JP2017128943A - Open shield method - Google Patents

Open shield method Download PDF

Info

Publication number
JP2017128943A
JP2017128943A JP2016009702A JP2016009702A JP2017128943A JP 2017128943 A JP2017128943 A JP 2017128943A JP 2016009702 A JP2016009702 A JP 2016009702A JP 2016009702 A JP2016009702 A JP 2016009702A JP 2017128943 A JP2017128943 A JP 2017128943A
Authority
JP
Japan
Prior art keywords
concrete box
open shield
box body
shield machine
propulsion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2016009702A
Other languages
Japanese (ja)
Other versions
JP6276300B2 (en
Inventor
植村 誠
Makoto Uemura
誠 植村
賢治郎 植村
Kenjiro Uemura
賢治郎 植村
廣明 竹川
Hiroaki Takegawa
廣明 竹川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP2016009702A priority Critical patent/JP6276300B2/en
Publication of JP2017128943A publication Critical patent/JP2017128943A/en
Application granted granted Critical
Publication of JP6276300B2 publication Critical patent/JP6276300B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide an open shield method which is easy and quick in performing road surface lining because a member width is narrow compared with a lining plate, low in a construction expense, can shorten a construction period, and can surely prevent the fracture of a sideway rock mass, in the open shield method of a propulsion type which repeats a process for excavating and discharging sediment in front of a front face or an upper face opening of an open shield machine, a process for advancing the shield machine with a concrete box body as a reaction force by elongating a propulsion jack, and a propulsion process for extruding the concrete box body by a base pushing jack which is installed at a start pile, and arranging and extruding a new concrete box body between the base pushing jack and the extruded concrete box body.SOLUTION: In a road part traverse point, steel pipes are arranged in upper and lower rows for the purpose of sideway land retention at left and right sides of a concrete box body passing position, and beam materials and the steel pipes are sequentially and laterally aligned and installed on the ground at an upper part than the concrete box body passing position to form a road surface lining, thus making an open shield machine and the concrete box body progress below the road surface lining.SELECTED DRAWING: Figure 1

Description

本発明は、上下水道、共同溝、電信、電話などの付設地下道等の地下構造物をオープンシールド工法で市街地などに施工する場合のオープンシールド工法に関するものである。   The present invention relates to an open shield method for constructing an underground structure such as an attached underground passage such as a water and sewage system, a common ditch, a telegraph, and a telephone in an urban area or the like by an open shield method.

推進タイプのオープンシールド工法は、通常のオープンシールド工法では、掘削・排土は地上に設置したショベル等の掘削機で行い、また、コンクリート函体のオープンシールド機のテール部へのセットも地上に設置したクローラクレーン等の揚重機で行うが、道路や橋桁や大きな配管等の構造物の直下を横切るような場合には、それがある箇所では前記掘削機や揚重機が配置できず、オープンシールド工法の施工が不可能となるのを解消するものである。   The propulsion type open shield method is a normal open shield method, where excavation and soil removal are performed by excavators such as excavators installed on the ground, and the set of concrete box on the tail of the open shield machine is also on the ground. Open crawlers such as crawler cranes that are installed, but if they cross directly under structures such as roads, bridge girders, and large pipes, the excavator and hoist cannot be placed where they are, and open shield This eliminates the impossibility of construction.

ところでこのようなオープンシールド工法によるコンクリート函体の埋設は市街地の道路下で施工されることが多く、施工中は通行止めとなるが、一日のうちの一定の時間は道路を開放して通行可能とすることが義務付けられている。   By the way, burying of concrete boxes by such an open shield method is often performed under roads in urban areas, and is closed during construction, but can be opened by opening the road for a certain time of day. Is required.

このため、オープンシールド機が発進坑から到達坑にまで到達するまでの間で、日々の施工終了後掘進を適宜中止し、オープンシールド機の上部開口すなわち道路の開削した部分に覆工板を布設して開口を一時的に閉塞し、この覆工板の上を自動車が走行し、また、人が歩行できるようにする必要がある。   For this reason, until the open shield machine reaches from the start pit to the arrival mine, the excavation is appropriately stopped after the completion of daily construction, and a lining plate is laid on the upper opening of the open shield machine, that is, on the open part of the road. Thus, it is necessary to temporarily close the opening so that the automobile can run on the lining board and that a person can walk.

この覆工板の布設は、従来、例えば、受桁を開口の側部に設置し、この上にクレーンなどで吊り上げた覆工板を一枚ずつ架け渡すようにして順次載せている。   For laying the lining plate, conventionally, for example, a girder is installed on the side of the opening, and the lining plates lifted by a crane or the like are placed on the lining plate one by one.

また、覆工板の撤去も布設の場合と反対の作業で行っている。この場合、施工場所が道路を横切るように直交するとき、道路の一方の側から他方の側に向けて覆工板を押出すようにして敷設する。   In addition, the removal of the lining plate is performed in the opposite manner to the case of laying. In this case, when the construction site is orthogonal so as to cross the road, the laying board is laid so as to extrude from one side of the road toward the other side.

前記のような覆工板の設置方法では、手間を要してその分だけ工期が長引くだけでなく、規制される交通時間も長くなって交通に及ぼす影響が大きい。   The above-described method of installing the lining board not only requires time and labor, but also increases the restricted traffic time and has a great influence on traffic.

そこで、例えば下記特許文献1に示すように、オープンシールド工法による施工に先行して覆工板を敷設して路面覆工を行い、さらに覆工板は発進坑から一方向に順次押出すことにより、交通障害を少なくする方法がある。
特開2005−307544号公報
Therefore, for example, as shown in Patent Document 1 below, the road surface is covered by laying a lining plate prior to the construction by the open shield method, and the lining plate is sequentially extruded in one direction from the starting pit. There are ways to reduce traffic obstacles.
JP 2005-307544 A

また、下記特許文献2は、前記特許文献1のような覆工板の設置方法では、施工場所の発進坑から一方向に覆工板を押出すものであり、夜間には両側交通とすることができても、交通量の多い昼間は片側交通となり、その分だけやはり工期が長引き、車両規制期間が長くなって交通に及ぼす影響が大きいとして、工期の短縮も図ることができる覆工板の設置方法として提案されたものである。
特開2010−242373号公報
Moreover, the following patent document 2 is a thing which extrudes a lining board in one direction from the starting pit of a construction place in the installation method of a lining board like the said patent document 1, and makes it a both-sides traffic at night. Even if it can be done, it will be one-sided traffic during the daytime when there is a lot of traffic, and the construction period will be prolonged accordingly, and the vehicle regulation period will be prolonged and the impact on traffic will be great. It was proposed as an installation method.
JP 2010-242373 A

この特許文献2は、オープンシールド機の前面または上面開口より前方の土砂を掘削・排土する工程と、推進ジャッキを伸長してコンクリート函体を反力にしてシールド機を前進させる工程と、シールド機のテール部内で縮めた推進ジャッキの後方に新たなコンクリート函体をセットする工程とを適宜繰り返して順次コンクリート函体を縦列に埋設するオープンシールド工法において、施工場所が道路と直交する方向の道路下では、道路を挟んで道路の両側に覆工板推進引込ジャッキを設置し、道路の一方の側から道路の略中央まで覆工板を推進し敷設した後、道路の他方の側から道路の略中央まで覆工板を推進し敷設することを要旨とするものである。   This patent document 2 discloses a process of excavating and discharging soil in front of the front or top opening of an open shield machine, a process of extending a propulsion jack and advancing the shield machine using a concrete box as a reaction force, In the open shield method, in which the concrete box is buried in series in sequence by repeating the process of setting a new concrete box behind the propulsion jack shrunk in the tail section of the machine, the road where the construction site is perpendicular to the road Below, the lining board propulsion jacks are installed on both sides of the road, the lining board is pushed and laid from one side of the road to the approximate center of the road, and then the road The gist is to push and lay the lining board to the approximate center.

特許文献2の本発明によれば、道路の片側半分に覆工板を敷設した後、残りの片側半分に反対方向から覆工板を敷設するようにしたから、道路の片側半分は常に開放されており、車両はこの片側半分を走行でき、全面的に交通規制されることなく、交通障害を少なくできる。   According to the invention of Patent Document 2, since the lining board is laid on the other half of the road after the laying board is laid from the opposite direction, the half of the road is always opened. Therefore, the vehicle can run on one half of this side, and traffic can be reduced without any traffic restrictions.

前記特許文献1も特許文献2も覆工板を布設するものである。ちなみに、覆工板は、地下鉄工事をはじめ、地下街の建設・地下配管工事など各種路面掘削工事のほか、仮設構台・桟橋用床板として広く利用されているものである。   In both Patent Document 1 and Patent Document 2, a lining plate is laid. By the way, the lining board is widely used as a temporary gantry and pier floor board as well as various road excavation works such as subway construction, underground city construction and underground piping work.

このように覆工板による路面覆工では、覆工板自体が幅や長さの大きな大型のものであり、受桁を開口の側部に設置し、この上にクレーンなどで吊り上げた覆工板を一枚ずつ架け渡すようにして順次載せるにしても時間と手間のかかる大仕事である。また、設置後も覆工板のガタツキをなくすための手間がかかる。   In this way, in the road surface lining by the lining plate, the lining plate itself is a large one having a large width and length, and the covering lining is installed on the side of the opening and lifted by a crane or the like. Even if the boards are placed one by one as if they are placed one by one, it is a big task that takes time and effort. In addition, it takes time and effort to eliminate backlash of the lining plate even after installation.

また、覆工板の撤去も布設の場合と反対の作業で行っているので同様である。   Also, the removal of the lining plate is the same because it is performed in the opposite operation to the case of laying.

前記特許文献1や特許文献2にしても、路面覆工に覆工板を使用するので、布設の仕方に工夫を凝らしたとはいえ、幅や長さの大きな大型の部材を使用することには変わりなく、問題は同様である。   Even in Patent Document 1 and Patent Document 2, since a lining plate is used for road surface lining, although devised in the way of laying, to use a large member having a large width or length The problem remains the same.

本発明の目的は前記従来例の不都合を解消し、覆工板と比べ部材幅が短いため路面覆工を行うのに、簡易かつ迅速に、工費も安く、工期も短縮できるオープンシールド工法を提供することにある。   The object of the present invention is to provide an open shield construction method that eliminates the inconveniences of the above-mentioned conventional example and that is simple and quick, has low construction costs, and shortens the construction period, because the member width is shorter than the lining plate. There is to do.

前記目的を達成するため請求項1記載の本発明は、オープンシールド機の前面又は上面開口より前方の土砂を掘削排土する工程と、推進ジャッキを伸長してコンクリート函体を反力にしてシールド機を前進させる工程と、コンクリート函体を発進坑に設置した元押しジャッキで押し出し、該元押しジャッキと押し出したコンクリート函体との間に新たなコンクリート函体を配設して押し出す推進工程を繰り返す推進タイプのオープンシールド工法において、道路部横断箇所では、コンクリート函体通過位置の左右脇に鋼管を側方土留めのために上下列に配設し、桁材を前記鋼管を上下列に配設した鋼管列の上方で、かつ、コンクリート函体通過位置より上に地上より順次横並びで据付けて路面覆工を形成し、その下をオープンシールド機およびコンクリート函体を掘進させることを要旨とするものである。   In order to achieve the above object, the present invention as claimed in claim 1 includes a step of excavating and discharging earth and sand ahead of the front or upper surface opening of an open shield machine, and extending a propulsion jack to shield the concrete box as a reaction force. A step of advancing the machine and a propulsion step of extruding the concrete box with a main jack installed in the starting pit, placing a new concrete box between the main jack and the extruded concrete box. In the repetitive propulsion type open shield method, steel pipes are arranged in the upper and lower rows at the left and right sides of the position where the concrete box passes, and the girders are arranged in the upper and lower rows at the side of the concrete box. A road surface lining is formed above the installed steel pipe row and above the concrete box passing position, side by side from the ground to form a road surface covering. It is an Abstract that is boring concrete box making bodies.

請求項1記載の本発明によれば、桁材により横並びで据付けて路面覆工を形成するので、従来の覆工板による路面覆工と比べ部材幅が短く、かつ車輛通行によるガタツキもなく、必要長さを確保でき、軽量で扱い易いものとなる。   According to the present invention of claim 1, since the road surface lining is formed by installing side by side with a girder, the member width is shorter than the road surface lining with a conventional lining plate, and there is no backlash due to vehicle traffic, The required length can be secured, and it is lightweight and easy to handle.

しかも、コンクリート函体を土被りありとして施工するのに桁材をコンクリート函体より上に設置することにより、設置および撤去が容易なものである。   In addition, when the concrete box is constructed with a cover, it is easy to install and remove by installing the girders above the concrete box.

桁材が受ける車輌荷重は桁受け材と基礎コンクリートを介して地山に伝達され、桁材は推進コンクリート函体とは離間されるため、コンクリート函体推進時の摩擦力の影響を受けなく、よって路面の変状がなく、工事施工中の路面の保守が必要ない。   The vehicle load received by the girder material is transmitted to the ground via the girder material and the foundation concrete, and the girder material is separated from the propulsion concrete box, so it is not affected by the frictional force when propelling the concrete box, Therefore, there is no road surface deformation and maintenance of the road surface during construction is not necessary.

また、コンクリート函体通過位置の左右両脇に上下列に鋼管を配設することにより、側部地山の崩壊をすることができる。側部地山の崩壊防止方法としては、鋼矢板による土留めや地盤改良等があるが、これらの方法は地上からの施工となるため、施工時に車輌の通行に支障をきたしてしまう。   Moreover, a side natural ground can be collapsed by arrange | positioning a steel pipe in an up-and-down row on the both sides of the concrete box passage position. As methods for preventing the collapse of the side ground, there are earth retaining with steel sheet piles, ground improvement, etc., but since these methods are construction from the ground, they impede vehicle traffic during construction.

しかし、本発明では、コンクリート函体通過位置の左右脇に上下列に配設する鋼管は、発進立坑からオーガを備えた掘進機により水平に掘進させるので鋼管施工時に車輌の通行に支障をきたすことはない。また、鋼矢板等より剛性の高い鋼管を配設するので、鋼矢板や地盤改良等より確実に地山の崩壊防止ができる。さらに、左右上下列に鋼管があることにより、コンクリート函体の敷設に使用するシールド機は、簡易的な刃口構造で良く、シールド機のコストダウンが図れる。   However, in the present invention, the steel pipes arranged in the upper and lower rows on the left and right sides of the position where the concrete box passes are made to dig horizontally from the starting vertical shaft by the excavator equipped with the auger, so that the passage of the vehicle is hindered during the construction of the steel pipe. There is no. Moreover, since a steel pipe having higher rigidity than that of a steel sheet pile or the like is disposed, the collapse of the natural ground can be surely prevented by steel sheet piles or ground improvement. Furthermore, since there are steel pipes in the left and right upper and lower rows, the shielding machine used for laying the concrete box may have a simple blade structure, and the cost of the shielding machine can be reduced.

以上述べたように本発明のオープンシールド工法は、オープンシールド機の前面又は上面開口より前方の土砂を掘削排土する工程と、推進ジャッキを伸長してコンクリート函体を反力にしてシールド機を前進させる工程と、コンクリート函体を発進坑に設置した元押しジャッキで押し出し、該元押しジャッキと押し出したコンクリート函体との間に新たなコンクリート函体を配設して押し出す推進工程を繰り返す推進タイプのオープンシールド工法において、覆工板と比べ部材幅が短いため路面覆工を行うのに、簡易かつ迅速に、工費も安く、工期も短縮でき、側部地山の崩壊防止を確実に行えるものである。   As described above, the open shield method according to the present invention includes a step of excavating and removing the soil in front of the front or upper surface opening of the open shield machine, and extending the propulsion jack to react the concrete box as a reaction force. Propulsion that repeats the process of advancing and pushing out the concrete box with a main jack installed in the starting pit, placing a new concrete box between the main jack and the extruded concrete box In the type of open shield method, the width of the member is shorter than that of the lining plate, so it is easy and quick, the construction cost is low, the construction period can be shortened, and the side ground can be reliably prevented from collapsing. Is.

以下、図面について本発明の実施の形態を詳細に説明する。図1は本発明のオープンシールド工法の1実施形態を示す縦断側面図、図2は縦断正面図で、図中8は発進立坑、13は到達立坑で、発進立坑8は発進基地として函体の布設及びシールド機据付、組立のため設けられるもの、到達立坑13は工事終点としてシールド機解体、撤去のため設けられるもので、これら立坑の築造のための土留工法としては、鋼矢板工法、親杭横矢板工法、ライナープレート工法等がある。   Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. 1 is a longitudinal side view showing an embodiment of the open shield method of the present invention, FIG. 2 is a longitudinal front view, 8 is a start shaft, 13 is a reach shaft, and the start shaft 8 is a box as a start base. The installation and assembly of shield machines, the installation of assembling, and the reach shaft 13 is provided for the dismantling and removal of the shield machine as the construction end point. As the earth retaining method for the construction of these shafts, steel sheet pile method, parent pile There are a horizontal sheet pile method and a liner plate method.

発進立坑8内にオープンシールド機の設置に先だち、道路部横断箇所αでは、コンクリート函体の通過位置の左右脇にルーフ筒体用の鋼管(パイプルーフ)37を上下列(図示では4段)に配設して、側方土留めのための鋼管列を形成した。   Prior to the installation of the open shield machine in the start shaft 8, at the road crossing point α, the steel pipes (pipe roofs) 37 for the roof cylinders are vertically arranged on the left and right sides of the passage position of the concrete box (four stages in the figure). To form a steel pipe row for lateral earth retaining.

この鋼管(パイプルーフ)37の設置は図示は省略するが、オーガを備えた推進機を発進立坑8に設置し、これにより掘進させる。   Although the installation of the steel pipe (pipe roof) 37 is not shown, a propulsion device having an auger is installed in the start shaft 8 and is thus excavated.

発進立坑8では、元押ジャッキ23の反力を支持するための支圧壁22を発進立坑8の最奥部に構築し、その前面に鋼材を組んで架台を形成し、元押ジャッキ23を設置する。   In the start shaft 8, a bearing wall 22 for supporting the reaction force of the main push jack 23 is constructed at the innermost part of the start vertical shaft 8, and a base is formed by assembling a steel material on the front surface thereof. Install.

また、発進立坑8の底部では砕石39とその上の基礎コンクリート40とで基礎を形成し、その上にH鋼をレール状に並べその上の全面に鉄板を設置してシールド機の据付及び発進のための受台25を形成する。   Also, at the bottom of the start shaft 8, a foundation is formed by the crushed stone 39 and the foundation concrete 40 thereabove, H steel is arranged in a rail shape thereon, and an iron plate is installed on the entire surface to install and start the shield machine. A cradle 25 is formed.

使用するオープンシールド機1は左右の側壁板1aとこれら側壁板1aに連結する底板1bとからなる前面、後面及び上面を開口したシールド機である。   The open shield machine 1 to be used is a shield machine having a front face, a rear face, and an upper face that are formed of left and right side wall plates 1a and a bottom plate 1b connected to the side wall plates 1a.

該オープンシールド機1は布設するコンクリート函体4の幅とシールド機の内径の幅がほぼ同一で、前記側壁板1aと底板1bの先端を刃口として形成し、また側壁板1aの中央又は後端近くにシールドジャッキ3を後方に向け上下に並べて配設する。   In the open shield machine 1, the width of the concrete box 4 to be installed and the inner diameter of the shield machine are substantially the same, the tip of the side wall plate 1a and the bottom plate 1b is formed as a cutting edge, and the center or rear of the side wall plate 1a. Near the end, the shield jacks 3 are arranged side by side facing up and down.

発進立坑8内にオープンシールド機1を設置し、推進させ、オープンシールド機1と元押ジャッキ23との間にコンクリート函体4を設置し、元押ジャッキ23で推進させる。   The open shield machine 1 is installed in the start shaft 8 and propelled, and the concrete box 4 is installed between the open shield machine 1 and the main push jack 23, and is pushed by the main push jack 23.

一番先頭になるコンクリート函体4の前にプレスバー(押角)15を介在させる。   A press bar (push angle) 15 is interposed in front of the topmost concrete box 4.

元押ジャッキ23の伸長幅が足りない場合は、ストラット24を配設する。   When the extension width of the main push jack 23 is insufficient, the strut 24 is disposed.

推進は、図示の例では切羽内の地山を人力により掘削し、オープンシールド機1を推進させる。もしくは図示は省略するがショベル等の掘削機でオープンシールド機1の前面又は上面から土砂を掘削しかつ排土してオープンシールド機1を推進させる。   In the example shown in the figure, the open shield machine 1 is propelled by manually excavating a natural ground in the face. Or although illustration is abbreviate | omitted, excavator, such as a shovel, excavates earth and sand from the front surface or upper surface of the open shield machine 1, and excavates it, and the open shield machine 1 is propelled.

このオープンシールド機1の推進は、布設したコンクリート函体4を反力にシールド機内部に装置したシールドジャッキ3により推進させる。   The open shield machine 1 is propelled by a shield jack 3 installed inside the shield machine against the installed concrete box 4 as a reaction force.

オープンシールド機1の推進の次に、支圧壁22を反力に元押ジャッキ23を使用して、布設した全てのコンクリート函体4を推進させる函体推進に移行する。   After the propulsion of the open shield machine 1, the process proceeds to the box propulsion in which all the installed concrete boxes 4 are propelled by using the main push jack 23 with the bearing wall 22 as a reaction force.

このようにして、オープンシールド機1の前面又は上面開口より前方の土砂を掘削・排土する工程と、シールドジャッキ3を伸長してコンクリート函体4を反力にしてシールド機を前進させる工程と、コンクリート函体4を発進立坑8に設置した元押ジャッキ23で押し出し、該元押ジャッキ23と押し出したコンクリート函体4との間に新たなコンクリート函体4を配設して押し出しを繰り返す工程を繰り返して、オープンシールド機1を到達立坑13まで到達させる。   In this manner, a step of excavating and discharging soil in front of the front or top opening of the open shield machine 1, a step of extending the shield jack 3 and causing the concrete box 4 to react to advance the shield machine The concrete box 4 is pushed out by the main pushing jack 23 installed in the start shaft 8, and the new concrete box 4 is disposed between the main pushing jack 23 and the pushed concrete box 4, and the pushing is repeated. Is repeated until the open shield machine 1 reaches the reaching shaft 13.

オープンシールド工法で施工を行なうのに道路部横断箇所αでは、路面覆工を施すが、これには覆工板を用いることなく、H鋼を桁材31として道路面に地上より据付けてフランジ31a面を上にして横並びで路面覆工を形成した。   Although the road surface crossing point α is constructed by the open shield method, road surface lining is performed. For this, without using a lining plate, H steel is used as a girder 31 on the road surface from the ground and the flange 31a. Road surface lining was formed side by side with the side up.

道路部横断箇所αの両側に基礎コンクリート32を打設し、その上にH型鋼による桁受材33を設置し、この桁受材33で桁材31の端部を支承する。また、桁材31は前記鋼管(パイプルーフ)37を上下列に配設してなる鋼管列の上方に位置して、順次横並びで据付けられ、その下をオープンシールド機1およびコンクリート函体4が通過できるようにする。   A foundation concrete 32 is placed on both sides of the road crossing point α, and a girder receiving material 33 made of H-shaped steel is installed thereon, and the end of the girder 31 is supported by the girder receiving material 33. Further, the girder 31 is positioned above the steel pipe row formed by arranging the steel pipes (pipe roofs) 37 in the upper and lower rows, and is sequentially installed side by side, below which the open shield machine 1 and the concrete box 4 are placed. Allow to pass.

桁材31であるH鋼は前記のようにフランジ31a面を上にして横並びで順次敷設してかつ連続させるが、桁材31はコンクリート函体4の上床板よりも上に設置するようにした。コンクリート函体4を土被りありとして施工する場合であり、桁材31をコンクリート函体4の上床板よりも上に設置することにより、設置および撤去が容易となる。   As described above, the H steel which is the spar 31 is continuously laid and arranged side by side with the flange 31a face up, but the spar 31 is installed above the upper floor board of the concrete box 4. . This is a case where the concrete box 4 is constructed with a cover, and installation and removal are facilitated by installing the girders 31 above the upper floor plate of the concrete box 4.

また、桁材31であるH鋼はウエブ31bを中にして上下に位置するフランジ31aの裏面からキープレート34をフランジ31aの端部よりも外側に突出するように取付け、これを隣接する桁材31のフランジ31aの裏側に当接させることで、桁材31をキープレート34を介して相互に固定できるものとする。   In addition, the H steel as the girder 31 is attached so that the key plate 34 protrudes outward from the end of the flange 31a from the back surface of the flange 31a positioned above and below the web 31b. It is assumed that the girders 31 can be fixed to each other via the key plate 34 by being brought into contact with the back side of the flange 31a of the 31.

桁材31であるH鋼は仕切り板状のスチフナー31cを有するものであり、これにより横並びにした際にフランジ31a同士が上下に重なりあって、入り込むような状態はなく、フランジ31aが平に並ぶ状態が得られる。   The steel H which is the girder 31 has a partition plate-like stiffener 31c, and when it is placed side by side, the flanges 31a overlap each other vertically so that they do not enter and the flanges 31a are arranged flat. A state is obtained.

このようにして道路部横断箇所αでは桁材31を順次並べ、その端部方向には溝形鋼を上下に重ねてなる縁材35を設置し、桁材31の上面に仮舗装としてアスファルト舗装による舗装すり付け36を施す。   In this way, the girder members 31 are sequentially arranged at the road crossing point α, and the edge members 35 formed by stacking the grooved steels are installed in the end direction, and the asphalt pavement is provided on the upper surface of the girder 31 as a temporary pavement. Apply pavement rubbing 36.

このようにして上部荷重は桁材31による路面覆工で受け、その下をオープンシールド機1を掘進させる。道路Aは歩道、道路Bは車道で、交通が可能である。   In this way, the upper load is received by the road surface lining by the girder 31 and the open shield machine 1 is dug under it. Road A is a sidewalk and road B is a roadway, and traffic is possible.

オープンシールド機1の後にコンクリート函体4が推進してくるが、コンクリート函体4に土被りがあり、桁材31を撤去しなくともコンクリート函体4はその下を通過可能であるが、コンクリート函体4の上部の埋め戻しの進行にともない、桁材31を1本ずつまたは数本ずつ撤去していく。   Although the concrete box 4 is propelled after the open shield machine 1, the concrete box 4 has a covering, and the concrete box 4 can pass under it without removing the girder 31. As the backfilling of the upper part of the box 4 progresses, the girders 31 are removed one by one or several.

コンクリート函体4の推進に従い、道路部横断箇所αの全ての桁材31を撤去し、オープンシールド機1を到達立坑13に入れて回収する。   In accordance with the promotion of the concrete box 4, all the girders 31 at the road crossing point α are removed, and the open shield machine 1 is put into the reaching shaft 13 and collected.

また、コンクリート函体4による地下構造物の施工後、鋼管(パイプルーフ)37はこれを到達立坑13側もしくは発進立坑8に押し抜き、回収することができる。   In addition, after the construction of the underground structure by the concrete box 4, the steel pipe (pipe roof) 37 can be pushed out to the arrival shaft 13 side or the start shaft 8 and recovered.

本発明のオープンシールド工法の1実施形態を示す縦断側面図である。It is a vertical side view which shows one Embodiment of the open shield construction method of this invention. 本発明のオープンシールド工法の1実施形態を示す縦断正面図である。It is a vertical front view which shows one Embodiment of the open shield construction method of this invention.

1…オープンシールド機 1a…側壁板
1b…底板 3…シールドジャッキ
4…コンクリート函体 4a…先頭函体
6…掘削機 8…発進立坑
13…到達立坑 15…プレスバー
22…支圧壁 23…元押ジャッキ
24…ストラット 25…受台
31…桁材 31a…フランジ
31b…ウエブ 31c…スチフナー
32…基礎コンクリート 33…桁受材
34…キープレート 35…縁材
36…舗装すり付け 37…鋼管(パイプルーフ)
39…砕石 40…基礎コンクリート
DESCRIPTION OF SYMBOLS 1 ... Open shield machine 1a ... Side wall plate 1b ... Bottom plate 3 ... Shield jack 4 ... Concrete box 4a ... Top box 6 ... Excavator 8 ... Starting shaft 13 ... Reaching shaft 15 ... Press bar 22 ... Bearing wall 23 ... Original Push jack 24 ... Strut 25 ... Receiving base 31 ... Girder 31a ... Flange 31b ... Web 31c ... Stiffener 32 ... Base concrete 33 ... Girder receiving material 34 ... Key plate 35 ... Edge material 36 ... Pavement rubbing 37 ... Steel pipe (pipe roof) )
39 ... Crushed stone 40 ... Foundation concrete

Claims (1)

オープンシールド機の前面又は上面開口より前方の土砂を掘削排土する工程と、推進ジャッキを伸長してコンクリート函体を反力にしてシールド機を前進させる工程と、コンクリート函体を発進坑に設置した元押しジャッキで押し出し、該元押しジャッキと押し出したコンクリート函体との間に新たなコンクリート函体を配設して押し出す推進工程を繰り返す推進タイプのオープンシールド工法において、道路部横断箇所では、コンクリート函体通過位置の左右脇に鋼管を側方土留めのために上下列に配設し、桁材を前記鋼管を上下列に配設した鋼管列の上方で、かつ、コンクリート函体通過位置より上に地上より順次横並びで据付けて路面覆工を形成し、その下をオープンシールド機およびコンクリート函体を掘進させることを特徴としたオープンシールド工法。   Excavation and excavation of the soil in front of the front or top opening of the open shield machine, the process of extending the propeller jack and using the concrete box as a reaction force to advance the shield machine, and installing the concrete box in the start pit In the propulsion type open shield construction method that repeats the propulsion process of extruding with the original push jack, and arranging and pushing out a new concrete box between the original push jack and the extruded concrete box, Steel pipes are arranged in the upper and lower rows for lateral earth retaining on the left and right sides of the concrete box passage position, and the girders are above the steel pipe row in which the steel pipes are arranged in the upper and lower rows, and the concrete box passage position. It is characterized in that it is installed side by side sequentially from above the ground to form a road surface lining, and below that, an open shield machine and a concrete box are dug up Over Pung shield method.
JP2016009702A 2016-01-21 2016-01-21 Open shield method Active JP6276300B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016009702A JP6276300B2 (en) 2016-01-21 2016-01-21 Open shield method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016009702A JP6276300B2 (en) 2016-01-21 2016-01-21 Open shield method

Publications (2)

Publication Number Publication Date
JP2017128943A true JP2017128943A (en) 2017-07-27
JP6276300B2 JP6276300B2 (en) 2018-02-07

Family

ID=59394548

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016009702A Active JP6276300B2 (en) 2016-01-21 2016-01-21 Open shield method

Country Status (1)

Country Link
JP (1) JP6276300B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113187497A (en) * 2021-04-13 2021-07-30 中国电建集团华东勘测设计研究院有限公司 Steel casing type pipe jacking shield machine receiving well structure and construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4405260A (en) * 1981-06-22 1983-09-20 Tepin Tsai Method of constructing underpass across railway and highway without affecting normal traffic thereof
JPS63171902A (en) * 1987-01-09 1988-07-15 株式会社技研製作所 Coated plate
JPH0462230A (en) * 1990-06-29 1992-02-27 Koichi Uemura Setting construction for underground structure
JPH09317374A (en) * 1996-05-31 1997-12-09 Makoto Uemura Method of construction of subsurface structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4405260A (en) * 1981-06-22 1983-09-20 Tepin Tsai Method of constructing underpass across railway and highway without affecting normal traffic thereof
JPS63171902A (en) * 1987-01-09 1988-07-15 株式会社技研製作所 Coated plate
JPH0462230A (en) * 1990-06-29 1992-02-27 Koichi Uemura Setting construction for underground structure
JPH09317374A (en) * 1996-05-31 1997-12-09 Makoto Uemura Method of construction of subsurface structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113187497A (en) * 2021-04-13 2021-07-30 中国电建集团华东勘测设计研究院有限公司 Steel casing type pipe jacking shield machine receiving well structure and construction method

Also Published As

Publication number Publication date
JP6276300B2 (en) 2018-02-07

Similar Documents

Publication Publication Date Title
JP4184400B2 (en) Construction method of underground structure
JP6251375B2 (en) Road surface lining method in propulsion type open shield method
CN101761068A (en) Box-raft pressure-bearing type foundation underpinning and construction reinforcing method for tunnel across pile foundation of bridge above river
KR101388521B1 (en) Construction method of underground structure under the pier with supporting piles
JP3586864B2 (en) Underground structure construction method and elevated traffic path
JP6944882B2 (en) How to build an invert in an existing tunnel
KR100986312B1 (en) Apparatus for guiding the driving force of steel pipe loop structure
KR20130014160A (en) The tunel execution method
JP4113187B2 (en) Construction method of underground structure
JP6276300B2 (en) Open shield method
JP7177233B2 (en) Start Reaction Force Structure and Method for Concrete Box or Open Shield Machine
JP5155236B2 (en) Installation method of lining board in open shield method
JP3917146B2 (en) Laying method and removing method of lining plate in open shield method
JP6307119B2 (en) Installation method of lining plate or protective work with square steel pipe
JP6375334B2 (en) Road lining method
JP4402640B2 (en) Open shield method
JP6871344B1 (en) Tunnel repair method and repair equipment for existing tunnels
JP6121504B1 (en) Road lining method
JP4349570B2 (en) Construction method of division box and underground level crossing
KR102225104B1 (en) Open shield method
KR102048831B1 (en) Non-excavation type tunnel structure using steel pipe loof and leading pipe and method of constructing thereof
KR102608601B1 (en) Sheet non excavation method for drilling a tunnel having a file reinforcing structure
JP5167578B2 (en) Construction method for underground structures
JP4319122B2 (en) Branch and junction structure of branching tunnel and its construction method
JP2014177787A (en) Open shield method

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20171215

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20180109

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20180111

R150 Certificate of patent or registration of utility model

Ref document number: 6276300

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250