JP2006024035A - Construction management system using mobile communication equipment - Google Patents

Construction management system using mobile communication equipment Download PDF

Info

Publication number
JP2006024035A
JP2006024035A JP2004202273A JP2004202273A JP2006024035A JP 2006024035 A JP2006024035 A JP 2006024035A JP 2004202273 A JP2004202273 A JP 2004202273A JP 2004202273 A JP2004202273 A JP 2004202273A JP 2006024035 A JP2006024035 A JP 2006024035A
Authority
JP
Japan
Prior art keywords
construction
data
item
progress
database
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2004202273A
Other languages
Japanese (ja)
Other versions
JP4030986B2 (en
JP2006024035A5 (en
Inventor
Itaru Koyama
山 至 小
Hideki Shindo
藤 英 樹 新
Maki Shinozuka
塚 真 樹 篠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ando Corp
Original Assignee
Ando Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ando Corp filed Critical Ando Corp
Priority to JP2004202273A priority Critical patent/JP4030986B2/en
Publication of JP2006024035A publication Critical patent/JP2006024035A/en
Publication of JP2006024035A5 publication Critical patent/JP2006024035A5/ja
Application granted granted Critical
Publication of JP4030986B2 publication Critical patent/JP4030986B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide a construction management system using mobile communication equipment always acquiring the latest numerical data about a progress condition of building construction in real time from a construction management server without requiring any input of data about the progress condition from a person. <P>SOLUTION: A process management server is provided with a communication means 11, a process management calculation means 12, a constructor supervisor database 13, a process database 14, and a memory 15 storing a construction progress list 16, a process chart 17, an overall process table 18 for each construction item and an overall process table 19. Data such as a construction place and a construction item are inherited by an electronic mail, and a transmitter and a transmission time are acquired from the electronic mail. <P>COPYRIGHT: (C)2006,JPO&NCIPI

Description

本発明は、携行可能な無線通信機能を有する移動通信機器、コンピューター(PDA等)、携帯電話を用いた施工管理システムに関する。   The present invention relates to a mobile communication device having a portable wireless communication function, a computer (PDA, etc.), and a construction management system using a mobile phone.

特に、建設の施行の進捗状況について、進捗状況のグラフ化、進捗状況の積算等について人間が入力をする必要がない完全に自動化された移動通信機器を用いた施工管理システムに関する。   In particular, the present invention relates to a construction management system using a fully automated mobile communication device that does not require human input regarding the progress of construction implementation, graphing of the progress, and integration of progress.

なお、本発明は任意の無線通信機能有する移動通信機器を使用することができるが、携帯電話を利用することが好ましいので、以下本明細書において、無線通信機能を有する移動通信機器を携帯電話に限定することなく、携帯電話を用いて本発明を説明する。   Although the present invention can use a mobile communication device having an arbitrary wireless communication function, it is preferable to use a mobile phone. Therefore, in the present specification, a mobile communication device having a wireless communication function is referred to as a mobile phone. Without limitation, the present invention will be described using a mobile phone.

一般に、建設の現場において、施工の指示、施工完了の報告、進捗状況の報告等について携帯電話が種々に利用されている。   In general, various mobile phones are used in construction sites for construction instructions, construction completion reports, progress reports, and the like.

従来から、PDAや携帯電話を用いて建設現場の施工の連絡や管理をする提案が種々されていた。   Conventionally, there have been various proposals for using a PDA or a mobile phone to communicate and manage the construction site.

また、建設現場において、施工管理をする施工管理センターを置き、該施工管理センターにコンピューターを備え、建設工事の進捗状況を当該コンピューターに入力し、建設工事の進捗状況をコンピューターによって管理することも広く行われていた。   It is also common to set up a construction management center for construction management at the construction site, to provide a computer in the construction management center, to input the progress of construction work into the computer, and to manage the progress of construction work by computer. It was done.

また、移動通信機器とコンピューターを組み合わせた施工管理システムも提案されていた。   Also, a construction management system that combines a mobile communication device and a computer has been proposed.

たとえば、所定の施工項目について、建設工事を監督する監督者が施工の進捗状況(進捗率)を入力して施工管理用コンピューターに送り、施工管理用コンピューターによって集計や進捗状況一覧等の処理を行い、施工管理者がこれらの出力を利用して施工管理を行うシステムが提案されている。   For example, the supervisor who supervises the construction work inputs the progress (progress rate) of the construction for a given construction item, sends it to the construction management computer, and processes the summary and progress list by the construction management computer. A system has been proposed in which a construction manager uses these outputs to perform construction management.

上記従来の技術によれば、それまで施工者や監督者等人間が施工管理センターに赴き、建設工事の進捗状況の報告を行う手間が省かれる。
特開2002−107099号公報 特開2002−295017号公報 特許第2847049号公報 特許第2848553号公報 特許第3373844号公報
According to the above-described conventional technique, it is possible to save the labor of a person such as a construction worker or supervisor who has visited the construction management center and reporting the progress of construction work.
JP 2002-107099 A JP 2002-295017 A Japanese Patent No. 2847049 Japanese Patent No. 2848553 Japanese Patent No. 3373844

しかし、上記従来の技術では、施工管理のいずれかの過程で、人間が介在して工事の進捗管理のための情報収集を指示し、あるいは、建設工事の進捗状況のデータ(進捗率のデータ等)を施工管理用コンピューターに送信するために進捗状況のデータ(進捗率のデータ等)を移動通信機器に入力し、あるいは、人間が建設工事の進捗状況のデータ(進捗率のデータ等)を操作して、建設工事の進捗状況を出力するようになっていた。   However, in the conventional technology described above, in any process of construction management, humans intervene to instruct information collection for construction progress management, or construction construction progress data (such as progress rate data) ) Is sent to the construction management computer, progress data (progress rate data, etc.) is input to the mobile communication device, or a person operates the construction progress data (progress rate data, etc.). Then, the progress of construction work was output.

このように、建設工事の進捗状況の管理を行うのに、途中で人間がデータの入力やデータの操作を行なうのでは、人間の労力が完全に省かれず、かつ、人間が入力しあるいは操作するまで正式な建設工事の進捗状況の数字が得られず、リアルタイムで施工管理を行うことができなかった。   In this way, in order to manage the progress of construction work, if human beings input data or manipulate data on the way, human labor is not completely saved, and human inputs or operations are performed. Until then, official construction progress figures could not be obtained and construction management could not be performed in real time.

そこで、本発明が解決しようとする課題は、途中で人間が進捗状況のデータ(進捗率のデータ等)を入力し、あるいは、工事の進捗状況のデータを出力するために人間がコンピューターの操作をする必要がなく、施工管理を開始した後は常に建設工事の進捗状況の最新の数字がリアルタイムで施工管理サーバーから得られる「移動通信機器を用いた施工管理システム」を提供することにある。   Therefore, the problem to be solved by the present invention is that a human inputs a progress data (such as progress rate data) on the way, or a human operates a computer in order to output construction progress data. It is not necessary to provide a “construction management system using a mobile communication device” in which the latest number of the progress of construction work is always obtained in real time from the construction management server after the construction management is started.

本発明による移動通信機器を用いた施工管理システムは、
移動通信機器と必要に応じて設けられる工程管理用コンピューターとデータ通信するための通信手段と、少なくとも施工者アドレスと施工場所と施工項目と監督者アドレスをデータ項目に含みそれらデータ項目のデータを対応可能に記憶する施工者監督者データベースと、施工場所と前記施工場所の施工項目と各施工項目の進捗のデータとを記憶する工程データベースと、前記施工者監督者データベースと前記工程データベースに対して検索と更新を行い、前記通信手段から受信した電子メールからデータを取得し送信の指示を行い、全施工場所の施工項目を施工場所ごとにグラフに示した工事進捗一覧表と各施工場所の施工項目の軸と時間軸を有し各施工項目を時間の棒グラフに表した工程チャートとをリンク可能に表示させるデータを算出する工程管理計算手段と、前記工事進捗一覧表と前記工程チャートと施工開始基準時のデータを記憶するメモリと、を有する工程管理サーバーを有し、
前記工程管理サーバーは、前記工程管理計算手段が前記工程データベースから各施工場所の最初の施工項目のデータを取得し、前記施工場所と施工項目のデータを用いて前記施工者管理者データベースから各施工場所の最初の施工者アドレスを検索して前記通信手段に命令して前記施工者アドレスに施工場所と施工開始の指示を含む施工開始用電子メールを送信させ、送信時間を施工開始基準時として前記メモリに記憶させ、
前記通信手段が、施工者の移動通信機器から、送信時間と施工場所のデータを含む施工済電子メールを受信すると、前記工程管理計算手段が、前記施工者の電子メールから送信者である施工者アドレスと施工場所のデータとを入力し前記施工者アドレスと施工場所のデータを用いて前記施工者監督者データベースから当該施工場所の施工項目の監督者アドレスを検索し、前記通信手段に命令して前記施工場所と前記施工項目と施工検査の指示を含む検査指示電子メールを前記監督者アドレスに送信させ、
前記通信手段が、監督者の移動通信機器から、送信時間と検査合否データと施工場所と施工項目のデータとを含む検査済電子メールを受信すると、前記工程管理計算手段が、前記検査済電子メールから前記検査合否データを取得し、前記検査合否データが不合格を示すデータである場合は、前記検査済電子メールから施工場所と施工項目のデータを取得し、前記施工場所と施工項目のデータを用いて前記施工者監督者データベースから施工者アドレスを検索し、前記通信手段に命令して前記施工場所の前記施工項目の再施工の指示を含む再施工指示電子メールを前記検索した施工者アドレスに送信させ、
前記検査合否データが合格である場合は、前記検査済電子メールから施工場所と施工項目のデータを取得し、前記施工場所と施工項目のデータを用いて前記工程データベースから進捗データが施工中の施工項目データを検索し、前記施工項目データの進捗データを完了に更新するとともに前記完了に更新した施工項目データの次の施工項目データの進捗データを施工中に更新し、前記工事進捗一覧表上の前記施工場所のグラフについて更新された施工項目の進捗データに応じてグラフを表示できるように工事進捗一覧表のデータを更新し、前記検査済電子メールから送信時間を取得し、前記施工開始基準との差を求めて前記施工場所の工程チャートの時間軸上の点と前記施工場所の施工項目の軸上の前記進捗データを完了に更新した施工項目とを特定し、当該施工項目の施工開始から施工完了まで時間を棒グラフとして表示する工程チャートのデータを更新し、前記工程データベースの前記施工場所の施工項目から進捗データが施工中の施工項目データを検索し、前記施工場所と施工項目のデータを用いて前記施工者監督者データベースから施工者アドレスを検索し、前記通信手段に命令して施工場所と施工開始の指示とを含む施工指示電子メールを前記施工者アドレスに送信させ、前記送信時間を前記進捗データが施工中の施工項目の施工開始時間として記憶する、ことを特徴とするものである。
Construction management system using mobile communication equipment according to the present invention,
Communication means for data communication with a mobile communication device and a process management computer provided as necessary, and at least the installer address, construction location, construction item, and supervisor address are included in the data item, and the data of the data item is supported Retrieving the construction manager supervisor database, the construction database, the construction database of the construction site, and the progress data of each construction item, the construction supervisor supervisor database, and the process database. Update data, obtain data from the e-mail received from the communication means, instruct the transmission, and display the work progress list for each work place and the work items for each work place. Calculate the data that can be linked to the process chart that has the axis and the time axis and represents each construction item in a bar graph of time. Has to a process control computing means, a memory for storing data during said construction progress schedule the process chart and construction starting reference, the process control server having,
In the process management server, the process management calculation means obtains data of the first construction item of each construction place from the process database, and uses the construction place and construction item data to perform each construction from the installer manager database. Search for the first builder address of the place and instruct the communication means to send a construction start e-mail including a construction place and a construction start instruction to the builder address, with the transmission time as the construction start reference time Memorize it in memory,
When the communication means receives a construction-completed email including transmission time and construction location data from the contractor's mobile communication device, the process management calculation means is a contractor who is a sender from the constructor's email. Enter the address and construction location data, search the supervisor address of the construction item of the construction location from the constructor supervisor database using the construction worker address and construction location data, and instruct the communication means An inspection instruction email including the construction location, the construction item, and a construction inspection instruction is transmitted to the supervisor address,
When the communication means receives an inspected e-mail including a transmission time, inspection pass / fail data, construction location, and construction item data from the supervisor's mobile communication device, the process management calculation means, the inspection management e-mail If the inspection acceptance / rejection data is data indicating failure, the construction location and construction item data are obtained from the inspected email, and the construction location and construction item data are obtained. Use the installer's supervisor database to search for the installer's address, and instruct the communication means to send the re-installation instruction e-mail including the instructions for re-installation of the construction item at the construction location to the searched installer's address. Send
If the inspection pass / fail data is acceptable, the construction location and construction item data are acquired from the inspected email, and the progress data from the process database is being constructed using the construction location and construction item data. Search the item data, update the progress data of the construction item data to completion, and update the progress data of the construction item data next to the construction item data updated to completion during construction, on the construction progress list Update the construction progress table data so that the graph can be displayed according to the progress data of the construction items updated for the construction place graph, obtain the transmission time from the inspected email, and the construction start standard and The construction item which updated the progress data on the point on the time axis of the process chart of the construction place and the construction item axis of the construction place to find the difference between them Update the process chart data that displays the time from the start of construction of the construction item to the completion of construction as a bar graph, and search the construction item data for which the progress data is under construction from the construction item at the construction location in the process database Then, using the construction location and construction item data, retrieve the construction worker address from the construction supervisor database, and instruct the communication means to send the construction instruction email including the construction location and construction start instruction. It transmits to a construction worker address, The said transmission time is memorize | stored as a construction start time of the construction item in which the said progress data is construction.

本発明による移動通信機器を用いた施工管理システムは、
移動通信機器と必要に応じて設けられる工程管理用コンピューターとデータ通信するための通信手段と、少なくとも施工者アドレスと施工場所と施工項目と監督者アドレスをデータ項目に含みそれらデータ項目のデータを対応可能に記憶する施工者監督者データベースと、施工場所と前記施工場所の施工項目と施工順序データと各施工項目の進捗のデータとを記憶する工程データベースと、前記施工者監督者データベースと前記工程データベースに対して検索を行い、前記通信手段から受信した電子メールからデータを取得し送信の指示を行い、全施工場所の施工項目を施工場所ごとにグラフに示した工事進捗一覧表と各施工場所の施工項目の軸と時間軸を有し各施工項目を時間の棒グラフに表した工程チャートとをリンク可能に表示させるデータを算出する工程管理計算手段と、前記工事進捗一覧表と前記工程チャートと施工開始基準時のデータを記憶するメモリと、を有する工程管理サーバーを有し、
前記工程管理サーバーは、前記工程管理計算手段が前記工程データベースから各施工場所の最初の施工項目のデータを取得し、前記施工場所と施工項目のデータを用いて前記施工者管理者データベースから各施工場所の最初の施工者アドレスを検索して前記通信手段に命令して前記施工者アドレスに施工場所と施工項目と施工開始の指示を含む施工開始用電子メールを送信させ、送信時間を施工開始基準時として前記メモリに記憶させ、
前記通信手段が、施工者の移動通信機器から、送信時間と施工場所と施工項目のデータを含む施工済電子メールを受信すると、前記工程管理計算手段が、前記施工者の電子メールから送信者である施工者アドレスと施工場所と施工項目のデータとを入力し前記施工者アドレスと施工場所と施工項目のデータを用いて前記施工者監督者データベースから当該施工項目の監督者アドレスを検索し、前記通信手段に命令して前記施工場所と前記施工項目と施工検査の指示を含む検査指示電子メールを前記監督者アドレスに送信させ、
前記通信手段が、監督者の移動通信機器から、送信時間と検査合否データと施工場所と施工項目のデータとを含む検査済電子メールを受信すると、前記工程管理計算手段が、前記検査済電子メールから前記検査合否データを取得し、前記検査合否データが不合格を示すデータである場合は、前記検査済電子メールから施工場所と施工項目のデータを取得し、前記施工場所と施工項目のデータを用いて前記施工者監督者データベースから施工者アドレスを検索し、前記通信手段に命令して前記施工場所の前記施工項目の再施工の指示を含む再施工指示電子メールを前記検索した施工者アドレスに送信させ、
前記検査合否データが合格である場合は、前記検査済電子メールから施工場所と施工項目のデータを取得し、前記工事進捗一覧表上の前記施工場所のグラフについて新たに完了した施工項目に応じてグラフを表示できるように工事進捗一覧表のデータを更新し、前記検査済電子メールから送信時間を取得し、前記施工開始基準との差を求めて前記施工場所の工程チャートの時間軸上の点と前記施工場所の施工項目の軸上の前記新たに完了した施工項目とを特定し、当該施工項目の施工開始から施工完了まで時間を棒グラフとして表示する工程チャートのデータを更新し、前記工程データベースを参照し前記施工場所の前記新たに完了した施工項目の進捗データを完了に更新し施工順序データを参照してその次に施工すべき施工項目データを検索し、前記施工場所と次に施工すべき施工項目のデータを用いて前記施工者監督者データベースから施工者アドレスを検索し、前記通信手段に命令して施工場所と施工項目と施工開始の指示とを含む施工指示電子メールを前記施工者アドレスに送信させ、前記送信時間を前記新たに施工開始の指示をした施工項目の施工開始時間として記憶する、ことを特徴とするものである。
Construction management system using mobile communication equipment according to the present invention,
Communication means for data communication with a mobile communication device and a process management computer provided as necessary, and at least the installer address, construction location, construction item, and supervisor address are included in the data item, and the data of the data item is supported The construction supervisor database that can be stored, the construction location, the construction items of the construction location, the construction order data, and the progress data of each construction item, the construction supervisor database, and the construction database. Search for data, obtain data from the e-mail received from the communication means, instruct the transmission, and display the construction progress list showing the construction items of all construction sites for each construction site and each construction site. A work chart that has a work item axis and a time axis, and displays each work item as a bar graph of time is displayed in a linkable manner. Includes a process control calculating means for calculating the over data, a memory for storing data during construction start reference to the construction progress schedule and the step charts, process control server having,
In the process management server, the process management calculation means obtains data of the first construction item of each construction place from the process database, and uses the construction place and construction item data to perform each construction from the installer manager database. Search for the first builder address of the place, instruct the communication means to send an e-mail for construction start including the construction place, construction item and construction start instruction to the builder address, and set the transmission time as the construction start standard. Sometimes stored in the memory,
When the communication means receives a construction-completed e-mail including transmission time, construction place and construction item data from the mobile communication device of the builder, the process management calculation means is a sender from the builder's e-mail. Enter a certain installer address, construction location and construction item data, and search for the supervisor address of the construction item from the construction supervisor database using the construction worker address, construction location and construction item data. Instruct the communication means to send an inspection instruction e-mail including the construction location, the construction item, and an instruction of construction inspection to the supervisor address,
When the communication means receives an inspected e-mail including a transmission time, inspection pass / fail data, construction location, and construction item data from the supervisor's mobile communication device, the process management calculation means, the inspection management e-mail If the inspection acceptance / rejection data is data indicating failure, the construction location and construction item data are obtained from the inspected email, and the construction location and construction item data are obtained. Use the installer's supervisor database to search for the installer's address, and instruct the communication means to send the re-installation instruction e-mail including the instructions for re-installation of the construction item at the construction location to the searched installer's address. Send
If the inspection pass / fail data is acceptable, obtain the data of the construction location and construction item from the inspected email, and according to the newly completed construction item for the construction location graph on the construction progress list Update the construction progress list data so that the graph can be displayed, obtain the transmission time from the inspected e-mail, find the difference from the construction start standard, and the point on the time axis of the process chart of the construction place And the newly completed construction item on the axis of the construction item of the construction place, update the process chart data that displays the time from the construction start of the construction item to the construction completion as a bar graph, the process database The progress data of the newly completed construction item at the construction location is updated to completion, and the construction item data to be constructed next is checked by referring to the construction sequence data. Then, using the data of the construction location and the next construction item to be constructed, retrieve the construction worker address from the construction supervisor database, and instruct the communication means to construct the construction location, the construction item, and the construction start instruction. The construction instruction e-mail including the above is transmitted to the installer address, and the transmission time is stored as the construction start time of the construction item for which the construction start instruction has been newly made.

前記施工管理計算手段はさらに、前記検査合否データが合格を示すデータであって、前記工程データベースの進捗データが施工中の施工項目データを進捗データが完了に更新したときは、前記工程データベースから施工項目データの種別ごとに進捗データが完了の施工データ項目と進捗データが施工中あるいは未だ施工中にも完了にもなっていない施工データ項目を検索して集計し、施工項目の種別ごとの完了率をグラフに表示する施工項目別全体工程表のデータを更新するようにすることができる。   The construction management calculation means further includes data indicating that the inspection pass / fail data is acceptable, and when the progress data of the process database updates the construction item data under construction to the completion of the progress data, the construction database starts construction from the process database. Search and aggregate construction data items whose progress data is completed for each item data type and construction data items whose progress data is under construction or not yet completed during construction, and the completion rate for each type of construction item It is possible to update the data of the entire process chart for each construction item for displaying the graph on the graph.

前記施工管理計算手段はさらに、前記検査合否データが合格を示すデータであって、前記工程データベースの進捗データが施工中の施工項目データを進捗データが完了に更新したときは、前記工程データベースから施工項目データの種別ごとに進捗データが完了の施工データ項目と進捗データが施工中あるいは未だ施工中にも完了にもなっていない施工データ項目を検索して集計し、施工項目の種別ごとの完了率を計算し、さらに各施工項目の完了率に各施工項目の全工事に対するウェイトを乗じて合計して全体工程完了率を算出し、前記検査済電子メールの送信時間から取得した時間と前記算出した全体工程完了率により、時間軸と全体工程の完了率の軸を有し時間経過に伴う全体工程の完了率の変化をグラフに表示する全体工程表のデータを更新するようにすることができる。   The construction management calculation means further includes data indicating that the inspection pass / fail data is acceptable, and when the progress data of the process database updates the construction item data under construction to the completion of the progress data, the construction database starts construction from the process database. Search and aggregate construction data items whose progress data is completed for each item data type and construction data items whose progress data is under construction or not yet completed during construction, and the completion rate for each type of construction item Calculate the total process completion rate by multiplying the completion rate of each construction item by the weight for all constructions of each construction item, and calculate the total process completion rate, and the time obtained from the transmission time of the inspected email and the calculated The data of the overall process table that displays the change in the completion rate of the overall process over time, with a time axis and the axis of the completion rate of the overall process. It can be made to update the.

本発明によれば、工程管理サーバーが工程データベースから工事現場の各施工場所の最初の施工項目を検索し、前記最初の施工項目の施工者アドレスを施工者監督者データベースから検索して施工場所を指示した施工開始用電子メールを送信する。   According to the present invention, the process management server retrieves the first construction item of each construction site on the construction site from the process database, retrieves the installer address of the first construction item from the installer supervisor database, and determines the construction site. Send the designated construction start e-mail.

その後、施工者が施工を完了したときは施工済電子メールを工程管理サーバーに送信し、これに対して工程管理サーバーは担当する監督者を施工者監督者データベースから検索しその監督者に検査指示電子メールを送信する。前記監督者が、検査済電子メールを工程管理サーバーに送信すると、工程管理サーバーが自動的に検査済電子メールから検査合否を判断し、検査が合格した場合は工程データベースを更新し、工事進捗一覧表、工程チャート、施工項目別全体工程表、全体工程表を更新する。   After that, when the installer completes the construction, a construction completion e-mail is sent to the process management server. In response to this, the process management server searches the supervisor supervisor database for the supervisor in charge, and instructs the supervisor to inspect it. Send an email. When the supervisor sends an inspected e-mail to the process management server, the process management server automatically determines the inspection pass / fail from the inspected e-mail, and if the inspection passes, the process database is updated, and the construction progress list Update table, process chart, overall process chart by construction item, and overall process chart.

一方、工程管理サーバーが自動的に検査済電子メールから検査合否を判断し、検査が不合格である場合は、工程管理サーバーから施工者に対して再施工を指示する再施工指示電子メールを送信する。この場合は、検査が合格するまで上記施工済み電子メール、検査指示電子メール、検査済電子メール等の送受信および合否の判定を繰り返す。   On the other hand, the process management server automatically determines pass / fail from the inspected e-mail, and if the inspection fails, the process management server sends a re-construction instruction e-mail instructing the installer to re-install. To do. In this case, the transmission / reception of the construction-completed e-mail, the inspection instruction e-mail, the inspected e-mail and the like and the determination of pass / fail are repeated until the inspection passes.

本発明においては、工程管理サーバーが工程データベースから工事現場の各施工場所の最初の施工項目を検索し上記施工開始用電子メールに施工場所のデータを記入して送信してから、施工済電子メール、検査指示電子メール、検査済電子メール、再施工指示電子メールの各メールにおいて、上記施工場所のデータが引き継がれる。   In the present invention, the process management server searches the process database for the first construction item of each construction site on the construction site, fills in the construction site data in the construction start e-mail, and transmits it. In each of the inspection instruction e-mail, the inspected e-mail, and the reconstruction instruction e-mail, the data of the construction place is taken over.

これにより、施工者と監督者は、自ら施工場所のデータを入力することなく、所定の施工項目が開始してから完了するまで、検査の合否の入力を除いて、単純な返信メールの送信だけを行うことで工程管理の情報収集がなされる。   As a result, the contractor and the supervisor can only send a simple reply e-mail, except for entering the pass / fail of the inspection, from the start to the completion of the predetermined construction item, without entering the data of the construction site by themselves. To collect information on process management.

また、本発明においては、送信者は電子メールの送信者から得られるため、工程管理サーバーが送信者のデータと工程データベースから次の行動を行う者を検索し、逐次次の行動を行う者に適当なタイミングで適当な指示をすることができる。次の行動を行う者に電子メールによって指示を与えた段階で工事の進捗状況が自動的に更新される。   In the present invention, since the sender is obtained from the sender of the e-mail, the process management server searches the sender's data and the process database for a person who performs the next action, An appropriate instruction can be given at an appropriate timing. The construction progress is automatically updated when an instruction is given by e-mail to the person who performs the next action.

また、本発明においては、電子メールの送信時間から時間のデータが得られるため、所定の施工場所の所定の施工項目の施工開始時間、施工完了時間、検査完了時間等のデータが自動的に取得される。これにより、時間の経過に伴う工事の進捗が自動的に取得される。   Also, in the present invention, since time data is obtained from the e-mail transmission time, data such as construction start time, construction completion time, inspection completion time, etc. of a predetermined construction item at a predetermined construction place are automatically acquired. Is done. Thereby, the progress of the construction over time is automatically acquired.

以上の自動的な機能が組み合わさることにより、本発明によれば、いったん工程管理が開始されると、人間が工事の進捗データ(工事の進捗率データ等)を入力することなく、自らのIDや担当の施工項目等の識別情報を入力することもなく、単純に電子メールに返信することによって自動的に工事の進捗状況のデータが取得され、工事進捗一覧表、工程チャート、施工項目別全体工程表、全体工程表等のデータに反映され、常に最新の工事進捗状況が工程管理サーバーから出力され、かつ、次の施工項目を行う施工者に自動的に次の施工の指示が送信される。   By combining the above automatic functions, according to the present invention, once the process management is started, the person's ID can be entered without inputting construction progress data (such as construction progress rate data). No need to input identification information such as construction items in charge or work in charge, simply by replying to e-mail, construction progress status data is automatically acquired, construction progress list, process chart, entire construction item The latest construction progress is always output from the process management server, and the next construction instruction is automatically sent to the installer who performs the next construction item. .

工事管理サーバーの出力は、工事管理サーバー自体の近傍に設置される表示装置に出力され、あるいは、インターネット等の情報通信網を通じて任意のコンピューターに送信される。これにより工事の管理者はリアルタイムで工事の管理を行うことができる。   The output of the construction management server is output to a display device installed in the vicinity of the construction management server itself, or transmitted to an arbitrary computer through an information communication network such as the Internet. As a result, the construction manager can manage the construction in real time.

また、施工項目が施工順序データを有する場合は、同一の施工者が複数の施工項目を施工し、あるいは、複数の施工項目が同時並行的に進行するような場合に適用することができる。   Moreover, when a construction item has construction order data, it can apply when the same installer constructs a plurality of construction items, or a plurality of construction items advance simultaneously.

この場合においても、いったん工程管理が開始されると、人間が工事の進捗データ(工事の進捗率データ等)を入力することなく、送信者が自らのIDや担当の施工項目等の識別情報を入力することもなく、単純に電子メールに返信することによって自動的に工事の進捗状況のデータが取得され、工事進捗一覧表、工程チャート、施工項目別全体工程表、全体工程表等のデータに反映され、常に最新の工事進捗状況が工程管理サーバーから出力される。   Even in this case, once the process management is started, the sender does not input construction progress data (construction progress rate data, etc.), and the sender can provide identification information such as his / her ID and the construction item in charge. By simply replying to an e-mail without input, construction progress data is automatically acquired, and it is converted into construction progress list, process chart, overall process chart for each work item, overall process chart, etc. Reflected, the latest construction progress is always output from the process management server.

その上、同時並行的に進行する施工項目に対して、各施工項目のそれぞれの施工者や監督者に適当なタイミングで作業等を指示することができる。   In addition, it is possible to instruct work and the like of each work item at an appropriate timing with respect to the work items proceeding in parallel.

以下に本発明の実施の形態について説明する。   Embodiments of the present invention will be described below.

図1は、本発明の一実施形態による移動通信機器を用いた工程管理システムの全体を示している。   FIG. 1 shows the entire process management system using a mobile communication device according to an embodiment of the present invention.

図1に示すように、本実施形態による移動通信機器を用いた工程管理システム1は、移動通信機器2と、移動通信網3と、インターネット4と、工程管理サーバー5とからなる。   As shown in FIG. 1, the process management system 1 using a mobile communication device according to the present embodiment includes a mobile communication device 2, a mobile communication network 3, the Internet 4, and a process management server 5.

移動通信網3は移動通信機器中継局6を有している。   The mobile communication network 3 has a mobile communication device relay station 6.

移動通信機器2は携帯電話でも携帯可能なコンピュータあるいはPDA等の通信機能を有する情報処理装置であってもよい。   The mobile communication device 2 may be a computer that can be carried by a mobile phone or an information processing device having a communication function such as a PDA.

インターネット4には必要に応じて工程管理用コンピューター7が接続されている。工程管理用コンピューター7は、工程管理サーバー5から工事進捗一覧表、工程チャート、全体工程表、施工項目別全体工程表等の工事進捗の情報を受信して、遠隔の場所で工事の進捗を監視することができるようになっている。   A process management computer 7 is connected to the Internet 4 as necessary. The process management computer 7 receives construction progress information such as a construction progress list, a process chart, an overall process chart, and an overall process chart for each construction item from the process management server 5 and monitors the progress of the construction at a remote location. Can be done.

工程管理用コンピューター7は、必要に応じて設けることができ、工程管理サーバー5の近傍に表示装置を設けてそこで工事の工程管理を行う場合は省略することができる。   The process management computer 7 can be provided as necessary, and can be omitted when a display device is provided in the vicinity of the process management server 5 and the construction process is managed there.

次に、本発明の中心的な部分である工程管理サーバー5の構成とその処理について説明する。   Next, the configuration and processing of the process management server 5 which is a central part of the present invention will be described.

図2は工程管理サーバー5の構成を示している。   FIG. 2 shows the configuration of the process management server 5.

図2に示すように、工程管理サーバー5は通信手段11と、工程管理計算手段12と、施工者監督者データベース13と、工程データベース14と、メモリ15とを有している。   As shown in FIG. 2, the process management server 5 includes a communication unit 11, a process management calculation unit 12, a contractor supervisor database 13, a process database 14, and a memory 15.

メモリ15には、工事進捗一覧表16、工程チャート17、施工項目別全体工程表18、全体工程表19等のデータが記憶されている。   The memory 15 stores data such as a construction progress list 16, a process chart 17, an overall process table 18 for each work item, and an overall process chart 19.

通信手段11は、移動通信機器2や工程管理用コンピューター7とデータ通信を行う手段である。   The communication means 11 is means for performing data communication with the mobile communication device 2 and the process management computer 7.

施工者監督者データベース13は、少なくとも施工者アドレス、施工場所、施工項目、監督者アドレスをデータ項目に含み、それらデータ項目のデータを対応可能に記憶管理するデータベースである。   The contractor supervisor database 13 is a database that includes at least a contractor address, a construction location, a construction item, and a supervisor address as data items, and stores and manages the data items so that they can be handled.

本明細書において「データベース」というときは、検索や更新を行うことができるように体系的に記憶されたデータと、それらのデータを記憶する記憶装置も含むものをいうものとする。   In this specification, the term “database” includes data systematically stored so that search and update can be performed and a storage device that stores the data.

施工場所というのは、たとえばマンションの建設工事現場で、工事がマンションの部屋ごとに行われるような場合に、各部屋がそれぞれ「施工場所」というように、工事現場で工事を行う上で場所が特定できる場合の施工場所である。   For example, when a construction site is an apartment construction site where the construction is performed for each apartment room, each room is called a “construction site”. This is the construction site when it can be identified.

施工項目というのは、たとえばマンションの部屋であれば、壁工事、床工事、天井工事、電気工事、水道工事、装備工事、玄関工事等の施工の種別の項目である。   For example, in the case of a condominium room, the construction items are items of construction types such as wall construction, floor construction, ceiling construction, electrical construction, waterworks construction, equipment construction, and entrance construction.

工程データベース14は、施工場所と、各施工場所の施工項目と、各施工項目の進捗のデータとを記憶するデータベースである。   The process database 14 is a database that stores construction locations, construction items at each construction location, and progress data of each construction item.

この実施形態では、前記工程データベース14の施工項目は、施工の順番に並べられて記憶されている(図2における項目1、項目2、項目3、・・・)。   In this embodiment, the construction items in the process database 14 are arranged and stored in the order of construction (item 1, item 2, item 3,... In FIG. 2).

施工項目の進捗データは、たとえば施工が開始された施工項目は“0”、施工が完了した施工項目は“1”、施工が開始されていない施工項目はその他の任意のデータを入れ、未施工、施工中、施工完了の状態が判別できるようにしたデータである。   The progress data of construction items is, for example, “0” for construction items where construction has started, “1” for construction items where construction has been completed, and any other data for construction items where construction has not started. This is data that allows the state of construction completion to be determined during construction.

工事進捗一覧表16は、視覚的に把握できるように工事現場の施工場所を表示し、かつ、各施工場所について施工項目と各施工項目が完了したか否かの進捗をグラフに表したものである。   The construction progress list 16 displays the construction site on the construction site so that it can be grasped visually, and shows the progress of each construction site and whether or not each construction item is completed in a graph. is there.

本実施形態では、図2に示すように、マンションを建設する工事現場において、各部屋を枡目で表し、さらに壁工事、床工事、天井工事、電気工事、水道工事、装備工事、玄関工事等の各部屋に必要な施工項目の全体で枡目が埋め尽くされるように、各枡目を施工項目数に応じて分割している。   In this embodiment, as shown in FIG. 2, in the construction site where the apartment is constructed, each room is represented by a grid, and further, wall construction, floor construction, ceiling construction, electrical construction, waterworks construction, equipment construction, entrance construction, etc. Each square is divided according to the number of construction items so that the whole construction items necessary for each room are filled.

この工事進捗一覧表は、壁工事等の所定の施工項目が完了するとその施工項目の部分が異なった色で塗りつぶされるように表示する。   This construction progress list is displayed such that when a predetermined construction item such as wall construction is completed, the construction item portion is filled with a different color.

これにより、工事進捗一覧表を見る者は、一目で工事現場全体で工事が遅れている施工場所や、全体の工事の進捗を把握することができるようになっている。   Thereby, a person viewing the construction progress list can grasp at a glance the construction site where construction is delayed in the whole construction site and the progress of the whole construction.

なお、各施工場所のグラフは図2の例のような分割された枡目に限られず、円グラフ、棒グラフでもよい。要するに、各施工項目が完了したか否かの進捗と全体の施工項目のうちどの施工項目が完了したかが把握できるものであればよい。   In addition, the graph of each construction place is not restricted to the divided | segmented square like the example of FIG. 2, A circle graph and a bar graph may be sufficient. In short, it is only necessary to be able to grasp the progress of whether or not each construction item is completed and which construction item is completed among the entire construction items.

工程チャート17は、時間軸と施工項目の軸を有し、各施工場所ごとに、施工項目の時間的経過を棒グラフに示したものである。   The process chart 17 has a time axis and an axis of construction items, and shows the progress of construction items over time in a bar graph for each construction place.

工程チャート17は、時間経過に伴う施工項目の推移を示しているので、工程チャート17上の施工項目の推移は工程データベース14の施工項目の施工の順番と対応している。   Since the process chart 17 shows the transition of construction items over time, the transition of construction items on the process chart 17 corresponds to the construction order of construction items in the process database 14.

施工項目別全体工程表18は、進捗状況(完了率%)の軸と、施工項目の軸を有している。施工項目別全体工程表18は、施工場所ごとに細分化せずに、工事現場全体で見た場合の各施工項目の進捗状況(完了率%)をグラフに表したものである。   The entire process table 18 by construction item has an axis of progress (completion rate%) and an axis of construction items. The entire process table 18 by construction item is a graph showing the progress (completion rate%) of each construction item when viewed from the entire construction site without being subdivided for each construction site.

たとえば、マンションの部屋の床工事であれば、たとえば全マンションの部屋の床工事が完了した時を100%とすると、現在床工事が完了している部屋数と全部屋の部屋数の比率が床工事の完了率となる。   For example, in the case of floor construction of condominium rooms, for example, if the floor construction of all condominium rooms is 100%, the ratio of the number of rooms that have been completed and the number of rooms in all rooms is the floor. Completion rate of construction.

床工事に限られず、壁工事、天井工事、電気工事等も施工項目ごとに完了率が計算され、施工項目別全体工程表18に表される。   Completion rates are calculated for each construction item for wall construction, ceiling construction, electrical construction, etc., not limited to floor construction, and are shown in the overall process table 18 for each construction item.

全体工程表19は、上記施工項目別全体工程表18の各施工項目の完了率に、全工事に対する各施工項目の比重(ウェイト)を乗じて合計し、それを時間の経過に応じてグラフ化したものである。図2の例では、全体工程表19のグラフは折れ線グラフであるが、棒グラフ、円グラフ等であってもよい。   The total process table 19 multiplies the completion rate of each construction item in the above-mentioned overall process table 18 by the construction item by the specific gravity (weight) of each construction item with respect to the total construction, and graphs it as time passes. It is a thing. In the example of FIG. 2, the graph of the overall process table 19 is a line graph, but may be a bar graph, a pie chart, or the like.

工程管理計算手段12は、施工者監督者データベース13と工程データベース14に対して検索と更新を行い、通信手段11が受信した電子メールからデータを取得し送信の指示を行い、工事進捗一覧表16と、工程チャート17と、施工項目別全体工程表18と、全体工程表19のデータを更新し、出力する手段である。   The process management calculation unit 12 searches and updates the installer supervisor database 13 and the process database 14, acquires data from the email received by the communication unit 11, instructs transmission, and the construction progress list 16 And means for updating and outputting the data of the process chart 17, the construction process-specific overall process chart 18, and the overall process chart 19.

以上が工程管理サーバー5の構成であるが、次に上記工程管理サーバー5の各構成の処理について以下に説明する。   The above is the configuration of the process management server 5. Next, processing of each component of the process management server 5 will be described below.

図3は、工程管理サーバー5における処理の流れを示している。   FIG. 3 shows the flow of processing in the process management server 5.

本発明による施工管理システムの施工管理が開始すると(ステップ100)、工程管理計算手段12が工程データベース14から各施工場所の最初の施工項目を検索する。   When the construction management of the construction management system according to the present invention is started (step 100), the process management calculation means 12 searches the process database 14 for the first construction item of each construction place.

続いて工程管理計算手段12は、施工者監督者データベース13を参照する。施工者監督者データベース13は、施工場所と施工項目が確定できれば対応する施工者アドレスや監督者アドレスを検索することができるので、工程管理計算手段12は、前記工程データベース14から検索した施工場所と最初の施工項目のデータを用いて施工者監督者データベース13から各施工場所の最初の施工項目を施工する施工者のアドレス(施工者アドレス)を取得する。   Subsequently, the process management calculation means 12 refers to the installer supervisor database 13. If the construction supervisor database 13 can determine the construction place and construction items, the construction manager address and supervisor address can be searched. Therefore, the process management calculation means 12 can search the construction place searched from the process database 14. Using the data of the first construction item, the address (constructor address) of the installer who constructs the first construction item at each construction location is acquired from the installer supervisor database 13.

次に、工程管理計算手段12は、前記施工者監督者データベース13から検索した施工者アドレスに対し、通信手段11に命令して施工場所と施工開始の指示を含む施工開始用電子メールを送信させる。   Next, the process management calculation means 12 instructs the communication means 11 to send a construction start e-mail including a construction place and a construction start instruction to the construction worker address retrieved from the construction supervisor database 13. .

上記施工開始用電子メールを送信すると、工程管理計算手段12はその送信時間を工程管理の基準的な時間となる施工開始基準時としてメモリ15に記憶させる(以上、ステップ110)。   When the construction start e-mail is transmitted, the process management calculation means 12 stores the transmission time in the memory 15 as the construction start reference time which is a standard time for process management (step 110).

上記施工開始用電子メールを受けた施工者は、指示にしたがって工事を開始し、工事が完了した時点で、施工開始用電子メールに返信メールを送信する。返信メールに施工者は新たに入力する必要がない。   The contractor who has received the construction start e-mail starts construction according to the instruction, and transmits a reply mail to the construction start e-mail when the construction is completed. The installer does not need to input a new reply email.

この返信メールは、施工済電子メールとして工程管理サーバー5の通信手段11によって受信される(ステップ120)。   This reply mail is received by the communication means 11 of the process management server 5 as a construction completed email (step 120).

施工開始用電子メールには施工場所のデータが含まれており、その返信メールである施工済電子メールには施工場所の情報が引き継がれる。したがって、施工済電子メールには、施工場所の情報と送信者である施工者(正確には施工者アドレス)の情報が含まれている。   The construction start e-mail includes construction site data, and the construction e-mail, which is a reply mail, carries the construction site information. Therefore, the construction-completed e-mail includes information on the construction place and information on the construction person who is the sender (more precisely, the construction person address).

なお、移動通信機器2として携帯電話を使用する場合は、電子メールのタイトル部に施工場所を含ませることによって、それ以降の返信メールに施工場所の情報が自動的に引き継がれる。   When a mobile phone is used as the mobile communication device 2, the construction location information is automatically taken over in subsequent reply mails by including the construction location in the title part of the e-mail.

通信手段11が施工済電子メールを受信すると、工程管理計算手段12は通信手段11の該施工済電子メールから施工者アドレスと施工場所のデータを取得し、これらの施工者アドレスと施工場所のデータを用いて施工者監督者データベース13を検索する。   When the communication means 11 receives the construction-completed e-mail, the process management calculation means 12 obtains the data of the installer address and the construction place from the construction-completed e-mail of the communication means 11, and the data of the installer address and the construction place. Is used to search the installer supervisor database 13.

施工者監督者データベース13は施工者アドレスと施工場所が特定できれば対応する施工項目と監督者アドレスが特定されるので、工程管理計算手段12は施工者監督者データベース13から該施工場所の施工項目の監督者アドレスを検索することができる。   If the installer supervisor database 13 can specify the installer address and the construction location, the corresponding construction item and supervisor address are specified. Therefore, the process management calculation unit 12 stores the construction item of the construction location from the installer supervisor database 13. The supervisor address can be searched.

監督者アドレスを検索すると、工程管理計算手段12は、通信手段11に命令して該監督者アドレスに、施工場所と施工項目と施工検査の指示を含む検査指示電子メールを送信させる(ステップ130)。   When the supervisor address is retrieved, the process management calculation means 12 instructs the communication means 11 to send an inspection instruction email including the construction location, construction item, and construction inspection instruction to the supervisor address (step 130). .

上記検査指示電子メールを受信した監督者は、該施工場所の施工項目について現場に赴いて検査を行う。   The supervisor who has received the inspection instruction e-mail goes to the site and inspects the construction items at the construction site.

検査完了後、監督者は検査が合格か不合格かの情報のみを入力して検査指示電子メールに対して返信メールを送信する。前記検査指示電子メールの返信メールは、工程管理サーバー5の通信手段11によって検査済電子メールとして受信される(ステップ140)。   After the inspection is completed, the supervisor inputs only information indicating whether the inspection is acceptable or not and sends a reply mail to the inspection instruction e-mail. The reply mail of the inspection instruction electronic mail is received as an inspected electronic mail by the communication means 11 of the process management server 5 (step 140).

検査済電子メールは、検査指示電子メールの施工場所、施工項目の情報を引き継ぎ、さらに送信時間と検査合否の情報を含む。   The inspected e-mail takes over the construction location and construction item information of the inspection instruction e-mail, and further includes information on transmission time and inspection pass / fail.

工程管理計算手段12は通信手段11から前記検査済電子メールの検査合否データを取得し、合否の判断を行う(ステップ150)。   The process management calculation means 12 acquires the inspection pass / fail data of the inspected e-mail from the communication means 11 and makes a pass / fail judgment (step 150).

検査済電子メールの検査合否データが不合格を示すデータである場合は、工程管理計算手段12は、検査済電子メールから施工場所と施工項目のデータを取得し、該施工場所と施工項目のデータを用いて、施工者監督者データベース13から担当の施工者のアドレスを検索し、通信手段11に命令して、施工項目と再施工の指示を含む再施工指示電子メールを前記検索した施工者アドレスに送信させる(ステップ160)。   When the inspection pass / fail data of the inspected e-mail is data indicating failure, the process management calculation means 12 acquires the data of the construction place and the construction item from the inspected e-mail, and the data of the construction place and the construction item. Is used to retrieve the address of the contractor in charge from the contractor supervisor database 13 and instruct the communication means 11 to retrieve the reconstructing instruction e-mail including the construction item and the reconstructing instruction. (Step 160).

この場合には、監督者の検査が合格するまで、上記ステップ120〜150の処理を繰り返す。   In this case, the processing of steps 120 to 150 is repeated until the supervisor's inspection passes.

一方、検査済電子メールの検査合否データが合格を示すデータである場合は、その施工場所と施工項目のデータを用いて工程データベース14から進捗データが「施工中」の施工項目データを検索し、工程データベース14の施工項目データの進捗データを「完了」に更新するとともに前記完了に更新した施工項目データの次の施工項目データの進捗データを「施工中」に更新する(ステップ170)。図2の工程データベース14の例では、たとえば施工中を示す“0”を、施工完了を示す“1”に更新し、新たに施工を開始した施工項目の進捗データを施工中の“0”に更新する。   On the other hand, if the inspection pass / fail data of the inspected e-mail is data indicating acceptance, the construction item data whose progress data is “under construction” is searched from the process database 14 using the construction place and construction item data. The progress data of the construction item data in the process database 14 is updated to “complete”, and the progress data of the construction item data next to the construction item data updated to the completion is updated to “under construction” (step 170). In the example of the process database 14 in FIG. 2, for example, “0” indicating that construction is in progress is updated to “1” that indicates completion of construction, and the progress data of the construction item that has newly started construction is changed to “0” that is being constructed. Update.

工程データベース14の進捗データの更新を行ったのちに、工程管理計算手段12は、工事進捗一覧表16、工程チャート17、施工項目別全体工程表18、全体工程表19の更新を行う。   After updating the progress data in the process database 14, the process management calculation means 12 updates the construction progress list 16, the process chart 17, the construction process-specific overall process chart 18, and the overall process chart 19.

最初に工事進捗一覧表16の更新について説明する。   First, the update of the construction progress list 16 will be described.

工事進捗一覧表16上の各施工場所は工程データベース14のデータ項目の“施工場所”に対応している。工事進捗一覧表16上の各施工場所のグラフを構成する各施工項目は、工程データベース14のデータ項目“施工場所”に記載された“施工項目”に対応している。各施工項目が完了したか否かは各施工項目の進捗データに対応している。   Each construction location on the construction progress list 16 corresponds to a “construction location” data item in the process database 14. Each construction item constituting the graph of each construction place on the construction progress list 16 corresponds to “construction item” described in the data item “construction place” of the process database 14. Whether each construction item is completed corresponds to the progress data of each construction item.

工程管理計算手段12は、工程データベース14のデータを更新した後は、工程データベース14のデータに合致するように、工事進捗一覧表16を表示させるためのデータを更新する(ステップ180)。工程管理計算手段12は、更新したデータのみについて工事進捗一覧表16のデータを更新してもよいし、工程データベース14の全データを工事進捗一覧表16に新たに反映させてもよい。   After updating the data in the process database 14, the process management calculation means 12 updates the data for displaying the construction progress list 16 so as to match the data in the process database 14 (step 180). The process management calculation unit 12 may update the data in the construction progress list 16 only for the updated data, or may newly reflect all the data in the process database 14 in the construction progress list 16.

次に工程チャート17の更新について説明する。   Next, the update of the process chart 17 will be described.

工程チャート17は、施工場所ごとに一つ作成され、施工項目の軸には各施工場所の施工項目が配置されている。施工項目の軸の上に配置される施工項目は工程データベース14の対応する施工場所の施工項目と一致している。   One process chart 17 is created for each construction site, and the construction item of each construction site is arranged on the axis of the construction item. The construction item arranged on the construction item axis coincides with the construction item of the corresponding construction place in the process database 14.

工程チャート17の時間軸は施工開始基準時を基点とし、施工開始基準時からの時間経過に応じて基点からの距離が増大するように構成されている。   The time axis of the process chart 17 has a construction start reference time as a base point, and is configured such that the distance from the base point increases with the passage of time from the construction start reference time.

工程チャート17上には、施工項目が時間との関係で、棒グラフのように表されている。工程データベース14の所定の施工場所の所定の施工項目の進捗データが「施工中」から「完了」に更新されると、その更新した時間すなわち検査済電子メールの送信時間が当該施工項目の施工完了の時間となり、工程チャート17上に当該施工項目の棒グラフを表示することができる。   On the process chart 17, the construction items are represented as bar graphs in relation to time. When the progress data of a predetermined construction item at a predetermined construction location in the process database 14 is updated from “under construction” to “completed”, the updated time, that is, the transmission time of the inspected email is completed. The bar graph of the construction item can be displayed on the process chart 17.

工程データベース14が更新されると、工程管理計算手段12は、検査済電子メールから送信時間のデータを取得し(ステップ190)、施工開始基準時との差を求めて棒グラフの終点を決定し、施工項目の軸上の対応する施工項目に整合する位置に上記棒グラフを表示するように工程チャート17のデータを更新する(ステップ200)。これにより、工程チャート17には、新たに施工が完了した施工項目が棒グラフとして表示される。   When the process database 14 is updated, the process management calculation means 12 obtains the transmission time data from the inspected e-mail (step 190), determines the difference from the construction start reference time, determines the end point of the bar graph, The data of the process chart 17 is updated so that the bar graph is displayed at a position matching the corresponding construction item on the construction item axis (step 200). Thereby, on the process chart 17, the construction item for which construction has been newly completed is displayed as a bar graph.

なお、工程チャート17は、施工が完了した施工項目のみを表示するようにしてもよいが、好ましくは、当初予定していた施工スケジュールを表示し、実際に完了した施工項目の棒グラフを識別可能に表示するようにする。   In addition, although the process chart 17 may be configured to display only the construction items for which the construction has been completed, it is preferable to display the construction schedule that was originally planned so that the bar graph of the construction items that are actually completed can be identified. Display it.

工事進捗一覧表16は全工事現場の進捗を一覧的に示しており、工程チャート17は各施工場所の進捗を示しているので、互いに全体と詳細の関係にある。   Since the construction progress list 16 shows the progress of all construction sites in a list, and the process chart 17 shows the progress of each construction site, they are in a relationship of the whole and details.

このため、工程管理計算手段12は、工事進捗一覧表16上の所定の施工場所をコンピューターの画面上でクリックすると、その施工場所の工程チャート17が表示させるのが好ましい。工事進捗一覧表16上の所定の施工場所をクリックするとその施工場所の工程チャート17が表示されるようにするのは通常のリンクの技術を使用することによって実現することができる。   For this reason, when the process management calculation means 12 clicks the predetermined construction place on the construction progress list 16 on the screen of the computer, it is preferable to display the process chart 17 of the construction place. When a predetermined construction place on the construction progress list 16 is clicked, the process chart 17 of the construction place can be displayed by using a normal link technique.

次に施工項目別全体工程表18と全体工程表19の更新について説明する。   Next, the update of the entire process table 18 and the entire process table 19 by construction item will be described.

更新された工程データベース14には各施工場所の各施工項目の進捗データが記載されている。特定の施工項目について集計すれば、該施工項目の全工事量のうち何パーセントが完了したかが計算することができる。   The updated process database 14 describes the progress data of each construction item at each construction place. If a specific construction item is tabulated, it can be calculated what percentage of the total construction amount of the construction item is completed.

施工項目別全体工程表18は、図2の例では横軸に施工完了のパーセントが示され、縦軸に各施工項目が配置されている。   In the overall process table 18 by construction item, the percentage of completion of construction is shown on the horizontal axis in the example of FIG. 2, and each construction item is arranged on the vertical axis.

工程データベース14の進捗データが更新されたときは、工程管理計算手段12は、工程データベース14から施工項目ごとに各施工場所の当該施工項目を検索し、検索した施工項目の進捗データについて集計し、全工事現場における各施工項目の完了率を計算し、施工項目別全体工程表18に表示するように施工項目別全体工程表18のデータを更新する(210)。   When the progress data in the process database 14 is updated, the process management calculation means 12 searches the process database 14 for the construction item for each construction item for each construction item, totals the progress data of the searched construction item, The completion rate of each construction item in all construction sites is calculated, and the data of the construction item-specific overall process table 18 is updated so as to be displayed in the construction item-specific overall process table 18 (210).

次に全体工程表19の更新について説明する。   Next, the update of the entire process table 19 will be described.

全体工程表19は、全工事量の完了率を時間経過とともにグラフに示したものである。   The overall process table 19 is a graph showing the completion rate of the total construction amount with time.

図2の例では、全体工程表19は、時間軸を横軸に、完了率(%)を縦軸に有している。   In the example of FIG. 2, the overall process table 19 has a time axis on the horizontal axis and a completion rate (%) on the vertical axis.

工程データベース14が更新されたときは、工程管理計算手段12は、最初に全工事現場の施工項目別の完了率を算出し、さらに各施工項目の完了率に各施工項目の全工事に対するウェイトを乗じて合計して全体工程完了率を算出する。   When the process database 14 is updated, the process management calculation means 12 first calculates a completion rate for each construction item at all construction sites, and further adds a weight for each construction item to the completion rate for each construction item. Multiply and total to calculate the overall process completion rate.

たとえば、「床工事」の全工事量に対するウェイトが10%とし、全工事現場の床工事のうち80%が完了したとすると、全工程に対する床工事の完了分の寄与は10%*80%となり、0.08となる。   For example, if the weight of the total floor work is 10%, and 80% of the floor work at all construction sites is completed, the contribution of the floor work to all processes will be 10% * 80%. 0.08.

全工程の完了分は全工事項目について上記計算を行い合計したものである。   Completion of all processes is the sum of the above calculations for all construction items.

工程管理計算手段12は、工程データベース14が更新されたときは、上記全工程に対する完了率の計算を行い、検査済電子メールから送信時間のデータを取得し(ステップ220)、全体工程表19上の時間軸の対応する位置と、縦軸の完了率軸の対応する位置の交点に点を表示し、グラフを形成するように、全体工程表19のデータを更新する(ステップ230)。   When the process database 14 is updated, the process management calculation means 12 calculates the completion rate for all the processes, acquires the transmission time data from the inspected e-mail (step 220), and on the entire process table 19 A point is displayed at the intersection of the corresponding position on the time axis and the corresponding position on the completion rate axis on the vertical axis, and the data of the entire process table 19 is updated so as to form a graph (step 230).

工程管理計算手段12は、上記更新した工事進捗一覧表16、工程チャート17、施工項目別全体工程表18、全体工程表19を工程管理サーバー5近傍の表示装置に出力し、あるいは、インターネット4を介して工程管理用コンピューター7に出力する。   The process management calculation means 12 outputs the updated construction progress list 16, process chart 17, construction item-specific overall process chart 18, and overall process chart 19 to a display device near the process management server 5, or uses the Internet 4. To the process management computer 7.

続いて以下のようにして、工程管理計算手段12は、次の施工項目を施工する施工者に施工指示電子メールを送信する。   Subsequently, the process management calculation means 12 transmits a construction instruction e-mail to the builder who constructs the next construction item as follows.

工程データベース14の各施工場所には施工項目が施工の順番に従って記憶されている。工程管理計算手段12は、所定の施工項目の施工が完了するとその進捗データを「施工中」から「完了」の状態に更新するとともに、その次の施工項目の進捗データを新たに「施工中」に更新する。   At each construction location in the process database 14, construction items are stored according to the order of construction. When the construction of the predetermined construction item is completed, the process management calculation means 12 updates the progress data from “under construction” to “completed”, and newly updates the progress data of the next construction item as “under construction”. Update to

工事進捗一覧表16、工程チャート17、施工項目別全体工程表18、全体工程表19を更新した後に、工程管理計算手段12は、工程データベース14から進捗データが「施工中」の施工項目データを検索し(ステップ240)、その施工場所と施工項目のデータを用いて施工者監督者データベース13から施工者アドレスを検索し(ステップ250)、通信手段11に命令して施工場所と施工開始の指示とを含む施工指示電子メールを前記施工者アドレスに送信させる(ステップ260)。このとき、工程管理計算手段12は、前記施工指示電子メールの送信時間をその施工項目の施工開始時間として記憶する。この施工開始時間は工程チャート17の当該施工項目の棒グラフの始点となる。   After updating the construction progress list 16, the process chart 17, the overall process chart 18 by construction item, and the overall process chart 19, the process management calculation means 12 reads the construction item data whose progress data is “under construction” from the process database 14. Search (step 240), search the installer address from the installer supervisor database 13 using the data of the construction location and construction item (step 250), and instruct the communication means 11 to instruct the construction location and construction start A construction instruction e-mail including the above is transmitted to the installer address (step 260). At this time, the process management calculation means 12 stores the transmission time of the construction instruction email as the construction start time of the construction item. This construction start time is the starting point of the bar graph of the construction item in the process chart 17.

それ以降、処理がステップ120に戻り、上記ステップ120〜260の処理を繰り返す。   Thereafter, the process returns to step 120, and the processes of steps 120 to 260 are repeated.

この工程管理システム1によれば、いったん工程管理が開始されると、施工場所、施工項目、施工者、監督者、工事の完了率等のデータを全く入力する必要がなく、単純な返信メールを送るのみで、最新の工事の進捗状況が常に工程管理サーバー5に情報収集され、工事の管理者に出力される。   According to this process management system 1, once process management is started, it is not necessary to input data such as construction location, construction item, installer, supervisor, completion rate of construction at all, and a simple reply mail is sent. By simply sending the information, the progress status of the latest construction is always collected in the process management server 5 and output to the construction manager.

また、本工程管理システム1によれば、一つの工事項目の施工が完了すると、工程管理サーバー5によって直ちに次に行う作業を行うべき者に作業が指示される。   Further, according to the process management system 1, when the construction of one construction item is completed, the process management server 5 instructs the person who should perform the next work immediately.

これにより、従来、連絡が遅れのために一つの作業と次の作業の間に生じていた無駄な時間を一掃することができ、効率のよい工事を行うことができる。   As a result, wasteful time that has conventionally occurred between one operation and the next operation due to a delay in communication can be eliminated, and efficient construction can be performed.

次に、同時並行的に複数の施工項目が進行する場合に適用できる工程管理システムについて説明する。   Next, a process management system that can be applied when a plurality of construction items progress simultaneously in parallel will be described.

図4は、上記複数の施工項目が並行的に進行する場合の工程管理システムの工程データベース20と工程チャート21を示している。   FIG. 4 shows a process database 20 and a process chart 21 of the process management system when the plurality of construction items proceed in parallel.

工程データベース20は、施工場所ごとの施工項目と進捗データの他に、各施工項目の施工順序のデータを有している。   The process database 20 has construction order data for each construction item in addition to construction items and progress data for each construction site.

工程チャート21は、一つの施工項目Aから施工項目Bと施工項目Cが分岐し、それ以降、施工項目Bは施工項目D,E・・・と続き、施工項目Cは施工項目F,G・・・と続く工程チャートを示している。   In the process chart 21, the construction item B and the construction item C branch from one construction item A, and thereafter, the construction item B continues with the construction items D, E...・ ・ The following process chart is shown.

施工順序のデータは、図4に一例を示しているように、一つの施工項目から複数の施工項目が分岐する場合に、一つの施工項目が完了したときに、その次の施工項目を特定することができるものである。   As shown in the example in FIG. 4, the construction order data specifies the next construction item when one construction item is completed when a plurality of construction items branch from one construction item. It is something that can be done.

図4の例では、以下の施工順序データを有している。

施工項目 施工順序データ
A 1
B 1−1
C 1−2
D 1−1−1
E 1−1−1−1
F 1−2−1
G 1−2−1−1
In the example of FIG. 4, it has the following construction order data.

Construction item Construction sequence data A 1
B 1-1
C 1-2
D 1-1-1
E 1-1-1-1
F 1-2-1
G 1-2-1-1

この場合に、一つの施工項目が完了すると、その施工項目の施工順序データを参照し、その施工順序データを継承する施工順序データを有する施工項目を、次の施工項目として特定する。   In this case, when one construction item is completed, the construction order data of the construction item is referred to, and the construction item having construction order data that inherits the construction order data is specified as the next construction item.

たとえば、施工項目Cが完了したときは、その施工順序データ“1−2”を継承する施工順序データ“1−2−1”を有する施工項目Fをその次の施工項目として特定する。   For example, when the construction item C is completed, the construction item F having the construction order data “1-2-1” that inherits the construction order data “1-2” is specified as the next construction item.

またたとえば、施工項目Aが完了すると、その施工順序データ“1”を継承する施工順序データ“1−1”と“1−2”の双方に次の施工を指示する。その場合に、施工順序データ“1−1”と“1−2”の優先順位のデータあるいはタイムラグのデータ(どの程度ずらして施工を開始するかのデータ)を付加するようにしてもよい。   Further, for example, when the construction item A is completed, the next construction is instructed to both the construction order data “1-1” and “1-2” inheriting the construction order data “1”. In that case, construction order data “1-1” and priority data of “1-2” or time lag data (how much the data is shifted to start construction) may be added.

それ以外の処理は、図3の処理とほぼ同様であるので、重複する説明を省略する。   The other processes are almost the same as the processes in FIG.

ただし、上記例では施工項目と施工順次データを別々のデータ項目としたが、施工項目の識別情報の中に施工順序データを含ませるようにした場合も本発明の範囲内である。   However, in the above example, the construction item and the construction sequential data are separate data items, but it is within the scope of the present invention to include construction order data in the construction item identification information.

また、上記例では「最初」の施工項目は一つとしたが、最初の施工項目が複数である場合もそのまま本発明に含まれる。   In the above example, the number of the first construction item is one, but a plurality of first construction items are also included in the present invention as they are.

また、上記例では施工項目が施工の種別を表していたが、施工項目には個別の識別情報を与え、別個に施工の種別のテータを記憶するようにしてもよい。   In the above example, the construction item represents the type of construction. However, individual identification information may be given to the construction item and the construction type data may be stored separately.

本発明によれば、複数の工事が平行して行われる場合も、それぞれの工事を特定し、それぞれの工事が完了すると、その次の工事の開始を自動的に指示することができる。また、工事進捗一覧表と工程チャートと施工項目別全体工程表と全体工程表に、同時並行に複数の工事が行われる場合の工事の進捗状況を常に最新の状態に自動的に更新し、出力するようにすることができる。   According to the present invention, even when a plurality of constructions are performed in parallel, each construction can be specified, and when each construction is completed, the start of the next construction can be automatically instructed. In addition, the construction progress list, process chart, and overall process chart for each construction item and the overall process chart are automatically updated to the latest status and output when multiple works are performed simultaneously. To be able to.

本発明の一実施形態による工程管理システムの構成図。The block diagram of the process management system by one Embodiment of this invention. 本発明の一実施形態による工程管理サーバーの構成図。The block diagram of the process management server by one Embodiment of this invention. 本発明の一実施形態による工程管理サーバーにおける処理のフローチャート。The flowchart of the process in the process management server by one Embodiment of this invention. 同時並行的に複数の工事が進行する場合の工程データベースと工程チャートの例を示した図。The figure which showed the example of the process database and process chart when several construction work progresses simultaneously.

符号の説明Explanation of symbols

1 工程管理システム
2 移動通信機器
3 移動通信網
4 インターネット
5 工程管理サーバー
6 移動通信機器中継局
7 工程管理用コンピューター
11 通信手段
12 工程管理計算手段
13 施工者監督者データベース
14 工程データベース
15 メモリ
16 工事進捗一覧表
17 工程チャート
18 施工項目別全体工程表
19 全体工程表
20 工程データベース
21 工程チャート
DESCRIPTION OF SYMBOLS 1 Process management system 2 Mobile communication equipment 3 Mobile communication network 4 Internet 5 Process management server 6 Mobile communication equipment relay station 7 Process management computer 11 Communication means 12 Process management calculation means 13 Contractor supervisor database 14 Process database 15 Memory 16 Construction Progress Table 17 Process Chart 18 Overall Process Table 19 by Construction Item Overall Process Table 20 Process Database 21 Process Chart

Claims (6)

移動通信機器と必要に応じて設けられる工程管理用コンピューターとデータ通信するための通信手段と、少なくとも施工者アドレスと施工場所と施工項目と監督者アドレスをデータ項目に含みそれらデータ項目のデータを対応可能に記憶する施工者監督者データベースと、施工場所と前記施工場所の施工項目と各施工項目の進捗のデータとを記憶する工程データベースと、前記施工者監督者データベースと前記工程データベースに対して検索と更新を行い、前記通信手段から受信した電子メールからデータを取得し送信の指示を行い、全施工場所の施工項目を施工場所ごとにグラフに示した工事進捗一覧表と各施工場所の施工項目の軸と時間軸を有し各施工項目を時間の棒グラフに表した工程チャートとをリンク可能に表示させるデータを算出する工程管理計算手段と、前記工事進捗一覧表と前記工程チャートと施工開始基準時のデータを記憶するメモリと、を有する工程管理サーバーを有し、
前記工程管理サーバーは、前記工程管理計算手段が前記工程データベースから各施工場所の最初の施工項目のデータを取得し、前記施工場所と施工項目のデータを用いて前記施工者管理者データベースから各施工場所の最初の施工者アドレスを検索して前記通信手段に命令して前記施工者アドレスに施工場所と施工開始の指示を含む施工開始用電子メールを送信させ、送信時間を施工開始基準時として前記メモリに記憶させ、
前記通信手段が、施工者の移動通信機器から、送信時間と施工場所のデータを含む施工済電子メールを受信すると、前記工程管理計算手段が、前記施工者の電子メールから送信者である施工者アドレスと施工場所のデータとを入力し前記施工者アドレスと施工場所のデータを用いて前記施工者監督者データベースから当該施工場所の施工項目の監督者アドレスを検索し、前記通信手段に命令して前記施工場所と前記施工項目と施工検査の指示を含む検査指示電子メールを前記監督者アドレスに送信させ、
前記通信手段が、監督者の移動通信機器から、送信時間と検査合否データと施工場所と施工項目のデータとを含む検査済電子メールを受信すると、前記工程管理計算手段が、前記検査済電子メールから前記検査合否データを取得し、前記検査合否データが不合格を示すデータである場合は、前記検査済電子メールから施工場所と施工項目のデータを取得し、前記施工場所と施工項目のデータを用いて前記施工者監督者データベースから施工者アドレスを検索し、前記通信手段に命令して前記施工場所の前記施工項目の再施工の指示を含む再施工指示電子メールを前記検索した施工者アドレスに送信させ、
前記検査合否データが合格である場合は、前記検査済電子メールから施工場所と施工項目のデータを取得し、前記施工場所と施工項目のデータを用いて前記工程データベースから進捗データが施工中の施工項目データを検索し、前記施工項目データの進捗データを完了に更新するとともに前記完了に更新した施工項目データの次の施工項目データの進捗データを施工中に更新し、前記工事進捗一覧表上の前記施工場所のグラフについて更新された施工項目の進捗データに応じてグラフを表示できるように工事進捗一覧表のデータを更新し、前記検査済電子メールから送信時間を取得し、前記施工開始基準との差を求めて前記施工場所の工程チャートの時間軸上の点と前記施工場所の施工項目の軸上の前記進捗データを完了に更新した施工項目とを特定し、当該施工項目の施工開始から施工完了まで時間を棒グラフとして表示する工程チャートのデータを更新し、前記工程データベースの前記施工場所の施工項目から進捗データが施工中の施工項目データを検索し、前記施工場所と施工項目のデータを用いて前記施工者監督者データベースから施工者アドレスを検索し、前記通信手段に命令して施工場所と施工開始の指示とを含む施工指示電子メールを前記施工者アドレスに送信させ、前記送信時間を前記進捗データが施工中の施工項目の施工開始時間として記憶する、ことを特徴とする移動通信機器を用いた施工管理システム。
Communication means for data communication with a mobile communication device and a process management computer provided as necessary, and at least the installer address, construction location, construction item, and supervisor address are included in the data item, and the data of the data item is supported Retrieving the construction manager supervisor database, the construction database, the construction database of the construction site, and the progress data of each construction item, the construction supervisor supervisor database, and the process database. Update data, obtain data from the e-mail received from the communication means, instruct the transmission, and display the work progress list for each work place and the work items for each work place. Calculate the data that can be linked to the process chart that has the axis and the time axis and represents each construction item in a bar graph of time. Has to a process control computing means, a memory for storing data during said construction progress schedule the process chart and construction starting reference, the process control server having,
In the process management server, the process management calculation means obtains data of the first construction item of each construction place from the process database, and uses the construction place and construction item data to perform each construction from the installer manager database. Search for the first builder address of the place and instruct the communication means to send a construction start e-mail including a construction place and a construction start instruction to the builder address, with the transmission time as the construction start reference time Memorize it in memory,
When the communication means receives a construction-completed email including transmission time and construction location data from the contractor's mobile communication device, the process management calculation means is a contractor who is a sender from the constructor's email. Enter the address and construction location data, search the supervisor address of the construction item of the construction location from the constructor supervisor database using the construction worker address and construction location data, and instruct the communication means An inspection instruction email including the construction location, the construction item, and a construction inspection instruction is transmitted to the supervisor address,
When the communication means receives an inspected e-mail including a transmission time, inspection pass / fail data, construction location, and construction item data from the supervisor's mobile communication device, the process management calculation means, the inspection management e-mail If the inspection acceptance / rejection data is data indicating failure, the construction location and construction item data are obtained from the inspected email, and the construction location and construction item data are obtained. Use the installer's supervisor database to search for the installer's address, and instruct the communication means to send the re-installation instruction e-mail including the instructions for re-installation of the construction item at the construction location to the searched installer's address. Send
If the inspection pass / fail data is acceptable, the construction location and construction item data are acquired from the inspected email, and the progress data from the process database is being constructed using the construction location and construction item data. Search the item data, update the progress data of the construction item data to completion, and update the progress data of the construction item data next to the construction item data updated to completion during construction, on the construction progress list Update the construction progress table data so that the graph can be displayed according to the progress data of the construction items updated for the construction place graph, obtain the transmission time from the inspected email, and the construction start standard and The construction item which updated the progress data on the point of the construction item of the construction place and the point on the time axis of the construction place of the construction place to find the difference Update the process chart data that displays the time from the start of construction of the construction item to the completion of construction as a bar graph, and search the construction item data for which the progress data is under construction from the construction item at the construction location in the process database Then, using the construction location and construction item data, retrieve the construction worker address from the construction supervisor database, and instruct the communication means to send the construction instruction email including the construction location and construction start instruction. A construction management system using a mobile communication device, characterized in that a transmission is made to a contractor address, and the transmission time is stored as a construction start time of a construction item whose construction data is being constructed.
前記施工管理計算手段はさらに、前記検査合否データが合格を示すデータであって、前記工程データベースの進捗データが施工中の施工項目データを進捗データが完了に更新したときは、前記工程データベースから施工項目データの種別ごとに進捗データが完了の施工データ項目と進捗データが施工中あるいは未だ施工中にも完了にもなっていない施工データ項目を検索して集計し、施工項目の種別ごとの完了率をグラフに表示する施工項目別全体工程表のデータを更新することを特徴とする請求項1に記載の移動通信機器を用いた施工管理システム。   The construction management calculation means further includes data indicating that the inspection pass / fail data is acceptable, and when the progress data of the process database updates the construction item data under construction to the completion of the progress data, the construction database starts construction from the process database. Search and aggregate construction data items whose progress data is completed for each item data type and construction data items whose progress data is under construction or not yet completed during construction, and the completion rate for each type of construction item The construction management system using the mobile communication device according to claim 1, wherein the data of the entire process chart for each construction item for displaying the chart on the graph is updated. 前記施工管理計算手段はさらに、前記検査合否データが合格を示すデータであって、前記工程データベースの進捗データが施工中の施工項目データを進捗データが完了に更新したときは、前記工程データベースから施工項目データの種別ごとに進捗データが完了の施工データ項目と進捗データが施工中あるいは未だ施工中にも完了にもなっていない施工データ項目を検索して集計し、施工項目の種別ごとの完了率を計算し、さらに各施工項目の完了率に各施工項目の全工事に対するウェイトを乗じて合計して全体工程完了率を算出し、前記検査済電子メールの送信時間から取得した時間と前記算出した全体工程完了率により、時間軸と全体工程の完了率の軸を有し時間経過に伴う全体工程の完了率の変化をグラフに表示する全体工程表のデータを更新することを特徴とする請求項1に記載の移動通信機器を用いた施工管理システム。   The construction management calculation means further includes data indicating that the inspection pass / fail data is acceptable, and when the progress data of the process database updates the construction item data under construction to the completion of the progress data, the construction database starts construction from the process database. Search and aggregate construction data items whose progress data is completed for each item data type and construction data items whose progress data is under construction or not yet completed during construction, and the completion rate for each type of construction item Calculate the overall process completion rate by multiplying the completion rate of each construction item by the weight for all construction items, and calculate the overall process completion rate, and the time obtained from the transmission time of the inspected email and the calculated The data of the overall process table that displays the change in the completion rate of the overall process over time, with a time axis and the axis of the completion rate of the overall process. Construction management system using the mobile communication system as set forth in claim 1, characterized in that updating. 移動通信機器と必要に応じて設けられる工程管理用コンピューターとデータ通信するための通信手段と、少なくとも施工者アドレスと施工場所と施工項目と監督者アドレスをデータ項目に含みそれらデータ項目のデータを対応可能に記憶する施工者監督者データベースと、施工場所と前記施工場所の施工項目と施工順序データと各施工項目の進捗のデータとを記憶する工程データベースと、前記施工者監督者データベースと前記工程データベースに対して検索を行い、前記通信手段から受信した電子メールからデータを取得し送信の指示を行い、全施工場所の施工項目を施工場所ごとにグラフに示した工事進捗一覧表と各施工場所の施工項目の軸と時間軸を有し各施工項目を時間の棒グラフに表した工程チャートとをリンク可能に表示させるデータを算出する工程管理計算手段と、前記工事進捗一覧表と前記工程チャートと施工開始基準時のデータを記憶するメモリと、を有する工程管理サーバーを有し、
前記工程管理サーバーは、前記工程管理計算手段が前記工程データベースから各施工場所の最初の施工項目のデータを取得し、前記施工場所と施工項目のデータを用いて前記施工者管理者データベースから各施工場所の最初の施工者アドレスを検索して前記通信手段に命令して前記施工者アドレスに施工場所と施工項目と施工開始の指示を含む施工開始用電子メールを送信させ、送信時間を施工開始基準時として前記メモリに記憶させ、
前記通信手段が、施工者の移動通信機器から、送信時間と施工場所と施工項目のデータを含む施工済電子メールを受信すると、前記工程管理計算手段が、前記施工者の電子メールから送信者である施工者アドレスと施工場所と施工項目のデータとを入力し前記施工者アドレスと施工場所と施工項目のデータを用いて前記施工者監督者データベースから当該施工項目の監督者アドレスを検索し、前記通信手段に命令して前記施工場所と前記施工項目と施工検査の指示を含む検査指示電子メールを前記監督者アドレスに送信させ、
前記通信手段が、監督者の移動通信機器から、送信時間と検査合否データと施工場所と施工項目のデータとを含む検査済電子メールを受信すると、前記工程管理計算手段が、前記検査済電子メールから前記検査合否データを取得し、前記検査合否データが不合格を示すデータである場合は、前記検査済電子メールから施工場所と施工項目のデータを取得し、前記施工場所と施工項目のデータを用いて前記施工者監督者データベースから施工者アドレスを検索し、前記通信手段に命令して前記施工場所の前記施工項目の再施工の指示を含む再施工指示電子メールを前記検索した施工者アドレスに送信させ、
前記検査合否データが合格である場合は、前記検査済電子メールから施工場所と施工項目のデータを取得し、前記工事進捗一覧表上の前記施工場所のグラフについて新たに完了した施工項目に応じてグラフを表示できるように工事進捗一覧表のデータを更新し、前記検査済電子メールから送信時間を取得し、前記施工開始基準との差を求めて前記施工場所の工程チャートの時間軸上の点と前記施工場所の施工項目の軸上の前記新たに完了した施工項目とを特定し、当該施工項目の施工開始から施工完了まで時間を棒グラフとして表示する工程チャートのデータを更新し、前記工程データベースを参照し前記施工場所の前記新たに完了した施工項目の進捗データを完了に更新し施工順序データを参照してその次に施工すべき施工項目データを検索し、前記施工場所と次に施工すべき施工項目のデータを用いて前記施工者監督者データベースから施工者アドレスを検索し、前記通信手段に命令して施工場所と施工項目と施工開始の指示とを含む施工指示電子メールを前記施工者アドレスに送信させ、前記送信時間を前記新たに施工開始の指示をした施工項目の施工開始時間として記憶する、ことを特徴とする移動通信機器を用いた施工管理システム。
Communication means for data communication with a mobile communication device and a process management computer provided as necessary, and at least the installer address, construction location, construction item, and supervisor address are included in the data item, and the data of the data item is supported The construction supervisor database that can be stored, the construction location, the construction items of the construction location, the construction order data, and the progress data of each construction item, the construction supervisor database, and the construction database. Search for data, obtain data from the e-mail received from the communication means, instruct the transmission, and display the construction progress list showing the construction items of all construction sites for each construction site and each construction site. A work chart that has a work item axis and a time axis, and displays each work item as a bar graph of time is displayed in a linkable manner. Includes a process control calculating means for calculating the over data, a memory for storing data during construction start reference to the construction progress schedule and the step charts, process control server having,
In the process management server, the process management calculation means obtains data of the first construction item of each construction place from the process database, and uses the construction place and construction item data to perform each construction from the installer manager database. Search for the first builder address of the place, instruct the communication means to send an e-mail for construction start including the construction place, construction item and construction start instruction to the builder address, and set the transmission time as the construction start standard. Sometimes stored in the memory,
When the communication means receives a construction-completed e-mail including transmission time, construction place and construction item data from the mobile communication device of the builder, the process management calculation means is a sender from the builder's e-mail. Enter a certain installer address, construction location and construction item data, and search for the supervisor address of the construction item from the construction supervisor database using the construction worker address, construction location and construction item data. Instruct the communication means to send an inspection instruction e-mail including the construction location, the construction item, and an instruction of construction inspection to the supervisor address,
When the communication means receives an inspected e-mail including a transmission time, inspection pass / fail data, construction location, and construction item data from the supervisor's mobile communication device, the process management calculation means, the inspection management e-mail If the inspection acceptance / rejection data is data indicating failure, the construction location and construction item data are obtained from the inspected email, and the construction location and construction item data are obtained. Use the installer's supervisor database to search for the installer's address, and instruct the communication means to send the re-installation instruction e-mail including the instructions for re-installation of the construction item at the construction location to the searched installer's address. Send
If the inspection pass / fail data is acceptable, obtain the data of the construction location and construction item from the inspected email, and according to the newly completed construction item for the construction location graph on the construction progress list Update the construction progress list data so that the graph can be displayed, obtain the transmission time from the inspected e-mail, find the difference from the construction start standard, and the point on the time axis of the process chart of the construction place And the newly completed construction item on the axis of the construction item of the construction place, update the process chart data that displays the time from the construction start of the construction item to the construction completion as a bar graph, the process database The progress data of the newly completed construction item at the construction location is updated to completion, and the construction item data to be constructed next is checked by referring to the construction sequence data. Then, using the data of the construction location and the next construction item to be constructed, retrieve the construction worker address from the construction supervisor database, and instruct the communication means to construct the construction location, the construction item, and the construction start instruction. Construction using a mobile communication device, characterized in that a construction instruction e-mail containing the construction item is transmitted to the builder address, and the transmission time is stored as a construction start time of the construction item for which a new construction start instruction has been issued. Management system.
前記施工管理計算手段はさらに、前記検査合否データが合格を示すデータであって、前記工程データベースの当該施工項目の進捗データを完了に更新したときは、前記工程データベースから施工項目データの種別ごとに進捗データが完了の施工データ項目と進捗データが完了になっていない施工データ項目を検索して集計し、施工項目の種別ごとの完了率をグラフに表示する施工項目別全体工程表のデータを更新することを特徴とする請求項4に記載の移動通信機器を用いた施工管理システム。   The construction management calculation means is data indicating that the inspection pass / fail data is acceptable, and when the progress data of the construction item in the process database is updated to completion, for each type of construction item data from the process database. Search and aggregate construction data items for which progress data is complete and construction data items for which progress data is not complete, and update the data for the entire process chart for each construction item that displays the completion rate for each type of construction item in a graph A construction management system using the mobile communication device according to claim 4. 前記施工管理計算手段はさらに、前記検査合否データが合格を示すデータであって、前記工程データベースの当該施工項目の進捗データを完了に更新したときは、前記工程データベースから施工項目データの種別ごとに進捗データが完了の施工データ項目と進捗データが完了になっていない施工データ項目を検索して集計し、施工項目の種別ごとの完了率を計算し、さらに各施工項目の完了率に各施工項目の全工事に対するウェイトを乗じて合計して全体工程完了率を算出し、前記検査済電子メールの送信時間から取得した時間と前記算出した全体工程完了率により、時間軸と全体工程の完了率の軸を有し時間経過に伴う全体工程の完了率の変化をグラフに表示する全体工程表のデータを更新することを特徴とする請求項4に記載の移動通信機器を用いた施工管理システム。   The construction management calculation means is data indicating that the inspection pass / fail data is acceptable, and when the progress data of the construction item in the process database is updated to completion, for each type of construction item data from the process database. Search and aggregate construction data items for which progress data is complete and construction data items for which progress data is not complete, calculate the completion rate for each type of construction item, and then add each construction item to the completion rate for each construction item. The total process completion rate is calculated by multiplying the weights for all the constructions in the above, and the time axis and the overall process completion rate are calculated based on the time obtained from the transmission time of the inspected e-mail and the calculated overall process completion rate. 5. The mobile communication according to claim 4, wherein the data of the entire process table having an axis and displaying a change in the completion rate of the entire process with time in a graph is updated. Construction management system using the vessel.
JP2004202273A 2004-07-08 2004-07-08 Construction management system using mobile communication equipment Active JP4030986B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004202273A JP4030986B2 (en) 2004-07-08 2004-07-08 Construction management system using mobile communication equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004202273A JP4030986B2 (en) 2004-07-08 2004-07-08 Construction management system using mobile communication equipment

Publications (3)

Publication Number Publication Date
JP2006024035A true JP2006024035A (en) 2006-01-26
JP2006024035A5 JP2006024035A5 (en) 2007-10-25
JP4030986B2 JP4030986B2 (en) 2008-01-09

Family

ID=35797258

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004202273A Active JP4030986B2 (en) 2004-07-08 2004-07-08 Construction management system using mobile communication equipment

Country Status (1)

Country Link
JP (1) JP4030986B2 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010140405A (en) * 2008-12-15 2010-06-24 Nec Fielding Ltd Operation progress management system, communication apparatus, management terminal, and operation progress management method
JP2020107341A (en) * 2018-12-27 2020-07-09 株式会社クボタ Waterworks management system, notification device, waterworks management method, and program
JP2020129312A (en) * 2019-02-09 2020-08-27 株式会社長谷工コーポレーション Building performance management method and performance management system
JP2021043883A (en) * 2019-09-13 2021-03-18 株式会社コトブキ産業 Work management device, work management system and construction management program
CN112734368A (en) * 2020-12-31 2021-04-30 大为国际工程咨询有限公司 Engineering cost progress management method, system and storage medium
JP2023079536A (en) * 2021-11-29 2023-06-08 株式会社バルカー Construction management method, system, program, apparatus, and recording medium

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010140405A (en) * 2008-12-15 2010-06-24 Nec Fielding Ltd Operation progress management system, communication apparatus, management terminal, and operation progress management method
JP2020107341A (en) * 2018-12-27 2020-07-09 株式会社クボタ Waterworks management system, notification device, waterworks management method, and program
JP2020129312A (en) * 2019-02-09 2020-08-27 株式会社長谷工コーポレーション Building performance management method and performance management system
JP7221717B2 (en) 2019-02-09 2023-02-14 株式会社長谷工コーポレーション Building progress control method and progress control system
JP2021043883A (en) * 2019-09-13 2021-03-18 株式会社コトブキ産業 Work management device, work management system and construction management program
CN112734368A (en) * 2020-12-31 2021-04-30 大为国际工程咨询有限公司 Engineering cost progress management method, system and storage medium
JP2023079536A (en) * 2021-11-29 2023-06-08 株式会社バルカー Construction management method, system, program, apparatus, and recording medium
JP7411623B2 (en) 2021-11-29 2024-01-11 株式会社バルカー Construction management methods, systems, programs, devices and recording media

Also Published As

Publication number Publication date
JP4030986B2 (en) 2008-01-09

Similar Documents

Publication Publication Date Title
US10607163B2 (en) LOD work package
US8989887B2 (en) Use of prediction data in monitoring actual production targets
JP2011053999A (en) Plant construction management system and operation process management method therefor
CN113177749A (en) Resource management method and device
US20140207512A1 (en) Timeline-Based Visual Dashboard For Construction
CN109558047B (en) BIM lightweight model-based property repair method and device and terminal equipment
JP4030986B2 (en) Construction management system using mobile communication equipment
US20070282781A1 (en) Method To Retrieve Data For An Equipment, Plant Or A Process
JP2006106861A (en) Maintenance management method and maintenance management program
JP7312581B2 (en) Concrete structure management device, information processing system, concrete structure management method, and program
US10789556B2 (en) Self control
JP2000214918A (en) Plant maintenance support system
JP2002030808A (en) Electronic work control system
JP7112277B2 (en) Remote attendance system and remote attendance method
CN107317722A (en) A kind of expansible system and method for data source
JP2006024035A5 (en)
JP2003167966A (en) Periodic maintenance management system
JP4896172B2 (en) Crisis management method, crisis management system, and crisis management support server
JP7368937B2 (en) Equipment management system
JP7173226B1 (en) Learning model generation device, driving situation estimation device, learning model generation method executed by learning model generation device, estimation method executed by driving situation estimation device, program
JPH08292985A (en) Maintenance work support device
CN116523471B (en) Information generation method, apparatus, electronic device and computer readable medium
JP2005157861A (en) On-site dispatch system, method and program
JP2002149904A (en) Facility management method, facility management service system, and facility management system
JP2008117261A (en) Construction planning system and construction planning method

Legal Events

Date Code Title Description
A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070906

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070921

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20071017

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 4030986

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101026

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131026

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250