CN114561873A - Bridge high pier construction method - Google Patents
Bridge high pier construction method Download PDFInfo
- Publication number
- CN114561873A CN114561873A CN202210257561.4A CN202210257561A CN114561873A CN 114561873 A CN114561873 A CN 114561873A CN 202210257561 A CN202210257561 A CN 202210257561A CN 114561873 A CN114561873 A CN 114561873A
- Authority
- CN
- China
- Prior art keywords
- formwork
- construction
- pier
- reinforcement cage
- pier column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/02—Piers; Abutments ; Protecting same against drifting ice
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/30—Adapting or protecting infrastructure or their operation in transportation, e.g. on roads, waterways or railways
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明公开了一种桥梁高墩施工方法,包括如下具体步骤:1)承台施工;2)墩柱钢筋施工;3)墩柱模板施工;4)浇筑施工;5)墩柱养护。本发明中,墩柱主筋用伸缩杆与钢管架连接,防止承台浇筑时钢筋上浮现象发生,提高了墩柱预埋主筋的施工精度;上层钢筋笼通过固定架临时焊接固定,固定架上设置托架筋,托架筋设置于焊缝上部,伸缩杆一端与抱箍耳板连接,抱箍耳板与抱箍体,为钢筋笼焊接施工提供了临时工作平台,降低了上层钢筋笼焊接的施工难度;在墩柱上设置系梁抱箍支模体系和钢模板对拉自稳体系,模板施工方便快捷;混凝土分次浇筑时采用冷缝模板,超灌混凝土从漏浆孔中回收,减少冷缝凿除施工。
The invention discloses a construction method for a high pier of a bridge, comprising the following specific steps: 1) construction of a cap; 2) construction of steel bars for a pier column; 3) construction of a pier column formwork; 4) pouring construction; 5) pier column maintenance. In the present invention, the main reinforcement of the pier column is connected with the steel pipe frame by a telescopic rod, which prevents the steel bar from floating up when the cap is poured, and improves the construction accuracy of the pre-buried main reinforcement of the pier column; the upper reinforcement cage is temporarily welded and fixed by the fixing frame, and the fixing frame is provided Bracket rib, the bracket rib is arranged on the upper part of the welding seam, one end of the telescopic rod is connected with the hoop ear plate, the hoop ear plate and the hoop body provide a temporary working platform for the welding construction of the reinforcement cage, and reduce the welding time of the upper reinforcement cage. Difficulty in construction; the tie beam hoop formwork support system and the steel formwork self-stabilizing system are set on the pier column, and the formwork construction is convenient and fast; when the concrete is poured in stages, the cold joint formwork is used, and the overfilled concrete is recovered from the leakage hole, reducing the Cold seam chiseling construction.
Description
技术领域technical field
本发明涉及一种桥梁高墩施工方法,主要适用于城市高架桥的高墩施工。The invention relates to a construction method for high piers of bridges, which is mainly suitable for the construction of high piers of urban viaducts.
背景技术Background technique
随着城市化进程的推进,城市各项发展离不开公路桥梁,推进了公路桥梁建设施工水平的提高。车辆的增多,对公路桥梁的质量提出更高要求,在一定程度上将公路桥梁高墩施工难度增大。做好高墩施工成为保证工程质量的重中之重。With the advancement of urbanization, the development of cities is inseparable from highways and bridges, which has promoted the improvement of the construction level of highways and bridges. The increase of vehicles has put forward higher requirements for the quality of highway bridges, and to a certain extent, the construction of high piers of highway bridges has become more difficult. Doing a good job in the construction of high piers has become the top priority of ensuring the quality of the project.
高墩施工是公路桥梁重要施工内容,施工会遇到以下施工问题:(1)承台浇筑施工时对墩柱预埋筋的抗浮作用,导致墩柱主筋定位不精准;(2)花瓶墩模板控制不精准;(3)上层钢筋笼临时焊接时临时稳固难题;(4)冷缝处理施工;(5)高墩喷淋养生施工。The construction of high piers is an important construction content of highway bridges. The construction will encounter the following construction problems: (1) The anti-floating effect of the pre-embedded reinforcement of the pier column during the pouring construction of the cap, resulting in inaccurate positioning of the main reinforcement of the pier column; (2) The vase pier Inaccurate control of formwork; (3) temporary stabilization problem during temporary welding of upper reinforcement cage; (4) cold seam treatment construction; (5) high pier spray health construction.
鉴于此,针对高墩施工时出现的一系列问题,亟待发明一种简单有效的桥梁高墩结构,来满足高墩施工质量控制要求,尤其对于城市高架高墩施工,具有显著节约施工成本、加快施工进度的优势。In view of this, in view of a series of problems in the construction of high piers, it is urgent to invent a simple and effective bridge high pier structure to meet the quality control requirements of high pier construction, especially for urban elevated high pier construction, which can significantly save construction costs and speed up Advantages of construction progress.
发明内容SUMMARY OF THE INVENTION
本发明的目的在于满足高墩施工质量控制要求,尤其对于城市高架高墩施工,具有显著节约施工成本、加快施工进度的优势。The purpose of the present invention is to meet the quality control requirements of high pier construction, especially for urban elevated high pier construction, it has the advantages of significantly saving construction costs and accelerating construction progress.
为实现上述技术目的,本发明采用了以下技术方案:For realizing the above-mentioned technical purpose, the present invention has adopted the following technical solutions:
一种桥梁高墩施工方法,包括如下具体步骤:A method for constructing a high pier of a bridge, comprising the following specific steps:
1)承台施工;承台浇筑前,在承台浇筑位置四周设置钢管架,然后绑扎承台主筋和连接筋,绑扎后得到承台骨架,并在承台骨架上绑扎墩柱主筋,墩柱主筋之间用钢丝固定,最外侧的墩柱主筋通过连接伸缩旋杆与钢管架连接,随后对承台进行浇筑,浇筑后,墩柱主筋伸出于承台的部分形成墩柱底部预埋主筋;1) Construction of the cap; The main reinforcement is fixed with steel wire, and the outermost main reinforcement of the pier column is connected with the steel pipe frame by connecting the telescopic rotating rod, and then the cap is poured. ;
2)墩柱钢筋施工;通过吊装工具将上层钢筋笼吊装至与墩柱底部预埋主筋对接的位置,并通过固定架临时焊接固定,随后将上层钢筋笼上的主筋逐根与墩柱底部预埋主筋焊接,焊接完成后拆除固定架;2) Reinforcing construction of the pier column; hoist the upper reinforcement cage to the position where it is connected to the pre-buried main reinforcement at the bottom of the pier column by hoisting tools, and temporarily weld and fix it through the fixing frame, and then connect the main reinforcement on the upper reinforcement cage to the pre-buried main reinforcement at the bottom of the pier column one by one. The main reinforcement is welded, and the fixing frame is removed after the welding is completed;
3)墩柱模板施工;在上层钢筋笼外侧安装钢模板,钢模板通过对拉第一螺栓拼装成型,用对拉第二螺栓使两侧钢模板体系固定,在系梁处设置系梁抱箍模板;3) Construction of pier and column formwork; steel formwork is installed on the outer side of the upper reinforcement cage, the steel formwork is assembled and formed by the first pair of bolts, the steel formwork system on both sides is fixed by the second pair of bolts, and the tie beam hoop is set at the tie beam template;
4)浇筑施工;冷缝浇筑前安装冷缝模板,冷缝模板安装于钢模板上,冷缝模板由模板本体和漏浆模板组成,漏浆模板上设置漏浆孔;4) Pouring construction; install cold seam formwork before pouring cold seam, cold seam formwork is installed on steel formwork, cold seam formwork is composed of formwork body and grout leakage formwork, and grout leakage hole is set on grout leakage formwork;
5)墩柱养护;墩柱在脱模后设置养护设备,养护设备的两侧用钢丝绳与绳筒连接,绳筒设置在墩柱的两侧,绳筒上设置电机,在墩柱四周设置养护架,养护架上设置轮滑,钢丝绳绕过滑轮,在墩柱下设置集水沟,集水沟内铺防渗布。5) Maintenance of the pier column; the pier column is set with maintenance equipment after demoulding, and the two sides of the maintenance equipment are connected with the rope drum with steel wire ropes. Roller skating is set on the maintenance frame, the wire rope goes around the pulley, a water collecting ditch is set under the pier column, and the anti-seepage cloth is laid in the water collecting ditch.
2.根据权利要求1所述的桥梁高墩施工方法,其特征在于,步骤1)中,连接伸缩旋杆一端与墩柱主筋相连,另一端通过连接扣件与钢管架相连。2. The method for constructing high bridge piers according to
作为优选,步骤2)中,在吊装现场的四周设置预埋固定件,上层钢筋笼通过缆风绳与四周的预埋固定件相连,缆风绳上设置手拉葫芦,通过手拉葫芦调节各个缆风绳的长度,从而对上层钢筋笼进行位置控制。Preferably, in step 2), pre-embedded fixtures are arranged around the hoisting site, the upper-layer reinforcement cage is connected to the surrounding pre-embedded fixtures through cable wind ropes, chain hoists are set on the cable wind ropes, and each The length of the cable wind rope to control the position of the upper reinforcement cage.
作为优选,步骤2)中,在对上层钢筋笼进行吊装时,在上层钢筋笼上安装有激光定位仪,通过激光定位仪对上层钢筋笼的位置进行检测,辅助控制上层钢筋笼的位置。Preferably, in step 2), when the upper reinforcement cage is hoisted, a laser locator is installed on the upper reinforcement cage, and the position of the upper reinforcement cage is detected by the laser locator to assist in controlling the position of the upper reinforcement cage.
作为优选,步骤2)中,固定架包括抱箍体、伸缩杆,抱箍体内侧设有若干个托架筋,抱箍体外侧设有若干个抱箍耳板,伸缩杆一端与抱箍耳板连接,另一端固定在承台上;在通过固定架对上层钢筋笼进行临时焊接固定时,将上层钢筋笼吊至固定架中,通过抱箍体上的托架筋托住上层钢筋笼并将托架筋与上层钢筋笼临时焊接固定;通过调节伸缩杆的高度来调节上层钢筋笼的固定高度,使上层钢筋笼上的主筋与墩柱底部预埋主筋一一对准。Preferably, in step 2), the fixing frame includes a hoop body and a telescopic rod, a number of bracket ribs are provided on the inside of the hoop body, and a number of hoop ear plates are provided on the outside of the hoop body, and one end of the telescopic rod is connected to the hoop ear When the upper reinforcement cage is temporarily welded and fixed by the fixing frame, the upper reinforcement cage is hoisted into the fixing frame, and the upper reinforcement cage is supported by the bracket bars on the hoop body. The bracket bars and the upper reinforcement cage are temporarily welded and fixed; the fixed height of the upper reinforcement cage is adjusted by adjusting the height of the telescopic rod, so that the main reinforcement on the upper reinforcement cage and the embedded main reinforcement at the bottom of the pier column are aligned one by one.
作为优选,所述抱箍体由两个半体组成,两个半体的一端之间铰接,两个半体的另一端上均设有抱箍连接口,两个半体上的抱箍连接口可通过螺栓连接。Preferably, the hoop body is composed of two halves, one end of the two halves is hinged, the other end of the two halves is provided with a hoop connection port, and the hoop on the two halves is connected The ports can be connected by bolts.
作为优选,步骤5)中,钢模板设置连接板,钢模板与冷缝模板之间用螺栓连接。Preferably, in step 5), the steel formwork is provided with a connecting plate, and the steel formwork and the cold seam formwork are connected by bolts.
作为优选,步骤5)中,漏浆模板上设置防滑纹和加强板。Preferably, in step 5), anti-skid patterns and reinforcing plates are arranged on the slurry leakage template.
本发明具有以下的特点和有益效果:The present invention has the following characteristics and beneficial effects:
1.墩柱主筋用伸缩杆与钢管架连接,防止承台浇筑时钢筋上浮现象发生,提高了墩柱预埋主筋的施工精度。1. The main reinforcement of the pier column is connected with the steel pipe frame by a telescopic rod, which prevents the reinforcement from floating up when the cap is poured, and improves the construction accuracy of the pre-buried main reinforcement of the pier column.
2.上层钢筋笼通过固定架临时焊接固定,固定架上设置托架筋,托架筋设置于焊缝上部,伸缩杆一端与抱箍耳板连接,抱箍耳板与抱箍体,为钢筋笼焊接施工提供了临时工作平台,降低了上层钢筋笼焊接的施工难度。2. The upper reinforcement cage is temporarily welded and fixed by the fixing frame. The fixing frame is provided with bracket ribs. The bracket ribs are arranged on the upper part of the welding seam. One end of the telescopic rod is connected with the hoop ear plate. The hoop ear plate and the hoop body are steel bars. The cage welding construction provides a temporary working platform, which reduces the construction difficulty of the upper reinforcement cage welding.
3.在墩柱上设置系梁抱箍支模体系和钢模板对拉自稳体系,模板施工方便快捷。3. The tie beam and hoop formwork support system and the steel formwork self-stabilizing system are set on the pier column, and the formwork construction is convenient and fast.
4.混凝土分次浇筑时采用冷缝模板,超灌混凝土从漏浆孔中回收,减少冷缝凿除施工。4. The cold joint formwork is used when the concrete is poured in stages, and the overfilled concrete is recovered from the slurry leakage hole to reduce the cold joint chiseling construction.
5.墩柱在脱模后设置养护设备,实现墩柱养护智能化作业。5. After the pier column is demolded, the maintenance equipment is set to realize the intelligent maintenance of the pier column.
附图说明Description of drawings
图1是本发明墩柱模板对拉示意图;Fig. 1 is the schematic diagram of pier column formwork pair pulling of the present invention;
图2是上层钢筋笼吊装示意图;Figure 2 is a schematic diagram of the hoisting of the upper reinforcement cage;
图3是上层钢筋笼焊接临时固定示意图;Figure 3 is a schematic diagram of the temporary fixation of the upper reinforcement cage welding;
图4是固定架的结构示意图;Fig. 4 is the structural representation of the fixing frame;
图5是冷缝模板的结构示意图;Fig. 5 is the structural representation of cold seam formwork;
图6是承台钢筋结构临时固定示意图;Figure 6 is a schematic diagram of the temporary fixing of the reinforcing steel structure of the cap;
图7是墩柱养护设备的示意图。Figure 7 is a schematic diagram of the pier column maintenance equipment.
其中:1.承台、2.对拉第一螺栓、3.对拉第二螺栓、4.系梁抱箍模板、5.钢模板、6.吊装工具、7.钢绳、8.缆风绳、9.手拉葫芦、10.预埋固定件、11.激光定位仪、12.吊装加强筋、13.上层钢筋笼、14.抱箍连接位、15.抱箍耳板、16.伸缩杆、17.墩柱底部预埋主筋、18.焊缝、19.抱箍体、20.箍筋、21.抱箍连接口、22.托架筋、23.防滑纹、24.加强板、25.模板本体、26.螺栓连接、27.连接板、28.漏浆孔、29.滑轮、30.钢丝绳、31.绳筒、32.电机、33.集水沟、34.防渗布、38.养护设备、39.钢管连接扣件、40.钢管架、41.连接筋、42.承台主筋、43.墩柱主筋、44.连接伸缩旋杆、45.墩柱、46.固定架、47.钢丝、48.系梁、49.冷缝模板、50.漏浆模板、51.养护架、52.混凝土。Among them: 1. Bearing platform, 2. The first bolt of the pair, 3. The second bolt of the pair, 4. The beam hoop formwork, 5. The steel formwork, 6. The lifting tool, 7. The steel rope, 8. The cable wind Rope, 9. Chain hoist, 10. Embedded fixture, 11. Laser locator, 12. Hoisting reinforcement, 13. Upper reinforcement cage, 14. Hoop connection position, 15. Hoop ear plate, 16. Telescopic Rod, 17. Pre-embedded main reinforcement at the bottom of pier column, 18. Welding seam, 19. Hoop body, 20. Hoop reinforcement, 21. Hoop connection port, 22. Bracket reinforcement, 23. Anti-skid pattern, 24. Reinforcing plate, 25. Formwork body, 26. Bolt connection, 27. Connecting plate, 28. Slurry hole, 29. Pulley, 30. Steel wire rope, 31. Rope drum, 32. Motor, 33. Ditch, 34. Anti-seepage cloth, 38. Maintenance equipment, 39. Steel pipe connection fasteners, 40. Steel pipe frame, 41. Connecting bars, 42. Main reinforcement of caps, 43. Main reinforcement of pier columns, 44. Connecting telescopic rods, 45. Pier columns, 46. Fixed frame , 47. Steel wire, 48. Tie beam, 49. Cold joint formwork, 50. Slurry formwork, 51. Curing frame, 52. Concrete.
具体实施方式Detailed ways
实施例一Example 1
所述桥梁高墩结构,包括承台1、墩柱45、上层钢筋笼13、钢模板5、养护设备38、上层钢筋笼13、固定架46等,还包括钢筋骨架定位装置、吊装定位装置、墩柱养护喷淋系统。The high pier structure of the bridge includes a
如图6所示,承台主筋42、连接筋41、墩柱主筋43绑扎后,相邻墩柱主筋43之间用钢丝47连接固定,墩柱主筋43竖直设置,最外侧的墩柱主筋43通过钢筋骨架定位装置进行固定。具体的,钢筋骨架定位装置包括,设置在承台1四周的钢管架40、连接伸缩旋杆44,最外侧的墩柱主筋43通过连接伸缩旋杆44与钢管架40相连。具体的,连接伸缩旋杆44的一端与墩柱主筋43相连,连接伸缩旋杆44的另一端设置连接扣件39并通过连接扣件39与钢管架10相连。由于最外侧的墩柱主筋43通过连接伸缩旋杆44与钢管架40相连,从而将承台主筋42、连接筋41、墩柱主筋43固定住,然后浇筑承台,承台浇筑完成后,墩柱主筋43伸出于承台的部分形成墩柱底部预埋主筋17。墩柱主筋用连接伸缩旋杆44与钢管架10连接,防止承台浇筑时钢筋上浮现象发生,提高了墩柱预埋主筋的施工精度。As shown in FIG. 6 , after the
如图2所示,上层钢筋笼13采用吊装工具6吊装,钢绳7连接设置在上层钢筋笼13上的吊装加强筋12和吊装工具6,通过吊装定位装置对上层钢筋笼13进行精准吊装,吊装定位装置包括设置在吊装现场四周的预埋固定件10,上层钢筋笼13通过缆风绳8与四周的预埋固定件10相连,缆风绳8上设置手拉葫芦9。在吊装时,上层钢筋笼13上安装有激光定位仪11,激光定位仪11为现有技术,激光定位仪11用于检测上层钢筋笼13的位置。其中,吊装工具6可以是吊车、起重机等。上层钢筋笼13外侧环绕设置有箍筋20。As shown in FIG. 2 , the
如图3和图4所示,固定架46包括抱箍体19、伸缩杆16,抱箍体19内侧设有托架筋22,抱箍体19外侧设有若干个抱箍耳板15,伸缩杆16一端与抱箍耳板15连接,另一端固定在承台1上。上层钢筋笼13在吊装时通过固定架46临时焊接固定,将上层钢筋笼13上的主筋逐根与墩柱底部预埋主筋17焊接,上层钢筋笼13与墩柱底部预埋主筋17的连接处形成焊缝18。托架筋22设置于焊缝18上部。As shown in FIGS. 3 and 4 , the fixing
其中,抱箍体19由两个半体组成,两个半体的一端之间在抱箍连接位14处铰接,两个半体的另一端上均设有抱箍连接口21,两个半体上的抱箍连接口21可通过螺栓连接。Among them, the
如图1所示,钢模板5通过对拉第一螺栓2拼装形成钢模板总成,用对拉第二螺栓3将两侧的钢模板总成连接固定,在系梁48设置系梁抱箍模板4,系梁抱箍模板4设置在两个钢模板总成之间。As shown in FIG. 1 , the
如图5所示,钢模板5与冷缝模板49用螺栓27连接,冷缝模板49连接在钢模板5的上方,钢模板5设置连接板7,冷缝模板49由模板本体25和漏浆模板50组成,漏浆模板50上设置漏浆孔28,漏浆模板上设置防滑纹23和加强板24。As shown in FIG. 5 , the
如图7所示,所述墩柱45在脱模后设置墩柱养护喷淋系统,墩柱养护喷淋系统包括养护设备38,具体的,养护设备38为一个作业平台,作业平台中间设置有通槽,墩柱45从通槽中穿过。养护设备38的两侧用钢丝绳30与绳筒31连接,绳筒31位于墩柱的两侧,绳筒31上设置电机32,在墩柱45四周设置养护架51,养护架51上设置轮滑29,钢丝绳30绕过滑轮29,在墩柱45下设置集水沟33,集水沟33内铺防渗布34。本方案中,集水沟33设置在墩柱45的两侧。通过电机32带动绳筒31旋转从而实现钢丝绳的收放,进而实现养护设备38的升降。As shown in FIG. 7 , the
实施例二
一种桥梁高墩结构的施工方法,包括以下步骤:A construction method for a high pier structure of a bridge, comprising the following steps:
(1)承台施工;承台浇筑前,在承台1浇筑位置四周设置钢管架40,然后绑扎承台主筋42和连接筋41,承台主筋42和连接筋41以横纵交错的方式进行绑扎,绑扎后得到承台骨架,并在承台骨架上绑扎墩柱主筋43,墩柱主筋43之间用钢丝47固定,最外侧的墩柱主筋43通过连接伸缩旋杆44与钢管架40连接,连接伸缩旋杆44一端与墩柱主筋43相连,另一端通过连接扣件39与钢管架40相连;随后对承台进行浇筑,浇筑后,墩柱主筋43伸出于承台的部分形成墩柱底部预埋主筋17。(1) Construction of the cap; before the cap is poured, the
(2)墩柱钢筋施工;上层钢筋笼13施工采用吊装工具6配合缆风绳8控制;在吊装现场的四周设置预埋固定件10,上层钢筋笼13通过缆风绳8与四周的预埋固定件10相连,缆风绳8上设置手拉葫芦9,通过手拉葫芦9调节各个缆风绳8的长度,从而对上层钢筋笼13进行位置控制;在上层钢筋笼13上安装激光定位仪11,借助激光定位仪11辅助定位,采用固定架46临时焊接固定,固定架46上设置抱箍体19和托架筋22,托架筋22设置于焊缝18上部并位于抱箍体19的内侧,伸缩杆16一端与抱箍体19上的抱箍耳板15连接;在通过固定架46对上层钢筋笼13进行临时焊接固定时,将上层钢筋笼13吊至固定架46中,通过抱箍体19上的托架筋22托住上层钢筋笼13并将托架筋22与上层钢筋笼13临时焊接固定;通过调节伸缩杆16的高度来调节上层钢筋笼13的固定高度,使上层钢筋笼13上的主筋与墩柱底部预埋主筋17一一对准,并逐根将上层钢筋笼13上的主筋与墩柱底部预埋主筋17焊接,随后拆除固定架46。(2) Construction of pier and column reinforcement; the construction of the
(3)墩柱模板施工;在上层钢筋笼13外侧安装钢模板5,钢模板5通过对拉第一螺栓2拼装成型,用对拉第二螺栓2使两侧钢模板体系固定,在系梁48处设置系梁抱箍模板4。上层钢筋笼13位于钢模板5中。(3) Construction of pier and column formwork;
(4)浇筑施工;冷缝浇筑前安装冷缝模板,钢模板5与冷缝模板49用螺栓27连接,冷缝模板49安装于钢模板5上,钢模板5设置连接板7,冷缝模板49由模板本体25和漏浆模板50组成,漏浆模板50上设置漏浆孔28,漏浆模板上设置防滑纹23和加强板24;(4) pouring construction; install cold seam formwork before cold seam pouring,
(5)墩柱养护;墩柱45在脱模后设置养护设备38,养护设备38的两侧用钢丝绳30与绳筒31连接,绳筒31设置在墩柱45的两侧,绳筒31上设置电机32,在墩柱45四周设置养护架51,养护架51上设置轮滑29,钢丝绳30绕过滑轮29,在墩柱45下设置集水沟33,集水沟33内铺防渗布34。(5) Maintenance of the pier column; the
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210257561.4A CN114561873B (en) | 2022-03-16 | 2022-03-16 | Construction method of high bridge pier |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210257561.4A CN114561873B (en) | 2022-03-16 | 2022-03-16 | Construction method of high bridge pier |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN114561873A true CN114561873A (en) | 2022-05-31 |
| CN114561873B CN114561873B (en) | 2023-08-08 |
Family
ID=81720018
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202210257561.4A Expired - Fee Related CN114561873B (en) | 2022-03-16 | 2022-03-16 | Construction method of high bridge pier |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN114561873B (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115110423A (en) * | 2022-06-24 | 2022-09-27 | 保利长大工程有限公司 | Rectangular pier construction process |
| CN118619070A (en) * | 2024-07-09 | 2024-09-10 | 核工业华东建设工程集团有限公司 | A formwork erection device for bridge construction |
Citations (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH10325126A (en) * | 1997-05-26 | 1998-12-08 | Nippon Steel Corp | Equipment for work on the underside of the Yasu Bridge structure |
| US8375678B1 (en) * | 2009-09-28 | 2013-02-19 | Felix E. Ferrer | Methods for construction of pre-fabricated modular reinforcement cages for concrete structures |
| JP2013108346A (en) * | 2011-10-26 | 2013-06-06 | Kajima Corp | Reinforcing method for reinforced concrete member |
| CN205676897U (en) * | 2016-06-22 | 2016-11-09 | 中国葛洲坝集团第五工程有限公司 | One is positioned at original ground following pier stud constructing device |
| CN106677069A (en) * | 2016-12-28 | 2017-05-17 | 杭州江润科技有限公司 | Construction method for overall formwork one-time forming structure of pier |
| WO2017084113A1 (en) * | 2015-08-10 | 2017-05-26 | 陈修缘 | Assembled lifting construction platform for pier column construction and construction method thereof |
| JP2018135688A (en) * | 2017-02-22 | 2018-08-30 | 三井住友建設株式会社 | Bridge pier and construction method thereof |
| CN109958061A (en) * | 2019-04-12 | 2019-07-02 | 北京市政建设集团有限责任公司 | A kind of working reinforcement installation method |
| WO2020001156A1 (en) * | 2018-06-29 | 2020-01-02 | 比亚迪股份有限公司 | Bridge and bridge pier thereof |
| CN111206493A (en) * | 2020-03-06 | 2020-05-29 | 中国电建集团贵阳勘测设计研究院有限公司 | Construction method and formwork device used to improve the qualified rate of steel bar protection layer for pier columns |
| CN111379219A (en) * | 2020-04-20 | 2020-07-07 | 中铁四局集团第二工程有限公司 | A prefabricated bridge pier column and cap connection structure and construction method thereof |
-
2022
- 2022-03-16 CN CN202210257561.4A patent/CN114561873B/en not_active Expired - Fee Related
Patent Citations (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH10325126A (en) * | 1997-05-26 | 1998-12-08 | Nippon Steel Corp | Equipment for work on the underside of the Yasu Bridge structure |
| US8375678B1 (en) * | 2009-09-28 | 2013-02-19 | Felix E. Ferrer | Methods for construction of pre-fabricated modular reinforcement cages for concrete structures |
| JP2013108346A (en) * | 2011-10-26 | 2013-06-06 | Kajima Corp | Reinforcing method for reinforced concrete member |
| WO2017084113A1 (en) * | 2015-08-10 | 2017-05-26 | 陈修缘 | Assembled lifting construction platform for pier column construction and construction method thereof |
| CN205676897U (en) * | 2016-06-22 | 2016-11-09 | 中国葛洲坝集团第五工程有限公司 | One is positioned at original ground following pier stud constructing device |
| CN106677069A (en) * | 2016-12-28 | 2017-05-17 | 杭州江润科技有限公司 | Construction method for overall formwork one-time forming structure of pier |
| JP2018135688A (en) * | 2017-02-22 | 2018-08-30 | 三井住友建設株式会社 | Bridge pier and construction method thereof |
| WO2020001156A1 (en) * | 2018-06-29 | 2020-01-02 | 比亚迪股份有限公司 | Bridge and bridge pier thereof |
| CN109958061A (en) * | 2019-04-12 | 2019-07-02 | 北京市政建设集团有限责任公司 | A kind of working reinforcement installation method |
| CN111206493A (en) * | 2020-03-06 | 2020-05-29 | 中国电建集团贵阳勘测设计研究院有限公司 | Construction method and formwork device used to improve the qualified rate of steel bar protection layer for pier columns |
| CN111379219A (en) * | 2020-04-20 | 2020-07-07 | 中铁四局集团第二工程有限公司 | A prefabricated bridge pier column and cap connection structure and construction method thereof |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115110423A (en) * | 2022-06-24 | 2022-09-27 | 保利长大工程有限公司 | Rectangular pier construction process |
| CN118619070A (en) * | 2024-07-09 | 2024-09-10 | 核工业华东建设工程集团有限公司 | A formwork erection device for bridge construction |
Also Published As
| Publication number | Publication date |
|---|---|
| CN114561873B (en) | 2023-08-08 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101781878B (en) | Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof | |
| CN105401679B (en) | Heavy grade cast-in-place concrete Sloping roof construction method | |
| CN205025086U (en) | Strength nature skeleton concrete beam construction suspend template in midair | |
| CN214459710U (en) | Wet seam hanging mould hoisting equipment | |
| CN112554077B (en) | Construction system and method of steel tube concrete assembled truss composite beam | |
| CN114892813B (en) | Large-span building main body supporting steel structure and construction method | |
| JP3440422B2 (en) | Bridge construction method and bridge construction device | |
| CN114561873B (en) | Construction method of high bridge pier | |
| CN111749140A (en) | A truss integral lift bridge high pier climbing formwork device and construction method | |
| CN108396630A (en) | The big box-beam structure of precast concrete with the connection of wet seam direction across bridge | |
| JP2006028881A (en) | Self-propelled PC slab erection machine and PC slab erection method | |
| CN113279337B (en) | A wet joint formwork installation and disassembly system and installation and disassembly construction method | |
| CN116537071A (en) | A hydraulic jacking integral steel frame platform and its construction method for turning over formwork | |
| CN112012365B (en) | A construction technology for pouring and forming of a large-scale sewage pool supporting arm rib beam type wall | |
| CN115522473A (en) | A bridge pier making machine and its construction method | |
| CN107829408B (en) | Rectangular aqueduct construction steel mould trolley | |
| CN113502756A (en) | Thin-wall pier hydraulic creeping formwork system and construction method thereof | |
| CN219548382U (en) | Empty layer hanging template system of granulating tower | |
| CN208473293U (en) | Narrow deformation joint easy-dismount template system | |
| CN220705161U (en) | Concrete floor post-cast strip hanging walking template system | |
| CN103147401A (en) | Construction method and structure of self-climbing portal frame | |
| CN116145540B (en) | A precast reinforced concrete cover slab and its construction method | |
| CN201588172U (en) | Integral single-tower non-dorsal-cord cable-stayed-bridge king tower lifting template | |
| CN205934962U (en) | A system of sliding for underground pipe gallery cast -in -situ construction | |
| CN215758549U (en) | Thin-wall pier hydraulic creeping formwork system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20230808 |
