JP2018109303A - Method to install or replace invert in tunnel in service - Google Patents
Method to install or replace invert in tunnel in service Download PDFInfo
- Publication number
- JP2018109303A JP2018109303A JP2017000008A JP2017000008A JP2018109303A JP 2018109303 A JP2018109303 A JP 2018109303A JP 2017000008 A JP2017000008 A JP 2017000008A JP 2017000008 A JP2017000008 A JP 2017000008A JP 2018109303 A JP2018109303 A JP 2018109303A
- Authority
- JP
- Japan
- Prior art keywords
- invert
- alternately
- lining
- tunnel
- roadbed material
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 51
- 239000000463 material Substances 0.000 claims abstract description 48
- 239000004567 concrete Substances 0.000 claims abstract description 36
- 238000009434 installation Methods 0.000 claims abstract description 13
- 239000011378 shotcrete Substances 0.000 claims description 17
- 238000005452 bending Methods 0.000 claims description 2
- 238000005507 spraying Methods 0.000 claims description 2
- 239000007921 spray Substances 0.000 claims 1
- 238000005266 casting Methods 0.000 abstract 1
- 238000010276 construction Methods 0.000 description 23
- 229910000831 Steel Inorganic materials 0.000 description 5
- 239000010959 steel Substances 0.000 description 5
- 239000010426 asphalt Substances 0.000 description 4
- 238000009412 basement excavation Methods 0.000 description 4
- 230000000903 blocking effect Effects 0.000 description 3
- 239000003673 groundwater Substances 0.000 description 3
- 238000007689 inspection Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 230000003466 anti-cipated effect Effects 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 238000005336 cracking Methods 0.000 description 1
- 230000006866 deterioration Effects 0.000 description 1
- 230000029058 respiratory gaseous exchange Effects 0.000 description 1
- 238000005096 rolling process Methods 0.000 description 1
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
Description
本発明は、一般車両が通行する供用中のトンネルを交通止めすることなくインバートの設置または打替え工法に関するものである。 The present invention relates to a method for installing or replacing an invert without stopping traffic in an in-service tunnel through which a general vehicle passes.
供用中のトンネルにおいて、膨張性地山の膨張や地山強度の低下や劣化により路面に変状をきたし、トンネルの建設時に設置したインバートの打替えが必要になる個所がある。また同様の理由でインバートが設けられていない路面に変状をきたし新たにインバートの設置が必要になる個所がある。 In tunnels in service, there are places where the road surface is deformed due to the expansion of inflatable grounds, the strength of grounds being lowered or deteriorated, and the inverts installed at the time of tunnel construction need to be replaced. For the same reason, there is a place where an invert is required due to a change in the road surface where no invert is provided.
路面変状の原因は、膨張性地山の膨張や、地山強度の低下や劣化の他に、左右分割施工(片側半断面施工)によるものがある。インバートを全断面一体に形成することは理想であるが、これはトンネル掘削を中断して行なわなければならないことから、インバートを形成する時に、コンクリートを片側ずつ打設する左右分割施工が多く行われている。しかしながらこの左右分割施工は、中央部に継ぎ目ができ強度が低下する問題がある。またコンクリートの打設に代わり、湾曲したコンクリートブロックを片側ずつ設置して、全体を湾曲させる工法(特許文献1)もある。しかしながら何れにしてもインバートが一体施工でないので強度が低い問題があった。 The cause of the road surface deformation is due to the expansion of the expansive natural ground, the decrease and deterioration of the natural ground strength, and the left and right split construction (one-side half-section construction). It is ideal to form the invert in an integral cross section, but this requires that tunnel excavation be interrupted, so when forming the invert, there are many left and right split constructions in which concrete is placed one side at a time. ing. However, this right and left divided construction has a problem that a seam is formed in the central portion and the strength is lowered. In place of placing concrete, there is also a construction method (Patent Document 1) in which curved concrete blocks are installed one side at a time and the whole is curved. In any case, however, there is a problem that the strength is low because the invert is not integrated.
更に設計段階の工程を見込んでいないことも原因と考えられる。例えばインバート部分のコンクリートを打設した後に、養生に時間がかかるため所定の強度に達する前に外力によりひび割れを発生させ構造を弱体化させる場合や、インバート上に路床材を埋め戻した場合の必要圧縮強度について、明確な規定がないため、搬入車両の輪荷重や転圧作業の荷重による原因も考えられる。 Furthermore, it is thought that this is because the process at the design stage is not anticipated. For example, after placing concrete in the invert part, it takes time to cure, so when cracking is caused by external force before reaching the specified strength and the structure is weakened, or when roadbed material is backfilled on invert Since there is no clear regulation about the required compressive strength, there may be a cause due to the wheel load of the carrying-in vehicle or the load of the rolling operation.
これらの原因を勘案するとインバートの打替えまたは設置にあたっては、全断面で施工することが最適であるが、交通規制の問題をクリアするためにはインバート桟橋という設備を使用する方法(特許文献2)がある。この桟橋を用いて桟橋を左右にスライドさせた場合、桟橋の路面が高いため、トンネル断面のサイズによっては建築限界の制限から掘削作業断面の確保や一般通行車両の通行断面確保に支障をきたす問題がある。また特許文献1のように片側ずつ施工して交互通行させれば交通を遮断することなく施工できるが、左右分割施工ではインバートを全断面一体施工できない問題があった。 Considering these causes, it is optimal to replace or install Invert with the entire cross section, but in order to clear the problem of traffic regulation, a method using equipment called Invert Pier (Patent Document 2) There is. If the jetty is slid to the left or right using this jetty, the road surface of the jetty is high, so depending on the size of the tunnel cross section, it may hinder securing the cross section of excavation work and securing the cross section of a general traffic vehicle due to limitations in construction There is. Moreover, if it constructs one side at a time like patent document 1 and makes it pass alternately, it can construct, without interrupting traffic, However, Inverted construction had the problem that invert could not be integrated in the whole cross section.
本発明は上記問題を改善し、片側交互通行を維持しながらインバートの全断面一体施工を行ない、強度と耐久性に優れた供用中のトンネルのインバートの打替えまたは設置する工法を提供するものである。 The present invention improves the above problems and provides a construction method for replacing or installing a tunnel invert in service with excellent strength and durability by carrying out the entire cross-section integrated construction of the invert while maintaining one-side alternate traffic. is there.
本発明の請求項1記載の供用中のトンネルのインバートの設置工法は、路面に変状をきたした供用中のトンネルのインバートの設置において、片側の舗装を交互に撤去する工程と、舗装を撤去した片側に複数本の杭を交互に打設する工程と、片側の打設した杭頭に横桁を設置して、この上に複数枚の覆工板を交互に敷設する工程と、片側の覆工板を取外して、路床材を掘削して交互に空間部を形成する工程と、中央側に覆工板を敷設し、両端側の覆工板を取外して、空間部の底面にコンクリートを打設して新たなインバートを全断面一体に形成する工程と、片側の覆工板を取り外し、他方の片側に覆工板を敷設して、片側のインバートの上を路床材で交互に埋め戻す工程と、埋め戻した路床材の上をコンクリートで舗装する工程とから成ることを特徴とするものである。 According to claim 1 of the present invention, there is provided a method for installing an invert of a tunnel in service, the step of alternately removing the pavement on one side in the installation of the invert of the tunnel in service having a deformed road surface, and the removal of the pavement. A step of alternately placing a plurality of piles on one side, a step of installing a cross girder on the head of a pile placed on one side, and laying a plurality of lining boards alternately thereon, The process of removing the lining board, excavating the roadbed material to alternately form the space part, laying the lining board on the center side, removing the lining board on both sides, and putting the concrete on the bottom of the space part To form a new invert with a cross-section, and remove the lining plate on one side, lay the lining plate on the other side, and alternately over the invert on one side with the roadbed material It consists of a backfilling process and a process of paving the backfilled roadbed with concrete. The one in which the features.
本発明の請求項2記載の供用中のトンネルのインバートの打替え工法は、路面に変状をきたした供用中のトンネルのインバートの打替えにおいて、片側の舗装を交互に撤去する工程と、舗装を撤去した片側に複数本の杭を交互に打設する工程と、片側の打設した杭頭に横桁を設置して、この上に複数枚の覆工板を交互に敷設する工程と、片側の覆工板を取外して、路床材を掘削して既設のインバートを交互に撤去して空間部を形成する工程と、中央側に覆工板を敷設し、両端側の覆工板を取外して、空間部の底面にコンクリートを打設して新たなインバートを全断面一体に形成する工程と、片側の覆工板を取り外し、他方の片側に覆工板を敷設して、片側のインバートの上を路床材で交互に埋め戻す工程と、埋め戻した路床材の上をコンクリートで舗装する工程とから成ることを特徴とするものである。 According to claim 2 of the present invention, the method for replacing the invert of the tunnel in service includes the step of alternately removing the pavement on one side in the replacement of the invert of the tunnel in service that has deformed the road surface, A step of alternately placing a plurality of piles on one side of removing the pile, a step of installing a cross girder on the pile head that has been placed on one side, and laying a plurality of lining boards alternately thereon, Remove the lining plate on one side, excavate the roadbed material and alternately remove the existing invert to form a space, and lay the lining plate on the center side, Removing and placing concrete on the bottom of the space to form a new invert in an integrated cross-section, removing the lining plate on one side and laying the lining plate on the other side, The process of alternately backfilling the top with roadbed material and the top of the backfilled roadbed material It is characterized in that comprising a step of paved with bets.
本発明の請求項3記載の供用中のトンネルのインバートの打替え工法は、路面に変状をきたした供用中のトンネルのインバートの打替えにおいて、片側の舗装を交互に撤去する工程と、舗装を撤去した片側に複数本の杭を交互に打設する工程と、片側の打設した杭頭に横桁を設置して、この上に複数枚の覆工板を交互に敷設する工程と、片側の覆工板を取外して、路床材を掘削して既設のインバートを交互に撤去して空間部を形成する工程と、中央側に覆工板を敷設し、両端側の覆工板を取外して、空間部の底面に吹付けコンクリートを湾曲して吹付ける工程と、吹付けコンクリートの上にコンクリートを打設して新たなインバートを全断面一体に形成する工程と、片側の覆工板を取り外し、他方の片側に覆工板を敷設して、片側のインバートの上を路床材で交互に埋め戻す工程と、埋め戻した路床材の上をコンクリートで舗装する工程とから成ることを特徴とするものである。 According to claim 3 of the present invention, a method for replacing the invert of a tunnel in service includes a step of alternately removing pavement on one side in the replacement of the invert of a tunnel in service that has deformed on the road surface, A step of alternately placing a plurality of piles on one side of removing the pile, a step of installing a cross girder on the pile head that has been placed on one side, and laying a plurality of lining boards alternately thereon, Remove the lining plate on one side, excavate the roadbed material and alternately remove the existing invert to form a space, and lay the lining plate on the center side, Removing and bending sprayed concrete on the bottom of the space, placing concrete on the shotcrete to form a new invert all in one piece, and one side lining plate And lay a lining plate on the other side and A step of backfilling alternately subgrade material over the top of the backfill was subgrade material is characterized in that comprising a step of paved with concrete.
本発明の請求項4記載の供用中のトンネルのインバートの設置または打替え工法は、請求項1または2、若しくは3において、更に地面を掘削して中央排水溝を撤去する工程の前に、バイパス水路に切換える工程と、インバートを形成する工程の後に、路床材を埋め戻してから中央排水溝を設置してバイパス水路を切換える工程とから成ることを特徴とするものである。 According to claim 4 of the present invention, the inverting or inversion method of the tunnel in service according to claim 1 is the bypass according to claim 1, 2 or 3 before the step of further excavating the ground and removing the central drainage groove. After the step of switching to the water channel and the step of forming the invert, the step of backfilling the road floor material, and then installing the central drainage channel and switching the bypass water channel are characterized by the above.
本発明の請求項5記載の供用中のトンネルのインバートの設置または打替え工法は、請求項1または2、若しくは3において、更に打設した杭頭に横桁を設置して、この上に複数枚の覆工板を交互に敷設する工程で、左右の横桁を一体に接合または接触させ、この左右一体となった横桁の両端部をアーチ形の覆工コンクリートの下部両端に接触させて切りばりを兼用したことを特徴とするものである。 According to Claim 5 of the present invention, the inverting or replacing method of the tunnel in service according to Claim 1 or 2 or 3 further comprises installing a cross beam on the pile head that has been further placed, In the process of laying the lining plates alternately, the left and right cross beams are joined or contacted together, and both ends of the left and right cross beams are brought into contact with the lower ends of the arched lining concrete. It is characterized by using a cutting edge.
本発明に係る請求項1記載の供用中のトンネルのインバートの設置工法によれば、建設時にインバートのないトンネルに新たにインバートを設置する場合で、覆工板上を一般車両通行の必要幅員を左右および中央部で常に確保して、全面通行止めすることなく施工することができる。しかも左右分割施工に比べて、継ぎ目のないインバートの全断面一体施工が可能で、しかもインバートがH形鋼などの杭で補強されているので強度と耐久性に優れた新たなインバートを形成して路面の変状を長期間に亘って防止することができる。また長距離区間を連続施工した場、複数の作業工程を同時に施工が可能で、手待ち時間を少なくして、効率的且つ経済的に安価に施工することができる。 According to the installation method of the invert of the tunnel in service according to claim 1 according to the present invention, when the invert is newly installed in the tunnel without the invert at the time of construction, the necessary width for passing the general vehicle on the lining plate is increased. It can always be secured at the left and right and the center, and construction can be done without blocking the entire surface. In addition, compared to the split construction on the left and right, it is possible to construct a seamless invert with an entire cross-section, and because the invert is reinforced with piles such as H-shaped steel, a new invert superior in strength and durability is formed. Deformation of the road surface can be prevented over a long period of time. Moreover, it is possible to construct a long-distance section continuously and a plurality of work processes at the same time, reduce the waiting time, and construct efficiently and economically.
本発明に係る請求項2記載の供用中のトンネルのインバートの打替え工法によれば、吹付けコンクリートの施工工程を省いて、インバート3を建設する工法で、請求項1と同様の効果が得られる。 According to the method for replacing the invert of the tunnel in service according to claim 2 of the present invention, the method of constructing the invert 3 by omitting the construction process of shotcrete has the same effect as that of claim 1. It is done.
本発明に係る請求項3記載の供用中のトンネルのインバートの打替え工法によれば、既設のインバートを打替えして、吹付けコンクリートを施工し、インバートを形成する場合で、インバートを施工する前に、掘削した空間部の底面は吹付けコンクリートを施工することにより、掘削後、早期にトンネルの強度を上げて安定させることができる。更に請求項1と同様の効果が得られる。 According to the inverting method for inverting a tunnel in service according to claim 3 according to the present invention, the existing invert is replaced, the shotcrete is applied, and the invert is formed. The bottom of the excavated space can be stabilized by increasing the strength of the tunnel at an early stage after excavation by constructing shotcrete. Further, the same effect as in the first aspect can be obtained.
また請求項4記載の供用中のトンネルのインバートの設置または打替え工法によれば、中央排水溝のあるトンネルの場合には、中央排水溝の撤去やバイパス水路の設置、水路の切換え、中央排水溝の設置などの工程を付加して、工事中にトンネル内に流入する地下水を排水することができる。 In addition, according to the installation or replacement method of the invert of the tunnel in service according to claim 4, in the case of a tunnel with a central drainage channel, the removal of the central drainage channel, the installation of the bypass channel, the switching of the channel, the central drainage It is possible to drain groundwater flowing into the tunnel during construction by adding a process such as installing a ditch.
また請求項5記載の供用中のトンネルのインバートの設置または打替え工法によれば、トンネルを形成する覆工コンクリートがインバートの除去に伴い、横桁が水平方向に変状するのを防止する切りばりを兼ねることができる。 Further, according to the installation or replacement method of the invert of the tunnel in use according to claim 5, the lining concrete forming the tunnel is cut to prevent the horizontal girder from being deformed in the horizontal direction as the invert is removed. Can also serve as a flash.
以下、既設のインバートを打替えして、吹付けコンクリートを施工し、インバートを形成する場合の、本発明の実施の一形態を図1ないし図5を参照して説明する。路面に変状をきたした供用中のトンネルのインバートを打替えする場合について詳細に説明する。図1(A)に示すように供用中のトンネル1は、アーチ形の覆工コンクリート2の底部に湾曲したインバート3が一体に形成され、インバート3の上に路床材4が盛られ、この上に路盤材5を介してコンクリートの舗装6が形成されている。舗装6の中央部の下には中央排水溝7が埋設され、更に舗装6の右端の覆工コンクリート2の横に監査路8が設けられている。 Hereinafter, an embodiment of the present invention will be described with reference to FIGS. 1 to 5 in the case where an existing invert is replaced and shotcrete is applied to form the invert. A detailed description will be given of the case where the invert of a tunnel in service that has deformed on the road surface is replaced. As shown in FIG. 1 (A), the tunnel 1 in service has a curved invert 3 formed integrally with the bottom of an arch-shaped lining concrete 2, and a roadbed material 4 is piled on the invert 3. A concrete pavement 6 is formed above via a roadbed material 5. A central drain groove 7 is buried under the center of the pavement 6, and an inspection path 8 is provided next to the lining concrete 2 at the right end of the pavement 6.
このトンネル1において、先ず第1工程で図中左側(一方の片側)の舗装6を撤去し路床材4を露出させ、この上を仮舗装する。この時、既設の図中右側(他方の片側)の舗装6は一点鎖線の枠で囲った一般車両通行帯10となり走行が可能である。 In this tunnel 1, first, in the first step, the pavement 6 on the left side (one side) in the figure is removed to expose the roadbed material 4, and the top is temporarily paved. At this time, the pavement 6 on the right side (the other side) in the existing drawing becomes a general vehicle lane 10 surrounded by a dashed-dotted frame and can travel.
次に図1(B)に示すように、第2工程で右側の舗装6を撤去して路床材4を露出させ、この上を仮舗装する。この第2工程では左側が一般車両通行帯10となる。この後、図1(C)に示すように第3工程で左側の路床材4にH形鋼などの杭12を所定の間隔で複数本打設し、既存のインバート3を貫通させて地山に打ち込む。この杭12の打設間隔は図示しない覆工板の横幅と縦の長さのピッチに合わせる。この後、アスファルトにより仮舗装する。この時、右側の仮舗装13が一般車両通行帯10になる。 Next, as shown in FIG. 1 (B), the pavement 6 on the right side is removed in the second step to expose the roadbed material 4, and this is temporarily paved. In this second step, the left side is the general vehicle lane 10. Thereafter, as shown in FIG. 1 (C), in the third step, a plurality of piles 12 such as H-section steel are placed at a predetermined interval on the left roadbed material 4, and the existing invert 3 is penetrated to form the ground. Drive into the mountains. The pitching interval of the piles 12 is adjusted to the pitch of the horizontal width and the vertical length of a cover plate (not shown). After this, temporarily paving with asphalt. At this time, the right temporary pavement 13 becomes the general vehicle lane 10.
次に図1(D)に示すように、第4工程で右側の路床材4に杭12を所定の間隔で複数本打設し、既存のインバート3を貫通させて地山に打ち込む。この後、アスファルトにより仮舗装する。この時、左側の仮舗装13が一般車両通行帯10になる。 Next, as shown in FIG. 1 (D), in the fourth step, a plurality of piles 12 are driven at a predetermined interval on the right roadbed material 4, and the existing invert 3 is penetrated and driven into a natural ground. After this, temporarily paving with asphalt. At this time, the left temporary pavement 13 becomes the general vehicle lane 10.
次に図2(E)に示すように、第5工程で左側の仮舗装13を撤去した後に、杭12の杭頭に横桁15を取付け、これと直交して複数枚の覆工板16を図5に示すように敷設する。この時、仮舗装した右側が一般車両通行帯10になる。 Next, as shown in FIG. 2 (E), after removing the left temporary pavement 13 in the fifth step, a cross beam 15 is attached to the pile head of the pile 12, and a plurality of lining plates 16 are orthogonal to this. Is laid as shown in FIG. At this time, the temporarily paved right side becomes a general vehicle lane 10.
次に図2(F)に示すように、第6工程で右側の仮舗装13を撤去した後に、杭12の杭頭に横桁15を取付け、これと直交して複数枚の覆工板16を同様に敷設する。左右の横桁15は一体に接合または接触させ、この左右一体となった横桁15の両端部をアーチ形の覆工コンクリート2の下部両端に接触させて取付けることにより、切りばりを兼用させている。この結果、覆工コンクリート2がインバート3の除去に伴い、水平方向に変状するのを防止することができる。この時、覆工板16を敷設した左側が一般車両通行帯10になる。 Next, as shown in FIG. 2 (F), after removing the right temporary pavement 13 in the sixth step, a cross girder 15 is attached to the pile head of the pile 12, and a plurality of lining plates 16 are orthogonal to this. Lay in the same way. The left and right cross beams 15 are integrally joined or contacted, and both end portions of the left and right cross beams 15 are attached to the lower end portions of the arched lining concrete 2 so that they can also be used as cutting edges. Yes. As a result, it is possible to prevent the lining concrete 2 from being deformed in the horizontal direction as the invert 3 is removed. At this time, the left side where the lining plate 16 is laid becomes the general vehicle lane 10.
次に図2(G)に示すように、第7工程で左側の覆工板16を取外し、路床材4を掘削して既設の左側のインバート3と中央排水溝7を撤去して空間部19を形成する。この中央排水溝7を撤去する前に、釜場にポンプを設置し、覆工コンクリート2の壁面にバイパス水路17を設けて、地下水をバイパス水路17に切換えて流す。この時、覆工板16を敷設した右側が一般車両通行帯10になる。 Next, as shown in FIG. 2G, in the seventh step, the left lining board 16 is removed, the roadbed material 4 is excavated, and the existing left invert 3 and the central drainage groove 7 are removed to remove the space portion. 19 is formed. Before removing the central drain groove 7, a pump is installed in the kettle, a bypass water channel 17 is provided on the wall surface of the lining concrete 2, and groundwater is switched to the bypass water channel 17 to flow. At this time, the right side on which the lining plate 16 is laid becomes the general vehicle lane 10.
次に図2(H)に示すように、第8工程で右側の覆工板16を取外し、路床材4を掘削して既設の右側のインバート3を撤去して空間部19を形成する。空間部19の底面は湾曲して掘削し、必要に応じて掘削した底面に湾曲したH形鋼などで補強する。 Next, as shown in FIG. 2 (H), the right lining plate 16 is removed in the eighth step, the roadbed material 4 is excavated, and the existing right invert 3 is removed to form a space portion 19. The bottom surface of the space portion 19 is curved and excavated, and if necessary, is reinforced with a curved H-shaped steel or the like on the excavated bottom surface.
次に図3(I)に示すように、第9工程で中央側に覆工板16を敷設し、両端側の覆工板16を取外して、空間部19の底面に短時間で硬化する吹付けコンクリート20を湾曲して左右全面に吹付ける。この吹付けコンクリート20はプレーンコンクリートに急結剤を添加したもので、吹付けコンクリート20を設置することにより掘削後、早期にトンネル1の強度を上げて安定させることができる。この時、覆工板16を敷設した中央側が一般車両通行帯10になる。 Next, as shown in FIG. 3 (I), in the ninth step, a lining plate 16 is laid on the center side, the lining plates 16 on both ends are removed, and a blow that hardens on the bottom surface of the space portion 19 in a short time. The glued concrete 20 is curved and sprayed to the entire left and right sides. The shotcrete 20 is obtained by adding a quick setting agent to plain concrete. By installing the shotcrete 20, the strength of the tunnel 1 can be increased and stabilized early after excavation. At this time, the central side where the lining plate 16 is laid becomes the general vehicle occupancy zone 10.
次に図3(J)に示すように、湾曲して形成された吹付けコンクリート20が硬化したら、第10工程でこの上にコンクリートを左右全面に湾曲して打設し、新たなインバート3を全断面一体に形成する。このインバート3は覆工コンクリート2Bの下部に設置するため、コンクリートのブリージングにより密着不良となりやすいので収縮量の少ないモルタルを注入して仕上げると良い。 Next, as shown in FIG. 3 (J), when the shotcrete 20 formed in a curve is cured, the concrete is curved and placed on the entire left and right sides in the tenth step, and a new invert 3 is formed. All cross sections are formed integrally. Since this invert 3 is installed in the lower part of the lining concrete 2B, it is liable to cause poor adhesion due to the breathing of the concrete.
コンクリートが硬化したら、図3(K)に示すように、第11工程で新たな中央排水溝7を設置する。この時、覆工板16を敷設した中央側が一般車両通行帯10になる。 When the concrete is hardened, a new central drain groove 7 is installed in the eleventh step as shown in FIG. At this time, the central side where the lining plate 16 is laid becomes the general vehicle occupancy zone 10.
次に図3(L)に示すように、第12工程で右側に覆工板16を敷設して、左側の覆工板16と横桁15を取外し、左側のインバート3の上の空間部19を路床材4で埋め戻し、この上をアスファルトで仮舗装をする。この時、覆工板16を敷設した右側が一般車両通行帯10になる。 Next, as shown in FIG. 3 (L), the lining plate 16 is laid on the right side in the twelfth step, the left lining plate 16 and the cross beam 15 are removed, and the space 19 above the invert 3 on the left side. Is backfilled with the roadbed material 4, and this is temporarily paved with asphalt. At this time, the right side on which the lining plate 16 is laid becomes the general vehicle lane 10.
次に図4(M)に示すように、第13工程で右側の覆工板16と横桁15を取外し、右側のインバート3の上の空間部19を路床材4で埋め戻し、この上をアスファルトで仮舗装する。この場合、インバート3の上に突出した杭12の杭頭を溶断して撤去しても良い。この時、左側の仮舗装13が一般車両通行帯10になる。 Next, as shown in FIG. 4 (M), the right lining board 16 and the cross beam 15 are removed in the thirteenth step, and the space 19 above the right invert 3 is backfilled with the roadbed material 4. Is temporarily paved with asphalt. In this case, the pile head of the pile 12 protruding above the invert 3 may be melted and removed. At this time, the left temporary pavement 13 becomes the general vehicle lane 10.
次に図4(N)に示すように、第14工程で仮舗装13を撤去し、インバート3の上に路床材4を埋め戻す。この後、地下水をバイパス水路17から中央排水溝7に切換えて流す。この後、覆工コンクリート2の壁面に取付けたバイパス水路17を取外す。次に、この路床材4の上に路盤材5を介して左右全面にコンクリートを打設して舗装6を形成すると共に、左右に監査路8を形成して、インバート3の打替え工事が完了する。このような打替え工事をトンネル1の入り口から例えば100mの範囲で施工し、順次トンネル1の軸方向に向かって繰り返して施工する。 Next, as shown in FIG. 4 (N), the temporary pavement 13 is removed in the 14th step, and the roadbed material 4 is refilled on the invert 3. Thereafter, the groundwater is switched from the bypass water channel 17 to the central drainage channel 7 to flow. Thereafter, the bypass water channel 17 attached to the wall surface of the lining concrete 2 is removed. Next, concrete is placed on the entire left and right sides of the roadbed material 4 via the roadbed material 5 to form the pavement 6 and the inspection roads 8 are formed on the left and right sides. Complete. Such replacement work is performed within a range of, for example, 100 m from the entrance of the tunnel 1, and is sequentially repeated in the axial direction of the tunnel 1.
上記供用中のトンネルのインバートの打替え工法によれば全面通行止めすることなく、片側交互通行を維持しながら施工できる。しかも継ぎ目のないインバートの全断面一体施工が可能で、しかもインバートがH形鋼などの杭で補強されているので強度と耐久性に優れたインバートを形成して路面の変状を長期間に亘って防止することができる。 According to the inversion method of inverting the tunnel in service, construction can be performed while maintaining one-way alternating traffic without blocking the entire surface. In addition, it is possible to construct an invert with a seamless cross-section, and because the invert is reinforced with piles such as H-shaped steel, an invert with excellent strength and durability is formed, and the road surface is deformed over a long period of time. Can be prevented.
また上記説明では既設のインバート3の吹付けコンクリート20を施工して新たなインバート3を建設する打替え工法について示したが、吹付けコンクリート20を省いて、インバート3を建設する工法でも良い。この場合、図1(A)から図2(H)までは同様で、図3(I)の吹付けコンクリート20の吹付け施工がなく、以下吹付けコンクリート20のない状態で、同様にインバート3を形成していく。 In the above description, the replacement method for constructing the new invert 3 by constructing the shotcrete 20 of the existing invert 3 is shown, but the method for constructing the invert 3 by omitting the shotcrete 20 may be used. In this case, FIG. 1 (A) to FIG. 2 (H) are the same, there is no spraying construction of the shotcrete 20 of FIG. 3 (I), and invert 3 similarly in the absence of the shotcrete 20 below. Will be formed.
また本発明は建設時にインバート3のないトンネル1に、新たにインバート3を設置する場合にも適用することができる。この場合、図1(A)から図2(F)までのインバート3はなく、図2(G)の既設の左側のインバート3を撤去する工程はなく、路床材4と地山だけを掘削する工程と、図2(H)の右側のインバート3を撤去する工程はなく、路床材4と地山だけを掘削する工程だけとなる。以下図3、図4と同様の工程で新たなインバート3を建設する。なおこの場合、吹付けコンクリート20を施工しない場合もある。 The present invention can also be applied to a case where the invert 3 is newly installed in the tunnel 1 without the invert 3 at the time of construction. In this case, there is no invert 3 from FIG. 1 (A) to FIG. 2 (F), there is no process of removing the existing left invert 3 in FIG. 2 (G), and only the roadbed material 4 and the ground are excavated. There is no step of removing the invert 3 on the right side of FIG. 2 (H) and only the step of excavating only the roadbed material 4 and the natural ground. Thereafter, a new invert 3 is constructed in the same process as in FIGS. In this case, the shotcrete 20 may not be constructed.
なお中央排水溝7のないトンネル1の場合には、中央排水溝7の撤去やバイパス水路17の設置、水路の切換え工程は不要である。 In the case of the tunnel 1 without the central drain groove 7, the removal of the central drain groove 7, the installation of the bypass water channel 17, and the process of switching the water channel are unnecessary.
1 トンネル
2 覆工コンクリート
3 インバート
4 路床材
5 路盤材
6 舗装
7 中央排水溝
8 監査路
10 一般車両通行帯
12 杭
13 仮舗装
15 横桁
16 覆工板
17 バイパス水路
19 空間部
20 吹付けコンクリート
1 tunnel
2 lining concrete
3 Invert
4 Roadbed materials
5 Roadbed material
6 Paving
7 Central drain
8 Audit Path
10 General vehicle lane
12 piles
13 Temporary paving
15 horizontal girder
16 Lining board
17 Bypass waterway
19 Space
20 Shotcrete
本発明の請求項4記載の供用中のトンネルのインバートの設置または打替え工法は、請求項1または2、若しくは3において、更に地面を掘削して中央排水溝を撤去する工程の前に、バイパス水路に切換える工程と、インバートを形成する工程の後に、中央排水溝を設置して、路床材を埋め戻してから中央排水溝を設置してバイパス水路を切換える工程とから成ることを特徴とするものである。 According to claim 4 of the present invention, the inverting or inversion method of the tunnel in service according to claim 1 is the bypass according to claim 1, 2 or 3 before the step of further excavating the ground and removing the central drainage groove. After the step of switching to the water channel and the step of forming the invert, the central drainage channel is installed, the roadbed material is backfilled, and then the central drainage channel is installed to switch the bypass channel. Is.
本発明に係る請求項1記載の供用中のトンネルのインバートの設置工法によれば、建設時にインバートのないトンネルに新たにインバートを設置する場合で、覆工板上を一般車両通行の必要幅員を左右および中央部で常に確保して、全面通行止めすることなく施工することができる。しかも左右分割施工に比べて、継ぎ目のないインバートの全断面一体施工が可能で、しかもインバートがH形鋼などの杭で補強されているので強度と耐久性に優れた新たなインバートを形成して路面の変状を長期間に亘って防止することができる。また長距離区間を連続施工した場合、複数の作業工程を同時に施工が可能で、手待ち時間を少なくして、効率的且つ経済的に安価に施工することができる。 According to the installation method of the invert of the tunnel in service according to claim 1 according to the present invention, when the invert is newly installed in the tunnel without the invert at the time of construction, the necessary width for passing the general vehicle on the lining plate is increased. It can always be secured at the left and right and the center, and construction can be done without blocking the entire surface. In addition, compared to the split construction on the left and right, it is possible to construct a seamless invert with an entire cross-section, and because the invert is reinforced with piles such as H-shaped steel, a new invert superior in strength and durability is formed. Deformation of the road surface can be prevented over a long period of time. Further, when the long distance section continuous construction, enables applying a plurality of work steps at the same time, it is possible to reduce the hand latency, efficiently and economically low cost construction.
本発明に係る請求項2記載の供用中のトンネルのインバートの打替え工法によれば、既設のインバートを交互に撤去して、新たにインバートを打設する工法で、請求項1と同様に、強度と耐久性に優れた新たなインバートを形成して路面の変状を長期間に亘って防止することができる。
According to the inverting method of the invert of the tunnel in service according to claim 2 according to the present invention, the existing invert is alternately removed, and the invert is newly installed. It is possible to form a new invert excellent in strength and durability and prevent road surface deformation over a long period of time.
Claims (5)
In the installation or replacement method of the invert of a tunnel in service according to claim 1, 2 or 3, further installing a cross girder on the pile head that has been laid, and laying a plurality of lining boards alternately thereon In this process, the left and right cross beams are joined or contacted together, and both ends of the left and right cross beams are brought into contact with the lower ends of the arch-shaped lining concrete, which is also used for cutting. Installation or replacement method for invert tunnels in service.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2017000008A JP6177468B1 (en) | 2017-01-02 | 2017-01-02 | Installation or replacement of tunnel inverts in service |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2017000008A JP6177468B1 (en) | 2017-01-02 | 2017-01-02 | Installation or replacement of tunnel inverts in service |
Publications (2)
Publication Number | Publication Date |
---|---|
JP6177468B1 JP6177468B1 (en) | 2017-08-09 |
JP2018109303A true JP2018109303A (en) | 2018-07-12 |
Family
ID=59559108
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2017000008A Active JP6177468B1 (en) | 2017-01-02 | 2017-01-02 | Installation or replacement of tunnel inverts in service |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP6177468B1 (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108798701A (en) * | 2018-06-01 | 2018-11-13 | 中铁第四勘察设计院集团有限公司 | Precast construction and its construction method in a kind of roads and tunnels |
CN110835903A (en) * | 2019-11-27 | 2020-02-25 | 中国水利水电第一工程局有限公司 | Bottom arch concrete protection device and method for water delivery tunnel in shape of horseshoe |
CN111501421A (en) * | 2020-04-29 | 2020-08-07 | 中铁二院工程集团有限责任公司 | Tunnel bottom structure capable of effectively preventing track slab from arching |
CN111560940A (en) * | 2020-05-09 | 2020-08-21 | 中铁二十局集团第三工程有限公司 | Treatment method of karst tunnel |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000130096A (en) * | 1998-10-21 | 2000-05-09 | Kumagai Gumi Co Ltd | Method for installing invert into batholith of existing mountain tunnel |
JP2000145386A (en) * | 1998-11-13 | 2000-05-26 | Kumagai Gumi Co Ltd | Member and method for repairing batholith of existing mountain tunnel |
JP2011117129A (en) * | 2009-11-30 | 2011-06-16 | Takenaka Doboku Co Ltd | Tunnel repairing and reinforcing apparatus |
JP2016102369A (en) * | 2014-11-28 | 2016-06-02 | 株式会社奥村組 | Construction method for invert in existing tunnel |
-
2017
- 2017-01-02 JP JP2017000008A patent/JP6177468B1/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000130096A (en) * | 1998-10-21 | 2000-05-09 | Kumagai Gumi Co Ltd | Method for installing invert into batholith of existing mountain tunnel |
JP2000145386A (en) * | 1998-11-13 | 2000-05-26 | Kumagai Gumi Co Ltd | Member and method for repairing batholith of existing mountain tunnel |
JP2011117129A (en) * | 2009-11-30 | 2011-06-16 | Takenaka Doboku Co Ltd | Tunnel repairing and reinforcing apparatus |
JP2016102369A (en) * | 2014-11-28 | 2016-06-02 | 株式会社奥村組 | Construction method for invert in existing tunnel |
Also Published As
Publication number | Publication date |
---|---|
JP6177468B1 (en) | 2017-08-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9322137B2 (en) | Method for building structures, particularly passages under operating railways or the like | |
KR101344063B1 (en) | The construction method of steel-concrete underpass | |
JP6177468B1 (en) | Installation or replacement of tunnel inverts in service | |
CN105908639B (en) | Prefabricated box culvert and rapid positioning construction method | |
KR101388521B1 (en) | Construction method of underground structure under the pier with supporting piles | |
KR101288601B1 (en) | Underpass using precast concrete pile and bottom slab and method for constructing the same | |
KR20160131410A (en) | Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method | |
KR100938395B1 (en) | The Construction Method of Underpass using Steel-Concrete Composite Wall Pile | |
JP5928944B2 (en) | Improvement method of abutment chest wall | |
JP5843413B1 (en) | Lowering method of existing tunnel | |
JP6170268B1 (en) | Ballast track subbase formation method | |
JP4406577B2 (en) | Digging road | |
JP6144726B2 (en) | Rehabilitation method for mountain road tunnels on expressway and suspension pier for rehabilitation method | |
KR101234091B1 (en) | Method of underground railway crossing over direct installation of precast concrete slab | |
KR20210055980A (en) | Underground roadway by top-down method using steel continuous wall in the earth without traffic control and temporary road and method for constructing the same | |
KR20210078779A (en) | Underground roadway removed upper structure between upper slab and surface of road after constructing the steel continuous wall in the earth by top-down method and method for constructing the same | |
JP2011063993A (en) | Method for reclaiming bridge | |
JP2013087516A (en) | Method of forming underground space under ground traffic road | |
JP2018044362A (en) | Method for easily constructing tunnel watchman passage using l-shaped precast concrete product | |
KR101288602B1 (en) | Underpass using precast concrete pile and method for constructing the same | |
KR20210055981A (en) | Underground roadway using steel continuous wall in the earth with minimum traffic control in constructing by top-down method and method for constructing the same | |
JP2007297807A (en) | Construction method for underground structure, and underground structure | |
Clarkson et al. | PIPE-JACKING APPLIED TO LARGE STRUCTURES. | |
KR101266094B1 (en) | Repairing and Reinfocing Method of Structure Approaches | |
JP7501869B2 (en) | Mountain tunnel renewal method and lining structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A975 | Report on accelerated examination |
Free format text: JAPANESE INTERMEDIATE CODE: A971005 Effective date: 20170615 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20170623 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20170711 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 6177468 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |