>
FIG. 5 shows a configuration example of the task management table I. As shown in FIG. The configuration shown in FIG. 5 is an example.
This task management table I is an example of an inspection progress management table used for managing the progress of inspection, for example, and a plurality of data 26-11, 26-12, . . . Prepare. The task management table I includes, for example, a task information section 40, a device name section 41, a reflection section 42, a construction information section 43, a management information input section 44, a completion monitoring section 45, and an authority section 46.

タスク情報部40は、検査対象となる1または複数のタスク情報が格納される領域である。このタスク情報部40には、たとえば検査を行う工程順序で、タスク情報B2、B3、「前検査」、C1、D1・・・などが並べて配置されている。さらにタスク情報部40には、たとえばタスク情報を分類する分類情報が設定されてもよい。 The task information section 40 is an area in which one or more pieces of task information to be inspected are stored. In this task information section 40, for example, task information B2, B3, "pre-inspection", C1, D1, . Further, classification information for classifying task information may be set in the task information section 40, for example.

装置名部41には、検査進捗管理の対象となる機器の装置名が格納される。
反映部42には、同一の装置に対して生成された他のタスク管理テーブルII、III、IVとの間で入力情報を相互に連動させるか否かを設定指示する情報が格納される。反映部42は、たとえばII、III、IVに対して「○」が設定されることで、検査進捗管理の判断結果や日付情報などを他のタスク管理テーブルII、III、IVに反映させる。
工事情報部43は、管理者により管理サーバ4の情報入力部14や各情報端末6の入力機能を利用して、テキスト情報や写真などのデータを入力可能な領域となっている。この工事情報部43には、たとえば定修工事における具体的な作業内容や検査の手順や注意点などのほか、機器特有の伝達情報などが格納されればよい。
The device name field 41 stores the device name of the device subject to inspection progress management.
The reflection unit 42 stores information for setting and instructing whether or not input information is mutually linked with other task management tables II, III, and IV generated for the same device. The reflecting unit 42, for example, by setting “◯” to II, III, and IV, reflects the determination result of examination progress management, date information, and the like in other task management tables II, III, and IV.
The construction information section 43 is an area in which data such as text information and photographs can be input by the manager using the information input section 14 of the management server 4 and the input functions of the information terminals 6 . The construction information section 43 may store, for example, specific work contents, inspection procedures, points to note, etc. in regular maintenance work, as well as transmission information unique to the equipment.

管理情報入力部44は、設定されたタスク情報に対し、その進捗状況やタスクが完了したか否か、その日付などの情報が格納される領域である。この管理情報入力部44は、たとえばタスク情報ごとに、他のタスク管理テーブルII、III、IVから実績情報が反映される部分については、「空白」となっており、実績情報を直接入力する部分についてはチェックボックスなどが設定されればよい。 The management information input section 44 is an area for storing information such as the progress status of the set task information, whether the task has been completed, and the date. In this management information input section 44, for example, for each task information, the portion where performance information is reflected from other task management tables II, III, and IV is "blank", and the portion for directly inputting performance information is blank. A check box or the like may be set for .

完了監視部45は、タスク管理テーブルIに設定された全てもしくは所定数のタスク情報の処理が完了したか否かについて、管理者によるチェック結果が入力される領域である。
権限部46は、タスクの完了判断や、管理情報入力部44および完了監視部45に対するチェック結果の入力処理を行える担当者に必要な権限情報が設定される。工事管理処理では、たとえばタスク管理テーブルIに対する情報入力において、その担当者が必要な権限を有していない場合には、入力情報の無効化もしくは情報の入力を禁止する処理を実行すればよい。
The completion monitoring section 45 is an area into which a check result by the administrator is input as to whether or not all or a predetermined number of task information set in the task management table I have been completed.
The authority section 46 is set with necessary authority information for a person in charge who can judge completion of a task and input processing of check results to the management information input section 44 and the completion monitoring section 45 . In the construction management process, for example, when inputting information to the task management table I, if the person in charge does not have the necessary authority, the input information may be invalidated or the input of information may be prohibited.

<タスク管理テーブルII>
図6は、タスク管理テーブルIIの構成例を示している。
このタスク管理テーブルII26-2は、たとえば定修工事や検査処理の作業予定の管理に用いる工程表であって、機器やプラント設備ごとに複数のデータ26-21、26-22、・・・26-2Nが含まれる。タスク管理テーブルIIには、たとえば日付部50、装置名部51、分類部52、タスク情報部53、工程管理部54が含まれる。
<Task management table II>
FIG. 6 shows a configuration example of the task management table II.
This task management table II 26-2 is a process chart used, for example, for managing work schedules such as regular maintenance work and inspection processing, and includes a plurality of data 26-21, 26-22, . -2N is included. The task management table II includes, for example, a date section 50, an apparatus name section 51, a classification section 52, a task information section 53, and a process management section .

日付部50は、定修工事や検査を行うカレンダー情報が設定されており、たとえば月日の記入枠を備える。
装置名部51は、監視対象の装置名を設定する領域である。
分類部52は、タスク情報の分類情報が格納される領域の一例であり、定修工事や検査の段階を示す情報が含まれる。
The date section 50 is set with calendar information for regular maintenance work and inspection, and includes, for example, a date entry frame.
The device name part 51 is an area for setting the name of the device to be monitored.
The classification section 52 is an example of an area in which classification information of task information is stored, and includes information indicating the stage of regular maintenance work and inspection.

タスク情報部53は、定修工事や検査の工程情報が格納される領域である。このタスク情報部53には、たとえば設定された順序を維持しつつ、処理内容に基づいて同時に実行可能なタスク情報を縦方向に配列するように調整処理が行われてもよい。
工程管理部54は、タスク情報部53に配列されたタスク情報に対して設定される処理の実行スケジュールについて、日ごと、または半日ごとの工程がカレンダー情報に表示される。この工程管理部54は、日数を表す枠内にタスク情報を表示する場合を示したが、斯かる表示状態に限らない。タスク管理テーブルIIでは、たとえばタスク情報部53のタスク情報を色分けや模様分けをするとともに、各タスク情報に対応した工程管理部54の枠内に同一の色や模様を付して表示してもよい。また工程管理部54には、工程およびカレンダー情報に沿って情報入力エリア55を備える。斯かる情報入力エリア55は、作業工程の実績情報として、工程開始日や完了日、進捗状況などが記入可能となっている。
The task information section 53 is an area in which process information of regular maintenance work and inspection is stored. Adjustment processing may be performed in the task information section 53 so as to vertically arrange task information that can be executed simultaneously based on the processing content while maintaining the set order, for example.
The process control unit 54 displays daily or half-day processes in the calendar information for the process execution schedule set for the task information arranged in the task information unit 53 . Although the process control unit 54 displays the task information within the frame representing the number of days, the display state is not limited to this. In the task management table II, for example, the task information in the task information section 53 is classified by color or pattern, and the same color or pattern is displayed in the frame of the process management section 54 corresponding to each task information. good. The process control section 54 also has an information input area 55 along with process and calendar information. In the information input area 55, it is possible to enter the process start date, completion date, progress status, etc. as actual information of the work process.

<タスク管理テーブルIII>
図7は、タスク管理テーブルIIIの構成例を示している。
このタスク管理テーブルIII26-3は、たとえば定修工事や検査処理の日毎の工程情報を通知するとともにその作業結果を格納して作業の進捗状況などを管理する日報の一例であって、機器やプラント設備ごとに複数のデータ26-31、26-32、・・・26-3Nで構成される。タスク管理テーブルIIIには、たとえばヘッダー部60、装置名部61、タスク情報部62、管理情報部63を備える。
<Task Management Table III>
FIG. 7 shows a configuration example of the task management table III.
This task management table III26-3 is an example of a daily report that notifies, for example, daily process information of regular maintenance work and inspection processing, stores the work results, and manages the progress of the work. Each facility is composed of a plurality of data 26-31, 26-32, . . . 26-3N. The task management table III includes a header section 60, a device name section 61, a task information section 62, and a management information section 63, for example.

ヘッダー部60は、日報の見出し情報を格納する領域であって、たとえば管理者もしくは日報に情報入力を行う担当者情報や日付情報、日報に表示される情報の説明などが含まれる。
装置名部61は、監視対象の装置名が格納される領域である。
タスク情報部62は、定修工事や検査の工程情報、タスクの分類情報が格納される領域である。
管理情報部63は、タスク情報の進捗状況を格納する領域であり、管理者により予定情報として工事結果や検査結果の情報、完了日のほか、プラントオーナーからの着工許可情報などが格納される。予定情報には、たとえば工程の開始である「新規」、工程の進行中である「継続」、工程の終了である「完了」について、それぞれ符号が割当てられている。
The header section 60 is an area for storing the headline information of the daily report, and includes, for example, information about the administrator or the person in charge of inputting information to the daily report, date information, description of information displayed in the daily report, and the like.
The device name part 61 is an area in which the name of the device to be monitored is stored.
The task information section 62 is an area in which process information of regular maintenance work and inspection, and task classification information are stored.
The management information section 63 is an area for storing the progress of task information, and stores information on construction results and inspection results as schedule information by the manager, completion dates, construction start permission information from the plant owner, and the like. In the schedule information, for example, codes are assigned to "new" indicating the start of a process, "continuing" indicating that the process is in progress, and "completion" indicating the end of the process.

<タスク管理テーブルIV>
図8は、タスク管理テーブルIVの構成例を示している。
このタスク管理テーブルIV26-4は、たとえば定修工事や検査処理の監視結果を格納する工事品質管理表であって、機器やプラント設備ごとに複数のデータ26-41、26-42、・・・26-4Nが含まれる。タスク管理テーブルIVには、たとえば分類部70、タスク情報部71、確認内容部72、検査内容部73、開始情報部74、監視結果部75、権限部76を備える。
<Task Management Table IV>
FIG. 8 shows a configuration example of the task management table IV.
This task management table IV26-4 is a construction quality management table that stores, for example, monitoring results of regular maintenance work and inspection processing, and includes a plurality of data 26-41, 26-42, . 26-4N included. The task management table IV includes, for example, a classification section 70, a task information section 71, a confirmation content section 72, an inspection content section 73, a start information section 74, a monitoring result section 75, and an authority section .

分類部70は、タスク情報の分類情報が格納される領域の一例であり、定修工事や検査の段階を示す情報が含まれる。
タスク情報部71は、定修工事や検査の工程情報が格納される領域である。
確認内容部72は、定修工事、検査での処理内容や注意事項などを記入可能な情報伝達領域である。この確認内容部72には、たとえば管理者が作業の担当者に対して与える指示内容や、過去の定修工事、検査での指摘事項などのテキスト情報が格納される。
The classification section 70 is an example of an area in which classification information of task information is stored, and includes information indicating stages of regular maintenance work and inspection.
The task information section 71 is an area in which process information of regular maintenance work and inspection is stored.
The confirmation content section 72 is an information transmission area in which maintenance work, process content and precautions in inspections can be entered. The confirmation content section 72 stores, for example, text information such as the content of instructions given by the manager to the person in charge of the work, past regular maintenance work, and items pointed out in inspections.

検査内容部73は、検査処理における実行手段を指定する指示情報が格納される。この指示情報には、たとえば管理者が直接見る、もしくは情報端末6のカメラを起動させ、撮影した画像を確認するなどの指示である「目視」や、報告書などで確認する「書類」などが含まれる。また検査内容部73の情報は、たとえばタスク管理テーブルIVを読み込んだ情報端末6への指示情報が含まれており、「目視」の情報である場合に、自動的にカメラアプリケーションを起動させてもよい。
開始情報部74は、定修工事、検査の着工開始日などを格納する領域であり、チェックした日付情報が格納されるほか、担当者や管理者の社名などが記録されてもよい。
監視結果部75は、定修工事、検査のチェック結果を格納する領域である。この監視結果部75には、たとえば管理者が直接入力するものや、他のタスク管理テーブルI、II、IIIに入力された情報が反映するものがある。
権限部76は、タスクの完了判断や、監視結果部75に対するチェック結果の入力処理を行える担当者の権限情報が設定される。工事管理処理では、たとえばタスク管理テーブルIVに対する情報入力において、その担当者が必要な権限を有していない場合には、入力情報の無効化もしくは情報入力を禁止する処理を実行すればよい。
The inspection content part 73 stores instruction information that designates execution means in inspection processing. This instruction information includes, for example, "visual observation", which is an instruction for the administrator to directly view or activate the camera of the information terminal 6 to check the captured image, and "documents" to be checked in a report or the like. included. The information in the inspection content section 73 includes, for example, instruction information to the information terminal 6 that has read the task management table IV. good.
The start information part 74 is an area for storing the start date of regular maintenance work and inspection, and in addition to storing the date information of the check, the name of the person in charge or the company of the manager may be recorded.
The monitoring result section 75 is an area for storing check results of regular maintenance work and inspections. The monitoring result part 75 includes, for example, a part directly input by an administrator and a part reflecting information input to other task management tables I, II, and III.
The authority section 76 is set with authority information of a person in charge who can judge completion of a task and input processing of check results to the monitoring result section 75 . In the construction management process, for example, in information input to the task management table IV, if the person in charge does not have the necessary authority, the input information may be invalidated or the information input prohibited.

<実績情報の入力>
図9は、実績情報の入力および他のタスク管理テーブルへの反映状態を示している。図9に示す処理内容は一例である。
ここでは、特定の工程における品質チェックおよび完了の実績情報をタスク管理テーブルIVに入力する場合を示している。
工事管理機能部22は、たとえば定修工事の施工およびタスク情報ごとの品質確認および完了確認を行う管理者が第2の端末32を通じてアクセスしてくると、タスク管理テーブルIVを通知して、タスク情報ごとの情報入力を可能にする。タスク管理テーブルIVには、たとえば図9Aに示すように、タスク情報ごとに開始情報部74に工事の着工開始日が入力されるとともに、監視結果部75に工事の品質確認の完了を表す情報や日付などの実績情報RA、RBなどが入力される。この定修工事に対する品質管理処理は、設定されているタスク情報順に実行されており、1のタスク情報に対する工事や検査が完了すると次のタスク情報に移行していく。
また品質確認では、タスク情報ごとに、検査内容部73の指示情報80を読み出し、この指定された内容で監視処理を行う。ここでは、「目視」の指示に基づき、管理者が肉眼で品質確認するとともに、第2の端末32のカメラを起動させて機器またはその機能部などの監視対象の画像を記録する。
<Enter performance information>
FIG. 9 shows how performance information is input and how it is reflected in other task management tables. The processing content shown in FIG. 9 is an example.
Here, a case is shown in which quality check and completion record information in a specific process are input to the task management table IV.
The construction management function unit 22 notifies the task management table IV when, for example, an administrator who carries out regular maintenance work and confirms the quality and completion of each task information accesses through the second terminal 32, and notifies the task management table IV. Enable information entry for each information. In the task management table IV, for example, as shown in FIG. 9A, the construction start date is input to the start information section 74 for each task information, and the monitoring result section 75 contains information indicating the completion of quality confirmation of the construction work. Performance information RA, RB, etc. such as dates are input. The quality control processing for this periodic maintenance work is executed in the order of the set task information, and when the construction or inspection for one piece of task information is completed, the process proceeds to the next task information.
In the quality check, the instruction information 80 of the inspection content section 73 is read out for each task information, and the monitoring process is performed according to the specified content. Here, based on the "visual inspection" instruction, the administrator checks the quality with the naked eye, and activates the camera of the second terminal 32 to record the image of the monitored object such as the device or its functional unit.

工事管理機能部22は、たとえばタスク管理テーブルIVに入力された品質確認の実績情報RAやRBなどを読み出すとともに、予め設定された反映先の指示情報に基づいて工事の工程を管理するタスク管理テーブルIIを読み出す。そして工事管理機能部22は、たとえば図9Bに示すように、取得した実績情報RAやRBを解析し、期間情報を棒グラフ状で表す実績情報を生成して、情報入力エリア55に反映させる。この期間情報は、たとえばタスク情報ごとの品質管理で入力した着工開始日と実績情報RA、RBの完了日を利用して生成すればよい。さらに工事管理機能部22は、実績情報RA、RBに基づく期間情報を反映させると、カレンダー機能などの日付もしくは曜日情報を利用して、同日もしくは同じ曜日に実行予定の次のタスク情報同士を連結して示す、所謂稲妻線81を生成して表示してもよい。 The construction management function unit 22 reads, for example, quality confirmation result information RA and RB input to the task management table IV, and also creates a task management table for managing the construction process based on preset reflection destination instruction information. Read II. Then, as shown in FIG. 9B, the construction management function unit 22 analyzes the acquired performance information RA and RB, generates performance information representing period information in a bar graph, and reflects it in the information input area 55 . This period information may be generated using, for example, the construction start date and the completion date of the performance information RA and RB that are input in quality control for each task information. Further, when the period information based on the performance information RA and RB is reflected, the construction management function unit 22 uses the date or day of the week information such as the calendar function to link the next task information scheduled to be executed on the same day or day of the week. , a so-called lightning line 81 may be generated and displayed.

また工事管理機能部22は、たとえば予め設定された反映先の指示情報に基づき、作業の進捗状況などの管理に利用するタスク管理テーブルIIIを読み出し、品質確認の実績情報RA、RBを反映させる。工事管理機能部22は、たとえば図9Cに示すように、タスク情報部62に設定されたタスク情報を参照し、取得した実績情報RA、RBなどを管理情報部63に入力する。 Further, the construction management function unit 22 reads the task management table III used for managing the progress of the work based on, for example, preset reflection destination instruction information, and reflects the quality confirmation performance information RA and RB. For example, as shown in FIG. 9C, the construction management function unit 22 refers to the task information set in the task information unit 62, and inputs the acquired performance information RA, RB, etc. to the management information unit 63. FIG.

品質確認の実績情報RA、RBには、日付情報とともに検査内容部73の指示情報に基づいて生成された付属情報82を備える。付属情報82は、たとえば図10に示すように、第2の端末32によって撮影した画像部84や、対象となる機器の装置名やタスク情報、日付、管理者名などを含む情報部86で構成される。この付属情報82は、たとえば第2の端末32、または第2の端末32から取得したデータを利用して工事管理機能部22が生成してもよい。 The quality confirmation record information RA and RB includes date information and attached information 82 generated based on the instruction information of the inspection content section 73 . For example, as shown in FIG. 10, the attached information 82 includes an image portion 84 captured by the second terminal 32, and an information portion 86 including the device name of the target device, task information, date, administrator name, and the like. be done. The attached information 82 may be generated by the construction management function unit 22 using, for example, the second terminal 32 or data acquired from the second terminal 32 .

<他の実績情報の入力>
図11は、他のタスク管理テーブルに入力した実績情報の反映処理を示している。図11に示す処理内容や構成は一例である。
ここでは、たとえば検査結果の実績情報をタスク管理テーブルI26-1に入力する場合を示している。
工事管理機能部22は、たとえば検査を行う管理者が第1の端末30を通じてアクセスしてくると、タスク管理テーブルIを通知して、タスク情報ごとの情報入力を可能にする。タスク管理テーブルIには、たとえば図11Aに示すように、タスク情報ごとに検査の完了を表すチェックボックスのクリックなどの実績情報RCが入力される。
<Enter other performance information>
FIG. 11 shows the reflection processing of performance information input to another task management table. The processing contents and configuration shown in FIG. 11 are examples.
Here, for example, the case of inputting performance information of inspection results to the task management table I26-1 is shown.
The construction management function unit 22 notifies the task management table I when, for example, an inspection manager accesses through the first terminal 30, and enables information input for each task information. In the task management table I, for example, as shown in FIG. 11A, performance information RC such as clicking of a check box indicating completion of inspection is input for each task information.

工事管理機能部22は、たとえばタスク管理テーブルIに入力された検査完了の実績情報RCを読み出すとともに、予め設定された反映先の指示情報に基づいて工事の工程を管理するタスク管理テーブルIVを読み出す。また工事管理機能部22は、たとえば管理サーバ4や外部データベースにあるカレンダー機能やタイマー機能などを利用し、タスク管理テーブルIに実績情報RCが入力された日付や時間情報を取得している。そして、工事管理機能部22は、たとえば図11Bに示すように、取得した実績情報RCを解析し、タスク管理テーブルIVに設定された同一または関連付けられたタスク情報を特定するとともに、その監視結果部75に対して実績情報RCによる日付や時間情報、検査を行った管理者情報などを自動入力する。 The construction management function unit 22 reads, for example, the inspection completion result information RC input to the task management table I, and reads the task management table IV for managing the construction process based on the preset instruction information of the destination to be reflected. . Also, the construction management function unit 22 acquires date and time information when the performance information RC is input to the task management table I using, for example, the calendar function and timer function of the management server 4 and an external database. Then, as shown in FIG. 11B, for example, the construction management function unit 22 analyzes the acquired performance information RC, identifies the same or associated task information set in the task management table IV, and monitors the results. 75, the date and time information based on the performance information RC, the information of the administrator who performed the inspection, etc. are automatically input.

工事管理機能部22は、管理者により特定のタスク管理テーブルに実績情報RA、RB、RCが入力されるとともに、斯かる実績情報実績情報RA、RB、RCが他のタスク管理テーブル反映した場合、内容に変遷のあったタスク管理テーブルや全てのタスク管理テーブルについて、設定された管理者の情報端末6に対して通知情報を送信する。 When performance information RA, RB, RC is input to a specific task management table by an administrator, and the performance information RA, RB, RC is reflected in another task management table, the construction management function unit 22 Notification information is transmitted to the information terminal 6 of the set administrator for the task management table whose content has changed or for all task management tables.

<工事管理処理について>
図12は、工事管理処理の処理手順を示している。図12に示す処理は、本開示の工事管理方法、プログラムの一例であり、本開示の技術は斯かる処理内容や処理手順に限定されない。
この工事管理処理には、たとえば図12に示すように、タスク情報の読み出し処理(S101)、タスク管理テーブルの生成処理(S102)、管理者の認証処理(S103)、管理者に対する権限の関係付け処理(S104)、実績情報の入力確認処理(S105)、入力権限の確認処理(S106)、反映指示の確認処理(S107)、実績情報の反映処理(S108)、タスク管理テーブルの通知および表示処理(S109)、タスクの完了確認処理(S110)を含む。
<About construction management processing>
FIG. 12 shows the processing procedure of construction management processing. The processing shown in FIG. 12 is an example of the construction management method and program of the present disclosure, and the technology of the present disclosure is not limited to such processing contents and processing procedures.
For example, as shown in FIG. 12, this construction management processing includes task information reading processing (S101), task management table generation processing (S102), manager authentication processing (S103), authority association with the manager. processing (S104), input confirmation processing of performance information (S105), confirmation processing of input authority (S106), confirmation processing of reflection instruction (S107), reflection processing of performance information (S108), notification and display processing of task management table (S109) and task completion confirmation processing (S110).

管理サーバ4は、定修工事や検査について設定された情報、もしくは管理者による入力操作を契機に工事管理プログラムを実行し、テーブル生成機能部20を立ち上げる。テーブル生成機能部20は、たとえばタスク情報DB24にアクセスすると、設定された監視対象である機器名やその種別情報、プラント情報などに関係付けられた定修工事や検査のタスク情報を読み出し(S101)、このタスク情報や機器情報、および管理機能T1~Tnの種類や数などの設定条件を利用してタスク管理テーブル(I~IV)26-1、26-2、26-3、26-4を生成する(S102)。 The management server 4 executes the construction management program and starts up the table generation function unit 20 with the information set about regular maintenance work and inspections or the input operation by the administrator as a trigger. When the table generation function unit 20 accesses the task information DB 24, for example, it reads the name of the equipment to be monitored, its type information, and task information for regular maintenance work and inspection associated with plant information (S101). , task information, device information, and setting conditions such as types and numbers of management functions T1 to Tn are used to create task management tables (I to IV) 26-1, 26-2, 26-3, and 26-4. Generate (S102).

管理サーバ4は、定修工事、検査の開始指示に基づいて工事管理プログラムを実行し、工事管理機能部22を立ち上げる。工事管理機能部22は、情報端末6を通じて取得した管理者の識別情報や階級情報などを利用して管理者を認証する(S103)とともに、権限テーブル38を読み出し、管理者の階級情報に対して権限の付与を含む関係付けを行う(S104)。
工事管理機能部22は、管理者の情報端末6から特定のタスク管理テーブルに対し、工事の内容監視や検査結果などの実績情報が入力されたか否かを監視する(S105)。工事管理機能部22は、特定のタスク管理テーブルに対して実績情報が入力されたと判断した場合(S105のYES)、その実績情報を入力した管理者の識別情報を取込み、入力操作に対する権限の有無を確認する(S106)。入力権限が無い場合(S106のNO)は、入力された実績情報を無効にし、入力権限を有する者による実績情報の入力があるまで待機する。
工事管理機能部22は、管理者の入力権限を確認すると(S106のYES)、実績情報が入力されたタスク情報、またはタスク管理テーブルに情報の反映指示が設定されているかを確認する(S107)。反映指示が設定されている場合(S107のYES)、工事管理機能部22は、その指示情報と、指示情報に設定された他のタスク管理テーブルを読み出すとともに、反映先の他のタスク管理テーブル26を利用した管理内容に基づいて、実績情報に基づく情報を生成し、他のタスク管理テーブル26に反映させる(S108)。そして工事管理機能部22は、たとえばタスク管理テーブル26に反映指示が設定されていない場合(S107のNO)または他のタスク管理テーブル26に対する実績情報の反映が完了すると、管理者の情報端末6に対してタスク管理テーブル26の通知や更新の表示処理を行う(S109)。
The management server 4 executes the construction management program based on the instruction to start regular maintenance work and inspection, and starts up the construction management function unit 22 . The construction management function unit 22 authenticates the manager by using the manager's identification information and rank information acquired through the information terminal 6 (S103), reads the authority table 38, and checks the manager's rank information. Association including granting of authority is performed (S104).
The construction management function unit 22 monitors whether performance information such as construction content monitoring and inspection results has been input to a specific task management table from the manager's information terminal 6 (S105). If the construction management function unit 22 determines that performance information has been input to a specific task management table (YES in S105), the construction management function unit 22 takes in the identification information of the manager who has input the performance information, and determines whether or not the administrator has authority for the input operation. (S106). If there is no input authority (NO in S106), the input performance information is invalidated, and the system waits until a person who has the input authority inputs the performance information.
When confirming the administrator's input authority (YES in S106), the construction management function unit 22 confirms whether the task information to which the performance information is input or whether an instruction to reflect the information is set in the task management table (S107). . If the reflection instruction is set (YES in S107), the construction management function unit 22 reads the instruction information and the other task management table set in the instruction information, and reads the other task management table 26 as the reflection destination. information based on the performance information is generated based on the content of management using , and is reflected in another task management table 26 (S108). Then, for example, when the reflection instruction is not set in the task management table 26 (NO in S107) or when reflection of the performance information to another task management table 26 is completed, the construction management function unit 22 sends the information terminal 6 of the manager In response, display processing for notification and update of the task management table 26 is performed (S109).

工事管理処理では、全てのタスクについての定修工事、検査が終わったか否かを判断し(S110)、全てのタスクについて完了していれば(S110のYES)、この処理を終了する。これに対し工事管理処理では、特定のタスク管理テーブルにおいて次の工程を示すタスク情報が有る場合、つまり全てのタスクが完了していなければ(S110のNO)、実績情報の入力まで待機状態となる。 In the construction management process, it is determined whether or not regular maintenance work and inspection have been completed for all tasks (S110). If all tasks have been completed (YES in S110), this process ends. On the other hand, in the construction management process, if there is task information indicating the next process in a specific task management table, that is, if all tasks have not been completed (NO in S110), the process waits until the performance information is input. .

〔第1の実施形態の効果〕
斯かる構成によれば、以下のいずかの効果が得られる。
[Effect of the first embodiment]
According to such a configuration, one of the following effects can be obtained.

(1) 管理機能ごとのタスク管理テーブルを自動生成できるとともに、特定のタスク管理テーブルに入力した実績情報を、関連する他のタスク管理テーブルに自動で反映させることができる。 (1) It is possible to automatically generate a task management table for each management function, and to automatically reflect performance information entered in a specific task management table in other related task management tables.

(2) タスク情報やタスク管理テーブルに設定された指示情報を読み取り、管理サーバ4によって自動で他のタスク管理テーブルに実績情報を反映させることができるので、タスク管理テーブルの探索やタスク情報の照合などの作業負荷の軽減が図れる。 (2) Task information and instruction information set in the task management table can be read, and the performance information can be automatically reflected in other task management tables by the management server 4, so that search of the task management table and collation of task information can be performed. It is possible to reduce the workload such as

(3) 実績情報をタスク管理テーブル間で自動的に反映させることで、タスク情報の照合作業や実績情報の入力作業において、選択ミスや入力ミスなどの人為的なミスを防止できるので、工事管理処理に対する信頼性が向上する。 (3) By automatically reflecting performance information between task management tables, it is possible to prevent human errors such as selection errors and input errors in task information collation work and performance information input work, so construction management is improved. Improves process reliability.

〔第2の実施形態〕
図13は、第2の実施形態に係る工事管理システムの構成例を示している。図13に示す構成は一例であり、斯かる内容に本開示の技術が限定されない。また、図13において、図1と同一構成に対しては同一の符号を付し、説明を省略する。
この工事管理システム2では、たとえば図13に示すように、定修工事や検査処理において、それぞれのタスク情報に対し、第1の管理者および第2の管理者の両者により品質確認および完了確認、または検査処理を行い、それぞれ実績情報を入力することでタスクを完了させる場合を示している。そこで、工事管理システム2では、端末30、32からそれぞれ入力情報や認証情報を取得するとともに、各端末30、32に対してタスク管理テーブル26を含む管理画面の提示やタスクの実行を促すアラート情報を通知する。このアラート情報は、たとえば管理者ごとに保有するメールアドレスに通知するほか、端末30、32に格納された時計やスケジュールアプリなどのアラーム機能を利用してもよく、または工事管理処理の順序になったときにタスク管理テーブル26を通知して表示部に表示させてもよい。
[Second embodiment]
FIG. 13 shows a configuration example of a construction management system according to the second embodiment. The configuration shown in FIG. 13 is an example, and the technology of the present disclosure is not limited to such content. In addition, in FIG. 13, the same reference numerals are assigned to the same configurations as in FIG. 1, and the description thereof is omitted.
In this construction management system 2, for example, as shown in FIG. 13, both the first manager and the second manager confirm the quality and the completion of each task information in regular maintenance work and inspection processing. Alternatively, a case is shown in which inspection processing is performed and the task is completed by inputting performance information. Therefore, the construction management system 2 acquires input information and authentication information from the terminals 30 and 32, respectively, and presents a management screen including the task management table 26 to each terminal 30 and 32, and alert information prompting execution of tasks. to notify you. This alert information may be sent to, for example, an e-mail address held by each manager, or may use the alarm function of a clock or schedule application stored in the terminals 30 and 32, or may be sent in the order of construction management processing. The task management table 26 may be notified and displayed on the display section when the task management table 26 is displayed.

<実績情報の入力>
図14は、実績情報の入力状態を示している。図14に示す処理内容は一例である。
ここでは、特定の工程における品質チェックおよび完了の実績情報をタスク管理テーブルIVに入力する場合を示している。
工事管理機能部22は、たとえば定修工事の施工およびタスク情報ごとの品質確認および完了確認を行う第2の管理者が端末32を通じてアクセスしてくると、タスク管理テーブルIV26-4を通知して、タスク情報ごとの情報入力を可能にする。タスク管理テーブルIVには、たとえば図14Aに示すように、タスク情報ごとに開始情報部74に工事の着工開始日が入力されるとともに、監視結果部75に工事の品質確認の完了を表す情報や日付などの実績情報RA、RBなどが入力される。またこのタスク管理テーブルIVには、たとえば第1の管理者に実績情報を入力させる入力部90が形成されている。この入力部90は、たとえば第2の管理者が実績情報RBを入力すると、管理権限の変移を示す処理として、入力部90の一部や全部の点滅表示や変色表示をさせてもよい。
<Enter performance information>
FIG. 14 shows the input state of performance information. The processing content shown in FIG. 14 is an example.
Here, a case is shown in which quality check and completion record information in a specific process are input to the task management table IV.
The construction management function unit 22 notifies the task management table IV26-4 when, for example, a second manager who carries out maintenance work and quality confirmation and completion confirmation for each task information accesses through the terminal 32. , to enable information entry for each task information. In the task management table IV, for example, as shown in FIG. 14A, the construction start date is input to the start information section 74 for each task information, and the monitoring result section 75 contains information indicating the completion of quality confirmation of the construction work. Performance information RA, RB, etc. such as dates are input. The task management table IV also includes an input section 90 for allowing the first administrator to input performance information. For example, when the second administrator inputs the record information RB, the input unit 90 may cause part or all of the input unit 90 to blink or change color as a process to indicate a change in management authority.

工事管理機能部22は、たとえば第2の管理者による実績情報RBの入力を確認すると、第1の端末30に対してアラート情報を通知してタスク情報の確認処理を行う旨を知らせるとともに、タスク管理テーブルIVを第1の端末30に表示させる。
工事管理機能部22は、たとえばアラート通知に応じて第1の管理者が端末30を通じてアクセスしてくると、認証処理を行った後にタスク管理テーブルIVを通知して、タスク情報ごとの情報入力を可能にする。タスク管理テーブルIVには、たとえば図14Bに示すように、第1の管理者によって入力部90に対して実績情報RDが入力される。この実績情報RDは、たとえば他の実績情報RA、RBと同様に工事の品質確認の完了を表す情報や日付でもよく、またはこれに加えて現在のタスク情報が完了したことや次のタスク情報への移行を示すチェック記号などであってもよい。
For example, when confirming the input of the performance information RB by the second manager, the construction management function unit 22 notifies the first terminal 30 of the alert information to notify that the task information confirmation process will be performed, and the task The management table IV is displayed on the first terminal 30 .
For example, when the first manager accesses through the terminal 30 in response to the alert notification, the construction management function unit 22 notifies the task management table IV after performing the authentication process, and asks for information input for each task information. enable. In the task management table IV, for example, as shown in FIG. 14B, performance information RD is input to the input unit 90 by the first administrator. This performance information RD may be, for example, information or date indicating the completion of quality confirmation of construction works like the other performance information RA and RB, or in addition to this, the completion of the current task information and the next task information. It may be a check mark or the like indicating the transition of .

なお、ここでは、工事の確認または検査結果の入力処理について、第2の管理者の次に第1の管理者の順序で実績情報を入力する場合を示したがこれに限らない。第1の管理者が先に実績情報を入力するようにしてもよい。 Here, regarding the input processing of confirmation of construction work or inspection results, a case is shown in which performance information is input in the order of the second manager and then the first manager, but the present invention is not limited to this. The first administrator may enter the performance information first.

そして工事管理処理では、第1の管理者および第2の管理者による実績情報RB、RDが入力されると、これらの情報のいずれかまたは両方が他のタスク管理テーブルに入力され、情報が共有される。実績情報RB、RDの反映先は、たとえば既述のように、タスク管理テーブルI、II、IIIのいずれか、または2以上の組み合せであればよい。 In the construction management process, when the performance information RB and RD by the first manager and the second manager are input, either or both of these information are input to another task management table, and the information is shared. be done. The result information RB and RD may be reflected in any one of the task management tables I, II, and III, or a combination of two or more, as described above.

<工事管理処理について>
図15は、工事管理処理の処理手順を示している。図15に示す処理は、本開示の工事管理方法、プログラムの一例であり、本開示の技術は斯かる処理内容や処理手順に限定されない。図15において、図12に示す処理内容と同一の部分については詳細な説明を割愛する。
<About construction management processing>
FIG. 15 shows the processing procedure of construction management processing. The processing shown in FIG. 15 is an example of the construction management method and program of the present disclosure, and the technology of the present disclosure is not limited to such processing contents and processing procedures. In FIG. 15, detailed description of the same parts as the processing contents shown in FIG. 12 is omitted.

この工事管理処理には、たとえば図15に示すように、タスク管理テーブルの生成処理(S201)、第2の管理者の認証処理(S202)、タスク管理テーブルの通知処理(S203)、実績情報の取得処理(S204)、入力権限の確認処理(S205)、第1の端末30への通知処理(S206)、第1の管理者の認証処理(S207)、タスク管理テーブルの通知処理(S208)、実績情報の取得処理(S209)、他のタスク管理テーブルへの反映処理(S210)、タスク管理テーブルの通知および表示処理(S211)、次のタスクへの移行処理(S212)を含む。 For example, as shown in FIG. 15, this construction management processing includes task management table generation processing (S201), second manager authentication processing (S202), task management table notification processing (S203), performance information Acquisition processing (S204), input authority confirmation processing (S205), notification processing to the first terminal 30 (S206), first administrator authentication processing (S207), task management table notification processing (S208), It includes a process of acquiring performance information (S209), a process of reflecting to another task management table (S210), a notification and display process of the task management table (S211), and a process of shifting to the next task (S212).

管理サーバ4は、テーブル生成機能部20を立ち上げ、設定された監視対象である機器名やその種別情報、タスク情報DB24に格納されたタスク情報を利用してタスク管理テーブル(I~IV)を生成する(S201)。
管理サーバ4は、工事管理プログラムの実行により工事管理機能部22を立ち上げると、第2の端末32を通じて取得した第2の管理者の識別情報や階級情報などにより認証する(S202)とともに、設定された管理機能のタスク管理テーブルを通知する(S203)。この認証処理には、管理者の識別情報に含まれる階級情報に応じた、実績情報の入力権限の付与も含む。
工事管理機能部22は、第2の端末32から入力された実績情報を取得し(S204)、入力権限を有する管理者が入力したことを確認すると(S205のYES)、第1の端末30に対してアラート情報などの通知処理を行う(S206)。また、工事管理機能部22は、入力権限が無い者により入力された場合(S205のNO)は、入力された実績情報を無効にし、入力権限を有する者による実績情報の入力があるまで待機すればよい。
The management server 4 activates the table generation function unit 20, and generates task management tables (I to IV) using the set monitoring target device name and its type information, and the task information stored in the task information DB 24. Generate (S201).
When the management server 4 starts up the construction management function unit 22 by executing the construction management program, the management server 4 authenticates the second manager based on the identification information and rank information of the second manager acquired through the second terminal 32 (S202). The task management table of the management function received is notified (S203). This authentication processing also includes the granting of the authority to input performance information according to the rank information included in the administrator's identification information.
The construction management function unit 22 acquires the performance information input from the second terminal 32 (S204), and when confirming that the administrator who has the input authority has input (YES in S205), the first terminal 30 In response, notification processing such as alert information is performed (S206). In addition, when the input is made by a person without input authority (NO in S205), the construction management function unit 22 invalidates the input performance information and waits until the performance information is input by a person who has the input authority. Just do it.

工事管理機能部22は、第1の端末30を通じて取得した第1の管理者の識別情報や階級情報などにより認証する(S207)とともに、設定された管理機能のタスク管理テーブルを通知する(S208)。工事管理機能部22は、第1の端末30から入力された実績情報を取得すると(S209)、反映の指示情報に基づき、一方または両方の実績情報もしくはこれらの実績情報を利用して生成した情報を他のタスク管理テーブルに反映させる(S210)。
工事管理機能部22は、第1の端末30、第2の端末32のいずれか一方または両方に対して、実績情報が入力されたタスク管理テーブルの通知や表示処理を行った(S211)後、定修工事、検査処理の次のタスクに移行する(S212)。
The construction management function unit 22 authenticates the first manager based on the identification information and rank information of the first manager acquired through the first terminal 30 (S207), and notifies the task management table of the set management function (S208). . When the construction management function unit 22 acquires the performance information input from the first terminal 30 (S209), based on the reflection instruction information, one or both of the performance information or information generated using these performance information is reflected in another task management table (S210).
The construction management function unit 22 notifies or displays the task management table in which the performance information is input to either or both of the first terminal 30 and the second terminal 32 (S211). After regular maintenance work and inspection processing, the routine proceeds to the next task (S212).

〔第2の実施形態の効果〕
斯かる構成によれば、以下のような効果が得られる。
[Effect of Second Embodiment]
According to such a configuration, the following effects are obtained.

(1) 第1の実施形態と同様の効果が得られる。
(2) 定修工事や検査について、複数の管理者により内容および完了確認を行う場合であっても、一方の管理者による実績情報の入力を契機に他の管理者にアラート情報を通知して管理処理の実行を促すことで、処理の迅速性を高めることができる。
(3) 複数の管理者により工事や検査の内容を確認し、実績情報を入力させることで、タスク処理の実施状態を精緻に管理でき、工事や検査のタスクの品質が高められる。
(1) An effect similar to that of the first embodiment can be obtained.
(2) Even if more than one manager confirms the content and completion of regular maintenance work and inspections, the input of performance information by one manager will trigger alert information to be sent to the other managers. Prompt execution of the management process can improve the speed of the process.
(3) By allowing multiple administrators to confirm the details of construction work and inspections and input performance information, it is possible to precisely manage the execution status of task processing and improve the quality of construction and inspection tasks.

〔他の実施の形態〕
以上説明した実施形態について、変形例を以下に列挙する。
[Other embodiments]
Modifications of the embodiment described above are listed below.

(1) 上記の実施形態では、プラント設備の定修工事や検査について記載しているが、本開示の技術は各種の工事や検査などに幅広く活用でき、上記実施の形態の内容に限定されない。 (1) In the above embodiments, regular maintenance work and inspections of plant equipment are described, but the technology of the present disclosure can be widely used in various constructions and inspections, and is not limited to the contents of the above embodiments.

(2) 本開示の工事管理システムは、管理サーバ4を情報端末6と独立させているが、これに限らない。工事管理システム2では、たとえばひとつの装置筐体にシステムを構成する処理部、入出力部、情報提示部を搭載し、既述の情報端末6を以て工事管理システムを構成してもよい。 (2) In the construction management system of the present disclosure, the management server 4 is made independent of the information terminal 6, but this is not the only option. In the construction management system 2, for example, the processing section, the input/output section, and the information presentation section that constitute the system may be mounted in one device housing, and the construction management system may be configured with the information terminal 6 described above.

(3) 上記実施では、第1の管理者がプラントオーナーであり、第2の管理者が工事を行う協力会社の場合を示したがこれに限らない。プラント設備の定修工事や検査について、第1の管理者および第2の管理者が共に協力会社であってもよい。これらの協力会社は、たとえばともに定修工事や検査を行う権限を有する場合や、それぞれが定修工事または検査のいずれか一方のみを行う場合、または一方の管理者は工事や検査の確認処理のみを行うものであってもよい。 (3) In the above implementation, the case where the first manager is the plant owner and the second manager is the cooperating company that performs the construction was shown, but this is not the only option. Both the first manager and the second manager may be cooperating companies for regular maintenance work and inspection of plant equipment. For example, if both of these subcontractors have the authority to perform periodic maintenance work and inspections, or if each performs only one of periodic maintenance work or inspections, or if one of the managers only performs confirmation processing for construction or inspection may be performed.

以上説明したように、本開示の技術の最も好ましい実施形態等について説明した。本開示の技術は、上記記載に限定されるものではない。特許請求の範囲に記載され、または発明を実施するための形態に開示された要旨に基づき、当業者において様々な変形や変更が可能である。斯かる変形や変更が、本開示の技術の範囲に含まれることは言うまでもない。
As described above, the most preferred embodiments and the like of the technology of the present disclosure have been described. The technology of the present disclosure is not limited to the above description. Various modifications and changes can be made by those skilled in the art based on the gist described in the claims or disclosed in the detailed description. It goes without saying that such modifications and changes are included in the technical scope of the present disclosure.

本開示の構成によれば、プラント設備や機器に対する定修工事や検査処理において、管理機能ごとに複数のタスク管理テーブルが自動生成できるとともに、特定の管理テーブルに対して入力した実績情報が、他のタスク管理テーブルに対して自動で反映させることができるので、関連するタスク情報の探索や複数のタスク管理テーブルへの入力などの作業負荷を軽減でき、かつ実績情報の誤入力などを防止でき、有用である。
According to the configuration of the present disclosure, it is possible to automatically generate a plurality of task management tables for each management function in regular maintenance work and inspection processing for plant equipment and equipment, and the performance information entered into a specific management table can be used by other Since it can be automatically reflected in the task management table of , it is possible to reduce the workload such as searching for related task information and inputting to multiple task management tables, and to prevent incorrect input of performance information. Useful.

2 工事管理システム
4 管理サーバ
6 情報端末
8 ネットワーク
10、302、322 処理部
12 記憶部
14、306 情報入力部
16、304 情報提示部
20 テーブル生成機能部
22 工事管理機能部
24 タスク情報DB
26、26-1、26-2、26-3、26-4、26-11、26-12、・・・26-1N、26-21、26-22、・・・26-2N、26-31、26-32、・・・26-3N、26-41、26-42、・・・26-4N タスク管理テーブル
30 第1の端末
32、32-1、32-m 第2の端末
324 情報入力・提示部
34 機器
36 IDタグ
38 権限テーブル
40、53、62、71 タスク情報部
41、51、61 装置名部
42 反映部
43 工事情報部
44 管理情報入力部
45 完了監視部
46 権限部
50 日付部
52、70 分類部
54 工程管理部
55 情報入力エリア
60 ヘッダー部
63 管理情報部
72 確認内容部
73 検査内容部
74 開始情報部
75 監視結果部
76 権限部
80 指示情報
81 稲妻線
82 付属情報
84 画像部
86 情報部
90 入力部

2 construction management system 4 management server 6 information terminal 8 network 10, 302, 322 processing unit 12 storage unit 14, 306 information input unit 16, 304 information presentation unit 20 table generation function unit 22 construction management function unit 24 task information DB
26, 26-1, 26-2, 26-3, 26-4, 26-11, 26-12, ... 26-1N, 26-21, 26-22, ... 26-2N, 26- 31, 26-32, ... 26-3N, 26-41, 26-42, ... 26-4N Task management table 30 First terminal 32, 32-1, 32-m Second terminal 324 Information Input/presentation unit 34 device 36 ID tag 38 authority table 40, 53, 62, 71 task information unit 41, 51, 61 device name unit 42 reflection unit 43 construction information unit 44 management information input unit 45 completion monitoring unit 46 authority unit 50 Date section 52, 70 Classification section 54 Process control section 55 Information input area 60 Header section 63 Management information section 72 Confirmation content section 73 Inspection content section 74 Start information section 75 Monitoring result section 76 Authority section 80 Instruction information 81 Lightning line 82 Attached information 84 image section 86 information section 90 input section

建設工事の進捗管理に関し、工事計画支援システムと、検査予定に関するデータを蓄積する検査予定データベース、検査予定と実績を統合した検査進捗データを蓄積する検査予実データベースとを有し、検査の進捗状況を工事進捗の物量に換算した工事進捗データを、工事計画支援システムに伝送する進捗確認システムとを組み合わせ、区画別工程と事進捗データを統合させ、工事進捗を表すチャート稲妻表示を付した工程表を表示することが知られている(たとえば、特許文献3)。 Regarding the progress management of construction work, we have a construction plan support system, an inspection schedule database that accumulates data related to inspection schedules, and an inspection schedule actual database that accumulates inspection progress data that integrates inspection schedules and actual results. Combined with a progress confirmation system that transmits construction progress data converted to physical quantity of construction progress to the construction plan support system, integrates the construction progress data with the process by section, and charts the progress chart with a lightning bolt display that shows the construction progress. is known (for example, Patent Document 3).

定修工事の発注者においては、その進捗管理に加え、その進捗に応じた検査などが主要な処理事項である。これに対し、受注者は、発注者のコンセプト、定修対象であるシステムの全体像を把握し、定修計画を策定して工事処理を実行し、発注者の検査を随時に受けて定修工事を完了することが求められる。
定修工事には工事の進捗、報告、検査許可、確認などの複数の工程が存在する。たとえば、ひとつの機器の定修工事が完了すれば、その完了の報告を受けた発注者から検査許可を受け、その検査結果が基準を満たすなど、合格域に達しなければ、次の工程に進むことができない。これは安全面からすれば優れた管理であるが、発注者の検査担当に工事の進捗が委ねられるなどの課題もある。発注者と受注者との間での情報共有が不可欠であるが、これが不十分であると、検査機器の位置の探索などのベーシックな点で工程間の時間的ロスを誘発するという課題がある。
For the orderer of regular maintenance work, in addition to the progress management, inspections according to the progress are major items to be handled. In response to this, the contractor grasps the concept of the ordering party and the overall picture of the system that is subject to periodic maintenance, formulates a periodic maintenance plan, executes the construction process, and undergoes periodic inspections by the ordering party at any time. Construction is required to be completed.
Regular maintenance work includes multiple processes such as progress of construction, reporting, permission for inspection, and confirmation. For example, when regular maintenance work for one piece of equipment is completed, inspection permission is obtained from the ordering party who received the completion report. I can't. This is excellent management from a safety point of view, but there are also issues such as entrusting the progress of construction to the person in charge of inspection by the ordering party. Information sharing between the ordering party and the contractor is essential, but if this is insufficient, there is a problem of inducing time loss between processes in basic points such as searching for the location of inspection equipment. .

上記目的を達成するため、本開示のプログラムの一側面は、コンピュータによって実行されるプログラムであって、データベースに記録されたタスク情報を利用して、管理機能で特定した二以上のタスク管理テーブルを作成する機能と、情報入力部により特定の前記タスク管理テーブルに入力されたタスクごとの実績情報を取得する機能と、前記情報入力部から取得した前記実績情報を他の前記タスク管理テーブルの何れかまたは二以上に反映させる機能と、前記実績情報の変遷を表す前記タスク管理テーブルの何れかまたは二以上を情報提示部に提示する機能とを前記コンピュータに実行させる。 In order to achieve the above object, one aspect of the program of the present disclosure is a program executed by a computer, which uses task information recorded in a database to create two or more task management tables specified by the management function. a function to acquire performance information for each task input to a specific task management table by an information input unit; and a function of presenting, to the information presenting unit, any one or more of the task management tables representing changes in the performance information.

第1の実施形態に係る工事管理システムの構成例を示す図である。It is a figure which shows the structural example of the construction management system which concerns on 1st Embodiment. タスク管理テーブルの生成機能を示す図である。FIG. 10 is a diagram showing a task management table generation function; 工事管理機能部による実績情報の反映機能を示す図である。It is a figure which shows the reflection function of performance information by a construction management function part. 管理者の認証処理および権限情報の付与の一例を示す図である。FIG. 10 is a diagram illustrating an example of administrator authentication processing and granting of authority information; タスク管理テーブルIの構成例を示す図である。3 is a diagram showing a configuration example of a task management table I; FIG. タスク管理テーブルIIの構成例を示す図である。FIG. 10 is a diagram showing a configuration example of a task management table II; タスク管理テーブルIIIの構成例を示す図である。FIG. 10 is a diagram showing a configuration example of a task management table III; タスク管理テーブルIVの構成例を示す図である。FIG. 10 is a diagram showing a configuration example of a task management table IV; 実績情報の入力および他のタスク管理テーブルへの反映状態の一例を示す図である。FIG. 10 is a diagram showing an example of input of performance information and a state of reflection to another task management table; 属情報の構成例を示す図である。It is a figure which shows the structural example of attached information . 実績情報の入力および他のタスク管理テーブルへの反映状態の他の例を示す図である。FIG. 10 is a diagram showing another example of the input of performance information and the state of reflection to other task management tables; 工事管理処理の一例を示すフローチャートである。It is a flow chart which shows an example of construction management processing. 第2の実施形態に係る工事管理システムの構成例を示す図である。It is a figure which shows the structural example of the construction management system which concerns on 2nd Embodiment. 実績情報の入力および他のタスク管理テーブルへの反映状態の一例を示す図である。FIG. 10 is a diagram showing an example of input of performance information and a state of reflection to another task management table; 工事管理処理の一例を示すフローチャートである。It is a flow chart which shows an example of construction management processing.

(3) 上記実施形態では、第1の管理者がプラントオーナーであり、第2の管理者が工事を行う協力会社の場合を示したがこれに限らない。プラント設備の定修工事や検査について、第1の管理者および第2の管理者が共に協力会社であってもよい。これらの協力会社は、たとえばともに定修工事や検査を行う権限を有する場合や、それぞれが定修工事または検査のいずれか一方のみを行う場合、または一方の管理者は工事や検査の確認処理のみを行うものであってもよい。
(3) In the above embodiment , the first manager is the plant owner, and the second manager is the cooperating company that performs the construction work, but this is not the only option. Both the first manager and the second manager may be cooperating companies for regular maintenance work and inspection of plant equipment. For example, if both of these subcontractors have the authority to perform periodic maintenance work and inspections, or if each performs only one of periodic maintenance work or inspections, or if one of the managers only performs confirmation processing for construction or inspection may be performed.

上記目的を達成するため、本開示の工事管理方法の一側面は、コンピュータにより実行される工事管理方法であって、前記コンピュータの情報処理部が、データベースに記録されたタスク情報の中から、管理機能ごとに管理対象として特定したタスク情報を抽出して、二以上のタスク管理テーブルを作成する工程と、前記コンピュータの情報入力部が、特定の前記タスク管理テーブルにタスクごとの実績情報を入力する工程と、前記情報処理部が、前記情報入力部から取得した前記実績情報を他の前記タスク管理テーブルの何れかまたは二以上に反映させる工程と、前記コンピュータの情報提示部が、前記実績情報の変遷を表す前記タスク管理テーブルの何れかまたは二以上を提示する工程とを含む。 In order to achieve the above object, one aspect of the construction management method of the present disclosure is a construction management method executed by a computer, wherein an information processing unit of the computer selects a management task from task information recorded in a database. a step of extracting task information specified as a management target for each function and creating two or more task management tables; a step in which the information processing unit reflects the performance information acquired from the information input unit in one or more of the other task management tables; and a step in which the information presentation unit of the computer reflects the performance information presenting one or more of the task management tables representing the transition.

上記目的を達成するため、本開示の工事管理システムの一側面は、二以上のタスク情報が格納されたデータベースと、前記データベースに記録されたタスク情報の中から、管理機能ごとに管理対象として特定したタスク情報を抽出して、二以上のタスク管理テーブルを作成する情報処理部と、特定の前記タスク管理テーブルにタスクごとの実績情報を入力する情報入力部とを備え、前記情報処理部が、前記情報入力部から取得した前記実績情報を他の前記タスク管理テーブルの何れかまたは二以上に反映させる。
この工事管理システムにおいて、さらに、前記情報処理部が、前記タスク管理テーブルに対する少なくとも閲覧、入力、改定を許可する権限を設定し、該権限と管理者の階級とを関連付ける。
In order to achieve the above object, one aspect of the construction management system of the present disclosure includes a database storing two or more pieces of task information, and among the task information recorded in the database, specified as a management target for each management function. an information processing unit that extracts the task information obtained and creates two or more task management tables; and an information input unit that inputs performance information for each task into a specific task management table, wherein the information processing unit The performance information acquired from the information input unit is reflected in one or more of the other task management tables.
In this construction management system, the information processing section further sets authority to permit at least viewing, inputting, and revision of the task management table, and associates the authority with the rank of the manager.

上記目的を達成するため、本開示のプログラムの一側面は、コンピュータによって実行されるプログラムであって、データベースに記録されたタスク情報の中から、管理機能ごとに管理対象として特定したタスク情報を抽出して、二以上のタスク管理テーブルを作成する機能と、情報入力部により特定の前記タスク管理テーブルに入力されたタスクごとの実績情報を取得する機能と、前記情報入力部から取得した前記実績情報を他の前記タスク管理テーブルの何れかまたは二以上に反映させる機能と、前記実績情報の変遷を表す前記タスク管理テーブルの何れかまたは二以上を情報提示部に提示する機能とを前記コンピュータに実行させる。 In order to achieve the above object, one aspect of the program of the present disclosure is a program executed by a computer, which extracts task information specified as a management target for each management function from task information recorded in a database. a function of creating two or more task management tables by doing so , a function of acquiring performance information for each task input to a specific task management table by an information input unit, and the performance information acquired from the information input unit to one or more of the other task management tables, and a function of presenting one or more of the task management tables representing changes in the performance information to an information presentation unit. Let

上記目的を達成するため、本開示の工事管理装置の一側面は、コンピュータにより工事を管理する工事管理装置であって、装置筐体と、二以上のタスク情報が格納されたデータベースを備える記憶部と、前記データベースに記録されたタスク情報の中から、管理機能ごとに管理対象として特定したタスク情報を抽出して、二以上のタスク管理テーブルを作成する情報処理部と、特定の前記タスク管理テーブルにタスクごとの実績情報を入力する情報入力部とを備え、前記情報処理部が、前記情報入力部から取得した前記実績情報を他の前記タスク管理テーブルの何れかまたは二以上に反映させる。 In order to achieve the above object, one aspect of the construction management device of the present disclosure is a construction management device that manages construction work using a computer, and includes a device housing and a storage unit that includes a database that stores two or more pieces of task information. an information processing unit that extracts task information specified as a management target for each management function from among the task information recorded in the database, and creates two or more task management tables; and a specific task management table. and an information input unit for inputting performance information for each task, and the information processing unit reflects the performance information acquired from the information input unit in one or more of the other task management tables.

上記目的を達成するため、本開示の記録媒体の一側面によれば、上記プログラムの何れかを格納している。

In order to achieve the above object, according to one aspect of the recording medium of the present disclosure, any one of the above programs is stored.

Claims (11)

コンピュータを用いた工事管理方法であって、
情報処理部が、データベースに記録されたタスク情報を利用して、管理機能で特定した二以上のタスク管理テーブルを作成する工程と、
情報入力部が、特定の前記タスク管理テーブルにタスクごとの実績情報を入力する工程と、
前記情報処理部が、前記情報入力部から取得した前記実績情報を他の前記タスク管理テーブルの何れかまたは二以上に反映させる工程と、
情報提示部が、前記実績情報の変遷を表す前記タスク管理テーブルの何れかまたは二以上を提示する工程と、
を含むことを特徴とする工事管理方法。
A construction management method using a computer,
a step in which the information processing unit uses the task information recorded in the database to create two or more task management tables specified by the management function;
an information input unit inputting performance information for each task into the specific task management table;
a step in which the information processing unit reflects the performance information acquired from the information input unit in one or more of the other task management tables;
an information presenting unit presenting one or more of the task management tables representing changes in the performance information;
A construction management method comprising:
前記情報処理部は、前記タスク管理テーブルに対する少なくとも閲覧、入力、改定の処理を許可する権限を設定し、該権限と管理者の階級情報とを関連付ける工程を含む、請求項1に記載の工事管理方法。 2. The construction management according to claim 1, wherein said information processing section includes a step of setting authority to permit at least viewing, inputting, and revision processing for said task management table, and associating said authority with manager's rank information. Method. 前記情報処理部が、特定の前記タスク管理テーブル内のタスク情報に関連付けられた他の前記タスク管理テーブル内のタスク情報に対し、前記実績情報または前記実績情報に基づいて生成された情報を入力する工程と、
を含む、請求項1または請求項2に記載の工事管理方法。
The information processing unit inputs the performance information or information generated based on the performance information to the task information in the other task management table associated with the task information in the specific task management table. process and
The construction management method according to claim 1 or 2, comprising:
二以上のタスク情報が格納されたデータベースと、
前記データベースに記録されたタスク情報を利用して、管理機能で特定した二以上のタスク管理テーブルを作成する情報処理部と、
特定の前記タスク管理テーブルにタスクごとの実績情報を入力する情報入力部と、
を備え、前記情報処理部が、前記情報入力部から取得した前記実績情報を他の前記タスク管理テーブルの何れかまたは二以上に反映させることを特徴とする工事管理システム。
a database storing two or more pieces of task information;
an information processing unit that uses the task information recorded in the database to create two or more task management tables specified by the management function;
an information input unit for inputting performance information for each task into the specific task management table;
wherein the information processing unit reflects the performance information acquired from the information input unit in one or more of the other task management tables.
さらに、前記情報処理部が、前記タスク管理テーブルに対する少なくとも閲覧、入力、改定を許可する権限を設定し、該権限と管理者の階級とを関連付けることを特徴とする請求項4に記載の工事管理システム。 5. The construction management according to claim 4, wherein the information processing unit sets authority to permit at least viewing, inputting, and revision of the task management table, and associates the authority with a manager's rank. system. さらに、前記実績情報の変遷を表す前記タスク管理テーブルの何れかまたは二以上を提示する情報提示部を備えることを特徴とする請求項4または5に記載の工事管理システム。 6. The construction management system according to claim 4, further comprising an information presentation unit that presents one or more of the task management tables representing changes in the performance information. コンピュータによって実行されるプログラムであって、
データベースに記録されたタスク情報を利用して、管理機能で特定した二以上のタスク管理テーブルを作成する機能と、
情報入力部により入力された特定の前記タスク管理テーブルにタスクごとの実績情報を取得する機能と、
前記情報入力部から取得した前記実績情報を他の前記タスク管理テーブルの何れかまたは二以上に反映させる機能と、
前記実績情報の変遷を表す前記タスク管理テーブルの何れかまたは二以上を情報提示部に提示する機能と、
を前記コンピュータに実行させるためのプログラム。
A program executed by a computer,
A function to create two or more task management tables specified by the management function using task information recorded in the database;
a function of acquiring performance information for each task in the specific task management table input by the information input unit;
a function of reflecting the performance information acquired from the information input unit in one or more of the other task management tables;
a function of presenting one or more of the task management tables representing transitions of the performance information to an information presentation unit;
A program for causing the computer to execute.
前記タスク管理テーブルに対する少なくとも閲覧、入力、改定の処理を許可する権限を設定し、該権限と管理者の階級情報とを関連付ける機能を前記コンピュータに実行させるための請求項7に記載のプログラム。 8. The program according to claim 7, for causing the computer to execute a function of setting an authority permitting at least viewing, inputting, and revising of the task management table, and associating the authority with manager's rank information. 特定の前記タスク管理テーブル内のタスク情報に関連付けられた他の前記タスク管理テーブル内のタスク情報を読み出す機能と、
前記実績情報を読み出し、または前記実績情報に基づいて入力情報を生成する機能と、
他の前記タスク管理テーブルに対して前記実績情報または前記入力情報を入力する機能と、
を前記コンピュータに実行させるための請求項7または請求項8に記載のプログラム。
a function of reading task information in other task management tables associated with task information in a specific task management table;
a function of reading the performance information or generating input information based on the performance information;
a function of inputting the performance information or the input information to the other task management table;
9. The program according to claim 7 or 8, for causing said computer to execute:
コンピュータにより工事を管理する工事管理装置であって、
装置筐体と、
二以上のタスク情報が格納されたデータベースを備える記憶部と、
前記データベースに記録されたタスク情報を利用して、管理機能で特定した二以上のタスク管理テーブルを作成する情報処理部と、
特定の前記タスク管理テーブルにタスクごとの実績情報を入力する情報入力部と、
を備え、前記情報処理部が、前記情報入力部から取得した前記実績情報を他の前記タスク管理テーブルの何れかまたは二以上に反映させることを特徴とする工事管理装置。
A construction management device for managing construction by a computer,
a device housing;
a storage unit comprising a database storing two or more pieces of task information;
an information processing unit that uses the task information recorded in the database to create two or more task management tables specified by the management function;
an information input unit for inputting performance information for each task into the specific task management table;
wherein the information processing unit reflects the performance information acquired from the information input unit in one or more of the other task management tables.
請求項1ないし請求項3の何れかの請求項に記載の工事管理方法に含まれる前記データベースおよび前記タスク管理テーブル、請求項4ないし請求項6に記載の工事管理システムに含まれる前記データベースおよび前記タスク管理テーブル、請求項7ないし請求項9に記載のプログラムの何れかまたは二以上を格納する記録媒体。

The database and the task management table included in the construction management method according to any one of claims 1 to 3, and the database and the task management table included in the construction management system according to claims 4 to 6. A recording medium storing a task management table and one or more of the programs according to claims 7 to 9.

JP2021193040A 2021-11-29 2021-11-29 Construction management methods, systems, programs, devices and recording media Active JP7411623B2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP2021193040A JP7411623B2 (en) 2021-11-29 2021-11-29 Construction management methods, systems, programs, devices and recording media
TW111140627A TW202324228A (en) 2021-11-29 2022-10-26 Method, system, program, device, and recording medium for construction management

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2021193040A JP7411623B2 (en) 2021-11-29 2021-11-29 Construction management methods, systems, programs, devices and recording media

Publications (2)

Publication Number Publication Date
JP2023079536A true JP2023079536A (en) 2023-06-08
JP7411623B2 JP7411623B2 (en) 2024-01-11

Family

ID=86647219

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021193040A Active JP7411623B2 (en) 2021-11-29 2021-11-29 Construction management methods, systems, programs, devices and recording media

Country Status (2)

Country Link
JP (1) JP7411623B2 (en)
TW (1) TW202324228A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006024035A (en) * 2004-07-08 2006-01-26 Ando Corp Construction management system using mobile communication equipment
JP2008065428A (en) * 2006-09-05 2008-03-21 Nikon Corp Thumbnail display system
JP2009003750A (en) * 2007-06-22 2009-01-08 Fuji Xerox Co Ltd Project management program and project management system
JP2009301273A (en) * 2008-06-12 2009-12-24 Nec Corp Gantt chart display method, data processor and program
JP2010055191A (en) * 2008-08-26 2010-03-11 Fujitsu Ltd Work management device, display controller, work management method, and work management program
JP2013134686A (en) * 2011-12-27 2013-07-08 Maeda Corp Process management system, management terminal, and process management method
WO2021005717A1 (en) * 2019-07-09 2021-01-14 株式会社日立製作所 System and method for assisting management of production
JP2021064265A (en) * 2019-10-16 2021-04-22 株式会社 日立産業制御ソリューションズ Work record analysis server, work record analysis method, and work record analysis program
JP2021149185A (en) * 2020-03-16 2021-09-27 株式会社東芝 Periodic inspection information cooperation system and periodic inspection information cooperation method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004076404A (en) 2002-08-19 2004-03-11 Takiya Kensetsu Kogyo Kk Work management system and work management method using biserial hierarchical structure
US20090210277A1 (en) 2008-02-14 2009-08-20 Hardin H Wesley System and method for managing a geographically-expansive construction project
JP2015049710A (en) 2013-09-02 2015-03-16 株式会社日立システムズ Project management device, program, and management method
JP5905146B2 (en) 2014-07-30 2016-04-20 明豊ファシリティワークス株式会社 Project progress management system and computer program

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006024035A (en) * 2004-07-08 2006-01-26 Ando Corp Construction management system using mobile communication equipment
JP2008065428A (en) * 2006-09-05 2008-03-21 Nikon Corp Thumbnail display system
JP2009003750A (en) * 2007-06-22 2009-01-08 Fuji Xerox Co Ltd Project management program and project management system
JP2009301273A (en) * 2008-06-12 2009-12-24 Nec Corp Gantt chart display method, data processor and program
JP2010055191A (en) * 2008-08-26 2010-03-11 Fujitsu Ltd Work management device, display controller, work management method, and work management program
JP2013134686A (en) * 2011-12-27 2013-07-08 Maeda Corp Process management system, management terminal, and process management method
WO2021005717A1 (en) * 2019-07-09 2021-01-14 株式会社日立製作所 System and method for assisting management of production
JP2021064265A (en) * 2019-10-16 2021-04-22 株式会社 日立産業制御ソリューションズ Work record analysis server, work record analysis method, and work record analysis program
JP2021149185A (en) * 2020-03-16 2021-09-27 株式会社東芝 Periodic inspection information cooperation system and periodic inspection information cooperation method

Also Published As

Publication number Publication date
JP7411623B2 (en) 2024-01-11
TW202324228A (en) 2023-06-16

Similar Documents

Publication Publication Date Title
US8041650B2 (en) Method and system for directed documentation of construction projects
JP2021061058A (en) Methods and systems for providing and receiving information for risk management in field
KR101422352B1 (en) System and method for manageing defect of construction site
US20110040660A1 (en) Monitoring And Management Of Lost Product
JP5848276B2 (en) Information recommendation providing device, program, and communication system
CA2337970A1 (en) Maintenance information management system and method of providing a maintenance plan
US20140344181A1 (en) Construction trade building information management system, software and method
CN112184945A (en) Mobile terminal inspection management method and system
TWI242740B (en) Systems and methods for coordinating QA events
KR20020041390A (en) Method for construction project management using internet and system therefor
JP7411623B2 (en) Construction management methods, systems, programs, devices and recording media
JP2007041799A (en) Project management support system
JP2023079537A (en) Construction management method, system, program, apparatus, and recording medium
JP7429217B2 (en) Report management methods, systems, programs, and devices
JP2023046204A (en) Production management device, production management method, and production management program
JP7116218B1 (en) Work management methods, systems and programs
JP5135295B2 (en) Project personnel selection support management system and program
CN115239179A (en) Chemical production operation flow system
JP2018173796A (en) Technical instructor dispatch support apparatus, technical instructor dispatch support system and technical instructor dispatch support method
RU2493596C1 (en) System and method of managing maintenance of buildings and structures
WO2021064877A1 (en) Work management device, work management method, and recording medium
US20240104455A1 (en) Information processing apparatus, information processing method, and non-transitory computer-readable storage medium
US20060004687A1 (en) Web-based event correction and prevention system
WO2022249309A1 (en) Progress management server and progress management system
KR102595680B1 (en) smart integrated safety management system with versatility

Legal Events

Date Code Title Description
A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230113

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230113

A871 Explanation of circumstances concerning accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A871

Effective date: 20230113

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230328

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230523

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230725

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230925

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20231212

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20231225

R150 Certificate of patent or registration of utility model

Ref document number: 7411623

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150