JP6170268B1 - Ballast track subbase formation method - Google Patents

Ballast track subbase formation method Download PDF

Info

Publication number
JP6170268B1
JP6170268B1 JP2017073276A JP2017073276A JP6170268B1 JP 6170268 B1 JP6170268 B1 JP 6170268B1 JP 2017073276 A JP2017073276 A JP 2017073276A JP 2017073276 A JP2017073276 A JP 2017073276A JP 6170268 B1 JP6170268 B1 JP 6170268B1
Authority
JP
Japan
Prior art keywords
roadbed
block
ballast
reinforced concrete
iron plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2017073276A
Other languages
Japanese (ja)
Other versions
JP2018172953A (en
Inventor
宏樹 大場
宏樹 大場
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Senken Kogyo Co Ltd
Original Assignee
Senken Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Senken Kogyo Co Ltd filed Critical Senken Kogyo Co Ltd
Priority to JP2017073276A priority Critical patent/JP6170268B1/en
Application granted granted Critical
Publication of JP6170268B1 publication Critical patent/JP6170268B1/en
Publication of JP2018172953A publication Critical patent/JP2018172953A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Machines For Laying And Maintaining Railways (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

【課題】鉄筋コンクリート路盤が架け渡された鉄道橋の解体にともなうバラスト軌道の路盤形成方法を提供する。【解決手段】鉄筋コンクリート路盤としての上床版12の底面側に支保25を組み、支保25の上に鉄板23を載置し、鉄板23と上床版12との間に複数の単管パイプ24を軌条直交方向に並べた状態で挟み込み、支保25の下端から鉄板23までをセメント系材料で埋め固めて支持層22を形成し、上床版12を軌条直交方向に分断して複数のブロック120に分割する。単管パイプ24により支持されるブロックのいずれか1つを選択して、選択したブロック周辺の道床バラスト4を除去し、単管パイプ24の上を滑らせるようにして引き抜いた後、引き抜くことにより生じた空間に砕石を投入して砕石路盤31を形成し、路盤上に道床バラスト4を埋め戻すことを、単管パイプ24により支持される個々のブロック120ごとに順次行う。【選択図】図13The present invention provides a ballast track method for forming a ballast track associated with the dismantling of a railway bridge over which a reinforced concrete roadbed is bridged. A support 25 is assembled on the bottom side of an upper floor slab 12 as a reinforced concrete roadbed, an iron plate 23 is placed on the support 25, and a plurality of single-pipe pipes 24 are railed between the iron plate 23 and the upper floor slab 12. The support layer 22 is formed by sandwiching the support 25 in a state of being arranged in the orthogonal direction, filling the cement plate material from the lower end of the support 25 to the iron plate 23, and dividing the upper floor slab 12 in the rail orthogonal direction to divide it into a plurality of blocks 120. . By selecting any one of the blocks supported by the single pipe 24, removing the ballast ballast 4 around the selected block, pulling it out by sliding on the single pipe 24, and then pulling it out The crushed stone roadbed 31 is formed by throwing crushed stone into the generated space, and the roadbed ballast 4 is backfilled on the roadbed sequentially for each block 120 supported by the single pipe 24. [Selection] Figure 13

Description

本発明は、バラスト軌道の路盤形成方法に関し、特に、鉄筋コンクリート路盤が架け渡された鉄道橋の解体にともなうバラスト軌道の路盤形成方法に関する。   The present invention relates to a ballast track roadbed forming method, and more particularly to a ballast track roadbed formation method associated with the dismantling of a railway bridge over which a reinforced concrete roadbed is bridged.

鉄道用のバラスト軌道は、路盤の施工基面上にバラスト道床を整形し、この道床上に多数の枕木を配設し、これらの枕木上に軌条(レール)を設置することにより設けられる。バラスト道床に用いられる砕石等(以下「道床バラスト」という。)には、鉄道車両の荷重を広く分散して路盤に伝えたり、鉄道車両通過時の騒音振動を減衰したり、鉄道車両の左右動や温度変化による軌条の伸縮に対する枕木位置の変動を抑制したり、軌道にクッション性を与えて乗り心地を良くしたりする等の機能ないし役割がある。河川にバラスト軌道を架け渡すために、河川上に架け渡されたコンクリート製の橋桁を鉄筋コンクリート路盤として、当該路盤上にバラスト軌道を設ける場合や、河川に設置された水路用ボックスカルバートの上床版(函体床版)を鉄筋コンクリート路盤として、当該路盤上にバラスト軌道を設ける場合がある。   A ballast track for railroads is provided by shaping a ballast roadbed on the construction base of the roadbed, arranging a number of sleepers on the roadbed, and installing rails on the sleepers. For crushed stones used for the ballast roadbed (hereinafter referred to as “roadbed ballast”), the load of the railroad vehicle is widely distributed and transmitted to the roadbed, the noise vibration when passing through the railroad vehicle is attenuated, There are functions and roles such as suppressing fluctuations in the position of sleepers with respect to the expansion and contraction of the rails due to changes in temperature and providing a cushioning property to the track to improve the ride comfort. In order to build a ballast track over a river, a concrete bridge girder bridged over the river is used as a reinforced concrete roadbed, and a ballast track is installed on the roadbed, or an upper floor slab ( A box floor slab) may be used as a reinforced concrete roadbed, and a ballast track may be provided on the roadbed.

鉄道用軌道の構造は様々な理由により変更されることがある。スラブ軌道は、鉄筋コンクリート路盤上にコンクリート板を敷設し、その板の上に軌条を設置する構造であり、省力化軌道の一つとして、バラスト道床の形成・保守が困難な高架橋や地下鉄、長大トンネル等に採用されている。特許文献1にはバラスト道床をコンクリート道床化する工法に関する技術が開示されている。もっとも、道床バラストには上述したような機能ないし役割があることから、例えば騒音振動対策が重視される家屋が近接した線路区間においてはバラスト軌道を採用する等、その用途等に応じて適宜使い分けがなされている。   The structure of a railroad track may be changed for various reasons. A slab track is a structure in which concrete plates are laid on a reinforced concrete roadbed, and rails are installed on the plates. As one of the labor-saving tracks, viaducts, subways, and long tunnels where the formation and maintenance of ballast roadbeds are difficult. Etc. Patent Document 1 discloses a technique related to a method for converting a ballast roadbed into a concrete roadbed. However, because the roadbed ballast has the functions and roles as described above, for example, a ballast track is adopted in a track section where a house where noise and vibration countermeasures are important is used, and the ballast can be properly used depending on the application. Has been made.

特開2011−225382号公報JP2011-225382A

河川の流路は、治水や利水のための河川改修整備または長期的な河岸の自然浸食により、人為的に変更されたり自然に変化したりすることがある。河川の流路が変更等されることにともない、鉄道営業線と河川の交差位置が変更され、旧河川上に鉄道用軌道を架け渡すために設置していた橋りょうやボックスカルバート(以下「橋りょう等」という。)が不要となる場合がある。この場合、橋りょう等を安全に運用するための保守点検コストの削減を図る観点から、橋りょう等の利用を廃して、旧河川を埋め立て、従来利用していた鉄筋コンクリート路盤を、砕石を投入して形成される路盤(以下「砕石路盤」という。)に変更することが考えられる。このような路盤構造の変更の要請は、河川に架け渡された橋りょう等に限らず、窪地のような凹地に架け渡された橋りょう全般にも生じ得る。   River flow paths may be artificially altered or naturally changed due to river improvement and maintenance for flood control or water use or long-term natural erosion of riverbanks. Along with the change of the river flow path, the crossing position of the railway business line and the river was changed, and bridges and box culverts (hereinafter referred to as “bridges, etc.”) installed to bridge the railway track on the old river ") May be unnecessary. In this case, from the viewpoint of reducing maintenance inspection costs for the safe operation of bridges, etc., the use of bridges, etc. is abolished, old rivers are reclaimed, and reinforced concrete roadbeds that have been used in the past are formed by crushed stone It is conceivable to change to a roadbed (hereinafter referred to as “crushed stone roadbed”). Such a request for the change of the roadbed structure can occur not only for bridges over rivers, but also for bridges over general depressions such as depressions.

しかしながら、砕石路盤に変更するために、橋りょう等の全部を解体撤去する方法を採ると、代替路線を仮設する等の大々的な工事が必要となるため、鉄道運行に支障をきたし、コストが増大するとともに工期が伸びてしまう。一方、砕石路盤に変更するために、橋りょう等の全部を砕石等で埋設し、その上に軌条を敷設する方法を採ると、軌条の高さ(レベル)を上げる工事が必要となり、鉄道車両の運行速度等に影響を及ぼしてしまう等の問題が生じる。加えて、各鉄道事業者は、軌道保守の観点から、線路下に電線路やガス管等の路盤横断物を埋設しようとする場合には路盤横断物を路盤の施工基面から所定の深さ以下(例えば施工基面から300mm以深)に埋設しなければならないといった基準を設けているところ、橋りょう等の全部を埋設してしまう方法では、埋設物が障害となって当該基準を充たすことができず、軌道保守に支障をきたすおそれがある。   However, taking the method of dismantling and removing all bridges, etc. to change to a crushed stone roadbed requires extensive construction such as temporary construction of alternative routes, which hinders railway operation and increases costs. At the same time, the construction period will increase. On the other hand, in order to change to a crushed stone roadbed, burying all of the bridges with crushed stones, etc., and laying a rail on it, it will be necessary to work to raise the level of the rail, Problems such as affecting the operation speed occur. In addition, from the viewpoint of track maintenance, each railroad operator, when trying to embed a roadbed crossing such as an electric wire or a gas pipe under the track, put the roadbed crossing from the construction base of the roadbed to a predetermined depth. The following standard (for example, a depth of 300 mm or more from the construction base) is provided. However, in the method of embedding all bridges, etc., the buried object becomes an obstacle and the standard can be satisfied. Therefore, the track maintenance may be hindered.

本発明は、上記課題に鑑みてなされたものであり、鉄筋コンクリート路盤が架け渡された鉄道橋の解体にともなうバラスト軌道の路盤形成方法を提供することを目的とする。   This invention is made | formed in view of the said subject, and it aims at providing the roadbed formation method of the ballast track | orbit accompanying the dismantling of the railway bridge over which the reinforced concrete roadbed was spanned.

本発明は、鉄筋コンクリート路盤が架け渡された鉄道橋の解体にともなうバラスト軌道の路盤形成方法であって、
(ア)前記鉄筋コンクリート路盤の底面側に鉄板支持用の支保を組み、当該支保の上に鉄板を載置し、当該鉄板上に複数の断面円形部材を軌条直交方向に並べ、前記支保の高さを調整して前記鉄板と前記鉄筋コンクリート路盤との間に前記断面円形部材を挟み込む工程と、
(イ)前記支保の下端から前記鉄板までセメント系材料で埋め固めて、前記鉄板に負荷される荷重を受ける支持層を形成する工程と、
(ウ)前記鉄筋コンクリート路盤が軌条延伸方向に所望の間隔でブロック状に分割された状態となるように、前記鉄筋コンクリート路盤を軌条直交方向に切削する工程と、
(エ)ブロック状に分割された状態の鉄筋コンクリート路盤を個々のブロックごとに軌条直交方向に引き抜き、引抜くことにより生じた空間に砕石を投入することにより、前記鉄筋コンクリート路盤を順次砕石路盤に変更する工程と、
を含むことを特徴とする。前記(ア)の工程においては、前記鉄筋コンクリート路盤の底面側にパイプサポートを立設して鉄板支持用の支保を組み、このパイプサポートを伸縮調整して断面円形部材を鉄板と鉄筋コンクリート路盤との間に挟み込むようにしても良い。また、前記(ウ)の工程にいう「分割された状態」には、ほぼ分割された状態を含むものとし、かかる状態のブロックを引き抜く際には、打撃力等を加えて隣接するブロック状の部分と完全に分割してから、軌条直交方向に引き抜くものとする。
The present invention is a method of forming a roadbed for a ballast track accompanying the dismantling of a railway bridge over which a reinforced concrete roadbed is bridged,
(A) Assembling a support for supporting an iron plate on the bottom side of the reinforced concrete roadbed, placing an iron plate on the support, arranging a plurality of circular cross-section members on the iron plate in the direction perpendicular to the rail, and height of the support Adjusting the circular plate member between the steel plate and the reinforced concrete roadbed by adjusting,
(A) a step of filling a cement-based material from the lower end of the support to the iron plate and forming a support layer that receives a load applied to the iron plate;
(C) cutting the reinforced concrete roadbed in the direction orthogonal to the rails so that the reinforced concrete roadbed is divided into blocks at desired intervals in the rail extension direction;
(D) Pulling out the reinforced concrete roadbed divided into blocks in the direction perpendicular to the rails for each block, and putting the crushed stone into the space created by the drawing, the reinforced concrete roadbed is sequentially changed to the crushed stone roadbed Process,
It is characterized by including. In the step (a), a pipe support is erected on the bottom side of the reinforced concrete roadbed and a support for supporting the steel plate is assembled, and the pipe support is stretched and adjusted so that the cross-sectional circular member is placed between the steel plate and the reinforced concrete roadbed. You may make it pinch. Further, the “divided state” referred to in the step (c) includes a substantially divided state, and when pulling out the block in such a state, an adjacent block-like portion is applied by applying striking force or the like. And after complete division, it is pulled out in the direction perpendicular to the rail.

本発明は、道床バラストを支持する鉄筋コンクリート路盤が架け渡された鉄道橋の解体にともなうバラスト軌道の路盤形成方法であって、
前記(エ)の工程が、
ブロック状に分割された状態の鉄筋コンクリート路盤のうち前記断面円形部材上にある各ブロックについて、
(a)いずれか1つを引抜対象部として選択し、
(b)引抜対象部周辺の道床バラスト含む砕石を除去し、前記断面円形部材上を滑らせるようにして当該引抜対象部を軌条直交方向に引き抜き、引き抜くことにより生じた前記鉄板上の空間に砕石を投入して砕石路盤を形成することにより、当該引抜対象部の区間を鉄筋コンクリート路盤から砕石路盤に変更した後、路盤上に道床バラストを埋め戻し、
(c)砕石路盤に変更された区間に隣接するブロックを次の引抜対象部として選択して前記(b)の工程を行うことを、前記断面円形部材上にある各ブロックについて個々に順次行う工程を含むものであっても良い。
The present invention is a method for forming a roadbed for a ballast track accompanying the dismantling of a railway bridge over which a reinforced concrete roadbed for supporting a roadbed ballast is bridged,
The step (d)
About each block on the cross-sectional circular member among the reinforced concrete roadbed divided into blocks,
(A) Select any one as a drawing target part,
(B) The crushed stone including the ballast ballast around the extraction target portion is removed, and the extraction target portion is extracted in the direction orthogonal to the rail so as to slide on the circular member in the cross section, and the crushed stone is created in the space on the iron plate generated by the extraction. After changing the section of the extraction target part from reinforced concrete roadbed to crushed stone roadbed by filling the roadbed ballast on the roadbed,
(C) A step of sequentially performing each of the blocks on the cross-sectional circular member individually by selecting the block adjacent to the section changed to the crushed stone roadbed as the next extraction target portion and performing the step (b). May be included.

本発明は、前記(a)において選択される引抜対象部は軌条直交方向に連続して開けられた削孔によりブロック状に分割されていることが好ましい。   In the present invention, it is preferable that the drawing target portion selected in (a) is divided into blocks by a drilling hole continuously opened in the direction perpendicular to the rail.

本発明は、前記断面円形部材は単管パイプであり、ブロック状に分割された状態の鉄筋コンクリート路盤のうち前記断面円形部材上にある各ブロックが、少なくとも2本以上の単管パイプにより支承されるように、前記(ア)の工程において前記単管パイプを複数並べて挟み込むことが好ましい。   According to the present invention, the circular member in cross section is a single pipe pipe, and each block on the circular cross section member of the reinforced concrete roadbed divided into blocks is supported by at least two single pipes. As described above, in the step (a), it is preferable that a plurality of the single pipes are arranged side by side.

本発明は、前記(ア)の工程の前に、前記鉄筋コンクリート路盤の下方にエアモルタルを打設してエアモルタル層を形成し、当該エアモルタル層の上にコンクリートを打設して保護層を形成する工程を含み、
前記(ア)の工程において、当該保護層上に前記支保を組むことにより、前記鉄板に負荷された荷重を前記支保及び前記支持層を介して前記保護層及び前記エアモルタル層で受けることが好ましい。
Before the step (a), the present invention forms an air mortar layer by placing an air mortar below the reinforced concrete roadbed, and places concrete on the air mortar layer to form a protective layer. Including the step of forming,
In the step (a), it is preferable that the load applied to the iron plate is received by the protective layer and the air mortar layer via the support and the support layer by assembling the support on the protective layer. .

本発明は、前記(エ)の工程の前に、前記鉄板の高さ位置近傍まで砕石による腹付盛土をして前記支持層の両脇に腹付部を形成し、当該腹付部の上に養生鉄板を敷く工程を含み、
前記(エ)の工程において、軌条直交方向に引き抜かれた前記ブロックを当該養生鉄板で受けるようにしても良い。
Before the step (d), the present invention forms a belly fill with crushed stone to the vicinity of the height position of the iron plate to form a bellows on both sides of the support layer, and Including the process of laying a curing iron plate on
In the step (d), the block drawn in the direction orthogonal to the rail may be received by the cured iron plate.

本発明によれば、従前の軌条の高さを維持して鉄道車両の安全かつ所定のタイムスケジュールによる運行を確保しながら、鉄筋コンクリート路盤が架け渡された鉄道橋の解体にともなうバラスト軌道の路盤形成を実現することができる。本発明によれば、鉄筋コンクリート路盤が架け渡された鉄道橋の利用を廃して、鉄道橋を安全に運用するための保守点検コストの削減を図ることができる。本発明によれば、代替輸送路線を仮設する等といった大々的な工事が不要であり、鉄道車両の運行が無い深夜等の限られた時間帯において工事期限に間に合うように確実かつ効率的に工事を進めることができる。   According to the present invention, the base of the ballast track is formed along with the dismantling of the railway bridge over which the reinforced concrete road base is bridged while maintaining the conventional rail height and ensuring the safety and operation of the railway vehicle according to a predetermined time schedule. Can be realized. ADVANTAGE OF THE INVENTION According to this invention, the use of the railway bridge over which the reinforced concrete roadbed was bridged can be abolished, and the maintenance inspection cost for operating a railway bridge safely can be aimed at. According to the present invention, a large-scale construction such as temporarily setting up an alternative transportation route is unnecessary, and the construction is surely and efficiently performed in time for the construction deadline in a limited time zone such as midnight when there is no operation of the railway vehicle. Can proceed.

本発明によれば、道床バラストを支持する鉄筋コンクリート路盤が架け渡された鉄道橋にあっては、従前通りの鉄道の運行に支障をきたすことなく、道床バラストを支持する鉄筋コンクリート路盤が架け渡されていた区間に新たに砕石路盤を形成することができ、当該砕石路盤上に道床バストを埋め戻すことによりバラスト軌道を再構築することもできる。日中等の鉄道車両の運行量が多い時間帯においては通常の運転走行を可能とする状態に戻すことが可能であり、鉄道車両の運行に支障をきたすことなく、バラスト軌道が敷設された鉄道橋の鉄筋コンクリート路盤を解体して、バラスト軌道が敷設された砕石路盤に変更することができる。   According to the present invention, in the railway bridge over which the reinforced concrete roadbed supporting the roadbed ballast is bridged, the reinforced concrete roadbed supporting the roadbed ballast is bridged without impeding the operation of the conventional railway. A new crushed stone roadbed can be formed in the section, and the ballast track can be reconstructed by refilling the roadbed bust on the crushed stone roadbed. Railroad bridges with a ballast track that can be returned to the normal driving mode during hours when there is a large amount of railcar operation such as during the daytime, without interfering with the operation of the railcar. The reinforced concrete roadbed can be disassembled and changed to a crushed stone roadbed with a ballast track.

旧河川に設置された水路用ボックスカルバートの上床版上にバラスト軌道が敷設された状況を模式的に示す平面図である。It is a top view which shows typically the condition where the ballast track | orbit was laid on the upper floor slab of the box culvert for waterways installed in the old river. 図1に示すボックスカルバートを軌条延伸方向から模式的に示すA−A断面図である。It is AA sectional drawing which shows the box culvert shown in FIG. 1 typically from a rail extending | stretching direction. 図1に示すボックスカルバートを軌条直交方向から模式的に示す正面図である。It is a front view which shows typically the box culvert shown in FIG. 1 from a rail orthogonal direction. エアモルタル等打設工程の一形態を適用した状況を模式的に示す正面図である。It is a front view which shows typically the condition which applied one form of placement processes, such as air mortar. 支保工程の一形態を適用した状況を模式的に示す正面図である。It is a front view which shows typically the condition which applied one form of the support process. 図5の部分拡大図である。It is the elements on larger scale of FIG. 支持層形成工程の一形態を適用した状況を模式的に示す正面図である。It is a front view which shows typically the condition which applied one form of the support layer formation process. 腹付工程の一形態を適用した状況を模式的に示す正面図である。It is a front view which shows typically the condition which applied one form of the stomaching process. 図8に示すボックスカルバートを軌条延伸方向から模式的に示すB−B断面図である。It is BB sectional drawing which shows typically the box culvert shown in FIG. 8 from a rail extending | stretching direction. 分割工程の一形態を適用した状況を模式的に示す正面図である。It is a front view which shows typically the condition which applied one form of the division | segmentation process. 除去工程の一形態を適用した状況を模式的に示す正面図であり、引抜対象部として選択したブロック周辺を拡大して示す部分断面図である。It is a front view which shows typically the condition which applied one form of the removal process, and is a fragmentary sectional view which expands and shows the block periphery selected as an extraction object part. 引抜き工程の一形態を適用中の状況を軌条延伸方向から模式的に示す説明図である。It is explanatory drawing which shows typically the condition in which one form of a drawing process is being applied from a rail extending direction. 砕石投入工程及び埋戻し工程の一形態を適用した状況を模式的に示す正面図であり、引き抜いたブロック周辺を拡大して示す部分断面図である。It is a front view which shows typically the condition which applied one form of a crushed stone injection | throwing-in process and a backfilling process, and is a fragmentary sectional view which expands and shows the extracted block periphery. 除去工程の一形態を第2のブロックに対して適用した状況を模式的に示す正面図であり、第2のブロック周辺を拡大して示す部分断面図である。It is a front view which shows typically the condition where one form of the removal process was applied with respect to the 2nd block, and is a fragmentary sectional view which expands and shows the 2nd block periphery. 砕石投入工程及び埋戻し工程の一形態を適用した状況を模式的に示す正面図であり、引き抜いたブロック周辺を拡大して示す部分断面図である。It is a front view which shows typically the condition which applied one form of a crushed stone injection | throwing-in process and a backfilling process, and is a fragmentary sectional view which expands and shows the extracted block periphery. 投入された砕石等の落下を防止するための土のうを設置した状況を模式的に示す平面図である。It is a top view which shows typically the condition which installed the sandbag for preventing falling of the crushed stone etc. which were thrown in. 側壁上部以外の上床版を撤去した状況を模式的に示す正面図であり、引き抜いたブロック周辺を拡大して示す部分断面図である。It is a front view which shows typically the situation which removed the upper floor slab other than the side wall upper part, and is a fragmentary sectional view which expands and shows the extracted block periphery. 除去工程の一形態を側壁上部のブロックに対して適用した状況を模式的に示す正面図であり、側壁上部のブロック周辺を拡大して示す部分断面図である。It is a front view which shows typically the condition which applied one form of the removal process with respect to the block of a side wall upper part, and is a fragmentary sectional view which expands and shows the block periphery of a side wall upper part. 埋戻し工程の一形態を適用した状況を模式的に示す正面図であり、引き抜いた側壁上部のブロック周辺を拡大して示す部分断面図である。It is a front view which shows typically the condition which applied one form of the backfilling process, and is a fragmentary sectional view which expands and shows the block periphery of the extracted side wall upper part. 除去工程の一形態を側壁上部左端のブロックに対して適用した状況を模式的に示す正面図であり、側壁上部のブロック周辺を拡大して示す部分断面図である。It is a front view which shows typically the condition which applied one form of the removal process with respect to the block of the upper left side wall, and is a fragmentary sectional view which expands and shows the block periphery of the upper side wall. 整形工程の一形態を適用した状況を模式的に示す部分断面図である。It is a fragmentary sectional view showing typically the situation where one form of the shaping process was applied. 図21に示すボックスカルバートを軌条延伸方向から模式的に示すC−C断面図である。It is CC sectional drawing which shows typically the box culvert shown in FIG. 21 from a rail extending | stretching direction. 旧河川に設置された橋りょうの橋桁上にバラスト軌道が敷設された状況を軌条直交方向から模式的に示す正面図である。It is a front view which shows typically the condition by which the ballast track | orbit was laid on the bridge girder of the bridge installed in the old river from a rail orthogonal direction. 図23に示す橋りょうに対して、エアモルタル等打設工程、支保工程及び支持層形成工程の一形態を適用した状況を軌条直交方向から模式的に示す正面図である。It is a front view which shows typically the condition which applied one form of an air mortar placing process, a support process, and a support layer formation process with respect to the bridge shown in FIG. 23 from a rail orthogonal direction. 図24に示す橋りょうに対して、腹付工程及び分割工程の一形態を適用した状況を軌条直交方向から模式的に示す正面図である。It is a front view which shows typically the condition which applied one form of the stomaching process and the division | segmentation process with respect to the bridge shown in FIG. 24 from a rail orthogonal direction.

以下、本発明の一実施の形態を図面に基づいて詳細に説明する。先ず、図1から図22に基づいて単線のバラスト軌道が敷設された水路用のボックスカルバートを例として説明するが、本発明の適用対象はこれに限られるものではなく、鉄筋コンクリート製の橋桁が架け渡された橋りょう(図23から図25参照)や、上り線または下り線の一方のみが鉄筋コンクリート製の橋りょうである場合にも適用することができ、更には、河川に架け渡された橋りょう等に限らず、窪地のような凹地に架け渡されたコンクリート製鉄道橋全般にも適用することができるものである。   Hereinafter, an embodiment of the present invention will be described in detail with reference to the drawings. First, a box culvert for a water channel provided with a single-line ballast track will be described as an example based on FIGS. 1 to 22, but the application target of the present invention is not limited to this, and a bridge girder made of reinforced concrete is installed. It can also be applied to bridges that have been handed over (see Figs. 23 to 25), or where only one of the up and down lines is a reinforced concrete bridge, and moreover to bridges over rivers, etc. The present invention is not limited to this, and can be applied to all concrete railway bridges spanned in depressions such as depressions.

図1から図3は、本発明が適用される前の、鉄道橋として利用されている水路用ボックスカルバート10を示したものであり、図1は旧河川に設置された水路用ボックスカルバート10の上床版12上にバラスト軌道1が敷設された状況を模式的に示す平面図であり、図2は図1に示すボックスカルバート10を軌条延伸方向から模式的に示すA−A断面図であり、図3は図1に示すボックスカルバート10を軌条直交方向から模式的に示す正面図である。   FIGS. 1 to 3 show a waterway box culvert 10 used as a railway bridge before the present invention is applied. FIG. 1 shows a waterway box culvert 10 installed in an old river. FIG. 2 is a plan view schematically showing a situation where the ballast track 1 is laid on the upper floor slab 12, and FIG. 2 is a cross-sectional view taken along line AA schematically showing the box culvert 10 shown in FIG. FIG. 3 is a front view schematically showing the box culvert 10 shown in FIG. 1 from the direction perpendicular to the rail.

先ず、図1から図3に基づいて、本発明を適用する前の鉄道橋の状況を説明する。図1に示す旧河川9は、以前は水路として利用されていたものであり、旧河川9にバラスト軌道1を架け渡すために、旧河川9を横断するように鉄道橋としてのボックスカルバート10が設置されている。このボックスカルバート10の上床版12を鉄筋コンクリート路盤として、当該路盤上にバラスト軌道1が敷設されている。即ち、道床バラスト4を支持する鉄筋コンクリート路盤(上床版12)が架け渡された鉄道橋(ボックスカルバート10)が、旧河川9を横断するように設置されているが、河川の流路が変更等されたことに伴い、本発明を適用する時点では旧河川9は水路として利用されていない。   First, the situation of the railway bridge before applying the present invention will be described based on FIGS. 1 to 3. The old river 9 shown in FIG. 1 was previously used as a waterway, and a box culvert 10 serving as a railway bridge crosses the old river 9 so as to cross the ballast track 1 over the old river 9. is set up. The upper floor slab 12 of the box culvert 10 is used as a reinforced concrete roadbed, and the ballast track 1 is laid on the roadbed. In other words, the railway bridge (box culvert 10) over which the reinforced concrete roadbed (upper floor slab 12) supporting the roadbed ballast 4 is installed is set across the old river 9, but the flow path of the river is changed. Accordingly, the old river 9 is not used as a waterway at the time of applying the present invention.

ボックスカルバート10は略ロ字状のトンネル11(貫通口)を有する角筒状の鉄筋コンクリート製のRC函体構造物であり、図3に示すように、地盤面上に略水平に設置される底版13と、底版13のそれぞれの両端から鉛直方向に立ち上がる一対の側壁14と、それぞれの側壁14に架け渡されるように配置され天井部を構成する上床版12(「函体床版」と称することもある。)とを有する。両河岸の土手8には護岸壁が施工されており、護岸壁の傾斜面に沿って鉄筋コンクリート製のウイング15(土留め壁)がボックスカルバート10の側壁14に一体として設けられている。トンネル11内は、従来は河川の水路として利用されていたが、本発明が適用される時点では水路としての利用を廃している。   The box culvert 10 is a rectangular reinforced concrete RC box structure having a substantially rectangular tunnel 11 (through hole). As shown in FIG. 3, the bottom slab is installed substantially horizontally on the ground surface. 13, a pair of side walls 14 rising vertically from both ends of the bottom plate 13, and an upper floor plate 12 that is arranged so as to be bridged over the respective side walls 14 and constitutes a ceiling portion (referred to as a “box floor plate”) There is also. A revetment wall is constructed on the banks 8 of both river banks, and a reinforced concrete wing 15 (a retaining wall) is integrally provided on the side wall 14 of the box culvert 10 along the inclined surface of the revetment wall. The inside of the tunnel 11 has been conventionally used as a river channel, but is no longer used as a channel when the present invention is applied.

上床版12を鉄筋コンクリート路盤として、この路盤上には道床バラスト4が敷設されており、道床バラスト4上に所定の間隔で多数の枕木5が配設され、これらの枕木5上に軌条3が設置されている。上床版12及びウイング15の幅員方向の両端部(路肩部)には地覆6が突設され、側面視で凹形状の構成となっており(図2参照)、路盤上に敷設された道床バラスト4の落下を防いでいる。旧河川9の両岸には従来一般に用いられる施工方法により砕石路盤が形成され、この砕石路盤上に道床バラストが整形されている。この両岸の道床バラスト上と上床版12に支持された道床バラスト4上には軌条3が設置されており、本発明が適用される時点においても、このバラスト軌道上を所定のタイムスケジュールにて鉄道車両が運行している。したがって、鉄道橋としてのボックスカルバートを解体する等の工事は、鉄道車両の運行が無い深夜等の限られた時間帯において確実かつ効率的に行わなければならない。   The upper floor slab 12 is a reinforced concrete roadbed, and a roadbed ballast 4 is laid on the roadbed. A number of sleepers 5 are arranged on the roadbed ballast 4 at predetermined intervals, and rails 3 are installed on these sleepers 5. Has been. A ground cover 6 projects from both ends (road shoulders) in the width direction of the upper floor slab 12 and the wing 15 and has a concave configuration in a side view (see FIG. 2), and the road bed laid on the roadbed The ballast 4 is prevented from falling. A crushed stone roadbed is formed on both banks of the old river 9 by a conventionally used construction method, and a roadbed ballast is shaped on the crushed stone roadbed. A rail 3 is installed on the road bed ballast on the both banks and on the road bed ballast 4 supported by the upper floor slab 12, and at the time when the present invention is applied, the ballast track has a predetermined time schedule. Railway vehicles are operating. Therefore, construction such as dismantling the box culvert as a railway bridge must be performed reliably and efficiently in a limited time zone such as midnight when there is no operation of the railway vehicle.

本形態においては、軌道保守の観点から、前述の基準を充たすように、ボックスカルバート10の上床版12を解体撤去するものである。トンネル11内は空洞であるから、上床版12を解体撤去することにより、路盤の施工基面から所定の深さ以下には路盤横断物を埋設してはならない等の基準を充たすように路盤や道床の厚さを確保することが可能となる。もっとも、鉄筋コンクリート製の上床版12は数十トンもの重量物であるため、本発明においては、その全てを一度に撤去せず、これをブロック状に分割して、分割された状態の鉄筋コンクリート路盤を個々に引き抜いて撤去するものである。この点、上床版12を細分化するほど各ブロックは軽量となるが、鉄道車両走行上の安全性に支障をきたしかねず、また、工期が長期化するおそれがある。そこで、本発明は、一定以上の幅ないし重量にて上床版12をブロック状に分割しつつ、引き抜き時の摩擦を低減して引抜き撤去を可能とすることにより、限られた工期内で確実に解体撤去作業を行うものである。   In this embodiment, from the viewpoint of track maintenance, the upper floor slab 12 of the box culvert 10 is dismantled and removed so as to satisfy the above-described criteria. Since the tunnel 11 is hollow, the upper floor slab 12 is dismantled and removed so that a roadbed crossing object must not be buried below a predetermined depth from the construction base of the roadbed. It is possible to secure the thickness of the roadbed. However, since the upper slab 12 made of reinforced concrete is a heavy article of several tens of tons, in the present invention, not all of them are removed at once, but this is divided into blocks, and the divided reinforced concrete roadbed is used. They are individually pulled out and removed. In this respect, each block becomes lighter as the upper floor slab 12 is subdivided, but it may interfere with the safety in running the railway vehicle, and the construction period may be prolonged. Therefore, the present invention reliably removes the upper floor slab 12 in a block shape with a certain width or weight while reducing the friction at the time of pulling and enabling the pulling and removing within a limited construction period. Demolition and removal work.

次に、適宜図面を参照しつつ、各工程を説明する。   Next, each process is demonstrated, referring drawings suitably.

<準備工程> 先ず、バックホウ等の重機を用いて、旧河川9内を土砂で埋め立て、旧河川9内に作業ヤードを形成する。この際、後述のエアモルタル等打設工程を施工するため、トンネル11に至るスロープ(図示しない)を造成しておく。重機の進入エリア等には適宜鉄板を敷いて養生しておく。鉄道車両運行のための信号通信ケーブル等が配線されている場合には、作業ヤードの外周に切り回す等して、各種作業の支障とならないようにしておく。ケーブルを保護するため、埋設された落ち蓋式のU型側溝内にケーブルを配置したり、高密度ポリエチレン管に挿通したうえでその周囲を仮囲い鋼板(万能鋼板)で防護したりするようにしても良い。バラスト軌道に沿って鋼製の歩道が並設されている場合には、足場を組んで、溶接作業により解体・撤去しておく。 <Preparation process> First, using heavy machinery such as a backhoe, the inside of the old river 9 is filled with earth and sand, and a work yard is formed in the old river 9. At this time, a slope (not shown) leading to the tunnel 11 is created in order to construct a casting process such as air mortar described later. Carefully place an iron plate in the entrance area of heavy machinery. When a signal communication cable or the like for railway vehicle operation is wired, it is cut around the outer periphery of the work yard so as not to interfere with various operations. To protect the cable, place the cable in the U-shaped side groove embedded in the falling lid, or insert it into a high-density polyethylene pipe and protect it with a temporary enclosure steel plate (universal steel plate). May be. When steel sidewalks are set up along the ballast track, a scaffold is built and dismantled and removed by welding.

<エアモルタル等打設工程> 図4は、図1から3に示すボックスカルバート10に対して、エアモルタル等打設工程の一形態を適用した状況を模式的に示す正面図である。準備工程を経た後、図4に示すように、鉄筋コンクリート路盤の下方、即ち上床版12の下方であるトンネル11内に、所定の高さ位置までエアモルタルを打設してエアモルタル層20を形成し、エアモルタル層20の上に保護層21を形成するコンクリートを打設する。 <Air Mortar Placing Step> FIG. 4 is a front view schematically showing a state in which one form of the air mortar placing step is applied to the box culvert 10 shown in FIGS. After passing through the preparation step, as shown in FIG. 4, an air mortar layer 20 is formed by placing air mortar up to a predetermined height in the tunnel 11 below the reinforced concrete roadbed, that is, below the upper floor slab 12. Then, concrete for forming the protective layer 21 is placed on the air mortar layer 20.

ここで、本工程の一形態を適用した状況を詳細に説明する。エアモルタル層20の形成については、先ず、上流側及び下流側双方のトンネル11を塞ぐように所定の高さ位置まで型枠(図示しない)を設置し、作業ヤード内にアジテータトラック及びコンクリートポンプ車を進入させて、図4に示すとおり、トンネル11内の底板13上から所定の高さ位置までエアモルタルを打設して、固化させることにより行う。エアモルタルはコンクリートに比して軽量であるため、自重による底版13への負荷を軽減しつつ、後述の支持層22の自重や、鉄板23に負荷された荷重等を支持することができる。エアモルタルを打設する高さは、後述する支保工程により組まれる支保25の高さ等を踏まえて決定する。   Here, the situation where one form of this process is applied is demonstrated in detail. Regarding the formation of the air mortar layer 20, first, a formwork (not shown) is installed up to a predetermined height so as to close both the upstream and downstream tunnels 11, and an agitator truck and a concrete pump car are installed in the work yard. As shown in FIG. 4, the air mortar is driven from the bottom plate 13 in the tunnel 11 to a predetermined height position and solidified. Since the air mortar is lighter than concrete, it can support the weight of the support layer 22 described later, the load applied to the iron plate 23, and the like while reducing the load on the bottom plate 13 due to its own weight. The height for placing the air mortar is determined based on the height of the support 25 assembled by the support process described later.

保護層21の形成については、エアモルタルが固化した後、エアモルタル層20の打設面上に所定の厚さ(例えば20cm程度)のコンクリートを打設、固化させることにより行う。保護層21を形成することにより、エアモルタル層20の気泡内への水分の浸入を抑制してエアモルタル層20の劣化を抑制することができ、更には、支保25を頑強に支持することができる。保護層21内にはビニール製の防水シートを敷くようにしても良く、これによりエアモルタル層20への水分の浸入をより確実に抑制することができる。   The protective layer 21 is formed by casting and solidifying concrete having a predetermined thickness (for example, about 20 cm) on the casting surface of the air mortar layer 20 after the air mortar is solidified. By forming the protective layer 21, it is possible to suppress the ingress of moisture into the bubbles of the air mortar layer 20 to suppress the deterioration of the air mortar layer 20, and to support the support 25 firmly. it can. A vinyl waterproof sheet may be laid in the protective layer 21, whereby the intrusion of moisture into the air mortar layer 20 can be more reliably suppressed.

なお、エアモルタルや保護層21形成のためのコンクリートの打設を省略することもできる。すなわち、本発明においては、エアモルタル層20や保護層21の形成はいずれも任意的に選択されるものであり、例えば、底版13から支保を組んで後述の鉄板23を支持するようにしても良く、この場合には、支保の下端である底板13から鉄板23までセメント系材料で埋め固めて、鉄板23に負荷される荷重を受ける支持層のみを形成するようにしても良い。   In addition, the placement of concrete for forming the air mortar or the protective layer 21 can be omitted. In other words, in the present invention, the formation of the air mortar layer 20 and the protective layer 21 is arbitrarily selected. For example, a support is provided from the bottom plate 13 to support a later-described iron plate 23. In this case, only the support layer that receives the load applied to the iron plate 23 may be formed by filling the bottom plate 13 that is the lower end of the support to the iron plate 23 with a cement-type material.

<支保工程> 図5は、図4に示すボックスカルバート10に対して、支保工程の一形態を適用した状況を模式的に示す正面図であり、図6は、単管パイプの周辺を拡大して示す図5の部分拡大図である。エアモルタル等打設工程を経た後、図5及び図6に示すとおり、鉄筋コンクリート路盤である上床版12の底面側に鉄板支持用の支保25を組み、支保25の上に鉄板23を載置し、鉄板23と上床版12との間に複数の断面円形部材である単管パイプ24を軌条直交方向に並べ、支保25の高さを調整して鉄板23と上床版12との間に単管パイプ24を挟み込む。なお、断面円形部材としては、中空の単管パイプ24に限らず、断面円形である中実の丸棒部材であっても良い。 <Supporting Step> FIG. 5 is a front view schematically showing a state in which one form of the supporting step is applied to the box culvert 10 shown in FIG. 4, and FIG. 6 is an enlarged view of the periphery of the single pipe. It is the elements on larger scale of FIG. After the air mortar placing process, as shown in FIGS. 5 and 6, a support 25 for supporting an iron plate is assembled on the bottom surface side of the upper floor slab 12 which is a reinforced concrete roadbed, and the iron plate 23 is placed on the support 25. A single pipe 24 having a plurality of circular members in cross section is arranged between the iron plate 23 and the upper floor slab 12 in the direction orthogonal to the rail, and the height of the support 25 is adjusted to provide a single pipe between the iron plate 23 and the upper floor slab 12. The pipe 24 is sandwiched. Note that the circular member having a circular cross section is not limited to the hollow single pipe 24 but may be a solid round bar member having a circular cross section.

ここで、本工程の一形態を適用した状況を詳細に説明する。先ず、エアモルタル等打設工程を経た後、鉄筋コンクリート路盤である上床版12の底面側、本形態においては保護層21上に従来一般に使用される伸縮可能なパイプサポート27を立設して、鉄板支持用の支保25を組む。パイプサポート27は支保25の高さ調整手段として機能する。パイプサポート27同士は、筋交いにより相互に連結して剛性を確保する。次に、支保25の上に鉄板23を載置する。鉄板23は、鉄筋コンクリート路盤である上床版12の裏面に対向して、別言すればトンネル11の天井面11aに対向して、略水平に保持された状態で支保25により支持されている。本形態においては、鉄板23は、支保25の一構成要素であるH鋼26により支持されている。それぞれのH鋼26は、軌条直交方向に沿って横向きに寝かせた状態(I型の状態)で、軌条延伸方向に一定の間隔で配置されており、上面側に鉄板23が載置され、下面側がパイプサポート27により支持されている。なお、これらの支保25の組み方は一例に過ぎない。   Here, the situation where one form of this process is applied is demonstrated in detail. First, after passing through a placing process such as air mortar, an expandable pipe support 27 that is conventionally used is erected on the bottom side of the upper floor slab 12, which is a reinforced concrete roadbed, in this embodiment, on the protective layer 21, The support 25 for support is assembled. The pipe support 27 functions as a height adjusting means for the support 25. The pipe supports 27 are connected to each other by bracing to ensure rigidity. Next, the iron plate 23 is placed on the support 25. The iron plate 23 is supported by the support 25 in a state of being held substantially horizontally facing the back surface of the upper floor slab 12 which is a reinforced concrete roadbed, in other words, facing the ceiling surface 11a of the tunnel 11. In this embodiment, the iron plate 23 is supported by H steel 26 that is one component of the support 25. Each H steel 26 is laid sideways along the rail orthogonal direction (I-type state), and is arranged at regular intervals in the rail extending direction, and an iron plate 23 is placed on the upper surface side, and the lower surface The side is supported by a pipe support 27. In addition, how to assemble these supports 25 is only an example.

次いで、鉄板23上に、所定の間隔おきに、複数の単管パイプ24を軌条直交方向に並べる。なお、軌条直交方向とは、厳密に軌条に直交する場合に限られず、ほぼ直交する場合であっても良い。単管パイプ24は、ボックスカルバート10の奥行き寸法(桁の幅)よりも長尺のものが用いられる。分割された状態にあるブロック状の各部分(以下、単に「ブロック」とも称する。)は、少なくとも2本以上の単管パイプ24により支承されるような間隔で配置されることが好ましい(図11参照)。本形態のように、上床版12が各枕木5の間で分割されるように切削する場合には、各枕木5の間に単管パイプ24が2本ずつ配置されるような間隔で、鉄板23上に単管パイプ24を並べる。次いで、パイプサポート27の付属ハンドルを操作してパイプサポート27を伸長させることにより鉄板23を押し上げて、トンネル11と鉄板23との間に単管パイプ24を挟み込む。これにより、鉄板23上を断面円形の単管パイプ24が転動しないようにするとともに、上床版12を切断等して切り離した際のブロック120の自重による衝撃で単管パイプ24が潰れないようにすることができる。なお、単管パイプ24を所定の位置に挟み込む前に位置ズレが発生しないように、上床版12の側面に杭ないし釘を打ち付け、これに単管パイプ24の端部に巻き付けた鋼線を結びつけるようにして、位置を確定させておいたうえで、パイプサポート27を操作して伸長させて鉄板23を押し上げることにより、単管パイプ24を所定の位置で挟み込むようにしても良い。   Next, a plurality of single pipes 24 are arranged on the iron plate 23 in the direction perpendicular to the rails at predetermined intervals. The rail orthogonal direction is not limited to being strictly orthogonal to the rail, and may be substantially orthogonal. The single pipe 24 is longer than the depth dimension (girder width) of the box culvert 10. Each block-like portion (hereinafter also simply referred to as “block”) in a divided state is preferably arranged at an interval so as to be supported by at least two single pipes 24 (FIG. 11). reference). When the upper floor slab 12 is cut so as to be divided between the sleepers 5 as in this embodiment, the iron plate is spaced at intervals such that two single pipes 24 are arranged between the sleepers 5. Single pipes 24 are arranged on 23. Next, by operating the handle attached to the pipe support 27 and extending the pipe support 27, the iron plate 23 is pushed up, and the single pipe 24 is sandwiched between the tunnel 11 and the iron plate 23. This prevents the single pipe 24 having a circular cross section from rolling on the iron plate 23 and prevents the single pipe 24 from being crushed by an impact caused by the weight of the block 120 when the upper floor slab 12 is cut off or the like. Can be. In addition, a pile or a nail is struck on the side surface of the upper floor slab 12 and a steel wire wound around an end portion of the single pipe pipe 24 is tied to the side face of the upper floor slab 12 so that the positional deviation does not occur before the single pipe pipe 24 is inserted into a predetermined position. Thus, after the position is fixed, the single pipe 24 may be sandwiched at a predetermined position by operating and extending the pipe support 27 to push up the iron plate 23.

<支持層形成工程> 図7は、図5に示すボックスカルバートに対して、支持層形成工程の一形態を適用した状況を模式的に示す正面図である。支保工程を経た後、図7に示すように、支保25の下端から鉄板23までセメント系材料で埋め固めて、鉄板23に負荷される荷重を受ける支持層22を形成する。本形態においては、作業ヤード内にアジテータトラック及びコンクリートポンプ車を進入させて、支保25の下端である保護層21の上面から鉄板23の底面位置までセメント系材料であるコンクリートで埋め固めることにより、保護層21の上に支持層22を形成し、鉄板23に負荷された荷重を支保25及び支持層22を介して保護層21及びエアモルタル層20で受けるように構成している。 <Support Layer Forming Step> FIG. 7 is a front view schematically showing a state in which one form of the support layer forming step is applied to the box culvert shown in FIG. After passing through the supporting step, as shown in FIG. 7, the support layer 22 that receives the load applied to the iron plate 23 is formed by filling and solidifying the cement plate material from the lower end of the support 25 to the iron plate 23. In this embodiment, an agitator truck and a concrete pump car enter the work yard, and are filled with concrete, which is a cement-based material, from the upper surface of the protective layer 21 that is the lower end of the support 25 to the bottom surface position of the iron plate 23. A support layer 22 is formed on the protective layer 21, and the load applied to the iron plate 23 is received by the protective layer 21 and the air mortar layer 20 via the support 25 and the support layer 22.

分割された状態にある各ブロック120は相当の重量物であるが(枕木設置スパンの一例である約60cm間隔でブロック状に分割した場合でも、1つのブロックあたり自重が約3〜4t)、支保25及び支持層22にて強固に支持することが可能である。分割されたブロック120等の荷重は支保25及び支持層22を介して保護層21やエアモルタル層20に伝わるが、支持層22がパイプサポート27の高さ寸法以上の厚みを持っており(図7参照)、当該荷重が保護層21に伝わるまでの間に相当程度分散するため、トンネル11内の下層をエアモルタル層20で充たすことにしても十分な強度を保って支持することができる。なお、本形態においては、支持層22を形成するためのコンクリートが鉄板23の高さ位置まで打設されているが、砂利が混入されることによりH鋼26の凹凸部などの細部にコンクリートが入り込みにくい場合には、コンクリートの打設をH鋼26の下端の高さ位置までに止め、H鋼26の下端から鉄板23の高さ位置までをモルタルにより充填することにより、支保25の下端から鉄板23までセメント系材料の一種であるコンクリート及びモルタルで埋め固めて支持層を形成ようにしても良い。   Each of the blocks 120 in a divided state is a considerable heavy object (even if divided into blocks at intervals of about 60 cm, which is an example of a sleeper installation span, its own weight is about 3 to 4 t per block). 25 and the support layer 22 can be firmly supported. The load of the divided block 120 and the like is transmitted to the protective layer 21 and the air mortar layer 20 through the support 25 and the support layer 22, but the support layer 22 has a thickness greater than the height of the pipe support 27 (see FIG. 7), since the load is considerably dispersed until the load is transmitted to the protective layer 21, even if the lower layer in the tunnel 11 is filled with the air mortar layer 20, it can be supported with sufficient strength. In this embodiment, the concrete for forming the support layer 22 is placed up to the height of the iron plate 23. However, the gravel is mixed into the concrete such as the concave and convex portions of the H steel 26. If it is difficult to enter, the concrete placement is stopped up to the height position of the lower end of the H steel 26, and the lower end of the H steel 26 to the height position of the iron plate 23 is filled with mortar. The support layer may be formed by filling the iron plate 23 with concrete and mortar which are a kind of cementitious material.

<腹付工程> 図8は、図7に示すボックスカルバートに対して、腹付工程の一形態を適用した状況を模式的に示す正面図であり、図9は、図8に示すボックスカルバートを軌条延伸方向から模式的に示すB−B断面図である。後述の引抜工程の前に、図8及び図9に示すように、鉄板23の高さ位置近傍まで砕石による腹付盛土をして支持層22の両脇に腹付部31aを形成しておく。そして、腹付部31aの上に養生鉄板(図示しない)を敷き、軌条直交方向に引き抜かれたブロックを養生鉄板で受けるようにする。なお、腹付工程は、後述の引抜工程の前であれば足り、後述の分割工程を経た後に行っても良い。 <Attaching process> FIG. 8 is a front view schematically showing a state in which one form of the applying process is applied to the box culvert shown in FIG. 7, and FIG. 9 shows the box culvert shown in FIG. It is a BB sectional view showing typically from a rail extension direction. Before the drawing step described later, as shown in FIGS. 8 and 9, a bellows embankment with crushed stone is performed to the vicinity of the height position of the iron plate 23, and bellows 31 a is formed on both sides of the support layer 22. . Then, a cured iron plate (not shown) is laid on the belly portion 31a, and the cured iron plate receives the block drawn in the direction perpendicular to the rail. The bellying step is sufficient if it is before the drawing step described later, and may be performed after the dividing step described later.

ここで、図8及び図9に示す本工程の一形態を詳細に説明する。先ず、支持層形成工程を経て、トンネル11内をモルタルやコンクリート等のセメント系材料で充填・固化させた後、作業ヤード内にバックホウを進入させ、図8及び図9に示すように、ボックスカルバート10の上流側及び下流側の埋立地面上に、鉄板23の高さ位置近傍まで砕石等による腹付盛土をして、支持層22の両脇に腹付部31aを形成しておく。腹付盛土内には、適宜、層圧管理材を挿入しておく。この腹付盛土により、上流側及び下流側双方のトンネル11の両脇は砕石等で覆われて埋設された状態となる。腹付部31aは、図22に示すとおり、砕石路盤の下側の腹付部を構成する。腹付部31aを形成した後、ブロック120引き抜き用のバックホウ7を上床版12の近傍に移動させるためのスロープ(図12参照)を岩ずり盛土材等を用いて築いておく。ブロック120を引き出す際の養生として、腹付部31aの上面に養生鉄板(図示しない)を敷いておく。   Here, one form of this process shown in FIG.8 and FIG.9 is demonstrated in detail. First, the tunnel 11 is filled and solidified with a cement-based material such as mortar or concrete through a support layer forming step, and then a backhoe is inserted into the work yard. As shown in FIGS. On the upstream and downstream reclaimed land surfaces of 10, belly embankment with crushed stone or the like is performed to the vicinity of the height position of the iron plate 23, and bellows portions 31 a are formed on both sides of the support layer 22. A laminar pressure management material is appropriately inserted into the belly embankment. By this belly embankment, both sides of the tunnel 11 on both the upstream side and the downstream side are covered with crushed stone and buried. As shown in FIG. 22, the belly portion 31 a constitutes a belly portion on the lower side of the crushed stone roadbed. After forming the belly portion 31a, a slope (see FIG. 12) for moving the backhoe 7 for pulling out the block 120 to the vicinity of the upper floor slab 12 is built using a rock embankment material or the like. As the curing for pulling out the block 120, a curing iron plate (not shown) is laid on the upper surface of the belly portion 31a.

上述の準備工程から腹付工程までは、道床バラスト4を支持する鉄筋コンクリート路盤(上床版12)が架け渡された鉄道橋の解体・撤去を伴うものではなく、平常どおりの鉄道車両の運行を確保することができる。   From the above preparation process to the bellowing process, it is not accompanied by the dismantling / removal of the railway bridge over which the reinforced concrete roadbed (upper floor slab 12) that supports the roadbed ballast 4 is bridged, but the operation of the railway vehicle as usual is secured. can do.

<分割工程> 図10は、図8に示すボックスカルバートに対して、分割工程の一形態を適用した状況を模式的に示す正面図である。腹付工程を経た後、図10に示すように、鉄筋コンクリート路盤である上床版12が軌条延伸方向に所望の間隔でブロック状に分割された状態となるように、上床版12を軌条直交方向に切削する。地覆6を備える場合には、地覆6の分割も行う。作業時間が深夜等の鉄道車両の運行が無い時間帯に限られているため、本形態においては、上床版12を概ね枕木1本ごとの設置間隔に対応させて約60cm間隔でブロック状に分割しておき、一回の作業で引抜き撤去する上床版12のサイズ及び重量を所定の範囲内に限定している。これにより、ブロック120の引抜き作業の負担や、路盤砕石や道床バラストの形成のための作業時間を減らし、限られた時間内で確実に作業を終わらせることができる。 <Division process> FIG. 10: is a front view which shows typically the condition which applied one form of the division process with respect to the box culvert shown in FIG. After passing the bellows process, as shown in FIG. 10, the upper floor slab 12 is placed in the direction perpendicular to the rail so that the upper floor slab 12 which is a reinforced concrete roadbed is divided into blocks at desired intervals in the rail extension direction. To cut. When the ground cover 6 is provided, the ground cover 6 is also divided. Since the working time is limited to a time zone when there is no operation of the railway vehicle such as late at night, in this embodiment, the upper floor slab 12 is divided into blocks at intervals of about 60 cm corresponding to the installation interval for each sleeper. In addition, the size and weight of the upper floor slab 12 that is pulled out and removed in one operation is limited to a predetermined range. As a result, it is possible to reduce the burden of the pulling work of the block 120 and the work time for forming the roadbed crushed stone and the roadbed ballast, and the work can be reliably finished within a limited time.

ここで、図10に示す本工程の一形態を詳細に説明する。本形態においては、上床版12が各枕木5間を断面としてブロック状に分割された状態となるように切削され、図10に示す場合にあっては上床版12が14個のブロック120に分割されている。上床版12を複数のブロック120に分割するための切削手段として、本形態においては、コアドリリングマシンとワイヤーソーイングマシンを適宜併用する。ただし、最初に引抜対象部として選択されるブロック121(以下「第1のブロック」という。)は、コアドリリングマシン等を用いて、軌条直交方向に貫通する引出し用縁切り削孔17(φ150)を上下方向に連続して開けることによりブロック状に分割しておくことが好ましい。引出し用縁切り削孔17により分割することにより、第1のブロック121に隣接するブロックとの接触面積が減り、第1のブロック121を引抜く際に生じる側面摩擦が低減するので引き抜き易くなる。   Here, one form of this process shown in FIG. 10 is demonstrated in detail. In the present embodiment, the upper floor slab 12 is cut so as to be divided into blocks in a cross section between the sleepers 5, and in the case shown in FIG. 10, the upper floor slab 12 is divided into 14 blocks 120. Has been. As a cutting means for dividing the upper floor slab 12 into a plurality of blocks 120, in this embodiment, a core drilling machine and a wire sawing machine are used in combination as appropriate. However, a block 121 (hereinafter referred to as a “first block”) that is first selected as a drawing target portion uses a core drilling machine or the like to penetrate the drawing edge cutting hole 17 (φ150) penetrating in the direction perpendicular to the rail. It is preferable to divide into blocks by continuously opening in the vertical direction. By dividing by the drawing edge cutting hole 17, the contact area with the block adjacent to the first block 121 is reduced, and the side friction generated when the first block 121 is pulled out is reduced, so that it is easy to pull out.

上床版12をブロック状に分割するには、先ず、コアドリリングマシンを用いて通し穴18(φ75)を軌条直交方向に向けて穿設し、この通し穴18にワイヤーソーを通して輪切りすることにより切削して分断する。なお、上床版12上面から数cm(例えば3cm)下の位置に通し穴18を設け、上床版12上面から数cm下の位置から下方へ縦方向に切削する方法を採ることにより、回転切削中のワイヤーソーが路盤上に積載された砕石を噛んでしまうことを防ぐこともできる。上床版12上面から数cm以深までの部分は、引抜工程前までに、ブレーカーにより打撃力を加えて破壊することにより隣接するブロック120と完全に分割することが可能である。すなわち、「分割された状態」は、ほぼ分割された状態を含むものであっても良い。   In order to divide the upper floor slab 12 into blocks, first, a core drilling machine is used to drill through-holes 18 (φ75) in the direction perpendicular to the rails, and cutting by cutting the through-holes 18 through a wire saw. Then divide. During the rotational cutting, a through hole 18 is provided at a position several cm (for example, 3 cm) below the upper surface of the upper floor slab 12, and a vertical cutting is performed from a position several cm below the upper surface of the upper floor slab 12. It is possible to prevent the wire saw from biting the crushed stone loaded on the roadbed. A part from the upper surface of the upper floor slab 12 to a depth of several centimeters or more can be completely divided from the adjacent block 120 by breaking with a breaker by applying a striking force before the drawing process. That is, the “divided state” may include a substantially divided state.

地覆6の分割は、地覆6の厚さが10数cm程度に過ぎないため、ブロック状に分割された状態にするための切削手段として例えばコアドリリングマシンを用いて、軌条直交方向に円筒状の地覆縁切り削孔16を連続して開けることにより行う。図2及び図9に示すように、上床版12の幅員方向の両端部(橋の路肩部分)には地覆6が突設され、側面視で凹形状の構成となっている。このうち、ブロック120の引き抜き方向側にある地覆6については、図10に示すように、枕木5間に設定した分割面に沿って円筒状の地覆縁切り用削孔16を上下方向に連続して開けることにより、隣り合う地覆6同士を縁切りしておく。一方、ブロック120の引き抜き方向とは反対側にある地覆については、その高さ寸法により引抜き工程時に軌条3に衝突する可能性がある場合には、コアドリリングマシンを用いて切断のうえ解体撤去しておき、図12に示すとおり、解体箇所に土のう30を積んでおいて砕石路盤31上に敷設された砕石等の落下を防いでおく。   Since the thickness of the ground cover 6 is only about several tens of centimeters, the ground cover 6 is cylindrical in a direction orthogonal to the rail using, for example, a core drilling machine as a cutting means for dividing the ground cover 6 into a block shape. This is performed by continuously opening the ground cover edge cutting holes 16. As shown in FIG.2 and FIG.9, the ground cover 6 protrudes from the both ends of the width direction of the upper floor slab 12 (the road shoulder portion of the bridge), and has a concave configuration in a side view. Among these, as for the ground cover 6 on the drawing direction side of the block 120, as shown in FIG. 10, a cylindrical ground cover cutting hole 16 is continuously formed in the vertical direction along the dividing surface set between the sleepers 5. Then, the adjacent ground coverings 6 are cut out by opening. On the other hand, if there is a possibility that the ground cover on the side opposite to the drawing direction of the block 120 may collide with the rail 3 during the drawing process due to its height dimension, it is cut using a core drilling machine and dismantled. In addition, as shown in FIG. 12, sandbags 30 are piled on the dismantled portions to prevent falling of crushed stones laid on the crushed stone roadbed 31.

上床版12をブロック状に分割する都度、鉄道車両運行の安全確保のため、隣り合うブロック120同士を相互にプレート状の連結金具28で繋いでおく。これにより、鉄道車両がボックスカルバート10上を安全に通過できるようにしておく。また、ブロック120のそれぞれに、例えばU字状の鉄筋アンカーを打ち込むことにより、重機によりブロック120を引き抜き撤去する際のフック29を設けておく。各ブロック120を支える単管パイプ24のそれぞれには、ブロック120の自重や鉄道車両通過時の車両荷重等が負荷されるが、これらの荷重は支持層22中を分散して伝わるので、トンネル11内の下層をエアモルタル層20としても強度上問題ない。加えて、断面が円形の単管パイプ24を用いることにより荷重を分散できるので、パイプの変形を抑制できる。この点、単管パイプ24に代えてアングル鋼(山形鋼)を用いることとし、アングル鋼の折り曲げ部を上向きにして△状に配置することによってブロック120との接点が小さくなるようにしても良いが、引き抜き時に、ブロック120等の重みでアングル鋼がつぶれる可能性があることから、単管パイプ等の断面円形部材を用いることが好適である。   Each time the upper floor slab 12 is divided into blocks, adjacent blocks 120 are connected to each other by a plate-shaped connecting bracket 28 in order to ensure the safety of railway vehicle operation. As a result, the railway vehicle is allowed to pass safely over the box culvert 10. Further, a hook 29 is provided in each of the blocks 120 when the block 120 is pulled out and removed by a heavy machine by driving a U-shaped reinforcing bar anchor, for example. Each of the single pipes 24 that support each block 120 is loaded with its own weight of the block 120, a vehicle load when passing through the railway vehicle, and the like. Even if the lower layer is the air mortar layer 20, there is no problem in strength. In addition, since the load can be dispersed by using the single pipe 24 having a circular cross section, deformation of the pipe can be suppressed. In this regard, angle steel (angle steel) may be used in place of the single pipe 24, and the contact point with the block 120 may be reduced by arranging the angle steel with its bent portion facing upward. However, since the angle steel may be crushed by the weight of the block 120 or the like during drawing, it is preferable to use a circular cross-section member such as a single pipe pipe.

<選択工程>(第1のブロック) 分割工程を経た後、鉄道車両の通過予定時刻を踏まえ、例えば各ブロック120を一晩に一つずつのペースで引き抜いて撤去するが、この引抜き工程に先立ち、ブロック状に分割された状態の鉄筋コンクリート路盤(上床版12)のうち断面円形部材(単管パイプ24)上にある各ブロック120について、いずれか1つを引抜対象部として選択する。本形態においては、前述のとおり、第1のブロック121が最初の引抜き対象として選択されている。 <Selection process> (first block) After passing through the division process, for example, each block 120 is pulled out and removed at a pace of one night, based on the scheduled passage time of the railway vehicle. One of the blocks 120 on the circular cross-section member (single pipe 24) in the reinforced concrete roadbed (upper floor slab 12) divided into blocks is selected as a drawing target portion. In the present embodiment, as described above, the first block 121 is selected as the first extraction target.

<除去工程>(第1のブロック) 図11は、図10に示すボックスカルバートに対して、除去工程の一形態を適用した状況を模式的に示す正面図であり、引抜対象部として選択したブロック周辺を拡大して示す部分断面図である。本工程においては、引抜対象部周辺、即ち引抜き対象部として選択したブロック周辺の道床バラスト4を含む砕石を除去する。本形態においては、図11に示すように、最初に引抜対象部として選択した第1のブロック121の周辺の道床バラスト4を含む砕石を第1のブロック121に被らないように斜面状に除去するものである。なお、作業の邪魔にならないように、好ましくは、第1のブロック121の上方にある枕木5を隣接する起終点方の枕木5に移動させて仮止めしておく。 <Removal Step> (First Block) FIG. 11 is a front view schematically showing a state in which one form of the removal step is applied to the box culvert shown in FIG. 10, and is a block selected as a drawing target portion It is a fragmentary sectional view which expands and shows a periphery. In this step, the crushed stone including the roadbed ballast 4 around the drawing target portion, that is, around the block selected as the drawing target portion is removed. In this embodiment, as shown in FIG. 11, the crushed stone including the roadbed ballast 4 around the first block 121 that is first selected as the extraction target portion is removed in a slope shape so as not to cover the first block 121. To do. In order not to disturb the work, preferably, the sleeper 5 above the first block 121 is moved to the adjacent sleeper 5 at the start and end points and temporarily fixed.

<引抜き工程>(第1のブロック) 図12は、図11に示すボックスカルバートに対して、引抜き工程の一形態を適用中の状況を軌条延伸方向から模式的に示す説明図であり、ブロックの引き抜き方向を図中左向きの矢印で示している。除去工程(第1のブロック)を経た後、図12に示すように、引抜対象部である第1のブロック121を断面円形部材である単管パイプ24の上を滑らせるようにして軌条直交方向に引き抜く。本形態においては、バックホウ7を上床版12の近傍に移動させ、バックホウ7のアームと第1のブロック121に設けられたフック29とをワイヤーで連結した後、第1のブロック121に固定された連結金具28を取り外し、土のう30を撤去した後、バックホウ7を後退移動させることにより第1のブロック121を単管パイプ24上をスライドさせるようにして引き抜いて撤去している。そして単管パイプ24の上を滑らせるようにして軌条直交方向に引き抜かれた第1のブロック121を腹付部31a上に敷設した養生鉄板(図示しない)で受けるようにしている。第1のブロック121を引き抜いた後は、第1のブロック121を支承していた単管パイプ24を撤去することが望ましい。 <Drawing Step> (First Block) FIG. 12 is an explanatory view schematically showing a situation in which one form of the drawing step is being applied to the box culvert shown in FIG. The drawing direction is indicated by a left-pointing arrow in the figure. After passing through the removing step (first block), as shown in FIG. 12, the first block 121, which is the object to be pulled out, is slid on the single pipe 24, which is a circular member in cross section, in the direction perpendicular to the rail. Pull out. In this embodiment, the backhoe 7 is moved to the vicinity of the upper floor slab 12, the arm of the backhoe 7 and the hook 29 provided on the first block 121 are connected by a wire, and then fixed to the first block 121. After removing the connecting fitting 28 and removing the sandbag 30, the backhoe 7 is moved backward to pull out the first block 121 so as to slide on the single pipe 24. The first block 121 drawn in the direction perpendicular to the rail so as to slide on the single pipe 24 is received by a cured iron plate (not shown) laid on the belly portion 31a. After pulling out the first block 121, it is desirable to remove the single pipe 24 that has supported the first block 121.

上床版12はブロック120ごとに引き抜いて撤去されるが、スムーズにブロックを引き出せないと、所定の時間内に工事を完了することができないおそれがあるため、引き抜く際に過大な摩擦抵抗が発生しないように対策を講じておく必要がある。この点、本形態においては、2本の単管パイプ24上を滑らせるようにして第1のブロック121を引き抜くことにより、ブロックを引き抜く際の下面における接点が小さくなるため、引抜き時に第1のブロック121の底面に生じる摩擦力を低減することができる。2本の単管パイプ24上を滑らせることにより、安定して引き抜くことができる。また、第1のブロック121は引出し用縁切り削孔17を開けることによりブロック状に分割されているので、隣接するブロックとの接触面積が少なく、引抜き時にブロック121の側面に生じる摩擦力を低減することができるので、ブロックの引抜き作業をスムーズに行うことができる。なお、前述のとおり、ブロック121の引き抜き方向とは反対側にある地覆については解体撤去済みであるため、引き抜きの際にブロック121に突設された地覆が軌条3に接触するおそれはない。   The upper floor slab 12 is pulled out and removed for each block 120, but if the block cannot be pulled out smoothly, there is a possibility that the construction cannot be completed within a predetermined time, so that excessive friction resistance does not occur when pulling out. It is necessary to take measures to ensure that In this respect, in the present embodiment, by pulling out the first block 121 so as to slide on the two single pipes 24, the contact point on the lower surface when the block is pulled out becomes smaller. The frictional force generated on the bottom surface of the block 121 can be reduced. By sliding on the two single pipes 24, it can be stably pulled out. Further, since the first block 121 is divided into blocks by opening the drawing edge cutting hole 17, the contact area with the adjacent block is small, and the frictional force generated on the side surface of the block 121 during drawing is reduced. As a result, the block can be pulled out smoothly. As described above, since the ground cover on the side opposite to the drawing direction of the block 121 has been dismantled, there is no possibility that the ground cover protruding from the block 121 will contact the rail 3 at the time of drawing. .

<砕石投入工程>(第1のブロック) 図13は、砕石投入工程及び埋戻し工程の一形態を適用した状況を模式的に示す正面図であり、引き抜いたブロック周辺を拡大して示す部分断面図である。引抜き工程(第1のブロック)を経た後、第1のブロック121を引き抜くことにより生じた鉄板23上の空間に砕石を投入して砕石路盤31を形成する。投入される砕石は、粒度調整砕石である。砕石を投入する箇所は引抜対象部として選択されたブロック121周辺に限られているため、転圧作業を含め、短時間で行うことができる。これにより、引抜対象部として選択された第1ブロック121の区間を鉄筋コンクリート路盤から砕石路盤に変更することができる。 <Crushing Stone Input Step> (First Block) FIG. 13 is a front view schematically showing a state in which one embodiment of the crushed stone charging step and the backfilling step is applied, and is a partial cross section showing an enlarged view of the extracted block periphery. FIG. After passing through the drawing step (first block), crushed stone is thrown into the space on the iron plate 23 generated by pulling out the first block 121 to form the crushed stone roadbed 31. The crushed stone to be input is a particle size adjusted crushed stone. Since the places where the crushed stone is introduced are limited to the periphery of the block 121 selected as the extraction target portion, it can be performed in a short time including the rolling operation. Thereby, the area of the 1st block 121 selected as an extraction object part can be changed from a reinforced concrete roadbed to a crushed stone roadbed.

<埋戻し工程>(第1のブロック) 砕石投入工程(第1のブロック)を経た後、図13に示すように、路盤上に道床バラスト4を埋め戻す。埋め戻される道床バラスト4は、除去工程(第1のブロック)において除去した道床バラストを再利用しても良いし、新たに準備した道床バラストを含むものであっても良い。道床バラスト4が崩落しないように、ブロック121を引き抜いた箇所のバラスト軌道1の両側に大型土のう32を設置しておくようにしても良い(図16参照)。道床バラスト4を埋め戻す箇所は引抜対象部のブロック121周辺の砕石路盤および未撤去の鉄筋コンクリート路盤(上床版12)上に限られているため、鉄道車両を運行に支障をきたすことなく、これらの作業を短時間で実施することが可能である。ブロック引抜き用のバックホウ7と砕石投入用の軌陸バックホウをそれぞれ準備すれば、限られた作業時間内でより確実に作業を終わらせることができる。道床バラスト4を投入して、砕石路盤31ないし未撤去の上床版12上にバラスト道床を復旧した後、枕木5を元の位置に戻して軌道を整備して、鉄道車両が運行可能な状態に復旧しておく。これにより、第1ブロック121の区間を道床バラスト4が敷設された砕石路盤31に変更することができる。なお、工期が夏場のような温度上昇期である場合には、道床安定剤を散布して軌条3の座屈を防ぐようにしても良い。 <Backfilling step> (First block) After passing through the crushed stone charging step (first block), the roadbed ballast 4 is backfilled on the roadbed as shown in FIG. The roadbed ballast 4 to be backfilled may reuse the roadbed ballast removed in the removal step (first block) or may include newly prepared roadbed ballast. Large sandbags 32 may be installed on both sides of the ballast track 1 where the block 121 is pulled out so that the roadbed ballast 4 does not collapse (see FIG. 16). Since the place where the roadbed ballast 4 is refilled is limited to the crushed stone roadbed around the block 121 and the unremoved reinforced concrete roadbed (upper floor slab 12), these railroad vehicles can be operated without hindering the operation of the railway vehicle. The work can be carried out in a short time. If the backhoe 7 for pulling out the block and the track backhoe for inputting crushed stone are prepared, the work can be completed more reliably within a limited work time. After loading the ballast ballast 4 and restoring the ballast roadbed on the crushed stone roadbed 31 or the unremoved upper floor slab 12, the sleepers 5 are returned to their original positions, the track is maintained, and the railway vehicle is ready for operation. Recover. Thereby, the area of the first block 121 can be changed to the crushed stone roadbed 31 on which the roadbed ballast 4 is laid. In addition, when a construction period is a temperature rise period like summer, you may make it prevent the buckling of the rail 3 by spraying a road bed stabilizer.

<選択工程>(第2のブロック) 第1のブロック121を引抜き撤去することにより砕石路盤に変更された区間に隣接するブロック122を、次の引抜対象部(以下「第2のブロック」という。)として選択する(図14参照)。 <Selection Step> (Second Block) The block 122 adjacent to the section changed to the crushed stone roadbed by pulling out and removing the first block 121 is referred to as the next extraction target portion (hereinafter referred to as “second block”). ) (See FIG. 14).

<除去工程>(第2のブロック) 図14は、除去工程の一形態を第2のブロックに対して適用した状況を模式的に示す正面図であり、第2のブロック周辺を拡大して示す部分断面図である。本工程においては、図14に示すように、次の引抜対象部周辺、即ち第2のブロック122周辺の道床バラスト4を含む砕石を除去する。これにより、当該選択したブロック122を単管パイプ24の上を滑らせるようにして軌条直交方向に引き抜くことができる状態としておく。本工程は、例えば、翌日以降の鉄道車両の運行が無い時間帯を利用して行われる。前述の除去工程(第1のブロック)と同様、図14に示すように、引抜対象部である第2のブロック122の周辺の道床バラスト4を含む砕石を第2のブロック122に被らないように斜面状に除去するとともに、好ましくは、第2のブロック122の上方にある枕木5を隣接する起終点方の枕木5に移動させて仮止めしておく。なお、道床安定剤を散布していたときは、バラスト融解剤を散布した後に除去作業を行う。 <Removal Step> (Second Block) FIG. 14 is a front view schematically showing a state in which one mode of the removal step is applied to the second block, and shows the periphery of the second block in an enlarged manner. It is a fragmentary sectional view. In this step, as shown in FIG. 14, the crushed stone including the roadbed ballast 4 around the next drawing target portion, that is, around the second block 122 is removed. As a result, the selected block 122 can be pulled out in the direction perpendicular to the rail so as to slide on the single pipe 24. This process is performed, for example, using a time zone in which there is no operation of the railway vehicle after the next day. As in the above-described removal step (first block), as shown in FIG. 14, the second block 122 is not covered with crushed stone including the roadbed ballast 4 around the second block 122 that is the extraction target portion. In addition, the sleeper 5 located above the second block 122 is preferably moved to the adjacent sleeper 5 at the start and end points and temporarily fixed. In addition, when the roadbed stabilizer is sprayed, the removal work is performed after spraying the ballast melting agent.

<引抜き工程>(第2のブロック) 砕石除去工程を経て、第2のブロック122の周辺の砕石を撤去した後、引き抜き作業の障害となる位置に設置された土のう30、32を移動させておき、その後、第1のブロック121と同様の工程により、引抜対象部である第2のブロック122を軌条直交方向に引き抜く。第1のブロック121を撤去しているため、第1のブロック121に隣接していた第2のブロックの側面(図14中左側面)は自由面となる。そこで、第2のブロック122が図14中右側面において隣接する第3のブロック123(第2のブロックの次に引抜対象部として選択するブロック)と密接した状態にある場合には、第2のブロック122を自由面側に逃がすように引き抜くようにすれば、第3のブロック123との接触摩擦を断ち切ることができ、よりスムーズに引き抜くことができる。なお、底面側に発生する摩擦は単管パイプ24上を滑らせることにより低減されることは、第1のブロック121の引抜き工程で述べたのと同様である。 <Drawing Step> (Second Block) After removing the crushed stone around the second block 122 through the crushed stone removing step, the sandbags 30 and 32 installed at the position where the drawing work is obstructed are moved. Then, the second block 122 that is the extraction target portion is extracted in the rail orthogonal direction by the same process as the first block 121. Since the first block 121 is removed, the side surface (left side surface in FIG. 14) of the second block adjacent to the first block 121 is a free surface. Therefore, when the second block 122 is in close contact with the third block 123 adjacent to the right side surface in FIG. 14 (the block to be selected as the extraction target portion next to the second block), the second block 122 If the block 122 is pulled out so as to escape to the free surface side, the contact friction with the third block 123 can be cut off and can be pulled out more smoothly. Note that the friction generated on the bottom side is reduced by sliding on the single pipe 24, as described in the drawing process of the first block 121.

<砕石投入工程>(第2のブロック) 図15は、砕石投入工程及び埋戻し工程の一形態を適用した状況を模式的に示す正面図であり、引き抜いた2番目のブロック周辺を拡大して示す部分断面図である。引抜き工程(第2のブロック)を経た後、第2のブロック122を引き抜くことにより生じた鉄板23上の空間に砕石を投入して砕石路盤31を形成する。これにより、当該引抜対象部として選択された第2のブロック122の区間を鉄筋コンクリート路盤から砕石路盤に変更する。砕石を投入する箇所は引き抜き対象のブロック122周辺に限られているため、転圧作業を含め、短時間で行うことができる。 <Crushing stone input process> (2nd block) FIG. 15: is a front view which shows typically the condition which applied one form of the crushed stone charging process and the backfilling process, and expanded the 2nd block periphery extracted. It is a fragmentary sectional view shown. After passing through the drawing step (second block), the crushed stone roadbed 31 is formed by throwing crushed stone into the space on the iron plate 23 generated by pulling out the second block 122. Thereby, the area of the 2nd block 122 selected as the said extraction object part is changed from a reinforced concrete roadbed to a crushed stone roadbed. Since the places where the crushed stone is introduced are limited to the periphery of the block 122 to be pulled out, it can be performed in a short time including the rolling work.

<埋戻し工程>(第2のブロック) 砕石投入工程(第2のブロック)を経た後、図15に示すように、路盤上に道床バラスト4を埋め戻して、路盤上にバラスト道床を復旧しておく。枕木5は元の位置に戻して軌道を整備しておき、鉄道車両が運行可能な状態に復旧しておく。その他の説明は第1のブロック121と同様であるから省略する。第2ブロックの除去工程、引抜き工程、砕石投入工程及び埋戻し工程は、一晩のうちに完了させることが望ましく、かつ、前述のとおり作業対象(区間)が限られていることから可能である。これにより、鉄道車両を運行に支障をきたすことなく、鉄道橋を構成する鉄筋コンクリート路盤の一部をバラスト軌道が敷設された砕石路盤に変更することができる。 <Backfilling step> (second block) After passing through the crushed stone charging step (second block), as shown in FIG. 15, the roadbed ballast 4 is backfilled on the roadbed, and the ballast roadbed is restored on the roadbed. Keep it. The sleepers 5 are returned to their original positions to maintain the track, and are restored to a state where the railway vehicle can be operated. Since other explanations are the same as those of the first block 121, they are omitted. It is desirable that the second block removal process, the drawing process, the crushed stone charging process, and the backfilling process be completed overnight, and the work target (section) is limited as described above. . Thereby, a part of the reinforced concrete roadbed constituting the railway bridge can be changed to a crushed stone roadbed on which a ballast track is laid without disturbing the operation of the railway vehicle.

図16は、投入された砕石等の落下を防止するための土のうを設置した状況を模式的に示す平面図であり、特に、第2のブロック122について埋戻し工程を終えた後の状況を示すものである。図16に示すように、砕石路盤31及び道床バラスト4が崩落しないように、適宜、ブロック121、122を引き抜いた箇所のバラスト軌道1の両側に大型の土のう32を設置しておく。   FIG. 16 is a plan view schematically showing a situation where a sandbag for preventing falling of crushed stones and the like that has been thrown in is installed, and particularly shows a situation after the backfilling process for the second block 122 is completed. Is. As shown in FIG. 16, large sandbags 32 are appropriately installed on both sides of the ballast track 1 where the blocks 121 and 122 are pulled out so that the crushed roadbed 31 and the roadbed ballast 4 do not collapse.

<第3のブロック以降> 第2のブロック122の撤去作業を終えた翌日以降の鉄道車両の運行が無い時間帯を利用して、第3のブロック123以降の撤去作業を行う。第3のブロック以降についても、砕石路盤に変更された区間に隣接するブロックの1つを引抜対象部として選択して(選択工程)、除去工程、引抜き工程、砕石投入工程及び埋戻し工程を行うことを、断面円形部材である単管パイプ24上にある各ブロックについて個々に順次行う。例えば一晩に1ブロックのペースで、選択工程、除去工程、引抜工程、砕石投入工程及び埋戻し工程を行うことにより、一晩に1ブロック区間分のペースで、徐々にバラスト軌道が敷設された砕石路盤に変更することができる。図17は、側壁上部以外の上床版を撤去した状況を模式的に示す正面図であり、引き抜いたブロック周辺を拡大して示す部分断面図である。図17に示すように、単管パイプ24上にあるブロック120を全て撤去して、砕石路盤31を形成し、当該砕石路盤31上に道床バラスト4を敷設して、砕石路盤31上にバラスト軌道1を復旧する。 <After the 3rd block> The removal work after the 3rd block 123 is performed using the time slot | zone when there is no operation of the rail vehicle after the next day after the removal work of the 2nd block 122 was completed. For the third and subsequent blocks, one of the blocks adjacent to the section changed to the crushed stone roadbed is selected as the extraction target part (selection process), and the removal process, the extraction process, the crushed stone input process, and the backfill process are performed. This is sequentially performed for each block on the single pipe 24 having a circular section. For example, by performing selection process, removal process, drawing process, crushed stone input process and backfill process at a pace of 1 block per night, the ballast track was gradually laid at a pace of 1 block per night. It can be changed to a crushed stone roadbed. FIG. 17 is a front view schematically showing a situation in which the upper floor slab other than the upper part of the side wall is removed, and is a partial cross-sectional view showing the extracted block periphery in an enlarged manner. As shown in FIG. 17, all the blocks 120 on the single pipe 24 are removed, a crushed stone roadbed 31 is formed, a roadbed ballast 4 is laid on the crushed stone roadbed 31, and a ballast track on the crushed stone roadbed 31. Restore 1

本発明によれば、従前の軌条を維持して鉄道車両の安全かつ所定のタイムスケジュールによる運行を確保しながら、深夜等の鉄道車両の運行が無い限られた時間帯において確実かつ効率的に工事を進めることができ、鉄筋コンクリート路盤としての上床版12を解体撤去して、バラスト軌道が敷設された砕石路盤に変更することができる。本発明によれば、夜間寝台鉄道車両や長距離貨物鉄道車両が運行されている鉄道区間のように、鉄道車両通過後に次の鉄道車両が通過するまでの間合い(間隔)が1時間程度に限られている場合であっても適用することが可能であり、仮に、一つの通過間隔内では除去工程、引抜き工程、砕石投入工程及び埋戻し工程の全てを施工できない場合又はそのおそれがある場合には、工程の途中で、道床バラスト4を除去したりブロックを撤去したりすることにより空になった空間にサンドルを仮設して軌条2を支えることにより鉄道車両を通過させ、通過後に工程の続きを施工することも可能である。   According to the present invention, while maintaining the conventional rails and ensuring the operation of the railway vehicle safely and according to a predetermined time schedule, the construction is reliably and efficiently performed in a limited time zone where there is no operation of the railway vehicle such as midnight. The upper floor slab 12 as a reinforced concrete roadbed can be dismantled and replaced with a crushed stone roadbed with a ballast track. According to the present invention, the interval (interval) until the next rail vehicle passes after the passage of the rail vehicle is limited to about one hour, as in a railway section in which a night sleeper rail vehicle or a long-distance cargo rail vehicle is operated. Even if it is, it is possible to apply, and if all of the removal process, drawing process, crushed stone input process and backfilling process cannot be performed or there is a possibility of it within one passage interval In the middle of the process, the railcar is passed by supporting the rail 2 by temporarily installing a sanddle in the empty space by removing the roadbed ballast 4 or removing the block. It is also possible to construct.

図18は、除去工程の一形態を側壁上部のブロックに対して適用した状況を模式的に示す正面図であり、側壁上部のブロック周辺を拡大して示す部分断面図である。側壁上部のブロック128を引き抜く際にも、当該ブロック128周辺の道床バラスト4を含む砕石を除去した後(図18参照)、バックホウ7を用いてこれを軌条直交方向に引き抜いて撤去する。図19は、埋戻し工程の一形態を適用した状況を模式的に示す正面図であり、引き抜いた側壁上部のブロック周辺を拡大して示す部分断面図である。引き抜き対象として選択したブロック128を引き抜くことにより生じた空間に砕石を投入することにより砕石路盤31を形成する。これにより、鉄筋コンクリート路盤を砕石路盤に変更し、次いで、道床バラスト4を埋め戻し、枕木5を元の位置に戻してバラスト軌道1を復旧しておき、鉄道車両が運行可能な状態に復旧しておく。   FIG. 18 is a front view schematically showing a state in which one mode of the removing step is applied to the block on the upper side wall, and is a partial cross-sectional view showing the periphery of the block on the upper side wall in an enlarged manner. Also when pulling out the block 128 at the upper side of the side wall, after removing the crushed stone including the roadbed ballast 4 around the block 128 (see FIG. 18), the backhoe 7 is used to pull it out in the direction perpendicular to the rail and remove it. FIG. 19 is a front view schematically showing a state in which one embodiment of the backfilling process is applied, and is a partial cross-sectional view showing an enlarged block periphery of the extracted upper side wall. The crushed stone roadbed 31 is formed by throwing crushed stone into the space generated by pulling out the block 128 selected as a drawing target. As a result, the reinforced concrete roadbed is changed to the crushed stone roadbed, then the roadbed ballast 4 is backfilled, the sleepers 5 are returned to their original positions, the ballast track 1 is restored, and the railway vehicle is restored to an operable state. deep.

図20は、除去工程の一形態を側壁上部左端のブロックに対して適用した状況を模式的に示す正面図であり、側壁上部のブロック周辺を拡大して示す部分断面図である。側壁上部左端のブロック129を撤去する際にも、ブロック129の周辺の道床バラスト4を含む砕石を除去した後、これを軌条直交方向に引き抜いて、引抜くことにより生じた空間に砕石を投入することにより、鉄筋コンクリート路盤を順次砕石路盤に変更する。なお、右側側壁上部のブロックも同様の方法により撤去する。   FIG. 20 is a front view schematically showing a state in which one mode of the removing step is applied to the left upper block of the side wall, and is a partial cross-sectional view showing the periphery of the upper block of the side wall in an enlarged manner. When removing the block 129 at the upper left end of the side wall, after removing the crushed stone including the roadbed ballast 4 around the block 129, the crushed stone is put in the space generated by pulling out the crushed stone in the direction orthogonal to the rail. Therefore, the reinforced concrete roadbed will be changed to a crushed stone roadbed in sequence. The block on the upper right side wall is also removed by the same method.

<整形工程> 図21は、整形工程の一形態を適用した状況を模式的に示す部分断面図である。図22は、図21に示すボックスカルバートを軌条延伸方向から模式的に示すC−C断面図である。上床版12を全て撤去して砕石路盤に変更した後(図21参照)、大型土のう32を撤去しながら、腹付部31a上に粒度調整砕石を用いて腹付盛土をすることにより、図22に示すように、側面視で台形状の法面を有する上部腹付部31bを砕石路盤31の両脇に整形する。次いで、上部腹付部31b上に道床バラスト4を敷設し、バラスト道床の両脇を整形する。以上の工程によれば、従前の軌条の高さを維持して鉄道車両の安全かつ所定のタイムスケジュールによる運行を確保しながら、砕石路盤31やバラスト道床を整形することができる。 <Shaping Step> FIG. 21 is a partial cross-sectional view schematically showing a situation where one form of the shaping step is applied. FIG. 22 is a CC cross-sectional view schematically showing the box culvert shown in FIG. 21 from the rail extending direction. After removing all the upper floor slabs 12 and changing to a crushed stone roadbed (see FIG. 21), while removing the large sandbag 32, by carrying out a flank embankment using a particle size-adjusted crushed stone on the abdomen 31a, FIG. As shown, the upper belly portion 31 b having a trapezoidal slope in side view is shaped on both sides of the crushed stone roadbed 31. Next, the road bed ballast 4 is laid on the upper belly portion 31b, and both sides of the ballast road bed are shaped. According to the above process, the crushed stone roadbed 31 and the ballast roadbed can be shaped while maintaining the height of the conventional rails and ensuring the operation of the railway vehicle in a safe and predetermined time schedule.

本発明は、橋台41の間に鉄筋コンクリート路盤としての橋桁42が架け渡された橋りょうタイプの鉄道橋にも適用することができる(図23から図25参照)。   The present invention can also be applied to a bridge-type railway bridge in which a bridge girder 42 as a reinforced concrete roadbed is bridged between abutments 41 (see FIGS. 23 to 25).

図23は、旧河川に設置された橋りょうの橋桁上にバラスト軌道が敷設された状況を軌条直交方向から模式的に示す正面図である。橋台41は、鉄筋コンクリート製の橋桁42の両端を支えている。橋桁42上にはバラスト軌道43が敷設されており、道床バラストが橋桁42により支持されている。橋台41間には旧来、水路(図示しない)が設けられていたが、本発明が適用される時点ではその用を廃している。橋りょうタイプの鉄道橋については、先ず、準備工程として、水路上に河床コンクリート44を整備する。既設の河床コンクリートが無い場合には、旧河川を埋め立てて整地した後、コンクリートを打設して新たに河床コンクリート44を形成する。河床コンクリート44があることにより、型枠の設置などエアモルタル層45の施工が行いやすくなるとともに、その上方に施工されるエアモルタル層45や支持層46、ブロック47等の荷重を分散して受けられるという効果がある。   FIG. 23 is a front view schematically showing the situation in which the ballast track is laid on the bridge girder of the bridge installed in the old river, from the direction perpendicular to the rail. The abutment 41 supports both ends of a reinforced concrete bridge girder 42. A ballast track 43 is laid on the bridge girder 42, and the roadbed ballast is supported by the bridge girder 42. Traditionally, a water channel (not shown) is provided between the abutments 41, but the use is abolished when the present invention is applied. For the bridge type railway bridge, first, as a preparation process, riverbed concrete 44 is prepared on the waterway. When there is no existing riverbed concrete, the old river is reclaimed and land is leveled, and then concrete is cast to form a new riverbed concrete 44. The existence of the riverbed concrete 44 facilitates the construction of the air mortar layer 45 such as the installation of a formwork, and also distributes and receives the loads of the air mortar layer 45, the support layer 46, the block 47, etc., which are constructed thereabove. There is an effect that is.

図24は、図23に示す橋りょうに対して、エアモルタル等打設工程、支保工程及び支持層形成工程の一形態を適用した状況を軌条直交方向から模式的に示す正面図である。図24に示すように、前記鉄筋コンクリート路盤(橋桁42)の下方にエアモルタルを打設してエアモルタル層45を形成し、当該エアモルタル層45の上にコンクリートを打設して保護層51を形成する工程を行った後、橋桁42の底面側に鉄板支持用の支保49を組み、支保49の上に鉄板48を載置し、鉄板48上に複数の断面円形部材としての単管パイプ50を軌条直交方向に並べ、支保49の高さを調整して鉄板48と橋桁42との間に単管パイプ50を挟み込む工程を行う。次に、支保49の下端から鉄板48までセメント系材料で埋め固めて、鉄板48に負荷される荷重を受ける支持層46を形成する工程を行う。保護層51上に支保49を組むことにより、鉄板48に負荷された荷重を支保49及び支持層46を介して保護層51及びエアモルタル層45で受けるようにしている。なお、単管パイプ50は、ブロック状に分割された状態の橋桁42のうち単管パイプ50上にある各ブロック47が、少なくとも2本以上の単管パイプ50により支承されるような間隔で鉄板48上に並べて挟み込まれている。これらの工程の詳細は、図1から図22を適宜参照して説明した前記実施の形態と同様であるので、詳細な説明は省略する。   FIG. 24 is a front view schematically showing, from the direction orthogonal to the rail, a state in which one form of the air mortar placing process, the supporting process and the support layer forming process is applied to the bridge shown in FIG. As shown in FIG. 24, an air mortar is formed below the reinforced concrete roadbed (bridge girder 42) to form an air mortar layer 45, and concrete is placed on the air mortar layer 45 to form a protective layer 51. After performing the forming step, a support 49 for supporting an iron plate is assembled on the bottom surface side of the bridge girder 42, an iron plate 48 is placed on the support 49, and a single pipe 50 as a plurality of circular members in cross section on the iron plate 48. Are arranged in the direction perpendicular to the rails, and the height of the support 49 is adjusted to sandwich the single pipe 50 between the iron plate 48 and the bridge girder 42. Next, a process of forming a support layer 46 that receives a load applied to the iron plate 48 by filling the support 49 with the cement-based material from the lower end to the iron plate 48 is performed. By assembling the support 49 on the protective layer 51, the load applied to the iron plate 48 is received by the protective layer 51 and the air mortar layer 45 via the support 49 and the support layer 46. The single pipe 50 is a steel plate at intervals such that each block 47 on the single pipe 50 in the bridge girder 42 divided into blocks is supported by at least two single pipes 50. 48 are sandwiched side by side. Details of these steps are the same as those of the above-described embodiment described with reference to FIGS. 1 to 22 as appropriate, and thus detailed description thereof is omitted.

図25は、図24に示す橋りょうに対して、腹付工程及び分割工程の一形態を適用した状況を軌条直交方向から模式的に示す正面図である。支持層46を形成した後、鉄板48の高さ位置近傍まで砕石による腹付盛土をして支持層46の両脇に腹付部52aを形成し、腹付部52aの上に養生鉄板を敷く工程を行う。次いで、鉄筋コンクリート路盤としての橋桁42が軌条延伸方向に所望の間隔でブロック状に分割された状態となるように、橋桁42を軌条直交方向にワイヤーソーイングマシンやコアドリリングマシン等を用いて切削する工程を行う。本形態においては、引抜対象部として最初に選択される第1のブロック47aは、軌条直交方向に連続して開けられた引抜き用縁切り削孔53によりブロック状に分割されている。分割された各ブロック47は引き抜かれるまでは相互に連結金具54により固定されている。腹付工程、分割工程の詳細は、図1から図22を適宜参照して説明した前記実施の形態と同様であるので、詳細な説明は省略する。   FIG. 25 is a front view schematically showing, from the direction orthogonal to the rail, a situation in which one form of the bellowing process and the dividing process is applied to the bridge shown in FIG. 24. After the support layer 46 is formed, a belly embankment with crushed stone is formed to the vicinity of the height position of the iron plate 48 to form a belly portion 52a on both sides of the support layer 46, and a cured iron plate is laid on the belly portion 52a. Perform the process. Next, a step of cutting the bridge girder 42 in a direction orthogonal to the rails using a wire sawing machine, a core drilling machine, or the like so that the bridge girder 42 as the reinforced concrete roadbed is divided into blocks at a desired interval in the rail extension direction. I do. In this embodiment, the first block 47a that is initially selected as the drawing target portion is divided into blocks by drawing edge cutting holes 53 that are continuously opened in the rail orthogonal direction. The divided blocks 47 are fixed to each other by the connecting metal 54 until they are pulled out. Details of the bellowing process and the dividing process are the same as those of the above-described embodiment described with reference to FIGS.

ブロック状に分割された状態の橋桁42のうち単管パイプ50上にある各ブロック47について、いずれか1つを引抜対象部として選択する。そして、引抜対象部である第1のブロック47a周辺の道床バラストを除去し、単管パイプ50上を滑らせるようにして第1のブロック47aを軌条直交方向に引き抜き、引き抜くことにより生じた鉄板48上の空間に砕石を投入して砕石路盤を形成することにより、当該引抜対象部の区間を鉄筋コンクリート路盤から砕石路盤に変更し、路盤上に道床バラストを埋め戻す工程を行う。道床バラストを埋め戻してバラスト軌道43を復旧することにより、軌道上を列車が運行可能となる。次いで、砕石路盤に変更された区間に隣接するブロック47を次の引抜対象部として選択して、当該工程を行うことを、単管パイプ50上にある各ブロック47に対して個々に順次行うことにより、橋桁42を順次撤去してバラスト軌道43が敷設された砕石路盤に順次変更することができる。これらの工程の詳細は、図1から図22を適宜参照して説明した前記実施の形態と同様であるので、詳細な説明は省略する。   Any one of the blocks 47 on the single pipe 50 in the bridge girder 42 divided into blocks is selected as a drawing target portion. Then, the roadbed ballast around the first block 47a, which is the extraction target portion, is removed, and the first block 47a is pulled out in the direction perpendicular to the rail so as to slide on the single pipe 50, and the iron plate 48 generated by pulling out. By throwing crushed stone into the upper space to form a crushed stone roadbed, the section of the drawing target portion is changed from a reinforced concrete roadbed to a crushed stone roadbed, and a roadbed ballast is refilled on the roadbed. By refilling the ballast ballast and restoring the ballast track 43, the train can be operated on the track. Next, the block 47 adjacent to the section changed to the crushed stone roadbed is selected as the next drawing target portion, and the process is performed individually for each block 47 on the single pipe 50. Thus, the bridge girder 42 can be sequentially removed and changed to a crushed stone roadbed in which the ballast track 43 is laid. Details of these steps are the same as those of the above-described embodiment described with reference to FIGS. 1 to 22 as appropriate, and thus detailed description thereof is omitted.

以上、主としてボックスカルバート10に本発明を適用した場合を主として説明したが、本発明は、スラブ軌道による鉄道橋を解体撤去して、当該鉄道橋が架け渡されていた区間に新たにバラスト軌道が敷設された砕石路盤を形成する場合の施工にも適用することができる。その他、本発明の技術的範囲が上記の形態ないし実施例に限定されないことはいうまでもない。例えば、本実施の形態においては、一晩に1ブロックのペースで除去工程、引抜き工程及び埋戻し工程を行っているが、鉄道車両が通過する間隔に余裕があれば、一晩で数ブロックを対象として施工をすることも可能である。また、1番目に引き抜くブロック(第1のブロック)は、上床版又は桁の中央に配置されているものであっても良く、これを引き抜いた後は、左右方向に同時に引抜き作業を行うようにしても良い。   As mentioned above, although the case where this invention was mainly applied to the box culvert 10 was mainly demonstrated, this invention dismantles and removes the railway bridge by a slab track, and a ballast track is newly provided in the area where the said railway bridge was bridged. The present invention can also be applied to the construction for forming a crushed crushed stone roadbed. In addition, it goes without saying that the technical scope of the present invention is not limited to the above embodiments or examples. For example, in this embodiment, the removal process, the drawing process, and the backfilling process are performed at a pace of one block per night. It is also possible to construct as a target. Further, the first block to be pulled out (first block) may be arranged in the center of the upper floor slab or the girder, and after pulling out the block, the pulling operation is performed simultaneously in the left-right direction. May be.

本発明は、鉄筋コンクリート路盤が架け渡された鉄道橋の解体にともなうバラスト軌道の路盤形成に適用することができる。   INDUSTRIAL APPLICABILITY The present invention can be applied to the formation of a ballast track base that accompanies the dismantling of a railway bridge over which a reinforced concrete roadbed is bridged.

1 バラスト軌道
3 軌条
4 道床バラスト
5 枕木
6 地覆
7 バックホウ
8 土手
9 旧河川
10 ボックスカルバート
11 トンネル
11a トンネルの天井面
12 上床版(鉄筋コンクリート路盤)
13 底版
14 側壁
15 ウイング
16 地覆縁切り削孔
17 引出し用縁切り削孔
18 通し穴
20 エアモルタル層
21 保護層
22 支持層
23 鉄板
24 単管パイプ(断面円形部材)
25 支保
26 H鋼
27 パイプサポート
28 連結金具
29 フック
30 土のう
31 砕石路盤
31a 腹付部
31b 上部腹付部
32 大型土のう
40 橋りょう
41 橋台
42 橋桁(鉄筋コンクリート路盤)
43 バラスト軌道
44 河床コンクリート
45 エアモルタル層
46 支持層
47 ブロック
47a 第1のブロック
48 鉄板
49 支保
50 単管パイプ(断面円形部材)
51 保護層
52a 腹付部
53 引抜き用縁切り削孔
54 連結金具
120 ブロック
121 第1のブロック
122 第2のブロック
123 第3のブロック
128 側壁上部のブロック
129 側壁上部左端のブロック
DESCRIPTION OF SYMBOLS 1 Ballast track 3 Rail 4 Road bed ballast 5 Sleeper 6 Ground cover 7 Backhoe 8 Bank 9 Old river 10 Box culvert 11 Tunnel 11a Tunnel ceiling surface 12 Upper deck (reinforced concrete roadbed)
DESCRIPTION OF SYMBOLS 13 Bottom plate 14 Side wall 15 Wing 16 Ground cover edge cut hole 17 Drawer edge cut hole 18 Through hole 20 Air mortar layer 21 Protective layer 22 Support layer 23 Iron plate 24 Single pipe pipe (section circular member)
25 Support 26 H Steel 27 Pipe Support 28 Connecting Bracket 29 Hook 30 Earthmoving 31 Crushed Stone 31a Abdomen 31b Upper Abdomen 31b Large Abdomen 32 Large Soil 40 Bridge 41 Abutment 42 Bridge Girder (Reinforced Concrete Subbase)
43 Ballast track 44 Riverbed concrete 45 Air mortar layer 46 Support layer 47 Block 47a First block 48 Iron plate 49 Support 50 Single pipe (cross-section circular member)
51 Protective Layer 52a Bellows 53 Pull-out Edge Cutting Hole 54 Connecting Metal 120 Block 121 First Block 122 Second Block 123 Third Block 128 Side Block Upper Block 129 Side Wall Upper Left Block

Claims (6)

鉄筋コンクリート路盤が架け渡された鉄道橋の解体にともなうバラスト軌道の路盤形成方法であって、
(ア)前記鉄筋コンクリート路盤の底面側に鉄板支持用の支保を組み、当該支保の上に鉄板を載置し、当該鉄板上に複数の断面円形部材を軌条直交方向に並べ、前記支保の高さを調整して前記鉄板と前記鉄筋コンクリート路盤との間に前記断面円形部材を挟み込む工程と、
(イ)前記支保の下端から前記鉄板までセメント系材料で埋め固めて、前記鉄板に負荷される荷重を受ける支持層を形成する工程と、
(ウ)前記鉄筋コンクリート路盤が軌条延伸方向に所望の間隔でブロック状に分割された状態となるように、前記鉄筋コンクリート路盤を軌条直交方向に切削する工程と、
(エ)ブロック状に分割された状態の鉄筋コンクリート路盤を個々のブロックごとに軌条直交方向に引き抜き、引抜くことにより生じた空間に砕石を投入することにより、前記鉄筋コンクリート路盤を順次砕石路盤に変更する工程と、
を含むことを特徴とするバラスト軌道の路盤形成方法。
A method of forming a ballast track subbase accompanying the dismantling of a railway bridge over which a reinforced concrete roadbed is bridged
(A) Assembling a support for supporting an iron plate on the bottom side of the reinforced concrete roadbed, placing an iron plate on the support, arranging a plurality of circular cross-section members on the iron plate in the direction perpendicular to the rail, and height of the support Adjusting the circular plate member between the steel plate and the reinforced concrete roadbed by adjusting,
(A) a step of filling a cement-based material from the lower end of the support to the iron plate and forming a support layer that receives a load applied to the iron plate;
(C) cutting the reinforced concrete roadbed in the direction orthogonal to the rails so that the reinforced concrete roadbed is divided into blocks at desired intervals in the rail extension direction;
(D) Pulling out the reinforced concrete roadbed divided into blocks in the direction perpendicular to the rails for each block, and putting the crushed stone into the space created by the drawing, the reinforced concrete roadbed is sequentially changed to the crushed stone roadbed Process,
A method of forming a roadbed for a ballast track, comprising:
道床バラストを支持する鉄筋コンクリート路盤が架け渡された鉄道橋の解体にともなうバラスト軌道の路盤形成方法であって、
前記(エ)の工程が、
ブロック状に分割された状態の鉄筋コンクリート路盤のうち前記断面円形部材上にある各ブロックについて、
(a)いずれか1つを引抜対象部として選択し、
(b)引抜対象部周辺の道床バラスト含む砕石を除去し、前記断面円形部材上を滑らせるようにして当該引抜対象部を軌条直交方向に引き抜き、引き抜くことにより生じた前記鉄板上の空間に砕石を投入して砕石路盤を形成することにより、当該引抜対象部の区間を鉄筋コンクリート路盤から砕石路盤に変更した後、路盤上に道床バラストを埋め戻し、
(c)砕石路盤に変更された区間に隣接するブロックを次の引抜対象部として選択して前記(b)の工程を行うことを、前記断面円形部材上にある各ブロックについて個々に順次行う
工程を含むことを特徴とする請求項1記載のバラスト軌道の路盤形成方法。
A method of forming a ballast track subbase along with the dismantling of a railway bridge over which a reinforced concrete roadbed supporting a roadbed ballast is bridged,
The step (d)
About each block on the cross-sectional circular member among the reinforced concrete roadbed divided into blocks,
(A) Select any one as a drawing target part,
(B) The crushed stone including the ballast ballast around the extraction target portion is removed, and the extraction target portion is extracted in the direction orthogonal to the rail so as to slide on the circular member in the cross section, and the crushed stone is created in the space on the iron plate generated by the extraction. After changing the section of the extraction target part from reinforced concrete roadbed to crushed stone roadbed by filling the roadbed ballast on the roadbed,
(C) The step of selecting the block adjacent to the section changed to the crushed stone roadbed as the next extraction target part and performing the step (b) is sequentially performed individually for each block on the circular cross-section member. The method for forming a ballast track roadbed according to claim 1, comprising:
前記(a)において選択される引抜対象部は軌条直交方向に連続して開けられた削孔によりブロック状に分割されていることを特徴とする請求項2記載のバラスト軌道の路盤形成方法。   3. The ballast track roadbed forming method according to claim 2, wherein the drawing target portion selected in (a) is divided into blocks by a drilling hole continuously opened in the direction perpendicular to the rail. 前記断面円形部材は単管パイプであり、
ブロック状に分割された状態の鉄筋コンクリート路盤のうち前記断面円形部材上にある各ブロックが、少なくとも2本以上の単管パイプにより支承されるように、前記(ア)の工程において前記単管パイプを複数並べて挟み込むことを特徴とする請求項1ないし3記載のバラスト軌道の路盤形成方法。
The circular member in cross section is a single pipe pipe,
In the step (a), the single pipe is removed so that each block on the circular member in cross section of the reinforced concrete roadbed divided into blocks is supported by at least two single pipes. 4. The method for forming a ballast track roadbed according to claim 1, wherein a plurality of the ballast tracks are inserted side by side.
前記(ア)の工程の前に、前記鉄筋コンクリート路盤の下方にエアモルタルを打設してエアモルタル層を形成し、当該エアモルタル層の上にコンクリートを打設して保護層を形成する工程を含み、
前記(ア)の工程において、当該保護層上に前記支保を組むことにより、前記鉄板に負荷された荷重を前記支保及び前記支持層を介して前記保護層及び前記エアモルタル層で受けることを特徴とする請求項1ないし4記載のバラスト軌道の路盤形成方法。
Before the step (a), an air mortar is placed below the reinforced concrete roadbed to form an air mortar layer, and a concrete is placed on the air mortar layer to form a protective layer. Including
In the step (a), by forming the support on the protective layer, the load applied to the iron plate is received by the protective layer and the air mortar layer through the support and the support layer. The method for forming a roadbed for a ballast track according to claim 1.
前記(エ)の工程の前に、前記鉄板の高さ位置近傍まで砕石による腹付盛土をして前記支持層の両脇に腹付部を形成し、当該腹付部の上に養生鉄板を敷く工程を含み、
前記(エ)の工程において、軌条直交方向に引き抜かれた前記ブロックを当該養生鉄板で受けることを特徴とする請求項1ないし5記載のバラスト軌道の路盤形成方法。


Prior to the step (d), a bellows embankment is made by crushed stone to the vicinity of the height position of the iron plate to form a belly portion on both sides of the support layer, and a cured iron plate is placed on the bellows portion. Including the laying process,
6. The method for forming a ballast track roadbed according to claim 1, wherein, in the step (d), the cured iron plate receives the block drawn in the direction perpendicular to the rail.


JP2017073276A 2017-03-31 2017-03-31 Ballast track subbase formation method Active JP6170268B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017073276A JP6170268B1 (en) 2017-03-31 2017-03-31 Ballast track subbase formation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017073276A JP6170268B1 (en) 2017-03-31 2017-03-31 Ballast track subbase formation method

Publications (2)

Publication Number Publication Date
JP6170268B1 true JP6170268B1 (en) 2017-07-26
JP2018172953A JP2018172953A (en) 2018-11-08

Family

ID=59384332

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017073276A Active JP6170268B1 (en) 2017-03-31 2017-03-31 Ballast track subbase formation method

Country Status (1)

Country Link
JP (1) JP6170268B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107326815A (en) * 2017-09-04 2017-11-07 岑森参 A kind of bridge construction device
CN108252165A (en) * 2018-03-30 2018-07-06 中铁二局第四工程有限公司 A kind of middle low speed magnetic suspension is low to put circuit road structure and its construction method
CN110792044A (en) * 2019-08-22 2020-02-14 中铁十二局集团有限公司 Construction method for quickly dismantling overpass
CN111287098A (en) * 2020-02-14 2020-06-16 中建八局第四建设有限公司 Device for dismantling Bailey beam and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002194704A (en) * 2000-12-26 2002-07-10 Taisei Corp Method for constructing girder
JP2003020603A (en) * 2001-07-04 2003-01-24 Shimizu Corp Method for replacing railroad bridge
JP2010053557A (en) * 2008-08-27 2010-03-11 Kajima Corp Railroad beam movement and installation device, railroad beam movement and installation method, and railroad beam removal method
JP2011089281A (en) * 2009-10-21 2011-05-06 Taisei Corp Method for rebuilding bridge

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002194704A (en) * 2000-12-26 2002-07-10 Taisei Corp Method for constructing girder
JP2003020603A (en) * 2001-07-04 2003-01-24 Shimizu Corp Method for replacing railroad bridge
JP2010053557A (en) * 2008-08-27 2010-03-11 Kajima Corp Railroad beam movement and installation device, railroad beam movement and installation method, and railroad beam removal method
JP2011089281A (en) * 2009-10-21 2011-05-06 Taisei Corp Method for rebuilding bridge

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107326815A (en) * 2017-09-04 2017-11-07 岑森参 A kind of bridge construction device
CN107326815B (en) * 2017-09-04 2019-01-11 广东众强建设工程有限公司 A kind of bridge construction device
CN108252165A (en) * 2018-03-30 2018-07-06 中铁二局第四工程有限公司 A kind of middle low speed magnetic suspension is low to put circuit road structure and its construction method
CN110792044A (en) * 2019-08-22 2020-02-14 中铁十二局集团有限公司 Construction method for quickly dismantling overpass
CN110792044B (en) * 2019-08-22 2021-09-03 中铁十二局集团有限公司 Construction method for quickly dismantling overpass
CN111287098A (en) * 2020-02-14 2020-06-16 中建八局第四建设有限公司 Device for dismantling Bailey beam and construction method thereof
CN111287098B (en) * 2020-02-14 2021-05-25 中建八局第四建设有限公司 Device for dismantling Bailey beam and construction method thereof

Also Published As

Publication number Publication date
JP2018172953A (en) 2018-11-08

Similar Documents

Publication Publication Date Title
JP6170268B1 (en) Ballast track subbase formation method
KR101258807B1 (en) Tunnel installation method and tunnel installation structure of crossing railroad
JP7061002B2 (en) How to repair a bridge
KR101388521B1 (en) Construction method of underground structure under the pier with supporting piles
CN108678000A (en) A kind of U-shaped retaining structure of roadbed Xia Chuan highways and its construction method
CN112575670B (en) T-shaped rigid frame bridge suitable for tunnel to pass through giant karst cave and construction technology thereof
CN211144503U (en) High steep topography bridge tunnel meets section open cut tunnel and connects long structure
CN105672356A (en) Underground structure of municipal pipeline group spanning tunnel and construction method for underground structure
JP2013237989A (en) Method for restoring bridge
JP6177468B1 (en) Installation or replacement of tunnel inverts in service
CN109989407B (en) Roadbed pile tube curtain supporting structure behind newly-added two-line platform of railway
CN105239475A (en) Line reinforced structure in culvert jacking process under complex existing railway line
CN108708290A (en) The case crane span structure hollow structure and cast-in-situ construction method of minor radius railway curve unit
CN101538832A (en) Construction method for controlling two-dimension jacking of large-scale case
JP4963506B2 (en) How to regenerate a bridge
CN103967052A (en) Method for protecting height difference soil bodies of bases of new frame structure bridge and old frame structure bridge
JP6144726B2 (en) Rehabilitation method for mountain road tunnels on expressway and suspension pier for rehabilitation method
CN106758852A (en) Across foundation pit enclosure to support beam trestle construction technology
KR100948059B1 (en) Constructing method for widening road using steel casing retaining wall
CN110670420A (en) Underground excavation maintenance method for ballastless track subgrade of operation railway
US3843988A (en) Method for excavating an underpass beneath an existing roadway
KR20120079987A (en) Method of pre-support tunneling reinforced by in-situ soil mixed with cement
CN113293665B (en) Roadbed reinforcing method for long side of railway bridge and culvert connection
JP5073960B2 (en) Construction method of underground structure and underground structure
CN105714856A (en) Underground air duct construction method with first negative structural layer and second negative structural layer in bottom-up

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20170425

A871 Explanation of circumstances concerning accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A871

Effective date: 20170427

A975 Report on accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A971005

Effective date: 20170509

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20170613

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20170629

R150 Certificate of patent or registration of utility model

Ref document number: 6170268

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150