KR102608601B1 - Sheet non excavation method for drilling a tunnel having a file reinforcing structure - Google Patents

Sheet non excavation method for drilling a tunnel having a file reinforcing structure Download PDF

Info

Publication number
KR102608601B1
KR102608601B1 KR1020230097181A KR20230097181A KR102608601B1 KR 102608601 B1 KR102608601 B1 KR 102608601B1 KR 1020230097181 A KR1020230097181 A KR 1020230097181A KR 20230097181 A KR20230097181 A KR 20230097181A KR 102608601 B1 KR102608601 B1 KR 102608601B1
Authority
KR
South Korea
Prior art keywords
linear guide
tunnel
rectangular pipe
sheet pile
ground disturbance
Prior art date
Application number
KR1020230097181A
Other languages
Korean (ko)
Inventor
정영수
Original Assignee
정영수
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 정영수 filed Critical 정영수
Priority to KR1020230097181A priority Critical patent/KR102608601B1/en
Application granted granted Critical
Publication of KR102608601B1 publication Critical patent/KR102608601B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/005Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by forcing prefabricated elements through the ground, e.g. by pushing lining from an access pit
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D15/00Props; Chocks, e.g. made of flexible containers filled with backfilling material
    • E21D15/02Non-telescopic props
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0621Shield advancing devices

Abstract

본 발명은 비개착 터널용 굴착시스템 및 그 공법에 관한 것이다. 본 발명의 비개착 터널용 굴착시스템은 지하 구조물인 터널의 내벽체에 순차적으로 압입 또는 추진되어 상기 터널의 내벽체 상부와 측부에 시공되는 복수 개의 시트 파일(SHEET PIlE); 추진용 유압잭을 작용으로 상기 터널의 추진구에서 도달구까지 직선 또는 곡선 이동하며, 토석의 굴착과 상기 시트 파일의 설치가 가능하게 유도하는 복수 개의 선형 유도 각형관; 상기 선형 유도 각형관의 상부에 결합하며, 상기 선형 유도 각형관의 압입 또는 추진 시 해당 위치에서 막장의 지반 교란이 진행되게 하는 상부 지반 교란부; 상기 선형 유도 각형관의 측부에 결합하며, 상기 선형 유도 각형관의 압입 또는 추진 시 해당 위치에서 막장의 지반 교란이 진행되게 하는 측부 지반 교란부; 상기 시트 파일들과 연결되고 상기 시트 파일들을 지지하는 복수 개의 토압 지지대; 및 상기 토압 지지대들과 연결되고 상기 토압 지지대들을 지지하는 복수 개의 터널 지보를 포함하며, 상기 선형 유도 각형관이 상기 도달구에서 회수되어 재사용되는 것을 특징으로 한다.The present invention relates to a trenchless tunnel excavation system and its construction method. The trenchless tunnel excavation system of the present invention includes a plurality of sheet piles (SHEET PILE) that are sequentially press-fitted or pushed into the inner wall of a tunnel, which is an underground structure, and are constructed on the upper and side parts of the inner wall of the tunnel; A plurality of linear guide rectangular pipes that move in a straight line or curve from the thrust port of the tunnel to the arrival port by the action of a hydraulic jack for propulsion and guide the excavation of earth and stone and the installation of the sheet pile; An upper ground disturbance unit that is coupled to the upper part of the linear guide rectangular pipe and causes ground disturbance to proceed at the corresponding position when the linear guide rectangular pipe is pressed in or pushed in; A side ground disturbance unit coupled to a side of the linear guide rectangular pipe and causing ground disturbance in the corresponding position when the linear guide rectangular pipe is pressed in or pushed in; A plurality of earth pressure supports connected to the sheet piles and supporting the sheet piles; And a plurality of tunnel supports connected to the earth pressure supports and supporting the earth pressure supports, wherein the linear guide square pipe is recovered from the arrival port and reused.

Description

비개착 터널용 굴착시스템 및 그 공법{Sheet non excavation method for drilling a tunnel having a file reinforcing structure}Excavation system for trenchless tunnel and method thereof {Sheet non excavation method for drilling a tunnel having a file reinforcing structure}

본 발명은, 비개착 터널용 굴착시스템 및 그 공법에 관한 것으로서, 더욱 상세하게는, 지하에 매설물이 많거나 교통량이 많은 장소와 같이 지표면을 걷어 내고 공사하기 어려운 곳에서 터 파기를 하지 않고 지하 구조물을 시공할 수 있음은 물론, 종전 공법들과 달리 선형 유도 각형관을 사용함으로써 선형의 직진성 또는 곡선의 작업을 원활하게 수행할 수 있을뿐더러 안전 문제를 효과적으로 해소할 수 있으며, 유압잭의 소형화 가능하고 선형 유도 각형관을 재사용할 수 있어서 공사비 절감에 이바지할 수 있는, 비개착 터널용 굴착시스템 및 그 공법에 관한 것이다.The present invention relates to an excavation system for a trenchless tunnel and its construction method, and more specifically, to an underground structure without digging in places where it is difficult to clear the ground surface and construct, such as places with a lot of buried underground stuff or a lot of traffic. Not only can construction be possible, but unlike previous construction methods, by using a linear guide square pipe, not only can linear straightness or curved work be performed smoothly, but safety issues can be effectively resolved, hydraulic jacks can be miniaturized, and linear guide pipes can be used. This relates to a trenchless tunnel excavation system and method that can reuse guided square pipes, thereby contributing to reducing construction costs.

최근 들어 도심지에는 지상 건물의 포화로 지하 공간의 이용이 늘어나고 있는 추세이다. 지하 공간 활용을 위하여 지하 구조물을 시공하는 방법은 크게 개착공법과 비개착공법으로 구분할 수 있다.Recently, the use of underground spaces is increasing in urban areas due to the saturation of above-ground buildings. Methods for constructing underground structures to utilize underground space can be broadly divided into trenchless construction methods and trenchless construction methods.

개착공법은 굴착을 위한 벽체(C.I.P, H-Pile+토류판, Sheet Pile 등)를 시공한 후 굴착진행과 동시에 지보재(Strut, 어스앵커 등)를 설치하면서 굴착하는 공법으로 일반적인 굴착공사에 가장 많이 이용된다. 하지만, 개착공법을 도심지 공사에 적용할 경우 교통체증의 유발, 지장물 이설비용 발생 등의 문제가 발생할 수 있다.The cut-and-cover method is a method of constructing a wall for excavation (C.I.P., H-Pile + earth plate, sheet pile, etc.) and then installing support materials (struts, earth anchors, etc.) while excavating. It is most commonly used in general excavation work. . However, when the cut-and-cut method is applied to urban construction, problems such as traffic congestion and the cost of moving obstacles may occur.

따라서, 최근 들어 도심지 공사에서는 교통 불편으로 인한 민원 해결과 지장물 이설비용을 최소화하기 위하여 비개착공법의 적용이 늘어나고 있는 추세이다. 현재 적용되는 비개착공법은 종류가 다양하며, 각기 다른 특징을 가지고 있기 때문에 각 현장 상황을 잘 고려하여 적용할 필요가 있다.Therefore, in recent years, there has been an increasing trend in the application of trenchless construction methods in urban construction to resolve civil complaints due to traffic inconveniences and minimize the cost of moving obstacles. There are various types of trenchless construction methods currently applied, and each has different characteristics, so it is necessary to carefully consider each site situation and apply it.

비개착공법을 소개한다.Introducing the trenchless construction method.

첫째, Pipe Roof 공법(Pipe Roof Method)이다. 이는 가장 널리 통용되는 비개착공법으로, 현재 적용되고 있는 많은 비개착공법들은 Pipe Roof 공법을 개량하여 발전시킨 공법들이다.First, the Pipe Roof Method. This is the most widely used trenchless construction method, and many of the trenchless construction methods currently being applied are methods developed by improving the Pipe Roof method.

둘째, PRS 공법(Pipe Roof Structure)이다. 강관의 한쪽에 수평방향으로 홈을 형성시키고 다른 쪽은 수평 홈과 맞물릴 수 있도록 앵글을 설치하여 여러 강관들을 이웃하게 서로 맞댄 상태로 연결시켜 횡방향 강성을 극대화시킴으로써 별도의 횡방향 지보재 없이 시행하는 공법이다.Second, it is the PRS method (Pipe Roof Structure). A groove is formed in the horizontal direction on one side of the steel pipe, and an angle is installed on the other side to engage with the horizontal groove, connecting several steel pipes next to each other to maximize lateral rigidity, which is performed without a separate lateral support material. It is a public method.

셋째, UPRS 공법(Upgrade Pipe Roof Structure)이다. 이는 PRS 공법을 개량한 공법으로 레일이 부착된 기성강관 묶음을 이용하여 강관 다발을 압입하는 공법이다.Third, it is the UPRS method (Upgrade Pipe Roof Structure). This is an improved method of the PRS method, and is a method of press-fitting a bundle of steel pipes using a bundle of ready-made steel pipes with rails attached.

넷째, STS 공법(Steel Tube Slab)이다. 공장에서 날개강판을 부착시킨 소형 강관을 사용하여 지중에 Roof를 형성하고 강관의 횡방향 연결부를 철근으로 보강한 후 몰탈을 타설하여 종횡으로 일체화된 라멘 구조체를 형성하고 지보재를 이용하여 굴착한 후 구조물을 시공하는 공법이다.Fourth, the STS method (Steel Tube Slab). At the factory, a roof is formed in the ground using small steel pipes with wing steel plates attached. After reinforcing the lateral connections of the steel pipes with rebar, mortar is poured to form a longitudinally and horizontally integrated ramen structure, and the structure is excavated using support materials. This is a construction method.

다섯째, TRcM 공법(Tubular Roof construction Method)이다. 작업구에서 종횡단 구배에 따라 선형을 조정할 수 있도록 선도관과 후속관 사이에 유압식 조정 장치를 장착한 강관을 유압잭으로 압입한 후 강관 내부를 굴착, 철근 배근 및 콘크리트를 타설하여 상부 슬래브를 완성시키고 PC판넬 및 Support잭을 이용하여 지중 수직벽을 설치한 후 내부를 굴착하여 구조물을 시공하는 공법이다. Fifth, the TRcM method (Tubular Roof construction Method). A steel pipe equipped with a hydraulic adjusting device between the lead pipe and the follow-up pipe is pressed in with a hydraulic jack so that the line can be adjusted according to the longitudinal and cross-sectional gradients at the work area, and then the upper slab is completed by excavating the inside of the steel pipe, placing reinforcing bars, and pouring concrete. This is a method of constructing a structure by installing an underground vertical wall using a PC panel and support jack and then excavating the inside.

여섯째, NTR 공법(New Tubular Roof)이다. 강관 내 토압지지대를 설치하고 압입관(D=2.2m) 상하, 좌우를 절개한 다음 절개된 외측 또는 상부를 철판으로 용접하여 방수한 후, 구조물 형성을 위한 거푸집 철근을 설치하고 콘크리트를 타설하여 구조체를 축조한 다음 내부 토사를 굴착하는 공법이다.Sixth, the NTR method (New Tubular Roof). Install the earth pressure support in the steel pipe, cut the top, bottom, left and right sides of the press-fit pipe (D=2.2m), weld the outside or top of the cut with a steel plate to waterproof it, install form reinforcement to form the structure, and pour concrete to create the structure. This is a method of constructing a building and then excavating the internal soil.

일곱째, TSM 공법(Tunnel of using Steel pipe Method)이다. 강관을 압입한 상태에서 강관 내부에 보강폼을 설치하고, 강관과 강관 사이에 슬롯홀을 형성한 후 철판으로 일체화한 다음, 형성된 Roof에 수직 지보재를 설치하면서 굴착하는 공법이다.Seventh, the TSM method (Tunnel of using Steel pipe Method). This is a method of installing reinforcing foam inside the steel pipe while press-fitting the steel pipe, forming a slot hole between the steel pipe and integrating it with a steel plate, and then excavating while installing a vertical support material on the formed roof.

여덟째, DSM 공법(Divided Shield Method)이다. 1900년대 중반 많이 이용되던 Messer Shield 공법을 개량 발전시킨 공법으로 Messer Shield 공법의 단점이었던 시공중 뒷꼬리부 처침 현상을 해결하였으며, 칼날 형태의 DSM 판넬(철판)을 인력으로 연속적으로 압입하여 임시 Roof와 벽체를 형성하는 공법이다. 또한, 철판의 약한 강성을 2열 지반보강 그라우팅으로 보강하여 굴착중 발생 가능한 지반의 이완 현상을 방지한다.Eighth, the DSM method (Divided Shield Method). This is an improved and developed method of the Messer Shield method, which was widely used in the mid-1900s. It solved the problem of the rear tail drooping during construction, which was a disadvantage of the Messer Shield method, and created a temporary roof and temporary roof by continuously press-fitting blade-shaped DSM panels (steel plates) by manpower. This is a method of forming a wall. In addition, the weak rigidity of the steel plate is reinforced with two-row ground reinforcement grouting to prevent ground loosening that may occur during excavation.

아홉째, Front Jacking 공법이다. 이는 강관을 이용하여 임시 지보(Roof)를 형성한 후, 미리 제작된 구조물을 유압잭을 이용하여 견인하는 공법이다.Ninth is the front jacking method. This is a method of forming a temporary roof using steel pipes and then towing the pre-fabricated structure using a hydraulic jack.

이상 간략하게 설명한 것처럼 비개착공법에는 여러 타입이 있는데, 이들의 가장 큰 개념은 굴착 전 지반 이완 등의 주변 변형을 억제할 수 있는 임시 지보를 설치한 후, 안전하게 굴착하여 구조물을 시공한다는 것이다.As briefly explained above, there are several types of trenchless construction methods, the biggest concept of which is to install temporary supports that can suppress surrounding deformation such as ground loosening before excavation, and then safely excavate to construct the structure.

따라서 공법 선정에 있어서 가장 중요한 점은 현장 적용성과 경제성이라 할 수 있다는 점을 두루 고려해볼 때, 기존 공법에서 좀 더 개선된 방식의 기술 개량이 필요하다.Therefore, considering that the most important factors in selecting a construction method are field applicability and economic feasibility, there is a need for technological improvements to improve the existing construction method.

대한민국특허청 출원번호 제10-2003-0072109호Korea Intellectual Property Office Application No. 10-2003-0072109

본 발명의 목적은, 지하에 매설물이 많거나 교통량이 많은 장소와 같이 지표면을 걷어 내고 공사하기 어려운 곳에서 터 파기를 하지 않고 지하 구조물을 시공할 수 있음은 물론, 종전 공법들과 달리 선형 유도 각형관을 사용함으로써 선형의 직진성 또는 곡선의 작업을 원활하게 수행할 수 있을뿐더러 안전 문제를 효과적으로 해소할 수 있으며, 유압잭의 소형화 가능하고 선형 유도 각형관을 재사용할 수 있어서 공사비 절감에 이바지할 수 있는, 비개착 터널용 굴착시스템 및 그 공법을 제공하는 것이다.The purpose of the present invention is to be able to construct an underground structure without digging the ground in places where it is difficult to clear the ground surface and construct, such as places where there are a lot of underground structures or a lot of traffic, and, unlike previous construction methods, a linear guided square structure can be constructed. By using pipes, not only can linear straightness or curved work be performed smoothly, but safety problems can also be effectively resolved. Hydraulic jacks can be miniaturized and linear guide square pipes can be reused, which can contribute to reducing construction costs. The purpose is to provide an excavation system and construction method for trenchless tunnels.

상기 목적은, 지하 구조물인 터널의 내벽체에 순차적으로 압입 또는 추진되어 상기 터널의 내벽체 상부와 측부에 시공되는 복수 개의 시트 파일(SHEET PIlE); 추진용 유압잭을 작용으로 상기 터널의 추진구에서 도달구까지 직선 또는 곡선 이동하며, 토석의 굴착과 상기 시트 파일의 설치가 가능하게 유도하는 복수 개의 선형 유도 각형관; 상기 선형 유도 각형관의 상부에 결합하며, 상기 선형 유도 각형관의 압입 또는 추진 시 해당 위치에서 막장의 지반 교란이 진행되게 하는 상부 지반 교란부; 상기 선형 유도 각형관의 측부에 결합하며, 상기 선형 유도 각형관의 압입 또는 추진 시 해당 위치에서 막장의 지반 교란이 진행되게 하는 측부 지반 교란부; 상기 시트 파일들과 연결되고 상기 시트 파일들을 지지하는 복수 개의 토압 지지대; 및 상기 토압 지지대들과 연결되고 상기 토압 지지대들을 지지하는 복수 개의 터널 지보를 포함하며, 상기 선형 유도 각형관이 상기 도달구에서 회수되어 재사용되는 것을 특징으로 하는 비개착 터널용 굴착시스템에 의해 달성된다.The above purpose is to sequentially press-fit or propel the inner wall of a tunnel, which is an underground structure, and construct a plurality of sheet piles on the upper and side parts of the inner wall of the tunnel; A plurality of linear guide rectangular pipes that move in a straight line or curve from the thrust port of the tunnel to the arrival port by the action of a hydraulic jack for propulsion and guide the excavation of earth and stone and the installation of the sheet pile; An upper ground disturbance unit that is coupled to the upper part of the linear guide rectangular pipe and causes ground disturbance to proceed at the corresponding position when the linear guide rectangular pipe is pressed in or pushed in; A side ground disturbance unit coupled to a side of the linear guide rectangular pipe and causing ground disturbance in the corresponding position when the linear guide rectangular pipe is pressed in or pushed in; A plurality of earth pressure supports connected to the sheet piles and supporting the sheet piles; And a plurality of tunnel supports connected to the earth pressure supports and supporting the earth pressure supports, wherein the linear guide square pipe is recovered from the reach and reused. This is achieved by an excavation system for a trenchless tunnel. .

상기 상부 지반 교란부와 상기 측부 지반 교란부 모두는, 상기 선형 유도 각형관의 상부와 측부의 단부보다 일부분이 노출되게 마련되며, 상기 선형 유도 각형관의 압입 또는 추진 시 막장의 지반 교란이 진행되게 하는 지반 교란용 회전 톱날; 상기 지반 교란용 회전 톱날을 회전시키기 위한 동력을 발생시키는 동력 발생부; 및 상기 동력 발생부에서 발생한 동력이 상기 지반 교란용 회전 톱날의 회전운동으로 전달되게 상기 동력 발생부와 상기 지반 교란용 회전 톱날을 연결해서 운동을 전달하는 운동 전달부를 포함할 수 있다.Both the upper ground disturbance portion and the side ground disturbance portion are provided so that a portion of the upper and side ends of the linear guide rectangular pipe is exposed, and when the linear guide rectangular pipe is pressed in or pushed, ground disturbance of the block progresses. Rotating saw blades for ground disturbance; a power generator that generates power to rotate the ground disturbance rotary saw blade; And it may include a motion transmission unit that connects the power generation unit and the ground disturbance rotating saw blade to transmit the motion so that the power generated by the power generation unit is transmitted to the rotational movement of the ground disturbing rotating saw blade.

상기 시트 파일은 상기 선형 유도 각형관 내에서 시트 파일 지지대에 의해 지지되며, 상기 시트 파일 지지대와 상기 시트 파일 사이에는 상기 시트 파일을 연결하는 시트 파일 연결 띠철판이 마련되며, 상기 시트 파일 연결 띠철판이 임시 지보에 의해 지지되며, 상기 선형 유도 각형관의 내벽에는 선형 유지를 위한 선형 유지 커넥터가 마련되며, 상기 선형 유도 각형관의 내벽에는 상기 선형 유도 각형관을 압입 또는 추진하기 위한 추진 밀대가 마련되며, 상기 시트 파일은 높이(H) 162~170mm, 폭(W) 650~750mm, 두께(T) 12~20mm로 제작되며, 상기 시트 파일의 설치 직후, 상기 시트 파일의 외부에 1차 모래채움 그라우팅이 수행된 다음, 상기 1차 모래채움 그라우팅의 외부로 2차 여굴채움 그라우팅이 수행될 수 있다.The sheet pile is supported by a sheet pile support within the linear guide rectangular pipe, and a sheet pile connecting steel strip connecting the sheet pile is provided between the sheet pile support and the sheet pile, and the sheet pile connecting steel strip is provided. It is supported by this temporary support, and a linear retaining connector is provided on the inner wall of the linear guide rectangular pipe for maintaining the linear shape. A pushing pusher for press-fitting or pushing the linear guide rectangular pipe is provided on the inner wall of the linear guide rectangular pipe. The sheet pile is manufactured with a height (H) of 162 to 170 mm, a width (W) of 650 to 750 mm, and a thickness (T) of 12 to 20 mm. Immediately after installation of the sheet pile, the outside of the sheet pile is first filled with sand. After grouting is performed, secondary overburden filling grouting may be performed outside the primary sand filling grouting.

상기 목적은, 추진용 유압잭을 작용으로 상기 터널의 추진구에서 도달구까지 직선 또는 곡선 이동하게 복수 개의 선형 유도 각형관을 설치하는 단계; 상기 선형 유도 각형관을 매개로 토석을 굴착하는 한편 복수 개의 시트 파일(SHEET PIlE)을 시공하는 단계; 상기 시트 파일들을 지지하는 복수 개의 토압 지지대를 시공하는 단계; 상기 토압 지지대들을 지지하는 복수 개의 터널 지보를 시공하는 단계; 및 상기 선형 유도 각형관을 상기 도달구에서 회수하는 단계를 포함하며, 상기 시트 파일의 설치 직후, 상기 시트 파일의 외부에 1차 모래채움 그라우팅이 수행된 다음, 상기 1차 모래채움 그라우팅의 외부로 2차 여굴채움 그라우팅이 수행되는 것을 특징으로 하는 비개착 터널용 굴착공법에 의해서도 달성된다.The purpose is to install a plurality of linear guide square pipes to move in a straight line or curve from the thrust port of the tunnel to the arrival port by the action of a hydraulic jack for propulsion; Excavating soil through the linear guide rectangular pipe and constructing a plurality of sheet piles (SHEET PILE); Constructing a plurality of earth pressure supports supporting the sheet piles; Constructing a plurality of tunnel supports supporting the earth pressure supports; And a step of recovering the linear guide square pipe from the arrival port, wherein immediately after installation of the sheet pile, primary sand filling grouting is performed on the outside of the sheet pile, and then performing primary sand filling grouting on the outside of the first sand filling grouting. It is also achieved by a trenchless tunnel excavation method, characterized in that secondary overburden filling grouting is performed.

본 발명에 따르면, 지하에 매설물이 많거나 교통량이 많은 장소와 같이 지표면을 걷어 내고 공사하기 어려운 곳에서 터 파기를 하지 않고 지하 구조물을 시공할 수 있음은 물론, 종전 공법들과 달리 선형 유도 각형관을 사용함으로써 선형의 직진성 또는 곡선의 작업을 원활하게 수행할 수 있을뿐더러 안전 문제를 효과적으로 해소할 수 있으며, 유압잭의 소형화 가능하고 선형 유도 각형관을 재사용할 수 있어서 공사비 절감에 이바지할 수 있는 효과가 있다.According to the present invention, it is possible to construct an underground structure without digging the ground in places where it is difficult to clear the ground surface and construct, such as places where there are a lot of underground structures or a lot of traffic, and unlike previous construction methods, the linear guided square pipe By using , linear straightness or curved work can be performed smoothly and safety problems can be effectively resolved. Hydraulic jacks can be miniaturized and linear guide square pipes can be reused, which can contribute to reducing construction costs. there is.

도 1은 본 발명의 일 실시예에 따른 비개착 터널용 굴착시스템의 개요도이다.
도 2는 도 1의 상세도로서 선형 유도 각형관의 추진 및 시트 파일을 설치하는 과정을 보인 도면이다.
도 3은 선형 유도 각형관 내부의 상부에 시트 파일이 결합된 도면이다.
도 4는 선형 유도 각형관 내부의 측부에 시트 파일이 결합된 도면이다.
도 5는 시트 파일의 제원이다.
도 6은 선형 유도 각형관의 상부 지반 교란부와 측부 지반 교란부를 도시한 도면이다.
도 7은 선형 유도 각형관과 시트 파일의 작업 개요도이다.
도 8은 터널의 완성 단면 구조도이다.
도 9는 도 8의 요부 확대도이다.
1 is a schematic diagram of an excavation system for a trenchless tunnel according to an embodiment of the present invention.
Figure 2 is a detailed view of Figure 1 showing the process of propulsion of a linear guide square pipe and installation of sheet piles.
Figure 3 is a diagram showing a sheet pile coupled to the top inside a linear guided rectangular pipe.
Figure 4 is a diagram showing a sheet pile coupled to the side of the linear guide rectangular pipe.
Figure 5 shows the specifications of the sheet pile.
Figure 6 is a diagram showing the upper ground disturbance section and the side ground disturbance section of the linear guided rectangular pipe.
Figure 7 is a schematic diagram of the operation of linear guided rectangular pipe and sheet pile.
Figure 8 is a completed cross-sectional structural diagram of the tunnel.
Figure 9 is an enlarged view of the main part of Figure 8.

본 발명의 이점 및 특징, 그리고 그것들을 달성하는 방법은 첨부되는 도면과 함께 상세하게 후술하는 실시예를 참조하면 명확해질 것이다.The advantages and features of the present invention and methods for achieving them will become clear by referring to the embodiments described in detail below along with the accompanying drawings.

그러나 본 발명은 이하에서 개시되는 실시예에 한정되는 것이 아니라 서로 다른 다양한 형태로 구현될 것이다.However, the present invention is not limited to the embodiments disclosed below and will be implemented in various different forms.

본 명세서에서, 본 실시예는 본 발명의 개시가 완전하여지도록 하며, 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에게 발명의 범주를 완전하게 알려주기 위해 제공되는 것이다. 그리고 본 발명은 청구항의 범주에 의해 정의될 뿐이다.In this specification, the present embodiments are provided to complete the disclosure of the present invention and to fully inform those skilled in the art of the scope of the invention. And the present invention is only defined by the scope of the claims.

따라서 몇몇 실시예에서, 잘 알려진 구성 요소, 잘 알려진 동작 및 잘 알려진 기술들은 본 발명이 모호하게 해석되는 것을 피하려고 구체적으로 설명되지 않는다.Accordingly, in some embodiments, well-known components, well-known operations and well-known techniques are not specifically described to avoid ambiguous interpretation of the invention.

명세서 전체에 걸쳐 동일 참조 부호는 동일 구성 요소를 지칭한다. 그리고 본 명세서에서 사용된(언급된) 용어들은 실시예를 설명하기 위한 것이며 본 발명을 제한하고자 하는 것은 아니다.Like reference numerals refer to like elements throughout the specification. And the terms used (mentioned) in this specification are for describing embodiments and are not intended to limit the present invention.

본 명세서에서, 단수형은 문어구에서 특별히 언급하지 않는 한 복수형도 포함한다. 또한, '포함(또는, 구비)한다'로 언급된 구성 요소 및 동작(작용)은 하나 이상의 다른 구성 요소 및 동작의 존재 또는 추가를 배제하지 않는다.In this specification, singular forms also include plural forms unless specifically stated in the phrase. In addition, components and operations (operations) referred to as 'including (or including)' do not exclude the presence or addition of one or more other components and operations.

다른 정의가 없다면, 본 명세서에서 사용되는 모든 용어(기술 및 과학적 용어를 포함)는 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에게 공통으로 이해될 수 있는 의미로 사용될 수 있을 것이다.Unless otherwise defined, all terms (including technical and scientific terms) used in this specification may be used with meanings that can be commonly understood by those skilled in the art to which the present invention pertains.

또한, 일반적으로 사용되는 사전에 정의된 용어들은 정의되어 있지 않은 한 이상적으로 또는 과도하게 해석되지 않는다.Additionally, terms defined in commonly used dictionaries are not interpreted ideally or excessively unless they are defined.

이하, 첨부도면을 참조하여 본 발명의 바람직한 실시예를 설명한다.Hereinafter, preferred embodiments of the present invention will be described with reference to the accompanying drawings.

도 1은 본 발명의 일 실시예에 따른 비개착 터널용 굴착시스템의 개요도, 도 2는 도 1의 상세도로서 선형 유도 각형관의 추진 및 시트 파일을 설치하는 과정을 보인 도면, 도 3은 선형 유도 각형관 내부의 상부에 시트 파일이 결합된 도면, 도 4는 선형 유도 각형관 내부의 측부에 시트 파일이 결합된 도면, 도 5는 시트 파일의 제원, 도 6은 선형 유도 각형관의 상부 지반 교란부와 측부 지반 교란부를 도시한 도면, 도 7은 선형 유도 각형관과 시트 파일의 작업 개요도, 도 8은 터널의 완성 단면 구조도, 도 9는 도 8의 요부 확대도이다.Figure 1 is a schematic diagram of an excavation system for a trenchless tunnel according to an embodiment of the present invention, Figure 2 is a detailed diagram of Figure 1 showing the process of propulsion of a linear guide square pipe and installing sheet piles, Figure 3 is a diagram showing the process of propulsion and installing sheet piles Figure 4 is a diagram showing sheet piles coupled to the top of the linear guided rectangular pipe, Figure 4 is a drawing of sheet piles coupled to the sides inside the linear guided rectangular pipe, Figure 5 is the specifications of the sheet pile, and Figure 6 is the upper part of the linear guided rectangular pipe. A drawing showing the ground disturbance section and the side ground disturbance section, FIG. 7 is a schematic diagram of the work of the linear guide square pipe and sheet pile, FIG. 8 is a completed cross-sectional structure of the tunnel, and FIG. 9 is an enlarged view of the main part of FIG. 8.

이들 도면을 참조하면, 본 발명은 지하에 매설물이 많거나 교통량이 많은 장소와 같이 지표면을 걷어 내고 공사하기 어려운 곳에서 터 파기를 하지 않고 지하 구조물을 시공할 수 있음은 물론, 종전 공법들과 달리 선형 유도 각형관(110)을 사용함으로써 선형의 직진성 또는 곡선의 작업을 원활하게 수행할 수 있을뿐더러 안전 문제를 효과적으로 해소할 수 있으며, 유압잭의 소형화 가능하고 선형 유도 각형관(110)을 재사용할 수 있어서 공사비 절감에 이바지할 수 있다.Referring to these drawings, the present invention not only allows construction of underground structures without digging in places where it is difficult to clear the ground surface and construct, such as places with many underground structures or heavy traffic, but also, unlike previous construction methods, By using the linear guide square pipe (110), not only can linear straightness or curved work be performed smoothly, but also safety problems can be effectively solved, hydraulic jacks can be miniaturized, and the linear guide square pipe (110) can be reused. This can contribute to reducing construction costs.

특히, 아래의 구조와 방법으로 시공되는 본 발명은 선형 유도 각형관(110)을 매개로 해서 시트 파일(100, SHEET PIlE)을 순차적으로 압입, 추진하는 방식이라서 소규모 추진력과 압입 시간이 짧다. 또한, 최소 토피고(노상 및 자장물 0.5m 이하) 구조물 시공이 가능하고, 지장물 또는 지반 변화에 신속한 대응이 가능하다. 또한, 지보의 지지력 확보로 처짐 방지 및 안전성이 확보되고, 굴착 및 배토성이 유리하고 지장물 조우 시 신속 조치가 가능하다. 또한, 타공법 대비 공기 단축 및 공사비 절감 효과가 크고, 방수에 탁월한 효과를 제공할 수 있다.In particular, the present invention, which is constructed using the structure and method below, is a method of sequentially press-fitting and propelling the sheet pile (100, SHEET PILE) using the linear guide square pipe 110, so the small-scale driving force and press-fit time are short. In addition, it is possible to construct structures with a minimum cover height (less than 0.5m of subgrade and magnetic barriers), and rapid response to obstacles or ground changes is possible. In addition, sagging is prevented and safety is ensured by securing the bearing capacity of the support, excavation and embankment properties are advantageous, and quick action is possible when obstacles are encountered. In addition, it has a significant effect of shortening the construction period and reducing construction costs compared to the perforated method, and can provide excellent waterproofing effects.

이러한 효과를 제공할 수 있는 본 실시예에 따른 비개착 터널용 굴착시스템은 시트 파일(100) 및 선형 유도 각형관(110)을 포함하며, 이들의 시공을 위한 아래 구조, 구성들을 포함한다.The trenchless tunnel excavation system according to this embodiment that can provide such effects includes sheet piles 100 and linear guide square pipes 110, and includes the following structures and configurations for their construction.

시트 파일(100)은 지하 구조물인 터널(도 8 및 도 9 참조)의 내벽체에 순차적으로 압입 또는 추진되어 터널의 내벽체 상부와 측부에 시공된다. 시트 파일(100)은 터널의 바닥을 제외한 상부와 측부 모두에 연속적으로 시공된다. 따라서, 시트 파일(100)은 복수 개다.The sheet pile 100 is sequentially press-fitted or pushed into the inner wall of a tunnel, which is an underground structure (see FIGS. 8 and 9), and is constructed on the upper and side parts of the inner wall of the tunnel. Sheet piles 100 are continuously constructed on both the top and sides except the bottom of the tunnel. Accordingly, there are a plurality of sheet piles 100.

시트 파일(100)에 추후 그라우팅 밸브(30)가 결합할 수 있다. 이를 매개로, 시트 파일(100)의 설치 직후, 시트 파일(100)의 외부에 1차 모래채움 그라우팅(171)이 수행된 다음, 1차 모래채움 그라우팅(171)의 외부로 2차 여굴채움 그라우팅이(172) 수행될 수 있다. 따라서, 완벽 방수가 가능해진다.The grouting valve 30 may later be coupled to the sheet pile 100. Through this, immediately after installation of the sheet pile 100, primary sand filling grouting 171 is performed on the outside of the sheet pile 100, and then secondary overburden filling grouting is performed on the outside of the primary sand filling grouting 171. This 172 can be performed. Therefore, complete waterproofing becomes possible.

시트 파일(100)은 도 5에 도시된 것처럼 높이(H) 162~170mm, 폭(W) 650~750mm, 두께(T) 12~20mm로 제작될 수 있다.The sheet pile 100 can be manufactured with a height (H) of 162 to 170 mm, a width (W) of 650 to 750 mm, and a thickness (T) of 12 to 20 mm, as shown in FIG. 5.

그리고, 시트 파일(100)은 선형 유도 각형관(110) 내에서 시트 파일 지지대(151)에 의해 지지되는데, 시트 파일 지지대(151)와 시트 파일(100) 사이에는 시트 파일(100)을 연결하는 시트 파일 연결 띠철판(152)이 마련된다. 따라서, 복수 개의 시트 파일(100)을 연결 시공할 수 있다. 이때, 시트 파일 연결 띠철판(152)이 임시 지보(153)에 의해 지지될 수 있다.In addition, the sheet pile 100 is supported by a sheet pile support 151 within the linear guided rectangular pipe 110, and between the sheet pile support 151 and the sheet pile 100 is a connection between the sheet pile 100. A sheet pile connection band steel plate (152) is provided. Therefore, a plurality of sheet piles 100 can be connected and constructed. At this time, the sheet pile connecting steel strip 152 may be supported by the temporary support 153.

한편, 선형 유도 각형관(110)은 추진구(A)가 위치하는 추진 작업대(20) 상에서부터 추진용 유압잭(10)을 작용으로 터널의 추진구(A)에서 도달구(B)까지 직선 또는 곡선 이동하는 구조물로서, 토석의 굴착과 시트 파일(100)의 설치가 가능하게 유도한다.On the other hand, the linear guide square pipe 110 runs in a straight line from the thrust port (A) of the tunnel to the arrival port (B) by applying the hydraulic jack (10) for propulsion from the propulsion worktable (20) where the propulsion port (A) is located. As a curved moving structure, it allows excavation of earth and stone and installation of sheet piles 100.

선형 유도 각형관(110)은 복수 개가 측방, 후방에 연결되어 사용될 수 있다. 선형 유도 각형관(110)의 내벽에는 선형 유지를 위한 복수 개의 선형 유지 커넥터(111)가 마련된다. 그리고, 선형 유도 각형관(110)의 내벽에는 선형 유도 각형관(110)을 압입 또는 추진하기 위한 추진 밀대(112)가 마련된다.A plurality of linear guide square tubes 110 may be connected to the side and rear. A plurality of linear maintenance connectors 111 are provided on the inner wall of the linear guide square tube 110 to maintain the linearity. In addition, a propulsion pusher 112 is provided on the inner wall of the linear guide rectangular pipe 110 for press-fitting or pushing the linear guide rectangular pipe 110.

선형 유도 각형관(110)에는 상부 지반 교란부(120)와 측부 지반 교란부(130)가 마련된다.The linear guide square pipe 110 is provided with an upper ground disturbance unit 120 and a side ground disturbance unit 130.

상부 지반 교란부(120)는 선형 유도 각형관(110)의 상부에 결합하며, 선형 유도 각형관(110)의 압입 또는 추진 시 해당 위치에서 막장의 지반 교란이 진행되게 하는 수단이다.The upper ground disturbance unit 120 is coupled to the upper part of the linear guide rectangular pipe 110, and is a means for causing ground disturbance at the corresponding position when the linear guide rectangular pipe 110 is pressed in or pushed.

이러한 상부 지반 교란부(120)는 선형 유도 각형관(110)의 상부의 단부보다 일부분이 노출되게 마련되며, 선형 유도 각형관(110)의 압입 또는 추진 시 막장의 지반 교란이 진행되게 하는 지반 교란용 회전 톱날(121)과, 지반 교란용 회전 톱날(121)을 회전시키기 위한 동력을 발생시키는 동력 발생부(122)와, 동력 발생부(122)에서 발생한 동력이 지반 교란용 회전 톱날(121)의 회전운동으로 전달되게 동력 발생부(122)와 지반 교란용 회전 톱날(121)을 연결해서 운동을 전달하는 운동 전달부(123)를 포함한다.This upper ground disturbance portion 120 is provided so that a portion of the upper end of the linear guide rectangular pipe 110 is exposed, and when the linear guide rectangular pipe 110 is pressed in or pushed in, the ground disturbance causes the ground disturbance to proceed. A power generator 122 that generates power to rotate the rotary saw blade 121 for ground disturbance, and the power generated from the power generator 122 to rotate the rotary saw blade 121 for ground disturbance. It includes a motion transmission unit 123 that transmits the motion by connecting the power generation unit 122 and the rotating saw blade 121 for ground disturbance to be transmitted as a rotational motion.

측부 지반 교란부(130)는 선형 유도 각형관(110)의 측부에 결합하며, 선형 유도 각형관(110)의 압입 또는 추진 시 해당 위치에서 막장의 지반 교란이 진행되게 하는 수단이다.The side ground disturbance unit 130 is coupled to the side of the linear guide rectangular pipe 110 and is a means for causing ground disturbance at the corresponding location when the linear guide rectangular pipe 110 is pressed in or pushed.

이러한 측부 지반 교란부(130)는 선형 유도 각형관(110)의 측부의 단부보다 일부분이 노출되게 마련되며, 선형 유도 각형관(110)의 압입 또는 추진 시 막장의 지반 교란이 진행되게 하는 지반 교란용 회전 톱날(131)과, 지반 교란용 회전 톱날(131)을 회전시키기 위한 동력을 발생시키는 동력 발생부(132)와, 동력 발생부(132)에서 발생한 동력이 지반 교란용 회전 톱날(131)의 회전운동으로 전달되게 동력 발생부(132)와 지반 교란용 회전 톱날(131)을 연결해서 운동을 전달하는 운동 전달부(133)를 포함한다.This side ground disturbance portion 130 is provided so that a portion of the side of the linear guide rectangular pipe 110 is exposed, and when the linear guide rectangular pipe 110 is pressed in or pushed in, the ground disturbance causes the ground disturbance to proceed. A power generator 132 that generates power to rotate the rotary saw blade 131 for ground disturbance, and the power generated from the power generator 132 to rotate the rotary saw blade 131 for ground disturbance. It includes a motion transmission unit 133 that transmits the motion by connecting the power generation unit 132 and the rotating saw blade 131 for ground disturbance to be transmitted as a rotational motion.

전술한 것처럼 선형 유도 각형관(110)은 추진구(A)가 위치하는 추진 작업대(20) 상에서부터 추진용 유압잭(10)을 작용으로 터널의 추진구(A)에서 도달구(B)까지 직선 또는 곡선 이동하는 구조물이다. 따라서, 도달구(B)에 도달한 선형 유도 각형관(110)은 회수되어 재사용될 수 있다. 따라서, 비용절감에 기여할 수 있다.As described above, the linear guide square pipe 110 moves in a straight line from the propulsion port (A) of the tunnel to the arrival port (B) by applying the hydraulic jack (10) for propulsion from the propulsion worktable (20) where the propulsion port (A) is located. Or it is a structure that moves along a curve. Accordingly, the linear guide square tube 110 that has reached the arrival port B can be recovered and reused. Therefore, it can contribute to cost reduction.

이하, 비개착 터널용 굴착시스템의 사용법을 설명한다.Hereinafter, the use of the trenchless tunnel excavation system will be described.

우선, 추진용 유압잭(10)을 작용으로 터널의 추진구(A)에서 도달구(B)까지 직선 또는 곡선 이동하게 복수 개의 선형 유도 각형관(110)을 설치한다.First, a plurality of linear guide square pipes (110) are installed to move in a straight line or curve from the thrust port (A) of the tunnel to the arrival port (B) by the action of the hydraulic jack for propulsion (10).

다음, 선형 유도 각형관(110)을 매개로 토석을 굴착하는 한편 복수 개의 시트 파일(100)을 시공한다. 시트 파일(100)은 터널 내의 상부와 측부 모두에 시공된다. 시공이 완료되면, 선형 유도 각형관(110)을 도달구(B)에서 회수한다.Next, the soil is excavated through the linear guide square pipe 110, and a plurality of sheet piles 100 are constructed. Sheet piles 100 are constructed on both the top and sides of the tunnel. When construction is completed, the linear guide square pipe 110 is recovered from the arrival port (B).

다음, 시트 파일(100)들을 지지하는 복수 개의 토압 지지대(150)를 시공한 후, 토압 지지대(150)들을 지지하는 복수 개의 터널 지보(160)를 시공한다.Next, after constructing a plurality of earth pressure supports 150 supporting the sheet piles 100, a plurality of tunnel supports 160 supporting the earth pressure supports 150 are constructed.

이처럼 시트 파일(100)의 설치 직후, 시트 파일(100)의 외부에 1차 모래채움 그라우팅(171)이 수행된 다음, 1차 모래채움 그라우팅(171)의 외부로 2차 여굴채움 그라우팅이(172)이 수행되게 함으로써, 시공이 마무리될 수 있다.In this way, immediately after installation of the sheet pile 100, primary sand filling grouting 171 is performed on the outside of the sheet pile 100, and then secondary overburden filling grouting is performed on the outside of the primary sand filling grouting 171 (172). ) is performed, construction can be completed.

이상 설명한 바와 같은 구조를 기반으로 작용을 하는 본 실시예에 따르면, 지하에 매설물이 많거나 교통량이 많은 장소와 같이 지표면을 걷어 내고 공사하기 어려운 곳에서 터 파기를 하지 않고 지하 구조물을 시공할 수 있음은 물론, 종전 공법들과 달리 선형 유도 각형관(110)을 사용함으로써 선형의 직진성 또는 곡선의 작업을 원활하게 수행할 수 있을뿐더러 안전 문제를 효과적으로 해소할 수 있으며, 유압잭의 소형화 가능하고 선형 유도 각형관(110)을 재사용할 수 있어서 공사비 절감에 이바지할 수 있게 된다.According to this embodiment, which operates based on the structure described above, it is possible to construct an underground structure without digging a site in places where it is difficult to clear the ground surface and construct, such as in places where there are a lot of buried underground items or a place with a lot of traffic. Of course, unlike previous methods, by using the linear guide square pipe 110, not only can linear straightness or curved work be performed smoothly, but safety problems can also be effectively solved, and hydraulic jacks can be miniaturized and linear guide square pipes can be used. The pipe 110 can be reused, contributing to reducing construction costs.

특히, 본 실시예의 경우, 소규모 추진력과 압입 시간이 짧으며, 최소 토피고(노상 및 자장물 0.5m 이하) 구조물 시공이 가능하고, 지장물 또는 지반 변화에 신속한 대응이 가능하며, 지보의 지지력 확보로 처짐 방지 및 안전성이 확보되고, 굴착 및 배토성이 유리하고 지장물 조우 시 신속 조치가 가능하며, 타공법 대비 공기 단축 및 공사비 절감 효과가 크고, 방수에 탁월한 효과를 제공할 수 있다.In particular, in the case of this embodiment, small-scale driving force and press-in time are short, construction of a structure with a minimum cover height (0.5 m or less for subgrade and self-covering) is possible, rapid response to obstacles or ground changes is possible, and the bearing capacity of the support is secured. This prevents sagging and ensures safety, has advantageous excavation and topping properties, allows quick action when encountering obstacles, has a significant effect on shortening the construction period and reducing construction costs compared to the perforated method, and can provide excellent waterproofing effects.

이처럼 본 발명은 기재된 실시예에 한정되는 것이 아니고, 본 발명의 사상 및 범위를 벗어나지 않고 다양하게 수정 및 변형할 수 있음은 이 기술의 분야에서 통상의 지식을 가진 자에게 자명하다. 따라서 그러한 수정예 또는 변형예들은 본 발명의 청구범위에 속한다고 하여야 할 것이다.As such, the present invention is not limited to the described embodiments, and it is obvious to those skilled in the art that various modifications and changes can be made without departing from the spirit and scope of the present invention. Therefore, it should be said that such modifications or variations fall within the scope of the claims of the present invention.

A : 추진구 B : 도달구
10 : 추진용 유압잭 100 : 시트 파일
110 : 선형 유도 각형관 111 : 선형 유지 커넥터
112 : 추진 밀대 120 : 상부 지반 교란부
121 : 상부 지반 교란용 회전 톱날 122 : 상부 동력 발생부
123 : 상부 운동 전달부 130 : 측부 지반 교란부
131 : 측부 지반 교란용 회전 톱날 132 : 측부 동력 발생부
133 : 측부 운동 전달부 151 : 시트 파일 지지대
152 : 시트 파일 연결 띠철판 153 : 임시 지보
150 : 토압 지지대 160 : 터널 지보
171 : 1차 모래채움 그라우팅 172 : 2차 여굴채움 그라우팅
A: Propulsion port B: Reach port
10: Hydraulic jack for propulsion 100: Sheet pile
110: Linear guide square tube 111: Linear retaining connector
112: Propulsion push bar 120: Upper ground disturbance section
121: Rotating saw blade for upper ground disturbance 122: Upper power generation unit
123: upper motion transmission unit 130: side ground disturbance unit
131: Rotating saw blade for side ground disturbance 132: Side power generation unit
133: side motion transmission unit 151: sheet pile support
152: Sheet pile connection steel plate 153: Temporary support
150: earth pressure support 160: tunnel support
171: 1st sand filling grouting 172: 2nd overburden filling grouting

Claims (4)

삭제delete 지하 구조물인 터널의 내벽체에 순차적으로 압입 또는 추진되어 상기 터널의 내벽체 상부와 측부에 시공되는 복수 개의 시트 파일(SHEET PIlE);
추진용 유압잭을 작용으로 상기 터널의 추진구에서 도달구까지 직선 또는 곡선 이동하며, 토석의 굴착과 상기 시트 파일의 설치가 가능하게 유도하는 복수 개의 선형 유도 각형관;
상기 선형 유도 각형관의 상부에 결합하며, 상기 선형 유도 각형관의 압입 또는 추진 시 해당 위치에서 막장의 지반 교란이 진행되게 하는 상부 지반 교란부;
상기 선형 유도 각형관의 측부에 결합하며, 상기 선형 유도 각형관의 압입 또는 추진 시 해당 위치에서 막장의 지반 교란이 진행되게 하는 측부 지반 교란부;
상기 시트 파일들과 연결되고 상기 시트 파일들을 지지하는 복수 개의 토압 지지대; 및
상기 토압 지지대들과 연결되고 상기 토압 지지대들을 지지하는 복수 개의 터널 지보를 포함하며,
상기 선형 유도 각형관이 상기 도달구에서 회수되어 재사용되고,
상기 상부 지반 교란부와 상기 측부 지반 교란부 모두는,
상기 선형 유도 각형관의 상부와 측부의 단부보다 일부분이 노출되게 마련되며, 상기 선형 유도 각형관의 압입 또는 추진 시 막장의 지반 교란이 진행되게 하는 지반 교란용 회전 톱날;
상기 지반 교란용 회전 톱날을 회전시키기 위한 동력을 발생시키는 동력 발생부; 및
상기 동력 발생부에서 발생한 동력이 상기 지반 교란용 회전 톱날의 회전운동으로 전달되게 상기 동력 발생부와 상기 지반 교란용 회전 톱날을 연결해서 운동을 전달하는 운동 전달부를 포함하는 것을 특징으로 하는 비개착 터널용 굴착시스템.
A plurality of sheet piles (SHEET PILE) sequentially press-fitted or pushed into the inner wall of a tunnel, which is an underground structure, and constructed on the upper and side parts of the inner wall of the tunnel;
A plurality of linear guide rectangular pipes that move in a straight line or curve from the thrust port of the tunnel to the arrival port by the action of a hydraulic jack for propulsion and guide the excavation of earth and stone and the installation of the sheet pile;
An upper ground disturbance unit that is coupled to the upper part of the linear guide rectangular pipe and causes ground disturbance to proceed at the corresponding position when the linear guide rectangular pipe is pressed in or pushed in;
A side ground disturbance unit coupled to a side of the linear guide rectangular pipe and causing ground disturbance in the corresponding position when the linear guide rectangular pipe is pressed in or pushed in;
A plurality of earth pressure supports connected to the sheet piles and supporting the sheet piles; and
It is connected to the earth pressure supports and includes a plurality of tunnel supports supporting the earth pressure supports,
The linear guide square tube is recovered from the arrival port and reused,
Both the upper ground disturbance unit and the side ground disturbance unit,
A rotating saw blade for ground disturbance, which is provided to expose a portion of the upper and side ends of the linear guide rectangular pipe, and which causes ground disturbance to proceed when the linear guide rectangular pipe is pressed in or pushed in;
a power generator that generates power to rotate the ground disturbance rotary saw blade; and
A trenchless tunnel comprising a motion transmission unit that connects the power generation unit and the ground disturbance rotary saw blade to transmit the motion so that the power generated by the power generator is transmitted to the rotational movement of the ground disturbance rotary saw blade. For excavation system.
지하 구조물인 터널의 내벽체에 순차적으로 압입 또는 추진되어 상기 터널의 내벽체 상부와 측부에 시공되는 복수 개의 시트 파일(SHEET PIlE);
추진용 유압잭을 작용으로 상기 터널의 추진구에서 도달구까지 직선 또는 곡선 이동하며, 토석의 굴착과 상기 시트 파일의 설치가 가능하게 유도하는 복수 개의 선형 유도 각형관;
상기 선형 유도 각형관의 상부에 결합하며, 상기 선형 유도 각형관의 압입 또는 추진 시 해당 위치에서 막장의 지반 교란이 진행되게 하는 상부 지반 교란부;
상기 선형 유도 각형관의 측부에 결합하며, 상기 선형 유도 각형관의 압입 또는 추진 시 해당 위치에서 막장의 지반 교란이 진행되게 하는 측부 지반 교란부;
상기 시트 파일들과 연결되고 상기 시트 파일들을 지지하는 복수 개의 토압 지지대; 및
상기 토압 지지대들과 연결되고 상기 토압 지지대들을 지지하는 복수 개의 터널 지보를 포함하며,
상기 선형 유도 각형관이 상기 도달구에서 회수되어 재사용되고,
상기 시트 파일은 상기 선형 유도 각형관 내에서 시트 파일 지지대에 의해 지지되며,
상기 시트 파일 지지대와 상기 시트 파일 사이에는 상기 시트 파일을 연결하는 시트 파일 연결 띠철판이 마련되며,
상기 시트 파일 연결 띠철판이 임시 지보에 의해 지지되며,
상기 선형 유도 각형관의 내벽에는 선형 유지를 위한 선형 유지 커넥터가 마련되며,
상기 선형 유도 각형관의 내벽에는 상기 선형 유도 각형관을 압입 또는 추진하기 위한 추진 밀대가 마련되며,
상기 시트 파일은 높이(H) 162~170mm, 폭(W) 650~750mm, 두께(T) 12~20mm로 제작되며,
상기 시트 파일의 설치 직후, 상기 시트 파일의 외부에 1차 모래채움 그라우팅이 수행된 다음, 상기 1차 모래채움 그라우팅의 외부로 2차 여굴채움 그라우팅이 수행되는 것을 특징으로 하는 비개착 터널용 굴착시스템.
A plurality of sheet piles (SHEET PILE) sequentially press-fitted or pushed into the inner wall of a tunnel, which is an underground structure, and constructed on the upper and side parts of the inner wall of the tunnel;
A plurality of linear guide rectangular pipes that move in a straight line or curve from the thrust port of the tunnel to the arrival port by the action of a hydraulic jack for propulsion and guide the excavation of earth and stone and the installation of the sheet pile;
An upper ground disturbance unit that is coupled to the upper part of the linear guide rectangular pipe and causes ground disturbance to proceed at the corresponding position when the linear guide rectangular pipe is pressed in or pushed in;
A side ground disturbance unit coupled to a side of the linear guide rectangular pipe and causing ground disturbance in the corresponding position when the linear guide rectangular pipe is pressed in or pushed in;
A plurality of earth pressure supports connected to the sheet piles and supporting the sheet piles; and
It is connected to the earth pressure supports and includes a plurality of tunnel supports supporting the earth pressure supports,
The linear guide square tube is recovered from the arrival port and reused,
The sheet pile is supported by a sheet pile support within the linear guide rectangular pipe,
A sheet pile connecting steel plate is provided between the sheet pile support and the sheet pile,
The sheet pile connecting steel plate is supported by temporary supports,
A linear maintenance connector is provided on the inner wall of the linear guide rectangular pipe to maintain the linearity,
A propulsion pusher is provided on the inner wall of the linear guide rectangular pipe to press-fit or propel the linear guide rectangular pipe,
The sheet pile is manufactured with a height (H) of 162 to 170 mm, a width (W) of 650 to 750 mm, and a thickness (T) of 12 to 20 mm.
Immediately after installation of the sheet pile, primary sand filling grouting is performed on the outside of the sheet pile, and then secondary overburden filling grouting is performed on the outside of the primary sand filling grouting. An excavation system for a trenchless tunnel. .
삭제delete
KR1020230097181A 2023-07-26 2023-07-26 Sheet non excavation method for drilling a tunnel having a file reinforcing structure KR102608601B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020230097181A KR102608601B1 (en) 2023-07-26 2023-07-26 Sheet non excavation method for drilling a tunnel having a file reinforcing structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020230097181A KR102608601B1 (en) 2023-07-26 2023-07-26 Sheet non excavation method for drilling a tunnel having a file reinforcing structure

Publications (1)

Publication Number Publication Date
KR102608601B1 true KR102608601B1 (en) 2023-12-01

Family

ID=89124374

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020230097181A KR102608601B1 (en) 2023-07-26 2023-07-26 Sheet non excavation method for drilling a tunnel having a file reinforcing structure

Country Status (1)

Country Link
KR (1) KR102608601B1 (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030072109A (en) 2002-03-05 2003-09-13 주식회사 하이닉스반도체 Method of fabricating high voltage semiconductor device
KR20090011442A (en) * 2007-07-26 2009-02-02 (주)동명기술공단종합건축사사무소 Tunnel boring method using sheet pile and tunnel structure therof
KR20100129839A (en) * 2009-06-02 2010-12-10 위성배 The construction method of shield tunneling

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030072109A (en) 2002-03-05 2003-09-13 주식회사 하이닉스반도체 Method of fabricating high voltage semiconductor device
KR20090011442A (en) * 2007-07-26 2009-02-02 (주)동명기술공단종합건축사사무소 Tunnel boring method using sheet pile and tunnel structure therof
KR20100129839A (en) * 2009-06-02 2010-12-10 위성배 The construction method of shield tunneling

Similar Documents

Publication Publication Date Title
US20150191877A1 (en) Method for building structures, particularly passages under operating railways or the like
KR101179778B1 (en) Method for constructing underground structure
CN106930321B (en) The construction method of underground structure is built in a kind of stake of pipe-jacking with large diameter combination hole
CN110043264B (en) Construction method for jacking prefabricated rectangular vertical shaft structural type
CN109555540B (en) Tunnel type prestressed pipe curtain structure and construction method
CN101761068A (en) Box-raft pressure-bearing type foundation underpinning and construction reinforcing method for tunnel across pile foundation of bridge above river
JP2006322222A (en) Construction method of large-sectional tunnel
KR100991630B1 (en) A container sleeve push ahead type tunnel manufacture method
CN109555535B (en) Lower-way truss type prestressed pipe curtain structure and construction method
KR101468613B1 (en) Underground structure construction method using the moveable temporary supporting frame
KR102608601B1 (en) Sheet non excavation method for drilling a tunnel having a file reinforcing structure
CN114635716B (en) Pipe shed advanced supporting method with built-in section steel and application thereof
JP7177233B2 (en) Start Reaction Force Structure and Method for Concrete Box or Open Shield Machine
CN113958322B (en) Tunnel excavation method under existing subway line
KR101479267B1 (en) Method for constructing tunnel by using pipe
KR102289576B1 (en) Top-down type underground structure construction method using earth support plate
JP2000291398A (en) Underground structure and construction method therefor
JPH07331998A (en) Constructing method of rock cavern
CN207470195U (en) Xia Lu purlins form prestressed pipe curtain system
JP4705467B2 (en) Construction method of underground structure
CN109339827A (en) The excavating construction method of multi-layer underground structure
KR102048831B1 (en) Non-excavation type tunnel structure using steel pipe loof and leading pipe and method of constructing thereof
KR20160103723A (en) The Construction Method and Structure of Non-excavation tunnel what press in extruding Steel pipe by Arch type Precast Upperslab
CN218969976U (en) Pushing structure suitable for pushing method construction continuous wall
KR102572805B1 (en) Underground structure using steel pipe form and trenchless construction method of the same

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant