JP2023068271A - Construction method of steel shell element - Google Patents

Construction method of steel shell element Download PDF

Info

Publication number
JP2023068271A
JP2023068271A JP2021179188A JP2021179188A JP2023068271A JP 2023068271 A JP2023068271 A JP 2023068271A JP 2021179188 A JP2021179188 A JP 2021179188A JP 2021179188 A JP2021179188 A JP 2021179188A JP 2023068271 A JP2023068271 A JP 2023068271A
Authority
JP
Japan
Prior art keywords
steel shell
shell element
steel
temporary
penetrated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2021179188A
Other languages
Japanese (ja)
Inventor
均 浅野
Hitoshi Asano
孝 田中
Takashi Tanaka
宏典 田中
Hironori Tanaka
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toda Corp
Original Assignee
Toda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toda Corp filed Critical Toda Corp
Priority to JP2021179188A priority Critical patent/JP2023068271A/en
Publication of JP2023068271A publication Critical patent/JP2023068271A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

To provide a construction method with a reduced construction period and cost through labor saving of work.SOLUTION: A construction method includes steps of inserting an adjacent steel shell element 3 to a steel shell element 2 to be inserted previously in a state in which a temporary steel pipe 6 is attached on the inserted steel shell element 2 after the temporary steel pipe 6 is attached thereon to enlarge a section to the adjacent steel shell element 3 side; and pulling the temporary steel pipe 6 after installation of the steel shell element 3. Surplus soil to be reduced after insertion installation of the steel shell element 3 is allowed to be reduced, because the surplus soil remaining between side plates of the previously inserted steel shell element 2 and the post inserted steel shell element 3 is reduced only by the amount equal to an area of an enlarged section through installation of the temporary steel pipe 6.SELECTED DRAWING: Figure 5

Description

本発明は、角形中空断面の鋼殻エレメントを順次、貫入済みの鋼殻エレメントと継手部同士を連結させながら貫入する手順を繰り返して、地盤中に前記鋼殻エレメントによる閉合断面の外殻構造体を構築した後、この外殻構造体の内部土砂を除去することにより構築される外殻先行トンネルにおいて、トンネル方向に断面積が一定のトンネルを構築するための鋼殻エレメントの構築方法に関する。 According to the present invention, a steel shell element having a rectangular hollow cross section is sequentially inserted into the ground while connecting the steel shell element and the joint part that have already been penetrated, and the outer shell structure having a closed cross section by the steel shell element is repeated in the ground. This relates to a method for constructing a steel shell element for constructing a tunnel having a constant cross-sectional area in the direction of the tunnel in the outer shell precedent tunnel constructed by removing the internal earth and sand of the outer shell structure after constructing.

従来より、道路路線や鉄道路線の下方に立体交差するトンネルを構築する工法の一つとして、特殊な継手を有するとともに、1m程度に分割された角形の鋼殻エレメントを、前記継手をつなぎ合わせながら連続して土中に設置し、その鋼殻エレメント内にコンクリートを充填して、それを部材とする外殻構造体を構築し、その後に、外殻構造体の内部の土砂を掘削除去することによってトンネルを完成させる非開削工法が実用化されている。 Conventionally, as one of the construction methods for constructing a grade-crossing tunnel under a road line or a railway line, a special joint is used, and square steel shell elements divided into about 1 m are connected while connecting the joint. Continuing to install in the ground, fill the steel shell elements with concrete, build an outer shell structure using it as a member, and then excavate and remove the earth and sand inside the outer shell structure. A non-excavation method for completing tunnels has been put into practical use.

本出願人においても、下記特許文献1において、貫入済みの鋼殻エレメントと連結させながら順次鋼殻エレメントを貫入することにより地下構造物を構築するための鋼殻エレメントの継手構造において、止水部を備えた新たな継手構造について提案を行った。 The applicant of the present application also discloses in Patent Document 1 below that in a steel shell element joint structure for constructing an underground structure by successively penetrating the steel shell elements while connecting with the steel shell elements that have already been penetrated, the water stop portion We proposed a new joint structure with

特開2015-71904号公報JP 2015-71904 A

上記特許文献1にも開示されるように、従来の鋼殻エレメントの施工は、図9に示されるように、鋼殻エレメント50として、一方の側面に、推進後に隣り合う鋼殻エレメント50、50の側板51、51間に残った土砂を除去するための開口52がエレメント軸方向に沿って所定の間隔で設けられるとともに、この開口52を封鎖するための閉止板53が設けられたものが用いられ、図10に示されるように、先行して貫入した鋼殻エレメント50の凹継手54に凸継手55を嵌合させながら、後行の鋼殻エレメント50を貫入した後、図11に示されるように、先行の鋼殻エレメント50の側板51と後行の鋼殻エレメント50の側板51との間に残った土砂を、側板51に設けられた開口52を塞ぐ閉止板53を取り外して、前記開口52から除去するという手順で行われていた。 As disclosed in the above-mentioned Patent Document 1, the construction of the conventional steel shell element is performed, as shown in FIG. An opening 52 is provided at a predetermined interval along the axial direction of the element for removing the earth and sand remaining between the side plates 51, 51 of the element, and a closing plate 53 for closing the opening 52 is provided. As shown in FIG. 10, while fitting the convex joint 55 to the concave joint 54 of the steel shell element 50 that has penetrated earlier, the following steel shell element 50 is penetrated, and then the steel shell element 50 is shown in FIG. As described above, the earth and sand remaining between the side plate 51 of the preceding steel shell element 50 and the side plate 51 of the following steel shell element 50 is removed by removing the closing plate 53 that blocks the opening 52 provided in the side plate 51, The procedure was to remove from the opening 52 .

このように、従来の施工では、先行する鋼殻エレメントと後行する鋼殻エレメントとの側板間の残土を、狭い坑内で人力で掘削除去しなければならないため、非常に手間がかかり、施工期間の長期化及びコストの増大を招いていた。 In this way, in the conventional construction, the surplus soil between the side plates of the preceding steel shell element and the following steel shell element must be manually excavated and removed in a narrow tunnel. This resulted in a prolonged period of time and an increase in costs.

そこで本発明の主たる課題は、作業の省力化を図り、工期及びコストを低減した鋼殻エレメントの構築方法を提供することにある。 SUMMARY OF THE INVENTION Accordingly, the main object of the present invention is to provide a method for constructing a steel shell element that saves labor and reduces construction period and cost.

上記課題を解決するために請求項1に係る本発明として、角形中空断面の鋼殻エレメントを順次、貫入済みの鋼殻エレメントと継手部同士を連結させながら貫入する手順を繰り返して、地盤中に前記鋼殻エレメントによる閉合断面の外殻構造体を構築した後、この外殻構造体の内部土砂を除去することにより外殻先行トンネルを構築する際の前記鋼殻エレメントの構築方法であって、
先行して貫入させる鋼殻エレメントに、隣り合う鋼殻エレメント側に断面を拡大させる仮鋼管が取り付けられ、
貫入済みの鋼殻エレメントに前記仮鋼管が取り付けられた状態で、次順の鋼殻エレメントを貫入し、この鋼殻エレメントの施工完了後、前記仮鋼管を引き抜くことを特徴とする鋼殻エレメントの構築方法が提供される。
In order to solve the above problem, as the present invention according to claim 1, the steel shell element having a rectangular hollow cross section is repeatedly penetrated into the ground while connecting the steel shell element and the joint part that have been penetrated one by one. A method for constructing the steel shell element when constructing an outer shell precedent tunnel by constructing an outer shell structure having a closed cross section using the steel shell elements, and then removing soil and sand inside the outer shell structure, the method comprising:
A temporary steel pipe that expands the cross section to the adjacent steel shell element side is attached to the steel shell element that is penetrated first,
A steel shell element characterized by penetrating the steel shell element in the next order in a state in which the temporary steel pipe is attached to the steel shell element that has already been penetrated, and pulling out the temporary steel pipe after the construction of this steel shell element is completed. A construction method is provided.

上記請求項1記載の発明では、先行して貫入させる鋼殻エレメントに、隣り合う鋼殻エレメント側に断面を拡大させる仮鋼管を取り付け、貫入済みの鋼殻エレメントに前記仮鋼管が取り付けられた状態で、隣り合う鋼殻エレメントを継手部同士を連結させながら貫入し、この後行する鋼殻エレメントの施工が完了した後、前記仮鋼管を引き抜く手順とする。これにより、前記仮鋼管を配置することによって拡大した断面の分だけ、先行して貫入させた鋼殻エレメントと次順の鋼殻エレメントとの側板間に溜まる残土の量が減少し、鋼殻エレメントの貫入設置後に掘削除去すべき残土の量が減少する。したがって、作業の省力化が図れ、工期及びコストの低減が可能になる。 In the invention according to claim 1, the steel shell element to be penetrated first is attached with a temporary steel pipe that expands the cross section toward the adjacent steel shell element, and the temporary steel pipe is attached to the steel shell element that has already been penetrated. Then, adjacent steel shell elements are penetrated while connecting the joint portions, and after the construction of the subsequent steel shell elements is completed, the temporary steel pipe is pulled out. As a result, the amount of surplus soil accumulated between the side plates of the previously penetrated steel shell element and the next steel shell element is reduced by the amount of the cross section enlarged by arranging the temporary steel pipe, and the steel shell element The amount of surplus soil to be excavated and removed after installation of the intrusion is reduced. Therefore, it is possible to save labor in the work and reduce the construction period and cost.

請求項2に係る本発明として、前記各鋼殻エレメントは、角形中空断面と前記仮鋼管とを合わせた形状の最大幅寸法と最大高さ寸法とから規定される基本断面寸法をトンネル方向に一定としてある請求項1記載の鋼殻エレメントの構築方法が提供される。 As the present invention according to claim 2, each of the steel shell elements has a basic cross-sectional dimension defined by a maximum width dimension and a maximum height dimension of a shape obtained by combining a rectangular hollow cross section and the temporary steel pipe in the tunnel direction. A method for constructing a steel shell element according to claim 1 is provided.

上記請求項2記載の発明では、各鋼殻エレメントの断面形状は、基本的に掘削機の掘削断面形状と合致させるのがよいため、各鋼殻エレメントの基本断面寸法をトンネル方向に一定としている。 In the second aspect of the invention, since the cross-sectional shape of each steel shell element should basically match the excavation cross-sectional shape of the excavator, the basic cross-sectional dimension of each steel shell element is constant in the tunnel direction. .

請求項3に係る本発明として、前記仮鋼管は、隣り合う鋼殻エレメント側に突出する継手部の先端部とほぼ一致する範囲まで断面が拡大するように配置されている請求項1、2いずれかに記載の鋼殻エレメントの構築方法が提供される。 As the present invention according to claim 3, the temporary steel pipe is arranged so that the cross section expands to a range that substantially coincides with the tip part of the joint part projecting to the side of the adjacent steel shell element. There is provided a method of constructing a steel shell element as described above.

上記請求項3記載の発明では、前記仮鋼管を、隣り合う鋼殻エレメント側に突出する継手部の先端部とほぼ一致する範囲まで断面が拡大するように配置することにより、鋼殻エレメントの貫入時に略矩形状の断面を掘削すればよくなり、掘削装置が単純化して汎用性が向上できる。 In the invention according to claim 3, the temporary steel pipe is arranged so that the cross section expands to a range that substantially coincides with the tip end portion of the joint portion projecting to the side of the adjacent steel shell element, thereby allowing the steel shell element to penetrate. In some cases, it is sufficient to excavate a substantially rectangular cross section, which simplifies the excavator and improves versatility.

請求項4に係る本発明として、前記仮鋼管は、鋼殻エレメントにボルトによって固定されており、前記ボルトを取り外すことにより引き抜き可能となる請求項1~3いずれかに記載の鋼殻エレメントの構築方法が提供される。 As the present invention according to claim 4, the steel shell element construction according to any one of claims 1 to 3, wherein the temporary steel pipe is fixed to the steel shell element with a bolt, and can be pulled out by removing the bolt. A method is provided.

上記請求項4記載の発明では、前記仮鋼管をボルトによって鋼殻エレメントに固定しており、このボルトを取り外すことによって仮鋼管の引き抜きを可能としているため、仮鋼管を位置ズレすることなく貫入できるとともに、簡単に引き抜くことができるようになる。 In the invention according to claim 4, the temporary steel pipe is fixed to the steel shell element by a bolt, and the temporary steel pipe can be pulled out by removing the bolt. Together with this, it can be easily pulled out.

請求項5に係る本発明として、貫入済みの鋼殻エレメントの凹継手に対して、次順の鋼殻エレメントの凸継手を連結させながら貫入する手順とする請求項1~4いずれかに記載の鋼殻エレメントの構築方法が提供される。 As the present invention according to claim 5, the step of penetrating while connecting the convex joint of the steel shell element in the next order to the concave joint of the steel shell element that has been penetrated. A method of constructing a steel shell element is provided.

上記請求項5記載の発明では、貫入させる際に、鋼殻エレメントの凹継手部分は連結無しに貫入させ、次順の鋼殻エレメントの貫入時に、凸継手を設置済みの鋼殻エレメントの凹継手に連結させた状態で貫入設置している。この手順によると、鋼殻エレメントの貫入精度及び効率が良好になるとともに、同時に止水性も確保し易くなる。 In the invention according to claim 5, when the steel shell element is penetrated, the concave joint portion of the steel shell element is penetrated without connecting, and when the next steel shell element is penetrated, the concave joint of the steel shell element whose convex joint has already been installed is inserted. It is intrusively installed in a state where it is connected to According to this procedure, the penetration accuracy and efficiency of the steel shell element are improved, and at the same time, it becomes easier to secure water stoppage.

請求項6に係る本発明として、前記鋼殻エレメントを貫入させる際に使用される掘削機は、正面掘削部の形状が前記鋼殻エレメントの角形中空断面と前記仮鋼管とを合わせた形状に整合し、かつ胴体部に前記継手部に対応する土砂部分を掘削するための補助カッターを備えるか、もしくは前記掘削機で前記継手部を包括する範囲の余掘りを行う請求項1~5いずれかに記載の鋼殻エレメントの構築方法が提供される。 According to a sixth aspect of the present invention, the excavator used for penetrating the steel shell element has a shape of the front excavation portion that matches the shape of the square hollow cross section of the steel shell element and the temporary steel pipe. and an auxiliary cutter for excavating the earth and sand portion corresponding to the joint portion is provided in the body portion, or the excavator performs over excavation in a range including the joint portion A method of constructing the described steel shell element is provided.

上記請求項6記載の発明では、前記鋼殻エレメントを貫入させる際に使用される掘削機として、正面掘削部の形状が前記鋼殻エレメントの角形中空断面と前記仮鋼管とを合わせた形状に整合し、かつ胴体部に前記継手部に対応する土砂部分を掘削するための補助カッターを備えるか、もしくは前記掘削機で前記継手部を包括する範囲の余掘を行うものを用いているため、掘削機による掘削部に鋼殻エレメントを貫入し易くなる。 In the invention according to claim 6, the excavator used for penetrating the steel shell element has a shape of the front excavation portion that matches the shape of the combination of the square hollow cross section of the steel shell element and the temporary steel pipe. In addition, since the body is equipped with an auxiliary cutter for excavating the earth and sand portion corresponding to the joint portion, or the excavator is used to excavate the range that includes the joint portion, excavation It becomes easier to penetrate the steel shell element into the excavated part by machine.

以上詳説のとおり本発明によれば、作業の省力化が図れ、工期及びコストが低減できる鋼殻エレメントの構築方法が提供できるようになる。 As described in detail above, according to the present invention, it is possible to provide a method of constructing a steel shell element that can save labor and reduce the construction period and cost.

本発明に従って構築される外殻構造体1の断面図である。1 is a cross-sectional view of a shell structure 1 constructed according to the invention; FIG. 外殻構造体1の施工手順(その1)を示す斜視図である。FIG. 4 is a perspective view showing a procedure (part 1) for constructing the outer shell structure 1; 外殻構造体1の施工手順(その2)を示す斜視図である。FIG. 10 is a perspective view showing a procedure (part 2) for constructing the outer shell structure 1; 外殻構造体1の施工手順(その3)を示す斜視図である。FIG. 11 is a perspective view showing a construction procedure (part 3) of the outer shell structure 1; 外殻構造体1の施工手順(その4)を示す斜視図である。FIG. 11 is a perspective view showing a construction procedure (part 4) of the outer shell structure 1; 掘削範囲を示す断面図である。It is a sectional view showing an excavation range. 掘削装置20の正面図である。1 is a front view of an excavator 20; FIG. 掘削装置20の縦断面図である。2 is a longitudinal sectional view of the drilling rig 20. FIG. 従来の鋼殻エレメント50を示す断面図である。FIG. 5 is a cross-sectional view showing a conventional steel shell element 50; 従来の鋼殻エレメント50の施工手順(その1)を示す断面図である。FIG. 10 is a cross-sectional view showing a procedure (part 1) for constructing a conventional steel shell element 50; 従来の鋼殻エレメント50の施工手順(その2)を示す断面図である。FIG. 10 is a cross-sectional view showing a procedure (part 2) for constructing a conventional steel shell element 50;

以下、本発明の実施の形態について図面を参照しながら詳述する。 BEST MODE FOR CARRYING OUT THE INVENTION Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.

本発明は、図1及び図2~図5に示されるように、角形中空断面の鋼殻エレメント3を順次、貫入済みの鋼殻エレメント2と継手部同士を連結させながら貫入する手順を繰り返して、地盤中に多数の鋼殻エレメントによって、断面視で矩形状や円形状、多角形状などの形状に閉合させた外殻構造体1を構築した後、この外殻構造体1の内部土砂を除去することにより外殻先行トンネルを構築する際の前記鋼殻エレメントの構築方法である。特に本発明は、トンネル方向に断面積が一定のトンネルを構築する方法である。 In the present invention, as shown in FIGS. 1 and 2 to 5, the procedure of inserting steel shell elements 3 having square hollow cross sections sequentially while connecting the steel shell elements 2 that have already been penetrated and joint portions is repeated. After constructing an outer shell structure 1 closed in a shape such as a rectangle, a circle, or a polygon in a cross-sectional view by a large number of steel shell elements in the ground, the internal earth and sand of this outer shell structure 1 is removed. This is a construction method of the steel shell element when constructing the outer shell precedent tunnel by doing. In particular, the invention is a method of constructing a tunnel with a constant cross-sectional area in the direction of the tunnel.

前記外殻先行トンネル構築方法は、周辺地盤への影響が少ないなどの利点を有するため、道路路線や鉄道路線などの路線下の地盤に非開削によって、アンダーパストンネルを構築する際の工法として多用されているものである。 Since the method for constructing tunnels in front of the outer shell has the advantage of having little impact on the surrounding ground, it is often used as a construction method for constructing underpass tunnels without excavation in the ground beneath roads, railways, etc. It is what is done.

本発明では特に、先行して貫入させる鋼殻エレメント2に、隣り合う鋼殻エレメント3側に断面を拡大させる仮鋼管6が取り付けられ、貫入済みの鋼殻エレメント2に前記仮鋼管6が取り付けられた状態で、隣り合う鋼殻エレメント3を貫入し、この鋼殻エレメント3の施工完了後、前記仮鋼管6を引き抜くことにより、外殻構造体1を構築する際の施工の省力化を図ったものである。以下、さらに具体的に詳述する。 In particular, in the present invention, a temporary steel pipe 6 is attached to the steel shell element 2 to be penetrated first, and the temporary steel pipe 6 is attached to the steel shell element 2 that has already been penetrated. In this state, the steel shell elements 3 adjacent to each other are penetrated, and after the construction of the steel shell elements 3 is completed, the temporary steel pipe 6 is pulled out, thereby saving labor in constructing the outer shell structure 1. It is. More specific details will be given below.

前記鋼殻エレメントは、断面形状及び貫入要領の違いによって、最初に貫入させる開始エレメント2と、外殻構造体1の上床版1A、下床版1B及び両側壁版1C、1Cの中間部分に配置される標準エレメント3、3…と、外殻構造体1の4つの隅角部に配置される調整エレメント4、4…と、最後に貫入させる閉合エレメント5との4種類の鋼殻エレメントに分類される。なお、図1において、各鋼殻エレメント2~5の内部に付した丸囲み数字は、貫入順序を示したものである。 The steel shell elements are arranged in the intermediate portions of the starting element 2 to be penetrated first, the upper floor slab 1A, the lower floor slab 1B, and the side wall slabs 1C, 1C of the outer shell structure 1, depending on the difference in cross-sectional shape and penetration procedure. Categorized into four types of steel shell elements: standard elements 3, 3 . be done. In FIG. 1, the circled numbers inside the steel shell elements 2 to 5 indicate the order of penetration.

先ず、前記開始エレメント2は、図2に示されるように、上板20、下板21及び側板22、22によって構成される角形中空断面のエレメントを基本形とする。前記上板20及び下板21の両側部にそれぞれ、側板22より外方に延びるとともに、隣接する鋼殻エレメント3に向けて延びる張出部材23、23を設けるとともに、この張出部材23の先端に部材長手方向に沿って凹継手24、24を設けている。前記張出部材23の張出長さは全長に亘ってほぼ一定である。 First, as shown in FIG. 2, the starting element 2 is basically an element having a rectangular hollow cross section composed of an upper plate 20, a lower plate 21 and side plates 22,22. On both sides of the upper plate 20 and the lower plate 21, projecting members 23, 23 extending outward from the side plate 22 and extending toward the adjacent steel shell element 3 are provided. , concave joints 24, 24 are provided along the longitudinal direction of the member. The extension length of the extension member 23 is substantially constant over the entire length.

前記開始エレメント2の両側板22、22にはそれぞれ、隣り合う鋼殻エレメント3側に断面を拡大させる仮鋼管6が取り付けられている。前記仮鋼管6は、断面略矩形のトンネル方向に延びる鋼管であり、前記側板22の外面に複数のボルト7…によって固定されている。 Temporary steel pipes 6 are attached to both side plates 22, 22 of the starting element 2, respectively, to enlarge the cross section toward the adjacent steel shell element 3 side. The temporary steel pipe 6 is a steel pipe having a substantially rectangular cross section and extending in the tunnel direction, and is fixed to the outer surface of the side plate 22 by a plurality of bolts 7 .

開始エレメント2において、前記仮鋼管6は、上板20及び下板21の各側方に延在する張出部材23、23及びその先端に設けられた凹継手24、24間にそれぞれ設けられている。すなわち、仮鋼管6の高さ寸法Hは、凹継手24、24の厚み分だけ、角形中空断面の高さ寸法Hより小さくなっている。前記仮鋼管6は、トンネル方向に一定の断面形状で形成されている。 In the starting element 2, the temporary steel pipes 6 are provided between overhang members 23, 23 extending to the sides of the upper plate 20 and the lower plate 21 and concave joints 24, 24 provided at the ends thereof. there is That is, the height dimension H6 of the temporary steel pipe 6 is smaller than the height dimension H of the rectangular hollow section by the thickness of the concave joints 24,24. The temporary steel pipe 6 is formed with a constant cross-sectional shape in the tunnel direction.

前記仮鋼管6を開始エレメント2に固定するには、複数のボルト7…が用いられる。前記ボルト7…による固定のため、開始エレメント2の側板22に通孔を設けるとともに、仮鋼管6の対応する位置に通孔を設け、その内側にナットを固定する。角形中空断面の内側からボルト7を前記通孔に挿通させ、前記ナットに螺合させる。これにより、開始エレメント2の貫入設置後に、角形中空断面の内部に作業員が入ってボルト7…の取り外し作業を行うことができる。 A plurality of bolts 7 are used to fix the temporary steel pipe 6 to the starting element 2 . For fixing by the bolts 7, through holes are provided in the side plates 22 of the starting element 2, and through holes are provided in the corresponding positions of the temporary steel pipe 6, and nuts are fixed inside them. A bolt 7 is inserted through the through hole from the inside of the rectangular hollow section and screwed into the nut. As a result, after the starting element 2 has been penetrated and installed, an operator can enter the interior of the rectangular hollow section to remove the bolts 7 .

上記開始エレメント2は、両側に凹継手24、24…を有するものであり、地盤中に最初に貫入設置される鋼殻エレメントとなる。鋼殻エレメント2の貫入設置の際に使用される掘削機は、前記角形中空断面と仮鋼管6とを合わせた形状の最大幅寸法Bと最大高さ寸法Hとから規定される基本断面寸法に整合した断面形状の掘削機40が用いられる。 The starting element 2 has concave joints 24, 24... on both sides, and serves as a steel shell element that is first penetratingly installed in the ground. The excavator used for penetrating installation of the steel shell element 2 has a basic cross-sectional dimension defined by the maximum width dimension B and the maximum height dimension H of the shape obtained by combining the square hollow cross section and the temporary steel pipe 6. A matching cross-sectional excavator 40 is used.

次いで、前記開始エレメント2の片側に隣接配置される標準エレメント3は、詳細には図3に示されるように、上板30、下板31及び側板32、32によって構成される角形中空断面のエレメントを基本形とする。前記上板30及び下板31の一方側(開始エレメント2側)には、側板32より外方に延びる張出部材33、33を設けるとともに、この張出部材33の先端に部材長手方向に沿って凸継手34を設けている。前記凸継手34を設けた反対側には、前記上板30及び下板31が側板32より外方に延びる張出部材35を設けるとともに、この張出部材35の先端に部材長手方向に沿って凹継手36を設けている。前記張出部材33、35の張出長さは全長に亘ってほぼ一定である。 Next, the standard element 3 arranged adjacent to one side of the starting element 2 is an element of rectangular hollow cross-section constituted by an upper plate 30, a lower plate 31 and side plates 32, 32, as shown in detail in FIG. is the basic form. On one side of the upper plate 30 and the lower plate 31 (on the side of the starting element 2), projecting members 33, 33 extending outward from the side plate 32 are provided. A convex joint 34 is provided at the end. On the opposite side of the convex joint 34, a protruding member 35 is provided in which the upper plate 30 and the lower plate 31 extend outward from the side plate 32. At the tip of the protruding member 35, a A concave joint 36 is provided. The extension length of the extension members 33 and 35 is substantially constant over the entire length.

前記標準エレメント3の凹継手36が設けられた側の側板32には、隣り合う鋼殻エレメント(当該標準エレメント3に対して連結して貫入される次の鋼殻エレメント)側に断面を拡大させる仮鋼管6が取り付けられている。一方、前記凸継手34が設けられた側の側板32には前記仮鋼管6が設けられていない。前記仮鋼管6は、前記開始エレメント2で用いたものと同様の構造であるので説明を省略する。 The side plate 32 on the side of the standard element 3 on which the concave joint 36 is provided has a cross section that is enlarged toward the adjacent steel shell element (the next steel shell element that is connected and penetrated with respect to the standard element 3). A temporary steel pipe 6 is attached. On the other hand, the temporary steel pipe 6 is not provided on the side plate 32 on which the convex joint 34 is provided. The temporary steel pipe 6 has the same structure as that used in the starting element 2, so the description thereof is omitted.

前記標準エレメント3の貫入設置の際に使用される掘削機としては、上記開始エレメント2で用いた掘削機40と同様の掘削機を用いることができる。 As an excavator used for penetrating installation of the standard element 3, an excavator similar to the excavator 40 used for the starting element 2 can be used.

前記標準エレメント3をいくつか隣接配置した後(図示例では3つ配置した後)、次順に前記調整エレメント4が隣接配置される。前記調整エレメント4は、代表的に図1におけるNo.5のエレメントで説明すると、上板、下板、側板によって構成される角形中空断面のエレメントを基本形とし、前記上板及び下板の一方側(1つ前に配置した標準エレメント3側)には、側板より外方に延びる張出部材を設けるとともに、この張出部材の先端に部材長手方向に沿って凸継手を設けている。また、両側板の下側(次順の標準エレメント3側)には、下板より外方に延びる張出部材を設けるとともに、この張出部材の先端に部材長手方向に沿って凹継手を設けている。前記張出部材の張出長さは全長に亘ってほぼ一定である。 After some of the standard elements 3 are arranged adjacently (three in the illustrated example), the adjustment elements 4 are arranged adjacently. The adjustment element 4, representatively explained with element No. 5 in FIG. A projecting member extending outward from the side plate is provided on (the side of the standard element 3 arranged one before), and a convex joint is provided at the tip of this projecting member along the longitudinal direction of the member. In addition, on the lower side of both side plates (on the side of the next standard element 3), an overhanging member extending outward from the lower plate is provided, and a concave joint is provided at the tip of this overhanging member along the longitudinal direction of the member. ing. The extension length of the extension member is substantially constant over the entire length.

前記調整エレメント4の凹継手が設けられた側の下板には、隣り合う鋼殻エレメント(当該調整エレメント4に対して連結して貫入される次の鋼殻エレメント3)側に断面を拡大させる仮鋼管6が取り付けられている。一方、前記凸継手が設けられた側の側板には前記仮鋼管6が設けられていない。前記仮鋼管6は、前記開始エレメント2で用いたものと同様の構造である。 The lower plate of the adjustment element 4 on the side where the concave joint is provided has a cross section that is enlarged toward the adjacent steel shell element (the next steel shell element 3 that is connected to and penetrates the adjustment element 4). A temporary steel pipe 6 is attached. On the other hand, the temporary steel pipe 6 is not provided on the side plate on which the convex joint is provided. The temporary steel tube 6 is of similar construction to that used in the starting element 2 .

最後に貫入させる閉合エレメント5は、図1におけるNo.15エレメントで説明すると、上板、下板、側板によって構成される角形中空断面のエレメントを基本形とし、前記上板及び下板の両側部にそれぞれ、側板より外方側に延びるとともに、隣接する鋼殻エレメント3に向けて延びる張出部材を設けるとともに、この張出部材の先端に部材長手方向に沿って凸継手を設けている。前記張出部材の張出長さは全長に亘ってほぼ一定である。 The closing element 5, which is inserted last, is basically an element with a square hollow cross-section consisting of an upper plate, a lower plate and a side plate. Each of them is provided with an overhang member extending outward from the side plate and extending toward the adjacent steel shell element 3, and a convex joint is provided at the tip of the overhang member along the longitudinal direction of the member. The extension length of the extension member is substantially constant over the entire length.

この鋼殻エレメント5には、前記仮鋼管6が設けられていない。すなわち、先行して貫入された両隣の鋼殻エレメント3、3にそれぞれ、最後に貫入させる閉合エレメント5側に断面を拡大させる仮鋼管6が設けられているため、閉合エレメント5には前記仮鋼管6を設ける必要がない。 The steel shell element 5 is not provided with the temporary steel pipe 6 . That is, since the steel shell elements 3, 3 on both sides that have been penetrated first are provided with the temporary steel pipes 6 that expand the cross section toward the closing element 5 side that is penetrated last, the temporary steel pipes 6 are provided on the closing element 5. 6 need not be provided.

上記各鋼殻エレメント2~4に取り付けられる仮鋼管6は、断面略矩形の外殻構造体1の軸方向に延びる鋼管であり、鋼殻エレメントのうち、次順に貫入させる鋼殻エレメントに対向する板部材に複数のボルト7…によって固定されている。この仮鋼管6が備えられた鋼殻エレメント2を貫入設置後、この貫入済みの鋼殻エレメント2に継手部同士を連結させながら次順の鋼殻エレメント3を貫入し、後行する鋼殻エレメント3の設置が完了したならば、先行して貫入させた鋼殻エレメントに取り付けられた仮鋼管6を、前記ボルト7…を取り外した上で引き抜く。 The temporary steel pipes 6 attached to the respective steel shell elements 2 to 4 are steel pipes extending in the axial direction of the outer shell structure 1 having a substantially rectangular cross section, and face the steel shell elements to be penetrated in order among the steel shell elements. It is fixed to the plate member by a plurality of bolts 7 . After penetrating and installing the steel shell element 2 provided with the temporary steel pipe 6, the following steel shell element 3 is penetrated while connecting the joint parts to the steel shell element 2 that has been penetrated, and the following steel shell element. When the installation of 3 is completed, the temporary steel pipe 6 attached to the previously penetrated steel shell element is pulled out after removing the bolts 7 .

このように、先行して貫入させる鋼殻エレメント2に、隣り合う鋼殻エレメント3側に断面を拡大させる仮鋼管6が取り付けられているため、前記仮鋼管6を配置することによって拡大した断面の分だけ、先行して貫入した鋼殻エレメント2と次順の鋼殻エレメント3との側板間に溜まる残土の量が減少し、鋼殻エレメント3の貫入設置後に掘削除去すべき残土の量が減少する。このため、作業の省力化が図れ、工期及びコストの低減が可能になる。 In this way, since the temporary steel pipe 6 that expands the cross section toward the adjacent steel shell element 3 side is attached to the steel shell element 2 that is penetrated first, the expanded cross section is obtained by arranging the temporary steel pipe 6. Accordingly, the amount of surplus soil that accumulates between the side plates of the steel shell element 2 that penetrates first and the steel shell element 3 that follows is reduced, and the amount of surplus soil that must be excavated and removed after the steel shell element 3 has been penetrated and installed is reduced. do. As a result, the work can be labor-saving, and the construction period and cost can be reduced.

また、後行する鋼殻エレメント3の貫入設置後、先行して貫入させた鋼殻エレメント2に取り付けられた仮鋼管6は引き抜いて除去されるため、前記仮鋼管6が鋼殻エレメント内におけるコンクリートの充填性に悪影響を及ぼすことがない。 In addition, after the steel shell element 3 that follows is inserted and installed, the temporary steel pipe 6 attached to the steel shell element 2 that has been penetrated first is pulled out and removed. It does not adversely affect the fillability of the

前記仮鋼管6の配設範囲は、外殻構造体1を構成したときに内周側及び外周側にそれぞれ配置された凹継手24、24間又は36、36間であって、次順の鋼殻エレメントに対向する板部材(図2に示される開始エレメント2の場合は側板22)の外面から、隣り合う標準エレメント3側に張り出した張出部材23の先端に設けられた凹継手24の先端までの間の略矩形の範囲である。したがって、先行して貫入させた凹継手24に連結挿入される凸継手34部分を除くと、仮鋼管6を含む鋼殻エレメントの断面形状は略矩形状となる(図6参照。)。 The provisional steel pipe 6 is arranged in a range between concave joints 24, 24 or between concave joints 36, 36 arranged respectively on the inner peripheral side and the outer peripheral side when the outer shell structure 1 is constructed. The tip of the concave joint 24 provided at the tip of the projecting member 23 projecting from the outer surface of the plate member facing the shell element (the side plate 22 in the case of the starting element 2 shown in FIG. 2) to the side of the adjacent standard element 3. is a substantially rectangular range between Therefore, the cross-sectional shape of the steel shell element including the temporary steel pipe 6 is substantially rectangular except for the portion of the convex joint 34 that is inserted and connected to the previously penetrated concave joint 24 (see FIG. 6).

次に、前記外殻構造体1を構築する手順に従いながら、鋼殻エレメント2~5の貫入要領について詳述する。 Next, while following the procedure for constructing the outer shell structure 1, the procedure for penetrating the steel shell elements 2 to 5 will be described in detail.

鋼殻エレメント2~5の貫入手順は、図1に示される外殻構造体1の断面図にNo.1~No.15の番号を付した順序とする。すなわち、多数の鋼殻エレメント2~5を矩形状に閉合させた矩形断面の内、上床版1A中央部の鋼殻エレメント2(No.1:開始エレメント)を最初に貫入させ、この鋼殻エレメント2を基点として両側にそれぞれ、水平方向に沿って順次鋼殻エレメント3、3…(標準エレメント)を貫入させて上床版1Aとなる部分を構築した後、その両端にそれぞれ隅角部用の鋼殻エレメント4(No.5:調整エレメント)を貫入させ、順次下方側に向かって鋼殻エレメント3、3…(標準エレメント)を貫入させて側壁1C、1Cを構築し、次いで下端隅角部の鋼殻エレメント4(No.11:調整エレメント)から順次水平方向に沿って鋼殻エレメント3、3…(標準エレメント)を貫入させ、最後に閉合エレメント5を貫入させて下床版1Bとなる部分を構築する手順によって、多数の鋼殻エレメント2~5によって断面視で矩形状に閉合させた外殻構造体1を構築する。 The procedure for penetrating the steel shell elements 2 to 5 is the order numbered No. 1 to No. 15 in the cross-sectional view of the shell structure 1 shown in FIG. That is, among the rectangular cross sections in which a large number of steel shell elements 2 to 5 are closed in a rectangular shape, the steel shell element 2 (No. 1: starting element) at the center of the upper floor slab 1A is first penetrated, 2 as a base point, the steel shell elements 3, 3, . The shell element 4 (No. 5: adjustment element) is penetrated, and the steel shell elements 3, 3 ... (standard elements) are sequentially penetrated downward to construct the side walls 1C, 1C, and then the lower end corners. Starting from the steel shell element 4 (No. 11: adjustment element), the steel shell elements 3, 3, . , an outer shell structure 1 is constructed in which a large number of steel shell elements 2 to 5 are closed in a rectangular shape when viewed in cross section.

更に詳しい貫入手順について、図2~図5に基づいて、開始エレメント2と、これに隣り合う標準エレメント3とを貫入させる場合を例に挙げ説明すると、先ずはじめに、図2に示されるように、両側板22、22にそれぞれ仮鋼管6を取り付けた開始エレメント2を貫入設置する。この開始エレメント2の貫入設置の際には掘削機40が使用される。前記掘削機が開始エレメントを牽引、もしくは元押しジャッキが前記掘削機と開始エレメント2を押しながら貫入する。前記掘削機40としては、例えば図7及び図8に示される掘削装置を使用することができる。図示された掘削機40は、密閉型の掘削装置であり、地下水位以下でも地盤改良無しに外殻構造体1の施工が行えるようにしたものである。前述した鋼殻エレメント2~5及び仮鋼管6を合わせた形状とほぼ同等の断面形状を成し、オーガスクリュー41の先端に設けられたメインカッター42とともに、所定数の遊星カッター43、43を備え、矩形断面に掘削を行う。排土方式はスクリューコンベア方式である。四隅にはそれぞれ凹継手24…に対応する土砂部分を掘削するための補助カッター44が着脱自在とされる。開始エレメント2の貫入時には、凹継手24、24…が備えられる四隅の隅角部位置に補助カッター44、44…が備えられ、標準エレメント3の貫入時には、非連結側となる凹継手36、36が備えられた上下隅角部位置に補助カッター44、44が備えられている。なお、前記補助カッター44を備えなくても、前記掘削機40によって凹継手36部分を包括する範囲の余掘りが行えるようにしてもよい。 A more detailed penetrating procedure will be explained based on FIGS. A starting element 2 with a temporary steel pipe 6 attached to each of the side plates 22, 22 is penetrated. An excavator 40 is used for the intrusive installation of the starting element 2 . The excavator pulls the starting element, or the pushing jack pushes the excavator and the starting element 2 while penetrating. As the excavator 40, for example, an excavator shown in FIGS. 7 and 8 can be used. The illustrated excavator 40 is a closed-type excavator, which enables construction of the outer shell structure 1 without ground improvement even below the ground water level. A main cutter 42 provided at the tip of an auger screw 41 and a predetermined number of planetary cutters 43, 43 are provided. , to excavate in a rectangular section. The soil discharge method is a screw conveyor method. Auxiliary cutters 44 for excavating earth and sand portions corresponding to the concave joints 24 are detachably attached to the four corners. When the starting element 2 is inserted, auxiliary cutters 44, 44 are provided at the four corner positions where the concave joints 24, 24, . Auxiliary cutters 44, 44 are provided at the upper and lower corner positions where the are provided. It should be noted that the excavator 40 may be used to excavate the area including the concave joint 36 without the auxiliary cutter 44 .

前記鋼殻エレメント2~4に仮鋼管6が備えられることによって、隣り合う鋼殻エレメントが貫入されるまでの間、前記掘削機40で掘削した壁面の崩壊が防止できる。 By equipping the steel shell elements 2 to 4 with the temporary steel pipes 6, it is possible to prevent the wall surface excavated by the excavator 40 from collapsing until the adjacent steel shell elements are penetrated.

前記開始エレメント2を貫入し終えたならば、図3に示されるように、この開始エレメント2に取り付けられた仮鋼管6をそのままにした状態で、この貫入済みの開始エレメント2の凹継手24に凸継手34を連結させながら、次順の隣り合う標準エレメント3(No.2)を貫入する。この標準エレメント3の貫入が完了した時点で、図4に示されるように、エレメント2、3間の仮鋼管6と、後行して貫入した鋼殻エレメント3の側板との間の隙間に、若干の土砂が残ることがある。 Once the starting element 2 has been penetrated, as shown in FIG. While connecting the convex joint 34, the next adjacent standard element 3 (No. 2) is penetrated. When the penetration of this standard element 3 is completed, as shown in FIG. Some sand may remain.

その後、図5に示されるように、先行して貫入させた開始エレメント2に取り付けられた仮鋼管6を引き抜く。前記仮鋼管6を引き抜く前に、開始エレメント2に対する固定用のボルト7、7…を全て取り外しておく。 Thereafter, as shown in FIG. 5, the temporary steel tube 6 attached to the previously penetrated starting element 2 is withdrawn. Before pulling out the temporary steel pipe 6, all the bolts 7, 7... for fixing to the start element 2 are removed.

前記仮鋼管6の引き抜き後、必要に応じて、この仮鋼管6と後行して貫入した標準エレメント3との間に溜まった残土を除去する。この残土を除去するには、仮鋼管6が取り付けられた側板に開口(図示せず)を設けておき、この開口を閉塞する蓋を取り外して、開口から人力で掘削除去する。従来の鋼殻エレメントでは、エレメント間の残土量が多いため、開口からの残土の除去作業がしやすいように、開口の大きさを大きくしたり、開口の形成ピッチを小さくしたりする必要があり、鋼殻エレメントの強度低下を招くおそれがあったが、本発明に係る鋼殻エレメントでは、前記仮鋼管6が設けられることにより、エレメント間の残土量が大幅に低減するため、開口から除去する残土量が少なく、開口の大きさを小さくしたり、開口の形成ピッチを大きくしたりすることができ、鋼殻エレメントの強度が確保できる。なお、残土を除去するための開口が前記仮鋼管6で塞がれる場合は、開口を閉塞する蓋を別途設けなくてもよい。 After the temporary steel pipe 6 is pulled out, if necessary, the surplus soil accumulated between the temporary steel pipe 6 and the standard element 3 that has penetrated subsequently is removed. In order to remove this surplus soil, an opening (not shown) is provided in the side plate to which the temporary steel pipe 6 is attached, the cover covering this opening is removed, and the excavation is removed manually from the opening. With conventional steel shell elements, there is a large amount of surplus soil between the elements, so it is necessary to increase the size of the openings and reduce the pitch of the openings to make it easier to remove the surplus soil from the openings. However, in the steel shell element according to the present invention, the provision of the temporary steel pipe 6 significantly reduces the amount of surplus soil between the elements, so it is removed from the opening. The amount of residual soil is small, the size of the openings can be made small, and the formation pitch of the openings can be increased, ensuring the strength of the steel shell element. In addition, when the opening for removing the surplus soil is closed with the temporary steel pipe 6, it is not necessary to separately provide a lid for closing the opening.

〔他の形態例〕
(1)上記形態例では、上床版の中央部を基点としてその両側にそれぞれ反対側の下床版の中央部まで順に構築したが、任意の位置を起点としてその両側にそれぞれその反対側まで順に構築してもよい。
[Other form examples]
(1) In the example above, the central part of the upper floor slab was used as a starting point, and it was constructed on both sides in order up to the central part of the lower floor slab on the opposite side. may be constructed.

(2)上記形態例では、貫入済みの鋼殻エレメント2の凹継手24に対して凸継手34を連結しながら後行の鋼殻エレメント3を貫入させるようにしたが、凹継手と凸継手がこれと逆の関係、すなわち貫入済みの鋼殻エレメント2の凸継手に対して凹継手を連結しながら後行の鋼殻エレメント3を貫入させるようにしてもよい。なお、凸継手と凹継手の関係は、本形態例で示したように、貫入済みの鋼殻エレメント2の凹継手2に対して、凸継手34を連結しながら後行の鋼殻エレメント3を貫入させるようにするのが望ましい。 (2) In the above embodiment, the following steel shell element 3 is inserted while the convex joint 34 is connected to the concave joint 24 of the steel shell element 2 that has already been penetrated. It is also possible to have a reverse relationship, that is, insert the following steel shell element 3 while connecting the concave joint to the convex joint of the steel shell element 2 that has already penetrated. As shown in this embodiment, the relationship between the convex joint and the concave joint is such that the following steel shell element 3 is connected while the convex joint 34 is connected to the concave joint 2 of the steel shell element 2 that has already penetrated. Penetration is preferable.

1…外殻構造体、2…鋼殻エレメント(開始エレメント)、3…鋼殻エレメント(標準エレメント)、4…鋼殻エレメント(調整エレメント)、5…鋼殻エレメント(閉合エレメント)、6…仮鋼管、7…ボルト、24・36…凹継手、34…凸継手、40…掘削機 DESCRIPTION OF SYMBOLS 1... Shell structure, 2... Steel shell element (starting element), 3... Steel shell element (standard element), 4... Steel shell element (adjusting element), 5... Steel shell element (closing element), 6... Temporary Steel pipe 7 Bolt 24 36 Concave joint 34 Convex joint 40 Excavator

Claims (6)

角形中空断面の鋼殻エレメントを順次、貫入済みの鋼殻エレメントと継手部同士を連結させながら貫入する手順を繰り返して、地盤中に前記鋼殻エレメントによる閉合断面の外殻構造体を構築した後、この外殻構造体の内部土砂を除去することにより外殻先行トンネルを構築する際の前記鋼殻エレメントの構築方法であって、
先行して貫入させる鋼殻エレメントに、隣り合う鋼殻エレメント側に断面を拡大させる仮鋼管が取り付けられ、
貫入済みの鋼殻エレメントに前記仮鋼管が取り付けられた状態で、次順の鋼殻エレメントを貫入し、この鋼殻エレメントの施工完了後、前記仮鋼管を引き抜くことを特徴とする鋼殻エレメントの構築方法。
After constructing an outer shell structure with a closed cross-section of the steel shell elements in the ground by repeating the procedure of penetrating the steel shell elements with square hollow cross sections sequentially while connecting the steel shell elements that have already been penetrated and the joint parts. , a method for constructing the steel shell element when constructing the outer shell precedent tunnel by removing the internal earth and sand of the outer shell structure,
A temporary steel pipe that expands the cross section to the adjacent steel shell element side is attached to the steel shell element that is penetrated first,
In a state in which the temporary steel pipe is attached to the steel shell element that has already been penetrated, the steel shell element is penetrated in the next order, and after the construction of this steel shell element is completed, the temporary steel pipe is pulled out. construction method.
前記各鋼殻エレメントは、角形中空断面と前記仮鋼管とを合わせた形状の最大幅寸法と最大高さ寸法とから規定される基本断面寸法をトンネル方向に一定としてある請求項1記載の鋼殻エレメントの構築方法。 2. The steel shell according to claim 1, wherein each of said steel shell elements has a basic cross-sectional dimension defined by a maximum width dimension and a maximum height dimension of a shape obtained by combining a square hollow cross section and said temporary steel pipe, which is constant in the tunnel direction. How the element is constructed. 前記仮鋼管は、隣り合う鋼殻エレメント側に突出する継手部の先端部とほぼ一致する範囲まで断面が拡大するように配置されている請求項1、2いずれかに記載の鋼殻エレメントの構築方法。 Construction of a steel shell element according to any one of claims 1 and 2, wherein the temporary steel pipe is arranged so that the cross section expands to a range that substantially coincides with the tip end portion of the joint portion projecting to the side of the adjacent steel shell element. Method. 前記仮鋼管は、鋼殻エレメントにボルトによって固定されており、前記ボルトを取り外すことにより引き抜き可能となる請求項1~3いずれかに記載の鋼殻エレメントの構築方法。 The steel shell element construction method according to any one of claims 1 to 3, wherein the temporary steel pipe is fixed to the steel shell element with a bolt, and can be pulled out by removing the bolt. 貫入済みの鋼殻エレメントの凹継手に対して、次順の鋼殻エレメントの凸継手を連結させながら貫入する手順とする請求項1~4いずれかに記載の鋼殻エレメントの構築方法。 The method for constructing a steel shell element according to any one of claims 1 to 4, wherein the step of inserting the steel shell element while connecting the convex joint of the next steel shell element to the concave joint of the steel shell element that has already been penetrated. 前記鋼殻エレメントを貫入させる際に使用される掘削機は、正面掘削部の形状が前記鋼殻エレメントの角形中空断面と前記仮鋼管とを合わせた形状に整合し、かつ胴体部に前記継手部に対応する土砂部分を掘削するための補助カッターを備えるか、もしくは前記掘削機で前記継手部を包括する範囲の余掘りを行う請求項1~5いずれかに記載の鋼殻エレメントの構築方法。 The excavator used for penetrating the steel shell element has a shape of the front excavation part that matches the shape of the square hollow cross section of the steel shell element and the temporary steel pipe, and the joint part is attached to the body part. The steel shell element construction method according to any one of claims 1 to 5, wherein an auxiliary cutter is provided for excavating the earth and sand portion corresponding to the above, or the excavator performs over excavation in a range including the joint portion.
JP2021179188A 2021-11-02 2021-11-02 Construction method of steel shell element Pending JP2023068271A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2021179188A JP2023068271A (en) 2021-11-02 2021-11-02 Construction method of steel shell element

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2021179188A JP2023068271A (en) 2021-11-02 2021-11-02 Construction method of steel shell element

Publications (1)

Publication Number Publication Date
JP2023068271A true JP2023068271A (en) 2023-05-17

Family

ID=86327192

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021179188A Pending JP2023068271A (en) 2021-11-02 2021-11-02 Construction method of steel shell element

Country Status (1)

Country Link
JP (1) JP2023068271A (en)

Similar Documents

Publication Publication Date Title
KR100866162B1 (en) Chair-type self-supported earth retaining wall constructing method
KR101179778B1 (en) Method for constructing underground structure
KR101069705B1 (en) Method for installing waterproofing steel plate in construction of undergound tunnel
CN107060803B (en) Tunnel construction method by utilizing pipe curtain grouting
KR101676814B1 (en) CFT pile Construction Method and the Shoring Method using the same file
KR20180124795A (en) An Earth Retaining Wall with Underground Buttresses and A Method of Constructing the same
KR101840226B1 (en) The guide holes of the form for soil auger dredges
KR100992597B1 (en) The support material for a tunnel and tunnel support
KR102521610B1 (en) Multi casing perforation device
KR101078080B1 (en) Earth retaining wall and it's construction method using the precast pile and ground reinforcement
KR101069702B1 (en) Method for installing waterproofing steel plate and soil-drop preventing plate in construction of undergound tunnel
KR102239089B1 (en) Underaround continued wall structure using casing and pile continuous connection and method therefor
KR100898969B1 (en) Tunnel Boring Method Using Sheet Pile and Tunnel Structure therof
JP3829319B2 (en) Construction method of underground hollow structure and its underground hollow structure
KR101974826B1 (en) The Precast Pile Having Interlocking Secant and The Earth Retaining Wall Method Constructed by It's Continuous Pile
JP2023068271A (en) Construction method of steel shell element
KR100562686B1 (en) The underground structure and it's construction method is using sheet pile and cast in a place concrete
KR101283663B1 (en) Method for digging two arch type tunnel
HU222363B1 (en) Process for building of continuous, impermeable slot-wall, which enlarge permeability road
KR200296444Y1 (en) Underaround continued wall structure using a large diameter cast-in-place pile installed by Benoto method
KR102197032B1 (en) Structure of steel pipe for work area to facilitate dismantling
KR101047257B1 (en) Construction method of earth wall using composite sheet pile
KR101524302B1 (en) Construction method for underground structure without temporary structure
KR102610909B1 (en) Method and structure of steel pipe propulsion using anchor installation inside steel pipe to prevent sinking
KR101516746B1 (en) Construction method for girder and construction method for underground structure without temporary structure using the same