JP2018135677A - Method for simultaneously replacing floor slabs for multiple bridges - Google Patents

Method for simultaneously replacing floor slabs for multiple bridges Download PDF

Info

Publication number
JP2018135677A
JP2018135677A JP2017030324A JP2017030324A JP2018135677A JP 2018135677 A JP2018135677 A JP 2018135677A JP 2017030324 A JP2017030324 A JP 2017030324A JP 2017030324 A JP2017030324 A JP 2017030324A JP 2018135677 A JP2018135677 A JP 2018135677A
Authority
JP
Japan
Prior art keywords
bridge
floor slab
bridges
slab
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2017030324A
Other languages
Japanese (ja)
Other versions
JP6181332B1 (en
Inventor
明夫 正司
Akio Shoji
明夫 正司
和也 崎谷
Kazuya Sakitani
和也 崎谷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Oriental Shiraishi Corp
Original Assignee
Oriental Shiraishi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Oriental Shiraishi Corp filed Critical Oriental Shiraishi Corp
Priority to JP2017030324A priority Critical patent/JP6181332B1/en
Application granted granted Critical
Publication of JP6181332B1 publication Critical patent/JP6181332B1/en
Publication of JP2018135677A publication Critical patent/JP2018135677A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

PROBLEM TO BE SOLVED: To provide a method for simultaneously replacing floor slabs for multiple bridges which allows floor slabs to be simultaneously replaced on multiple bridges in a shortened construction period.SOLUTION: A method for simultaneously replacing floor slabs for multiple bridges which allows floor slabs for multiple bridges to be collectively replaced in the same construction period includes: a heavy machinery and material carry-in process in which, prior to commencement of floor slab replacement work, heavy machinery and new floor slabs, to be used in the floor slab replacement work, are carried-in via one or both of the bridges located at each end (bridge A and bridge D) of a plurality of bridges (bridge A to bridge D) undergoing floor slab replacement work in the same construction period; an existing floor slab stocking process in which replaced existing floor slabs are stocked on either a road connecting the bridges located at each end (bridge A and bridge D), its surrounding area, or both, after commencement of floor slab replacement work on the bridges located at each end (bridge A and bridge D); and an existing floor slab carry-out process in which the stocked existing floor slabs are carried-out via one or both of the bridges located at each end after completion of the floor slab replacement work on the bridges located at each end.SELECTED DRAWING: Figure 2

Description

本発明は、橋梁の床版を取り替える床版取替工法に関し、詳しくは、複数の橋の床版を同時に取り替えて工期を短縮する複数橋の床版同時取替工法に関するものである。   The present invention relates to a floor slab replacement method for replacing a bridge floor slab, and more particularly to a simultaneous bridge floor slab replacement method for simultaneously replacing a plurality of bridge floor slabs.

従来、迂回路の必要性等の理由から、橋梁の床版の取替工事は、一橋ずつ行われていた。例えば、特許文献1には、既設の合成桁の床版を撤去し、プレキャスト床版を架設する際の桁とプレキャスト床版を合成する前に生じる主桁の横倒れを防止するとともに既存の防止対策における欠点を除去することを目的として、プレキャスト床版に形成した箱抜き部を主桁の上フランジ上に位置させて載置し、主桁方向の箱抜き部間を固定点間距離とし、箱抜き部でプレキャスト床版と主桁とを仮固定し、プレキャスト床版の架設完了後に固定を解除して箱抜き部にコンクリートを打設する主桁横倒れ座屈の防止工法が開示されている(特許文献1の請求項1、明細書の段落[0008]〜[0010]、図面の図1、図9等参照)。   Conventionally, replacement of bridge decks has been done one by one because of the necessity of a detour. For example, in Patent Literature 1, the existing composite girder floor slab is removed, and the main girder is prevented from falling down before the precast floor slab is combined with the precast floor slab. For the purpose of eliminating defects in measures, the box opening part formed in the precast floor slab is placed on the upper flange of the main girder, and the distance between the box opening parts in the main girder direction is the distance between the fixed points. A precast floor slab and main girder are temporarily fixed at the box opening part, and after the precast floor slab has been installed, the fixing is released and concrete is placed on the box opening part. (See claim 1 of Patent Document 1, paragraphs [0008] to [0010] of the specification, FIG. 1 and FIG. 9 of the drawings, etc.).

また、特許文献2には、取替えられる位置の既設床版1における鋼桁4のウェブ6を、橋軸方向に沿って上下方向に切断して、既設床版1を鋼桁4の上側ウェブ9bごと撤去し、別途製作された、既設床版1と同形同大の新設床版20を、既設鋼桁の下側ウェブ9a上に配置して、鋼桁下側ウェブ9aと新設床版20の鋼桁上側ウェブ29とを一体に接合する橋梁コンクリート床版の取替え工法が開示されている(特許文献2の請求項1、明細書の段落[0022]〜[0031]、図面の図1、図2等参照)。   Moreover, in patent document 2, the web 6 of the steel girder 4 in the existing floor slab 1 of the position to replace is cut | disconnected up and down along a bridge-axis direction, and the existing floor slab 1 is used for the upper web 9b of the steel girder 4. A new floor slab 20 having the same shape and the same size as the existing floor slab 1 is disposed on the lower web 9a of the existing steel girder, and the steel girder lower web 9a and the new floor slab 20 are manufactured separately. A bridge concrete floor slab replacement method for integrally joining the steel girder upper web 29 is disclosed (claim 1 of patent document 2, paragraphs [0022] to [0031] of the specification, FIG. 1 of the drawings, (See FIG. 2 etc.)

しかし、従来のように一橋ずつ床版の取替工事を行っていると全ての橋の床版取替を完了するのに何十年も掛かってしまい、橋梁の老朽化に追いつけないという問題が生じてきた。このため、近年、IC(インターチェンジ)ごとにまとめて複数の橋の床版取替工事を行うことが要請されつつある。   However, if the floor slab replacement work is done one by one as in the past, it will take decades to complete the replacement of the floor slabs of all the bridges, and there is a problem that it can not keep up with the aging of the bridge It has occurred. For this reason, in recent years, it is being requested to perform floor plate replacement work for a plurality of bridges collectively for each IC (interchange).

しかしながら、橋梁下から取替工事を施工ができない場合は、複数の橋の床版取替工事を同時に行うと、次のような問題がある。例えば、図7に示すように、A橋〜D橋の4つの橋の床版取替工事を同時に行おうとする場合、両端に位置するA橋とD橋の床版取替工事に着工すると、A橋とD橋を通過させて、既設床版S1の搬出や新設床版S2の搬入ができない。このため、A橋とD橋の床版取替工事が完了するまでの間、B橋とC橋の床版取替工事を行うことができないという問題があった。つまり、従来の床版取替工法では、複数の橋を同時に施工できず、工期を短縮できないという問題があった。また、交通規制の期間をできるだけ短くしたいという要請からさらなる工期短縮が求められている。   However, when the replacement work cannot be performed from under the bridge, there are the following problems when the floor slab replacement work of a plurality of bridges is performed simultaneously. For example, as shown in FIG. 7, when the floor slab replacement work for four bridges, A bridge to D bridge, is to be performed at the same time, when the construction of the floor slabs for A bridge and D bridge located at both ends is started, It is impossible to carry out the existing floor slab S1 or carry in the new floor slab S2 through the A and D bridges. For this reason, there was a problem that the floor slab replacement work for the B and C bridges could not be performed until the floor slab replacement work for the A and D bridges was completed. That is, the conventional floor slab replacement method has a problem that a plurality of bridges cannot be constructed at the same time, and the construction period cannot be shortened. In addition, further shortening of the construction period is required due to a request to shorten the traffic regulation period as much as possible.

特開平8−218327号公報JP-A-8-218327 特開2007−239365号公報JP 2007-239365 A

そこで、本発明は、前述した問題に鑑みて案出されたものであり、その目的とするところは、複数の橋の床版を同時に取り替えて工期を短縮する複数橋の床版同時取替工法を提供することにある。   Accordingly, the present invention has been devised in view of the above-described problems, and the object of the present invention is to simultaneously replace the floor slabs of a plurality of bridges to shorten the construction period and simultaneously replace the slabs of a plurality of bridges. Is to provide.

第1発明に係る複数橋の床版同時取替工法は、複数の橋の床版を同一施工期間内にまとめて取り替える複数橋の床版同時取替工法であって、同一施工期間内に床版取替工事を行う複数の橋のうち、両端に位置する橋の床版取替工事の着工前に、これらの橋のいずれか一方又は両方を通過させて床版取替工事を行う重機及び新設床版を搬入する重機資材搬入工程と、前記両端に位置する橋の床版取替工事の着工後に、前記両端に位置する橋同士を繋ぐ道路とその周辺の一方又は両方に取り替えた既存床版をストックする既存床版ストック工程と、前記両端に位置する橋の床版取替工事の完了後に、これらの橋のいずれか一方又は両方を通過させてストックした既存床版を搬出する既存床版搬出工程と、を行うことを特徴とする。   The multiple bridge floor slab simultaneous replacement method according to the first invention is a multiple bridge floor slab simultaneous replacement method in which a plurality of bridge floor slabs are collectively replaced within the same construction period. Heavy machines that perform floor slab replacement work by passing either or both of these bridges before the start of the floor slab replacement work of the bridges located at both ends of the plurality of bridges that perform plate replacement work, and After the start of heavy equipment material loading process to carry in the new floor slab and the floor slab replacement work of the bridges located at both ends, the existing floor replaced with one or both of the road connecting the bridges located at both ends and the surrounding area After completing the existing floor slab stocking process to stock slabs and the floor slab replacement work for the bridges located at both ends, the existing floor slabs are transported through one or both of these bridges and the existing floor slabs are unloaded. A plate unloading step.

第2発明に係る複数橋の床版同時取替工法は、第1発明において、前記重機資材搬入工程では、前記両端に位置する橋の床版取替工事の着工前に、これらの橋のいずれか一方又は両方を通過させてトレーラーやフォークリフトなどの資材移動手段を搬入することを特徴とする。   In the first invention, the simultaneous replacement method for floor slabs of a plurality of bridges according to the second aspect of the present invention may be any of these bridges before the construction of the floor slab replacement work for the bridges located at both ends in the heavy machinery material carrying-in process. One or both of them are passed, and material moving means such as a trailer or a forklift is carried in.

第3発明に係る複数橋の床版同時取替工法は、第1発明又は第2発明において、前記重機資材搬入工程で搬入した重機及び新設床版を用いて、前記両端に位置する橋のいずれかの橋の床版取替工事を行うことを特徴とする。   In the first invention or the second invention, the simultaneous replacement method for floor slabs of a plurality of bridges according to the third invention is any of the bridges located at both ends using the heavy machinery and new floor slabs carried in the heavy machinery material loading step. The bridge slab replacement work is performed.

第4発明に係る複数橋の床版同時取替工法は、第1発明又は第2発明において、床版を同一施工期間内にまとめて取り替える複数の橋の数が3橋以上であり、前記重機資材搬入工程で搬入した重機及び新設床版を用いて、前記両端に位置する橋以外の橋の床版取替工事を行うことを特徴とする。   In the first and second inventions, the method for simultaneous replacement of floor slabs for a plurality of bridges according to the fourth aspect of the present invention is such that the number of a plurality of bridges for replacing the floor slabs together in the same construction period is three or more bridges, Using the heavy machinery and new floor slabs carried in the material carrying-in process, floor slab replacement work for bridges other than the bridges located at both ends is performed.

第1発明〜第4発明によれば、複数の橋の床版を同時に取り替えて床版取替工事の工期を短縮することができる。   According to the 1st invention-the 4th invention, the floor plan of a floor slab replacement work can be shortened by exchanging the floor slab of a plurality of bridges simultaneously.

特に、第2発明によれば、床版取替工事の着工前にトレーラーやフォークリフトなどの資材移動手段を搬入するので、撤去した既設床版のストック位置と、新設床版のストック位置等を容易に入れ替えることができ、床版取替工事の作業効率を向上させて、さらに工期を短縮することができる。   In particular, according to the second invention, since the material moving means such as a trailer or a forklift is carried in before the start of the slab replacement work, the stock position of the removed existing slab and the stock position of the newly installed slab can be easily The work efficiency of the floor slab replacement work can be improved, and the construction period can be further shortened.

特に、第3発明によれば、重機資材搬入工程で搬入した重機及び新設床版を用いて、両端に位置する橋のいずれかの橋の床版取替工事を行うので、両端に位置する橋の少なくとも一方では、橋の両側から床版の取替工事を行えることとなり、さらに、工期を短縮することができる。   In particular, according to the third invention, because the floor slab replacement work for either of the bridges located at both ends is performed using the heavy machinery and the new floor slab carried in the heavy machinery material carry-in process, the bridges located at both ends At least one of these will allow the floor slabs to be replaced from both sides of the bridge, further reducing the construction period.

特に、第4発明によれば、重機資材搬入工程で搬入した重機及び新設床版を用いて、両端に位置する橋以外の橋の床版取替工事を行うので、両端に位置する橋とそれ以外の橋の床版取替工事を同時に行うことができる。このため、工期を短縮することができる。   In particular, according to the fourth invention, the floor slab replacement work for bridges other than the bridges located at both ends is performed using the heavy machinery and the new floor slabs carried in the heavy machinery material carry-in process. It is possible to replace the floor slabs of other bridges at the same time. For this reason, a construction period can be shortened.

本発明の第1実施形態に係る複数橋の床版同時取替工法の各工程を示すフローチャートである。It is a flowchart which shows each process of the floor slab simultaneous replacement construction method of multiple bridges concerning 1st Embodiment of this invention. 第1実施形態に係る複数橋の床版同時取替工法を説明する説明図である。It is explanatory drawing explaining the floor slab simultaneous replacement construction method of the multiple bridge which concerns on 1st Embodiment. 本発明の第2実施形態に係る複数橋の床版同時取替工法の各工程を示すフローチャートである。It is a flowchart which shows each process of the floor slab simultaneous replacement construction method of multiple bridges concerning 2nd Embodiment of this invention. 第2実施形態に係る複数橋の床版同時取替工法を説明する説明図である。It is explanatory drawing explaining the floor slab simultaneous replacement construction method of the multiple bridge which concerns on 2nd Embodiment. 本発明の第3実施形態に係る複数橋の床版同時取替工法の各工程を示すフローチャートである。It is a flowchart which shows each process of the floor slab simultaneous replacement construction method of the several bridge concerning 3rd Embodiment of this invention. 第3実施形態に係る複数橋の床版同時取替工法を説明する説明図である。It is explanatory drawing explaining the floor slab simultaneous replacement construction method of multiple bridges concerning 3rd Embodiment. 従来の複数橋の床版同時取替工法を説明する説明図である。It is explanatory drawing explaining the conventional floor slab simultaneous replacement construction method of multiple bridges.

以下、本発明に係る複数橋の床版同時取替工法を実施するための一実施形態について、図面を参照しながら詳細に説明する。   Hereinafter, an embodiment for carrying out a simultaneous slab replacement method for a plurality of bridges according to the present invention will be described in detail with reference to the drawings.

[第1実施形態]
先ず、図1、図2を用いて、本発明の第1実施形態に係る複数橋の床版同時取替工法について説明する。本実施形態に係る複数橋の床版同時取替工法を適用してA橋〜D橋までの4つの橋の床版を同一施工期間内に同時に取り替える場合を例示して説明する。また、橋としては、鋼桁G1の上に鉄筋コンクリート製の既設床版S1がスタッドボルト等で合成された合成桁の橋を例示する。
[First Embodiment]
First, the simultaneous replacement method of floor slabs for a plurality of bridges according to the first embodiment of the present invention will be described with reference to FIGS. 1 and 2. The case where the floor slabs of four bridges from A bridge to D bridge are simultaneously replaced within the same construction period by applying the simultaneous slab replacement method for a plurality of bridges according to this embodiment will be described as an example. Moreover, as a bridge, the bridge of the composite girder by which the existing floor slab S1 made from reinforced concrete was synthesize | combined with the stud bolt etc. on the steel girder G1 is illustrated.

図1は、本発明の第1実施形態に係る複数橋の床版同時取替工法の各工程を示すフローチャートであり、図2は、本発明の第1実施形態に係る複数橋の床版同時取替工法を説明する説明図である。   FIG. 1 is a flowchart showing the steps of the simultaneous replacement method for floor slabs of a plurality of bridges according to the first embodiment of the present invention, and FIG. 2 shows the simultaneous slab of multiple bridges according to the first embodiment of the present invention. It is explanatory drawing explaining a replacement construction method.

(1)重機資材搬入工程
図1、図2に示すように、第1実施形態に係る複数橋の床版同時取替工法では、A橋〜D橋のうち、両端に位置するA橋とD橋の床版取替工事の着工前に、A橋とD橋を通過させて床版取替工事を行う重機及び新設床版S2を搬入する重機資材搬入工程を行う。
(1) Heavy machinery material carrying-in process As shown in FIGS. 1 and 2, in the simultaneous slab replacement method for a plurality of bridges according to the first embodiment, A bridge and D located at both ends of A bridge to D bridge. Prior to the start of the bridge slab replacement work, a heavy equipment material carrying-in process for carrying in the heavy slab and the newly installed floor slab S2 through the A bridge and the D bridge is performed.

ここで、重機とは、ラフタークレーンCLやクローラークレーンなどの自走式揚重機を主に指し、トレーラーTLやフォークリフトなどの資材移動手段を含む概念である。また、新設床版S2とは、老朽化して劣化した既設床版S1(図7等参照)と取り替える新設のプレキャスト床版を指している。   Here, the heavy machinery mainly refers to a self-propelled lifting machine such as a rough terrain crane CL or a crawler crane, and is a concept including a material moving means such as a trailer TL or a forklift. The new floor slab S2 refers to a new precast floor slab that replaces the existing floor slab S1 that has deteriorated due to deterioration (see FIG. 7 and the like).

本工程では、A橋の床版取替工事の着工前に、A橋を通過させてB橋の床版取替工事を行うラフタークレーンCLやトレーラーTLなどの重機やB橋用の新設床版S2bをA橋とB橋間のエリアA2に搬入する。それに加え、D橋の床版取替工事の着工前に、D橋を通過させてC橋の床版取替工事を行うラフタークレーンCLやトレーラーTLなどの重機やC橋用の新設床版S2cをD橋とC橋間のエリアA4に搬入する。勿論、A橋とD橋のいずれか一方の橋を通過させて、B橋の床版取替工事を行う重機やB橋用の新設床版S2bをエリアA2に搬入し、C橋の床版取替工事を行う重機やC橋用の新設床版S2cをエリアA4に搬入しても構わない。   In this process, before the construction of the slab replacement work for the A bridge, the new slabs for heavy equipment such as the rough terrain crane CL and the trailer TL that pass the A bridge and perform the slab replacement work for the B bridge and the B bridge S2b is carried into the area A2 between the A bridge and the B bridge. In addition, the new floor slab S2c for heavy equipment such as the rough terrain crane CL and the trailer TL that passes the D bridge and performs the floor slab replacement work for the C bridge before the start of the replacement work for the D bridge floor slab S2c To the area A4 between the D and C bridges. Of course, passing through one of the bridges A and D, carry the heavy equipment for replacing the slabs of the B bridge and the new slab S2b for the B bridge into the area A2, and the floor slab of the C bridge. A heavy machine for replacement work or a new floor slab S2c for the C bridge may be carried into the area A4.

また、必要に応じて、本工程では、電動ホイストなどの揚重装置が付いた、既設床版S1や新設床版S2などの資材移動用の門型クレーンや、架設桁で床版の取り替えを行う場合の架設桁用の架設機材など、も併せてエリアA2やエリアA4に搬入してもよい。   Also, if necessary, in this process, the floor slab can be replaced with a portal crane for moving materials such as the existing floor slab S1 and the new floor slab S2, equipped with a lifting device such as an electric hoist, or a built-up girder. The erection equipment for the erection girder in the case of carrying out may also be carried into the area A2 or the area A4.

なお、本工程では、B橋やC橋の床版取替工事の着工前に、B橋やC橋を通過させて、B橋やC橋の床版取替工事を行う重機やB橋用の新設床版S2bやC橋用の新設床版S2cを、B橋とC橋間のエリアA3に搬入してもよい。そうすることで、エリアA2やエリアA4からのB橋やC橋の床版取替工事と同時に、エリアA3からB橋やC橋の床版取替工事を行うことが可能となり、更なる工期短縮を達成することができるからである。   In addition, in this process, before the start of the slab replacement work for the B and C bridges, for heavy machinery and B bridges that pass the B and C bridges and perform the slab replacement work for the B and C bridges. The new floor slab S2b and the new floor slab S2c for the C bridge may be carried into the area A3 between the B bridge and the C bridge. By doing so, it is possible to replace the floor slabs of the B and C bridges from the area A2 and the area A4 and at the same time to replace the floor slabs of the B and C bridges from the area A3. This is because shortening can be achieved.

(2)床版切断工程
次に、本発明の第1実施形態に係る複数橋の床版同時取替工法では、既設床版S1をラフタークレーンCL等で揚重可能な大きさいに切断する床版切断工程を行う。
(2) Floor slab cutting step Next, in the simultaneous slab replacement method for a plurality of bridges according to the first embodiment of the present invention, a floor for cutting an existing floor slab S1 to a size capable of being lifted by a rough terrain crane CL or the like. A plate cutting process is performed.

具体的には、ダイヤモンドカッターやワイヤソー等のコンクリート切断手段を用いて、前述のラフタークレーンCL等の自走式揚重機で揚重可能な大きさに切断する。本実施形態に係る複数橋の床版同時取替工法では、この床版切断工程をA橋〜D橋の4橋全て同時に(同一工程で並行して)行う。   Specifically, using a concrete cutting means such as a diamond cutter or a wire saw, it is cut into a size that can be lifted by a self-propelled lifting machine such as the aforementioned rough terrain crane CL. In the simultaneous slab replacement method for a plurality of bridges according to the present embodiment, this slab cutting process is performed simultaneously for all four bridges of A bridge to D bridge (in the same process in parallel).

(3)既設床版撤去工程
次に、本実施形態に係る複数橋の床版同時取替工法では、前工程で所定の大きさに切断した既設床版S1を撤去する既設床版撤去工程を行う。
(3) Existing floor slab removal process Next, in the simultaneous replacement method of floor slabs of a plurality of bridges according to the present embodiment, an existing floor slab removal process for removing the existing floor slab S1 cut to a predetermined size in the previous process. Do.

既設床版S1がスタッドジベル等で鋼桁G1と合成されている場合は、それらの合成部分をコールピックハンマーや油圧ブレーカーなどの斫り機等を用いて、斫り取って鋼桁G1と切り離し撤去する。勿論、既設のスタッドジベルなどの合成部分を溶断したり、根本から切断したりして、鋼桁G1と切り離してもよいことは云うまでもない。   When the existing floor slab S1 is combined with the steel girder G1 by a stud gibber or the like, the combined part is scraped off using a drilling machine such as a call pick hammer or a hydraulic breaker to separate it from the steel girder G1. Remove. Of course, it goes without saying that a synthetic part such as an existing stud gibber may be cut off from the base and cut off from the steel girder G1.

本実施形態に係る複数橋の床版同時取替工法では、A橋までのエリアA1に設置したラフタークレーンCL等を用いて、前工程で切断した既設床版S1をA橋の鋼桁G1上からトレーラーTL等で搬出する。それと同時に(同一工程で並行して)、エリアA2に設置したラフタークレーンCL等を用いて、前工程で切断した既設床版S1をB橋の鋼桁G1上から撤去し、エリアA2の道路及びその周辺にストックする。   In the simultaneous slab replacement method for a plurality of bridges according to the present embodiment, the existing floor slab S1 cut in the previous process using the rough terrain crane CL installed in the area A1 up to the A bridge is used on the steel beam G1 of the A bridge. Carry out from the trailer TL. At the same time (in parallel with the same process), the existing floor slab S1 cut in the previous process is removed from the steel beam G1 of the B bridge using the rough terrain crane CL installed in the area A2, and the road in the area A2 and Stock around it.

また、これと同時に、エリアA5に設置したラフタークレーンCL等を用いて、前工程で切断した既設床版S1をD橋の鋼桁G1上からトレーラーTL等で搬出する。それと同時に、エリアA4に設置したラフタークレーンCL等を用いて、前工程で切断した既設床版S1をC橋の鋼桁G1上から撤去し、エリアA4の道路及びその周辺にストックする。   At the same time, using the rough terrain crane CL installed in the area A5, the existing floor slab S1 cut in the previous process is carried out from the steel beam G1 of the D bridge by the trailer TL. At the same time, the existing floor slab S1 cut in the previous process is removed from the steel girder G1 of the C bridge using a rough terrain crane CL installed in the area A4 and stocked on the road in the area A4 and its surroundings.

(4)新設床版設置工程
次に、本実施形態に係る複数橋の床版同時取替工法では、新設床版S2を鋼桁G1に載置して所定の位置に据え付ける新設床版設置工程を行う。
(4) New floor slab installation process Next, in the multiple bridge floor slab simultaneous replacement method according to this embodiment, a new floor slab installation process in which the new floor slab S2 is placed on the steel girder G1 and installed at a predetermined position. I do.

具体的には、本工程では、前述のラフタークレーンCL等を用いて、予め搬入しておいた新設床版S2を吊り上げて所定の位置に据え付ける。   Specifically, in this step, the previously installed new floor slab S2 is lifted and installed at a predetermined position using the aforementioned rough terrain crane CL or the like.

本実施形態に係る複数橋の床版同時取替工法では、エリアA1に設置したラフタークレーンCL等を用いて、エリアA1に新たに搬入したA橋用の新設床版S2aをA橋の鋼桁G1上に設置する。それと同時に、エリアA2に設置したラフタークレーンCL等を用いて、前述の重機資材搬入工程でエリアA2に搬入・ストックしておいたB用の新設床版S2bをB橋の鋼桁G1上に設置する。   In the simultaneous slab replacement method for a plurality of bridges according to the present embodiment, a new floor slab S2a for A bridge newly introduced into area A1 using a rough terrain crane CL or the like installed in area A1 is used as a steel girder for A bridge. Install on G1. At the same time, using the rough terrain crane CL installed in area A2, the new floor slab S2b for B that has been loaded and stocked in area A2 in the heavy machinery material loading process described above is installed on the steel beam G1 of the B bridge. To do.

また、これと同時に、エリアA5に設置したラフタークレーンCL等を用いて、D橋までのエリアA5に新たに搬入したD橋用の新設床版S2dをD橋の鋼桁G1上に設置する。それと同時に、エリアA3に設置したラフタークレーンCL等を用いて、前述の重機資材搬入工程でエリアA4に搬入・ストックしておいたC用の新設床版S2cをC橋の鋼桁G1上に設置する。   At the same time, the new floor slab S2d for the D bridge newly introduced into the area A5 up to the D bridge is installed on the steel beam G1 of the D bridge using the rough terrain crane CL installed in the area A5. At the same time, using the rough terrain crane CL installed in area A3, the new floor slab S2c for C that has been loaded and stocked in area A4 in the heavy machinery material loading process described above is installed on the steel beam G1 of the C bridge. To do.

(5)スタッド立設工程
次に、本実施形態に係る複数橋の床版同時取替工法では、前工程で設置した新設床版S2のコッター(合成用の孔)内の鋼桁G1の上面に新設のスタッドジベルを立設するスタッド立設工程を行う。
(5) Stud Standing Step Next, in the simultaneous replacement method of the multiple bridge floor slabs according to this embodiment, the upper surface of the steel girder G1 in the cotter (hole for synthesis) of the new floor slab S2 installed in the previous step. A stud erection process is performed to erect a newly installed stud gibber.

具体的には、本工程では、スタッド溶接機の溶接ガンをスタッドジベルに押し当てて、鋼桁G1の上面にスタッドジベルを1本ずつ溶植して新設床版S2のコッター(合成用の孔)内に立設していく。なお、スタッドジベルを溶植するのではなく、鋼桁G1に削孔してその孔にボルト等をボルト接合して立設しても構わない。   Specifically, in this process, the welding gun of the stud welding machine is pressed against the stud gibber, and the stud gibber is melted one by one on the upper surface of the steel girder G1, and the cotter (hole for synthesis) of the newly installed floor slab S2 is obtained. ) Instead of planting the stud gibber, the steel girder G1 may be drilled and a bolt or the like may be bolted to the hole to stand upright.

なお、本実施形態に係る複数橋の床版同時取替工法では、このスタッド立設工程をA橋〜D橋の4橋全て同時に(同一工程で並行して)行う。   In addition, in the simultaneous slab replacement method for a plurality of bridges according to the present embodiment, this stud standing process is performed simultaneously for all four bridges A bridge to D bridge (in the same process in parallel).

(6)充填材充填工程
次に、本実施形態に係る複数橋の床版同時取替工法では、新設床版S2のコッター内に無収縮モルタルなどの充填材を充填する充填材充填工程を行う。
(6) Filler Filling Step Next, in the simultaneous slab replacement method for multiple bridges according to the present embodiment, a filler filling step of filling a filler such as a non-shrink mortar into the cotter of the new floor slab S2 is performed. .

本工程で使用する充填材としては、無収縮モルタルの他、一般的なコンクリートやモルタルなどの水和反応により硬化するセメント硬化物を用いることができる。但し、コッターのスタッドジベルとの隙間が狭い場合は、粗骨材がないモルタルが好ましく、硬化時の乾燥収縮が極めて少ない無収縮モルタルがさらに好ましい。また、コスト面を考慮しなければ、充填材として樹脂等を用いることも可能である。   As a filler used in this step, a hardened cement cured by a hydration reaction such as general concrete or mortar can be used in addition to non-shrink mortar. However, when the gap between the cotter and the stud gibber is narrow, a mortar having no coarse aggregate is preferable, and a non-shrinkable mortar with extremely little drying shrinkage at the time of curing is more preferable. If cost is not taken into consideration, it is also possible to use a resin or the like as the filler.

なお、本実施形態に係る複数橋の床版同時取替工法では、この充填材充填工程もA橋〜D橋の4橋全て同時に(同一工程で並行して)行う。   In addition, in the simultaneous slab replacement method for a plurality of bridges according to the present embodiment, this filling material filling process is also performed at the same time for all four bridges A bridge to D bridge (in the same process in parallel).

本工程を行った後、充填材が硬化するまでの養生期間をとって、新設床版S2上にアスファルト舗装を施すなど、その他の必要な作業を行った上、エリアA2及びエリアA4にストックしていた既設床版S1や残りの資材を搬出する。そして、ラフタークレーンCLなどの自走式揚重機、及びトレーラーTLなどの資材移動手段を含む重機を搬出し、本実施形態に係る複数橋の床版同時取替工法の床版取替作業が終了する。   After performing this process, take a curing period until the filler hardens, perform other necessary work such as asphalt pavement on the new floor slab S2, and stock it in area A2 and area A4 The existing floor slab S1 and the remaining materials that have been removed are carried out. Then, a self-propelled lifting machine such as a rough terrain crane CL and a heavy machine including a material moving means such as a trailer TL are carried out, and the floor slab replacement work of the simultaneous replacement method of the floor slabs of the multiple bridges according to this embodiment is completed To do.

以上のように、本発明の第1実施形態に係る複数橋の床版同時取替工法によれば、両端に位置するA橋とD橋の床版取替工事の着工前に、A橋とD橋を通過させて床版取替工事を行う重機及び新設床版S2を搬入する。このため、後工程である(2)床版切断工程〜(6)充填材充填工程において、A橋〜D橋の4橋全て同時に行うことが可能となる。よって、床版取替工事の作業効率を向上させて、床版取替工事の工期を短縮することができる。   As described above, according to the simultaneous slab replacement method for a plurality of bridges according to the first embodiment of the present invention, before the start of the slab replacement work for both the A bridge and the D bridge, A heavy machine and a new floor slab S2 that carry out the floor slab replacement work by passing through the D bridge are carried in. For this reason, in (2) floor slab cutting process to (6) filling material filling process, which are subsequent processes, all four bridges of A bridge to D bridge can be performed simultaneously. Therefore, the work efficiency of the floor slab replacement work can be improved and the construction period of the floor slab replacement work can be shortened.

また、第1実施形態に係る複数橋の床版同時取替工法によれば、A橋とD橋の床版取替工事の着工前に、トレーラーTLやフォークリフトなどの資材移動手段をエリアA2やエリアA4に搬入する。このため、A橋とD橋の床版取替工事の着工後にも、エリアA2やエリアA4において、撤去した既設床版S1のストック位置と、新設床版S2のストック位置等を容易に入れ替えることができる。よって、床版取替工事の作業効率を向上させて、さらに工期を短縮することができる。   Further, according to the simultaneous replacement method of the floor slabs of the plurality of bridges according to the first embodiment, the material transfer means such as the trailer TL or the forklift is set in the area A2 or the like before the start of the floor slab replacement work of the A bridge and the D bridge. Carry into area A4. For this reason, even after the start of the slab replacement work for the A and D bridges, the stock position of the removed existing slab S1 and the stock position of the newly installed slab S2 can be easily replaced in area A2 and area A4. Can do. Therefore, the work efficiency of the floor slab replacement work can be improved and the construction period can be further shortened.

[第2実施形態]
次に、図3、図4を用いて、本発明の第2実施形態に係る複数橋の床版同時取替工法について説明する。第1実施形態と同様に、本実施形態に係る複数橋の床版同時取替工法を適用してA橋〜D橋までの4つの橋の床版を同一施工期間内に同時に取り替える場合を例示して説明する。
[Second Embodiment]
Next, the simultaneous replacement method for floor slabs of a plurality of bridges according to the second embodiment of the present invention will be described with reference to FIGS. As in the first embodiment, the case where the floor slabs of four bridges from A bridge to D bridge are simultaneously replaced within the same construction period by applying the method of simultaneous replacement of the slabs of multiple bridges according to this embodiment is illustrated. To explain.

図3は、本発明の第2実施形態に係る複数橋の床版同時取替工法の各工程を示すフローチャートであり、図4は、本発明の第2実施形態に係る複数橋の床版同時取替工法を説明する説明図である。   FIG. 3 is a flowchart showing the steps of the simultaneous replacement method for a plurality of bridge slabs according to the second embodiment of the present invention, and FIG. 4 shows the simultaneous slab for a plurality of bridges according to the second embodiment of the present invention. It is explanatory drawing explaining a replacement construction method.

(1)重機資材搬入工程
図3、図4に示すように、第2実施形態に係る複数橋の床版同時取替工法では、A橋〜D橋のうち、両端に位置するA橋とD橋の床版取替工事の着工前に、A橋とD橋を通過させて床版取替工事を行う重機及び新設床版S2を搬入する重機資材搬入工程を行う。
(1) Heavy machinery material carrying-in process As shown in FIGS. 3 and 4, in the simultaneous slab replacement method for multiple bridges according to the second embodiment, A bridge and D located at both ends of A bridge to D bridge. Prior to the start of the bridge slab replacement work, a heavy equipment material carrying-in process for carrying in the heavy slab and the newly installed floor slab S2 through the A bridge and the D bridge is performed.

本工程では、第1実施形態と同様に、A橋の床版取替工事の着工前に、A橋を通過させて、B橋の床版取替工事を行うラフタークレーンCLやトレーラーTLなどの重機や、B橋用の新設床版S2bを、A橋とB橋間のエリアA2に搬入する。それに加え、A橋を通過させてA橋の床版取替工事を行う重機やA橋用の新設床版S2aをエリアA2に搬入する。   In this step, as in the first embodiment, before the start of the bridge slab replacement work of A bridge, the rough terrain crane CL, trailer TL, etc. that passes the A bridge and performs the bridge slab replacement work of B bridge A heavy machine or a new floor slab S2b for the B bridge is carried into the area A2 between the A bridge and the B bridge. In addition, a heavy machine that passes through the A bridge and performs a floor slab replacement work for the A bridge and a new floor slab S2a for the A bridge are carried into the area A2.

また、本工程では、第1実施形態と同様に、D橋の床版取替工事の着工前に、D橋を通過させてC橋の床版取替工事を行う重機やC橋用の新設床版S2cを、D橋とC橋間のエリアA4に搬入する。それに加え、D橋を通過させてD橋の床版取替工事を行う重機やD橋用の新設床版S2dをエリアA2に搬入する。   In addition, in this process, as in the first embodiment, before the start of the D bridge floor slab replacement work, a new heavy machine or C bridge will be installed to pass the D bridge and perform the C bridge floor slab replacement work. The floor slab S2c is carried into the area A4 between the D bridge and the C bridge. In addition, a heavy machine that passes through the D bridge and performs a floor slab replacement work for the D bridge and a new floor slab S2d for the D bridge are carried into the area A2.

(2)床版切断工程
次に、本発明の第2実施形態に係る複数橋の床版同時取替工法では、第1実施形態と同様に、既設床版S1をラフタークレーンCL等で揚重可能な大きさいに切断する床版切断工程を行う。このとき、本実施形態に係る複数橋の床版同時取替工法では、この床版切断工程をA橋〜D橋の4橋全て同時に行う。
(2) Floor slab cutting step Next, in the simultaneous slab replacement method for multiple bridges according to the second embodiment of the present invention, the existing floor slab S1 is lifted by a rough terrain crane CL or the like as in the first embodiment. A floor slab cutting process is performed to cut to a possible size. At this time, in the simultaneous slab replacement method for a plurality of bridges according to the present embodiment, this slab cutting process is performed simultaneously for all four bridges of the A bridge to the D bridge.

(3)既設床版撤去工程
次に、本実施形態に係る複数橋の床版同時取替工法では、前工程で所定の大きさに切断した既設床版S1を撤去する既設床版撤去工程を行う。
(3) Existing floor slab removal process Next, in the simultaneous replacement method of floor slabs of a plurality of bridges according to the present embodiment, an existing floor slab removal process for removing the existing floor slab S1 cut to a predetermined size in the previous process. Do.

本実施形態に係る複数橋の床版同時取替工法では、エリアA1に設置したラフタークレーンCL等を用いて、前工程で切断した既設床版S1をA橋の鋼桁G1上からトレーラーTL等で搬出する。それと同時に、エリアA2に設置したラフタークレーンCL等を用いて、前工程で切断した既設床版S1をB橋の鋼桁G1上から撤去し、エリアA2にストックする。それに加え、エリアA2に設置したもう1台のラフタークレーンCL等を用いて、前工程で切断した既設床版S1をA橋の鋼桁G1上から撤去し、エリアA2にストックする。   In the simultaneous slab replacement method for a plurality of bridges according to the present embodiment, the existing floor slab S1 cut in the previous process is removed from the steel beam G1 of the A bridge by using a rough terrain crane CL or the like installed in the area A1. Unload at. At the same time, the existing floor slab S1 cut in the previous step is removed from the steel beam G1 of the B bridge using a rough terrain crane CL installed in the area A2, and stocked in the area A2. In addition, the existing floor slab S1 cut in the previous process is removed from the steel girder G1 of the A bridge using another rough terrain crane CL installed in the area A2, and stocked in the area A2.

また、これと同時に、エリアA5に設置したラフタークレーンCL等を用いて、前工程で切断した既設床版S1をD橋の鋼桁G1上からトレーラーTL等で搬出する。それと同時に、エリアA4に設置したラフタークレーンCL等を用いて、前工程で切断した既設床版S1をC橋の鋼桁G1上から撤去し、エリアA4の道路及びその周辺にストックする。それに加え、エリアA4に設置したもう1台のラフタークレーンCL等を用いて、前工程で切断した既設床版S1をD橋の鋼桁G1上から撤去し、エリアA4にストックする。   At the same time, using the rough terrain crane CL installed in the area A5, the existing floor slab S1 cut in the previous process is carried out from the steel beam G1 of the D bridge by the trailer TL. At the same time, the existing floor slab S1 cut in the previous process is removed from the steel girder G1 of the C bridge using a rough terrain crane CL installed in the area A4 and stocked on the road in the area A4 and its surroundings. In addition, the existing floor slab S1 cut in the previous process is removed from the steel girder G1 of the D bridge by using another rough terrain crane CL installed in the area A4 and stocked in the area A4.

(4)新設床版設置工程
次に、本実施形態に係る複数橋の床版同時取替工法では、第1実施形態と同様に、新設床版S2を鋼桁G1に載置して所定の位置に据え付ける新設床版設置工程を行う。
(4) New floor slab installation process Next, in the multiple bridge floor slab simultaneous replacement method according to the present embodiment, the new floor slab S2 is placed on the steel girder G1 in the same manner as in the first embodiment. A new floor slab installation process will be installed.

本実施形態に係る複数橋の床版同時取替工法では、エリアA1に設置したラフタークレーンCL等を用いて、A橋までのエリアA1に新たに搬入したA橋用の新設床版S2aをA橋の鋼桁G1上に設置する。それと同時に、エリアA2に設置したラフタークレーンCL等を用いて、前述の重機資材搬入工程でエリアA2に搬入・ストックしておいたB用の新設床版S2bをB橋の鋼桁G1上に設置する。それに加え、エリアA2に設置したもう1台のラフタークレーンCL等を用いて、前述の重機資材搬入工程でエリアA2に搬入・ストックしておいたA橋用の新設床版S2aをA橋の鋼桁G1上に設置する。   In the simultaneous slab replacement method for a plurality of bridges according to the present embodiment, a new floor slab S2a for A bridge newly introduced into the area A1 up to the A bridge using the rough terrain crane CL installed in the area A1 is A. Installed on the steel girder G1 of the bridge. At the same time, using the rough terrain crane CL installed in area A2, the new floor slab S2b for B that has been loaded and stocked in area A2 in the heavy machinery material loading process described above is installed on the steel beam G1 of the B bridge. To do. In addition, using the other rough terrain crane CL installed in area A2, the newly installed floor slab S2a for A bridge that has been loaded and stocked in area A2 in the heavy machinery material loading process described above is used for steel of A bridge. Install on the girder G1.

また、これと同時に、エリアA5に設置したラフタークレーンCL等を用いて、D橋までのエリアA5に新たに搬入したD橋用の新設床版S2dをD橋の鋼桁G1上に設置する。それと同時に、エリアA3に設置したラフタークレーンCL等を用いて、前述の重機資材搬入工程でエリアA4に搬入・ストックしておいたC用の新設床版S2cをC橋の鋼桁G1上に設置する。それに加え、エリアA4に設置したもう1台のラフタークレーンCL等を用いて、前述の重機資材搬入工程でエリアA4に搬入・ストックしておいたD橋用の新設床版S2dをD橋の鋼桁G1上に設置する。   At the same time, the new floor slab S2d for the D bridge newly introduced into the area A5 up to the D bridge is installed on the steel beam G1 of the D bridge using the rough terrain crane CL installed in the area A5. At the same time, using the rough terrain crane CL installed in area A3, the new floor slab S2c for C that has been loaded and stocked in area A4 in the heavy machinery material loading process described above is installed on the steel beam G1 of the C bridge. To do. In addition, using the other rough terrain crane CL installed in area A4, the newly installed floor slab S2d for D bridge that has been loaded and stocked in area A4 in the heavy machinery material loading process described above is used as steel for D bridge. Install on the girder G1.

次に、本実施形態に係る複数橋の床版同時取替工法では、第1実施形態と同様に、(5)スタッド立設工程、及び(6)充填材充填工程を行う。スタッド立設工程と充填材充填工程は、第1実施形態と特に相違がないため説明を省略する。   Next, in the simultaneous slab replacement method for a plurality of bridges according to the present embodiment, (5) a stud standing process and (6) a filler filling process are performed as in the first embodiment. Since the stud erecting step and the filler filling step are not particularly different from those of the first embodiment, description thereof is omitted.

以上の工程を行った後、充填材が硬化するまでの養生期間をとって、新設床版S2上にアスファルト舗装を施すなど、その他の必要な作業を行った上、エリアA2及びエリアA4にストックしていた既設床版S1や残りの資材を搬出する。そして、ラフタークレーンCLなどの自走式揚重機、及びトレーラーTLなどの資材移動手段を含む重機を搬出し、本実施形態に係る複数橋の床版同時取替工法の床版取替作業が終了する。   After performing the above steps, take a curing period until the filler is hardened, and perform other necessary work such as asphalt pavement on the new floor slab S2, and stock it in area A2 and area A4 The existing floor slab S1 and the remaining materials that have been removed are carried out. Then, a self-propelled lifting machine such as a rough terrain crane CL and a heavy machine including a material moving means such as a trailer TL are carried out, and the floor slab replacement work of the simultaneous replacement method of the floor slabs of a plurality of bridges according to this embodiment is completed. To do.

以上のように、本発明の第2実施形態に係る複数橋の床版同時取替工法によれば、両端に位置するA橋とD橋の床版取替工事の着工前に、A橋とD橋を通過させてA橋とD橋の床版取替工事を行う重機及び新設床版S2を搬入する。このため、後工程である(2)床版切断工程〜(4)新設床版設置工程において、A橋とD橋の両側からの床版取替工事が可能となる。よって、床版取替工事の作業効率を向上させて、床版取替工事の工期を短縮することができる。   As described above, according to the simultaneous slab replacement method for a plurality of bridges according to the second embodiment of the present invention, before the start of the slab replacement work for both the A bridge and the D bridge, A heavy machine and a new floor slab S2 for carrying out the floor slab replacement work for the A bridge and the D bridge are carried through the D bridge. For this reason, in the subsequent steps (2) floor slab cutting step to (4) new floor slab installation step, the floor slab replacement work from both sides of the A bridge and the D bridge becomes possible. Therefore, the work efficiency of the floor slab replacement work can be improved and the construction period of the floor slab replacement work can be shortened.

[第3実施形態]
次に、図5、図6を用いて、本発明の第3実施形態に係る複数橋の床版同時取替工法について説明する。本実施形態に係る複数橋の床版同時取替工法を適用してA’橋及びB’橋の2つの橋の床版を同一施工期間内に同時に取り替える場合を例示して説明する。
[Third Embodiment]
Next, the multiple bridge floor slab simultaneous replacement method according to the third embodiment of the present invention will be described with reference to FIGS. 5 and 6. The case where the floor slabs of the two bridges A ′ bridge and B ′ bridge are simultaneously replaced within the same construction period by applying the floor slab simultaneous replacement method according to the present embodiment will be described as an example.

図5は、本発明の第3実施形態に係る複数橋の床版同時取替工法の各工程を示すフローチャートであり、図6は、本発明の第3実施形態に係る複数橋の床版同時取替工法を説明する説明図である。   FIG. 5 is a flowchart showing the steps of the simultaneous replacement method for a plurality of bridge slabs according to the third embodiment of the present invention, and FIG. 6 shows the simultaneous slab for a plurality of bridges according to the third embodiment of the present invention. It is explanatory drawing explaining a replacement construction method.

(1)重機資材搬入工程
図5、図6に示すように、第3実施形態に係る複数橋の床版同時取替工法では、第1及び第2実施形態と同様に、A’橋とB’橋の床版取替工事の着工前に、A’橋とB’橋を通過させて床版取替工事を行う重機及び新設床版S2を搬入する重機資材搬入工程を行う。
(1) Heavy equipment material carrying-in process As shown in FIGS. 5 and 6, in the simultaneous slab replacement method for multiple bridges according to the third embodiment, A ′ bridge and B as in the first and second embodiments. Prior to the start of the bridge slab replacement work, a heavy equipment material carrying-in process for carrying in the heavy slab replacement work and the new floor slab S2 through the A 'and B' bridges is performed.

本工程では、A’橋の床版取替工事の着工前に、A’橋を通過させてA’橋の床版取替工事を行うラフタークレーンCLやトレーラーTLなどの重機や、A橋用の新設床版S2a’を、A’橋とB’橋間のエリアA2’に搬入する。それに加え、B’橋を通過させてB’橋の床版取替工事を行う重機や、B’橋用の新設床版S2aを、エリアA2’に搬入する。   In this process, before the start of the construction work for replacing the floor slab of A 'bridge, heavy equipment such as a rough terrain crane CL and a trailer TL that passes the A' bridge and performs the construction work for replacing the floor slab of A 'bridge, The new floor slab S2a ′ is carried into the area A2 ′ between the A ′ bridge and the B ′ bridge. In addition, a heavy machine that passes through the B 'bridge and performs a floor slab replacement work for the B' bridge and a new floor slab S2a for the B 'bridge are carried into the area A2'.

(2)床版切断工程
次に、本発明の第3実施形態に係る複数橋の床版同時取替工法では、第1実施形態及び第2実施形態と同様に、既設床版S1をラフタークレーンCL等で揚重可能な大きさに切断する床版切断工程を行う。このとき、本実施形態に係る複数橋の床版同時取替工法では、この床版切断工程をA’橋、B’橋で同時に行う。
(2) Floor slab cutting step Next, in the simultaneous slab replacement method for a plurality of bridges according to the third embodiment of the present invention, the existing floor slab S1 is replaced with a rough terrain crane, as in the first and second embodiments. A floor slab cutting process is carried out to cut to a size that can be lifted by CL or the like. At this time, in the simultaneous slab replacement method for a plurality of bridges according to the present embodiment, this slab cutting process is simultaneously performed on the A ′ bridge and the B ′ bridge.

(3)既設床版撤去工程
次に、本実施形態に係る複数橋の床版同時取替工法では、第1実施形態及び第2実施形態と同様に、前工程で所定の大きさに切断した既設床版S1を撤去する既設床版撤去工程を行う。
(3) Existing floor slab removal process Next, in the multiple bridge floor slab simultaneous replacement method according to the present embodiment, as in the first and second embodiments, it was cut into a predetermined size in the previous process. An existing floor slab removal step for removing the existing floor slab S1 is performed.

本実施形態に係る複数橋の床版同時取替工法では、エリアA1’に設置したラフタークレーンCL等を用いて、前工程で切断した既設床版S1をA’橋の鋼桁G1上からトレーラーTL等で搬出する。それと同時に、エリアA2’に設置したラフタークレーンCL等を用いて、前工程で切断した既設床版S1をA’橋の鋼桁G1上から撤去し、エリアA2’にストックする。   In the simultaneous bridge floor slab replacement method according to the present embodiment, the existing floor slab S1 cut in the previous process is trailed from the steel beam G1 of the A 'bridge using the rough terrain crane CL installed in the area A1'. Unload by TL. At the same time, using the rough terrain crane CL installed in the area A2 ', the existing floor slab S1 cut in the previous process is removed from the steel beam G1 of the A' bridge and stocked in the area A2 '.

また、エリアA3’に設置したラフタークレーンCL等を用いて、前工程で切断した既設床版S1をB’橋の鋼桁G1上からトレーラーTL等で搬出する。それと同時に、エリアA2’に設置したラフタークレーンCL等を用いて、前工程で切断した既設床版S1をB’橋の鋼桁G1上から撤去し、エリアA2’にストックする。   Further, using the rough terrain crane CL installed in the area A3 ', the existing floor slab S1 cut in the previous process is carried out from the steel beam G1 of the B' bridge by a trailer TL or the like. At the same time, the existing floor slab S1 cut in the previous process is removed from the steel beam G1 of the B 'bridge using the rough terrain crane CL installed in the area A2' and stocked in the area A2 '.

(4)新設床版設置工程
次に、本実施形態に係る複数橋の床版同時取替工法では、第1実施形態及び第2実施形態と同様に、新設床版S2を鋼桁G1に載置して所定の位置に据え付ける新設床版設置工程を行う。
(4) New floor slab installation process Next, in the multiple bridge floor slab replacement method according to this embodiment, the new floor slab S2 is mounted on the steel girder G1 as in the first and second embodiments. A new floor slab installation process is carried out.

本実施形態に係る複数橋の床版同時取替工法では、エリアA1’に設置したラフタークレーンCL等を用いて、エリアA1’に新たに搬入したA’橋用の新設床版S2a’をA’橋の鋼桁G1上に設置する。それと同時に、エリアA2’に設置したラフタークレーンCL等を用いて、前述の重機資材搬入工程でエリアA2’に搬入・ストックしておいたA’橋用の新設床版S2bをA’橋の鋼桁G1上に設置する。   In the simultaneous slab replacement method for a plurality of bridges according to the present embodiment, a new floor slab S2a ′ for A ′ bridge newly loaded into area A1 ′ is used by using a rough terrain crane CL or the like installed in area A1 ′. 'Install on the steel girder G1 of the bridge. At the same time, using the rough terrain crane CL installed in the area A2 ′, the new floor slab S2b for the A ′ bridge that has been loaded and stocked in the area A2 ′ in the heavy machinery material loading process described above is used for the steel of the A ′ bridge. Install on the girder G1.

また、これと同時に、エリアA3’に設置したラフタークレーンCL等を用いて、B’橋までのエリアA3’に新たに搬入したB’橋用の新設床版S2b’をB’橋の鋼桁G1上に設置する。それと同時に、エリアA2’に設置したもう1台のラフタークレーンCL等を用いて、前述の重機資材搬入工程でエリアA2’に搬入・ストックしておいたB’橋用の新設床版S2bをB’橋の鋼桁G1上に設置する。   At the same time, using a rough terrain crane CL installed in area A3 ′, the newly installed floor slab S2b ′ for B ′ bridge newly introduced into area A3 ′ up to B ′ bridge is replaced with a steel girder for B ′ bridge. Install on G1. At the same time, using the other rough terrain crane CL installed in area A2 ′, the newly installed floor slab S2b for B ′ bridge that has been loaded and stocked in area A2 ′ in the aforementioned heavy machinery material loading process B 'Install on the steel girder G1 of the bridge.

次に、本実施形態に係る複数橋の床版同時取替工法では、第1実施形態及び第2実施形態と同様に、(5)スタッド立設工程、及び(6)充填材充填工程を行う。スタッド立設工程と充填材充填工程は、第1実施形態及び第2実施形態と特に相違がないため説明を省略する。   Next, in the simultaneous slab replacement method for a plurality of bridges according to the present embodiment, (5) a stud standing step and (6) a filler filling step are performed as in the first and second embodiments. . Since the stud erecting step and the filler filling step are not particularly different from the first embodiment and the second embodiment, description thereof is omitted.

以上の工程を行った後、充填材が硬化するまでの養生期間をとって、新設床版S2上にアスファルト舗装を施すなど、その他の必要な作業を行った上、エリアA2’にストックしていた既設床版S1や残りの資材を搬出する。そして、ラフタークレーンCLなどの自走式揚重機、及びトレーラーTLなどの資材移動手段を含む重機を搬出し、本実施形態に係る複数橋の床版同時取替工法の床版取替作業が終了する。   After performing the above steps, take a curing period until the filler hardens, perform other necessary work such as asphalt paving on the new floor slab S2, and stock it in area A2 ' The existing floor slab S1 and the remaining materials are carried out. Then, a self-propelled lifting machine such as a rough terrain crane CL and a heavy machine including a material moving means such as a trailer TL are carried out, and the floor slab replacement work of the simultaneous replacement method of the floor slabs of a plurality of bridges according to this embodiment is completed. To do.

以上のように、本発明の第3実施形態に係る複数橋の床版同時取替工法によれば、A’橋とB’橋の床版取替工事の着工前に、A’橋とB’橋を通過させてA’橋とB’橋の床版取替工事を行う重機及び新設床版S2を搬入する。このため、後工程である(2)床版切断工程〜(4)新設床版設置工程において、A’橋とB’橋の両側からの床版取替工事が可能となる。よって、床版取替工事の作業効率を向上させて、床版取替工事の工期を短縮することができる。   As described above, according to the simultaneous replacement method of floor slabs of a plurality of bridges according to the third embodiment of the present invention, before the start of the floor slab replacement work of A ′ bridge and B ′ bridge, A ′ bridge and B The heavy machinery and the newly installed floor slab S2 that carry out the floor slab replacement work of the A 'and B' bridges through the bridge are carried in. Therefore, in the subsequent steps (2) floor slab cutting step to (4) newly installed floor slab installation step, the floor slab replacement work from both sides of the A 'bridge and the B' bridge becomes possible. Therefore, the work efficiency of the floor slab replacement work can be improved and the construction period of the floor slab replacement work can be shortened.

以上、本発明の第1〜第3実施形態に係る複数橋の床版同時取替工法について詳細に説明した。しかし、前述した又は図示した実施形態は、いずれも本発明を実施するにあたって具体化した一実施形態を示したものに過ぎず、これらによって本発明の技術的範囲が限定的に解釈されてはならないものである。   As mentioned above, the floor slab simultaneous replacement construction method of the plurality of bridges according to the first to third embodiments of the present invention has been described in detail. However, each of the above-described or illustrated embodiments is merely a specific embodiment for carrying out the present invention, and the technical scope of the present invention should not be construed as being limited thereto. Is.

G1:(既設)鋼桁
S1:既設床版
S2:新設床版
S2a:A橋用の新設床版(新設床版)
S2b:B橋用の新設床版(新設床版)
S2c:C橋用の新設床版(新設床版)
S2d:D橋用の新設床版(新設床版)
S2a’:A’橋用の新設床版(新設床版)
S2b’:B’橋用の新設床版(新設床版)
CL:ラフタークレーン
TL:トレーラー
G1: (existing) steel girder S1: existing floor slab S2: new floor slab S2a: new floor slab for A bridge (new floor slab)
S2b: New floor slab for B bridge (new floor slab)
S2c: New floor slab for C bridge (new floor slab)
S2d: New slab for D bridge (new slab)
S2a ': New floor slab for A' bridge (new floor slab)
S2b ': New floor slab for B' bridge (new floor slab)
CL: Rough terrain crane TL: Trailer

第1発明に係る複数橋の床版同時取替工法は、3橋以上の複数の橋の床版を同一施工期間内にまとめて取り替える複数橋の床版同時取替工法であって、同一施工期間内に床版取替工事を行う3橋以上の前記複数の橋のうち、両端に位置する橋の床版取替工事の着工前に、これらの橋のいずれか一方又は両方を通過させて床版取替工事を行う重機及び新設床版を搬入する重機資材搬入工程と、前記両端に位置する橋の床版取替工事の着工後に、前記両端に位置する橋同士を繋ぐ道路とその周辺の一方又は両方に取り替えた既存床版をストックする既存床版ストック工程と、前記両端に位置する橋の床版取替工事の完了後に、これらの橋のいずれか一方又は両方を通過させてストックした既存床版を搬出する既存床版搬出工程と、を備え、前記重機資材搬入工程で搬入した重機及び新設床版を用いて、前記両端に位置する橋とそれ以外の橋の床版取替工事を同一施工期間内に各橋同時に行うことを特徴とする。 The simultaneous slab replacement method for multiple bridges according to the first invention is a simultaneous slab replacement method for multiple bridges in which the slabs of three or more bridges are replaced together within the same construction period. Before starting construction of floor slab replacement work for the bridges located at both ends of the above three or more bridges that will perform floor slab replacement work within the period, either one or both of these bridges will be allowed to pass. Heavy equipment to carry in the slab replacement work and heavy equipment material loading process to carry in the newly installed slab, and the road connecting the bridges located at both ends and the surrounding area after the start of the slab replacement work of the bridge located at both ends After completion of the existing floor slab stocking process for stocking the existing floor slab replaced with one or both of the above and the floor slab replacement work of the bridges located at both ends, the stock is passed through either or both of these bridges. An existing floor slab unloading step for unloading the existing floor slab , Using the heavy machinery and new floor slabs carried in the machine material carrying-in process, the floor slab replacement work for the bridges located at both ends and the other bridges is simultaneously performed within the same construction period .

第1発明〜第発明によれば、重機資材搬入工程で搬入した重機及び新設床版を用いて、両端に位置する橋以外の橋の床版取替工事を行うので、両端に位置する橋とそれ以外の橋の床版取替工事を同時に行うことができる。このため、工期を短縮することができる。 According to 1st invention- 3rd invention, since the floor slab replacement | exchange construction of bridges other than a bridge located in both ends is performed using the heavy machinery carried in the heavy machinery material carrying-in process and a newly installed floor slab, the bridge located in both ends And other bridge deck replacement works can be performed at the same time. For this reason, a construction period can be shortened.

Claims (4)

複数の橋の床版を同一施工期間内にまとめて取り替える複数橋の床版同時取替工法であって、
同一施工期間内に床版取替工事を行う複数の橋のうち、両端に位置する橋の床版取替工事の着工前に、これらの橋のいずれか一方又は両方を通過させて床版取替工事を行う重機及び新設床版を搬入する重機資材搬入工程と、
前記両端に位置する橋の床版取替工事の着工後に、前記両端に位置する橋同士を繋ぐ道路とその周辺の一方又は両方に取り替えた既存床版をストックする既存床版ストック工程と、
前記両端に位置する橋の床版取替工事の完了後に、これらの橋のいずれか一方又は両方を通過させてストックした既存床版を搬出する既存床版搬出工程と、を行うこと
を特徴とする複数橋の床版同時取替工法。
It is a method for simultaneous replacement of multiple slab floor slabs within the same construction period.
Among the multiple bridges that will be replaced during the same construction period, before starting the replacement work for the bridges located at both ends, pass one or both of these bridges to remove the floor slab. Heavy equipment material carrying-in process for carrying in heavy equipment for replacement work and new floor slabs;
After the start of the floor slab replacement work of the bridges located at both ends, an existing floor slab stock process for stocking the existing floor slabs replaced with one or both of the road connecting the bridges located at both ends and the surroundings;
An existing floor slab unloading step of unloading the existing floor slabs stocked by passing through one or both of the bridges after completion of the floor slab replacement work of the bridges located at both ends. The simultaneous replacement method for floor slabs of multiple bridges.
前記重機資材搬入工程では、前記両端に位置する橋の床版取替工事の着工前に、これらの橋のいずれか一方又は両方を通過させてトレーラーやフォークリフトなどの資材移動手段を搬入すること
を特徴とする請求項1に記載の複数橋の床版同時取替工法。
In the heavy machinery material carrying-in process, before starting the construction work for replacing the floor slabs of the bridges located at both ends, the material moving means such as a trailer or a forklift is carried through one or both of these bridges. The simultaneous replacement method for floor slabs of a plurality of bridges according to claim 1 characterized by the above.
前記重機資材搬入工程で搬入した重機及び新設床版を用いて、前記両端に位置する橋のいずれかの橋の床版取替工事を行うこと
を特徴とする請求項1又は2に記載の複数橋の床版同時取替工法。
3. The plurality of bridges according to claim 1, wherein a floor slab replacement work of any one of the bridges located at both ends is performed using the heavy equipment and the new floor slab carried in the heavy equipment material carrying-in process. Bridge floor plate simultaneous replacement method.
床版を同一施工期間内にまとめて取り替える複数の橋の数が3橋以上であり、
前記重機資材搬入工程で搬入した重機及び新設床版を用いて、前記両端に位置する橋以外の橋の床版取替工事を行うこと
を特徴とする請求項1又は2に記載の複数橋の床版同時取替工法。
The number of multiple bridges that replace floor slabs together within the same construction period is 3 or more,
The bridge slab replacement work for bridges other than the bridges located at both ends is performed using the heavy machinery and the newly installed floor slab carried in the heavy machinery material carrying-in process. Floor slab simultaneous replacement method.
JP2017030324A 2017-02-21 2017-02-21 Simultaneous replacement method of floor slabs for multiple bridges Active JP6181332B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017030324A JP6181332B1 (en) 2017-02-21 2017-02-21 Simultaneous replacement method of floor slabs for multiple bridges

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017030324A JP6181332B1 (en) 2017-02-21 2017-02-21 Simultaneous replacement method of floor slabs for multiple bridges

Publications (2)

Publication Number Publication Date
JP6181332B1 JP6181332B1 (en) 2017-08-16
JP2018135677A true JP2018135677A (en) 2018-08-30

Family

ID=59605021

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017030324A Active JP6181332B1 (en) 2017-02-21 2017-02-21 Simultaneous replacement method of floor slabs for multiple bridges

Country Status (1)

Country Link
JP (1) JP6181332B1 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08218327A (en) * 1995-02-09 1996-08-27 Sho Bond Constr Co Ltd Preventive construction of main-girder lateral buckling to be generated in replacement of floor slab of composite girder with precast floor slab
JP2002123456A (en) * 2000-10-13 2002-04-26 Canon Inc Method and device for processing image and storage medium
JP2005307684A (en) * 2004-04-26 2005-11-04 Showa Concrete Ind Co Ltd Laying apparatus of precast concrete floor board
JP2007239365A (en) * 2006-03-10 2007-09-20 Kawada Industries Inc Replacement method of bridge concrete floor plate and concrete floor plate

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08218327A (en) * 1995-02-09 1996-08-27 Sho Bond Constr Co Ltd Preventive construction of main-girder lateral buckling to be generated in replacement of floor slab of composite girder with precast floor slab
JP2002123456A (en) * 2000-10-13 2002-04-26 Canon Inc Method and device for processing image and storage medium
JP2005307684A (en) * 2004-04-26 2005-11-04 Showa Concrete Ind Co Ltd Laying apparatus of precast concrete floor board
JP2007239365A (en) * 2006-03-10 2007-09-20 Kawada Industries Inc Replacement method of bridge concrete floor plate and concrete floor plate

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
福田健作、外5名: "合理化継手を使用したプレキャストPC床版取替工事について", 川田技報, vol. vol.35/jan.,2016, JPN6017009104, 1 January 2016 (2016-01-01), JP, pages 32 - 37, ISSN: 0003519324 *

Also Published As

Publication number Publication date
JP6181332B1 (en) 2017-08-16

Similar Documents

Publication Publication Date Title
CA2880553C (en) Method and apparatus for lifting and leveling a concrete panel
JP5266291B2 (en) Construction method of bridge deck and joint structure of precast deck
CN106703834A (en) Secondary lining integral formworking construction method for tunnel with super-large cross section
JP3867149B2 (en) Steel slab structure of bridge and steel slab reinforcement method
JP2015229818A (en) Composite structure of steel girder and precast floor slab, and construction method therefor
CN110005169A (en) A kind of cracking resistance process with stressed seamless terrace
CN113250098A (en) New bridge and old bridge wet joint crack-resistant construction method and new bridge and old bridge wet joint crack-resistant structure
JP6771987B2 (en) Floor slab replacement method for steel synthetic girders and PC floor slab
CN101082382A (en) Lay out method of pipeline and synthetic pipeline with pipe frame component
CN113681676B (en) High-temperature steam-curing construction method for UHPC steel-concrete composite beam prefabricated bridge deck without coarse aggregate
JP2007327255A (en) Fatigue-resistant steel floor slab
JP6715667B2 (en) Reconstruction method for lining of existing 2-lane road tunnel
JP2007107195A (en) Steel floor slab reinforcing construction method and precast reinforcing slab used therefor
JP6181332B1 (en) Simultaneous replacement method of floor slabs for multiple bridges
KR101404481B1 (en) Bridge construction method using road decking panel at limited space for girder manufacturing
KR101705315B1 (en) Precast concrete panels and their installation method
US6595718B2 (en) Exo-lift
JP6969909B2 (en) How to reinforce steel synthetic girders
JP6541520B2 (en) Renewed construction method of existing road and rebuilt road
CN114562129A (en) Trinity reinforcing method for basement roof on crawler crane
JP7185567B2 (en) Bridge pier repair method
CN114561873A (en) Bridge high pier construction method
KR101258841B1 (en) Precast concrete slab construction method of bridge
KR102193641B1 (en) Thin precast pavement structure, construction method of thin precast pavement, and manufacturing method of thin precast pavement
CN115366247B (en) Pretensioned prestressed concrete hollow slab tensioning construction method

Legal Events

Date Code Title Description
A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20170516

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20170718

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20170719

R150 Certificate of patent or registration of utility model

Ref document number: 6181332

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250