JP2021123961A - Construction method of pile head part reinforcement structure, and mold - Google Patents

Construction method of pile head part reinforcement structure, and mold Download PDF

Info

Publication number
JP2021123961A
JP2021123961A JP2020018790A JP2020018790A JP2021123961A JP 2021123961 A JP2021123961 A JP 2021123961A JP 2020018790 A JP2020018790 A JP 2020018790A JP 2020018790 A JP2020018790 A JP 2020018790A JP 2021123961 A JP2021123961 A JP 2021123961A
Authority
JP
Japan
Prior art keywords
pile head
formwork
foundation
pile
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2020018790A
Other languages
Japanese (ja)
Inventor
正道 安永
Masamichi Yasunaga
正道 安永
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2020018790A priority Critical patent/JP2021123961A/en
Publication of JP2021123961A publication Critical patent/JP2021123961A/en
Pending legal-status Critical Current

Links

Images

Abstract

To provide a rational construction method of a pile head part reinforcement structure of a foundation pile installed into the ground.SOLUTION: A method for connecting a foundation pile 2 installed into the ground and a foundation structure (for example, foundation slab 4) constructed above a pile head part of the foundation pile 2, and constructing a pile head part reinforcement structure 3 for reinforcing the pile head part of the foundation pile 2 includes: an excavation recess formation step (S2) of excavating ground G so as to expose the pile head part of the foundation pile 2, and thereby forming an excavation recess 20 in the ground G; a first mold installation step (S4) of installing a first cylindrical mold 10 on a bottom surface 20a of the excavation recess 20 so as to surround the periphery of the pile head part of the exposed foundation pile 2; and a concrete installation step (S8) of installing concrete 15 into the first mold 10. The first mold 10 is made of precast concrete. The pile head part reinforcement structure 3 includes the first mold 10, and the concrete 15 installed into the first mold 10.SELECTED DRAWING: Figure 3

Description

本発明は、地中に打設された基礎杭の杭頭部を補強する杭頭部補強構造の構築方法と、この杭頭部補強構造の構築に用いられる型枠とに関する。 The present invention relates to a method for constructing a pile head reinforcing structure for reinforcing the pile head of a foundation pile placed in the ground, and a formwork used for constructing the pile head reinforcing structure.

特許文献1は、フーチングの下部に挿入される杭頭を補強する杭頭補強構造を開示している。特許文献1における杭頭補強構造の第1態様は、周囲筋、スターラップ、及びフーチング一体筋を組み立て形成された杭頭補強ユニットを杭頭部分に設置してなるものである。特許文献1における杭頭補強構造の第2態様は、フーチング一体筋が上方に向かって突出したプレキャストコンクリート製杭頭補強ユニットを杭頭部分に設置してなるものである。 Patent Document 1 discloses a pile head reinforcing structure for reinforcing the pile head inserted in the lower part of the footing. The first aspect of the pile head reinforcement structure in Patent Document 1 is that a pile head reinforcement unit formed by assembling a peripheral bar, a stirrup, and a footing integral bar is installed on the pile head portion. The second aspect of the pile head reinforcement structure in Patent Document 1 is a precast concrete pile head reinforcement unit in which a footing integral bar protrudes upward is installed in the pile head portion.

特許第2891167号公報Japanese Patent No. 2891167

しかしながら、特許文献1における杭頭補強構造の第1態様では、鉄筋からなる杭頭補強ユニットの設置箇所に場所打ちでコンクリートが打設される。このため、杭頭補強ユニットの設置箇所にて、型枠の設置、コンクリートの打設、養生、型枠の撤去などを行う必要があり、工事に時間がかかる。
また、特許文献1における杭頭補強構造の第2態様では、プレキャストコンクリート製杭頭補強ユニットが大型化すると、その運搬や設置に手間がかかる。
However, in the first aspect of the pile head reinforcement structure in Patent Document 1, concrete is cast in place at the installation location of the pile head reinforcement unit made of reinforcing bars. For this reason, it is necessary to install the formwork, place concrete, cure, and remove the formwork at the installation location of the pile head reinforcement unit, which takes time for construction.
Further, in the second aspect of the pile head reinforcement structure in Patent Document 1, when the size of the precast concrete pile head reinforcement unit is increased, it takes time and effort to transport and install the precast concrete pile head reinforcement unit.

本発明は、このような実状に鑑み、地中に打設された基礎杭の杭頭部を補強する杭頭部補強構造の、より合理的な構築方法、及び、この構築に用いられ得る型枠を提供することを課題とする。 In view of such an actual situation, the present invention relates to a more rational construction method of a pile head reinforcement structure for reinforcing the pile head of a foundation pile placed underground, and a mold that can be used for this construction. The challenge is to provide a frame.

そのため本発明に係る杭頭部補強構造の構築方法は、地中に打設された基礎杭と、基礎杭の杭頭部の上方に構築される基礎構造体とを連結し、かつ、杭頭部を補強する杭頭部補強構造を構築する方法である。本発明に係る杭頭部補強構造の構築方法は、杭頭部を露出させるように地盤を掘削することで地盤に掘削凹部を形成する掘削凹部形成工程と、露出した杭頭部の周囲を囲むように筒状の第1型枠を掘削凹部の底面上に設置する第1型枠設置工程と、第1型枠内にコンクリートを打設するコンクリート打設工程と、を含む。第1型枠はプレキャストコンクリート製である。杭頭部補強構造は、第1型枠と、第1型枠内に打設されるコンクリートとを含んで構成される。 Therefore, in the method for constructing the pile head reinforcement structure according to the present invention, the foundation pile placed in the ground and the foundation structure constructed above the pile head of the foundation pile are connected and the pile head is constructed. This is a method of constructing a pile head reinforcement structure that reinforces the part. The method for constructing the pile head reinforcement structure according to the present invention includes an excavation recess forming step of forming an excavation recess in the ground by excavating the ground so as to expose the pile head, and surrounding the exposed pile head. The first formwork installation step of installing the tubular first formwork on the bottom surface of the excavation recess and the concrete placing step of placing concrete in the first formwork are included. The first formwork is made of precast concrete. The pile head reinforcement structure includes a first formwork and concrete placed in the first formwork.

本発明に係る型枠は、地中に打設された基礎杭の杭頭部の補強に用いられる型枠である。本発明に係る型枠は、上下方向に延びる筒状であり、かつ、プレキャストコンクリート製である本体部と、本体部に埋設されて本体部の周方向に延びる第1鉄筋と、一部が本体部に埋設されて残部が本体部の内部空間に露出する第2鉄筋と、を備える。ここで、内部空間内に杭頭部が挿入され、かつ、コンクリートが打設される。 The formwork according to the present invention is a formwork used for reinforcing the pile head of a foundation pile placed underground. The formwork according to the present invention has a main body portion that is tubular and is made of precast concrete that extends in the vertical direction, a first reinforcing bar that is embedded in the main body portion and extends in the circumferential direction of the main body portion, and a part of the main body. It is provided with a second reinforcing bar that is embedded in the portion and the remaining portion is exposed in the internal space of the main body portion. Here, the pile head is inserted into the internal space and concrete is poured.

本発明によれば、杭頭部の補強に用いられる型枠(第1型枠)は、筒状のプレキャストコンクリート製である。ゆえに、当該型枠内にコンクリートを打設した後に当該型枠を撤去することなく残置して杭頭部補強構造の外殻として活用することができる。また、当該型枠は筒状であるので、杭頭部補強構造を中実タイプのプレキャスト部材で構成するよりも明らかに軽量である。ゆえに、運搬や設置の手間が軽減され得る。従って、杭頭部補強構造の構築の合理化を図ることができる。 According to the present invention, the formwork (first formwork) used for reinforcing the pile head is made of tubular precast concrete. Therefore, after the concrete is cast in the formwork, the formwork can be left without being removed and used as the outer shell of the pile head reinforcing structure. Further, since the formwork has a tubular shape, it is clearly lighter than the pile head reinforcing structure composed of a solid type precast member. Therefore, the labor of transportation and installation can be reduced. Therefore, it is possible to rationalize the construction of the pile head reinforcement structure.

本発明の第1実施形態における基礎の概略構成を示す図The figure which shows the schematic structure of the foundation in 1st Embodiment of this invention. 前記第1実施形態における第1型枠の概略構成を示す図The figure which shows the schematic structure of the 1st formwork in said 1st Embodiment 前記第1実施形態における基礎の構築方法を示すフローチャートA flowchart showing a method of constructing a foundation in the first embodiment. 前記第1実施形態における基礎の構築方法を示す図The figure which shows the method of constructing the foundation in the said 1st Embodiment 前記第1実施形態における基礎の構築方法を示す図The figure which shows the method of constructing the foundation in the said 1st Embodiment 前記第1実施形態における基礎の構築方法を示す図The figure which shows the method of constructing the foundation in the said 1st Embodiment 前記第1実施形態における基礎の構築方法を示す図The figure which shows the method of constructing the foundation in the said 1st Embodiment 前記第1実施形態における基礎の構築方法を示す図The figure which shows the method of constructing the foundation in the said 1st Embodiment 本発明の第2実施形態における基礎の概略構成を示す図The figure which shows the schematic structure of the foundation in 2nd Embodiment of this invention.

以下、本発明の実施の形態について、図面を参照して説明する。 Hereinafter, embodiments of the present invention will be described with reference to the drawings.

図1は、本発明の第1実施形態における基礎1の概略構成を示す図である。詳しくは、図1(ア)は基礎1の縦断面図であり、図1(イ)は基礎1の上面図である。尚、図1(ア)及び(イ)では、図示簡略化のため、後述する第1〜第3鉄筋11〜13、杭頭補強筋17、及び、鉄筋22の図示を省略している。 FIG. 1 is a diagram showing a schematic configuration of a foundation 1 according to the first embodiment of the present invention. Specifically, FIG. 1A is a vertical cross-sectional view of the foundation 1, and FIG. 1B is a top view of the foundation 1. In FIGS. 1 (a) and 1 (b), the first to third reinforcing bars 11 to 13, the pile head reinforcing bars 17, and the reinforcing bars 22, which will be described later, are omitted for simplification of the illustration.

基礎1は、例えば、工場に設置される設備基礎である。本実施形態における基礎1は、複数の基礎杭2と、各基礎杭2の杭頭部(上端部)に各別に構築される複数の杭頭部補強構造3と、これら杭頭部補強構造3上に構築される基礎スラブ4と、を含んで構成される。ここで、基礎スラブ4は、本発明の「基礎構造体」の一例であり、基礎杭2の杭頭部の上方に構築されるものである。 The foundation 1 is, for example, an equipment foundation installed in a factory. The foundation 1 in the present embodiment includes a plurality of foundation piles 2, a plurality of pile head reinforcement structures 3 separately constructed on the pile heads (upper ends) of each foundation pile 2, and these pile head reinforcement structures 3. It is configured to include the foundation slab 4 constructed above. Here, the foundation slab 4 is an example of the "foundation structure" of the present invention, and is constructed above the pile head of the foundation pile 2.

本実施形態では、基礎1を構成する基礎杭2と杭頭部補強構造3とが地中(地盤G中)に位置し、また、基礎スラブ4の少なくとも下部が地中に位置している。すなわち、本実施形態では、地面GSより下方に、基礎スラブ4の少なくとも下部と、杭頭部補強構造3と、基礎杭2とが位置している。 In the present embodiment, the foundation pile 2 and the pile head reinforcing structure 3 constituting the foundation 1 are located in the ground (in the ground G), and at least the lower part of the foundation slab 4 is located in the ground. That is, in the present embodiment, at least the lower part of the foundation slab 4, the pile head reinforcing structure 3, and the foundation pile 2 are located below the ground GS.

基礎杭2は、例えばコンクリート製又は鋼製である。本実施形態では、基礎杭2がPHC杭であるとして以下説明するが、基礎杭2はPHC杭に限らず、PHC杭以外の周知の杭(例えば鋼管杭)であってもよい。 The foundation pile 2 is made of, for example, concrete or steel. In the present embodiment, the foundation pile 2 will be described below as a PHC pile, but the foundation pile 2 is not limited to the PHC pile and may be a well-known pile (for example, a steel pipe pile) other than the PHC pile.

本実施形態では、基礎杭2は、地中に打設されて上下方向に延びている。図1(イ)に示す配置では、16個の基礎杭2が、平面視でマトリクス状(図では4個×4個)に互いに平行に配置されている。尚、基礎1を構成する基礎杭2の個数及び配置は、図1に図示されているものに限らない。 In the present embodiment, the foundation pile 2 is driven into the ground and extends in the vertical direction. In the arrangement shown in FIG. 1 (a), 16 foundation piles 2 are arranged in a matrix (4 × 4 in the figure) in parallel with each other in a plan view. The number and arrangement of the foundation piles 2 constituting the foundation 1 are not limited to those shown in FIG.

杭頭部補強構造3は、基礎杭2と基礎スラブ4とを連結するものであり、また、基礎杭2の杭頭部を補強するものである。杭頭部補強構造3は、第1型枠10と、第1型枠10内に打設されるコンクリート15と、複数の杭頭補強筋17(図8参照)とを含んで構成される。第1型枠10の詳細については、図2を用いて後述する。 The pile head reinforcement structure 3 connects the foundation pile 2 and the foundation slab 4, and also reinforces the pile head of the foundation pile 2. The pile head reinforcing structure 3 includes a first formwork 10, concrete 15 cast in the first formwork 10, and a plurality of pile head reinforcing bars 17 (see FIG. 8). Details of the first formwork 10 will be described later with reference to FIG.

本実施形態では、基礎スラブ4は、水平に延びる厚い板状であり、平面視で矩形状である。しかしながら、基礎スラブ4の形状はこれに限らない。基礎スラブ4は、後述する鉄筋22(図8参照)を備えるコンクリート製(鉄筋コンクリート製(RC製))である。
図1(イ)に示すように、基礎杭2及び杭頭部補強構造3については、平面視で、基礎スラブ4に内包されるように配置されている。
In the present embodiment, the foundation slab 4 has a thick plate shape extending horizontally and a rectangular shape in a plan view. However, the shape of the foundation slab 4 is not limited to this. The foundation slab 4 is made of concrete (made of reinforced concrete (made of RC)) including the reinforcing bar 22 (see FIG. 8) described later.
As shown in FIG. 1A, the foundation pile 2 and the pile head reinforcing structure 3 are arranged so as to be included in the foundation slab 4 in a plan view.

図2は第1型枠10の概略構成を示す図である。詳しくは、図2(ア)は、第1型枠10の縦断面図であり、図2(イ)のB−B断面に対応する。図2(イ)は、第1型枠10の横断面図であり、図2(ア)のA−A断面に対応する。 FIG. 2 is a diagram showing a schematic configuration of the first mold 10. Specifically, FIG. 2A is a vertical cross-sectional view of the first formwork 10, and corresponds to the BB cross section of FIG. 2B. FIG. 2A is a cross-sectional view of the first formwork 10, and corresponds to the AA cross section of FIG. 2A.

第1型枠10は、地中に打設された基礎杭2の杭頭部の補強に用いられる型枠である。第1型枠10は、筒状の本体部10aと、複数の第1鉄筋(外周部鉄筋)11と、複数の第2鉄筋(内部鉄筋)12と、複数の第3鉄筋(接続部鉄筋)13とを備える。つまり、第1型枠10は筒状であり、第1鉄筋11と第2鉄筋12と第3鉄筋13とを有する。 The first formwork 10 is a formwork used for reinforcing the pile head of the foundation pile 2 placed in the ground. The first formwork 10 includes a tubular main body portion 10a, a plurality of first reinforcing bars (outer peripheral reinforcing bars) 11, a plurality of second reinforcing bars (internal reinforcing bars) 12, and a plurality of third reinforcing bars (connecting portion reinforcing bars). 13 and. That is, the first formwork 10 has a tubular shape and has a first reinforcing bar 11, a second reinforcing bar 12, and a third reinforcing bar 13.

第1型枠10(詳しくは本体部10a)はプレキャストコンクリート製である。本実施形態では、第1型枠10(詳しくは本体部10a)は、上下方向に延びる筒状であり、矩形断面を有している。しかしながら、第1型枠10(詳しくは本体部10a)の断面形状は矩形に限らず、例えば円形であってもよい。第1型枠10(詳しくは本体部10a)の上面及び下面はそれぞれ開口している。 The first formwork 10 (specifically, the main body 10a) is made of precast concrete. In the present embodiment, the first mold 10 (specifically, the main body portion 10a) has a cylindrical shape extending in the vertical direction and has a rectangular cross section. However, the cross-sectional shape of the first mold 10 (specifically, the main body portion 10a) is not limited to a rectangle, and may be, for example, a circle. The upper surface and the lower surface of the first mold 10 (specifically, the main body 10a) are open.

第1型枠10の内部空間(本体部10aの内周面によって囲まれる空間)10b内には、基礎杭2の杭頭部が挿入され得る。また、この内部空間10bには、コンクリート15が打設され得る。本体部10aの壁厚は、例えば15cm〜20cmの範囲内である。 The pile head of the foundation pile 2 can be inserted into the internal space (space surrounded by the inner peripheral surface of the main body 10a) 10b of the first formwork 10. Further, concrete 15 can be cast in the internal space 10b. The wall thickness of the main body 10a is, for example, in the range of 15 cm to 20 cm.

第1鉄筋11は、本体部10aに埋設されており、本体部10aの周方向に延びている。第1鉄筋11は、第1型枠10(詳しくは本体部10a)の断面形状に従う環状である。ゆえに、本実施形態では、第1鉄筋11は、矩形の環状である。第1型枠10を構成する複数の第1鉄筋11は、上下方向に互いに間隔を空けて並んでいる。図2(ア)は、3つの第1鉄筋11が上下方向に互いに間隔を空けて並んでいる例を示しているが、第1型枠10を構成する第1鉄筋11の個数は3つに限らず任意の個数であり得る。 The first reinforcing bar 11 is embedded in the main body portion 10a and extends in the circumferential direction of the main body portion 10a. The first reinforcing bar 11 is an annular shape that follows the cross-sectional shape of the first mold 10 (specifically, the main body portion 10a). Therefore, in the present embodiment, the first reinforcing bar 11 is a rectangular ring. The plurality of first reinforcing bars 11 constituting the first formwork 10 are arranged at intervals in the vertical direction. FIG. 2A shows an example in which the three first reinforcing bars 11 are arranged in the vertical direction at intervals from each other, but the number of the first reinforcing bars 11 constituting the first formwork 10 is three. The number is not limited and may be any number.

第1型枠10を構成する複数の第2鉄筋12は、平面視で井形に配置されている。第2鉄筋12は、水平方向に直線状に延びており、両端部が本体部10aに埋設されて、それ以外の部分が本体部10aの内部空間10bに露出している。すなわち、第2鉄筋12は、その一部(例えば両端部)が本体部10aに埋設されて残部(例えば両端部以外の部分)が本体部10aの内部空間10bに露出している。この第2鉄筋12における内部空間10bに露出する部分については、この内部空間10b内に基礎杭2の杭頭部が挿入されるときに基礎杭2の杭頭部及び/又は杭頭補強筋17をかわせる位置に配置されている。 The plurality of second reinforcing bars 12 constituting the first formwork 10 are arranged in a well shape in a plan view. The second reinforcing bar 12 extends linearly in the horizontal direction, both ends thereof are embedded in the main body portion 10a, and the other portions are exposed in the internal space 10b of the main body portion 10a. That is, a part (for example, both ends) of the second reinforcing bar 12 is embedded in the main body portion 10a, and the remaining portion (for example, a portion other than both ends) is exposed in the internal space 10b of the main body portion 10a. Regarding the portion of the second reinforcing bar 12 exposed to the internal space 10b, when the pile head of the foundation pile 2 is inserted into the internal space 10b, the pile head of the foundation pile 2 and / or the pile head reinforcing bar 17 It is placed in a position to dodge.

第3鉄筋13は、上下方向に直線状に延びている。第3鉄筋13は、本体部10aの上端部から上方に露出して延びている。第3鉄筋13は、杭頭部補強構造3と基礎スラブ4とを接続するための鉄筋である。 The third reinforcing bar 13 extends linearly in the vertical direction. The third reinforcing bar 13 extends upward from the upper end portion of the main body portion 10a. The third reinforcing bar 13 is a reinforcing bar for connecting the pile head reinforcing structure 3 and the foundation slab 4.

従って、第1型枠10は、鉄筋コンクリート製(RC製)のプレキャスト型枠である。
ここで、第1鉄筋11と第2鉄筋12と第3鉄筋13とは、杭頭部補強構造3を構成する鉄筋の略全てであり、第1型枠10の製造時に第1型枠10に組み込まれるものである。
また、第3鉄筋13(杭頭部補強構造3と基礎スラブ4とを接続するための鉄筋)は、第1型枠10の製造時に第1型枠10に設置され得るものである。
Therefore, the first formwork 10 is a precast formwork made of reinforced concrete (made of RC).
Here, the first reinforcing bar 11, the second reinforcing bar 12, and the third reinforcing bar 13 are substantially all of the reinforcing bars constituting the pile head reinforcing structure 3, and the first formwork 10 is used when the first formwork 10 is manufactured. It is to be incorporated.
Further, the third reinforcing bar 13 (reinforcing bar for connecting the pile head reinforcing structure 3 and the foundation slab 4) can be installed in the first formwork 10 at the time of manufacturing the first formwork 10.

第1型枠10は、杭頭部補強構造3の構築時の埋設型枠(換言すれば残置型枠)として機能する。ゆえに、第1型枠10(詳しくは本体部10a)の外周部寸法は、杭頭部補強構造3の外周部寸法に略一致している。従って、第1型枠10は、杭頭部補強構造3の外殻をなすものである。 The first formwork 10 functions as a buried formwork (in other words, a remaining formwork) at the time of construction of the pile head reinforcing structure 3. Therefore, the outer peripheral dimension of the first formwork 10 (specifically, the main body portion 10a) substantially matches the outer peripheral dimension of the pile head reinforcing structure 3. Therefore, the first formwork 10 forms the outer shell of the pile head reinforcing structure 3.

第1型枠10の製造時には、外面にメタルフォームなどの一般型枠を用い、内面にパンチングフォーム(登録商標)などの埋設型枠(換言すれば残置型枠)を用いることが好ましい。これにより、第1型枠10の製造時に内型枠の撤去を不要とすることができるので、第1型枠10の製造を容易にすることができる。
尚、第1型枠10の製造時には、外面と内面との双方にメタルフォームなどの一般型枠を用いてもよい。又は、第1型枠10の製造時には、外面と内面との双方にパンチングフォーム(登録商標)などの埋設型枠(換言すれば残置型枠)を用いてもよい。
At the time of manufacturing the first formwork 10, it is preferable to use a general formwork such as metal foam on the outer surface and an embedded formwork (in other words, a residual formwork) such as punching foam (registered trademark) on the inner surface. As a result, it is possible to eliminate the need to remove the inner formwork when manufacturing the first formwork 10, so that the manufacture of the first formwork 10 can be facilitated.
When manufacturing the first mold 10, a general mold such as metal foam may be used on both the outer surface and the inner surface. Alternatively, when manufacturing the first formwork 10, an embedded formwork (in other words, a remaining formwork) such as punching foam (registered trademark) may be used on both the outer surface and the inner surface.

第1型枠10については、シールドトンネルのセグメントのような寸法精度を要しないので、製造時に金型は必要なく、一般型枠などで簡易かつ低コストで製造することができる。また、第1型枠10の製造場所については、施工現場から離れた工場などでの製造にこだわることなく、例えば施工現場にて、後述する図3のステップS4(第1型枠設置工程)に先立って製造されてもよい。 Since the first mold 10 does not require dimensional accuracy as in the shield tunnel segment, a mold is not required at the time of manufacturing, and a general mold or the like can be manufactured easily and at low cost. Further, regarding the manufacturing location of the first formwork 10, without being particular about manufacturing in a factory away from the construction site, for example, at the construction site, in step S4 (first formwork installation process) of FIG. 3 described later. It may be manufactured in advance.

次に、本実施形態における基礎1の構築方法について、前述の図1及び図2に加えて、図3〜図8を用いて説明する。
図3は、本実施形態における基礎1の構築方法を示すフローチャートである。図4〜図8は、本実施形態における基礎1の構築方法を示す図である。
ここで、図3〜図8に示す基礎1の構築方法は、杭頭部補強構造3の構築方法を含むものである。
Next, the method of constructing the foundation 1 in the present embodiment will be described with reference to FIGS. 3 to 8 in addition to FIGS. 1 and 2 described above.
FIG. 3 is a flowchart showing a method of constructing the foundation 1 in the present embodiment. 4 to 8 are diagrams showing a method of constructing the foundation 1 in the present embodiment.
Here, the method of constructing the foundation 1 shown in FIGS. 3 to 8 includes a method of constructing the pile head reinforcing structure 3.

基礎1の構築では、まず、ステップS1(基礎杭打設工程)にて、基礎杭2の杭頭部高さが設計高さになるように、基礎杭2の杭頭部にヤットコ(鋼製の仮杭)6を取り付けて、基礎杭2を地中(地盤G中)に打設する(図4(ア)参照)。この基礎杭2の地中への打設が完了した後に、ヤットコ6は撤去される。 In the construction of the foundation 1, first, in step S1 (foundation pile driving process), the pile head of the foundation pile 2 is made of yatko (steel) so that the height of the pile head of the foundation pile 2 becomes the design height. (Temporary pile) 6 is attached, and the foundation pile 2 is driven into the ground (in the ground G) (see FIG. 4 (a)). After the foundation pile 2 has been driven into the ground, the yatko 6 is removed.

次に、ステップS2(掘削凹部形成工程)にて、基礎杭2の杭頭部を露出させるように地盤Gを地面GS側から下方に掘削することで地盤Gに掘削凹部20を形成する(図4(イ)参照)。 Next, in step S2 (excavation recess forming step), the excavation recess 20 is formed in the ground G by excavating the ground G downward from the ground GS side so as to expose the pile head of the foundation pile 2 (FIG. 4 (a)).

次に、掘削凹部20の底面20aのうち、基礎杭2の杭頭部近傍の、杭頭部補強構造3が構築される部分に、砕石層(図示せず)を設置し、更にその上に均しコンクリート(図示せず)の施工を行う(第1砕石層設置・均しコンクリート施工工程)。ここで、この工程で施工される均しコンクリートの上面の高さが杭頭部補強構造3の下面の設計高さと略一致するように、前述のステップS2にて掘削凹部20の底面20aの高さが適宜調整されている。 Next, a crushed stone layer (not shown) is installed on the bottom surface 20a of the excavation recess 20 near the pile head of the foundation pile 2 where the pile head reinforcing structure 3 is constructed, and further on the crushed stone layer (not shown). Perform leveling concrete (not shown) (first crushed stone layer installation / leveling concrete construction process). Here, the height of the bottom surface 20a of the excavation recess 20 in step S2 described above so that the height of the upper surface of the leveling concrete constructed in this step substantially matches the design height of the lower surface of the pile head reinforcing structure 3. Is adjusted accordingly.

次に、ステップS3(杭頭補強筋設置工程)にて、基礎杭2の杭頭部に複数の杭頭補強筋17を設置する(図5(ウ)参照)。杭頭補強筋17は、基礎杭2の杭頭部から上方に延びる鉄筋である。本実施形態のように基礎杭2がPHC杭である場合には、杭頭補強筋17として、例えばNCPアンカー(登録商標)を用いることができる。しかしながら、杭頭補強筋17は、NCPアンカー(登録商標)に限らない。 Next, in step S3 (pile head reinforcing bar installation step), a plurality of pile head reinforcing bars 17 are installed on the pile head of the foundation pile 2 (see FIG. 5 (c)). The pile head reinforcing bar 17 is a reinforcing bar extending upward from the pile head of the foundation pile 2. When the foundation pile 2 is a PHC pile as in the present embodiment, for example, an NCP anchor (registered trademark) can be used as the pile head reinforcing bar 17. However, the pile head reinforcing bar 17 is not limited to the NCP anchor (registered trademark).

次に、ステップS4(第1型枠設置工程)にて、図示しないライナープレートなどの高さ調整部材を用いて第1型枠10の設置高さの調整をしながら、第1型枠10を、前述の均しコンクリート上(掘削凹部20の底面20a上)に設置する(図5(エ)参照)。この設置時には、露出した基礎杭2の杭頭部の周囲を囲むように(換言すれば、平面視で、露出した基礎杭2の杭頭部を内包するように)第1型枠10が前述の均しコンクリート上(掘削凹部20の底面20a上)に設置される。この設置後において、基礎杭2の杭頭部の上面は、第1型枠10の下面よりも高位に位置し、かつ、第1型枠10の上面より低位に位置する。このようにして、第1型枠10の内部空間10b内に基礎杭2の杭頭部が挿入される。 Next, in step S4 (first formwork installation step), the first formwork 10 is set while adjusting the installation height of the first formwork 10 using a height adjusting member such as a liner plate (not shown). , Installed on the above-mentioned leveling concrete (on the bottom surface 20a of the excavation recess 20) (see FIG. 5 (d)). At the time of this installation, the first formwork 10 is described above so as to surround the pile head of the exposed foundation pile 2 (in other words, to include the pile head of the exposed foundation pile 2 in a plan view). It is installed on the leveled concrete (on the bottom surface 20a of the excavation recess 20). After this installation, the upper surface of the pile head of the foundation pile 2 is located higher than the lower surface of the first formwork 10 and lower than the upper surface of the first formwork 10. In this way, the pile head of the foundation pile 2 is inserted into the internal space 10b of the first formwork 10.

次に、ステップS5(第1埋め戻し工程)にて、掘削凹部20内における第1型枠10の周囲を埋め戻す(図6(オ)参照)。この埋め戻しには、前述のステップS2の掘削凹部20の形成時に発生した掘削土砂が用いられることが好ましいが、その他の土砂などが用いられてもよい。 Next, in step S5 (first backfilling step), the periphery of the first formwork 10 in the excavation recess 20 is backfilled (see FIG. 6 (e)). For this backfilling, it is preferable to use the excavated earth and sand generated when the excavation recess 20 in step S2 is formed, but other earth and sand may be used.

次に、前述の埋め戻しにより上昇した掘削凹部20の底面20a’のうち、基礎スラブ4が構築される部分に、砕石層(図示せず)を設置し、更にその上に均しコンクリート(図示せず)の施工を行う(第2砕石層設置・均しコンクリート施工工程)。ここで、この工程で施工される均しコンクリートの上面の高さが、前述のステップS4にて設置された第1型枠10の天端の高さと略一致するように、前述のステップS5での埋め戻し高さが適宜調整されている。尚、前述のステップS4にて設置された第1型枠10の天端の高さは、基礎スラブ4の下面の高さと略一致し得る。 Next, a crushed stone layer (not shown) is installed in the portion of the bottom surface 20a'of the excavation recess 20 raised by the above-mentioned backfilling where the foundation slab 4 is constructed, and the leveled concrete (not shown) is further placed on the crushed stone layer (not shown). (Not shown) (2nd crushed stone layer installation / leveling concrete construction process). Here, in step S5 described above, the height of the upper surface of the leveling concrete constructed in this step substantially matches the height of the top edge of the first formwork 10 installed in step S4 described above. The backfill height of is adjusted accordingly. The height of the top of the first formwork 10 installed in step S4 described above may be substantially the same as the height of the lower surface of the foundation slab 4.

次に、ステップS6(鉄筋組み立て工程)にて、基礎スラブ4を構成する鉄筋22を組み立てる(図6(カ)参照)。この工程では、前述の第2砕石層設置・均しコンクリート施工工程にて施工された均しコンクリート上(前述のステップS5にて埋め戻された領域の上面上)にて鉄筋22が組み立てられる。 Next, in step S6 (reinforcing bar assembling step), the reinforcing bars 22 constituting the foundation slab 4 are assembled (see FIG. 6 (f)). In this step, the reinforcing bar 22 is assembled on the leveled concrete constructed in the second crushed stone layer installation / leveling concrete construction step described above (on the upper surface of the region backfilled in step S5 described above).

次に、ステップS7(第2型枠設置工程)にて、基礎スラブ4を構築するための第2型枠25を設置する(図7(キ)参照)。この工程では、前述の第2砕石層設置・均しコンクリート施工工程にて施工された均しコンクリート上(前述のステップS5にて埋め戻された領域の上面上)にて第2型枠25が設置される。第2型枠25は、ステップS6にて組み立てられた鉄筋22の周囲を囲むように設置される。ここで、第2型枠25は、例えば、メタルフォームなどの一般型枠である。また、第2型枠25は、例えば、基礎スラブ4の外周部寸法をカバーする内周部寸法を有する筒状であり、複数の型枠部材を組み立てることで形成され得る。 Next, in step S7 (second formwork installation step), the second formwork 25 for constructing the foundation slab 4 is installed (see FIG. 7 (g)). In this step, the second formwork 25 is placed on the leveled concrete constructed in the above-mentioned second crushed stone layer installation / leveling concrete construction step (on the upper surface of the area backfilled in the above-mentioned step S5). Will be installed. The second formwork 25 is installed so as to surround the reinforcing bar 22 assembled in step S6. Here, the second formwork 25 is a general formwork such as a metal foam. Further, the second formwork 25 has, for example, a tubular shape having an inner peripheral dimension that covers the outer peripheral dimension of the foundation slab 4, and can be formed by assembling a plurality of formwork members.

尚、本実施形態では、ステップS6(鉄筋組み立て工程)の後にステップS7(第2型枠設置工程)を実施しているが、これとは逆に、ステップS7(第2型枠設置工程)の後にステップS6(鉄筋組み立て工程)を実施してもよい。又は、ステップS6(鉄筋組み立て工程)とステップS7(第2型枠設置工程)とを並行して実施してもよい。 In the present embodiment, step S7 (second formwork installation step) is carried out after step S6 (reinforcing bar assembly step), but conversely, step S7 (second formwork installation step) Later, step S6 (reinforcing bar assembly step) may be carried out. Alternatively, step S6 (reinforcing bar assembly step) and step S7 (second formwork installation step) may be carried out in parallel.

次に、ステップS8(コンクリート打設工程)にて、第1型枠10内へのコンクリート15の打設と、第2型枠25内へのコンクリート15の打設と一括して実施する(図7(ク)参照)。すなわち、杭頭部補強構造3を構成するコンクリート15の打設と、基礎スラブ4を構成するコンクリート15の打設とを同時に行う。 Next, in step S8 (concrete placing step), the placing of the concrete 15 in the first formwork 10 and the placing of the concrete 15 in the second formwork 25 are carried out collectively (FIG. 6). 7 (K)). That is, the concrete 15 forming the pile head reinforcing structure 3 and the concrete 15 forming the foundation slab 4 are placed at the same time.

打設されたコンクリート15が硬化した後、ステップS9(第2型枠撤去工程)にて、第2型枠25の撤去を行う(図8(ケ)参照)。 After the cast concrete 15 is hardened, the second formwork 25 is removed in step S9 (second formwork removal step) (see FIG. 8 (K)).

次に、ステップS10(第2埋め戻し工程)にて、掘削凹部20を所定高さ(例えば地面GSの高さ)まで埋め戻す(図8(コ)参照)。この埋め戻しには、前述のステップS2の掘削凹部20の形成時に発生した掘削土砂が用いられることが好ましいが、その他の土砂などが用いられてもよい。
この工程では、掘削凹部20における、基礎スラブ4の少なくとも一部の周囲が埋め戻され得る。
以上のようにして、杭頭部補強構造3を含む基礎1の構築が行われ得る。
Next, in step S10 (second backfilling step), the excavation recess 20 is backfilled to a predetermined height (for example, the height of the ground GS) (see FIG. 8 (ko)). For this backfilling, it is preferable to use the excavated earth and sand generated when the excavation recess 20 in step S2 is formed, but other earth and sand may be used.
In this step, at least a part of the circumference of the foundation slab 4 in the excavation recess 20 can be backfilled.
As described above, the foundation 1 including the pile head reinforcing structure 3 can be constructed.

本実施形態によれば、杭頭部補強構造3の構築方法は、地中に打設された基礎杭2と、基礎杭2の杭頭部の上方に構築される基礎構造体(例えば基礎スラブ4)とを連結し、かつ、基礎杭2の杭頭部を補強する杭頭部補強構造3を構築する方法である。杭頭部補強構造3の構築方法は、基礎杭2の杭頭部を露出させるように地盤Gを掘削することで地盤Gに掘削凹部20を形成する掘削凹部形成工程(ステップS2)と、露出した基礎杭2の杭頭部の周囲を囲むように筒状の第1型枠10を掘削凹部20の底面20a上に設置する第1型枠設置工程(ステップS4)と、第1型枠10内にコンクリート15を打設するコンクリート打設工程(ステップS8)と、を含む。第1型枠10はプレキャストコンクリート製である。杭頭部補強構造3は、第1型枠10と、第1型枠10内に打設されるコンクリート15とを含んで構成される。ゆえに、第1型枠10内にコンクリート15を打設した後に第1型枠10を撤去することなく残置して杭頭部補強構造3の外殻として活用することができる。また、第1型枠10は筒状であるので、杭頭部補強構造3を中実タイプのプレキャスト部材で構成するよりも明らかに軽量である。ゆえに、運搬や設置の手間が軽減され得る。従って、杭頭部補強構造3の構築の合理化を図ることができる。 According to the present embodiment, the method of constructing the pile head reinforcing structure 3 is a foundation pile 2 placed in the ground and a foundation structure (for example, a foundation slab) constructed above the pile head of the foundation pile 2. This is a method of constructing a pile head reinforcing structure 3 that connects with 4) and reinforces the pile head of the foundation pile 2. The method of constructing the pile head reinforcing structure 3 includes an excavation recess forming step (step S2) of forming an excavation recess 20 in the ground G by excavating the ground G so as to expose the pile head of the foundation pile 2 and an exposure. The first formwork installation step (step S4) in which the tubular first formwork 10 is installed on the bottom surface 20a of the excavation recess 20 so as to surround the pile head of the foundation pile 2 and the first formwork 10 It includes a concrete placing step (step S8) in which the concrete 15 is placed therein. The first formwork 10 is made of precast concrete. The pile head reinforcing structure 3 includes a first formwork 10 and concrete 15 cast in the first formwork 10. Therefore, after the concrete 15 is placed in the first formwork 10, the first formwork 10 can be left without being removed and used as the outer shell of the pile head reinforcing structure 3. Further, since the first formwork 10 has a tubular shape, it is clearly lighter than the pile head reinforcing structure 3 made of a solid type precast member. Therefore, the labor of transportation and installation can be reduced. Therefore, it is possible to rationalize the construction of the pile head reinforcing structure 3.

また本実施形態によれば、杭頭部補強構造3の構築方法は、第1型枠設置工程(ステップS4)の後であって、かつ、コンクリート打設工程(ステップS8)に先立って、掘削凹部20内における第1型枠10の周囲を埋め戻す第1埋め戻し工程(ステップS5)を更に含む。ゆえに、第1型枠設置工程(ステップS4)の完了後に直ちに第1埋め戻し工程(ステップS5)を実施することができるので、その後引き続いて基礎スラブ4などの基礎構造体の工事(ステップS6〜S10)にかかることができ、全体工期を大幅に短縮できる。また、第1埋め戻し工程(ステップS5)での埋め戻しには、掘削凹部形成工程(ステップS2)で発生した掘削土砂を用いることができるので、当該掘削土砂を施工現場の近くに置いて直ぐに当該埋め戻しに利用することができる。従って、当該掘削土砂を遠方に運搬・仮置きしなくてよい。更に、第1埋め戻し工程(ステップS5)での埋め戻しにより、コンクリート打設工程(ステップS8)における第1型枠10の下端からのコンクリート漏れの発生を抑制することができる。 Further, according to the present embodiment, the method of constructing the pile head reinforcing structure 3 is excavation after the first formwork installation step (step S4) and prior to the concrete placing step (step S8). The first backfilling step (step S5) of backfilling the periphery of the first mold 10 in the recess 20 is further included. Therefore, since the first backfilling step (step S5) can be carried out immediately after the completion of the first formwork installation step (step S4), the construction of the foundation structure such as the foundation slab 4 (steps S6 to S6) is subsequently performed. It is possible to take S10), and the entire construction period can be significantly shortened. Further, since the excavated earth and sand generated in the excavation recess forming step (step S2) can be used for the backfilling in the first backfilling step (step S5), the excavated earth and sand is immediately placed near the construction site. It can be used for the backfilling. Therefore, it is not necessary to transport and temporarily store the excavated soil in a distant place. Further, by backfilling in the first backfilling step (step S5), it is possible to suppress the occurrence of concrete leakage from the lower end of the first formwork 10 in the concrete placing step (step S8).

また本実施形態によれば、杭頭部補強構造3の構築方法は、第1埋め戻し工程(ステップS5)の後であって、かつ、コンクリート打設工程(ステップS8)に先立って、第1埋め戻し工程(ステップS5)で埋め戻された領域の上面上に、基礎構造体(例えば基礎スラブ4)を構築するための第2型枠25を設置する第2型枠設置工程(ステップS7)を更に含む。コンクリート打設工程(ステップS8)では、第1型枠10内へのコンクリート15の打設と、第2型枠25内へのコンクリート15の打設と一括して実施する。これにより、杭頭部補強構造3を構成するコンクリート15の打設と、基礎構造体(例えば基礎スラブ4)を構成するコンクリート15の打設とを同時に行うことができるので、全体工期を更なる短縮を図ることができる。 Further, according to the present embodiment, the method of constructing the pile head reinforcing structure 3 is the first method after the first backfilling step (step S5) and prior to the concrete placing step (step S8). A second formwork installation step (step S7) in which a second formwork 25 for constructing a foundation structure (for example, a foundation slab 4) is installed on the upper surface of the area backfilled in the backfilling step (step S5). Is further included. In the concrete placing step (step S8), the placing of the concrete 15 in the first formwork 10 and the placing of the concrete 15 in the second formwork 25 are carried out collectively. As a result, the concrete 15 forming the pile head reinforcing structure 3 and the concrete 15 forming the foundation structure (for example, the foundation slab 4) can be placed at the same time, so that the entire construction period can be further extended. It can be shortened.

また本実施形態によれば、杭頭部補強構造3の構築方法は、第1埋め戻し工程(ステップS5)の後であって、かつ、コンクリート打設工程(ステップS8)に先立って、第1埋め戻し工程(ステップS5)で埋め戻された領域の上面上で、基礎構造体(例えば基礎スラブ4)を構成する鉄筋22を組み立てる鉄筋組み立て工程(ステップS6)を更に含む。ゆえに、第1埋め戻し工程(ステップS5)の完了後に直ちに鉄筋組み立て工程(ステップS6)を実施することができるので、全体工期を更なる短縮を図ることができる。 Further, according to the present embodiment, the method of constructing the pile head reinforcing structure 3 is the first method after the first backfilling step (step S5) and prior to the concrete placing step (step S8). A reinforcing bar assembling step (step S6) for assembling the reinforcing bars 22 constituting the foundation structure (for example, the foundation slab 4) is further included on the upper surface of the region backfilled in the backfilling step (step S5). Therefore, since the reinforcing bar assembling step (step S6) can be carried out immediately after the completion of the first backfilling step (step S5), the entire construction period can be further shortened.

また本実施形態によれば、第1型枠10の製造時に、杭頭部補強構造3を構成する鉄筋の略全て(第1鉄筋11、第2鉄筋12、及び第3鉄筋13)が第1型枠10に組み込まれる。また、第1型枠10の製造時に、杭頭部補強構造3と基礎構造体(例えば基礎スラブ4)とを接続するための鉄筋(第3鉄筋13)が第1型枠10に設置される。ゆえに、施工現場での配筋作業などを大幅に減らすことができる。 Further, according to the present embodiment, at the time of manufacturing the first formwork 10, substantially all the reinforcing bars (first reinforcing bar 11, second reinforcing bar 12, and third reinforcing bar 13) constituting the pile head reinforcing structure 3 are first. It is incorporated into the mold 10. Further, at the time of manufacturing the first formwork 10, reinforcing bars (third reinforcing bars 13) for connecting the pile head reinforcing structure 3 and the foundation structure (for example, the foundation slab 4) are installed in the first formwork 10. .. Therefore, it is possible to significantly reduce the bar arrangement work at the construction site.

また本実施形態によれば、第1型枠10の製造時に埋設型枠を用いる。換言すれば、第1型枠10は、その内面側及び/又は外面側が埋設型枠で構成されている。これにより、第1型枠10の製造時の脱型作業を減らすことができる。 Further, according to the present embodiment, the buried formwork is used at the time of manufacturing the first formwork 10. In other words, the inner surface side and / or the outer surface side of the first formwork 10 is composed of an embedded formwork. As a result, it is possible to reduce the demolding work at the time of manufacturing the first mold 10.

また本実施形態によれば、杭頭部補強構造3の構築方法は、掘削凹部形成工程(ステップS2)の後であって、かつ、コンクリート打設工程(ステップS8)に先立って、基礎杭2の杭頭部に杭頭補強筋17を設置する杭頭補強筋設置工程(ステップS3)を更に含む。杭頭部補強構造3は、杭頭補強筋17を更に含んで構成される。これにより、基礎杭2の杭頭部と杭頭部補強構造3との一体性を向上させることができる。 Further, according to the present embodiment, the method of constructing the pile head reinforcing structure 3 is after the excavation recess forming step (step S2) and prior to the concrete placing step (step S8), the foundation pile 2 The pile head reinforcing bar installation step (step S3) of installing the pile head reinforcing bar 17 on the pile head of the pile head is further included. The pile head reinforcing structure 3 is configured to further include a pile head reinforcing bar 17. As a result, the integrity of the pile head of the foundation pile 2 and the pile head reinforcing structure 3 can be improved.

また本実施形態によれば、杭頭部補強構造3の構築方法は、コンクリート打設工程(ステップS8)の後に、第2型枠撤去工程(ステップS9)と、第2埋め戻し工程(ステップS10)とを更に含む。第2型枠撤去工程(ステップS9)では、第2型枠25の撤去を行う。第2埋め戻し工程(ステップS10)では、掘削凹部20内における、基礎構造体(例えば基礎スラブ4)の少なくとも一部の周囲を埋め戻す。第2埋め戻し工程(ステップS10)での埋め戻しにも、掘削凹部形成工程(ステップS2)で発生した掘削土砂を用いることができる。 Further, according to the present embodiment, the method of constructing the pile head reinforcing structure 3 includes a second formwork removing step (step S9) and a second backfilling step (step S10) after the concrete placing step (step S8). ) And more. In the second formwork removing step (step S9), the second formwork 25 is removed. In the second backfilling step (step S10), at least a part of the circumference of the foundation structure (for example, the foundation slab 4) in the excavation recess 20 is backfilled. The excavated earth and sand generated in the excavation recess forming step (step S2) can also be used for the backfilling in the second backfilling step (step S10).

また本実施形態によれば、地中に打設された基礎杭2の杭頭部の補強に用いられる型枠(第1型枠10)は、上下方向に延びる筒状であり、かつ、プレキャストコンクリート製である本体部10aと、本体部10aに埋設されて本体部10aの周方向に延びる第1鉄筋11と、一部が本体部10aに埋設されて残部が本体部10aの内部空間10bに露出する第2鉄筋12と、を備える。内部空間10b内に基礎杭2の杭頭部が挿入され、かつ、コンクリート15が打設される。ゆえに、型枠(第1型枠10)は、杭頭部補強構造3の外殻として活用され得る。 Further, according to the present embodiment, the formwork (first formwork 10) used for reinforcing the pile head of the foundation pile 2 placed in the ground has a tubular shape extending in the vertical direction and is precast. A main body portion 10a made of concrete, a first reinforcing bar 11 embedded in the main body portion 10a and extending in the circumferential direction of the main body portion 10a, and a part thereof embedded in the main body portion 10a and the remaining portion in the internal space 10b of the main body portion 10a. A second reinforcing bar 12 to be exposed is provided. The pile head of the foundation pile 2 is inserted into the internal space 10b, and the concrete 15 is placed. Therefore, the formwork (first formwork 10) can be utilized as the outer shell of the pile head reinforcing structure 3.

また本実施形態によれば、型枠(第1型枠10)は、本体部10aの上端部から上方に露出して延びる第3鉄筋13を更に備える。この第3鉄筋13を、杭頭部補強構造3と基礎構造体(例えば基礎スラブ4)との接続部鉄筋として活用することができる。 Further, according to the present embodiment, the formwork (first formwork 10) further includes a third reinforcing bar 13 that extends upward from the upper end portion of the main body portion 10a. The third reinforcing bar 13 can be used as a connecting reinforcing bar between the pile head reinforcing structure 3 and the foundation structure (for example, the foundation slab 4).

次に、図9を用いて、本発明の第2実施形態について説明する。
図9は、本実施形態における基礎1’の概略構成を示す図である。詳しくは、図9(ア)は基礎1’の縦断面図であり、図9(イ)は基礎1’の上面図である。尚、図9(ア)及び(イ)では、図示簡略化のため、前述の第1〜第3鉄筋11〜13及び杭頭補強筋17の図示と、後述するペデスタル31及び地中梁32を構成する鉄筋の図示とを省略している。
前述の第1実施形態と異なる点について説明する。
Next, a second embodiment of the present invention will be described with reference to FIG.
FIG. 9 is a diagram showing a schematic configuration of a foundation 1'in this embodiment. Specifically, FIG. 9A is a vertical sectional view of the foundation 1', and FIG. 9B is a top view of the foundation 1'. In addition, in FIGS. 9A and 9B, for simplification of the illustration, the above-mentioned first to third reinforcing bars 11 to 13 and the pile head reinforcing bar 17 are shown, and the pedestal 31 and the underground beam 32 described later are shown. The illustration of the constituent reinforcing bars is omitted.
The points different from the above-described first embodiment will be described.

前述の第1実施形態では、本発明の「基礎構造体」の一例として基礎スラブ4が採用されていたが、本実施形態では、本発明の「基礎構造体」の別の例として、ペデスタル31及び地中梁32が採用されている。 In the above-mentioned first embodiment, the basic slab 4 is adopted as an example of the "basic structure" of the present invention, but in the present embodiment, the pedestal 31 is another example of the "basic structure" of the present invention. And the underground beam 32 is adopted.

基礎1’は、複数の基礎杭2と、各基礎杭2の杭頭部に各別に構築される複数の杭頭部補強構造3と、杭頭部補強構造3上に立設されて上下方向に延びるペデスタル31と、隣り合うペデスタル31の下端部同士を連結するように水平に延びる地中梁32と、を含んで構成される。ここで、ペデスタル31及び地中梁32は、基礎杭2の杭頭部の上方に構築されるものである。 The foundation 1'is erected on a plurality of foundation piles 2, a plurality of pile head reinforcement structures 3 separately constructed on the pile heads of each foundation pile 2, and a pile head reinforcement structure 3 in the vertical direction. A pedestal 31 extending in the direction of the pedestal 31 and an underground beam 32 extending horizontally so as to connect the lower ends of adjacent pedestals 31 are included. Here, the pedestal 31 and the underground beam 32 are constructed above the pile head of the foundation pile 2.

本実施形態では、基礎1’を構成する地中梁32が地中に位置し、また、ペデスタル31の少なくとも下部が地中に位置している。すなわち、本実施形態では、地面GSより下方に、ペデスタル31の少なくとも下部と、地中梁32とが位置している。 In the present embodiment, the underground beam 32 constituting the foundation 1'is located in the ground, and at least the lower part of the pedestal 31 is located in the ground. That is, in the present embodiment, at least the lower part of the pedestal 31 and the underground beam 32 are located below the ground GS.

図9(イ)に示す配置では、9個の基礎杭2が、平面視でマトリクス状(図では3個×3個)に互いに平行に配置されている。尚、基礎1’を構成する基礎杭2の個数及び配置は、図9に図示されているものに限らない。 In the arrangement shown in FIG. 9A, nine foundation piles 2 are arranged in a matrix (3 × 3 in the figure) parallel to each other in a plan view. The number and arrangement of the foundation piles 2 constituting the foundation 1'are not limited to those shown in FIG.

本実施形態では、杭頭部補強構造3は、基礎杭2とペデスタル31とを連結するものであり、また、基礎杭2の杭頭部を補強するものである。また、杭頭部補強構造3を構成する第1型枠10の第3鉄筋13は、杭頭部補強構造3とペデスタル31とを接続するための鉄筋として機能する。 In the present embodiment, the pile head reinforcing structure 3 connects the foundation pile 2 and the pedestal 31, and reinforces the pile head of the foundation pile 2. Further, the third reinforcing bar 13 of the first formwork 10 constituting the pile head reinforcing structure 3 functions as a reinforcing bar for connecting the pile head reinforcing structure 3 and the pedestal 31.

本実施形態では、ペデスタル31及び地中梁32は、図示しない鉄筋を備えるコンクリート製(鉄筋コンクリート製(RC製))である。
図9に示すように、本実施形態では、ペデスタル31の外周面と杭頭部補強構造3の外周面(第1型枠10の外周面)とが略面一になっている。
In the present embodiment, the pedestal 31 and the underground beam 32 are made of concrete (reinforced concrete (RC)) having reinforcing bars (not shown).
As shown in FIG. 9, in the present embodiment, the outer peripheral surface of the pedestal 31 and the outer peripheral surface of the pile head reinforcing structure 3 (the outer peripheral surface of the first formwork 10) are substantially flush with each other.

尚、本実施形態では、地中梁32がペデスタル31を介して(つまり間接的に)杭頭部補強構造3に連結されているが、この他、地中梁32が杭頭部補強構造3に直接的に連結されてもよい。 In the present embodiment, the underground beam 32 is connected to the pile head reinforcing structure 3 via the pedestal 31 (that is, indirectly), but in addition to this, the underground beam 32 is connected to the pile head reinforcing structure 3. May be directly linked to.

従って、本実施形態、及び、前述の第1実施形態によれば、本発明の「基礎構造体」は、基礎スラブ4、ペデスタル31、及び地中梁32の少なくとも1つを含み得ることが容易に理解されよう。 Therefore, according to the present embodiment and the first embodiment described above, it is easy that the "foundation structure" of the present invention may include at least one of the foundation slab 4, the pedestal 31, and the underground beam 32. Will be understood by.

図示の実施形態はあくまで本発明を例示するものであり、本発明は、説明した実施形態により直接的に示されるものに加え、特許請求の範囲内で当業者によりなされる各種の改良・変更を包含するものであることは言うまでもない。 The illustrated embodiments merely illustrate the present invention, and the present invention makes various improvements and modifications made by those skilled in the art within the scope of the claims, in addition to those directly shown by the described embodiments. It goes without saying that it is an inclusion.

1,1’…基礎、2…基礎杭、3…杭頭部補強構造、4…基礎スラブ、6…ヤットコ、10…第1型枠、10a…本体部、10b…内部空間、11…第1鉄筋、12…第2鉄筋、13…第3鉄筋、15…コンクリート、17…杭頭補強筋、20…掘削凹部、20a,20a’…底面、22…鉄筋、25…第2型枠、31…ペデスタル、32…地中梁、G…地盤、GS…地面 1,1'... foundation, 2 ... foundation pile, 3 ... pile head reinforcement structure, 4 ... foundation slab, 6 ... yatko, 10 ... first formwork, 10a ... main body, 10b ... internal space, 11 ... first Reinforcing bar, 12 ... 2nd reinforcing bar, 13 ... 3rd reinforcing bar, 15 ... Concrete, 17 ... Pile head reinforcement, 20 ... Excavation recess, 20a, 20a'... Bottom surface, 22 ... Reinforcing bar, 25 ... 2nd formwork, 31 ... Pedestal, 32 ... Underground beam, G ... Ground, GS ... Ground

Claims (10)

地中に打設された基礎杭と、前記基礎杭の杭頭部の上方に構築される基礎構造体とを連結し、かつ、前記杭頭部を補強する杭頭部補強構造を構築する方法であって、
前記杭頭部を露出させるように地盤を掘削することで地盤に掘削凹部を形成する掘削凹部形成工程と、
前記露出した前記杭頭部の周囲を囲むように筒状の第1型枠を前記掘削凹部の底面上に設置する第1型枠設置工程と、
前記第1型枠内にコンクリートを打設するコンクリート打設工程と、
を含み、
前記第1型枠はプレキャストコンクリート製であり、
前記杭頭部補強構造は、前記第1型枠と、前記第1型枠内に打設されるコンクリートとを含んで構成される、
杭頭部補強構造の構築方法。
A method of connecting a foundation pile placed in the ground and a foundation structure constructed above the pile head of the foundation pile and constructing a pile head reinforcement structure for reinforcing the pile head. And
An excavation recess forming step of forming an excavation recess in the ground by excavating the ground so as to expose the pile head,
A first formwork installation step of installing a tubular first formwork on the bottom surface of the excavation recess so as to surround the exposed pile head.
The concrete placing process of placing concrete in the first formwork and
Including
The first formwork is made of precast concrete and
The pile head reinforcing structure includes the first formwork and concrete cast in the first formwork.
How to build a pile head reinforcement structure.
前記第1型枠設置工程の後であって、かつ、前記コンクリート打設工程に先立って、前記掘削凹部内における前記第1型枠の周囲を埋め戻す第1埋め戻し工程を更に含む、請求項1に記載の杭頭部補強構造の構築方法。 The claim further includes a first backfilling step of backfilling the periphery of the first formwork in the excavation recess after the first formwork installation step and prior to the concrete placing step. The method for constructing a pile head reinforcing structure according to 1. 前記第1埋め戻し工程の後であって、かつ、前記コンクリート打設工程に先立って、前記埋め戻された領域の上面上に、前記基礎構造体を構築するための第2型枠を設置する第2型枠設置工程を更に含み、
前記コンクリート打設工程では、前記第1型枠内へのコンクリート打設と、前記第2型枠内へのコンクリート打設と一括して実施する、請求項2に記載の杭頭部補強構造の構築方法。
After the first backfilling step and prior to the concrete placing step, a second formwork for constructing the foundation structure is installed on the upper surface of the backfilled area. Including the second formwork installation process
The pile head reinforcing structure according to claim 2, wherein in the concrete placing step, the concrete placing in the first formwork and the concrete placing in the second formwork are carried out collectively. How to build.
前記第1埋め戻し工程の後であって、かつ、前記コンクリート打設工程に先立って、前記埋め戻された領域の上面上で、前記基礎構造体を構成する鉄筋を組み立てる鉄筋組み立て工程を更に含む、請求項2又は請求項3に記載の杭頭部補強構造の構築方法。 After the first backfilling step and prior to the concrete placing step, the reinforcing bar assembling step of assembling the reinforcing bars constituting the foundation structure is further included on the upper surface of the backfilled area. , The method for constructing the pile head reinforcing structure according to claim 2 or 3. 前記第1型枠の製造時に、前記杭頭部補強構造を構成する鉄筋の略全てが前記第1型枠に組み込まれる、請求項1〜請求項4のいずれか1つに記載の杭頭部補強構造の構築方法。 The pile head according to any one of claims 1 to 4, wherein substantially all of the reinforcing bars constituting the pile head reinforcing structure are incorporated into the first form at the time of manufacturing the first form. How to build a reinforced structure. 前記第1型枠の製造時に、前記杭頭部補強構造と前記基礎構造体とを接続するための鉄筋が前記第1型枠に設置される、請求項1〜請求項5のいずれか1つに記載の杭頭部補強構造の構築方法。 Any one of claims 1 to 5, wherein a reinforcing bar for connecting the pile head reinforcing structure and the foundation structure is installed in the first formwork at the time of manufacturing the first formwork. How to construct the pile head reinforcement structure described in. 前記第1型枠の製造時に埋設型枠を用いる、請求項1〜請求項6のいずれか1つに記載の杭頭部補強構造の構築方法。 The method for constructing a pile head reinforcing structure according to any one of claims 1 to 6, wherein an embedded form is used at the time of manufacturing the first form. 前記掘削凹部形成工程の後であって、かつ、前記コンクリート打設工程に先立って、前記杭頭部に杭頭補強筋を設置する杭頭補強筋設置工程を更に含み、
前記杭頭部補強構造は、前記杭頭補強筋を更に含んで構成される、請求項1〜請求項7のいずれか1つに記載の杭頭部補強構造の構築方法。
A pile head reinforcing bar installation step of installing a pile head reinforcing bar on the pile head is further included after the excavation recess forming step and prior to the concrete placing step.
The method for constructing a pile head reinforcing structure according to any one of claims 1 to 7, wherein the pile head reinforcing structure further includes the pile head reinforcing bar.
地中に打設された基礎杭の杭頭部の補強に用いられる型枠であって、
上下方向に延びる筒状であり、かつ、プレキャストコンクリート製である本体部と、
前記本体部に埋設されて前記本体部の周方向に延びる第1鉄筋と、
一部が前記本体部に埋設されて残部が前記本体部の内部空間に露出する第2鉄筋と、
を備え、
前記内部空間内に前記杭頭部が挿入され、かつ、コンクリートが打設される、型枠。
A formwork used to reinforce the pile head of a foundation pile placed underground.
The main body, which has a tubular shape extending in the vertical direction and is made of precast concrete,
A first reinforcing bar embedded in the main body and extending in the circumferential direction of the main body,
A second reinforcing bar that is partially embedded in the main body and the rest is exposed in the internal space of the main body.
With
A formwork in which the pile head is inserted into the internal space and concrete is cast.
前記本体部の上端部から上方に露出して延びる第3鉄筋を更に備える、請求項9に記載の型枠。 The mold according to claim 9, further comprising a third reinforcing bar that is exposed and extends upward from the upper end portion of the main body portion.
JP2020018790A 2020-02-06 2020-02-06 Construction method of pile head part reinforcement structure, and mold Pending JP2021123961A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020018790A JP2021123961A (en) 2020-02-06 2020-02-06 Construction method of pile head part reinforcement structure, and mold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020018790A JP2021123961A (en) 2020-02-06 2020-02-06 Construction method of pile head part reinforcement structure, and mold

Publications (1)

Publication Number Publication Date
JP2021123961A true JP2021123961A (en) 2021-08-30

Family

ID=77459122

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020018790A Pending JP2021123961A (en) 2020-02-06 2020-02-06 Construction method of pile head part reinforcement structure, and mold

Country Status (1)

Country Link
JP (1) JP2021123961A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113738377A (en) * 2021-09-06 2021-12-03 中铁二局第四工程有限公司 Construction method of main structure of station by rock stratum hole-pile method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113738377A (en) * 2021-09-06 2021-12-03 中铁二局第四工程有限公司 Construction method of main structure of station by rock stratum hole-pile method

Similar Documents

Publication Publication Date Title
JP2837128B2 (en) Construction method of cast-in-place concrete pile
JP2020094457A (en) Steel tower foundation structure and its construction method
JP6543176B2 (en) Building method
KR101324231B1 (en) Soil cement wall structure and method for constructing thereof
JP2021123961A (en) Construction method of pile head part reinforcement structure, and mold
JP5131645B2 (en) Construction method of steel tower foundation
JP6678487B2 (en) How to build an underground structure
JP7232714B2 (en) how to build a foundation
JP3760304B2 (en) Building foundation construction method
JP2010133206A (en) Structure and construction method for newly-built structure using existing pile
JP7386095B2 (en) Underground structure construction method
JP6475554B2 (en) Construction method of shaft and construction method of underground storage tank
JP7128094B2 (en) Construction method of foundation structure
JP7112939B2 (en) Joint structure between pile and foundation concrete, precast concrete body, and construction method
JP2005002671A (en) Underpinning method and viaduct
JP6924682B2 (en) Pile head seismic isolation structure and its construction method
KR101077242B1 (en) Construction method of basement structure using retaining wall and steel column
JP2017206882A (en) Method of constructing underground structure
JP6924683B2 (en) Pile head seismic isolation structure and its construction method
JP2017214722A (en) Construction method of base structure, and base structure
JP6938198B2 (en) Construction method
JP6402056B2 (en) Vertical shaft, underground storage tank, vertical shaft construction method and underground storage tank construction method
JP4475116B2 (en) Vertical shaft structure and its construction method
JP6534026B2 (en) Seismic isolation building and its construction method
JP2010150818A (en) Pneumatic caisson and method for constructing the same