JP2012036661A - Method for constructing underground tank - Google Patents

Method for constructing underground tank Download PDF

Info

Publication number
JP2012036661A
JP2012036661A JP2010178692A JP2010178692A JP2012036661A JP 2012036661 A JP2012036661 A JP 2012036661A JP 2010178692 A JP2010178692 A JP 2010178692A JP 2010178692 A JP2010178692 A JP 2010178692A JP 2012036661 A JP2012036661 A JP 2012036661A
Authority
JP
Japan
Prior art keywords
side wall
construction
bottom plate
roof
underground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2010178692A
Other languages
Japanese (ja)
Other versions
JP4702674B1 (en
Inventor
Mitsuo Nagashima
三雄 永島
Masaki Wakabayashi
雅樹 若林
Masanori Tsuchiya
雅徳 土屋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2010178692A priority Critical patent/JP4702674B1/en
Application granted granted Critical
Publication of JP4702674B1 publication Critical patent/JP4702674B1/en
Publication of JP2012036661A publication Critical patent/JP2012036661A/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

PROBLEM TO BE SOLVED: To provide a method for constructing an underground tank capable of eliminating the need for a site to store surplus soil for an embankment and shortening a construction period.SOLUTION: A method for constructing an underground tank comprises: an underground continuous wall construction process to construct a cylindrical underground continuous wall 5 in the ground G; a side wall upper section construction process to construct a side wall upper section 31 in a manner that protrudes upward inside the underground continuous wall 5; an inside excavation process to excavate inside the underground continuous wall 5 after the side wall upper section construction process and to heap surplus soil generated by excavation around the side wall upper section 31; a bottom slab construction process to construct a bottom slab 2; a side wall lower section construction process to construct a side wall lower section 32 and integrate the side wall lower section 32 and the side wall upper section 31; and a roof installation process to install a roof 4 on an upper edge section 3a of a side wall 3.

Description

本発明は、例えば、液化天然ガス等の低温液体の貯蔵に用いられる地下タンクの施工方法に関する。   The present invention relates to a method for constructing an underground tank used for storing a low-temperature liquid such as liquefied natural gas.

従来より、液化天然ガス(LNG)等の低温液体の貯蔵タンクとして、底版と、底版の周囲に沿って構築された側壁と、側壁の上部を覆う屋根を備える地下タンクが使用されている。このような地下タンクは、掘削された地盤に建設されるため、その建設により地下タンクの容量と同程度の残土が生じている。   2. Description of the Related Art Conventionally, as a storage tank for a low-temperature liquid such as liquefied natural gas (LNG), an underground tank having a bottom plate, a side wall constructed along the periphery of the bottom plate, and a roof covering the top of the side wall has been used. Since such an underground tank is constructed on the excavated ground, the construction produces residual soil having the same capacity as the underground tank.

近年では、側壁上部が、地下タンクが構築される前の地盤面よりも上方に位置し、この側壁上部の外周に盛土を行うことで、地中に埋設された形態とした地下タンクが提案され、建設されている(例えば、特許文献1および2参照)。このような地下タンクを建設する際に、側壁上部の外周の盛土に、掘削で生じた残土の一部を使用することで、残土の処分量を減らすことができる。   In recent years, an underground tank has been proposed in which the upper part of the side wall is located above the ground surface before the underground tank is constructed, and embedding is performed on the outer periphery of the upper part of the side wall, thereby embedding in the ground. (See, for example, Patent Documents 1 and 2). When constructing such an underground tank, the amount of disposal of the remaining soil can be reduced by using a part of the remaining soil generated by excavation for the embankment on the outer periphery of the upper side wall.

特開2010−53891号公報JP 2010-53891 A 特開2009−127263号公報JP 2009-127263 A

このような掘削で生じた残土を側壁上部の外周に盛土する地下タンクの施工方法では、側壁の上部を構築した後に盛土を行っている。つまり、一般的には、盛土は地下タンク本体が完成した後に行われている。
このため、地盤が掘削されてから地下タンク本体が完成するまでの期間中(概ね1年〜1年半)、盛土に使用する残土を保管する必要があり、残土を保管するための用地の確保や、残土の管理に労力がかかっている。
特に、建設地が狭隘な場合には、建設地外に残土を仮置きする用地が必要となるため、この用地の確保にコストがかかるとともに、その手続も必要となり手間がかかる。さらに、残土を仮置きする用地と地下タンク建設地との間の残土の運搬に時間(工期)や費用がかかるという問題もある。
In the construction method of the underground tank which fills the residual soil generated by such excavation on the outer periphery of the upper part of the side wall, the embankment is performed after the upper part of the side wall is constructed. In other words, in general, embankment is performed after the underground tank body is completed.
For this reason, during the period from when the ground is excavated to the completion of the underground tank body (approximately one to one and a half years), it is necessary to store the remaining soil used for embankment, and secure a site for storing the remaining soil In addition, it takes effort to manage the remaining soil.
In particular, when the construction site is small, a site for temporarily placing the remaining soil outside the construction site is required, so that it takes a cost to secure this site and requires a procedure for it. Furthermore, there is a problem that it takes time (construction period) and cost to transport the remaining soil between the site for temporarily placing the remaining soil and the underground tank construction site.

本発明は、上述する問題点に鑑みてなされたもので、盛土用の残土を保管するための用地を不要とすることができ、工期を短縮することができる地下タンクの施工方法を提供することを目的とする。   The present invention has been made in view of the above-described problems, and provides a construction method for an underground tank that can eliminate the site for storing the remaining soil for embankment and can shorten the construction period. With the goal.

上記目的を達成するため、本発明に係る地下タンクの施工方法は、底版と、該底版の周囲に沿って構築された円筒状の側壁と、該側壁の上部を覆う屋根と、を備え、前記底版と前記側壁の下部が地中に埋設されて、前記側壁の上部の周囲が盛土された地下タンクの施工方法であって、地盤中に円筒状の地中連続壁を構築する地中連続壁構築工程と、前記地中連続壁の内側で上方へ突出する形態に前記側壁の上部を構築する側壁上部構築工程と、該側壁上部構築工程の後に前記地中連続壁の内部を掘削するとともに掘削で生じた残土の一部を前記側壁の上部の周囲に盛土する内部掘削工程と、前記底版を構築する底版構築工程と、前記側壁の下部を構築し該側壁の下部を前記側壁の上部と一体化させる側壁下部構築工程と、前記側壁の上端部に屋根を設置する屋根設置工程と、を備えることを特徴とする。   In order to achieve the above object, an underground tank construction method according to the present invention includes a bottom plate, a cylindrical side wall constructed around the bottom plate, and a roof covering an upper portion of the side wall, A method for constructing an underground tank in which a bottom plate and a lower part of the side wall are buried in the ground, and a periphery of the upper part of the side wall is embanked, and a continuous underground wall for constructing a cylindrical underground continuous wall in the ground A construction step, a sidewall upper construction step for constructing an upper portion of the side wall in a form protruding upward inside the underground continuous wall, and excavating and excavating the interior of the underground continuous wall after the sidewall upper construction step An internal excavation step of embedding a part of the remaining soil generated in the periphery of the upper portion of the side wall, a bottom plate building step of building the bottom plate, a lower portion of the side wall, and a lower portion of the side wall integrated with the upper portion of the side wall On the side wall lower part construction process and the upper end of the side wall Characterized in that it comprises a roof installation step of installing the roots, the.

本発明では、側壁上部構築工程の後に内部掘削工程を行うため、地中連続壁の内部を掘削して生じた残土の一部をそのまま側壁の上部の外周に盛土することができる。これにより、盛土に使用する残土を保管する必要がなく、残土を保管する用地の確保や残土の管理などの必要がないため、残土の保管にかかるコストや労力を削減することができる。
また、内部掘削と共にその残土をそのまま盛土することができるため、地下タンクが構築された後に盛土を行う従来の地下タンクの施工方法と比べて、工期を短縮することができる。
In the present invention, since the internal excavation process is performed after the side wall upper construction process, a part of the residual soil generated by excavating the inside of the underground continuous wall can be directly filled on the outer periphery of the upper part of the side wall. Accordingly, it is not necessary to store the remaining soil used for the embankment, and it is not necessary to secure a site for storing the remaining soil or to manage the remaining soil, so that it is possible to reduce costs and labor required for storing the remaining soil.
Moreover, since the remaining soil can be embanked as it is with the internal excavation, the construction period can be shortened as compared with a conventional underground tank construction method in which embankment is performed after the underground tank is constructed.

また、本発明に係る地下タンクの施工方法では、前記内部掘削工程の後に前記底版構築工程を行い該底版構築工程の後に前記側壁下部構築工程を行い、該側壁下部構築工程では、前記側壁の下部を下方から上方に向って段階的に構築し、前記屋根設置工程では、前記側壁下部構築工程と並行して前記底版上で前記屋根を形成し、前記側壁下部構築工程の後に、前記屋根を上昇させて前記側壁の上端部に設置してもよい。
このように、屋根設置工程では、側壁下部構築工程と並行して底版上で屋根を形成し、側壁下部構築工程の後に、屋根を上昇させて側壁の上端部に設置することにより、側壁下部の構築と屋根の形成を同時に行うことができるため、工期を短縮することができる。
In the underground tank construction method according to the present invention, the bottom slab construction process is performed after the internal excavation process, and the side wall lower construction process is performed after the bottom slab construction process. In the roof installation process, the roof is formed on the bottom plate in parallel with the side wall lower part construction process, and the roof is raised after the side wall lower part construction process. You may let it be installed in the upper end part of the said side wall.
In this way, in the roof installation process, the roof is formed on the bottom plate in parallel with the side wall lower part construction process, and after the side wall lower part construction process, the roof is raised and installed at the upper end of the side wall. Since construction and roof formation can be performed simultaneously, the construction period can be shortened.

また、本発明に係る地下タンクの施工方法では、前記側壁下部構築工程では、前記内部掘削工程と並行して前記側壁の下部を上方から下方に向って段階的に構築し、前記側壁下部構築工程の後に前記底版構築工程を行ってもよい。
このように、側壁下部構築工程では、内部掘削工程と並行して側壁の下部を上方から下方に向って段階的に構築することにより、内部掘削工程と同時に側壁の下部を構築することができるため、工期を短縮することができる。
Further, in the underground tank construction method according to the present invention, in the side wall lower part construction step, the lower part of the side wall is constructed in stages from the top to the bottom in parallel with the internal excavation step, and the side wall lower part construction step The bottom plate construction step may be performed after the step.
Thus, in the side wall lower part construction process, the lower part of the side wall can be constructed at the same time as the internal excavation process by constructing the lower part of the side wall stepwise from the upper side in parallel with the internal excavation process. The construction period can be shortened.

本発明によれば、地中連続壁の内部を掘削して生じた残土の一部をそのまま側壁上部の外周に盛土することができることにより、盛土に使用する残土を保管する必要がなく、残土を保管する用地の確保や残土の管理などの必要がないため、残土の保管にかかるコストや労力を削減することができる。
また、内部掘削と共にその残土を盛土することができるため、地下タンクが構築された後に盛土を行う従来の地下タンクの施工方法と比べて、工期を短縮することができる。
According to the present invention, a part of the remaining soil generated by excavating the inside of the underground continuous wall can be directly embanked on the outer periphery of the upper portion of the side wall, so there is no need to store the remaining soil used for embankment. Since there is no need to secure a site for storage and management of the remaining soil, it is possible to reduce costs and labor for storing the remaining soil.
Moreover, since the remaining soil can be embanked together with the internal excavation, the construction period can be shortened compared with the conventional underground tank construction method in which the embankment is performed after the underground tank is constructed.

本発明の実施形態による地下タンクの一例を示す図である。It is a figure which shows an example of the underground tank by embodiment of this invention. 地盤改良工程を説明する図である。It is a figure explaining a ground improvement process. 地中連続壁構築工程を説明する図である。It is a figure explaining an underground continuous wall construction process. 側壁上部構築工程を説明する図である。It is a figure explaining a side wall upper part construction process. 内部掘削工程を説明する図である。It is a figure explaining an internal excavation process. 底版構築工程を説明する図である。It is a figure explaining a bottom plate construction process. 側壁下部構築工程を説明する図である。It is a figure explaining a side wall lower part construction process. 屋根設置工程を説明する図である。It is a figure explaining a roof installation process.

以下、本発明の実施形態による地下タンクの施工方法について、図1乃至図8に基づいて説明する。
(地下タンク)
図1に示すように、本実施形態による地下タンク1は、例えば、LNG貯蔵タンクとして使用されるものであり、地盤G面より下方に配された平面視略円形状の底版2と、略円筒状の側壁3と、側壁3の上端部3aに支持されたドーム状の屋根4と、を備えている。
Hereinafter, the construction method of the underground tank by embodiment of this invention is demonstrated based on FIG. 1 thru | or FIG.
(Underground tank)
As shown in FIG. 1, the underground tank 1 according to the present embodiment is used as, for example, an LNG storage tank, and has a bottom plate 2 having a substantially circular shape in plan view disposed below the ground G surface, and a substantially cylindrical shape. And a dome-shaped roof 4 supported by the upper end 3 a of the side wall 3.

また、側壁3の下端部3b側の外周の地盤Gには、側壁3の外周面に沿った形状で平面視円環状の地中連続壁5が設けられていて、地中連続壁5の外周の地盤Gには、地盤改良体6が施工されている。また、地中連続壁5と地盤改良体6との間には、LNGの冷熱が底版2を通して地盤Gに伝わることで地盤Gが凍結することを防止する底部ヒーター12が設置されている。   Further, the ground G on the outer periphery of the side wall 3 on the lower end 3b side is provided with an underground continuous wall 5 having a shape along the outer peripheral surface of the side wall 3 and having an annular shape in plan view. The ground improvement body 6 is constructed on the ground G. In addition, a bottom heater 12 is installed between the underground continuous wall 5 and the ground improvement body 6 to prevent the ground G from freezing as the cold heat of LNG is transmitted to the ground G through the bottom plate 2.

底版2は、鉄筋コンクリート造で、掘削された地盤G上に設けられた砕石層11の上部に構築されている。底版2の内部には、地下タンク1内の温度調整を行う底部ヒーター12が設置されている。   The bottom slab 2 is made of reinforced concrete, and is constructed on the crushed stone layer 11 provided on the ground G excavated. A bottom heater 12 that adjusts the temperature in the underground tank 1 is installed inside the bottom plate 2.

側壁3は、鉄筋コンクリート造で、下端部3bが底版2の外縁部2aに剛に接合されている。つまり、底版2および側壁3は有底円筒状に構成されている。
この地下タンク1が施工される前の地盤面を施工前地盤面Gaとすると、側壁3は上部31が施工前地盤面Gaの上方に位置し、下部32が施工前地盤面Gaの下方に位置している。側壁3の上部31の外周は、施工前地盤面Gaより上側に盛土Gcが施されている。このため、地下タンク1は地下に配された構成となっている。
ここで、側壁3の上部31を側壁上部31とし、側壁3の下部32を側壁下部32として以下説明する。
The side wall 3 is made of reinforced concrete, and the lower end 3 b is rigidly joined to the outer edge 2 a of the bottom plate 2. That is, the bottom plate 2 and the side wall 3 are formed in a bottomed cylindrical shape.
Assuming that the ground surface before the underground tank 1 is constructed is the pre-construction ground surface Ga, the side wall 3 has an upper portion 31 located above the pre-construction ground surface Ga and a lower portion 32 located below the pre-construction ground surface Ga. is doing. The outer periphery of the upper portion 31 of the side wall 3 is provided with embankment Gc above the ground surface Ga before construction. For this reason, the underground tank 1 has a structure arranged underground.
Here, the upper part 31 of the side wall 3 will be described as the side wall upper part 31 and the lower part 32 of the side wall 3 will be described as the side wall lower part 32.

地中連続壁5は、土留めとして地盤Gの崩落を防ぐ機能や止水機能を備えている。地中連続壁5は、地下タンク1の底版2よりもさらに深く構築されており、下端部5bは難透水層(洪積粘性土層)13まで達している。
地中連続壁5は、例えば、コンクリートなどで構築されている。
地盤改良体6は、例えば、サンドコンパクションパイル工法などにより形成されていて、地下タンク1の周辺の地盤Gの液状化対策として設けられている。
The underground continuous wall 5 has a function of preventing the ground G from collapsing and a water stop function as a soil retaining. The underground continuous wall 5 is constructed deeper than the bottom slab 2 of the underground tank 1, and the lower end portion 5 b reaches the hardly permeable layer (cold clay layer) 13.
The underground continuous wall 5 is constructed of, for example, concrete.
The ground improvement body 6 is formed by, for example, a sand compaction pile method or the like, and is provided as a countermeasure against liquefaction of the ground G around the underground tank 1.

屋根4は、平面視において円形状に形成され、側壁3の上端部3aに架設される複数の骨組材15と、骨組材15の下側に配される保冷材16と、骨組材15の上側に配される屋根材17と、を備えている。
側壁3の上端部3aには、側壁3に骨組材15を固定するためのリングプレート19が設置されている。リングプレート19は、側壁3の上端部3aに沿った平面視円環状の円錐台状に鋼板で形成されている。
なお、屋根4の構造は、上記以外の構造であってもよい。
底版2と側壁3との内面には、図示しない保冷材と、この保冷材の内側に取り付けられた例えば、ステンレス薄鋼板製のメンブレン材と、を備える保冷層(内槽)18が形成されている。
The roof 4 is formed in a circular shape in plan view, and includes a plurality of frame members 15 installed on the upper end portion 3 a of the side wall 3, a cold insulation material 16 disposed below the frame material 15, and an upper side of the frame material 15. And a roofing material 17 arranged on the roof.
A ring plate 19 for fixing the frame material 15 to the side wall 3 is installed at the upper end portion 3 a of the side wall 3. The ring plate 19 is formed of a steel plate in a circular truncated cone shape along the upper end portion 3 a of the side wall 3.
The structure of the roof 4 may be a structure other than the above.
On the inner surfaces of the bottom plate 2 and the side wall 3, a cold insulation layer (inner tub) 18 including a cold insulation material (not shown) and a membrane material made of, for example, a stainless steel sheet attached inside the cold insulation material is formed. Yes.

(地下タンクの施工方法)
次に、上述した地下タンク1の施工方法について図面を用いて説明する。
本実施形態による地下タンクの施工方法は、図1に示す地下タンク1が構築される地中連続壁5の内側の地盤Gの掘削に先行して、側壁上部31を構築するものである。
(地盤改良工程)
まず、図2に示すように、地下タンク1外周側の地盤Gの地盤改良を行う。
この地盤改良は、例えば、サンドコンパクションパイル工法などにより行う。地盤改良体6の形状や大きさは、地下タンク1の形状や地盤Gの強度を考慮して決定する。
(Underground tank construction method)
Next, the construction method of the underground tank 1 mentioned above is demonstrated using drawing.
The construction method of the underground tank according to the present embodiment constructs the side wall upper portion 31 prior to excavation of the ground G inside the underground continuous wall 5 in which the underground tank 1 shown in FIG. 1 is constructed.
(Ground improvement process)
First, as shown in FIG. 2, the ground of the ground G on the outer periphery side of the underground tank 1 is improved.
This ground improvement is performed by, for example, a sand compaction pile method. The shape and size of the ground improvement body 6 are determined in consideration of the shape of the underground tank 1 and the strength of the ground G.

(地中連続壁設置工程)
続いて、地盤改良体6の内側に、平面視円環状の地中連続壁5を構築する。
図3に示すように、地中連続壁5の構築は、地下タンク1の設置予定箇所の周囲に沿って地中連続壁掘削機で掘削溝を設け、その溝内に鉄筋を配してコンクリートを打設する周知技術により構築する。このとき、下端部5bが難透水層13に達するように地中連続壁5を構築する。
(Underground continuous wall installation process)
Subsequently, the underground continuous wall 5 having an annular shape in plan view is constructed inside the ground improvement body 6.
As shown in FIG. 3, the underground continuous wall 5 is constructed by providing an underground continuous wall excavator along the periphery of the place where the underground tank 1 is to be installed and providing a reinforcing groove in the groove to provide concrete. It is constructed by a well-known technique for setting up. At this time, the underground continuous wall 5 is constructed so that the lower end 5b reaches the hardly water-permeable layer 13.

(側壁上部構築工程)
続いて、図4に示すように、地中連続壁5の内周側に地中連続壁5より上方へ突出する形態に側壁上部31を構築する。
側壁上部31は、その形状に沿って鉄筋を配し、コンクリートを打設して構築する。このように構築された側壁上部31は、円筒状に形成され、地中連続壁5に支持されている。
側壁上部31を地中連続壁5に支持させるには、例えば、側壁上部31の外周に側壁3に固定された張り出し部(不図示)を設け、この張り出し部を地中連続壁5の上端部に引っ掛けてもよく、鉄筋(不図示)で側壁上部31と地中連続壁5とを固定してもよい。
(Sidewall construction process)
Then, as shown in FIG. 4, the side wall upper part 31 is constructed in the form which protrudes upward from the underground continuous wall 5 on the inner peripheral side of the underground continuous wall 5.
The side wall upper portion 31 is constructed by arranging reinforcing bars along the shape and placing concrete. The side wall upper part 31 constructed in this way is formed in a cylindrical shape and supported by the underground continuous wall 5.
In order to support the side wall upper portion 31 on the underground continuous wall 5, for example, an overhang portion (not shown) fixed to the side wall 3 is provided on the outer periphery of the side wall upper portion 31, and this overhang portion is the upper end portion of the underground continuous wall 5. The side wall upper portion 31 and the underground continuous wall 5 may be fixed by a reinforcing bar (not shown).

(内部掘削工程)
続いて、図5に示すように、地下タンク1の内部の地盤Gの掘削を行う。
この工程では、地中連続壁5の内側を、砕石層11(図1参照)を設置可能な深さまで掘削する。そして、掘削によって発生した残土の一部を直接側壁上部31の外周に運搬し、側壁上部31の外方に盛土Gcを行う。なお、盛土量を超える分の残土については、建設地の他の場所で使用したり、外部へ搬出して処分したりする。
このとき、側壁上部31は、盛土Gcによって外方から土圧を受けるが、平面視リング状に形成されていることにより、土圧のような外方からの荷重に対して強固な構造となるため、安定した状態に保たれている。
なお、盛土を行う時期は、内部掘削工程の中で適宜選択される。一般的には、内部掘削工程の初期に行われるが、残土が盛土に適さない土質の場合は内部掘削工程の中期や後期で行われることもある。
(Internal drilling process)
Subsequently, as shown in FIG. 5, the ground G inside the underground tank 1 is excavated.
In this step, the inside of the underground continuous wall 5 is excavated to a depth where the crushed stone layer 11 (see FIG. 1) can be installed. Then, a part of the remaining soil generated by excavation is directly conveyed to the outer periphery of the side wall upper portion 31, and embankment Gc is performed outside the side wall upper portion 31. In addition, the remaining soil that exceeds the amount of embankment is used elsewhere in the construction site, or taken out and disposed of outside.
At this time, the side wall upper portion 31 receives the earth pressure from the outside by the embankment Gc, but has a strong structure against an outside load such as earth pressure by being formed in a ring shape in plan view. Therefore, it is kept in a stable state.
In addition, the time for embankment is appropriately selected in the internal excavation process. Generally, it is performed at the initial stage of the internal excavation process, but when the remaining soil is not suitable for embankment, it may be performed in the middle or later stage of the internal excavation process.

(底版構築工程)
続いて、図6に示すように、内部掘削工程で掘削された地盤G上に底版2を構築する。 底版2の構築は、地盤G上に砕石層11を配し、その上部に鉄筋を配してコンクリートを打設することで底版2を構築する。このとき、底版2に底部ヒーター12を設置する。
(Bottom plate construction process)
Subsequently, as shown in FIG. 6, the bottom slab 2 is constructed on the ground G excavated in the internal excavation process. The bottom plate 2 is constructed by placing the crushed stone layer 11 on the ground G, placing a reinforcing bar on the top thereof, and placing concrete into the bottom plate 2. At this time, the bottom heater 12 is installed on the bottom plate 2.

(側壁下部構築工程)
続いて、図7に示すように、側壁下部32を構築する。
側壁下部32は、底版2と一体化させ、下方から上方に向って、所定高さ毎に鉄筋を配してコンクリートを順次打ち継いで打設することで構築する。
本実施形態では、側壁下部32は、底版2の上部に構築されるハンチ部32aと、ハンチ部32aの上部に構築される第1側壁下部32bと、第1側壁下部32bの上部に構築されるとともに側壁上部31と連結される第2側壁下部32cと、から構成されている。
このため、ハンチ部32a、第1側壁下部32b、第2側壁下部32cの順に構築し、第2側壁下部32cを側壁上部31と連結させて一体化させる。この第2側壁下部32cと側壁上部31とを一体化させる具体的な方法としては、例えば、第2側壁下部32cのコンクリート打設に際して、そのコンクリート天端を側壁上部31の下端より若干下げて打設し、第2側壁下部32cと側壁上部31との間に形成された若干の隙間に、無収縮コンクリートを充填する方法があり、この方法により第2側壁下部32cと側壁上部31との一体化を図ることができる。
これにより、側壁下部32が完成するとともに側壁3が完成する。
(Side wall bottom construction process)
Then, as shown in FIG. 7, the side wall lower part 32 is constructed.
The side wall lower part 32 is constructed by integrating with the bottom plate 2 and arranging the reinforcing bars at predetermined heights from the lower side to the upper side and successively casting concrete.
In this embodiment, the side wall lower part 32 is constructed on the upper part of the first side wall lower part 32b, the first side wall lower part 32b constructed on the upper part of the haunch part 32a, the upper part of the haunch part 32a. A second side wall lower portion 32c connected to the side wall upper portion 31 is also included.
For this reason, the hunch 32a, the first side wall lower part 32b, and the second side wall lower part 32c are constructed in this order, and the second side wall lower part 32c is connected to the side wall upper part 31 and integrated. As a specific method for integrating the second side wall lower portion 32c and the side wall upper portion 31, for example, when placing the concrete on the second side wall lower portion 32c, the concrete top end is slightly lowered from the lower end of the side wall upper portion 31 and placed. There is a method of filling non-shrinkage concrete into a slight gap formed between the second side wall lower portion 32 c and the side wall upper portion 31. By this method, the second side wall lower portion 32 c and the side wall upper portion 31 are integrated. Can be achieved.
Thereby, the side wall lower part 32 is completed and the side wall 3 is completed.

また、この側壁下部構築工程と前後または並行して、側壁3の上端部3aに、リングプレート19(図1参照)を取り付ける。リングプレート19を取り付ける際に、側壁3の上端部3aにコンクリートで形成された側壁頂部材(不図示)を側壁3の上端部3aと一体化するように設置し、この側壁頂部材にリングプレート19を支持させてもよい。   In addition, a ring plate 19 (see FIG. 1) is attached to the upper end portion 3a of the side wall 3 in parallel with the side wall lower portion construction step. When the ring plate 19 is attached, a side wall top member (not shown) made of concrete is installed on the upper end portion 3 a of the side wall 3 so as to be integrated with the upper end portion 3 a of the side wall 3. 19 may be supported.

(屋根設置工程)
続いて、屋根4を設置する。
まず、図8に示すように、底版2上で屋根4を組み立てる。屋根4の組み立ては、骨組材15を組み立てた後に、この骨組材15に保冷材16および屋根材17を取り付ける。この屋根組立工程は、側壁下部構築工程と並行して行ってもよいし、側壁下部構築工程が完了してから行ってもよい。
次に、屋根4を、例えば、エアリフトやジャッキアップ、クレーン等による吊り上げなどの上昇手段(不図示)を使用して上昇させ、骨組材15をリングプレート19に固定する。これにより、図1に示すように、屋根4が側壁3の上端部3aに設置される。
(Roof installation process)
Subsequently, the roof 4 is installed.
First, as shown in FIG. 8, the roof 4 is assembled on the bottom plate 2. In assembling the roof 4, after the frame material 15 is assembled, the cold insulation material 16 and the roof material 17 are attached to the frame material 15. This roof assembling process may be performed in parallel with the side wall lower part construction process or after the side wall lower part construction process is completed.
Next, the roof 4 is lifted by using lifting means (not shown) such as an air lift, jack-up, lifting by a crane or the like, and the frame material 15 is fixed to the ring plate 19. Thereby, the roof 4 is installed in the upper end part 3a of the side wall 3, as shown in FIG.

そして、この屋根設置工程の後に、側壁3の内周側に保冷材およびメンブレンを設置する内槽工事を行う。また、側部ヒーター8の設置を行うとともに、盛土Gcの表面を平坦に整える。なお、盛土Gcの表面を平坦に整える際に、盛土されている地盤の表面に更に盛土Gcを行ってもよい。
このようにして地下タンク1が完成する。
And after this roof installation process, the inner tank construction which installs a cold insulating material and a membrane in the inner peripheral side of the side wall 3 is performed. Moreover, while installing the side part heater 8, the surface of the embankment Gc is prepared flat. In addition, when preparing the surface of the embankment Gc to be flat, the embankment Gc may be further applied to the surface of the ground that has been embanked.
In this way, the underground tank 1 is completed.

本実施形態による地下タンク1の施工方法によれば、側壁上部構築工程の後に内部掘削工程を行うため、地中連続壁5の内部を掘削して生じた残土をそのまま側壁上部31の外周に運搬し、側壁上部31の外周の盛土Gcに使用することができる。これにより、従来の地下タンクの施工方法のように、盛土Gcに使用する残土を地下タンク1の本体が構築される期間中に保管する必要がない。このため、残土を保管する用地の確保や残土の管理などの必要がなく、残土の保管にかかるコストや労力を削減することができる。
また、内部掘削を行うとともに、盛土を行うため、地下タンクが構築された後に盛土Gcを行う従来の地下タンクの施工方法と比べて、工期を短縮することができる。
According to the construction method of the underground tank 1 according to the present embodiment, since the internal excavation process is performed after the side wall upper construction process, the residual soil generated by excavating the inside of the underground continuous wall 5 is conveyed to the outer periphery of the side wall upper part 31 as it is. And it can be used for the embankment Gc of the outer periphery of the side wall upper part 31. Thereby, unlike the conventional underground tank construction method, it is not necessary to store the remaining soil used for the embankment Gc during the period when the main body of the underground tank 1 is constructed. For this reason, it is not necessary to secure a site for storing the remaining soil and to manage the remaining soil, and it is possible to reduce costs and labor required for storing the remaining soil.
Moreover, since the excavation and the embankment are performed, the construction period can be shortened as compared with the conventional underground tank construction method in which the embankment Gc is performed after the underground tank is constructed.

以上、本発明による地下タンクの施工方法の実施形態について説明したが、本発明は上記の実施形態に限定されるものではなく、その趣旨を逸脱しない範囲で適宜変更可能である。
例えば、上述した実施形態では、地中連続壁5の内部を掘削した後に底版2を構築し、この後に側壁下部32を下方から上方に向って構築する順巻工法を用いているが、順巻工法に代わって、地中連続壁5の内部掘削と並行して、その掘削深度に合わせて側壁下部32を上方から下方に向って構築し、側壁下部32が構築された後に底版2を構築して側壁下部32と底版2とを一体化させる逆巻工法を用いてもよい。
As mentioned above, although embodiment of the construction method of the underground tank by this invention was described, this invention is not limited to said embodiment, In the range which does not deviate from the meaning, it can change suitably.
For example, in the embodiment described above, the bottom slab 2 is constructed after excavating the inside of the underground continuous wall 5, and then the side wall lower portion 32 is constructed from below to above, using the forward winding method. Instead of the construction method, in parallel with the excavation of the underground continuous wall 5, the lower side wall 32 is constructed from the upper side to the lower side according to the excavation depth, and the bottom plate 2 is constructed after the lower side wall 32 is constructed. Alternatively, a reverse winding method for integrating the side wall lower portion 32 and the bottom plate 2 may be used.

また、上述した実施形態では、側壁下部32が、ハンチ部32a、第1側壁下部32b、第2側壁下部32cの3つから構成され、側壁下部32をハンチ部32a、第1側壁下部32b、第2側壁下部32cの3段階で構築しているが、側壁下部32全体を一度に構築してもよいし、側壁下部32を2段階や4以上の段階で構築してもよい。また、底版2とハンチ部32aとを同時に構築してもよい。
また、上述した実施形態では、側壁3の上端部3aにリングプレート19取り付けて、このリングプレート19に屋根4の骨組材15を固定しているが、屋根4を側壁3の上端部3aへ固定する方法は、これ以外の方法でもよい。
In the above-described embodiment, the side wall lower portion 32 includes three parts, that is, the hunch portion 32a, the first side wall lower portion 32b, and the second side wall lower portion 32c, and the side wall lower portion 32 includes the hunch portion 32a, the first side wall lower portion 32b, and the first side wall lower portion 32c. Although the two side wall lower parts 32c are constructed in three stages, the entire side wall lower part 32 may be constructed at one time, or the side wall lower parts 32 may be constructed in two stages or four or more stages. Moreover, you may build the base 2 and the haunch part 32a simultaneously.
In the above-described embodiment, the ring plate 19 is attached to the upper end portion 3 a of the side wall 3, and the frame material 15 of the roof 4 is fixed to the ring plate 19, but the roof 4 is fixed to the upper end portion 3 a of the side wall 3. A method other than this may be used.

また、上述した実施形態では、屋根4を底版2上で形成し、エアリフト等で上昇させて側壁3の上端部3aに設置しているが、底版2以外の場所で屋根4を形成してもよい。また、上部側壁31が構築されたら、すぐに屋根4を上部側壁31に取り付けてもよい。このとき、屋根4の一部に開口部を設けて、この開口部から資機材の出し入れや残土の搬出などを行うようにすれば、全天候において内部掘削工程を行うことができる。
要するに、本発明は、側壁上部構築工程後に内部掘削工程を行うものであり、底版構築工程、側壁下部構築工程、屋根設置工程、の施工時期や順序は実現可能な限りにおいて限定するものではない。
In the above-described embodiment, the roof 4 is formed on the bottom plate 2 and lifted by an air lift or the like and installed on the upper end portion 3a of the side wall 3. However, even if the roof 4 is formed at a place other than the bottom plate 2, Good. Further, as soon as the upper side wall 31 is constructed, the roof 4 may be attached to the upper side wall 31. At this time, if an opening is provided in a part of the roof 4 so that materials and equipment can be taken in and out and the remaining soil can be carried out from the opening, the internal excavation process can be performed in all weather.
In short, the present invention performs the internal excavation process after the side wall upper part construction process, and the construction timing and order of the bottom plate construction process, the side wall lower part construction process, and the roof installation process are not limited as long as they can be realized.

1 地下タンク
2 底版
3 側壁
3a 上端部
3b 下端部
4 屋根
5 地中連続壁
6 地盤改良体
31 側壁上部
32 側壁下部
G 地盤
Gc 盛土
DESCRIPTION OF SYMBOLS 1 Underground tank 2 Bottom plate 3 Side wall 3a Upper end part 3b Lower end part 4 Roof 5 Underground continuous wall 6 Ground improvement body 31 Side wall upper part 32 Side wall lower part G Ground Gc Embankment

上記目的を達成するため、本発明に係る地下タンクの施工方法は、底版と、該底版の周囲に沿って構築された円筒状の側壁と、該側壁の上部を覆う屋根と、を備え、前記底版と前記側壁の下部が地中に埋設されて、前記側壁の上部の周囲が盛土された地下タンクの施工方法であって、地盤中に円筒状の地中連続壁を構築する地中連続壁構築工程と、前記地中連続壁の内側を該地中連続壁の上端側に沿って掘削し、該地中連続壁の内側で該地中連続壁に支持されるとともに該地中連続壁の上端よりも上方へ突出する形態に、前記側壁の上部を構築する側壁上部構築工程と、該側壁上部構築工程の後に前記地中連続壁の内部を掘削するとともに掘削で生じた残土の一部を前記側壁の上部の周囲に盛土する内部掘削工程と、前記底版を構築する底版構築工程と、前記側壁の下部を構築し該側壁の下部を前記側壁の上部と一体化させる側壁下部構築工程と、前記側壁の上端部に屋根を設置する屋根設置工程と、を備えることを特徴とする。
In order to achieve the above object, an underground tank construction method according to the present invention includes a bottom plate, a cylindrical side wall constructed around the bottom plate, and a roof covering an upper portion of the side wall, A method for constructing an underground tank in which a bottom plate and a lower part of the side wall are buried in the ground, and a periphery of the upper part of the side wall is embanked, and a continuous underground wall for constructing a cylindrical underground continuous wall in the ground A construction step, excavating the inside of the underground continuous wall along the upper end side of the underground continuous wall, and being supported by the underground continuous wall inside the underground continuous wall and of the underground continuous wall Side wall upper construction process for constructing the upper part of the side wall in a form projecting upward from the upper end, and excavating the interior of the underground continuous wall after the side wall upper construction process and a part of the residual soil generated by the excavation An internal excavation process for embedding around the upper part of the side wall, and a bottom plate for constructing the bottom plate A side wall lowering step for building the lower part of the side wall and integrating the lower part of the side wall with the upper part of the side wall; and a roof setting step for installing a roof on the upper end of the side wall. And

Claims (3)

底版と、
該底版の周囲に沿って構築された円筒状の側壁と、
該側壁の上部を覆う屋根と、を備え、前記底版と前記側壁の下部が地中に埋設されて、前記側壁の上部の周囲が盛土された地下タンクの施工方法であって、
地盤中に円筒状の地中連続壁を構築する地中連続壁構築工程と、
前記地中連続壁の内側で上方へ突出する形態に、前記側壁の上部を構築する側壁上部構築工程と、
該側壁上部構築工程の後に前記地中連続壁の内部を掘削するとともに掘削で生じた残土の一部を前記側壁の上部の周囲に盛土する内部掘削工程と、
前記底版を構築する底版構築工程と、
前記側壁の下部を構築し該側壁の下部を前記側壁の上部と一体化させる側壁下部構築工程と、
前記側壁の上端部に屋根を設置する屋根設置工程と、を備えることを特徴とする地下タンクの施工方法。
The bottom plate,
Cylindrical side walls built around the perimeter of the bottom plate,
A roof covering the upper part of the side wall, and a method of constructing an underground tank in which the bottom plate and the lower part of the side wall are buried in the ground, and the periphery of the upper part of the side wall is embanked,
Underground continuous wall construction process to construct a cylindrical underground continuous wall in the ground,
Side wall upper construction step of constructing the upper part of the side wall in a form protruding upward inside the underground continuous wall;
An internal excavation step of excavating the inside of the underground continuous wall after the side wall upper construction step and embedding a part of the residual soil generated by excavation around the upper portion of the side wall;
A bottom plate construction step of constructing the bottom plate;
Side wall lower construction step of constructing the lower part of the side wall and integrating the lower part of the side wall with the upper part of the side wall;
And a roof installation step of installing a roof at the upper end of the side wall.
前記内部掘削工程の後に前記底版構築工程を行い
該底版構築工程の後に前記側壁下部構築工程を行い、該側壁下部構築工程では、前記側壁の下部を下方から上方に向って段階的に構築し、
前記屋根設置工程では、前記側壁下部構築工程と並行して前記底版上で前記屋根を形成し、前記側壁下部構築工程の後に、前記屋根を上昇させて前記側壁の上端部に設置することを特徴とする請求項1に記載の地下タンクの施工方法。
The bottom slab construction process is performed after the internal excavation process, and the side wall lower part construction process is performed after the bottom slab construction process, and in the side wall lower part construction process, the lower part of the side wall is constructed stepwise from below to above,
In the roof installation step, the roof is formed on the bottom plate in parallel with the side wall lower part construction step, and after the side wall lower part construction step, the roof is raised and installed on the upper end portion of the side wall. The construction method of the underground tank of Claim 1.
前記側壁下部構築工程では、前記内部掘削工程と並行して前記側壁の下部を上方から下方に向って段階的に構築し、
前記側壁下部構築工程の後に前記底版構築工程を行うことを特徴とする請求項1に記載の地下タンクの施工方法。

In the side wall lower part construction process, in parallel with the internal excavation process, the lower part of the side wall is constructed stepwise from above to below,
The construction method for an underground tank according to claim 1, wherein the bottom plate construction step is performed after the side wall lower portion construction step.

JP2010178692A 2010-08-09 2010-08-09 Construction method of underground tank Expired - Fee Related JP4702674B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010178692A JP4702674B1 (en) 2010-08-09 2010-08-09 Construction method of underground tank

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010178692A JP4702674B1 (en) 2010-08-09 2010-08-09 Construction method of underground tank

Publications (2)

Publication Number Publication Date
JP4702674B1 JP4702674B1 (en) 2011-06-15
JP2012036661A true JP2012036661A (en) 2012-02-23

Family

ID=44237089

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010178692A Expired - Fee Related JP4702674B1 (en) 2010-08-09 2010-08-09 Construction method of underground tank

Country Status (1)

Country Link
JP (1) JP4702674B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016169474A (en) * 2015-03-11 2016-09-23 大成建設株式会社 Vertical shaft, underground storage tank, construction method for vertical shaft, and construction method for underground storage tank
JP2016204848A (en) * 2015-04-16 2016-12-08 大成建設株式会社 Vertical shaft construction method and underground storage tank construction method
CN107035965A (en) * 2017-03-31 2017-08-11 武汉冶钢结构有限责任公司 Earthing formula storage tank sand bed structure and its construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016169474A (en) * 2015-03-11 2016-09-23 大成建設株式会社 Vertical shaft, underground storage tank, construction method for vertical shaft, and construction method for underground storage tank
JP2016204848A (en) * 2015-04-16 2016-12-08 大成建設株式会社 Vertical shaft construction method and underground storage tank construction method
CN107035965A (en) * 2017-03-31 2017-08-11 武汉冶钢结构有限责任公司 Earthing formula storage tank sand bed structure and its construction method
CN107035965B (en) * 2017-03-31 2019-10-25 武汉一冶钢结构有限责任公司 Earthing formula storage tank sand bed structure and its construction method

Also Published As

Publication number Publication date
JP4702674B1 (en) 2011-06-15

Similar Documents

Publication Publication Date Title
CN101691751B (en) Construction method for making ultra-long artificial excavating pile penetrate cave and ultra-long pile penetrating cave
CN103015456B (en) Rapid pit-in-pit form erecting method in foundation slab of buried concrete structure
CN104389318B (en) Reinforced concrete-steel structure hybrid gravity foundation for offshore wind power and construction method thereof
CN103821676A (en) Tower foundation of wind generating set
JP4702674B1 (en) Construction method of underground tank
JP2014088714A (en) Temporary supporting method for foundation
JP2015036493A (en) Method for constructing underground storage tank
JP2012158891A (en) Construction method of pit-in type tank
JP2012112162A (en) Earth retaining wall and construction method of earth retaining wall
JP6584979B2 (en) Construction method of underground tank structure, underground tank structure
CN110685287A (en) Double-row pile foundation pit supporting system with drainage ditch and retaining wall and construction method
JP5207086B2 (en) Construction method of underground tank
JP5684096B2 (en) Jack storage member for storing the jack that lifts the foundation of the house
JP2011236705A (en) Foundation structure of structure and method of constructing the same
JP6475554B2 (en) Construction method of shaft and construction method of underground storage tank
JP4475116B2 (en) Vertical shaft structure and its construction method
CN210031905U (en) Pile plate type platform structure for slope-caving excavation subway station hoisting shield
CN208328940U (en) A kind of support system
JP2019031821A (en) Construction method of underground tank
JP6402056B2 (en) Vertical shaft, underground storage tank, vertical shaft construction method and underground storage tank construction method
JP3160485U (en) Deep foundation foundation pile reinforcement bar construction
JP2021123961A (en) Construction method of pile head part reinforcement structure, and mold
KR101658826B1 (en) Method and structure to build underground structures using the border structure
CN105525618B (en) Domed foundation pit supporting construction and its construction method
JP6778528B2 (en) How to update the tank

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20110224

R150 Certificate of patent or registration of utility model

Ref document number: 4702674

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees