Prior art keywords
wall
reinforcement
connective
wall surface
handrail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2017241258A
Other languages
Japanese (ja)
Other versions
JP6346369B1 (en
Inventor
準 伊藤
Jun Ito
準 伊藤
光男 片岡
Mitsuo Kataoka
光男 片岡
一人 岡山
Kazuto Okayama
一人 岡山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shikoku Block Kogyo Co Ltd
Original Assignee
Shikoku Block Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shikoku Block Kogyo Co Ltd filed Critical Shikoku Block Kogyo Co Ltd
Priority to JP2017241258A priority Critical patent/JP6346369B1/en
Application granted granted Critical
Publication of JP6346369B1 publication Critical patent/JP6346369B1/en
Publication of JP2019108701A publication Critical patent/JP2019108701A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Retaining Walls (AREA)

Abstract

To ensure the safety of workers at the time of wall material assembly and human power filling soil leveling and compaction, which is work near the wall material of a vertical or near-vertical slope in reinforced soil wall construction.SOLUTION: In reinforced soil wall construction, connectives provided on wall materials are used outside the purpose taking into consideration their strength, and a safety fence comprising a connecting portion attached to a connective protruding from the wall material when the wall material is opened, a support portion standing on the connecting portion, and a handrail portion installed substantially horizontally between the support portions is provided.SELECTED DRAWING: Figure 1

Description

本発明は、補強土壁工事の施工時の安全対策に関するものである。   The present invention relates to a safety measure at the time of construction of reinforced earth wall construction.

「補強土壁とは、盛土内に敷設した補強材と鉛直または鉛直に近い壁面材とを連結し、壁面材に作用する土圧と補強材の引抜き抵抗が釣り合いを保つことにより、土留め壁として安定を保つ土工構造物をいう」(道路土工-擁壁工指針 平成24年版 社団法人日本道路協会 p223)。   “Reinforcing earth wall connects the reinforcing material laid in the embankment to the vertical or near vertical wall material, and the earth pressure acting on the wall material and the pulling resistance of the reinforcing material keep balance, so the earth retaining wall Earthwork structure to keep stable as “(road earthwork-retaining wall construction guidelines 2012 edition Japan Road Association p223).

前記補強土壁の内、本発明に係る補強土壁は、コンクリート製の壁面材と鋼製の帯状の補強材を用いたものである。   Among the above-mentioned reinforced earth walls, the reinforced earth wall according to the present invention uses a wall material made of concrete and a band-shaped reinforcing material made of steel.

補強土壁は、盛土材、補強材、壁面材が相互に拘束され一体となって安定するものであり、その施工手順は、排水工や基礎工等の施工後に補強土壁工として壁面の形成と補強材の敷設、盛土材のまき出し・締固めが繰り返される(前記文献p274)。   Reinforcing earth wall is the one where embankment material, reinforcement material and wall material are mutually restrained and integrated as one piece, and its construction procedure is to form the wall surface as reinforcement earth wall after construction such as drainage work and foundation work And laying of reinforcements, rolling out and compacting of filling materials are repeated (the above-mentioned document p. 274).

前記施工手順を更に具体的に記すと、壁面材をクレーンで吊り上げた後、所定の位置で吊り降ろし、その構造形式に応じて、人力で壁面の勾配を調整しながら組み立てる。盛土面に応じた補強材を敷設する。次に盛土材を1層当たりの仕上がり厚さを20cm〜30cm以下となるように敷き均し、締め固める。その際の留意事項として、壁面際の1.0m以内は重機による敷き均し、締固めは行わず、人力で行われる。壁面の施工精度に影響するからである。   More specifically, after the wall surface material is lifted by a crane, the wall material is suspended at a predetermined position and assembled while adjusting the slope of the wall surface manually according to the structure type. Install reinforcements according to the embankment surface. Next, the filling material is spread and leveled so that the finished thickness per layer is 20 cm to 30 cm or less. As a matter to be noted at that time, within 1.0 m of the wall surface, it is spread by heavy equipment, and it is done by human power without compaction. It is because it affects the construction accuracy of the wall surface.

本発明の安全対策は、前記施工手順における壁面材組立て時の転落防止と壁面近傍での人力による盛土敷き均し、締固めに係るものである。壁面パネル(壁面材)の開口部における安全策として、着脱自在に固定される把持部と開口部前側に設ける水平手摺を備えた発明があり(特開2005-188170号)、開口部を挟んで壁面材の上端部に少なくとも2つの鉤状係止具の鉤部をそれぞれ引掛けて、鉤状係止具に開口部を横切る棒状部材を係止する柵の発明がある(特開2012-154085号)。しかしながら、これら先行技術において、壁面材の壁面外側の安全柵では、作業の安全対策として十分ではない点や最も危険を伴う作業である壁面材の組立ての際、壁面材のコネクティブ(補強材連結金具)部分が支障になるため、柵を外さざるを得ない点などの問題がある。また、盛土材の人力敷き均し、締固めの際の壁面材から突設されたコネクティブへの躓き防止等の安全対策になり得ない。   The safety measures of the present invention relate to prevention of falling during wall surface material assembly in the above-mentioned construction procedure and leveling and compaction of the earth by human power near the wall surface. As a safety measure at the opening of the wall panel (wall material), there is an invention provided with a grip that is detachably fixed and a horizontal handrail provided on the front of the opening (Japanese Patent Laid-Open No. 2005-188170). There is an invention of a fence in which the hooks of at least two hook-shaped fasteners are hooked on the upper end of the wall surface material, and the hook-shaped fasteners are engaged with the rod-like members crossing the opening (Japanese Patent Laid-Open No. 2012-154085 issue). However, in these prior arts, the safety fence on the outside of the wall surface of the wall surface material is not sufficient as a safety measure for the work, or is the most dangerous operation when assembling the wall surface material. There is a problem such as having to remove the fence because the part is an obstacle. In addition, it can not be a safety measure such as prevention of spreading to the connectives that are protrusively provided from the wall material at the time of compaction and human resources leveling the filling material.

特開2005−188170号公報JP, 2005-188170, A 特開2012−154085号公報JP, 2012-154085, A

「道路土工 擁壁工指針(平成24年版)」社団法人日本道路協会出版"Road earthwork Retaining wall construction guidelines (2012 version)" Japan Road Association publication 「補強土(テールアルメ)壁工法設計・施工マニュアル第4回改訂版(平成26年8月)」一般社団法人土木研究センター出版"Reinforcement soil (tail arme) wall method design, construction manual fourth revised edition (August, 2014) general public foundation corporation public works research center publication

解決しようとする課題は、補強土壁工における鉛直またはそれに近い壁面材付近における作業である壁面材組立てや人力盛土敷き均し・締固め時の作業員の安全を図るものである。   The problem to be solved is to ensure the safety of workers at the time of wall surface material assembly, which is work in the vicinity of a wall surface material at or near the vertical surface wall in reinforced soil wall construction, and manual filling and leveling and compaction.

本発明は、 補強土壁工事において、壁面材開口時に壁面材に設けられたコネクティブをその強度を考慮しつつ目的外に使用するもので、壁面材に突設されたコネクティブに装着する連結部と、該連結部に立設する支柱部と、該支柱部間に略水平に架設する手摺部と、を備えた安全柵を提供するものである。   The present invention is intended to use a connective provided on a wall surface material at the time of opening the wall surface outside the purpose in consideration of the strength in reinforcing earth wall work, and a connecting portion to be attached to the connective provided protruding on the wall surface. To provide a safety fence provided with a support post erected on the connection part and a handrail extending substantially horizontally between the support posts.

補強土壁工事において、本発明の安全柵は、鉛直またはそれに近い勾配の壁面材の付近の壁面材組立て時に、作業員の手摺や安全ベルト設置柵となり、作業時の安全対策となる。また、壁面材周辺における盛土敷き均し・締固め作業時には、壁面材から盛土側に突設されたコネクティブへの作業員の躓きや接触による危険から作業員を保護する。   In reinforced earth wall construction, the safety fence of the present invention becomes a worker's handrail or safety belt installation fence at the time of wall surface assembly near a wall material of a vertical or near slope, and provides safety measures during work. In addition, during leveling and compacting work in the vicinity of wall materials, workers are protected from danger due to workers coming into contact with the connectives protruding from the wall material to the side of the filling.

図1は、本発明の安全柵を設けた説明図である。(実施例1)FIG. 1 is an explanatory view in which the safety fence of the present invention is provided. Example 1 図2は、連結部及び支柱部の詳細を示した説明図である。(実施例1)FIG. 2 is an explanatory view showing details of the connecting portion and the support portion. Example 1 図3は、連結部及び支柱部の詳細を示した説明図である。(実施例1)FIG. 3 is an explanatory view showing details of the connecting portion and the support portion. Example 1 図4は、支柱部及び手摺部の詳細を示した説明図である。(実施例1)FIG. 4 is an explanatory view showing details of the support portion and the handrail portion. Example 1 図5は、本発明の安全柵の設置手順を示した説明図である。(実施例1)FIG. 5 is an explanatory view showing the installation procedure of the safety fence of the present invention. Example 1 図6は、壁面材建込み時の説明図である。(実施例1)FIG. 6 is an explanatory view at the time of wall surface construction. Example 1 図7は、人力土工部等を示した説明図である。(実施例1)FIG. 7 is an explanatory view showing a human-powered earthwork section and the like. Example 1 図8は、補強部の実施例を示した説明図である。(実施例2)FIG. 8 is an explanatory view showing an embodiment of the reinforcing portion. (Example 2) 図9は、補強土壁工事の施工手順等を示した説明図である。FIG. 9 is an explanatory view showing a construction procedure and the like of reinforced soil wall construction. 図10は、一般的なコンクリート壁面材のコネクティブの構造を示した説明図である。FIG. 10 is an explanatory view showing the structure of a typical concrete wall surface connective.

図9(1)〜図9(3)に補強土壁工事の施工手順の概略を示す。図9(1)の状態でaの壁面材1を組立て、盛土面14に盛土材の13まき出し、敷き均し、締固めを行い、図9(2)の盛土面まで盛土を施工後、図9(2)に示すように、補強材12端部をコネクティブ11に取付け、補強材を盛土面に敷設する。その後、前記同様に盛土工を進めることによって、盛土面が図9(3)の状態になったときに、bの壁面材を組立てることになる。この作業の繰返しを行い、盛土面を所定の高さにするものである。   The outline of the construction procedure of reinforcement earth wall construction is shown in Drawing 9 (1)-Drawing 9 (3). Assemble the wall material 1 of a in the state of Fig. 9 (1), pour out 13 of the embankment material on the embankment surface 14, lay it on, level it and compact it, and after constructing the embankment to the embankment surface of Fig. 9 (2) As shown in FIG. 9 (2), the end of the reinforcing member 12 is attached to the connective 11, and the reinforcing member is laid on the filling surface. Thereafter, by proceeding with the filling work in the same manner as described above, when the filling surface is in the state of FIG. 9 (3), the wall surface material of b is assembled. This work is repeated to set the filling surface to a predetermined height.

壁面材開口部とは、上記の施工の間、図9(1)や図9(3)に示す次の壁面材1を建込む既設置の壁面材に挟まれた箇所である。組み立てる前の状態が壁面材開口時というが、補強土壁の工事中は常に開口部は存在する。しかしながら、施工中における同一の壁面組立て状態で盛土面14が最も高い、新たな壁面材建込み前が、作業員にとって最も危険な状態である。また、図9(1)に示す壁面際1mの箇所18において、重機での締固め作業等は、壁面材の前倒れの危険を伴うため、人力によって慎重に行わる。壁面材組立て作業時の作業員出入りも含めて、この個所は、作業員の往来が最も著しい場所となる。   The wall surface material opening portion is a portion sandwiched by the already installed wall surface material into which the next wall surface material 1 shown in FIG. 9 (1) and FIG. 9 (3) is built during the above construction. It is said that the condition before assembling is when the wall material is open, but the opening is always present during the construction of the reinforced earth wall. However, before building a new wall material where the fill surface 14 is the highest in the same wall assembly state during construction, it is the most dangerous state for the workers. Further, at a location 18 of 1 m in the wall surface shown in FIG. 9 (1), the compaction work with heavy machinery and the like is carried out carefully by human power because it involves the risk of front wall falling. This point is the place where the traffic of workers is most significant, including the workers entering and leaving the wall material assembly work.

壁面材1に突設するコネクティブ11(壁面材と補強材を連結する連結金具のことをいう。以下同じ。)は、種々の構造のものがあり、その設置間隔は、現場条件によって設計する補強材12の配置によって決定されるが、補強材の敷設やその後の盛土材13の敷き均し・締固めの施工性を勘案した規則的配置となっている。一般的な配置例として、図9(4−1)〜図9(4−4)に示すような4本取り、6本取り、8本取り、12本取り等(非特許文献2p49〜p50)がある。構造に関しては、補強材の幅、厚みに応じて、図10(1)壁面材側面図及び図10(2)壁面材平面図に示すような鋼板1枚タイプ、図10(3)及び(4)に示すような鋼板2枚による補強材を挟み込むタイプなどがある。また、コネクティブの連結ボルト挿入孔16の1つのタイプ(図10(3))や2つのタイプ(図10(1))などがある。連結ボルト等の連結金具15は12mm〜16mmが用いられるため、連結ボルト挿入孔は15mm〜18mm程度の直径である。   There are various structures of connective 11 (It is a connection metal fitting which connects a wall surface material and a reinforcement material. It is the same in the following.) Which protrudes in wall surface material 1, and the installation interval is a reinforcement designed by field conditions. Although it is determined by the arrangement of the material 12, it is a regular arrangement taking into consideration the installation of reinforcing material and the workability of laying and compacting the filling material 13 thereafter. As a general arrangement example, as shown in FIG. 9 (4-1) to FIG. 9 (4-4), four picks, six picks, eight picks, 12 picks, etc. (non-patent documents 2p49 to p50) There is. Regarding the structure, depending on the width and thickness of the reinforcing material, one steel plate type as shown in FIG. 10 (1) wall surface material side view and FIG. 10 (2) wall surface material plan view, FIGS. There is a type such as sandwiching a reinforcing material by two steel plates as shown in). There are also one type (FIG. 10 (3)) and two types (FIG. 10 (1)) of the connecting bolt insertion holes 16 of the connective. Since 12 mm to 16 mm is used for the connection fitting 15 such as a connection bolt, the connection bolt insertion hole has a diameter of about 15 mm to 18 mm.

本発明は、補強土壁工事における安全対策に関するものである為、実施例等に関しては、壁面材1は、簡易に表現することとし、ジベルやその貫入孔、水平目地材や透水防砂材、補強材のリブ等の記載や図示は省略する。また、実施例は、コネクティブ11の4本取りに設置したものを例として記載する。必要に応じて、設置本数の多いものについて記載する。支柱部4及び手摺部5に関しては、円管を基本とした実施例を示すが、支柱部に関しては、円管の他、角パイプや溝形鋼、山形鋼等の形鋼など支柱としての強度を有するものであればよい。手摺に関しては、円管以外、棒材等もある。   Since the present invention relates to safety measures in reinforced earth wall construction, the wall material 1 is simply expressed in the examples, etc., and the dowel, its penetration hole, horizontal joint material, water-permeable sand-proof material, reinforcement The description and illustration of the ribs and the like of the material are omitted. Moreover, an Example describes as an example what was installed in 4 pieces of connective 11. If necessary, describe as many as possible. Although an embodiment based on a circular pipe is shown for the column 4 and the handrail 5, the column as a column, in addition to the circular pipe, the strength as a square pipe, channel steel, shaped steel such as angle steel, etc. as a column What is necessary is just to have. With regard to handrails, there are also bars and the like other than circular pipes.

図1は、本発明の安全柵2の設置状況図である。壁面材1に突設されたコネクティブ11に連結部3を装着し、連結ピン33によって、係止している。該連結部の支柱基礎部31に支柱部4が立設している。該支柱部間に手摺受部41に支持され水平に架設する手摺部5を備えた安全柵が、壁面の内側(盛土面14側)に全体に渡り、設置されている。本図では、壁面材組立て時にのみならず、盛土施工時の安全対策を勘案して、壁面全延長に、工事期間中設置される状況を示している。   FIG. 1 is an installation situation diagram of the safety fence 2 of the present invention. The connecting portion 3 is attached to the connective 11 protruding from the wall surface material 1 and locked by the connecting pin 33. The support 4 is erected on the support base 31 of the connecting portion. A safety fence provided with a handrail portion 5 supported by the handrail receiving portion 41 and constructed horizontally between the support portions is installed over the entire inside of the wall surface (the filling surface 14 side). This figure shows the situation where it is installed during the construction period for the full extension of the wall surface, taking into consideration the safety measures at the time of embankment construction as well as the wall surface material assembly.

図2及び図3は、コネクティブ11における連結部3及び支柱部4の設置状況の詳細を示すものである。図10に示すコネクティブの鋼板1枚及び2枚のタイプに、安全柵2を施したものである。図2(1)側面図、図2(2)平面図及び図2(3)正面図には、コネクティブを上下に鋼板で挟み、正面視「ロの字」型の連結部の装着の実施例を示している。図2(1)及び図2(3)に示すように、壁材から突設されたコネクティブの鋼板の根元部を残し、コネクティブの上下面を接するように覆い、コネクティブのボルト挿入孔16に連通する位置に連結孔32を設け、連結ピン33によって係止されている。図2(2)に示すように、コネクティブ端部19より、更に先端方向に支柱基礎部31を設け、その位置に支柱部を立設させている。   FIG. 2 and FIG. 3 show details of the installation situation of the connecting portion 3 and the support portion 4 in the connective 11. The safety fence 2 is applied to the connective steel plate type and two types shown in FIG. Fig. 2 (1) Side view, Fig. 2 (2) top view and Fig. 2 (3) front view, the embodiment of the attachment of the connecting part of the front view "ro-shaped" shape, sandwiching the connective between the steel plate up and down Is shown. As shown in FIG. 2 (1) and FIG. 2 (3), leaving the base of the connective steel plate protruding from the wall material, covering the upper and lower surfaces of the connective in contact with each other and communicating with the bolt insertion hole 16 of the connective The connection hole 32 is provided at the position where the connection pin 33 is locked. As shown in FIG. 2 (2), a pillar base portion 31 is provided further in the distal direction from the connective end 19, and the pillar portion is erected at that position.

図2(4)側面図、図2(5)平面図、図2(6)A−A断面図に示す連結部3は、前記同様コネクティブ11を上下に鋼板で挟むものではあるが、図2(4)、図2(6)に示すように側面視「コの字」型の連結部の装着の例である。本例では、図2(4)及び(5)に示すように、コネクティブ端部19を跨ぐように支柱基礎部31を設け、その位置に支柱部4を立設させ、その結果、支柱部基礎の端部は、コネクティブ端部より盛土側になる。   Although the connecting portion 3 shown in FIG. 2 (4) side view, FIG. 2 (5) plan view, and FIG. 2 (6) AA cross section is similar to the above, the connective 11 is sandwiched between steel plates at the top and bottom. (4) As shown in FIG. 2 (6), it is an example of mounting | wearing of the connection part of a side view "コ" type | mold. In this example, as shown in FIGS. 2 (4) and 2 (5), a pillar base 31 is provided so as to straddle the connective end 19, and the pillar 4 is erected at that position. The end of the is closer to the embankment than the connective end.

図3(1)側面図、図3(2)平面図及び図3(3)A−A断面図は、図10(3)に示す鋼板2枚のタイプのコネクティブ11に安全柵2を施したものである。本例において、連結部3は、前記側面視「コの字」型を2枚の鋼板を挟む状態で装着している。この鋼板2枚型のコネクティブに対応する連結部としては、コネクティブの上位にある鋼板のみを挟み込む連結部もあるが、この場合は、連結部である下の鋼板の板厚は補強材12の厚み以下とする必要がある。図は省略する。支柱基礎部は、図2(4)と同様に、コネクティブ端部上に設けている。図3(4)〜図3(6)は、鋼板1枚タイプのコネクティブに直接、台座を有する支柱部を立設させている事例である。   In Fig. 3 (1) side view, Fig. 3 (2) plan view and Fig. 3 (3) sectional view taken along the line AA, the safety fence 2 is applied to the connective 11 of the two steel plate type shown in Fig. 10 (3) It is a thing. In the present embodiment, the connecting portion 3 is mounted so as to sandwich the two steel plates in the side view “C” shape. Although there is a connection part which sandwiches only the steel plate in the upper part of the connective as a connection part corresponding to the connective of this two-sheet type steel plate, in this case, the thickness of the lower steel plate which is the connection part is the thickness of the reinforcing member 12 It is necessary to do the following. The illustration is omitted. The column base is provided on the connective end as in FIG. 2 (4). FIG. 3 (4)-FIG. 3 (6) are examples which make the support | pillar part which has a base stand in the steel plate 1 sheet type connective directly.

本発明に関して、コネクティブ11と連結部3及び支柱部4は、連結部の「ロの字」型若しくは「コの字図」型、連結ピン若しくは連結ボルト・ナット等、異なる組合せによって、種々の構造のものが考えられる。但し、コネクティブに直接支柱部を立設する場合や支柱部基礎31がコネクティブ端部19上にある場合は、以下のことに留意しなければならない。図9(4−3)若しくは(4−4)に示すような上下方向に複数段のコネクティブが配置されている壁面材の最上段以外の高さのコネクティブに安全柵を設置する場合、支柱部設置には、他の段にあるコネクティブが支障になる。   In the context of the present invention, the connective 11 and the connection part 3 and the support part 4 have various structures depending on different combinations such as the “R” or “U” shape of the connection part, the connection pin or the connection bolt / nut, etc. Can be considered. However, in the case of erecting the support directly on the connective or in the case where the support base 31 is on the connective end 19, the following should be noted. When installing a safety fence on a connective with heights other than the top of the wall material where the connectives of multiple steps are arranged vertically as shown in Fig. 9 (4-3) or (4-4), the support section Other stages of connectivity are disrupted by installation.

図4は、支柱部4及び手摺受部41並びに手摺部5の詳細を示すものである。(1)〜(4)に4種類の手摺受部41を示すが、枝番(−1)〜(−3)は手摺部側面図、手摺部正面図、手摺部背面図を表す。手摺部は、開口部を挟む複数の支柱部の手摺受部41によって、略水平に支持されている。図4(1−1)〜(1−3)に示す手摺部は、手摺受部は、両端が螺子きりされたU型の金属棒の中央部に手摺部を配置し、該金属棒の両端部が支柱部の中心線付近の上下に配された2孔を貫通しナットで締め付けることによって、手摺部を水平方向に締付け固定するものである。手摺受部の構造は、種々想定されるが、単に手摺部を水平方向にボルト及びナットで支柱材に固定したのが図4(2−1)〜図4(2−3)である。図4(3−1)〜図4(3−3)は、足場の組立て等で用いられる所謂「単管クランプ」(以下単管クランプ46という。)と呼ばれる金具で固定したものである。支柱部や手摺受部や手摺部は、目的外にコネクティブに負担をかけるものであり、仮設材であることも勘案すると、できるだけ軽量、簡易で、設置が容易なものが望ましい。機能的には、複数の支柱部に支持された手摺部が支柱部の盛土側に略水平に設置され、作業員の転落を防止できる構造であればよい。図4(4−1)〜(4−3)は、前記単管クランプを2箇所に用いて、支柱部と手摺部の間に円管を配して、手摺部を盛土側に前出ししたものである。コネクティブ11に対して直接支柱部を立設する場合には、この前出しの構造を選択せざるを得ない。詳細は「0024」で説明する。   FIG. 4 shows details of the support 4 and the handrail receiving portion 41 and the handrail 5. Although four types of handrail receiving parts 41 are shown in (1) to (4), branch numbers (-1) to (-3) represent handrail side view, handrail front and handrail back view. The handrail portion is supported substantially horizontally by a plurality of handrail receiving portions 41 supporting the opening portion. In the handrail portion shown in FIGS. 4 (1-1) to (1-3), the handrail receiving portion arranges the handrail portion at the center portion of the U-shaped metal rod screwed at both ends, and both ends of the metal rod The handrail portion is clamped and fixed in the horizontal direction by passing through two holes disposed at the top and bottom near the center line of the support portion and tightening with a nut. Although various structures of the handrail receiving part are assumed, it is FIG. 4 (2-1)-FIG. 4 (2-3) which fixed the handrail part to a pillar material only with a bolt and a nut in the horizontal direction. 4 (3-1) to 4 (3-3) are fixed by metal fittings called so-called “single-tube clamps” (hereinafter referred to as single-tube clamps 46) used in the assembly of a scaffold or the like. The supporting column, handrail receiving part and handrail part are burdened connectively outside the purpose, and considering that they are temporary materials, it is desirable that they be as light and easy as possible, and easy to install. Functionally, the handrail portion supported by the plurality of support portions may be installed substantially horizontally on the embankment side of the support portion so as to prevent the worker from falling. In Fig. 4 (4-1) to (4-3), using the single-tube clamps at two locations, a circular pipe is disposed between the support portion and the handrail portion, and the handrail portion is advanced to the embankment side It is a thing. In the case where the support portion is erected directly on the connective 11, this front structure must be selected. Details will be described in “0024”.

図5に、本発明の安全柵2の設置手順を示す。図5(1)は、p1〜p3の壁面材1に関して、その建込み前は、開口部17であり、その開口部を跨ぐ状態で旧安全柵が設置されている。図5(2)に示すように、その安全柵を利用して、p1〜p3の壁面材が建て込まれる。次に、盛土部の盛土を進めることによって、連結部3装着に係るコネクティブ11の位置に盛土面14が至る。その段階で旧安全柵を撤去しているのが、図5(3)の状態である。コネクティブに補強材12端部を連結し、該補強材を盛土面に敷設する。更に、盛土材13敷き均し、締固めを行い、補強材が一定の引張強度を有した段階で、新たな安全柵を設置した状態が図5(4)である。従って、本発明に係る安全柵は、連結材を装着したコネクティブにかかる補強材の敷設とその後の一部の盛土期間を除いて、工事期間中設置しうる。   The installation procedure of the safety fence 2 of this invention is shown in FIG. 5 (1) is the opening part 17 before the installation regarding the wall surface material 1 of p1-p3, and the old safety fence is installed in the state which straddles the opening part. As shown in FIG. 5 (2), the wall materials of p1 to p3 are erected using the safety fence. Next, by advancing the filling of the filling portion, the filling surface 14 reaches the position of the connective 11 related to the attachment of the connecting portion 3. It is a state of FIG. 5 (3) that the old security fence is removed at that stage. Connect the end of the reinforcing material 12 to the connective, and lay the reinforcing material on the filling surface. Furthermore, FIG. 5 (4) shows a state where a new safety fence is installed at a stage where the filling material 13 is spread and compacted, and the reinforcing material has a certain tensile strength. Therefore, the safety fence according to the present invention can be installed during the construction period except for the laying of the reinforcing material of the connective material with the connecting material and a part of the filling period thereafter.

図6(1)に壁面材1の建て込み状況図を示す。クレーン(図では、ワイヤロープ20のみ表示)によって吊り上げられ所定の開口部17に据えられる。図6(2)の側面図は、開口部を跨ぐ手摺部5と壁面材に突設するコネクティブ11との位置関係を明示している。従来、壁面材の降下作業の際、安全柵2を撤去しなければならなかったのは、手摺がコネクティブに衝突するのを避けるためである。本発明の安全柵2を施した場合、図6(2)に示すように、建込みの際、手摺部5が壁面材に突設するコネクティブの支障になることはない。即ち、連結部3がコネクティブに装着されることによって、連結部の先端部は、コネクティブ先端より盛土側に伸長し、支柱部4は、該連結部の盛土側端部付近にある支柱基礎部31に立設される。更に盛土側に水平に架設される手摺部5は、壁面材組立て時の建込みに必要な作業空間を確保できる位置に架設されているためである。また、図6(3)に示すように、連結部を装着することなく、コネクティブに支柱部を立設して、手摺受部41で盛土側に伸長する部材を備えることによっても同様な効果が得られる。しかしながら、手摺受部の荷重が大きくなり、支柱から伸びた手摺受部は、支柱部からの片持ち構造になっているおり、手摺部の荷重が支柱部や更にコネクティブに悪影響をもたらし、得策ではない。図6(4)に示すように、多段のコネクティブが装着された壁面材(図9(4−3)、(4−4)等)への対応に際し、最上段への連結部の装着が適当でないと判断される場合、中段部への連結部の装着には、支柱部がコネクティブ端部19の盛土側になるような連結部を採用しなければならない。   FIG. 6 (1) shows a construction situation of the wall material 1. It is lifted by a crane (in the drawing, only the wire rope 20 is shown) and is placed at a predetermined opening 17. The side view of FIG. 6 (2) clearly shows the positional relationship between the handrail portion 5 straddling the opening and the connective 11 protruding from the wall surface material. Conventionally, when lowering the wall material, the safety fence 2 had to be removed in order to prevent the handrail from crashing in a connective manner. When the safety fence 2 of the present invention is provided, as shown in FIG. 6 (2), the handrail portion 5 does not interfere with the connective protrusion provided on the wall surface material at the time of installation. That is, by mounting the connecting portion 3 in a connective manner, the tip end portion of the connecting portion extends from the connective tip to the filling side, and the support portion 4 is a support base portion 31 near the filling side end of the connecting portion. It is set up at Furthermore, it is because the handrail part 5 constructed horizontally on the embankment side is constructed in the position which can ensure the work space required for the construction at the time of wall surface material assembly. In addition, as shown in FIG. 6 (3), the same effect can be obtained by providing a supporting member erected in a connective manner without attaching the connecting part and providing a member extending to the filling side by the handrail receiving part 41. can get. However, the load on the handrail receiving part is large, and the handrail receiving part extended from the post has a cantilever structure from the post, and the load on the handrail adversely affects the post and the connective, Absent. As shown in Fig. 6 (4), attachment of the connecting part to the top is appropriate when dealing with a wall surface material (Fig. 9 (4-3), (4-4), etc.) on which multiple stages of connectors are attached. If it is not determined that the connection portion should be attached to the middle step, the connection portion must be adopted such that the support portion is on the filling side of the connective end 19.

図7(1)に示すように、壁面材直近の1mの範囲18において、壁面材への影響等を勘案して、重機による作業は、行われず、人力作業で盛土が行われ、壁面材の建込み作業も含めて、最も作業員の往来著しいエリアとなっている。本発明の安全柵を設置した状況と作業員の関係(概ね身長165cm〜170cm程度の作業員を表示している。)を図7(2)に示す。(a)〜(b)の盛土期間は、下方のコネクティブでは躓き、上方のコネクティブでは肩の接触等が最も発生しやすい期間であり、P1を挟む両側の壁面材のコネクティブに装着された連結部から支柱部4が立設され、手摺部5は全区間に渡って設置されている。従って、本安全柵は、直接的又は視線誘導効果によって、躓きや接触を防止する役割を果たす。また、(c)の盛土面において、連結材を設置するコネクティブは設置しやすい高さであり、次の壁面材を安全に建て込めるものであることを示している。   As shown in Fig. 7 (1), in the range 18 of 1m which is the closest to the wall material, the work with heavy machinery is not performed in consideration of the influence on the wall material etc. The filling is carried out by manual work. It has become the area with the most frequent workers, including construction work. The relationship between the situation where the safety fence of the present invention is installed and the workers (generally displaying a worker with a height of about 165 cm to 170 cm) is shown in FIG. 7 (2). The earthing period in (a) to (b) is a period in which the lower connective is open and the upper connective is most susceptible to contact with the shoulder, etc. A connecting portion attached to the connective wall surface material sandwiching P1 The column 4 is erected, and the handrail 5 is installed over the entire section. Therefore, the safety fence plays a role of preventing the roar or contact by the direct or gaze guidance effect. In addition, on the embankment surface of (c), the connective for installing the connecting material is at a height that is easy to install, and indicates that the next wall material can be safely erected.

図8では、本発明によるコネクティブ11の目的外使用に関して、十分な強度を有しない場合の補強措置を備えた安全柵2を示す。図8(1)は、コネクティブを上下に鋼板で挟み、上方の鋼板の一方端部を支柱部基礎31として、支柱部を立設させる正面視「ロの字」型の連結部3の中央側面断面を表示している。この連結部の上下の鋼板について、他方端部を伸長するとともに、コネクティブ突設位置の壁面の上面若しくは下面で接するように、L字型に加工された片持ち補強部34を示している。図では、上面及び下面の両方で補強する片持ち補強部を表している。特に、上面への補強は、壁面材1の建込時手摺部5に、該壁面材が衝突して、支柱部に壁面側に倒れ込む方向に大きな力が働いた場合等に、作業員の転落防止を勘案した時その効果を発揮する。また、上下両面への補強に関しては、安全柵を設置した時のコネクティブの片持ち梁としての強度に不足が生じる時など採用を検討する必要がある。補強部に関しては、側面視「コの字」型に関しても同様であり、鋼板2枚タイプのコネクティブに関しても同様であるので図面は省略する。図8(2)は、側面視「コの字」型の連結部に等辺山形鋼を図のように立設し、支柱部としたものである。補強部としては、該形鋼の一方の内面に回転軸を有し回動する平板で、一方端は、壁面材の壁面に達し、他方端は前記山形鋼の他方の内面に達する、厚みが山形鋼と同程度の平板を設置するものである。該平板は、山形鋼側上角、壁面側下角に丸面の面取り状の加工を施している。該加工によって、図に示すように、前記形鋼の立設方向の上方から、壁面への水平方向までの90度の回動が自在であり、水平方向で係止した時、支柱部に壁面方向への倒れ込みを抑止し、コネクティブの片持ち部を補強するものである。図8(1)の上面補強と同様な効果を発揮する。   FIG. 8 shows a safety fence 2 provided with reinforcing measures in the case of not having sufficient strength with respect to the purposeless use of the connective 11 according to the present invention. In FIG. 8 (1), the central side surface of the connecting portion 3 in the front view “R” shape in which the support is erected by sandwiching the connectives with steel plates in the upper and lower sides and using one end of the upper steel plate as the support base 31. The cross section is displayed. In the upper and lower steel plates of the connecting portion, the cantilever reinforcing portion 34 processed into an L shape is shown so as to extend the other end and contact with the upper surface or the lower surface of the wall surface of the connective protrusion position. The figure shows a cantilever reinforcement that reinforces on both the top and bottom surfaces. In particular, reinforcement to the upper surface is caused by falling of a worker when, for example, the wall material collides with the handrail portion 5 when the wall material 1 is built, and a large force acts on the support in the direction of falling to the wall side. Demonstrate its effect when considering the prevention. In addition, with regard to reinforcement on both the upper and lower sides, it is necessary to consider adoption when there is a lack of strength as a cantilever of a connective when a safety fence is installed. The same applies to the reinforcing portion in the "U-shaped" side view, and the same applies to the connective type of the two steel plate type, so the drawing is omitted. In Fig. 8 (2), equilateral angle steels are erected as shown in the figure in a U-shaped connecting portion in a side view to form a support. The reinforcing portion is a flat plate that rotates with one rotation axis on one inner surface of the section steel, one end reaching the wall surface of the wall material, and the other end reaching the other inner surface of the angle steel A flat plate comparable to the angle steel is installed. The flat plate is chamfered to have round surfaces at the upper angle on the angle steel side and the lower angle on the wall surface side. By this processing, as shown in the figure, a 90 degree rotation from the upper side in the erecting direction of the section to the horizontal direction to the wall surface is free, and when locked in the horizontal direction It restrains falling in the direction, and reinforces the cantilever of the connective. The same effect as the upper surface reinforcement of FIG. 8 (1) is exerted.

支柱部4の下方端が盛土面に達することによって、コネクディブ11への負担を軽減する補強となり得る。図8(3)は、コネクティブに装着された連結部3に設置された支柱部が連結部で垂直方向に固定されると同時に、連結部を貫通し、下方の盛土面に至る支柱延伸部47を有する構造を示したものである(盛土面の表示は省略している。)。図8(3)は、鋼板2枚タイプのコネクティブに正面視「ロの字」型の連結部の側面版が連結部端部より突出し、延設された帯体が支柱部を環装している。 盛土部に到達した支柱部基礎は、支柱に係る荷重の一部を盛土面が負担することとなり、目的が達成される。図8(4)は、鋼板2枚タイプのコネクティブに正面視「ロの字」型の連結部が装着されているが、支柱部内部に支柱心棒47を入れ子式に有しており、支柱部を連結部に固定する際には、支柱部基礎の支柱中心部に設けられた支柱心棒貫通孔35を貫通して心棒先端が盛土面に達するとともに、心棒の上方端付近の螺子きりされた個所が支柱部基礎に固定されたナットと螺合する構造になっている。支柱に係る荷重の一部を盛土面が負担することとなるとともに、盛土の進行によって、心棒下方端が盛土面下に沈下した場合においても、心棒を回転させることによって、容易に引き抜くことができる。また、支柱部心棒の直径をボルト挿入孔以下とすることによって、コネクティブに支柱部を立設する安全柵に対しても設置可能である。このような支柱延伸部等は、片持ち補強部を備えた安全柵においても設置可能である。   When the lower end of the support portion 4 reaches the filling surface, it can be a reinforcement that reduces the load on the connective 11. In FIG. 8 (3), at the same time as the support portion installed in the connection portion 3 attached to the connective portion is vertically fixed in the connection portion, the support extension portion 47 which penetrates the connection portion and reaches the lower embankment surface Indicates a structure having the following (the display of the fill surface is omitted). In Fig. 8 (3), the side plate of the "R-shaped" type connection part in front view protrudes from the end part of the connection part in the two steel plate type connective, and the extended strip body rings the support part. There is. In the column foundation that has reached the embankment area, the embankment surface bears a part of the load applied to the columns, and the purpose is achieved. In FIG. 8 (4), the connecting part of the front view “R” shape is attached to the two steel plate type connective, but the supporting rod 47 is nested inside the supporting member, and the supporting member is In fixing the joint to the connection part, the tip of the stem reaches the filling surface through the support stem through hole 35 provided at the center of the support of the foundation of the support section, and a screwed portion near the upper end of the stem Is screwed into a nut fixed to the column foundation. The embankment surface bears a part of the load related to the columns, and even when the lower end of the mandrel sinks under the embankment surface by the progress of the embankment, it can be easily pulled out by rotating the mandrel . Further, by setting the diameter of the support shaft section to be equal to or less than the bolt insertion hole, the support fence can be installed on a safety fence in which the support section is erected. Such a post extension or the like can also be installed in a safety fence provided with a cantilever reinforcement.

1 壁面材、11 コネクティブ、12 補強材、13 盛土材、14 盛土面、15 連結金具(ボルト、ナット等)、16 ボルト挿入孔、17 開口部、18 壁面際1mの箇所、19 コネクティブ端部、20 ワイヤロープ
2 安全柵
3 連結部、31 支柱基礎部、32 連結孔、33 連結ピン若しくはボルト・ナット、34 片持ち補強部、35 支柱心棒貫通孔
4 支柱部、41 手摺受部、42 U字材、43 支柱孔、44 止金具、45 盛土面若しくは土中基礎部、46 単管クランプ、47 支柱延伸部若しくは支柱心棒
5 手摺部
Reference Signs List 1 wall surface material, 11 connective, 12 reinforcing material, 13 fill material, 14 fill surface, 15 connection metal fittings (bolts, nuts, etc.), 16 bolt insertion hole, 17 opening, 18 wall 1m location, 19 connective end, Reference Signs List 20 wire rope 2 safety fence 3 connection portion, 31 support base portion, 32 connection hole, 33 connection pin or bolt / nut, 34 cantilever reinforcement portion, 35 support shaft stem through hole 4 support portion, 41 handrail receiving portion, 42 U-shaped Materials, 43 post holes, 44 fasteners, 45 embankment surface or foundation in the earth, 46 single tube clamps, 47 post extensions or post stems
5 Handrail

Claims (4)

壁面材に帯状の補強材を連結し、盛土部に前記補強材を敷設して、盛土を敷き均し・締め固める補強土壁工事において、
壁面材に突設されたコネクティブに装着する連結部と、
該連設部に立設する支柱部と、
該支柱部間に略水平に架設する手摺部と、
を備えた安全柵。
In reinforcement earth wall construction which connects band-shaped reinforcement to wall surface material, lays the reinforcement in the embankment part, and lays and compacts the earth,
A connecting part to be attached to a connective member protruding from the wall material;
A supporting column erected on the connecting section;
A handrail that is erected substantially horizontally between the columns;
Safety fence equipped with
壁面材に帯状の補強材を連結し、盛土部に前記補強材を敷設して、盛土を敷き均し・締め固める補強土壁工事において、
壁面材に突設されたコネクティブに立設する支柱部と、
該支柱部間に略水平に架設する手摺部と、
を備えた安全柵。
In reinforcement earth wall construction which connects band-shaped reinforcement to wall surface material, lays the reinforcement in the embankment part, and lays and compacts the earth,
A post erected on a connective piece protruding from the wall material,
A handrail that is erected substantially horizontally between the columns;
Safety fence equipped with
壁面材に帯状の補強材を連結し、盛土部に前記補強材を敷設して、盛土を敷き均し・締め固める補強土壁工において、
壁面材に突設されたコネクティブの片持ち構造を保護する片持ち補強部を備えた請求項1若しくは請求項2の安全柵。
In reinforcement earth wall construction which connects band-like reinforcement material to wall surface material, lays the above-mentioned reinforcement material in the embankment part, and lays out and consolidates the embankment,
The safety fence according to claim 1 or 2, further comprising a cantilever reinforcing portion for protecting the cantilever structure of the connector protrudingly provided on the wall surface material.
壁面材に帯状の補強材を連結し、盛土部に前記補強材を敷設して、盛土を敷き均し・締め固める補強土壁工において、
請求項1、請求項2若しくは請求項3の支柱部の一部が盛土面に達する構造を有する支柱部である安全柵。
In reinforcement earth wall construction which connects band-like reinforcement material to wall surface material, lays the above-mentioned reinforcement material in the embankment part, and lays out and consolidates the embankment,
A safety fence which is a pillar portion having a structure in which a part of the pillar portion according to claim 1, 2 or 3 reaches a filling surface.
JP2017241258A 2017-12-17 2017-12-17 Safety fence for reinforced earthwork Active JP6346369B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017241258A JP6346369B1 (en) 2017-12-17 2017-12-17 Safety fence for reinforced earthwork

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017241258A JP6346369B1 (en) 2017-12-17 2017-12-17 Safety fence for reinforced earthwork

Publications (2)

Publication Number Publication Date
JP6346369B1 JP6346369B1 (en) 2018-06-20
JP2019108701A true JP2019108701A (en) 2019-07-04

Family

ID=62635720

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017241258A Active JP6346369B1 (en) 2017-12-17 2017-12-17 Safety fence for reinforced earthwork

Country Status (1)

Country Link
JP (1) JP6346369B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7078241B1 (en) * 2021-10-08 2022-05-31 四国ブロック工業株式会社 Fence for safety measures of residual formwork construction

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114934468A (en) * 2022-03-28 2022-08-23 中国五冶集团有限公司 Rubble retaining wall anti-collision railing structure and construction method

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6113316A (en) * 1997-06-17 2000-09-05 Northern Stresswall Canada Ltd. Retaining wall system
JP2003239233A (en) * 2002-02-13 2003-08-27 Maruei Concrete Industries Co Ltd Concrete product capable of mounting protective fence support thereon, and method for mounting protective fence support
JP4088542B2 (en) * 2002-03-12 2008-05-21 和光コンクリート工業株式会社 Structure of L-type retaining wall block with protective fence
JP4812135B2 (en) * 2008-06-26 2011-11-09 和 熊谷 Tools for laminating reinforced earth retaining walls
JP5345642B2 (en) * 2011-01-25 2013-11-20 三敬鋼機株式会社 Method for forming reinforced earth wall and safety fence
JP2016121457A (en) * 2014-12-24 2016-07-07 大成建設株式会社 Safety fence for being installed on reinforced soil wall

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7078241B1 (en) * 2021-10-08 2022-05-31 四国ブロック工業株式会社 Fence for safety measures of residual formwork construction

Also Published As

Publication number Publication date
JP6346369B1 (en) 2018-06-20

Similar Documents

Publication Publication Date Title
US10006186B2 (en) Earth anchor and construction method therefor
JP5351382B2 (en) Method for assembling shaft scaffolding and method for removing shaft scaffolding
JP2019108701A (en) Fence for safety measures of reinforced soil wall construction
KR101955852B1 (en) Struts and support for wall shoring structure
KR20130124266A (en) Structure and method of constructing concrete footing structure of top structure
KR20200122912A (en) Bracket Device for Precast Concrete Pole
JP6831714B2 (en) Tower crane foundation and tower crane
JP3146282U (en) Protective fence
CN208486272U (en) A kind of constructing structure of two-tube diagonal brace deep basal pit
CN103993738A (en) Floor penetrating and anchoring type overhanging unloading steel platform
KR20120131996A (en) Structure of temporary installation for land-side protection wall, and construction method thereof
KR101127475B1 (en) Device for connecting wales
KR20170139186A (en) Connecting structure between column and footing structure
JP2016180223A (en) Earth retaining frame, and construction method thereof
JP6918613B2 (en) Wall structure and wall construction method
JP5905802B2 (en) Construction method of breakwater using multi-purpose post
JP5516643B2 (en) Earth retaining wall reinforcement structure and method
JP6461690B2 (en) Foundation structure and foundation construction method
CN204715720U (en) The attachment supporting arrangement of the attachment type raise scaffold outside the building section of receipts within the walls
KR200422931Y1 (en) A pile head reinforcement structure of steel pile
JP5028323B2 (en) Ground anchor method
CN110158498B (en) Construction method of elastic passive protective net upright post structure
CN210086160U (en) Detachable and easily-stored flood control device
JP2014031714A (en) Wooden pole support device
KR102157520B1 (en) Safety scaffolding and installation method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20180226

A871 Explanation of circumstances concerning accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A871

Effective date: 20180226

A975 Report on accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A971005

Effective date: 20180302

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20180327

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20180423

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20180522

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20180524

R150 Certificate of patent or registration of utility model

Ref document number: 6346369

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250